Draft v1.0 prepared by NEER. Not adopted by the Government of Goa, and has no legal force. About this draft

Chapter 1Policy, Applicability and Adoption


1.1 Purpose and objectives

1.1.1 This Manual sets the minimum standards for the planning, design, construction, operation and maintenance of stormwater systems in Goa. It applies to private development and to public works, as set out in Clause 1.5.

1.1.2 The Manual has the following objectives:

  • (a) to make stormwater management a condition of development approval, so that new development and redevelopment do not increase flood peaks or runoff volumes downstream;
  • (b) to retain frequent rainfall on site, so that groundwater recharge is sustained and pollutant loads are reduced;
  • (c) to size storage for the long-duration multi-day south-west monsoon storms of June–September, as well as for short-duration intensities;
  • (d) to design outfalls for tidal, khazan-sluice and river tailwater, including the case where the outfall is closed;
  • (e) to protect tanks (tollems), marshes, rivers, supply channels and surplus courses as part of the drainage system;
  • (f) to give every element of the drainage network a safe overland path for the 1% AEP (100-yr) storm;
  • (g) to make design inputs, approvals and facility records public, so that designs can be checked and repeated; and
  • (h) to make sure that facilities, once built, are maintained and remain effective.

1.1.3 This Manual does not replace the rainwater harvesting (RWH) mandate, the Goa Land Development and Building Construction Regulations, 2010 (GLDBCR 2010), or the statutes on waterbodies. It adds runoff control requirements to them (Clause 1.8).

Commentary. Goa's floods come from three mechanisms, often together. The first is monsoon rain falling at high tide: the State Disaster Management Plan names "heavy intensity precipitation in conjunction with high tides" as the cause of drainage congestion in low-lying areas (GIM, 2014). In Panaji this floods Mala, Patto, 18th June Road, Miramar and the land along St Inez creek, which carries most of the city's storm drains, on about 15–20 days of a monsoon (as reported). The second is river flooding from upstream rain and dam releases. The Valvanti floods the Bicholim and Sanquelim markets (2000, 2005 and 2007; North Goa DDMP, 2012). Paroda on the Kushavati, below Selaulim dam, flooded in every year from 2017 to 2021 (South Goa DMP, 2022). Releases from Tillari dam in Maharashtra flooded villages in Pernem, Bicholim and Bardez in August 2019 (as reported). Over 10–23 July 2021 the State received 1,047.3 mm against a normal of 471 mm, and Sattari, Bicholim, Ponda and Dharbandora were among the worst hit (IMD, as reported). The third is the short, intense storm: about 271 mm fell in 7 hours at Canacona on 2 October 2009 and flooded the Talpona and Galgibag rivers (Goa SAPCC).

Lost and neglected storage makes all three worse. Goa's khazans, bunded tidal fields of about 135 km² (NCSCM, draft CZMP, 2021), drain through sluice gates that their tenants, not the State, maintain, and the High Court has repeatedly ordered filled paddy land, lagoons and water bodies restored. No CAG audit of Goa's drainage was found, and no Goa town has a stormwater master plan or a stated design return period. Objectives (b) to (e) address the storage and tailwater failures, which a drain-sizing manual alone cannot fix.

No national instrument requires on-site detention. CPHEEO (2019) is advisory and describes peak control only as typical practice. NDMA (2010) says detention and retention "will" be included but gives no sizing rule. MBBL 2016 and GLDBCR 2010 mandate RWH only. Objective (a) is therefore the main new step this Manual takes.


1.2 Stormwater management hierarchy

1.2.1 Every development to which Chapter 4 applies shall consider stormwater measures in the following order. A designer shall not use a lower measure in place of a higher one that is practicable on the site.

  1. Preserve — keep or restore natural drainage features, tanks, wetlands, permeable soils, trees and overland flow paths (Chapter 7).
  2. Retain — hold the runoff from the retention depth of Annex 2E on site, by infiltration, reuse or evapotranspiration (Chapters 4 and 8).
  3. Detain — store larger storms temporarily and release them at or below the rates in Chapter 4, checked against downstream and tailwater conditions (Chapters 4 and 5).
  4. Convey — carry the remaining flow safely in the minor system, and the 1% AEP flow in the major system (Chapters 6 and 9).

1.2.2 Maintenance underlies all four measures. A measure that cannot be maintained by its owner under Chapter 10 shall not be credited.

1.2.3 Credits from higher measures reduce the requirements of lower ones. Preserved areas and retained volume reduce detention storage as set out in Chapter 4.

Figure 1.1 — Stormwater management hierarchy Four stacked bars, widest at top: Preserve, Retain, Detain, Convey, with a Maintain bar underneath spanning all. A downward arrow shows the order of consideration; an upward arrow shows that credits from higher measures reduce lower ones. Order of consideration Credits reduce lower measures 1 PRESERVE Chapter 7 Keep tanks, wetlands, marshes, permeable soils, trees and flow paths 2 RETAIN Chapters 4, 8 Hold the Annex 2E depth on site: infiltrate, reuse, evaporate 3 DETAIN Chapters 4, 5 Store larger storms; release below pre-development peaks 4 CONVEY Chapters 6, 9 Minor system, plus a 1% AEP overland path MAINTAIN — underlies every measure Chapter 10 A measure that its owner cannot maintain earns no credit (Clause 1.2.2) Use a lower measure only for what the measures above it cannot practicably achieve (Clause 1.2.1).

