Chapter 10Submittals, Review, Operation & Maintenance and Enforcement
10.1 Purpose and scope
10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:
- (a) the submittal stages and their contents (Clauses 10.3–10.4);
- (b) the compliance calculator (Clause 10.5);
- (c) professional certification and review (Clauses 10.6–10.7);
- (d) construction inspection and as-built certification (Clauses 10.8–10.9);
- (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
- (f) handover of public assets (Clause 10.14);
- (g) enforcement (Clause 10.15); and
- (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).
10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.
10.2 Definitions
| Term | Meaning in this chapter |
|---|---|
| Submittal | A set of documents lodged with the Authority at one of the stages of Clause 10.3. |
| Drainage report | The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4. |
| Stormwater facility | Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private. |
| Hold point | A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8). |
| As-built certificate | The certificate of Clause 10.9 that the facility was built as approved and performs as designed. |
| Owner | The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset. |
| O&M plan | The operation and maintenance plan of Clause 10.11. |
| Facility register | The public register of facilities of Clause 10.17. |
Other terms are defined in Clause 1.4.
10.3 Submittal stages
10.3.1 Submittals shall be made in the following stages, linked to the approval steps of TNCDBR 2019 (Table 10.1):
Table 10.1 — Submittal stages and linked approvals
| Stage | Submittal | When | Linked approval |
|---|---|---|---|
| 0 | Pre-application meeting and Form 1-1 (Applicability Determination) | Before the planning permission or layout application | None (advisory record) |
| 1 | Preliminary drainage report | With the planning permission or layout application | Planning permission / layout approval |
| 2 | Final drainage design | Before building permit, or before commencement where the permit is issued with the planning permission | Building permit / commencement |
| 3 | Construction inspections at hold points | During construction | None (records filed) |
| 4 | As-built certificate and verification tests | Before the completion certificate | Completion / occupancy certificate |
| 5 | Maintenance declaration registered, or handover of public assets | Before or with the completion certificate | Completion certificate; asset acceptance |
| 6 | Annual declarations and inspection reports | Every year after completion | Continuing compliance |
10.3.2 Stage 0 is mandatory for:
- (a) sites of 2 ha or more;
- (b) sites in a flood-sensitive catchment;
- (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
- (d) sites draining to a tidal outfall or adjoining a waterbody.
For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.
10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.
10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.
10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.
Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.
Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the TNCDBR steps a Tamil Nadu applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.
10.4 Required contents and checklists
10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:
- (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
- (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
- (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
- (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
- (e) the pre-development condition and hydrologic method (Chapter 3);
- (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
- (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
- (h) the downstream extent and tailwater case (Chapter 5);
- (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
- (j) the land reserved for facilities and maintenance access (Clause 10.13).
10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:
- (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
- (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
- (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
- (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
- (e) construction drawings, details and specifications of every facility;
- (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
- (g) the hold-point schedule (Clause 10.8);
- (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
- (i) the model input files and the GIS data of Clause 10.4.4; and
- (j) the certificates of Clause 10.6.
10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.
10.4.4 Digital submittal.
- (a) Reports and drawings shall be submitted as searchable PDF.
- (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
- (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (43N or 44N), with attributes as listed in Annex 10B.
- (d) Levels shall be stated relative to a named vertical datum. The relationship to the tidal datums used in Chapter 5 shall be stated.
10.4.5 Summary of forms used in submittals (Table 10.2):
Table 10.2 — Forms used in submittals
| Form | Title | Stage |
|---|---|---|
| 1-1 | Applicability Determination | 0 or 1 |
| 1-2 | Variance / Waiver Request | 1 |
| 2-1 | Design Rainfall Sheet | 1, 2 |
| 10-1 | Drainage Report Checklist | 1, 2 |
| 10-2 | Compliance Calculator Summary | 1, 2, 4 |
| 10-3 | Professional Design Certificate | 1, 2 |
| 10-4 | Hold-Point Inspection Record | 3 |
| 10-5 | As-built Certificate | 4 |
| 10-6 | Maintenance Declaration | 5 |
| 10-7 | Annual Maintenance Declaration and Inspection Report | 6 |
| 10-8 | Asset Handover Certificate | 5 |
Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Chennai's drains were designed for a stated intensity with no stated return period (CAG / IIT Madras rapid assessment, 2016). Form 2-1 and Form 10-2 ensure that every design states its inputs.
