Draft v1.0 prepared by NEER. Not adopted by the Government of Maharashtra, and has no legal force. About this draft

Chapter 6Minor and Major Drainage Systems


6.1 Purpose and scope

6.1.1 This chapter sets the level of service and the hydraulic criteria for the conveyance system that carries runoff from a development, a road or a public drainage scheme to a receiving waterway, tank or outfall. It covers:

  • (a) the dual drainage concept: a minor system and a major system (Clause 6.3);
  • (b) design return periods by land use and road class (Clause 6.4);
  • (c) street hydraulics: spread, depth and flow hazard (Clause 6.5);
  • (d) inlets, including clogging (Clause 6.6);
  • (e) pipes and open and covered drains (Clause 6.7);
  • (f) hydraulic grade line analysis (Clause 6.8);
  • (g) overland flow paths, ponding at sags and building floor levels (Clauses 6.9 to 6.11);
  • (h) culverts and road crossings (Clause 6.12); and
  • (i) Maharashtra construction-practice requirements for covered drains, silt, solid waste, utilities and desilting access (Clause 6.13).

6.1.2 The detailed hydraulic design of individual structures (culverts, channels, energy dissipators, screens, pumps, gates, manholes) is in Chapter 9. Rainfall is in Chapter 2, runoff methods in Chapter 3, on-site storage in Chapter 4, tailwater in Chapter 5, waterbodies in Chapter 7 and water quality in Chapter 8.

6.1.3 This chapter applies to all public drains, all roads with kerbs or roadside drains, and all private drainage systems in developments that meet the applicability thresholds of Chapter 1. In Tier B local bodies, the simplified procedures and design aids referred to in Chapter 1 may be used for elements serving ≤ 16 ha, but the criteria of this chapter still apply.

Commentary. Maharashtra's drains have been designed for frequent storms, and outside Mumbai with no stated level of service at all. Mumbai's island-city drains, more than 100 years old, were designed for 25 mm/h at a runoff coefficient of 0.5 "during low tide hours". The Natu Committee (1975) recommended 50 mm/h at C = 1.0, the BRIMSTOWAD report (1993) reiterated it, and the Fact Finding Committee kept it for small catchments (FFC, 2006; CAG Report No. 6 of 2014). By BRIMSTOWAD's own table, 50 mm/h is about a "2 in 1 year" one-hour storm, roughly a six-month event; the 1-in-10-year one-hour intensity in the same table is 109 mm/h. The committee added 70 mm/h (1 in 10 years) for river channel corridors, 80 mm/h (1 in 25) for cross-drainage works on feeder roads and 100 mm/h (1 in 100) for arterial roads, and asked MCGM to build a 15-minute IDF; none was found during research. The CAG found that "flooding of low-lying areas, even when rainfall is less than 50 mm per hour, continues to be a regular feature" (2014). Outside Mumbai, no State or municipal design standard for storm drains was found: neither UDCPR 2020 nor DCPR 2034 has a drain-design clause, and UDCPR Regulation 2.7.2 makes the developer build a layout's storm drains without saying what they must carry. In July 2026 MCGM announced a ₹10,000 crore programme for 300 to 350 chronic flooding spots, with IIT Bombay preparing the DPR (press report); it is a works programme, not a new design standard. Fixing the rainfall (Chapter 2) is only half the answer. The other half is a second, surface-level system that carries the flows the pipes cannot, without flooding buildings. That is the dual drainage concept of this chapter, taken from Kansas City Metro APWA Section 5600 (5601.8, Levels of Service), which requires every element to have a 1% AEP overflow path.


6.2 Definitions

Term Meaning in this Manual
Minor system Inlets, pipes, covered drains and open drains that carry runoff up to the minor design AEP of Table 6.1 without surcharge above the limits of Clause 6.8.
Major system The surface flow paths (streets, overland flow paths, open channels, floodways and storage) that carry flow above the capacity of the minor system, up to the 1% AEP (100-yr) event.
Overland flow path A defined surface route, in public land or a recorded easement, that carries major-system flow to a receiving waterway.
Spread (T) Width of flow in the gutter and carriageway, measured from the face of the kerb.
Sag A low point on a road or flow path from which water can leave only through an inlet or by ponding to an overflow level. A trapped sag has no surface overflow route.
Clogging factor The fraction of an inlet's clean hydraulic capacity assumed lost to debris (Clause 6.6.3).
Hydraulic grade line (HGL) The line joining the free-surface levels in a conduit system, or the piezometric levels where the system is under pressure.
Covered drain A rectangular drain, usually beside a road, closed by cast-in-situ or precast cover slabs that form a footpath.
Sediment allowance The depth or area of a drain or pipe assumed filled with silt when its design capacity is computed (Clause 6.7.8).
Check event An AEP rarer than the design AEP at which the combined minor and major system must still meet the limits of Table 6.2.
High-density area An area notified as such by the approving authority under Clause 6.4.4.
Class I area An urban local body with a population of 1 lakh or more (the CPHEEO definition).

6.3 The dual drainage concept

6.3.1 Every drainage system shall be designed as two systems that work together:

  • (a) a minor system that carries the minor design flow of Table 6.1 below ground or in drains, keeping streets usable and spread within Table 6.2; and
  • (b) a major system that carries all flow above the minor-system capacity, up to the 1% AEP (100-yr) flow, on the surface without entering buildings and within the depth and hazard limits of Clause 6.5.

6.3.2 Every element has a 1% path. Every inlet, sag, pipe, drain, culvert and storage element shall have an identified 1% AEP overland flow path to a receiving waterway, tank or outfall. The path shall be shown on the drainage plan (Clause 6.15).

6.3.3 Major-system design flow. The major system at any point shall carry the 1% AEP peak flow less the minor-system capacity at that point. The minor-system capacity used in this subtraction is the capacity of the inlets after the clogging factors of Clause 6.6.3, or the pipe capacity, whichever is less. At sags and at any location used to set building floor levels, the major system shall also be checked with the minor system fully blocked (Clause 6.10.3).

6.3.4 Rainfall and method. Design flows shall use the rainfall of Chapter 2 (including the climate factor of Clause 2.8) and the methods of Chapter 3:

  • (a) the Rational Method only for catchments ≤ 16 ha and a single conveyance element. It shall not be used to accumulate flows down a network whose total catchment exceeds 16 ha;
  • (b) a hydrograph method with hydraulic routing (for example SWMM, HEC-HMS with a hydraulic model, or an equivalent 1D/2D model) for networks above 16 ha and for any network with storage, pumping or a tidal outfall;
  • (c) a minimum time of concentration of 10 minutes.

6.3.5 No transfer between catchments. Neither the minor nor the major system shall divert flow from one natural catchment to another unless the approving authority accepts a catchment-wide study showing no adverse effect.

Commentary. The CPHEEO (2019) manual defines major and minor systems in its glossary but gives no return period for the major system. APWA 5600 (2006, 5601.8) requires the system to convey the 1% peak and, where in-system capacity is less, an overflow system to carry the remainder. Clause 6.3.3 subtracts only the clogged inlet capacity, not the full pipe capacity, because in practice the pipes cannot take more water than the inlets admit. The fully-blocked check at sags has no direct precedent; this Manual sets it because of the Mumbai experience that drains under footpaths are often silted or blocked by solid waste when the heaviest rain arrives (CPHEEO 2019 Part A, Ch 1 and 2, Figures 1.2 and 2.1 on solid waste dumping in drains). The prohibition on inter-catchment transfer follows the DID Malaysia 2008 submission checklist, which prohibits inter-catchment diversion.


6.4 Design return periods

6.4.1 The minor system, roads and crossings shall be designed for the AEPs of Table 6.1. Where both a land-use row and a road-class row apply to an element, the rarer AEP (longer return period) governs.

