Draft v1.0 prepared by NEER. Not adopted by the Government of Keralam, the Government of Puducherry (for Mahé) or the Lakshadweep Administration, and has no legal force. About this draft

Chapter 11Basin and City Stormwater Master Plans


11.1 Purpose and scope

11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.

11.1.2 A BSMP shall:

  • (a) map flood hazard for the basin under existing and future conditions;
  • (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
  • (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
  • (d) reserve land for regional storage, kulam and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
  • (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
  • (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).

11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.

Commentary. CAG found that Keralam had river master plans for only one of its 44 rivers (the Chaliyar), that flood works worth ₹178.99 crore in 2014–19 were done without being linked to a comprehensive plan, and that the flood plains of the State have not been identified or demarcated (CAG Report No. 6 of 2021, paras 2.2 and 2.3). No Keralam city has a published stormwater drainage master plan: Kochi had none and no drainage map of its primary and secondary networks (CAG 2025). Work now under way is project-based: a 74-ward stormwater DPR for Kochi tendered in January 2025 and the KMRL canal scheme (IURWTS). A site-level manual cannot fix basin-level problems: lost tank storage, outfalls blocked by tides or sand bars, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:

  • Denver's Mile High Flood District prepares major drainageway master plans that set regional facilities and release rates.
  • The Kansas City APWA criteria rest on regional watershed studies (MARC).
  • England's Surface Water Management Plans (Defra, Surface Water Management Plan Technical Guidance, 2010) set a phased method of preparation, risk assessment, options and implementation.
  • Malaysia's MSMA requires drainage master plans for urban areas.

This chapter adapts that method to Keralam's backwaters and kayals, Kuttanad polders, paddy wetlands and kulams, two monsoons with the SW monsoon dominant, and tidal and sand-bar outfalls.


11.2 Definitions

Term Meaning in this Manual
Basin The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3.
Basin Stormwater Master Plan (BSMP) The plan for one basin prepared under this chapter.
Lead Authority The body responsible for preparing a BSMP (Clause 11.4).
Level of service (LoS) The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6).
Flood hazard map A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario.
Regional facility A storage, conveyance or outfall work serving more than one development, identified in a BSMP.
Capital Improvement Programme (CIP) The ranked, costed list of works in a BSMP (Clause 11.8.4).

11.3 Planning unit: the basin, not the ward

11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.

11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.

11.3.3 For the three largest urban areas, the basins are at least the following:

  • Kochi: the Kochi canal network draining to the Vembanad backwaters (the Edappally, Chilavannoor, Perandoor, Thevara, Market and Konthuruthy canal catchments), and the lower Periyar reach that receives drainage from the Aluva–Nedumbassery area, including the Chengalthodu;
  • Thiruvananthapuram: the Amayizhanjan thodu – Akkulam basin, with its outfall through the Veli pozhi; and the Karamana basin;
  • Kozhikode: the Kallai basin and the Korapuzha basin, with the Canoli canal treated as linking them; and
  • the West Coast Canal reaches (the Parvathy Puthanar, the T.S. canal and the Canoli canal), treated as linking the basins they cross.

Other Tier A bodies shall define their basins in the first BSMP. The basins include the Ashtamudi catchment for Kollam and the kole lands and Kanoli canal catchment for Thrissur. Bodies that drain through Kuttanad to southern Vembanad and the Thottappally spillway (the lower Pamba, Achankovil, Manimala and Meenachil reaches), such as Alappuzha, are expected to need a BSMP under Clause 11.4.2(c). Where the Irrigation Department has a river basin plan for a river that a city lies on (for example the Periyar, Chalakudy or Pamba), the BSMP shall take its river boundary conditions from that plan.

