Draft v1.0 prepared by NEER. Not adopted by the Government of Gujarat or the Administration of Dadra and Nagar Haveli and Daman and Diu, and has no legal force. About this draft

Chapter 7Waterbodies, Tanks (Talavs) and Setbacks


7.1 Purpose and scope

7.1.1 This chapter treats waterbodies as part of the drainage system. It sets the rules for:

  • (a) identifying and mapping every waterbody that a development or public work affects;
  • (b) the setback zones around waterbodies, and the uses allowed in each zone;
  • (c) fill in flood-prone land, and the compensatory storage needed where fill is allowed;
  • (d) counting tank (talav) storage, including tank cascades, as design storage;
  • (e) restoring and desilting tanks and ponds;
  • (f) protecting supply channels, surplus courses, inlets and outlets;
  • (g) wetlands, marshes and estuaries, including Nalsarovar and Thol Lake, the khadis of Surat, the creeks, mudflats and mangroves of the Gulfs of Kachchh and Khambhat, and the urban talavs of Ahmedabad and Vadodara;
  • (h) the interface with encroachment and its removal;
  • (i) fee-in-lieu contributions to regional tank storage (with Chapter 4); and
  • (j) the safety of tank bunds and other embankments.

7.1.2 This chapter applies to every development and public work to which this Manual applies under Chapter 1 and that:

  • (a) adjoins a waterbody or lies wholly or partly within its setback (Clause 7.4);
  • (b) discharges to a waterbody, directly or through a drain, within the downstream analysis extent of Chapter 5; or
  • (c) alters a waterbody, its bund, sluice, surplus weir, supply channel or surplus course.

7.1.3 Where a statute or statutory rule sets a wider setback or a stricter restriction, the statute governs (Clause 1.3.3). Nothing in this chapter authorises any work that the Gujarat Town Planning and Urban Development Act, 1976 and the CGDCR 2017 made under it, the Gujarat Irrigation and Drainage Act, 2013, the directions of the Gujarat High Court on water bodies in Shailesh R. Shah v. State of Gujarat (2002), the Coastal Regulation Zone Notification, 2019 as applied through the approved CZMPs, the Wetlands (Conservation and Management) Rules, 2017, or any other law, prohibits.

Commentary. No statewide Act for the protection of tanks or lakes was found in Gujarat during research for this Manual. Waterbodies are protected instead by the building code, an irrigation statute and the High Court. CGDCR 2017 bars development on land designated as a water body, pond or talav in the Development Plan, defines a talav to include plots so designated "under the revised development plan or any other legitimate records" (Regulation 2.118), and keeps buildings 9 m from a talav, canal or nala and development 30 m from the bank of an unembanked river (Regulation 17.1). The Gujarat Irrigation and Drainage Act, 2013 lets the State notify a river, stream or natural drainage course and prohibit obstructions in it (section 11), but no such notification for an urban stream was found. In Shailesh R. Shah v. State of Gujarat, 2002 (3) GLH 642, the High Court directed that every lake and pond in the State be notified in the Gazette, never alienated or put to any other use, recharged "by appropriate storm water drains", and cleared of encroachment, and that a no-construction periphery be fixed and notified for each (paragraph 24, as quoted by the High Court in 2024). On 1 August 2024 the Court found "indiscriminate land filling of the ponds/lakes/water bodies", which "may also be prime reason for water clogging", and directed every District Collector to survey the water bodies of the district. Whether the Gazette notification of 2002 was ever issued, and what the Collectors' surveys found, were not established. Counts of Ahmedabad's lakes disagree: about 630 within the civic limits in 1999 against 122 under AMC in 2020 (as reported, on different bases). On the coast, the CAG found that the Coastal Zone Management Plans had not been updated under the CRZ Notification, 2019 by August 2022 (CAG, Report No. 3 of 2022). No audit of the loss of talavs, nalas or khadis in any Gujarat city was found. This chapter gives the design rules that protect waterbody storage and conveyance. It does not replace the town planning, Revenue, irrigation, coastal and wetland procedures that record and protect waterbodies in law, or the High Court's directions.


7.2 Definitions

Term Meaning in this Manual
Waterbody A river, stream or nala (vokla, kaans), canal, lake, tank or pond (talav, sarovar), reservoir, check dam or bandhara pond, tidal river or creek (khadi), salt pan, marsh, mudflat or mangrove, supply channel or surplus course, perennial or seasonal (as in Chapter 1).
Tank (talav) A waterbody impounded by an earthen bund, fed by its own catchment and/or a supply channel, with a surplus weir and one or more sluices.
Tank cascade A chain of tanks in which the surplus or sluice outflow of one tank feeds the next (as in Chapter 3).
Full tank level (FTL) The crest level of the surplus weir (overflow, waste weir or spillway) of a tank, or the permanent crest of its regulating structure. The tank holds water up to FTL without spilling.
Maximum water level (MWL) The highest water level in a tank when the surplus weir passes the tank's design flood. For this Manual, it is the greater of the level recorded by the WRD and the level computed for the 1% AEP (100-yr) inflow with the climate factor of Clause 2.8 (Clause 7.7.4).
Top bund level (TBL) The crest level of the tank bund.
Waterspread The area of a tank submerged at FTL.
Foreshore The land around a tank between the FTL contour and the MWL contour. Foreshore land is flooded whenever the tank surpluses, and is part of the tank's flood storage.
Supply channel (feeder channel, canal or nala) A channel that brings water from a river, anicut or upstream tank into a tank.
Surplus course The channel that carries the overflow of a surplus weir to the next tank, a river, a drain or the sea.
Sluice (sluice gate or outlet) A controlled outlet through a tank bund, usually to an irrigation channel.
Top of bank For a channel, the break in slope at the edge of the channel. Where it cannot be identified, the edge of the water surface at the 50% AEP (2-yr) flow.
1% AEP flood extent The land flooded by the 1% AEP (100-yr) flood with the climate factor of Clause 2.8, from a hydraulic model that meets Chapter 3 and Chapter 5, or from a map adopted by the Authority under Clause 7.3.4.
Floodway The waterbody and the adjoining land that must be kept free of obstruction to pass the 1% AEP flood without raising the 1% AEP water level by more than 0.1 m at any point (Clause 7.6.1). For a tank, all land below MWL.
Flood fringe The part of the 1% AEP flood extent outside the floodway.
Zone 1 (waterbody protection zone) The inner setback zone defined in Clause 7.4.3.
Zone 2 (flood fringe setback) The outer setback zone defined in Clause 7.4.4.
Setback Zone 1 and Zone 2 together.
Compensatory storage Excavated storage that replaces flood storage lost to fill, under Clause 7.6.4.
Flood cushion Storage below FTL kept empty, under a documented operating rule, to absorb a flood (Clause 7.8).

Gujarat terms. The following terms are used in this chapter in addition to those above (see also Annex 7E):

