Draft v1.0 prepared by NEER. Not adopted by the Government of Maharashtra, and has no legal force. About this draft

Chapter 1Policy, Applicability and Adoption


1.1 Purpose and objectives

1.1.1 This Manual sets the minimum standards for the planning, design, construction, operation and maintenance of stormwater systems in Maharashtra. It applies to private development and to public works, as set out in Clause 1.5.

1.1.2 The Manual has the following objectives:

  • (a) to make stormwater management a condition of development approval, so that new development and redevelopment do not increase flood peaks or runoff volumes downstream;
  • (b) to retain frequent rainfall on site, so that groundwater recharge is sustained and pollutant loads are reduced;
  • (c) to size storage for the long-duration multi-day south-west monsoon storms of June–September, as well as for short-duration intensities;
  • (d) to design outfalls for tidal and creek tailwater, and river tailwater raised by dam releases and backwater, including the case where the outfall is closed;
  • (e) to protect tanks (talavs), marshes, rivers, supply channels and surplus courses as part of the drainage system;
  • (f) to give every element of the drainage network a safe overland path for the 1% AEP (100-yr) storm;
  • (g) to make design inputs, approvals and facility records public, so that designs can be checked and repeated; and
  • (h) to make sure that facilities, once built, are maintained and remain effective.

1.1.3 This Manual does not replace the rainwater harvesting (RWH) mandate, the Unified Development Control and Promotion Regulations for Maharashtra State, 2020 and the Development Control and Promotion Regulations for Greater Mumbai, 2034 (UDCPR 2020 and DCPR 2034), or the statutes on waterbodies. It adds runoff control requirements to them (Clause 1.8).

Commentary. Maharashtra's floods come from three mechanisms, often together. The first is monsoon rain on a tide-locked coast. Mumbai's island city is largely reclaimed land with drains that date from the 1860s; of its 186 storm-water outfalls, 45 lie below mean sea level and only 6 above high tide (FFC, 2006; MCGM, 2008). On 26 July 2005 Santacruz recorded 944.2 mm in 24 hours (IMD) while a high tide of 4.48 m peaked at 15:30, inside the most intense hours of the storm (FFC, 2006). The floods of 24 July to 5 August 2005 affected 33 of the State's 34 districts, killed more than 1,100 people and caused losses put at Rs 10,000 crore (CAG, 2006). The second is river flooding from dam releases and backwater. On the Krishna, Panchganga and Warna, Kolhapur and Sangli flooded in 2005, 2019 and 2021; in August 2019 the releases from nine reservoirs came almost together, the river at Narsoba Wadi rose above its 1914 and 2005 levels, and 55 people died in the two districts (SANDRP, 2020; PTI, as reported). Chiplun on the Vashishti was more than half submerged on 22 July 2021 (as reported). The third is the short, intense storm on encroached nallahs and lake outlets inland: the Ambil Odha flood in Pune on 25 September 2019, in which some 17 to 26 people died (reports differ), and the Nagpur storm of 23 September 2023, more than 109 mm in about three hours, when Ambazari lake overflowed into the Nag river and four people died (as reported).

Lost and neglected storage makes all three worse. Mangroves, mudflats and salt pans around Mumbai have been reclaimed; some 10,000 structures were removed from the banks of the Mithi after 2005 (MMRDA, 2023); the holding ponds of Navi Mumbai silt up; and Pune's river-front works narrow the river in places (as reported). Mumbai's own upgrade has lagged: the BRIMSTOWAD works sanctioned at Rs 1,200 crore had cost Rs 1,764.55 crore by September 2013, only 16 of 58 works were complete, four of eight pumping stations had no site, and "flooding of low-lying areas, even when rainfall is less than 50 mm per hour, continues to be a regular feature" (CAG Report No. 6 of 2014). Mogra and Mahul, two of those stations, were still unbuilt in 2026 (as reported). No stormwater design standard for a city outside Mumbai was found in research for this Manual. Objectives (b) to (e) address the storage and tailwater failures, which a drain-sizing manual alone cannot fix.

No national instrument requires on-site detention. CPHEEO (2019) is advisory and describes peak control only as typical practice. NDMA (2010) says detention and retention "will" be included but gives no sizing rule. MBBL 2016 and UDCPR 2020 and DCPR 2034 mandate RWH only. Objective (a) is therefore the main new step this Manual takes.


1.2 Stormwater management hierarchy

1.2.1 Every development to which Chapter 4 applies shall consider stormwater measures in the following order. A designer shall not use a lower measure in place of a higher one that is practicable on the site.

  1. Preserve — keep or restore natural drainage features, tanks, wetlands, permeable soils, trees and overland flow paths (Chapter 7).
  2. Retain — hold the runoff from the retention depth of Annex 2E on site, by infiltration, reuse or evapotranspiration (Chapters 4 and 8).
  3. Detain — store larger storms temporarily and release them at or below the rates in Chapter 4, checked against downstream and tailwater conditions (Chapters 4 and 5).
  4. Convey — carry the remaining flow safely in the minor system, and the 1% AEP flow in the major system (Chapters 6 and 9).

1.2.2 Maintenance underlies all four measures. A measure that cannot be maintained by its owner under Chapter 10 shall not be credited.

1.2.3 Credits from higher measures reduce the requirements of lower ones. Preserved areas and retained volume reduce detention storage as set out in Chapter 4.

