11.1 Purpose and scope

11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.

11.1.2 A BSMP shall:

  • (a) map flood hazard for the basin under existing and future conditions;
  • (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
  • (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
  • (d) reserve land for regional storage, talav and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
  • (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
  • (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).

11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.

Commentary. Surat is the only Gujarat city found with a city-wide storm water plan. SMC's Storm Water Drainage Action Plan 2019 records about 986 km of drains, covering about 70% of the city's road length, with 42 gated outfalls to the Tapi, but it is a coverage plan without a stated design storm (SMC 2019). After the khadi floods of July 2026 the State announced ₹500 crore for the khadis, and SMC had about 188 km of creeks surveyed for a hydrology model and new danger levels (press reports). In Ahmedabad no city-wide plan was found. AMC prepared a zone master plan for Ambli, Bopal, Ghuma and Shela in August 2026 after the July floods (press report), and AUDA is building 166 km of drains in six peri-urban towns under an ADB loan, designed in Sanand for a 1-year storm (ADB 2023). In Vadodara the Navalawala Committee was reported to recommend river desilting and an additional Ajwa spillway after the 2024 flood (press reports). No storm water master plan or stated design return period was found, in the sources reviewed for this Manual, for Vadodara, Rajkot, Bhavnagar, Jamnagar, Junagadh, Gandhinagar or Bhuj. A site-level manual cannot fix basin-level problems: lost tank storage, outfalls locked by high tide or gated shut against a river in flood, river reaches raised by dam releases, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:

  • Denver's Mile High Flood District prepares major drainageway master plans that set regional facilities and release rates.
  • The Kansas City APWA criteria rest on regional watershed studies (MARC).
  • England's Surface Water Management Plans (Defra, Surface Water Management Plan Technical Guidance, 2010) set a phased method of preparation, risk assessment, options and implementation.
  • Malaysia's MSMA requires drainage master plans for urban areas.

This chapter adapts that method to Gujarat's tide-locked outfalls and tidal creeks (khadis) in Surat and on the Gulfs of Khambhat and Kachchh, the dam-regulated rivers through its cities (the Tapi below Ukai, the Vishwamitri below Ajwa and Pratappura, the Sabarmati below Dharoi), the talavs and kaans that once carried and stored Ahmedabad's and Vadodara's storm water, the bandharas and tidal regulators of the Saurashtra and Kachchh coast, and a short SW monsoon with damaging cyclone storms in May and in October and November.


11.2 Definitions

Term Meaning in this Manual
Basin The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3.
Basin Stormwater Master Plan (BSMP) The plan for one basin prepared under this chapter.
Lead Authority The body responsible for preparing a BSMP (Clause 11.4).
Level of service (LoS) The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6).
Flood hazard map A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario.
Regional facility A storage, conveyance or outfall work serving more than one development, identified in a BSMP.
Capital Improvement Programme (CIP) The ranked, costed list of works in a BSMP (Clause 11.8.4).

11.3 Planning unit: the basin, not the ward

11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.

11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.

11.3.3 For the main urban areas, and for the river reaches that flood every few years, the basins are at least the following:

  • Surat: the Tapi through the city, tidal below the Singanpore weir-cum-causeway, with its level set by the tide and by releases from Ukai dam, with the catchments of the 42 gated storm drain outfalls in five zones as sub-basins; and the khadis (tidal creeks), including the Mithi, Kankra, Varachha, Chhaprabhatha, Bhedwad and Koyali khadis and the other creeks of the 188 km surveyed in 2026, each with its whole catchment, including any part outside the corporation;
  • Vadodara: the Vishwamitri through the city, with releases from Ajwa and Pratappura reservoirs as a boundary condition, and the kaans (natural storm channels) that drain to it, including the Bhukhi kaas from Chhani talav;
  • Ahmedabad: the Sabarmati through the city, including the riverfront reach, with releases from Dharoi dam as a boundary condition; the chains of talavs linked under the lake-interlinking programme; and the western peri-urban catchments (Ambli, Bopal, Ghuma, Shela and Sanand) that drain through Bopal and Bhadreti lakes to the Gota–Godhavi canal; and
  • Rajkot: the Aji through the city, with releases from Aji dam as a boundary condition to be checked.

