Draft v1.0 prepared by NEER. Not adopted by the Government of Maharashtra, and has no legal force. About this draft

Annexes to Chapter 7Waterbodies, Tanks (Talavs) and Setbacks

These annexes support Chapter 7. They give the inventory field specification, the fixed-width setback table, a template operating rule, the desilting and restoration specification, a glossary of Marathi waterbody terms, and the three forms that Clause 7.15 requires. Where an annex cannot yet be completed it says so and gives the rule to use in the meantime. The forms are draft forms; the template and model text are for consideration by a competent authority and are not in force.


Annex 7A — Statewide waterbody GIS layer and inventory fields

Supports Clauses 7.3.1, 7.3.3 and 7.3.5 of Chapter 7.

To be prepared. This annex will contain the statewide GIS layer of waterbodies required by Clause 7.3.1, prepared by each Authority with the WRD and the Revenue Department. It needs the Revenue village maps and the land records kept under the Maharashtra Land Revenue Code, 1966, including land recorded as tank, nallah or water course; the rivers, nallahs, water bodies and WRD blue and red flood lines shown on the Development Plan or Regional Plan under the MRTP Act, 1966; and, in the coastal districts, the mangroves, mangrove buffers and High Tide Line of the approved Coastal Zone Management Plan (CZMP) maps; the WRD and Gram Panchayat tank registers with FTL and MWL; surveyed levels on a common datum; the ISRO National Wetland Inventory and Assessment (NRSC); Survey of India topographic maps; and any list of waterbodies published under court directions. Until it is published, each Applicant identifies waterbodies from all the sources of Clause 7.3.3, with the larger extent governing, and records them on the Waterbody Sheet (Form 7-1).

The field specification below is complete. It is written so that every field the chapter asks for (Clause 7.3.1(a) to (g)) has a defined name, type and source, and so that the same fields can be filled from a project's Form 7-1.

7A.1 Layers

  • WB_POLY — one polygon per waterbody: the Revenue record boundary (Clause 7.3.1(c)).
  • WB_FTL — the surveyed FTL contour (tanks, lakes, ponds) or top of bank (channels), as a polygon or line.
  • WB_MWL — the MWL contour of each tank, as a polygon.
  • WB_FLOOD — the 1% AEP flood extent, where mapped (Clause 7.3.1(f)), with the floodway where delineated (Clause 7.6.1).
  • WB_STRUCT — points for surplus weirs, sluices, regulators, inlets and drain outfalls.
  • WB_LINK — lines for supply channels, surplus courses and the links between tanks in a cascade (Clause 7.3.1(e)).
  • WB_ENCR — polygons of known encroachments, each with the date recorded (Clause 7.3.1(g)).
  • WB_SETBACK — Zone 1 and Zone 2 polygons (Clause 7.4), derived from the layers above.

All layers shall carry the waterbody identifier (WB_ID) so that they can be joined. All levels shall be stated to one datum (Clause 7.3.5), named in the layer metadata.

Table 7A.1 — Attribute fields of the waterbody inventory (WB_POLY)

Field Type Unit / domain Required Content Clause
WB_ID Text District code + serial Yes Unique identifier, never reused 7.3.1
WB_NAME Text — Yes Name as in Revenue and WRD records, with local name 7.3.1(a)
WB_NAME_MR Text Marathi script Yes Name in Marathi 7.3.1(a)
WB_TYPE Code Table 7A.2 Yes Waterbody type 7.2, 7.3.1(a)
SURVEY_NOS Text Village, survey and subdivision numbers Yes Revenue survey numbers of the waterbody 7.3.1(a)
VILLAGE Text — Yes Revenue village, taluka and district 7.3.1(a)
CUSTODIAN Code Table 7A.2 Yes Custodian body 7.3.1(b)
AREA_REC Number ha Yes Area within the Revenue record boundary 7.3.1(c)
AREA_FTL Number ha Tanks Waterspread at FTL, surveyed 7.2, 7.3.1(d)
FTL Number m (datum) Tanks Full tank level 7.3.1(d)
MWL Number m (datum) Tanks Maximum water level (Clause 7.2 definition) 7.3.1(d)
MWL_BASIS Code WRD record / 1% AEP computed Tanks Which value governs MWL 7.2
TBL Number m (datum) Tanks Top bund level, lowest point 7.3.1(d)
WEIR_CREST Number m (datum) Tanks Surplus weir crest level 7.3.1(d)
WEIR_LEN Number m Tanks Surplus weir crest length 7.3.1(d)
WEIR_TYPE Text — Tanks Surplus weir type (for example fixed crest, with shutters or falling boards) 7.3.1(d)
SLUICE_N Integer — Tanks Number of sluices; details in WB_STRUCT 7.3.1(d)
SUPPLY_CH Text WB_ID(s) Tanks Supply channel(s) feeding the tank 7.3.1(d)
SURPLUS_CS Text WB_ID(s) Tanks Surplus course(s) leaving the tank 7.3.1(d)
UPSTR_WB Text WB_ID(s) Cascades Upstream tank(s) in the cascade 7.3.1(e)
DNSTR_WB Text WB_ID Cascades Downstream tank, river, drain or sea outfall 7.3.1(e)
CATCH_AREA Number ha Channels Drainage area at the downstream end of the reach (for the 8 ha trigger of Clause 7.4.1(b) and Table 7.1) 7.4.1
DATUM Text — Yes Datum of all levels; conversion from any older WRD datum 7.3.5
LEVEL_DATE Date — Tanks Date of the level survey 7.7.1(a)
SSC_DATE Date — Tanks Date of the latest stage–storage survey 7.7.1(b)
FLOOD_SRC Code Adopted map / site study / none Yes Source of the 1% AEP extent 7.3.4
FLOODWAY Code Delineated / whole 1% extent / below MWL Yes Basis of the floodway 7.6.1
ENCR_KNOWN Code Yes / No Yes Known encroachment; details in WB_ENCR 7.3.1(g)
CREDITED Code Yes / No Tanks Storage counted under Clause 7.7, with the scheme reference 7.7.1
WETLAND Code Notified / listed / other Wetlands Status under Clause 7.12.1 7.12.1
SOURCES Text — Yes Sources used, from the list in Clause 7.3.3(a) to (e) 7.3.3
UPDATED Date — Yes Date of the last edit, and by whom 7.3.1

