Draft v1.0 prepared by NEER. Not adopted by the Government of Karnataka, and has no legal force. About this draft

Chapter 11Basin and City Stormwater Master Plans


11.1 Purpose and scope

11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.

11.1.2 A BSMP shall:

  • (a) map flood hazard for the basin under existing and future conditions;
  • (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
  • (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
  • (d) reserve land for regional storage, kere and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
  • (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
  • (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).

11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.

Commentary. Bengaluru is the only Karnataka city found with a published drainage master plan. The Master Plan for Remodeling of Storm Water Drains in Eight Zones of BBMP (STUP Consultants, October 2010) was prepared "as per CPHEEO norms" from IMD rainfall of 1976–2008. It adopted a 2-year return period for most locations and gave 5-year intensities of 85.0 mm/h at 15 minutes and 52.3 mm/h at 60 minutes, and its IDF table is internally inconsistent: the 5-minute, 5-year intensity (124.9 mm/h) exceeds the 10-year value (119.4 mm/h). CAG found that the plan identified only primary and secondary drains, made no provision for buffer zones, and considered only rainfall although large unassessed sewage flows ran in the drains (Report No. 2 of 2021). Practice has since moved to a 5-year return period: a drain calculation filed by BBMP's Engineer-in-Chief before the NGT in 2024 uses "5 year return period (Urban Areas) at 70mm" per hour, but it is one drain's calculation, and no circular fixing a city-wide standard was found. The World Bank's Karnataka Water Security and Resilience Program (P506272; an IBRD loan of US$426 million, approved in June 2025) provides for integrated flood management plans for Bengaluru's four sub-catchments, lining of a further 173 km of drains with about 80 km more to be lined or rehabilitated, and zonal flood-management performance scores across the 860 km network (World Bank Technical Assessment, 2025). No stormwater master plan or design return period was found for Mangaluru, Mysuru, Hubballi–Dharwad, Belagavi or Kalaburagi. A site-level manual cannot fix basin-level problems: lost tank storage, outfalls blocked by tides or sand bars, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:

  • Denver's Mile High Flood District prepares major drainageway master plans that set regional facilities and release rates.
  • The Kansas City APWA criteria rest on regional watershed studies (MARC).
  • England's Surface Water Management Plans (Defra, Surface Water Management Plan Technical Guidance, 2010) set a phased method of preparation, risk assessment, options and implementation.
  • Malaysia's MSMA requires drainage master plans for urban areas.

This chapter adapts that method to Karnataka's kere, kunte and katte cascades and the rajakaluves that link them, Bengaluru's valley systems, a monsoon season from June to October preceded in the south interior by heavy May storms, and outfalls held up by full tanks downstream, by estuary mouths and tides on the coast, and by rivers swollen by reservoir releases in the north.


11.2 Definitions

Term Meaning in this Manual
Basin The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3.
Basin Stormwater Master Plan (BSMP) The plan for one basin prepared under this chapter.
Lead Authority The body responsible for preparing a BSMP (Clause 11.4).
Level of service (LoS) The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6).
Flood hazard map A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario.
Regional facility A storage, conveyance or outfall work serving more than one development, identified in a BSMP.
Capital Improvement Programme (CIP) The ranked, costed list of works in a BSMP (Clause 11.8.4).

11.3 Planning unit: the basin, not the ward

11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.

11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.

11.3.3 For the largest urban areas, the basins are at least the following:

  • Bengaluru: the Koramangala–Challaghatta valley, draining through Bellandur and Varthur lakes to the Dakshina Pinakini; the Hebbal valley; and the Vrishabhavathi valley. Each is delineated with its tank chains and rajakaluves across the five City Corporations and into the BDA and BMRDA areas beyond them, building on the 633 sub-catchments already mapped for the city's drains;
  • Mangaluru: the catchments draining to the Netravati–Gurupura estuary, with the estuary mouth between the Bengre spit and Ullal as the outfall condition, and the catchments draining directly to the sea; and
  • Udupi: the catchments draining to the Swarna–Sita estuary at Malpe.

Other Tier A bodies shall define their basins in the first BSMP. These include Mysuru, with the catchments of its lakes (for example Kukkarahalli, Karanji and Lingambudhi), Hubballi–Dharwad, Belagavi and Kalaburagi. Bodies on dam-regulated estuaries, such as Karwar on the Kali and Honnavar on the Sharavathi, and towns on the Krishna, Malaprabha, Ghataprabha and Bhima, are expected to need a BSMP under Clause 11.4.2(c). Every basin that drains to a tank takes the tank's water level as its outfall condition (Chapter 5). Where WRD or the dam operator has a design flood or release schedule for a river that a city lies on, the BSMP shall take its river boundary conditions from it.