Basin Stormwater Master Plan (BSMP) — process and links to site design 1. Basin set-up Delineate by basin, not ward (Cl. 11.3) Lead Authority + partners 2. Data DEM, drains, tanks, tides, flood marks (Cl. 11.5) 3. Model 1D–2D, 24–72 h storms, tide, continuous sim. calibrate to past floods 4. Gap vs LoS Scenarios: existing, future ± site controls, climate (Cl. 11.6–11.7) 5. Options Restore tanks first, then regional storage, conveyance, outfalls 6. Outputs (Cl. 11.8.4) — approved by State Stormwater Technical Committee • Flood hazard maps 10% / 1% / 0.2% AEP • Flood-sensitive catchments, basin release rates • Regional facility sites and fee-in-lieu rate • Capital Improvement Programme, ranked • Pre-monsoon maintenance programme • Monitoring network • Open data + public map viewer • Annual report, pre-monsoon Land-use plan Statutory master plan: reserve storage sites, flow paths, hazard zoning (Cl. 11.9) Site design Ch 4 release rates, regional detention and fee-in-lieu (Cl. 4.13, 4.5.6) Floors and setbacks 1% AEP future-with-plan map sets floor levels (Ch 6) and setbacks (Ch 7) Public works CIP funds: ULB, State, Union; O&M and desilting (Ch 10) Review every 10 yr, after a >1% AEP event, or plan revision (Cl. 11.11)

Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.

Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. CAG found two drains in Keralam that failed at the next reach: in Thiruvananthapuram a new drain was connected to a secondary drain with no outlet instead of the Thettiyar thodu, and in Kozhikode a drain widened from 40 cm to 1.5 m kept a 40 cm last 200 m through private land (CAG 2025, Chapter IV). In Kochi, canals are owned by the Irrigation Department and drains by the Corporation, and the High Court has had to direct the two to work to one cleaning calendar (WP(C) 23911/2018). This clause makes the basin the planning unit. It also requires the West Coast Canal reaches to be treated as links, because they connect the outfalls of several basins and a decision in one basin changes water levels in the others.


11.4 Who prepares, and when

11.4.1 Lead Authority.

  • For a basin wholly within one Municipal Corporation: the Corporation.
  • For a basin in the Kochi region that crosses local-body boundaries: GCDA, with the Kochi Corporation, the other local bodies and the Irrigation Department as partners.
  • For other basins that cross local-body boundaries: the Municipal Corporation with the largest share of the basin, with the other local bodies, the LSGD Planning Wing (District Town Planner) and the Irrigation Department as partners.
  • For basins draining through Kuttanad, or to an outlet that the Irrigation Department operates (the Thottappally spillway, the Thanneermukkom barrage or a pozhi cut under its orders): the Irrigation Department, with the local bodies.
  • In Tier B bodies: the Lead Authority is named by the LSGD Planning Wing. Basins draining to a common kayal, canal or river reach may be grouped into one district-level plan.

The Irrigation Department shall be a partner in every BSMP that includes a river, canal or tank under its control.

11.4.2 When a BSMP is required.

  • (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
  • (b) A BSMP is required before:
    • any regional detention or fee-in-lieu is accepted under Clause 4.13;
    • a fee held under Clause 4.5.6.3 is spent; and
    • a basin-specific release rate is applied under Clause 11.8.3.
  • (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.

11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.


11.5 Data and surveys

11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:

Table 11.1 — Minimum data and surveys for a BSMP

Data Minimum requirement
Terrain Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum
Drain network Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm
Waterbodies Survey of every tank, kulam, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment
Rivers and canals Cross-sections at no more than 200 m spacing and at every structure
Outfalls and coast Tidal datums and surge values (Annex 5A); mouth and sand-bar behaviour; gates and pumps
Rainfall and levels All available rain gauges (IMD, the Irrigation Department (Kerala-WRIS) and CUSAT-ACARR) and water-level records, including those for the 2018, 2019, 2023 and 2024 events
Flood evidence Surveyed flood marks and mapped flood extents from past events, including public reports
Land use Existing land use and imperviousness; future land use from the statutory master plan
Soils and groundwater HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones
Sewer interaction Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots

Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the flat coastal plain a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The 2018, 2019, 2023 and 2024 events are the best calibration data Keralam has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.