Table 6.1 — Design AEPs for conveyance (matches Clause 2.4)

Element Design AEP (return period) Check event Basis
Minor system: Mumbai, Thane and Pune core and other high-density areas 10% (10-yr) 1% (100-yr) overland path This Manual (see Commentary)
Minor system: other Class I areas 20% (5-yr) 1% overland path This Manual; CPHEEO Table 4.1
Minor system: other areas 50% (2-yr) 1% overland path This Manual; CPHEEO Table 4.1
Arterial road drainage and crossings 2% (50-yr) for arterials that are notified evacuation or emergency routes; 4% (25-yr) for other arterials Next higher AEP: 1% for a 2% design; 2% for a 4% design This Manual (25–50-yr); split set by this Manual
Collector road drainage and crossings 4% (25-yr) 2% (50-yr) This Manual
Local road drainage and crossings 10% (10-yr) 4% (25-yr) This Manual
Road underpasses and other trapped sags on public roads 2% (50-yr) 1% (100-yr) This Manual (Clause 6.10.5)
Airports, railway stations, power stations and other critical infrastructure 1% (100-yr) in Class I areas; 2% (50-yr) elsewhere — CPHEEO 2019 Table 4.1
Major (overland) system, every element 1% (100-yr) — This Manual
Building floor levels 1% level + 0.5 m freeboard — This Manual (Clause 6.11)

6.4.2 Check events. At the check event of Table 6.1, the combined minor and major system shall carry the check-event flow within the 1% AEP limits of Table 6.2 and without water entering any building. The 1% overland path requirement of Clause 6.3.2 applies in addition to the check event.

6.4.3 Higher standards. An approving authority may adopt a rarer AEP for any element, including through the high-powered committee route in Note 2 of CPHEEO Table 4.1. It shall not adopt a more frequent AEP than Table 6.1.

6.4.4 High-density areas. The approving authority shall notify, by map, the high-density areas to which the 10% AEP minor-system standard applies. Until it does, the 10% AEP standard applies to:

  • (a) the whole area of the Municipal Corporation of Greater Mumbai, the island city and the suburbs;
  • (b) the areas of the Thane and Pune Municipal Corporations planned as the core or central business district in the applicable Development Plan; and
  • (c) any area in a Tier A body where the master plan permits a floor space index above the base value for the zone.

6.4.5 Retrofit. Where an existing drain cannot practicably be enlarged to the Table 6.1 AEP, the shortfall shall be made good by upstream storage (Chapter 4), regional storage (Chapter 7) or an improved major-system path. The approving authority shall record the residual level of service.

Commentary. The values in Table 6.1 match the Clause 2.4 summary and add rows for underpasses and critical infrastructure. They exceed the CPHEEO (2019) national advisory minimums of 5-yr for Class I cities and 2-yr elsewhere (CPHEEO Part A, Table 4.1). Note 2 of that table allows a State committee to adopt higher values. The 10-yr tier for high-density areas follows Gupta (IIT Bombay), who recommends "1 in 10 year for residential-high density", and Malaysia's MSMA 2, which uses 10-yr minor and 100-yr major systems for link houses, apartments, commercial and industrial land. The road values resolve a conflict in Indian codes. IRC:SP:50-2013 recommends 1–2 years for urban road drains. IRC:SP:42-2014 suggests 25 years for urban roadside drains and a check flood at the next higher return period. APWA 5600 (2006) uses 50-yr for arterial, 25-yr for collector and 10-yr for residential street crossings. Table 6.1 adopts the APWA tiers and the IRC:SP:42 check-flood concept. Splitting arterials into 50-yr evacuation routes and 25-yr others has no direct precedent and is set by this Manual. The 50-yr standard for underpasses is likewise set by this Manual, because an underpass is a trapped sag where the failure mode is deep water on a live carriageway. The default high-density areas in Clause 6.4.4 are set by this Manual and apply until the approving authority notifies a map.


6.5 Street hydraulics: spread, depth and flow hazard

6.5.1 Gutter flow. Flow in a triangular kerb-and-gutter section shall be computed with the modified Manning (Izzard) equation:

Q = (Ku / n) · Sx^(5/3) · SL^(1/2) · T^(8/3)

where Q is the gutter flow (m³/s), Ku = 0.376 (SI), n is the Manning roughness of the gutter (Table 6.6), Sx is the cross slope (m/m), SL is the longitudinal slope (m/m) and T is the spread (m). Composite and depressed gutter sections shall be analysed by the methods of FHWA HEC-22 (4th edition, 2024).

6.5.2 Spread and depth limits. Street flow shall not exceed the limits of Table 6.2.

Table 6.2 — Street flow limits

Road class Minor design event (Table 6.1) Check event and 1% AEP event
Arterial Spread shall leave at least one through lane in each direction clear of water. No flow across the crown. Depth ≤ 150 mm at the crown and ≤ 350 mm at the deepest point; hazard limits of Clause 6.5.3
Collector Spread T ≤ 3 m. No flow across the crown except at a sag intersection. As above
Local Spread T ≤ 3 m. Flow shall not overtop the kerb. As above
All classes, at intersections Cross-flow over the crown ≤ 0.03 m³/s at sag intersections and superelevation transitions; none at mid-block sags. As above

6.5.3 Flow hazard limits. In the check event and the 1% AEP event, the product of depth (D, m) and velocity (V, m/s) of street and overland flow shall not exceed the limits of Table 6.3.

Table 6.3 — Flow hazard limits for streets and overland flow paths

Location Required hazard class (Table 6.4) Limits
Carriageways of all roads H2 or better D·V ≤ 0.6 m²/s; D ≤ 0.35 m (Table 6.2); V ≤ 2.0 m/s
Footpaths, pedestrian crossings, school, hospital and transit-stop frontages H1 D·V ≤ 0.3 m²/s; D ≤ 0.3 m; V ≤ 2.0 m/s
Notified evacuation and emergency routes H1 D·V ≤ 0.3 m²/s; D ≤ 0.3 m; V ≤ 2.0 m/s
Overland flow paths in public open space or easements, away from roads H3 or better, with warning signs D·V ≤ 0.6 m²/s; D ≤ 1.2 m; V ≤ 2.0 m/s

Table 6.4 — Combined flood hazard vulnerability classes (reproduced for reference)

Class Description D·V limit (m²/s) Depth limit D (m) Velocity limit V (m/s)
H1 Generally safe for vehicles, people and buildings ≤ 0.3 0.3 2.0
H2 Unsafe for small vehicles ≤ 0.6 0.5 2.0
H3 Unsafe for vehicles, children and the elderly ≤ 0.6 1.2 2.0
H4 Unsafe for vehicles and people ≤ 1.0 2.0 2.0
H5 Unsafe for vehicles and people; buildings vulnerable to structural damage ≤ 4.0 4.0 4.0
H6 Unsafe for vehicles and people; all buildings vulnerable to failure > 4.0 — —

Source: AIDR Guideline 7-3, Technical flood risk management guideline: Flood hazard (2014), Tables 1 and 2, modelled after Smith and Wasko (2012).

6.5.4 Depth and velocity for Clause 6.5.3 shall be taken from the gutter-flow calculation for simple sections, or from a 1D or 2D hydraulic model where flow leaves the kerb-and-gutter section.

Dual drainage street cross-section Minor and major (dual) drainage in a kerbed street: section (not to scale) 1% AEP water level Road boundary Road boundary Footpath Plinth Building Lowest habitable floor and openings ≥ 0.5 m freeboard above 1% level Building Crown ≤ 150 mm at crown (1% AEP) ≤ 350 mm at deepest point (1% AEP) Minor-event spread T (≤ 3 m on local streets; one lane clear on arterials) Kerb inlet with silt sump Minor-system pipe: design AEP per Table 6.1; HGL ≥ 0.3 m below inlet rim (Clause 6.8) Major system: the street carries flow above pipe capacity along its length, up to the 1% AEP flow Minor (design) event flow 1% AEP (major) event Limit set by this Manual Silt sump Vertical scale exaggerated. Values are the Chapter 6 criteria (Clauses 6.5, 6.8 and 6.11).

Figure 6.1 — Minor and major drainage in a kerbed street. Original drawing for this Manual, adapted from Kansas City Metro APWA, Section 5600 (2006, 5601.8) and FHWA, HEC-22 Urban Drainage Design Manual (4th ed., 2024).

