Chapter 1Policy, Applicability and Adoption
1.1 Purpose and objectives
1.1.1 This Manual sets the minimum standards for the planning, design, construction, operation and maintenance of stormwater systems in Andhra Pradesh. It applies to private development and to public works, as set out in Clause 1.5.
1.1.2 The Manual has the following objectives:
- (a) to make stormwater management a condition of development approval, so that new development and redevelopment do not increase flood peaks or runoff volumes downstream;
- (b) to retain frequent rainfall on site, so that groundwater recharge is sustained and pollutant loads are reduced;
- (c) to size storage for the long-duration cyclone and depression storms of October–December and monsoon storms of June–September, as well as for short-duration intensities;
- (d) to design outfalls for tidal and river tailwater, including the case where the outfall is closed;
- (e) to protect tanks (cheruvulu), marshes, rivers, supply channels and surplus courses as part of the drainage system;
- (f) to give every element of the drainage network a safe overland path for the 1% AEP (100-yr) storm;
- (g) to make design inputs, approvals and facility records public, so that designs can be checked and repeated; and
- (h) to make sure that facilities, once built, are maintained and remain effective.
1.1.3 This Manual does not replace the rainwater harvesting (RWH) mandate, the Andhra Pradesh Building Rules, 2017 (APBR 2017), or the statutes on waterbodies. It adds runoff control requirements to them (Clause 1.8).
1.2 Stormwater management hierarchy
1.2.1 Every development to which Chapter 4 applies shall consider stormwater measures in the following order. A designer shall not use a lower measure in place of a higher one that is practicable on the site.
- Preserve — keep or restore natural drainage features, tanks, wetlands, permeable soils, trees and overland flow paths (Chapter 7).
- Retain — hold the runoff from the retention depth of Annex 2E on site, by infiltration, reuse or evapotranspiration (Chapters 4 and 8).
- Detain — store larger storms temporarily and release them at or below the rates in Chapter 4, checked against downstream and tailwater conditions (Chapters 4 and 5).
- Convey — carry the remaining flow safely in the minor system, and the 1% AEP flow in the major system (Chapters 6 and 9).
1.2.2 Maintenance underlies all four measures. A measure that cannot be maintained by its owner under Chapter 10 shall not be credited.
1.2.3 Credits from higher measures reduce the requirements of lower ones. Preserved areas and retained volume reduce detention storage as set out in Chapter 4.
Figure 1.1 — Stormwater management hierarchy: preserve, retain, detain, convey, with maintenance underlying each measure. Original drawing for this Manual, adapted from Mid-America Regional Council / Kansas City Metro Chapter APWA, "Layers of Stormwater Management", APWA 5600 Manual Factsheet, 2025 (concept).
Commentary. The order follows the "layers" of Kansas City Metro APWA Section 5600, Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet, 2025). The same logic is behind Georgia's runoff-reduction standard and CSE's "attenuate and infiltrate first" principle (CSE, 2023). For Andhra Pradesh, the top layer has a particular meaning: much of the State's flood storage sits in its tanks and in Kolleru. The first Census of Water Bodies counted 1,90,777 water bodies in the State, 1,13,425 of them tanks, and reported encroachment in 3,920 (Ministry of Jal Shakti, 2023). Kolleru is listed by Ramsar as "a natural flood balancing reservoir" between the Godavari and Krishna deltas, and the Supreme Court recorded in 2006 that bunds raised inside it had diminished its retention capacity and submerged upstream mandals. Losing that storage cannot be offset economically by pipes.
1.3 Legal basis and status
1.3.1 Notification. This Manual shall be given statutory effect by the Government of Andhra Pradesh through:
- (a) an amendment to APBR 2017 that makes compliance with this Manual a condition of planning permission, building permit, layout approval and completion certificate, for development to which Clause 1.5 applies; and
- (b) bye-laws or standing orders of each urban local body (ULB), adopting the Manual for works executed or approved by that ULB, including the ULB's own drains and roads.
1.3.2 Higher State standards. The design return periods and performance criteria of this Manual exceed the national advisory minimums of the CPHEEO Manual on Storm Water Drainage Systems (2019). The State shall constitute, by notification, a high-powered committee (the State Stormwater Technical Committee, Clause 1.9) to adopt these higher standards. This is the route that CPHEEO (2019) provides for higher return periods.
1.3.3 Precedence. Within its scope, this Manual governs where it is stricter than CPHEEO (2019), IRC:SP:42-2014, IRC:SP:50-2013 or any departmental standard. Where a statute or statutory rule sets a stricter requirement (for example a waterbody setback), the statute governs.
1.3.4 Design-practice standard for public works. Departments and ULBs that procure drainage, road or waterbody works shall require compliance with this Manual in detailed project reports (DPRs) and contracts, from the dates in Clause 1.11.
Commentary. APBR 2017 was issued by G.O.Ms.No.119, Municipal Administration and Urban Development (MA&UD) Department, dated 28-03-2017, on the model of MBBL 2016, and applies in the APCRDA area outside the Capital City Area, in every Metropolitan Region and Urban Development Authority, Municipal Corporation, Municipality and Nagar Panchayat, and in Gram Panchayat areas under notified Master Plans. It already carries rainwater harvesting as a condition of the Occupancy Certificate (Rules 152–155), green buffers along waterbodies (Rule 54(11)), a bar on permits for land liable to flood or in natural waterways (Rule 54(9)(f) and (h)) and a minimum plinth of 450 mm (Rule 4(1)(a)(i)). The Andhra Pradesh Land Development (Layout and Sub-division) Rules, 2017 (G.O.Ms.No.275, 18-07-2017) repeat the buffers at Rule 8(11) and require layout infrastructure "as per the specifications approved by the Competent/Executive Authority" (Rule 14). APBR 2017 is the natural instrument for a statewide condition of approval. It is amended regularly: G.O.Ms.No.273 of 19-12-2025 amended it without changing the drainage, waterbody or rainwater harvesting rules. MoHUA told Parliament in July 2026 that urban flooding "falls under the purview of the State Governments and the ULBs" and listed the CPHEEO manual among "advisory guidelines" (Lok Sabha AU1847). The State therefore needs no central approval to adopt higher standards. CPHEEO's Note 2 to Table 4.1 (§4.4.1.4) allows "a high powered committee constituted by State/UT Government through a notification" to adopt higher return periods. Clause 1.3.2 uses that route so that higher standards are on record for centrally funded schemes.
