Chapter 5Downstream and Tailwater Analysis
5.1 Purpose and scope
5.1.1 This chapter sets two checks that every regulated development and every public drainage project must pass.
- The downstream analysis (Clauses 5.3 to 5.5) confirms that the project does not make flooding worse below its outfall.
- The tailwater analysis (Clauses 5.6 to 5.13) sets the water level the system discharges into, including tide, storm surge, sea-level rise, river backwater and sand-bar closure. It also requires the system to cope when its outfall is closed.
5.1.2 This chapter applies to:
- (a) every site to which Chapter 4 applies;
- (b) every minor- and major-system drainage project under Chapter 6; and
- (c) every regional detention or tank restoration project under Clause 4.13 and Chapter 7.
5.1.3 Rainfall and joint-occurrence inputs come from Chapter 2, in particular Clauses 2.5.3 and 2.12. Hydrologic methods come from Chapter 3. Site release criteria come from Chapter 4. Hydraulic design of gates, culverts and pumps follows Chapter 9.
5.1.4 No tidal outfalls in Rajasthan. Rajasthan is landlocked: it has no coast, no tide and no Coastal Regulation Zone. No outfall in the State discharges to the sea, a tidal creek or an estuary, so the provisions of this chapter that depend on tide, storm surge, sea-level rise or a river mouth do not apply in Rajasthan: Clause 5.7 and Annex 5A, cases J1 to J3 of Table 5.2, the tidal lock windows of Clause 5.10.3, the seawater requirement of Clause 5.11.3(a) (gates and seats shall still be of corrosion-resistant materials), and Clause 5.13. They are kept so that the clause numbers of this Manual match its other State editions. In Rajasthan the receiving water is one of three kinds: none at all, where a site or the catchment it drains to has no defined outfall and ends in a closed depression, as in much of the inland drainage of the west and north (Clause 4.12.7); a lake, sagar or talab, often held at its full level by gates or an escape channel; or a river, reached directly, through a gate in a bank or ghat wall or through a pumping station, whose level is often set by the releases of the dams upstream, together with the drains and canals of WRD and the nalas of a Municipal Corporation, Council or Board, a development authority, an Urban Improvement Trust or RIICO that lead to it, and:
- (a) its tailwater is set by Clauses 5.6 and 5.8, including Clause 5.8.5;
- (b) where Clauses 5.10 to 5.12, Form 5-1 or Chapter 6 refer to the J1 tailwater or the J1 tidal curve, the minor-system tailwater of Clause 5.6.2 or 5.8.5 applies, as a time series where the receiving level varies; where they refer to the J2 tailwater or to HAT + surge + SLA, the major-system tailwater applies: the design-AEP river level of Clause 5.8.4(b), or the major-system tailwater of Clause 5.8.5, whichever is higher at the outfall;
- (c) the outfall-closed check of Clause 5.10 applies where an outfall is closed by a lake, a river or a receiving drain, with the river lock of Clause 5.8.5(b) and the lake closure of Clause 5.8.5(c) in place of the tidal lock windows; and
- (d) where there is no defined outfall, Clause 4.12.7 and Clause 5.8.5(a) apply: the outfall is treated as closed for the whole storm and after it (Clause 5.9.4), and the downstream analysis ends at the storage or at the closed depression that receives it.
5.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Analysis point | A location on the downstream system where pre- and post-project conditions are compared (Clause 5.3.3). |
| Contributing catchment | The whole area draining to an analysis point, on and off site. |
| Major drain | A channel listed as a major drain in the basin plan or Annex 5B, or any river, WRD canal, the Dravyavati (the former Amanishah nala) of Jaipur and the Dhund to which it discharges, the Naharika, Ambabari, Ganda, Jawahar, Brahmapuri and Nagtalai nalas and the other nalas of Jaipur, the Jojari and the Bandi and the Bhairav, RTO and other nalas of Jodhpur that drain to the Jojari, the Ayad (Ahar) at Udaipur, the escape channel of Ana Sagar at Ajmer, the nalas of Kota that drain to the Chambal, any drain or canal of WRD, including the Indira Gandhi Canal (IGNP) and its distributaries and escapes, any drain maintained by a Municipal Corporation, a Municipal Council, a Municipal Board, a development authority, an Urban Improvement Trust or RIICO with an internal width of 1.0 m or more, any irrigation canal that receives storm water, or a tidal creek. |
| Chart datum (CD) | The datum of the published tide tables and nautical charts, to which tidal heights are referred. |
| Mean sea level (MSL) | Average sea level over a long period at a tide gauge. |
| MHWS | Mean high water springs: the average of high waters at spring tides. |
| HAT | Highest astronomical tide: the highest level predicted under average meteorological conditions over a full tidal cycle (18.6 years). |
| Storm surge | The rise in sea level above the astronomical tide caused by wind and low pressure, mainly during cyclones. |
| Still-water level | Astronomical tide plus surge, excluding individual waves. |
| Sea-level allowance (SLA) | The allowance added to present-day tidal levels for sea-level rise over the design life (Clause 5.7.4). |
| Tailwater | The water level at the downstream end of a drain, outlet or storage. |
| Tide-lock | The condition in which the tailwater is at or above the upstream water level, so a gravity outfall cannot discharge. |
| Lock window | A period during which the outfall-closed check of Clause 5.10 sets gravity discharge to zero. |
| Sand bar | A bar of beach sand that partly or fully closes a river mouth or creek inlet. |
| Project datum | The levelling datum used on the project drawings. It must be tied to a Survey of India benchmark (Clause 5.7.2). |
5.3 Extent of the downstream analysis
5.3.1 The downstream analysis shall start at each site or project outfall. It shall continue downstream to the first of:
- (a) the point at which the project area is 10% or less of the contributing catchment;
- (b) the next tank, talab or other waterbody with a surplus weir or controlled outlet; or
- (c) the next major drain, or the sea.
The end point itself shall be analysed (Figure 5.1).
5.3.2 Where the analysis ends at a tank or talab under 5.3.1(b), it shall report:
- the change in the tank's maximum water level; and
- the change in surplus-weir discharge, for the AEPs and durations of Clause 5.4.3.
If the maximum water level rises, the analysis shall continue below the surplus weir to the next end point.
5.3.3 Analysis points shall be set at least at:
- (a) each site outfall;
- (b) each confluence with a drain or channel whose contributing catchment is at least half that of the receiving drain at that point;
- (c) each culvert, bridge or road crossing;
- (d) each location recorded as flood-prone by the local body, JMC, RSDMA or WRD; and
- (e) each building or road segment lying within the 1% AEP flood extent along the route. Representative points may be used where buildings are closely spaced.
