Draft v1.0 prepared by NEER. Not adopted by the Government of Maharashtra, and has no legal force. About this draft

Chapter 10Submittals, Review, Operation & Maintenance and Enforcement


10.1 Purpose and scope

10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:

  • (a) the submittal stages and their contents (Clauses 10.3–10.4);
  • (b) the compliance calculator (Clause 10.5);
  • (c) professional certification and review (Clauses 10.6–10.7);
  • (d) construction inspection and as-built certification (Clauses 10.8–10.9);
  • (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
  • (f) handover of public assets (Clause 10.14);
  • (g) enforcement (Clause 10.15); and
  • (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).

10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.

Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. CAG's audit of the Brihanmumbai Storm Water Drain (BRIMSTOWAD) project (Report No. 6 of 2014, para 4.1) shows how a plan stalls without a process to carry it through. Watson Hawksley's 1993 report had costed the works at ₹616.30 crore at 1991-92 prices, and only about ₹260 crore of work was done in the following ten years (MCGM 2008). After the floods of July 2005 the Government of India sanctioned ₹1,200 crore. By September 2013 MCGM had spent ₹1,764.55 crore, only 16 of the 58 works were complete, and a revised estimate of ₹3,884.61 crore had not been approved. The updated master plan, due from MWH by December 2009, existed only as drafts for the City and the Eastern suburbs in July 2013. Of the eight pumping stations, four had not been started because no sites had been chosen, and works stopped where encroachments were not removed. CAG recorded that "flooding of low-lying areas, even when rainfall is less than 50 mm per hour, continues to be a regular feature". CAG's earlier audit of the 2005 floods found warning systems out of order and could not verify ₹39.96 crore of Mithi desilting reported by MMRDA (CAG 2006). These are failures of process, not of engineering knowledge. The approval route also shapes this chapter. In Greater Mumbai, building proposals are approved by the Municipal Commissioner under DCPR 2034. An MCZMA NOC is needed in the Coastal Regulation Zone, but the list of special NOCs in Regulation 59 includes no drainage, WRD or flood clearance. MCGM's Storm Water Drains department is named only in the urban renewal cluster rules, where it may require a margin along a trained nallah wider than 6 m (DCPR 2034); whether it comments on other building proposals was not confirmed. Elsewhere, the Planning Authority grants development permission under the MRTP Act 1966 and Chapter 2 of UDCPR 2020. That Authority is the Municipal Corporation, the Municipal Council or Nagar Panchayat, a special planning authority such as CIDCO in Navi Mumbai, PMRDA or NMRDA in their own areas, or MMRDA where it is the Planning Authority. Plans must show water courses, water bodies and drains. The plinth is certified by the architect or licensed engineer, and officers check about 10% of cases (UDCPR 2.2 and 2.8.4). Agencies that restrict development must give the Authority their maps, so that applicants are not sent to each department for an NOC (UDCPR 3.1.13). Neither code asks for a drainage report. MIDC, NAINA, JNPT, the hill-station councils, eco-sensitive areas and Lonavala are outside UDCPR, and their regulations were not reviewed for this Manual. Every stormwater item in this chapter is therefore written so that the architect or engineer on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it at the plinth and occupancy stages. This chapter is the process.


10.2 Definitions

Term Meaning in this chapter
Submittal A set of documents lodged with the Authority at one of the stages of Clause 10.3.
Drainage report The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4.
Stormwater facility Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private.
Hold point A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8).
As-built certificate The certificate of Clause 10.9 that the facility was built as approved and performs as designed.
Owner The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset.
O&M plan The operation and maintenance plan of Clause 10.11.
Facility register The public register of facilities of Clause 10.17.

Other terms are defined in Clause 1.4.


10.3 Submittal stages

10.3.1 Submittals shall be made in the following stages, linked to the approval steps of UDCPR 2020 and DCPR 2034 (Table 10.1):

Table 10.1 — Submittal stages and linked approvals

Stage Submittal When Linked approval
0 Pre-application meeting and Form 1-1 (Applicability Determination) Before the planning permission or layout application None (advisory record)
1 Preliminary drainage report With the planning permission or layout application Planning permission / layout approval
2 Final drainage design Before building permit, or before commencement where the permit is issued with the planning permission Building permit / commencement
3 Construction inspections at hold points During construction None (records filed)
4 As-built certificate and verification tests Before the completion certificate Completion / occupancy certificate
5 Maintenance declaration registered, or handover of public assets Before or with the completion certificate Completion certificate; asset acceptance
6 Annual declarations and inspection reports Every year after completion Continuing compliance

10.3.2 Stage 0 is mandatory for:

  • (a) sites of 2 ha or more;
  • (b) sites in a flood-sensitive catchment;
  • (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
  • (d) sites draining to a tidal outfall or adjoining a waterbody.

