Draft v1.0 prepared by NEER. Not adopted by the Government of Keralam, the Government of Puducherry (for Mahé) or the Lakshadweep Administration, and has no legal force. About this draft

Chapter 1Policy, Applicability and Adoption


1.1 Purpose and objectives

1.1.1 This Manual sets the minimum standards for the planning, design, construction, operation and maintenance of stormwater systems in Keralam. It applies to private development and to public works, as set out in Clause 1.5.

1.1.2 The Manual has the following objectives:

  • (a) to make stormwater management a condition of development approval, so that new development and redevelopment do not increase flood peaks or runoff volumes downstream;
  • (b) to retain frequent rainfall on site, so that groundwater recharge is sustained and pollutant loads are reduced;
  • (c) to size storage for the long-duration multi-day south-west monsoon storms of June–September, as well as for short-duration intensities;
  • (d) to design outfalls for tidal and river tailwater, including the case where the outfall is closed;
  • (e) to protect tanks (kulams), marshes, rivers, supply channels and surplus courses as part of the drainage system;
  • (f) to give every element of the drainage network a safe overland path for the 1% AEP (100-yr) storm;
  • (g) to make design inputs, approvals and facility records public, so that designs can be checked and repeated; and
  • (h) to make sure that facilities, once built, are maintained and remain effective.

1.1.3 This Manual does not replace the rainwater harvesting (RWH) mandate, the Kerala Municipality Building Rules, 2019 and Kerala Panchayat Building Rules, 2019 (KMBR/KPBR 2019), or the statutes on waterbodies. It adds runoff control requirements to them (Clause 1.8).

Commentary. Keralam had its worst floods since 1924 in August 2018. Rainfall over 1–19 August was 758.6 mm against a normal of 287.6 mm (+164%), 341 landslides occurred in 10 districts, and 433 lives were lost between 22 May and 29 August (PDNA, 2018). The CAG performance audit of flood preparedness in Kerala (Report No. 6 of 2021) found:

  • no flood plain zoning law, and flood plains not identified or demarcated (para 2.3);
  • a flood hazard map only at 1:50,000, not prepared to the CWC criterion (para 2.4);
  • 913 encroachments of water bodies in the districts audited, 832 of them on the Kanoli canal (Appendix 2.1); and
  • built-up area in the Periyar basin up about 450% between 1985 and 2015; with 1985 land use, the modelled 2018 flood depth at Neeleswaram fell from 12.32 m to 10.03 m (para 4.1).

Floods and landslides followed in 2019, 2020, 2021 and 2024; the Wayanad landslides of 30 July 2024 came after 586 mm of rain in two days at Kalladi (Kerala-WRIS). City streets also flood in short storms: IMD confirmed 103 mm in one hour at Kalamassery, Kochi, on 28 May 2024. Three failure modes recur: undersized drains; lost storage in backwaters, paddy wetlands and kulams; and outfalls held up by spring tides, high backwater levels or sand bars (PDNA, 2018). Objectives (b) to (e) address the last two, which a drain-sizing manual alone cannot fix.

No national instrument requires on-site detention. CPHEEO (2019) is advisory and describes peak control only as typical practice. NDMA (2010) says detention and retention "will" be included but gives no sizing rule. MBBL 2016 and KMBR/KPBR 2019 mandate RWH only. Objective (a) is therefore the main new step this Manual takes.


1.2 Stormwater management hierarchy

1.2.1 Every development to which Chapter 4 applies shall consider stormwater measures in the following order. A designer shall not use a lower measure in place of a higher one that is practicable on the site.

  1. Preserve — keep or restore natural drainage features, tanks, wetlands, permeable soils, trees and overland flow paths (Chapter 7).
  2. Retain — hold the runoff from the retention depth of Annex 2E on site, by infiltration, reuse or evapotranspiration (Chapters 4 and 8).
  3. Detain — store larger storms temporarily and release them at or below the rates in Chapter 4, checked against downstream and tailwater conditions (Chapters 4 and 5).
  4. Convey — carry the remaining flow safely in the minor system, and the 1% AEP flow in the major system (Chapters 6 and 9).

1.2.2 Maintenance underlies all four measures. A measure that cannot be maintained by its owner under Chapter 10 shall not be credited.

1.2.3 Credits from higher measures reduce the requirements of lower ones. Preserved areas and retained volume reduce detention storage as set out in Chapter 4.

