Annexes to Chapter 3Hydrologic Methods
These annexes support Chapter 3. Annex 3C sets out benchmark test problems for software acceptance, and Forms 3-1 and 3-2 are the submittal forms required by Clause 3.17. Annexes 3A, 3B, 3D and 3E need survey, gauging or published report data that this draft does not yet contain; each gives the intended layout and the interim rule of Chapter 3 that applies until it is published. The forms are draft forms and have no statutory status.
Annex 3A — Karnataka soil series to HSG lookup; seasonal high water table map
Supports Clauses 3.7 and 3.10 of Chapter 3.
To be prepared. This annex will contain (a) a lookup from each soil series mapped in Karnataka to its hydrologic soil group (HSG), in both the drained and the undrained state, and (b) a map of the depth to the seasonal high groundwater table in the monsoon season (June–October). It needs NBSS&LUP and Karnataka State Remote Sensing Applications Centre (KSRSAC) series maps with their scales, measured saturated hydraulic conductivity and depth to an impermeable layer for each series, and observation-well records from the Central Ground Water Board and the Ground Water Directorate, supplemented by piezometers in coastal sand areas. Until it is published, use the interim rules of Chapter 3: assign HSG from measured saturated hydraulic conductivity and depth to an impermeable layer or water table by the criteria of NEH Part 630, Ch. 7 (Clause 3.7.2); verify it by site infiltration tests wherever retention relies on infiltration (Clause 3.7.3); take the seasonal high water table from site piezometers, trial pits or the nearest observation well (Clause 3.10.2); and assign HSG D wherever that level is within 0.6 m of the ground surface (Clause 3.10.1).
Table 3A.1 — Soil series to HSG lookup (layout)
| Soil series | District(s) | Taxonomic class | Surface texture | Saturated hydraulic conductivity (mm/h) | Depth to impermeable layer (m) | HSG, drained | HSG, undrained | Source map and scale |
|---|---|---|---|---|---|---|---|---|
Table 3A.2 — Seasonal high water table, by mapping unit (layout)
| Mapping unit or grid cell | Observation wells used | Years of June–October record | Highest June–October level below ground (m) | Within 0.6 m of ground (Clause 3.10.1)? | Data source |
|---|---|---|---|---|---|
Annex 3B — Karnataka CN calibration and supplementary land covers (paddy, plantations)
Supports Clauses 3.8 and 3.15 of Chapter 3.
To be prepared. This annex will contain (a) curve numbers calibrated against observed rainfall and runoff in Karnataka catchments, compared with the TR-55 values of Table 3.5, and (b) curve numbers for land covers that Table 3.5 does not list: bunded paddy fields (ponded and fallow), including valley-floor paddy in the command of a kere, and tree plantations in the Malnad and on the coast. It needs paired rainfall–runoff records for small gauged catchments of known cover and soil, from WRD gauging sites, agricultural research stations and tank gauges, analysed by event and by antecedent moisture. Until it is published: the pre-development reference stays open space in good condition for every site (Clause 3.3.2), so these covers do not enter the pre-development run; for off-site existing conditions, use the nearest Table 3.5 or TR-55 cover row, including the cultivated rows (Clause 3.8.3(c)), and state the row chosen and the reason on Form 3-1; land under standing water at the start of the design storm is modelled as water surface with no losses (Table 3.5; Clause 3.10.4(b)). Any departure from these defaults requires calibration under Clause 3.15 (Clause 3.15.1(d)).
Table 3B.1 — Supplementary land covers, AMC II (layout)
| Cover type | HSG A | HSG B | HSG C | HSG D | Ia ratio | Basis (catchments, events, years) |
|---|---|---|---|---|---|---|
| Paddy, bunded, ponded | ||||||
| Paddy, bunded, fallow between seasons | ||||||
| Valley-floor paddy in the command of a kere | ||||||
| Tree plantations (Malnad and coast) | ||||||
| Other (state) |
Table 3B.2 — CN calibration catchments (layout)
| Catchment | District | Area (km²) | Dominant HSG and cover | Events used | Table 3.5 CN | Calibrated CN | Calibrated ÷ Table 3.5 |
|---|---|---|---|---|---|---|---|
Annex 3C — Benchmark test problems for software acceptance
Supports Clauses 3.5, 3.6, 3.8, 3.9, 3.11, 3.12 and 3.16 of Chapter 3.