For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.

10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.

10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.

10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.

Figure 10.1 — Submittal, review and approval workflow Two columns: applicant stages 0 to 6 on the left, Approving Authority actions and approval gates on the right. Stages 1 and 2 can be returned with comments for resubmittal. Stage 6 repeats every year. Applicant / certifying professional Approving Authority Stage 0 — Pre-application Form 1-1 Applicability Determination Confirms applicability; advises Mandatory: ≥ 2 ha, flood-sensitive, tidal Stage 1 — Preliminary drainage report Forms 2-1, 10-1, 10-2, 10-3 comments Check 5 days; review 15 (resubmit 10) → Planning permission / layout Stage 2 — Final drainage design Models, GIS, draft O&M plan, Form 10-3 comments Review 15 working days (resubmit 10) → Building permit / commencement Stage 3 — Construction Hold-point inspections, Form 10-4 Notified of key hold points (3 working days); may attend Stage 4 — As-built certification Survey, re-run, drawdown tests, Form 10-5 Accepts as-built certificate → Completion certificate Stage 5 — Maintenance declaration Form 10-6, or handover with Form 10-8 Enters facility / asset register → Public asset accepted Stage 6 — Every year, pre-monsoon Form 10-7 annual declaration Inspects; enforces (Clause 10.15) Publishes register (Clause 10.17) yearly Approval gate (accent text) Returned with comments; resubmit Periods in working days (Clause 10.7)

Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.

Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the UDCPR/DCPR steps a Maharashtra applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.


10.4 Required contents and checklists

10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:

  • (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
  • (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
  • (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
  • (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
  • (e) the pre-development condition and hydrologic method (Chapter 3);
  • (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
  • (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
  • (h) the downstream extent and tailwater case (Chapter 5);
  • (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
  • (j) the land reserved for facilities and maintenance access (Clause 10.13).

10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:

  • (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
  • (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
  • (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
  • (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
  • (e) construction drawings, details and specifications of every facility;
  • (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
  • (g) the hold-point schedule (Clause 10.8);
  • (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
  • (i) the model input files and the GIS data of Clause 10.4.4; and
  • (j) the certificates of Clause 10.6.

10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.

10.4.4 Digital submittal.

  • (a) Reports and drawings shall be submitted as searchable PDF.
  • (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
  • (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (43N, or 44N east of 78° E), with attributes as listed in Annex 10B.
  • (d) Levels shall be stated relative to a named vertical datum. The relationship to the tidal datums (chart datum, mean sea level on the GTS datum and, in Mumbai, the Town Hall Datum) used in Chapter 5 shall be stated.

10.4.5 Summary of forms used in submittals (Table 10.2):

Table 10.2 — Forms used in submittals

Form Title Stage
1-1 Applicability Determination 0 or 1
1-2 Variance / Waiver Request 1
2-1 Design Rainfall Sheet 1, 2
10-1 Drainage Report Checklist 1, 2
10-2 Compliance Calculator Summary 1, 2, 4
10-3 Professional Design Certificate 1, 2
10-4 Hold-Point Inspection Record 3
10-5 As-built Certificate 4
10-6 Maintenance Declaration 5
10-7 Annual Maintenance Declaration and Inspection Report 6
10-8 Asset Handover Certificate 5

Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Mumbai's island-city drains were designed for 25 mm/h with a runoff coefficient of 0.5 "during low tide hours". The Natu Committee (1975) recommended 50 mm/h with C = 1.0, BRIMSTOWAD (1993) repeated these criteria, and the Fact Finding Committee kept 50 mm/h for small catchments (FFC 2006; CAG Report No. 6 of 2014). By the BRIMSTOWAD table that the FFC reproduces, 50 mm/h is roughly a "2 in 1 year" one-hour intensity, a storm expected about every six months; the 1-in-10-year one-hour intensity in the same table is 109 mm/h. The FFC added 70 mm/h (1 in 10 years) for river channel corridors, 80 mm/h (1 in 25) for cross-drainage works on feeder roads and 100 mm/h (1 in 100) for main arterial roads. It also asked MCGM to build a 15-minute IDF, but no adopted MCGM IDF was found. The Mithi was designed for a 1-in-10-year flood on the MCGM reach and 1-in-100 on the MMRDA reach (MMRDA 2023). The design criteria of the MWH update of BRIMSTOWAD have not been published. Outside Mumbai, no State circular and no municipal document stating a design storm for public drains was found. Form 2-1 and Form 10-2 ensure that every design states its inputs.