Figure 1.1 — Stormwater management hierarchy: preserve, retain, detain, convey, with maintenance underlying each measure. Original drawing for this Manual, adapted from Mid-America Regional Council / Kansas City Metro Chapter APWA, "Layers of Stormwater Management", APWA 5600 Manual Factsheet, 2025 (concept).

Commentary. The order follows the "layers" of Kansas City Metro APWA Section 5600, Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet, 2025). The same logic is behind Georgia's runoff-reduction standard and CSE's "attenuate and infiltrate first" principle (CSE, 2023). For Goa, the top layer has a particular meaning: much of the State's flood storage sits in its khazans, paddy fields, mangroves, creeks and tollems. The Regional Plan for Goa 2021 puts water bodies and paddy fields and khazans in its no-development Eco-sensitive Zone I, but its taluka maps do not show seasonal nallahs and small ponds (TCP Department, RPG-21, §3.6). Losing that storage cannot be offset economically by pipes.


1.3.1 Notification. This Manual shall be given statutory effect by the Government of Goa through:

  • (a) an amendment to GLDBCR 2010 that makes compliance with this Manual a condition of planning permission, building permit, layout approval and completion certificate, for development to which Clause 1.5 applies; and
  • (b) bye-laws or standing orders of each urban local body (ULB), adopting the Manual for works executed or approved by that ULB, including the ULB's own drains and roads.

1.3.2 Higher State standards. The design return periods and performance criteria of this Manual exceed the national advisory minimums of the CPHEEO Manual on Storm Water Drainage Systems (2019). The State shall constitute, by notification, a high-powered committee (the State Stormwater Technical Committee, Clause 1.9) to adopt these higher standards. This is the route that CPHEEO (2019) provides for higher return periods.

1.3.3 Precedence. Within its scope, this Manual governs where it is stricter than CPHEEO (2019), IRC:SP:42-2014, IRC:SP:50-2013 or any departmental standard. Where a statute or statutory rule sets a stricter requirement (for example a waterbody setback), the statute governs.

1.3.4 Design-practice standard for public works. Departments and ULBs that procure drainage, road or waterbody works shall require compliance with this Manual in detailed project reports (DPRs) and contracts, from the dates in Clause 1.11.

Commentary. GLDBCR 2010 is made under the Goa (Regulation of Land Development and Building Construction) Act, 2008 (Goa Act 6 of 2008), has been in force since 8 November 2010, and applies statewide, in the Corporation, Municipal Council, Village Panchayat and planning-area alike. It already asks for the route of every drain to its "ultimate discharge on to public drains, public nallah or natural water courses" (Reg. 12.2), for plots and roads to be developed "so as to prevent water logging and flooding" (Reg. 12.5), and, "as far as possible", for no buildings in the flood-prone areas identified by GSDMA (Reg. 19). It sets no design storm, return period, runoff coefficient or detention requirement. It is amended regularly (2011, 2015, 2016 and twice in 2018 in the consolidation read for this Manual) and is the natural instrument for a statewide condition of approval. MoHUA told Parliament in July 2026 that urban flooding "falls under the purview of the State Governments and the ULBs" and listed the CPHEEO manual among "advisory guidelines" (Lok Sabha AU1847). The State therefore needs no central approval to adopt higher standards. CPHEEO's Note 2 to Table 4.1 (§4.4.1.4) allows "a high powered committee constituted by State/UT Government through a notification" to adopt higher return periods. Clause 1.3.2 uses that route so that higher standards are on record for centrally funded schemes.


1.4 Definitions

1.4.1 The following terms apply throughout this Manual. Chapter-specific terms are defined in each chapter (for example Clause 2.2).

