Draft v1.0 prepared by NEER. Not adopted by the Government of Madhya Pradesh or any authority or local body, and has no legal force. About this draft

Madhya Pradesh · Draft v1.0

Madhya Pradesh Stormwater Design Manual

About this draft

Status. This is Draft v1.0 of the Madhya Pradesh Stormwater Design Manual. It was prepared by Neer as a proposed stormwater design standard for Madhya Pradesh.

Not adopted. This Manual has not been adopted, notified or endorsed by the Government of Madhya Pradesh or by any of its departments, local bodies or agencies. In particular, it has not been adopted, notified or endorsed by the Urban Development and Housing Department (UDHD), the Directorate of Town and Country Planning (T&CP), the Water Resources Department (WRD), the Narmada Valley Development Authority (NVDA), the Environmental Planning and Coordination Organisation (EPCO), any development authority, any Municipal Corporation, Nagar Palika Parishad, Nagar Parishad or other local body, or any other agency. Where it names a body, such as the Revenue Department, the Madhya Pradesh State Wetland Authority, the Madhya Pradesh Pollution Control Board (MPPCB), the Madhya Pradesh State Disaster Management Authority (MPSDMA), the Madhya Pradesh Urban Development Company (MPUDC), the Public Health Engineering Department (PHED), the Bhopal Municipal Corporation (BMC), the Bhopal Development Authority (BDA) or a district administration, it describes the role that body would have if the Manual were adopted. It does not say the body has agreed to that role.

No legal force. Until a competent authority adopts it, with or without changes, this Manual has no legal force. The Bhumi Vikas Rules, development plans, drainage schemes, orders of courts and tribunals and approval conditions in force continue to apply.

Names. Some places, rivers and lakes have more than one name or spelling in statutes, sources and on IMD and CWC stations:

  • Narmadapuram was formerly Hoshangabad. IMD's Hoshangabad observatory, CWC's Hoshangabad gauge on the Narmada and older sources keep the old name; Sethani Ghat is the riverside ghat at Narmadapuram whose level the press reports in floods. Older sources also write Bhilsa for Vidisha, Saugor for Sagar, Nimach for Neemuch and Pachmari for Pachmarhi, name East Nimar and West Nimar for the districts of Khandwa and Khargone, and give Nowgong (also Nowgaon), a town in Chhatarpur district, as an IMD station. Before November 2000 the "Madhya Pradesh" of IMD and CWC sources includes districts now in Chhattisgarh;
  • IMD's observatory for Bhopal is at Bairagarh, the airport, and is called Bhopal (Bairagarh) in this Manual; the observatories for Indore and Jabalpur are Indore (A) and Jabalpur (A), at the airports;
  • the Bhoj Wetland, the Ramsar site at Bhopal, is made up of the Upper Lake and the Lower Lake. The Upper Lake is also called Bhojtal and Bada Talab (the big talab). Its outflow passes through the sluice gates of the Bhadbhada dam to the Kaliasot river and the Kaliasot dam. The Kaliasot is also written Kaliyasot;
  • the Kanh, the river of Indore, is also written Khan, the form of some reports; the Kshipra is also written Shipra; Yashwant Sagar is also written Yeshwant Sagar;
  • Malwa is the basalt plateau of western Madhya Pradesh around Indore, Ujjain, Dewas, Ratlam and Mandsaur; the Gird is the region of Gwalior, in the north; Nimar is the lower Narmada valley around Khargone, Barwani and Khandwa; Bundelkhand and Baghelkhand are the regions of the north-east, around Sagar and Chhatarpur and around Rewa and Satna. The names describe regions, not administrative units.

This Manual uses the first form and keeps the others where a title, a source or a station uses them. Some names of bodies need a word of explanation:

  • a Municipal Corporation (Nagar Palika Nigam) is constituted under the Madhya Pradesh Municipal Corporation Act, 1956, and a Nagar Palika Parishad (Municipal Council) or Nagar Parishad under the Madhya Pradesh Municipalities Act, 1961. All three are urban local bodies (ULBs). Under the 1956 Act public tanks, streams, drains and watercourses vest in the Corporation (s.82);
  • BMC is the Bhopal Municipal Corporation, not the Brihanmumbai Municipal Corporation; IMC is the Indore Municipal Corporation;
  • T&CP is the Directorate of Town and Country Planning, under UDHD. It prepares the development plans of cities and grants development permission for layouts; the ULB grants building permission (MPBVR 2012, rules 2(5) and 2(8)). The Directorate writes its own name TNCP in its file numbers; the two forms are the same body;
  • a development authority, such as BDA in Bhopal or the Indore Development Authority (IDA), is a town development authority under the Madhya Pradesh Nagar Tatha Gram Nivesh Adhiniyam, 1973. GDA in this Manual is the Gwalior Development Authority, not the Ghaziabad Development Authority;
  • WRD (Jal Sansadhan Vibhag) is the State's water resources department, and is named in this Manual as the State groundwater agency; no State groundwater law was found. NVDA is the Narmada Valley Development Authority. The dams whose releases raise the Narmada and its tributaries, such as Bargi, Tawa and Indira Sagar, are operated by State agencies; the operating rules, and which agency operates each dam, were not confirmed for this Manual;
  • EPCO is the Environmental Planning and Coordination Organisation, the State nodal agency for wetlands and lakes and the secretariat of the Madhya Pradesh State Wetland Authority, constituted in January 2018 under the Wetlands (Conservation and Management) Rules, 2017;
  • MPUDC is the Madhya Pradesh Urban Development Company, which implements urban water supply, sewerage and drainage projects funded by the Asian Development Bank;
  • nistar (निस्तार) is the community's right of use over village land and tanks. Tanks over which a village exercised rights of irrigation or nistar vested in the State on 6 April 1959, and those rights survive the vesting (Madhya Pradesh Land Revenue Code, 1959, s.251); and
  • a tehsil is the revenue subdivision of a district, under a Tehsildar.