Other Tier A bodies, including Bhavnagar, Jamnagar, Junagadh, Gandhinagar and Bhuj, shall define their basins in the first BSMP that covers them. Where WRD or the Competent Authority has a design flood, a high flood level or an operating rule for a river, dam, bandhara or tidal regulator that a town lies on, the BSMP shall take its river boundary conditions from it, and shall show those levels against its own 1% AEP map.

Basin Stormwater Master Plan (BSMP) — process and links to site design 1. Basin set-up Delineate by basin, not ward (Cl. 11.3) Lead Authority + partners 2. Data DEM, drains, tanks, tides, flood marks (Cl. 11.5) 3. Model 1D–2D, 24–72 h storms, tide, continuous sim. calibrate to past floods 4. Gap vs LoS Scenarios: existing, future ± site controls, climate (Cl. 11.6–11.7) 5. Options Restore tanks first, then regional storage, conveyance, outfalls 6. Outputs (Cl. 11.8.4) — approved by State Stormwater Technical Committee • Flood hazard maps 10% / 1% / 0.2% AEP • Flood-sensitive catchments, basin release rates • Regional facility sites and fee-in-lieu rate • Capital Improvement Programme, ranked • Pre-monsoon maintenance programme • Monitoring network • Open data + public map viewer • Annual report, pre-monsoon Land-use plan Statutory master plan: reserve storage sites, flow paths, hazard zoning (Cl. 11.9) Site design Ch 4 release rates, regional detention and fee-in-lieu (Cl. 4.13, 4.5.6) Floors and setbacks 1% AEP future-with-plan map sets floor levels (Ch 6) and setbacks (Ch 7) Public works CIP funds: ULB, State, Union; O&M and desilting (Ch 10) Review every 10 yr, after a >1% AEP event, or plan revision (Cl. 11.11)

Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.

Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. Responsibility in Gujarat is divided by body as well as by boundary. Drains vest in the Municipal Corporations under the Gujarat Provincial Municipal Corporations Act 1949 and are an obligatory duty (sections 63(4) and 153). Outside the corporations, the urban development authorities make the development plans and town planning schemes and, like AUDA in Sanand, build drains. WRD (the Narmada, Water Resources, Water Supply and Kalpsar Department) runs the dams, canals and flood embankments, and may notify natural drainage courses under the Irrigation and Drainage Act 2013. The Surat khadis show why the basin has to be the unit. They collect rain across many wards, and they end in the tidal Tapi, where SMC's sluice regulators close them against a river in flood. Backflow from the Kankra khadi into the Mithi khadi was described in a civil-society study of 2025 (as reported). In Vadodara the Vishwamitri receives releases from Ajwa and Pratappura, and the Vishwamitri Committee found that the Delhi–Mumbai Expressway at Sadad aggravated the 2024 waterlogging (press report). This clause makes the basin the planning unit. It also requires the Gota–Godhavi canal to be treated as a link, because it already receives storm water from Bopal and Bhadreti lakes in Ahmedabad's western suburbs.


11.4 Who prepares, and when

11.4.1 Lead Authority.

  • For a basin wholly within one Municipal Corporation: the Corporation (for example AMC, SMC, VMC or RMC).
  • For a basin that extends beyond a Municipal Corporation into the area of its urban development authority: the Corporation, with the authority as partner (AMC with AUDA, SMC with SUDA, VMC with VUDA, RMC with RUDA).
  • For a basin wholly within an urban development authority's area outside the corporation: the authority, with the municipalities and gram panchayats as partners (for example AUDA for the Sanand and other peri-urban schemes).
  • For the Sabarmati riverfront reach in Ahmedabad: AMC, with SRFDCL and WRD as partners.
  • For basins that drain to a river reach whose level is set by dam releases (for example the Tapi below Ukai at Surat, the Vishwamitri below Ajwa and Pratappura at Vadodara, the Sabarmati below Dharoi at Ahmedabad and the Aji at Rajkot), or that include a drainage course notified under section 11 of the Irrigation and Drainage Act 2013: WRD for the river, the dams and the notified course, with the Corporation as Lead Authority for the urban basin and WRD as partner.
  • For other basins that cross local-body boundaries: the Municipal Corporation or municipality with the largest share of the basin, with the development authority for the area and the other local bodies as partners.
  • In Tier B bodies: the Lead Authority is named by UDD. Basins draining to a common river reach or creek may be grouped into one district-level plan.

