Chapter 7Waterbodies, Khazans and Setbacks
7.1 Purpose and scope
7.1.1 This chapter treats waterbodies as part of the drainage system. It sets the rules for:
- (a) identifying and mapping every waterbody that a development or public work affects;
- (b) the setback zones around waterbodies, and the uses allowed in each zone;
- (c) fill in flood-prone land, and the compensatory storage needed where fill is allowed;
- (d) counting tank (tollem) storage, including tank cascades, as design storage;
- (e) restoring and desilting tanks and ponds;
- (f) protecting supply channels, surplus courses, inlets and outlets;
- (g) wetlands, marshes and estuaries, including the khazans, the estuaries, creeks and mangroves of the Mandovi, Zuari, Chapora and Sal, and Nanda Lake (Ramsar);
- (h) the interface with encroachment and its removal;
- (i) fee-in-lieu contributions to regional tank storage (with Chapter 4); and
- (j) the safety of tank bunds and other embankments.
7.1.2 This chapter applies to every development and public work to which this Manual applies under Chapter 1 and that:
- (a) adjoins a waterbody or lies wholly or partly within its setback (Clause 7.4);
- (b) discharges to a waterbody, directly or through a drain, within the downstream analysis extent of Chapter 5; or
- (c) alters a waterbody, its bund, sluice, surplus weir, supply channel or surplus course.
7.1.3 Where a statute or statutory rule sets a wider setback or a stricter restriction, the statute governs (Clause 1.3.3). Nothing in this chapter authorises any work that the Goa, Daman and Diu Town and Country Planning Act, 1974 (sections 17A and 17B), the Goa Agricultural Tenancy Act, 1964, the Goa, Daman and Diu Irrigation Act, 1973, the Coastal Regulation Zone Notification, 2011 as applied through the CZMP of Goa, the Wetlands (Conservation and Management) Rules, 2017, or any other law, prohibits.
7.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Waterbody | A river, tidal river or estuary, creek, nallah (stream or natural drain), canal, lake, tank or pond (tollem), temple tank, spring, khazan (bunded tidal paddy land) with its poiem, paddy field, marsh, mudflat or mangrove, supply channel or surplus course, perennial or seasonal (as in Chapter 1). |
| Tank (tollem) | A waterbody impounded by an earthen bund, fed by its own catchment and/or a supply channel, with a surplus weir and one or more sluices. |
| Tank cascade | A chain of tanks in which the surplus or sluice outflow of one tank feeds the next (as in Chapter 3). |
| Full tank level (FTL) | The crest level of the surplus weir (overflow or spillway) of a tank, or the permanent crest of its regulating structure. The tank holds water up to FTL without spilling. |
| Maximum water level (MWL) | The highest water level in a tank when the surplus weir passes the tank's design flood. For this Manual, it is the greater of the level recorded by the WRD and the level computed for the 1% AEP (100-yr) inflow with the climate factor of Clause 2.8 (Clause 7.7.4). |
| Top bund level (TBL) | The crest level of the tank bund. |
| Waterspread | The area of a tank submerged at FTL. |
| Foreshore | The land around a tank between the FTL contour and the MWL contour. Foreshore land is flooded whenever the tank surpluses, and is part of the tank's flood storage. |
| Supply channel (feeder nallah) | A channel that brings water from a river, anicut or upstream tank into a tank. |
| Surplus course | The channel that carries the overflow of a surplus weir to the next tank, a river, a drain or the sea. |
| Sluice (sluice gate; in a khazan bund, the mano) | A controlled outlet through a tank bund, usually to an irrigation channel. |
| Top of bank | For a channel, the break in slope at the edge of the channel. Where it cannot be identified, the edge of the water surface at the 50% AEP (2-yr) flow. |
| 1% AEP flood extent | The land flooded by the 1% AEP (100-yr) flood with the climate factor of Clause 2.8, from a hydraulic model that meets Chapter 3 and Chapter 5, or from a map adopted by the Authority under Clause 7.3.4. |
| Floodway | The waterbody and the adjoining land that must be kept free of obstruction to pass the 1% AEP flood without raising the 1% AEP water level by more than 0.1 m at any point (Clause 7.6.1). For a tank, all land below MWL. |
| Flood fringe | The part of the 1% AEP flood extent outside the floodway. |
| Zone 1 (waterbody protection zone) | The inner setback zone defined in Clause 7.4.3. |
| Zone 2 (flood fringe setback) | The outer setback zone defined in Clause 7.4.4. |
| Setback | Zone 1 and Zone 2 together. |
| Compensatory storage | Excavated storage that replaces flood storage lost to fill, under Clause 7.6.4. |
| Flood cushion | Storage below FTL kept empty, under a documented operating rule, to absorb a flood (Clause 7.8). |
Goa terms. The following terms are used in this chapter in addition to those above (see also Annex 7E):
| Term | Meaning in this Manual |
|---|---|
| Khazan | Low-lying land beside a tidal river or creek, reclaimed from the estuary by an outer bund and drained through sluice gates (manos), and used for salt-tolerant paddy, fish and, in places, salt. The Goa Agricultural Tenancy Act, 1964 calls it "Khajan land": "low land situated near creeks or riversides". For this Manual a khazan is a tidal polder. Its storage is flood storage; unless a survey shows that it lies above the 1% AEP flood level, fill in a khazan is fill below that level, and Clause 7.6 applies in addition to every other permission. Its storage may be counted as design storage only under Clauses 7.7 and 7.8. |
| Outer (protective) bund | The bund between a khazan and the river or creek. Its maintenance is the duty of the tenants (sections 26(3) and 35 of the Tenancy Act), with a Government contribution for bunds specified as protective bunds. It is a tank bund for Clause 7.14. Since the 2020 amendment of the CRZ Notification, 2011 (S.O. 1422(E)), the High Tide Line in a khazan runs along a bund or sluice gate built before 19 February 1991. |
| Mano (sluice gate) | A sluice gate in a khazan bund, traditionally of wood, that opens when the water inside is higher than the tide outside and shuts on the rising tide. Tenants have the right to operate it and the duty to maintain it (section 38 of the Tenancy Act); in some villages the comunidade lets it each year to a lessee (as reported). For this Manual it is a tidal non-return outlet operated by a third party: its capacity is a tailwater-dependent outflow under Chapter 5, and no flood cushion may be assumed behind it except under Clause 7.8. |
| Poiem (poim) | A depression or pit inside a khazan, near the sluice gate and at its lowest level, that holds water and fish. Storage in a poiem below the sill of the mano is not flood storage (Clause 7.9.3). |
| Tollem | A village tank or lake. Where its outlet openings (sadd) are closed by planks (daram), FTL is the top of the planks normally in place; where it has an overflow, FTL is the overflow invert; otherwise it is the lowest point of the rim. Plank openings are a controllable outlet only under an operating rule (Clause 7.8). |
| Nallah | A natural stream or drain, perennial or seasonal; the term used in GLDBCR 2010 and the Regional Plan. A nallah draining 8 ha or more is a natural channel under Clause 7.4.1(b) whether or not it is shown on the Regional Plan or an ODP. |
| Tidal-influenced water body | A river, creek, backwater or lagoon influenced by the tide, up to the limit where salinity is 5 parts per thousand in the driest season, as defined in the CRZ Notification. In Goa the tide travels about 40 km up the Mandovi and Zuari, so outfalls far inland can still be tidal; tailwater is taken from Chapter 5. |
| Low-lying land | Land 50 cm or more below the adjoining ground (section 17A of the TCP Act, 1974). Its filling needs the prior written permission of the Chief Town Planner. For this Manual, fill on low-lying land is presumed to be below the 1% AEP flood level unless a survey shows otherwise, and Clause 7.6 applies in addition to the section 17A permission. |
| Spring | A place where groundwater comes to the surface, with the pool, seepage area and channel it feeds. A spring is a waterbody; Zone 1 is measured from the edge of the pool or seepage area. |
7.3 Inventory and mapping of waterbodies
7.3.1 Statewide inventory. The Authority, with the WRD and the Revenue Department, shall maintain a GIS layer of every waterbody in its area (Annex 7A). For each waterbody it shall record:
- (a) its type (Clause 7.2), name and survey numbers;
- (b) its custodian (the WRD, the Agriculture Department (Soil Conservation Division), the ULB, the Village Panchayat, a comunidade, a khazan tenants' association, the Forest Department or another body);
- (c) its boundary as recorded in Revenue records;
- (d) for tanks: FTL, MWL, TBL, the surplus weir crest length and type, sluices, the supply channel and the surplus course, each with its datum;
- (e) its position in any tank cascade, with the upstream and downstream tanks;
- (f) the 1% AEP flood extent, where mapped; and
- (g) known encroachments, with the date recorded.