Term Meaning in this Manual
Approving Authority (the Authority) The body that grants planning permission, building permit or layout approval for a development, or that sanctions a public work: the Corporation of the City of Panaji, a Municipal Council or a Village Panchayat, with the no-objection certificate of the TCP Department where the Goa (Regulation of Land Development and Building Construction) Act, 2008 requires it, or a planning and development authority (PDA) in its planning area, or a department for its own works.
Applicant The owner, developer or department that seeks approval, and its successors in title.
Development Any building, layout, sub-division, road, paving or land-use change that requires approval under GLDBCR 2010 or that is executed as a public work.
Redevelopment Development on a site where impervious cover already exists.
Land disturbance Clearing, grading, excavation, filling or paving of land, measured in plan area over the whole of a common plan of development (Clause 1.5.5).
Impervious area Roofs, paving, compacted gravel, decks and other surfaces that prevent infiltration. Permeable paving designed to Chapter 8 is counted as pervious only for the area it treats.
New or replaced impervious area Impervious area created, or removed and rebuilt down to the subgrade, by the development. Resurfacing that leaves the base in place is not "replaced".
Retention Permanent removal of runoff from the drainage system on site, by infiltration, reuse or evapotranspiration (Chapter 4).
Detention Temporary storage of runoff with a controlled outlet, emptied after the storm (Chapter 4).
Rainwater harvesting (RWH) Collection of rainfall for supply or recharge under the RWH mandate. RWH storage is not detention unless Chapter 4 allows it.
Minor system Drains, pipes and inlets designed for the minor-system AEP of Chapter 6.
Major system The overland and floodway path that carries the 1% AEP (100-yr) flow (Chapter 6).
Pre-development condition Greenfield: open land in good condition for the mapped hydrologic soil group. Existing impervious cover is not counted (Chapter 3).
Flood-sensitive catchment The catchments of St Inez creek and of the Mala and Ourem creeks in Panaji, the Valvanti river-front of Bicholim and Sanquelim, Paroda on the Kushavati below Selaulim dam, the settlements that drain through khazan sluice gates, and any catchment the Authority notifies (Chapter 4; Annex 1B).
Waterbody A river, stream, canal, tank (tollem), lake, pond, marsh, supply channel or surplus course, whether perennial or seasonal (Chapter 7).
Regional facility A detention, retention or tank storage facility serving more than one development, built or restored under a basin plan (Chapter 4).
Tier A / Tier B authority An Approving Authority classed under Clause 1.6.
Policy supplement The set of adoptable alternative clauses in Clause 1.7 and Annex 1C.
Drainage report The preliminary or final report required by Chapter 10.
Registered professional A person registered under GLDBCR 2010 to prepare and sign the relevant plans, with any further qualification required by Clause 10.6.
Compliance calculator The State-issued tool for computing and reporting compliance (Clause 10.5).
Maintenance declaration The registered undertaking by an owner to maintain a stormwater facility (Clause 10.10).
Variance Approval to depart from a numeric requirement, with equivalent performance shown (Clause 1.10).
Waiver Approval that a requirement does not apply to a site, on the grounds in Clause 1.10.
Notified Published by the Government or the State Stormwater Technical Committee in the Official Gazette of the Government of Goa.

Commentary. "Replaced" impervious area is defined to the subgrade so that redevelopment of a fully paved site is captured, while routine resurfacing is not. This follows the approach of the APWA 5600 (2025.01) redevelopment triggers (MARC Supplement, 2025).


1.5 Applicability

1.5.1 Who is covered. This Manual applies to:

  • (a) all development requiring planning permission, building permit or layout approval under GLDBCR 2010;
  • (b) all drainage, road, bridge, culvert, waterbody and flood-mitigation works executed by a ULB, a State department, a board, or a State undertaking; and
  • (c) works executed by Central agencies or their contractors within Goa, to the extent that the Authority's approval or no-objection is required.

1.5.2 Retention and detention threshold. Chapters 4 and 5 (retention, detention, downstream and tailwater analysis) apply to any development that, over the common plan of development, involves:

  • (a) land disturbance of 0.1 ha or more; or
  • (b) new or replaced impervious area of 500 m² or more.

1.5.3 RWH. The existing RWH mandate continues to apply as set by Regulation 14.3.2 and Annexure V of GLDBCR 2010: rooftop rainwater storage for reuse, mandatory on plots of more than 4,000 m² (private buildings with 40 units or more, public and institutional buildings with more than 2,000 m² of floor area, and all commercial and industrial development) and recommendatory for all other construction, as now. This Manual does not change it.

1.5.4 Provisions that apply at every size. The following apply to all development under Clause 1.5.1, whatever its size, unless exempted by Clause 1.5.8:

  • (a) no sewage connection to a storm drain (Chapter 8);
  • (b) lowest habitable floor and openings at or above the 1% AEP level plus 0.5 m, where a 1% AEP level is mapped or determinable (Chapter 6);
  • (c) waterbody setbacks and the no-fill zone (Chapter 7); and
  • (d) no obstruction of a natural drainage path or major-system flow path (Chapter 6).

1.5.5 Common plan of development. The thresholds of Clause 1.5.2 apply to the total area of a development, including all phases, plots and sub-divisions under one layout approval or one ownership at the date of application. A development shall not be divided to avoid the thresholds.

1.5.6 Redevelopment. For redevelopment, the thresholds apply to new plus replaced impervious area. Retention and detention apply to the whole of the new and replaced impervious area, and the pre-development condition is greenfield (Clause 1.4). Where greenfield control cannot be achieved on a constrained redevelopment site, the relief route of Clause 4.5.6 applies: a minimum on-site cut of 50% from existing peaks, with the shortfall paid as fee-in-lieu into basin storage.

1.5.7 Linear public works. For roads, widening and other linear works, the impervious area threshold applies to the added impervious area within each drainage catchment crossed. Retention and detention shall be provided within the right of way, or in a regional facility under Chapter 4, where the right of way cannot hold them.

1.5.8 Exemptions. The following are exempt from Chapters 4 and 5:

  • (a) a single dwelling on its own plot, where the thresholds of Clause 1.5.2 are not met; and
  • (b) linear road resurfacing that adds no impervious area.