Term Meaning in this Manual
Water course As defined in CGDCR 2017 (Regulation 2.117): "a natural channel or an artificial channel formed by draining or diversion of a natural channel meant for carrying clear, storm or waste water". A water course draining 8 ha or more is a natural channel under Clause 7.4.1(b), whether or not it is shown on the Development Plan.
Water body; talav; lake As defined in CGDCR 2017 (Regulation 2.118): "a natural existing low lying ground forming a natural water body or wherein rain water gets collected and/or plots designated as Talav under the revised development plan or any other legitimate records". It is a tank, lake or pond under Clause 7.2, whether or not it has a bund and surplus weir.
Statutory clearances The minimum distances of CGDCR 2017 Regulation 17.1 (repeated in Regulation 20.1.4): 30 m between the bank of a river with no embankment and "any development work"; 15 m between a river embankment and "any building", or any wider clearance prescribed by Government order; and 9 m between the boundary of "any other water body such as lake (talav), canal or nala" and "any building". The 15 m and 9 m clearances restrict buildings only; for this Manual Zone 1 also excludes fill, paving and walls within them (Clause 7.5.1).
Redirected water course A water course through low-lying land without a well-defined bank that the Competent Authority has allowed an applicant to "restrict or re-direct" to an alignment and cross-section it determines (CGDCR 17.1(4)). For this Manual the redirected section may be used only where it keeps the full recorded width and passes the 1% AEP flow, and Zone 1 is measured from the boundary of Clause 7.13.1 (Clauses 7.10.2 and 7.13.2).
High flood level (HFL) The level that CGDCR 2017 leaves to the Competent Authority (Regulation 2.55), and from which, where it is higher than the road crown and the existing ground, the established level of a building unit is fixed; the plinth of a habitable building is at least 0.45 m above that level (Regulation 13.1.5). The Code gives HFL no return period. For this Manual, floor levels are set by Clause 7.6.6 and Chapter 6 from the 1% AEP flood level; the statutory plinth rule continues to apply where higher.
Flood and restricted zones The zones of the Development Plans that restrict use near rivers and lakes: "Restricted Agriculture Zone (High Flood Zone)" (AGZ4), "Flood Prone Area/Zone", and the restricted zones RZ1 to RZ4 of VUDA, of which RZ1 permits only works needed to control floods or prevent pollution, RZ2 the same with up to 5% of ground-floor development, and RZ3 no development (CGDCR 2017, Part II, and Regulation 8.5). They are statutory lines under Clause 7.4.5. They are not the 1% AEP flood extent of Clause 7.2 unless the Authority adopts them under Clause 7.3.4 with a design flood that includes the climate factor of Clause 2.8.
Notified drainage course A river, stream or natural drainage course, or a reach of one, in which the State has prohibited obstructions by notification under section 11 of the Gujarat Irrigation and Drainage Act, 2013. The notified reach is "held to be a drainage work". It is a statutory corridor under Clause 7.4.5.
Lake periphery The area around a lake or pond "in which there will be no construction allowed", to be determined and notified under direction [G] of the High Court in Shailesh R. Shah v. State of Gujarat (2002). Where notified, it is a statutory line under Clause 7.4.5. None was found notified.
Kaans (kāṃs) In Vadodara, a natural storm channel, such as the Bhukhi kaas, which runs 8.72 km from Chhani talav to the Vishwamitri (VMC report to the NGT, 2024). It is a natural channel under Clause 7.4.1(b) and, where it carries a talav's surplus, a surplus course under Clause 7.10.
Khadi (khāḍī) A tidal creek, as in Surat, where the khadis carry storm water to the Tapi and back up at high tide and when the Tapi is high. A khadi is a tidal water body: its tailwater is taken from Chapter 5, and a sluice regulator at its mouth is a controllable outlet under Clause 7.8.
Bandhara; tidal regulator In WRD salinity-control usage, a bandhara is "a solid non-gated wall with crest level above high tide level" across a coastal river, and a tidal regulator a "structure with gates on large river to stop tidal ingress into the river bed" (CAG, 2010). For this Manual both are fixed controls on the tailwater of any drain that discharges upstream of them (Chapter 5); the pond behind a bandhara is a tank under Clause 7.2 only for Clauses 7.7 and 7.8 where its storage is counted.
Check dam A low weir across a stream or nala that holds water for recharge and irrigation, built in large numbers under the State's water-conservation programmes. It is a structure on a natural channel: Clauses 7.10.3 and 7.14 apply to it, and its pond is counted as storage only under Clause 7.7.
Percolation tank A tank or pond used to recharge groundwater, which section 2(2)(g) of the Gujarat Irrigation and Drainage Act, 2013 includes in "canal". It is a tank under Clause 7.2.
Irrigation canal used as an outfall A WRD canal, or a branch of the Narmada canal system, that receives storm water, as the Gota–Godhavi canal receives the overflow of Bhadreti lake in AUDA's Sanand scheme (ADB, 2023). A canal is a waterbody with the 9 m clearance of CGDCR 17.1(3); its capacity and levels for a storm discharge are set by its owner, and the discharge needs the owner's consent (Clause 7.4.5).
Mangrove Mangroves are ecologically sensitive CRZ-I areas under the Coastal Regulation Zone Notification, 2011 (CRZ-IA under the 2019 Notification), mapped on the CZMPs prepared under the 2011 Notification and approved in 2019–20, which govern until CZMPs under the 2019 Notification are approved. No Gujarat court order setting a statewide mangrove buffer was found; the CRZ Notification and the CZMP govern any work in or near them (Clause 7.12.6(b)).

7.3 Inventory and mapping of waterbodies

7.3.1 Statewide inventory. The Authority, with the WRD and the Revenue Department, shall maintain a GIS layer of every waterbody in its area (Annex 7A). For each waterbody it shall record:

  • (a) its type (Clause 7.2), name and survey numbers;
  • (b) its custodian (the WRD, AMC, SMC, VMC or another municipal corporation, a Municipality, AUDA or another urban development authority, GIDC, the Gram Panchayat, the Revenue Department (through the District Collector), the Forest Department or another body);
  • (c) its boundary as recorded in Revenue records;
  • (d) for tanks: FTL, MWL, TBL, the surplus weir crest length and type, sluices, the supply channel and the surplus course, each with its datum;
  • (e) its position in any tank cascade, with the upstream and downstream tanks;
  • (f) the 1% AEP flood extent, where mapped; and
  • (g) known encroachments, with the date recorded.

7.3.2 Project mapping. Every drainage report shall include a Waterbody Sheet (Form 7-1) showing all waterbodies:

  • (a) within the site;
  • (b) within 100 m of the site boundary; and
  • (c) downstream, to the extent of the downstream analysis of Chapter 5.

The sheet shall show, on a plan at a scale of 1:1,000 or larger for (a) and (b):

  • the Revenue record boundary;
  • the surveyed FTL or top of bank;
  • the MWL contour (tanks) and the 1% AEP flood extent;
  • Zone 1 and Zone 2 (Clause 7.4); and
  • every supply channel, surplus course, sluice and surplus weir.

7.3.3 Sources. Waterbodies shall be identified from all of the following. Where they conflict, the larger waterbody extent governs:

  • (a) Revenue village maps and land records, including land recorded as talav, nala or water course; the water bodies, ponds and talavs designated on the Development Plan or a Town Planning Scheme under the GTPUD Act, 1976, and the plots designated as talav in "any other legitimate records" (CGDCR 2017, Regulation 2.118); any Gazette notification or Collector's survey of water bodies made under the High Court's directions in Shailesh R. Shah v. State of Gujarat; and, in the coastal districts, the mangroves and High Tide Line of the approved Coastal Zone Management Plan (CZMP) maps;
  • (b) WRD and Gram Panchayat tank registers and records of FTL and MWL;
  • (c) the Authority's inventory (Clause 7.3.1) and any list published under court directions;
  • (d) historical topographic maps and satellite imagery, including the ISRO National Wetland Inventory and Assessment; and
  • (e) a site survey by a licensed surveyor, levelled to the datum stated in Clause 7.3.5.

7.3.4 Flood extent maps. The Authority may adopt 1% AEP flood extent or flood depth maps for its area. A depth map adopted under this clause also sets floor levels under Clause 6.11. Where a map has been adopted, it shall be used unless a site hydraulic study under Chapters 3 and 5 shows a larger extent. Where no map has been adopted, the Applicant shall determine the 1% AEP extent by a hydraulic study for:

  • (a) any site in a flood-sensitive catchment (Chapter 1);
  • (b) any site of 1 ha or more adjoining a waterbody; and
  • (c) any site where the Authority so requires.

For other sites, the fixed-width setback of Clause 7.4.6 may be used.

7.3.5 Datum. All levels in this chapter shall be stated to one datum, stated on every drawing. Where WRD records use a local or older datum, the conversion to the project datum shall be surveyed and stated.

Commentary. No 1% AEP flood map of any Gujarat city was found, and Gujarat has no system of statutory flood lines along its rivers. CGDCR 2017 leaves the high flood level to the Competent Authority (Regulation 2.55), takes flood-prone areas from the Flood Atlas of the Central Water Commission and the Vulnerability Atlas of India, 1997, and regulates them through use zones such as the "Restricted Agriculture Zone (High Flood Zone)" and the restricted zones RZ1 to RZ4 of the Vadodara plan (Part II and Regulation 8.5). SMC prepared a flood inundation and flood prediction map of Surat in 2010 (SMC, Projects Executed), which was not read. The National Green Tribunal directed the demarcation of the whole floodplain of the Vishwamitri in Vadodara on 25 May 2021 (as reported); whether it was done was not established. Under the High Court's order of 1 August 2024, the District Collectors are to survey the water bodies of each district, with separate reports for municipal and urban development authority areas; their reports were not found. On the coast, the CZMPs in force are those prepared under the CRZ Notification, 2011 and approved by MoEF&CC in January 2019 and February 2020, and their update under the CRZ Notification, 2019 was still pending in August 2022 (CAG, Report No. 3 of 2022). Clause 7.3.4 lets the Authority adopt larger-scale flood maps once they are issued. Until then, the Applicant must produce the extent for larger and flood-sensitive sites, and because Gujarat has no flood lines, that extent governs wherever it has been mapped. Clause 7.3.3 makes the larger of the recorded and surveyed extents govern, because the Revenue boundary and the surveyed water edge often differ, and either may have been reduced by encroachment. The 100 m search band in Clause 7.3.2 is set by this Manual.


7.4 Setbacks

7.4.1 Waterbodies to which setbacks apply. Setbacks apply to:

  • (a) every waterbody recorded under Clause 7.3.1 or found under Clause 7.3.3, whatever its size; and
  • (b) every natural channel, whether recorded or not, that drains 8 ha or more at the site.

7.4.2 Two zones. The setback has two zones, shown in Figure 7.1:

  • Zone 1 (waterbody protection zone), next to the waterbody; and
  • Zone 2 (flood fringe setback), outside Zone 1.