Figure 1.1 — Stormwater management hierarchy Four stacked bars, widest at top: Preserve, Retain, Detain, Convey, with a Maintain bar underneath spanning all. A downward arrow shows the order of consideration; an upward arrow shows that credits from higher measures reduce lower ones. Order of consideration Credits reduce lower measures 1 PRESERVE Chapter 7 Keep tanks, wetlands, marshes, permeable soils, trees and flow paths 2 RETAIN Chapters 4, 8 Hold the Annex 2E depth on site: infiltrate, reuse, evaporate 3 DETAIN Chapters 4, 5 Store larger storms; release below pre-development peaks 4 CONVEY Chapters 6, 9 Minor system, plus a 1% AEP overland path MAINTAIN — underlies every measure Chapter 10 A measure that its owner cannot maintain earns no credit (Clause 1.2.2) Use a lower measure only for what the measures above it cannot practicably achieve (Clause 1.2.1).

Figure 1.1 — Stormwater management hierarchy: preserve, retain, detain, convey, with maintenance underlying each measure. Original drawing for this Manual, adapted from Mid-America Regional Council / Kansas City Metro Chapter APWA, "Layers of Stormwater Management", APWA 5600 Manual Factsheet, 2025 (concept).

Commentary. The order follows the "layers" of Kansas City Metro APWA Section 5600, Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet, 2025). The same logic is behind Georgia's runoff-reduction standard and CSE's "attenuate and infiltrate first" principle (CSE, 2023). For Maharashtra, the top layer has a particular meaning: much of the State's flood storage sits in the mangroves, mudflats and creeks of the Konkan, the floodplains inside the WRD blue and red flood lines, the holding ponds of Navi Mumbai, and the talavs of the interior, including some 6,700 ex-malgujari tanks in eastern Vidarbha (as reported). Since the High Court's judgment of 17 September 2018 (PIL No. 87 of 2006), every mangrove in the State is protected with a 50 m buffer (as reported), but floodplains without drawn flood lines, and most tanks, have no comparable protection beyond the distances in UDCPR 2020. Losing that storage cannot be offset economically by pipes.


1.3.1 Notification. This Manual shall be given statutory effect by the Government of Maharashtra through:

  • (a) an amendment to UDCPR 2020 and DCPR 2034 that makes compliance with this Manual a condition of planning permission, building permit, layout approval and completion certificate, for development to which Clause 1.5 applies; and
  • (b) bye-laws or standing orders of each urban local body (ULB), adopting the Manual for works executed or approved by that ULB, including the ULB's own drains and roads.

1.3.2 Higher State standards. The design return periods and performance criteria of this Manual exceed the national advisory minimums of the CPHEEO Manual on Storm Water Drainage Systems (2019). The State shall constitute, by notification, a high-powered committee (the State Stormwater Technical Committee, Clause 1.9) to adopt these higher standards. This is the route that CPHEEO (2019) provides for higher return periods.

1.3.3 Precedence. Within its scope, this Manual governs where it is stricter than CPHEEO (2019), IRC:SP:42-2014, IRC:SP:50-2013 or any departmental standard. Where a statute or statutory rule sets a stricter requirement (for example a waterbody setback), the statute governs.

1.3.4 Design-practice standard for public works. Departments and ULBs that procure drainage, road or waterbody works shall require compliance with this Manual in detailed project reports (DPRs) and contracts, from the dates in Clause 1.11.

Commentary. Maharashtra has two building codes, both made under the Maharashtra Regional and Town Planning Act, 1966. UDCPR 2020 has applied since 3 December 2020 to every Planning Authority and Regional Plan area except Greater Mumbai, MIDC, NAINA, JNPT, the hill-station Municipal Councils, the eco-sensitive regions notified by MoEF&CC and Lonavala (UDCPR 1.1). DCPR 2034 applies in Greater Mumbai; the Development Plan was sanctioned by UDD notification No. TPB-4317/629/CR-118/2017/DP/UD-11 of 8 May 2018. Both codes already bar sites within 15 m of a river or 6 m of a nallah (UDCPR 3.1.1(ii); DCPR 18(b)), require rainwater harvesting on plots of 500 m² or more, and set a plinth above the high flood level; UDCPR also refuses sites "incapable of being well drained" (3.1.1), adopts WRD's blue and red flood lines (3.1.3), and makes the developer build the storm drains of a layout (2.7.2). Neither sets a design storm, return period, runoff coefficient or detention requirement. A modification of both under the MRTP Act is the natural route for a statewide condition of approval; the two tracks are why Clause 1.3.1(a) names both. MoHUA told Parliament in July 2026 that urban flooding "falls under the purview of the State Governments and the ULBs" and listed the CPHEEO manual among "advisory guidelines" (Lok Sabha AU1847). The State therefore needs no central approval to adopt higher standards. CPHEEO's Note 2 to Table 4.1 (§4.4.1.4) allows "a high powered committee constituted by State/UT Government through a notification" to adopt higher return periods. Clause 1.3.2 uses that route so that higher standards are on record for centrally funded schemes.


1.4 Definitions

1.4.1 The following terms apply throughout this Manual. Chapter-specific terms are defined in each chapter (for example Clause 2.2).