Exempt development remains subject to the RWH mandate and to Clause 1.5.4.

1.5.9 Applicability determination. The Applicant shall record the applicability decision on Form 1-1 (Applicability Determination) with the first submittal under Chapter 10. The Authority may confirm or correct it at the pre-application stage.

Figure 1.2 — Applicability decision flowchart Flowchart for Clause 1.5: approval test, exemption test, size threshold test, and flood-sensitive catchment test, leading to the requirements that apply. Development or public work (Clause 1.5.1) Needs building-rules approval, or is it a public work? No Manual not triggered; other rules apply Yes Exempt under Clause 1.5.8? (single dwelling below the threshold, or road resurfacing that adds no impervious area) Yes Exempt from Chapters 4–5. RWH (where mandated) and Clause 1.5.4 still apply No Land disturbance ≥ 0.1 ha, or new or replaced impervious area ≥ 500 m² (Clause 1.5.2)? No Below threshold: RWH (where mandated) and Clause 1.5.4 apply Yes Chapters 4 and 5 apply: retention, detention, downstream and tailwater analysis (+ RWH, 1.5.4) In a flood-sensitive catchment (Annex 1B)? Yes Mixed-frequency rule; full methods only; no Policy Supplement alternatives No Standard rule: Q_post ≤ 0.9 × Q_pre Tier B: design-aid route may be used (Clause 1.7) Decision Chapters 4–5 requirements Chapters 4–5 do not apply

Figure 1.2 — Applicability decision flowchart for Clause 1.5. Original drawing for this Manual.

Commentary. The thresholds have no single direct precedent; they are set by this Manual. Precedents span a wide range:

  • Singapore controls peak runoff from developments of 0.2 ha or more (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5).
  • Malaysia's 2008 DID checklist used on-site detention for sites up to 0.1 ha and community ponds above that.
  • The APWA 5600 (2025.01) Policy Supplement offers alternative triggers of ¼ acre (about 0.1 ha) disturbed, or 1 acre (about 0.4 ha) with 10,000 sq ft (about 930 m²) impervious, and warns agencies not to exceed a 1-acre trigger.
  • MBBL 2016 makes recharge mandatory for buildings over 500 m².

The 0.1 ha / 500 m² trigger sits at the strict end of these, because typical Goa plots are small and the cumulative effect of many small plots is what fills Panaji's drains. For small buildings, GLDBCR 2010 sets a minimum plinth of 45 cm above the access or pathway (Reg. 13.9), with no reference to any flood level.

Clause 1.5.4(b) has no direct precedent; this Manual sets it because floor levels are the cheapest protection a building can have, and it would be perverse to protect only large developments. Where no 1% AEP level is mapped, Chapter 6 gives the method for small sites.


1.6 Tiered adoption

1.6.1 Tier A authorities. The following are Tier A:

  • (a) the Corporation of the City of Panaji (CCP);
  • (b) every Approving Authority within the planning area of a planning and development authority (PDA) under the Goa Town and Country Planning Act, 1974, as those areas are notified from time to time: the PDAs themselves (GPPDA, the North Goa PDA (NGPDA), the South Goa PDA (SGPDA) and any other PDA), and the Municipal Councils and Village Panchayats in their planning areas; and
  • (c) the Municipal Councils of Margao, Mormugao (Vasco), Mapusa and Ponda, the towns that keep Outline Development Plans under the Regional Plan for Goa 2021.

1.6.2 Tier B authorities. All other Municipal Councils are Tier B.

1.6.3 What differs between tiers. All criteria of this Manual apply in both tiers. The tiers differ only in method and review:

Table 1.1 — Differences between Tier A and Tier B authorities

Item Tier A Tier B
Performance criteria (Chapters 2–9) Apply in full Apply in full
Hydrologic method for storage Hydrograph method (Chapter 3) Hydrograph method, or the design-aid route of Clause 1.7 where eligible
Compliance calculator (Clause 10.5) Required as a summary Required; may be the sole calculation on the design-aid route
Policy supplement alternatives (Clause 1.7) Only with State Stormwater Technical Committee concurrence May be adopted by council resolution
Technical review By the Authority By the Authority, with TCP Department regional support or an empanelled reviewer (Clause 10.7)
Flood-sensitive catchment rule Applies Applies

1.6.4 Moving between tiers. A Tier B authority may opt into Tier A by council resolution. The Government may notify a Tier B authority as Tier A when it becomes a Corporation, joins the planning area of a planning and development authority (PDA), or is found by a post-event review (Clause 10.16) to need the full methods.

1.6.5 Flood-sensitive catchments override tier. In a flood-sensitive catchment, whatever the tier, the alternatives of Clause 1.7 are available only as Table 1.2 allows: S-1 (the design-aid route) for sites of 0.5 ha or less (Clause 4.14.1), and S-5 fee-in-lieu where a basin plan has been notified (Clause 1.10.3(d)). S-2, S-3 and S-4 are not available.