GCZMA shall be consulted on every BSMP that proposes works in the Coastal Regulation Zone, and every BSMP that proposes a discharge to a WRD canal shall record WRD's consent to it.

WRD shall be a partner in every BSMP that includes a river, canal or tank under its control.

11.4.2 When a BSMP is required.

  • (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
  • (b) A BSMP is required before:
    • any regional detention or fee-in-lieu is accepted under Clause 4.13;
    • a fee held under Clause 4.5.6.3 is spent; and
    • a basin-specific release rate is applied under Clause 11.8.3.
  • (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.

11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.


11.5 Data and surveys

11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:

Table 11.1 — Minimum data and surveys for a BSMP

Data Minimum requirement
Terrain Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum
Drain network Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm
Waterbodies Survey of every tank, talav, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment
Rivers and canals Cross-sections at no more than 200 m spacing and at every structure
Outfalls and coast Tidal datums and surge values (Annex 5A), with the datum of every level named (chart datum, GTS/MSL or a local port datum); outfall invert levels against high tide and against river flood levels; gates, sluice regulators, pumping stations, bandharas and tidal regulators, with their operating rules; the high flood levels fixed by the Competent Authority; dam releases upstream
Rainfall and levels All available rain gauges (IMD, including the Ahmedabad, Surat, Vadodara, Rajkot and Bhuj stations; the taluka rain gauges reported daily by the State Emergency Operation Centre; the gauges of WRD's State Water Data Centre and its flood control units; and municipal ward gauges such as AMC's) and water-level records, including those for the August 2006 (Surat), July 2019 and August 2024 (Vadodara), September 2021 (Rajkot), July 2023 (Junagadh) and July 2026 (Ahmedabad and Surat) events
Flood evidence Surveyed flood marks and mapped flood extents from past events, including public reports
Land use Existing land use and imperviousness; future land use from the statutory master plan
Soils and groundwater HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones
Sewer interaction Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots

Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the flat alluvial plains of Ahmedabad and central Gujarat, along Surat's khadis and on the low coasts of the Gulfs of Khambhat and Kachchh a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The August 2006 (Surat), July 2019 and August 2024 (Vadodara), September 2021 (Rajkot), July 2023 (Junagadh) and July 2026 (Ahmedabad and Surat) events are the best calibration data Gujarat has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.


11.6 Levels of service

11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.

Table 11.2 — Minimum levels of service

Element Minimum level of service
Minor system The design AEP of Chapter 6 (Table 6.1)
Habitable buildings No flooding above floor level in the 1% AEP (100-yr) event
Critical facilities (hospitals, emergency services, substations, water and sewage plants) No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event
Evacuation routes and arterial roads Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event
Ponding drain time Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event
Tank and talav storage No net loss of flood storage below the MWL in the basin, measured against the earliest available survey
Outfalls Functioning under the joint and outfall-closed cases of Chapter 5

Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that nobody has measured. In Shailesh R. Shah v. State of Gujarat (2002) the High Court directed that every lake and pond in the State be notified in the Gazette and never put to another use, and that no-construction peripheries be fixed lake by lake. Whether that notification was ever issued was not found, and in 2024 the Court ordered every District Collector to survey the water bodies (order of 1 August 2024). The Sujalam Sufalam Jal Abhiyan has claimed large additions to storage since 2018 by deepening talavs and desilting check dams, but these figures are the State's own and have not been audited (press reports).


11.7 Modelling and scenarios

11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:

  • the minor system;
  • the major (overland) system;
  • rivers, canals and tanks; and
  • the outfalls.

Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.

11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.

11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.