5.3.4 Small sites. For sites of less than 0.5 ha, the Authority may accept a simplified downstream statement (Form 5-2) in place of the full analysis, where all of the following hold:
- the receiving public drain has documented capacity for its minor-system design flow (Chapter 6);
- no flood-prone location is recorded within 500 m downstream; and
- the site does not drain to a tidal or backwater-affected outfall.
Figure 5.1 — Extent of downstream analysis: analysis points A–D, the contributing area at each point, the 10% point, and the next talab or major drain as an alternative end point. Schematic; percentages are illustrative. Original drawing for this Manual, adapted from the ten-percent rule in the Georgia Stormwater Management Manual (2016, Vol. 2 §3.1.9) and KC APWA Section 5600 (2006, 5601.5).
Commentary. The 10% rule has established precedent. KC APWA 5600 (2006) required the downstream system to be analysed "to the point the development's land mass is less than 10% of the total watershed". The Georgia manual makes the ten-percent analysis a mandatory standard (GSMM 2016, Standard #8). The tank or major-drain end point has no direct precedent; this Manual adds it for Rajasthan. In Jaipur, where the Dravyavati (the former Amanishah nala) collects the nalas of the walled city, Sanganer and the newer colonies along about 47.5 km before it discharges to the Dhund (JDA, Dravyavati EIA), in Udaipur, where the lakes form a chain from Pichola and Fateh Sagar through the Ayad (Ahar) to Udai Sagar (as reported), and in Jodhpur, where the city's nalas run south and south-east to the Jojari, a tributary of the Luni (NIH, 2025), the 10% point can lie many kilometres downstream, across several tanks. A tank with a working surplus weir changes the hydrograph completely, so the analysis is better ended there and the tank level reported. Clause 5.3.2 prevents that end point from hiding a rise in the tank level. The small-site statement (5.3.4) and its 500 m distance have no direct precedent and are set by this Manual.
5.4 What the analysis must check
5.4.1 Scenarios. Each analysis shall compare:
- (a) Existing: the present downstream system and present land use of the whole contributing catchment, with the project site at its pre-project state; and
- (b) With project: the same, with the project and all its controls (Chapter 4) in place.
Where the Authority's basin plan defines future land use, the Authority may also require:
- (c) Future: the catchment fully developed under the plan, all to Chapter 4 standards, with and without the project.
5.4.2 Quantities to be checked at every analysis point:
- (a) Capacity: peak flow against the capacity of every channel, pipe, culvert and crossing, for the minor-system AEP of that element (Chapter 6) and for 1% AEP;
- (b) Flood levels: 1% AEP maximum water level at buildings (at the lowest opening) and on roads (at the crown and at the deepest point);
- (c) Velocities: peak velocity for 50%, 10% and 1% AEP;
- (d) Timing of combined peaks: the hydrograph at each confluence, showing the time to peak of the project outflow and of the receiving drain; and
- (e) Duration of inundation: on roads and at buildings, the time above the Chapter 6 depth limits.
5.4.3 Storms. The analysis shall use:
- 50%, 10% and 1% AEP;
- the duration set of Clause 2.5.2, at least the durations that give the highest level at each analysis point (these will usually be longer than at the site); and
- the 24-, 48- and 72-hour storms in every case.
The AMC rule of Clause 2.11.4 applies. Areal reduction follows Clause 2.7, applied to the contributing catchment at each analysis point and never to the site storage.
5.4.4 Method. The analysis shall:
- use a hydrograph method that combines hydrographs at confluences (SWMM, HEC-HMS, or an equivalent);
- include a hydraulic model with backwater (SWMM dynamic wave, HEC-RAS, or equivalent) wherever tailwater or backwater affects any analysis point; and
- not use the Rational Method at any analysis point, because it cannot represent timing.
Off-site areas shall be modelled at their present land use. Upstream detention shall be included only where it is built, maintained and documented.
5.4.5 Tailwater. The downstream end of the model shall use the tailwater of Clauses 5.6 to 5.9 and the sand-bar condition of Clause 5.13 where applicable.
Commentary. Clause 5.4.2(d) exists because detention changes when the site's water arrives, not only how much arrives (Clause 4.16). A Colorado State University thesis and a Water (2016) optimisation study both found that delayed site releases can coincide with the main-stem peak and raise it. Georgia's manual states the result directly: some structural practices "fail to reduce discharge peaks to pre-development levels downstream" because of "peak flow timing and runoff volume effects" (GSMM 2016). The duration-of-inundation check (5.4.2(e)) matters in the lake- and river-controlled cities of Rajasthan and in its closed depressions: in September 2019 the Kota Barrage was reported releasing about 6.5 to 6.9 lakh cusec through 18 or all 19 of its gates, and low-lying Nayapura, Balita and Gavndi in Kota were evacuated (as reported); in July 2025 Ana Sagar was reported at 15 ft 11 in on its gauge against a full level of 13 ft, its escape gates were opened and JLN Hospital and the Chaupati in Ajmer were flooded (as reported); and after the Barmer storm of August 2006 Kawas was reported still under 3 to 4 ft of water seven months later, because the low ground it stands in has no outfall (as reported). Detention that prolongs releases can lengthen that time even when it lowers the peak.
5.5 Acceptance criteria
5.5.1 The project is acceptable if, at every analysis point and for every AEP and duration of Clause 5.4.3, comparing "with project" to "existing":
- (a) the 1% AEP maximum water level does not rise by more than 10 mm at any habitable building, at any building's lowest opening, or on any road carriageway;
- (b) no building that is not flooded in the existing case is flooded with the project, and no building or road that meets the Chapter 6 freeboard or depth limits in the existing case fails them;
- (c) peak flow does not exceed the existing peak at the minor-system AEP of each element, or at 1% AEP;
- (d) peak velocity in lined channels stays within the permissible velocity for the lining (Chapter 6: 3.0 m/s maximum); and
- (e) in unlined or natural channels, peak velocity for 50% and 10% AEP does not increase by more than 10%, unless protection is provided under Chapter 9.
5.5.2 The duration of inundation under 5.4.2(e) shall be reported. The Authority may refuse a project that increases the duration of road closure on an arterial or emergency route.
5.5.3 Where the criteria are not met, the project shall do one or more of the following:
- (a) reduce release rates or increase storage (Chapter 4);
- (b) build downstream improvements, with the consent of the owner of the downstream system. These shall not transfer the problem further downstream, and shall be re-analysed under this chapter;
- (c) contribute to a regional facility under Clause 4.13; or
- (d) under Clause 5.5.4, change the release strategy.