Some abbreviations have more than one meaning:

  • AMC is the antecedent moisture condition in Chapters 2 and 3; this Manual does not use it for any municipal body;
  • HFL is the highest flood level recorded at a gauge, as CWC uses it. It is not a design level, and sources sometimes give different values for the same gauge. The "highest water level" of Rule 50 of the Bhumi Vikas Rules is not defined in those rules, and this Manual proposes a definition of its own (Chapter 7);
  • FTL is the full tank level of a lake or tank and FRL the full reservoir level of a dam; the values published for the same lake sometimes differ, and some are given in feet;
  • MPBVR 2012 is also written MPBVN (Madhya Pradesh Bhumi Vikas Niyam), the form CAG uses;
  • NGT CZ is the Central Zone bench of the National Green Tribunal, at Bhopal; and
  • SWD is a storm water drain.

The sense is clear from the context. Hindi terms used in the text, such as talab (तालाब, a pond or tank that holds rainwater; also tal, ताल, the form of many named lakes), talaiya (तलैया, a small pond), sagar (सागर, a large tank or reservoir, used in names such as Yashwant Sagar and Sakhya Sagar), jheel (झील, a lake or marsh), bawdi (बावड़ी, a step-well), kund (कुंड, a small walled tank, often sacred), nala (natural drain or large storm drain), nali (small street drain), bandh (बाँध, a dam or embankment) and nistar, are explained where they first appear.

Use with care. Clauses and values may change after review. Designers remain responsible for their designs and for checking the data they use. Neer accepts no liability for decisions made on the basis of this draft.

Disclosure. Neer publishes the India Flood Atlas, a national map of modelled 1% AEP flood depth. Clause 6.11.3 names it as one example of a regional map that an Approving Authority may adopt for floor levels. The Manual does not require the Atlas; any map adopted under Clause 7.3.4 may be used.

Comments. Comments and corrections are welcome at info@neer.ai.

Preface

Madhya Pradesh's cities flood for three reasons. Bhopal showed the first on 14 August 2006, when 291.6 mm of rain fell in a day on a city with no design storm for its drains; it shows the second in its lakes, whose buffers are still being argued before the National Green Tribunal (NGT) while the land around them is built on; and Narmadapuram showed the third in August 2020, when the gates of the dams upstream were opened and the Narmada rose against the town's outfalls.

  1. Intense monsoon storms on black soils that stop absorbing once wet, with no published design storm. No design return period, design storm or rainfall intensity–duration–frequency (IDF) relationship has been published for the drains of any city in Madhya Pradesh. A storm water master plan for Bhopal by Tata Consulting Engineers is cited in the literature, but its return period and rainfall were not found. Much of the State lies on black soils: when dry they crack and take in water, but once they are wet and the cracks have closed, infiltration almost stops (about 0.2 mm/h, as reported). On 14 August 2006 Bhopal (Bairagarh) recorded 291.6 mm, its highest day, and 903.9 mm in the month; 12 deaths were reported in the city, and the Upper Lake was reported to have reached its full level and the Bhadbhada gates to have been opened. Bhopal's July record, 275.7 mm on 22 July 1973, is older. On 4 July 2005 Sagar recorded 475.6 mm, about 1.7 times the 50-year day on the CWC map for the town (about 280 mm), and from 2 to 3 August 2021 Shivpuri district received 454.6 mm in 38 hours, as reported, about 1.9 times the 50-year day on the map; more than 1,100 villages on the Sindh were reported affected. In Indore, "even 25mm of rainfall in 1–2 hours can cause water logging on most of the roads", and only 20% of the roads had storm water drains, a city vulnerability assessment found; the floods it lists followed days of about 80–190 mm, roughly a 2- to 10-year day on the reanalysis grids of NIH-DHAARA. Bhopal's self-assessment for the Smart Cities Mission put its storm drain coverage at 24.57%.
  2. Cities built around lakes and on nalas, whose buffers are disputed and encroached. Bhopal is built around the Upper and Lower Lakes, the Bhoj Wetland, a Ramsar site since 2002; Indore has Sirpur and Yashwant Sagar, and Shivpuri Sakhya Sagar, all Ramsar sites since 2022. Around the Upper Lake the NGT has barred any construction within 50 m of the full tank level (FTL) in urban areas and 250 m in rural areas, and ordered the FTL line surveyed again, as reported in September 2026; a State order of 2023 cutting the buffer to 33 m has been reported but was not verified, and the FTL itself is given as 508.04 m or 508.65 m. Along the Kaliasot and the Kerwa a 33 m green belt rests on Bhopal's Development Plan 2005 and on NGT orders of 2014; the Supreme Court was reported in March 2025 to have set aside a related bar, and what remains in force is not clear. The Bhumi Vikas Rules, 2012 bar building within 9 m of the highest water level of a water body or watercourse and 15 m of a river, but define neither the water body nor the level. When the Comptroller and Auditor General (CAG) checked 539 development permissions in Bhopal, Gwalior, Indore, Jabalpur and Ujjain, the setback applied to 60 and was properly imposed and drawn in only 23; on site builders "did not maintain the required 9/15 m free space", and in three colonies the nala "was covered by laying Hume pipes, encroached upon and concreted". A State order of September 2006, as CAG cites it, had already named the encroachment of nalas, and construction on and beside them, as the main cause of waterlogging in cities. Many nalas also carry sewage into the lakes: Bhopal was reported in 2026 to leave about 240 MLD of its sewage untreated, and the NGT has ordered every outfall into the Upper and Lower Lakes mapped.
  3. Rivers and dam releases that lock the outfalls. The Narmada rose to 301.33 m at Hoshangabad on 27 August 1972, 7.5 m above the danger level of 293.8 m, and set its highest levels at Barmanghat and Mandleshwar in August 1973, as CWC's bulletins give them. Those floods came before the large dams were built. Today the river at Jabalpur, Narmadapuram and Mandleshwar rises with the releases from Bargi, Tawa and Indira Sagar: in late August 2020, with all 13 gates of Tawa, 17 of the 21 gates of Bargi and 22 gates of Indira Sagar open, the Narmada at Sethani Ghat was reported at 297.75 m, against a danger level of 293 m, and about 3,000 people were rescued; on 30 August 2020 the river set its highest level at Handia, 274.9 m. The press called the Sethani Ghat level a 48-year record, which the CWC record of 1972 does not support. Bhopal's own outfalls are held by gates: in August 2022, with 7 of the 13 gates of Kaliasot, 5 of the 11 of Bhadbhada and 5 of the 8 of Kerwa open, about 200 colonies were reported waterlogged. In September 2019 the Gandhi Sagar reservoir stood above its maximum water level for at least a day, and more than 16,000 people were moved in Mandsaur and Neemuch, as reported. No danger level or highest flood level was found for the Narmada at Gwarighat in Jabalpur, the Kshipra at Ujjain or the Kanh at Indore.