Commentary. The Izzard form of Manning's equation with Ku = 0.376 is used both in FHWA HEC-22 and in the CPHEEO (2019) manual (Part A, Example 5.5, where the constant is written Kc = 0.376). The arterial spread rule (one lane clear) and the 3 m spread for local and collector streets are close to the APWA 5600 (2006, 5604.2) limit of 12 ft (3.66 m) from the back of kerb in each outside lane. The cross-flow limit of 0.03 m³/s is the SI equivalent of the APWA limit of 1.0 cfs at intersection sumps and superelevation transitions, with no cross-flow at mid-block sumps. The 150 mm and 350 mm depth limits are close to the APWA 5600 limits for 1% overflow at road crossings (7 in, about 180 mm, at the crown; 14 in, about 360 mm, at the deepest point). Mumbai's criterion of no flooding above 15 cm (IRC:SP:50-2013, §6.4.1) is a local precedent for the 150 mm crown value.

The hazard classes of Table 6.4 are the combined hazard curves published by the Australian Institute for Disaster Resilience (AIDR Guideline 7-3, 2014), which are modelled after Smith and Wasko (2012). Requiring H2 or better on carriageways means the 1% depth limit of 350 mm (Table 6.2) governs the depth, and the D·V product controls fast, shallow flow on steep streets. H2 is described as "unsafe for small vehicles". Two-wheelers are the dominant vehicles on Maharashtra streets, so the 1% event must be treated as a road-closure event on all roads except notified evacuation routes, which must meet H1. The assignment of hazard classes to locations in Table 6.3 has no direct precedent and is set by this Manual.


6.6 Inlets

6.6.1 Inlet types. Inlets may be kerb-opening inlets, grate inlets, combination inlets (a grate with a kerb opening) or slotted and trench drains. On public streets:

  • (a) kerb-opening or combination inlets shall be used, unless the approving authority accepts grate-only inlets for a specific location;
  • (b) inlet openings shall be set at road level, with a gutter depression where practicable, so that water is not held on the carriageway by a raised kerb or footpath;
  • (c) grates in carriageways, cycle lanes and footpaths shall be of a bicycle- and pedestrian-safe pattern (Chapter 9, Clause 9.11).

6.6.2 Inlet capacity. The clean capacity of inlets on grade and in sags shall be computed by the methods of FHWA HEC-22 (4th edition, 2024), or from tested ratings published by the manufacturer for the exact grate and kerb-opening geometry. The empirical kerb-inlet equations of CPHEEO (2019) Part A §5.6.2 may be used as a cross-check only.

6.6.3 Clogging factors. The design capacity of every inlet shall be its clean capacity reduced by the clogging factors of Table 6.5:

Table 6.5 — Inlet clogging factors (share of clean capacity assumed lost)

Inlet type On grade In a sag
Grate 50% 50%
Kerb opening 10% 20%
Combination Apply the grate and kerb factors to each part separately Apply the grate and kerb factors to each part separately

Design capacity = (1 − clogging factor) × clean capacity.

6.6.4 Inlet spacing. Inlets shall be located by a sequential calculation that starts at the top of each gutter run. At each inlet, the intercepted flow is computed, and the bypass flow is added to the gutter flow arriving at the next inlet. Spacing shall be such that the spread limits of Table 6.2 are met everywhere in the minor design event. In addition:

  • (a) inlet spacing shall not exceed 30 m on kerbed roads, whatever the calculation gives;
  • (b) inlets shall be provided at every sag, immediately upstream of pedestrian crossings and intersections, upstream of bridge decks and superelevation transitions, and at the end of every gutter run;
  • (c) bypass flow from the last inlet of a run shall not be passed onto a road of a higher class or into private land.

6.6.5 Sag inlets. At a sag on a kerbed road:

  • (a) the sag inlet's design capacity (after clogging) shall be not less than the total minor design flow arriving at the sag;
  • (b) flanking inlets shall be placed on each side of a sag on any road where ponding could spread beyond the Table 6.2 limits, and at every underpass;
  • (c) the ponding at the sag shall comply with Clause 6.10.

6.6.6 Inlet connections. The pipe connecting an inlet to the main drain shall have a diameter of at least 300 mm and shall be laid at a gradient that gives at least 0.9 m/s at the inlet's design flow.

6.6.7 Silt sumps. Every inlet chamber on a public road shall have a silt sump at least 300 mm deep below the invert of its outlet pipe, accessible for cleaning from the surface.

Inlet spacing, spread and clogging plan Gutter spread, inlet interception and clogging: plan (not to scale) Footpath Kerb Crown / lane line Spread limit T(max), Clause 6.5 Longitudinal grade Inlet on grade: intercepts Qi = E·Q; the bypass flow goes to the next inlet Inlet spacing: set so that T ≤ T(max) Sag: main inlet plus flanking inlets; ponding limit and overflow path (Clause 6.10) Clogging factors (share of clean capacity lost), Clause 6.6 Inlet type On grade Sag Grate 50% 50% Kerb opening 10% 20% Combination Each part as above Each part as above Gutter flow spread (minor event) Ponding at sag Assumed clogged portion Kerb opening

Figure 6.2 — Gutter spread, inlet interception and clogging. Original drawing for this Manual, adapted from FHWA, HEC-22 Urban Drainage Design Manual (3rd ed., 2009; 4th ed., 2024) and CPHEEO, Manual on Storm Water Drainage Systems (2019).

Commentary. The clogging factors are more severe than the APWA 5600 (2006, 5604.2) rating of sump inlets at 80% of theoretical capacity (a 20% reduction), because grates in Maharashtra streets are routinely blinded by plastic and leaves. CPHEEO (2019) Part A shows solid waste dumped in drains as a primary cause of drain failure (Figures 1.2 and 2.1). APWA 5600 (2006) allows only kerb-opening inlets on public streets; Clause 6.6.1(a) is less strict because combination inlets are useful on flat roads. The 30 m maximum spacing and the treatment of combination inlets in Table 6.5 have no direct precedent and are set by this Manual. Roads on Mumbai's reclaimed land, parts of which lie below high-tide level, are very flat, which shortens the calculated spacing anyway. A fixed cap stops a single blocked inlet from leaving a long dry gutter run. The 300 mm silt sump is set by this Manual. It matches the 0.3 m sump shown on the CPHEEO catch-basin detail (CPHEEO 2019, Figure 5.9).


6.7 Pipes and open and covered drains

6.7.1 Uniform flow. Pipe and drain capacity shall be computed with Manning's equation:

V = (1/n) · R^(2/3) · S^(1/2); Q = A · V

where V is the mean velocity (m/s), n is the Manning roughness (Table 6.6), R is the hydraulic radius (m), S is the friction slope (m/m), A is the flow area (m²) and Q is the discharge (m³/s). Where backwater from a tailwater, a junction or a structure affects the water level, a gradually varied flow (standard step) or hydraulic network model shall be used, and the HGL requirements of Clause 6.8 apply.

6.7.2 Manning roughness. Design values of n shall be taken from Table 6.6. For concrete pipes and masonry or concrete drains, the design value shall be not less than the "fair" or "rough" condition value listed, to allow for sediment, biofilm and ageing.

Table 6.6 — Manning's n for design (from CPHEEO 2019)

Material Condition n (CPHEEO) Minimum design n in this Manual
Cement concrete pipe (collar joints) Good / fair 0.013 / 0.015 0.015
Spun concrete pipe (RCC, PSC) with S/S joints Manufacturer's design value 0.011 0.013
HDPE / uPVC pipe — 0.010 0.011
Plastic (smooth), asbestos cement — 0.011 0.011
Concrete drain, steel trowelled / wood trowelled — 0.014 / 0.015 0.015
Sand and cement plaster — 0.015 0.015
Brick masonry Good / rough 0.015 / 0.017 0.017
Masonry Bad condition 0.020 0.020
Rubble set in cement — 0.017 0.017
Earth channel Regular, good / ordinary 0.020 / 0.025 0.025
Earth channel With stones and weeds / poor 0.030 / 0.035 0.035
Earth channel Partly obstructed by debris or weeds 0.050 0.050
Gutter: concrete — 0.013 0.013
Gutter: hot-mix asphalt — 0.015 0.015
Gutter: sprayed seal — 0.018 0.018

Source of the CPHEEO column: CPHEEO (2019) Part A, Table 5.1 (itself from the CPHEEO Manual on Sewerage and Sewage Treatment Systems, 2013) and Table 5.8 (gutters).