Table 7A.2 — Code lists

Code list Values Clause
WB_TYPE River; stream or nallah (nālā, ōḍhā); canal; lake; tank or pond (talav); ex-malgujari tank; reservoir; tidal river or estuary; creek (khāḍī); khajan; salt pan; marsh; mudflat; mangrove; supply channel; surplus course 7.2
CUSTODIAN WRD (including its irrigation development corporations, such as VIDC); MCGM or other municipal corporation; Municipal Council or Nagar Panchayat; MMRDA; CIDCO or other Special Planning Authority; Gram Panchayat; Revenue Department; Forest Department (Mangrove Cell); water users' association; other (name) 7.3.1(b)
Structure (WB_STRUCT) Surplus weir; sluice; regulator; inlet; drain outfall; gross pollutant trap; crossing 7.3.1(d), 7.10
Encroachment (WB_ENCR) Building; fill; road; wall; dumping; cultivation; other — each with date recorded, area (m²) and source 7.3.1(g), 7.13

Table 7A.3 — Attribute fields of structures (WB_STRUCT)

Field Type Unit Content Clause
STR_ID Text — Unique identifier 7.3.1(d)
WB_ID Text — Waterbody served 7.3.1(d)
STR_TYPE Code Table 7A.2 Structure type 7.3.1(d)
CREST_SILL Number m (datum) Weir crest or sluice sill level 7.7.1(a)
LENGTH_SIZE Text m Weir crest length, or sluice opening size 7.7.1(a)
GATED Code Yes / No Controllable outlet (needed for a flood cushion, Clause 7.8.2(a)) 7.8.2
CONDITION Code Serviceable / defective Result of the latest pre-monsoon inspection, with date 7.7.1(d), 7.14.4

Annex 7B — Fixed-width setback table (alternative S-3, with Annex 1C)

Supports Clauses 7.3.4, 7.4.3, 7.4.6 and 7.4.7 of Chapter 7, and alternative S-3 of the Policy Supplement (Annex 1C).

7B.1 When the table may be used

The fixed-width setback may be used only where all of the following apply:

  • (a) the Authority has not adopted a 1% AEP flood extent map for the waterbody (Clause 7.3.4);
  • (b) Clause 7.3.4 does not require the Applicant to determine the 1% AEP extent by a hydraulic study: the site is not in a flood-sensitive catchment, is not a site of 1 ha or more adjoining a waterbody, and the Authority has not asked for a study; and
  • (c) the waterbody is one to which setbacks apply (Clause 7.4.1): any recorded or found waterbody, and any natural channel draining 8 ha or more at the site.

Where an Authority adopts alternative S-3 under Clause 1.7, the table below is the S-3 table. Clause 1.7.3(e) provides for the S-3 table to be issued by the State Stormwater Technical Committee. Until it is issued, the values are those of Clause 7.4.6, repeated here without change.

Table 7B.1 — Fixed-width setback by waterbody class (alternative S-3)

Waterbody class Drainage area at the site Total setback (Zone 1 + Zone 2) Of which Zone 1 Measured from
Channel, small 8 ha to 65 ha 25 m 15 m (6 m along a nallah) Top of bank (Clause 7.4.3)
Channel, medium 65 ha to 20 km² 40 m 15 m (6 m along a nallah) Top of bank
Channel, large, and rivers More than 20 km² 50 m 20 m Top of bank
Tank, lake or pond Any MWL contour + 25 m To the MWL contour, and not less than 15 m (6 m along a nallah) from FTL FTL contour (Zone 1); MWL contour (total)
Marsh, estuary or backwater Any As notified by the Authority, and not less than 50 m 15 m (6 m along a nallah) The waterbody boundary of Clause 7.13.1

Values from Clause 7.4.6 (Table 7.1). Zone 2 is the total setback less Zone 1.