Behind all three lies lost storage. The talabs, tals and sagars that once held rain are protected mainly by vesting and by the courts. The Municipal Corporation Act, 1956 vests public tanks in the Corporation and bars their use for any other purpose (s.82(2)), but still lets the Commissioner order a private tank filled up if it appears injurious to health (s.202). The Land Revenue Code vests village tanks in the State and preserves the rights of irrigation and nistar in them (s.251). No wetland in Madhya Pradesh had been notified under the Wetlands Rules, 2017 as of January 2023, as reported. Bhopal has had no new development plan since 2005: the State returned the drafts for 2021 and 2031 and asked for a plan for 2047, which had not been published when CAG reported.

Design for Madhya Pradesh therefore has to cover a monsoon that comes first to the south and last to the north-west, on plateaus whose black soils seal in July and whose cities drain to lakes and to rivers held up by dams. The monsoon normally reaches Khandwa by 16 June, Jabalpur by 19 June, Bhopal and Indore by 20 June and Neemuch by 25 June, and withdraws between 26 September at Neemuch and 6 October at Seoni; in the Narmada valley about 90% of the year's rain falls from June to October. Annual normals run from about 700–800 mm in the north-west (705.1 mm at Bhind and 785.9 mm at Gwalior) to about 1,500–1,600 mm in the south-east (1,528.4 mm at Mandla and 1,597.6 mm at Seoni), and more than 2,000 mm at Pachmarhi. Large days fall outside the season too: 100.1 mm at Hoshangabad on 24 April 1998, 269.4 mm at Satna on 4 October 1978 and 270.8 mm at Guna on 9 October 1985. Groundwater is stressed in the west: the State's stage of extraction was 59.1% in 2022, and 26 of its 317 assessment units, most of them in Malwa, were over-exploited.

National guidance sizes public drains but does not control the runoff that new building adds. This Manual makes stormwater a condition of development approval. Every development above a modest size must:

  • hold frequent rainfall on site;
  • release the large storms no faster than the undeveloped land did, or slower where catchments already flood; and
  • show that its outfall still works when the receiving nala, lake or river is high, when the gates of a lake or dam downstream are open, or when the flap gate on its outfall is shut.

The Manual also sets how public drains, roads, nalas, talabs, lakes and other water bodies, gated and pumped outfalls and basin-wide master plans are designed, so that private sites and public works aim at the same standard.

The Manual draws on leading stormwater standards from India and abroad. Each is adapted to Madhya Pradesh's south-west monsoon from mid-June to early October and the intense storms that come with it; the Narmada, the Chambal, the Betwa, the Sone, the Tapi and the Wainganga, the dams that regulate them and the lakes and reservoirs into which so many city drains empty; the deep black soils of Malwa and the Narmada valley, the sandstone of the Vindhyan plateau, the granite of Bundelkhand, the alluvium and ravines of the Gird, and the hard-rock aquifers of the Deccan trap, over-drawn in Malwa; the talabs, sagars, bawdis and kunds; and cities whose old cores, new colonies on the edges of lakes and nalas, and basements turn ordinary storms into floods.

  1. National base. The CPHEEO Manual on Storm Water Drainage Systems (2019). This Manual builds on it and sets higher standards where it allows a State to do so. IRC road-drainage codes and the NDMA urban flood guidelines are also used.
  2. Overall structure. Kansas City Metro APWA Section 5600 (Version 2025.01), the most recent comprehensive regional standard. It supplies the preserve, retain, detain, convey and maintain sequence and the required retention volume.
  3. Design rainfall. The CWC Flood Estimation Reports for the seven subzones that cover Madhya Pradesh, 1(b) Chambal, 1(c) Betwa, 1(d) Sone, 3(a) Mahi and Sabarmati, 3(b) Lower Narmada and Tapi, 3(c) Upper Narmada and Tapi and 3(f) Lower Godavari, as the interim source. No published analysis of short-duration rainfall for a station in the State was found; IMD's atlas of return-period rainfall maps for Central India (2008) is known but could not be obtained for this Manual. IMD's rainfall intensity curve for Jabalpur (Das et al., 2022) is used only as a check on storms of up to 3 hours, and frequency analysis of hourly rainfall by the National Institute of Hydrology (NIH), Roorkee, for comparison only.
  4. Monsoon practice. The PUB Singapore Code of Practice on Surface Water Drainage (7th ed., 2025), for the fixed-coefficient route for small sites and drainage reserves. Malaysia's MSMA 2 (2012), for monsoon design storms and simplified on-site detention.
  5. Runoff reduction and treatment. The Georgia Stormwater Management Manual (2016), for runoff reduction and downstream analysis. CIRIA C753 The SuDS Manual (2015), for the treatment train. The Mile High Flood District criteria manual, for outlet and storage design.
  6. Local rules. The Madhya Pradesh Nagar Tatha Gram Nivesh Adhiniyam, 1973 and the Nagar Tatha Gram Nivesh Niyam, 1975; the Madhya Pradesh Bhumi Vikas Rules, 2012; the Madhya Pradesh Municipal Corporation Act, 1956 and the Madhya Pradesh Municipalities Act, 1961; the Madhya Pradesh Land Revenue Code, 1959; the Madhya Pradesh Nagarpalika (Colony Development) Rules, 2021; the Wetlands (Conservation and Management) Rules, 2017; and the orders of the NGT, the High Court of Madhya Pradesh and the Supreme Court on lakes, rivers, nalas and sewage. This Manual follows them or, where disclosed, makes them stricter. The Bhumi Vikas Rules are cited from their text as notified in the Gazette in 2012 (notification No. F-3-131-2012-32 of 30 May 2012); a consolidated text "updated up to 6th March 2025" exists but could not be read, amendments of December 2025 and August 2026 and a draft of June 2026 have been reported, none of them seen to touch drainage, and every rule cited must be checked against the current text. The Municipalities Act, 1961 was not read; the Niyam, 1975 and the Colony Development Rules, 2021 are cited as CAG quotes them.