Purpose. Software not listed in Clause 3.16.1 shall reproduce the results of the five problems below (Clause 3.16.3). Each problem is fully specified and uses only the methods and tables of Chapter 3, so every answer can be checked by hand. The acceptance tolerance is ±5% on each tabulated result, the equivalence threshold of Clause 3.16.2; for closed-form results (Problems 3C-1 to 3C-4), software should agree to the rounding shown. The submittal shall report the software result next to each answer below.
Illustrative — not design values. The inputs (areas, intensities, rainfall depths, slopes and the basin) are chosen for testing only. They are not design data for any site.
Problem 3C-1 — Rational Method peak (Clause 3.5)
Inputs. A 2.0 ha catchment draining to one inlet: 1.2 ha concrete paving and roofs, C = 0.90 (Table 3.2, upper half of 0.80–0.95); 0.8 ha lawns on sandy soil, average slope, C = 0.15 (Table 3.2, upper half of 0.10–0.15). Design AEP 1% (100-yr). Rainfall intensity at Tc, including the climate factor: i = 120 mm/h.
Part (b): a separate 0.5 ha fully paved catchment, C = 0.90, design AEP 1%, i = 150 mm/h.
Table 3C.1 — Problem 3C-1 solution
| Step | Calculation | Result |
|---|---|---|
| Composite C (Clause 3.5.4) | (1.2 × 0.90 + 0.8 × 0.15) / 2.0 | 0.60 |
| Frequency factor (Table 3.3) | 1% AEP | Cf = 1.25 |
| C · Cf (≤ 1.0) | 0.60 × 1.25 | 0.75 |
| Peak flow (Clause 3.5.1) | 0.75 × 120 × 2.0 / 360 | Q = 0.500 m³/s |
| Part (b): C · Cf | 0.90 × 1.25 = 1.125, capped at 1.0 (Clause 3.5.3) | 1.00 |
| Part (b): peak flow | 1.00 × 150 × 0.5 / 360 | Q = 0.208 m³/s |
Problem 3C-2 — Time of concentration by the segment method (Clause 3.6)
Inputs. Pre-development flow path: sheet flow over greenfield, n = 0.15 (Clause 3.6.3), L = 30 m, S = 0.01; P2 (50% AEP 24-hour rainfall, no climate factor) = 80 mm. Shallow concentrated flow, unpaved, L = 200 m, S = 0.01. Channel flow, L = 400 m, bank-full velocity V = 1.0 m/s (given).
Table 3C.2 — Problem 3C-2 solution
| Segment | Calculation | Travel time |
|---|---|---|
| Sheet flow (Clause 3.6.2(a)) | 0.091 × (0.15 × 30)^0.8 / (80^0.5 × 0.01^0.4) = 0.2138 h | 12.83 min |
| Shallow concentrated (Clause 3.6.2(c)) | V = 4.918 × 0.01^0.5 = 0.4918 m/s; 200 / (3,600 × 0.4918) = 0.1130 h | 6.78 min |
| Channel (Clause 3.6.2(d)) | 400 / (3,600 × 1.0) = 0.1111 h | 6.67 min |
| Tc (Clause 3.6.1; ≥ 10 min) | 12.83 + 6.78 + 6.67 | 26.27 min |
| Lag (Clause 3.6.5) | 0.6 × 26.27 | 15.76 min |
Problem 3C-3 — SCS-CN runoff depth, AMC and Ia sensitivity (Clause 3.8)
Inputs. Pre-development reference on HSG C: CN = 74 at AMC II (Table 3.5), all pervious. Cumulative rainfall P = 100 mm; second case P = 25 mm.
Table 3C.3 — Problem 3C-3 solution
| Case | S (mm) | Ia (mm) | Runoff Q (mm), P = 100 mm | Runoff Q (mm), P = 25 mm |
|---|---|---|---|---|
| (a) AMC II, Ia = 0.2S: S = 25,400 / 74 − 254 | 89.24 | 17.85 | 39.38 | 0.53 |
| (b) AMC III, Ia = 0.2S: CN(III) = 23 × 74 / (10 + 0.13 × 74) = 86.75 | 38.80 | 7.76 | 64.93 | — |
| (c) AMC II, Ia = 0.05S: S0.05 = 25.4 × 1.33 × (89.24 / 25.4)^1.15 | 143.31 | 7.17 | 36.49 | 1.97 |
Runoff is Q = (P − Ia)² / (P − Ia + S). Case (c) gives less runoff than case (a) at 100 mm but more at 25 mm, as Clause 3.8.5 and Figure 3.3 describe.