11.7.4 Scenarios. Each BSMP shall model at least:

  • (a) Existing: existing land use, network, tanks and outfalls;
  • (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
  • (c) Future, controlled: future land use with the site controls of Chapter 4;
  • (d) Future, with plan: scenario (c) plus the works of the CIP; and
  • (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8 and the sea-level allowance of Chapter 5.

11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the August 2006 (Surat), July 2019 and August 2024 (Vadodara), September 2021 (Rajkot), July 2023 (Junagadh) and July 2026 (Ahmedabad and Surat) events where data exist.

Figure 11.2 — BSMP model schematic Schematic plan of a basin model: design rainfall over sub-catchments; two tanks in cascade with surplus course; a 1D drain network linked to a 2D surface grid; a river or canal reach with an inter-basin link; an outfall with a flap gate and pumps; and a tidal or river level boundary. Numbered notes on the right explain each element. BSMP model: elements required by Clause 11.7 (schematic, not to scale) Sea / receiving water 1 S1 S2 S3 2 Upper tank Lower tank start level start level 3 2D surface 5 4 River / canal (1D) 6 Inter-basin link Gate Pumps 7 8 1 Design rainfall Ch. 2 storms incl. 24, 48, 72 h; 50%, 10%, 1%, 0.2% AEP; areal reduction (Cl. 2.7.3, 11.7.2) 2 Sub-catchments Runoff by Ch. 3 methods; land use for each scenario (a)–(e) of Cl. 11.7.4 3 Tanks and ponds Surveyed FTL, MWL, stage–storage, sluices, surplus weirs (Cl. 11.5.1); start level from continuous run (Cl. 3.13.5, 11.7.3) 4 1D drain network Minor system: drains, pipes, culverts with surveyed inverts and silt (Cl. 11.5.1) 5 2D surface Major (overland) system on the DEM, 0.15 m RMSE or better; exchange with 1D at inlets and manholes 6 Rivers and canals (1D) Sections ≤ 200 m apart and at every structure; diversions between basins mapped (Cl. 11.3.2) 7 Outfall Flap or tide gates and pumps; joint and outfall-closed cases of Ch. 5 8 Downstream boundary Tide (MHWS; HAT + surge + sea-level allowance) or river level, per Ch. 5 Calibrate and validate with at least two major past flood events where data exist (Cl. 11.7.5).

Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and talavs with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.

Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).


11.8 Options, outputs and the Capital Improvement Programme

11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:

  1. Protect and restore storage: talavs, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
  2. Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
  3. Conveyance upgrades to drains, canals and culverts;
  4. Outfall works: gates, sluice regulators on tidal creeks, pumping stations and the storage behind them;
  5. Property-level protection where works cannot reach the level of service; and
  6. Non-structural measures: flood warning (for example the Surat early-warning system for Ukai releases and khadi floods, IMD district rainfall warnings read with the predicted high tides, and advance notice of releases from the dams upstream of Surat, Vadodara and Ahmedabad), flood-hazard zoning, emergency planning and public information.

11.8.2 Option assessment. Each option shall be assessed for:

  • reduction in flood risk (buildings and people flooded; expected annual damage);
  • capital and 30-year maintenance cost;
  • land required;
  • effect on groundwater recharge and saline intrusion (Chapter 8);
  • effect on downstream basins and the Gota–Godhavi canal; and
  • who benefits.

11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.

11.8.4 Outputs. Each BSMP shall produce:

  • (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
  • (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
  • (c) regional facility sites, with storage volumes, land needs and the sites they serve;
  • (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
  • (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
  • (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
  • (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.