10.5 Compliance calculator
10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:
- (a) applies the applicability tests of Clause 1.5;
- (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
- (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
- (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
- (e) on alternative S-2, gives the permissible site discharge for each AEP; and
- (f) produces the Compliance Calculator Summary (Form 10-2).
10.5.2 Use.
- (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
- (b) On the design-aid route, the calculator may be the only storage calculation.
- (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.
10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.
10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.
Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Tamil Nadu calculator serves Tier B authorities in particular, where it may be the whole calculation.
10.6 Professional certification
10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or DTCP:
- (a) Tier A sites of 1 ha or more;
- (b) any site in a flood-sensitive catchment;
- (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
- (d) any pumped facility, tide gate or regional facility.
10.6.2 Empanelment criteria shall be issued by DTCP and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.
10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:
- (a) the design complies with this Manual, except for variances listed and approved;
- (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
- (c) the models submitted reproduce the results reported.
10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.
10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.
Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the TNCDBR registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.
10.7 Review procedure and timelines
10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.
10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:
- (a) 15 working days of acceptance for a first submittal; and
- (b) 10 working days of acceptance for a resubmittal.
10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.
10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the DTCP list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.
10.7.5 Concurrent clearances. Where a WRD NOC or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.
10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.
10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.
Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.
10.8 Construction inspection
10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:
- (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
- (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
- (c) the infiltration tests of Clause 10.9.3;
- (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
- (e) pumps and controls, at commissioning.
10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.
10.8.3 Protection during construction.
- (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
- (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
- (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.
Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.
Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.
10.9 As-built certification
10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:
- (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
- (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
- (c) the completed hold-point records (Form 10-4); and
- (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).
10.9.2 Acceptance. The as-built facility is accepted where:
- (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
- (b) the outlet dimensions and inverts match the approved design; and
- (c) the re-run shows compliance with every criterion of Chapters 4 and 5.
Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.
10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.
10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.
Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.
10.10 Maintenance declarations and covenants
10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:
- (a) identify each facility, its location and the approved O&M plan;
- (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
- (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
- (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
- (e) be registered so that it runs with the land and is disclosed to purchasers.
10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.
10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 30 September each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.
10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.
Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Tamil Nadu because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 30 September date is set by this Manual to fall before the north-east monsoon (October–December), when most Tamil Nadu extreme rainfall occurs.
10.11 O&M plans
10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:
- (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
- (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
- (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
- (d) inspection checklists matching Form 10-7;
- (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
- (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
- (g) safety measures for confined spaces, deep water and public access;
- (h) access routes and equipment needed (Clause 10.13);
- (i) an annual cost estimate and who pays it; and
- (j) the records to be kept, and for how long.
10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.
Commentary. CAG (2017) recommended that the storm water drain network be expanded "with due importance to design of water carrying capacity" and annual maintenance. Clause 10.11.1(e) responds to Chembarambakkam, where CAG found that the operating rules had not been revised since 1993 and that communications had been down before the flood. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.
10.12 Inspection frequencies
10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:
Table 10.3 — Minimum owner inspection frequencies
| Facility type | Routine | Pre-monsoon (by 30 Sep) | After a heavy-rainfall event |
|---|---|---|---|
| Retention / infiltration (soakaways, trenches, bioretention, permeable paving) | Every 6 months | Yes | Yes |
| Surface detention basin or multi-use OSR area | Every 6 months | Yes | Yes |
| Underground or podium detention tank, gravity outlet | Every 6 months | Yes | Yes |
| Pumped detention, pumps and controls | Monthly test run | Yes, with full duty test | Yes |
| Flap / tide gate, non-return valve | Every 3 months | Yes, with seal test | Yes |
| Gross pollutant trap / first-flush device | Every 3 months | Yes | Yes |
| Private drains and inlets | Every 6 months | Yes | — |
A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district.