7.4.3 Zone 1 width. Zone 1 is measured outward from the FTL contour (tanks, lakes and ponds) or from the top of bank (channels). Where both apply, use whichever gives the wider zone. Zone 1 extends to the greatest of:

  • (a) 9 m, the clearance that CGDCR 2017 (Regulation 17.1(3)) keeps between the boundary of a lake (talav), canal or nala and any building, applied here to every waterbody and to all the works that Clause 7.5.1 excludes; along a river, Zone 1 is not less than the 30 m that Regulation 17.1(1) keeps between the bank of a river without an embankment and any development work, or, where the river is embanked, the 15 m that Regulation 17.1(2) keeps between the embankment and any building (see the Disclosure below);
  • (b) the outer edge of the floodway (Clause 7.6.1); and
  • (c) for a tank, the MWL contour.

7.4.4 Zone 2 width. Zone 2 extends from the outer edge of Zone 1 to the 1% AEP flood extent plus 10 m. Where the 1% AEP flood extent lies inside Zone 1, Zone 2 is 10 m wide.

7.4.5 Statutory and approval setbacks. Where a statute, a statutory rule, a condition of planning permission or WRD's consent for a work on one of its canals or on a drainage course notified under section 11 of the Gujarat Irrigation and Drainage Act, 2013, a GCZMA recommendation or CRZ clearance, or a permission of the wetland authority sets a setback wider than Zone 1 or Zone 2, the wider setback governs for the uses it restricts.

7.4.6 Fixed-width setback where no 1% AEP extent is available. Where Clause 7.3.4 does not require a hydraulic study and no map has been adopted, the setback (Zone 1 plus Zone 2) shall be not less than the following, measured as in Clause 7.4.3:

Table 7.1 — Fixed-width setback where no 1% AEP extent is available

Waterbody Total setback (Zone 1 + Zone 2) Of which Zone 1
Channel draining 8 ha to 65 ha 25 m 9 m
Channel draining 65 ha to 20 km² 40 m 9 m
Channel draining more than 20 km², and rivers 50 m 20 m
Tank, lake or pond MWL contour + 25 m to MWL contour, and not less than 9 m from FTL
Marsh, estuary or backwater as notified by the Authority, and not less than 50 m 9 m

This table is the alternative S-3 of the Policy Supplement (Annex 1C) and may be adopted under Clause 1.7.

7.4.7 Minimum in all cases. No setback under this chapter, and no variance under Clause 1.10, shall reduce Zone 1 below 9 m (Clause 1.10.3(c)).

Commentary. The 9 m minimum is the clearance that CGDCR 2017 (Regulation 17.1(3)) keeps between the boundary of a lake (talav), canal or nala and any building, applied here as a corridor along the whole waterbody and to fill, paving and walls as well as buildings. Along rivers, the wider clearances of Regulation 17.1(1) and (2), 30 m from the bank of a river without an embankment to any development work and 15 m from a river embankment to any building, are the floor of Zone 1 and govern under Clause 7.4.5, including where Table 7.1 gives a smaller Zone 1 (see the Disclosure below). Extending the setback to the mapped 1% AEP extent plus a margin follows the Kansas City Metro APWA Section 5600 (2025.01) two-zone structure:

  • APWA Zone 1 (streamside) is measured from top of bank, and only utility and road crossings are allowed in it.
  • APWA Zone 2 is the 1% AEP flood extent plus 10 ft (about 3 m), for streams draining 20–40 acres.
  • APWA lowered the trigger for stream setbacks from 40 acres to 20 acres (about 8 ha) in 2025.01.

(MARC, APWA 5600 Policy Supplement, Nov 2025.) Clause 7.4.1(b) adopts the 8 ha trigger. This Manual's 10 m margin is wider than APWA's 10 ft and has no direct precedent. This Manual sets it because Gujarat flood maps are mostly coarser than US maps, the alluvial plains of Ahmedabad and central Gujarat, the margins of Surat's khadis and the coasts of the Gulfs of Khambhat and Kachchh are very flat (so a small error in level moves the flood edge a long way), and the margin gives room for maintenance access along the waterbody.

The fixed-width table in Clause 7.4.6 is set by this Manual. Its channel widths are scaled from the 2006 APWA default stream buffers, which were 40 ft, 60 ft, 100 ft and 120 ft (12, 18, 30 and 37 m) for drainage areas of less than 40 acres, 40–160 acres, 160–5,000 acres and more than 5,000 acres (KC APWA 5600, 2006, §5605.3). They are rounded up and floored at the statutory 9 m minimum. APWA offered a fixed-width table for the same reason: communities objected that the 1% extent is often unmapped for small drainage areas (MARC Supplement, 2025). The table should be replaced by mapped extents as soon as the Authority adopts them.

URDPFI (2015) reserves the area flooded at a 10-year frequency for parks and playgrounds, and allows residential use in the 25-year flood zone only on stilts, with minimum plinth levels and no basements. This chapter is stricter. It keeps habitable buildings out of the whole 1% AEP extent plus margin, because the 1% AEP (100-yr) event is the major-system standard of this Manual (Chapter 6).

Gujarat's building code sets fixed clearances from waterbodies, framed as distances from buildings rather than as corridors, and with no link to flood levels. CGDCR 2017 Regulation 17.1 requires a minimum clearance of 30 m between the bank of a river "where there is no embankment" and "any development work"; 15 m between the embankment of a river and "any building", or any wider clearance prescribed by a general or specific order of Government, "whichever is more"; and 9 m between the boundary of "any other water body such as lake (talav), canal or nala" and "any building". Where a water course passes through low-lying land without a well-defined bank, the Competent Authority may let the applicant "restrict or re-direct" it to an alignment and cross-section it determines (Regulation 17.1(4)). Because only the river clause speaks of "any development work", a compound wall, fill or paving within 9 m of a nala or talav may not be caught by the Code. No development is permitted on land designated as a water body, pond or talav in the Development Plan, and the zone tables add flood and restricted zones: the "Restricted Agriculture Zone (High Flood Zone)", the restricted zones RZ1 to RZ4 around the river and lakes of Vadodara, and a 30 m margin from the river edge in Gandhinagar's Recreational Zone I (Table 6.36). The Sabarmati Riverfront has its own regulations, which prevail in its zone (Regulation 8.4.4). The Code has no flood-line system: it leaves the high flood level to each Competent Authority (Regulation 2.55). The High Court directed in 2002 that a no-construction periphery be fixed and notified for each lake and pond (Shailesh R. Shah, direction [G]), but no notified periphery was found. Clause 7.4.7 makes the statutory 9 m the floor of Zone 1 for every waterbody, measured along the whole waterbody and applied to fill, paving and walls as well as buildings, and keeps the 30 m and 15 m of the river clauses as the floor of Zone 1 along rivers.

Disclosure. The setbacks of this chapter start from the statutory distances of CGDCR 2017 Regulation 17.1 and add a hydraulic corridor set by this Manual where it is wider. Zone 1 is never less than 30 m from the bank of a river without an embankment, 15 m from a river embankment, and 9 m from a talav, canal or nala, and it extends to the floodway and, for a tank, to the MWL contour where these are wider; Zone 2 extends to the 1% AEP flood extent plus 10 m (Clauses 7.4.3, 7.4.4 and 7.4.7). Because Gujarat has no statutory flood lines, the 1% AEP extent of this Manual, where it has been mapped (Clause 7.3.4), is the only flood-based line, and it governs. This chapter is stricter than statute in the following respects:

  • Corridor, not building clearance. The 15 m and 9 m clearances of Regulation 17.1 apply to "any building". Here Zone 1 also excludes fill, paving, compound walls, dumping and stockpiles (Clause 7.5.1), and applies to every natural channel draining 8 ha or more, shown on the Development Plan or not (Clause 7.4.1(b)).
  • Measurement. The Code measures from the bank, embankment or boundary of the waterbody, and lets a low-lying water course be re-directed to a section the Competent Authority sets (Regulation 17.1(4)). Here setbacks run from the larger of the Revenue record boundary and the surveyed FTL or top of bank (Clause 7.13.1), so a nala narrowed by redirection or encroachment is measured at its recorded width.
  • Floodway and flood fringe. Where the floodway of a nala or river is wider than the statutory clearance, Zone 1 extends to it, and no habitable building is placed in Zone 2, which runs to the 1% AEP extent with the climate factor plus 10 m, except in a developed-fringe area notified under Clause 7.6.6. The Code ties levels only to a high flood level that each Competent Authority fixes, with no stated return period (Regulation 2.55).
  • Fixed widths. Where no flood extent is mapped, Table 7.1 sets a total setback of 25 m to 50 m along channels, of which the statutory 9 m (20 m for the largest channels) is Zone 1. Along a river, the statutory 30 m from an unembanked bank governs where it is wider than the 20 m of Table 7.1 (Clause 7.4.5).
  • Tanks and lakes. The Code sets 9 m from a talav to a building, and the High Court's lake-by-lake peripheries have not been found notified. Here every tank, lake or pond has Zone 1 to its MWL contour and not less than 9 m from FTL; the same 9 m around marshes, creeks and backwaters, which the Code does not name, is set by this Manual; and the total setback is at least the MWL contour plus 25 m where no flood extent is mapped (Table 7.1).