6.7.3 Velocity limits. At the minor design flow:

  • (a) minimum (self-cleansing) velocity: 0.6 m/s in open and covered drains and 0.9 m/s in pipes;
  • (b) maximum velocity: 3.0 m/s in lined drains and in pipes, unless the drain or pipe is designed as a chute under Chapter 9. CPHEEO permits up to 6.0 m/s in plastic or plastic-lined pipes in hilly regions; this may be used in Mahabaleshwar, Panchgani, Matheran, Lonavala–Khandala and Igatpuri and other hill towns with the approving authority's agreement;
  • (c) maximum velocity in unlined and vegetated channels: Chapter 9, Table 9.2;
  • (d) the Froude number of flow in open and covered drains shall not exceed 0.8 at the design flow, unless the drain is designed for supercritical flow under Chapter 9.

6.7.4 Gradient. Each pipe and drain shall be laid at a gradient that achieves Clause 6.7.3(a). Where flat terrain or a fixed outfall level makes this impossible, the designer shall:

  • (a) report the velocity achieved;
  • (b) double the sediment allowance of Clause 6.7.8; and
  • (c) provide access for mechanical desilting at the spacing of Clause 6.13.2.

6.7.5 Pipe flow condition. Pipes shall be sized so that the minor design flow does not exceed the pipe-full capacity. The greater discharge that a circular pipe carries at about 0.95 of its depth shall not be relied on.

6.7.6 Minimum sizes.

  • (a) Pipes: 300 mm internal diameter; 450 mm for public mains.
  • (b) Open drains: bed width 0.3 m.
  • (c) Covered public drains (drains closed by cover slabs): clear internal width 0.6 m and clear internal depth 0.6 m.

6.7.7 Cover to pipes. Pipes shall have at least 0.6 m of cover to finished level, and at least 0.9 m under carriageways unless a structural design for the traffic load is submitted. Where the seasonal high groundwater table is within 1 m of the pipe crown, the pipe shall be checked for flotation with the pipe empty (CPHEEO 2019, Table 11.2) and anchored where necessary.

6.7.8 Sediment allowance. The design capacity of open drains, covered drains and pipes of 600 mm diameter or more shall be computed with the following depth of sediment at the invert:

  • (a) open and covered drains: the greater of 75 mm and 10% of the clear internal depth;
  • (b) pipes of 600 mm diameter or more: 5% of the internal diameter;
  • (c) pipes below 600 mm: no allowance, but Clause 6.7.3(a) shall be met.

The Manning n for the reduced section shall be that of the drain material in Table 6.6.

6.7.9 Freeboard in open and covered drains. At the minor design flow, the water surface (computed with the sediment allowance) shall be below the top of the drain wall, or below the soffit of the cover slab in a covered drain, by at least the freeboard of Table 6.7.

Table 6.7 — Minimum freeboard in open and covered drains

Drain Minimum freeboard Source
Bed width up to 300 mm 100 mm CPHEEO 2019 Table 5.3 (from IRC:SP:50-2013)
Bed width 300–900 mm 150 mm CPHEEO 2019 Table 5.3
Bed width 900–1,500 mm 300 mm CPHEEO 2019 Table 5.3
Wider drains and engineered channels, Q < 3 m³/s 450 mm CPHEEO 2019 Table 5.12 (from IS 7784 (Part 1): 1993)
Q 3 to < 30 m³/s 600 mm As above
Q 30 to < 300 m³/s 900 mm As above
Q 300 to < 3,000 m³/s 1,200 mm As above
Q ≥ 3,000 m³/s 1,500 mm As above
Any roadside drain Not less than 150 mm IRC:SP:42-2014
Steep (supercritical) channels Equal to the flow depth CPHEEO 2019 §5.3.2

At bends, the freeboard shall be measured from the water level on the outside of the bend, including the superelevation Δy = V²T / (2 g rc), where T is the top width and rc the centreline radius (CPHEEO 2019, Eq. 5.29).

6.7.10 Bends and junctions.

  • (a) The centreline radius of a bend in a drain shall be at least 3 times the drain width (CPHEEO 2019 §5.3.3). In engineered channels it shall be at least 2 times the top width and not less than 30 m (CPHEEO 2019 Table 5.11).
  • (b) Where drains meet, a junction sump shall be provided with an internal width of at least twice the width of the outgoing drain. Incoming drains shall enter at less than a right angle to the outgoing flow, and the outgoing invert shall be below the sump floor so that water does not stand in the sump (CPHEEO 2019 §5.3.4).

6.7.11 Manholes and access chambers on pipes. Manholes shall be provided at every junction, change of size, alignment or gradient, and at the head of every pipe. Spacing on straight runs shall not exceed Table 6.8.

Table 6.8 — Maximum spacing of manholes on straight pipe runs

Pipe diameter Maximum spacing
300–600 mm 40 m
700–1,000 mm 100 m
1,050–1,400 mm 150 m
1,500 mm and above 300 m

Source: CPHEEO 2019 Table 11.5. Manhole sizes, drops and covers: Chapter 9, Clause 9.12.

Open and covered drain sections Drain sections: freeboard, sediment allowance and access (not to scale) (a) Open lined drain (b) Covered roadside drain Design water surface Edge protection (Clause 6.13.8) Freeboard (Table 6.7) Sediment allowance: capacity is computed above this level (Clause 6.7.8) Bed width B ≥ 0.3 m (open drain) Carriageway Removable cover panel with lifting recess Slab Kerb inlet opening at road level, with silt sump (Cl. 6.13) Design water surface Freeboard to soffit No utility pipe or cable may cross through the flow area or freeboard (Clause 6.13.6) Clear width ≥ 0.6 m for covered public drains (Clause 6.7.6) Design flow Sediment allowance

Figure 6.3 — Drain sections: freeboard, sediment allowance and access. Original drawing for this Manual, adapted from CPHEEO, Manual on Storm Water Drainage Systems (2019), Tables 5.3 and 5.12, and IRC:SP:50-2013.

Commentary. The n values are those of CPHEEO (2019) Table 5.1. The higher minimum design values have no direct precedent; this Manual sets them because CPHEEO notes that the 0.011 value for spun pipes "may be taken as given by the manufacturer". That is a clean-pipe value, and Maharashtra drains carry heavy silt and solid waste. The 0.6 m/s minimum velocity is CPHEEO's (Table 5.2), based on carrying 0.09 mm sand (§5.3.1). The 0.9 m/s value for pipes is stricter, because a silted pipe cannot be cleaned as easily as an open drain. The 3.0 m/s maximum is from CPHEEO Table 5.2 (WPCF/ASCE 1982). The Froude limit of 0.8 is from CPHEEO §5.3, which advises avoiding critical flow because the water surface becomes unstable.

The 0.6 m × 0.6 m minimum for covered drains has no direct precedent and is set by this Manual. A covered drain narrower than this cannot be desilted by hand or by small machines through a cover opening, and silted, inaccessible drains were a recurring finding after the June 1985 floods in Mumbai, after which the BRIMSTOWAD study (1993) called for the drains to be desilted, cleared of utilities and encroachments and rehabilitated (MCGM, 2008), and in the CAG's audit of the programme that followed, where works stopped because encroachments had not been removed (CAG Report No. 6 of 2014). The 0.6 m minimum cover is the value used in the CPHEEO (2019) worked pipe-design computation sheet (Part A, Chapter 5). The 0.9 m cover under carriageways is set by this Manual.

The sediment allowance values (75 mm or 10% for drains, 5% for large pipes) are set by this Manual. No Indian standard sets a sediment allowance for design. Mumbai's experience is that drains run partly full of silt for much of the year, so a capacity computed for a clean section overstates the real capacity.

The CPHEEO freeboard table (Table 5.3) prints the first row as "Beyond 300 mm bed width". Read with the second row ("Beyond 300 mm & up to 900 mm"), the first row must mean "up to 300 mm"; Table 6.7 is written that way. The CPHEEO manhole spacing table (Table 11.5) gives overlapping ranges (700–1,050 mm and 1,000–1,400 mm); Table 6.8 removes the overlap by assigning 1,050 mm to the 150 m class.