Basin Stormwater Master Plan (BSMP) — process and links to site design 1. Basin set-up Delineate by basin, not ward (Cl. 11.3) Lead Authority + partners 2. Data DEM, drains, tanks, tides, flood marks (Cl. 11.5) 3. Model 1D–2D, 24–72 h storms, tide, continuous sim. calibrate to past floods 4. Gap vs LoS Scenarios: existing, future ± site controls, climate (Cl. 11.6–11.7) 5. Options Restore tanks first, then regional storage, conveyance, outfalls 6. Outputs (Cl. 11.8.4) — approved by State Stormwater Technical Committee • Flood hazard maps 10% / 1% / 0.2% AEP • Flood-sensitive catchments, basin release rates • Regional facility sites and fee-in-lieu rate • Capital Improvement Programme, ranked • Pre-monsoon maintenance programme • Monitoring network • Open data + public map viewer • Annual report, pre-monsoon Land-use plan Statutory master plan: reserve storage sites, flow paths, hazard zoning (Cl. 11.9) Site design Ch 4 release rates, regional detention and fee-in-lieu (Cl. 4.13, 4.5.6) Floors and setbacks 1% AEP future-with-plan map sets floor levels (Ch 6) and setbacks (Ch 7) Public works CIP funds: ULB, State, Union; O&M and desilting (Ch 10) Review every 10 yr, after a >1% AEP event, or plan revision (Cl. 11.11)

Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.

Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. Bengaluru's drains were not laid out by ward: most are the old supply and surplus courses of its tank chains. BBMP told the NGT that the city's storm water drains "were not planned for flood water management but are erstwhile irrigation channels" (BBMP compliance report, 2021). The city lies on four valleys, Hebbal, Koramangala, Challaghatta and Vrishabhavathi (CAG 2021), whose drains now run across five City Corporations and out into the BDA and BMRDA areas. Ownership is split along other lines again: the land under the drains is Revenue land, construction and maintenance sit with the GBA and the City Corporations, sewage in the drains is BWSSB's, and the lakes are held by the GBA, BDA, the Forest Department and Minor Irrigation, with KTCDA as regulator; the World Bank found that the drain and lake departments "largely work in silos" (World Bank 2025). CAG also found that BDA's master plan and BBMP's master plan of drains classified the same drains differently. This clause makes the basin the planning unit. It also requires the rajakaluves that join one tank to the next to be treated as links, because a change to one tank's kodi (surplus weir) or one drain's section changes water levels in every tank below it.


11.4 Who prepares, and when

11.4.1 Lead Authority.

  • For a basin wholly within one City Corporation of Greater Bengaluru, or within one other Municipal Corporation: the Corporation.
  • For a Bengaluru basin that crosses City Corporation boundaries, including the Koramangala–Challaghatta, Hebbal and Vrishabhavathi valleys: the GBA, which plans storm water drain works that cut across City Corporations, with the City Corporations, BDA and the BMRDA local planning authorities for the parts of the basin beyond the GBA area, BWSSB for sewage in the drains, and KSNDMC for gauges and flood modelling as partners.
  • For a basin draining to a chain of tanks held by the Minor Irrigation and Ground Water Development Department outside a Municipal Corporation: that Department, with the local bodies as partners.
  • For a basin whose outfall is a river reach regulated by WRD dams or barrages (for example towns on the Krishna, Malaprabha, Ghataprabha or Bhima): WRD, with the local bodies as partners.
  • For other basins that cross local-body boundaries: the Urban Development Authority for the area, or where there is none the Municipal Corporation or council with the largest share of the basin, with the other local bodies as partners.
  • In Tier B bodies: the Lead Authority is named by UDD. Basins draining to a common kere cascade or river reach may be grouped into one district-level plan.

The Minor Irrigation and Ground Water Development Department shall be a partner in every BSMP that includes a tank under its control, and KTCDA shall be consulted on every BSMP that proposes works in a tank or its buffer.

WRD shall be a partner in every BSMP that includes a river, canal or tank under its control.

11.4.2 When a BSMP is required.

  • (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
  • (b) A BSMP is required before:
    • any regional detention or fee-in-lieu is accepted under Clause 4.13;
    • a fee held under Clause 4.5.6.3 is spent; and
    • a basin-specific release rate is applied under Clause 11.8.3.
  • (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.

11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.


11.5 Data and surveys

11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:

Table 11.1 — Minimum data and surveys for a BSMP

Data Minimum requirement
Terrain Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum
Drain network Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm
Waterbodies Survey of every tank, kere, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment
Rivers and canals Cross-sections at no more than 200 m spacing and at every structure
Outfalls and coast Tidal datums and surge values (Annex 5A); mouth and sand-bar behaviour; gates and pumps
Rainfall and levels All available rain gauges (IMD, the KSNDMC telemetric rain gauges, weather stations and drain water-level sensors, and the UAS Bangalore agromet station at GKVK) and water-level records, including those for the 2017, 2019, 2022 and 2024 events
Flood evidence Surveyed flood marks and mapped flood extents from past events, including public reports
Land use Existing land use and imperviousness; future land use from the statutory master plan
Soils and groundwater HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones
Sewer interaction Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots

Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the flat coastal plain a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The 2017, 2019, 2022 and 2024 events are the best calibration data Karnataka has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.


