Draft v1.0 prepared by NEER. Not adopted by the Government of Andhra Pradesh or the Government of Puducherry (for Yanam), and has no legal force. About this draft

Chapter 9Hydraulic Design of Structures


9.1 Purpose and scope

9.1.1 This chapter sets the hydraulic design methods for the structures used in the minor and major systems (Chapter 6), in retention and detention facilities (Chapter 4), at outfalls (Chapter 5) and at waterbodies (Chapter 7). It covers:

  • (a) pipes and box drains (Clause 9.3);
  • (b) culverts (Clause 9.4);
  • (c) open channels (Clause 9.5);
  • (d) energy dissipators, outlet protection and drop structures (Clause 9.6);
  • (e) detention outlet structures (Clause 9.7);
  • (f) trash racks and screens (Clause 9.8);
  • (g) pumps and sumps (Clause 9.9);
  • (h) tide gates, flap gates and non-return valves (Clause 9.10);
  • (i) inlets and gratings (Clause 9.11);
  • (j) manholes, junction chambers and access (Clause 9.12); and
  • (k) materials and durability, including coastal and saline exposure (Clause 9.13).

9.1.2 Structural design is outside the scope of this Manual. Structures shall be designed structurally to the applicable Indian Standards and IRC codes, for example IS 456 (plain and reinforced concrete), IS 458 (concrete pipes), IRC:SP:13 (small bridges and culverts) and the IRC bridge codes. Where this chapter refers to a structural standard, it does so only for durability (Clause 9.13) or hydraulic performance.

9.1.3 Design flows, design AEPs and level-of-service limits come from Chapters 2 to 7. This chapter does not change them.

Commentary. APWA Section 5600 places most structure hydraulics in its sections on inlets and manholes (5604), enclosed pipe systems (5606), engineered channels (5607) and detention (5608). CPHEEO (2019) spreads them across Chapters 5, 6, 8 and 11. This chapter gathers them in one place and points to the US Federal Highway Administration (FHWA) hydraulic circulars for methods that Indian codes do not cover in enough detail: HDS-5 for culverts, HEC-14 for energy dissipators, HEC-22 for inlets and access holes, and HEC-24 for pump stations. The FHWA editions cited are those listed in the FHWA hydraulics library as of October 2026.


9.2 General requirements

9.2.1 Tailwater. Every structure that discharges to a tidal or river-influenced water body shall be analysed with the tailwater conditions of Chapter 5: MHWS for minor-system design, HAT plus surge for major-system design, each with the +0.3 m sea-level allowance, and the joint case of Clause 2.12.

9.2.2 Climate factor. Design flows shall include the climate factor of Clause 2.8.

9.2.3 Maintenance access. Every structure shall be accessible for inspection and cleaning by the methods in Clause 9.12 and Chapter 10, without manual entry into confined spaces wherever practicable.

9.2.4 Design life. Structures shall be designed for a service life of at least 50 years for concrete and masonry works, and at least 25 years for mechanical and electrical equipment, unless the approving authority agrees otherwise.

9.2.5 Blockage. Where a structure can be blocked by debris, it shall be checked in the blocked condition set out in this chapter, and a safe overflow route shall exist for that condition (Chapter 6, Clause 6.3.2).

Commentary. The design-life values in Clause 9.2.4 have no direct precedent; this Manual sets them because they are needed to decide when the climate factor applies (Clause 2.8.2 applies it to elements with a design life over 25 years).


9.3 Pipes and box drains

9.3.1 Capacity and roughness. Pipe and box-drain capacity shall be computed by Manning's equation with the design n of Chapter 6, Table 6.6. For precast or cast-in-situ RCC box drains, the design n shall be at least 0.015.

9.3.2 Partly full flow. Depth, velocity and discharge in partly full circular pipes shall be computed from the hydraulic-element relationships for circular sections (for example CPHEEO 2019, Table 5.5). The minimum velocity of Clause 6.7.3 applies at the design flow.

9.3.3 Pressure flow. Where a pipe runs full or surcharged, the HGL shall be computed under Chapter 6, Clause 6.8, with friction and structure losses.

9.3.4 Steep pipes. Where the design flow in a pipe is supercritical (Froude number above 1), the designer shall:

  • (a) locate any hydraulic jump and show that it occurs in a structure designed to contain it, not in a pipe run;
  • (b) provide air venting where the jump can seal the pipe; and
  • (c) meet the maximum velocity of Clause 6.7.3(b).

9.3.5 Changes of size and direction.

  • (a) Pipe size shall not decrease downstream.
  • (b) Pipes shall join only at manholes or junction chambers, except that inlet connections may join pipes of 1,200 mm or more through a factory-made junction.
  • (c) Changes of direction greater than 90° in a single structure are not permitted.

9.3.6 Flotation. Pipes and box drains in high groundwater shall be checked for flotation (Chapter 6, Clause 6.7.7).

Commentary. The design n of 0.015 for box drains is set by this Manual to match the "fair" concrete value in Table 6.6. Clauses 9.3.4 and 9.3.5 follow common practice in FHWA HEC-22 and other manuals. A jump inside a pipe run causes pressure surges and can blow off manhole covers.


9.4 Culverts

9.4.1 Method. Culverts shall be designed by the methods of FHWA Hydraulic Design of Highway Culverts, HDS-5, 3rd edition (2012), or by software that implements them (for example FHWA HY-8). The design headwater is the greater of the headwater under inlet control (HWi) and the headwater under outlet control (HWo).

9.4.2 Inlet control. HWi shall be computed from the HDS-5 inlet-control equations or nomographs for the barrel shape, material and inlet edge condition actually built.

9.4.3 Outlet control. HWo shall be computed as:

HWo = ho + H − L·S

H = [1 + ke + (19.63 n² L) / R^1.33] · V² / 2g (SI units, full barrel)

ho = the greater of TW and (dc + D)/2

where ho is the outlet water depth used for control (m), H is the total head loss through the barrel (m), L is the barrel length (m), S is the barrel slope (m/m), ke is the entrance loss coefficient (Table 9.1), n is the barrel roughness, R is the hydraulic radius (m), V is the barrel velocity (m/s), TW is the tailwater depth above the outlet invert (m), dc is the critical depth (m) and D is the barrel rise (m). Part-full barrels under outlet control shall be analysed by backwater calculation as set out in HDS-5.