Why this Manual is needed

India has no uniform stormwater design standard. The CPHEEO Manual on Storm Water Drainage Systems (2019) is the country's first manual dedicated to storm water drainage, but it is advisory. The Ministry of Housing and Urban Affairs lists it among advisory guidelines and treats urban flooding as a matter for State Governments and urban local bodies. None of the national rules or State building rules reviewed for this Manual makes runoff control a condition of building approval, and neither does the Model Building Bye-Laws 2016.

The national documents leave key values open, or give different answers.

  • Return periods. CPHEEO recommends 5 years for drains in Class I cities and 2 years elsewhere, and lets a State committee adopt higher values. A 2023 CPHEEO presentation shows a different table. IRC:SP:50-2013 suggests 1–2 years for urban road drains; IRC:SP:42-2014 suggests 25 years. An engineer designing a drain in Madhya Pradesh can cite 1, 2, 5 or 25 years, depending on the code chosen.
  • Detention. CPHEEO describes limiting peak outflow to pre-development rates as general practice. It uses no "shall" and names no storm frequencies.
  • Climate. The NDMA Urban Flooding Guidelines (2010) call for detention and retention facilities and for rainfall curves adjusted for climate change, but give no sizing rule or return period.
  • Design rainfall. No national document gives design rainfall that a designer can apply directly to a given town. Each project chooses its own source. IMD's 2022 national set of rainfall intensity curves has two panels for the State: the panel for Indore repeats the curve printed for many other cities and is not used in this Manual, and the panel for Jabalpur, a curve of its own, gives about 195 mm for a 50-year day, against about 320 mm on the CWC map and Jabalpur's record day of 342.9 mm in 1915. The CWC reports for the State's seven subzones date from 1986 to 2004; their ratios of the 1-hour to the 24-hour rain run from 0.31 to 0.37, and the losses they assume from 1 to 5 mm/h on the same black-soil country. The reanalysis grids of NIH-DHAARA read 379 mm for a 50-year day at Narmadapuram, above the map's 320–360 mm, and 198 mm at Gwalior, against about 280 mm on the map. The largest hourly falls recorded on the self-recording gauges of the CWC reports, 51–90 mm (90 mm at Jabalpur on 17 June 1980), lie below the 50-year hour that the maps and ratios give, about 90–120 mm; but those records are short and old, and no sub-daily station analysis has been published to show which short-storm value is right.

Madhya Pradesh has no drainage design standard of its own. Research for this Manual found no design standard, IDF relationship or circular of UDHD, T&CP, WRD, any development authority or any Municipal Corporation that fixes return periods or design rainfall for storm drains, and no detailed project report (DPR) for a storm drain under the Atal Mission for Rejuvenation and Urban Transformation (AMRUT) or the Smart Cities Mission that states one. This Manual is offered as a technical companion to the Bhumi Vikas Rules, the Municipal Corporation Act and the development plans: it supplies the design storm, detention, water-level and buffer values that they leave open. It has not been adopted by UDHD, T&CP or any other body. In particular:

  • The building rules require recharge and drainage, but not detention. The Bhumi Vikas Rules, 2012 require rain or roof water harvesting on every building on a plot of more than 140 m², by one of three fixed recipes in Appendices H-1 to H-3 (percolation pits, a pebble bed or a recharge well), with no volume or sizing rule (rule 81(4)); require rainwater harvesting in layouts of 2 ha or more (rule 16(5)(h)); let the Authority require surface water drains within the curtilage (rule 51) and the connection of rain-water pipes to a drain (rule 81(2)); and bar building on a site that "is not drained properly or is incapable of being well drained" (rule 50(f)). CAG found harvesting structures not built in 41 of 185 cases checked. No rule requires on-site detention, limits peak runoff or sets "zero runoff";
  • The water rule has no defined water level. Rule 50(b) bars building within 9 m of the highest water level of a water body or watercourse and 15 m of a river, "or as prescribed in the development plan". The rules define drain, drainage and street, but not water body, watercourse, nala, highest water level or full tank level, and the setback was imposed and drawn in only 23 of the 60 permissions where CAG found it applied. The Municipal Corporation Act bars building over a drain or watercourse vested in the Corporation without written permission (s.198) and erecting or occupying a building within 100 ft of a municipal drain until a drain sufficient for its effectual drainage is built (s.203). No setback in metres from nalas, other than rule 50, was found;
  • Basements and plinths are covered, flood-prone land is not. The rules require plinths more than 45 cm above the surrounding ground "so that adequate drainage of the site is assured" (rule 68), limit the plinth of a building with a basement to 0.45 m and require arrangements to keep surface drainage out of the basement (rule 76), and ask site plans to show water bodies, "flood affected areas" and contours at 0.3 m where the slope is steeper than 1 in 20 (rule 16(4)(j)). None of them says how a flood-affected area is to be drawn;
  • There is no State floodplain order. No floodplain zoning law or order of WRD was found. The working limits come from the courts: on the Narmada a 25-year floodplain to be kept free of development, under an NGT judgment of 2025, and a 300 m ban reported from the High Court whose status is not clear, while a parliamentary reply records WRD as saying there was "no proposal" for such a ban; on the Kshipra at Ujjain, 200 m under an interim order of the High Court of January 2026; around the Upper Lake, 50 m from the FTL; and along the Kaliasot and Kerwa, 33 m. The Wetlands Rules bar permanent construction within 50 m of the mean high flood level of a notified wetland, and none was found notified. None of these reaches the nalas and talabs inside most cities;
  • The development plans are old. Bhopal is still planned under its Development Plan 2005; the drafts for 2021 and 2031 were returned, and the plan for 2047 that the State asked for had not been published when CAG reported; and
  • No document sets the lake or river level for which an outfall is designed. The FTL of the Upper Lake is given as both 508.04 m and 508.65 m; the Narmada's highest level at Narmadapuram is 301.33 m in the CWC record but a lower 2020 level was reported as a record; and no danger level or highest flood level was found for Jabalpur, Ujjain or Indore. Danger levels and highest flood levels are flood-warning levels and records, not design levels.