10.5 Compliance calculator

10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:

  • (a) applies the applicability tests of Clause 1.5;
  • (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
  • (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
  • (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
  • (e) on alternative S-2, gives the permissible site discharge for each AEP; and
  • (f) produces the Compliance Calculator Summary (Form 10-2).

10.5.2 Use.

  • (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
  • (b) On the design-aid route, the calculator may be the only storage calculation.
  • (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.

10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.

10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.

Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Maharashtra calculator serves Tier B authorities in particular, where it may be the whole calculation.


10.6 Professional certification

10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or UDD:

  • (a) Tier A sites of 1 ha or more;
  • (b) any site in a flood-sensitive catchment;
  • (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
  • (d) any pumped facility, tide gate or regional facility.

10.6.2 Empanelment criteria shall be issued by UDD and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.

10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:

  • (a) the design complies with this Manual, except for variances listed and approved;
  • (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
  • (c) the models submitted reproduce the results reported.

10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.

10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.

Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the UDCPR/DCPR registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.


10.7 Review procedure and timelines

10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.

10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:

  • (a) 15 working days of acceptance for a first submittal; and
  • (b) 10 working days of acceptance for a resubmittal.

10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.

10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the UDD list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.

10.7.5 Concurrent clearances. Where an MCZMA recommendation (in the Coastal Regulation Zone), the approval of a tentative blue flood line by WRD's Chief Engineer (UDCPR 2020, Regulation 3.1.3(ii)) or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.

10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.

10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.

Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.


10.8 Construction inspection

10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:

  • (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
  • (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
  • (c) the infiltration tests of Clause 10.9.3;
  • (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
  • (e) pumps and controls, at commissioning.

10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.

10.8.3 Protection during construction.

  • (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
  • (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
  • (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.

Figure 10.2 — Construction hold points from approval to handover Vertical timeline from Stage 2 approval through construction, verification tests and as-built certification to the maintenance declaration or asset handover. Diamonds mark hold points (a) to (e) of Clause 10.8.1; each step shows the form used. Construction hold points: approval to as-built and handover (not to scale in time) Hold point: work stops until inspected and recorded Other required step Stage 2 Approval Stage 3 Construction Stage 4 Tests and as-built Stage 5 Declaration or handover Final design approved; hold-point schedule set Schedule of hold points approved with the design (Cl. 10.4.2(g), 10.8.1) Form 10-4 (schedule) Protect retention and infiltration areas Fenced off from traffic and stockpiles (Cl. 10.8.3(a)) (a) Excavated base of each facility Retention, infiltration, detention: before media, liner or structure Form 10-4 3-day notice * (b) Outlet structure, orifice, trash screen Before backfill, or before the facility is first allowed to fill Form 10-4 3-day notice * (d) Outfall, flap or tide gate, non-return valve Before the downstream connection is made Form 10-4 (e) Pumps and controls At commissioning Form 10-4 Area stabilised; temporary sediment removed Infiltration not in service until stabilised (Cl. 10.8.3(b), (c)) (c) Verification tests Infiltration retention empties within 72 h; pumps at duty point; gates open and seal (Cl. 10.9.3) Form 10-4 As-built survey and re-run; certificate accepted Licensed surveyor; calculator and model re-run; then completion certificate (Cl. 10.9) Forms 10-5, 10-2 Private facility: maintenance declaration Registered to run with the land; owner and successors bound (Cl. 10.10) Form 10-6 Public asset: handover to the ULB Cleaned, inspected inside, land or easement transferred; defects liability for at least one full monsoon season (Cl. 10.14) Form 10-8 * Notice: for sites under Clause 10.6.1 the Authority is given at least 3 working days’ notice of hold points (a) and (b), and may attend. Every hold point is inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs (Cl. 10.8.2).

Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.

Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.


10.9 As-built certification

10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:

  • (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
  • (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
  • (c) the completed hold-point records (Form 10-4); and
  • (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).

