Annexes to Chapter 11Basin and City Stormwater Master Plans
These annexes support Chapter 11. They give a terms of reference template for a Basin Stormwater Master Plan (BSMP), the layout of the basin list and boundary layer, the layout and method for depth–damage curves, the standard for publishing BSMP data and models, and the annual implementation report form. Annexes 11B and 11C need data that are not yet available; they say so and give the rule to use in the meantime. The template and the form are a model and a draft form for consideration by a competent authority, and are not in force.
Annex 11A — BSMP terms of reference template
Supports Clauses 11.1 to 11.12 of Chapter 11.
Model text for consideration by a competent authority. Not in force. The Lead Authority adapts this template for each basin. Items in "[ ]" are for the Lead Authority to complete. Clause references are to this Manual, which the consultant shall follow in full.
11A.1 Background and purpose
- The [Lead Authority] intends to prepare a Basin Stormwater Master Plan for the [name] basin under Chapter 11 of the Goa Stormwater Design Manual.
- The BSMP shall (Clause 11.1.2):
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service for each part of the drainage system;
- (c) identify, cost and rank the works, storage and land needed to reach that level of service;
- (d) identify land to be reserved in the statutory land-use plan for regional storage, tollem and tank restoration and major flow paths;
- (e) set the basin inputs for site design: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4; and
- (f) recommend catchments for notification as flood-sensitive.
- The BSMP may make the site criteria of Chapters 4 to 8 stricter for the basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6 (Clause 11.1.3).
11A.2 Client, partners and study area
- Client: [Lead Authority] (Clause 11.4.1).
- Partners: WRD, wherever the basin includes a river, canal or tank under its control, and [other local bodies, GPPDA or TCP Department, GSDMA] (Clause 11.4.1).
- Study area: the whole of the [name] basin, draining to [outfall], as delineated under Clause 11.3, including the parts outside the client's limits (Clause 11.3.1). The provisional boundary is in [Annex 11B / attached map]. The consultant shall confirm it in Task 2.
- Links to other basins: [for example the Cumbarjua canal corridor]. Diversions between basins by canal, drain or surplus course shall be mapped and represented in the model (Clause 11.3.2).
11A.3 Team
- The study shall be led by an engineer empanelled as a Stormwater Design Professional with the basin modelling endorsement of Annex 10E (Clause 11.4.3).
- The team shall include at least: [a hydrologist; a hydraulic modeller; a coastal or tidal specialist where the basin has a tidal outfall; a GIS and survey lead; a planner; a cost engineer; a community engagement lead]. The client sets the minimum qualifications and experience of each.
11A.4 Tasks
Task 1 — Inception. Review existing studies, data and projects in the basin. Prepare a data inventory against Table 11.1, a gap list, a survey plan, a consultation plan, and the work programme. Deliver the inception report.
Task 2 — Data and surveys. Assemble, survey where missing, and quality-check every item of Table 11.1 (Clause 11.5.1):
- (a) terrain: DEM from LiDAR or photogrammetry with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum, with the accuracy test reported;
- (b) drain network: every public drain, culvert and outfall, with invert levels, sizes, condition and silt depth; private drains above 600 mm;
- (c) waterbodies: every tank, tollem, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels and encroachment, in the fields of Annex 7A;
- (d) rivers and canals: cross-sections at no more than 200 m spacing and at every structure;
- (e) outfalls and coast: tidal datums and surge values from Annex 5A or, until it is published, from the site-specific study of Clause 5.7; tide levels up the estuary at each outfall; khazan bund crest and sluice-gate (mano) sill levels and who operates each gate; releases from dams upstream; gates and pumps;
- (f) rainfall and water levels: all available records (IMD, including the Panjim and Mormugao observatories and the 14 stations of the IMD Goa daily rainfall table, and any gauges of WRD), including the June 1999, October 2009, August 2019, July 2021 and August 2026 events;
- (g) flood evidence: surveyed flood marks and mapped extents of past events, including public reports, photographs and residents' records;
- (h) land use: existing land use and imperviousness; future land use from the statutory master plan;
- (i) soils and groundwater: HSG map (Annex 3A or Clause 3.7.2), seasonal high groundwater, aquifer and recharge zones; and
- (j) sewer interaction: known cross-connections, dry-weather flow in drains, solid-waste hotspots.