7.3.2 Project mapping. Every drainage report shall include a Waterbody Sheet (Form 7-1) showing all waterbodies:
- (a) within the site;
- (b) within 100 m of the site boundary; and
- (c) downstream, to the extent of the downstream analysis of Chapter 5.
The sheet shall show, on a plan at a scale of 1:1,000 or larger for (a) and (b):
- the Revenue record boundary;
- the surveyed FTL or top of bank;
- the MWL contour (tanks) and the 1% AEP flood extent;
- Zone 1 and Zone 2 (Clause 7.4); and
- every supply channel, surplus course, sluice and surplus weir.
7.3.3 Sources. Waterbodies shall be identified from all of the following. Where they conflict, the larger waterbody extent governs:
- (a) Revenue village survey plans and survey records of the Directorate of Settlement and Land Records (DSLR), including land recorded as "Rice", the paddy and khazan land and water bodies shown in the Regional Plan for Goa 2021 (khazans marked "K"), and the khazans, mangroves and High Tide Line of the approved Coastal Zone Management Plan (CZMP 2011) maps;
- (b) WRD and Village Panchayat tank registers and records of FTL and MWL;
- (c) the Authority's inventory (Clause 7.3.1) and any list published under court directions;
- (d) historical topographic maps and satellite imagery, including the ISRO National Wetland Inventory and Assessment; and
- (e) a site survey by a licensed surveyor, levelled to the datum stated in Clause 7.3.5.
7.3.4 Flood extent maps. The Authority may adopt 1% AEP flood extent or flood depth maps for its area. A depth map adopted under this clause also sets floor levels under Clause 6.11. Where a map has been adopted, it shall be used unless a site hydraulic study under Chapters 3 and 5 shows a larger extent. Where no map has been adopted, the Applicant shall determine the 1% AEP extent by a hydraulic study for:
- (a) any site in a flood-sensitive catchment (Chapter 1);
- (b) any site of 1 ha or more adjoining a waterbody; and
- (c) any site where the Authority so requires.
For other sites, the fixed-width setback of Clause 7.4.6 may be used.
7.3.5 Datum. All levels in this chapter shall be stated to one datum, stated on every drawing. Where WRD records use a local or older datum, the conversion to the project datum shall be surveyed and stated.
Commentary. No 1% AEP flood map of any Goa town was found. GLDBCR 2010 Regulation 19 keeps buildings out of flood-prone areas identified in the plans of the GSDMA "as far as possible", but no GSDMA flood hazard map was seen during research for this Manual, and the Regional Plan for Goa 2021 itself states that "flooding area data, high flood level (expected) area data is required from Water Resources Department" (RPG-21, Release One, §4.7). The Regional Plan maps water bodies at taluka scale and says that seasonal nallahs and small ponds may be missing from its maps, to be added in settlement-level plans (§3.6). The most detailed official maps of waterbodies are the CZMP maps under the CRZ Notification, 2011, at 1:25,000 and 1:4,000, which show the High Tide Line, the CRZ lines, the khazans and the mangroves; they cover only the tidal zone. In Panaji, a committee led by Imagine Panaji Smart City was set up in April 2024 to map the storm drain network, much of it from the Portuguese period, but no map from it was found. The GSWA had identified 42 wetlands by November 2022 (GSWA report to the NGT). Clause 7.3.4 lets the Authority adopt larger-scale flood maps once they are issued. Until then, the Applicant must produce the extent for larger and flood-sensitive sites. Clause 7.3.3 makes the larger of the recorded and surveyed extents govern, because the Revenue boundary and the surveyed water edge often differ, and either may have been reduced by encroachment. The 100 m search band in Clause 7.3.2 is set by this Manual.
7.4 Setbacks
7.4.1 Waterbodies to which setbacks apply. Setbacks apply to:
- (a) every waterbody recorded under Clause 7.3.1 or found under Clause 7.3.3, whatever its size; and
- (b) every natural channel, whether recorded or not, that drains 8 ha or more at the site.
7.4.2 Two zones. The setback has two zones, shown in Figure 7.1:
- Zone 1 (waterbody protection zone), next to the waterbody; and
- Zone 2 (flood fringe setback), outside Zone 1.
7.4.3 Zone 1 width. Zone 1 is measured outward from the FTL contour (tanks, lakes and ponds) or from the top of bank (channels). Where both apply, use whichever gives the wider zone. Zone 1 extends to the greatest of:
- (a) 15 m, the minimum set by this Manual (no Goa statute or regulation sets a general setback from nallahs, non-tidal rivers or tanks; see the Disclosure below);
- (b) the outer edge of the floodway (Clause 7.6.1); and
- (c) for a tank, the MWL contour.
7.4.4 Zone 2 width. Zone 2 extends from the outer edge of Zone 1 to the 1% AEP flood extent plus 10 m. Where the 1% AEP flood extent lies inside Zone 1, Zone 2 is 10 m wide.
7.4.5 Statutory and approval setbacks. Where a statute, a statutory rule, a condition of planning permission or a WRD NOC, a GCZMA clearance or a GSWA permission sets a setback wider than Zone 1 or Zone 2, the wider setback governs for the uses it restricts.
7.4.6 Fixed-width setback where no 1% AEP extent is available. Where Clause 7.3.4 does not require a hydraulic study and no map has been adopted, the setback (Zone 1 plus Zone 2) shall be not less than the following, measured as in Clause 7.4.3:
Table 7.1 — Fixed-width setback where no 1% AEP extent is available
| Waterbody | Total setback (Zone 1 + Zone 2) | Of which Zone 1 |
|---|---|---|
| Channel draining 8 ha to 65 ha | 25 m | 15 m |
| Channel draining 65 ha to 20 km² | 40 m | 15 m |
| Channel draining more than 20 km², and rivers | 50 m | 20 m |
| Tank, lake or pond | MWL contour + 25 m | to MWL contour, and not less than 15 m from FTL |
| Marsh, estuary or backwater | as notified by the Authority, and not less than 50 m | 15 m |
This table is the alternative S-3 of the Policy Supplement (Annex 1C) and may be adopted under Clause 1.7.
7.4.7 Minimum in all cases. No setback under this chapter, and no variance under Clause 1.10, shall reduce Zone 1 below 15 m (Clause 1.10.3(c)).
Commentary. The 15 m minimum is set by this Manual, because GLDBCR 2010 and the Regional Plan for Goa 2021 set no numeric setback from nallahs, rivers or tanks (see the Disclosure below). Extending the setback to the mapped 1% AEP extent plus a margin follows the Kansas City Metro APWA Section 5600 (2025.01) two-zone structure:
- APWA Zone 1 (streamside) is measured from top of bank, and only utility and road crossings are allowed in it.
- APWA Zone 2 is the 1% AEP flood extent plus 10 ft (about 3 m), for streams draining 20–40 acres.
- APWA lowered the trigger for stream setbacks from 40 acres to 20 acres (about 8 ha) in 2025.01.
(MARC, APWA 5600 Policy Supplement, Nov 2025.) Clause 7.4.1(b) adopts the 8 ha trigger. This Manual's 10 m margin is wider than APWA's 10 ft and has no direct precedent. This Manual sets it because Goa flood maps are mostly coarser than US maps, the ground on the coastal plain and in the khazans is very flat (so a small error in level moves the flood edge a long way), and the margin gives room for maintenance access along the waterbody.
The fixed-width table in Clause 7.4.6 is set by this Manual. Its channel widths are scaled from the 2006 APWA default stream buffers, which were 40 ft, 60 ft, 100 ft and 120 ft (12, 18, 30 and 37 m) for drainage areas of less than 40 acres, 40–160 acres, 160–5,000 acres and more than 5,000 acres (KC APWA 5600, 2006, §5605.3). They are rounded up and floored at the 15 m minimum. APWA offered a fixed-width table for the same reason: communities objected that the 1% extent is often unmapped for small drainage areas (MARC Supplement, 2025). The table should be replaced by mapped extents as soon as the Authority adopts them.