Table 9.1 — Entrance loss coefficients ke (outlet control, full or partly full)

Barrel and inlet ke
Concrete pipe, projecting from fill, socket (groove) end 0.2
Concrete pipe, projecting from fill, square-cut end 0.5
Concrete pipe, headwall or headwall with wingwalls, socket end 0.2
Concrete pipe, headwall or headwall with wingwalls, square edge 0.5
Concrete pipe, headwall, rounded entrance (radius = D/12) 0.2
Concrete pipe, mitred to conform to fill slope 0.7
Concrete pipe, bevelled edges 0.2
Corrugated metal pipe, projecting from fill 0.9
RCC box, headwall parallel to embankment, square edge on three sides 0.5
RCC box, headwall parallel to embankment, three edges rounded or bevelled 0.2
RCC box, wingwalls at 30°–75° to barrel, square-edged crown 0.4
RCC box, wingwalls at 10°–25° to barrel, square-edged crown 0.5
RCC box, wingwalls parallel (extension of sides), square-edged crown 0.7

Source: FHWA HDS-5 (2012), entrance loss coefficient table (Appendix C).

9.4.4 Tailwater. TW shall be the higher of:

  • (a) the normal or backwater depth in the downstream channel at the design flow; and
  • (b) the tailwater level of Clause 9.2.1, for culverts within tidal or river backwater reach.

9.4.5 Headwater limits. At the design AEP of Chapter 6, Table 6.1:

  • (a) HW/D shall not exceed 1.2;
  • (b) the headwater shall be at least 0.3 m below the edge of the road shoulder at the upstream face; and
  • (c) the headwater shall not raise water levels at any upstream building or property boundary above the limits of Chapter 6, Clause 6.12.2(d).

9.4.6 Road overtopping. Flow over the road in the check and 1% AEP events shall be computed with the broad-crested weir equation:

Qr = Cd · L · h^1.5

where Qr is the overtopping flow (m³/s), L is the length of the overtopping section (m) and h is the depth of the headwater above the road crest (m). Cd shall be taken from HDS-5 for the road surface and the ratio of h to road width, and shall not exceed 1.66 (SI). The culvert and overtopping flows shall be balanced at a common headwater. The overtopping depths and hazard shall meet Chapter 6, Clause 6.12.

9.4.7 Outlet velocity. The outlet velocity at the design AEP and at the 1% AEP shall be computed and the outlet protected under Clause 9.6.

9.4.8 Barrels and debris.

  • (a) Multi-barrel culverts shall be avoided in debris-prone urban drains. Where they are used, one barrel shall carry the dry-weather flow, and the inlet shall have a debris fin or deflector.
  • (b) Culverts shall meet the minimum size and blockage checks of Chapter 6, Clauses 6.12.4 and 6.12.5.
  • (c) Culvert inverts shall match the bed of the drain. They shall not be set above the bed, which traps silt and water upstream.

9.4.9 Headwalls and cut-offs. Inlets and outlets shall have headwalls, wingwalls and cut-off walls designed to prevent piping and undermining.

Culvert inlet and outlet control Culvert hydraulics: inlet control and outlet control (profile, not to scale) (a) Inlet control Road HWi HWi depends only on Q and the inlet (shape, edge, skew); read from the HDS-5 inlet-control nomographs or equations. The barrel flows part full; barrel roughness, length and tailwater do not affect HWi. Control section near the inlet Low tailwater (b) Outlet control Road Energy grade line He Hf (barrel friction) Ho HWo TW H Barrel length L at slope S HWo = ho + H − L·S, with H = He + Hf + Ho and ho = max[TW, (dc + D)/2]. The barrel flows full or part full; roughness, length, slope and tailwater all matter. Design headwater = the greater of HWi and HWo (Clause 9.4).

Figure 9.1 — Culvert hydraulics: inlet control and outlet control. Original drawing for this Manual, adapted from FHWA, Hydraulic Design of Highway Culverts, HDS-5 (3rd ed., 2012).

Commentary. HDS-5 (3rd ed., FHWA-HIF-12-026, April 2012) merged the culvert design material of HEC-5, HEC-10 and HEC-13 and is the current FHWA culvert manual. The outlet-control equation in Clause 9.4.3 is the HDS-5 energy equation in SI units: the friction coefficient 19.63 equals 2g. The ke values in Table 9.1 are reproduced from HDS-5. The weir coefficient cap of 1.66 (SI) is the conversion of the APWA 5600 (2006) limit of C ≤ 3.0 (US units) for overtopping calculations. The headwater limits of Clause 9.4.5 are set by this Manual: HW/D ≤ 1.2 keeps the inlet from operating far into submerged-orifice flow at the design event, where small increases in flow give large increases in headwater. Clause 9.4.8(c) has no direct precedent; it is included because raised culvert inverts are common in Andhra Pradesh where a road is rebuilt on top of an old culvert, and they hold standing water and silt upstream.


9.5 Open channels

9.5.1 Flow computation. Open channels shall be designed by Manning's equation for uniform flow, with the n of Table 6.6. Water levels shall be computed by gradually varied flow (standard step) analysis where tailwater, bridges, culverts, bends or changes of section affect them, which in coastal Andhra Pradesh is the normal case.

9.5.2 Flow regime. At the design flow, the Froude number shall not exceed 0.8 (CPHEEO 2019, §5.3), unless the channel is designed as a supercritical chute. Flows with a Froude number between 0.8 and 1.2 are not permitted at the design flow in any channel.