7B.2 Rules of application

  • (a) Measurement. Measure horizontally on plan, outward from the boundary of Clause 7.13.1: the larger of the Revenue record boundary and the surveyed FTL (or top of bank). Where FTL and top of bank both apply, use whichever gives the wider zone (Clause 7.4.3).
  • (b) Drainage area. For a channel, use the drainage area at the downstream end of the reach that adjoins the site. Where a reach crosses a class limit within the site, apply the wider setback to the whole reach within the site.
  • (c) Both banks. The setback applies on each bank of a channel and all round a tank, lake, pond or marsh.
  • (d) Statutory minimum, extended by this Manual. Zone 1 is never less than 15 m (6 m along a nallah) (Clause 7.4.7). A wider statutory or approval setback governs for the uses it restricts (Clause 7.4.5).
  • (e) Stricter of the two. Where a hydraulic study is made voluntarily, the setback is the wider of Table 7B.1 and Clauses 7.4.3 and 7.4.4.
  • (f) Record. The basis of the setback (fixed width) shall be stated on the Waterbody Sheet (Form 7-1) and in the approval (Clause 7.4, Disclosure).
  • (g) Review. The table shall be reviewed within 2 years of the Authority adopting 1% AEP flood maps (Clause 7.16.1).

7B.3 Source of the channel widths

The channel widths were set by this Manual with reference to the 2006 Kansas City APWA default stream buffers, rounded up and floored at the statutory 15 m (river) and 6 m (nallah) minimum (Clause 7.4.6, commentary). The source values, as cited in the chapter, are:

Table 7B.2 — Source buffers cited in Clause 7.4.6 (KC APWA 5600, 2006, §5605.3)

Drainage area (source, acres) Approximate SI equivalent Source buffer
Less than 40 ac Less than 16 ha 40 ft (12 m)
40–160 ac 16–65 ha 60 ft (18 m)
160–5,000 ac 65 ha – 20 km² 100 ft (30 m)
More than 5,000 ac More than 20 km² 120 ft (37 m)

The 65 ha and 20 km² class limits in Table 7B.1 are the SI equivalents of 160 ac and 5,000 ac. The 8 ha lower limit is the 20-acre trigger of APWA 2025.01 (Clause 7.4.1(b)).


Annex 7C — Template tank operating rule, with flood cushion

Supports Clauses 7.7.1(c), 7.7.3, 7.8 and 7.14.4 of Chapter 7.

Model text for consideration by a competent authority. Not in force. For tanks under WRD control, the operating rule is WRD's rule (Clause 7.8.4); this template sets out the content that Clause 7.8 asks for, so that the custodian's rule can be checked against it. Text in square brackets is to be completed for each tank.

7C.1 Identification

  1. Tank: [name, WB_ID of Annex 7A, village, taluka, district].
  2. Custodian: [WRD division / ULB / Gram Panchayat / other].
  3. Cascade position: upstream tank(s) [ ]; downstream tank, river or drain [ ].
  4. Datum: [ ]. Surveyed levels (Clause 7.7.1(a)), date of survey [ ]: FTL [ ] m; MWL [ ] m; TBL (lowest point) [ ] m; surplus weir crest [ ] m, length [ ] m; sluice sills [ ] m.
  5. Stage–storage curve (Clause 7.7.1(b)): survey date [ ]; attached as Schedule 1.
  6. Controllable outlets (Clause 7.8.2(a)): [gated sluice / regulator / none]; capacity at FTL [ ] m³/s.

7C.2 Purposes and priority

  1. The tank serves [irrigation of a command area of [ ] ha / drinking water supply / recharge / flood storage]. Irrigation and water supply remain primary unless the custodian records otherwise (Clause 7.8.2(d)).

7C.3 Levels and dates through the year (Clause 7.8.1(a))

  1. The tank shall be operated to the levels in Table 7C.1.

Table 7C.1 — Rule levels by period (to be completed for each tank)

Period Target level (m) Upper limit (m) Lower limit (m) Purpose
[1 Jan – date] [ ] FTL [ ] Holding for irrigation / supply
[date – start of cushion period] [ ] FTL [ ] Holding
[Flood-cushion period, if any] Cushion level [ ] Cushion level [ ] [ ] Flood cushion (Clause 7.8.2)
[End of cushion period – 31 Dec] [ ] FTL [ ] Refilling
  1. Where no flood cushion is adopted, the starting level for design is FTL (Clause 7.7.3) and the row for the cushion period is deleted.

7C.4 Flood cushion (Clause 7.8.2)

  1. Cushion level: [ ] m, which is [ ] m below FTL, giving a cushion volume of [ ] m³ from Schedule 1.
  2. Dates: the cushion applies from [ ] to [ ].
  3. Drawdown: the tank can be drawn down from FTL to the cushion level through [outlet] in [ ] hours, with a release not exceeding the maximum release rate of paragraph 18.
  4. Reliability: continuous simulation (Clause 3.13) over the record [years] shows that the cushion is available at the start of a design storm in [ ]% of SW monsoon seasons, which shall be at least 90%. The simulation report is Schedule 2.
  5. Yield: the custodian accepts the loss of irrigation or supply yield stated in Schedule 3 [and the compensation recorded there].
  6. Where the tank has no controllable outlet, this section does not apply and no flood cushion is assumed (Clause 7.8.3).