Figure 1.1 — Stormwater management hierarchy Four stacked bars, widest at top: Preserve, Retain, Detain, Convey, with a Maintain bar underneath spanning all. A downward arrow shows the order of consideration; an upward arrow shows that credits from higher measures reduce lower ones. Order of consideration Credits reduce lower measures 1 PRESERVE Chapter 7 Keep tanks, wetlands, marshes, permeable soils, trees and flow paths 2 RETAIN Chapters 4, 8 Hold the Annex 2E depth on site: infiltrate, reuse, evaporate 3 DETAIN Chapters 4, 5 Store larger storms; release below pre-development peaks 4 CONVEY Chapters 6, 9 Minor system, plus a 1% AEP overland path MAINTAIN — underlies every measure Chapter 10 A measure that its owner cannot maintain earns no credit (Clause 1.2.2) Use a lower measure only for what the measures above it cannot practicably achieve (Clause 1.2.1).

Figure 1.1 — Stormwater management hierarchy: preserve, retain, detain, convey, with maintenance underlying each measure. Original drawing for this Manual, adapted from Mid-America Regional Council / Kansas City Metro Chapter APWA, "Layers of Stormwater Management", APWA 5600 Manual Factsheet, 2025 (concept).

Commentary. The order follows the "layers" of Kansas City Metro APWA Section 5600, Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet, 2025). The same logic is behind Georgia's runoff-reduction standard and CSE's "attenuate and infiltrate first" principle (CSE, 2023). For Keralam, the top layer has a particular meaning: much of the State's flood storage sits in its backwaters (kayals), paddy wetlands and kulams. The water-holding capacity of Vembanad lake alone is reported to have fallen by about 78–85% (NCESS; KUFOS). Losing that storage cannot be offset economically by pipes.


1.3.1 Notification. This Manual shall be given statutory effect by the Government of Keralam through:

  • (a) an amendment to KMBR/KPBR 2019 that makes compliance with this Manual a condition of planning permission, building permit, layout approval and completion certificate, for development to which Clause 1.5 applies; and
  • (b) bye-laws or standing orders of each urban local body (ULB), adopting the Manual for works executed or approved by that ULB, including the ULB's own drains and roads.

1.3.2 Higher State standards. The design return periods and performance criteria of this Manual exceed the national advisory minimums of the CPHEEO Manual on Storm Water Drainage Systems (2019). The State shall constitute, by notification, a high-powered committee (the State Stormwater Technical Committee, Clause 1.9) to adopt these higher standards. This is the route that CPHEEO (2019) provides for higher return periods.

1.3.3 Precedence. Within its scope, this Manual governs where it is stricter than CPHEEO (2019), IRC:SP:42-2014, IRC:SP:50-2013 or any departmental standard. Where a statute or statutory rule sets a stricter requirement (for example a waterbody setback), the statute governs.

1.3.4 Design-practice standard for public works. Departments and ULBs that procure drainage, road or waterbody works shall require compliance with this Manual in detailed project reports (DPRs) and contracts, from the dates in Clause 1.11.

Commentary. KMBR 2019 and KPBR 2019 were notified by the Local Self Government Department (G.O.(P) Nos. 77 and 78/2019/LSGD) and already carry rainwater harvesting (Rule 76), a permeable open-space rule (Rule 26(8)), a bar on building on flood-liable or floodable land (Rule 22(3)) and a bar on obstructing natural drains (Rule 22(4)). They are the natural instrument for a statewide condition of approval. They are amended regularly: the amendments of 29 Oct 2025 (SRO 1240/2025 and SRO 1241/2025) rewrote Rule 22(3) and Rule 76. MoHUA told Parliament in July 2026 that urban flooding "falls under the purview of the State Governments and the ULBs" and listed the CPHEEO manual among "advisory guidelines" (Lok Sabha AU1847). The State therefore needs no central approval to adopt higher standards. CPHEEO's Note 2 to Table 4.1 (§4.4.1.4) allows "a high powered committee constituted by State/UT Government through a notification" to adopt higher return periods. Clause 1.3.2 uses that route so that higher standards are on record for centrally funded schemes.


1.4 Definitions

1.4.1 The following terms apply throughout this Manual. Chapter-specific terms are defined in each chapter (for example Clause 2.2).