So each agency and each local body interprets the central manual its own way. BMC, IMC and the other Municipal Corporations, the Nagar Palika Parishads and Nagar Parishads, T&CP, the development authorities, WRD, NVDA, Smart City companies, MPUDC, road agencies, their consultants and funding agencies fill the gaps differently. Two drains on the same street, built by different agencies, can be sized for different storms from different rainfall sources. A nala in Bhopal can pass through colonies laid out by T&CP and wards cleaned by BMC and end in a lake whose level is set by dam gates, with no agreed level for which its outfall is designed. And a reviewer has no common basis against which to check a design.

What this Manual does about it. It turns those open choices into one State standard:

  • one source and method for design rainfall across the seven CWC subzones, in three rainfall zones, with a checked station analysis to govern where one exists (Chapter 2);
  • named return periods for every drainage element (Chapters 2 and 6);
  • a required pre- versus post-development rule for private sites (Chapter 4);
  • a required tailwater check for outfalls to nalas, lakes, reservoirs and rivers, gated, flap-gated or pumped, against a design lake or river level (Chapter 5);
  • a definition of the highest water level that rule 50 leaves open, and corridors and setbacks along nalas and around talabs and lakes, which no rule now sizes, proposed by this Manual (Chapter 7);
  • recharge first in the over-drawn hard-rock aquifers of Malwa, no infiltration credit on deep black soil once its cracks close, and treatment where nalas carry sewage (Chapter 8); and
  • basin-wide master plans, so that the agencies that share a basin plan together (Chapter 11).

It uses the route the CPHEEO manual itself provides: a State may adopt standards higher than the national values (CPHEEO 2019, Table 4.1, Note 2). A Municipal Corporation, a development authority or T&CP can still adopt a stricter standard (Chapter 1).

Sources: CPHEEO (2019) Part A §4.4–4.5 and Table 4.1; CPHEEO presentation to CSE (August 2023); IRC:SP:50-2013 §6; IRC:SP:42-2014 §6; NDMA (2010) Urban Flooding Guidelines, para 6.6.2; MoHUA Model Building Bye-Laws (2016); Government of Madhya Pradesh, Madhya Pradesh Bhumi Vikas Rules, 2012, notification No. F-3-131-2012-32 of 30 May 2012, made under s.85(1) read with s.24(3) of the Madhya Pradesh Nagar Tatha Gram Nivesh Adhiniyam, 1973 (No. 23 of 1973), Madhya Pradesh Gazette (Extraordinary), 1 June 2012 (English translation), rules 2, 16, 47, 50, 51, 60, 67, 68, 76 and 81 and Appendices H-1 to H-3 (the numbers of rules 50 and 51 are not printed on the scanned pages read and are inferred from their position); amendments of 15 December 2025 (No. UDH-3/0324/2025/18-5) and 28 August 2026 and draft No. TNCP/1/6/0006/2025 of 29 June 2026 (as summarised; not read); Madhya Pradesh Municipal Corporation Act, 1956 (Act 23 of 1956), ss.2, 66, 82, 190–204; Madhya Pradesh Land Revenue Code, 1959 (Act 20 of 1959), s.251; Madhya Pradesh Nagar Tatha Gram Nivesh Niyam, 1975 and Madhya Pradesh Nagarpalika (Colony Development) Rules, 2021, rr.22–23 (as cited by CAG); Wetlands (Conservation and Management) Rules, 2017, rr.4(2)(vi) and 5(1); CAG, Report on Management of Town and Country Planning, Government of Madhya Pradesh, Report No. 5 of 2025 (performance audit, 2018–23), paras 3.3.1 and 3.5.10 and Chapter I, with the State order of September 2006 as cited there (date of tabling not confirmed [TBC]); NGT (Central Zone), Dr. Subhash C. Pandey v. State of Madhya Pradesh, order of 27 May 2014 and later orders, and the State's status report (as recorded and quoted); NGT (Central Zone), O.A. 77/2020 and O.A. 12/2025 on the Upper Lake, and the order on outfalls into the Upper and Lower Lakes (as reported, September 2026); NGT (Central Zone), Kirtikumar Sadashiv Bhatt v. Narmada Water Resources (as reported, September 2025; O.A. number and date of judgment not found); High Court of Madhya Pradesh (Indore bench), order of January 2026 on the Kshipra, and reports of the order on a 300 m zone along the Narmada; Supreme Court of India, order of about 17 March 2025 (as reported); Lok Sabha and Rajya Sabha replies on rooftop rainwater harvesting and on a ban along the Narmada (as quoted; dates not confirmed); MoEF&CC list of Ramsar sites (as reported); Mongabay (January 2023) on the notification of wetlands; Sachdeva (2009), "Urban Floods: Case Study of Bhopal", Disaster & Development (NIDM) 3(1), citing the Tata Consulting Engineers storm water master plan for Bhopal; TARU, ACCCRN City Vulnerability Assessment for Indore, pp. 58–59; Bhopal Smart City self-assessment annexures; CWC, Flood Estimation Reports for Subzones 1(b) (C/16/1988), 1(c) (B/17/1989), 1(d) (S/15/1987), 3(a) (MS/13/1986), 3(b) (LNT/3(b)/R-7/47/2004), 3(c) (UNT-3(c)/R-6/46/2002) and 3(f) (LG-3(f)/R-2/24/1995), including their isopluvial plates and the annexes of self-recording gauges; IMD, Extremes of Temperature and Rainfall for Indian Stations (up to 2012); IMD, Climate of Madhya Pradesh (1981); IMD, Pai et al. (2020), new normal dates of onset and withdrawal of the south-west monsoon, Table 2; Das et al. (2022), MAUSAM 73(4), Fig. 4(xi) and 4(xiii); IMD, Atlas of State-wise Generalized Isopluvial (Return Period) Maps of Central India (Part-III), ATL/08/02 (2008) (cited; not obtained); NIH-DHAARA (accessed 6 November 2026); CGWB and the State, Dynamic Ground Water Resources 2022, as annexed to the State's report in NGT O.A. 694/2023; CWC flood bulletins for the Narmada (highest flood and danger levels as given in search summaries; not read; datum to be confirmed [TBC]); SANDRP on the Gandhi Sagar dam in September 2019 and on the Sindh floods of 2021; reports of the Bhopal floods of July 1973, August 2006 and August 2022, the Shivpuri rain of August 2021, the Narmada flood and dam releases of August 2020, the Upper Lake's full tank level and the opening of the Bhadbhada, Kaliasot and Kerwa gates, and Bhopal's sewage (press and secondary sources).


