Chapter 5Downstream and Tailwater Analysis
5.1 Purpose and scope
5.1.1 This chapter sets two checks that every regulated development and every public drainage project must pass.
- The downstream analysis (Clauses 5.3 to 5.5) confirms that the project does not make flooding worse below its outfall.
- The tailwater analysis (Clauses 5.6 to 5.13) sets the water level the system discharges into, including tide, storm surge, sea-level rise, river backwater and sand-bar closure. It also requires the system to cope when its outfall is closed.
5.1.2 This chapter applies to:
- (a) every site to which Chapter 4 applies;
- (b) every minor- and major-system drainage project under Chapter 6; and
- (c) every regional detention or tank restoration project under Clause 4.13 and Chapter 7.
5.1.3 Rainfall and joint-occurrence inputs come from Chapter 2, in particular Clauses 2.5.3 and 2.12. Hydrologic methods come from Chapter 3. Site release criteria come from Chapter 4. Hydraulic design of gates, culverts and pumps follows Chapter 9.
5.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Analysis point | A location on the downstream system where pre- and post-project conditions are compared (Clause 5.3.3). |
| Contributing catchment | The whole area draining to an analysis point, on and off site. |
| Major drain | A channel listed as a major drain in the basin plan or Annex 5B, or any river, WRD canal, the major nallahs of Greater Mumbai (those wider than 1.5 m in the MCGM storm-water drain inventory), the Ambil Odha in Pune, or a tidal creek. |
| Chart datum (CD) | The datum of the published tide tables and nautical charts, to which tidal heights are referred. |
| Mean sea level (MSL) | Average sea level over a long period at a tide gauge. |
| MHWS | Mean high water springs: the average of high waters at spring tides. |
| HAT | Highest astronomical tide: the highest level predicted under average meteorological conditions over a full tidal cycle (18.6 years). |
| Storm surge | The rise in sea level above the astronomical tide caused by wind and low pressure, mainly during cyclones. |
| Still-water level | Astronomical tide plus surge, excluding individual waves. |
| Sea-level allowance (SLA) | The allowance added to present-day tidal levels for sea-level rise over the design life (Clause 5.7.4). |
| Tailwater | The water level at the downstream end of a drain, outlet or storage. |
| Tide-lock | The condition in which the tailwater is at or above the upstream water level, so a gravity outfall cannot discharge. |
| Lock window | A period during which the outfall-closed check of Clause 5.10 sets gravity discharge to zero. |
| Sand bar | A bar of beach sand that partly or fully closes a river mouth or creek inlet. |
| Project datum | The levelling datum used on the project drawings. It must be tied to a Survey of India benchmark (Clause 5.7.2). |
5.3 Extent of the downstream analysis
5.3.1 The downstream analysis shall start at each site or project outfall. It shall continue downstream to the first of:
- (a) the point at which the project area is 10% or less of the contributing catchment;
- (b) the next tank, talav or other waterbody with a surplus weir or controlled outlet; or
- (c) the next major drain, or the sea.
The end point itself shall be analysed (Figure 5.1).
5.3.2 Where the analysis ends at a tank or talav under 5.3.1(b), it shall report:
- the change in the tank's maximum water level; and
- the change in surplus-weir discharge, for the AEPs and durations of Clause 5.4.3.
If the maximum water level rises, the analysis shall continue below the surplus weir to the next end point.
5.3.3 Analysis points shall be set at least at:
- (a) each site outfall;
- (b) each confluence with a drain or channel whose contributing catchment is at least half that of the receiving drain at that point;
- (c) each culvert, bridge or road crossing;
- (d) each location recorded as flood-prone by the local body, MCGM, MSDMA or WRD; and
- (e) each building or road segment lying within the 1% AEP flood extent along the route. Representative points may be used where buildings are closely spaced.
5.3.4 Small sites. For sites of less than 0.5 ha, the Authority may accept a simplified downstream statement (Form 5-2) in place of the full analysis, where all of the following hold:
- the receiving public drain has documented capacity for its minor-system design flow (Chapter 6);
- no flood-prone location is recorded within 500 m downstream; and
- the site does not drain to a tidal or backwater-affected outfall.
Figure 5.1 — Extent of downstream analysis: analysis points A–D, the contributing area at each point, the 10% point, and the next talav or major drain as an alternative end point. Schematic; percentages are illustrative. Original drawing for this Manual, adapted from the ten-percent rule in the Georgia Stormwater Management Manual (2016, Vol. 2 §3.1.9) and KC APWA Section 5600 (2006, 5601.5).
Commentary. The 10% rule has established precedent. KC APWA 5600 (2006) required the downstream system to be analysed "to the point the development's land mass is less than 10% of the total watershed". The Georgia manual makes the ten-percent analysis a mandatory standard (GSMM 2016, Standard #8). The tank or major-drain end point has no direct precedent; this Manual adds it for Maharashtra. In the Mumbai suburbs, where a nallah runs to the Mithi, Dahisar, Poisar or Oshiwara and then through a tidal creek (the Mithi alone is 17.84 km long and takes the spill of Vihar and Powai lakes), and in eastern Vidarbha, where a drain can pass through a chain of ex-malgujari talavs, the 10% point can lie many kilometres downstream, across several tanks. A tank with a working surplus weir changes the hydrograph completely, so the analysis is better ended there and the tank level reported. Clause 5.3.2 prevents that end point from hiding a rise in the tank level. The small-site statement (5.3.4) and its 500 m distance have no direct precedent and are set by this Manual.
5.4 What the analysis must check
5.4.1 Scenarios. Each analysis shall compare:
- (a) Existing: the present downstream system and present land use of the whole contributing catchment, with the project site at its pre-project state; and
- (b) With project: the same, with the project and all its controls (Chapter 4) in place.
Where the Authority's basin plan defines future land use, the Authority may also require:
- (c) Future: the catchment fully developed under the plan, all to Chapter 4 standards, with and without the project.
5.4.2 Quantities to be checked at every analysis point:
- (a) Capacity: peak flow against the capacity of every channel, pipe, culvert and crossing, for the minor-system AEP of that element (Chapter 6) and for 1% AEP;
- (b) Flood levels: 1% AEP maximum water level at buildings (at the lowest opening) and on roads (at the crown and at the deepest point);
- (c) Velocities: peak velocity for 50%, 10% and 1% AEP;
- (d) Timing of combined peaks: the hydrograph at each confluence, showing the time to peak of the project outflow and of the receiving drain; and
- (e) Duration of inundation: on roads and at buildings, the time above the Chapter 6 depth limits.
5.4.3 Storms. The analysis shall use:
- 50%, 10% and 1% AEP;
- the duration set of Clause 2.5.2, at least the durations that give the highest level at each analysis point (these will usually be longer than at the site); and
- the 24-, 48- and 72-hour storms in every case.
The AMC rule of Clause 2.11.4 applies. Areal reduction follows Clause 2.7, applied to the contributing catchment at each analysis point and never to the site storage.