Term Meaning in this Manual
Approving Authority (the Authority) The body that grants planning permission, building permit or layout approval for a development, or that sanctions a public work: MCGM in Greater Mumbai, under DCPR 2034; elsewhere, the Planning Authority under the Maharashtra Regional and Town Planning Act, 1966 and UDCPR 2020 (a Municipal Corporation, Municipal Council or Nagar Panchayat, a Special Planning Authority such as CIDCO, or MMRDA, PMRDA or NMRDA in its area), or a department for its own works.
Applicant The owner, developer or department that seeks approval, and its successors in title.
Development Any building, layout, sub-division, road, paving or land-use change that requires approval under UDCPR 2020 and DCPR 2034 or that is executed as a public work.
Redevelopment Development on a site where impervious cover already exists.
Land disturbance Clearing, grading, excavation, filling or paving of land, measured in plan area over the whole of a common plan of development (Clause 1.5.5).
Impervious area Roofs, paving, compacted gravel, decks and other surfaces that prevent infiltration. Permeable paving designed to Chapter 8 is counted as pervious only for the area it treats.
New or replaced impervious area Impervious area created, or removed and rebuilt down to the subgrade, by the development. Resurfacing that leaves the base in place is not "replaced".
Retention Permanent removal of runoff from the drainage system on site, by infiltration, reuse or evapotranspiration (Chapter 4).
Detention Temporary storage of runoff with a controlled outlet, emptied after the storm (Chapter 4).
Rainwater harvesting (RWH) Collection of rainfall for supply or recharge under the RWH mandate. RWH storage is not detention unless Chapter 4 allows it.
Minor system Drains, pipes and inlets designed for the minor-system AEP of Chapter 6.
Major system The overland and floodway path that carries the 1% AEP (100-yr) flow (Chapter 6).
Pre-development condition Greenfield: open land in good condition for the mapped hydrologic soil group. Existing impervious cover is not counted (Chapter 3).
Flood-sensitive catchment The catchments of the Mithi river and Mahim Creek, of the tide-locked outfalls of Greater Mumbai and of the Navi Mumbai holding ponds, the river-fronts of Kolhapur on the Panchganga and of Sangli and Miraj on the Krishna and the Warna, the catchments of the Ambil Odha in Pune and of the Nag river in Nagpur, and the low-lying town of Chiplun on the Vashishti, and any catchment the Authority notifies (Chapter 4; Annex 1B).
Waterbody A river, stream, canal, tank (talav), lake, pond, marsh, supply channel or surplus course, whether perennial or seasonal (Chapter 7).
Regional facility A detention, retention or tank storage facility serving more than one development, built or restored under a basin plan (Chapter 4).
Tier A / Tier B authority An Approving Authority classed under Clause 1.6.
Policy supplement The set of adoptable alternative clauses in Clause 1.7 and Annex 1C.
Drainage report The preliminary or final report required by Chapter 10.
Registered professional A person registered under UDCPR 2020 and DCPR 2034 to prepare and sign the relevant plans, with any further qualification required by Clause 10.6.
Compliance calculator The State-issued tool for computing and reporting compliance (Clause 10.5).
Maintenance declaration The registered undertaking by an owner to maintain a stormwater facility (Clause 10.10).
Variance Approval to depart from a numeric requirement, with equivalent performance shown (Clause 1.10).
Waiver Approval that a requirement does not apply to a site, on the grounds in Clause 1.10.
Notified Published by the Government or the State Stormwater Technical Committee in the Maharashtra Government Gazette.

Commentary. "Replaced" impervious area is defined to the subgrade so that redevelopment of a fully paved site is captured, while routine resurfacing is not. This follows the approach of the APWA 5600 (2025.01) redevelopment triggers (MARC Supplement, 2025).


1.5 Applicability

1.5.1 Who is covered. This Manual applies to:

  • (a) all development requiring planning permission, building permit or layout approval under UDCPR 2020 and DCPR 2034;
  • (b) all drainage, road, bridge, culvert, waterbody and flood-mitigation works executed by a ULB, a State department, a board, or a State undertaking; and
  • (c) works executed by Central agencies or their contractors within Maharashtra, to the extent that the Authority's approval or no-objection is required.

1.5.2 Retention and detention threshold. Chapters 4 and 5 (retention, detention, downstream and tailwater analysis) apply to any development that, over the common plan of development, involves:

  • (a) land disturbance of 0.1 ha or more; or
  • (b) new or replaced impervious area of 500 m² or more.

1.5.3 RWH. The existing RWH mandate continues to apply as set by Regulation 13.3 of UDCPR 2020 and Regulation 62 of DCPR 2034: rainwater harvesting structures of the types in their Schedules on plots of 500 m² or more (and, under UDCPR, on the layout open spaces and amenity spaces of housing societies), with a levy of up to Rs 1,000 a year for every 100 m² of built-up area where they are not provided or maintained, as now. This Manual does not change it.

1.5.4 Provisions that apply at every size. The following apply to all development under Clause 1.5.1, whatever its size, unless exempted by Clause 1.5.8:

  • (a) no sewage connection to a storm drain (Chapter 8);
  • (b) lowest habitable floor and openings at or above the 1% AEP level plus 0.5 m, where a 1% AEP level is mapped or determinable (Chapter 6);
  • (c) waterbody setbacks and the no-fill zone (Chapter 7); and
  • (d) no obstruction of a natural drainage path or major-system flow path (Chapter 6).

1.5.5 Common plan of development. The thresholds of Clause 1.5.2 apply to the total area of a development, including all phases, plots and sub-divisions under one layout approval or one ownership at the date of application. A development shall not be divided to avoid the thresholds.

1.5.6 Redevelopment. For redevelopment, the thresholds apply to new plus replaced impervious area. Retention and detention apply to the whole of the new and replaced impervious area, and the pre-development condition is greenfield (Clause 1.4). Where greenfield control cannot be achieved on a constrained redevelopment site, the relief route of Clause 4.5.6 applies: a minimum on-site cut of 50% from existing peaks, with the shortfall paid as fee-in-lieu into basin storage.

1.5.7 Linear public works. For roads, widening and other linear works, the impervious area threshold applies to the added impervious area within each drainage catchment crossed. Retention and detention shall be provided within the right of way, or in a regional facility under Chapter 4, where the right of way cannot hold them.