Problem 3C-4 — Separate vs composite impervious representation, and SCS unit hydrograph peak (Clauses 3.9 and 3.11.2)
Inputs, part (a). A site that is 50% directly connected impervious (CN 98) and 50% open space on HSG B (CNp = 61), AMC II, Ia = 0.2S, P = 25 mm.
Inputs, part (b). A sub-area of A = 2.5 km² with Tc = 1.0 h and computation interval Δt = 0.1 h.
Table 3C.4 — Problem 3C-4 solution
| Step | Calculation | Result |
|---|---|---|
| (a) Impervious half (Clause 3.9.2) | S = 5.18 mm, Ia = 1.04 mm; Q = 23.96² / (23.96 + 5.18) | 19.70 mm |
| (a) Pervious half | S = 162.39 mm, Ia = 32.48 mm > P | 0 mm |
| (a) Area-weighted runoff, separate sub-areas | 0.5 × 19.70 + 0.5 × 0 | 9.85 mm |
| (a) Composite CN (Clause 3.9.4) | 61 + 0.50 × (98 − 61) | 79.5 |
| (a) Runoff with composite CN | S = 65.50 mm, Ia = 13.10 mm; Q = 11.90² / (11.90 + 65.50) | 1.83 mm |
| (b) Interval check (Clause 3.11.3(a)) | 0.133 × 1.0 = 0.133 h ≥ Δt = 0.1 h | satisfied |
| (b) Lag and time to peak (Clause 3.11.2) | tL = 0.6 × 1.0 = 0.60 h; tp = 0.1 / 2 + 0.60 | tp = 0.65 h |
| (b) Unit hydrograph peak, Q = 1 mm | 0.208 × 2.5 × 1 / 0.65 | qp = 0.800 m³/s per mm |
Part (a) reproduces the comparison in the commentary to Clause 3.9 (about 9.9 mm vs 1.8 mm).
Problem 3C-5 — Level-pool (modified Puls) storage routing (Clause 3.12.1)
Inputs. A detention basin with vertical sides and plan area 500 m², with the stage–storage–discharge relationship of Table 3C.5. Triangular inflow hydrograph: 0 at t = 0, rising linearly to 0.50 m³/s at t = 30 min, falling linearly to 0 at t = 90 min. Basin empty at t = 0. Routing interval Δt = 10 min (600 s). No tailwater.
Table 3C.5 — Problem 3C-5 stage–storage–discharge relationship
| Stage (m) | Storage S (m³) | Outflow O (m³/s) |
|---|---|---|
| 0.0 | 0 | 0.00 |
| 0.5 | 250 | 0.05 |
| 1.0 | 500 | 0.10 |
| 1.5 | 750 | 0.15 |
| 2.0 | 1,000 | 0.20 |
| 2.5 | 1,250 | 0.25 |
Method. The storage-indication equation is (I1 + I2) + (2S1/Δt − O1) = (2S2/Δt + O2). The table gives O = S / 5,000 (S in m³, O in m³/s), so 2S/Δt + O = 17.667 O and 2S/Δt − O = 15.667 O, and each step is O2 = [(I1 + I2) + 15.667 O1] / 17.667. Software interpolating linearly in Table 3C.5 shall give the same result.