How to use this Manual

Clauses and commentary. Numbered clauses (for example 4.5.2) are the requirements of this Manual and use "shall". Paragraphs headed Commentary explain the reason for a clause and cite its precedent. They are guidance, not requirements. Where a value has no direct precedent elsewhere, the commentary says so and explains why this Manual sets it.

Return periods. Storms are described both by annual exceedance probability (AEP) and by return period. For example, "1% AEP (100-yr)" means a storm with a 1-in-100 chance of being equalled or exceeded in any year.

Illustrative values. Worked examples and figures marked "Illustrative — not design values" show method and scale only. Design values come from the sources set in Chapter 2.

Annexes and forms. Each chapter lists the annexes and forms it relies on. They follow the chapters, grouped by chapter, and hold the forms to submit, worked examples, templates, model text and standard drawings. Annexes that need data not yet collected are marked To be prepared. They say what they will contain, and the clause that depends on them states the rule that applies in the meantime.

Figures. All figures are original drawings prepared for this Manual. Where a figure follows a published concept, its caption credits the source.

Where to start.

If you are… Read first
A developer or architect Chapter 1 (does it apply?), Chapter 4 (what to provide), Chapter 10 (what to submit)
A design engineer Chapters 2–6, then 8 and 9
A local body or approving authority Chapters 1, 10 and 11
A planner or waterbody manager Chapters 7 and 11

Contents

Ch Title Annexes and forms
1 Policy, Applicability and Adoption Annexes 1
2 Design Rainfall and Design Storms Annexes 2
3 Hydrologic Methods Annexes 3
4 Site Runoff Control: Retention and Detention Annexes 4
5 Downstream and Tailwater Analysis Annexes 5
6 Minor and Major Drainage Systems Annexes 6
7 Waterbodies, Talabs (Ponds) and Setbacks Annexes 7
8 Water Quality and Recharge Annexes 8
9 Hydraulic Design of Structures Annexes 9
10 Submittals, Review, Operation & Maintenance and Enforcement Annexes 10
11 Basin and City Stormwater Master Plans Annexes 11