11.6 Levels of service

11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.

Table 11.2 — Minimum levels of service

Element Minimum level of service
Minor system The design AEP of Chapter 6 (Table 6.1)
Habitable buildings No flooding above floor level in the 1% AEP (100-yr) event
Critical facilities (hospitals, emergency services, substations, water and sewage plants) No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event
Evacuation routes and arterial roads Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event
Ponding drain time Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event
Tank and kere storage No net loss of flood storage below the MWL in the basin, measured against the earliest available survey
Outfalls Functioning under the joint and outfall-closed cases of Chapter 5

Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects how much tank storage Karnataka had and how fast it has gone. Citing IISc, CAG records 1,452 water bodies holding 35 TMC in the Bengaluru area in the early 1800s, against 194 holding 5 TMC by 2016, with about 1.2 TMC usable after siltation; 18 of the 210 lakes in BBMP's charge were disused (Report No. 2 of 2021). A committee of the State Legislature reported about 11,000 acres of lake land encroached across 1,545 lakes in Bengaluru Urban and Rural districts (interim findings, January 2016, as reported). The first Census of Water Bodies counted 17,015 tanks in the State but reported no encroached urban water body (Ministry of Jal Shakti, reference year 2017-18), so a census entry is no evidence that a tank is intact. Karnataka Act No. 19 of 2026 now allows roads, bridges, pipelines and treatment plants between the FTL and the MWL of a tank provided its original capacity is not reduced (KTCDA Act, s.12(2)); the rule in Table 11.2 gives that proviso a measurable test.


11.7 Modelling and scenarios

11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:

  • the minor system;
  • the major (overland) system;
  • rivers, canals and tanks; and
  • the outfalls.

Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.

11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.

11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.

11.7.4 Scenarios. Each BSMP shall model at least:

  • (a) Existing: existing land use, network, tanks and outfalls;
  • (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
  • (c) Future, controlled: future land use with the site controls of Chapter 4;
  • (d) Future, with plan: scenario (c) plus the works of the CIP; and
  • (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8 and the sea-level allowance of Chapter 5.

11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the 2017, 2019, 2022 and 2024 events where data exist.

Figure 11.2 — BSMP model schematic Schematic plan of a basin model: design rainfall over sub-catchments; two tanks in cascade with surplus course; a 1D drain network linked to a 2D surface grid; a river or canal reach with an inter-basin link; an outfall with a flap gate and pumps; and a tidal or river level boundary. Numbered notes on the right explain each element. BSMP model: elements required by Clause 11.7 (schematic, not to scale) Sea / receiving water 1 S1 S2 S3 2 Upper tank Lower tank start level start level 3 2D surface 5 4 River / canal (1D) 6 Inter-basin link Gate Pumps 7 8 1 Design rainfall Ch. 2 storms incl. 24, 48, 72 h; 50%, 10%, 1%, 0.2% AEP; areal reduction (Cl. 2.7.3, 11.7.2) 2 Sub-catchments Runoff by Ch. 3 methods; land use for each scenario (a)–(e) of Cl. 11.7.4 3 Tanks and ponds Surveyed FTL, MWL, stage–storage, sluices, surplus weirs (Cl. 11.5.1); start level from continuous run (Cl. 3.13.5, 11.7.3) 4 1D drain network Minor system: drains, pipes, culverts with surveyed inverts and silt (Cl. 11.5.1) 5 2D surface Major (overland) system on the DEM, 0.15 m RMSE or better; exchange with 1D at inlets and manholes 6 Rivers and canals (1D) Sections ≤ 200 m apart and at every structure; diversions between basins mapped (Cl. 11.3.2) 7 Outfall Flap or tide gates and pumps; joint and outfall-closed cases of Ch. 5 8 Downstream boundary Tide (MHWS; HAT + surge + sea-level allowance) or river level, per Ch. 5 Calibrate and validate with at least two major past flood events where data exist (Cl. 11.7.5).

Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and keres with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.

Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).


11.8 Options, outputs and the Capital Improvement Programme

11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:

  1. Protect and restore storage: keres, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
  2. Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
  3. Conveyance upgrades to drains, canals and culverts;
  4. Outfall works: gates, pumps, and mouth and sand-bar management;
  5. Property-level protection where works cannot reach the level of service; and
  6. Non-structural measures: flood warning (for example the KSNDMC urban flood model and Varuna Mitra alerts for Bengaluru), flood-hazard zoning, emergency planning and public information.