6.8 Hydraulic grade line

6.8.1 HGL analysis. For every pipe and covered-drain network, the designer shall compute the HGL for the minor design event and for the check event, starting at the outfall and working upstream. The analysis shall include friction losses and losses at junctions, manholes, bends, inlets, outlets and gates.

6.8.2 Starting water level. The starting (tailwater) level at the outfall shall be the higher of:

  • (a) the tailwater level of Chapter 5: mean high water springs (MHWS) plus the sea-level allowance of +0.3 m for minor-system design at tidal outfalls, and the level in the receiving drain, river or tank for the coincident event at other outfalls; and
  • (b) the level computed at the outlet pipe from the critical depth and the pipe diameter, (dc + D)/2, where the receiving water is lower.

6.8.3 Minor-event limit. In the minor design event, the HGL shall be at least 0.3 m below the rim of every inlet and the cover level of every manhole and access chamber.

6.8.4 Check-event and 1% limit. In the check event and the 1% AEP event, the HGL may rise above the inlet rims. Water that leaves the minor system shall then be carried by the major system within the limits of Table 6.2 and shall not enter any building. Manholes that can surcharge above ground in these events shall have bolted or locked covers (Chapter 9, Clause 9.12).

6.8.5 Structure losses. Losses at manholes and junctions shall be computed by the energy-based access-hole method of FHWA HEC-22 (2009 or 2024 edition), or by an equivalent method in an approved hydraulic model. A simplified loss-coefficient method (h = K V²/2g) with coefficients from HEC-22 may be used for Tier B networks below 16 ha.

6.8.6 Invert and soffit levels. Where pipe size increases at a manhole, the soffits (crowns) of the incoming and outgoing pipes shall be matched, or the outgoing soffit set lower. The outgoing invert shall not be higher than the lowest incoming invert. Vertical drops in manholes shall follow Chapter 9, Clause 9.12.

6.8.7 Gates and valves. The head loss through flap gates and non-return valves in the open position shall be included in the HGL (Chapter 9, Clause 9.10).

6.8.8 Private connections. Building drainage that connects to a public drain whose 1% HGL is above the building's lowest drainage fitting shall have a non-return valve.

Commentary. The 0.3 m clearance between the minor-event HGL and the inlet rim is set by this Manual. It keeps a margin for losses that a model underestimates, and it stops water from bubbling out of inlets in the event the system is designed for. In Mumbai, 180 of the 186 storm-water outfalls lie below high-tide level and 45 below mean sea level, and parts of the island city, such as Sat Rasta, Lower Parel and Grant Road, are themselves below high tide (Fact Finding Committee, 2006). MCGM's Commissioner called waterlogging "unavoidable" when about 300 mm falls in a short span with a 4.5 m high tide (press report, July 2026). A drain whose HGL is started from a free outfall, at a sea or creek that stands at high tide for hours of every monsoon storm, fails in exactly that way. An HGL computed from the outfall, with the tidal tailwater of Chapter 5, exposes those errors at design stage. The MHWS plus 0.3 m starting level is from CPHEEO (2019) Table 6.2. The access-hole method is described in HEC-22 from the 2009 edition onward.


6.9 Major system: overland flow paths, easements and drainage reserves

6.9.1 Streets as the primary major system. Streets shall be graded so that the 1% AEP major-system flow is carried along the road reserve to a receiving waterway without being trapped, except at sags designed under Clause 6.10.

6.9.2 Overland flow paths outside streets. Where a major-system path leaves the road reserve, it shall be:

  • (a) in public land, in the recreational open space of a layout, or in an easement recorded on the layout approval and the title;
  • (b) at least as wide as the 1% AEP flow top width plus 0.5 m on each side, and not less than 3.0 m;
  • (c) kept free of buildings, compound walls, fences, fill, stored materials and planting that would obstruct flow;
  • (d) graded to a continuous fall with no sag that lacks an outlet; and
  • (e) within the hazard limits of Table 6.3.

6.9.3 Compound walls. A compound wall or fence shall not be built across a mapped overland flow path. Where a wall must cross one, it shall have openings with a total area that passes the 1% AEP flow with a 50% blockage, without raising the upstream water level above the limits of this chapter.

6.9.4 Access along open drains. Open drains with a top width of 2 m or more shall have a maintenance access strip at least 3.5 m wide along one bank, connected to a public road at intervals of not more than 500 m.

6.9.5 Supply channels, surplus courses and tanks. Tank supply channels and surplus courses are part of the major system and shall be protected under Chapter 7.

6.9.6 Drainage reserves. A drainage reserve is a strip of land, including the drain, kept free of buildings so that the drain can be maintained, widened and used as a flood path. A drainage reserve shall be provided:

  • (a) along every public drain or channel with an internal width of 1.0 m or more that runs through or along a layout or site being developed or redeveloped;
  • (b) along every drain or channel shown in an adopted Basin Stormwater Master Plan (Chapter 11), at the width of the future drain in that plan; and
  • (c) along every new public drain with an internal width of 1.0 m or more built by a public body.

6.9.7 Width. The reserve shall be not less than the width in Table 6.9, measured from the drain's internal width W. The width is based on the required drain size (for a planned drain, the size in the master plan), not the existing size. Where the access strip of Clause 6.9.4 is wider than the margin in Table 6.9, the wider governs.

Table 6.9 — Minimum drainage reserve width (adopted from PUB Singapore)

Internal width of drain, W Open drain Closed (covered) drain
1.0 m to 1.2 m 3.0 m W + 0.6 m
more than 1.2 m to 3.0 m W + 2.6 m W + 1.6 m
more than 3.0 m to 4.5 m W + 3.5 m W + 1.6 m
more than 4.5 m to 6.0 m W + 4.5 m W + 3.0 m
more than 6.0 m to 9.0 m W + 6.0 m W + 3.0 m
more than 9.0 m to 25.0 m W + 7.5 m W + 3.0 m
more than 25.0 m W + 12.0 m W + 3.0 m

For an open drain, the larger part of the margin shall be on the side used for maintenance access.

6.9.8 Use and protection.

  • (a) The reserve shall be shown as a separate plot on the layout or site plan and transferred to the Approving Authority free of cost, as roads and open space reservations are. Where the drain is a WRD channel, the reserve is transferred to WRD.
  • (b) No building, compound wall, fence, ramp, step, fill or other structure shall be built in the reserve. Compound walls and boundary fences shall stand outside it.
  • (c) The access strip in the reserve shall be level and continuous, and connected to a public road. Bollards or posts and chains may be used at entrances to keep out vehicles other than maintenance vehicles.
  • (d) Where the reserve is not fenced off, its edge shall be marked with concrete markers at not more than 50 m spacing.
  • (e) Services shall cross under the drain, with at least 1.0 m clearance below the invert, or over it on an approved structure. Services shall not run along the reserve inside the drain section.
  • (f) A structure within 2 m of the edge of the reserve shall be designed to remain stable when the drain is excavated to 1.0 m below its invert. The design shall be signed by a qualified structural engineer.
  • (g) The reserve counts toward the site's open space requirements only where the Approving Authority's rules allow it; it does not reduce any setback required by Chapter 7.

Drainage reserve: open drain cross-section Drainage reserve along an open drain (cross-section, schematic, not to scale) No-structure zone: the whole reserve (Clause 6.9.8(b)) no building, compound wall, fence, ramp, step or fill W (internal width) Access strip: level, continuous, linked to a public road; bollards or posts and chains at entrances (6.9.8(c)) Compound wall outside the reserve (6.9.8(b)) Building and compound wall outside the reserve Reserve width: not less than Table 6.9, from the required drain size (Clause 6.9.7) smaller margin larger margin, maintenance side (6.9.7) 2 m Structure within 2 m of the reserve edge: stable with the drain excavated 1.0 m below its invert; signed by a structural engineer (6.9.8(f)) 1.0 m below invert ≥ 1.0 m clear below invert for services crossing under the drain (6.9.8(e)) Service pipe or duct, crossing in a sleeve Concrete markers at ≤ 50 m where not fenced (6.9.8(d)) No-structure zone 2 m stability-check zone Future excavation, 1.0 m below invert

Figure 6.4 — Drainage reserve along an open drain: reserve width from Table 6.9, no-structure zone, access strip on the maintenance side, the 1.0 m service clearance below the invert and the 2 m stability-check zone (Clauses 6.9.6 to 6.9.8). Original drawing for this Manual, adapted from PUB Singapore, Code of Practice on Surface Water Drainage (7th ed., with Addendum No. 3, 2025), clauses 5.1, 5.3, 9.6 and 9.7 and Appendix 1.