URDPFI (2015) reserves the area flooded at a 10-year frequency for parks and playgrounds, and allows residential use in the 25-year flood zone only on stilts, with minimum plinth levels and no basements. This chapter is stricter. It keeps habitable buildings out of the whole 1% AEP extent plus margin, because the 1% AEP (100-yr) event is the major-system standard of this Manual (Chapter 6).
Goa's building and planning rules set no numeric setback from nallahs, non-tidal rivers or tanks. GLDBCR 2010 asks only for the distance from a river bank where the property is within 100 m of it (application form, item 13), and requires roads and plots to be developed "so as to prevent water logging and flooding" (Regulation 12.5). The Regional Plan for Goa 2021 puts water bodies, paddy fields and khazans in its no-development zone ECO-1 but gives them no width, so the edge of the zone is the edge of the waterbody as mapped. The distances that do exist come from other regimes: the Coastal Regulation Zone along the sea and tidal waters (see the Disclosure below); the line 50 m from the mean high flood level of the past ten years in every wetland notified by the GSWA; and, in Panaji, section 173 of the City of Panaji Corporation Act, 2002, which bars a building within 15 m of a municipal drain until it is connected to a drain, a rule about drainage connection, not a setback. Section 11 of the Goa, Daman and Diu Irrigation Act, 1973 allows the Government to notify limits along "any river, stream or natural drainage course" within which no obstruction may be formed; no such notification was found. Section 17A of the TCP Act controls the filling of low-lying land but sets no distance from water. Clause 7.4.7 makes 15 m the floor everywhere.
Disclosure. Goa has no general statutory setback from nallahs, non-tidal rivers or tanks. The 15 m minimum Zone 1 of Clauses 7.4.3 and 7.4.7, and every value derived from it in Table 7.1, is set by this Manual as a hydraulic corridor. It is not found in GLDBCR 2010, the Regional Plan for Goa 2021 or any Goa Act. The setback is applied as the larger of that corridor and any statutory line, so the Manual is stricter than statute wherever no statutory line exists: along inland nallahs and rivers above the tidal limit, around tollems and springs, and along tidal water in the municipal areas that the CZMP classes as CRZ-II, where there is no no-development zone. What does exist, and governs wherever it is wider (Clause 7.4.5), is:
- CRZ Notification, 2011, through the CZMP of Goa. The CRZ Notification, 2019 does not yet apply in Goa: under its paragraph 6(i) the CZMP made under the 2011 Notification continues until a revised plan is approved, and Goa's CZMP 2019 was still in draft in June 2026 (news reports). The CZMP 2011 was approved in September 2022 (news reports; the approval letter was not seen). In CRZ-III it sets a no-development zone of 200 m from the High Tide Line on the seafront and of 100 m or the width of the creek, whichever is less, along tidal-influenced water bodies; the draft CZMP applies the latter to the Tiracol, Chapora, Mandovi, Zuari, Sal and Talpona and to the creeks and backwaters. Mangroves larger than 1,000 m² have a 50 m buffer. Since the 2020 amendment (S.O. 1422(E)), the High Tide Line in a khazan runs along a bund or sluice gate built before 1991, and no development is permitted in khazan land (paragraph 8.V.3). The Panaji, Mapusa, Bicholim, Mormugao, Cuncolim and Canacona municipal areas are CRZ-II. Storm water drains and tidal regulators are among the works the Notification permits in the CRZ, with appraisal by the GCZMA. Once a CZMP under the 2019 Notification is approved, the tidal-water line is expected to become 50 m or the creek width.
- Wetlands (Conservation and Management) Rules, 2017. Every GSWA notification read bars permanent construction, other than boat jetties, within 50 m of the mean high flood level observed in the past ten years. How that level is fixed, and on what datum, was not stated in the notifications read; the Applicant shall obtain it from the GSWA, and the line governs wherever it lies outside Zone 1.
- TCP Act, 1974, section 17A, and the Regional Plan. Filling of low-lying land needs permission, and water bodies, paddy fields and khazans are no-development ECO-1 land. Neither is a distance setback.
This Manual sets 15 m as the floor because it is above the smallest APWA default stream buffer (12 m) from which Table 7.1 is scaled; because it leaves room for a maintenance track, desilting machinery and bank planting along nallahs and tollem edges that depend on regular cleaning; and because it can be marked on the ground before a flood extent is mapped. It adds nothing where the CRZ or a wetland line applies and is wider, but sets a floor on the many seasonal nallahs, tollems, springs and khazan edges that the Regional Plan does not map. The statutory route to make such a corridor binding already exists in section 11 of the Irrigation Act, 1973. Until a statute, rule, notification or ODP adopts it, the 15 m minimum is this Manual's recommended standard and the statutory lines above remain the only legal minimum. Approving authorities should state in each approval which was applied.
Figure 7.1 — Waterbody setback zones: section through a tank or channel showing FTL, the 1% AEP flood level, the 15 m minimum line, Zone 1 and Zone 2. Original drawing for this Manual, adapted from Kansas City Metro APWA, Section 5600 Version 2025.01 and Policy Supplement (MARC, 2025).
7.5 Uses permitted in each zone
7.5.1 Zone 1. No building, fill, paving, retaining wall, boundary wall, compound wall, dumping of earth, debris or solid waste, storage of materials, or construction-stage stockpile shall be placed in Zone 1. Only the following are permitted, each subject to the custodian's NOC:
- (a) road, rail and utility crossings that meet Clause 7.10.3;
- (b) flood and drainage works: outfalls, inlet structures, gross pollutant traps, sluices, surplus weirs, bund strengthening and bank protection;
- (c) native vegetation, planting and habitat works;
- (d) unpaved or permeable footpaths and maintenance tracks at existing ground level; and
- (e) waterbody restoration under Clause 7.9.
7.5.2 Zone 2. No habitable building, basement, school, hospital, fuel store or hazardous-material store shall be placed in Zone 2. The following are permitted:
- (a) all uses permitted in Zone 1;
- (b) parks, playgrounds, open-air sports fields and urban agriculture;
- (c) open-sided structures (shelters, pavilions) with no walls that obstruct flow;
- (d) surface parking with permeable surfacing at existing ground level, where the 1% AEP flood depth is not more than 0.3 m;
- (e) retention, detention and water quality facilities under Chapters 4 and 8, provided they are outside the floodway and their storage is not counted twice (Clause 7.6.5); and
- (f) fill, only for (a) to (e) or for essential public infrastructure, and only with compensatory storage under Clause 7.6.4.
7.5.3 Fences. Fences in Zone 1 and Zone 2 shall be open (chain-link or railing) with no plinth wall above existing ground level, so that they do not obstruct flow or trap debris.
7.5.4 Open space reservation. Zone 2 land may be counted toward the open space required by GLDBCR 2010, where the Authority agrees. Zone 1 land shall be handed over to the custodian or kept free of private use, as the Authority decides.
Commentary. The permitted uses follow APWA 2025.01: in Zone 1, only utility and road crossings; in Zone 2, linear utilities, trails and open-sided structures; no clearing, grading, fill or paving in either zone without approval (MARC Supplement, 2025). Clause 7.5.2 adds parks and playgrounds, the uses URDPFI (2015) allows in the 10-year flood zone. The ban on walls in Clauses 7.5.1 and 7.5.3 responds to urban Goa practice: compound walls along channels and tanks act as dams in floods, and are often the first step toward encroachment. The 0.3 m depth limit for parking in Clause 7.5.2(d) has no direct precedent and is set by this Manual.
7.6 Floodway, flood fringe and compensatory storage
7.6.1 Floodway delineation. The floodway shall be delineated by a hydraulic model of the 1% AEP flood (with the climate factor), using the encroachment method: the conveyance of the flood fringe is removed equally from both banks until the 1% AEP water level rises by 0.1 m. Where the floodway has not been delineated, the whole 1% AEP flood extent shall be treated as floodway. For a tank, all land below MWL is floodway.
7.6.2 No fill in the floodway. No fill, building, embankment, raised road or other obstruction shall be placed below the 1% AEP flood level within the floodway, except the works permitted in Zone 1 under Clause 7.5.1(a) and (b). Those works shall be shown by hydraulic analysis to raise the 1% AEP water level by no more than 0.01 m, upstream or downstream, outside the Applicant's land.
7.6.3 Fill in the flood fringe. Fill below the 1% AEP flood level in the flood fringe is permitted only:
- (a) for uses permitted under Clause 7.5.2, or outside the setback where the Authority has notified a developed-fringe area under Clause 7.6.6; and
- (b) with compensatory storage under Clause 7.6.4.