Confirm the basin boundary and the inter-basin diversions (Clause 11.3.2). Deliver the data report and the data in the formats of Annex 11D.
Task 3 — Model build. Build a coupled 1D–2D hydraulic model of the minor system, the major (overland) system, rivers, canals and tanks, and the outfalls (Clause 11.7.1; Figure 11.2). Use the methods of Chapter 3 and the tidal and river boundaries of Chapter 5. Run the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs, with areal reduction under Clause 2.7.3 (Clause 11.7.2). Where the basin has tank cascades, run continuous simulation under Clause 3.13 with the full IMD gridded daily record where available, and at least 30 years, disaggregated by the temporal patterns of Annex 2D. The two-step approach of Clause 3.13.5 may be used: starting tank levels and antecedent conditions from the continuous run are passed to the design-storm runs (Clause 11.7.3).
Task 4 — Calibration and validation. Calibrate and validate the model under Clause 3.15, using at least two of the June 1999, October 2009, August 2019, July 2021 and August 2026 events where data exist (Clause 11.7.5). Report the performance measures of Clause 3.15.4 and the reasonableness check of Clause 3.15.6.
Task 5 — Scenarios and hazard maps. Model the scenarios of Clause 11.7.4: (a) existing; (b) future, uncontrolled; (c) future, controlled; (d) future, with plan; and (e) climate, applied to (a) and (d). Produce flood hazard maps of extent, depth, velocity and hazard class (H1–H6, Chapter 6) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan (Clause 11.8.4(a)).
Task 6 — Level-of-service assessment. Compare scenarios (a), (c) and (d) with the levels of service of Table 11.2 and any stricter levels the client adopts (Clause 11.6.1). Map every shortfall.
Task 7 — Options. Develop options in the order of Clause 11.8.1: protect and restore storage; regional retention and detention, sited by modelling; conveyance; outfall works; property-level protection; non-structural measures. Assess each option for the criteria of Clause 11.8.2: reduction in flood risk (buildings and people flooded, and expected annual damage using Annex 11C); capital and 30-year maintenance cost; land required; effect on groundwater recharge and saline intrusion; effect on downstream basins and the Cumbarjua canal; and who benefits.
Task 8 — Basin inputs for site design. Where scenario (c) does not meet the level of service, propose basin release rates (m³/s/ha) by AEP and sub-catchment (Clause 11.8.3). Recommend catchments for notification as flood-sensitive, with the evidence of Clause 4.5.4.1. Identify regional facility sites, with storage volumes, land needs and the sites they serve, and compute the fee-in-lieu unit rate, including land, construction and 10 years of maintenance (Clauses 4.13.3, 11.8.4(c), (d)).
Task 9 — Capital Improvement Programme. Rank the works by risk reduction per rupee, with cost, phasing and responsible agency (Clause 11.8.4(e)).
Task 10 — Maintenance and monitoring. Prepare the pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Clause 11.8.4(f); Chapters 7 and 10). Specify monitoring needs: new rain gauges, level sensors and flood-mark survey points (Clause 11.8.4(g); Clause 10.16.1).
Task 11 — Land-use integration. Prepare the material for the statutory land-use plan required by Clause 11.9.1: sites to be reserved; the 1% AEP hazard map with the Chapter 7 setbacks; land in hazard classes H5–H6 in the 1% AEP event; and open space locations that can form part of flow paths or regional storage.
Task 12 — Consultation. Publish the draft BSMP for public comment for at least 60 days, with public meetings in each affected local body (Clause 11.10.1). Keep a log of comments and responses.
Task 13 — Final BSMP and publication. Revise the BSMP after consultation. Prepare the package for approval by the State Stormwater Technical Committee, including the model for review (Clause 11.11.1). Publish the data, models, maps and CIP under Annex 11D (Clause 11.10.2).