11.6 Levels of service

11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.

Table 11.2 — Minimum levels of service

Element Minimum level of service
Minor system The design AEP of Chapter 6 (Table 6.1)
Habitable buildings No flooding above floor level in the 1% AEP (100-yr) event
Critical facilities (hospitals, emergency services, substations, water and sewage plants) No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event
Evacuation routes and arterial roads Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event
Ponding drain time Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event
Tank and kulam storage No net loss of flood storage below the MWL in the basin, measured against the earliest available survey
Outfalls Functioning under the joint and outfall-closed cases of Chapter 5

Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects the loss of Vembanad's storage: its water-holding capacity is estimated to have fallen from 2.45 to 0.56 km³ (NCESS, as reported) or from 2,617.5 to 384.7 million m³ (KUFOS, as reported), and in August 2018 the lake absorbed only about 0.6 of the roughly 1.63 billion m³ that flowed into it (CWC 2018, as reported). In the Periyar basin, water bodies shrank by about 17% between 1985 and 2015 (CAG Report No. 6 of 2021, para 4.1).


11.7 Modelling and scenarios

11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:

  • the minor system;
  • the major (overland) system;
  • rivers, canals and tanks; and
  • the outfalls.

Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.

11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.

11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.

11.7.4 Scenarios. Each BSMP shall model at least:

  • (a) Existing: existing land use, network, tanks and outfalls;
  • (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
  • (c) Future, controlled: future land use with the site controls of Chapter 4;
  • (d) Future, with plan: scenario (c) plus the works of the CIP; and
  • (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8 and the sea-level allowance of Chapter 5.

11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the 2018, 2019, 2023 and 2024 events where data exist.

Figure 11.2 — BSMP model schematic Schematic plan of a basin model: design rainfall over sub-catchments; two tanks in cascade with surplus course; a 1D drain network linked to a 2D surface grid; a river or canal reach with an inter-basin link; an outfall with a flap gate and pumps; and a tidal or river level boundary. Numbered notes on the right explain each element. BSMP model: elements required by Clause 11.7 (schematic, not to scale) Sea / receiving water 1 S1 S2 S3 2 Upper tank Lower tank start level start level 3 2D surface 5 4 River / canal (1D) 6 Inter-basin link Gate Pumps 7 8 1 Design rainfall Ch. 2 storms incl. 24, 48, 72 h; 50%, 10%, 1%, 0.2% AEP; areal reduction (Cl. 2.7.3, 11.7.2) 2 Sub-catchments Runoff by Ch. 3 methods; land use for each scenario (a)–(e) of Cl. 11.7.4 3 Tanks and ponds Surveyed FTL, MWL, stage–storage, sluices, surplus weirs (Cl. 11.5.1); start level from continuous run (Cl. 3.13.5, 11.7.3) 4 1D drain network Minor system: drains, pipes, culverts with surveyed inverts and silt (Cl. 11.5.1) 5 2D surface Major (overland) system on the DEM, 0.15 m RMSE or better; exchange with 1D at inlets and manholes 6 Rivers and canals (1D) Sections ≤ 200 m apart and at every structure; diversions between basins mapped (Cl. 11.3.2) 7 Outfall Flap or tide gates and pumps; joint and outfall-closed cases of Ch. 5 8 Downstream boundary Tide (MHWS; HAT + surge + sea-level allowance) or river level, per Ch. 5 Calibrate and validate with at least two major past flood events where data exist (Cl. 11.7.5).

Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and kulams with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.

Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).