7.6.4 Compensatory storage. Where fill is placed in the flood fringe, compensatory storage shall be provided that (Figure 7.2):
- (a) replaces at least 1.0 m³ of storage for each 1.0 m³ of fill placed below the 1% AEP flood level;
- (b) is provided at equivalent levels: the volume lost and the volume replaced shall be balanced in each elevation band of not more than 0.3 m, from the normal water level (or the 50% AEP level, where higher) up to the 1% AEP flood level;
- (c) is in the same reach of the same waterbody, hydraulically connected to it, and not further downstream than the fill;
- (d) drains freely by gravity back to the waterbody as the flood recedes, with no pumping and no permanent pool below the normal water level;
- (e) is built before, or at the same time as, the fill is placed; and
- (f) is secured by a covenant or handover so that it is never filled later.
7.6.5 No double counting. Compensatory storage shall not be counted as detention or retention storage under Chapter 4. Detention and retention storage placed within the 1% AEP flood extent shall be counted only for the volume above the 1% AEP flood level, unless a model of the joint event (Clause 2.12) shows that it is available.
7.6.6 Developed-fringe areas. The Authority may notify, by map, areas of existing built-up land within the 1% AEP flood extent but outside the floodway, where it is impractical to apply Zone 2 to redevelopment. In a notified developed-fringe area:
- (a) redevelopment may be approved without the Zone 2 restriction;
- (b) the lowest habitable floor and all openings shall be at least 0.5 m above the 1% AEP flood level (Chapter 6);
- (c) basements are not permitted;
- (d) the redevelopment shall cause no net loss of flood storage below the 1% AEP flood level (Clause 7.6.4), and stilt construction may be used for this; and
- (e) Zone 1 continues to apply in full.
Commentary. The 1:1 compensatory storage at equivalent levels is set by this Manual. A simple volume balance is not enough: storage excavated below the normal water level is full before the flood arrives and gives no flood benefit. Storage gained high up does not replace storage lost low down, because the low storage is used in every flood and the high storage only in the largest. Balancing volume within each elevation band avoids both problems. The 0.3 m band, the 0.01 m allowance for crossings, and the use of the encroachment method in Clause 7.6.1 are set by this Manual; the encroachment method is the standard way to delineate a floodway in a one-dimensional hydraulic model. The 0.1 m limit on the rise in the 1% AEP water level is tighter than the 1 ft (about 0.3 m) used by the US National Flood Insurance Program. Goa's khazans and coastal plains are flat, and much of the khazan land lies near or below the level of high tide, so a small rise in level spreads flooding over a wide area, and many small encroachments along the same channel add up.
The nearest Goa rule to a foreshore is the GSWA line: each notified wetland, such as Carambolim Lake (2023) and Nanda Lake (2021), has a zone of influence that includes a 50 m buffer, and permanent construction is barred within 50 m of the mean high flood level observed in the past ten years. In Panaji, Mala lake is used as the retention basin of the Mala flood pumping station (as reported), so its foreshore is part of the city's flood storage. Treating all land below MWL as floodway (Clause 7.6.1) means that no new building or fill is approved in a tank foreshore.
The developed-fringe mechanism of Clause 7.6.6 is set by this Manual. Large parts of low-lying Panaji around the St Inez creek and Mala, and the market areas of Bicholim and Sanquelim on the Valvanti already lie within the 1% AEP extent. A blanket Zone 2 ban on redevelopment there would stop the replacement of older, lower buildings with buildings raised above flood level. The mechanism follows the URDPFI (2015) approach for the 25-year flood zone (stilts, minimum plinth, no basements), applied here to the 1% AEP extent.
Figure 7.2 — Compensatory storage by elevation band: section through the flood fringe showing fill placed below the 1% AEP flood level and an equal or greater volume excavated within each band of not more than 0.3 m, from the normal water level (or 50% AEP level) up to the 1% AEP level, with the excavation draining back to the waterbody by gravity. Band-by-band calculation on Form 7-3. Original drawing for this Manual, illustrating the method of Clause 7.6.4, which is set by this Manual.
7.7 Tank cascades as design storage
Goa has few impounded irrigation tanks with surplus weirs and sluices. Its storages are tollems, many built and once kept by the comunidades, whose outlets are closed by planks; khazans, which are tidal polders held by an outer bund and drained through manos; and a few urban lakes, such as Mala lake in Panaji, held by pumps or gates. In this Manual, Clauses 7.7 and 7.8 apply to any of these whose storage is counted: a tollem, a khazan or its poiem operated under a sluice rule, or a lake held by a pumping station or regulator. A chain of tollem, nallah, khazan and creek in which each drains into the next is a tank cascade for Clause 7.7.2. The irrigation reservoirs, such as Selaulim and Anjunem, and the Tillari dam in Maharashtra, are not tanks for these clauses: their releases and levels enter a design as tailwater (Chapter 5).
7.7.1 When tank storage may be counted. The storage of a tank or tank cascade may be counted as design storage (in a basin plan, a regional facility or a fee-in-lieu scheme under Clause 7.11) only where all of the following are met:
- (a) Surveyed levels. FTL, MWL, TBL, the surplus weir crest and length, and the sluice sill levels have been surveyed to the datum of Clause 7.3.5 within the previous 5 years.
- (b) Stage–storage curve. A stage–storage curve has been derived from a bathymetric and topographic survey of the waterspread and foreshore within the previous 5 years, or after the last desilting, whichever is later.
- (c) Operating rule. A documented operating rule has been agreed with the custodian (Clause 7.8).
- (d) Maintained structures. The surplus weir, sluices and bund are maintained under an O&M plan (Chapter 10), and the latest pre-monsoon inspection found them serviceable.
- (e) Custodian concurrence. WRD, or the other custodian, concurs in writing.
Storage in a tank that fails any of (a) to (e) shall not be counted, though the tank shall still be modelled as an existing feature (Chapter 3).
7.7.2 Modelling. Tank cascades shall be modelled under Clause 3.12.5 (level-pool routing of each tank, with surplus weir and sluice ratings) and Clause 3.13 (continuous simulation). The whole cascade, from the uppermost tank whose surplus can reach the site or facility to the next river, major drain or sea outfall, shall be modelled together, including any khazan, poiem and mano (sluice gate) through which the outflow passes to the estuary, as shown in Figure 7.3.
7.7.3 Starting level. The starting level in every tank shall be FTL for the design-storm analysis. A lower starting level may be used only under a flood-cushion operating rule that meets Clause 7.8.
7.7.4 Design maximum level. For the 1% AEP inflow with the climate factor, routed through the cascade:
- (a) the computed maximum level shall be not higher than MWL (as defined in Clause 7.2); and
- (b) the freeboard from the computed maximum level to the lowest point of the bund (TBL) shall be not less than WRD's freeboard standard for the tank.
Where (a) or (b) fails, the tank storage above FTL shall not be counted until the surplus weir capacity is increased or the bund raised under Clause 7.7.6.
7.7.5 Creditable volume. The creditable design storage of a tank is the volume between the starting level (Clause 7.7.3) and the computed maximum level of Clause 7.7.4, less any volume already committed to another facility or scheme.
7.7.6 Changes to FTL, weirs and bunds. No surplus weir crest shall be raised or lowered, no shutters or falling boards shall be added, and no bund shall be raised, cut or breached except under a design approved by the custodian that:
- (a) routes the cascade under Clause 7.7.2;
- (b) shows the effect on flood levels in the foreshore and upstream, and on flows in the surplus course and downstream; and
- (c) checks the bund under Clause 7.14.
Commentary. This Manual allows tank cascades to be used as design storage subject to three basic conditions (surveyed FTL, a documented operating rule and maintained surplus weirs). Clause 7.7.1 adds the stage–storage survey and the custodian's concurrence, because the storage a tank actually offers depends on its silt level and on who controls the sluices. The 5-year survey interval is set by this Manual.
The FTL starting level follows Clause 3.12.5. A khazan drains only when the tide outside falls below the water inside: in a monsoon spell that coincides with spring tides its manos stay shut, and it fills from its own catchment. The State and district disaster management plans name exactly this coincidence of heavy rain and high tide as the cause of flooding in low-lying areas (GSDMP 2014; North Goa DDMP 2012-13). Rain over Goa from 10 to 23 July 2021 was 1,047 mm, against a normal of 471 mm (IMD, as reported). Tollems and khazans should be expected to be full, or their soils saturated, by the peak of the south-west monsoon. A tank cascade passes floods from one tank to the next, so a design that counts storage in one tank and ignores the surplus arriving from the tank above it will overstate the benefit. That is why Clause 7.7.2 requires the whole cascade to be modelled.