5.4.4 Method. The analysis shall:
- use a hydrograph method that combines hydrographs at confluences (SWMM, HEC-HMS, or an equivalent);
- include a hydraulic model with backwater (SWMM dynamic wave, HEC-RAS, or equivalent) wherever tailwater or backwater affects any analysis point; and
- not use the Rational Method at any analysis point, because it cannot represent timing.
Off-site areas shall be modelled at their present land use. Upstream detention shall be included only where it is built, maintained and documented.
5.4.5 Tailwater. The downstream end of the model shall use the tailwater of Clauses 5.6 to 5.9 and the sand-bar condition of Clause 5.13 where applicable.
Commentary. Clause 5.4.2(d) exists because detention changes when the site's water arrives, not only how much arrives (Clause 4.16). A Colorado State University thesis and a Water (2016) optimisation study both found that delayed site releases can coincide with the main-stem peak and raise it. Georgia's manual states the result directly: some structural practices "fail to reduce discharge peaks to pre-development levels downstream" because of "peak flow timing and runoff volume effects" (GSMM 2016). The duration-of-inundation check (5.4.2(e)) matters in Mumbai, where 180 of the city's 186 storm-water outfalls lie below high-tide level and it is the low-tide hours that "have been providing relief" (Fact Finding Committee, 2006), so that flooding on a day when heavy rain meets a high tide lasts until the tide falls, and in Kolhapur and Sangli, where the 2019 flood on the Krishna and Panchganga ran from 25 July to 13 August (Wadnere Committee, as summarised by SANDRP). Detention that prolongs releases can lengthen that time even when it lowers the peak.
5.5 Acceptance criteria
5.5.1 The project is acceptable if, at every analysis point and for every AEP and duration of Clause 5.4.3, comparing "with project" to "existing":
- (a) the 1% AEP maximum water level does not rise by more than 10 mm at any habitable building, at any building's lowest opening, or on any road carriageway;
- (b) no building that is not flooded in the existing case is flooded with the project, and no building or road that meets the Chapter 6 freeboard or depth limits in the existing case fails them;
- (c) peak flow does not exceed the existing peak at the minor-system AEP of each element, or at 1% AEP;
- (d) peak velocity in lined channels stays within the permissible velocity for the lining (Chapter 6: 3.0 m/s maximum); and
- (e) in unlined or natural channels, peak velocity for 50% and 10% AEP does not increase by more than 10%, unless protection is provided under Chapter 9.
5.5.2 The duration of inundation under 5.4.2(e) shall be reported. The Authority may refuse a project that increases the duration of road closure on an arterial or emergency route.
5.5.3 Where the criteria are not met, the project shall do one or more of the following:
- (a) reduce release rates or increase storage (Chapter 4);
- (b) build downstream improvements, with the consent of the owner of the downstream system. These shall not transfer the problem further downstream, and shall be re-analysed under this chapter;
- (c) contribute to a regional facility under Clause 4.13; or
- (d) under Clause 5.5.4, change the release strategy.
5.5.4 Timing exception. Where the analysis shows that detention raises downstream levels because of timing, the Authority may vary the site release-rate criteria of Clause 4.5. This applies only where the site discharges within the lower tenth of the contributing catchment, directly to a major drain, tidal creek or the sea, and only on the following conditions:
- (a) the varied strategy meets 5.5.1;
- (b) the retention requirement (Clause 4.4) and WQv treatment (Chapter 8) are met in full; and
- (c) the outfall-closed check (Clause 5.10) is met.
Commentary. The 10 mm tolerance (5.5.1(a)) has no direct precedent. It is meant to be at or below the numerical precision of a typical one-dimensional model, so that "no increase" can be tested without arguing over rounding. The 10% velocity tolerance is likewise set by this Manual. The timing exception in 5.5.4 follows the Georgia manual, where the downstream analysis can show "that peak controls are not needed" and allow them to be waived (GSMM 2016, Standard #8). It is limited here to sites low in the catchment, which is where synchronisation with the main-stem peak is most likely (Water 2016, 8(7):290). It is not available above that, because the evidence on scale (Clause 4.16) shows that early release from many upstream sites raises peaks.
5.6 Tailwater: general and non-tidal outfalls
5.6.1 Every drain, outlet and storage shall be designed against a stated tailwater. A free outfall shall be assumed only where the outlet invert is above the maximum receiving water level for the case being checked.
5.6.2 Minor-system tailwater, non-tidal. The tailwater is the receiving system's water level at the time of the minor-system peak, from the downstream model. Where no model exists, use:
- for a receiving pipe, its obvert; or
- for a receiving open drain, its full-bank level less freeboard (Chapter 6).
5.6.3 Major-system tailwater, non-tidal. The tailwater is the receiving system's 1% AEP water level, unless Clause 5.8 allows a coincident lower level.
5.6.4 Tidal and backwater outfalls. Clauses 5.7 to 5.13 apply in addition.
5.6.5 Storage elements. Detention, tanks and pumped sumps shall be routed with a time-varying tailwater (Clause 4.6.6), not a constant level, wherever the tailwater varies with tide or with the receiving system's hydrograph.
5.7 Tidal tailwater: datums, surge and sea-level allowance
5.7.1 Design tailwater levels. For outfalls to the sea, tidal creeks, estuaries, backwaters and tidal reaches of rivers and canals:
Table 5.1 — Design tailwater levels for tidal outfalls
| Design case | Tailwater |
|---|---|
| Minor-system design (Chapter 6) | MHWS + SLA |
| Major-system design and storage design | HAT + surge + SLA, with the surge term defined in Clause 5.7.3 |
| Joint case (Clause 2.12(b)) | 1% AEP still-water level + SLA |
The SLA is +0.3 m minimum (Clause 5.7.4). The cases to be run are listed in Clause 5.9.
5.7.2 Sources and datums.
- (a) Tidal levels. MHWS, HAT and MSL shall be taken from the current edition of the Indian tide tables published by the National Hydrographic Office (NHO) or by the Survey of India, for the nearest standard or secondary port, or from the port authority's published tidal levels. The edition and port shall be stated.
- (b) Datum conversion. Tide-table heights are referred to chart datum. They shall be converted to the project datum through a documented connection between chart datum, the tide gauge zero and a Survey of India benchmark. The offset and its source shall be stated on Form 5-1.
- (c) Estuaries, creeks and canals. For outfalls inside estuaries, creeks, backwaters or tidal canals (for example the Mahim, Mahul, Thane and Malad creeks in Mumbai, the Ulhas estuary, and the tidal reaches of the Vashishti at Chiplun and the Savitri at Mahad), tidal levels may differ from the open coast. Open-coast levels shall be used unless measured levels over at least one spring–neap cycle, or a calibrated hydrodynamic model, justify a different value. No reduction below open-coast levels shall be taken without such evidence.
- (d) Interim. Until Annex 5A is published, the designer shall obtain the values directly from the sources in (a) and record them.