7C.5 Releases (Clause 7.8.1(b) to (d))

  1. Sluice and regulator settings at each level: Table 7C.2.
  2. Operator: the sluices and regulators are operated by [post]. A release above [ ] m³/s may be ordered only by [post], or, in an emergency, by [post].
  3. Maximum release rate: [ ] m³/s. This rate, added to the flow from the downstream catchment, does not flood buildings downstream (Schedule 4 gives the downstream check).
  4. No person shall cut, lower or breach the bund or surplus weir except under the custodian's emergency procedure (Clause 7.14.5).

Table 7C.2 — Outlet settings by level (to be completed for each tank)

Tank level (m) Sluice 1 Sluice 2 Regulator Expected outflow (m³/s) Notes
Below cushion level [ ] [ ] [ ] [ ]
Cushion level to FTL [ ] [ ] [ ] [ ]
FTL (weir begins to spill) [ ] [ ] [ ] [ ]
Above FTL to MWL [ ] [ ] [ ] [ ] Check freeboard to TBL (Clause 7.7.4(b))

7C.6 Forecasts, warnings and communication (Clause 7.8.1(e) and (f))

  1. The triggers and actions are in Table 7C.3.
  2. Before any release under this rule, the operator shall inform the ULBs and the district administration downstream, and residents by the means stated in Schedule 5, at least [ ] hours before the release where the forecast allows.

Table 7C.3 — Triggers and actions (to be completed for each tank)

Trigger Source Action By whom
IMD district heavy-rainfall warning for the catchment IMD Read gauges [ ] hourly; check outlets are free; confirm the tank is at or below its rule level [ ]
IMD or MSDMA red alert IMD, MSDMA Begin releases needed to reach the rule level, within the maximum release rate; notify downstream bodies (paragraph 21) [ ]
City forecast system warning, where available [ ] [ ] [ ]
Tank level reaches FTL Gauge Record outflow hourly; inspect bund and weir [ ]
Tank level reaches [MWL − [ ] m] Gauge Emergency procedure; warning to the breach area of any emergency action plan (Clause 7.14.3(c)) [ ]

7C.7 Records and review (Clause 7.8.1(g))

  1. During the SW monsoon (1 June to 30 September) the operator shall record daily: the tank level, every release (time, rate and duration), and every gate setting. Outside the SW monsoon, records shall be kept [weekly].
  2. Records shall be kept with the O&M plan (Chapter 10) and given to the Authority on request.
  3. The tank shall be inspected before the SW monsoon (by 31 May) and after every heavy-rainfall event (Clause 7.14.4).
  4. This rule shall be reviewed after any event in which the tank surplused at a level above [ ] m, after any change to the weir, sluices or bund (Clause 7.7.6), and in any case with the review of the Manual.

Schedules: 1 stage–storage curve; 2 continuous simulation report; 3 yield and compensation; 4 downstream check of the maximum release; 5 communication list.


Annex 7D — Desilting and restoration specification

Supports Clauses 7.7.1(b), 7.9 and 7.14.4 of Chapter 7.

This specification applies to every desilting, restoration or deepening of a tank, pond or other waterbody under Clause 7.9. Values are those of Chapter 7. Where the chapter does not set a value, it is marked "to be confirmed in design" and shall be stated in the works design.

7D.1 Pre-works survey (Clause 7.9.1)

  • (a) Topographic and bathymetric survey of the waterspread, foreshore (to the MWL contour), bund, surplus weir and sluices, levelled to the datum of Clause 7.3.5. Survey grid and point density: to be confirmed in design.
  • (b) Original bed level found by test pits or augering on a grid (grid spacing to be confirmed in design), and from historical records where available. Each pit log shall show the silt thickness, the level of the original bed, and any clay or silt layer below it.
  • (c) Silt testing where the tank receives urban runoff or sewage: samples from the pits of (b), tested for heavy metals and other contaminants before disposal is planned. The parameters and limits shall be those the Maharashtra Pollution Control Board directs.
  • (d) Structures: condition of the bund (seepage, slips, cracks, animal burrows, trees), surplus weir and sluices, as in Clause 7.14.4.
  • (e) Existing stage–storage curve from the survey of (a).

7D.2 Limits of excavation (Clauses 7.9.2 and 7.9.3)

  • (a) Desilting removes accumulated sediment down to the original bed level of 7D.1(b), and no deeper.
  • (b) Deepening below the original bed only with a hydrogeological report showing each of Clause 7.9.3(a) to (c).
  • (c) Storage created below the lowest sluice sill is not flood storage, and shall not be shown as such in the revised stage–storage curve.
  • (d) Excavation shall stay clear of the bund toe by a distance to be confirmed in design, so that the bund's stability is not reduced.

7D.3 Edges and safety (Clause 7.9.4)

Where the public has access to the edge:

  • (a) side slopes no steeper than 1V:4H from 0.5 m above FTL down to 1.2 m below FTL; or
  • (b) a level safety bench at least 3 m wide, between 0.3 m and 0.5 m below FTL; and
  • (c) no isolated deep pit or vertical cut left in the bed. Borrow pits shall be regraded to the bed.