1.4 Definitions
1.4.1 The following terms apply throughout this Manual. Chapter-specific terms are defined in each chapter (for example Clause 2.2).
| Term | Meaning in this Manual |
|---|---|
| Approving Authority (the Authority) | The body that grants planning permission, building permit or layout approval for a development, or that sanctions a public work: APCRDA, an Urban Development Authority (including VMRDA), DTCP where the rules require its approval or opinion, or a Municipal Corporation, Municipality, Nagar Panchayat or Gram Panchayat within the powers delegated to it under APBR 2017, or a department for its own works. |
| Applicant | The owner, developer or department that seeks approval, and its successors in title. |
| Development | Any building, layout, sub-division, road, paving or land-use change that requires approval under APBR 2017 or that is executed as a public work. |
| Redevelopment | Development on a site where impervious cover already exists. |
| Land disturbance | Clearing, grading, excavation, filling or paving of land, measured in plan area over the whole of a common plan of development (Clause 1.5.5). |
| Impervious area | Roofs, paving, compacted gravel, decks and other surfaces that prevent infiltration. Permeable paving designed to Chapter 8 is counted as pervious only for the area it treats. |
| New or replaced impervious area | Impervious area created, or removed and rebuilt down to the subgrade, by the development. Resurfacing that leaves the base in place is not "replaced". |
| Retention | Permanent removal of runoff from the drainage system on site, by infiltration, reuse or evapotranspiration (Chapter 4). |
| Detention | Temporary storage of runoff with a controlled outlet, emptied after the storm (Chapter 4). |
| Rainwater harvesting (RWH) | Collection of rainfall for supply or recharge under the RWH mandate. RWH storage is not detention unless Chapter 4 allows it. |
| Minor system | Drains, pipes and inlets designed for the minor-system AEP of Chapter 6. |
| Major system | The overland and floodway path that carries the 1% AEP (100-yr) flow (Chapter 6). |
| Pre-development condition | Greenfield: open land in good condition for the mapped hydrologic soil group. Existing impervious cover is not counted (Chapter 3). |
| Flood-sensitive catchment | The Budameru catchment in and above Vijayawada, the Kondaveeti Vagu and Pala Vagu catchments of the Amaravati capital city, the built-up areas within the Kolleru lake extent, the Swarnamukhi and tank-cascade catchments of Tirupati, and any catchment the Authority notifies (Chapter 4; Annex 1B). |
| Waterbody | A river, stream, canal, tank (cheruvu), lake, pond, marsh, supply channel or surplus course, whether perennial or seasonal (Chapter 7). |
| Regional facility | A detention, retention or tank storage facility serving more than one development, built or restored under a basin plan (Chapter 4). |
| Tier A / Tier B authority | An Approving Authority classed under Clause 1.6. |
| Policy supplement | The set of adoptable alternative clauses in Clause 1.7 and Annex 1C. |
| Drainage report | The preliminary or final report required by Chapter 10. |
| Registered professional | A person registered under APBR 2017 to prepare and sign the relevant plans, with any further qualification required by Clause 10.6. |
| Compliance calculator | The State-issued tool for computing and reporting compliance (Clause 10.5). |
| Maintenance declaration | The registered undertaking by an owner to maintain a stormwater facility (Clause 10.10). |
| Variance | Approval to depart from a numeric requirement, with equivalent performance shown (Clause 1.10). |
| Waiver | Approval that a requirement does not apply to a site, on the grounds in Clause 1.10. |
| Notified | Published by the Government or the State Stormwater Technical Committee in the Andhra Pradesh Gazette. |
Commentary. "Replaced" impervious area is defined to the subgrade so that redevelopment of a fully paved site is captured, while routine resurfacing is not. This follows the approach of the APWA 5600 (2025.01) redevelopment triggers (MARC Supplement, 2025).
1.5 Applicability
1.5.1 Who is covered. This Manual applies to:
- (a) all development requiring planning permission, building permit or layout approval under APBR 2017;
- (b) all drainage, road, bridge, culvert, waterbody and flood-mitigation works executed by a ULB, a State department, a board, or a State undertaking; and
- (c) works executed by Central agencies or their contractors within Andhra Pradesh, to the extent that the Authority's approval or no-objection is required.
1.5.2 Retention and detention threshold. Chapters 4 and 5 (retention, detention, downstream and tailwater analysis) apply to any development that, over the common plan of development, involves:
- (a) land disturbance of 0.1 ha or more; or
- (b) new or replaced impervious area of 500 m² or more.
1.5.3 RWH. The existing RWH mandate continues to apply as set by section 17 of the Andhra Pradesh Water, Land and Trees Act, 2002 and Rule 152 and Table 35 of APBR 2017: to premises and plots of 200 m² and above, and to every commercial, public, group housing and other non-residential building whatever its plot size, as now. This Manual does not change it.
1.5.4 Provisions that apply at every size. The following apply to all development under Clause 1.5.1, whatever its size, unless exempted by Clause 1.5.8:
- (a) no sewage connection to a storm drain (Chapter 8);
- (b) lowest habitable floor and openings at or above the 1% AEP level plus 0.5 m, where a 1% AEP level is mapped or determinable (Chapter 6);
- (c) waterbody setbacks and the no-fill zone (Chapter 7); and
- (d) no obstruction of a natural drainage path or major-system flow path (Chapter 6).