5.5.4 Timing exception. Where the analysis shows that detention raises downstream levels because of timing, the Authority may vary the site release-rate criteria of Clause 4.5. This applies only where the site discharges within the lower tenth of the contributing catchment, directly to a major drain, tidal creek or the sea, and only on the following conditions:
- (a) the varied strategy meets 5.5.1;
- (b) the retention requirement (Clause 4.4) and WQv treatment (Chapter 8) are met in full; and
- (c) the outfall-closed check (Clause 5.10) is met.
Commentary. The 10 mm tolerance (5.5.1(a)) has no direct precedent. It is meant to be at or below the numerical precision of a typical one-dimensional model, so that "no increase" can be tested without arguing over rounding. The 10% velocity tolerance is likewise set by this Manual. The timing exception in 5.5.4 follows the Georgia manual, where the downstream analysis can show "that peak controls are not needed" and allow them to be waived (GSMM 2016, Standard #8). It is limited here to sites low in the catchment, which is where synchronisation with the main-stem peak is most likely (Water 2016, 8(7):290). It is not available above that, because the evidence on scale (Clause 4.16) shows that early release from many upstream sites raises peaks.
5.6 Tailwater: general and non-tidal outfalls
5.6.1 Every drain, outlet and storage shall be designed against a stated tailwater. A free outfall shall be assumed only where the outlet invert is above the maximum receiving water level for the case being checked.
5.6.2 Minor-system tailwater, non-tidal. The tailwater is the receiving system's water level at the time of the minor-system peak, from the downstream model. Where no model exists, use:
- for a receiving pipe, its obvert; or
- for a receiving open drain, its full-bank level less freeboard (Chapter 6).
5.6.3 Major-system tailwater, non-tidal. The tailwater is the receiving system's 1% AEP water level, unless Clause 5.8 allows a coincident lower level.
5.6.4 Tidal and backwater outfalls. Clauses 5.7 to 5.13 apply in addition.
5.6.5 Storage elements. Detention, tanks and pumped sumps shall be routed with a time-varying tailwater (Clause 4.6.6), not a constant level, wherever the tailwater varies with tide or with the receiving system's hydrograph.
5.7 Tidal tailwater: datums, surge and sea-level allowance
5.7.1 Design tailwater levels. For outfalls to the sea, tidal creeks, estuaries, backwaters and tidal reaches of rivers and canals:
Table 5.1 — Design tailwater levels for tidal outfalls
| Design case | Tailwater |
|---|---|
| Minor-system design (Chapter 6) | MHWS + SLA |
| Major-system design and storage design | HAT + surge + SLA, with the surge term defined in Clause 5.7.3 |
| Joint case (Clause 2.12(b)) | 1% AEP still-water level + SLA |
The SLA is +0.3 m minimum (Clause 5.7.4). The cases to be run are listed in Clause 5.9.
5.7.2 Sources and datums.
- (a) Tidal levels. MHWS, HAT and MSL shall be taken from the current edition of the Indian tide tables published by the National Hydrographic Office (NHO) or by the Survey of India, for the nearest standard or secondary port, or from the port authority's published tidal levels. The edition and port shall be stated.
- (b) Datum conversion. Tide-table heights are referred to chart datum. They shall be converted to the project datum through a documented connection between chart datum, the tide gauge zero and a Survey of India benchmark. The offset and its source shall be stated on Form 5-1.
- (c) Estuaries, creeks and canals. For outfalls inside estuaries, creeks, backwaters or tidal canals (for example the estuaries of the coastal States; there is none in Rajasthan, Clause 5.1.4), tidal levels may differ from the open coast. Open-coast levels shall be used unless measured levels over at least one spring–neap cycle, or a calibrated hydrodynamic model, justify a different value. No reduction below open-coast levels shall be taken without such evidence.
- (d) Interim. Until Annex 5A is published, the designer shall obtain the values directly from the sources in (a) and record them.
5.7.3 Storm surge.
- (a) Major-system and storage design. The surge term in "HAT + surge" is the 10% AEP (10-yr) storm surge for the coastal segment, given in Annex 5A. The 1% AEP surge is used only in the joint case of Clause 2.12(b), with the 10-yr 48-hour storm. That keeps the two cases symmetric, so that a rare rainfall is never paired with a rare surge.
- (b) Joint case. The 1% AEP still-water level for Clause 2.12(b) is taken from Annex 5A.
- (c) Until Annex 5A is published, both values shall be taken from a site-specific study using INCOIS, IMD or NCCR surge hindcasts or return-level analyses. The study shall state its source, method and record length.
- (d) Wave set-up shall be added where the outfall faces the open sea without a protected entrance.
5.7.4 Sea-level allowance. The SLA shall be:
- (a) +0.3 m minimum for every element;
- (b) greater than 0.3 m where the State, JDA or the Authority adopts a higher projection for the planning area; and
- (c) assessed for the design life of the element. For elements with a design life of more than 50 years, the designer shall report the effect of a sea-level rise of twice the SLA as a sensitivity run.
Figure 5.2 — Tidal outfall: flap gate, property non-return valve, and the design tailwater levels (MHWS + 0.3 m for the minor system; HAT + surge + 0.3 m for the major system), with a seasonal sand bar at the mouth. Schematic, not to scale. Original drawing for this Manual, adapted from the tidal tailwater table in MoHUA/CPHEEO Manual on Storm Water Drainage Systems (2019), Part A, Table 6.2.
Commentary. CPHEEO (2019) Table 6.2 sets the design tailwater for coastal outfalls as:
- MHWN to MHWS for a minor storm (more frequent than 1 in 5 years);
- MHWS to HAT for a major storm; and
- "Effect of climate change: additional 0.3 m".
CPHEEO also says the joint probability of storm, tide and surge "should" be considered, with the state maritime board consulted. This Manual takes the upper end of each CPHEEO range, adds surge for the major system, and makes the joint case explicit (Clause 2.12). CPHEEO does not require surge to be added; this Manual adds it because the surge records of the coastal States showed why it is needed there; Rajasthan has no coast, and the surge term does not arise in the State.
Indian tide tables have been published by the Survey of India since the nineteenth century (Survey of India, Tidal Predictions). Current Indian tidal predictions also appear in the NHO's tide tables. One port document describes the current edition as covering 95 Indian ports, based on NHO observations and on data from civil ports, NIO and INCOIS (Adani Ports, Dahej tide table 2025, citing NHO INP-12). INCOIS runs coastal tide gauges and issues storm-surge and swell-surge warnings. None of these is used for design in Rajasthan, which has no coast, and Annex 5A is not prepared for the State (Clause 5.1.4).