List of tables

TableTitle
1.1Differences between Tier A and Tier B authorities
1.2Policy supplement: adoptable alternatives S-1 to S-5
1.3Relationship with other instruments
1.4Roles and responsibilities under this Manual
1.5Working assignment of drainage elements under this Manual
2.1Design return periods (summary)
2.2Interim climate factors
2.3Illustrative scale of the mixed-frequency rule (not design values)
3.1Permitted hydrologic methods
3.2Runoff coefficient C (for AEP of 10% or more frequent)
3.3Frequency factor Cf
3.4Manning's n for sheet flow (USDA SCS TR-55, 1986, Table 3-1)
3.5Runoff curve numbers, AMC II, Ia = 0.2S (USDA SCS TR-55, 1986, Tables 2-2a and 2-2c)
4.1Design storms to be routed for detention sizing
4.2Illustrative example: peak discharges and storage used, by duration (Illustrative — not design values)
4.3Tier B permissible site discharge and site storage requirement (template)
4.3AFixed release coefficients (provisional)
5.1Design tailwater levels for tidal outfalls
5.2Joint-probability cases for tidal and riverine outfalls
6.1Design AEPs for conveyance (matches Clause 2.4)
6.2Street flow limits
6.3Flow hazard limits for streets and overland flow paths
6.4Combined flood hazard vulnerability classes (reproduced for reference)
6.5Inlet clogging factors (share of clean capacity assumed lost)
6.6Manning's n for design (from CPHEEO 2019)
6.7Minimum freeboard in open and covered drains
6.8Maximum spacing of manholes on straight pipe runs
6.9Minimum drainage reserve width (adopted from PUB Singapore)
7.1Fixed-width setback where no 1% AEP extent is available
8.1Pollutants of concern, sources and primary controls
8.2Required Level of Service for sites that are not redevelopment
8.3BMP Value Ratings and suitability in Madhya Pradesh
9.1Entrance loss coefficients ke (outlet control, full or partly full)
9.2Maximum permissible mean velocities in channels
9.3Riprap classes and apron dimensions (HEC-14)
9.4Minimum internal size of manholes
9.5Minimum IS 456 exposure classes for Madhya Pradesh locations
10.1Submittal stages and linked approvals
10.2Forms used in submittals
10.3Minimum owner inspection frequencies
10.4Graduated enforcement response
11.1Minimum data and surveys for a BSMP
11.2Minimum levels of service
1A.1Tier A authorities as defined in Clause 1.6.1
1A.2Register of Tier A authorities (layout)
1B.1Flood-sensitive catchments listed in Clause 4.5.3.2
1B.2Attributes of the flood-sensitive catchment layer (layout)
1C.1Alternatives adopted by this resolution
1D.1Schedule: alternatives adopted (layout)
2A.1Benchmark comparison of design depths (layout)
2A.2Rainfall zones (layout)
2B.1Ratios P(t)/P(24h) by zone (layout)
2B.2Fixed-interval adjustment factors (Clause 2.6.3)
2C.1Grid-to-point factors (layout)
2D.1Cumulative fraction of storm depth against cumulative fraction of storm time (layout, one table per zone, duration class and quartile)
2E.1Retention depth P_R by zone (layout)
3A.1Soil series to HSG lookup (layout)
3A.2Seasonal high water table, by mapping unit (layout)
3B.1Supplementary land covers, AMC II (layout)
3B.2CN calibration catchments (layout)
3C.1Problem 3C-1 solution
3C.2Problem 3C-2 solution
3C.3Problem 3C-3 solution
3C.4Problem 3C-4 solution
3C.5Problem 3C-5 stage–storage–discharge relationship
3C.6Problem 3C-5 routed outflow
3C.7Benchmark results to be reported by the applicant
3D.1Calibrated peak rate factors (layout)
3E.1SUH relationships by subzone (layout)
3E.2Worked example outline (layout)
4A.1Attributes of the shallow-groundwater zone layer (layout)
4B.1Contents of Annex 4B and their status
4B.2Tier B PSD and SSR (layout of Table 4.3)
4B.3Retention credit factor C_R (layout)
4B.4Largest orifice diameter (mm) for a permissible discharge at a given head (Cd = 0.60, free discharge)
4B.5Fixed release coefficients C_10 and C_2 (provisional, Table 4.3A)
4C.1Inputs (Illustrative — not design values)
4C.2Design rainfall depths, mm (Illustrative — not design values)
4C.3Curve numbers and abstractions (Illustrative — not design values)
4C.4Storm runoff depth Q, mm (Illustrative — not design values)
4C.5Unit hydrograph parameters (Illustrative — not design values)
4C.6Stage–storage–discharge, trial outlet (Illustrative — not design values)
4C.7Routing of the 100-yr 72-hour storm through the trial outlet, around the peak (Illustrative — not design values)
4C.8Routing of the 100-yr 72-hour storm through the trial outlet, hourly (Illustrative — not design values)
4C.9Results for the trial outlet (120 mm and 470 mm orifices) (Illustrative — not design values)
4C.10Stage–storage–discharge, revised outlet (Illustrative — not design values)
4C.11Results for the revised outlet (170 mm and 460 mm orifices) (Illustrative — not design values)
4C.12Retention credit by routing, revised outlet (Illustrative — not design values)
4C.13Outlet checks, revised outlet (Illustrative — not design values)
4C.14Summary of the revised design (Illustrative — not design values)
5A.1Use of the Annex 5A values in the design tailwater (Table 5.1)
5A.2Tidal datums, surge and still-water levels by coastal segment (layout)
5B.1Water bodies named in Chapter 5
5B.2Attributes of the Annex 5B layers (layout)
5C.1Inputs (Illustrative — not design values)
5C.2Outfall-closed check results (Illustrative — not design values)
5C.3Volume balance, 1% AEP 48-hour storm, Run B (Illustrative — not design values)
5C.4Stage hydrograph, 1% AEP 48-hour storm, Run B (Illustrative — not design values)
5C.5Summary (Illustrative — not design values)
6A.1Interim requirements for inlets until Annex 6A is published (from Chapters 6 and 9)
6A.2Register of standard inlet types (layout)
6A.3Capacity on grade (layout; one table per inlet type)
6A.4Capacity in a sag (layout; one table per inlet type)
6B.1Sediment allowances already set by Chapter 6 (provisional, to be calibrated)
6B.2Sediment yield by land use and drain type (layout)
6B.3Calibration of the sediment allowance (layout)
6C.1Dimensions on the standard drawings and their source clauses
7A.1Attribute fields of the waterbody inventory (WB_POLY)
7A.2Code lists
7A.3Attribute fields of structures (WB_STRUCT)
7B.1Fixed-width setback by waterbody class (alternative S-3)
7B.2Source buffers cited in Clause 7.4.6 (KC APWA 5600, 2006, §5605.3)
7C.1Rule levels by period (to be completed for each tank)
7C.2Outlet settings by level (to be completed for each tank)
7C.3Triggers and actions (to be completed for each tank)
7D.1Hold points for desilting and restoration works
7E.1Waterbodies
7E.2Channels, embankments and parts of the system
7E.3Statutory terms
7E.4Terms not yet verified
8A.1Water quality rainfall depths by zone (layout)
8A.23-month ARI intensity by duration (layout)
8B.1Required LoS for redevelopment (layout)
8B.2Worked example: composite VR (illustrative)
8B.3Composite VR of treatment trains (layout)
8C.1Monitoring site register (layout)
8C.2Event record (layout; parameters of Clause 8.13.2)
8C.3Performance summary and proposed VR (layout)
8D.1Pretreatment (all BMPs)
8D.2Bioretention and rain gardens (Figure 8.2)
8D.3Vegetated swales
8D.4Vegetated filter strips
8D.5Permeable pavement
8D.6Infiltration trenches and basins (Figure 8.3)
8D.7Wet ponds (extended wet detention)
8D.8Constructed wetlands
8D.9Gross pollutant traps and outfall screens
8D.10Oil-grit separators
8D.11Infiltration and recharge criteria (all infiltrating BMPs)
8D.12Bioretention filter media and layers
8D.13Indicative plants for bioretention, swales and filter strips
8D.14Indicative plants for constructed wetlands and wet ponds
8D.15Species not to be planted
8E.1Selection of measures (Clause 8.12.3)
8E.2ESC timing and inspection (Clauses 8.12.2 and 8.12.5)
9A.1HDS-5 inlet-control coefficients for common inlets
9A.2Inputs for the worked example
9A.3Critical depth and specific head (D = 1.2 m)
9A.4Inlet-control headwater
9A.5Outlet-control headwater
9A.6Governing headwater and checks
9A.7Riprap apron sizing
9A.8Summary of the worked example (Illustrative — not design values)
9B.1Dimensions and rules on the standard drawings and their source clauses
9C.1Pump station design checklist
9C.2Control levels (values to be set in design)
10A.1Calculator inputs
10A.2Calculations the calculator shall perform
10B.1Layers
10B.2Attributes of SW_FAC (facilities)
10B.3Attributes of SW_OUTF (outfalls)
10B.4Attributes of SW_CATCH (catchments)
10B.5Attributes of SW_FLOW and SW_CONV (flow paths and conveyance)
10B.6Metadata (SW_META)
10B.7Facility type codes (FAC_TYPE)
10B.8Status codes (STATUS)
10B.9Inspection result codes (INSP_RES)
10C.1Access dimensions set by the Manual
10C.2Access dimensions not set by the Manual (to be confirmed in design)
10D.1Contents of an O&M plan
10D.2Retention and infiltration (soakaways, trenches, bioretention, permeable paving)
10D.3Surface detention basin or multi-use open space area
10D.4Underground or podium detention tank, gravity outlet
10D.5Pumped detention, pumps and controls
10D.6Flap or tide gate, non-return valve
10D.7Gross pollutant trap or first-flush device
10D.8Private drains and inlets
11A.1Deliverables
11B.1Basins named in Clause 11.3.3 (provisional)
11B.2Attributes of the basin boundary layer (layout)
11C.1Depth–damage curve (layout, one table per building type)
11D.1Items to be published

