Draft v1.0 prepared by NEER. Not adopted by the Government of Maharashtra, and has no legal force. About this draft

Chapter 11Basin and City Stormwater Master Plans


11.1 Purpose and scope

11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.

11.1.2 A BSMP shall:

  • (a) map flood hazard for the basin under existing and future conditions;
  • (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
  • (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
  • (d) reserve land for regional storage, talav and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
  • (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
  • (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).

11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.

Commentary. Mumbai is the only city in Maharashtra found with a stormwater master plan. BRIMSTOWAD (Watson Hawksley, 1993) divided the city into 121 catchments and costed its works at ₹616.30 crore at 1991-92 prices (MCGM 2008). Its update by MWH, begun in 2006, existed only as drafts for the City and the Eastern suburbs in 2013 (CAG Report No. 6 of 2014). The Mithi has its own master plan of 25 May 2010, prepared under the Mithi River Development and Protection Authority set up after the 2005 floods (MMRDA 2023). In July 2026 MCGM announced a ₹10,000 crore flood-mitigation programme for 300 to 350 chronic flooding hotspots, for which IIT Bombay is preparing the DPR and NDRF funding is being sought (press report). It is a hotspot programme, not a revised design standard or a basin plan. Elsewhere the work found is project-based: Nagpur's ₹266.63 crore flood-mitigation project after the flood of September 2023, and Pune's riverfront development, which narrows the river in places (press reports; SANDRP 2024). No stormwater master plan or stated design return period was found, in the sources reviewed for this Manual, for Pune, Thane, Nashik, Nagpur or the other corporations. A site-level manual cannot fix basin-level problems: lost tank storage, outfalls locked by high tide, river reaches raised by dam releases and backwater, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:

  • Denver's Mile High Flood District prepares major drainageway master plans that set regional facilities and release rates.
  • The Kansas City APWA criteria rest on regional watershed studies (MARC).
  • England's Surface Water Management Plans (Defra, Surface Water Management Plan Technical Guidance, 2010) set a phased method of preparation, risk assessment, options and implementation.
  • Malaysia's MSMA requires drainage master plans for urban areas.

This chapter adapts that method to Maharashtra's tide-locked outfalls and creeks in Mumbai and the Konkan, the short steep rivers of the Konkan with their khajan lands, the dam-regulated rivers of the Desh and the Krishna basin with WRD's blue and red flood lines, the black-soil plains and malgujari talavs of Vidarbha, and a single SW monsoon with damaging storms in May on the coast and in October and November inland.


11.2 Definitions

Term Meaning in this Manual
Basin The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3.
Basin Stormwater Master Plan (BSMP) The plan for one basin prepared under this chapter.
Lead Authority The body responsible for preparing a BSMP (Clause 11.4).
Level of service (LoS) The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6).
Flood hazard map A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario.
Regional facility A storage, conveyance or outfall work serving more than one development, identified in a BSMP.
Capital Improvement Programme (CIP) The ranked, costed list of works in a BSMP (Clause 11.8.4).

11.3 Planning unit: the basin, not the ward

11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.

11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.

11.3.3 For the main urban areas, and for the river reaches that flood every few years, the basins are at least the following:

  • Mumbai: the Mithi, 17.84 km from Vihar lake to Mahim Creek, with a catchment of 7,295 ha that receives the spill of the Vihar and Powai lakes; the Dahisar, Poisar and Oshiwara rivers of the western suburbs; the island-city catchments that drain to the sea through the outfalls and pumping stations of BRIMSTOWAD; and the catchments of the eastern suburbs that drain to Mahul and Thane creeks;
  • Navi Mumbai: the catchments of the CIDCO tidal holding ponds that drain to Thane Creek;
  • Pune: the Mula–Mutha below Khadakwasla dam, with the Ambil Odha as a named sub-basin;
  • Kolhapur: the Panchganga reach through the city;
  • Sangli–Miraj–Kupwad: the Krishna reach through the city, with its river boundary set by upstream releases and by backwater from the Krishna downstream;
  • Nagpur: the Nag river, with Ambazari lake; and
  • Chiplun: the Vashishti and the Shiv Nadi, with releases from the dams upstream and the tide in the Vashishti estuary as boundary conditions to be checked.