5.8 Riverine backwater
5.8.1 Where it applies. Outfalls to rivers and canals whose water level in a storm can exceed the outfall invert shall be designed with riverine backwater. This includes:
- the Chambal at Kota below the Gandhi Sagar, Rana Pratap Sagar and Jawahar Sagar dams and the Kota Barrage, and the nalas of the city that end in it (Clauses 5.8.3 and 5.8.5(b) and (d));
- the Chambal at Dholpur (Clause 5.8.5(b) and (d));
- the Banas at Tonk below the Bisalpur dam, the Luni at Balotra, the West Banas at Abu Road and the Gambhiri at Chittorgarh (Clause 5.8.5(b));
- the Dravyavati (the former Amanishah nala) of Jaipur and the Dhund below it, the Jojari and the Bandi at Jodhpur, the Ayad (Ahar) at Udaipur, and the Ghaggar at Hanumangarh and Sri Ganganagar, for which no gauge level was found (Clause 5.8.5(b));
- Pichola, Swaroop Sagar, Fateh Sagar and Udai Sagar at Udaipur, Ana Sagar and its escape channel at Ajmer, Kailana and Takhat Sagar at Jodhpur, Man Sagar (Jal Mahal) at Jaipur, and the pond of the Kota Barrage, with every nala that ends in them (Clause 5.8.5(c));
- any drain or canal of WRD, the Indira Gandhi Canal (IGNP) and its distributaries and escapes, and any irrigation or lift canal that receives storm water (Clause 5.8.5(f)); and
- elsewhere: any river or WRD channel listed in Annex 5B.
5.8.2 River levels. River water levels shall be taken from:
- (a) WRD design flood levels or recorded highest flood levels for the reach, where published; or
- (b) a hydraulic model (HEC-RAS or equivalent) of the river reach. The model shall use:
- the river design flood from a hydrograph method (Chapter 3), with continuous simulation where Chapter 3 requires it;
- the tidal boundary of Clause 5.7 at the mouth; and
- the sand-bar condition of Clause 5.13.
5.8.3 Reservoir and tank releases. Where a reservoir or tank upstream can release to the river (for example the Gandhi Sagar, Rana Pratap Sagar and Jawahar Sagar dams and the Kota Barrage on the Chambal above Kota and Dholpur, the Bisalpur dam on the Banas above Tonk, the Panchana dam in Karauli, the escape gates of Ana Sagar at Ajmer, and the gated links between the lakes of Udaipur), the river level shall include the release given by the reservoir's operating rule for the storm being checked. Where there is no published rule, it shall include the largest recorded release.
5.8.4 Coincidence of site storm and river flood. Unless a joint-probability study is accepted by the Authority, the more severe of the following governs:
- (a) the site design storm (AEP as required), with the river at its 10% AEP (10-yr) level; and
- (b) the site 10% AEP storm, with the river at its design-AEP level (1% AEP for the major system).
The two storms in each pair shall have the same duration and timing where they are generated by the same rainfall event.
5.8.5 Catchments with no outfall, river-locked outfalls, lake outfalls and escape gates, rivers driven by dam releases, the Chambal at Kota and Dholpur, and discharges to WRD channels and canals.
- (a) Catchments with no outfall. Where a site, or the catchment it drains to, has no defined outfall (Clause 4.12.7), as in the interdunal depressions and the town sites of the Thar, Shekhawati and the canal command, and in the Sambhar basin:
- there is no receiving water and no tailwater. The outfall is treated as closed for the whole storm and after it (Clause 5.9.4): the storage shall hold the 72-hour design volume of Clause 4.12.7(a) below the level of its overflow, and shall be emptied only by infiltration, evaporation or reuse within the time of Clause 4.12.7(c), with no gravity or pumped discharge credited to a drain, nala or road;
- where the site drains to a public basin or to a closed depression that also receives other land, the downstream analysis of Clauses 5.3 to 5.5 shall end at that basin or depression, and shall report its maximum water level in the 1% AEP 72-hour storm, with the whole area that drains to it at its present land use, with and without the project; Clause 5.5.1 applies at every building, road and plot around it. The basin or depression shall start the storm at the level that the 10% AEP 72-hour storm leaves in it 7 days after that storm ends, or higher where its flood marks or the records of the local body or the Collector show it (set by this Manual);
- the overflow path of Clause 4.12.7(d) shall be traced to where it ends, with its depth and velocity on every road and plot it crosses, within the limits of Table 6.3; it shall not end on a neighbour's land or in another catchment (Clause 4.12.7(e)), and a pump or a pipe that moves the water onto a road, a neighbour's land or another catchment is not an outfall; and
- where the depression is a lake or a wetland, such as Sambhar Lake (a Ramsar site), item (c) also applies, and no storm water shall be discharged to it without the consents of that item.
- (b) River-locked outfalls. For an outfall to a river directly, through a gate in a bank, ghat wall or embankment or through a pumping station, or into a drain that itself discharges in one of those ways, the designer shall identify the body that operates each gate and pumping station, and obtain the sill of each gate, the crest of the bank or wall, the installed pumping capacity and the operating levels, including the river level at which each gate is closed. Every level shall state its datum and its connection to the gauge datum of the nearest CWC or WRD gauge.