Table 3C.6 — Problem 3C-5 routed outflow
| Time (min) | Inflow I (m³/s) | Outflow O (m³/s) | Storage (m³) | Stage (m) |
|---|---|---|---|---|
| 0 | 0.0000 | 0.0000 | 0.0 | 0.000 |
| 10 | 0.1667 | 0.0094 | 47.2 | 0.094 |
| 20 | 0.3333 | 0.0367 | 183.3 | 0.367 |
| 30 | 0.5000 | 0.0797 | 398.4 | 0.797 |
| 40 | 0.4167 | 0.1226 | 612.8 | 1.226 |
| 50 | 0.3333 | 0.1511 | 755.7 | 1.511 |
| 60 | 0.2500 | 0.1670 | 835.2 | 1.670 |
| 70 | 0.1667 | 0.1717 | 858.6 | 1.717 |
| 80 | 0.0833 | 0.1664 | 832.1 | 1.664 |
| 90 | 0.0000 | 0.1523 | 761.5 | 1.523 |
| 120 | 0.0000 | 0.1062 | 531.1 | 1.062 |
| 180 | 0.0000 | 0.0517 | 258.3 | 0.517 |
Results. Peak outflow 0.172 m³/s at 70 min; peak storage 859 m³; peak stage 1.72 m. The inflow peak of 0.50 m³/s is reduced to 34% of its value.
Table 3C.7 — Benchmark results to be reported by the applicant
| Problem | Result | Benchmark | Software result | Difference (%) | Within ±5%? |
|---|---|---|---|---|---|
| 3C-1 | Q, main case (m³/s) | 0.500 | |||
| 3C-1 | Q, part (b) (m³/s) | 0.208 | |||
| 3C-2 | Tc (min) | 26.27 | |||
| 3C-3 | Q, case (a), P = 100 mm (mm) | 39.38 | |||
| 3C-3 | Q, case (b), P = 100 mm (mm) | 64.93 | |||
| 3C-3 | Q, case (c), P = 100 mm (mm) | 36.49 | |||
| 3C-3 | Q, case (c), P = 25 mm (mm) | 1.97 | |||
| 3C-4 | Runoff, separate sub-areas (mm) | 9.85 | |||
| 3C-4 | Runoff, composite CN (mm) | 1.83 | |||
| 3C-4 | qp (m³/s per mm) | 0.800 | |||
| 3C-5 | Peak outflow (m³/s) | 0.172 | |||
| 3C-5 | Peak storage (m³) | 859 |
Annex 3D — Peak rate factor study for flat coastal land
Supports Clauses 3.11.5 and 3.15 of Chapter 3.
To be prepared. This annex will contain peak rate factors calibrated for unchannelled, flat coastal-plain land in Karnataka, with the limits of slope, drainage density and land cover within which each factor may be used. It needs observed rainfall and flow or water-level records for small, flat, undrained coastal catchments (WRD gauging sites, GBA and KSDMA level sensors, tank gauges), catchment geometry from survey or a DEM, and calibration of the SCS unit hydrograph peak to those events under Clause 3.15. Until it is published, use the standard factor 484 (PRF′ = 0.208) for all land (Clause 3.11.5): a lower factor may be used only after the authority adopts calibrated values in this annex (Clause 3.11.5(c)), and then only for land that stays unchannelled, in the same way in both the pre- and post-development runs (Clause 3.11.5(a) and (b)).
Table 3D.1 — Calibrated peak rate factors (layout)
| Catchment | Area (km²) | Mean slope (m/m) | Drainage condition | Events used | Calibrated PRF (US customary) | PRF′ (SI) | Range of applicability |
|---|---|---|---|---|---|---|---|
Annex 3E — CWC SUH parameters for subzones 3(e), 3(h), 3(i) and 5(b), with worked example
Supports Clauses 3.4.3 and 3.11.4 of Chapter 3.
To be prepared. This annex will tabulate, for CWC subzones 3(e) (Upper Godavari), 3(h) (Krishna and Pennar), 3(i) (Kaveri) and 5(b) (Malabar Coast), the regression relationships for the synthetic unit hydrograph parameters, the design storm duration, loss rate, base flow, areal reduction and time distribution, each with its reference to the Flood Estimation Report, and a worked example for one catchment. It needs the CWC Flood Estimation Reports for the Kaveri subzone 3(i) (CB/11/1985, January 1986), the Krishna and Pennar subzone 3(h) (revised, KP-3(h)/R-5/45/2000), the West Coast Region subzones 5(a) and 5(b) (K&M/19/1992), of which subzone 5(b) covers coastal Karnataka, and the Upper Godavari subzone 3(e), which covers Bidar (see the References of Chapter 3), with the subzone boundaries within Karnataka confirmed on the reports' index maps, transcribed and checked against the published reports, and a catchment with physiographic parameters measured from survey or a DEM. Until it is published, take all SUH inputs directly from the applicable Flood Estimation Report (Clause 3.11.4(a)), apply the 24-hour design rainfall of Clauses 2.3.3(b) and 2.7.3 with the climate factor of Clause 2.8 (Clause 3.11.4(b)), report the SUH result alongside the HEC-HMS or SWMM result for the existing natural condition (Clause 3.11.4(c)), and, where the hydrograph model gives a lower 1% AEP peak, either justify it by calibration under Clause 3.15 or adopt the SUH peak (Clause 3.11.4(d)).