Other Tier A bodies, including Thane, Kalyan–Dombivli, Vasai–Virar, Nashik, Chhatrapati Sambhajinagar and Solapur, shall define their basins in the first BSMP that covers them. Where WRD has a flood-line study, a design flood or an operating rule for a river or dam that a town lies on, the BSMP shall take its river boundary conditions from it, and shall show the blue and red flood lines against its own 1% AEP map.

Basin Stormwater Master Plan (BSMP) — process and links to site design 1. Basin set-up Delineate by basin, not ward (Cl. 11.3) Lead Authority + partners 2. Data DEM, drains, tanks, tides, flood marks (Cl. 11.5) 3. Model 1D–2D, 24–72 h storms, tide, continuous sim. calibrate to past floods 4. Gap vs LoS Scenarios: existing, future ± site controls, climate (Cl. 11.6–11.7) 5. Options Restore tanks first, then regional storage, conveyance, outfalls 6. Outputs (Cl. 11.8.4) — approved by State Stormwater Technical Committee • Flood hazard maps 10% / 1% / 0.2% AEP • Flood-sensitive catchments, basin release rates • Regional facility sites and fee-in-lieu rate • Capital Improvement Programme, ranked • Pre-monsoon maintenance programme • Monitoring network • Open data + public map viewer • Annual report, pre-monsoon Land-use plan Statutory master plan: reserve storage sites, flow paths, hazard zoning (Cl. 11.9) Site design Ch 4 release rates, regional detention and fee-in-lieu (Cl. 4.13, 4.5.6) Floors and setbacks 1% AEP future-with-plan map sets floor levels (Ch 6) and setbacks (Ch 7) Public works CIP funds: ULB, State, Union; O&M and desilting (Ch 10) Review every 10 yr, after a >1% AEP event, or plan revision (Cl. 11.11)

Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.

Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. Responsibility in Maharashtra is divided by body as well as by boundary. Drains vest in MCGM under the Mumbai Municipal Corporation Act 1888, in the other corporations under the Maharashtra Municipal Corporations Act 1949, and in the councils under the 1965 Act. WRD draws the blue and red flood lines and operates the dams. CIDCO built the Navi Mumbai holding ponds and drains, and later handed the drains to the Navi Mumbai Municipal Corporation (SACON 2024). The Mithi shows why the basin has to be the unit. It crosses many wards, receives the spill of the Vihar and Powai lakes, and ends in tidal Mahim Creek. The UDD GR of 29 July 2015 divides its works between MCGM and MMRDA, which designed their reaches for different return periods, and UDD made the Mithi River Development and Protection Authority the coordinating agency in 2014 (MMRDA 2023). This clause makes the basin the planning unit. It also requires the Mithi river to be treated as a link, because the lake spills upstream and the tide at its mouth set water levels in every ward it drains.


11.4 Who prepares, and when

11.4.1 Lead Authority.

  • For a basin wholly within one Municipal Corporation: the Corporation (in Greater Mumbai, MCGM through its Storm Water Drains department).
  • For the Mithi basin: one BSMP for the whole river, prepared by MCGM and MMRDA, each leading for the reach assigned to it by the UDD GR of 29 July 2015, with the Mithi River Development and Protection Authority as the coordinating body.
  • For a basin in the Mumbai Metropolitan Region that crosses local-body boundaries (for example the catchments draining to Thane Creek): the Municipal Corporation with the largest share of the basin, with the other local bodies, MMRDA and, for the Navi Mumbai holding ponds, CIDCO as partners.
  • For a Pune basin that crosses the boundary between the Pune and Pimpri-Chinchwad Municipal Corporations or extends into the PMRDA area: the Corporation with the largest share, with the other Corporation and PMRDA as partners.
  • For a Nagpur basin that extends beyond the Corporation: the Nagpur Municipal Corporation, with NMRDA as partner.
  • For basins that drain to a river reach whose level is set by dam releases or backwater (for example the Mula–Mutha below Khadakwasla, the Panchganga at Kolhapur, the Krishna at Sangli and the Vashishti at Chiplun): WRD, which draws the blue and red flood lines and operates the dams, with the local bodies as partners.
  • For other basins that cross local-body boundaries: the Municipal Corporation or Council with the largest share of the basin, with the planning authority for the area and the other local bodies as partners.
  • In Tier B bodies: the Lead Authority is named by UDD. Basins draining to a common river reach or creek may be grouped into one district-level plan.