1.5.5 Common plan of development. The thresholds of Clause 1.5.2 apply to the total area of a development, including all phases, plots and sub-divisions under one layout approval or one ownership at the date of application. A development shall not be divided to avoid the thresholds.
1.5.6 Redevelopment. For redevelopment, the thresholds apply to new plus replaced impervious area. Retention and detention apply to the whole of the new and replaced impervious area, and the pre-development condition is greenfield (Clause 1.4). Where greenfield control cannot be achieved on a constrained redevelopment site, the relief route of Clause 4.5.6 applies: a minimum on-site cut of 50% from existing peaks, with the shortfall paid as fee-in-lieu into basin storage.
1.5.7 Linear public works. For roads, widening and other linear works, the impervious area threshold applies to the added impervious area within each drainage catchment crossed. Retention and detention shall be provided within the right of way, or in a regional facility under Chapter 4, where the right of way cannot hold them.
1.5.8 Exemptions. The following are exempt from Chapters 4 and 5:
- (a) a single dwelling on its own plot, where the thresholds of Clause 1.5.2 are not met; and
- (b) linear road resurfacing that adds no impervious area.
Exempt development remains subject to the RWH mandate and to Clause 1.5.4.
1.5.9 Applicability determination. The Applicant shall record the applicability decision on Form 1-1 (Applicability Determination) with the first submittal under Chapter 10. The Authority may confirm or correct it at the pre-application stage.
Figure 1.2 — Applicability decision flowchart for Clause 1.5. Original drawing for this Manual.
Commentary. The thresholds have no single direct precedent; they are set by this Manual. Precedents span a wide range:
- Singapore controls peak runoff from developments of 0.2 ha or more (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5).
- Malaysia's 2008 DID checklist used on-site detention for sites up to 0.1 ha and community ponds above that.
- The APWA 5600 (2025.01) Policy Supplement offers alternative triggers of ¼ acre (about 0.1 ha) disturbed, or 1 acre (about 0.4 ha) with 10,000 sq ft (about 930 m²) impervious, and warns agencies not to exceed a 1-acre trigger.
- MBBL 2016 makes recharge mandatory for buildings over 500 m².
The 0.1 ha / 500 m² trigger sits at the strict end of these, because typical Andhra Pradesh plots are small and the cumulative effect of many small plots is what fills Visakhapatnam's drains. The self-certification route of APBR 2017 for non-high-rise buildings (2025) is unaffected for small buildings that fall under the single-dwelling exemption or below the thresholds.
Clause 1.5.4(b) has no direct precedent; this Manual sets it because floor levels are the cheapest protection a building can have, and it would be perverse to protect only large developments. Where no 1% AEP level is mapped, Chapter 6 gives the method for small sites.
1.6 Tiered adoption
1.6.1 Tier A authorities. The following are Tier A:
- (a) Greater Visakhapatnam Municipal Corporation and Vijayawada Municipal Corporation;
- (b) all Approving Authorities within the area of the Andhra Pradesh Capital Region Development Authority (APCRDA), as notified from time to time, including the Municipal Corporations, Municipalities and Gram Panchayats in it; and
- (c) the Municipal Corporations of Guntur, Nellore, Tirupati, Kakinada, Rajamahendravaram and Kurnool, and every other Municipal Corporation in the State.
1.6.2 Tier B authorities. All other Municipalities and Nagar Panchayats are Tier B.
1.6.3 What differs between tiers. All criteria of this Manual apply in both tiers. The tiers differ only in method and review:
Table 1.1 — Differences between Tier A and Tier B authorities
| Item | Tier A | Tier B |
|---|---|---|
| Performance criteria (Chapters 2–9) | Apply in full | Apply in full |
| Hydrologic method for storage | Hydrograph method (Chapter 3) | Hydrograph method, or the design-aid route of Clause 1.7 where eligible |
| Compliance calculator (Clause 10.5) | Required as a summary | Required; may be the sole calculation on the design-aid route |
| Policy supplement alternatives (Clause 1.7) | Only with State Stormwater Technical Committee concurrence | May be adopted by council resolution |
| Technical review | By the Authority | By the Authority, with DTCP regional support or an empanelled reviewer (Clause 10.7) |
| Flood-sensitive catchment rule | Applies | Applies |
1.6.4 Moving between tiers. A Tier B authority may opt into Tier A by council resolution. The Government may notify a Tier B authority as Tier A when it becomes a Corporation, joins the area of the Andhra Pradesh Capital Region Development Authority (APCRDA), or is found by a post-event review (Clause 10.16) to need the full methods.
1.6.5 Flood-sensitive catchments override tier. In a flood-sensitive catchment, whatever the tier, the alternatives of Clause 1.7 are available only as Table 1.2 allows: S-1 (the design-aid route) for sites of 0.5 ha or less (Clause 4.14.1), and S-5 fee-in-lieu where a basin plan has been notified (Clause 1.10.3(d)). S-2, S-3 and S-4 are not available.
Commentary. Greater Visakhapatnam Municipal Corporation, with its own engineering wing, and a Nagar Panchayat with one assistant engineer cannot be asked to review the same hydrograph models. The Kansas City solution was to keep one regional standard and publish adoptable alternatives for the most contested criteria, so that smaller agencies can "opt down" without leaving the standard (MARC Supplement, Nov 2025). The tiers here keep the performance criteria the same in both tiers and vary only the method, so that a building in a Tier B town is protected to the same level as one in Visakhapatnam.
1.7 Policy supplement: adoptable alternatives
1.7.1 The Government shall publish, with this Manual, a Policy Supplement (Annex 1C) of alternative clauses. An Approving Authority may adopt one or more alternatives under the conditions in Clause 1.7.3.