Term Meaning in this Manual
Approving Authority (the Authority) The body that grants planning permission, building permit or layout approval for a development, or that sanctions a public work: the Secretary of the Municipal Corporation, Municipality or Grama Panchayat under KMBR/KPBR 2019, with the LSGD Planning Wing where those rules require its approval, or a department for its own works.
Applicant The owner, developer or department that seeks approval, and its successors in title.
Development Any building, layout, sub-division, road, paving or land-use change that requires approval under KMBR/KPBR 2019 or that is executed as a public work.
Redevelopment Development on a site where impervious cover already exists.
Land disturbance Clearing, grading, excavation, filling or paving of land, measured in plan area over the whole of a common plan of development (Clause 1.5.5).
Impervious area Roofs, paving, compacted gravel, decks and other surfaces that prevent infiltration. Permeable paving designed to Chapter 8 is counted as pervious only for the area it treats.
New or replaced impervious area Impervious area created, or removed and rebuilt down to the subgrade, by the development. Resurfacing that leaves the base in place is not "replaced".
Retention Permanent removal of runoff from the drainage system on site, by infiltration, reuse or evapotranspiration (Chapter 4).
Detention Temporary storage of runoff with a controlled outlet, emptied after the storm (Chapter 4).
Rainwater harvesting (RWH) Collection of rainfall for supply or recharge under the RWH mandate. RWH storage is not detention unless Chapter 4 allows it.
Minor system Drains, pipes and inlets designed for the minor-system AEP of Chapter 6.
Major system The overland and floodway path that carries the 1% AEP (100-yr) flow (Chapter 6).
Pre-development condition Greenfield: open land in good condition for the mapped hydrologic soil group. Existing impervious cover is not counted (Chapter 3).
Flood-sensitive catchment The catchments of the Kochi city canals, the Thiruvananthapuram city canals (Amayizhanjan thodu, Thettiyar and Parvathy Puthanar), the Canoli canal in Kozhikode, and the built-up areas of Kuttanad, and any catchment the Authority notifies (Chapter 4; Annex 1B).
Waterbody A river, stream, canal, tank (kulam), lake, pond, marsh, supply channel or surplus course, whether perennial or seasonal (Chapter 7).
Regional facility A detention, retention or tank storage facility serving more than one development, built or restored under a basin plan (Chapter 4).
Tier A / Tier B authority An Approving Authority classed under Clause 1.6.
Policy supplement The set of adoptable alternative clauses in Clause 1.7 and Annex 1C.
Drainage report The preliminary or final report required by Chapter 10.
Registered professional A person registered under KMBR/KPBR 2019 to prepare and sign the relevant plans, with any further qualification required by Clause 10.6.
Compliance calculator The State-issued tool for computing and reporting compliance (Clause 10.5).
Maintenance declaration The registered undertaking by an owner to maintain a stormwater facility (Clause 10.10).
Variance Approval to depart from a numeric requirement, with equivalent performance shown (Clause 1.10).
Waiver Approval that a requirement does not apply to a site, on the grounds in Clause 1.10.
Notified Published by the Government or the State Stormwater Technical Committee in the Kerala Gazette.

Commentary. "Replaced" impervious area is defined to the subgrade so that redevelopment of a fully paved site is captured, while routine resurfacing is not. This follows the approach of the APWA 5600 (2025.01) redevelopment triggers (MARC Supplement, 2025).


1.5 Applicability

1.5.1 Who is covered. This Manual applies to:

  • (a) all development requiring planning permission, building permit or layout approval under KMBR/KPBR 2019;
  • (b) all drainage, road, bridge, culvert, waterbody and flood-mitigation works executed by a ULB, a State department, a board, or a State undertaking; and
  • (c) works executed by Central agencies or their contractors within Keralam, to the extent that the Authority's approval or no-objection is required.

1.5.2 Retention and detention threshold. Chapters 4 and 5 (retention, detention, downstream and tailwater analysis) apply to any development that, over the common plan of development, involves:

  • (a) land disturbance of 0.1 ha or more; or
  • (b) new or replaced impervious area of 500 m² or more.

1.5.3 RWH. The existing RWH mandate continues to apply as set by Rule 76 of KMBR/KPBR 2019: groundwater recharge for new buildings on terrain sloping 20° or less, and rooftop rainwater storage for new buildings with built-up area above 300 m², as now. This Manual does not change it.

1.5.4 Provisions that apply at every size. The following apply to all development under Clause 1.5.1, whatever its size, unless exempted by Clause 1.5.8:

  • (a) no sewage connection to a storm drain (Chapter 8);
  • (b) lowest habitable floor and openings at or above the 1% AEP level plus 0.5 m, where a 1% AEP level is mapped or determinable (Chapter 6);
  • (c) waterbody setbacks and the no-fill zone (Chapter 7); and
  • (d) no obstruction of a natural drainage path or major-system flow path (Chapter 6).