1.5.8 Exemptions. The following are exempt from Chapters 4 and 5:

  • (a) a single dwelling on its own plot, where the thresholds of Clause 1.5.2 are not met; and
  • (b) linear road resurfacing that adds no impervious area.

Exempt development remains subject to the RWH mandate and to Clause 1.5.4.

1.5.9 Applicability determination. The Applicant shall record the applicability decision on Form 1-1 (Applicability Determination) with the first submittal under Chapter 10. The Authority may confirm or correct it at the pre-application stage.

Figure 1.2 — Applicability decision flowchart Flowchart for Clause 1.5: approval test, exemption test, size threshold test, and flood-sensitive catchment test, leading to the requirements that apply. Development or public work (Clause 1.5.1) Needs building-rules approval, or is it a public work? No Manual not triggered; other rules apply Yes Exempt under Clause 1.5.8? (single dwelling below the threshold, or road resurfacing that adds no impervious area) Yes Exempt from Chapters 4–5. RWH (where mandated) and Clause 1.5.4 still apply No Land disturbance ≥ 0.1 ha, or new or replaced impervious area ≥ 500 m² (Clause 1.5.2)? No Below threshold: RWH (where mandated) and Clause 1.5.4 apply Yes Chapters 4 and 5 apply: retention, detention, downstream and tailwater analysis (+ RWH, 1.5.4) In a flood-sensitive catchment (Annex 1B)? Yes Mixed-frequency rule; full methods only; no Policy Supplement alternatives No Standard rule: Q_post ≤ 0.9 × Q_pre Tier B: design-aid route may be used (Clause 1.7) Decision Chapters 4–5 requirements Chapters 4–5 do not apply

Figure 1.2 — Applicability decision flowchart for Clause 1.5. Original drawing for this Manual.

Commentary. The thresholds have no single direct precedent; they are set by this Manual. Precedents span a wide range:

  • Singapore controls peak runoff from developments of 0.2 ha or more (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5).
  • Malaysia's 2008 DID checklist used on-site detention for sites up to 0.1 ha and community ponds above that.
  • The APWA 5600 (2025.01) Policy Supplement offers alternative triggers of ¼ acre (about 0.1 ha) disturbed, or 1 acre (about 0.4 ha) with 10,000 sq ft (about 930 m²) impervious, and warns agencies not to exceed a 1-acre trigger.
  • MBBL 2016 makes recharge mandatory for buildings over 500 m².

The 0.1 ha / 500 m² trigger sits at the strict end of these, because typical Maharashtra plots are small and the cumulative effect of many small plots is what fills Mumbai's drains. For small buildings, UDCPR 2020 sets a plinth of at least 30 cm above the surrounding ground and, in areas subject to flooding, at least 45 cm above the high flood level (Reg. 9.1); DCPR 2034 sets 60 cm above the high flood level in Greater Mumbai, or 45 cm for stilt and covered parking, with the architect certifying the basis (Reg. 37(1)).

Clause 1.5.4(b) has no direct precedent; this Manual sets it because floor levels are the cheapest protection a building can have, and it would be perverse to protect only large developments. Where no 1% AEP level is mapped, Chapter 6 gives the method for small sites.


1.6 Tiered adoption

1.6.1 Tier A authorities. The following are Tier A:

  • (a) the Municipal Corporation of Greater Mumbai (MCGM);
  • (b) every Approving Authority within the Mumbai Metropolitan Region (MMR) or the region of the Pune or Nagpur Metropolitan Region Development Authority (PMRDA, NMRDA), as those regions are notified from time to time: in the MMR, the Municipal Corporations of Thane, Navi Mumbai, Kalyan–Dombivli, Ulhasnagar, Bhiwandi–Nizampur, Mira–Bhayandar, Vasai–Virar and Panvel, CIDCO and any other Special Planning Authority, and MMRDA where it is the Planning Authority; the Pune, Pimpri-Chinchwad and Nagpur Municipal Corporations; PMRDA and NMRDA in their own areas; and the Municipal Councils and Nagar Panchayats in the three regions; and
  • (c) every other Municipal Corporation constituted under the Maharashtra Municipal Corporations Act, 1949, as constituted from time to time, including those of Nashik, Chhatrapati Sambhajinagar, Kolhapur, Sangli–Miraj–Kupwad, Solapur and Amravati.

1.6.2 Tier B authorities. All other Municipal Councils and Nagar Panchayats are Tier B.

1.6.3 What differs between tiers. All criteria of this Manual apply in both tiers. The tiers differ only in method and review:

Table 1.1 — Differences between Tier A and Tier B authorities

Item Tier A Tier B
Performance criteria (Chapters 2–9) Apply in full Apply in full
Hydrologic method for storage Hydrograph method (Chapter 3) Hydrograph method, or the design-aid route of Clause 1.7 where eligible
Compliance calculator (Clause 10.5) Required as a summary Required; may be the sole calculation on the design-aid route
Policy supplement alternatives (Clause 1.7) Only with State Stormwater Technical Committee concurrence May be adopted by council resolution
Technical review By the Authority By the Authority, with UDD regional support or an empanelled reviewer (Clause 10.7)
Flood-sensitive catchment rule Applies Applies

1.6.4 Moving between tiers. A Tier B authority may opt into Tier A by council resolution. The Government may notify a Tier B authority as Tier A when it becomes a Corporation, joins the Mumbai Metropolitan Region (MMR) or the region of the Pune or Nagpur Metropolitan Region Development Authority (PMRDA, NMRDA), or is found by a post-event review (Clause 10.16) to need the full methods.