1.7.2 The alternatives are:
Table 1.2 — Policy supplement: adoptable alternatives S-1 to S-5
| No. | Main-text requirement | Adoptable alternative | Eligibility |
|---|---|---|---|
| S-1 | Storage sized by hydrograph method (Chapter 3) | Design-aid route: retention and detention volumes taken from the unit-storage tables (m³ per ha, by rainfall zone, soil group and impervious fraction) in Annex 4 and the compliance calculator | Sites ≤ 2 ha outside flood-sensitive catchments; ≤ 0.5 ha within them (as Clause 4.14.1) |
| S-2 | Release rate Q_post(T) ≤ 0.9 × Q_pre(T), computed for the site | Permissible site discharge (PSD): a tabulated unit-area release rate (m³/s/ha) by zone and AEP, derived from the 0.9 × Q_pre rule | Any site outside flood-sensitive catchments |
| S-3 | Waterbody setback extended to the mapped 1% AEP flood extent plus margin (Chapter 7) | Fixed-width setback table by waterbody class, where no 1% AEP extent is mapped. Never less than the Zone 1 minimum of Clause 7.4.7 | Waterbodies with no mapped 1% AEP extent |
| S-4 | Downstream analysis by hydraulic model (Chapter 5) | Screening checklist of downstream capacity and known flooding, with a model only where the screen fails | Sites < 1 ha, outside flood-sensitive catchments, not discharging to a tidal outfall |
| S-5 | On-site detention | Fee-in-lieu toward a regional facility or restored tank storage in a master-planned basin (Chapter 4) | Where a basin plan has been notified |
1.7.3 Conditions on adoption.
- (a) An alternative shall not lower any criterion below the values of this Manual. S-1 and S-2 are simplified methods for meeting the same criterion. They are not lower criteria.
- (b) A Tier B authority adopts an alternative by council resolution, sent to the State Stormwater Technical Committee within 30 days. A Tier A authority needs the Committee's concurrence before adoption.
- (c) The adopted alternatives shall be published on the Authority's website and in the register of Clause 10.17.
- (d) Retention (Annex 2E depth) cannot be replaced by any alternative, except where fee-in-lieu under S-5 funds equivalent retention in the same basin.
- (e) The tables for S-1, S-2 and S-3 shall be issued by the State Stormwater Technical Committee, and reviewed with Chapter 2 (Clause 2.14).
Commentary. The supplement follows the model of the APWA 5600 (2025.01) Policy Supplement, which gives alternatives for the four most contested criteria (applicability, Rational Method limits, stream setback trigger, and Zone 2 setback width). Two of those map onto S-3 and onto the applicability threshold of Clause 1.5.2. Alternative S-3 copies the APWA answer to the same problem: the 1% AEP extent is not mapped for small drainage areas, so a fixed-width table is offered. S-2 follows the Kansas City 2011 shift from "match existing" to fixed unit-area release rates. Local agencies preferred a set rate because existing conditions were hard to determine consistently (MARC Evolution deck). It also reflects the Sydney Water permissible site discharge (PSD) method. The 2 ha / 0.5 ha limits for S-1 (matching Clause 4.14.1) and the 1 ha limit for S-4 have no direct precedent; they are set by this Manual.
1.8 Relationship with other instruments
1.8.1 This Manual shall be applied together with the instruments below. Where they overlap, Clause 1.3.3 governs.
Table 1.3 — Relationship with other instruments
| Instrument | Relationship |
|---|---|
| RWH mandate (APWALTA 2002, s.17; APBR 2017, Rules 152–155 and Table 35) | Continues unchanged from 200 m², and for all commercial, public, group housing and other non-residential buildings; RWH remains a condition of the Occupancy Certificate. Neither instrument sets a volume or depth. RWH storage is not detention unless it is a dedicated empty-on-arrival volume with an outlet, and RWH sumps are assumed full at the start of October–December storms (Chapter 4). Recharge structures may count toward retention where they meet Chapters 4 and 8. |
| Waterbody buffers (APBR 2017, Rule 54(11); Layout Rules 2017, Rule 8(11)) | Continue as statutory minima: no building or development in a river or nala bed or within the FTL of a lake, tank, cheruvu, kunta or shikam land; 30 m from the FTL of tanks of 10 ha or more; 9 m from smaller tanks and shikam land; 9 m from canals, vagus, nalas and storm water drains more than 10 m wide and 2 m from those up to 10 m wide; for rivers, 100 m outside and 50 m within local-authority limits in the 2017 text [TBC: whether G.O.Ms.No.223 of 2018 changed the 100 m figure in APBR]. FTL and river boundaries are as certified by WRD and the Revenue Department. The setbacks of Chapter 7, including a maintenance corridor wider than the 2 m drain buffer, apply in addition; where they are wider, this Manual is stricter than the rules. |
| Flood-liable land and natural waterways (APBR 2017, Rule 54(9)(f) and (h); Layout Rules 2017, Rule 8(9)) | Continue. A plot barred by these rules is not made buildable by compliance with this Manual. Where an owner seeks to prove under Rule 54(9)(f) that a site will not be subject to flooding, the proof should include the 1% AEP level, floor levels, flow paths and flood storage of Chapters 6 and 7. |
