Chapter 11Basin and City Stormwater Master Plans
11.1 Purpose and scope
11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.
11.1.2 A BSMP shall:
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
- (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
- (d) reserve land for regional storage, cheruvu and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
- (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
- (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).
11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.
11.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Basin | The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3. |
| Basin Stormwater Master Plan (BSMP) | The plan for one basin prepared under this chapter. |
| Lead Authority | The body responsible for preparing a BSMP (Clause 11.4). |
| Level of service (LoS) | The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6). |
| Flood hazard map | A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario. |
| Regional facility | A storage, conveyance or outfall work serving more than one development, identified in a BSMP. |
| Capital Improvement Programme (CIP) | The ranked, costed list of works in a BSMP (Clause 11.8.4). |
11.3 Planning unit: the basin, not the ward
11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.
11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.
11.3.3 For the largest urban areas, the basins are at least the following:
- Hyderabad: the catchment of each major nala that drains to the Musi or to its tributary the Esa within the Core Urban Region, each as a basin, with the Musi reach it joins as its outfall condition; the catchment of Hussain Sagar, with its inlet and outlet nalas; and the catchments of the Osman Sagar and Himayat Sagar reservoirs upstream of the city. Each is delineated with its lake chains across GHMC, Cyberabad and Malkajgiri and into the HMDA area beyond them. The boundary of the Musi is that certified by the Irrigation and Revenue Departments (G.O.Ms.No.168, Rule 3(a)(ii)(1), as amended by G.O.Ms.No.7 of 2016); and
- Khammam: the catchments draining to the Munneru, with the Munneru level as the outfall condition.
Other Tier A bodies shall define their basins in the first BSMP. These include Greater Warangal, with the catchments of its tanks and nalas, Karimnagar, Nizamabad and Ramagundam. Towns on the Godavari, such as Bhadrachalam, and on the Krishna and its tributaries are expected to need a BSMP under Clause 11.4.2(c). Every basin that drains to a tank takes the tank's water level as its outfall condition (Chapter 5). Where the Irrigation Department or the dam operator has a design flood or release schedule for a river that a city lies on, the BSMP shall take its river boundary conditions from it.
Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.
Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. Hyderabad's drains were not laid out by ward. Its lakes were once "connected by a 'cascade system'", now broken by encroachment (Rangari et al. 2021), and many of its nalas run from one lake to the next before they reach the Musi. Since February 2026 the core city has been split among three Corporations, GHMC, Cyberabad and Malkajgiri (G.O.Ms.No.55, 11 February 2026), after 27 surrounding local bodies were merged into GHMC in December 2025, so nalas cross Corporation boundaries on their way to the Musi. Responsibility is split along other lines again: the drains vest in the Corporations, tank FTLs are surveyed by the Irrigation Department and notified by HMDA's Lake Protection Committee, encroachments are removed by HYDRAA, and sewerage is HMWSSB's. CAG found that a drain proposed from Patancheru to Gangaram cheruvu had to be realigned because much of its length "was not traceable" (Report No. 3 of 2018). This clause makes the basin the planning unit. It also requires the nalas that join one cheruvu to the next to be treated as links, because a change to one tank's surplus weir or one nala's section changes water levels in every tank below it. Mission Kakatiya already took up the chain tanks of each mandal first (G.O.Ms.No.44 I&CAD, 2015).
11.4 Who prepares, and when
11.4.1 Lead Authority.
- For a basin wholly within one Corporation of the Core Urban Region (GHMC, Cyberabad or Malkajgiri), or within one other Municipal Corporation: the Corporation.
- For a Hyderabad basin that crosses Corporation boundaries or extends beyond the Core Urban Region, including the Musi nala catchments and the Hussain Sagar catchment: HMDA, with the Corporations, the other local bodies of the HMDA area, the Irrigation Department, HYDRAA (for encroachments and flood response), HMWSSB (for sewerage) and TGDPS (for rain gauges) as partners.
- For the catchments of the Osman Sagar and Himayat Sagar drinking-water reservoirs: HMWSSB, with HMDA, the Irrigation Department and the local bodies in the catchment as partners.
- For a basin draining to a chain of tanks held by the Irrigation Department outside a Municipal Corporation, or whose outfall is a river reach controlled by its reservoirs and barrages (for example the Godavari at Bhadrachalam): the Irrigation Department, with the local bodies as partners.
- For other basins that cross local-body boundaries: the Urban Development Authority for the area, or where there is none the Municipal Corporation or municipality with the largest share of the basin, with the other local bodies as partners.