11A.5 Deliverables
Table 11A.1 — Deliverables
| No. | Deliverable | Task | Due (months from start) |
|---|---|---|---|
| D1 | Inception report, data inventory and survey plan | 1 | [ ] |
| D2 | Data report and data sets (Annex 11D) | 2 | [ ] |
| D3 | Model build report and model files | 3 | [ ] |
| D4 | Calibration and validation report | 4 | [ ] |
| D5 | Scenario results, hazard maps and level-of-service assessment | 5, 6 | [ ] |
| D6 | Options report, with basin inputs for site design | 7, 8 | [ ] |
| D7 | Draft BSMP with draft CIP, for consultation | 9–12 | [ ] |
| D8 | Final BSMP, consultation log, approval package and open-data release | 13 | [ ] |
11A.6 Ownership and publication
All data, models, maps and reports produced under these terms are owned by the Lead Authority and shall be published under Annex 11D. The consultant shall not use any software licence, data licence or format that prevents publication, or that prevents a third party from re-running the model with the stated software version.
Annex 11B — Basin lists and boundaries for Tier A bodies
Supports Clauses 11.3 and 11.4 of Chapter 11.
To be prepared. This annex will contain the list of basins for every Tier A body, with a GIS layer of basin boundaries delineated under Clause 11.3.2. It needs the list of Tier A bodies (Annex 1A), a DEM of the accuracy of Clause 11.5.1, the drain, nallah and creek network (including the Portuguese-era drains of Panaji, which are not yet mapped), the khazan bunds and sluice gates, and the basin and sub-basin maps held by WRD, the TCP Department, the Planning and Development Authorities, CCP and the Municipal Councils (other likely sources: Survey of India, NRSC, GSDMA and the CZMP maps). Until it is published, the basins of Panaji, Margao and Mapusa and the river reaches named in Clause 11.3.3 are at least those named there; other Tier A bodies define their basins in their first BSMP (Clause 11.3.3); and the interim arrangements of Clause 11.12 apply in every basin without an approved BSMP.
Table 11B.1 — Basins named in Clause 11.3.3 (provisional)
| Tier A body or area | Basin | Note from Chapter 11 |
|---|---|---|
| Panaji | St Inez creek | Takes most of the city's storm water drains |
| Panaji | Mala | Mala lake and the WRD flood pumping station |
| Panaji | Ourem creek | — |
| Margao | Storm water nallahs draining to the Sal | — |
| Mapusa | Mapusa river | — |
| Paroda | Kushavati below Selaulim dam | River boundary includes dam releases |
| Bicholim and Sanquelim | Valvanti | — |
| North Goa villages (Pernem, Bicholim and Bardez talukas) | Reaches flooded by Tillari dam releases (Maharashtra) | River boundary includes dam releases |
| Mandovi and Zuari basins | Cumbarjua canal | Treated as linking the basins it joins |
| Other towns, including Vasco and Ponda | To be defined in the first BSMP | Clause 11.3.3 |
Table 11B.2 — Attributes of the basin boundary layer (layout)
| Field | Type | Content |
|---|---|---|
| BASIN_ID | Text | Basin identifier |
| NAME_EN, NAME_KOK | Text | Basin name in English and Konkani |
| TIER_A | Text | Tier A body or bodies in the basin |
| OUTFALL | Text | Outfall to the sea, river or major waterbody (Clause 11.2) |
| AREA_KM2 | Real | Basin area, km² |
| LEAD_AUTH | Text | Lead Authority (Clause 11.4.1) |
| PARTNERS | Text | Partners, including WRD where it applies |
| LINKS | Text | Diversions to and from other basins (Clause 11.3.2) |
| BSMP_STAT | Text | None / in preparation / draft published / approved |
| BSMP_DATE | Date | Date of approval of the current BSMP |
| REVIEW_DUE | Date | Date of the next review (Clause 11.11.2) |
Annex 11C — Depth–damage curves for Goa building types
Supports Clause 11.8.2 of Chapter 11.