| Layout Rules 2017 (open space and utilities, Rule 13; specifications, Rule 14) | Open space (10% of the layout) may hold multi-use retention or detention, for example a sunken playfield, provided it remains usable recreational space outside storm periods and is designed to Chapter 4. Utility sites may hold RWH structures. This Manual is offered as the drainage specification under Rule 14 for a Competent Authority that chooses to adopt it. |
| Master Plans and Zonal Development Plans (APCRDA Act, 2014; AP Metropolitan Region and Urban Development Authorities Act, 2016; AP Town Planning Act, 1920) | A Master Plan or Zonal Development Plan may vary the default buffers of Rule 54(11) (Rule 54(11)(c)); it shall not reduce them below the Zone 1 minimum of Clause 7.4.7 for development to which this Manual applies. Flood-sensitive catchments and drainage corridors should be shown on the plan maps. Land for regional facilities should be reserved in the plan. |
| AP Water, Land and Trees Act, 2002 (ss. 23 and 35(2)) | Waterbodies and nalas may be notified, demarcated and cleared of encroachment, and encroaching a tank, nala or drainage course is an offence. The setbacks and storage rules of Chapter 7 apply in addition. |
| AP Municipalities Act, 1965 (ss. 133, 147, 153 and 155) and the Municipal Corporation Acts | Public drains and watercourses vest in the council, except irrigation works (s.133 proviso), and may not be obstructed (s.153). The Commissioner may direct how roof water is discharged (s.155), which is a route for the ULB bye-law of Clause 1.3.1(b). Outfalls into irrigation tanks, canals and drains need WRD consent (Chapters 5 and 7). |
| WRD delta drains and irrigation canals (AP Drainage Cess Act, 1985) | The Act levies a cess for the drainage of the Krishna, Godavari and Pennar deltas, whose major drains are WRD works. A connection to them needs WRD consent and an allotted discharge, with the tailwater checks of Chapter 5. Irrigation canals are not stormwater outfalls without WRD permission. |
| CRZ Notification 2019 and the Andhra Pradesh Coastal Zone Management Plan | Governs development along the coast and tidal waters (APBR 2017, Rule 54(9)(g) and 54(11)(d)). The CZMP under CRZ 2019 is still a draft; until it is approved, the CZMP prepared under CRZ 2011 applies. Where a CRZ width is wider than the setback of Chapter 7, the CRZ width governs (Clause 1.3.3). |
| Kolleru Wildlife Sanctuary (G.O.Ms.No.120 EFS&T, 04-10-1999) and Ramsar site | No fill, bund or drain re-routing within the sanctuary boundary (+5 ft MSL contour). The lake extent up to the +10 ft contour should be treated as flood storage under the no-fill and compensatory-storage rules of Chapter 7. |
| CPHEEO Manual on Storm Water Drainage Systems (2019) | Engineering reference. This Manual sets higher return periods under Clause 1.3.2. |
| NDMA Guidelines on Management of Urban Flooding (2010) and MoHUA SOP (2017) | This Manual puts into effect the NDMA directives on catchment-based design, detention and retention, waterbody protection and climate-adjusted IDF. |
| NDMA Urban Flood Risk Management Programme (UFRMP) and AMRUT 2.0 | Works funded under these programmes shall comply with this Manual. The development controls of Chapters 4–5 protect the capacity those works create. |
| IRC:SP:42-2014 and IRC:SP:50-2013 | Apply to road drainage only where they do not conflict with Chapter 6. |
| MBBL 2016, Chapter 9 | Model for RWH and for the inspection regime in Chapter 10. |
Commentary. RWH in Andhra Pradesh is framed as a water supply and recharge measure. It works well for that purpose. It cannot, however, be relied on for flood control in the monsoon, because RWH sumps are usually full or the ground saturated by the time an October–November cyclone or depression arrives after weeks of rain. The Manual therefore keeps harvest volume and attenuation volume apart, while letting recharge count as retention where it truly removes water from the system.
In its audit of the preservation of water bodies, the CAG recalled the Ministry of Urban Development's 2013 advisory that a storm water management plan be prepared for each city, and found none in the ULBs it test-checked (CAG, Report for the year ended March 2018, Ch. III). In Amaravati, trunk packages that included "reservoirs and development of river streams" had ₹3,213.41 crore spent and idle, and the "Blue Master Plan" for flood protection was still at a preliminary stage (CAG, Report for the year ended March 2021, para 2.1). No development-control condition in the State limits the runoff from new plots into the drains and streams such works create. Linking Chapters 4–5 to approvals closes that gap.
No flood plain zoning law has been enacted in Andhra Pradesh, according to national reporting (Deccan Herald, 2024). Rule 54(11)(c) of APBR 2017 lets a Master Plan or Zonal Development Plan set its own waterbody buffers. Showing flood-sensitive catchments, drainage corridors and regional facility sites on those plans now is cheaper than retrofitting later.