- Design river level. The river level of Clause 5.8.2 at the outfall shall be, for the major-system cases (Clause 5.8.4(b)), the 1% AEP river level at the outfall: the 100-year level of a flood-frequency study or floodplain delineation that gives a level at the outfall, or a level from a hydraulic model under Clause 5.8.2(b), with the dam releases of item (d). The level shall in no case be less than the highest recorded level at the nearest CWC or WRD gauge on the same river, transferred to the outfall. The highest levels found during research (Table 5B.1), from the CWC bulletins of September 2019 and a 2022 copy of the CWC site list, none read in a CWC site sheet [TBC], are: the Chambal at Kota City 248.68 m (16 September 2019) and at Dholpur 145.54 m (23 August 1996; another value, 142.55 m, is not supported by the CWC bulletins read), the Banas at Tonk 262.05 m (9 September 1973), the Luni at Balotra 108.755 m (18 July 1979), the West Banas at Abu Road 265.4 m (31 August 1973) and the Gambhiri at Chittorgarh 409.24 m (24 July 1992). Where a later flood has exceeded the listed level, the later level governs. The recorded level shall be transferred along the river with the water-surface slope of the flood that set it, from the CWC and WRD gauge records, or from the model. Until either is available, the recorded level of the nearest gauge upstream applies unchanged at the outfall, except that where the outfall lies between two gauges on the same river, with no tributary joining between them, the level may be interpolated linearly by river distance between the highest recorded levels of the two gauges (set by this Manual). The Kota City gauge applies to the Chambal below the Kota Barrage; an outfall to the pond above the barrage takes the pond level of item (c), and the position of the gauge relative to each outfall is to be confirmed with CWC [TBC]. No danger level or highest flood level was found for the Dravyavati, the Jojari or the Bandi, the Ayad at Udaipur, the Ghaggar at Hanumangarh and Sri Ganganagar, or any river in the State's closed basins [TBC]. The Dravyavati was designed to pass the 100-year flood, but neither its design discharge nor its design water levels were found (JDA, Dravyavati EIA) [TBC]. On such a reach, and for an outfall upstream of every gauge on its reach, the river level shall be the higher of the level from a model under Clause 5.8.2(b), or JDA's design water-surface profile of the 100-year flood where JDA provides it for the Dravyavati, and the highest flood level surveyed at the outfall from flood marks and from the records of the local body, WRD or the Collector, with its source stated; an outfall shall not be designed on such a reach without one of them (set by this Manual). For the cases with the river at its 10% AEP level (Clause 5.8.4(a)), the level shall be taken from the same model or a frequency analysis of the gauge record, and not less than the danger level at the nearest gauge, transferred in the same way: 242 m at Kota City (240 m in the CWC bulletin of 2019; 242 m from 2022), 130.79 m at Dholpur (129.79 m in 2019), 262.8 m at Tonk, 259 m at Abu Road and 407.9 m at Chittorgarh (all set by this Manual, from CWC [TBC]). Where the danger level is higher than the highest recorded level, as at Tonk, the design river level of this item shall be not less than the danger level (set by this Manual). Where no danger level has been found, as at Balotra, the 10% AEP case shall use the design river level of this item until a frequency analysis is accepted (set by this Manual). The datum of every level is to be confirmed for each gauge [TBC].
- Tailwater. The tailwater at the outfall shall be the higher of that river level beyond the gate, bank or wall, and the maximum level in the drain behind it, computed by routing the drain as a closed storage for as long as the river stands above the level behind it, with the inflow of the whole catchment that drains to it, its storage as surveyed in its present condition, net of silt, sand, encroachment and vegetation, and an outflow of no more than the pumping capacity that the operator confirms in writing is available in a storm, and in no case more than the installed capacity of the permanent pumps less the largest pump (set by this Manual), with gravity discharge through the gate only while the river is lower than the level behind it. Pumps shall deliver against the design river level of this item, and every pump, panel and control shall remain operable with the river at that level (Clause 5.12.5).
- River lock. Portable dewatering pumps brought in for an event, and capacity that has been sanctioned or proposed but not commissioned, shall not be counted. The outfall-closed check of Clause 5.10 applies with a single lock that lasts for as long as the river stays above the outfall invert, or above the level at which its gate is closed if that is lower, taken from the river model or from the stage record of the nearest CWC or WRD gauge in the flood that set the highest recorded level (2019 at Kota City; 1996 at Dholpur; 1973 at Tonk and Abu Road; 1979 at Balotra; 1992 at Chittorgarh) or in a comparable flood, with the dam releases of item (d), and not less than 72 hours, covering the whole of the 48- and 72-hour storms of Clause 5.10.2, so that storage and pumping handle the full storm volume (Clause 5.9.4) and the drawdown of Clause 5.10.5 is met by pumping until the lock ends (set by this Manual). A shorter lock may be used only where the outfall invert is above the 1% AEP river level of this item, or where a gauge analysis under Clause 5.10.6, including the releases of the dams above, shows it and the Authority approves it. Floor levels and pumped outfalls behind a gate, bank, ghat wall or embankment shall also be checked for the failure of the gate and for a breach of the bank or wall, with the land and drains behind it filled to the river level beyond it.
- (c) Lake outfalls and escape gates. For an outfall to a lake, sagar or talab, directly or through a nala that ends in it, such as Pichola, Swaroop Sagar, Fateh Sagar and Udai Sagar at Udaipur, Ana Sagar at Ajmer, Kailana and Takhat Sagar at Jodhpur, Man Sagar (Jal Mahal) at Jaipur, and the pond of the Kota Barrage:
- Consent. Storm water shall not be discharged to a lake without the written consent of its custodian, the body that holds and operates it: WRD for its reservoirs and the Kota Barrage, the Municipality for a tank vested in it under s.68 of the Rajasthan Municipalities Act 2009, or another custodian the State names (the custodian of each Udaipur lake, of Ana Sagar and its escape gates, and of Kailana and Takhat Sagar was not confirmed during research [TBC]). Where the lake is a lake under the Rajasthan Lakes (Protection and Development) Authority Act 2015, any permission that the Lakes Development Authority requires within the lake's boundaries or protected area shall also be obtained; where it is a Ramsar site (Sambhar, Keoladeo, Menar or Khichan) or a notified wetland, any permission that the State Wetland Authority requires shall be obtained, and the interim directions of the High Court on wetlands and their catchments (order of 1 June 2026) apply (Chapter 7). Kailana and Takhat Sagar are fed by the Rajiv Gandhi Lift Canal (NIH, 2025), and an outfall to either needs the custodian's written consent to the quality of the water as well as its volume. An outfall that carries dry-weather flow is dealt with under Clause 8.9.
- Design lake level. The tailwater for the major-system and storage cases shall be the lake's maximum water level (MWL) as WRD or the custodian publishes it, or, where only the full tank level (FTL) is published, FTL plus the surcharge in the lake's design flood, computed from the rating of its spillway, weir, escape channel and gates with the gates operated only as the custodian's written rule provides. Where neither the MWL nor the surcharge has been published, the tailwater is FTL + 0.5 m (set by this Manual) [TBC]. In every case it shall be not less than the highest level recorded at the lake (set by this Manual). The minor-system tailwater is the FTL, or the level at which the custodian's rule opens the gates if that is higher. The project's discharge shall be included in the lake level (Clauses 5.3.2 and 5.12.3).