5.7.3 Storm surge.
- (a) Major-system and storage design. The surge term in "HAT + surge" is the 10% AEP (10-yr) storm surge for the coastal segment, given in Annex 5A. The 1% AEP surge is used only in the joint case of Clause 2.12(b), with the 10-yr 48-hour storm. That keeps the two cases symmetric, so that a rare rainfall is never paired with a rare surge.
- (b) Joint case. The 1% AEP still-water level for Clause 2.12(b) is taken from Annex 5A.
- (c) Until Annex 5A is published, both values shall be taken from a site-specific study using INCOIS, IMD or NCCR surge hindcasts or return-level analyses. The study shall state its source, method and record length.
- (d) Wave set-up shall be added where the outfall faces the open sea without a protected entrance.
5.7.4 Sea-level allowance. The SLA shall be:
- (a) +0.3 m minimum for every element;
- (b) greater than 0.3 m where the State, MMRDA or the Authority adopts a higher projection for the planning area, for example a projection based on the INCOIS (2025) estimates for Mumbai of about 0.42 m (SSP2-4.5) and 0.67 m (SSP5-8.5) of mean-sea-level rise by 2100; and
- (c) assessed for the design life of the element. For elements with a design life of more than 50 years, the designer shall report the effect of a sea-level rise of twice the SLA as a sensitivity run.
Figure 5.2 — Tidal outfall: flap gate, property non-return valve, and the design tailwater levels (MHWS + 0.3 m for the minor system; HAT + surge + 0.3 m for the major system), with a seasonal sand bar at the mouth. Schematic, not to scale. Original drawing for this Manual, adapted from the tidal tailwater table in MoHUA/CPHEEO Manual on Storm Water Drainage Systems (2019), Part A, Table 6.2.
Commentary. CPHEEO (2019) Table 6.2 sets the design tailwater for coastal outfalls as:
- MHWN to MHWS for a minor storm (more frequent than 1 in 5 years);
- MHWS to HAT for a major storm; and
- "Effect of climate change: additional 0.3 m".
CPHEEO also says the joint probability of storm, tide and surge "should" be considered, with the state maritime board consulted. This Manual takes the upper end of each CPHEEO range, adds surge for the major system, and makes the joint case explicit (Clause 2.12). CPHEEO does not require surge to be added; this Manual adds it because the INCOIS (2025) estimate that surge and wave set-up add about 1.54 m to the 100-year sea level at Mumbai, on top of a modelled tidal maximum of 2.64 m, showed why it is needed in Maharashtra.
Indian tide tables have been published by the Survey of India since the nineteenth century; at Mumbai (Apollo Bandar) a tide gauge has records from 1878 (PSMSL station 43), referred to chart datum since 1937, and its annual means for 2015–2024 put mean sea level about 2.70 m above chart datum (derived for this Manual from the PSMSL data, to be confirmed against the tide tables) (Survey of India, Tidal Predictions). Current Indian tidal predictions also appear in the NHO's tide tables. One port document describes the current edition as covering 95 Indian ports, based on NHO observations and on data from civil ports, NIO and INCOIS (Adani Ports, Dahej tide table 2025, citing NHO INP-12). INCOIS runs coastal tide gauges and issues storm-surge and swell-surge warnings. Its 2025 technical report gives 100-year extreme sea levels for Mumbai (4.22 m above mean sea level at present, made up of a modelled tidal maximum of 2.64 m and 1.54 m of surge and wave set-up; 4.59 m and 4.88 m by 2100 under SSP2-4.5 and SSP5-8.5), but no value for Ratnagiri or the other Konkan ports, or for points inside the creeks, was found during research. No surge return-level product for the Mumbai creeks or the Konkan estuaries suitable for design was found during research, and the National Hydrographic Office values of MHWS and HAT for Mumbai (Apollo Bandar) and Ratnagiri were not seen [TBC], which is why Annex 5A is needed. The sources also mix datums. The Fact Finding Committee (2006) gives Mumbai's tide levels on the GTS (mean sea level) datum, with an average high tide of 2.5 m and an annual highest tide of 2.75 m; MCGM's lake and drain levels are on Town Hall Datum; and the datum of the 4.48 m high tide of 26 July 2005, and of the 4.5 m high tide that MCGM uses as an operational trigger, is not stated. Every level used under this chapter shall therefore name its datum. The long-term trend at Mumbai is 1.16 ± 0.20 mm/yr for 1878–2020 (PSMSL, which warns that its trends are not for planning use); the sea-level allowance of Clause 5.7.4 does not depend on it.
5.8 Riverine backwater
5.8.1 Where it applies. Outfalls to rivers and canals whose water level in a storm can exceed the outfall invert shall be designed with riverine backwater. This includes:
- in Mumbai: the Mithi and Mahim creek, the Dahisar, Poisar and Oshiwara, and the Mahul, Thane and Malad creeks;
- in Navi Mumbai: Thane creek and the tidal holding ponds that drain to it (with the tailwater of Clause 5.8.5);
- in Thane and Kalyan: the Ulhas estuary;
- on the Konkan coast: the tidal reaches of the Vashishti at Chiplun, with the releases of Clause 5.8.3, and of the Savitri at Mahad, and the bunded khajan lands of the creeks (Clause 5.8.5);
- in Kolhapur and Sangli: the Panchganga, the Warna and the Krishna, with the releases of Clause 5.8.3 and the backwater of Clause 5.8.5;
- in Pune and Pimpri-Chinchwad: the Mutha below Khadakwasla, the Mula and the Indrayani, with the WRD flood lines;
- in Nagpur: the Nag river below Ambazari lake;
- in Akola: the Morna; and
- elsewhere: any river or WRD channel listed in Annex 5B.
5.8.2 River levels. River water levels shall be taken from:
- (a) WRD design flood levels or recorded highest flood levels for the reach, where published; or
- (b) a hydraulic model (HEC-RAS or equivalent) of the river reach. The model shall use:
- the river design flood from a hydrograph method (Chapter 3), with continuous simulation where Chapter 3 requires it;
- the tidal boundary of Clause 5.7 at the mouth; and
- the sand-bar condition of Clause 5.13.
5.8.3 Reservoir and tank releases. Where a reservoir or tank upstream can release to the river (for example Koyna and Kolkewadi above the Vashishti at Chiplun, the Warna, Tulshi, Kasari, Kumbhi and the other dams of the upper Krishna basin above Kolhapur and Sangli, Khadakwasla above the Mutha at Pune, or Vihar and Powai lakes, which spill to the Mithi in Mumbai), the river level shall include the release given by the reservoir's operating rule for the storm being checked. Where there is no published rule, it shall include the largest recorded release.
5.8.4 Coincidence of site storm and river flood. Unless a joint-probability study is accepted by the Authority, the more severe of the following governs:
- (a) the site design storm (AEP as required), with the river at its 10% AEP (10-yr) level; and
- (b) the site 10% AEP storm, with the river at its design-AEP level (1% AEP for the major system).
The two storms in each pair shall have the same duration and timing where they are generated by the same rainfall event.