9.5.3 Permissible velocities. Mean velocity at the design flow shall not exceed the limits of Table 9.2.

Table 9.2 — Maximum permissible mean velocities in channels

Lining or soil Maximum velocity (m/s) Source
Concrete lining 3.0 CPHEEO 2019 Table 5.11
Riprap lining 1.8 CPHEEO 2019 Table 5.11
Grassed lining 1.2 CPHEEO 2019 Table 5.11
Stabilised earthen channel (modified natural channel) 2.0, or the critical velocity if less CPHEEO 2019 §5.10.3
Unlined, fine sand 0.46 Fortier and Scobey (1926), clear water
Unlined, sandy loam 0.53 As above
Unlined, silt loam 0.61 As above
Unlined, firm loam 0.76 As above
Unlined, stiff clay 1.14 As above
Unlined, fine gravel 0.76 As above
Unlined, coarse gravel 1.22 As above

Flexible linings (vegetation, riprap, geosynthetics) may instead be designed by the permissible shear stress method of FHWA HEC-15, Design of Roadside Channels with Flexible Linings, 3rd edition (2005).

9.5.4 Longitudinal slope. In engineered channels, the longitudinal slope shall not exceed 0.4% for natural linings and 0.2% for concrete linings, unless drop structures (Clause 9.6.6) or a chute are provided (CPHEEO 2019, Table 5.11).

9.5.5 Freeboard and bends. Freeboard shall meet Chapter 6, Table 6.7, measured above the water level that includes superelevation at bends. Bend radii shall meet Chapter 6, Clause 6.7.10.

9.5.6 Side slopes. Unless a structural or geotechnical design supports a steeper slope:

  • (a) unlined earth channels shall have side slopes no steeper than 1V:2H; and
  • (b) grassed channels that are mown shall have side slopes no steeper than 1V:3H.

9.5.7 Low-flow channel. Channels with a bed width of 3 m or more shall have a defined low-flow channel that carries the dry-weather flow at the self-cleansing velocity of Clause 6.7.3.

9.5.8 Transitions. Changes of section shall use gradual transitions. Abrupt expansions and contractions are not permitted in supercritical flow.

9.5.9 Linings in high groundwater. Lined channels in areas of high groundwater or tidal influence shall have weep holes with filters, or shall be designed to resist uplift with the channel empty.

9.5.10 Natural channels. Natural channels shall be preserved where possible (CPHEEO 2019, §5.10.3 note; Chapter 7). Where a natural channel must be modified, its capacity shall meet the design AEP of Chapter 6 and its velocities shall meet Table 9.2.

Commentary. The lined-channel velocities and slopes are CPHEEO (2019) Table 5.11 values. The unlined-soil values are the classic Fortier and Scobey (1926) permissible velocities for clear water, as reproduced in Chow (1959). They are given for soils common in Andhra Pradesh (coastal sands, red sandy and loamy soils, delta alluvium and black cotton soils). The ban on Froude numbers between 0.8 and 1.2 extends CPHEEO's advice to avoid critical flow, where the water surface "becomes unstable and wavy" (§5.3). This extension is made by this Manual. The side slopes and the low-flow channel are also set by this Manual, because many Andhra Pradesh urban channels carry sewage-mixed dry-weather flow until the cross-connections of Chapter 8 are removed. A wide flat bed then deposits sludge across its whole width, and a low-flow channel keeps the dry-weather flow concentrated.


9.6 Energy dissipators, outlet protection and drop structures

9.6.1 When required. Outlet protection or an energy dissipator shall be provided at every pipe, culvert and channel outlet where the outlet velocity at the design AEP or the 1% AEP exceeds the permissible velocity of the receiving channel in Table 9.2, and at every outlet to an unlined channel, tank or waterbody.

9.6.2 Method. Energy dissipators and outlet protection shall be designed by the methods of FHWA HEC-14, Hydraulic Design of Energy Dissipators for Culverts and Channels, 3rd edition (2006), selecting the dissipator type by its range of application.

9.6.3 Riprap aprons. For a circular outlet discharging to a flat apron, the median riprap size shall be computed with the HEC-14 apron equation:

D50 = 0.2 · D · [Q / (g^0.5 · D^2.5)]^(4/3) · (D / TW)

where D50 is the median stone size (m), D is the culvert diameter or rise (m), Q is the design discharge (m³/s), g = 9.81 m/s² and TW is the tailwater depth (m). Where TW is not known, it shall be taken as 0.4D.

Apron length and thickness shall follow the HEC-14 riprap-class table (Table 9.3). The apron width at the outlet shall be at least 3D and shall flare to the downstream channel.

Table 9.3 — Riprap classes and apron dimensions (HEC-14)

Class D50 (mm) Apron length Apron thickness
1 125 4D 3.5 D50
2 150 4D 3.3 D50
3 250 5D 2.4 D50
4 350 6D 2.2 D50
5 500 7D 2.0 D50
6 550 8D 2.0 D50

Source: FHWA HEC-14 (2006), §10.2 and Table 10.1, as reproduced in state-agency design worksheets. Where the computed D50 exceeds Class 6, a riprap basin or a structural stilling basin shall be used.

9.6.4 Riprap filter and grading. Riprap shall be placed on a granular filter or a geotextile. Stone shall be angular, durable and graded so that the D50 of Clause 9.6.3 is met.

Riprap apron at a pipe or culvert outlet Riprap apron at a pipe or culvert outlet (plan and section, schematic, not to scale) (a) Plan Pipe or culvert Downstream channel ≥ 3D at outlet (9.6.3) Apron length La: 4D to 8D by riprap class (Table 9.3) Flares to the downstream channel; end width to be confirmed in design D Headwall (b) Section along the centreline Cut-off wall (9.4.9); depth to be confirmed in design TW: tailwater depth; where not known, 0.4D (9.6.3) Thickness: 2.0 to 3.5 × D50 by class (Table 9.3) Granular filter or geotextile (9.6.4) D D50 = 0.2 · D · [Q / (g^0.5 · D^2.5)]^(4/3) · (D / TW) (9.6.3) D50 above Class 6 (550 mm): riprap basin or stilling basin

Figure 9.2 — Riprap apron at a pipe or culvert outlet: apron width at least 3D at the outlet, flaring to the downstream channel; length and thickness from Table 9.3; stone on a granular filter or geotextile (Clauses 9.6.3 and 9.6.4). Original drawing for this Manual, adapted from FHWA, Hydraulic Design of Energy Dissipators for Culverts and Channels, HEC-14 (3rd ed., 2006), §10.2.