- In Tier B bodies: the Lead Authority is named by the MA&UD Department. Basins draining to a common chain of tanks or river reach may be grouped into one district-level plan.
HMDA's Lake Protection Committee shall be consulted on every BSMP that proposes works in a notified lake or its buffer, and HYDRAA on every BSMP in the Core Urban Region.
The Irrigation Department shall be a partner in every BSMP that includes a river, canal or tank under its control.
11.4.2 When a BSMP is required.
- (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
- (b) A BSMP is required before:
- any regional detention or fee-in-lieu is accepted under Clause 4.13;
- a fee held under Clause 4.5.6.3 is spent; and
- a basin-specific release rate is applied under Clause 11.8.3.
- (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.
11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.
11.5 Data and surveys
11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:
Table 11.1 — Minimum data and surveys for a BSMP
| Data | Minimum requirement |
|---|---|
| Terrain | Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum |
| Drain network | Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm |
| Waterbodies | Survey of every tank, cheruvu, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment |
| Rivers and canals | Cross-sections at no more than 200 m spacing and at every structure |
| Outfalls | Receiving-water levels: FTL and MWL of downstream tanks, river and reservoir levels and release records (Chapter 5); surplus weirs and sluices; gates and pumps |
| Rainfall and levels | All available rain gauges (IMD, the TGDPS automatic weather station network, the GHMC rain gauges and the ICRISAT recording gauges at Patancheru) and water-level records, including those for the August 2000, October 2020, July 2023 and September 2024 events |
| Flood evidence | Surveyed flood marks and mapped flood extents from past events, including public reports |
| Land use | Existing land use and imperviousness; future land use from the statutory master plan |
| Soils and groundwater | HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones |
| Sewer interaction | Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots |
Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the flat floors of tank beds and nala valleys a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The August 2000, October 2020, July 2023 and September 2024 events are the best calibration data Telangana has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.
11.6 Levels of service
11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.
Table 11.2 — Minimum levels of service
| Element | Minimum level of service |
|---|---|
| Minor system | The design AEP of Chapter 6 (Table 6.1) |
| Habitable buildings | No flooding above floor level in the 1% AEP (100-yr) event |
| Critical facilities (hospitals, emergency services, substations, water and sewage plants) | No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event |
| Evacuation routes and arterial roads | Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event |
| Ponding drain time | Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event |
| Tank and cheruvu storage | No net loss of flood storage below the MWL in the basin, measured against the earliest available survey |
| Outfalls | Functioning under the joint and outfall-closed cases of Chapter 5 |
Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects how much tank storage Telangana's cities have lost. HMDA's Lake Protection Committee identified 185 lakes within GHMC in 2013. CAG found only 159 of them traceable, 17 not traceable and nine fully encroached (Report No. 3 of 2018), and the Irrigation Department reported 8,718 encroachments within the FTL and 5,343 within the buffer of GHMC lakes (before the NGT, 2022). Of the 2,978 lakes on HMDA's register, 1,352 had final FTL notifications on 1 November 2026, most of them issued in 2024 and 2025 (this Manual's count of the HMDA lakes portal). The first Census of Water Bodies counted 3,032 encroached water bodies in the State (reference year 2017-18). Mission Kakatiya aimed to restore tanks to their original FTL (G.O.Ms.No.44 I&CAD, 2015); the rule in Table 11.2 gives that aim a measurable test.
11.7 Modelling and scenarios
11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:
- the minor system;
- the major (overland) system;
- rivers, canals and tanks; and
- the outfalls.
Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.
11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.
11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.
11.7.4 Scenarios. Each BSMP shall model at least:
- (a) Existing: existing land use, network, tanks and outfalls;
- (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
- (c) Future, controlled: future land use with the site controls of Chapter 4;
- (d) Future, with plan: scenario (c) plus the works of the CIP; and
- (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8.
11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the August 2000, October 2020, July 2023 and September 2024 events where data exist.
Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and cheruvulu with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.
Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).
11.8 Options, outputs and the Capital Improvement Programme
11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:
- Protect and restore storage: cheruvulu, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
- Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
- Conveyance upgrades to drains, canals and culverts;
- Outfall works: gates, pumps, and the surplus weirs and sluices of receiving tanks;
- Property-level protection where works cannot reach the level of service; and
- Non-structural measures: flood warning (for example IMD and TGDPS rainfall alerts and HYDRAA's monsoon response in the Core Urban Region), flood-hazard zoning, emergency planning and public information.