1.5.5 Common plan of development. The thresholds of Clause 1.5.2 apply to the total area of a development, including all phases, plots and sub-divisions under one layout approval or one ownership at the date of application. A development shall not be divided to avoid the thresholds.

1.5.6 Redevelopment. For redevelopment, the thresholds apply to new plus replaced impervious area. Retention and detention apply to the whole of the new and replaced impervious area, and the pre-development condition is greenfield (Clause 1.4). Where greenfield control cannot be achieved on a constrained redevelopment site, the relief route of Clause 4.5.6 applies: a minimum on-site cut of 50% from existing peaks, with the shortfall paid as fee-in-lieu into basin storage.

1.5.7 Linear public works. For roads, widening and other linear works, the impervious area threshold applies to the added impervious area within each drainage catchment crossed. Retention and detention shall be provided within the right of way, or in a regional facility under Chapter 4, where the right of way cannot hold them.

1.5.8 Exemptions. The following are exempt from Chapters 4 and 5:

  • (a) a single dwelling on its own plot, where the thresholds of Clause 1.5.2 are not met; and
  • (b) linear road resurfacing that adds no impervious area.

Exempt development remains subject to the RWH mandate and to Clause 1.5.4.

1.5.9 Applicability determination. The Applicant shall record the applicability decision on Form 1-1 (Applicability Determination) with the first submittal under Chapter 10. The Authority may confirm or correct it at the pre-application stage.

Figure 1.2 — Applicability decision flowchart Flowchart for Clause 1.5: approval test, exemption test, size threshold test, and flood-sensitive catchment test, leading to the requirements that apply. Development or public work (Clause 1.5.1) Needs building-rules approval, or is it a public work? No Manual not triggered; other rules apply Yes Exempt under Clause 1.5.8? (single dwelling below the threshold, or road resurfacing that adds no impervious area) Yes Exempt from Chapters 4–5. RWH (where mandated) and Clause 1.5.4 still apply No Land disturbance ≥ 0.1 ha, or new or replaced impervious area ≥ 500 m² (Clause 1.5.2)? No Below threshold: RWH (where mandated) and Clause 1.5.4 apply Yes Chapters 4 and 5 apply: retention, detention, downstream and tailwater analysis (+ RWH, 1.5.4) In a flood-sensitive catchment (Annex 1B)? Yes Mixed-frequency rule; full methods only; no Policy Supplement alternatives No Standard rule: Q_post ≤ 0.9 × Q_pre Tier B: design-aid route may be used (Clause 1.7) Decision Chapters 4–5 requirements Chapters 4–5 do not apply

Figure 1.2 — Applicability decision flowchart for Clause 1.5. Original drawing for this Manual.

Commentary. The thresholds have no single direct precedent; they are set by this Manual. Precedents span a wide range:

  • Singapore controls peak runoff from developments of 0.2 ha or more (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5).
  • Malaysia's 2008 DID checklist used on-site detention for sites up to 0.1 ha and community ponds above that.
  • The APWA 5600 (2025.01) Policy Supplement offers alternative triggers of ¼ acre (about 0.1 ha) disturbed, or 1 acre (about 0.4 ha) with 10,000 sq ft (about 930 m²) impervious, and warns agencies not to exceed a 1-acre trigger.
  • MBBL 2016 makes recharge mandatory for buildings over 500 m².

The 0.1 ha / 500 m² trigger sits at the strict end of these, because typical Keralam plots are small and the cumulative effect of many small plots is what fills Thiruvananthapuram's drains. The self-certified building permit route of KMBR/KPBR 2019 is unaffected for small buildings that fall under the single-dwelling exemption or below the thresholds.

Clause 1.5.4(b) has no direct precedent; this Manual sets it because floor levels are the cheapest protection a building can have, and it would be perverse to protect only large developments. Where no 1% AEP level is mapped, Chapter 6 gives the method for small sites.


1.6 Tiered adoption

1.6.1 Tier A authorities. The following are Tier A:

  • (a) Thiruvananthapuram Municipal Corporation and Kochi Municipal Corporation;
  • (b) all Approving Authorities within the area of the Greater Cochin Development Authority (GCDA), as notified from time to time, including the Municipalities and Grama Panchayats in it; and
  • (c) the Municipal Corporations of Kollam, Thrissur, Kozhikode and Kannur, and every other Municipal Corporation in the State.