MCZMA shall be consulted on every BSMP that proposes works in the Coastal Regulation Zone, and every BSMP that proposes work affecting mangroves shall record the leave of the High Court that the work will need.

WRD shall be a partner in every BSMP that includes a river, canal or tank under its control.

11.4.2 When a BSMP is required.

  • (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
  • (b) A BSMP is required before:
    • any regional detention or fee-in-lieu is accepted under Clause 4.13;
    • a fee held under Clause 4.5.6.3 is spent; and
    • a basin-specific release rate is applied under Clause 11.8.3.
  • (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.

11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.


11.5 Data and surveys

11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:

Table 11.1 — Minimum data and surveys for a BSMP

Data Minimum requirement
Terrain Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum
Drain network Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm
Waterbodies Survey of every tank, talav, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment
Rivers and canals Cross-sections at no more than 200 m spacing and at every structure
Outfalls and coast Tidal datums and surge values (Annex 5A), with the datum of every level named (chart datum, GTS/MSL or Town Hall Datum); outfall invert levels against high tide; gates, pumping stations and holding ponds, with their operating rules; WRD blue and red flood lines; dam releases upstream
Rainfall and levels All available rain gauges (IMD, including the Santacruz and Colaba observatories; the MCGM automatic weather stations; the autographic rain gauges and gauge-discharge sites of the WRD Hydrology Project; and the MAHAVEDH revenue-circle weather stations) and water-level records, including those for the July 2005, August 2017, July–September 2019, July 2021 and September 2023 events
Flood evidence Surveyed flood marks and mapped flood extents from past events, including public reports
Land use Existing land use and imperviousness; future land use from the statutory master plan
Soils and groundwater HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones
Sewer interaction Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots

Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on Mumbai's reclaimed land and creek fringes and on the flat floodplains of the Desh rivers a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The July 2005, August 2017, July–September 2019, July 2021 and September 2023 events are the best calibration data Maharashtra has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.


11.6 Levels of service

11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.

Table 11.2 — Minimum levels of service

Element Minimum level of service
Minor system The design AEP of Chapter 6 (Table 6.1)
Habitable buildings No flooding above floor level in the 1% AEP (100-yr) event
Critical facilities (hospitals, emergency services, substations, water and sewage plants) No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event
Evacuation routes and arterial roads Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event
Ponding drain time Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event
Tank and talav storage No net loss of flood storage below the MWL in the basin, measured against the earliest available survey
Outfalls Functioning under the joint and outfall-closed cases of Chapter 5

Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that nobody has measured. Of about 6,700 ex-malgujari tanks in Vidarbha, 1,833 had been rejuvenated by 2023 (press report). The National Wetland Inventory and Assessment counts about 44,714 wetlands in Maharashtra, against about 15,865 in a 2020 State affidavit, and only 57 of the 475 inventoried wetlands in Mumbai were verified in January 2020 (SANDRP 2021). The Thane district wetland committee denied wetland status to eight lakes, including the NRI and TS Chanakya flamingo lakes of Navi Mumbai, and the Chief Minister ordered an inquiry on 12 May 2026 (press report).


11.7 Modelling and scenarios

11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:

  • the minor system;
  • the major (overland) system;
  • rivers, canals and tanks; and
  • the outfalls.

Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.

11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.

11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.

11.7.4 Scenarios. Each BSMP shall model at least:

  • (a) Existing: existing land use, network, tanks and outfalls;
  • (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
  • (c) Future, controlled: future land use with the site controls of Chapter 4;
  • (d) Future, with plan: scenario (c) plus the works of the CIP; and
  • (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8 and the sea-level allowance of Chapter 5.

11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the July 2005, August 2017, July–September 2019, July 2021 and September 2023 events where data exist.

Figure 11.2 — BSMP model schematic Schematic plan of a basin model: design rainfall over sub-catchments; two tanks in cascade with surplus course; a 1D drain network linked to a 2D surface grid; a river or canal reach with an inter-basin link; an outfall with a flap gate and pumps; and a tidal or river level boundary. Numbered notes on the right explain each element. BSMP model: elements required by Clause 11.7 (schematic, not to scale) Sea / receiving water 1 S1 S2 S3 2 Upper tank Lower tank start level start level 3 2D surface 5 4 River / canal (1D) 6 Inter-basin link Gate Pumps 7 8 1 Design rainfall Ch. 2 storms incl. 24, 48, 72 h; 50%, 10%, 1%, 0.2% AEP; areal reduction (Cl. 2.7.3, 11.7.2) 2 Sub-catchments Runoff by Ch. 3 methods; land use for each scenario (a)–(e) of Cl. 11.7.4 3 Tanks and ponds Surveyed FTL, MWL, stage–storage, sluices, surplus weirs (Cl. 11.5.1); start level from continuous run (Cl. 3.13.5, 11.7.3) 4 1D drain network Minor system: drains, pipes, culverts with surveyed inverts and silt (Cl. 11.5.1) 5 2D surface Major (overland) system on the DEM, 0.15 m RMSE or better; exchange with 1D at inlets and manholes 6 Rivers and canals (1D) Sections ≤ 200 m apart and at every structure; diversions between basins mapped (Cl. 11.3.2) 7 Outfall Flap or tide gates and pumps; joint and outfall-closed cases of Ch. 5 8 Downstream boundary Tide (MHWS; HAT + surge + sea-level allowance) or river level, per Ch. 5 Calibrate and validate with at least two major past flood events where data exist (Cl. 11.7.5).

Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and talavs with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.

Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).


11.8 Options, outputs and the Capital Improvement Programme

11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:

  1. Protect and restore storage: talavs, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
  2. Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
  3. Conveyance upgrades to drains, canals and culverts;
  4. Outfall works: gates, pumping stations and tidal holding ponds;
  5. Property-level protection where works cannot reach the level of service; and
  6. Non-structural measures: flood warning (for example IMD district rainfall warnings read with the predicted high tides in Mumbai and the Konkan, and advance notice of dam releases on regulated rivers), flood-hazard zoning, emergency planning and public information.

11.8.2 Option assessment. Each option shall be assessed for:

  • reduction in flood risk (buildings and people flooded; expected annual damage);
  • capital and 30-year maintenance cost;
  • land required;
  • effect on groundwater recharge and saline intrusion (Chapter 8);
  • effect on downstream basins and the Mithi river; and
  • who benefits.

11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.

11.8.4 Outputs. Each BSMP shall produce:

  • (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
  • (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
  • (c) regional facility sites, with storage volumes, land needs and the sites they serve;
  • (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
  • (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
  • (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
  • (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.