11.8.2 Option assessment. Each option shall be assessed for:
- reduction in flood risk (buildings and people flooded; expected annual damage);
- capital and 30-year maintenance cost;
- land required;
- effect on groundwater recharge (Chapter 8);
- effect on downstream basins and the Musi river; and
- who benefits.
11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.
11.8.4 Outputs. Each BSMP shall produce:
- (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
- (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
- (c) regional facility sites, with storage volumes, land needs and the sites they serve;
- (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
- (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
- (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
- (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.
Commentary. Restoring storage comes first because Telangana already has a regional storage system: its chain tanks, in which each cheruvu's surplus weir spills to the next. The first Census of Water Bodies counted 64,055 water bodies in the State, including 16,292 tanks (Ministry of Jal Shakti, reference year 2017-18), and Mission Kakatiya set out to restore 46,531 minor-irrigation tanks, taking up chain tanks first and restoring each "to its original FTL by raising the weir where they are disturbed or lowered" (G.O.Ms.No.44 I&CAD, 2015; NITI Aayog DMEO). In Hyderabad, a model of GHMC Zone XII showed 34.05 km² flooded in October 2020 against 21.95 km² in August 2000, despite less rain, which the authors attribute to further urbanisation and the encroachment of lakes (Rangari et al. 2021). Conveyance upgrades on their own move water faster to an outfall that may be held up by a full tank or a river in flood. Lined drains also cut recharge in a State whose aquifers are mostly weathered crystalline rock: such rocks underlie about 83% of Telangana, are weathered to 3–20 m and yield 0.1–5 litres per second (CGWB 2021). In a wet year the water table rises close to the surface in the season of the design storms: in November 2020, 38% of monitored wells had water within 2 m of ground level, against 2% in May 2020, mainly in Warangal, Khammam, Hyderabad, Ranga Reddy, Karimnagar, Nalgonda, Mahabubnagar and Adilabad districts (CGWB 2021). Near Hyderabad about 11% of rainfall becomes groundwater recharge (CGWB 2006, as quoted by Dourte et al. 2013). Deeper or lined drains can lower or cut off the water table, and can drain the tank beds that recharge it, which is why groundwater recharge is an assessment criterion. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.
11.9 Integration with land-use planning
11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the Master Plans and zoning regulations made under the HMDA Act 2008, including the Metropolitan Development Plan 2031 (G.O.Ms.No.33 MA&UD, 2013) and its successor for the Hyderabad Metropolitan Region as redrawn by G.O.Ms.No.68 MA&UD (2025); the plans of the Future City Development Authority (G.O.Ms.No.69 MA&UD, 2025) and of the Urban Development Authorities; and the Master Plans and Detailed Planning Schemes of municipalities, which under s.171 of the Telangana Municipalities Act 2019 already include a drainage plan. In particular:
- (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
- (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
- (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
- (d) the organised open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.
11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.
Commentary. Telangana has no numeric flood-plain rule. G.O.Ms.No.168 bars building in the bed of a river or nala and within the FTL of any lake, pond, cheruvu, kunta or shikam land, and keeps a green buffer around them (Rule 3(a)), but it has no rule on flood levels, low-lying land or plinth heights, and it regulates cellars by plot size alone (Rule 5). The Metropolitan Development Plan 2031 adds an Open Space Buffer use zone of at least 30 m around the FTL of existing water bodies (G.O.Ms.No.33 MA&UD, 2013). Along the Musi, the line of the river bed and its buffer is being fixed by survey and court order: in December 2024 the High Court directed eviction from the FTL, river bed and buffer (WP 27110 of 2024, as reported). A BSMP gives these provisions the 1% AEP map they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because under G.O.Ms.No.168 (2012), Rule 3(a)(iii)(3), the green buffer along a lake, nala or river may be reckoned as part of a layout's tot lot or organised open space, and the Metropolitan Development Plan 2031 already asks layout works to channel nalas so as to conserve or harvest the water in the nearest water body or public open space; because that land then serves as open space, storage placed in it must stay usable as one. Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.
11.10 Consultation and publication
11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.
11.10.2 After approval, the following shall be published as open data:
- the model files;
- the flood hazard maps;
- the data of Clause 11.5.1, except security-sensitive asset details; and
- the CIP.
They shall also be shown on a public map viewer.
Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.
11.11 Approval, review and reporting
11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.
11.11.2 Review. Each BSMP shall be reviewed:
- every 10 years;
- within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
- when the statutory land-use plan is revised.