Figure 7.3 — Tollem, nallah, khazan and estuary in section: a village and urban catchment on the laterite slope with detention and treatment, a tollem with its plank outlet and setback, a spring at the foot of the slope, a nallah, a khazan field with its poiem, the outer (protective) bund with its mano (sluice gate), mangroves on the river side of the bund, and the tidal estuary that sets the tailwater; with the High Tide Line at the bund (S.O. 1422(E), 2020) and the CRZ line of the CZMP 2011. Original drawing for this Manual; concept from the khazan system as described in the Goa Agricultural Tenancy Act, 1964, the draft CZMP of Goa (NCSCM, 2021) and published accounts (Down To Earth, 2007; Sonak, 2014), with setback zones adapted from Kansas City Metro APWA, Section 5600 Version 2025.01 (MARC, 2025).
7.8 Operating rules and pre-monsoon flood cushion
7.8.1 Operating rule content. Every tank whose storage is counted under Clause 7.7 shall have a written operating rule, agreed by the custodian and kept with the O&M plan (Chapter 10). It shall state:
- (a) the levels and dates for filling, holding and drawdown through the year;
- (b) the sluice and regulator settings at each level;
- (c) who operates the sluices and regulators, and who may order a release;
- (d) the maximum release rate, set so that the release, added to the flow from the downstream catchment, does not cause flooding of buildings downstream;
- (e) the forecast and warning triggers (IMD district warnings, GSDMA alerts, and city forecast systems where available) and the actions taken at each trigger;
- (f) communication with downstream ULBs and residents before any release; and
- (g) the records to be kept: daily levels in the SW monsoon, releases, and gate settings.
7.8.2 Flood cushion. A tank may be operated with a flood cushion (a level below FTL during part of the SW monsoon), and the cushion counted under Clause 7.7.3, only where:
- (a) the tank has a gated sluice, regulator or other controllable outlet able to draw the tank down to the cushion level in the time stated in the rule;
- (b) the operating rule fixes the cushion level and the dates it applies;
- (c) continuous simulation (Clause 3.13) shows that the cushion is available at the start of a design storm in at least 90% of SW monsoon seasons in the record, allowing for the rain that usually comes before the peak storm;
- (d) the custodian accepts any loss of irrigation or water-supply yield, and any agreed compensation is recorded; and
- (e) the release needed to create or restore the cushion meets Clause 7.8.1(d).
7.8.3 No storage credit without control. Where a tank has no controllable outlet, no flood cushion shall be assumed, whatever the past practice.
7.8.4 Coordination. For tanks under WRD control, the operating rule shall be WRD's rule. This Manual does not authorise any other body to operate a WRD tank.
Commentary. No Goa operating rule for a tollem, khazan or urban lake that keeps a flood cushion was found, and no release protocol for the Selaulim, Anjunem or Tillari dams was found either. Khazan sluice gates are operated by tenants, their associations or a lessee, not by a public body (section 38 of the Goa Agricultural Tenancy Act, 1964). Their interests can run against flood storage: in the Corlim khazan case the Soil Conservation Division reported deliberate damage to rebuilt sluice gates to let in salt water for fish, and the High Court handed the gates to the tenants' association with a duty to prevent it (Dr Jainath Dhulapkar v State of Goa, WP 357/2022, 4 January 2023, as summarised). The Mala flood pumping station in Panaji uses Mala lake as a retention basin (as reported), but its operating rule was not seen. Without an agreed rule with dates, levels and a named operator, storage behind a gate cannot be relied on. Clause 7.8.2 turns that principle into a rule that can be checked, with a reliability test, because a cushion that is usually refilled by June and July rain gives no protection in a June–August monsoon spell. The 90% reliability in Clause 7.8.2(c) has no direct precedent and is set by this Manual.
Paddy, fish, salt and village water supply remain the primary purposes of most of these waterbodies. A flood cushion has a cost in yield or in the crop calendar, which is why Clause 7.8.2(d) requires the custodian, for a khazan the tenants' association, to accept it.
7.9 Restoration, desilting and deepening
7.9.1 Pre-works survey. Before any desilting or restoration, the proponent shall:
- (a) survey the waterspread, foreshore, bund, weirs and sluices (Clause 7.7.1(a) and (b));
- (b) find the original bed level by test pits or augering on a grid, and from historical records where available; and
- (c) where the tank receives urban runoff or sewage, test the silt for heavy metals and other contaminants before disposal is planned.
7.9.2 Desilting limit. Desilting shall remove accumulated sediment down to the original bed level. It shall not deepen the tank below the original bed, except under Clause 7.9.3.
7.9.3 Deepening. Deepening below the original bed is permitted only where a hydrogeological report shows that:
- (a) it will not cut through a clay or silt layer that holds water in the tank or protects an aquifer from polluted water;
- (b) in coastal areas, it will not draw saline water into the tank or the aquifer; and
- (c) the extra storage will be refilled and used, and will not stand stagnant below the sluice sill.
Storage created below the lowest sluice sill shall not be counted as flood storage.
7.9.4 Safe edges. Where the public has access to the waterbody edge:
- (a) side slopes shall be no steeper than 1V:4H from 0.5 m above FTL down to 1.2 m below FTL, or a level safety bench at least 3 m wide shall be provided between 0.3 m and 0.5 m below FTL; and
- (b) no isolated deep pit or vertical cut shall be left in the bed.
7.9.5 Storage not to be reduced. Restoration shall not reduce the storage below MWL. Islands, walkways, bund widening into the waterspread, ring roads, parking, buildings and "lake-front" platforms within the waterspread or foreshore shall be counted as lost storage and shall be offset under Clause 7.6.4.
7.9.6 Silt disposal. Desilted material shall not be placed within the setback, on the bund (except for approved bund strengthening), or on any flood path. Silt found to be contaminated shall be disposed of as the Goa State Pollution Control Board directs.
7.9.7 Inlet treatment. Every restoration of a tank that receives urban runoff shall include sediment and gross pollutant control at each inlet: a sediment forebay, a constructed wetland inlet zone, or a gross pollutant trap (Chapter 8), so that the restored storage does not silt up again.
7.9.8 Timing. Desilting shall be completed, and the waterbody made safe, by 15 May each year (Chapter 10).
Commentary. Desilting is Goa's main pre-monsoon drainage work, but no Goa rule fixes a date for it: the district disaster management authorities review preparedness in May and issue orders under section 33 of the Disaster Management Act, 2005, as in Margao in 2025, where PWD was directed to complete the cleaning of all drains and cross-drains (as reported), and in May 2025 the State released pre-monsoon funds to municipalities and Village Panchayats (as reported). In Panaji, Imagine Panaji Smart City reported removing over 70,000 m³ of debris and silt from the St Inez creek in 2024 (as reported). The 15 May deadline matches the pre-monsoon inspection date of Chapter 10. The limits on deepening are set by this Manual. Deepening tanks to "increase capacity" is common, but it can breach the silt and clay layer that holds water in the tank, it can let polluted urban water reach the aquifer, it can draw salt water toward the coast, and it creates storage below the sluice sill that never empties and gives no flood benefit. Deep pits with steep sides are also a drowning hazard. The slope and bench values in Clause 7.9.4 are adapted from common pond-safety practice; they have no Goa precedent.
7.10 Supply channels, surplus courses, inlets and outlets
7.10.1 Part of the major system. Supply channels and surplus courses are part of the major drainage system (Chapter 6). They shall be protected as waterbodies, with Zone 1 and Zone 2 setbacks under Clause 7.4.
7.10.2 No closure or covering. No supply channel or surplus course shall be closed, filled, diverted, covered, culverted along its length, or converted into a road or a closed drain, except under a design approved by the custodian that keeps or increases its 1% AEP capacity and its access for maintenance.
7.10.3 Crossings. Every road, rail, utility or access crossing of a waterbody, supply channel or surplus course shall:
- (a) pass the 1% AEP flow (with the climate factor), or the surplus of the upstream tank at its MWL, whichever is greater, with the freeboard required by Chapter 9;
- (b) not reduce the waterway width at the crossing below the full channel width as recorded in Revenue records or as surveyed, whichever is greater;
- (c) keep the channel bed level and grade; and
- (d) not raise the 1% AEP water level by more than the limit in Clause 7.6.2.