1.9 Roles and responsibilities
1.9.1 The responsibilities below apply under this Manual. They do not change any agency's statutory powers.
Table 1.4 — Roles and responsibilities under this Manual
| Agency | Role under this Manual |
|---|---|
| Municipal Administration and Urban Development (MA&UD) Department | Would own the Manual. Would issue the APBR 2017 and Layout Rules 2017 amendments. Would constitute and service the State Stormwater Technical Committee. |
| State Stormwater Technical Committee (Clause 1.3.2) | Would adopt higher standards, issue Annexes, tables and the compliance calculator, concur with Tier A alternatives, decide variances referred to it and review the Manual (Clause 1.12). |
| Directorate of Town and Country Planning (DTCP) | Would approve or give its opinion on larger developments and layouts where the rules require it, and post-verify approvals above its thresholds. Would provide technical support to Tier B authorities and maintain the empanelled reviewer list (Clause 10.7). |
| APCRDA and its delivery company (ADCL) | Approving Authority in the APCRDA area within its powers. Would apply this Manual to the capital city drains, streams, reservoirs and flood pumping it designs and builds, and embed flood-sensitive catchments and regional facility sites in its plans. |
| VMRDA and the other Urban Development Authorities | Approving Authority for development outside the powers delegated to local bodies. Would embed flood-sensitive catchments and regional facility sites in Master Plans and Zonal Development Plans. |
| Municipal Corporations (including GVMC), Municipalities and Nagar Panchayats | Approving Authority for building permits and layouts within their delegated powers, through the online building permission system. Owner of road-side, secondary and outfall drains. Would receive handed-over assets (Clause 10.14), and inspect and enforce (Clauses 10.12–10.15). |
| Public Health and Municipal Engineering Department (PHMED) | Designs and builds drainage works for ULBs and hands them over. Would apply this Manual to those designs. |
| Commissioner and Director of Municipal Administration (CDMA) | Supervises ULBs and centrally funded urban schemes. Would require compliance with this Manual in drainage works it funds or monitors. |
| Water Resources Department (WRD) | Custodian of rivers, vagus, diversion channels (including the Budameru and its diversion channel), delta drains, irrigation canals and tanks. Would provide FTL, surplus-weir (alugu, kalingulu) levels, design water levels and operating rules (Chapters 5 and 7), certify FTL and river boundaries with the Revenue Department, consent to outfalls into its works and concur with regional tank-storage credits (Chapter 4). |
| Andhra Pradesh State Disaster Management Authority (APSDMA) and District Disaster Management Authorities | Would hold hazard and flood maps, notify or recommend flood-sensitive catchments and lead the post-event review (Clause 10.16). |
| Revenue Department | Maintains land and waterbody records, certifies FTL and river boundaries with WRD, and evicts encroachments on tank beds and watercourses. |
| Andhra Pradesh Pollution Control Board (APPCB) | Would act on dry-weather flow and sewage reaching drains, rivers and the sea (Chapter 8). |
| R&B Department, NHAI, Indian Railways and other road and rail owners | Would apply this Manual to road drainage (Chapter 6), culverts and linear works (Clause 1.5.7), and match culvert capacity to the drains they connect. |
| Andhra Pradesh Coastal Zone Management Authority (APCZMA) | Advises on CRZ limits for coastal sites and outfalls. |
Commentary. Ownership of Andhra Pradesh's urban drainage is split three ways. Natural streams, vagus, diversion channels and delta drains are WRD works; road-side and outfall drains in towns belong to the ULB, though PHMED often designs and builds them; and in the Amaravati capital city APCRDA and ADCL build both the drains and the flood system. The 2024 Vijayawada flood came mainly from the Budameru, a WRD stream, not from the city drains, and after it the MA&UD Minister ordered encroachments removed from city outfall drains to the Krishna, one of them narrowed from 10 ft to 2 ft, while a WRD technical committee examined the Budameru banks (Deccan Chronicle, 26 Jul 2025). A manual that names one owner for each task does not fix institutions by itself, but it removes ambiguity about who signs what.
1.10 Variances and waivers
1.10.1 Variance. The Authority may grant a variance from a numeric requirement where the Applicant shows, through a report certified under Clause 10.6, that:
- (a) compliance is impracticable because of site conditions such as a high groundwater table, contaminated soil, rock, or a site area too small for the required facility; and
- (b) the proposed alternative gives equal or better performance at the downstream point of Chapter 5, or the shortfall is made up by fee-in-lieu or off-site works in the same catchment.
1.10.2 Waiver. The Authority may waive Chapter 4 detention requirements (not retention) where a hydraulic analysis certified under Clause 10.6 shows that the site discharges directly to the sea, or to a tidal reach with no flood-prone property downstream, and that undetained flow does not worsen the outfall-closed condition of Chapter 5.
1.10.3 No variance or waiver. No variance or waiver shall be granted for:
- (a) a sewage connection to a storm drain;
- (b) the lowest habitable floor level of Chapter 6;
- (c) any reduction of a waterbody setback below the Zone 1 minimum of Clause 7.4.7, or any fill or construction in the no-fill zone of Chapter 7; or
- (d) the retention requirement in a flood-sensitive catchment, except by fee-in-lieu under Clause 1.7.
1.10.4 Procedure.
- (a) The request shall be made on Form 1-2 (Variance / Waiver Request) with the preliminary drainage report.
- (b) A Tier B authority shall refer any variance on a site of 1 ha or more to the State Stormwater Technical Committee.
- (c) A decision shall state its reasons and any conditions, and shall be entered in the public register of Clause 10.17.
- (d) A variance runs with the approval. It lapses if the approval lapses.
Commentary. The 2006 APWA 5600 included a waivers section (5601.6), and Georgia allows waivers where downstream analysis shows a peak control is unnecessary. The waiver of Clause 1.10.2 is narrow: on a tidal coast, undetained flow can help by passing through before the tide closes the outfall, but only an analysis can show that. This Manual requires every decision to be published because publication deters case-by-case erosion of the standard; the CAG found 34 of 74 test-checked tanks in six ULBs encroached and five, among them the Kummari, Gunadala and Nalla Cheruvu in Vijayawada, entirely built over (CAG, Report for the year ended March 2018, Ch. III).
1.11 Transition provisions
1.11.1 Effective date. This Manual takes effect for new applications 6 months after notification (the effective date).
1.11.2 Applications in process. An application filed complete before the effective date may be decided under the rules in force when it was filed, if a decision is issued within 12 months of the effective date. Otherwise, this Manual applies.
1.11.3 Phased start for Tier B. In Tier B authorities, Chapters 4 and 5 apply from 24 months after notification, except in flood-sensitive catchments, where they apply from the effective date.
1.11.4 Public works. DPRs sanctioned before the effective date may proceed as sanctioned. Any DPR revised or re-tendered after the effective date shall comply. Departments shall report non-compliant works in progress to the State Stormwater Technical Committee within 12 months.
1.11.5 Before the annexes are issued. Until an annex referred to in this Manual is issued, the Applicant shall use the method stated in the clause, with values agreed with the Authority and recorded in the drainage report.