Commentary. Corporation of the City of Panaji, with the support of WRD, PWD and Imagine Panaji Smart City on its larger drains, and a Village Panchayat with one assistant engineer cannot be asked to review the same hydrograph models. The Kansas City solution was to keep one regional standard and publish adoptable alternatives for the most contested criteria, so that smaller agencies can "opt down" without leaving the standard (MARC Supplement, Nov 2025). The tiers here keep the performance criteria the same in both tiers and vary only the method, so that a building in a Tier B town is protected to the same level as one in Panaji.


1.7 Policy supplement: adoptable alternatives

1.7.1 The Government shall publish, with this Manual, a Policy Supplement (Annex 1C) of alternative clauses. An Approving Authority may adopt one or more alternatives under the conditions in Clause 1.7.3.

1.7.2 The alternatives are:

Table 1.2 — Policy supplement: adoptable alternatives S-1 to S-5

No. Main-text requirement Adoptable alternative Eligibility
S-1 Storage sized by hydrograph method (Chapter 3) Design-aid route: retention and detention volumes taken from the unit-storage tables (m³ per ha, by rainfall zone, soil group and impervious fraction) in Annex 4 and the compliance calculator Sites ≤ 2 ha outside flood-sensitive catchments; ≤ 0.5 ha within them (as Clause 4.14.1)
S-2 Release rate Q_post(T) ≤ 0.9 × Q_pre(T), computed for the site Permissible site discharge (PSD): a tabulated unit-area release rate (m³/s/ha) by zone and AEP, derived from the 0.9 × Q_pre rule Any site outside flood-sensitive catchments
S-3 Waterbody setback extended to the mapped 1% AEP flood extent plus margin (Chapter 7) Fixed-width setback table by waterbody class, where no 1% AEP extent is mapped. Never less than the Zone 1 minimum of Clause 7.4.7 Waterbodies with no mapped 1% AEP extent
S-4 Downstream analysis by hydraulic model (Chapter 5) Screening checklist of downstream capacity and known flooding, with a model only where the screen fails Sites < 1 ha, outside flood-sensitive catchments, not discharging to a tidal outfall
S-5 On-site detention Fee-in-lieu toward a regional facility or restored tank storage in a master-planned basin (Chapter 4) Where a basin plan has been notified

1.7.3 Conditions on adoption.

  • (a) An alternative shall not lower any criterion below the values of this Manual. S-1 and S-2 are simplified methods for meeting the same criterion. They are not lower criteria.
  • (b) A Tier B authority adopts an alternative by council resolution, sent to the State Stormwater Technical Committee within 30 days. A Tier A authority needs the Committee's concurrence before adoption.
  • (c) The adopted alternatives shall be published on the Authority's website and in the register of Clause 10.17.
  • (d) Retention (Annex 2E depth) cannot be replaced by any alternative, except where fee-in-lieu under S-5 funds equivalent retention in the same basin.
  • (e) The tables for S-1, S-2 and S-3 shall be issued by the State Stormwater Technical Committee, and reviewed with Chapter 2 (Clause 2.14).

Commentary. The supplement follows the model of the APWA 5600 (2025.01) Policy Supplement, which gives alternatives for the four most contested criteria (applicability, Rational Method limits, stream setback trigger, and Zone 2 setback width). Two of those map onto S-3 and onto the applicability threshold of Clause 1.5.2. Alternative S-3 copies the APWA answer to the same problem: the 1% AEP extent is not mapped for small drainage areas, so a fixed-width table is offered. S-2 follows the Kansas City 2011 shift from "match existing" to fixed unit-area release rates. Local agencies preferred a set rate because existing conditions were hard to determine consistently (MARC Evolution deck). It also reflects the Sydney Water permissible site discharge (PSD) method. The 2 ha / 0.5 ha limits for S-1 (matching Clause 4.14.1) and the 1 ha limit for S-4 have no direct precedent; they are set by this Manual.