9.6.5 Stilling basins. Where velocities or Froude numbers are above the range of riprap aprons and basins, a structural stilling basin or impact basin shall be designed from HEC-14 or from the US Bureau of Reclamation basin types it describes.

9.6.6 Drop structures. Drop structures shall be used where the channel slope would otherwise exceed Clause 9.5.4 or the velocity limit of Table 9.2.

  • (a) For a straight vertical drop, the drop number D = q² / (g h³) shall be computed, where q is the unit discharge (m²/s) and h is the drop height (m). The pool geometry shall be set from the Rand (1955) relationships: drop length Ld/h = 4.30 D^0.27; pool depth Yp/h = 1.00 D^0.22; sequent depths y1/h = 0.54 D^0.425 and y2/h = 1.66 D^0.27.
  • (b) Baffled chutes and stepped drops shall be designed by HEC-14 or US Bureau of Reclamation methods.
  • (c) The height of a single vertical drop in a public drain shall not exceed 1.5 m. Drops shall have edge protection under Chapter 6, Clause 6.13.8.

9.6.7 Coastal and beach outfalls. Outfalls onto beaches or into estuaries shall be protected against wave action and scour. Where littoral sand can close the outfall, the outfall shall be designed so that it can be reopened by machine, and the drainage system shall be checked with the outfall closed under Chapter 5.

Commentary. HEC-14 (3rd ed., FHWA-NHI-06-086, July 2006) is the current FHWA energy-dissipator manual. The apron equation and the class table are from HEC-14 §10.2 (Equation 10.4 and Table 10.1). The equation and table are given here as reproduced in secondary design documents (a Tennessee handbook and a state-agency riprap worksheet). The 3D apron width is from the same sources. A Purdue study (JTRP) found the HEC-14 apron method somewhat conservative within its range of application. The Rand (1955) drop relationships are standard and are reproduced in Chow (1959). The 1.5 m limit on a single vertical drop has no direct precedent; this Manual sets it for public safety in urban drains.


9.7 Detention outlet structures

9.7.1 Primary outlet. The primary outlet of a detention facility shall:

  • (a) produce the release rates and drawdown times of Chapter 4;
  • (b) work without mechanical parts or operator action, except in pumped facilities (Clause 9.9);
  • (c) have no orifice smaller than 50 mm, and every orifice shall be protected by a trash screen (Clause 9.8.5); and
  • (d) be accessible for cleaning from the surface.

9.7.2 Orifices. Orifice flow shall be computed as:

Q = Cd · A · (2 g h)^0.5

where A is the orifice area (m²) and h is the head (m) on the centroid of the orifice, or the difference between the upstream and downstream water levels where the orifice is submerged. Cd shall be 0.60 for a sharp-edged orifice in a thin plate. Other edge conditions shall use published tested values.

9.7.3 Weirs. Weir flow shall be computed as Q = Cw · L · H^1.5, with:

  • (a) sharp-crested rectangular weirs: Cw = 1.84 (SI), with the effective length reduced by 0.1 H for each end contraction;
  • (b) V-notch weirs: Q = 1.38 · tan(θ/2) · H^2.5 (SI), where θ is the notch angle; and
  • (c) broad-crested weirs and spillway crests: Cw = 1.44 to 1.70 (SI), selected from published tables for the crest shape and head.

Submerged weirs shall be corrected for submergence from published relationships.

9.7.4 Stage–discharge rating. For multi-stage outlets (orifices and weirs in a riser, with an outlet pipe), the designer shall compute, at each stage, the discharge under every possible control (each orifice, each weir, riser crest, and the outlet pipe under inlet and outlet control) and use the smallest combined value. The rating shall be tabulated from the outlet invert to the emergency spillway crest plus the design head.

9.7.5 Tailwater. Ratings shall be computed with the tailwater of Clause 9.2.1. Where the receiving water can rise above the outlet, the outlet shall have a flap gate or non-return valve under Clause 9.10, and the storage shall meet the outfall-closed check of Chapter 5.

9.7.6 Emergency spillway. The emergency spillway shall pass the 1% AEP inflow with the primary outlet assumed blocked and the basin full at the start, with 0.3 m freeboard to the embankment crest. High-hazard basins shall also be checked for the 0.2% AEP inflow (Chapter 4).

9.7.7 Outlet pipes through embankments. Outlet pipes through embankments shall have a filter diaphragm or seepage collars to prevent piping along the pipe, and a flared or headwalled inlet.

9.7.8 Anti-vortex. Riser outlets with a design head above the riser crest greater than the riser diameter shall have an anti-vortex plate.

Commentary. The 50 mm minimum orifice with a trash screen, the emergency-spillway criterion and the drawdown times are core criteria of this Manual (Chapter 4). The minimum orifice is smaller than the APWA 5600 (2006, 5608.4) minimum of 3 in (about 75 mm). It allows the low release rates of the Chapter 4 mixed-frequency rule on small sites, and it relies on a good screen (Clause 9.8.5). The "no mechanical parts" rule follows APWA 5600 (2006, 5608.4), which requires the primary outlet to function unattended. The orifice and weir coefficients are standard textbook values (for example Brater and King, Handbook of Hydraulics; Chow 1959). The 1.84 sharp-crested coefficient and the 0.1H end-contraction correction are the Francis formula in SI units. The broad-crested range 1.44–1.70 is the SI equivalent of the US range 2.6–3.1 commonly tabulated. Clauses 9.7.7 and 9.7.8 follow common dam and detention practice.