To be prepared. This annex will contain depth–damage curves for the main building types of Goa cities, for structure and contents, for use in computing expected annual damage under Clause 11.8.2. It needs a building-type classification and building stock data (Census housing tables, property-tax records, Lead Authority GIS), damage surveys and claims from the June 1999, October 2009, August 2019, July 2021 and August 2026 floods (Revenue Department and GSDMA damage assessments, insurers), and replacement costs (PWD schedules of rates). Until it is published, each BSMP shall state the depth–damage relations it uses and their source, and shall report the reduction in buildings and people flooded for every option (Clause 11.8.2), which does not depend on the curves.
Table 11C.1 — Depth–damage curve (layout, one table per building type)
| Depth of water above floor level (m) | 0 | 0.25 | 0.5 | 1.0 | 1.5 | 2.0 | 3.0 |
|---|---|---|---|---|---|---|---|
| Structure damage (% of replacement cost) | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Contents damage (% of contents value) | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Building type, source and year of costs | ______ |
11C.1 Use in option assessment
Expected annual damage (EAD) is computed for each scenario from the damages at the modelled AEPs. With damages D_1, D_2, … at annual exceedance probabilities P_1 > P_2 > …, using at least the 50%, 10%, 1% and 0.2% AEP results of Clause 11.7.2:
EAD ≈ Σ ½ × (D_i + D_(i+1)) × (P_i − P_(i+1))
The reduction in EAD between scenario (c) and scenario (d), or between options, is the risk-reduction benefit used to rank works per rupee (Clause 11.8.4(e)). The BSMP shall state how damages beyond the 0.2% AEP and below the 50% AEP were treated.
Annex 11D — BSMP data and model publication standard
Supports Clauses 11.5.1 and 11.10 of Chapter 11, and Clause 10.17 of Chapter 10.
11D.1 What is published, and when
Table 11D.1 — Items to be published
| Item | Format | At draft (Clause 11.10.1) | At approval (Clause 11.10.2) |
|---|---|---|---|
| BSMP report, with the level-of-service assessment and options | Searchable PDF | Yes | Yes, final |
| Flood hazard maps: extent, depth, velocity, hazard class, for each AEP and scenario of Clause 11.8.4(a) | GeoTIFF rasters; extents also as GeoPackage polygons | Yes | Yes |
| Capital Improvement Programme | CSV and PDF | Draft | Yes |
| Basin release rates, recommended flood-sensitive catchments, regional facility sites, fee-in-lieu unit rate | GeoPackage and CSV | Yes | Yes |
| Data of Table 11.1 (terrain, drains, waterbodies, cross-sections, tidal and surge values, rainfall and levels, flood evidence, land use, soils and groundwater, sewer interaction) | GeoTIFF (terrain); GeoPackage (features); CSV (tables and time series) | Summary | Yes, except security-sensitive asset details |
| Model files: native, runnable, with all boundary-condition, rainfall and control files, the software name and version, and a run log | Native format, zipped | No | Yes |
| Calibration and validation report | Searchable PDF | Yes | Yes |
| Consultation log of comments and responses | PDF or CSV | — | Yes |
11D.2 Formats and references
- (a) Raster data shall be GeoTIFF, preferably cloud-optimised, with the cell size stated. Vector data shall be GeoPackage. Tables and time series shall be CSV in UTF-8, with a header row and units in the column names.
- (b) Horizontal and vertical references shall be as in Annex 10B.1(b) and (c). The vertical datum and its relationship to the Chapter 5 tidal datums shall be stated in every data set that carries levels.
- (c) Times shall be in Indian Standard Time, written as ISO 8601 (yyyy-mm-ddThh:mm+05:30). Units shall be SI.
- (d) Hazard map files shall be named
<basin>_<scenario>_<AEP>_<variable>.tif, where scenario is a to e of Clause 11.7.4, AEP is written as 50, 10, 1 or 0p2, and variable is depth, velocity, hazard or extent; for examplest-inez_d_1_depth.tif. - (e) Waterbody data shall use the fields of Annex 7A. Facility and outfall data shall use the fields of Annex 10B.