1.8 Relationship with other instruments

1.8.1 This Manual shall be applied together with the instruments below. Where they overlap, Clause 1.3.3 governs.

Table 1.3 — Relationship with other instruments

Instrument Relationship
RWH mandate (GLDBCR 2010, Reg. 14.3.2 and Annexure V) Continues unchanged: rooftop storage for reuse is mandatory only on plots of more than 4,000 m² (private buildings with 40 or more units, public and institutional buildings with more than 2,000 m² of floor area, and all commercial and industrial development) and recommendatory elsewhere; tanks hold 200 L per person, at least 10 m³. A 2019 Rajya Sabha answer gives the threshold for residential complexes as 2,000 m² [TBC]. The storage tank is not detention unless it is a dedicated empty-on-arrival volume with an outlet, and tanks are assumed full at the start of SW monsoon storms (Chapter 4). Recharge structures may count toward retention where they meet Chapters 4 and 8.
Drainage, flooding and plinth provisions of GLDBCR 2010 (Regs. 12.2, 12.5, 13.9 and 19) Continue. The roadside drain widths of Table X (0.30 m to 0.50 m a side) are minimums; drains are sized under Chapter 6. A plot barred by Reg. 19 as flood-prone is not made buildable by compliance with this Manual. The 45 cm plinth of Reg. 13.9 and the floor level of Clause 1.5.4(b) both apply; the higher governs.
Goa Town and Country Planning Act, 1974, ss. 17A and 17B (cutting land of gradient 1:10 or more; filling land 50 cm or more below the adjoining ground) Continue. Filling low-lying land needs the prior written permission of the Chief Town Planner (Land use), with a fine of not less than Rs 10 lakh for breach. The s.17A application is where the flood-storage and drainage-path checks of Chapters 4 and 7 should be made.
Regional Plan for Goa 2021 and the Outline Development Plans of Panaji, Taleigao, Mapusa, Vasco, Margao and Ponda Water bodies (rivers, tanks, nallahs, creeks), paddy fields and khazans, mangroves, sand dunes and mud flats are in Eco-sensitive Zone I, with no development other than agriculture on paddy and khazan land. Seasonal nallahs missing from the taluka maps are mapped at site scale under Chapter 7. Flood-sensitive catchments and regional facility sites should be shown in the plans. This Manual does not decide zoning or zone changes.
Goa Municipalities Act, 1968, City of Panaji Corporation Act, 2002 and Goa Panchayat Raj Act, 1994 Public drains vest in the local body, and building over them needs its consent (Municipalities Act s.205; CCP Act s.168). The CCP Act already allows separate drains for sewage and for rain-water (s.174) and bars building within 15 m of a municipal drain until a drain is connected (s.173); Chapter 8 applies the separation statewide. The Sarpanch removes encroachments on drains (Panchayat Raj Act s.64(1)(k)).
Goa, Daman and Diu Irrigation Act, 1973 (Act 18 of 1973), ss. 11, 14, 75, 76 and 80 Section 11 lets the Government notify limits along "any river, stream or natural drainage course" within which obstruction is prohibited. It is the statutory route for the protected drainage corridors of Chapter 7; no such notification was found. Outfalls into WRD drainage works, flood embankments and channels need WRD consent; the outfall rules of Chapters 5 and 9 apply in addition.
Goa Agricultural Tenancy Act, 1964 (ss. 26(3), 35, 38 and 42-A) and the 1975 Rules on tenants' associations Tenants, through their associations, maintain khazan bunds and operate the sluice gates (manos); the Government contributes to bunds specified as protective bunds. An outfall into a khazan therefore depends on a gate the State does not operate; Chapters 5 and 7 require the designer to identify the association, the gate operation and the bund crest level.
Wetlands (Conservation and Management) Rules, 2017, as applied by the Goa State Wetland Authority Each Goa wetland notification bars permanent construction within 50 m of "the mean high flood level observed in the past ten years" and prohibits the discharge of untreated wastes from settlements. Where that line is wider than the setback of Chapter 7, it governs (Clause 1.3.3). Nanda Lake is Goa's only Ramsar site.
CRZ Notification 2011, through the Goa Coastal Zone Management Plan 2011 (approved in September 2022, as reported) CRZ 2019 does not yet apply in Goa: its para 6(i) keeps the 2011 plan in force until a plan under it is approved, and Goa's was still in draft in June 2026. The 2011 rules give a 200 m No Development Zone on the seafront and 100 m, or the width of the creek if less, along tidal water bodies, with a 50 m buffer around mangroves of more than 1,000 m²; since the 2020 amendment the HTL in a khazan follows a bund or sluice gate built before 1991. Storm-water drains are permitted works. CRZ categories and lines are taken from the approved map sheets, and govern where wider than Chapter 7 (Clause 1.3.3).
GLDBCR 2010 and RPG-21 (no general setback from rivers, nallahs or creeks) Goa has no general statutory waterway setback in metres. The minimum setback of Chapter 7 (Clause 7.4.7) is set by this Manual; CRZ and wetland lines govern where wider.
CPHEEO Manual on Storm Water Drainage Systems (2019) Engineering reference. This Manual sets higher return periods under Clause 1.3.2.
NDMA Guidelines on Management of Urban Flooding (2010) and MoHUA SOP (2017) This Manual puts into effect the NDMA directives on catchment-based design, detention and retention, waterbody protection and climate-adjusted IDF.
NDMA Urban Flood Risk Management Programme (UFRMP) and AMRUT 2.0 Works funded under these programmes shall comply with this Manual. The development controls of Chapters 4–5 protect the capacity those works create.
IRC:SP:42-2014 and IRC:SP:50-2013 Apply to road drainage only where they do not conflict with Chapter 6.
MBBL 2016, Chapter 9 Model for RWH and for the inspection regime in Chapter 10.

Commentary. RWH in Goa is framed as a water supply and recharge measure. It works well for that purpose. It cannot, however, be relied on for flood control in the SW monsoon, because RWH sumps are usually full or the ground saturated by the time a June–August monsoon spell arrives after weeks of rain. The Manual therefore keeps harvest volume and attenuation volume apart, while letting recharge count as retention where it truly removes water from the system.