10.9.2 Acceptance. The as-built facility is accepted where:

  • (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
  • (b) the outlet dimensions and inverts match the approved design; and
  • (c) the re-run shows compliance with every criterion of Chapters 4 and 5.

Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.

10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.

10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.

Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.


10.10 Maintenance declarations and covenants

10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:

  • (a) identify each facility, its location and the approved O&M plan;
  • (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
  • (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
  • (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
  • (e) be registered so that it runs with the land and is disclosed to purchasers.

10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.

10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 May each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.

10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.

Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Maharashtra because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 May date is set by this Manual to fall before the south-west monsoon (June–September), when most Maharashtra extreme rainfall occurs.


10.11 O&M plans

10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:

  • (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
  • (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
  • (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
  • (d) inspection checklists matching Form 10-7;
  • (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
  • (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
  • (g) safety measures for confined spaces, deep water and public access;
  • (h) access routes and equipment needed (Clause 10.13);
  • (i) an annual cost estimate and who pays it; and
  • (j) the records to be kept, and for how long.

10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.

Commentary. In Mumbai the gates and pumping stations at the outfalls are run by MCGM's Storm Water Drains department, a separate department since November 1993 (MCGM 2008). The Haji Ali station is being upgraded under a contract that includes 15 years of operation and maintenance (press report, March 2025). No operating rules for the stations were found in the public domain. In Navi Mumbai the drains of the CIDCO new town discharge through 11 tidal holding ponds whose gates open at ebb tide and close at high tide (SACON 2024; press reports). Their operation collides with mangrove protection: in 2018 the High Court was reported to have ordered CIDCO to keep the sluice gates open, with 70 of 76 gates then reported open (press report). The operating rule of item (e) for a holding pond therefore has to respect mangrove protection, which since the High Court judgment of 17 September 2018 requires the Court's leave before mangroves are cut for a public project. River levels at many inland outfalls are set by dam releases. In Pune the Khadakwasla release breached the blue flood line of the Mutha at 45,474 cusec in 2019 and at 35,574 cusec on 25 July 2024, well below the 60,000 cusec for which the line was drawn (SANDRP 2024). In August 2019 the nine projects of the Krishna basin in Kolhapur, Sangli and Satara released almost at the same time between 5 and 7 August (SANDRP 2020). The operating rules for these releases were not found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.


10.12 Inspection frequencies

10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:

Table 10.3 — Minimum owner inspection frequencies

Facility type Routine Pre-monsoon (by 31 May) After a heavy-rainfall event
Retention / infiltration (soakaways, trenches, bioretention, permeable paving) Every 6 months Yes Yes
Surface detention basin or multi-use recreational open space area Every 6 months Yes Yes
Underground or podium detention tank, gravity outlet Every 6 months Yes Yes
Pumped detention, pumps and controls Monthly test run Yes, with full duty test Yes
Flap / tide gate, non-return valve Every 3 months Yes, with seal test Yes
Gross pollutant trap / first-flush device Every 3 months Yes Yes
Private drains and inlets Every 6 months Yes —

A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district.

10.12.2 Authority inspections. The Authority shall inspect:

  • (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
  • (b) a random sample of at least 10% of other facilities each year.

10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).

Figure 10.3 — Maintenance cycle and responsibility A one-year strip from January to December with the south-west monsoon (June to September) shaded as the main season, and May (storms on the Konkan coast) and October–November (storms in the interior) shaded more lightly. Lanes show routine inspections, the pre-monsoon inspection and Form 10-7 declaration due by 31 May, inspections after heavy rainfall, and Authority inspections. Boxes below show who is responsible: the owner, the ULB and the Authority. Maintenance cycle and responsibility (Clauses 10.10–10.12, 10.14) South-west monsoon May, coast Oct–Nov storms, inland Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 31 May Routine Monthly: pump test run Every 3 months: gates, valves, GPTs Every 6 months: retention, detention, drains Pre-monsoon Every facility inspected; pump full duty test; gate seal test; defects corrected After heavy rain After each day at or above IMD “heavy rainfall”, or a district red alert Annual declaration Form 10-7 Form 10-7 lodged by 31 May: Tier A facilities; pumped, tide-gate and regional facilities anywhere Authority At least every 2 years (every year if flood-sensitive) for sites ≥ 1,000 m² or Cl. 10.6.1(c), (d); 10% random sample of others each year → facility register (Cl. 10.17) Who is responsible Owner — private facility Maintenance declaration, Form 10-6; binds successors in title (Cl. 10.10.1) Layouts and apartments: the association; the developer until it accepts (Cl. 10.10.2) Inspects; lodges Form 10-7 ULB — handed-over public asset Accepted with Form 10-8 (Cl. 10.14) O&M plan in the asset register, funded in the annual budget (Cl. 10.11.2) Developer liable for defects and routine maintenance for ≥ one SW monsoon (Cl. 10.14.2) Authority Inspects and records results in the facility register (Cl. 10.12.2–10.12.3) Enforces: notice, penalty, works in default with cost recovered (Cl. 10.15) Publishes the register (Cl. 10.17) Tick positions within the year are illustrative; only the 31 May deadline is fixed. Damaging storms also hit the Konkan coast in May and the interior in October–November.

Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 May) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the south-west monsoon (June–September); tick positions within the year are illustrative.

Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The pre-monsoon deadline is set for the SW monsoon, whose normal onset is in the first half of June in the Konkan and the Desh and about 11–17 June at Nagpur (ICAR-CRIDA district plans). NDMA (2010) sets 31 March for pre-monsoon desilting nationally. In Mumbai, MCGM already works to 31 May. For 2026 it set that date for its nallah desilting, aiming at 80% of the year's desilting by 31 May and 10% each during and after the monsoon, and an extension to 3 June was later reported (press reports). This Manual adopts 31 May as the outer limit. Work in the Konkan should finish earlier, because pre-monsoon storms do occur: Ratnagiri recorded 637.0 mm on 31 May 2006 and Santacruz 190.8 mm on 19 May 2000 (IMD). Damaging storms also come after the season in the interior. Pune's 24-hour record is 181.1 mm on 5 October 2010, Kolhapur's is 205.0 mm on 14 November 1966 (IMD), and Pune district receives about 27% of its annual rainfall in October–December (ICAR-CRIDA). The post-event inspections of Table 10.3 cover these storms.


10.13 Maintenance access

10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.

10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.

10.13.3 Underground facilities. Tanks shall have:

  • (a) an access opening over the inlet, the outlet and each chamber;
  • (b) fixed ladders or steps, and ventilation for confined-space entry;
  • (c) a sump or low point for sediment removal; and
  • (d) headroom sufficient for manual cleaning.

10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.

10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.

Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Maharashtra cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.


10.14 Handover of public assets to the ULB

10.14.1 Drains, roads, recreational open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:

  • (a) the as-built certificate (Clause 10.9) has been accepted;
  • (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
  • (c) the land, or an easement over it, has been transferred to the ULB;
  • (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
  • (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.

10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full south-west monsoon season after handover. The ULB may hold a security deposit for this period.

10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.

10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.

Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Maharashtra drainage show up only in the first SW monsoon.


10.15 Enforcement

10.15.1 Offences. The following are contraventions of this Manual:

  • (a) building without an approved drainage design where one is required;
  • (b) building a facility other than as approved;
  • (c) removing, filling, covering, reducing or changing the use of a facility without approval;
  • (d) failing to maintain a facility, or to submit Form 10-7;
  • (e) a sewage connection to a storm drain;
  • (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
  • (g) obstructing a natural drainage path or major-system flow path; and
  • (h) false or negligent certification.

10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):

Table 10.4 — Graduated enforcement response

Step Action
1 Written notice stating the contravention, the clause breached, the remedy and a compliance period.
2 Stop-work order, or withholding of the completion certificate, for development not yet complete.
3 Penalty under the applicable Act or rules.
4 Works in default by the Authority, with the cost recovered from the owner.
5 Disconnection of the private drain connection to the public system, where this causes no hazard to others.
6 Report of the certifying professional to the registering authority, and suspension from the empanelled list.

10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.

10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.

10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.

Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which UDCPR 2020 and DCPR 2034 are made and from the municipal Acts. The graduated steps are set by this Manual. The powers exist but are used mostly when a court steps in. In Mumbai, drains are an obligatory duty of MCGM, which has drainage powers under sections 220 to 239 of the Mumbai Municipal Corporation Act 1888 (MCGM 2008). The other corporations act under the Maharashtra Municipal Corporations Act 1949 and the councils under the Maharashtra Municipal Councils, Nagar Panchayats and Industrial Townships Act 1965, whose drain sections were not reviewed for this Manual. For the rainwater harvesting rule, both codes provide only an annual levy of up to ₹1,000 for every 100 m² of built-up area (UDCPR 2020, Regulation 13.3(c); DCPR 2034, Regulation 62). Much of the enforcement has come through the courts. About 10,000 encroachments have been removed along the Mithi (MMRDA 2023), and CAG found BRIMSTOWAD works stopped where encroachments stood (CAG Report No. 6 of 2014). The High Court ordered WRD to redraw Pune's flood lines (PIL No. 36 of 2021, orders of 26 June 2024 and 30 June 2025), but the lines are still not final (SANDRP 2026). Its Nagpur Bench directed the removal of encroachments on the Nag river after the 2023 flood (order of 17 January 2024, as reported). The National Green Tribunal has set time limits for marking flood lines in Dhule, Nandurbar, Jalgaon and Akola (order of 15 September 2023, as summarised). This shows that a rule without routine enforcement does little. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.


10.16 Monitoring and post-event review

10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.

10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:

  • (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
  • (b) tide and river levels at the outfalls, each on a named datum, the state of any tide gate, holding-pond gate or pumping station on the outfall, and releases from any dam upstream;
  • (c) flooded locations, depths and durations, with flood marks surveyed where possible;
  • (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
  • (e) recommended actions.

10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), MSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.

10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.

Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Maharashtra has two examples of the review this Clause requires. The Fact Finding Committee on the Mumbai floods, chaired by Dr Madhav Chitale, reported in March 2006 on the floods of 26–27 July 2005. It reviewed the rainfall, tides and the BRIMSTOWAD design basis, and recommended the tiered design intensities and the urban hydrology cell described in this chapter. The Wadnere Committee reported on the 2019 floods in the Krishna sub-basin in May 2020. It found that backwater from Almatti dam in Karnataka was not responsible, a finding that one member, who resigned, and others contest (SANDRP 2020). CAG had linked Almatti backwater to Sangli's floods of 2005 (CAG 2006). For Chiplun in July 2021, an expert committee recommended dredging the Vashishti and the Shiv Nadi (press report). No published technical review was found for the Pune flood of 25 September 2019 on the Ambil Odha, for which between 17 and 26 deaths were reported (press reports; SANDRP 2024). Nor was one found for the Nagpur flood of 23 September 2023, when more than 109 mm fell in three hours and Ambazari lake overflowed. That flood is instead being followed in High Court proceedings (press reports). The urban-flood role of MSDMA and its current State Disaster Management Plan were not reviewed for this Manual. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.


10.17 Data publication

10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:

  • (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
  • (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
  • (c) the register of variances and waivers (Clause 1.10);
  • (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
  • (e) enforcement actions (Clause 10.15.5); and
  • (f) event reports and post-event reviews (Clause 10.16).

10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.

10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.

10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.

Commentary. Transparency is a design criterion in its own right here. Much of the information on which Mumbai's drainage depends could not be found in the public domain: the MWH master plan that updates BRIMSTOWAD; the design basis of the ₹10,000 crore flood-mitigation programme announced in July 2026, for which IIT Bombay is preparing the DPR; an outfall inventory with invert levels against the tide; the number of gated outfalls; the capacities and operating rules of the pumping stations; and a statement of how chart datum, the GTS datum and the Town Hall Datum relate. The fifteen-minute records of MCGM's automatic weather stations are also unpublished. Outside Mumbai, the WRD circulars and methods behind the blue and red flood lines, the operating rules of the dams whose releases set river levels at the outfalls, the report of the expert committee on Pune's flood lines and the full Wadnere Committee report were not found either. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.


10.18 Review of this chapter

10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.


References (chapter)

Annexes and forms

Annex / Form Content
10A Compliance calculator and user guide
10B GIS data specification and attribute schema
10C Maintenance access dimensions
10D Model O&M plans by facility type
10E Empanelment criteria for Stormwater Design Professionals and reviewers
Form 10-1 Drainage Report Checklist
Form 10-2 Compliance Calculator Summary
Form 10-3 Professional Design Certificate
Form 10-4 Hold-Point Inspection Record
Form 10-5 As-built Certificate
Form 10-6 Maintenance Declaration
Form 10-7 Annual Maintenance Declaration and Inspection Report
Form 10-8 Asset Handover Certificate
Form 2-1 Design Rainfall Sheet (Chapter 2)