1.6.2 Tier B authorities. All other Municipalities are Tier B.

1.6.3 What differs between tiers. All criteria of this Manual apply in both tiers. The tiers differ only in method and review:

Table 1.1 — Differences between Tier A and Tier B authorities

Item Tier A Tier B
Performance criteria (Chapters 2–9) Apply in full Apply in full
Hydrologic method for storage Hydrograph method (Chapter 3) Hydrograph method, or the design-aid route of Clause 1.7 where eligible
Compliance calculator (Clause 10.5) Required as a summary Required; may be the sole calculation on the design-aid route
Policy supplement alternatives (Clause 1.7) Only with State Stormwater Technical Committee concurrence May be adopted by council resolution
Technical review By the Authority By the Authority, with LSGD regional support or an empanelled reviewer (Clause 10.7)
Flood-sensitive catchment rule Applies Applies

1.6.4 Moving between tiers. A Tier B authority may opt into Tier A by council resolution. The Government may notify a Tier B authority as Tier A when it becomes a Corporation, joins the area of the Greater Cochin Development Authority (GCDA), or is found by a post-event review (Clause 10.16) to need the full methods.

1.6.5 Flood-sensitive catchments override tier. In a flood-sensitive catchment, whatever the tier, the alternatives of Clause 1.7 are available only as Table 1.2 allows: S-1 (the design-aid route) for sites of 0.5 ha or less (Clause 4.14.1), and S-5 fee-in-lieu where a basin plan has been notified (Clause 1.10.3(d)). S-2, S-3 and S-4 are not available.

Commentary. Thiruvananthapuram Municipal Corporation, with its own engineering staff, and a Grama Panchayat with one assistant engineer cannot be asked to review the same hydrograph models. The Kansas City solution was to keep one regional standard and publish adoptable alternatives for the most contested criteria, so that smaller agencies can "opt down" without leaving the standard (MARC Supplement, Nov 2025). The tiers here keep the performance criteria the same in both tiers and vary only the method, so that a building in a Tier B town is protected to the same level as one in Thiruvananthapuram.


1.7 Policy supplement: adoptable alternatives

1.7.1 The Government shall publish, with this Manual, a Policy Supplement (Annex 1C) of alternative clauses. An Approving Authority may adopt one or more alternatives under the conditions in Clause 1.7.3.

1.7.2 The alternatives are:

Table 1.2 — Policy supplement: adoptable alternatives S-1 to S-5

No. Main-text requirement Adoptable alternative Eligibility
S-1 Storage sized by hydrograph method (Chapter 3) Design-aid route: retention and detention volumes taken from the unit-storage tables (m³ per ha, by rainfall zone, soil group and impervious fraction) in Annex 4 and the compliance calculator Sites ≤ 2 ha outside flood-sensitive catchments; ≤ 0.5 ha within them (as Clause 4.14.1)
S-2 Release rate Q_post(T) ≤ 0.9 × Q_pre(T), computed for the site Permissible site discharge (PSD): a tabulated unit-area release rate (m³/s/ha) by zone and AEP, derived from the 0.9 × Q_pre rule Any site outside flood-sensitive catchments
S-3 Waterbody setback extended to the mapped 1% AEP flood extent plus margin (Chapter 7) Fixed-width setback table by waterbody class, where no 1% AEP extent is mapped. Never less than the Zone 1 minimum of Clause 7.4.7 Waterbodies with no mapped 1% AEP extent
S-4 Downstream analysis by hydraulic model (Chapter 5) Screening checklist of downstream capacity and known flooding, with a model only where the screen fails Sites < 1 ha, outside flood-sensitive catchments, not discharging to a tidal outfall
S-5 On-site detention Fee-in-lieu toward a regional facility or restored tank storage in a master-planned basin (Chapter 4) Where a basin plan has been notified

1.7.3 Conditions on adoption.

  • (a) An alternative shall not lower any criterion below the values of this Manual. S-1 and S-2 are simplified methods for meeting the same criterion. They are not lower criteria.
  • (b) A Tier B authority adopts an alternative by council resolution, sent to the State Stormwater Technical Committee within 30 days. A Tier A authority needs the Committee's concurrence before adoption.
  • (c) The adopted alternatives shall be published on the Authority's website and in the register of Clause 10.17.
  • (d) Retention (Annex 2E depth) cannot be replaced by any alternative, except where fee-in-lieu under S-5 funds equivalent retention in the same basin.
  • (e) The tables for S-1, S-2 and S-3 shall be issued by the State Stormwater Technical Committee, and reviewed with Chapter 2 (Clause 2.14).