No Goa town has a stormwater master plan or a stated design return period. In Panaji, Imagine Panaji Smart City has re-laid roads and drains since about 2022, WRD has built a flood pumping station at Mala that uses Mala lake as a retention basin (reported cost about Rs 170 crore), and St Inez creek has been desilted and walled; a committee set up in April 2024 to map the city's storm-drain network, much of it Portuguese-era, had published no output that research for this Manual could find (as reported). No development-control condition stops new plots from using up the capacity such works create. Linking Chapters 4–5 to approvals closes that gap.

Goa's planning law already holds most of the tools. RPG-21 puts water bodies and khazans in a no-development zone, s.17A requires permission to fill low-lying land, and a 2018 amendment of the Land Revenue Code (new s.33(3)) lets the Collector restore filled low-lying, khazan or water-body land at the offender's cost, without notice; the enacted amendment's number and date are [TBC], though the High Court has referred to orders under it. None of these instruments says how high a flood reaches or how much storage a filled plot removes; this Manual supplies that technical test. Showing flood-sensitive catchments and regional facility sites in the plans now is cheaper than retrofitting later.


1.9 Roles and responsibilities

1.9.1 The responsibilities below apply under this Manual. They do not change any agency's statutory powers.

Table 1.4 — Roles and responsibilities under this Manual

Agency Role under this Manual
Town and Country Planning (TCP) Department (Chief Town Planner) Would own the Manual. Would issue the GLDBCR amendment. Would constitute and service the State Stormwater Technical Committee. Gives the no-objection certificate on applications forwarded by local bodies, and decides s.17A applications to cut slopes or fill low-lying land. Embeds flood-sensitive catchments and regional facility sites in the Regional Plan and the Outline Development Plans. Technical support to Tier B authorities. Maintains the empanelled reviewer list (Clause 10.7).
State Stormwater Technical Committee (Clause 1.3.2) Adopts higher standards. Issues Annexes, tables and the compliance calculator. Concurs with Tier A alternatives. Decides variances referred to it. Reviews the Manual (Clause 1.12).
Planning and development authorities (GPPDA, NGPDA, SGPDA and others) Approving Authority for development permission in their planning areas. Apply this Manual to the works they execute. Reserve regional facility sites in their plans.
Corporation of the City of Panaji (CCP), Municipal Councils and Village Panchayats Approving Authority for construction licences, with the TCP no-objection certificate where the law requires it. Owner of the public drains vested in them. Receive handed-over assets (Clause 10.14). Inspect and enforce (Clauses 10.12–10.15). CCP may require separate drains for sewage and rain-water (CCP Act s.174).
Water Resources Department (WRD) Responsible for flood control, anti-sea-erosion and drainage works, including nallah walls, flood embankments, khazan sluice repairs, St Inez creek and the Mala pumping station. Would notify protected drainage corridors under s.11 of the Irrigation Act, 1973 (Chapter 7). Provides design water levels, high flood levels and gate operating rules (Chapters 5 and 7). Consents to outfalls into its works. Concurs with regional storage credits (Chapter 4). Administers the rainwater harvesting policy.
Public Works Department (PWD) Applies this Manual to road drains, cross drains and culverts (Chapter 6) and to linear works (Clause 1.5.7); GLDBCR drains are built to PWD specifications. Its sewerage divisions identify and remove sewage connections to storm drains (Chapter 8).
Sewerage and Infrastructural Development Corporation of Goa (SIDCGL) Sewerage agency in its areas. Identifies and removes sewage connections to storm drains (Chapter 8). Keeps its mains and chambers out of drain sections.
Imagine Panaji Smart City Development Ltd (IPSCDL) Applies this Manual to the drains and roads it builds in Panaji. Hands its drain records and as-built levels to CCP (Clause 10.14).
Goa State Disaster Management Authority (GSDMA) and the District Disaster Management Authorities (DDMAs) Hazard and flood mapping, including the flood-prone areas that GLDBCR Reg. 19 refers to. Notify or recommend flood-sensitive catchments. Pre-monsoon preparedness, including orders under s.33 of the Disaster Management Act, 2005. Lead the post-event review (Clause 10.16).
Goa Coastal Zone Management Authority (GCZMA) Appraises outfalls, sluices and drains in the CRZ. Advises on CRZ categories and the HTL from the approved Coastal Zone Management Plan.
Goa State Wetland Authority (GSWA) Notifies wetlands and their 50 m lines under the Wetlands Rules, 2017. Advises on outfalls into notified wetlands (Chapter 7).
Khazan tenants' associations, with the Directorate of Agriculture (Soil Conservation Division) and the Mamlatdar Tenants' associations maintain khazan bunds and operate the sluice gates (manos) under the Goa Agricultural Tenancy Act, 1964. Would be consulted on any outfall through a khazan bund, and would agree its gate operation (Chapters 5 and 7). The Soil Conservation Division subsidises and restores protective bunds; the Mamlatdar may order neglected works.
Revenue Department and the Directorate of Settlement and Land Records Maintain land records, including land recorded as rice (paddy) and khazan, used for setbacks and storage rules. The Collector may restore filled low-lying, khazan or water-body land under s.33(3) of the Land Revenue Code.