Commentary. Restoring storage comes first because Gujarat's storage is being lost while its conveyance is being enlarged. Ahmedabad was reported to have about 630 lakes within its limits in 1999, against 122 under AMC in 2020 (press report). The lake-interlinking programme begun in 2003 connected 41 lakes to storm drains and the Narmada canal by 2011 (secondary sources). In 2024 the High Court found ponds and lakes being filled across the State and said this "may also be prime reason for water clogging" (order of 1 August 2024). In Vadodara the Vishwamitri Committee reported waterways and ravines "filled or encroached upon" (press report), and in Surat a 2025 study criticised walls and roads built on the floodplains of the khadis (as reported). The Vadodara storm of 31 July 2019, about 424 mm in six hours (press reports), is far beyond what any drain network is designed to carry, so storage and flow paths have to take what conveyance cannot. Conveyance upgrades on their own move water faster to an outfall that may be tide-locked or gated shut against a river in flood. Groundwater differs sharply across Gujarat. In the alluvium of north and central Gujarat the water table is generally deep, and the CGDCR requires percolating wells for recharge on building units of 500 m² or more (Regulation 17.2.2). In Saurashtra the black soils are mostly shallow over basalt, so recharge is limited and infiltration close to foundations can raise a perched water table. Along the Saurashtra and Kachchh coast, salinity ingress had affected 779 villages by 1976, and the High Level Committee works against it were 41% complete in March 2010 (CAG 2010). Recharge and deeper drains near the coast can draw saline water inland, which is why groundwater and saline intrusion are assessment criteria. The CGWB year book for Gujarat could not be obtained for this Manual. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.


11.9 Integration with land-use planning

11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the Development Plans and Town Planning Schemes made under the Gujarat Town Planning and Urban Development Act 1976, including those of the urban development authorities, and, for the Sabarmati riverfront, the SRFDCL master plan. In particular:

  • (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
  • (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
  • (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
  • (d) the common plot of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.

11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.

Commentary. Gujarat has no flood-line system of the kind that ties land use to mapped flood levels. CGDCR 2017 takes the ground level of a building unit as the highest of the road crown, the existing ground and the high flood level, and leaves the high flood level to be "decided by Competent Authority" without a return period (Regulation 2.55). The plinth must be 0.45 m above that level (Regulation 13.1.5). Flood-prone land is identified from the CWC Flood Atlas and the Vulnerability Atlas of India (CGDCR Part II), and the development plans use local zones such as the "Restricted Agriculture Zone (High Flood Zone)" and VUDA's restricted zones RZ1 to RZ4, of which RZ3 allows no development. The statutory setbacks are 30 m from the bank of a river without an embankment, 15 m from a river embankment, and 9 m from a talav, canal or nala (Regulation 17.1). The National Green Tribunal directed in 2021 that the whole Vishwamitri floodplain be demarcated (press report), and in Ahmedabad the Sabarmati Riverfront narrowed the river to about 263–275 m, with its flood capacity disputed (press reports). A BSMP gives the Development Plans the 1% AEP drainage-flood map that they need. Using common plot land as storage or flow path has no direct precedent; this Manual adopts it because CGDCR 2017 already requires at least half of the open space of a building unit, including its common plot, to be left permeable for rain water percolation (Regulation 13.1.3), and lets a building unit of more than 4,000 m² provide a water retention pond of at least 300,000 litres (Regulation 17.2.2); because that land then serves as open space, storage placed in it must stay usable as one. Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.


11.10 Consultation and publication

11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.

11.10.2 After approval, the following shall be published as open data:

  • the model files;
  • the flood hazard maps;
  • the data of Clause 11.5.1, except security-sensitive asset details; and
  • the CIP.

They shall also be shown on a public map viewer.

Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.


11.11 Approval, review and reporting

11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.

11.11.2 Review. Each BSMP shall be reviewed:

  • every 10 years;
  • within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
  • when the statutory land-use plan is revised.

11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each SW monsoon (by 31 May). The report shall show:

  • CIP progress;
  • the fee-in-lieu ledger (Clause 4.13.4);
  • maintenance completed; and
  • any flooding against the levels of service.

11.12 Interim arrangements

11.12.1 Until a BSMP is approved for a basin:

  • (a) all site criteria of Chapters 4 to 8 apply in full;
  • (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
  • (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
  • (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.

References (chapter)

Annexes and forms

Annex / Form Content
11A BSMP terms of reference template
11B Basin lists and boundaries for Tier A bodies
11C Depth–damage curves for Gujarat building types
11D BSMP data and model publication standard
Form 11-1 Annual implementation report