9.8 Trash racks and screens

9.8.1 Where required. Trash racks or screens shall be provided:

  • (a) where an open drain enters a pipe, covered drain or culvert longer than 30 m (Chapter 6, Clause 6.13.4);
  • (b) at every detention outlet orifice (Clause 9.7.1);
  • (c) at the inlet of every pump sump (Clause 9.9); and
  • (d) at outfalls to waterbodies, as part of the gross pollutant trap of Chapter 8.

9.8.2 Conduit-entrance racks. Racks at the entrance to conduits and culverts shall have:

  • (a) clear bar spacing not less than 75 mm and not more than half the smallest internal dimension of the conduit;
  • (b) a gross area at least 4 times the conduit's cross-sectional area;
  • (c) a mean velocity through the rack at the design flow, with 50% of the rack blocked, of not more than 1.0 m/s; and
  • (d) an inclination no steeper than 1V:2H where the rack is to be raked by hand, with a working platform and handrail.

9.8.3 Head loss. Head loss through a clean rack shall be computed with the Kirschmer equation:

hr = β · (t / b)^(4/3) · (V² / 2g) · sin θ

where t is the bar thickness, b is the clear bar spacing, V is the approach velocity, θ is the angle of the rack from the horizontal, and β is the bar shape factor (2.42 for sharp-edged rectangular bars; 1.79 for circular bars). The HGL and headwater shall be checked with the rack 50% blocked (head loss computed with half the open area).

9.8.4 Overflow when blocked. Every rack shall have an overflow route so that a fully blocked rack does not flood buildings or exceed the limits of Chapter 6.

9.8.5 Detention outlet screens. Screens over detention orifices shall have openings smaller than the orifice they protect, and an open area at least 10 times the orifice area.

9.8.6 Pump sump screens. Bar screens at pump-station inlets shall have a clear spacing smaller than the largest solid the pumps can pass, as stated by the pump manufacturer. Screens shall be built in removable modules, and a mechanically raked screen shall be used where the design inflow exceeds 1 m³/s.

9.8.7 Safety. Racks at the entrance to long conduits shall prevent people from being drawn in. They shall be designed for the hydrostatic load of a fully blocked rack.

Commentary. CPHEEO (2019, §8.3.1.3) describes pump-station bar screens with a spacing of "approximately 58 mm", built in modules, with an emergency overflow in case of clogging. Clause 9.8.6 follows that approach but links the spacing to the pump's solids-passing size, which varies by pump. The 50% blockage check matches the grate clogging factor of Chapter 6. The Kirschmer equation and its shape factors are standard (Kirschmer 1926, as reproduced in hydraulic handbooks). The rack spacing, area ratio, through-velocity, the 30 m conduit length trigger, the 10× screen area for orifices and the 1 m³/s trigger for mechanical raking have no direct precedent and are set by this Manual.


9.9 Pumps and sumps

9.9.1 When pumping is used. Pumping shall be used only where gravity drainage cannot meet the requirements of Chapters 5 and 6, for example at road underpasses (Chapter 6, Clause 6.10.5), basements, low-lying areas and outfalls that are tide-locked under the outfall-closed check of Chapter 5.

9.9.2 Design inflow and storage. The station shall be designed with the inflow hydrograph routed through the catchment and any upstream storage. Pump capacity and storage shall be chosen together:

  • (a) the station shall meet the design AEP of the element it serves (for underpasses, the 2% AEP with a 1% AEP check);
  • (b) where the station serves a tidal outfall, storage plus pumps shall hold the 48 h design volume with the outfall throttled for the tidal-lock duration (default: two consecutive high tides of 6 h each), as required by Chapter 5; and
  • (c) the pumps shall be selected for the full range of static head between the lowest sump level against the lowest tailwater, and the highest tailwater (HAT plus surge plus 0.3 m).

9.9.3 Wet-well volume. The effective wet-well volume (between the pump-stop and the lowest pump-start level) shall be the greatest of:

  • (a) where variable-speed drives and automatic controls are installed, 5 minutes of the minimum inflow (CPHEEO 2019, §8.3.3);
  • (b) otherwise, 10 to 15 minutes of the peak inflow, or the volume needed for the pump manufacturer's minimum cycle time, from V = Q · t (CPHEEO 2019, Eq. 8.1); and
  • (c) for constant-speed pumps, the volume V = Θ · q / 4 for each pump, where Θ is the minimum cycle time recommended by the motor manufacturer and q is the pump capacity (FHWA HEC-24, 2001).

9.9.4 Duty and standby.

  • (a) Duty pumps shall be of the same size where practicable (CPHEEO 2019, §8.3.3).
  • (b) Standby capacity shall be at least equal to the largest duty pump, and not less than 50% of the number of duty pumps.
  • (c) Duty and standby roles shall alternate automatically.

9.9.5 Pump type. Pumps shall be solids-handling (non-clog) types suited to stormwater with sand and debris. Axial-flow pumps shall be used only behind a screen that meets Clause 9.8.6, because they cannot handle debris (CPHEEO 2019, §8.3.2).

9.9.6 Sump and intake design. Sump geometry, pump spacing, minimum submergence and approach flow conditions shall follow the pump manufacturer's requirements and ANSI/HI 9.8 (Rotodynamic Pumps for Pump Intake Design). A physical hydraulic model study shall be carried out where any pump exceeds 1 m³/s, or where the sump does not follow standard ANSI/HI 9.8 geometry. The minimum clear space between adjacent pumps or motors is 0.6 m for small and medium units and 1.0 m for large units (CPHEEO 2019, §8.2.5).

9.9.7 Silt and screens. A silt trap and a bar screen shall be provided upstream of the wet well (Clause 9.8.6; Chapter 6, Clause 6.13.3).

9.9.8 Controls and monitoring.

  • (a) Pumps shall be controlled by a primary level sensor (ultrasonic, radar or pressure) with an independent float-switch back-up.
  • (b) High-level and pump-fault alarms shall be sent by telemetry to the local body's control room.
  • (c) Sump levels, pump run hours and power status shall be logged and kept for at least 5 years.