7.10.4 Capacity. The design capacity of a surplus course shall be the greater of the surplus weir discharge at MWL and the 1% AEP flow from its own catchment, combined as the cascade model (Clause 7.7.2) shows.
7.10.5 Protection at structures. Outlets of surplus weirs and sluices, and drain outfalls into waterbodies, shall have energy dissipation and scour protection designed under Chapter 9, so that the flow leaving them does not erode the bund, the bank or the channel bed.
7.10.6 Drain outfalls into waterbodies. A storm drain outfall into a tank, channel or wetland shall:
- (a) have its invert at or above the normal water level of the receiving waterbody, unless the drain is designed for submerged outfall under Chapter 5;
- (b) be located and aligned so that it does not cut through or weaken a tank bund;
- (c) have a gross pollutant trap and first-flush treatment (Chapter 8); and
- (d) not carry sewage or dry-weather flow (Chapter 8).
Commentary. This Manual protects supply channels and surplus courses as part of the major system. In urban areas they are often the first to be lost. Surplus courses are narrowed by culverts and compound walls, and supply channels are covered and turned into roads, which cuts the tank off from its source or leaves its surplus with nowhere to go. The St Inez creek, about 3.7 km long, carries the flow of most of Panaji's storm drains; a box conduit under D.B. Marg has raised its bed, and a sand bar and a walkway bridge at its mouth impede tidal flushing (as reported, 2026). In August 2026 a Panaji drain near the Police headquarters was found obstructed by sewerage chambers built into it (as reported). In 2021 the High Court restrained construction of a bypass over a water body at Chinchinim until the procedure for roads across water bodies had been followed (as reported). Clause 7.10.3(b) prevents a crossing from narrowing a channel to its current, encroached width.
7.11 Fee-in-lieu and regional tank storage
7.11.1 Where a basin plan has been notified, and the Authority has adopted alternative S-5 of the Policy Supplement (Clause 1.7), a development may pay a fee in lieu of on-site detention under Chapter 4. The fee shall be applied to restoring or creating storage in a tank, pond or regional facility in the same basin.
7.11.2 Tank storage funded by fee-in-lieu shall:
- (a) meet Clause 7.7.1 in full before it is counted;
- (b) be downstream of the contributing development and upstream of the flood-prone area it is meant to protect;
- (c) be created, or under construction, before the development it serves is occupied, or within a period the basin plan fixes; and
- (d) be recorded in the register of Clause 10.17 with the developments that funded it, so that the same volume is not sold twice.
7.11.3 Fee-in-lieu does not replace:
- (a) the retention requirement of Chapter 4, which is always met on site; or
- (b) the water quality requirement of Chapter 8, which is met on site or in a regional facility treating the same runoff before it reaches the tank.
Commentary. Chapter 4 provides for fee-in-lieu toward restored tollem or tank storage in master-planned basins. Malaysia's 2008 DID checklist allowed on-site detention only for small sites and required community ponds for larger areas (DID, 2008). Goa's tollems and khazans can serve the same purpose if their storage is restored and controlled. The TCP Act already defines a transferable development right "for posterity" for land such as water bodies, riverine land and khazan land (section 2(30B)), which could be one way to secure such storage, though it sets no technical standard for it. Clause 7.11.2(b) matters because a tank downstream of the flood-prone area protects nothing. Clause 7.11.3 keeps retention on site: it is the volume-control layer of this Manual, and a regional tank cannot recharge the aquifer under the developed site.
7.12 Wetlands, marshes and estuaries
7.12.1 Scope. This clause applies to marshes, swamps, backwaters, estuaries, and tidal creeks and lagoons, including:
- (a) wetlands notified under the Wetlands (Conservation and Management) Rules, 2017 or listed by the Goa State Wetland Authority (GSWA);
- (b) the Ramsar site Nanda Lake at Quepem, and the other wetlands notified by the GSWA, such as Carambolim, Batim, Sulabhat, Conem, Pali, Durga (Chinchinim), Cottombi, Xeldem, Toyyar, Dashi and Sarzora lakes;
- (c) the khazans, the estuaries and tidal creeks of the Tiracol, Chapora, Mandovi, Zuari, Sal and Talpona, the Cumbarjua canal, the mudflats, and the mangroves along them, including the Dr Salim Ali Bird Sanctuary at Chorao; and
- (d) any other marsh, estuary or creek that the Authority notifies.
7.12.2 No drainage of wetlands. No drain, channel, cut or pump shall be designed to drain a wetland, to lower its normal water level, or to reduce the period for which it is wet, except under a plan approved by the wetland authority.
7.12.3 Inflows. Every drain discharging into a wetland in Clause 7.12.1 shall:
- (a) meet Clause 7.10.6;
- (b) pass through water quality treatment for the WQv of its catchment (Chapter 8) before entering the wetland; and
- (c) where practicable, spread its flow across a vegetated margin rather than discharge at one point.
7.12.4 Hydraulic connectivity. Roads, embankments and utility corridors across or along a wetland shall have openings that:
- (a) pass the 1% AEP flow without raising the 1% AEP water level by more than the limit in Clause 7.6.2; and
- (b) keep the wetland's normal water exchange, including tidal exchange in estuaries, with openings spread along the crossing so that no part of the wetland is cut off.
7.12.5 Storage counted at basin scale only. Wetland storage shall be included in basin and regional models. It shall not be counted as detention for any individual development.
7.12.6 Tidal wetlands and estuaries. For estuaries and tidal wetlands:
- (a) tailwater shall be taken from Chapter 5 (Clause 2.12 joint cases);
- (b) works shall also comply with the Coastal Regulation Zone Notification in force; and
- (c) mouth-opening works, training walls and dredging are outside the scope of this Manual and need their own studies.
7.12.7 No dumping. No solid waste, construction debris or dredged material shall be placed in a wetland or its setback.
Commentary. Nanda Lake, Goa's only Ramsar site (no. 2471, designated in 2022), is notified by the GSWA as "Nanda Lake or Nanda tollem" with an area of 1,04,550 m² (about 10.5 ha), while its Ramsar record gives 42.01 ha; the difference has not been explained. The GSWA had identified 42 wetlands by November 2022, of which 8 were notified (GSWA report to the NGT); by June 2026, 25 had been notified, and 16 of them were reported to be under pressure, with "hydrological alteration" described as a major concern (as reported). The draft CZMP maps 135.55 km² of khazan and 41.12 km² of mangrove in Goa (NCSCM, 2021). The CRZ Notification, 2011 requires the khazans to be mapped and bars development in khazan land (paragraph 8.V.3). Clause 7.12.2 targets a specific risk: drains built to relieve flooding next to a marsh can drain the marsh itself, and once it is dry it is encroached. Every GSWA notification read prohibits the "discharge of untreated wastes … from industries, cities, towns, villages and other human settlements" into the wetland, so an outfall to a notified wetland needs the treatment of Clause 7.12.3. Sewage reaches Goa's creeks and rivers through storm drains: the High Court closed a public interest case in August 2025 with directions to stop sewage entering the Sal river from Margao's storm drains, and a case on sewage entering the Colva creek through drains ran from 2011 to 2025; raw sewage also enters the St Inez creek in Panaji (all as reported). The rules on outfalls and treatment in Clause 7.12.3 respond to these.
7.13 Encroachment interfaces
7.13.1 Boundary. For design under this Manual, the boundary of a waterbody is the larger of its Revenue record boundary and its surveyed FTL (or top of bank), as in Clause 7.3.3. Setbacks are measured from that boundary.
7.13.2 No reliance on encroached land. No design shall:
- (a) count, as storage or conveyance, land within a waterbody boundary that is occupied by encroachment, unless its removal is ordered and funded; or
- (b) treat the encroached width of a channel as its design width.
7.13.3 Public works in encroached reaches. Where a public drainage work passes through an encroached reach:
- (a) it shall be designed for the full waterbody width (Clause 7.13.1);
- (b) where the full width cannot be cleared before the work is built, the design report shall state the interim capacity and the flood risk until it is cleared; and
- (c) the work shall be built so that the full width can be restored later without rebuilding it.
7.13.4 Boundary marking. Every development adjoining a waterbody shall, before the completion certificate:
- (a) mark the outer edge of Zone 1 on the ground with permanent survey markers at intervals of not more than 30 m and at every change of direction; and
- (b) show the setback zones on the approved layout plan and in the sale documents of every plot that includes setback land.