5.8.5 Creek holding ponds, flood gates, irrigation canals, and dam-release and backwater reaches.
-
(a) Tidal holding ponds. For an outfall into a tidal holding pond (a pond behind a creek bund that stores town drainage while its gates are shut at high tide and empties at ebb, as in Navi Mumbai), or into a drain that ends in one, the tailwater at the pond shall be the maximum level computed by routing the pond for each case of Clause 5.9, with:
- the routing starting at the higher of the lowest level the gates can draw the pond down to at low water and the level observed at the most recent pre-monsoon survey;
- the pond's storage as surveyed in its present condition, net of silt and vegetation, and not its design storage;
- the gates discharging only while the creek level of Clause 5.7 is below the level in the pond, through their surveyed opening in their present condition; and
- the inflow of the whole catchment that drains to the pond.
No storage shall be credited that can be regained only by desilting, deepening or clearing within a mangrove area or its 50 m buffer, until the permissions that work needs (the leave of the High Court and CRZ clearance, Clause 6.11.6) have been granted and the work is done.
-
(b) Gated creek outfalls and khajan lands. For an outfall through a flood gate, sluice or bund to a tidal creek, including drainage through the bunded tidal lands (khajan) of the Konkan creeks, the designer shall identify the body that operates the gate and survey the gate sill and the bund crest. Where the gate can discharge for only part of each tide, the lock windows of Clause 5.10 shall be extended to the period for which the creek stands above the level upstream of the gate (Clause 5.10.6). Floor levels and pumped outfalls behind a bund shall also be checked for a breach of the bund, with the land behind it filled to the creek level.
-
(c) Dam-release and backwater reaches. For an outfall to a river reach whose level is set by releases from dams upstream or by the pond or backwater of a dam or barrage downstream (for example the Krishna, Panchganga and Warna at Kolhapur and Sangli, or the Mutha below Khadakwasla), the river level of Clause 5.8.2 shall:
- include the releases of Clause 5.8.3 from every dam above the reach, combined as they occurred in the largest recorded event, unless an operating rule in force staggers them;
- be computed with the downstream boundary of the river model at the full reservoir level of the next dam or barrage downstream, or at its recorded level in the largest recorded event if that is higher, unless the model is carried far enough downstream that moving the boundary changes the level at the outfall by less than 10 mm; and
- for the major-system cases, be not less than WRD's red flood line level at the outfall, where a red line has been drawn.
-
(d) Irrigation canals. Town drainage shall not be discharged to an irrigation canal without the permission of WRD or the canal's owner. Where permission is given, the tailwater is the higher of the canal's full supply level during irrigation releases and its flood level for the coincident case of 5.8.4, and the outfall shall have a flap gate where the full supply level is above the outfall invert.
No gate or release operation that helps drainage, such as opening a holding-pond gate early, drawing a pond down before a storm or staggering dam releases, shall be assumed unless the operator's written records show it. Where the outfall invert is below the tailwater of this clause, the outfall shall have its own flap gate (Clause 5.11) and, where the outfall-closed check requires it, pumping (Clause 5.12), with the pumped volume included in the routing of the pond or the river level (Clause 5.12.3).
Commentary. In large continental river basins, a site storm and a river flood are usually treated as roughly independent. That is the basis of tables of coincident frequencies such as FHWA HEC-22 Table 7.3. Maharashtra's rivers break that assumption on both sides of the Western Ghats. The Konkan rivers are short and fall from a Ghats crest where the annual rainfall reaches about 6,200 mm at Mahabaleshwar and Gaganbawada (CWC Flood Estimation Report, subzone 3(h)) to tidal creeks, so the same south-west monsoon spell raises the town drains, the river and, at high tide, the creek together, as at Chiplun and Mahad in July 2021. East of the Ghats the rivers are regulated. In August 2019 the Warna, Tulshi, Kasari and Kumbhi reservoirs were already 72–80% full when the heavy rain began, rainfall in Kolhapur, Sangli and Satara ran at 344% to 431% above normal, and releases from the nine projects of the upper Krishna came "nearly simultaneous[ly]" from 5 to 7 August (WRD figures, as reported by SANDRP, 2020), so the town's own storm and the river flood came from the same spell. Clause 5.8.4 therefore pairs a design event on one side with a 10-yr event on the other, in the same way as Clause 2.12(b). This pairing has no direct precedent. It is more severe than an independence assumption would give.
Clause 5.8.3 reflects three Maharashtra cases. In Pune, releases from Khadakwasla took the Mutha above its blue flood line at 45,474 cusec in 2019 and at 35,574 cusec on 25 July 2024, although the line is drawn for 60,000 cusec, and MERI now puts the blue-line discharge of the Mutha above the Mula confluence at about 1,07,738 cusec (SANDRP, 2024 and 2026). In the upper Krishna basin, releases from the Warna, Tulshi, Kasari, Kumbhi and the other projects came together from 5 to 7 August 2019 (SANDRP, 2020). At Chiplun, residents blamed releases from Kolkewadi and Koyna for the flood of 22 July 2021 (press reports), but no release record for that day was found during research. No published operating rule or release hydrograph for any of these dams was found, so until one is published the largest recorded release applies, and that record is itself to be obtained from WRD.
Clause 5.8.5 is set by this Manual. Maharashtra has no delta drains, but it has three settings in which the tailwater at a town outfall is set by a structure, and by how it is worked, rather than by the open tide or a free river.
The first is the tidal holding pond. CIDCO built Navi Mumbai's drainage around 11 holding ponds and more than 75 km of storm-water drains, with gates that shut at high tide and open at ebb (SACON report for NMMC, 2024, as summarised; press). Flooding in the city has been blamed on silted ponds and failed flap gates (press reports). The ponds also lie among mangroves: in 2018 fishermen at Uran petitioned the High Court against two of them, and the Court was reported to have ordered CIDCO to keep sluice gates open (press, 2018). Since the High Court's judgment of 17 September 2018 (PIL No. 87 of 2006), a public project may cut mangroves only with the leave of the Court under paragraph 83(viii) and with CRZ clearance (WP (L) No. 17795 of 2026, 17 September 2026). That is why Clause 5.8.5(a) credits only the storage a pond has now, and none that depends on clearing it until the permissions are in hand. Whether a pond should be desilted through mangroves is a question for the Court and MCZMA. The design should not assume the answer.
The second is the bunded tidal land of the Konkan creeks, the khajan, "ground recovered from the sea by an embankment" (Molesworth, 1857), which drains through gates or sluices in its bund. No record of who works these gates, or of their sill and bund levels, was found during research, so Clause 5.8.5(b) requires both to be found and surveyed, as at any other gated creek outfall.