9.9.9 Power supply.

  • (a) The station shall have two independent power sources: the grid supply and a standby generator (or a second independent grid feeder) able to run all duty pumps at once (CPHEEO 2019, §2.4.2.3(j)).
  • (b) Fuel for at least 72 hours of continuous operation of all duty pumps shall be stored on site, above the flood level of Clause 9.9.10.
  • (c) Changeover to standby power shall be automatic.

9.9.10 Flood protection of the station. The floor of the electrical and control room, the generator and the transformer shall be at least 0.5 m above the 1% AEP flood level at the station (Chapter 6, Clause 6.11). Access to the station for maintenance vehicles shall remain usable in the 1% AEP event.

9.9.11 Discharge. Each pump shall have its own rising main, or a non-return valve and an isolating valve where mains combine. Rising mains shall discharge into a delivery chamber or outfall fitted with a flap gate or non-return valve under Clause 9.10. Discharge piping shall be sized by a recognised friction formula (CPHEEO 2019, §8.3.9).

9.9.12 Emergency connections. Every station shall have a hard-standing area and a quick-coupling connection for mobile pumps to discharge into the delivery chamber.

Stormwater pump station schematic Stormwater pump station: wet well, screens, levels and outfall (section, not to scale) Panels, controls, standby generator Floor ≥ 1% + 0.5 m Incoming drain Silt trap and bar screen (Clause 9.8) Duty 1 Duty 2 Standby NRV + isolating valve on each main Inflow invert Standby start, alarm Duty 2 start Duty 1 start All pumps stop V = Q·t Delivery chamber Flap gate Tailwater (Ch 5) Receiving drain, river or creek Duty capacity, wet-well volume and controls: Clause 9.9. Standby ≥ largest duty pump. Power: two sources (grid + generator). The station and its storage are checked with the outfall closed for the tidal-lock duration (Chapter 5). Levels illustrative; set start and stop levels from the pump curves, the minimum submergence and the allowable starts per hour.

Figure 9.3 — Stormwater pump station: wet well, screens, levels and outfall. Original drawing for this Manual, adapted from CPHEEO, Manual on Storm Water Drainage Systems (2019), Chapter 8, and FHWA, Highway Stormwater Pump Station Design, HEC-24 (2001).

Commentary. CPHEEO (2019) Chapter 8 covers stormwater pumping: wet-well sizing (§8.3.3), pump types (§8.3.2), trash screens (§8.3.1.3), space requirements (§8.2.5) and the need for generator sets "as standby for emergency operation during failure of electricity" (§2.4.2.3). It recommends standby units of "minimum 50% of the duty pump units". Clause 9.9.4(b) is stricter: the standby must at least equal the largest duty pump, so the station still meets its design duty with its largest pump out of service. This stricter rule is set by this Manual. FHWA HEC-24 (Highway Stormwater Pump Station Design, FHWA-NHI-01-007, 2001) is the FHWA pump-station manual. The 72 h fuel storage is set by this Manual to match the 72 h design storm of Chapter 2. The model-study trigger, the telemetry and data-retention requirements, and the emergency connection have no direct precedent and are set by this Manual.


9.10 Tide gates, flap gates and non-return valves

9.10.1 Where required. Flap gates, tide gates or non-return valves shall be provided on every outfall whose invert is below the 1% AEP still-water level of the receiving water (Chapter 5).

9.10.2 Types. Acceptable devices are:

  • (a) hinged flap gates (cast iron, ductile iron, stainless steel, HDPE or composite);
  • (b) elastomeric in-line or end-of-pipe check valves (duckbill type); and
  • (c) penstocks or sluice gates, manual or motorised, as a secondary closure.

9.10.3 Secondary closure. Outfalls of 900 mm or more, and every outfall serving a pumped or storage system, shall have a penstock or stop-log slot upstream of the flap gate so that the gate can be maintained, and as a back-up if the gate jams open.

9.10.4 Hydraulics. The head loss through the device in the open position shall be taken from the manufacturer's tested data and included in the HGL (Chapter 6, Clause 6.8.7). Flap gates shall open at a small head difference (CPHEEO 2019, §6.3.10.1).

9.10.5 Sand and debris. At beach, estuary and creek outfalls where sand or debris can hold a gate open or shut:

  • (a) the gate shall be housed in a chamber with surface access, or elastomeric check valves shall be used; and
  • (b) the gate shall be inspected after every high-tide or surge event during the monsoon season (Chapter 10).

9.10.6 Materials. Hinges, pins, links and fixings shall be of corrosion-resistant material (CPHEEO 2019, §6.3.10.1). In coastal and tidal locations this means stainless steel grade 316, bronze or a non-metallic material (Clause 9.13).

9.10.7 Storage behind gates. Where gates close during a storm, the storage or pumping behind them shall meet the outfall-closed check of Chapter 5.

Commentary. CPHEEO (2019, §6.3.10.1) describes flap gates and flood gates at outfalls to tidal waters. It notes that "adequate storage may be necessary if pumping is to be avoided during the closure of the gate" and that hinge pins and links "should be of corrosion-resistant materials". Gates are required below the 1% still-water level because Andhra Pradesh outfalls are closed by the sea and by rivers in flood. Cyclone Hudhud raised the sea 1.4 m above the predicted tide at Visakhapatnam port on 12 October 2014 (IMD), and during the Budameru flood of September 2024, with the Krishna in record flood at Prakasam Barrage, Krishna water was reported to flow back into the Budameru Diversion Channel (CWC data and press reports, via SANDRP and The South First). Clauses 9.10.3 and 9.10.5 are set by this Manual because a flap gate jammed open by sand lets the sea back into the drain network, and one jammed shut blocks it.