Table 3E.1 — SUH relationships by subzone (layout)
| Parameter | Symbol | Unit | Subzone 3(e) relationship | Subzone 3(h) relationship | Subzone 3(i) relationship | Subzone 5(b) relationship | Report reference |
|---|---|---|---|---|---|---|---|
| Time from centre of unit rainfall to peak | tp | h | [TBC] | tp = 0.325 (L·Lc/√S)^0.447 | tp = 0.553 (L·Lc/√S)^0.405 | tp = 1.5607 qp^−1.0814 | 3(h): Table 3.3; 3(i), 5(b): [TBC] |
| Peak discharge per unit area | qp | m³/s per km² | [TBC] | qp = 0.996 tp^−0.497 | qp = 2.043 / tp^0.872 | qp = 0.9178 (L/S)^−0.4313, as printed; L/√S [TBC] | 3(h): Table 3.3; 3(i), 5(b): [TBC] |
| Width of UH at 50% of peak | W50 | h | [TBC] | W50 = 2.389 qp^−1.065 | W50 = 2.197 / qp^1.067 | W50 = 1.9251 qp^−1.0896 | 3(h): Table 3.3; 3(i), 5(b): [TBC] |
| Width of UH at 75% of peak | W75 | h | [TBC] | W75 = 1.415 qp^−1.067 | W75 = 1.325 / qp^1.088 | W75 = 1.0189 qp^−1.0443 | 3(h): Table 3.3; 3(i), 5(b): [TBC] |
| Width of rising limb at 50% of peak | WR50 | h | [TBC] | WR50 = 0.753 qp^−1.229 | WR50 = 0.799 / qp^1.138 | WR50 = 0.5788 qp^−1.1072 | 3(h): Table 3.3; 3(i), 5(b): [TBC] |
| Width of rising limb at 75% of peak | WR75 | h | [TBC] | WR75 = 0.558 qp^−1.088 | WR75 = 0.536 / qp^1.109 | WR75 = 0.3469 qp^−1.0538 | 3(h): Table 3.3; 3(i), 5(b): [TBC] |
| Base width of UH | TB | h | [TBC] | TB = 7.392 tp^0.524 | TB = 5.083 tp^0.733 | TB = 7.3801 tp^0.7343 | 3(h): Table 3.3; 3(i), 5(b): [TBC] |
| Design storm duration | TD | h | [TBC] | TD = 1.1 tp | TD = 1.1 tp | 1.1 tp to TB, whichever gives the higher peak | [TBC] |
| Design loss rate | — | mm/h | [TBC] | 1 (printed "1 mm/hr") | 5 (the report also gives 7.5–15; conditions [TBC]) | 1.9 (modal value) | [TBC] |
| Design base flow | — | m³/s per km² | [TBC] | 0.05 | 0.05 | 0.15 | [TBC] |
Note: relationships as printed in the CWC reports for subzones 3(h) (KP-3(h)/R-5/45/2000), 3(i) (CB/11/1985) and 5(a) and 5(b) (K&M/19/1992), read from scanned copies and checked against the page images; L, Lc and S are in the units each report defines. The subzone 3(e) report (Upper Godavari, which covers the Manjira catchment in Bidar district) was not transcribed. In the subzone 5(b) peak equation the printed term is L/S; the other subzones use L·Lc/√S, and whether L/√S was meant is to be checked against a clean copy of the report [TBC]. Some highway reports attribute these subzone 5(b) equations to the East Coast report; they are printed in the West Coast report. The subzone 3(i) report applies its relationships to catchments of 25–1,000 km², and up to 3,000 km² with judgement, so between 3,000 and 5,000 km² in that subzone the SUH is a benchmark only. Subzone by basin, to be confirmed on the index maps of the reports [TBC]: 3(i), the Kaveri basin and the upper Palar and Ponnaiyar (Bengaluru, Mysuru, Mandya, Hassan, Chamarajanagara, Kolar, and Kodagu east of the Ghats); 3(h), the Krishna basin, including the Tungabhadra, Bhima, Malaprabha and Ghataprabha, and the North Pennar headwaters (north and central Karnataka, Chitradurga and Tumakuru); 5(b), the west-flowing rivers, including the Kali, Sharavathi and Netravati (Uttara Kannada, Udupi, Dakshina Kannada and the Ghats parts of Shivamogga, Chikkamagaluru and Kodagu); 3(e), the Manjira in Bidar. No part of Karnataka lies in subzones 3(f) or 4(a) to 4(c).