- Levels known only as gauge readings. The full levels of the Udaipur lakes and of Ana Sagar are known only as readings on each lake's own gauge, in feet above a gauge zero whose level was not found: Pichola 11 ft, Fateh Sagar 13 ft (14 ft in another report), Udai Sagar 24 ft and Ana Sagar 13 ft, with readings of up to 15 ft 11 in reported at Ana Sagar before its escape gates were opened in July 2025 (as reported). Their FTL in metres is therefore [TBC]. For an outfall to such a lake, the designer shall tie the gauge zero to the project datum and a Survey of India benchmark by levelling, with the custodian's confirmation of the full gauge reading and of the highest reading on record, and state the tie on Form 5-1; no outfall to such a lake shall be designed without that tie (set by this Manual). Where two full readings are reported, the higher applies until the custodian confirms the level (Fateh Sagar 14 ft). At Ana Sagar the highest reading on record (15 ft 11 in, as reported) is above FTL + 0.5 m, so it governs until a surcharge is published.
- Levels published in metres. Kailana has an FRL of 273.7 m and Takhat Sagar of 269.75 m above MSL (NIH, 2025), so their lake tailwater is 274.2 m and 270.25 m where no MWL is published. The Kota Barrage pond has an FRL of 260.3 m and an MWL of 260.9 m or 261.2 m in two CWC listings; 261.2 m applies until WRD confirms it [TBC]. No FTL was found for Man Sagar, Swaroop Sagar or Ramgarh [TBC].
- The Udaipur chain. Each lake of the chain shall be routed with the outflow of the lakes above it in the same storm: Bada Madar to Fateh Sagar, Pichola and Fateh Sagar to the Ayad, and the Ayad to Udai Sagar, with the gate between Pichola and Fateh Sagar closed once Fateh Sagar reaches 11 ft on its gauge, as reported, unless the custodian's written rule says otherwise (set by this Manual).
- Closed outfall. Where the outfall invert is below the design lake level of this item, the outfall shall be treated as closed for the whole storm (Clause 5.9.4), with storage and pumping handling the full storm volume, unless the custodian's stage record shows the lake below the invert at the start of comparable storms and the Authority accepts it. The lake starts every design storm at FTL, or at its full gauge reading (Clause 7.7.3). No lowering of the lake before a storm and no early or additional gate opening shall be assumed unless the custodian's written operating rule and records show it.
- Below the gates. An outfall to the channel below a lake's gates, weir or escape, such as the escape channel of Ana Sagar, the Ayad below Pichola and Fateh Sagar, and the Chambal below the Kota Barrage, shall take the river or channel level of item (b) with the release of Clause 5.8.3 from the gates above it, at the largest gate opening on record as the custodian states it (as reported: the Ana Sagar escape gates opened 30 inches in July 2025; 18 or all 19 gates of the Kota Barrage in September 2019), coincident with the design storm on the city under item (d). Floor levels and pumped outfalls below a dam, gated lake or escape shall also be checked for the release that results from a gate failing open.
- (d) Rivers driven by dam releases. For an outfall to a river below a dam or a gated lake, such as the Chambal at Kota and Dholpur below the Gandhi Sagar, Rana Pratap Sagar and Jawahar Sagar dams and the Kota Barrage, the Banas at Tonk below the Bisalpur dam, and the escape channel of Ana Sagar:
- in addition to the cases of Clause 5.8.4, the site design storm (each AEP required) shall be run with the river at the level that results from the largest recorded release of the dams above, with the flow of the catchment below them as it occurred in the same event (set by this Manual), until WRD publishes an operating rule [TBC]. As reported, the Kota Barrage released between 4.42 lakh cusec (CWC, 14 September 2019) and 7.9 lakh cusec (about 22,400 m³/s) in September 2019; the higher value applies until WRD gives the record (set by this Manual). The largest recorded release of each dam shall be obtained from WRD and stated [TBC];
- the river level shall not be reduced on the ground that the flood comes from rain that falls outside the city or outside the State, or that the site storm is small, and the release shall be placed before, during and after the site storm;
- an outfall in Kota to the Chambal below the barrage shall take the level of item (b), not less than 248.68 m at the Kota City gauge transferred to the outfall, with the releases of all four dams included; and
- an outfall in Dholpur shall take the level of item (b), not less than 145.54 m at the Dholpur gauge transferred to the outfall.
- (e) WRD consent; the High Flood Line; court lines. No outfall structure, gate, pumping station or drain shall be built in the bed, bank or floodplain of a river, or of a reservoir or canal of WRD, without the consent of WRD; the procedure for that consent was not found during research [TBC].
- The State's High Flood Line. The Supreme Court has directed the State to determine and demarcate the High Flood Line and an ecological buffer zone for all the river systems in the State and, until that is done, to grant no fresh permissions facilitating industrial, commercial or residential development within the identified river corridors (In Re: 2 Million Lives at Risk, Contamination in Jojari River, Rajasthan, order of 7 August 2026). The designer shall state whether the outfall lies in an identified river corridor and whether the High Flood Line has been demarcated for the reach. Where it has, the design river level of item (b) shall be not less than the High Flood Line at the outfall, and the High Flood Line may be used as the 1% AEP level of item (b) only where the study that produced it gives its return period as 100 years or rarer; the return period is not stated in the order [TBC] (set by this Manual).
- Court lines. The designer shall also check the outfall against the lines that courts have set or are setting, as they stand at the time of design (Chapter 7): the 100 m from the edge of the Jojari, and 500 m for hazardous industries from its flood line or flow path (Supreme Court, interim order of 24 August 2026, as reported); the no-construction zone around the Udaipur lakes (notification of 17 January 1997; 200 m from the high flood level around Udai Sagar, as reported) and the High Court's directions of 2025 and 2026 on the Fateh Sagar catchment and the Udaipur lakes (as reported); the removal of structures from the Ana Sagar wetland (NGT, 2023; Supreme Court, 2023–2025, as reported); the catchment of the Ramgarh dam (Abdul Rahman, 2004; suo motu, 2011 and 2012; Supreme Court, 2017); and land recorded as gair mumkin nala, nadi or talab (Ramji Lal Saini, 2026). Whether a drain outfall is permitted within each line is to be confirmed with the authority concerned before design [TBC].
