Chapter 11Basin and City Stormwater Master Plans


11.1 Purpose and scope

11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.

11.1.2 A BSMP shall:

  • (a) map flood hazard for the basin under existing and future conditions;
  • (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
  • (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
  • (d) reserve land for regional storage, tollem and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
  • (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
  • (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).

11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.

Commentary. No Goa town has a published stormwater drainage master plan or a stated design return period, and no CAG audit of drainage or flood control in Goa was found (CAG Report No. 4 of 2025 on Goa covers urban waste management). In Panaji the master plan reportedly directed by the High Court in 1997 has not been prepared, and the drain-mapping committee set up in April 2024 has published nothing. Margao adopted a layout of its storm water nallahs and drains in November 2023, following High Court directions in a PIL on sewage reaching the Sal; nothing was found for Mapusa, Vasco or Ponda. Work under way is project-based: WRD's flood pumping station at Mala and its St Inez creek works, and the drain works of the Panaji Smart City Mission (press reports). A site-level manual cannot fix basin-level problems: lost tank storage, outfalls blocked by high tide or by neglected khazan sluice gates, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:

  • Denver's Mile High Flood District prepares major drainageway master plans that set regional facilities and release rates.
  • The Kansas City APWA criteria rest on regional watershed studies (MARC).
  • England's Surface Water Management Plans (Defra, Surface Water Management Plan Technical Guidance, 2010) set a phased method of preparation, risk assessment, options and implementation.
  • Malaysia's MSMA requires drainage master plans for urban areas.

This chapter adapts that method to Goa's estuaries and tidal creeks, its khazan lands with their bunds, sluice gates and poiems, the laterite plateaux and their tollems, a single dominant SW monsoon, and rivers that dam releases upstream can raise.


11.2 Definitions

Term Meaning in this Manual
Basin The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3.
Basin Stormwater Master Plan (BSMP) The plan for one basin prepared under this chapter.
Lead Authority The body responsible for preparing a BSMP (Clause 11.4).
Level of service (LoS) The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6).
Flood hazard map A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario.
Regional facility A storage, conveyance or outfall work serving more than one development, identified in a BSMP.
Capital Improvement Programme (CIP) The ranked, costed list of works in a BSMP (Clause 11.8.4).

11.3 Planning unit: the basin, not the ward

11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.

11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.

11.3.3 For the main urban areas, and for the river reaches that flood every few years, the basins are at least the following:

  • Panaji: the St Inez creek basin, which takes most of the city's storm water drains; the Mala basin, with Mala lake and the WRD flood pumping station; and the Ourem creek basin;
  • Margao: the basins of the storm water nallahs that drain to the Sal;
  • Mapusa: the basins draining to the Mapusa river;
  • Paroda: the Kushavati reach below Selaulim dam, which floods Zuna Bazar and Paroda Bazar;
  • Bicholim and Sanquelim: the Valvanti reaches through the two markets;
  • the villages of Pernem, Bicholim and Bardez talukas flooded by releases from the Tillari dam (Maharashtra), with river boundary conditions that include those releases; and
  • the Cumbarjua canal, treated as linking the Mandovi and Zuari basins it joins.

Other towns, including Vasco and Ponda, shall define their basins in the first BSMP that covers them. Where WRD has a study or an operating rule for a river or dam that a town lies on (for example the Mandovi, Zuari, Sal or Chapora, or the Selaulim, Anjunem or Tillari dam), the BSMP shall take its river boundary conditions from it.