11D.3 Metadata
Every published data set shall carry: title; description; Lead Authority; source and method; date of capture; accuracy (for the DEM, the measured vertical RMSE); horizontal and vertical reference; scenario and AEP, where relevant; BSMP version; licence; and a contact.
11D.4 Withholding and personal data
- (a) Security-sensitive details of critical assets may be withheld, with the reason recorded and published (Clauses 10.17.3, 11.10.2). The flood hazard maps and the model shall still be published; only the sensitive attributes are removed.
- (b) Personal data shall not be published (Clause 10.17.3). Flood evidence collected from residents shall be published without names or contact details unless the person consents.
11D.5 Licence, viewer and versions
- (a) Published data and models shall be released under the Government Open Data Licence – India or an equivalent open licence (Clause 10.17.4).
- (b) The hazard maps, regional facility sites and CIP shall also be shown on a public map viewer (Clause 11.10.2).
- (c) Each approved BSMP shall carry a version number and date. Superseded versions shall stay available, marked as superseded, so that designs approved under them can be checked.
- (d) The published model package shall allow a third party with the stated software version to reproduce the published results. Designers may use its boundary conditions for site designs in the basin (Clause 11.10, Commentary).
Form 11-1 — Annual implementation report
Supports Clause 11.11.3 of Chapter 11, with Clauses 4.5.6.3 and 4.13.4 of Chapter 4.
Draft form — Goa Stormwater Design Manual, Draft v1.0. Published by the Lead Authority for each basin with an approved BSMP before each south-west monsoon, by 15 May (Clause 11.11.3).
Table 11F.1 — Form 11-1, Section A: Basin and plan
| No. | Field | Entry |
|---|---|---|
| A1 | Basin; Lead Authority; partners | ______ |
| A2 | BSMP version and date of approval | ______ |
| A3 | Reporting year (1 June to 31 May) | ______ |
| A4 | Date of publication (by 15 May) and web address | ______ |
Table 11F.2 — Form 11-1, Section B: CIP progress
| CIP rank | Work | Agency | Cost in CIP (₹) | Spent this year (₹) | Spent to date (₹) | Status | Expected completion |
|---|---|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
Table 11F.3 — Form 11-1, Section C: Fee-in-lieu ledger (Clauses 4.5.6.3(c) and 4.13.4)
| Regional facility or tank | Volume credited to sites (m³) | Volume delivered (m³) | Fees received (₹) | Fees spent (₹) | Fees held, with year received |
|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ |
| Basin total: volume owed and delivered | ______ | ______ | ______ | ______ | ______ |
Table 11F.4 — Form 11-1, Section D: Maintenance completed (Clause 11.8.4(f))
| No. | Item | Planned | Done | Date completed |
|---|---|---|---|---|
| D1 | Desilting of drains and canals (length, km; volume, m³) | ______ | ______ | ______ |
| D2 | Tank and tollem desilting and restoration (tanks, number; storage restored, m³) | ______ | ______ | ______ |
| D3 | Gate tests (number of gates) | ______ | ______ | ______ |
| D4 | Pump station duty tests (number of stations) | ______ | ______ | ______ |
| D5 | Tank operating rules reviewed with the custodian (number) | ______ | ______ | ______ |
| D6 | Monitoring added: rain gauges, level sensors, flood-mark points (Clause 11.8.4(g)) | ______ | ______ | ______ |
Table 11F.5 — Form 11-1, Section E: Flooding against the levels of service
| Event (dates) | Rainfall compared with the design depths (Clause 10.16.2(a)) | Level-of-service element (Table 11.2) | Location | Met (yes / no) | Event report reference (Clause 10.16.2) |
|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ |
Table 11F.6 — Form 11-1, Section F: Review triggers and sign-off
| No. | Field | Entry |
|---|---|---|
| F1 | Event exceeding the 1% AEP design depth in the basin this year (yes / no). If yes, review due within 2 years (Clause 11.11.2) | ______ |
| F2 | Statutory land-use plan revised this year (yes / no) (Clause 11.11.2) | ______ |
| F3 | Next 10-year review due (date) | ______ |
| F4 | Officer of the Lead Authority: name, designation, signature, date | ______ |