- (f) WRD channels, canals and canal escapes, and the nalas of other bodies. Storm water shall not be discharged to a drain or canal of WRD, to the Indira Gandhi Canal (IGNP), its distributaries, its escapes or another irrigation or lift canal, or to a drain of RIICO or another owner, without the written consent of WRD or the channel's owner. A supply canal or a lift canal is not a drainage outfall, and an IGNP escape is an outlet for canal water, not for storm water, unless WRD consents in writing (set by this Manual). Where consent is given:
- the discharge shall not exceed the rate the consent allows;
- the tailwater is the higher of the channel's design water level as WRD or the owner states it and its level in the coincident case of Clause 5.8.4, computed from all the storm water it receives, including the nalas of other bodies, and with its downstream boundary at the river or lake level of items (b) and (c); until a design water level is published for a channel, the computed level governs [TBC];
- the channel shall be taken in its present condition, net of silt, sand, encroachment and obstruction by crossing services, and a widening, lining, remodelling or diversion that has been proposed but not completed shall not be counted; and
- the outfall shall have a flap gate (Clause 5.11) where the design water level or the computed level is above the outfall invert.
No pump, gate, sluice or dam operation that helps drainage, such as pumping a drain down before a storm, lowering a lake before a storm, closing a gate late or opening dam gates early, shall be assumed unless the operator's written records show it. Where the outfall invert is below the tailwater of this clause, the outfall shall have its own flap gate (Clause 5.11) and, where the outfall-closed check requires it, pumping (Clause 5.12), with the pumped volume included in the routing of the drain, the lake or the river (Clause 5.12.3). Pumping shall not be used to move water out of a catchment with no outfall (item (a)).
Commentary. In large continental river basins, a site storm and a river flood are usually treated as roughly independent. That is the basis of tables of coincident frequencies such as FHWA HEC-22 Table 7.3. Rajasthan's rivers break that assumption, because a dam stores the first rain of a monsoon spell and spills when it is already full, at the time the same spell is falling on the city below, and because the State's largest storms are slow-moving monsoon systems that fall on the city and its river together. The Kota flood of September 2019 came from the releases of the Chambal dams after the same monsoon spell had filled them (SANDRP, 2019). The Jaipur storm of 19 July 1981, when 326.0 mm fell at Jaipur and 589.2 mm at Kanota in a day (IMD), raised the Banas at Baranwada to its highest recorded level, 202.865 m, on 20 July (CWC list, as copied by SANDRP). The highest level of the West Banas at Abu Road, 265.4 m, was set on 31 August 1973, in the storm that brought 635.0 mm to Pindwara on 1 September (IMD). The two cannot be treated as independent, and a local storm can fall before, during or after the release. Clause 5.8.4 therefore pairs a design event on one side with a 10-yr event on the other, in the same way as Clause 2.12(b). This pairing has no direct precedent. It is more severe than an independence assumption would give.
Clause 5.8.3 reflects the dams above the State's cities. The Chambal reaches Kota below a cascade of four dams: Gandhi Sagar in Madhya Pradesh (full reservoir level about 399.9 m, maximum water level 401 m), Rana Pratap Sagar (full reservoir level 352.8 m, maximum water level 354.18 m), Jawahar Sagar, and the Kota Barrage (full reservoir level 260.3 m; maximum water level 260.9 m in the CWC bulletin of 2019 and 261.2 m in a 2022 copy of the CWC list) (CWC; SANDRP, 2022); the barrage has 19 radial gates (as reported). In September 2019, with the Gandhi Sagar gates reported opened late (SANDRP, 2019) and 12 to 19 gates opened at the Kota Barrage on 13–14 September, the barrage was reported releasing about 4.42 lakh cusec on 14 September (CWC daily report, seen only as a search summary), and 6.5 lakh cusec through 18 gates, 6.93 lakh cusec through 19 gates or 7.9 lakh cusec in the days that followed (as reported); a government document seen only as an extract gives 7.2 lakh cusec and a revised design spillway discharge of 24,953 m³/s, and is not used [TBC]. The Chambal then runs on to Dholpur, where its highest recorded level, 145.54 m, was set on 23 August 1996 (CWC). On the Banas, the Bisalpur dam (full reservoir level 315.5 m, CWC) stands above Tonk. The Panchana dam (full reservoir level 258.62 m, as listed) releases towards Bharatpur, where its water is reported to reach Keoladeo through the Ajan bund. In the cities, Ana Sagar is held at its full gauge by four escape gates, and the lakes of Udaipur are joined by gated channels (as reported). No operating rule or release record for any of these dams or gates was obtained during research, and no CWC hourly stage record for any gauge in the State was obtained [TBC]. Until they are, the largest recorded release applies, with the flow of the catchment below the dam as it occurred in the same event (Clause 5.8.5(d)). The levels used in this Manual come from the CWC bulletins of 16 and 17 September 2019, read through archived copies, from search summaries of later bulletins and from a 2022 copy of the CWC site list (SANDRP); their datum and gauge zero are to be confirmed from CWC [TBC].
Clause 5.8.5 is set by this Manual. In Rajasthan the tailwater at a city outfall is set not by the tide but by a lake held at its full gauge by gates or an escape channel, by a river held high by the releases of the dams above it, or, over much of the west and north, by nothing at all, because the land has no outfall. No document found during research gives a design level for any of them. The Rajasthan Municipalities Act 2009 requires the drain of a building to empty into a municipal drain or a place set apart within fifty feet, or else into a cess-pool (s.202(2), as read from a third-party copy), but it does not say against which level. No State floodplain-zoning law or WRD order was found, and the only design return period published for a city channel is the Dravyavati's 100-year flood.
The first is the catchment with no outfall. About 60% of the State drains inland (as reported); much of Jaisalmer, Bikaner and Barmer has no defined drainage, the IGNP command near Bikaner is reported to have no natural drainage system at all, and the Sambhar salt lake is the end of a closed basin of about 5,500–5,700 km² (as reported). In such a catchment the governing failure is the volume of a multi-day storm, not a 1-hour peak: in August 2006 about 577 mm fell on Barmer in 3 days against an annual normal of about 277 mm, and the water stood at Kawas for months (as reported). Item (a) therefore applies the 72-hour design volume of Clause 4.12.7, treats the outfall as closed for the whole storm and after it, and makes the overflow path end on public land, because a site that drains to a closed depression either stores its water or puts it on someone else's land. The starting level of a shared basin or depression, the level left by a 10-year 72-hour storm a week earlier, is set by this Manual so that a depression already holding water from an earlier spell is not treated as empty; it is to be replaced by the depression's own flood marks and records.