Where a statutory line is wider, it governs (Clause 7.4.5): any wider clearance from a river embankment prescribed by Government order (Regulation 17.1(2)); a water body, flood or restricted zone of the Development Plan (AGZ4, RZ1 to RZ3); the 30 m river-edge margin in Gandhinagar; a lake periphery notified under the High Court's directions; a drainage course notified under section 11 of the Gujarat Irrigation and Drainage Act, 2013; and every mangrove and other CRZ line of the approved CZMPs. The reasons for the corridor are the floods of Surat in 2006 (Tapi) and 2026 (khadis), Vadodara in 2019 and 2024 (Vishwamitri) and Ahmedabad in 2026, the High Court's finding in 2024 that the filling of water bodies "may also be prime reason for water clogging", and the absence of flood lines along every urban river and nala. Until a statute or rule adopts them, the statutory clearances remain the legal minimum and this chapter's further values are the Manual's recommended standard. Approving authorities should state in each approval which of the two was applied.

Waterbody setback zones: cross-section Waterbody setback: Zone 1 and Zone 2, with Gujarat's statutory clearances (section, not to scale) Zone 1 Waterbody protection Zone 2 Flood fringe setback Developable land Waterbody: tank bed, channel, marsh (no development) FTL (crest of surplus weir) / top of bank 1% AEP (100-yr) flood level, with climate factor (or MWL for tanks) Bed (surveyed, original) park, path floor ≥ 1% level + 0.5 m ≥ 9 m talav, canal, nala greater of statutory clearance and floodway to mapped 1% AEP extent + 10 m margin 1% extent 9 m 15 m 30 m (river) Zone 1: no buildings, fill, paving or dumping. Crossings, utilities, flood works and native vegetation only. Zone 2: no habitable buildings. Parks, unpaved paths, open-sided structures; fill only with 1:1 compensatory storage. Setback measured from FTL (tanks, lakes) or top of bank (channels), whichever gives the wider zone. This Manual: Zone 1 and Zone 2 Statute: CGDCR 2017, Regulation 17.1 9 m from a talav (lake), canal or nala to any building (17.1(3)) 15 m from a river embankment to any building (17.1(2)) 30 m from the bank of an unembanked river to any development work (17.1(1)) No statutory flood lines; HFL fixed by each Competent Authority (Reg. 2.55). Along a river, Zone 1 ≥ 30 m (unembanked) or 15 m (embanked); the mapped 1% AEP extent sets Zone 2. Wider statutory lines govern: DP water body and flood or restricted zones (AGZ4, RZ1–RZ3); lake peripheries notified under the High Court's directions; notified drainage courses; mangroves and CRZ lines.

Figure 7.1 — Waterbody setback zones: section through a tank or channel showing FTL, the 1% AEP flood level, the statutory 9 m minimum line, Zone 1 and Zone 2. Original drawing for this Manual, adapted from Kansas City Metro APWA, Section 5600 Version 2025.01 and Policy Supplement (MARC, 2025).


7.5 Uses permitted in each zone

7.5.1 Zone 1. No building, fill, paving, retaining wall, boundary wall, compound wall, dumping of earth, debris or solid waste, storage of materials, or construction-stage stockpile shall be placed in Zone 1. Only the following are permitted, each subject to the custodian's NOC:

  • (a) road, rail and utility crossings that meet Clause 7.10.3;
  • (b) flood and drainage works: outfalls, inlet structures, gross pollutant traps, sluices, surplus weirs, bund strengthening and bank protection;
  • (c) native vegetation, planting and habitat works;
  • (d) unpaved or permeable footpaths and maintenance tracks at existing ground level; and
  • (e) waterbody restoration under Clause 7.9.

7.5.2 Zone 2. No habitable building, basement, school, hospital, fuel store or hazardous-material store shall be placed in Zone 2. The following are permitted:

  • (a) all uses permitted in Zone 1;
  • (b) parks, playgrounds, open-air sports fields and urban agriculture;
  • (c) open-sided structures (shelters, pavilions) with no walls that obstruct flow;
  • (d) surface parking with permeable surfacing at existing ground level, where the 1% AEP flood depth is not more than 0.3 m;
  • (e) retention, detention and water quality facilities under Chapters 4 and 8, provided they are outside the floodway and their storage is not counted twice (Clause 7.6.5); and
  • (f) fill, only for (a) to (e) or for essential public infrastructure, and only with compensatory storage under Clause 7.6.4.

7.5.3 Fences. Fences in Zone 1 and Zone 2 shall be open (chain-link or railing) with no plinth wall above existing ground level, so that they do not obstruct flow or trap debris.

7.5.4 Open space reservation. Zone 2 land may be counted toward the common plot required by CGDCR 2017, where the Authority agrees. Zone 1 land shall be handed over to the custodian or kept free of private use, as the Authority decides.

Commentary. The permitted uses follow APWA 2025.01: in Zone 1, only utility and road crossings; in Zone 2, linear utilities, trails and open-sided structures; no clearing, grading, fill or paving in either zone without approval (MARC Supplement, 2025). Clause 7.5.2 adds parks and playgrounds, the uses URDPFI (2015) allows in the 10-year flood zone. The ban on walls in Clauses 7.5.1 and 7.5.3 responds to urban Gujarat practice: compound walls along channels and tanks act as dams in floods, and are often the first step toward encroachment. The 0.3 m depth limit for parking in Clause 7.5.2(d) has no direct precedent and is set by this Manual.


7.6 Floodway, flood fringe and compensatory storage

7.6.1 Floodway delineation. The floodway shall be delineated by a hydraulic model of the 1% AEP flood (with the climate factor), using the encroachment method: the conveyance of the flood fringe is removed equally from both banks until the 1% AEP water level rises by 0.1 m. Where the floodway has not been delineated, the whole 1% AEP flood extent shall be treated as floodway. For a tank, all land below MWL is floodway.

7.6.2 No fill in the floodway. No fill, building, embankment, raised road or other obstruction shall be placed below the 1% AEP flood level within the floodway, except the works permitted in Zone 1 under Clause 7.5.1(a) and (b). Those works shall be shown by hydraulic analysis to raise the 1% AEP water level by no more than 0.01 m, upstream or downstream, outside the Applicant's land.

7.6.3 Fill in the flood fringe. Fill below the 1% AEP flood level in the flood fringe is permitted only:

  • (a) for uses permitted under Clause 7.5.2, or outside the setback where the Authority has notified a developed-fringe area under Clause 7.6.6; and
  • (b) with compensatory storage under Clause 7.6.4.

7.6.4 Compensatory storage. Where fill is placed in the flood fringe, compensatory storage shall be provided that (Figure 7.2):

  • (a) replaces at least 1.0 m³ of storage for each 1.0 m³ of fill placed below the 1% AEP flood level;
  • (b) is provided at equivalent levels: the volume lost and the volume replaced shall be balanced in each elevation band of not more than 0.3 m, from the normal water level (or the 50% AEP level, where higher) up to the 1% AEP flood level;
  • (c) is in the same reach of the same waterbody, hydraulically connected to it, and not further downstream than the fill;
  • (d) drains freely by gravity back to the waterbody as the flood recedes, with no pumping and no permanent pool below the normal water level;
  • (e) is built before, or at the same time as, the fill is placed; and
  • (f) is secured by a covenant or handover so that it is never filled later.

7.6.5 No double counting. Compensatory storage shall not be counted as detention or retention storage under Chapter 4. Detention and retention storage placed within the 1% AEP flood extent shall be counted only for the volume above the 1% AEP flood level, unless a model of the joint event (Clause 2.12) shows that it is available.

7.6.6 Developed-fringe areas. The Authority may notify, by map, areas of existing built-up land within the 1% AEP flood extent but outside the floodway, where it is impractical to apply Zone 2 to redevelopment. In a notified developed-fringe area:

  • (a) redevelopment may be approved without the Zone 2 restriction;
  • (b) the lowest habitable floor and all openings shall be at least 0.5 m above the 1% AEP flood level (Chapter 6);
  • (c) basements are not permitted;
  • (d) the redevelopment shall cause no net loss of flood storage below the 1% AEP flood level (Clause 7.6.4), and stilt construction may be used for this; and
  • (e) Zone 1 continues to apply in full.

Commentary. The 1:1 compensatory storage at equivalent levels is set by this Manual. A simple volume balance is not enough: storage excavated below the normal water level is full before the flood arrives and gives no flood benefit. Storage gained high up does not replace storage lost low down, because the low storage is used in every flood and the high storage only in the largest. Balancing volume within each elevation band avoids both problems. The 0.3 m band, the 0.01 m allowance for crossings, and the use of the encroachment method in Clause 7.6.1 are set by this Manual; the encroachment method is the standard way to delineate a floodway in a one-dimensional hydraulic model. The 0.1 m limit on the rise in the 1% AEP water level is tighter than the 1 ft (about 0.3 m) used by the US National Flood Insurance Program. The alluvial plains of Ahmedabad and central Gujarat, the margins of Surat's khadis and the coasts of the Gulfs of Khambhat and Kachchh are flat, so a small rise in level spreads flooding over a wide area, and many small encroachments along the same channel add up.