The third is the dam-release and backwater reach of the Krishna basin. Kolhapur and Sangli flood when releases from the upstream dams arrive together and the Krishna backs up; Sangli has flooded in 1853, 1856, 1914, 2005, 2006 and 2019 (SANDRP, 2019). Whether the backwater of the Almatti dam, downstream in Karnataka, raised the levels at Sangli is disputed. The CAG wrote of 2005 that action on the lines it recommended "would have avoided Almatti dam backwater effect faced by Sangli district" (CAG, Floods in Maharashtra, 2006). The Wadnere Committee found the Almatti backwater not responsible for the 2019 flood (report of 28 May 2020), but a member who resigned and SANDRP contest that finding, pointing to the lack of a gauging station near the Irwin bridge and to river cross-sections dating from 2012 (SANDRP, 2020). Clause 5.8.5(c) does not decide the question. It puts the model's downstream boundary at the pond level, or carries the model far enough downstream for the boundary not to matter, so that the designer's own model shows whether the backwater reaches the outfall. The red-line floor in (c) applies because WRD's flood lines are the State's own statement of the 100-year level, although the discharges behind them have been contested: WRD's own affidavit called Pune's 2011 and 2016 lines unscientific, and Kolhapur's draft discharges were alleged to have been cut by more than half between drafts (SANDRP, 2026; PTI, 2019). The canal rule in (d) is also set by this Manual; no WRD rule on town drainage into irrigation canals was found during research.
5.9 Joint-probability cases
5.9.1 Every element draining to a tidal or backwater-affected outfall shall be checked for the cases below. The most severe governs each design quantity: storage, water level, pipe size and pump capacity.
Table 5.2 — Joint-probability cases for tidal and riverine outfalls
| Case | Rainfall | Tailwater | Applies to | Basis |
|---|---|---|---|---|
| J1 | Minor-system design AEP, Tc to 24 h | MHWS + SLA (tidal curve) | Minor system | Clause 2.12(a); Clause 5.7.1 |
| J2 | 1% AEP, all durations of Clause 2.5.2 | HAT + surge + SLA | Major system, detention, tanks, pumped systems | Clause 5.7.1 |
| J3 | 10% AEP, 48 h | 1% AEP still-water level + SLA | Major system, detention, tanks, pumped systems | Clause 2.12(b) |
| J4 | Design AEP, 48 h (72 h reported) | Tidal curve per J1 with two 6 h lock windows (Clause 5.10) | All storage and every gated or tide-affected outfall | Clause 5.10 |
| R1 | Site design AEP | River at 10% AEP level | Riverine outfalls | Clause 5.8.4(a) |
| R2 | Site 10% AEP | River at design-AEP level | Riverine outfalls | Clause 5.8.4(b) |
5.9.2 For storage elements, the 48- and 72-hour storms shall be run with the J2 and J3 tailwaters (Clause 2.5.3).
5.9.3 For tidally influenced riverine outfalls, R1 and R2 shall be run with the river model's downstream boundary at the J1 tidal curve. The Authority may also require them at J2.
5.9.4 Where tailwater is constant at a level above the outfall invert for the whole storm, the case is treated as a fully closed outfall. Storage and pumps shall then handle the full storm volume.
Commentary. Clause 2.12 sets two joint cases. Case (a) is design rainfall with MHWS plus the sea-level allowance. Case (b) is the 10-yr, 48-hour storm with the 1% still-water level. This Manual adds HAT plus surge for major-system design (Clause 5.7.1). Case J2 combines these. J4 is the outfall-closed check, which tests the timing of tide against the storm rather than a single level. Rainfall and surge share a cyclone cause, so they cannot be treated as independent (Clause 2.12 commentary). These cases are simple surrogates, to be replaced when a statistical joint analysis of IMD rainfall and tide-gauge records is adopted.
5.10 Outfall-closed (tide-locked) storage check
5.10.1 Where it applies. The check applies to:
- every storage facility;
- every minor- and major-system element; and
- every pumped system
whose outfall invert is below HAT + surge + SLA, or which drains to a reach subject to tide-lock or sand-bar closure (Clause 5.13).
5.10.2 Storm. Use the 48-hour design storm built per Clause 2.9.2 (peak day last), at:
- the AEP of the element: 1% AEP for detention, tanks and the major system; the minor-system AEP for minor drains; and
- AMC III.
The 72-hour storm shall also be run and reported.
5.10.3 Lock windows. Unless a site study under 5.10.6 gives otherwise:
- (a) the outfall is closed for two consecutive lock windows of 6 hours each, centred on two consecutive high tides of the local tidal curve. For a semi-diurnal tide, the window starts are therefore about 12.4 hours apart.
- (b) During each lock window, gravity discharge is zero.
- (c) Between lock windows, gravity discharge is computed against the J1 tidal curve, including the head loss of the flap gate and any non-return valve.
- (d) The first lock window shall be placed so that it is centred on the peak 1-hour block of the final 24 hours of the storm. A second run with the first window starting at that peak block shall also be made. The more severe governs.
5.10.4 Requirement. Storage plus pumping (where provided) shall hold the inflow so that, throughout the check:
- (a) the maximum stage in any detention facility stays below its emergency spillway crest, so the spillway does not operate. Where the outfall-closed stage is higher than the 1% AEP maximum water level of the free-outfall design, it becomes the facility's 1% AEP maximum water level for Clause 4.9.3, and the spillway crest, freeboard and wall height are set from it;
- (b) the maximum stage in the minor and major systems meets the Chapter 6 limits: building floor levels, and street depths of no more than 150 mm at the crown and no more than 350 mm at the deepest point; and
- (c) no property connection surcharges above the lowest opening it serves, or a non-return valve is fitted under Clause 5.11.
In volume terms, over each lock window and the full storm:
V_inflow ≤ V_storage available + V_pumped + V_gravity (between locks)
This shall be demonstrated by routing, not by a single volume balance. The release from each facility after a lock window ends may exceed the release caps of Chapter 4, because the facility is emptying into a drain that has just reopened. That release shall be included in the downstream analysis (Clauses 5.4 and 5.9).
5.10.5 Drawdown after the storm. After the second lock window, the storage shall drain under the J1 tidal curve. The drawdown requirement of Clause 4.7 shall be met, with pumping where gravity cannot meet it (Clause 5.12).
5.10.6 Site study. A longer or shorter lock may be used where a site study gives a time series of still-water level for the design case. The study may use a calibrated hydrodynamic model, gauge records of past events, or a surge hindcast. Locks shorter than the default require the Authority's approval. A longer lock shall be used where:
- sand-bar closure (Clause 5.13) or river backwater (Clause 5.8) keeps the outfall closed for longer; or
- the gauge record shows tailwater above the outfall invert for more than 6 hours per tide in comparable past events.
Figure 5.3 — Outfall-closed check: 48-hour storm with the peak day last (Clause 2.9.2), tailwater of astronomical tide plus surge, two 6-hour design lock windows, and the resulting stage upstream of the flap gate. Illustrative — not design values. Original drawing for this Manual, adapted from the tidal tailwater and joint-probability concepts of MoHUA/CPHEEO Manual on Storm Water Drainage Systems (2019), Part A, §6.3.6.