Commentary. Drainage reserves follow Singapore, where "the width of a drainage reserve is based on the required drain size" and the reserve is set aside as a separate plot, "kept free of all encumbrances" (PUB Code of Practice on Surface Water Drainage, 7th ed. with Addendum No. 3, 2025, cl. 1.1). Table 6.9 reproduces PUB's Appendix 1 widths. Clauses 6.9.8(b) to (f) follow PUB clauses 5.1 (no structure within a drain or drainage reserve), 5.3 and 5.3.1 (stability for excavation 1.0 m below the invert; engineer's calculations within 2 m of the reserve), 9.6 (level, continuous access, with bollards or posts and chains) and 9.7 (markers at a maximum of 50 m). The 1.0 m clearance for services crossing under a drain is from PUB's development-plan guidance. In Maharashtra, buildings and compound walls are often built up to the edge of a drain, so it cannot be widened or desilted by machine. Reserving the land when a plot is developed or redeveloped is the cheapest time to secure it, because widening later needs land acquisition. Basing the width on the master-plan drain size (6.9.6(b)) protects the land a future drain will need. In Maharashtra, both building codes keep buildings back from water courses, by fixed distances. Under UDCPR 2020 Regulation 3.1.1(ii), a site is not eligible for building if it lies entirely within 15 m of the edge of the water mark of a major water course (a river) or 6 m of a minor water course (a nallah); DCPR 2034 Regulation 18(b) sets the same distances in Greater Mumbai, unless arrangements to the Commissioner's satisfaction are made to drain the flow. Where a nallah is trained, margins are measured from the edge of the trained nallah, and in Mumbai's urban renewal cluster schemes the margin along a trained nallah is 6.0 m, "or as required by SWD Department of MCGM, whichever is greater". The 15 m and 9 m distances of UDCPR Regulations 4.12 and 3.4.5 apply only to green belts and to recreational open space beside rivers and nallahs. Along rivers, UDCPR Regulation 3.1.3 adopts the flood lines drawn by WRD: the land from the river bank to the blue line (the 25-year flood in WRD practice; the regulation does not state the return period) is a prohibited zone, and the land between the blue line and the red line (the 100-year flood) is a restrictive zone in which building is allowed with the plinth 0.45 m above the red-line level; where no lines have been drawn, a tentative blue line is set from the maximum observed flood, and the 50 m landward of it is a no-construction zone. These distances are statutory minimums. They are not drawn from the drain's hydraulics: the 6 m nallah distance bars only a site lying wholly inside it, and it does not change with the size of the nallah or with the flow the nallah must carry. This Manual therefore adds a hydraulic corridor: the reserve of Table 6.9, based on the drain size needed to carry the design flow (Clause 6.9.7), the access strip of Clause 6.9.4 on the access bank, and, along a nallah that drains 8 ha or more, the setbacks of Clause 7.4 measured from its top of bank. The wider of the statutory distance and the hydraulic corridor governs. Where the corridor is wider, it is stricter than statute and is set by this Manual. Where the Mumbai Commissioner relaxes the distance under Regulation 18(b) against drainage arrangements, those arrangements should meet this chapter. Along a river the blue and red lines govern as well; where they are not final, as in Pune, where the High Court ordered an expert committee to redraw them on 30 June 2025 (as reported), the designer shall use the most recent lines approved by WRD and also report the 1% AEP level computed under Chapter 7. UDCPR Regulation 3.1.13 requires agencies that impose restrictions to give their maps to the Planning Authority, so that applicants need not seek separate NOCs; the corridor should be mapped and lodged in the same way, not made a new NOC.

Commentary. Requirements 6.9.2(b)–(e), 6.9.3 and 6.9.4 have no direct precedent and are set by this Manual. Compound walls around individual plots are almost universal in Maharashtra and are one of the most common ways that overland flow paths get blocked. The 50% blockage assumption for wall openings is set to match the grate clogging factor of Clause 6.6.3. The 3.5 m access width is set by this Manual, sized for a small excavator or desilting vehicle. For comparison, APWA 5600 (2006, 5608.4) requires a 15 ft (about 4.6 m) maintenance access strip for detention facilities.


6.10 Ponding at sags and low points

6.10.1 Minor event. At every sag, the minor design flow shall be removed by inlets (after clogging) with ponded spread within Table 6.2.

6.10.2 1% AEP event. At every sag:

  • (a) the ponded depth shall not exceed 350 mm at the deepest point of the carriageway;
  • (b) a surface overflow route shall be provided (for example over a lowered kerb and footpath into a designated overland flow path), so that the ponding level cannot rise above the overflow level; and
  • (c) building floor levels around the sag shall comply with Clause 6.11.

6.10.3 Fully-blocked check. At sags, the 1% AEP ponding level shall also be computed with the minor system fully blocked and all flow leaving by the surface overflow route. Floor levels around the sag shall be set from the higher of the two ponding levels.

6.10.4 Trapped sags. Where a sag has no surface overflow route, the inlets and conduits (after clogging) shall carry the 1% AEP flow, and the approving authority shall agree the arrangement.

6.10.5 Road underpasses. Underpasses and other trapped sags on public roads shall:

  • (a) be drained by a minor system (with pumping under Chapter 9, Clause 9.9, where gravity drainage is not possible) designed for the 2% AEP (50-yr) flow, checked at the 1% AEP flow;
  • (b) have flanking inlets at both approaches to intercept flow before it reaches the low point;
  • (c) be protected from inflow from surrounding streets by raised approach crests where practicable; and
  • (d) have depth markers and automatic warning or closure signals that operate at 150 mm depth on the carriageway.

Commentary. The fully-blocked check, the trapped-sag rule and the underpass requirements have no direct precedent and are set by this Manual. Clause 6.10.5(d) links the 150 mm crown depth limit of Table 6.2 to the point at which traffic should stop.


6.11 Building floor levels

6.11.1 The lowest habitable floor, and every opening through which water could enter a building (doors, ventilators, basement ramps, lift pits and service entries), shall be at least 0.5 m above the 1% AEP flood level.

6.11.2 The 1% AEP flood level is the highest of:

  • (a) the 1% AEP major-system water level in the street or overland flow path next to the building (Clauses 6.9 and 6.10, including the fully-blocked check at sags);
  • (b) the 1% AEP flood level of any river, channel, tank or waterbody (Chapter 7); and
  • (c) the 1% AEP level with the tailwater of Chapter 5; and
  • (d) where the Approving Authority has adopted a 1% AEP flood depth map under Clause 7.3.4, the ground level at the plot plus the mapped 1% AEP depth.

6.11.3 Default where no level has been computed. For a plot below the Chapter 1 thresholds, or where no 1% AEP level has been computed for the plot, the lowest habitable floor and openings shall be at least the higher of:

  • (a) 0.65 m above the highest crown level of the road on which the plot fronts; and
  • (b) where an adopted 1% AEP flood depth map covers the plot, the ground level plus the mapped 1% AEP depth plus 0.5 m.

The Approving Authority may adopt a regional map, such as a State-approved map or a published national map of modelled 1% AEP flood depth (for example the India Flood Atlas), until a local study replaces it. A map that does not model storm surge shall not be used in place of Clause 6.11.6.

6.11.4 Basements. The crest of every basement ramp and the sill of every basement opening shall meet Clause 6.11.1. Basement drainage shall be pumped to the surface drain through a non-return valve.

6.11.5 Services. Electrical panels, transformers, standby generators, lift machinery and pumps that serve a building shall meet Clause 6.11.1.