10.12.2 Authority inspections. The Authority shall inspect:
- (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
- (b) a random sample of at least 10% of other facilities each year.
10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).
Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 30 September) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the north-east monsoon (October–December); tick positions within the year are illustrative.
Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The pre-monsoon deadline is set for the NE monsoon. NDMA (2010) sets 31 March for pre-monsoon desilting nationally, which suits the south-west monsoon but is six months early for coastal Tamil Nadu.
10.13 Maintenance access
10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.
10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.
10.13.3 Underground facilities. Tanks shall have:
- (a) an access opening over the inlet, the outlet and each chamber;
- (b) fixed ladders or steps, and ventilation for confined-space entry;
- (c) a sump or low point for sediment removal; and
- (d) headroom sufficient for manual cleaning.
10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.
10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.
Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Tamil Nadu cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.
10.14 Handover of public assets to the ULB
10.14.1 Drains, roads, OSR facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:
- (a) the as-built certificate (Clause 10.9) has been accepted;
- (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
- (c) the land, or an easement over it, has been transferred to the ULB;
- (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
- (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.
10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full north-east monsoon season after handover. The ULB may hold a security deposit for this period.
10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.
10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.
Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Tamil Nadu drainage show up only in the first NE monsoon.
10.15 Enforcement
10.15.1 Offences. The following are contraventions of this Manual:
- (a) building without an approved drainage design where one is required;
- (b) building a facility other than as approved;
- (c) removing, filling, covering, reducing or changing the use of a facility without approval;
- (d) failing to maintain a facility, or to submit Form 10-7;
- (e) a sewage connection to a storm drain;
- (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
- (g) obstructing a natural drainage path or major-system flow path; and
- (h) false or negligent certification.
10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):
Table 10.4 — Graduated enforcement response
| Step | Action |
|---|---|
| 1 | Written notice stating the contravention, the clause breached, the remedy and a compliance period. |
| 2 | Stop-work order, or withholding of the completion certificate, for development not yet complete. |
| 3 | Penalty under the applicable Act or rules. |
| 4 | Works in default by the Authority, with the cost recovered from the owner. |
| 5 | Disconnection of the private drain connection to the public system, where this causes no hazard to others. |
| 6 | Report of the certifying professional to the registering authority, and suspension from the empanelled list. |
10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.
10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.
10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.
Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which TNCDBR 2019 is made and from the municipal Acts. The graduated steps are set by this Manual. CAG (2017) found that tank encroachment kept rising despite the 2007 tank protection Act, which shows that a law without routine enforcement does little. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.
10.16 Monitoring and post-event review
10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.
10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:
- (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
- (b) tide and river levels at the outfalls;
- (c) flooded locations, depths and durations, with flood marks surveyed where possible;
- (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
- (e) recommended actions.
10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), TNSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.
10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.
Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. After the 2015 floods the CAG audit and the IIT Madras rapid assessment provided the evidence base. After 2021 and 2023 no comparable published review was found. The Thiruppugazh committee report (March 2023) remains unpublished. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.
10.17 Data publication
10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:
- (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
- (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
- (c) the register of variances and waivers (Clause 1.10);
- (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
- (e) enforcement actions (Clause 10.15.5); and
- (f) event reports and post-event reviews (Clause 10.16).
10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.
10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.
10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.
Commentary. Transparency is a design criterion in its own right here. The Thiruppugazh committee's 161 recommendations guided major drain contracts, yet the report has never been published, so its standards cannot be checked or cited. A Kovalam basin design deck cited a 68 mm/h "maximum rainfall intensity", with no return period stated in the published extract. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.
10.18 Review of this chapter
10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.