11.8.2 Option assessment. Each option shall be assessed for:

  • reduction in flood risk (buildings and people flooded; expected annual damage);
  • capital and 30-year maintenance cost;
  • land required;
  • effect on groundwater recharge and saline intrusion (Chapter 8);
  • effect on downstream basins and the rajakaluve network; and
  • who benefits.

11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.

11.8.4 Outputs. Each BSMP shall produce:

  • (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
  • (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
  • (c) regional facility sites, with storage volumes, land needs and the sites they serve;
  • (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
  • (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
  • (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
  • (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.

Commentary. Restoring storage comes first because Karnataka already has a regional storage system: its kere, kunte and katte cascades, in which each tank's kodi spills to the next. In Bengaluru, Bellandur alone receives three chains of lakes from a catchment of about 148 km² and spills to Varthur (secondary source). The 2010 drain master plan itself proposed detention ponds on institutional, defence and park land and retention basins at drain confluences (STUP 2010), and the World Bank programme includes nature-based solutions in all eight zones (World Bank 2025). Conveyance upgrades on their own move water faster to an outfall that may be tide-locked. Lined drains also cut recharge in a State that depends on groundwater: 35 of 176 taluks were classed as over-exploited in 2008–09 (Karnataka SAPCC 2013). Bengaluru lined 491 km of drains between 2005 and 2012 and plans a further 173 km under the World Bank programme (World Bank 2025), while the NGT has directed "No further channelization and concretization of Rajakaluves" in the Bellandur case (order of 18 December 2019, as quoted by BBMP). BBMP replied that it avoids concreting drains wider than 4 m and uses U-drains with percolation openings in narrower ones. No published data were found for this Manual on groundwater levels near Bengaluru's tanks and valleys, or on saline intrusion along the coast. Deeper or lined drains can lower or cut off the water table, which is why groundwater recharge is an assessment criterion. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.


11.9 Integration with land-use planning

11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the Master Plans and zoning regulations made under the Karnataka Town and Country Planning Act 1961, including the Revised Master Plan for Bengaluru and its successor, the plans of the BMRDA local planning authorities, and those of the Urban Development Authorities and other planning authorities elsewhere. In particular:

  • (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
  • (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
  • (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
  • (d) the parks and open spaces of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.

11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.

Commentary. Karnataka has no numeric flood-plain rule. In Bengaluru the RMP 2015 zoning regulations bar fresh development permissions in the valley zone, allowing only treatment plants, and roads, drains, culverts and bridges that do not obstruct the water course (Regulation 4.12.2(ii)). UDD 235 MNJ 2025(E) of 5 January 2026 bars basements "in the flood prone areas/low lying areas as notified by the competent authority", but no method for that notification has been set. Outside the valley zone, the Bengaluru building bye-laws require only a plinth of at least 0.45 m, set "so that adequate drainage from the site is assured" (Bye-law 19.1). CAG also found that drains shown as primary and secondary on BBMP's map appeared as secondary and tertiary in the draft RMP 2031 (Report No. 2 of 2021). A BSMP gives these provisions the 1% AEP map they need, and one drain classification for planners and engineers to share. Using park and open space land as storage or flow path has no direct precedent; this Manual adopts it because in Bengaluru the valley land and the lake buffer within a layout may already be counted towards its reservation of parks and open spaces (RMP 2015 Zoning Regulations, Regulation 4.12.2(ii), subject to section 17 of the KTCP Act 1961 and section 32 of the BDA Act 1976); because that land then serves as a park, storage placed in it must stay usable as one. Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.


11.10 Consultation and publication

11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.

11.10.2 After approval, the following shall be published as open data:

  • the model files;
  • the flood hazard maps;
  • the data of Clause 11.5.1, except security-sensitive asset details; and
  • the CIP.

They shall also be shown on a public map viewer.

Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.


11.11 Approval, review and reporting

11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.

11.11.2 Review. Each BSMP shall be reviewed:

  • every 10 years;
  • within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
  • when the statutory land-use plan is revised.

11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each monsoon (by 30 April). The report shall show:

  • CIP progress;
  • the fee-in-lieu ledger (Clause 4.13.4);
  • maintenance completed; and
  • any flooding against the levels of service.

11.12 Interim arrangements

11.12.1 Until a BSMP is approved for a basin:

  • (a) all site criteria of Chapters 4 to 8 apply in full;
  • (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
  • (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
  • (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.

References (chapter)

Annexes and forms

Annex / Form Content
11A BSMP terms of reference template
11B Basin lists and boundaries for Tier A bodies
11C Depth–damage curves for Karnataka building types
11D BSMP data and model publication standard
Form 11-1 Annual implementation report