Commentary. The supplement follows the model of the APWA 5600 (2025.01) Policy Supplement, which gives alternatives for the four most contested criteria (applicability, Rational Method limits, stream setback trigger, and Zone 2 setback width). Two of those map onto S-3 and onto the applicability threshold of Clause 1.5.2. Alternative S-3 copies the APWA answer to the same problem: the 1% AEP extent is not mapped for small drainage areas, so a fixed-width table is offered. S-2 follows the Kansas City 2011 shift from "match existing" to fixed unit-area release rates. Local agencies preferred a set rate because existing conditions were hard to determine consistently (MARC Evolution deck). It also reflects the Sydney Water permissible site discharge (PSD) method. The 2 ha / 0.5 ha limits for S-1 (matching Clause 4.14.1) and the 1 ha limit for S-4 have no direct precedent; they are set by this Manual.


1.8 Relationship with other instruments

1.8.1 This Manual shall be applied together with the instruments below. Where they overlap, Clause 1.3.3 governs.

Table 1.3 — Relationship with other instruments

Instrument Relationship
RWH mandate (KMBR/KPBR 2019, Rule 76, as amended on 29 Oct 2025) Continues unchanged: recharge for new buildings on terrain sloping 20° or less, unless the site is waterlogged or the subsoil impermeable; rooftop storage of 25 or 50 L per m² of footprint where built-up area exceeds 300 m². The storage tank is not detention unless it is a dedicated empty-on-arrival volume with an outlet, and tanks are assumed full at the start of SW monsoon storms (Chapter 4). Recharge structures may count toward retention where they meet Chapters 4 and 8.
Permeable open space (KMBR/KPBR 2019, Rule 26(8): at least 50% of open space unpaved or permeable) Continues. Open space may hold multi-use retention or detention (for example a sunken lawn or playfield), provided its use remains available outside storm periods and the facility is designed to Chapter 4.
Flood-liable land and natural drains (KMBR/KPBR 2019, Rules 22(3) and 22(4)) Continue. A plot barred by Rule 22(3) is not made buildable by compliance with this Manual. The flow-path, floor-level and setback rules of Chapters 6 and 7 apply in addition.
Master Plans, Detailed Town Planning Schemes and Interim Development Orders under the Kerala Town and Country Planning Act, 2016 Floodable areas and water-body and buffer zones in these plans are used in Chapter 7. Flood-sensitive catchments should be shown on the plan maps. Land for regional facilities should be reserved in the plan.
Kerala Conservation of Paddy Land and Wetland Act, 2008 (ss. 3, 11 and 27A) Governs the conversion of paddy land and the reclamation of wetland. The land set apart for water conservancy measures under the proviso to s.27A(2) may be designed to serve as retention or detention under Chapter 4, where it meets that chapter.
Kerala Irrigation and Water Conservation Act, 2003 (ss. 5, 9 and 38) Structures in or across a watercourse need Government sanction, and cross-drainage works shall not be obstructed. Outfalls into canals and watercourses held by the Irrigation Department need its consent; the outfall rules of Chapters 5 and 9 apply in addition.
CRZ Notification 2019 and the approved Kerala Coastal Zone Management Plan Governs development along the coast, backwaters and tidal canals, with referral to KCZMA. Where a CRZ width is wider than the setback of Chapter 7, the CRZ width governs (Clause 1.3.3).
KMBR/KPBR 2019 (no general setback from rivers, canals or backwaters) Keralam has no general statutory waterway setback. The minimum setback of Chapter 7 (Clause 7.4.7) is set by this Manual; statutory widths that apply to particular waters, such as CRZ or a Master Plan green strip, govern where wider.
CPHEEO Manual on Storm Water Drainage Systems (2019) Engineering reference. This Manual sets higher return periods under Clause 1.3.2.
NDMA Guidelines on Management of Urban Flooding (2010) and MoHUA SOP (2017) This Manual puts into effect the NDMA directives on catchment-based design, detention and retention, waterbody protection and climate-adjusted IDF.
NDMA Urban Flood Risk Management Programme (UFRMP) and AMRUT 2.0 Works funded under these programmes shall comply with this Manual. The development controls of Chapters 4–5 protect the capacity those works create.
IRC:SP:42-2014 and IRC:SP:50-2013 Apply to road drainage only where they do not conflict with Chapter 6.
MBBL 2016, Chapter 9 Model for RWH and for the inspection regime in Chapter 10.