9.11 Inlets and gratings

9.11.1 Hydraulics. Inlet capacity, spacing and clogging shall follow Chapter 6, Clause 6.6.

9.11.2 Load class. Gratings, covers and frames shall be rated for the traffic at their location. Load classes shall be those of IS 1726 (cast iron manhole covers and frames) or EN 124 (gully tops and manhole tops), at least:

  • (a) carriageways and medians: EN 124 class D400 or the equivalent heavy-duty IS class;
  • (b) kerb-side channel inlets within 0.5 m of the kerb: class C250 or equivalent; and
  • (c) footpaths and cycle tracks: class B125 or equivalent.

9.11.3 Grate pattern.

  • (a) Grates in carriageways, cycle tracks and footpaths shall not have openings parallel to the direction of travel wider than 25 mm.
  • (b) Grate types without tested capacity data shall be rated by the weir and orifice methods of FHWA HEC-22 (2024), with the clogging factors of Chapter 6.

9.11.4 Kerb openings. Kerb-opening inlets shall have a clear opening height of at least 100 mm and a length of at least 1.0 m. Where a kerb inlet discharges through the wall of a covered drain (Chapter 6, Clause 6.13.1), the opening shall be at road level.

9.11.5 Security. Gratings and covers on public land shall be hinged or locked to their frames, so that they cannot be removed without a tool.

9.11.6 Inlet chambers. Inlet chambers shall have the silt sump of Chapter 6, Clause 6.6.7, and shall be sized so that the sump can be emptied by a suction or grab machine.

Commentary. NDMA (2010, §4.13) cites IS 5961 for cast-iron gratings for drainage inlets. The load classes are based on the EN 124 classes used internationally. The 25 mm limit on parallel openings is set for cyclist and pedestrian safety. APWA 5600 (2006, 5604.2) requires kerb openings of at least 4 ft (about 1.2 m) long and 6 in (about 150 mm) clear height. Clause 9.11.4 sets smaller minimums suited to the narrower roads and lower kerbs common in Andhra Pradesh towns.


9.12 Manholes, junction chambers and access

9.12.1 Location and spacing. Manholes shall be provided at the locations and spacings of Chapter 6, Clause 6.7.11 and Table 6.8. Where pipes are too large for a standard manhole, a junction chamber with a riser to the surface shall be used (CPHEEO 2019, §11.3.7.3).

9.12.2 Minimum internal size. Manholes shall have at least the internal dimensions of Table 9.4 (CPHEEO 2019, §11.3.7.6):

Table 9.4 — Minimum internal size of manholes

Shape and depth Minimum internal size
Rectangular, depth below 0.9 m 900 mm × 800 mm
Rectangular, depth 0.9–2.5 m 1,200 mm × 900 mm
Circular, depth above 0.9 m and up to 1.65 m 900 mm diameter
Circular, depth above 1.65 m and up to 2.30 m 1,200 mm diameter
Circular, depth above 2.30 m and up to 6.0 m 1,500 mm diameter
Circular, depth above 6.0 m and up to 9.0 m 1,800 mm diameter

The manhole shall also be large enough to fit the largest pipe connected plus the benching on each side.

9.12.3 Access openings. The clear access opening of manholes and access chambers on public drains shall be at least 600 mm, so that cleaning equipment can be lowered.

9.12.4 Drops. Where the difference between incoming and outgoing inverts exceeds 0.6 m, a drop connection shall be provided. Below 0.6 m, the difference shall be taken up by adjusting the slope of the incoming pipe or the benching (CPHEEO 2019, §11.3.7.5). The invert drop across a manhole where pipe size changes shall be at least the following fraction of the difference in diameters (CPHEEO 2019, Table 11.6):

  • conduits below 400 mm: one-half;
  • 400 mm to 900 mm: two-thirds;
  • above 900 mm: four-fifths.

9.12.5 Benching. Manhole floors shall be benched to at least the crown of the outgoing pipe, with channels shaped to guide flow from each incoming pipe.

9.12.6 Surcharge. Manholes on mains where the 1% AEP HGL can rise above the cover (Chapter 6, Clause 6.8.4) shall have bolted, locked or hinged covers designed for that pressure.

9.12.7 Mechanical cleaning. Manholes, chambers and covered drains shall be designed for cleaning by machine (suction, jetting, grab or robotic equipment) from the surface. Fixed ladders shall be of corrosion-resistant, encapsulated material where provided.

Commentary. The size and drop requirements are from CPHEEO (2019) Chapter 11. The 600 mm access opening, the benching rule and the bolted covers are set by this Manual. Designing for mechanical cleaning supports the prohibition on hazardous manual cleaning under The Prohibition of Employment as Manual Scavengers and their Rehabilitation Act, 2013.


9.13 Materials and durability

9.13.1 Exposure classes. Concrete structures shall be designed for the exposure class of IS 456: 2000, Table 3. In Andhra Pradesh the minimum classes of Table 9.5 apply unless a site investigation shows a more severe condition:

Table 9.5 — Minimum IS 456 exposure classes for Andhra Pradesh locations

Location Minimum IS 456 exposure class
Inland drains and structures Moderate
Drains and structures in the coastal environment, and any drain that carries or may carry sewage-mixed flow Severe
Structures exposed to sea-water spray, or in contact with saline or aggressive groundwater Very severe
Structures in the tidal zone Extreme

9.13.2 Concrete. Minimum concrete grade, maximum water–cement ratio, minimum cement content and nominal cover to reinforcement shall be those of IS 456 for the exposure class. For the reader's convenience, IS 456 sets the minimum reinforced-concrete grades as M25 (moderate), M30 (severe), M35 (very severe) and M40 (extreme), and the nominal covers as 30, 45, 50 and 75 mm respectively.

9.13.3 Aggressive ground. Groundwater and soil at every structure in coastal and delta areas shall be tested for chlorides and sulphates. Cement type and concrete mix shall be chosen to suit the results under IS 456.

9.13.4 Sewage-mixed flow. Pipes and covered drains that carry, or may carry, sewage-mixed flow shall be protected against sulphide (crown) corrosion, by a sacrificial concrete thickness, a corrosion-resistant lining or a non-concrete pipe material.