1.6.5 Flood-sensitive catchments override tier. In a flood-sensitive catchment, whatever the tier, the alternatives of Clause 1.7 are available only as Table 1.2 allows: S-1 (the design-aid route) for sites of 0.5 ha or less (Clause 4.14.1), and S-5 fee-in-lieu where a basin plan has been notified (Clause 1.10.3(d)). S-2, S-3 and S-4 are not available.

Commentary. Municipal Corporation of Greater Mumbai, with its own Storm Water Drains department, and a Nagar Panchayat with one assistant engineer cannot be asked to review the same hydrograph models. The Kansas City solution was to keep one regional standard and publish adoptable alternatives for the most contested criteria, so that smaller agencies can "opt down" without leaving the standard (MARC Supplement, Nov 2025). The tiers here keep the performance criteria the same in both tiers and vary only the method, so that a building in a Tier B town is protected to the same level as one in Mumbai.


1.7 Policy supplement: adoptable alternatives

1.7.1 The Government shall publish, with this Manual, a Policy Supplement (Annex 1C) of alternative clauses. An Approving Authority may adopt one or more alternatives under the conditions in Clause 1.7.3.

1.7.2 The alternatives are:

Table 1.2 — Policy supplement: adoptable alternatives S-1 to S-5

No. Main-text requirement Adoptable alternative Eligibility
S-1 Storage sized by hydrograph method (Chapter 3) Design-aid route: retention and detention volumes taken from the unit-storage tables (m³ per ha, by rainfall zone, soil group and impervious fraction) in Annex 4 and the compliance calculator Sites ≤ 2 ha outside flood-sensitive catchments; ≤ 0.5 ha within them (as Clause 4.14.1)
S-2 Release rate Q_post(T) ≤ 0.9 × Q_pre(T), computed for the site Permissible site discharge (PSD): a tabulated unit-area release rate (m³/s/ha) by zone and AEP, derived from the 0.9 × Q_pre rule Any site outside flood-sensitive catchments
S-3 Waterbody setback extended to the mapped 1% AEP flood extent plus margin (Chapter 7) Fixed-width setback table by waterbody class, where no 1% AEP extent is mapped. Never less than the Zone 1 minimum of Clause 7.4.7, which is at least the statutory 15 m from a river and 6 m from a nallah Waterbodies with no mapped 1% AEP extent
S-4 Downstream analysis by hydraulic model (Chapter 5) Screening checklist of downstream capacity and known flooding, with a model only where the screen fails Sites < 1 ha, outside flood-sensitive catchments, not discharging to a tidal outfall
S-5 On-site detention Fee-in-lieu toward a regional facility or restored tank storage in a master-planned basin (Chapter 4) Where a basin plan has been notified

1.7.3 Conditions on adoption.

  • (a) An alternative shall not lower any criterion below the values of this Manual. S-1 and S-2 are simplified methods for meeting the same criterion. They are not lower criteria.
  • (b) A Tier B authority adopts an alternative by council resolution, sent to the State Stormwater Technical Committee within 30 days. A Tier A authority needs the Committee's concurrence before adoption.
  • (c) The adopted alternatives shall be published on the Authority's website and in the register of Clause 10.17.
  • (d) Retention (Annex 2E depth) cannot be replaced by any alternative, except where fee-in-lieu under S-5 funds equivalent retention in the same basin.
  • (e) The tables for S-1, S-2 and S-3 shall be issued by the State Stormwater Technical Committee, and reviewed with Chapter 2 (Clause 2.14).

Commentary. The supplement follows the model of the APWA 5600 (2025.01) Policy Supplement, which gives alternatives for the four most contested criteria (applicability, Rational Method limits, stream setback trigger, and Zone 2 setback width). Two of those map onto S-3 and onto the applicability threshold of Clause 1.5.2. Alternative S-3 copies the APWA answer to the same problem: the 1% AEP extent is not mapped for small drainage areas, so a fixed-width table is offered. S-2 follows the Kansas City 2011 shift from "match existing" to fixed unit-area release rates. Local agencies preferred a set rate because existing conditions were hard to determine consistently (MARC Evolution deck). It also reflects the Sydney Water permissible site discharge (PSD) method. The 2 ha / 0.5 ha limits for S-1 (matching Clause 4.14.1) and the 1 ha limit for S-4 have no direct precedent; they are set by this Manual.