Commentary. RWH in Keralam is framed as a water supply and recharge measure. It works well for that purpose. It cannot, however, be relied on for flood control in the SW monsoon, because RWH sumps are usually full or the ground saturated by the time a late-July or August monsoon depression arrives after weeks of rain. The Manual therefore keeps harvest volume and attenuation volume apart, while letting recharge count as retention where it truly removes water from the system.

Stormwater works under AMRUT in Keralam's nine mission cities covered only 5.59% of the identified gap in the drain network; Kochi built 1.38 km of new drain against a 110 km gap, and most of its test-checked spending went on maintenance and desilting (CAG AMRUT audit, 2025). No development-control condition currently stops new plots from using up the capacity such works create. Linking Chapters 4–5 to approvals closes that gap.

Rule 22(3) of KMBR/KPBR already bars building on land shown as floodable in a Master Plan, and the Thiruvananthapuram Master Plan 2040 has Conservation, Water Body and Buffer-Water Body zones. Showing flood-sensitive catchments and regional facility sites on Master Plans now is cheaper than retrofitting later.


1.9 Roles and responsibilities

1.9.1 The responsibilities below apply under this Manual. They do not change any agency's statutory powers.

Table 1.4 — Roles and responsibilities under this Manual

Agency Role under this Manual
Local Self Government Department (LSGD) Would own the Manual. Would issue the KMBR/KPBR amendment. Would constitute and service the State Stormwater Technical Committee.
State Stormwater Technical Committee (Clause 1.3.2) Adopts higher standards. Issues Annexes, tables and the compliance calculator. Concurs with Tier A alternatives. Decides variances referred to it. Reviews the Manual (Clause 1.12).
LSGD Planning Wing (Chief Town Planner, District Town Planners) Approves or concurs with larger developments and layouts where KMBR/KPBR require it. Embeds flood-sensitive catchments and regional facility sites in Master Plans under the Kerala Town and Country Planning Act, 2016. Technical support to Tier B authorities. Maintains the empanelled reviewer list (Clause 10.7).
Development authorities (GCDA, TRIDA and others) Apply this Manual to the works they execute. Reserve regional facility sites in their plans.
Municipal Corporations, Municipalities and Grama Panchayats Approving Authority for building permits, issued by the Secretary under KMBR/KPBR through K-SMART. Owner of road-side and secondary drains, and of the public watercourses vested in them. Receives handed-over assets (Clause 10.14). Inspects and enforces (Clauses 10.12–10.15).
Irrigation Department Custodian of major canals, thodus, rivers and irrigation works under the Kerala Irrigation and Water Conservation Act, 2003. Provides design water levels, regulator operating rules (including Thanneermukkom and Thottappally) and bar-cutting practice (Chapters 5 and 7). Consents to outfalls into its canals. Concurs with regional storage credits (Chapter 4).
Kerala State Disaster Management Authority (KSDMA) and District Disaster Management Authorities (DDMAs) Hazard and flood mapping. Notify or recommend flood-sensitive catchments. Pre-monsoon preparedness under the Orange Book. Lead the post-event review (Clause 10.16). The District Collector, as DDMA chair, coordinates multi-agency drain and canal works.
Kerala Water Authority (KWA) Sewerage agency in its areas. Identifies and removes sewage connections to storm drains (Chapter 8). Keeps its mains out of drain sections.
PWD, NHAI, Southern Railway, KMRL and other road and rail owners Apply this Manual to road drainage (Chapter 6), culverts and linear works (Clause 1.5.7). Match culvert capacity to the drains they connect.
KSEB and other utility owners Keep cables and pipes out of drain sections, and move those that obstruct flow.
Revenue Department Maintains land and waterbody records, including the Basic Tax Register entries for paddy land and wetland, used for setbacks and storage rules.
Kerala Coastal Zone Management Authority (KCZMA) Advises on CRZ limits for sites referred to it under KMBR/KPBR.

Commentary. Ownership of Keralam's urban drainage is split: major canals and thodus lie with the Irrigation Department, road-side drains with the local body, culverts under tracks with Southern Railway and under highways with NHAI, and pipes and cables in drains with KWA and KSEB. The Kerala High Court, in WP(C) 23911/2018 on waterlogging in Kochi, has had to set a cleaning calendar that assigns canals to the Irrigation Department and drains to the Corporation, and to direct a city drainage map made "using scientific methods". A manual that names one owner for each task does not fix institutions by itself, but it removes ambiguity about who signs what.