Table 3E.2 — Worked example outline (layout)
| Step | Content | Clause |
|---|---|---|
| 1 | Catchment area, main stream length, length to centroid and equivalent slope, from survey or DEM | 3.11.4(a) |
| 2 | SUH parameters from Table 3E.1 and the plotted unit hydrograph | 3.11.4(a) |
| 3 | Design storm duration, point and areal 24-hour rainfall with climate factor, time distribution | 3.11.4(a), (b) |
| 4 | Effective rainfall after the design loss rate; convolution with the SUH; base flow added | 3.11.4(a) |
| 5 | 1% AEP peak compared with the HEC-HMS or SWMM peak for the existing natural condition | 3.11.4(c), (d) |
Form 3-1 — Hydrologic Calculation Summary
Supports Clauses 3.4, 3.6, 3.7, 3.8, 3.10–3.13, 3.15–3.17 of Chapter 3.
Draft form — Karnataka Stormwater Design Manual, Draft v1.0. One form per submittal. Attach the documents listed in Section H.
A. Project
Table 3F.1 — Form 3-1: project
| Field | Entry |
|---|---|
| A1. Project name and applicant | |
| A2. Location (village or ward, survey numbers, district) | |
| A3. Site area (ha) and number of points of comparison (POCs) | |
| A4. Catchment class: standard (Clause 2.11.2) or flood-sensitive (Clause 2.11.3) | |
| A5. Design Rainfall Sheet reference (Form 2-1) |
B. Method and software (Clauses 3.4, 3.11, 3.12, 3.16)
Table 3F.2 — Form 3-1: method and software
| Field | Entry |
|---|---|
| B1. Purpose of each calculation (conveyance, storage, comparison, catchment study) | |
| B2. Contributing area for each purpose (ha or km²) | |
| B3. Method used and the row of Table 3.1 that permits it | |
| B4. Reason for the choice of method | |
| B5. Software and version; engine and version for packages built on SWMM or HEC (Clause 3.16.1, 3.16.2) | |
| B6. For other software: benchmark results of Annex 3C attached (Table 3C.7) and the 5% comparison of Clause 3.16.2 | |
| B7. Runoff transform (Clause 3.11.1) | |
| B8. Computation interval Δt (h), with 0.133 Tc of the smallest sub-area and the hyetograph time step (Clause 3.11.3(a)) | |
| B9. Storage routing and channel routing methods (Clauses 3.12.1, 3.12.2) | |
| B10. Dynamic-wave routing required? If yes, which condition of Clause 3.12.4 | |
| B11. CWC SUH benchmark required (25–5,000 km², Clause 3.11.4)? Result reference | |
| B12. Continuous simulation required (Clause 3.13.1)? Record used and starting tank levels (Clause 3.13.5) | |
| B13. Calibration required (Clause 3.15.1)? Calibration report reference |
C. Soils and groundwater (Clauses 3.3.3(b), 3.7, 3.10)
Table 3F.3 — Form 3-1: soils and groundwater
| Field | Entry |
|---|---|
| C1. HSG source map, scale and lookup used (Clause 3.7.1, Annex 3A) or NEH Part 630, Ch. 7 assignment (Clause 3.7.2) | |
| C2. Infiltration tests: number, locations, depths, results (Clause 3.7.3) | |
| C3. Seasonal high water table: depth below ground and source (Clause 3.10.2) | |
| C4. Areas within 0.6 m assigned HSG D (Clause 3.10.1) | |
| C5. Disturbed pervious areas and HSG downgrade applied (Clause 3.3.3(b)) |
D. Parameters by sub-area and condition (Clauses 3.3, 3.5, 3.8, 3.9; Clause 3.17 item 4)
Table 3F.4 — Form 3-1: parameters by sub-area and condition
| Sub-area | Condition (pre / post) | Area (ha) | Impervious: roofs / paved / roads (ha) | DCIA (ha) | Disconnected (ha) | HSG | CN, AMC II | CN, AMC III (pervious part) | C and Cf (if Rational) | Tc (min) |
|---|---|---|---|---|---|---|---|---|---|---|
E. Time of concentration worksheet (Clause 3.6)
One worksheet per sub-area and condition.