No Gujarat rule protecting the land between a talav's full level and its flood level was found: CGDCR 2017 measures its 9 m from the boundary of the talav (Regulation 17.1(3)), and the lake peripheries directed by the High Court in 2002 were not found notified. Ahmedabad's talavs are part of its flood path. AUDA's storm water scheme for Sanand routes the flow of its drains through Bhadreti lake, modelled by the Modified Puls method, with an overflow box drain to the Gota–Godhavi canal (ADB, 2023), and in July 2026 Bopal lake filled and its excess was released to the same canal (as reported). The land between full level and flood level of such a talav stores flood water that would otherwise reach the canal or the streets below it. Treating all land below MWL as floodway (Clause 7.6.1) means that no new building or fill is approved in a tank foreshore.

The developed-fringe mechanism of Clause 7.6.6 is set by this Manual. Large parts of Surat, 80 to 95% of which was flooded in August 2006 (as reported), and the areas of Vadodara along the Vishwamitri that flooded in 2019 and 2024 already lie within the 1% AEP extent. A blanket Zone 2 ban on redevelopment there would stop the replacement of older, lower buildings with buildings raised above flood level. The mechanism follows the URDPFI (2015) approach for the 25-year flood zone (stilts, minimum plinth, no basements), applied here to the 1% AEP extent.

Compensatory storage by elevation band: section Compensatory storage by elevation band (section, not to scale) A. Fill in the flood fringe B. Compensatory excavation, same reach waterbody waterbody permitted use drains back by gravity 1% AEP flood level Normal water level (or 50% AEP if higher) Band 1 Band 1 Band 2 Band 2 Band 3 Band 3 Band 4 Band 4 Orange: fill below the 1% level = volume lost Blue: excavation below the 1% level = volume gained Grey: cut above the 1% level, no credit Volume per band (m³), Form 7-3 worked example: illustrative, not design values 60 180 Band 1 180 300 Band 2 300 390 Band 3 420 450 Band 4 Volume lost (fill) Volume gained (excavation) Bands of not more than 0.3 m, from the normal water level to the 1% AEP level. Volume gained ≥ volume lost in every band (Clause 7.6.4(b)).

Figure 7.2 — Compensatory storage by elevation band: section through the flood fringe showing fill placed below the 1% AEP flood level and an equal or greater volume excavated within each band of not more than 0.3 m, from the normal water level (or 50% AEP level) up to the 1% AEP level, with the excavation draining back to the waterbody by gravity. Band-by-band calculation on Form 7-3. Original drawing for this Manual, illustrating the method of Clause 7.6.4, which is set by this Manual.


7.7 Tank cascades as design storage

Gujarat has no tank Act and few impounded tanks of the classic type with an earthen bund, a waste weir and irrigation sluices in its towns. The storages that matter for urban drainage are of five kinds. The first is the urban talav, often a natural depression with no surplus weir: Ahmedabad's lake interlinking programme, begun in 2003, covered 72 notified urban lakes, of which 41 had been connected with storm water drains and linked to the Narmada canal by 2011, at a cost of Rs 190 crore (as reported); Kankaria lake's front was redeveloped by 2008, and Chandola lake was historically fed by the Khari cut canal (as reported). The second is the talav that feeds a natural channel, as Chhani talav in Vadodara, in which "only the rain water is stored", feeds the Bhukhi kaas (VMC, 2024). The third is the village talav and check dam deepened or built under the State's water-conservation campaigns: the State reports more than 1.2 lakh works under the Sujalam Sufalam Jal Abhiyan from 2018 to 2026 (as reported; not audited). The fourth is the percolation tank, which the Gujarat Irrigation and Drainage Act, 2013 counts as a "canal" (section 2(2)(g)). The fifth is the salinity-control works of the Saurashtra and Kachchh coast, recharge tanks, bandharas, tidal regulators and spreading channels, of which only 41% of the works recommended by the High Level Committees had been completed by March 2010 (CAG, 2010). Clauses 7.7 and 7.8 apply to any of these whose storage is counted, and a chain of talav, interlinking drain, canal and nala in which each drains into the next is a tank cascade for Clause 7.7.2. The WRD's dams and the reservoirs upstream of the cities, such as Ukai on the Tapi, Dharoi on the Sabarmati and Ajwa and Pratappura above Vadodara, are not tanks for these clauses: their releases and levels enter a design as tailwater (Chapter 5). A bandhara or tidal regulator downstream of an outfall is a fixed control on its tailwater (Chapter 5).

7.7.1 When tank storage may be counted. The storage of a tank or tank cascade may be counted as design storage (in a basin plan, a regional facility or a fee-in-lieu scheme under Clause 7.11) only where all of the following are met:

  • (a) Surveyed levels. FTL, MWL, TBL, the surplus weir crest and length, and the sluice sill levels have been surveyed to the datum of Clause 7.3.5 within the previous 5 years.
  • (b) Stage–storage curve. A stage–storage curve has been derived from a bathymetric and topographic survey of the waterspread and foreshore within the previous 5 years, or after the last desilting, whichever is later.
  • (c) Operating rule. A documented operating rule has been agreed with the custodian (Clause 7.8).
  • (d) Maintained structures. The surplus weir, sluices and bund are maintained under an O&M plan (Chapter 10), and the latest pre-monsoon inspection found them serviceable.
  • (e) Custodian concurrence. WRD, or the other custodian, concurs in writing.

Storage in a tank that fails any of (a) to (e) shall not be counted, though the tank shall still be modelled as an existing feature (Chapter 3).

7.7.2 Modelling. Tank cascades shall be modelled under Clause 3.12.5 (level-pool routing of each tank, with surplus weir and sluice ratings) and Clause 3.13 (continuous simulation). The whole cascade, from the uppermost tank whose surplus can reach the site or facility to the next river, major drain or sea outfall, shall be modelled together, including every talav, interlinking drain, canal and nala through which the outflow passes to the river, as in the Ahmedabad pattern shown in Figure 7.3.

7.7.3 Starting level. The starting level in every tank shall be FTL for the design-storm analysis. A lower starting level may be used only under a flood-cushion operating rule that meets Clause 7.8.

7.7.4 Design maximum level. For the 1% AEP inflow with the climate factor, routed through the cascade:

  • (a) the computed maximum level shall be not higher than MWL (as defined in Clause 7.2); and
  • (b) the freeboard from the computed maximum level to the lowest point of the bund (TBL) shall be not less than WRD's freeboard standard for the tank.

Where (a) or (b) fails, the tank storage above FTL shall not be counted until the surplus weir capacity is increased or the bund raised under Clause 7.7.6.

7.7.5 Creditable volume. The creditable design storage of a tank is the volume between the starting level (Clause 7.7.3) and the computed maximum level of Clause 7.7.4, less any volume already committed to another facility or scheme.

7.7.6 Changes to FTL, weirs and bunds. No surplus weir crest shall be raised or lowered, no shutters or falling boards shall be added, and no bund shall be raised, cut or breached except under a design approved by the custodian that:

  • (a) routes the cascade under Clause 7.7.2;
  • (b) shows the effect on flood levels in the foreshore and upstream, and on flows in the surplus course and downstream; and
  • (c) checks the bund under Clause 7.14.

Commentary. This Manual allows tank cascades to be used as design storage subject to three basic conditions (surveyed FTL, a documented operating rule and maintained surplus weirs). Clause 7.7.1 adds the stage–storage survey and the custodian's concurrence, because the storage a tank actually offers depends on its silt level and on who controls the sluices. The 5-year survey interval is set by this Manual.

The FTL starting level follows Clause 3.12.5. Gujarat's largest floods have come in the middle of the south-west monsoon, when talavs and reservoirs are full and soils wet. At Surat in August 2006, the outflow from Ukai rose to about 907,000 cusec at 8 pm on 8 August, and the releases coincided with days of high tide (SANDRP, 2006, compiling Central Water Commission and Central Electricity Authority bulletins). At Vadodara, Ajwa overflowed in the storm of 31 July 2019, and on 26 to 29 August 2024 the Vishwamitri rose to about 37 ft against a danger mark of 25 ft (as reported). At Ahmedabad in July 2026, Bopal lake was already full when its catchment flooded, and its excess had to be released to the Gota–Godhavi canal (as reported). A tank cascade passes floods from one tank to the next, so a design that counts storage in one tank and ignores the surplus arriving from the tank above it will overstate the benefit. That is why Clause 7.7.2 requires the whole cascade to be modelled.

Talav chain to a canal and the river: the Ahmedabad pattern (plan) Talav chain to a canal and the river: the Ahmedabad pattern (plan, schematic, not to scale) River (e.g. Sabarmati) river stage and dam releases set tailwater (Ch. 5) 30 m 17.1(1) Urban catchment percolating wells, RWH on-site retention and treatment (Chapters 4 and 8) storm drain (along roads) GPT + DWF dry-weather flow to sewer feed from the Narmada canal: a talav filled before the monsoon starts the storm at FTL (Cl. 7.7.3) Talav 1 (urban lake) interlinking drain (surplus course, Cl. 7.10) Talav 2 routes the flood (as Bhadreti lake) foreshore (FTL to MWL) surplus nala (vokla) to the river overflow box drain Irrigation canal (e.g. Gota–Godhavi): outfall only with the canal owner's consent; canal level is the tailwater Zone 1: ≥ 9 m from FTL (CGDCR 17.1(3)) and to the MWL contour Zone 2 to 1% AEP extent + 10 m water at FTL foreshore (FTL to MWL) Zone 1 Zone 2 30 m river clearance Model the whole chain together, from the uppermost talav to the river and the canal (Clause 7.7.2); count talav storage only under Clause 7.7.1. No levels shown: no published levels for these talavs were found. Every level in a design must be surveyed and stated on one datum (Clause 7.3.5).