Basin Stormwater Master Plan (BSMP) — process and links to site design 1. Basin set-up Delineate by basin, not ward (Cl. 11.3) Lead Authority + partners 2. Data DEM, drains, tanks, tides, flood marks (Cl. 11.5) 3. Model 1D–2D, 24–72 h storms, tide, continuous sim. calibrate to past floods 4. Gap vs LoS Scenarios: existing, future ± site controls, climate (Cl. 11.6–11.7) 5. Options Restore tanks first, then regional storage, conveyance, outfalls 6. Outputs (Cl. 11.8.4) — approved by State Stormwater Technical Committee • Flood hazard maps 10% / 1% / 0.2% AEP • Flood-sensitive catchments, basin release rates • Regional facility sites and fee-in-lieu rate • Capital Improvement Programme, ranked • Pre-monsoon maintenance programme • Monitoring network • Open data + public map viewer • Annual report, pre-monsoon Land-use plan Statutory master plan: reserve storage sites, flow paths, hazard zoning (Cl. 11.9) Site design Ch 4 release rates, regional detention and fee-in-lieu (Cl. 4.13, 4.5.6) Floors and setbacks 1% AEP future-with-plan map sets floor levels (Ch 6) and setbacks (Ch 7) Public works CIP funds: ULB, State, Union; O&M and desilting (Ch 10) Review every 10 yr, after a >1% AEP event, or plan revision (Cl. 11.11)

Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.

Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. Drains in Goa vest in the Corporation, the Municipal Councils and the Panchayats under their own Acts, while PWD builds road drains, WRD is in charge of "Flood Control, Anti-Sea Erosion and Drainage Works", IPSCDL has rebuilt Panaji's roads and drains, and the tenants maintain the khazan bunds and gates. No order dividing responsibility for urban drainage among them was found. St Inez creek, about 3.7 km long, takes the flow from most of Panaji's storm water drains, and its flushing is impeded by a box conduit, a sand bar and a footbridge at the mouth (press report), so a drain plan for any one ward of central Panaji depends on it. This clause makes the basin the planning unit. It also requires the Cumbarjua canal, which joins the Mandovi and the Zuari, to be treated as a link, because a decision on one side changes water levels on the other.


11.4 Who prepares, and when

11.4.1 Lead Authority.

  • For a basin wholly within the Corporation of the City of Panaji: CCP.
  • For a basin in the Panaji area that crosses the Corporation boundary (for example into the Taleigao planning area): GPPDA, with CCP, the other local bodies, IPSCDL and WRD as partners.
  • For a basin in another planning area that crosses local-body boundaries: the Municipal Council with the largest share of the basin, with the Planning and Development Authority for the area, the other local bodies, the TCP Department and WRD as partners.
  • For basins that drain through khazan bunds and sluice gates, or to a river reach whose level is set by dam releases (the Kushavati at Paroda below Selaulim dam, the Valvanti at Bicholim and Sanquelim, and the North Goa reaches flooded by releases from the Tillari dam in Maharashtra): WRD, with the local bodies and, for khazans, the tenants' associations and the Soil Conservation Division of the Directorate of Agriculture.
  • In Tier B bodies and village panchayat areas: the Lead Authority is named by the TCP Department. Basins draining to a common estuary or river reach may be grouped into one district-level plan.

WRD shall be a partner in every BSMP that includes a river, canal or tank under its control.

11.4.2 When a BSMP is required.

  • (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
  • (b) A BSMP is required before:
    • any regional detention or fee-in-lieu is accepted under Clause 4.13;
    • a fee held under Clause 4.5.6.3 is spent; and
    • a basin-specific release rate is applied under Clause 11.8.3.
  • (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.

11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.


11.5 Data and surveys

11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:

Table 11.1 — Minimum data and surveys for a BSMP

Data Minimum requirement
Terrain Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum
Drain network Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm
Waterbodies Survey of every tank, tollem, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment
Rivers and canals Cross-sections at no more than 200 m spacing and at every structure
Outfalls and coast Tidal datums and surge values (Annex 5A); tide levels up the estuary at the outfall; khazan bund crest and sluice-gate (mano) sill levels, and who operates each gate; dam releases upstream; gates and pumps
Rainfall and levels All available rain gauges (IMD, including the Panjim and Mormugao observatories and the 14 stations of the IMD Goa daily rainfall table, and any gauges of WRD) and water-level records, including those for the June 1999, October 2009, August 2019, July 2021 and August 2026 events
Flood evidence Surveyed flood marks and mapped flood extents from past events, including public reports
Land use Existing land use and imperviousness; future land use from the statutory master plan
Soils and groundwater HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones
Sewer interaction Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots

Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the flat estuarine and khazan lowlands a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The June 1999, October 2009, August 2019, July 2021 and August 2026 events are the best calibration data Goa has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.