7D.4 Storage not reduced (Clause 7.9.5)

  • (a) Islands, walkways, bund widening into the waterspread, ring roads, parking, buildings and lake-front platforms within the waterspread or foreshore are lost storage.
  • (b) Lost storage shall be offset by compensatory storage at equivalent levels, band by band, using Form 7-3.

7D.5 Silt handling and disposal (Clause 7.9.6)

  • (a) Desilted material shall not be placed within the setback, on the bund (except approved bund strengthening), or on any flood path.
  • (b) Contaminated silt shall be disposed of as the Maharashtra Pollution Control Board directs.
  • (c) Haul routes and temporary stockpiles shall meet the construction erosion and sediment control rules of Clause 8.12, including stockpiles outside Zone 1.

7D.6 Inlets (Clause 7.9.7)

Every inlet that brings urban runoff shall have a sediment forebay, a constructed wetland inlet zone or a gross pollutant trap, designed under Chapter 8 (Annex 8D).

7D.7 Timing (Clause 7.9.8)

Desilting shall be complete, and the waterbody made safe, by 31 May. No excavation shall be left open, and no sluice or weir left dismantled, during the SW monsoon.

7D.8 Completion records

  • (a) As-built survey and revised stage–storage curve. The curve is the one that Clause 7.7.1(b) requires "after the last desilting".
  • (b) Volume removed, its disposal site, and the silt test results.
  • (c) Photographs of the bund, weir, sluices and inlet works.
  • (d) Update of the inventory record (Annex 7A: SSC_DATE, LEVEL_DATE, CONDITION).

Table 7D.1 — Hold points for desilting and restoration works

Hold point Check Clause
1. Before excavation Pre-works survey, pit logs, silt tests, and hydrogeological report if deepening 7.9.1, 7.9.3
2. Original bed reached Levels checked against pit logs; no excavation below the original bed unless approved 7.9.2
3. Edges formed Side slopes or safety bench as 7D.3 7.9.4
4. Inlet works Forebay, wetland inlet zone or GPT built 7.9.7
5. Completion (by 31 May) As-built survey, stage–storage curve, silt disposal record 7.9.8, 7.7.1(b)

Annex 7E — Glossary of Marathi waterbody terms and regional variants

Supports Clause 7.2 and Clause 7.3 of Chapter 7.

The terms below are Marathi words for waterbodies and their parts. Spellings in Roman script vary (for example nala, nalla and nallah), and usage differs between regions. The name used in the Revenue, WRD, municipal or Gram Panchayat record for each waterbody should be recorded in the inventory (Annex 7A) alongside the Manual's term. Only terms whose meaning was confirmed in J. T. Molesworth's A Dictionary, Marathi and English (2nd edition, 1857), or in a statute or regulation, are listed in Tables 7E.1 to 7E.3; the meanings are Molesworth's, and modern usage may be narrower or wider. Others are listed in Table 7E.4 as not yet verified. The list is to be extended by the State Stormwater Technical Committee, with modern WRD and Development Plan usage.

Table 7E.1 — Waterbodies and land

Marathi term Meaning Source of the term Manual term (Clause 7.2)
तलाव, तळाव (talāv, taḷāv; talav) A tank or reservoir Molesworth, pp. 369, 372 Tank or pond (talav)
तळावडी (taḷāvaḍī) A small tank Molesworth, p. 372 Tank or pond (talav)
नाला (nālā; nallah) A rivulet or irregular stream, or its dry bed; a drain, sewer or gutter Molesworth, p. 460; "nallah" is the minor water course of UDCPR 2020, Regulation 1.3 Nallah
ओढा (ōḍhā) A brook, rivulet or dry gully Molesworth, p. 119 Nallah (natural channel)
खाडी (khāḍī) An arm of the sea; a creek or an inlet Molesworth, p. 202 Creek (tidal water body)
खाजण (khājaṇ; khajan) Cultivable land along the coast or inlets exposed to tidal overflow; ground recovered from the sea by an embankment Molesworth, p. 202 Khajan
खजिना (khajinā) Among other senses, the reservoir that serves a set of salt pans Molesworth, p. 190 Salt pan (with its reservoir)

Table 7E.2 — Parts of a waterbody and its system

Marathi term Meaning Source of the term Manual term (Clause 7.2)
बंधारा (bandhārā) A dam or embankment; a raised field boundary; the damming of flowing water Molesworth, p. 564 Bund (tank bund or embankment, Clause 7.14)
सांडवा (sāṇḍavā) A sluice, floodgate or vent through a dam or mound; a masonry channel for water Molesworth, p. 842 Sluice
मोरी (mōrī) A little channel to carry off water Molesworth, p. 671 Outlet channel

Table 7E.3 — Management and statutory terms

Term Meaning
nallah (minor water course); river (major water course) The two classes of water course in UDCPR 2020 (Regulation 1.3) and the basis of the 6 m and 15 m distances of UDCPR 3.1.1(ii) and DCPR 2034 Regulation 18(b)
blue flood line; red flood line The WRD flood lines adopted by UDCPR 2020 (Regulation 3.1.3); see the definitions after Clause 7.2
prohibited zone; restrictive zone The land between the river bank and the blue line, and between the blue and red lines (UDCPR 3.1.3)
water users' association The association of irrigators to which the maintenance of a restored ex-malgujari tank has been tied (as reported)

Table 7E.4 — Terms not yet verified

The following terms are in published use for Maharashtra's waterbodies, but their meaning was not confirmed in a dictionary or an official source during research for this Manual. They shall not be used in a record or a drawing as defined terms until verified.