7.13.5 Retaining walls. No retaining wall, bund or embankment shall be built along the edge of a waterbody, within Zone 1, to protect or reclaim land, except to protect existing public infrastructure under the custodian's approval.
Commentary. Goa's main legal controls on the loss of waterbodies are against filling. Under section 17A of the TCP Act, filling low-lying land without the Chief Town Planner's permission is an offence, with a fine of not less than Rs 10 lakh (section 17B), though a prosecution needs sanction under section 124 (as reported). A 2018 amendment to the Land Revenue Code (new section 33(3); enactment details not confirmed) lets the Collector restore filled low-lying land, khazan land or a water body without notice, at the offender's cost; the High Court has relied on orders under it in ordering the demolition of structures in low-lying paddy fields (2021), and in 2025 directed a resort to restore a lagoon at Siolim to its original size (as reported). No count of encroached waterbodies in Goa was found. This Manual cannot evict anyone. It can stop designs from treating encroachment as permanent (Clause 7.13.2), make public works restorable to full width (Clause 7.13.3), and make the setback visible on the ground and in property documents so that new buyers know it is there (Clause 7.13.4). The 30 m marker interval is set by this Manual.
7.14 Safety of tank bunds and embankments
7.14.1 Dam Safety Act screening. For every tank, and every embankment built or altered under this Manual, the designer shall determine whether it is a "specified dam" under the Dam Safety Act, 2021. Under the Act, a specified dam is a dam:
- (a) more than 15 m high, measured from the lowest point of the general foundation area to the top of the dam; or
- (b) between 10 m and 15 m high, where the crest length is not less than 500 m, or the reservoir capacity is not less than one million m³, or the maximum flood discharge dealt with by the dam is not less than 2,000 m³/s, or the dam has specially difficult foundation problems, or the dam is of unusual design.
Where it is a specified dam, the Act and the requirements of the State Dam Safety Organisation govern, in addition to this Manual.
7.14.2 Hazard class. Every tank bund and detention embankment that is not a specified dam shall be given a hazard class:
- High hazard: a breach could flood a habitable building, a school, a hospital, an arterial road or critical infrastructure.
- Low hazard: any other case.
7.14.3 High-hazard embankments. For high-hazard tank bunds and embankments:
- (a) the surplus weir or spillway shall pass the 1% AEP inflow at MWL with the freeboard of Clause 7.7.4(b), and shall be checked for the 0.2% AEP (500-yr) inflow without overtopping the bund (as for detention basins in Chapter 4);
- (b) a breach analysis shall map the area flooded by a breach at MWL;
- (c) an emergency action plan shall be prepared, with the warning and evacuation arrangements for the breach area; and
- (d) the design shall be certified and independently checked under Clause 10.6.
7.14.4 Inspection. Every tank whose storage is counted under Clause 7.7, and every high-hazard embankment, shall be inspected before the SW monsoon (by 15 May) and after every heavy-rainfall event (Chapter 10) for seepage, slips, cracks, animal burrows, trees on the bund, and blockage of the weir and sluices.
7.14.5 No unauthorised cutting. No person shall cut, lower or breach a tank bund or surplus weir during a flood except under the custodian's emergency procedure.
Commentary. The definition of a specified dam is quoted from the Dam Safety Act, 2021 (Act 41 of 2021). The Act defines a "dam" as an artificial barrier constructed across rivers or tributaries to impound or divert water. It excludes flood embankments, dikes and guide bunds. Tollem bunds and the outer bunds of khazans are low banks of earth and laterite, well under 10 m high, and will not be specified dams; Goa's irrigation reservoirs, such as Selaulim and Anjunem, and the Tillari dam in Maharashtra, are outside this Manual. Where the storage of a khazan is counted under Clause 7.7, its outer bund is a tank bund for Clause 7.14.2. Whether a tank bund that is not across a river or tributary is a "dam" under the Act is not clear from its text. Dam releases have flooded Goa villages: releases from the Tillari dam in Maharashtra flooded villages in Pernem, Bicholim and Bardez in August 2019 (as reported), and Paroda, on the Kushavati below Selaulim dam, flooded in each year from 2017 to 2021 (South Goa Disaster Management Plan, 2022). No release protocol for these dams was found. After a disaster the Soil Conservation Division of the Agriculture Department restores breached protective bunds of khazans at full cost and recovers the farmers' share (North Goa DDMP 2012-13). The hazard classes, the breach analysis and the emergency action plan for high-hazard tanks are set by this Manual. They extend the Chapter 4 requirement for detention basins (1% AEP spillway with outlet blocked, 0.2% AEP for high-hazard basins) to tanks that are counted as design storage.
7.15 Submittal requirements
Every drainage report for a development or work under Clause 7.1.2 shall include:
- the Waterbody Sheet (Form 7-1) under Clause 7.3.2, with the setback zones and their basis (mapped extent, hydraulic study or fixed width);
- the hydraulic study of the 1% AEP extent and floodway, where Clause 7.3.4 requires it;
- the Compensatory Storage Calculation (Form 7-3), by elevation band, where fill is proposed in the flood fringe;
- for any tank storage counted: the Tank Storage Credit Sheet (Form 7-2), with the survey, stage–storage curve, operating rule, cascade model results and custodian concurrence of Clause 7.7.1;
- for any crossing, outfall or work in Zone 1: the custodian's NOC and the hydraulic analysis of Clause 7.6.2 or 7.10.3;
- for restoration or desilting: the pre-works survey, silt tests and hydrogeological report of Clause 7.9; and
- for any embankment: the Dam Safety Act screening and hazard class of Clause 7.14.
7.16 Review and update
7.16.1 This chapter shall be reviewed with the rest of the Manual (Chapter 1). The fixed-width table of Clause 7.4.6 shall also be reviewed within 2 years of the Authority adopting 1% AEP flood maps for its area.
7.16.2 Where the Authority adopts new 1% AEP flood maps, they apply to new submittals 6 months after adoption, unless the Authority notifies otherwise.