Commentary. Restoring storage comes first because Maharashtra's storage is being lost while its conveyance is being enlarged. On the Mithi, widening and deepening raised the holding capacity about twofold and the discharge capacity about threefold (MMRDA 2023), but the river still ends in a tidal creek. The Fact Finding Committee on the Mumbai floods found that the 26 July 2005 storm, about 380 mm in three hours at Vihar, would have overwhelmed even a fully built BRIMSTOWAD system (FFC 2006). The coast has storage in its mangroves, which the High Court has protected since 2018, in its mudflats, and in the Navi Mumbai holding ponds, whose operation has been contested in court. Inland, eastern Vidarbha has about 6,700 ex-malgujari tanks (press report, 2023), and Pune's Ambil Odha flooded in 2019 along an encroached channel (SANDRP 2024). Conveyance upgrades on their own move water faster to an outfall that may be tide-locked or held up by a river in flood. In the basalt of the Deccan plateau, groundwater lies in thin weathered and vesicular zones of low storage, so recharge is limited, and infiltration close to foundations on black soils can raise a perched water table. In May 2015 the depth to water ranged from near ground level in Satara, Sangli, Raigad, Nashik, Nandurbar, Kolhapur and Thane districts to more than 50 m below ground elsewhere (CGWB 2015, as reported). In Mumbai's reclaimed land and along the creeks the water table is shallow and rises and falls with the tide. Deeper drains near the creeks can draw saline water inland, which is why groundwater and saline intrusion are assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.


11.9 Integration with land-use planning

11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the Development Plans and Regional Plans made under the Maharashtra Regional and Town Planning Act 1966, including the Development Plan for Greater Mumbai 2034, and the plans of the special planning authorities. In particular:

  • (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
  • (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
  • (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
  • (d) the recreational open space (ROS) of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.

11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.

Commentary. UDCPR 2020 already ties land use to WRD's flood lines (Regulation 3.1.3). Between the river bank and the blue line, the 25-year flood line, construction is prohibited except for open uses. Between the blue line and the red line, the 100-year flood line, building is allowed with the plinth 0.45 m above the red line. Where no lines exist, a tentative blue line is drawn from the maximum observed flood, with a 50 m no-construction zone landward of it. The return periods come from WRD practice, not from the regulation. Plinths must be at least 45 cm above the high flood level (UDCPR 9.1), or 60 cm in Mumbai (DCPR 2034, Regulation 37(1)). Yet the lines cover only rivers, they map river floods rather than drainage floods, and they are contested. Pune's lines were drawn in 2011 and redrawn in 2016, and remain unsettled after the High Court's order of 30 June 2025. In Kolhapur, the design discharges of the Panchganga lines were reportedly cut by more than half between drafts (press report, allegation). A BSMP gives the Development Plans the 1% AEP drainage-flood map that they need. Using recreational open space land as storage or flow path has no direct precedent; this Manual adopts it because UDCPR 2020 already lets the recreational open space of a layout next to a river or nallah lie in the green belt, after leaving 15 m from a river and 9 m from a nallah (Regulations 3.4.5 and 4.12), and DCPR 2034 requires at least half of the ground-level part of the recreational open space in Mumbai to be left unpaved on "mother earth" to let water percolate; because that land then serves as open space, storage placed in it must stay usable as one. Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.


11.10 Consultation and publication

11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.

11.10.2 After approval, the following shall be published as open data:

  • the model files;
  • the flood hazard maps;
  • the data of Clause 11.5.1, except security-sensitive asset details; and
  • the CIP.

They shall also be shown on a public map viewer.

Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.


11.11 Approval, review and reporting

11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.

11.11.2 Review. Each BSMP shall be reviewed:

  • every 10 years;
  • within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
  • when the statutory land-use plan is revised.

11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each SW monsoon (by 31 May). The report shall show:

  • CIP progress;
  • the fee-in-lieu ledger (Clause 4.13.4);
  • maintenance completed; and
  • any flooding against the levels of service.

11.12 Interim arrangements

11.12.1 Until a BSMP is approved for a basin:

  • (a) all site criteria of Chapters 4 to 8 apply in full;
  • (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
  • (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
  • (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.

References (chapter)

Annexes and forms

Annex / Form Content
11A BSMP terms of reference template
11B Basin lists and boundaries for Tier A bodies
11C Depth–damage curves for Maharashtra building types
11D BSMP data and model publication standard
Form 11-1 Annual implementation report