Term Reported meaning Status
मालगुजारी तलाव (mālgujārī talāv; ex-malgujari or ex-malguzari tank) Tank of east Vidarbha built by malguzars (revenue farmers) Secondary sources only (press); used in this Manual as a descriptive name, defined after Clause 7.2
कोल्हापुरी बंधारा (kolhāpurī bandhārā; Kolhapur-type weir) Low weir across a river with removable gates or needles, closed after the monsoon Not verified; no WRD or CWC definition read
सांडवा (sāṇḍavā) as "spillway" Spillway or waste weir of a dam or tank, in modern WRD usage Not verified; Molesworth gives "sluice, floodgate, vent" (Table 7E.2). Do not use sāṇḍavā for the surplus weir until confirmed
मोरी (mōrī) as "culvert" Culvert or drain outlet, in modern usage Not verified; Molesworth gives "a little channel to carry off water" (Table 7E.2)
नदी (nadī) River Common usage; not looked up
पाट (pāṭ) Irrigation channel Not verified

The Manual uses the terms in the last column of Tables 7E.1 and 7E.2, and the Maharashtra terms defined after Clause 7.2.


Form 7-1 — Waterbody Sheet

Supports Clauses 7.3.2, 7.4 and 7.15(1) of Chapter 7.

Draft form — Maharashtra Stormwater Design Manual, Draft v1.0. One sheet per waterbody. Attach the plan of Clause 7.3.2 at 1:1,000 or larger.

Table 7F.1 — Form 7-1, Section A: Project and waterbody

No. Field Entry Clause
A1 Project name and Authority file number ______ —
A2 Waterbody name (English and Marathi) and inventory ID (Annex 7A), if any ______ 7.3.1
A3 Waterbody type (Clause 7.2) ______ 7.2
A4 Position: within the site / within 100 m of the site boundary / downstream within the Chapter 5 extent ______ 7.3.2
A5 Survey numbers and village ______ 7.3.1(a)
A6 Custodian ______ 7.3.1(b)
A7 Sources checked (tick): Revenue village maps and land records, DP or RP maps with WRD flood lines, CZMP maps ☐; WRD / Gram Panchayat registers ☐; Authority inventory or court list ☐; historical maps and imagery, including NWIA ☐; site survey ☐ ______ 7.3.3
A8 Where sources conflict: which extent governs (the larger) ______ 7.3.3
A9 Datum of all levels, and conversion from any WRD datum ______ 7.3.5

Table 7F.2 — Form 7-1, Section B: Levels and features

No. Field Entry Clause
B1 FTL (tanks, lakes, ponds) or top of bank (channels), m ______ 7.2
B2 MWL (tanks), m, and basis (WRD record or 1% AEP computed) ______ 7.2
B3 TBL, lowest point (tanks), m ______ 7.3.1(d)
B4 1% AEP flood level, m, and source (adopted map / hydraulic study / not available) ______ 7.3.4
B5 Drainage area at the site (channels), ha ______ 7.4.1(b)
B6 Supply channels, surplus courses, sluices and surplus weirs shown on plan (yes / no) ______ 7.3.2
B7 Known encroachments, with date recorded ______ 7.3.1(g)

Table 7F.3 — Form 7-1, Section C: Setback

No. Field Entry Clause
C1 Basis of setback: mapped extent / hydraulic study / fixed width (Annex 7B) ______ 7.15(1)
C2 Is a hydraulic study required under Clause 7.3.4 (a) / (b) / (c)? ______ 7.3.4
C3 Floodway outer edge, m from FTL or top of bank, and how delineated ______ 7.6.1
C4 Zone 1 width, m (greatest of 15 m (6 m along a nallah), floodway edge, MWL contour) ______ 7.4.3
C5 Zone 2 width, m (to 1% AEP extent + 10 m, or 10 m) ______ 7.4.4
C6 Wider statutory or approval setback, if any, and its source ______ 7.4.5
C7 Setback applied: Manual standard / a wider statutory line: the WRD blue or red flood line (UDCPR 3.1.3), or the 50 m no-construction zone beyond a tentative blue line; 100 m from the high flood line of a natural lake in a Regional Plan area (UDCPR 3.1.12); 50 m from the mean high flood level of a wetland (UDCPR 3.1.1(xiv)); a mangrove and its 50 m buffer, or another CRZ line; or other (state which) ______ 7.4, Disclosure
C8 Uses proposed in Zone 1 and Zone 2, and the custodian's NOC for any work in Zone 1 ______ 7.5, 7.15(5)
C9 Fill proposed in the flood fringe (yes / no); if yes, Form 7-3 attached ______ 7.6.3
C10 Zone 1 marker positions shown (not more than 30 m apart) ______ 7.13.4

Table 7F.4 — Form 7-1, Section D: Prepared by

Field Entry
Name, registration and empanelment number (Clause 10.6) ______
Signature and date ______
Licensed surveyor for the levels (name, licence number) ______

Form 7-2 — Tank Storage Credit Sheet

Supports Clauses 7.7, 7.8, 7.11, 7.14 and 7.15(4) of Chapter 7.