9.13.5 Pipes. Concrete pipes shall comply with IS 458, with the class selected by structural design. Other pipe materials (for example ductile iron, HDPE or structured-wall plastic pipes) shall comply with the applicable Indian Standard and be approved by the approving authority.

9.13.6 Metalwork. Within 5 km of the coast, and in all tidal and saline locations:

  • (a) fixings, hinges, ladders, handrails and screen frames shall be stainless steel grade 316, or hot-dip galvanised steel with a protective coating, or a non-metallic material; and
  • (b) dissimilar metals shall be isolated from each other.

9.13.7 Masonry. New public drains in Tier A bodies shall be in reinforced or plain concrete. Brick or stone masonry may be used for drains in Tier B bodies only if it is plastered on the wetted face and meets the n value of Table 6.6.

Commentary. The IS 456 exposure classes and the grade and cover values are quoted from IS 456: 2000 (Tables 3, 5 and 16) for convenience. The standard governs, and designers shall use its current amendment. Assigning Andhra Pradesh locations to exposure classes, the 5 km coastal band, the sulphide-corrosion requirement and the ban on new masonry drains in Tier A bodies have no direct precedent and are set by this Manual. Drains that receive sewage cross-connections (a common condition, Chapter 8) generate hydrogen sulphide, which attacks unprotected concrete above the water line.


9.14 Submittal requirements

Every structure design shall be submitted with a Hydraulic Structures Report (Form 9-1) containing, as applicable:

  1. culvert calculations (HDS-5 or HY-8 output) with HWi, HWo, outlet velocity, tailwater, overtopping and the blockage check;
  2. channel water-surface profiles, velocities, Froude numbers and freeboard;
  3. outlet protection and dissipator design, with riprap sizing;
  4. detention outlet stage–discharge tables and the emergency spillway check;
  5. screen and rack design with the 50% blocked check;
  6. a pump station design report: inflow hydrograph, storage, pump curves and system curves, wet-well volume, controls, power supply and the Chapter 5 outfall-closed check;
  7. gate and valve selection with head-loss data;
  8. inlet, grate and cover load classes; and
  9. an exposure class and materials statement (Clause 9.13).

References (chapter)

  • Federal Highway Administration (2012). Hydraulic Design of Highway Culverts, Hydraulic Design Series No. 5, 3rd edition, FHWA-HIF-12-026.
  • Federal Highway Administration (2006). Hydraulic Design of Energy Dissipators for Culverts and Channels, Hydraulic Engineering Circular No. 14, 3rd edition, FHWA-NHI-06-086.
  • Federal Highway Administration (2005). Design of Roadside Channels with Flexible Linings, Hydraulic Engineering Circular No. 15, 3rd edition, FHWA-IF-05-114.
  • Federal Highway Administration (2024). Urban Drainage Design Manual, Hydraulic Engineering Circular No. 22, 4th edition, FHWA-HIF-24-006.
  • Federal Highway Administration (2001). Highway Stormwater Pump Station Design, Hydraulic Engineering Circular No. 24, FHWA-NHI-01-007.
  • FHWA Hydraulics Engineering publications listing. https://www.fhwa.dot.gov/Engineering/hydraulics/library_listing.cfm
  • MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Volume I, Part A: Engineering Design. §2.4.2.3, §5.3, Tables 5.5, 5.11, 5.12, §6.3.10.1, Chapter 8, Chapter 11. https://www.mohua.gov.in/static/uploads/2025/10/8a2456c722036d78c72a698898ef846d.pdf
  • Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (5604.2, 5608.4); and Version 2025.01 (Dec 2025).
  • Bureau of Indian Standards. IS 456: 2000, Plain and Reinforced Concrete — Code of Practice (Tables 3, 5 and 16).
  • Bureau of Indian Standards. IS 458, Precast Concrete Pipes (with and without Reinforcement) — Specification (current revision).
  • Bureau of Indian Standards. IS 1726, Cast Iron Manhole Covers and Frames; IS 5961, Cast Iron Gratings for Drainage Purposes; IS 12592, Precast Concrete Manhole Covers and Frames (current revisions).
  • European Committee for Standardization. EN 124, Gully tops and manhole tops for vehicular and pedestrian areas.
  • Hydraulic Institute. ANSI/HI 9.8, Rotodynamic Pumps for Pump Intake Design (current edition).
  • Indian Roads Congress. IRC:SP:13, Guidelines for the Design of Small Bridges and Culverts (current revision).
  • Chow, V.T. (1959). Open-Channel Hydraulics. McGraw-Hill. (Fortier and Scobey 1926 permissible velocities; Rand 1955 drop relationships.)
  • Fortier, S. and Scobey, F.C. (1926). Permissible canal velocities. Transactions of the ASCE 89.
  • Rand, W. (1955). Flow geometry at straight drop spillways. Proceedings of the ASCE 81.
  • Brater, E.F. and King, H.W. Handbook of Hydraulics. McGraw-Hill.
  • Tennessee Department of Environment and Conservation (2026). Erosion Prevention and Sediment Control Handbook, §4.3.6 Riprap Apron (reproduces the HEC-14 apron equation and table). https://www.tn.gov/content/dam/tn/environment/water/stormwater/epsc-handbook/dwr-npdes-sop-g-16-erosion-prevention-sediment-control-handbook-01092026-4.3.6%20-riprap-apron.pdf
  • Purdue University Joint Transportation Research Program. Study of riprap apron design at culvert outlets. https://docs.lib.purdue.edu/jtrp/1704
  • CIRIA (2019). Culvert, screen and outfall manual, C786. London: CIRIA.
  • National Disaster Management Authority (2010). National Guidelines: Management of Urban Flooding, §4.13.
  • Government of India. The Prohibition of Employment as Manual Scavengers and their Rehabilitation Act, 2013.

Annexes and forms

Annex / Form Content
9A HDS-5 inlet-control coefficients and worked culvert example in SI units
9B Standard drawings: headwalls, riprap aprons, drop structures, trash racks, detention risers
9C Pump station design checklist and standard control philosophy
Form 9-1 Hydraulic Structures Report checklist