Table 3F.5 — Form 3-1: time of concentration worksheet
| Segment | Flow type | Surface and n (Table 3.4) | L (m) | S (m/m) | P2 (mm) | V (m/s) | Tt (min) |
|---|---|---|---|---|---|---|---|
| 1 | Sheet | — | |||||
| 2 | Shallow concentrated | — | |||||
| 3 | Channel or pipe | — | |||||
| Tc (not less than 10 min) |
E1. Is the post-development Tc shorter than the pre-development Tc? If not, explain (Clause 3.6.6): ______
F. Rainfall and losses (Clauses 3.8.4, 3.8.5, 3.11.5, 3.12, 3.3.5)
Table 3F.6 — Form 3-1: rainfall, losses and starting levels
| Field | Entry |
|---|---|
| F1. AEPs and durations run; climate factor applied (Chapter 2) | |
| F2. AMC used for each duration (Clause 3.8.4) | |
| F3. Ia ratio for design runs; Ia = 0.05S sensitivity run made (Clause 3.8.5) | |
| F4. Peak rate factor used; if lower than 484, the Annex 3D value and the land it applies to (Clause 3.11.5) | |
| F5. Starting water level of each tank or waterbody, and its basis (Clauses 3.12.5, 3.13.5) | |
| F6. Off-site run-on: land use assumed for conveyance and for the comparison (Clause 3.3.5) | |
| F7. Incidental storage counted? If yes, the authority's acceptance (Clause 3.12.3) |
G. Departures
Table 3F.7 — Form 3-1: departures from Chapter 3
| No. | Clause departed from | Value used in place of the Chapter 3 value | Justification |
|---|---|---|---|
| 1 | |||
| 2 |
H. Attachments (Clause 3.17)
Table 3F.8 — Form 3-1: attachments
| Item | Attached (yes / no / not applicable) | Reference |
|---|---|---|
| H1. Catchment maps, pre- and post-development, with sub-areas, Tc flow paths, POCs and off-site run-on | ||
| H2. HSG map, water-table data and infiltration test results | ||
| H3. Parameter tables (Section D) and Tc worksheets (Section E) | ||
| H4. Design Rainfall Sheet (Form 2-1) and hyetographs | ||
| H5. Hydrograph tables and plots; stage–storage and stage–discharge tables; routed outflows; peak water levels | ||
| H6. Form 3-2 for each POC | ||
| H7. Calibration report (Clause 3.15) | ||
| H8. Native model input and output files (Clause 3.16.4) |
I. Statement by the responsible engineer (Clause 3.17 item 10)
I state that the methods and parameters of Chapter 3 of the Karnataka Stormwater Design Manual (Draft v1.0) have been used in this submittal, and that every departure is listed and justified in Section G.
Table 3F.9 — Form 3-1: statement by the responsible engineer
| Field | Entry |
|---|---|
| Name | |
| Qualification and registration number | |
| Organisation | |
| Signature | |
| Date |
Draft form — Karnataka Stormwater Design Manual, Draft v1.0.
Form 3-2 — Pre- vs Post-Development Comparison
Supports Clauses 3.8.5, 3.11.5 and 3.14 of Chapter 3.
Draft form — Karnataka Stormwater Design Manual, Draft v1.0. One form for each point of comparison (POC). Flows in m³/s, volumes in m³.