11.6 Levels of service

11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.

Table 11.2 — Minimum levels of service

Element Minimum level of service
Minor system The design AEP of Chapter 6 (Table 6.1)
Habitable buildings No flooding above floor level in the 1% AEP (100-yr) event
Critical facilities (hospitals, emergency services, substations, water and sewage plants) No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event
Evacuation routes and arterial roads Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event
Ponding drain time Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event
Tank and tollem storage No net loss of flood storage below the MWL in the basin, measured against the earliest available survey
Outfalls Functioning under the joint and outfall-closed cases of Chapter 5

Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of low-lying storage that nobody has measured. The khazan area is given as 18,951 ha (Almeida 1967, as cited by Sonak 2014), about 18,500 ha (SAPCC) and 135.55 km² mapped from WRD data in the draft CZMP (NCSCM 2021). Of Goa's 25 notified wetlands, 16 were reported to be under pressure in June 2026, with hydrological alteration a major concern (press report). The High Court found that almost all the zone changes it examined were from paddy fields, natural cover, no-development zone and orchard to settlement (Goa Foundation v. State of Goa, WP No. 16 of 2023, 13 March 2025, as reported).


11.7 Modelling and scenarios

11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:

  • the minor system;
  • the major (overland) system;
  • rivers, canals and tanks; and
  • the outfalls.

Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.

11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.

11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.

11.7.4 Scenarios. Each BSMP shall model at least:

  • (a) Existing: existing land use, network, tanks and outfalls;
  • (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
  • (c) Future, controlled: future land use with the site controls of Chapter 4;
  • (d) Future, with plan: scenario (c) plus the works of the CIP; and
  • (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8 and the sea-level allowance of Chapter 5.

11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the June 1999, October 2009, August 2019, July 2021 and August 2026 events where data exist.

Figure 11.2 — BSMP model schematic Schematic plan of a basin model: design rainfall over sub-catchments; two tanks in cascade with surplus course; a 1D drain network linked to a 2D surface grid; a river or canal reach with an inter-basin link; an outfall with a flap gate and pumps; and a tidal or river level boundary. Numbered notes on the right explain each element. BSMP model: elements required by Clause 11.7 (schematic, not to scale) Sea / receiving water 1 S1 S2 S3 2 Upper tank Lower tank start level start level 3 2D surface 5 4 River / canal (1D) 6 Inter-basin link Gate Pumps 7 8 1 Design rainfall Ch. 2 storms incl. 24, 48, 72 h; 50%, 10%, 1%, 0.2% AEP; areal reduction (Cl. 2.7.3, 11.7.2) 2 Sub-catchments Runoff by Ch. 3 methods; land use for each scenario (a)–(e) of Cl. 11.7.4 3 Tanks and ponds Surveyed FTL, MWL, stage–storage, sluices, surplus weirs (Cl. 11.5.1); start level from continuous run (Cl. 3.13.5, 11.7.3) 4 1D drain network Minor system: drains, pipes, culverts with surveyed inverts and silt (Cl. 11.5.1) 5 2D surface Major (overland) system on the DEM, 0.15 m RMSE or better; exchange with 1D at inlets and manholes 6 Rivers and canals (1D) Sections ≤ 200 m apart and at every structure; diversions between basins mapped (Cl. 11.3.2) 7 Outfall Flap or tide gates and pumps; joint and outfall-closed cases of Ch. 5 8 Downstream boundary Tide (MHWS; HAT + surge + sea-level allowance) or river level, per Ch. 5 Calibrate and validate with at least two major past flood events where data exist (Cl. 11.7.5).

Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and tollems with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.

Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).


11.8 Options, outputs and the Capital Improvement Programme

11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:

  1. Protect and restore storage: tollems, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
  2. Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
  3. Conveyance upgrades to drains, canals and culverts;
  4. Outfall works: gates, pumps, and the repair and operation of khazan bunds and sluice gates;
  5. Property-level protection where works cannot reach the level of service; and
  6. Non-structural measures: flood warning (for example IMD district rainfall warnings for North Goa, South Goa and Kushavati, read with the predicted high tides), flood-hazard zoning, emergency planning and public information.