1.10 Variances and waivers

1.10.1 Variance. The Authority may grant a variance from a numeric requirement where the Applicant shows, through a report certified under Clause 10.6, that:

  • (a) compliance is impracticable because of site conditions such as a high groundwater table, contaminated soil, rock, or a site area too small for the required facility; and
  • (b) the proposed alternative gives equal or better performance at the downstream point of Chapter 5, or the shortfall is made up by fee-in-lieu or off-site works in the same catchment.

1.10.2 Waiver. The Authority may waive Chapter 4 detention requirements (not retention) where a hydraulic analysis certified under Clause 10.6 shows that the site discharges directly to the sea, or to a tidal reach with no flood-prone property downstream, and that undetained flow does not worsen the outfall-closed condition of Chapter 5.

1.10.3 No variance or waiver. No variance or waiver shall be granted for:

  • (a) a sewage connection to a storm drain;
  • (b) the lowest habitable floor level of Chapter 6;
  • (c) any reduction of a waterbody setback below the Zone 1 minimum of Clause 7.4.7, or any fill or construction in the no-fill zone of Chapter 7; or
  • (d) the retention requirement in a flood-sensitive catchment, except by fee-in-lieu under Clause 1.7.

1.10.4 Procedure.

  • (a) The request shall be made on Form 1-2 (Variance / Waiver Request) with the preliminary drainage report.
  • (b) A Tier B authority shall refer any variance on a site of 1 ha or more to the State Stormwater Technical Committee.
  • (c) A decision shall state its reasons and any conditions, and shall be entered in the public register of Clause 10.17.
  • (d) A variance runs with the approval. It lapses if the approval lapses.

Commentary. The 2006 APWA 5600 included a waivers section (5601.6), and Georgia allows waivers where downstream analysis shows a peak control is unnecessary. The waiver of Clause 1.10.2 is narrow: on a tidal coast, undetained flow can help by passing through before the tide closes the outfall, but only an analysis can show that. This Manual requires every decision to be published because publication deters case-by-case erosion of the standard; the scale of what is at stake is shown by CAG (2021), which counted 913 encroachments of water bodies in the districts it audited, 832 of them on the Kanoli canal in Thrissur.


1.11 Transition provisions

1.11.1 Effective date. This Manual takes effect for new applications 6 months after notification (the effective date).

1.11.2 Applications in process. An application filed complete before the effective date may be decided under the rules in force when it was filed, if a decision is issued within 12 months of the effective date. Otherwise, this Manual applies.

1.11.3 Phased start for Tier B. In Tier B authorities, Chapters 4 and 5 apply from 24 months after notification, except in flood-sensitive catchments, where they apply from the effective date.

1.11.4 Public works. DPRs sanctioned before the effective date may proceed as sanctioned. Any DPR revised or re-tendered after the effective date shall comply. Departments shall report non-compliant works in progress to the State Stormwater Technical Committee within 12 months.

1.11.5 Before the annexes are issued. Until an annex referred to in this Manual is issued, the Applicant shall use the method stated in the clause, with values agreed with the Authority and recorded in the drainage report.

Commentary. The 6-month lead time matches the lead time for NIH-DHAARA updates in Clause 2.14.2. Singapore gave a similar interval for its 2025 detention addendum (issued 16 Apr 2025, applied from 1 Oct 2025). The 12- and 24-month periods are set by this Manual to let Tier B authorities train staff and to let the State issue the design-aid tables (Clause 1.7).


1.12 Review and amendment

1.12.1 The State Stormwater Technical Committee shall review this Manual every 10 years, and after any event that exceeds the 1% AEP design depth as set out in Clause 2.14.1.

1.12.2 Amendments shall be notified in the Gazette, published with a change log, and take effect 6 months after notification unless the notification states otherwise.

1.12.3 Any person may propose an amendment to the Committee. Proposals and the Committee's decisions shall be published.


References (chapter)

Annexes and forms

Annex / Form Content
1A List of Tier A authorities, with GCDA area boundary
1B Maps of flood-sensitive catchments
1C Policy Supplement: text of alternatives S-1 to S-5 and model council resolution
1D Model KMBR/KPBR amendment and model ULB bye-law
Form 1-1 Applicability Determination
Form 1-2 Variance / Waiver Request