6.11.6 Coastal band. The coastal band is the land within 500 m landward of the High Tide Line along the sea front, as defined by the CRZ Notification, 2019, with the High Tide Line as demarcated in the approved Coastal Zone Management Plan. Where the Survey of India Hazard Line lies further inland than 500 m, the band extends to the Hazard Line. Within the coastal band, in addition to Clauses 6.11.1 to 6.11.5:

  • (a) the lowest habitable floor and every opening shall also be at least 0.5 m above the coastal flood level, which is the 1% AEP still-water level (Clause 5.7.3(b), Annex 5A) plus twice the sea-level allowance of Clause 5.7.4 (so at least 0.6 m), because buildings have a design life of more than 50 years (Clause 5.7.4(c));
  • (b) where the plot fronts the open beach, the coastal flood level shall include wave set-up from a site study;
  • (c) no habitable room, electrical service room or plant listed in Clause 6.11.5 shall be placed in a basement; and
  • (d) every basement opening, ramp crest and ventilation opening shall meet Clause 6.11.6(a).

Clause 6.11.6 does not authorise any construction that the CRZ Notification prohibits. Where both apply, the stricter governs.

Coastal band floor level Coastal band: minimum floor level and extent of the band (schematic, not to scale) (a) Level stack for the lowest habitable floor (Clause 6.11.6(a), (b)) (b) Extent of the band (plan) Datum Ground + 2 × sea-level allowance (Clause 5.7.4), so at least 0.6 m + wave set-up from a site study, where the plot fronts the open beach (6.11.6(b)) + 0.5 m freeboard (6.11.6(a)) 1% AEP still-water level (Clause 5.7.3(b), Annex 5A) Coastal flood level Lowest habitable floor and every opening at or above No habitable room, electrical room or listed plant in a basement (6.11.6(c)) Clauses 6.11.1 to 6.11.5 (1% AEP level + 0.5 m, and the defaults of 6.11.3) also apply; the higher floor level governs. CRZ prohibitions are not relaxed. Sea 500 m landward of HTL High Tide Line (HTL), as in the approved CZMP (CRZ Notification, 2019) 500 m line Hazard Line (Survey of India) Coastal band: to 500 m from HTL, or to the Hazard Line where it lies further inland (Clause 6.11.6)

Figure 6.5 — Coastal band: the minimum floor level built up from the 1% AEP still-water level, twice the sea-level allowance, wave set-up where the plot fronts the open beach and 0.5 m freeboard; and the extent of the band, to 500 m from the High Tide Line or to the Hazard Line where it lies further inland (Clause 6.11.6). Original drawing for this Manual, adapted from the CRZ Notification, 2019 (para 1(i) and Annexure IV) and PUB Singapore, Code of Practice on Surface Water Drainage (7th ed.), cl. 2.1.1.

Commentary. The 0.5 m freeboard above the 1% AEP level follows the DID Malaysia 2008 checklist (platform and lowest floor at 100-yr ARI + 0.5 m). It is more than the APWA 5600 (2006, 5601.8 A2) requirement of 1 ft (about 0.3 m) above the 1% stage. The 0.65 m default in Clause 6.11.3 is derived from the other limits of this chapter, not separately sourced: the 1% water level at the crown may be up to 150 mm (Table 6.2), plus the 0.5 m freeboard. It has no direct precedent and applies to plots where no flood level exists. URDPFI (2015) also links minimum plinth levels to flood frequency in its flood-plain zoning, which is covered in Chapter 7.

Clause 6.11.3(b) lets a small plot use a mapped 1% AEP depth where no local study exists, instead of guessing from the road level alone. Modelled national maps are coarse (about 30 m), and most model rainfall and river flooding but not storm surge, which is why 6.11.3 keeps the road-crown check and Clause 6.11.6 sets a separate coastal rule.

The coastal band of Clause 6.11.6 uses the 500 m line of the CRZ Notification, 2019 (G.S.R. 37(E), para 1(i): "the land area from High Tide Line ... to 500 meters on the landward side"), because every coastal authority already maps it and it needs no new survey. The Hazard Line, demarcated by the Survey of India to show the extent of flooding and shoreline change, extends the band where it lies further inland (CRZ Notification, 2019, Annexure IV). The band takes the coastal level from the joint-case still-water level of Chapter 5 rather than from the rainfall map. The higher standard reflects the setting: a coastal flood rises with the sea, cannot be drained while the tide is up, and will rise further with the sea. Singapore takes the same approach with a fixed minimum platform level of 4.0 m above datum on its southern coast and 4.5 m on its northern coast, whatever the rainfall flood level (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 2.1.1). Maharashtra's tide and surge levels vary too much along its coast for one fixed level, so this Manual uses the computed still-water level instead. Using twice the sea-level allowance applies the sensitivity case of Clause 5.7.4(c) as the design case, because a building, unlike a drain, cannot easily be raised later. The basement restriction in 6.11.6(c) is set by this Manual: a basement in the coastal band fills from the sea as well as from rain, and cannot be pumped out to a tide-locked outfall. In Maharashtra, the CRZ Notification, 2019 applies through approved plans. The Bombay High Court's judgment of 17 September 2026 records that the Coastal Zone Management Plan map of Greater Mumbai, prepared by NCSCM under the 2019 Notification, is approved, with mangroves, and a 50 m buffer around them, mapped as CRZ-IA; the date of approval was not seen (2021 and 2022 are both reported). For Thane, Raigad, Palghar, Ratnagiri and Sindhudurg, the NCZMA was reported to have approved the plans under the 2019 Notification on 1 August 2023 (press report). The designer should confirm the current plan, and the High Tide Line it shows, with MCZMA. Two further rules apply along the creeks. Since the High Court's judgment of 17 September 2018 (PIL No. 87 of 2006), the mangroves of the State are protected with a 50 m buffer, reported to apply whatever the area of the stand; a public project may cut mangroves only with the leave of the Court under paragraph 83(viii) of that judgment, and with CRZ clearance granted by MoEF&CC on the recommendation of MCZMA, as in WP (L) No. 17795 of 2026. Drain widening, outfall extensions, holding ponds, pumping stations and flood gates in a mangrove belt are such works, and this Manual authorises none of them. And DCPR 2034 is reported to keep a buffer of only 6 m (3 m in some cases) along tidal water bodies, well inside the CRZ distances (press report); where both apply, the wider governs. Clause 6.11.6 adds a floor-level rule and relaxes neither.


6.12 Culverts and road crossings

6.12.1 Design AEP. A culvert or bridge that carries a road over a drain or waterway shall pass the design AEP flow of Table 6.1 for that road class without overtopping the road, and with the headwater limits of Chapter 9, Clause 9.4. Where the waterway is a State highway or national highway crossing, the design AEP shall also be not less than that of IRC:SP:42-2014 §7.1.4 for the span. The rarer AEP governs.

6.12.2 Check event and 1% AEP. At the check event and at the 1% AEP event, the crossing and the road together shall pass the flow:

  • (a) with overtopping depth ≤ 150 mm at the road crown and ≤ 350 mm at the deepest point of the road;
  • (b) within the hazard limits of Table 6.3;
  • (c) with no overtopping at all of arterial roads that are notified evacuation routes; and
  • (d) without raising the 1% AEP flood level at any upstream building or property boundary above the level for the existing condition, unless the affected owners and the approving authority agree.

6.12.3 Where overtopping is not permitted. Overtopping in the 1% AEP event is permitted only where the structure span is less than 6 m and the 1% AEP peak flow is not more than 7 m³/s, unless a guard rail is installed downstream of the overtopping section. Otherwise, the crossing shall pass the 1% AEP flow without overtopping.

6.12.4 Blockage check. The 1% AEP check shall be repeated with a blocked inlet:

  • (a) 50% of the inlet area blocked for culverts with a span or diameter below 1.5 m; and
  • (b) 20% blocked for larger culverts.

The results of this check shall meet Clause 6.12.2(a) and (d).

6.12.5 Minimum size. Culverts under public roads shall be at least 900 mm in diameter, or 900 mm × 900 mm for box culverts.

6.12.6 Hydraulic design. Culvert hydraulics, including inlet and outlet control, tailwater, road overtopping and outlet protection, shall follow Chapter 9, Clauses 9.4 and 9.6.