1.8 Relationship with other instruments

1.8.1 This Manual shall be applied together with the instruments below. Where they overlap, Clause 1.3.3 governs.

Table 1.3 — Relationship with other instruments

Instrument Relationship
RWH mandate (UDCPR 2020, Reg. 13.3 and Schedule; DCPR 2034, Reg. 62) Continues unchanged: rainwater harvesting structures on plots of 500 m² or more (and, under UDCPR, on the layout open spaces and amenity spaces of housing societies), with a levy of up to Rs 1,000 a year for every 100 m² of built-up area for default. The Schedules list structure types (wells, recharge pits, trenches, storage tanks) but no storage volume per m². RWH storage is not detention unless it is a dedicated empty-on-arrival volume with an outlet, and tanks are assumed full at the start of SW monsoon storms (Chapter 4). Recharge structures may count toward retention where they meet Chapters 4 and 8.
Site, drainage and plinth provisions of UDCPR 2020 (Regs. 2.2, 2.7.2, 3.1.1 and 9.1) Continue. A site barred by Reg. 3.1.1 (insanitary or incapable of being drained, below the prescribed datum level, within the prohibitive flood-line zone, or wholly within 15 m of a river or 6 m of a nallah) is not made eligible by compliance with this Manual. The storm drains that Reg. 2.7.2 requires the developer of a layout to build are sized under Chapter 6. The plinth of Reg. 9.1 and the floor level of Clause 1.5.4(b) both apply; the higher governs.
DCPR 2034 for Greater Mumbai (Regs. 18(b), 37, 59 and 62, and the open-space rules) Continue. Reg. 18(b) bars sites within 6 m of a nallah or 15 m of a river unless drainage arrangements satisfy the Commissioner; a relaxation under it does not relax Chapter 7. The roof-drainage rule of Reg. 37 (one 10 cm pipe for every 40 m² of roof) and the 60 cm plinth above the high flood level continue, and the higher of that plinth and Clause 1.5.4(b) governs. Open space kept on unpaved "mother earth" counts as pervious (Chapter 3) and may hold retention. In URC schemes the nallah margin is 6 m or as MCGM's Storm Water Drains department requires, whichever is greater.
WRD blue and red flood lines, adopted by UDCPR 2020, Reg. 3.1.3 (WRD circulars of 1989 and 2 March 2015 and the MERI circular of 16 November 2015, as reported) Continue. River bank to blue line is a prohibited zone and blue to red line a restrictive zone, where building is allowed with the plinth 0.45 m above the red line; where no lines are drawn, a tentative blue line with a 50 m no-construction zone applies. The return periods (25-yr blue, 100-yr red) come from WRD practice, not from the regulation. This Manual does not redraw the lines; it uses the approved red-line level as a 1% AEP level (Clause 1.5.4(b)) and adds the corridor of Chapter 7 where wider. Pune's lines were not final in 2026 despite the High Court's order of 30 June 2025 in PIL No. 36 of 2021 (as reported).
Lakes, dams and wetlands (UDCPR 2020, Regs. 3.1.12 and 3.1.1(xiv); WRD circular of 8 March 2018) Continue. In Regional Plan areas no construction is allowed within 100 m of the high flood line of a natural lake; around dams the WRD distances apply; no site may lie wholly within 50 m of a wetland's mean high flood level under the Wetlands (Conservation and Management) Rules, 2017. Where these are wider than the setback of Chapter 7, they govern (Clause 1.3.3).
Maharashtra Regional and Town Planning Act, 1966 Development Plans and Regional Plans carry the reservations for nallahs, rivers, flood lines and lakes, and UDCPR 2020 and DCPR 2034 are sanctioned under the Act. Flood-sensitive catchments and regional facility sites should be shown in the plans. This Manual does not decide zoning.
Mumbai Municipal Corporation Act, 1888; Maharashtra Municipal Corporations Act, 1949; Maharashtra Municipal Councils, Nagar Panchayats and Industrial Townships Act, 1965 Drains vest in the local body. In Mumbai their construction, maintenance and cleaning is an obligatory duty of MCGM (s.61(a)), ss.220–239 give its drainage powers, and s.239 lets the Commissioner require separate drains for sewage and for rain-water; Chapter 8 applies the separation statewide. The drain sections of the 1949 and 1965 Acts were not reviewed for this Manual [TBC].
Mangrove protection: judgment of the Bombay High Court of 17 September 2018 in PIL No. 87 of 2006 All mangroves in the State, with a 50 m buffer, are protected, and a public project may cut mangroves only with the High Court's leave under para 83(viii) (as applied in WP (L) No. 17795 of 2026, decided 17 September 2026). An outfall extension, nallah widening, holding pond or pumping station in a mangrove belt therefore needs that leave as well as CRZ clearance; Chapters 5 and 7 require the designer to show either.
CRZ Notification 2019, through the approved Coastal Zone Management Plans Mumbai's CZMP under CRZ 2019 has been approved, with mangroves and their 50 m buffer mapped as CRZ-IA; the plans for Thane, Palghar, Raigad, Ratnagiri and Sindhudurg were approved by NCZMA on 1 August 2023 (as reported) and their final notification is [TBC]. MCZMA's no-objection is needed for development in the CRZ (DCPR 2034, Reg. 59). CRZ categories and lines are taken from the approved maps, and govern where wider than Chapter 7 (Clause 1.3.3).
Statutory waterway setback (UDCPR 2020, Reg. 3.1.1(ii); DCPR 2034, Reg. 18(b)) 15 m from the edge of the water mark of a river and 6 m from that of a nallah. In UDCPR the bar applies only where the entire site lies within the strip, and the 15 m and 9 m distances of Regs. 3.4.5 and 4.12 apply only to green belts and open space. The setback of Chapter 7 (Clause 7.4.7) is never less than 15 m or 6 m, and is wider where the hydraulic corridor of Chapter 7 requires; that wider part is stricter than the statute and is set by this Manual.
CPHEEO Manual on Storm Water Drainage Systems (2019) Engineering reference. This Manual sets higher return periods under Clause 1.3.2.
NDMA Guidelines on Management of Urban Flooding (2010) and MoHUA SOP (2017) This Manual puts into effect the NDMA directives on catchment-based design, detention and retention, waterbody protection and climate-adjusted IDF.
NDMA Urban Flood Risk Management Programme (UFRMP) and AMRUT 2.0 Works funded under these programmes shall comply with this Manual. The development controls of Chapters 4–5 protect the capacity those works create.
IRC:SP:42-2014 and IRC:SP:50-2013 Apply to road drainage only where they do not conflict with Chapter 6.
MBBL 2016, Chapter 9 Model for RWH and for the inspection regime in Chapter 10.

Commentary. RWH in Maharashtra is framed as a water supply and recharge measure. It works well for that purpose. It cannot, however, be relied on for flood control in the SW monsoon, because RWH sumps are usually full or the ground saturated by the time a July or August monsoon storm arrives after weeks of rain. The Manual therefore keeps harvest volume and attenuation volume apart, while letting recharge count as retention where it truly removes water from the system.