Commentary. The outfall-closed check is the distinctive Maharashtra requirement in this Manual. Mumbai shows why. Of the 186 storm-water outfalls counted by the Fact Finding Committee, 45 lie below mean sea level, 135 lie above it but below high tide, and only 6 lie above high tide; few are gated, and "it is the low tide periods … that have been providing relief" (Fact Finding Committee, 2006). The island city's drains, laid from the 1860s, were designed for 25 mm/h "during low tide hours". On 26 July 2005 the high tide peaked at 4.48 m at 15:30, inside a burst of about 380 mm in three hours between 14:30 and 17:30, and the committee found that "even if the entire system had been upgraded as per BRIMSTOWAD, the same would not have been adequate" (FFC, 2006). The city's answer has been storage and pumping behind its outfalls, and it is still incomplete. BRIMSTOWAD planned eight storm-water pumping stations. Six now operate, at Haji Ali, Irla, Love Grove, Cleveland Bunder, Britannia and Gazdarbandh (press reports). Mogra and Mahul were still unbuilt about twenty years on, four of the eight having been held up for want of sites (CAG Report No. 6 of 2014); work at Mogra was reported to begin in October 2026. The CAG found that "flooding of low-lying areas, even when rainfall is less than 50 mm per hour, continues to be a regular feature" (2014). In July 2026 MCGM's Commissioner called waterlogging "unavoidable" when about 300 mm falls in a short span with a 4.5 m high tide (press report). A rate rule cannot help when there is no outlet: an orificed basin behind a closed gate simply fills.
The default of two consecutive 6-hour locks has no direct precedent. It represents gravity outfalls failing to discharge for about half of each tidal cycle around the two high tides nearest the storm peak. Figure 5.3 shows why both windows matter. The first lock catches the storm peak. The second arrives before the storage has drained, so the stage rises again.
Placing the first window on the rainfall peak is deliberately unfavourable. Cyclone rainfall and surge share a cause, and Clause 2.12 already treats them as dependent. The check replaces neither the J2 and J3 level checks nor the downstream analysis; it adds a test of timing and volume.
5.11 Flap gates, tide gates and non-return valves
5.11.1 Where required. A flap gate, tide gate or equivalent non-return device is required on every outfall whose invert is below the 1% AEP still-water level (Clause 5.7.3). It is also required on outfalls into irrigation channels under Clause 5.8.5.
5.11.2 Hydraulics. The design shall include:
- the gate's head loss and opening head, from the manufacturer's certified head–discharge curve; and
- the reduction in effective outfall capacity when the gate is partly open.
Gates shall not be assumed to seal perfectly in the outfall-closed check unless they are tested.
5.11.3 Construction.
- (a) Gates, hinges and seats shall be of corrosion-resistant materials suitable for seawater (Clause 4.12.5).
- (b) The gate shall be set so that sand, silt or debris on the downstream side cannot hold it shut or open. Where the bed is mobile, the gate invert shall be raised above the bed, or the approach shall be protected.
- (c) A trash screen shall be provided upstream where the gate could be jammed by debris.
- (d) A stop-log slot or penstock shall be provided upstream for maintenance isolation on outfalls larger than 600 mm.
- (e) The gate chamber shall be accessible at all tides, with its access above HAT + surge + SLA.
5.11.4 Non-return valves on property connections. A non-return valve, or a backwater valve with an accessible cleaning eye, is required on every property drainage connection where the lowest opening served is below:
- the major-system tailwater (J2) at the point of connection; or
- the maximum stage in the outfall-closed check (Clause 5.10).
Basement drainage shall in addition be pumped to a level above both, with its own non-return valve.
5.11.5 Inspection. Gates and valves shall be inspected and operated:
- before 31 May each year;
- after every event in which they closed against a storm flow; and
- as set in the maintenance plan (Chapter 10).
Commentary. The requirement for gates below the 1% still-water level is set by this Manual. The construction details follow common coastal-drainage practice. A gate that is jammed open by debris lets the tide into the drain. A gate held shut by a sand bank turns a gravity outfall into a dead end. Both failures occur in Maharashtra. In Navi Mumbai, flooding has been blamed on silted holding ponds and failed flap gates, and the municipal corporation tendered for new flap gates at Koparkhairane in 2026 (press reports and tender notice); in Mumbai, only a few of the 186 outfalls are gated at all (Fact Finding Committee, 2006). The 31 May inspection date is set ahead of the SW monsoon.
5.12 Pumped outfalls
5.12.1 When required. Pumping shall be provided where gravity discharge cannot meet:
- the outfall-closed check of Clause 5.10;
- the drawdown requirement of Clause 4.7; or
- the J2 and J3 cases.
Pumping shall not be used where a gravity solution meets these requirements.
5.12.2 Capacity.
- (a) The duty pumps together, with the storage provided, shall pass every case of Clause 5.9 (including J4), demonstrated by routing.
- (b) Standby capacity at least equal to the largest duty pump shall be installed (duty + 1 standby as a minimum).
- (c) Pump capacity shall be stated at the static head for the J2 tailwater, not at mean tide.
5.12.3 Effect on the receiving water. Pumped discharge to a river, canal or creek shall be included in the river or creek level analysis of Clause 5.8. Pumping that raises the receiving water level above the acceptance criteria of Clause 5.5 elsewhere is not permitted.
5.12.4 Power supply. Pumping stations shall have either:
- two independent power supplies; or
- standby generation for 100% of the duty capacity, with on-site fuel for at least 72 hours of duty operation.
Changeover shall be automatic.
5.12.5 Flood immunity. Electrical panels, control equipment, generators and fuel storage shall be set above the higher of:
- the 1% AEP flood level + 0.5 m; and
- HAT + surge + SLA + 0.5 m.
Access to the station shall remain usable in the 1% AEP event.
5.12.6 Discharge arrangement. Rising mains shall discharge:
- over a level above the J2 tailwater; or
- through a non-return valve and a flap gate.
The arrangement shall prevent back-siphoning.
5.12.7 Controls and monitoring. Each station shall have:
- automatic level control;
- remote alarms for high level, pump failure and power failure, sent to the operator; and
- a level and run-time log kept for at least 5 years.
Wet wells shall be sized to keep pump starts within the manufacturer's limits.
5.12.8 Screens. Inlet screens shall be provided with a cleaning method that works during a storm (a mechanical rake, or duplicate screens).
5.12.9 Testing. Every pumped outfall shall be test-run at full duty, including on standby power, before 31 May each year. Private pumped systems shall be covered by a registered maintenance declaration (Chapter 10).
Commentary. Duty + standby, 72 hours of fuel and flood-immune electrics have no single direct precedent and are set by this Manual. The 72-hour fuel figure matches the longest mandatory design storm (Clause 2.5.2). A pump station that depends only on grid power can stop exactly when it is needed, because supply to flooded areas is often switched off for safety. Singapore's April 2025 amendments added annual maintenance declarations for pumped detention tanks (PUB Addendum No. 3). Clause 5.12.9 and Chapter 10 adopt the same approach. Clause 5.12.3 prevents pumping that simply moves water from one tide-locked drain into a tide-locked river.