References (chapter)
- Comptroller and Auditor General of India (2017). Report No. 4 of 2017: Performance Audit of Flood Management and Response in Chennai and its Suburban Areas (Executive Summary, paras 5.2, 5.6.1, 5.8.5 and recommendations). https://cag.gov.in/uploads/download_audit_report/2016/Executive_summary_of_Report_No_4_of_2017_-_Performance_Audit_of_Flood_Management_and_Response_in_Chennai_.pdf
- Narasimhan, B. et al. (2016). Chennai Floods 2015: A Rapid Assessment. IIT Madras / CAG. https://www.cag.org.in/sites/default/files/database/chennai-floods-rapid-assessment-report_1.pdf
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities, §5608 (easements, maintenance, submittals) and §5609 (plan requirements). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Mid-America Regional Council (2025). Stormwater management page: 2025 Stormwater Standards Manual, Compliance Calculator, Calculator Start-Up Guide, Policy Supplement. https://www.marc.org/environment/environment-plans/stormwater-management
- PUB Singapore (2018, with Addendum No. 3 of 16 Apr 2025). Code of Practice on Surface Water Drainage, 7th ed. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
- PUB Singapore (2024). On-site Stormwater Detention Tank Technical Guide. https://www.pub.gov.sg/-/media/PUB/PDF/detentionTank.pdf
- PUB Singapore (11 Nov 2024). Amendments to Sewerage and Drainage Act (press release). https://www.pub.gov.sg/Resources/News-Room/PressReleases/2024/11/Amendments-to-Sewerage-and-Drainage-Act
- MoHUA (2016). Model Building Bye-Laws, Chapter 9, §9.6. https://web.archive.org/web/2022/https://mohua.gov.in/upload/uploadfiles/files/MBBL.pdf
- National Disaster Management Authority (2010). National Guidelines on Management of Urban Flooding. https://sdma.goa.gov.in/sites/default/files/2022-05/management_urban_flooding.pdf
- The Realty Today. Tamil Nadu Government Sets 15–30 Day Deadlines for Building Approvals (secondary source on NOC timelines). https://therealtytoday.com/news/trending/tamil-nadu-government-sets-15-30-day-deadlines-for-building-approvals/
- Verified.RealEstate. Tamil Nadu Building Permit Rules: New Timeline for Faster Approvals (secondary source on the 5-day inspection and 24-day permission timelines). https://community.verified.realestate/article/tamil-nadu-building-permit-rules-new-timeline-for-faster-approvals/?amp=1
- DT Next (2026). Release Thiruppugazh committee report (secondary source on report status). https://www.dtnext.in/news/tamilnadu/release-thiruppugazh-committee-report-anbumani-ramadoss-demands-govt-801849
- NGT (Kovalam M3 drain documents, citing GCC design deck). https://www.greentribunal.gov.in/sites/default/files/news_updates/3_8.pdf
Annexes and forms
| Annex / Form | Content |
|---|---|
| 10A | Compliance calculator and user guide |
| 10B | GIS data specification and attribute schema |
| 10C | Maintenance access dimensions |
| 10D | Model O&M plans by facility type |
| 10E | Empanelment criteria for Stormwater Design Professionals and reviewers |
| Form 10-1 | Drainage Report Checklist |
| Form 10-2 | Compliance Calculator Summary |
| Form 10-3 | Professional Design Certificate |
| Form 10-4 | Hold-Point Inspection Record |
| Form 10-5 | As-built Certificate |
| Form 10-6 | Maintenance Declaration |
| Form 10-7 | Annual Maintenance Declaration and Inspection Report |
| Form 10-8 | Asset Handover Certificate |
| Form 2-1 | Design Rainfall Sheet (Chapter 2) |
Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. The CAG audit of the 2015 Chennai flood found that drains were built to an incorrect design intensity and that desilting in 2014 and 2015 had not started before the monsoon (CAG Report No. 4 of 2017, paras 5.2 and 5.6.1). Both are failures of process, not of engineering knowledge. This chapter is the process.