Mumbai is the one city in the State with a stated drainage design basis, and it is spending heavily to meet it: BRIMSTOWAD's works since 2007, the widening of the Mithi to about 30 m and its deepening by about 2 m, and, from July 2026, a flood-mitigation programme reported at Rs 10,000 crore for some 300–350 chronic flooding locations, with IIT Bombay preparing the detailed project report (MMRDA, 2023; as reported). No development-control condition stops new plots in the same catchments from using up the capacity such works create. Linking Chapters 4–5 to approvals closes that gap.

Maharashtra's planning law already holds many of the tools. UDCPR 2020 adopts WRD's flood lines and refuses sites that cannot be drained; DCPR 2034 lets MCGM's Storm Water Drains department fix nallah margins in some schemes; and UDCPR 3.1.13 requires every department that imposes a restriction to give the Planning Authority the map of it, so that no applicant has to seek a separate no-objection certificate. That clause is the route for the flood-sensitive catchments, drainage corridors and regional facility sites of this Manual: they should be lodged with the Planning Authority and shown in the Development Plans, not issued as a new NOC. None of these instruments says how high a flood reaches or how much storage a filled plot removes; this Manual supplies that technical test.


1.9 Roles and responsibilities

1.9.1 The responsibilities below apply under this Manual. They do not change any agency's statutory powers.

Table 1.4 — Roles and responsibilities under this Manual

Agency Role under this Manual
Urban Development Department (UDD) Would own the Manual. Would issue the modification of UDCPR 2020 and DCPR 2034 under the MRTP Act. Would constitute and service the State Stormwater Technical Committee. Sanctions Development Plans and Regional Plans, in which flood-sensitive catchments and regional facility sites should be shown. Technical support to Tier B authorities, through its Town Planning offices. Maintains the empanelled reviewer list (Clause 10.7).
State Stormwater Technical Committee (Clause 1.3.2) Adopts higher standards. Issues Annexes, tables and the compliance calculator. Concurs with Tier A alternatives. Decides variances referred to it. Reviews the Manual (Clause 1.12).
Municipal Corporation of Greater Mumbai (MCGM), Storm Water Drains department Approving Authority in Greater Mumbai under DCPR 2034. Owner of the storm-water drains, nallahs, outfalls and pumping stations, whose construction, maintenance and cleaning is an obligatory duty (MMC Act 1888, s.61(a); ss.220–239). Sets nallah margins where DCPR 2034 leaves them to it. Would apply this Manual to its own works, including the BRIMSTOWAD works and the hotspot programme. Inspects and enforces (Clauses 10.12–10.15).
Other Municipal Corporations, Municipal Councils and Nagar Panchayats Approving Authority for development permission under UDCPR 2020 in their areas. Owner of the public drains vested in them under the Maharashtra Municipal Corporations Act, 1949 or the Municipal Councils Act, 1965. Receive handed-over assets (Clause 10.14). Inspect and enforce (Clauses 10.12–10.15).
Mumbai Metropolitan Region Development Authority (MMRDA) Owner of the downstream reach of the Mithi (about 6 km) and secretariat of the Mithi River Development and Protection Authority. Applies this Manual to the works it executes and, where it is the Planning Authority, to the development it approves.
Mithi River Development and Protection Authority (MRDPA) Coordinates the Mithi works of MCGM and MMRDA. Would agree the Mithi flood-sensitive catchment boundary and the design levels of the river (Chapters 4, 5 and 7).
City and Industrial Development Corporation (CIDCO) Special Planning Authority for its areas, including NAINA. Builder of Navi Mumbai's holding ponds and drains. Would provide the pond levels and gate operating rules used for tailwater (Chapter 5), and reserve regional facility sites in its plans.
Pune and Nagpur Metropolitan Region Development Authorities (PMRDA, NMRDA) Approving Authority for development permission in the parts of their regions where they are the Planning Authority. Reserve regional facility sites and drainage corridors in their plans.
Water Resources Department (WRD), with the Maharashtra Engineering Research Institute (MERI) Draws the blue (25-yr) and red (100-yr) flood lines, approved by the regional Chief Engineer (UDCPR 3.1.3; WRD circulars, as reported), and the high flood levels around lakes and dams (UDCPR 3.1.12). Operates the dams whose releases set river tailwater. Provides design water levels and release scenarios (Chapters 5 and 7). Consents to outfalls into its works. Runs the Hydrology Project rain-gauge network (Annex 2A).
Maharashtra State Disaster Management Authority (MSDMA) and the District Disaster Management Authorities (DDMAs) Hazard and flood mapping. Notify or recommend flood-sensitive catchments. Pre-monsoon preparedness, including orders under s.33 of the Disaster Management Act, 2005. Lead the post-event review (Clause 10.16).
Maharashtra Coastal Zone Management Authority (MCZMA) Recommends CRZ clearance and gives the no-objection required by DCPR 2034 (Reg. 59) for outfalls, drains, holding ponds and pumping stations in the CRZ. Advises on CRZ categories and the HTL from the approved Coastal Zone Management Plans.
Forest Department (Mangrove Cell) Custodian of mangroves on government land. Consulted on any work in a mangrove or its 50 m buffer, for which the leave of the High Court is needed under the judgment of 17 September 2018 (Chapters 5 and 7).
Groundwater Surveys and Development Agency (GSDA) Advises on groundwater levels, recharge and infiltration rules (Chapters 3, 4 and 8).
Maharashtra Pollution Control Board (MPCB) Regulates discharges of sewage and effluent into rivers and storm drains. Supports the removal of sewage connections to storm drains (Chapter 8).
Revenue Department Maintains land records under the Maharashtra Land Revenue Code, 1966, including the nallahs, tanks and government land used for setbacks and storage rules.