Draft form — Maharashtra Stormwater Design Manual, Draft v1.0. One sheet per tank whose storage is counted. Storage that fails any item in Section B shall not be counted (Clause 7.7.1).

Table 7F.5 — Form 7-2, Section A: Tank and scheme

No. Field Entry Clause
A1 Tank name and inventory ID (Annex 7A); custodian ______ 7.3.1
A2 Scheme in which storage is counted: basin plan / regional facility / fee-in-lieu (S-5) ______ 7.7.1, 7.11
A3 Cascade modelled: uppermost tank ______ to outfall ______ ______ 7.7.2
A4 Datum ______ 7.3.5

Table 7F.6 — Form 7-2, Section B: Conditions for counting storage

No. Condition Date / reference Met (yes / no) Clause
B1 FTL, MWL, TBL, weir crest and length, sluice sills surveyed within the previous 5 years ______ ______ 7.7.1(a)
B2 Stage–storage curve from a bathymetric and topographic survey within 5 years or after the last desilting, whichever is later ______ ______ 7.7.1(b)
B3 Documented operating rule agreed with the custodian (Annex 7C) ______ ______ 7.7.1(c), 7.8
B4 Weir, sluices and bund under an O&M plan; latest pre-monsoon inspection found them serviceable ______ ______ 7.7.1(d), 7.14.4
B5 Custodian's written concurrence ______ ______ 7.7.1(e)

Table 7F.7 — Form 7-2, Section C: Levels and creditable volume

No. Item Value Clause
C1 Starting level: FTL, or cushion level under a rule meeting Clause 7.8.2, m ______ 7.7.3
C2 If a cushion is used: controllable outlet (type) and drawdown time, h ______ 7.8.2(a)
C3 If a cushion is used: reliability from continuous simulation, % of SW monsoon seasons (≥ 90%) ______ 7.8.2(c)
C4 Computed maximum level, 1% AEP inflow with climate factor routed through the cascade, m ______ 7.7.4
C5 MWL, m; is C4 ≤ MWL? ______ 7.7.4(a)
C6 Freeboard C4 to TBL, m; WRD freeboard standard, m; met? ______ 7.7.4(b)
C7 Storage between C1 and C4, from the stage–storage curve, m³ ______ 7.7.5
C8 Volume already committed to another facility or scheme, m³ ______ 7.7.5
C9 Creditable volume = C7 − C8, m³ ______ 7.7.5
C10 Register entry under Clause 10.17 (fee-in-lieu storage) ______ 7.11.2(d)

Table 7F.8 — Form 7-2, Section D: Bund safety

No. Item Entry Clause
D1 Specified dam under the Dam Safety Act, 2021? Height, crest length, capacity, maximum flood discharge ______ 7.14.1
D2 Hazard class: high / low ______ 7.14.2
D3 High hazard: weir passes 1% AEP at MWL with freeboard; 0.2% AEP check without overtopping ______ 7.14.3(a)
D4 High hazard: breach analysis and emergency action plan (references) ______ 7.14.3(b), (c)
D5 High hazard: independent check under Clause 10.6 (name) ______ 7.14.3(d)

Table 7F.9 — Form 7-2, Section E: Signatures

Role Name and designation Signature and date
Designer (Clause 10.6) ______ ______
Independent checker, where Clause 7.14.3(d) applies ______ ______
Custodian's concurrence (Clause 7.7.1(e)) ______ ______

Form 7-3 — Compensatory Storage Calculation (by elevation band)

Supports Clauses 7.6.3 to 7.6.5, 7.9.5 and 7.15(3) of Chapter 7.

Draft form — Maharashtra Stormwater Design Manual, Draft v1.0.

Method

  1. Fix the lower limit: the normal water level of the waterbody, or the 50% AEP (2-yr) level where higher (Clause 7.6.4(b)).
  2. Fix the upper limit: the 1% AEP flood level (with the climate factor).
  3. Divide the range into bands of not more than 0.3 m. The top band may be thinner.
  4. For each level z at a band boundary, measure on plan:
    • A_fill(z): the area of the fill footprint where existing ground is below z; and
    • A_cut(z): the area of the excavation where finished ground is below z and existing ground was above z (new flooded area).
  5. For each band, by the average end-area method: V = (A(z_bottom) + A(z_top)) / 2 × band thickness. Do this for fill (volume lost) and for excavation (volume gained).
  6. Check each band: volume gained ≥ volume lost. A surplus in one band does not make up a shortfall in another (Clause 7.6.4(b)).
  7. Check the other conditions of Clause 7.6.4(c) to (f) in Section C.