11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each monsoon (by 31 May). The report shall show:
- CIP progress;
- the fee-in-lieu ledger (Clause 4.13.4);
- maintenance completed; and
- any flooding against the levels of service.
11.12 Interim arrangements
11.12.1 Until a BSMP is approved for a basin:
- (a) all site criteria of Chapters 4 to 8 apply in full;
- (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
- (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
- (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.
References (chapter)
- Comptroller and Auditor General of India (2018). Report No. 3 of 2018: Report on Local Bodies for the year ended 31 March 2017, Government of Telangana, Chapter IV, paras 4.7.1 (master plans) and 4.7.4 (encroachments and lakes). https://cag.gov.in/webroot/uploads/download_audit_report/2018/Local%20Bodies%20AR%202016-17%20Full%20Report.pdf
- Defra (2010). Surface Water Management Plan Technical Guidance. Department for Environment, Food and Rural Affairs, London.
- Mile High Flood District (Denver). Master planning programme and Urban Storm Drainage Criteria Manual.
- Mid-America Regional Council (2025). APWA Stormwater Standards Supplement; KC Metro APWA Section 5600, Version 2025.01.
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- Irrigation & CAD Department, North Tanks Division, Hyderabad. Counter affidavit in O.A. 163 of 2021 (SZ), National Green Tribunal, 22 March 2022 (Lake Protection Committee procedure; 185 GHMC lakes; encroachments; SNDP sanction). https://www.greentribunal.gov.in/sites/default/files/news_updates/16321_2.pdf
- Ramana, R.V. (National Institute of Hydrology, 2013–16). Evaluation of urban storm water network in Hyderabad city using SWMM. https://nihroorkee.gov.in/studies_2014-2025/18-Evaluation%20of%20urban%20storm%20water%20network%20in%20Hyderabad%20city%20using%20SWMM_RVRamana.pdf
- Rangari, V.A., Bhatt, C.M. and Umamahesh, N.V. (2021). Rapid assessment of the October 2020 Hyderabad urban flood and risk analysis using geospatial data. Current Science 120(12), 1840–1847.
- Government of Telangana. G.O.Ms.No.55 MA&UD, 11-02-2026 (constitution of the Greater Hyderabad, Cyberabad and Malkajgiri Municipal Corporations). https://tg-bn-website-assets.flowwlabs.tech/GOs-and-ACTs/GO.Ms.No.55_11-02-2026.pdf
- Government of Telangana. GHMC (Amendment) Ordinance No. 11 of 2025 (Schedule-X: the 27 merged local bodies). https://prsindia.org/files/bills_acts/bills_states/telangana/2025/Ord11of2025TS.pdf
- Government of Telangana. G.O.Ms.No.44 I&CAD (Reforms), 13-03-2015 (Mission Kakatiya guidelines). http://web.archive.org/web/20240704110606/https://missionkakatiya.cgg.gov.in/jsp/G.O.Ms_No.44_dt_13-03-2015.pdf
- NITI Aayog, DMEO (2021). Water Resources case study 6: Mission Kakatiya. https://dmeo.gov.in/sites/default/files/2021-08/Package9_WaterResources_CaseStudy6.pdf
- Ministry of Jal Shakti (2023). First Census of Water Bodies, Vol. 2, State-wise report (Telangana). https://mowr.nic.in/irrigationcensus/sites/default/files/State20230825411930292.pdf
- Hyderabad Metropolitan Development Authority. Lakes portal: FTL and buffer notifications (read 1 November 2026). https://lakes.hmda.gov.in/
- Central Ground Water Board (2021). Ground Water Year Book, Telangana State, 2020-21, §§2.3–2.4 and depth-to-water tables. http://web.archive.org/web/20250406103807/https://cgwb.gov.in/old_website/Regions/SR/Reports/GWYB%20Telangana%202020-2021.pdf
- Dourte, D., Shukla, S., Singh, P. and Haman, D. (2013). Rainfall intensity-duration-frequency relationships for Andhra Pradesh, India. Journal of Hydrologic Engineering 18(3), 324–330 (accepted manuscript). https://oar.icrisat.org/7271/1/JHE_Rainfall%20intensity_manuscript_singh_2012.pdf
- Government of Andhra Pradesh. G.O.Ms.No.168 MA&UD (M), 07-04-2012 (Building Rules, 2012, continued in Telangana), Rules 3(a), 5 and 15(a), with Annexure-VI (G.O.Ms.No.350 MA, 09-06-2000, rainwater harvesting). https://tg-bn-website-assets.flowwlabs.tech/GOs-and-ACTs/1_GOMsNo_168_MA_UD_dt_07042012.pdf