References (chapter)
- Government of Goa. The Goa (Regulation of Land Development and Building Construction) Act, 2008 and the Goa Land Development and Building Construction Regulations, 2010, incorporating amendments up to September 2018 (Regulations 2(71), 2(88), 12.2, 12.5, 14.3.2, 19 and Annexure V; application form). TCP Department consolidation, copy at https://media.biltrax.com/wp-content/uploads/2019/08/DCR_Goa_2010.pdf
- Government of Goa. The Goa, Daman and Diu Town and Country Planning Act, 1974 (Act 21 of 1975), sections 2(30B), 17A and 17B. https://oss-data-in.vaquill.ai/legislation/IND_state_6813/act.pdf
- Town and Country Planning Department, Goa. Regional Plan for Goa 2021, Release One (§§3.6, 3.7, 3.21, 4.7, Appendix XI) and Release Three. https://web.archive.org/web/2024id_/https://tcp.goa.gov.in/wp-content/uploads/2017/Regional-Plan-report-1-2-3/RPG21RELEASE1final.pdf ; https://tcp.goa.gov.in/wp-content/uploads/2017/Regional-Plan-report-1-2-3/release%203_final_rpg2021.pdf
- Government of Goa. The Goa, Daman and Diu Irrigation Act, 1973 (Act 18 of 1973), sections 2(5), 2(6), 11 and 80. https://prsindia.org/files/bills_acts/acts_states/goa/1973/1973GOA18.pdf
- Government of Goa. The Goa Agricultural Tenancy Act, 1964, sections 2, 26(3), 35, 38 and 42-A, with Goa Act 33 of 2021. https://prsindia.org/files/bills_acts/acts_states/goa/1964/1964GOA7.pdf
- Government of Goa. The City of Panaji Corporation Act, 2002 (Goa Act 1 of 2003), sections 173 and 174. https://oss-data-in.vaquill.ai/legislation/IND_state_19803/act.pdf
- Government of Goa. The Goa Land Revenue Code (Amendment) Bill, 2018 (Bill No. 14 of 2018), new section 33(3). https://prsindia.org/files/bills_acts/bills_states/goa/2018/Bill%2014%20of%202018%20Goa.pdf
- Ministry of Environment and Forests (2011). Coastal Regulation Zone Notification, S.O. 19(E), 6 January 2011, with amendments (paragraphs 7, 8.III and 8.V.3), compilation filed in NGT Appeal 42/2022. https://www.greentribunal.gov.in/sites/default/files/news_updates/CRZ%20Notification%202011%20with%20amendment%20in%20Appeal%20No.42-2022%20(page%20nos.816-857).pdf ; Ministry of Environment, Forest and Climate Change (2019). CRZ Notification, G.S.R. 37(E), 18 January 2019 (paragraphs 2.3 and 6(i)). https://czmp.ncscm.res.in/2019-notification.pdf
- NCSCM (2021). Draft Report on Coastal Zone Management Plan of Goa as per CRZ Notification, 2011 (quoting S.O. 1422(E), 1 May 2020), filed as Annexure B in NGT OA 42/2023 (WZ). https://www.greentribunal.gov.in/sites/default/files/news_updates/Rejoinder%20of%20the%20Applicant%20in%20OA%20No.42-2023%20(page%20nos.529-754).pdf
- Goa State Wetland Authority. Fourteenth Quarterly Report in NGT OA 141/2017, with the notifications of Carambolim, Nanda and other lakes. https://www.greentribunal.gov.in/sites/default/files/news_updates/Fourteenth%20Quarterly%20Report%20by%20GSWA%20in%20OA%20No.141-2017%20(page%20nos.1819-1927).pdf ; GSWA report to the NGT, 3 November 2022 (summary). https://indiaenvironmentportal.org.in/in-court/goa-state-wetland-authority-report-to-the-ngt-on-wetlands-03112022
- Government of India. The Dam Safety Act, 2021 (Act 41 of 2021). https://www.casemine.com/act/in/626f9167714d58ef62b50d09 ; CWC, Specified Dam. https://rrssd.cwc.gov.in/specified-dam
- MoHUA (2015). Urban and Regional Development Plans Formulation and Implementation (URDPFI) Guidelines, Vol I. https://web.archive.org/web/2022/https://mohua.gov.in/upload/uploadfiles/files/URDPFI%20Guidelines%20Vol%20I(2).pdf
- Mid-America Regional Council (2025). APWA Stormwater Standards Supplement (Section 5600, Version 2025.01). https://www.marc.org/document/apwa-stormwater-standards-supplement
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (§5605.3 stream buffers). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Department of Irrigation and Drainage Malaysia (2008). Submission Checklist for Stormwater Management. https://www.water.gov.my/jps/resources/auto%20download%20images/5844dfbba8fc1.pdf
- Goa Institute of Management for GSDMA (2014). State Disaster Management Plan, Part I. https://thebastion.co.in/sites/default/files/State%20Disaster%20Management%20Plan%20(Part%20I%20of%20VI).pdf ; District Disaster Management Plan, North Goa, 2012-13. https://www.sdma.goa.gov.in/sites/default/files/2022-07/District%20Disaster%20Management%20Plan%20(North)_0.pdf ; Disaster Management Plan, South Goa, 2022, Part I. https://sdma.goa.gov.in/sites/default/files/2022-07/Disaster%20Management%20Plan%20South%20Goa%202022%20Part%20I.pdf
- Ramsar Convention. Ramsar Information Sheet, Nanda Lake (site no. 2471). https://rsis.ramsar.org/ris/2471
- High Court of Bombay at Goa. Dr Jainath Dhulapkar v State of Goa, WP 357/2022, 4 January 2023 (summary). https://lawtext.in/judgement.php?bid=46308
- Reports of High Court orders and planning cases (secondary): LiveLaw (May 2026), https://www.livelaw.in/amp/articles/bombay-high-court-goa-addresses-challenges-goa-planning-regime-535734 ; The Goan (22 Sep 2021, Chinchinim), https://www.thegoan.net/goa-news/court-halts-bypass-work-in-chinchinim-water-body/74698.html ; The Goan (14 Aug 2025, Salpem lake), https://www.thegoan.net/goa-news/salpem-lake-pollution-hc-closes-pil-with-strong-court-directives/134803.html ; The Goan (9 Aug 2025, Colva creek), https://www.thegoan.net/goa-news/finally-14year-battle-on-colva-creek-sewage-ends/134519.html ; Navhind Times (24 Sep 2025, Siolim lagoon), https://www.navhindtimes.in/2025/09/24/goanews/hc-directs-resort-to-restore-siolim-lagoon-to-original-size/
- Reports of Panaji drainage (secondary): The Goan (7 Apr 2024; 15 Feb 2026; 3 Aug 2026), https://www.thegoan.net/goa-news/%EF%BB%BFpanel-set-up-to-map-panajis-storm-water-drain-network/111972.html ; https://www.thegoan.net/goa-news/creek-vs-city-fathers-accountability-in-focus-at-ccp-polls/143532.html ; https://www.thegoan.net/goa-news/mayor-apologises-as-ccp-probes-drain-blockage-behind-panaji-flooding/152130.html ; Gomantak Times (22 Jun 2023, Mala pumping station), https://www.gomantaktimes.com/news/goa/will-smart-city-panjim-flood-or-will-not-this-monsoon
- Reports of CZMP and wetland status (secondary): The Goan (16 Mar 2025; 14 Jun 2026; 18 Jun 2026), https://thegoan.net/goa-news/centre-rejects-goa’s-revised-coastal-plan/127501.html ; https://www.thegoan.net/goa-news/nczma-turns-heat-on-goa-over-stalled-coastal-plan/149659.html ; https://www.thegoan.net/goa-news/alarm-over-goa’s-notified-wetlands/149785.html
- Reports of dam releases and pre-monsoon orders (secondary): The Goan (2025), https://www.thegoan.net/goa-news/flood-warning-prompts-urgent-drain-cleaning-orders-from-dma-in-margao/130712.html ; https://www.thegoan.net/goa-news/govt-releases-funds-for-local-bodies-to-carry-out-premonsoon-works/130569.html
- Government of Goa. State Action Plan on Climate Change 2.0, 2020–2030 (sent to MoEFCC on 13 April 2022) (khazan area). https://napccindia.moef.gov.in/resources/pdfs/goa-sapcc-2.0.pdf
- Bose, I. (2007). Goa's disappearing khazan farms dying a slow death. Down To Earth, 15 June 2007. https://www.downtoearth.org.in/environment/goas-disappearing--khazan--farms-dying-a-slow-death-6110 ; Jacob, G. J. Khazans of Goa: a socio-cultural perspective. Sahapedia. http://www.sahapedia.org/khazans-goa-socio-cultural-perspective ; Sonak, S. (2014). Khazan Ecosystems of Goa. Springer, ISBN 978-94-007-7202-1.
- Government of India. Wetlands (Conservation and Management) Rules, 2017; Coastal Regulation Zone Notification, 2019.
Annexes and forms
| Annex / Form | Content |
|---|---|
| 7A | Statewide waterbody GIS layer and inventory fields |
| 7B | Fixed-width setback table (alternative S-3, with Annex 1C) |
| 7C | Template tank operating rule, with flood cushion |
| 7D | Desilting and restoration specification |
| 7E | Glossary of Konkani waterbody terms and regional variants |
| Form 7-1 | Waterbody Sheet |
| Form 7-2 | Tank Storage Credit Sheet |
| Form 7-3 | Compensatory Storage Calculation (by elevation band) |
Commentary. No audit or official study of the loss of Goa's waterbodies to development was found during research for this Manual, and no CAG audit of Goa's drainage, flood control or khazans was found. The record that exists is in plans and court orders. The Regional Plan for Goa 2021 places all rivers, tanks, nallahs, creeks and reservoirs, and all paddy fields and khazans, in its no-development eco-sensitive zone (ECO-1), but maps water bodies only at taluka scale and states that "dry nallas (Seasonal) and small ponds may not be reflected" (RPG-21, Release One, §3.6). Reviewing the zone changes made under the TCP Act, the High Court found that "almost all the conversions are from paddy fields, natural cover, no development zone and orchard to settlement zones" (Goa Foundation v State of Goa, PIL WP 16/2023, 13 March 2025, as reported). The State and district disaster management plans name the mechanism of flooding as heavy rain coinciding with high tide, which congests drainage in low-lying areas (GSDMP 2014; North Goa DDMP 2012-13). The khazans that store that water behind their bunds cover about 135.55 km² on the maps of the draft CZMP (WRD data), against about 18,500 ha in the State Action Plan on Climate Change; the figures have not been reconciled. This chapter gives the design rules that protect that storage. It does not replace the TCP, Revenue, WRD, coastal and wetland procedures that record and protect waterbodies in law.