Commentary. Ownership of Maharashtra's drainage is split. In Mumbai, MCGM's Storm Water Drains department, a separate department since November 1993 on BRIMSTOWAD's advice, owns the drains, nallahs, outfalls and pumping stations; the Mithi is divided between MCGM (about 11.84 km) and MMRDA (about 6 km) under a UDD resolution of 29 July 2015, with the Mithi River Development and Protection Authority, formed on 19 August 2005, as coordinator (MMRDA, 2023). Navi Mumbai's holding ponds and drains were built by CIDCO and later handed to the Municipal Corporation (as reported). Outside the cities, WRD draws the flood lines and operates the dams whose releases set river levels at Pune, Kolhapur, Sangli and Chiplun, while the local bodies own the drains that discharge into those rivers; in Nagpur a High Court-monitored committee has directed the work on Ambazari lake and the Nag river (as reported). A manual that names one owner for each task does not fix institutions by itself, but it removes ambiguity about who signs what.


1.10 Variances and waivers

1.10.1 Variance. The Authority may grant a variance from a numeric requirement where the Applicant shows, through a report certified under Clause 10.6, that:

  • (a) compliance is impracticable because of site conditions such as a high groundwater table, contaminated soil, rock, or a site area too small for the required facility; and
  • (b) the proposed alternative gives equal or better performance at the downstream point of Chapter 5, or the shortfall is made up by fee-in-lieu or off-site works in the same catchment.

1.10.2 Waiver. The Authority may waive Chapter 4 detention requirements (not retention) where a hydraulic analysis certified under Clause 10.6 shows that the site discharges directly to the sea, or to a tidal reach with no flood-prone property downstream, and that undetained flow does not worsen the outfall-closed condition of Chapter 5. A site that drains into a holding pond whose gates close at high tide, as in Navi Mumbai, or through a sluice in a Konkan khajan bund, does not discharge to a tidal reach for this clause, because the gate is closed whenever the tide outside is higher than the water behind it.

1.10.3 No variance or waiver. No variance or waiver shall be granted for:

  • (a) a sewage connection to a storm drain;
  • (b) the lowest habitable floor level of Chapter 6;
  • (c) any reduction of a waterbody setback below the Zone 1 minimum of Clause 7.4.7, which is at least the statutory 15 m from a river and 6 m from a nallah, or any fill or construction in the no-fill zone of Chapter 7; or
  • (d) the retention requirement in a flood-sensitive catchment, except by fee-in-lieu under Clause 1.7.

1.10.4 Procedure.

  • (a) The request shall be made on Form 1-2 (Variance / Waiver Request) with the preliminary drainage report.
  • (b) A Tier B authority shall refer any variance on a site of 1 ha or more to the State Stormwater Technical Committee.
  • (c) A decision shall state its reasons and any conditions, and shall be entered in the public register of Clause 10.17.
  • (d) A variance runs with the approval. It lapses if the approval lapses.

Commentary. The 2006 APWA 5600 included a waivers section (5601.6), and Georgia allows waivers where downstream analysis shows a peak control is unnecessary. The waiver of Clause 1.10.2 is narrow: on a tidal coast, undetained flow can help by passing through before the tide closes the outfall, but only an analysis can show that. This Manual requires every decision to be published because publication deters case-by-case erosion of the standard; in Pune, for example, the river flood lines were redrawn in 2016 some 50–60 m inward of the 2011 lines, and an affidavit of WRD's own engineer later called both sets unscientific (SANDRP, 2024 and 2026, as reported).


1.11 Transition provisions

1.11.1 Effective date. This Manual takes effect for new applications 6 months after notification (the effective date).

1.11.2 Applications in process. An application filed complete before the effective date may be decided under the rules in force when it was filed, if a decision is issued within 12 months of the effective date. Otherwise, this Manual applies.

1.11.3 Phased start for Tier B. In Tier B authorities, Chapters 4 and 5 apply from 24 months after notification, except in flood-sensitive catchments, where they apply from the effective date.

1.11.4 Public works. DPRs sanctioned before the effective date may proceed as sanctioned. Any DPR revised or re-tendered after the effective date shall comply. Departments shall report non-compliant works in progress to the State Stormwater Technical Committee within 12 months.

1.11.5 Before the annexes are issued. Until an annex referred to in this Manual is issued, the Applicant shall use the method stated in the clause, with values agreed with the Authority and recorded in the drainage report.

Commentary. The 6-month lead time matches the lead time for NIH-DHAARA updates in Clause 2.14.2. Singapore gave a similar interval for its 2025 detention addendum (issued 16 Apr 2025, applied from 1 Oct 2025). The 12- and 24-month periods are set by this Manual to let Tier B authorities train staff and to let the State issue the design-aid tables (Clause 1.7).


1.12 Review and amendment

1.12.1 The State Stormwater Technical Committee shall review this Manual every 10 years, and after any event that exceeds the 1% AEP design depth as set out in Clause 2.14.1.

1.12.2 Amendments shall be notified in the Gazette, published with a change log, and take effect 6 months after notification unless the notification states otherwise.

1.12.3 Any person may propose an amendment to the Committee. Proposals and the Committee's decisions shall be published.


References (chapter)

Annexes and forms

Annex / Form Content
1A List of Tier A authorities, with the MMR, PMRDA and NMRDA boundaries
1B Maps of flood-sensitive catchments
1C Policy Supplement: text of alternatives S-1 to S-5 and model council resolution
1D Model UDCPR/DCPR amendment and model ULB bye-law
Form 1-1 Applicability Determination
Form 1-2 Variance / Waiver Request