- Government of Telangana. G.O.Ms.No.7 MA&UD (M1), 05-01-2016 (amendment to Rule 3(a)(ii)(1): river buffer and river boundary). https://tg-bn-website-assets.flowwlabs.tech/GOs-and-ACTs/3_GOMsNo_7_MA_UD_dt_05012016.pdf
- Government of Andhra Pradesh. G.O.Ms.No.33 MA&UD (I1), 24-01-2013 (Metropolitan Development Plan 2031 for the Hyderabad Metropolitan Region; zoning regulations 1.8.2 and 1.9). https://tg-bn-website-assets.flowwlabs.tech/GOs-and-ACTs/27_GOMsNo_33_MA_UD_dt_24012013.pdf
- Government of Telangana. G.O.Ms.No.68 MA&UD (Plg.I), 12-03-2025 (Hyderabad Metropolitan Region redrawn). https://tg-bn-website-assets.flowwlabs.tech/GOs-and-ACTs/G.O.Ms.No.68_HMDA_EXPANSION_GO_12-03-2025.pdf
- Government of Telangana. G.O.Ms.No.69 MA&UD, 12-03-2025 (Future City Development Authority). https://tg-bn-website-assets.flowwlabs.tech/GOs-and-ACTs/G.O.Ms.No.69_FCDA_GO_12-03-2025.pdf
- Government of Telangana. Telangana Municipalities Act 2019 (Act No. 11 of 2019), s.171. https://tg-bn-website-assets.flowwlabs.tech/GOs-and-ACTs/44_Municipaliteis_Act_English.pdf
- LiveLaw (3 Dec 2024). Telangana High Court on the Musi riverfront: encroachments and unauthorised constructions, WP 27110 of 2024 (secondary source). https://www.livelaw.in/amp/high-court/telangana-high-court/telangana-high-court-musi-riverfront-project-encroachment-unauthorized-constructions-supreme-court-guidelines-277151
- HYDRAA. Disaster Management (monsoon protocol and links to TGDPS rainfall). https://hydraa.telangana.gov.in/functions/disaster-management
- Telangana State Development Planning Society. Telangana Weather Data 2023–2025 (Open Data Telangana, via AIKosh). https://aikosh.indiaai.gov.in/home/datasets/details/telangana_weather_data_2023_2025.html
Annexes and forms
| Annex / Form | Content |
|---|---|
| 11A | BSMP terms of reference template |
| 11B | Basin lists and boundaries for Tier A bodies |
| 11C | Depth–damage curves for Telangana building types |
| 11D | BSMP data and model publication standard |
| Form 11-1 | Annual implementation report |
Commentary. Hyderabad has had two storm drainage master plans and has implemented neither. After the flood of August 2000, the then Municipal Corporation of Hyderabad engaged Kirloskar Consultants, who in 2006 identified 71 drains for improvement. GHMC then engaged Voyants Solutions, whose draft comprehensive master plan and DPRs for 102 drains, submitted in December 2011, were still unapproved in 2017. By then GHMC had taken up 24 of the Kirloskar drains and two of the Voyants drains, and the State said that works could not proceed "due to encroachments and stiff resistance from people" (CAG, Report No. 3 of 2018). After the October 2020 floods the State sanctioned the Strategic Nala Development Programme (SNDP), Phase I at ₹858 crore (G.O.Rt.No.286 MA&UD (GHMC-II), 6 April 2021, as stated by the Irrigation Department to the NGT). The design return period and intensity of the Kirloskar, Voyants and SNDP works were not found published. An NIH model of GHMC Zone XII found that the network "is not sufficient to drain two-year return period storm" (NIH, 2013–16). No stormwater master plan was found for Warangal, Khammam, Karimnagar, Nizamabad or Ramagundam. A site-level manual cannot fix basin-level problems: lost tank storage, outfalls held up by full tanks downstream or by rivers in flood, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:
This chapter adapts that method to Telangana's chain tanks, the cheruvulu and kuntas linked by nalas and vagus in which each tank's surplus weir (alugu) spills to the next; to Hyderabad's lake chains, whose nalas drain to the Musi; to a monsoon season from June to October whose heaviest Hyderabad storms come in late September and October; and to outfalls held up by full tanks downstream and by rivers in flood, such as the Musi below its reservoirs, the Godavari at Bhadrachalam and the Munneru at Khammam. Telangana has no coast, so the tidal and sand-bar provisions of this chapter do not arise.