11.8.2 Option assessment. Each option shall be assessed for:

  • reduction in flood risk (buildings and people flooded; expected annual damage);
  • capital and 30-year maintenance cost;
  • land required;
  • effect on groundwater recharge and saline intrusion (Chapter 8);
  • effect on downstream basins and the Cumbarjua canal; and
  • who benefits.

11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.

11.8.4 Outputs. Each BSMP shall produce:

  • (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
  • (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
  • (c) regional facility sites, with storage volumes, land needs and the sites they serve;
  • (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
  • (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
  • (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
  • (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.

Commentary. Restoring storage comes first because Goa already has a regional storage system: the khazans with the poiems inside their bunds, the mangroves and mudflats of the estuaries, the tollems and the notified wetlands. WRD already uses Mala lake as the retention basin for its Panaji pumping station (press report). The State Disaster Management Plan (2014) attributes urban floods to faulty planning, the choking of drainage systems and unplanned growth. Conveyance upgrades on their own move water faster to an outfall that may be tide-locked. In Goa the water table is shallow after the monsoon, with minimum post-monsoon depths of about 0.4–1.2 m below ground in the district records (CGWB, as reported), and in the khazans and estuarine fringes it rises and falls with the tide. Salt water reaches about 65 km up the Mandovi and the Zuari in the dry season (Qasim and Sen Gupta 1981, as reported), and the khazan bunds and sluice gates are what keep it off the fields. Deeper drains, or a drain cut through a khazan bund, can lower the water table and let saline water in, which is why groundwater and saline intrusion are assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.


11.9 Integration with land-use planning

11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the Regional Plan for Goa 2021 and the Outline Development Plans of the planning areas, under the Goa Town and Country Planning Act 1974. In particular:

  • (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
  • (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
  • (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
  • (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.

11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.

Commentary. GLDBCR 2010 already says that "as far as possible" no buildings shall be permitted in flood-prone areas identified in the disaster management plans (Regulation 19), and counts as natural-hazard-prone the areas flooded by back flow in drains or inadequate drainage "as identified through local surveys in the development plan" (Regulation 2(88)). The Regional Plan for Goa 2021 places all rivers, nallahs, creeks and tanks, and the paddy fields and khazans, in its no-development ECO-1 zone, but admits that seasonal nallahs and small ponds may not appear on its taluka maps, and records that flooding and high flood level data are needed from WRD. None of these provisions rests on a flood map. A BSMP gives the Regional Plan and the Outline Development Plans the 1% AEP map that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because GLDBCR 2010 already requires the roads and open spaces of a sub-division to be developed "so as to prevent water logging and flooding" (Regulation 12.5(b)); because that land then serves as open space, storage placed in it must stay usable as one. Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.


11.10 Consultation and publication

11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.

11.10.2 After approval, the following shall be published as open data:

  • the model files;
  • the flood hazard maps;
  • the data of Clause 11.5.1, except security-sensitive asset details; and
  • the CIP.

They shall also be shown on a public map viewer.

Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.


11.11 Approval, review and reporting

11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.

11.11.2 Review. Each BSMP shall be reviewed:

  • every 10 years;
  • within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
  • when the statutory land-use plan is revised.

11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each SW monsoon (by 15 May). The report shall show:

  • CIP progress;
  • the fee-in-lieu ledger (Clause 4.13.4);
  • maintenance completed; and
  • any flooding against the levels of service.

11.12 Interim arrangements

11.12.1 Until a BSMP is approved for a basin:

  • (a) all site criteria of Chapters 4 to 8 apply in full;
  • (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
  • (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
  • (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.

References (chapter)

Annexes and forms

Annex / Form Content
11A BSMP terms of reference template
11B Basin lists and boundaries for Tier A bodies
11C Depth–damage curves for Goa building types
11D BSMP data and model publication standard
Form 11-1 Annual implementation report