Figure 7.3 — Talav chain to a canal and the river, the Ahmedabad pattern, in plan (schematic, not to scale): an urban catchment with on-site retention, percolating wells and treatment; a storm drain along the roads with a gross pollutant trap and dry-weather flow interception; an urban talav with its foreshore, the statutory 9 m clearance of CGDCR 17.1(3) and the setback zones of Clause 7.4, and a feed from the Narmada canal that can fill it before the monsoon; an interlinking drain to a second talav that routes the flood, as Bhadreti lake does in AUDA's Sanand scheme; an overflow box drain to an irrigation canal, as the Gota–Godhavi canal receives it; and a surplus nala to a river whose stage and dam releases set the tailwater, with the 30 m clearance from an unembanked river bank of CGDCR 17.1(1). No levels are shown because none were published for these talavs. Original drawing for this Manual; concept from the Sanand storm water scheme (ADB, 2023), Ahmedabad's lake interlinking programme (as reported) and CGDCR 2017 Regulation 17.1, with setback zones adapted from Kansas City Metro APWA, Section 5600 Version 2025.01 (MARC, 2025).


7.8 Operating rules and pre-monsoon flood cushion

7.8.1 Operating rule content. Every tank whose storage is counted under Clause 7.7 shall have a written operating rule, agreed by the custodian and kept with the O&M plan (Chapter 10). It shall state:

  • (a) the levels and dates for filling, holding and drawdown through the year;
  • (b) the sluice and regulator settings at each level;
  • (c) who operates the sluices and regulators, and who may order a release;
  • (d) the maximum release rate, set so that the release, added to the flow from the downstream catchment, does not cause flooding of buildings downstream;
  • (e) the forecast and warning triggers (IMD district warnings, GSDMA alerts, and city forecast systems where available) and the actions taken at each trigger;
  • (f) communication with downstream ULBs and residents before any release; and
  • (g) the records to be kept: daily levels in the SW monsoon, releases, and gate settings.

7.8.2 Flood cushion. A tank may be operated with a flood cushion (a level below FTL during part of the SW monsoon), and the cushion counted under Clause 7.7.3, only where:

  • (a) the tank has a gated sluice, regulator or other controllable outlet able to draw the tank down to the cushion level in the time stated in the rule;
  • (b) the operating rule fixes the cushion level and the dates it applies;
  • (c) continuous simulation (Clause 3.13) shows that the cushion is available at the start of a design storm in at least 90% of SW monsoon seasons in the record, allowing for the rain that usually comes before the peak storm;
  • (d) the custodian accepts any loss of irrigation or water-supply yield, and any agreed compensation is recorded; and
  • (e) the release needed to create or restore the cushion meets Clause 7.8.1(d).

7.8.3 No storage credit without control. Where a tank has no controllable outlet, no flood cushion shall be assumed, whatever the past practice.

7.8.4 Coordination. For tanks under WRD control, the operating rule shall be WRD's rule. This Manual does not authorise any other body to operate a WRD tank.

Commentary. No operating rule for a Gujarat talav, check dam or urban lake that keeps a flood cushion was found. Dam releases are the largest controlled flows reaching the State's cities. At Ukai in 2006 the flood cushion had been designed on the assumption that the Tapi through Surat could carry 8.5 lakh cusec, while the Chair of the Central Water Commission put its capacity at 3.5 to 4.0 lakh cusec, (SANDRP, 2006), and the reservoir had passed its rule level by 3 August, five days before the peak release (as reported; the rule level itself is given differently by different sources). At Vadodara in August 2024, the gates of Ajwa were closed to cut the flow to the Vishwamitri with the reservoir at 213.8 ft against a danger mark of 214 ft, and the Navalawala committee, formed in September 2024, recommended desilting of the river and an additional spillway at Ajwa (as reported; its report was not found). Ahmedabad's interlinked lakes are linked to the Narmada canal (as reported), and a lake topped up from the canal before the monsoon starts the storm full. Without an agreed rule with dates, levels and a named operator, storage behind a gate cannot be relied on. Clause 7.8.2 turns that principle into a rule that can be checked, with a reliability test, because a cushion that is usually refilled by June and July rain gives no protection in a July or August monsoon spell. The 90% reliability in Clause 7.8.2(c) has no direct precedent and is set by this Manual.

Irrigation, drinking water and groundwater recharge remain the primary purposes of most of Gujarat's talavs, check dams and percolation tanks, and the State's water-conservation campaigns aim to fill them, not to keep them empty. A flood cushion has a cost in stored water, which is why Clause 7.8.2(d) requires the custodian to accept it.


7.9 Restoration, desilting and deepening

7.9.1 Pre-works survey. Before any desilting or restoration, the proponent shall:

  • (a) survey the waterspread, foreshore, bund, weirs and sluices (Clause 7.7.1(a) and (b));
  • (b) find the original bed level by test pits or augering on a grid, and from historical records where available; and
  • (c) where the tank receives urban runoff or sewage, test the silt for heavy metals and other contaminants before disposal is planned.

7.9.2 Desilting limit. Desilting shall remove accumulated sediment down to the original bed level. It shall not deepen the tank below the original bed, except under Clause 7.9.3.

7.9.3 Deepening. Deepening below the original bed is permitted only where a hydrogeological report shows that:

  • (a) it will not cut through a clay or silt layer that holds water in the tank or protects an aquifer from polluted water;
  • (b) in coastal areas, it will not draw saline water into the tank or the aquifer; and
  • (c) the extra storage will be refilled and used, and will not stand stagnant below the sluice sill.

Storage created below the lowest sluice sill shall not be counted as flood storage.

7.9.4 Safe edges. Where the public has access to the waterbody edge:

  • (a) side slopes shall be no steeper than 1V:4H from 0.5 m above FTL down to 1.2 m below FTL, or a level safety bench at least 3 m wide shall be provided between 0.3 m and 0.5 m below FTL; and
  • (b) no isolated deep pit or vertical cut shall be left in the bed.

7.9.5 Storage not to be reduced. Restoration shall not reduce the storage below MWL. Islands, walkways, bund widening into the waterspread, ring roads, parking, buildings and "lake-front" platforms within the waterspread or foreshore shall be counted as lost storage and shall be offset under Clause 7.6.4.

7.9.6 Silt disposal. Desilted material shall not be placed within the setback, on the bund (except for approved bund strengthening), or on any flood path. Silt found to be contaminated shall be disposed of as the Gujarat Pollution Control Board directs.

7.9.7 Inlet treatment. Every restoration of a tank that receives urban runoff shall include sediment and gross pollutant control at each inlet: a sediment forebay, a constructed wetland inlet zone, or a gross pollutant trap (Chapter 8), so that the restored storage does not silt up again.

7.9.8 Timing. Desilting shall be completed, and the waterbody made safe, by 31 May each year (Chapter 10).

Commentary. Desilting is a main pre-monsoon work in Gujarat's towns and villages. The State reported the desilting of 3,661 check dams under the 2026 Sujalam Sufalam campaign (as reported), and VMC reported that the Bhukhi kaas is cleaned every year before the monsoon (VMC, 2024). In Surat, about 13 km of the Mithi khadi, which had 3 to 4 ft of silt, is to be dredged at a cost of about Rs 30 crore (as reported, October 2026). No published AMC desilting deadline was found. The 31 May deadline matches the pre-monsoon inspection date of Chapter 10. The limits on deepening are set by this Manual. Deepening tanks to "increase capacity" is common, but it can breach the silt and clay layer that holds water in the tank, it can let polluted urban water reach the aquifer, it can draw salt water toward the coast, and it creates storage below the sluice sill that never empties and gives no flood benefit. Deep pits with steep sides are also a drowning hazard. The slope and bench values in Clause 7.9.4 are adapted from common pond-safety practice; they have no Gujarat precedent.


7.10 Supply channels, surplus courses, inlets and outlets

7.10.1 Part of the major system. Supply channels and surplus courses are part of the major drainage system (Chapter 6). They shall be protected as waterbodies, with Zone 1 and Zone 2 setbacks under Clause 7.4.

7.10.2 No closure or covering. No supply channel or surplus course shall be closed, filled, diverted, covered, culverted along its length, or converted into a road or a closed drain, except under a design approved by the custodian that keeps or increases its 1% AEP capacity and its access for maintenance.

7.10.3 Crossings. Every road, rail, utility or access crossing of a waterbody, supply channel or surplus course shall:

  • (a) pass the 1% AEP flow (with the climate factor), or the surplus of the upstream tank at its MWL, whichever is greater, with the freeboard required by Chapter 9;
  • (b) not reduce the waterway width at the crossing below the full channel width as recorded in Revenue records or as surveyed, whichever is greater;
  • (c) keep the channel bed level and grade; and
  • (d) not raise the 1% AEP water level by more than the limit in Clause 7.6.2.