A. Point of comparison (Clause 3.14.2)
Table 3F.10 — Form 3-2: point of comparison
| Field | Entry |
|---|---|
| A1. POC identifier and location | |
| A2. Area draining to the POC: site (ha) and off-site run-on (ha) | |
| A3. Off-site run-on passes through site storage? (Clause 3.14.2(c)) | |
| A4. Catchment class: standard (Clause 2.11.2) or flood-sensitive (Clause 2.11.3) | |
| A5. Tailwater applied, including joint cases of Clause 2.12 (Clause 3.14.9(c)) | |
| A6. Flood-sensitive only: largest 10% AEP pre-development peak over all durations, the cap of Clause 2.11.3 (Clause 3.14.7) | |
| A7. Flood-sensitive only: 50% AEP pre-development peak at the pre-development critical duration (Clause 2.11.3) |
B. Peak flows (Clauses 3.14.7–3.14.10)
Limit: standard catchments 0.9 × Q_pre for the same AEP and duration (Clause 3.14.10(a)); flood-sensitive catchments the caps A6 (for 1% AEP) and A7 (for 50% AEP) (Clause 3.14.10(b)).
Table 3F.11 — Form 3-2: peak flows by AEP and duration
| AEP | Duration (h) | AMC | Q_pre | Q_post, uncontrolled | Q_post, routed | Limit | Met? |
|---|---|---|---|---|---|---|---|
| 50% (2-yr) | 1 | II | |||||
| 50% (2-yr) | 2 | II | |||||
| 50% (2-yr) | 3 | II | |||||
| 50% (2-yr) | 6 | II | |||||
| 50% (2-yr) | 12 | III | |||||
| 50% (2-yr) | 24 | III | |||||
| 50% (2-yr) | 48 | III | |||||
| 50% (2-yr) | 72 | III | |||||
| 10% (10-yr) | 1 | II | |||||
| 10% (10-yr) | 2 | II | |||||
| 10% (10-yr) | 3 | II | |||||
| 10% (10-yr) | 6 | II | |||||
| 10% (10-yr) | 12 | III | |||||
| 10% (10-yr) | 24 | III | |||||
| 10% (10-yr) | 48 | III | |||||
| 10% (10-yr) | 72 | III | |||||
| 1% (100-yr) | 1 | II | |||||
| 1% (100-yr) | 2 | II | |||||
| 1% (100-yr) | 3 | II | |||||
| 1% (100-yr) | 6 | II | |||||
| 1% (100-yr) | 12 | III | |||||
| 1% (100-yr) | 24 | III | |||||
| 1% (100-yr) | 48 | III | |||||
| 1% (100-yr) | 72 | III |
C. Volumes and storage (Clauses 3.14.8–3.14.10)
Table 3F.12 — Form 3-2: volumes and storage
| AEP | Governing duration (h) | Runoff volume, pre | Runoff volume, post uncontrolled | Retention volume | Detention storage required | Peak water level in storage (m) |
|---|---|---|---|---|---|---|
| 50% (2-yr) | ||||||
| 10% (10-yr) | ||||||
| 1% (100-yr) |
C1. Governing duration for storage, and the 24, 48 and 72 h results (Clause 3.14.10): ______
D. Sensitivity runs (Clauses 3.8.5, 3.14.11)
Table 3F.13 — Form 3-2: sensitivity runs
| Run | Governing storm (AEP, duration) | Change in Q_post, routed (%) | Change in required storage (%) | Retention volume or WQv governing (Clause 3.8.5(c)) |
|---|---|---|---|---|
| Ia = 0.05S | ||||
| Standard peak rate factor (only where a lower factor is used) | — |
E. Associated checks (Clause 3.14.12)
Table 3F.14 — Form 3-2: associated checks
| Check | Result | Reference in submittal |
|---|---|---|
| Drawdown times (Chapter 4) | ||
| Minimum orifice and trash screen (Chapter 4) | ||
| Emergency spillway (Chapter 4) | ||
| Outfall-closed storage check (Chapter 5) | ||
| Downstream analysis (Chapter 5) |
F. Statement by the responsible engineer
I state that this comparison has been made by the procedure of Clause 3.14, with the same design storms in the pre- and post-development runs, and that no runoff has been diverted from one natural catchment to another to meet the criterion (Clause 3.14.2(b)).
Table 3F.15 — Form 3-2: statement by the responsible engineer
| Field | Entry |
|---|---|
| Name | |
| Qualification and registration number | |
| Signature | |
| Date |
Draft form — Karnataka Stormwater Design Manual, Draft v1.0.