5.13 Sand-bar closure of river mouths
5.13.1 Where it applies. This clause applies to outfalls into any river or creek whose mouth is subject to seasonal sand-bar closure. That includes any creek or river mouth on the Konkan coast that a pre-monsoon survey shows closed or restricted by sand, and any other mouth listed in Annex 5B.
5.13.2 Assumption at the start of the SW monsoon. The mouth shall be assumed closed by a bar at the start of the June–September season, at the crest level of the most recent pre-monsoon survey. This applies unless WRD certifies that:
- a mouth-maintenance programme (dredging, bar cutting or training walls) has kept the mouth open at the start of each of the previous three SW monsoon seasons; and
- the programme is funded for the current season.
5.13.3 Tailwater with a closed mouth. With the mouth closed, the tailwater at the outfall shall be the higher of:
- (a) the tidal tailwater of Clause 5.7; and
- (b) the level in the river reach behind the bar, computed with the bar as a weir at its surveyed crest level. That level shall include the river flow of Clause 5.8 and the head needed to pass the flow over or through the bar.
5.13.4 No credit for emergency cutting. Bar cutting or breaching during the storm shall not be assumed in design, unless WRD has a documented operating procedure, with equipment stationed for it. Where it does, the bar may be assumed lowered to the procedure's target level only after the time the procedure states.
5.13.5 Outfall-closed check. Where the closed-mouth level of 5.13.3(b) exceeds the outfall invert for longer than the default lock windows, the lock duration of Clause 5.10 shall be extended to that period.
Commentary. The research for this Manual found no record of seasonal sand-bar closure at the mouths of Maharashtra's rivers or creeks, and no WRD or municipal procedure for clearing them. The nearest problem found is on Mumbai's open-sea frontage, where the Coastal Road reclamation is reported to move outfalls about 200 m seaward on average and to extend about six drains to the project boundary, and where waterlogging at Breach Candy in 2025 was blamed on the reclamation (press reports; details not verified). So Clause 5.13.4 gives no credit for cutting at present, and the mouths to which Clause 5.13.1 applies are to be confirmed by pre-monsoon survey and listed in Annex 5B. Clause 5.13.2 has no direct precedent. It puts the burden of proof on showing that the mouth is open rather than assuming it.
5.14 Documentation
Every project subject to this chapter shall submit a Downstream and Tailwater Report (Form 5-1). It shall contain:
- a plan of the analysis extent showing:
- the site;
- each analysis point with its contributing catchment area and the site's percentage of it; and
- the end point and the reason it was chosen (Clause 5.3);
- the model description:
- software and version;
- the network schematic, with survey sources for the drains and crossings;
- land use and CN for off-site areas;
- any upstream detention included; and
- calibration or validation evidence where available;
- for each analysis point, AEP and duration, the existing and with-project:
- peak flow;
- time to peak;
- maximum water level and velocity; and
- duration of inundation (Clause 5.4);
- the comparison against Clause 5.5, with each failure identified and the remedy adopted;
- the tailwater derivation:
- tide-table edition and port;
- MHWS, HAT and MSL relative to chart datum;
- the datum connection to the Survey of India benchmark and the project datum;
- surge source and value;
- SLA; and
- river levels and their sources (Clauses 5.6 to 5.8);
- the joint-case table of Clause 5.9 with results;
- the outfall-closed check (Clause 5.10):
- storm and lock alignment;
- stage hydrographs; and
- the volume balance for each lock window;
- a schedule of flap gates, tide gates and non-return valves, with certified head–discharge data (Clause 5.11);
- pumped outfall design, power supply, flood immunity and controls, where provided (Clause 5.12);
- the sand-bar assumption and supporting WRD certification, where relevant (Clause 5.13); and
- inspection and maintenance requirements for Chapter 10.
Small sites under Clause 5.3.4 shall submit Form 5-2 (Simplified Downstream Statement) instead.
References (chapter)
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A, §6.3.6 and Table 6.2 (coastal tailwater; +0.3 m climate allowance). https://web.archive.org/web/2024/https://mohua.gov.in/upload/uploadfiles/files/VolumeI-Part%20A-Engineering-Design.pdf
- MoHUA / CPHEEO (2013). Manual on Sewerage and Sewage Treatment Systems (pumping stations).
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (5601.5, ten-percent downstream analysis). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Atlanta Regional Commission / Georgia EPD (2016). Georgia Stormwater Management Manual, Vol. 1 (Standard #8) and Vol. 2 §3.1.9. https://documents.atlantaregional.com/gastormwater/GSMM_2016%20EDITION_FINAL_V1.pdf
- MARC. The Evolution of Regional Stormwater Design Standards. https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Optimisation of urban detention (2016). Water 8(7):290. https://doi.org/10.3390/w8070290
- Colorado State University. Spatially Dependent On-Site Detention Policies (thesis). https://mountainscholar.org/bitstreams/f4dbec4e-a44f-4933-8d54-a097e741f44a/download
- Government of Maharashtra (2006). Fact Finding Committee on Mumbai Floods, Final Report, Vol. I (chair Dr Madhav Chitale), March 2006 (outfalls, tide levels, 26 July 2005 storm and tide, BRIMSTOWAD storm table). https://questionofcities.org/wp-content/uploads/2022/07/Fact-Finding-Committee-on-Mumbai-Floods.pdf
- MCGM, Chief Engineer (Storm Water Drains) (2008). RTI Manual, Chapter 1 (drain inventory, outfalls, BRIMSTOWAD). https://portal.mcgm.gov.in/irj/go/km/docs/documents/MCGM%20Department%20List/Chief%20Engineer%20(Storm%20Water%20Drains)/RTI%20Manuals/Ch%20Engineer_SWD_RTI_E01.pdf
- Comptroller and Auditor General of India (2014). Audit Report (Local Bodies) for the year ended March 2013, Government of Maharashtra, Report No. 6 of 2014, Chapter IV, para 4.1, Implementation of Brihanmumbai Storm Water Drain Project by MCGM. https://cag.gov.in/uploads/download_audit_report/2014/Maharashtra_Report_6_2014_Chap_4.pdf
- Comptroller and Auditor General of India (2006). Audit Report (Floods in Maharashtra) for the year ended 31 March 2006, Chapters I and VI. https://cag.gov.in/uploads/old_reports/state/Maharashtra/2006/Civil_Performance/civilper_chap_1.pdf ; https://cag.gov.in/uploads/old_reports/state/Maharashtra/2006/Civil_Performance/civilper_chap_6.pdf