7.10.4 Capacity. The design capacity of a surplus course shall be the greater of the surplus weir discharge at MWL and the 1% AEP flow from its own catchment, combined as the cascade model (Clause 7.7.2) shows.

7.10.5 Protection at structures. Outlets of surplus weirs and sluices, and drain outfalls into waterbodies, shall have energy dissipation and scour protection designed under Chapter 9, so that the flow leaving them does not erode the bund, the bank or the channel bed.

7.10.6 Drain outfalls into waterbodies. A storm drain outfall into a tank, channel or wetland shall:

  • (a) have its invert at or above the normal water level of the receiving waterbody, unless the drain is designed for submerged outfall under Chapter 5;
  • (b) be located and aligned so that it does not cut through or weaken a tank bund;
  • (c) have a gross pollutant trap and first-flush treatment (Chapter 8); and
  • (d) not carry sewage or dry-weather flow (Chapter 8).

Commentary. This Manual protects supply channels and surplus courses as part of the major system. In urban areas they are often the first to be lost. Surplus courses are narrowed by culverts and compound walls, and supply channels are covered and turned into roads, which cuts the tank off from its source or leaves its surplus with nowhere to go. Gujarat's code lets the Competent Authority have a water course through low-lying land "restrict[ed] or re-direct[ed]" to a section it sets (CGDCR 17.1(4)), and the Gujarat Irrigation and Drainage Act, 2013 lets the Government approve "the crossing of natural drain, diversion of natural drain by earthen bund or by any means" (section 10(3)), while also allowing a natural drainage course to be notified and its obstruction prohibited (section 11). In Vadodara, the Bhukhi kaas has been covered in places and left open in others (VMC, 2024), and a committee formed under the State Human Rights Commission found waterways and ravines being "filled or encroached upon" and reported that the Delhi–Mumbai Expressway near Sadad worsened the waterlogging of 2024 (as reported). In Surat, a study of 2025 criticised walls and roads built on the floodplains of the Mithi and Koyali khadis (as reported). AUDA's Sanand scheme discharges the overflow of Bhadreti lake to the Gota–Godhavi irrigation canal (ADB, 2023): a canal designed to carry irrigation water then becomes part of the major drainage system, which is why Clause 7.10 and the canal owner's consent (Clause 7.4.5) apply to it. Clause 7.10.3(b) prevents a crossing from narrowing a channel to its current, encroached width.


7.11 Fee-in-lieu and regional tank storage

7.11.1 Where a basin plan has been notified, and the Authority has adopted alternative S-5 of the Policy Supplement (Clause 1.7), a development may pay a fee in lieu of on-site detention under Chapter 4. The fee shall be applied to restoring or creating storage in a tank, pond or regional facility in the same basin.

7.11.2 Tank storage funded by fee-in-lieu shall:

  • (a) meet Clause 7.7.1 in full before it is counted;
  • (b) be downstream of the contributing development and upstream of the flood-prone area it is meant to protect;
  • (c) be created, or under construction, before the development it serves is occupied, or within a period the basin plan fixes; and
  • (d) be recorded in the register of Clause 10.17 with the developments that funded it, so that the same volume is not sold twice.

7.11.3 Fee-in-lieu does not replace:

  • (a) the retention requirement of Chapter 4, which is always met on site; or
  • (b) the water quality requirement of Chapter 8, which is met on site or in a regional facility treating the same runoff before it reaches the tank.

Commentary. Chapter 4 provides for fee-in-lieu toward restored talav or tank storage in master-planned basins. Malaysia's 2008 DID checklist allowed on-site detention only for small sites and required community ponds for larger areas (DID, 2008). In Gujarat the nearest existing forms of shared storage are AUDA's use of Bhadreti lake to route the storm water of Sanand (ADB, 2023) and Ahmedabad's lake interlinking programme (as reported). CGDCR 2017 lets a building unit of more than 4,000 m² provide a water retention pond of at least 300,000 litres in place of most of its percolating wells (Regulation 17.2.2(d)), but that pond is on the site. None of these sets a technical standard for counting storage. Clause 7.11.2(b) matters because a tank downstream of the flood-prone area protects nothing. Clause 7.11.3 keeps retention on site: it is the volume-control layer of this Manual, and a regional tank cannot recharge the aquifer under the developed site.


7.12 Wetlands, marshes and estuaries

7.12.1 Scope. This clause applies to marshes, swamps, backwaters, estuaries, and tidal creeks and lagoons, including:

  • (a) wetlands notified under the Wetlands (Conservation and Management) Rules, 2017 or listed by the State Wetland Authority;
  • (b) the Ramsar sites of Gujarat, Nalsarovar, Thol Lake, Wadhvana and Khijadia, and Chhari-Dhand in Kachchh (reported in 2026 to be a Ramsar site);
  • (c) Surat's khadis, including the Varachha, Chhaprabhatha, Mithi and Kankra khadis, the tidal Tapi below the Singanpore weir, the tidal creeks, mudflats and estuaries of the Gulfs of Khambhat and Kachchh, and every mangrove area, including those of Nani Chirai and Moti Chirai in Kachchh that the National Green Tribunal ordered restored;
  • (d) the notified urban lakes of Ahmedabad, including those in the lake interlinking programme, Kankaria and Chandola, and the talavs of Vadodara, including Chhani talav, with the kaans that join them; and
  • (e) any other marsh, creek or lake that the Authority notifies or that is notified under the directions of the High Court.

7.12.2 No drainage of wetlands. No drain, channel, cut or pump shall be designed to drain a wetland, to lower its normal water level, or to reduce the period for which it is wet, except under a plan approved by the wetland authority.

7.12.3 Inflows. Every drain discharging into a wetland in Clause 7.12.1 shall:

  • (a) meet Clause 7.10.6;
  • (b) pass through water quality treatment for the WQv of its catchment (Chapter 8) before entering the wetland; and
  • (c) where practicable, spread its flow across a vegetated margin rather than discharge at one point.

7.12.4 Hydraulic connectivity. Roads, embankments and utility corridors across or along a wetland shall have openings that:

  • (a) pass the 1% AEP flow without raising the 1% AEP water level by more than the limit in Clause 7.6.2; and
  • (b) keep the wetland's normal water exchange, including tidal exchange in estuaries, with openings spread along the crossing so that no part of the wetland is cut off.

7.12.5 Storage counted at basin scale only. Wetland storage shall be included in basin and regional models. It shall not be counted as detention for any individual development.

7.12.6 Tidal wetlands and estuaries. For estuaries and tidal wetlands:

  • (a) tailwater shall be taken from Chapter 5 (Clause 2.12 joint cases);
  • (b) works shall also comply with the Coastal Regulation Zone Notification in force; and
  • (c) mouth-opening works, training walls and dredging are outside the scope of this Manual and need their own studies.

7.12.7 No dumping. No solid waste, construction debris or dredged material shall be placed in a wetland or its setback.

Commentary. Gujarat's wetlands near its cities include four Ramsar sites listed by MoEF&CC: Nalsarovar (designated on 24 September 2012, 12,000 ha), Thol Lake Wildlife Sanctuary and Wadhvana Wetland (both on 5 April 2021, 699 ha and 630 ha) and Khijadia (13 April 2021); Chhari-Dhand in Kachchh was reported in January 2026 to have become a fifth. Whether a State Wetland Authority has been constituted under the Wetlands (Conservation and Management) Rules, 2017 could not be confirmed, and no list of wetlands notified under those Rules was found. Gujarat has India's second-largest mangrove cover, 23.66% of the national total (Rajya Sabha reply, February 2025, as cited), most of it in Kachchh. The CAG found that salt-pan bunds 9,511 m long had destroyed about 117 ha of mangroves at Nani Chirai and Moti Chirai in Kachchh; the National Green Tribunal ordered their restoration within six months on 11 September 2019, but none had been done by March 2022. It also found a shortfall of 1,968.80 ha in the 9,415 ha of mangrove plantation claimed, and that the Gujarat Coastal Zone Management Authority had no dedicated staff (CAG, Report No. 3 of 2022). No Gujarat court order setting a statewide mangrove buffer was found, so the CRZ Notification, 2019 and the approved CZMPs govern work in or near mangroves. A drain outfall, khadi widening, sluice regulator or pumping station in a mangrove belt therefore needs CRZ clearance as well as compliance with this chapter. Surat's khadis are tidal creeks that the city regulates at their mouths: SMC built a sluice regulator with four 4.0 m by 4.0 m electric gates on the Varachha khadi in 2013–14, designed for a Tapi flood of 8.0 lakh cusec, and another on the Chhaprabhatha khadi in 2016, designed for 10.0 lakh cusec (SMC, Projects Executed). Khadi flooding struck Surat three times in July 2026; the State announced Rs 500 crore for khadi works, and a survey of about 188 km of creeks and a hydrology model to reset their danger levels followed (as reported). Clause 7.12.2 targets a specific risk: drains built to relieve flooding next to a marsh can drain the marsh itself, and once it is dry it is encroached. Sewage reaches Gujarat's talavs, kaans and khadis through the storm drains. In Vadodara, 20 to 25 MLD of sewage that had been flowing in the Bhukhi kaas was diverted to a new 50 MLD treatment plant at Chhani in 2021–22 (VMC, 2024). The GPMC Act, 1949 lets the Commissioner require one drain for sewage and sullage and "another and an entirely distinct drain for rain water" (section 174), and CGDCR 2017 leaves the norms for drains and sewers to the Gujarat Pollution Control Board (Regulation 13.10). The High Court's direction that lakes be recharged "by appropriate storm water drains" (Shailesh R. Shah, direction [D]) works only if those drains carry no sewage. The rules on outfalls and treatment in Clause 7.12.3 respond to these.