Commentary. The 6-month lead time matches the lead time for NIH-DHAARA updates in Clause 2.14.2. Singapore gave a similar interval for its 2025 detention addendum (issued 16 Apr 2025, applied from 1 Oct 2025). The 12- and 24-month periods are set by this Manual to let Tier B authorities train staff and to let the State issue the design-aid tables (Clause 1.7).
1.12 Review and amendment
1.12.1 The State Stormwater Technical Committee shall review this Manual every 10 years, and after any event that exceeds the 1% AEP design depth as set out in Clause 2.14.1.
1.12.2 Amendments shall be notified in the Gazette, published with a change log, and take effect 6 months after notification unless the notification states otherwise.
1.12.3 Any person may propose an amendment to the Committee. Proposals and the Committee's decisions shall be published.
References (chapter)
- Government of Andhra Pradesh (2017). Andhra Pradesh Building Rules, 2017 (G.O.Ms.No.119, MA&UD (M) Department, 28-03-2017). https://crda.ap.gov.in/apcrdacommuni/media/apcrdadocs/developmentpromotion/Andhra%20Pradesh%20G.O.Ms.No.119,Dt.28-03-2017-AP%20Building%20Rules-2017.pdf; consolidated with G.O.Ms.No.401 (2017), No.223 (2018) and No.180 (2020): https://www.amrut.mohua.gov.in/uploads/reform/ulb/AP-Building-Rules-2017-GOMsNo119pdf.pdf
- Government of Andhra Pradesh (2025). Amendments to the Andhra Pradesh Building Rules, 2017 (G.O.Ms.No.273, MA&UD (M) Department, 19-12-2025; AP Gazette Extraordinary No.854). https://simpliance.in/download/file/dXBsb2Fkcy9nb3Z0bm90aWZpY2F0aW9uL05vdGlmaWNhdGlvbiByZWdhcmRpbmcgYW1lbmRtZW50cyB0byBBUCBCdWlsZGluZyBSdWxlcywgMjAxNy5wZGY=
- Government of Andhra Pradesh (2017). Andhra Pradesh Land Development (Layout and Sub-division) Rules, 2017 (G.O.Ms.No.275, MA&UD (H) Department, 18-07-2017), with G.O.Ms.No.178 (2020). http://vmrda.gov.in/new%20pdf/G.O.Ms.No.275.pdf
- Andhra Pradesh Water, Land and Trees Act, 2002 (Act 10 of 2002), ss. 17, 23 and 35. https://www.ielrc.org/content/e0202.pdf (unofficial text); Andhra Pradesh Water, Land and Trees Rules, 2004 (G.O.Ms.No.339 PR&RD, 06-11-2004), Rule 16. https://www.ielrc.org/content/e0427.pdf
- Andhra Pradesh Municipalities Act, 1965 (Act 6 of 1965), ss. 35, 133, 147, 153 and 155. https://faolex.fao.org/docs/pdf/ind198181.pdf
- Andhra Pradesh Metropolitan Region and Urban Development Authorities Act, 2016 (Act 5 of 2016). https://www.indiacode.nic.in/handle/123456789/10814
- Government of Andhra Pradesh (2024). G.O.Ms.No.120, MA&UD Department, 12-11-2024 (APCRDA jurisdiction). https://crda.ap.gov.in/APCRDADOCS/GOSACTSRULES/Capital%20City/01~11292024MAUD_33866_MS120.pdf
- Andhra Pradesh Drainage Cess Act, 1985. https://www.indiacode.nic.in/handle/123456789/16260
- Comptroller and Auditor General of India. Report on Economic Sector and PSUs, Government of Andhra Pradesh, for the year ended March 2018, Chapter III: Preservation of Water Bodies in Andhra Pradesh. https://cag.gov.in/uploads/download_audit_report/2017/12%20Section%20B%20Chapter%203%20Compliance%20Audit-05fce732f327b79.84269190.pdf
- Ministry of Environment, Forest and Climate Change (2019). Coastal Regulation Zone Notification, G.S.R. 37(E), 18 Jan 2019. https://czmp.ncscm.res.in/2019-notification.pdf
- National Coastal Zone Management Authority (2019). Minutes of the 37th meeting, 25 Feb 2019 (Andhra Pradesh CZMPs). https://moef.gov.in/uploads/2019/07/Minutes_37thMeetingNCZMA.pdf
- Principal Chief Conservator of Forests (Wildlife), Andhra Pradesh (2023). Report to the NGT (SZ) in O.A. 3/2023 on Kolleru, with the Supreme Court judgment of 10 Apr 2006 annexed. https://www.greentribunal.gov.in/sites/default/files/news_updates/323_1.pdf
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A, §4.4.1.4 (Table 4.1 and notes).
- Kakkar, R. (CPHEEO) (2023). Understanding Urban Stormwater Management. CSE, Aug 2023.
- National Disaster Management Authority (2010). National Guidelines on Management of Urban Flooding.
- MoHUA (2016). Model Building Bye-Laws, Chapter 9.