List of figures

FigureTitle
1.1Stormwater management hierarchy
1.2Applicability decision flowchart
2.1Design rainfall source hierarchy and adjustments
2.2Design hyetographs
2.3From design rainfall source to design storm
3.1Selection of hydrologic method
3.2Time of concentration: flow segments along the longest flow path (schematic)
3.3SCS-CN runoff depth versus rainfall depth
3.4Two-step continuous simulation: starting tank level (schematic)
3.5Pre- and post-development hydrographs
4.1Pre-development 10-yr, post-development 100-yr uncontrolled, and detained hydrographs (illustrative)
4.2Detention storage stack and multi-stage outlet (schematic)
4.3Fixed-coefficient route: release caps, storage by the mass-curve method and two-stage outlet (schematic)
5.1Extent of downstream analysis
5.2Tidal outfall section with flap gate and design tailwater levels
5.3Tide-locked outfall timeline (illustrative)
6.1Minor and major drainage in a kerbed street
6.2Gutter spread, inlet interception and clogging
6.3Drain sections: freeboard, sediment allowance and access
6.4Drainage reserve: cross-section (schematic)
6.5Coastal band: floor level stack and extent of the band (schematic)
7.1Waterbody setback zones
7.2Compensatory storage by elevation band (schematic)
7.3City lake and sluice-gate outfall: inflow nalas, a gated city lake with its FTL, MWL, monsoon water line and buffer, and the sluice gates releasing to a downstream nala or river
8.1Treatment train
8.2Bioretention cell
8.3Infiltration trench
9.1Culvert hydraulics: inlet control and outlet control
9.2Riprap apron at a pipe or culvert outlet (schematic)
9.3Stormwater pump station: wet well, screens, levels and outfall
10.1Submittal, review and approval workflow
10.2Construction hold points from approval to handover
10.3Maintenance cycle and responsibility
11.1Basin master plan process
11.2BSMP model schematic
6C.1Covered roadside drain with removable covers
6C.2Access and junction chamber on a covered drain
6C.3Kerb inlet with silt sump
8E.1Silt fence: section and plan (schematic)
8E.2Sediment basin with surface dewatering outlet: section (schematic)
8E.3Stabilised construction exit: plan and section (schematic)
8E.4Drain inlet protection (schematic)
9B.1Culvert headwalls, wingwalls and cut-off walls
9B.2Straight vertical drop structure
9B.3Trash rack at a conduit entrance
9B.4Detention outlet riser and emergency spillway

Abbreviations

Abbreviation Meaning
AEP Annual exceedance probability
AMC Antecedent moisture condition
AMRUT Atal Mission for Rejuvenation and Urban Transformation
APWA American Public Works Association
ARF Areal reduction factor
AWS Automatic weather station
BDA Bhopal Development Authority
BMC Bhopal Municipal Corporation (not the Brihanmumbai Municipal Corporation)
BSMP Basin Stormwater Master Plan
CAG Comptroller and Auditor General of India
CGWA Central Ground Water Authority
CGWB Central Ground Water Board
CN Curve number (SCS/NRCS method)
CPCB Central Pollution Control Board
CPHEEO Central Public Health and Environmental Engineering Organisation
CSE Centre for Science and Environment
CWC Central Water Commission
DP Development plan (under the Madhya Pradesh Nagar Tatha Gram Nivesh Adhiniyam, 1973)
DPR Detailed project report
DWF Dry-weather flow
EIA Environmental impact assessment
EPCO Environmental Planning and Coordination Organisation, Madhya Pradesh
ESC Erosion and sediment control
FAR Floor area ratio
FER Flood Estimation Report (CWC)
FRL Full reservoir level
FTL / MWL Full tank level / maximum water level
GDA Gwalior Development Authority (not the Ghaziabad Development Authority)
HAT / MHWS Highest astronomical tide / mean high water springs (coastal terms; not applicable in Madhya Pradesh)
HFL High flood level (the highest level recorded at a gauge)
HGL Hydraulic grade line
HSG Hydrologic soil group
IDA Indore Development Authority
IDF Intensity–duration–frequency
IMC Indore Municipal Corporation
IMD India Meteorological Department
IRC Indian Roads Congress
MLD Million litres a day
MMC Act Madhya Pradesh Municipal Corporation Act, 1956
MoEF&CC Ministry of Environment, Forest and Climate Change
MoHUA Ministry of Housing and Urban Affairs
MP Madhya Pradesh (in the names of Acts and bodies)
MPBVR 2012 Madhya Pradesh Bhumi Vikas Rules, 2012 (also MPBVN, Madhya Pradesh Bhumi Vikas Niyam)
MPPCB Madhya Pradesh Pollution Control Board
MPSDMA Madhya Pradesh State Disaster Management Authority
MPUDC Madhya Pradesh Urban Development Company
NDMA National Disaster Management Authority
NGT National Green Tribunal (CZ: its Central Zone bench, at Bhopal)
NIH National Institute of Hydrology, Roorkee
NOC No-objection certificate
NVDA Narmada Valley Development Authority
PHED Public Health Engineering Department, Madhya Pradesh
PSD Permissible site discharge
RRV Required retention volume
RWH Rainwater harvesting
SANDRP South Asia Network on Dams, Rivers and People
SLA Sea-level allowance (coastal term; not applicable in Madhya Pradesh)
SoI Survey of India
SRRG Self-recording rain gauge
STP Sewage treatment plant
SUH Synthetic unit hydrograph (CWC)
SW monsoon / JJAS South-west monsoon, June–September
SWD Storm water drain
T&CP Directorate of Town and Country Planning, Madhya Pradesh (also written TNCP)
UDHD Urban Development and Housing Department, Government of Madhya Pradesh
ULB Urban local body (a Municipal Corporation, Nagar Palika Parishad or Nagar Parishad)
UTM Universal Transverse Mercator
WQv Water quality volume
WRD Water Resources Department, Government of Madhya Pradesh
WSUD Water-sensitive urban design