11.8 Options, outputs and the Capital Improvement Programme

11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:

  1. Protect and restore storage: kulams, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
  2. Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
  3. Conveyance upgrades to drains, canals and culverts;
  4. Outfall works: gates, pumps, and mouth and sand-bar management;
  5. Property-level protection where works cannot reach the level of service; and
  6. Non-structural measures: flood warning (for example the CWRDM flood-forecasting project under G.O.(Rt) No. 623/2024/DMD), flood-hazard zoning, emergency planning and public information.

11.8.2 Option assessment. Each option shall be assessed for:

  • reduction in flood risk (buildings and people flooded; expected annual damage);
  • capital and 30-year maintenance cost;
  • land required;
  • effect on groundwater recharge and saline intrusion (Chapter 8);
  • effect on downstream basins and the West Coast Canal; and
  • who benefits.

11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.

11.8.4 Outputs. Each BSMP shall produce:

  • (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
  • (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
  • (c) regional facility sites, with storage volumes, land needs and the sites they serve;
  • (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
  • (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
  • (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
  • (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.

Commentary. Restoring storage comes first because Keralam already has a regional storage system: the backwaters and kayals, the paddy wetlands and the kulams. The 2018 PDNA called for "room for the river" and for clearing and protecting traditional and natural drainage. Conveyance upgrades on their own move water faster to an outfall that may be tide-locked. In the coastal lowlands and Kuttanad the water table is close to the surface (in August 2021, 73% of observation wells in Alappuzha district were less than 2 m below ground; CGWB 2022), and the Thanneermukkom barrage and Thottappally spillway shutters are operated to keep saline water out of the paddy polders. Deeper drains can lower the water table and let saline water in, which is why groundwater and saline intrusion are assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.


11.9 Integration with land-use planning

11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: Master Plans, Detailed Town Planning Schemes and Interim Development Orders under the Kerala Town and Country Planning Act 2016. In particular:

  • (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
  • (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
  • (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
  • (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.

11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.

Commentary. The Kerala Town and Country Planning Act 2016 already requires a Master Plan to address natural hazard prone areas, including areas of significant flood flow or inundation, and drainage (s.34(3)). Since October 2025, KMBR/KPBR Rule 22(3) bars construction on land shown as floodable in a Master Plan, Detailed Town Planning Scheme or Interim Development Order. The Thiruvananthapuram Master Plan 2040 has Water Body and Buffer-Water Body zones. CAG (2021) found that Keralam has no flood-plain zoning law and that the State flood-hazard map is at 1:50,000. A BSMP gives Master Plans the 1% AEP map that these provisions need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because Keralam development already leaves land open that can serve this purpose: KMBR/KPBR 2019 Rule 26(8) keeps at least 50% of a plot's open space unpaved or permeable, and section 27A of the Kerala Conservation of Paddy Land and Wetland Act 2008 sets apart 10% of a converted parcel larger than 20.2 ares for water conservancy measures. Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.


11.10 Consultation and publication

11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.

11.10.2 After approval, the following shall be published as open data:

  • the model files;
  • the flood hazard maps;
  • the data of Clause 11.5.1, except security-sensitive asset details; and
  • the CIP.

They shall also be shown on a public map viewer.

Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.


11.11 Approval, review and reporting

11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.

11.11.2 Review. Each BSMP shall be reviewed:

  • every 10 years;
  • within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
  • when the statutory land-use plan is revised.

11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each SW monsoon (by 15 May). The report shall show:

  • CIP progress;
  • the fee-in-lieu ledger (Clause 4.13.4);
  • maintenance completed; and
  • any flooding against the levels of service.

11.12 Interim arrangements

11.12.1 Until a BSMP is approved for a basin:

  • (a) all site criteria of Chapters 4 to 8 apply in full;
  • (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
  • (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
  • (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.

References (chapter)

Annexes and forms

Annex / Form Content
11A BSMP terms of reference template
11B Basin lists and boundaries for Tier A bodies
11C Depth–damage curves for Keralam building types
11D BSMP data and model publication standard
Form 11-1 Annual implementation report