- Lok Sabha Unstarred Question 1847, 30 Jul 2026 (MoHUA). https://sansad.in/getFile/lsapps/loksabhaquestions/annex/188/AU1847_x29brZ.pdf
- National Remote Sensing Centre (2024). Hydrological and Hydrodynamic Modelling: The Budameru River Flash Floods Simulation. https://apsac.ap.gov.in/wp-content/uploads/2024/09/Budameru_Flood%20Modelling_NRSC.pdf
- The Federal (2024). Human encroachment rather than rivulet Budameru is sorrow of Vijayawada, 11 Sep 2024 (secondary source). https://thefederal.com/category/states/south/andhra-pradesh/human-encroachment-rather-than-rivulet-budameru-is-sorrow-of-vijayawada-144040
- SANDRP (2024). Andhra Pradesh: Prakasam Barrage damaged by sand boats again (CWC hydrograph reproduced; secondary source). https://sandrp.in/2024/09/04/andhra-pradesh-prakasam-barrage-damaged-by-sand-boats-again/
- Sphere India (2024). Situation Report 2: Floods in Andhra Pradesh and Telangana, 9 Sep 2024. https://www.sphereindia.org.in/sites/default/files/2024-10/SI%20Sitrep-2_Floods%20in%20AP%20%26%20Telangana_09-09-2024.pdf
- India Meteorological Department, RSMC New Delhi. Very Severe Cyclonic Storm Hudhud over the Bay of Bengal, 7–14 October 2014. https://rsmcnewdelhi.imd.gov.in/uploads/report/26/26_fac6af_hud.pdf
- SANDRP (2021). Andhra Pradesh: dam-induced flood disaster in November 2021 (secondary source). https://sandrp.in/2021/12/05/andhra-pradesh-dam-induced-flood-disaster-in-november-2021/; Rivers crossing HFLs in Oct–Nov 2021. https://sandrp.in/2021/12/12/rivers-crossing-hfls-in-oct-nov-2021/
- India Meteorological Department (2023). Hourly bulletin, 5 Dec 2023, 05:00 UTC (Cyclone Michaung). https://rsmcnewdelhi.imd.gov.in/uploads/archive/48/48_412797_12.%20Hourly%20Bulletin%2005122023-0500%20UTC.pdf
- India Meteorological Department (2025). Press release, 29 Oct 2025 (Cyclone Montha). https://mausam.imd.gov.in/Forecast/marquee_data/Press%20Release%2029-10-2025.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Mid-America Regional Council (2025). APWA 5600 Manual Factsheet; APWA Stormwater Standards Supplement (7 Nov 2025). https://www.marc.org/document/apwa-stormwater-standards-supplement
- Mid-America Regional Council. The Evolution of Regional Stormwater Design Standards (presentation). https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Kansas City Metro Chapter APWA (2006). Section 5600, §5601.6 Waivers.
- PUB Singapore (2018, with Addendum No. 3 of 16 Apr 2025). Code of Practice on Surface Water Drainage, 7th ed.
- Department of Irrigation and Drainage Malaysia (2008). Submission Checklist for Stormwater Management.
- Centre for Science and Environment (2023). Urban Stormwater Management (presentation).
- Comptroller and Auditor General of India. Compliance Audit, Government of Andhra Pradesh, for the year ended March 2021, Chapter II, para 2.1: Development of Capital City Amaravati. https://cag.gov.in/uploads/download_audit_report/2023/Chapter-II-Compliance-Audit-Observations-0651175e5d96711.62083733.pdf
- Ministry of Jal Shakti (2023). First Census of Water Bodies, Volume 2, Andhra Pradesh chapter. https://mowr.nic.in/irrigationcensus/sites/default/files/State20230825411930292.pdf
- Ramsar Convention. Annotated list of Ramsar sites, India: Kolleru Lake (site 1209). https://rsis.ramsar.org/sites/default/files/rsiswp_search/exports/Ramsar-Sites-annotated-summary-India.pdf
- Deccan Chronicle (2025). Encroachments on drains of Vijayawada to be removed: Narayana, 26 Jul 2025 (secondary source). https://www.deccanchronicle.com/southern-states/andhra-pradesh/encroachments-on-drains-of-vijayawada-to-be-removed-narayana-1893885
- Deccan Herald (2024). Centre pushes for mandatory floodplain zoning law as only 4 states comply (secondary source). https://deccanherald.com/india/centre-pushes-for-mandatory-floodplain-zoning-law-as-only-4-states-comply-3125564
Annexes and forms
| Annex / Form | Content |
|---|---|
| 1A | List of Tier A authorities, with APCRDA area boundary |
| 1B | Maps of flood-sensitive catchments |
| 1C | Policy Supplement: text of alternatives S-1 to S-5 and model council resolution |
| 1D | Model APBR amendment and model ULB bye-law |
| Form 1-1 | Applicability Determination |
| Form 1-2 | Variance / Waiver Request |
Commentary. Floods in Andhra Pradesh come from cyclones, from multi-day storms on full tanks and rivers, and from small streams that pass through its cities. On 31 Aug–2 Sep 2024 the Budameru breached its flood banks at three points and flooded much of Vijayawada while the Krishna reached a record inflow of 11.36 lakh cusecs at Prakasam Barrage; 45 people died and about 6.44 lakh were affected in the State (NRSC, 2024; The Federal, 2024; CWC data via SANDRP; Sphere India, 2024). Cyclone Hudhud crossed Visakhapatnam on 12 Oct 2014 with a 1.4 m surge and gusts of 260 km/h, and 46 people died (IMD RSMC report). In November 2021 the Annamayya dam on the Cheyyeru breached after an upstream ring bund failed, about 125 tank and bund breaches were reported, the Pennar at Nellore Anicut rose to a new highest flood level of 19.57 m, and 44 people died (SANDRP, 2021). Cyclones Michaung (December 2023) and Montha (October 2025) each gave more than 20 cm in a day on the south coast (IMD). The CAG found 34 of 74 test-checked tanks encroached and five entirely built over, and no storm water management plan in the ULBs it audited (CAG, Report for the year ended March 2018, Ch. III). Three failure modes recur: drains and streams narrowed by encroachment; lost storage in cheruvulu, kuntas and Kolleru; and outfalls held up by river stage, lake level or tide. Objectives (b) to (e) address the last two, which a drain-sizing manual alone cannot fix.
No national instrument requires on-site detention. CPHEEO (2019) is advisory and describes peak control only as typical practice. NDMA (2010) says detention and retention "will" be included but gives no sizing rule. MBBL 2016 and APBR 2017 mandate RWH only. Objective (a) is therefore the main new step this Manual takes.