- MMRDA (2023). S. Deshpande, Mithi River Development Project, presentation, 30 May 2023. https://mumbaifirst.org/wp-content/uploads/2023/04/Session-4_Shankar-Deshpande-MMRDA.pdf
- Free Press Journal (8 Jul 2026). BMC plans ₹10,000 crore flood mitigation project with IIT Bombay; (2026) Mogra pumping station work to begin on October 15 after 20-year wait. https://www.freepressjournal.in/mumbai/mumbai-bmc-plans-10000-crore-flood-mitigation-project-with-iit-bombay-to-seek-ndrf-funding ; https://www.freepressjournal.in/mumbai/mogra-pumping-station-work-to-begin-on-october-15-after-20-year-wait-to-ease-andheri-flooding
- SACON (2024). Report for NMMC on the holding ponds of Navi Mumbai (as summarised). https://www.sacon.in/wp-content/uploads/2024/04/2024-PR268-NMMC-Holding-Pond_GQ_04.03.2024.pdf
- NMMC (2026). Tender for providing and fixing FRP flap gates at Koparkhairane. https://www.publicservicesmap.in/tenders/98124-providing-and-fixing-frp-flap-gate-at-brid--maha-2026-nmmc-1299358-1
- Bombay High Court. Bombay Environmental Action Group v. State of Maharashtra, PIL No. 87 of 2006, judgment of 17 September 2018 (mangroves; as summarised). https://www.casemine.com/commentary/in/bombay-high-court-establishes-robust-legal-framework-for-mangrove-preservation-under-article-21/view
- Bombay High Court. Brihanmumbai Municipal Corporation v. Union of India, WP (L) No. 17795 of 2026, judgment of 17 September 2026 (leave under para 83(viii); Mumbai CZMP under the CRZ Notification, 2019). https://www.livelaw.in/pdf_upload/2026/09/17/brihanmumbai-municipal-corporation-vs-union-of-india-700815.pdf
- SANDRP (2019; 2020). Sangli and Narsoba Wadi painted red with record flood levels (10 Oct 2019); Maharashtra floods 2019: don't waste the crisis (26 May 2020); Maharashtra Upper Krishna basin flood 2019: Vadnere Committee 2 (6 Jun 2020). https://sandrp.in/2019/10/10/sangli-and-narsoba-wadi-painted-red-with-record-flood-levels/ ; https://sandrp.in/2020/05/26/maharashtra-floods-2019-dont-waste-the-crisis ; https://sandrp.in/2020/06/06/maharashtra-upper-krishna-basin-flood-2019-vadnere-committee-2-a-report-with-difference/
- Udayavani (2020). Panel gives clean chit to Karnataka over 2019 floods in Kolhapur, Sangli. https://www.udayavani.com/english-news/panel-gives-clean-chit-to-ktaka-over-2019-floods-in-kolhapur-sangli
- SANDRP (30 Aug 2024; 11 Aug 2026). Flood lines, riverfront development and citizen heroes: story of Pune floods; Corruption in flood lines regulation in Pune. https://sandrp.in/2024/08/30/flood-lines-riverfront-development-and-citizen-heroes-story-of-pune-floods/ ; https://sandrp.in/2026/08/11/corruption-in-flood-lines-regulation-in-pune/
- PTI, via National Herald (22 Aug 2019). Maharashtra floods: activist casts doubt over redefining of Kolhapur flood lines. https://www.nationalheraldindia.com/national/maharashtra-floods-activist-casts-doubt-over-redefining-of-kolhapur-flood-lines
- Al Jazeera (30 Jul 2021). Maharashtra deadly floods: Chiplun, Konkan region; NewsClick (2021). Experts suggest ways to prevent floods in Konkan, Kolhapur. https://www.aljazeera.com/news/2021/7/30/maharashtra-deadly-floods-chiplun-konkan-region ; https://www.newsclick.in/Experts-Suggest-Ways-Prevent-Floods-Konkan-Kolhapur
- Hindustan Times (October 2018). Report on the CIDCO holding ponds at Uran and the opening of their sluice gates (via PressReader; as summarised).
- Molesworth, J.T. (1857). A Dictionary, Marathi and English, 2nd ed., Bombay (khājaṇ, p. 202), via DSAL. https://dsal.uchicago.edu/dictionaries/molesworth/
- Survey of India. Tidal Predictions: Geodetic and Research Branch. https://www.geographyandyou.com/survey-of-india/tidal-predictions-geodetic-and-research-branch-survey-of-india
- GLOSS. India national report (tide-gauge network and datums). https://gloss-sealevel.org/gloss/gloss/sites/gloss/files/publications/documents/india_ge9.pdf
- Adani Ports (2025). Tide Table 2025, Dahej (notes on NHO INP-12 coverage and data sources). https://www.adaniports.com/-/media/Project/Ports/PortsAndTerminals/Dahej-Port/Marine-Documents/Tide-Table-2025-Dahej.pdf
- INCOIS. Storm-surge and swell-surge warning services. https://incois.gov.in/
- INCOIS (2025). Technical Report ESSO-INCOIS-OMDA-TR-04(2025) (extreme sea-level components and projections, Mumbai). https://incois.gov.in/documents/Reports/TechnicalReports/TR_ESSO-INCOIS-OMDA-TR-04(2025)_20250725114934.pdf
- PSMSL. Station 43, Mumbai/Bombay (Apollo Bandar) (station page, annual RLR data and datum history); and relative sea-level trends table. https://psmsl.org/data/obtaining/stations/43.php ; https://psmsl.org/products/trends/trends.txt
- FHWA. HEC-22 Urban Drainage Design Manual (current edition), Table 7.3 (coincident frequencies).
- Purdue University JTRP (2023). Development of a Multiple Water Course Joint Probability Analysis Procedure for Indiana Watersheds, FHWA/IN/JTRP-2023/09. https://docs.lib.purdue.edu/jtrp/1820
- PUB Singapore (2025). Code of Practice on Surface Water Drainage, 7th ed., Addendum No. 3. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
Annexes and forms
| Annex / Form | Content |
|---|---|
| 5A | Tidal datums (MSL, MHWS, HAT vs CD and Survey of India datum), surge allowances and 1% still-water levels by coastal segment |
| 5B | Major drains, riverine outfall reaches, and river mouths subject to sand-bar closure; map |
| 5C | Worked example: outfall-closed check for a Mumbai creek-side site |
| Form 5-1 | Downstream and Tailwater Report |
| Form 5-2 | Simplified Downstream Statement (small sites) |
Commentary. Maharashtra's drains fail in two places that site design does not see. At the outfall, the sea shuts them: in Mumbai, 180 of the 186 storm-water outfalls lie below high-tide level (Fact Finding Committee, 2006), and on 26 July 2005 the high tide peaked at 4.48 m at 15:30, inside the most intense hours of the storm. Downstream, the rivers rise on dam releases and backwater: in August 2019 releases from the dams of the upper Krishna basin came together from 5 to 7 August and Kolhapur and Sangli were in flood for nearly three weeks (SANDRP, 2020), Chiplun on the Vashishti was more than half submerged on 22 July 2021 (press reports), and in Pune the Mutha crossed its blue flood line on 25 July 2024 with Khadakwasla releasing 35,574 cusec, against the 60,000 cusec for which the line is drawn (SANDRP, 2024). A detention basin that meets every release rate in Chapter 4 still fails if the drain below it is already full, or if its outfall is shut. This chapter makes both failure modes part of the design.