Commentary. Ownership of Goa's drainage is split: road drains with PWD, nallahs, flood embankments and khazan sluices with WRD, local drains with CCP, the Municipal Councils and the Village Panchayats, Panaji's new drains with Imagine Panaji Smart City, khazan bunds and gates with the tenants' associations, and sewerage with SIDCGL and PWD. A High Court order of 13 October 1997 reportedly directed a master plan for Panaji's storm drains; in 2022–23 CCP and the Goa State Urban Development Agency were still disputing who should prepare it (as reported). A manual that names one owner for each task does not fix institutions by itself, but it removes ambiguity about who signs what.


1.10 Variances and waivers

1.10.1 Variance. The Authority may grant a variance from a numeric requirement where the Applicant shows, through a report certified under Clause 10.6, that:

  • (a) compliance is impracticable because of site conditions such as a high groundwater table, contaminated soil, rock, or a site area too small for the required facility; and
  • (b) the proposed alternative gives equal or better performance at the downstream point of Chapter 5, or the shortfall is made up by fee-in-lieu or off-site works in the same catchment.

1.10.2 Waiver. The Authority may waive Chapter 4 detention requirements (not retention) where a hydraulic analysis certified under Clause 10.6 shows that the site discharges directly to the sea, or to a tidal reach with no flood-prone property downstream, and that undetained flow does not worsen the outfall-closed condition of Chapter 5. A site that drains into a khazan through a sluice gate (mano) does not discharge to a tidal reach for this clause, because the gate is closed whenever the tide outside is higher than the water behind it.

1.10.3 No variance or waiver. No variance or waiver shall be granted for:

  • (a) a sewage connection to a storm drain;
  • (b) the lowest habitable floor level of Chapter 6;
  • (c) any reduction of a waterbody setback below the Zone 1 minimum of Clause 7.4.7, or any fill or construction in the no-fill zone of Chapter 7; or
  • (d) the retention requirement in a flood-sensitive catchment, except by fee-in-lieu under Clause 1.7.

1.10.4 Procedure.

  • (a) The request shall be made on Form 1-2 (Variance / Waiver Request) with the preliminary drainage report.
  • (b) A Tier B authority shall refer any variance on a site of 1 ha or more to the State Stormwater Technical Committee.
  • (c) A decision shall state its reasons and any conditions, and shall be entered in the public register of Clause 10.17.
  • (d) A variance runs with the approval. It lapses if the approval lapses.

Commentary. The 2006 APWA 5600 included a waivers section (5601.6), and Georgia allows waivers where downstream analysis shows a peak control is unnecessary. The waiver of Clause 1.10.2 is narrow: on a tidal coast, undetained flow can help by passing through before the tide closes the outfall, but only an analysis can show that. This Manual requires every decision to be published because publication deters case-by-case erosion of the standard; the High Court of Bombay at Goa observed of the zone changes before it that "almost all the conversions are from paddy fields, natural cover, no development zone and orchard to settlement zones" (Goa Foundation v. State of Goa, PIL WP No. 16 of 2023, 13 Mar 2025, as reported).


1.11 Transition provisions

1.11.1 Effective date. This Manual takes effect for new applications 6 months after notification (the effective date).

1.11.2 Applications in process. An application filed complete before the effective date may be decided under the rules in force when it was filed, if a decision is issued within 12 months of the effective date. Otherwise, this Manual applies.

1.11.3 Phased start for Tier B. In Tier B authorities, Chapters 4 and 5 apply from 24 months after notification, except in flood-sensitive catchments, where they apply from the effective date.

1.11.4 Public works. DPRs sanctioned before the effective date may proceed as sanctioned. Any DPR revised or re-tendered after the effective date shall comply. Departments shall report non-compliant works in progress to the State Stormwater Technical Committee within 12 months.

1.11.5 Before the annexes are issued. Until an annex referred to in this Manual is issued, the Applicant shall use the method stated in the clause, with values agreed with the Authority and recorded in the drainage report.

Commentary. The 6-month lead time matches the lead time for NIH-DHAARA updates in Clause 2.14.2. Singapore gave a similar interval for its 2025 detention addendum (issued 16 Apr 2025, applied from 1 Oct 2025). The 12- and 24-month periods are set by this Manual to let Tier B authorities train staff and to let the State issue the design-aid tables (Clause 1.7).


1.12 Review and amendment

1.12.1 The State Stormwater Technical Committee shall review this Manual every 10 years, and after any event that exceeds the 1% AEP design depth as set out in Clause 2.14.1.

1.12.2 Amendments shall be notified in the Gazette, published with a change log, and take effect 6 months after notification unless the notification states otherwise.

1.12.3 Any person may propose an amendment to the Committee. Proposals and the Committee's decisions shall be published.


References (chapter)

Annexes and forms

Annex / Form Content
1A List of Tier A authorities, with PDA planning-area boundaries
1B Maps of flood-sensitive catchments
1C Policy Supplement: text of alternatives S-1 to S-5 and model council resolution
1D Model GLDBCR amendment and model ULB bye-law
Form 1-1 Applicability Determination
Form 1-2 Variance / Waiver Request