Commentary. The design AEPs are those of Table 6.1. The overtopping limits are the street-depth limits of Table 6.2. The span and flow threshold in Clause 6.12.3 is the SI conversion of APWA 5600 (2006): overtopping allowed only where the structure span is under 20 ft and the 1% peak is 250 cfs or less, unless a downstream guard fence is installed. IRC:SP:42-2014 (§7.1.4) sets 25-yr for NH/SH culverts up to 2 m span and 50-yr for 2–6 m spans. The blockage percentages in Clause 6.12.4 and the 900 mm minimum size have no direct precedent and are set by this Manual. The 50% value matches the grate clogging factor.


6.13 Maharashtra construction-practice requirements

6.13.1 Covered roadside drains. Where a roadside drain is covered by slabs that form a footpath:

  • (a) it shall be designed as an open channel with the freeboard of Table 6.7 measured to the soffit of the cover slab, and its HGL shall meet Clause 6.8 measured to the footpath and inlet levels;
  • (b) road runoff shall enter through openings in the drain wall at road level (Clause 6.6.1(b)), each with a silt sump (Clause 6.6.7), at the spacing of Clause 6.6.4;
  • (c) footpath runoff shall enter through slots or grated openings in the cover, not by ponding on the footpath; and
  • (d) the clear section shall meet Clause 6.7.6(c).

6.13.2 Removable covers and access openings. Covered drains shall have:

  • (a) removable cover panels at not more than 10 m centres, each at least 0.6 m long and spanning the full clear width, with recessed lifting points, liftable by two workers or by a hand-operated lifting device, and flush with the footpath;
  • (b) access chambers with a clear opening of at least 0.6 m × 0.6 m at every junction, bend and change of section, and at not more than 30 m centres on straight runs; and
  • (c) covers rated for the traffic or pedestrian load at their location (Chapter 9, Clause 9.11).

6.13.3 Silt traps. In addition to the inlet sumps of Clause 6.6.7, silt trap chambers shall be provided:

  • (a) upstream of every culvert under an arterial road;
  • (b) upstream of every pump station and detention facility; and
  • (c) at every outfall to a tank, river or other waterbody (with the gross pollutant trap required by Chapter 8).

Each silt trap shall be sized to hold the sediment expected between scheduled cleanings, using the sediment yield in Annex 6B, and shall be reachable by a desilting vehicle.

6.13.4 Garbage and gross pollutant screens. Screens shall be provided where an open drain enters a covered drain, a pipe or a culvert, and at outfalls under Chapter 8. Each screen shall:

  • (a) be designed under Chapter 9, Clause 9.8;
  • (b) have a bypass or overflow, so that a fully blinded screen does not flood properties or the road beyond the limits of this chapter; and
  • (c) be checked hydraulically with 50% of its area blocked.

6.13.5 No building over drains. No structure other than an approved crossing or a removable cover shall be built over a public drain. Shop frontages, ramps and steps that cross a drain shall be removable or shall leave access openings that meet Clause 6.13.2.

6.13.6 Utilities. No water main, sewer, power or telecom cable, gas pipe or duct shall be laid along, or pass through, the flow area or freeboard of any drain. A utility that must cross a drain shall:

  • (a) cross above the cover soffit or below the drain invert, inside a sleeve; and
  • (b) be shown on the drainage plan with its level.

Where an existing utility crossing obstructs a drain, its area shall be deducted from the drain section, with a 50% blockage allowance for the debris it traps, until the utility is relocated. The utility owner shall relocate it when the drain is rebuilt.

6.13.7 Sewage. No sewage connection is permitted to a storm drain (Chapter 8). Covered drains shall be built with sealed joints where they run next to sewers.

6.13.8 Edge protection. Open drains deeper than 1.0 m beside a footpath, a carriageway or a public open space shall have railings or barriers. Open drains of any depth shall not be left uncovered across a footpath.

6.13.9 As-built levels. The as-built invert levels of every public drain, pipe and manhole shall be surveyed and submitted (Chapter 10). Inverts shall be within ±15 mm of design. An HGL re-check shall be submitted where they are not.

6.13.10 Desilting. Public drains shall be desilted before the south-west monsoon each year, as set out in Chapter 10.

Commentary. Clause 6.13 has no direct precedent; this Manual sets it on the basis of Maharashtra practice. Most urban drains in the State are covered roadside drains under footpaths. They are often built with continuous cast-in-situ slabs and few openings, so they cannot be cleaned and fill with silt and solid waste within a season. CPHEEO (2019) notes that uncovered channels "are prone to the dumping of garbage" (Part A, Ch 2), which is why the drains are covered. Covering without access openings simply moves the problem out of sight. NDMA (2010) recommends that pre-monsoon desilting be complete by 31 March. In Maharashtra the south-west monsoon sets in on the Konkan coast in the second week of June and over Nagpur in the week of 11–17 June (ICAR-CRIDA district contingency plans), and May storms can be heavy (Ratnagiri recorded 637.0 mm on 31 May 2006, IMD), so Clause 6.13.10 refers to the south-west monsoon and Chapter 10 sets the 31 May deadline. MCGM already works to that date: for 2026 it set 31 May for desilting, with a target of 80% of the silt removed before the monsoon and 10% each during and after it (press report). The interior cities also have damaging storms after the monsoon (Pune 181.1 mm on 5 October 2010; Kolhapur 205.0 mm on 14 November 1966, IMD), so drains should be inspected again once the south-west monsoon ends.

Clause 6.13.7 matters in Maharashtra. Mumbai's storm drains carry dry-weather flow: BRIMSTOWAD recommended that it be diverted to the sewage pumping system (MCGM, 2008), and the pollution of the Mithi has been the subject of an MPCB study (MMRDA, 2023). The Mumbai Municipal Corporation Act, 1888 makes the construction, maintenance and cleaning of drains an obligatory duty of MCGM (s.61(a)), and lets the Commissioner require separate drains for sullage and for "rain-water and un-polluted sub-soil water" (s.239). The drain sections of the Maharashtra Municipal Corporations Act, 1949, which governs the other corporations, and of the Maharashtra Municipal Councils, Nagar Panchayats and Industrial Townships Act, 1965 were not reviewed for this Manual.

The 10 m and 30 m spacings and the ±15 mm tolerance have no direct precedent and are set by this Manual. Clause 6.13.6 responds to the common sight of water mains and cables running through drains. Each one traps debris and reduces the section. Mechanical cleaning through cover openings, rather than manual entry, is assumed throughout, consistent with the Prohibition of Employment as Manual Scavengers and their Rehabilitation Act, 2013.


6.14 Outfalls

6.14.1 Outfalls shall be designed for the tailwater conditions of Chapter 5. Outfalls below the 1% AEP still-water level shall have flap or tide gates or non-return valves (Chapter 5 and Chapter 9, Clause 9.10).

6.14.2 Outfall protection and energy dissipation shall be designed under Chapter 9, Clause 9.6. Outfalls to tanks and waterbodies shall also meet Chapters 7 and 8.


6.15 Submittal requirements

Every conveyance submittal shall include a Conveyance Design Report (Form 6-1) containing:

  1. a catchment plan showing sub-catchments, the minor system, inlet locations and the major-system overland flow paths for the 1% AEP event (Clause 6.3.2);
  2. the land-use and road-class AEP adopted for each element (Table 6.1), and the high-density area status;
  3. design flows, with the rainfall sheet of Chapter 2 and the method of Chapter 3;
  4. gutter spread, depth and D·V checks for the minor, check and 1% events (Tables 6.2 and 6.3);
  5. an inlet schedule with clean capacity, clogging factor, design capacity and bypass flow (Clause 6.6);
  6. pipe and drain design tables with n, velocity, sediment allowance and freeboard (Clause 6.7);
  7. HGL profiles for the minor and check events, with the tailwater used (Clause 6.8);
  8. sag ponding levels, including the fully-blocked check (Clause 6.10);
  9. a floor-level schedule for every building (Clause 6.11);
  10. culvert and crossing calculations (Clause 6.12 and Chapter 9); and
  11. a utilities-crossing schedule and access-opening layout for covered drains (Clause 6.13).

References (chapter)

Annexes and forms

Annex / Form Content
6A Standard inlet types for Maharashtra with capacity curves (on grade and sag)
6B Sediment yield for silt-trap sizing and calibration of the sediment allowance
6C Standard drawings: covered roadside drain with removable covers, access chamber, inlet with silt sump
Form 6-1 Conveyance Design Report checklist