7.13 Encroachment interfaces

7.13.1 Boundary. For design under this Manual, the boundary of a waterbody is the larger of its Revenue record boundary and its surveyed FTL (or top of bank), as in Clause 7.3.3. Setbacks are measured from that boundary.

7.13.2 No reliance on encroached land. No design shall:

  • (a) count, as storage or conveyance, land within a waterbody boundary that is occupied by encroachment, unless its removal is ordered and funded; or
  • (b) treat the encroached width of a channel as its design width.

7.13.3 Public works in encroached reaches. Where a public drainage work passes through an encroached reach:

  • (a) it shall be designed for the full waterbody width (Clause 7.13.1);
  • (b) where the full width cannot be cleared before the work is built, the design report shall state the interim capacity and the flood risk until it is cleared; and
  • (c) the work shall be built so that the full width can be restored later without rebuilding it.

7.13.4 Boundary marking. Every development adjoining a waterbody shall, before the completion certificate:

  • (a) mark the outer edge of Zone 1 on the ground with permanent survey markers at intervals of not more than 30 m and at every change of direction; and
  • (b) show the setback zones on the approved layout plan and in the sale documents of every plot that includes setback land.

7.13.5 Retaining walls. No retaining wall, bund or embankment shall be built along the edge of a waterbody, within Zone 1, to protect or reclaim land, except to protect existing public infrastructure under the custodian's approval.

Commentary. Gujarat's main controls on building in waterbodies are the clearances and zones of CGDCR 2017, the High Court's directions and the orders of the National Green Tribunal. The High Court directed in 2002 that encroachments on lakes and ponds be recorded and removed and the responsibility of officers fixed (Shailesh R. Shah, direction [F]), and in 2024 found the land-filling of water bodies continuing in towns, villages and even wildlife sanctuaries. In Ahmedabad, a public interest petition on Makarba lake has been pending since 2016, and the High Court directed AMC to fence Thaltej lake in 2015 (as reported). The National Green Tribunal ordered the removal of unauthorised structures along the Vishwamitri in 2021 (as reported), and VMC reported no encroachment on the Bhukhi kaas in 2024 (VMC, 2024). Under the Gujarat Irrigation and Drainage Act, 2013, a canal officer may order the removal of an obstruction in a notified drainage course and remove it at the cost of the person responsible (sections 12 and 13). The sections of the municipal Acts under which encroachments on nalas are removed were not reviewed for this Manual, and no statewide count of encroached waterbodies was found. This Manual cannot evict anyone. It can stop designs from treating encroachment as permanent (Clause 7.13.2), make public works restorable to full width (Clause 7.13.3), and make the setback visible on the ground and in property documents so that new buyers know it is there (Clause 7.13.4). The 30 m marker interval is set by this Manual.


7.14 Safety of tank bunds and embankments

7.14.1 Dam Safety Act screening. For every tank, and every embankment built or altered under this Manual, the designer shall determine whether it is a "specified dam" under the Dam Safety Act, 2021. Under the Act, a specified dam is a dam:

  • (a) more than 15 m high, measured from the lowest point of the general foundation area to the top of the dam; or
  • (b) between 10 m and 15 m high, where the crest length is not less than 500 m, or the reservoir capacity is not less than one million m³, or the maximum flood discharge dealt with by the dam is not less than 2,000 m³/s, or the dam has specially difficult foundation problems, or the dam is of unusual design.

Where it is a specified dam, the Act and the requirements of the State Dam Safety Organisation govern, in addition to this Manual.

7.14.2 Hazard class. Every tank bund and detention embankment that is not a specified dam shall be given a hazard class:

  • High hazard: a breach could flood a habitable building, a school, a hospital, an arterial road or critical infrastructure.
  • Low hazard: any other case.

7.14.3 High-hazard embankments. For high-hazard tank bunds and embankments:

  • (a) the surplus weir or spillway shall pass the 1% AEP inflow at MWL with the freeboard of Clause 7.7.4(b), and shall be checked for the 0.2% AEP (500-yr) inflow without overtopping the bund (as for detention basins in Chapter 4);
  • (b) a breach analysis shall map the area flooded by a breach at MWL;
  • (c) an emergency action plan shall be prepared, with the warning and evacuation arrangements for the breach area; and
  • (d) the design shall be certified and independently checked under Clause 10.6.

7.14.4 Inspection. Every tank whose storage is counted under Clause 7.7, and every high-hazard embankment, shall be inspected before the SW monsoon (by 31 May) and after every heavy-rainfall event (Chapter 10) for seepage, slips, cracks, animal burrows, trees on the bund, and blockage of the weir and sluices.

7.14.5 No unauthorised cutting. No person shall cut, lower or breach a tank bund or surplus weir during a flood except under the custodian's emergency procedure.

Commentary. The definition of a specified dam is quoted from the Dam Safety Act, 2021 (Act 41 of 2021). The Act defines a "dam" as an artificial barrier constructed across rivers or tributaries to impound or divert water. It excludes flood embankments, dikes and guide bunds. The bunds of most village talavs, check dams and bandharas are low and are not expected to be specified dams, but each shall be screened under Clause 7.14.1; a check dam across a stream or nala is an artificial barrier across a river or tributary in the Act's sense. The WRD's dams, such as Ukai and Dharoi, and the reservoirs above Vadodara, Ajwa and Pratappura, enter this Manual only as sources of inflow and tailwater (Chapter 5). Where the storage of a water retention pond or an urban talav is counted under Clause 7.7, its embankment is a tank bund for Clause 7.14.2. Whether a tank bund that is not across a river or tributary is a "dam" under the Act is not clear from its text. Dam releases have flooded Gujarat's cities: Ukai's releases flooded Surat in 2006, Ajwa and Pratappura bear on Vadodara's floods of 2019 and 2024, and a release of about 1.3 lakh cusec from Dharoi in 2017 submerged the lower promenade of the Sabarmati Riverfront in Ahmedabad (as reported). Surat has an early-warning system for Ukai releases and khadi floods, run by SMC with the Surat Climate Change Trust and TARU, with the WRD and GSDMA among its partners (TARU and SMC, project summary). The CAG found the gates of the Rukmavati tidal regulator not working (CAG, 2010). No release protocol for these dams was read for this Manual. The hazard classes, the breach analysis and the emergency action plan for high-hazard tanks are set by this Manual. They extend the Chapter 4 requirement for detention basins (1% AEP spillway with outlet blocked, 0.2% AEP for high-hazard basins) to tanks that are counted as design storage.


7.15 Submittal requirements

Every drainage report for a development or work under Clause 7.1.2 shall include:

  1. the Waterbody Sheet (Form 7-1) under Clause 7.3.2, with the setback zones and their basis (mapped extent, hydraulic study or fixed width);
  2. the hydraulic study of the 1% AEP extent and floodway, where Clause 7.3.4 requires it;
  3. the Compensatory Storage Calculation (Form 7-3), by elevation band, where fill is proposed in the flood fringe;
  4. for any tank storage counted: the Tank Storage Credit Sheet (Form 7-2), with the survey, stage–storage curve, operating rule, cascade model results and custodian concurrence of Clause 7.7.1;
  5. for any crossing, outfall or work in Zone 1: the custodian's NOC and the hydraulic analysis of Clause 7.6.2 or 7.10.3;
  6. for restoration or desilting: the pre-works survey, silt tests and hydrogeological report of Clause 7.9; and
  7. for any embankment: the Dam Safety Act screening and hazard class of Clause 7.14.

7.16 Review and update

7.16.1 This chapter shall be reviewed with the rest of the Manual (Chapter 1). The fixed-width table of Clause 7.4.6 shall also be reviewed within 2 years of the Authority adopting 1% AEP flood maps for its area.

7.16.2 Where the Authority adopts new 1% AEP flood maps, they apply to new submittals 6 months after adoption, unless the Authority notifies otherwise.


References (chapter)

Annexes and forms

Annex / Form Content
7A Statewide waterbody GIS layer and inventory fields
7B Fixed-width setback table (alternative S-3, with Annex 1C)
7C Template tank operating rule, with flood cushion
7D Desilting and restoration specification
7E Glossary of Gujarati waterbody terms and regional variants
Form 7-1 Waterbody Sheet
Form 7-2 Tank Storage Credit Sheet
Form 7-3 Compensatory Storage Calculation (by elevation band)