Figure 7.2 in Chapter 7 shows the method.

Table 7F.10 — Form 7-3, Section A: Levels

No. Field Entry Clause
A1 Waterbody, reach, and inventory ID ______ 7.6.4(c)
A2 Normal water level, m; 50% AEP level, m; lower limit (the higher), m ______ 7.6.4(b)
A3 1% AEP flood level with climate factor, m (upper limit) ______ 7.6.4(b)
A4 Band thickness, m (≤ 0.3) and number of bands ______ 7.6.4(b)
A5 Datum ______ 7.3.5

Table 7F.11 — Form 7-3, Section B: Band-by-band balance

Band From (m) To (m) A_fill bottom (m²) A_fill top (m²) Volume lost (m³) A_cut bottom (m²) A_cut top (m²) Volume gained (m³) Gained ≥ lost?
1 ______ ______ ______ ______ ______ ______ ______ ______ ______
2 ______ ______ ______ ______ ______ ______ ______ ______ ______
3 ______ ______ ______ ______ ______ ______ ______ ______ ______
4 ______ ______ ______ ______ ______ ______ ______ ______ ______
Total ______ ______

Add rows as needed.

Table 7F.12 — Form 7-3, Section C: Other conditions

No. Condition Met (yes / no) and evidence Clause
C1 Fill is in the flood fringe, not the floodway, and for a permitted use ______ 7.6.2, 7.6.3
C2 Excavation is in the same reach of the same waterbody, hydraulically connected, and not further downstream than the fill ______ 7.6.4(c)
C3 Excavation drains by gravity as the flood recedes; no pumping; no permanent pool below normal water level ______ 7.6.4(d)
C4 Excavation built before, or at the same time as, the fill ______ 7.6.4(e)
C5 Covenant or handover so that it is never filled (reference) ______ 7.6.4(f)
C6 Not counted as detention or retention under Chapter 4 ______ 7.6.5
C7 Signature of designer (Clause 10.6) and date ______ 10.6

Worked example

Illustrative — not design values. A site in the flood fringe of a channel needs a fill pad for a permitted Zone 2 use (Clause 7.5.2). The inputs are assumed.

  • Normal water level 10.00 m; 50% AEP level 9.80 m. Lower limit = 10.00 m (the higher).
  • 1% AEP flood level 11.20 m. Range 1.20 m, so four bands of 0.30 m.
  • The fill footprint is 1,600 m². Existing ground across the footprint rises evenly from 10.00 m to 11.20 m, so the area of footprint below each level is: 0 m² at 10.00 m; 400 m² at 10.30 m; 800 m² at 10.60 m; 1,200 m² at 10.90 m; 1,600 m² at 11.20 m.
  • The excavation is a graded cut beside the channel, with its floor at 10.00 m. The new flooded area below each level (first trial) is: 300 m² at 10.00 m; 900 m² at 10.30 m; 1,100 m² at 10.60 m; 1,500 m² at 10.90 m; 1,500 m² at 11.20 m.

Step 1 — volume lost, band by band (V = average area × 0.3 m):

  • Band 1: (0 + 400) / 2 × 0.3 = 60 m³
  • Band 2: (400 + 800) / 2 × 0.3 = 180 m³
  • Band 3: (800 + 1,200) / 2 × 0.3 = 300 m³
  • Band 4: (1,200 + 1,600) / 2 × 0.3 = 420 m³
  • Total: 960 m³

Step 2 — volume gained, first trial:

Table 7F.13 — Worked example: first trial (illustrative)

Band From (m) To (m) Volume lost (m³) A_cut bottom (m²) A_cut top (m²) Volume gained (m³) Gained ≥ lost?
1 10.00 10.30 60 300 900 180 Yes
2 10.30 10.60 180 900 1,100 300 Yes
3 10.60 10.90 300 1,100 1,500 390 Yes
4 10.90 11.20 420 1,500 1,500 450 Yes
Total 960 1,320

Every band passes. Note that a simple total balance would hide a failure if, for example, the cut were made deeper and narrower: suppose the designer instead offers a cut with new flooded areas of 1,400 m² at 10.00 m, 1,400 m² at 10.30 m, 1,000 m² at 10.60 m, 600 m² at 10.90 m and 200 m² at 11.20 m.

Table 7F.14 — Worked example: deeper, narrower cut (illustrative)

Band From (m) To (m) Volume lost (m³) A_cut bottom (m²) A_cut top (m²) Volume gained (m³) Gained ≥ lost?
1 10.00 10.30 60 1,400 1,400 420 Yes
2 10.30 10.60 180 1,400 1,000 360 Yes
3 10.60 10.90 300 1,000 600 240 No
4 10.90 11.20 420 600 200 120 No
Total 960 1,140

The total gained (1,140 m³) exceeds the total lost (960 m³), but bands 3 and 4 are short by 60 m³ and 300 m³. The surplus low down cannot be counted against them: the low storage fills early in every flood and is not available when the fill takes away storage near the peak. This design fails Clause 7.6.4(b) and must be regraded so that the upper bands gain at least as much as they lose, as in the first trial.