The second is the lake. Several of the State's cities stand around lakes: Udaipur around Pichola, Fateh Sagar and Udai Sagar, Ajmer around Ana Sagar, Jodhpur with Kailana and Takhat Sagar, and Jaipur with Man Sagar (Jal Mahal). A lake at its full level does not fall for the rest of the monsoon; it passes its inflow over a weir or through its gates or escape, and its level rises above FTL by whatever head the flood needs. Ana Sagar is held at 13 ft on its gauge by opening its escape gates, but readings of 14 ft to 15 ft 11 in have been reported before they were opened (as reported), and Fateh Sagar has been reported held 20–25 cm above its design full level with sandbags (India Water Portal, 2010). Item (c) therefore takes the MWL, or FTL plus the design-flood surcharge, as the tailwater, and not less than the highest level recorded, and treats an outfall below it as closed for the whole storm, which is what Clause 5.9.4 already requires when the tailwater stays above the outfall. No MWL and no surcharge was found for any of the lakes, so FTL + 0.5 m is set as the interim value: it is the freeboard that this Manual uses for floor levels (Clause 6.11.1), and it is a floor, not an estimate of the surcharge, which depends on the gates and the flood [TBC]. The levels of the Udaipur lakes and of Ana Sagar raise a further problem: they are published, by custodians and the press alike, as gauge readings in feet above a gauge zero whose level was not found, so 13 ft on the Ana Sagar gauge cannot be compared with a drain invert in metres until the gauge zero is levelled to a benchmark. That is why item (c) requires a survey tie before any outfall to such a lake is designed. Only Kailana and Takhat Sagar have published full reservoir levels in metres above MSL (NIH, 2025). The custodian's consent is required because a storm drain added to a lake raises its level for every other outfall, and because the lakes also receive the cities' sewage: the High Court has directed that no untreated sewage reach the wetlands of the State or their catchments (order of 1 June 2026), which is the subject of Clause 8.9.
The third is the river below a dam. Outside the Chambal, most of the State's rivers are short-lived in flood: the Luni and its tributaries rise in flash floods in dry beds, such as the flood of July 1979 that set the highest level at Balotra (Dhir et al., 1982, as cited by Singh et al., 1992). On their own they would lock an outfall for hours, not days. But a dam spills only when it is full, and it goes on spilling while the inflow lasts and while its level is brought back to its full reservoir level. At Kota the barrage gates were opened from 13–14 September 2019, releases of 4.42 to 7.9 lakh cusec were reported over the following days, and the river at Kota City set its highest level on 16 September (CWC; as reported), so the river stood high for about three days at least. No hourly stage record for any gauge in the State was obtained during research [TBC]. The single lock of at least 72 hours therefore covers the whole of the longest design storm of Clause 2.5.2, so that the site does not rely on the river falling during the storm, which a dam release does not allow; it matches the 72-hour design volume of Clause 4.12.7, and it is to be lengthened from the gauge record of the flood that set the highest recorded level on each river. The CWC levels listed in item (b) come from the CWC bulletins of September 2019, read through archived copies, and from a 2022 copy of the CWC site list; their datum and gauge zero are to be confirmed [TBC]. The danger level is used as the floor of the 10% AEP level because the rivers have crossed it by wide margins in recent floods, by 6.68 m at Kota City in 2019 and 14.75 m at Dholpur in 1996 (CWC), so a level reached about once in ten years is unlikely to lie below it; it is to be replaced by a frequency analysis of the CWC record [TBC]. At Tonk the danger level (262.8 m) is above the highest recorded level (262.05 m, 1973), so item (b) takes the danger level as the floor of both cases rather than let the 1% AEP level fall below the 10% AEP level. Item (b) counts only the permanent pumps less the largest one, for the same reason that Clause 5.12.2(b) requires a standby pump.
The fourth is the coincidence of the release and the storm. Item (d) runs the design storm on the city with the river at the largest recorded release because the rain that fills a reservoir and the rain on the city come from the same monsoon spell (see the Commentary to Clause 5.8.4). The Chambal floods at Kota are driven by dams outside the city and partly outside the State, and SANDRP attributes the 2019 flood to the late opening of the Gandhi Sagar gates (SANDRP, 2019). The reported releases conflict, from 4.42 lakh cusec in the CWC report of 14 September to 7.9 lakh cusec in the press, so item (d) takes the highest until WRD gives the record. For the Dravyavati, the Jojari, the Ayad and the Ghaggar no level was found at all, which is why item (b) requires a modelled or surveyed level on those reaches and does not let an outfall be designed without one.
The fifth is the body that owns the receiving water, and the line that the courts are drawing. The dams, reservoirs and canals are WRD's, the public tanks and street drains vest in the Municipality (Rajasthan Municipalities Act 2009, s.68), the lakes fall under the Lakes Act 2015 once notified, and no rule dividing the natural nalas from the municipal drains was found (Chapter 6, Clause 6.9). Items (c), (e) and (f) ask for the owner's consent and design level because a design that discharges to a channel or a lake cannot be checked without them. The Indira Gandhi Canal and the lift canals that feed the city reservoirs carry supply water; a canal escape that takes storm water in a storm would put it where the canal operator does not expect it. The Supreme Court's order of 7 August 2026 will produce a High Flood Line for every river in the State, and item (e) makes the Manual's design river level no lower than that line when it is demarcated, so that a drain is not designed to a level that the State has already found too low. The court lines of item (e) are listed because they decide where an outfall can be built, not its level; their status is set out in Chapter 7.
5.9 Joint-probability cases
5.9.1 Every element draining to a tidal or backwater-affected outfall shall be checked for the cases below. The most severe governs each design quantity: storage, water level, pipe size and pump capacity.
Table 5.2 — Joint-probability cases for tidal and riverine outfalls
| Case | Rainfall | Tailwater | Applies to | Basis |
|---|---|---|---|---|
| J1 | Minor-system design AEP, Tc to 24 h | MHWS + SLA (tidal curve) | Minor system | Clause 2.12(a); Clause 5.7.1 |
| J2 | 1% AEP, all durations of Clause 2.5.2 | HAT + surge + SLA | Major system, detention, tanks, pumped systems | Clause 5.7.1 |
| J3 | 10% AEP, 48 h | 1% AEP still-water level + SLA | Major system, detention, tanks, pumped systems | Clause 2.12(b) |
| J4 | Design AEP, 48 h (72 h reported) | Tidal curve per J1 with two 6 h lock windows (Clause 5.10) | All storage and every gated or tide-affected outfall | Clause 5.10 |
| R1 | Site design AEP | River at 10% AEP level | Riverine outfalls | Clause 5.8.4(a) |
| R2 | Site 10% AEP | River at design-AEP level | Riverine outfalls | Clause 5.8.4(b) |
5.9.2 For storage elements, the 48- and 72-hour storms shall be run with the J2 and J3 tailwaters (Clause 2.5.3).
5.9.3 For tidally influenced riverine outfalls, R1 and R2 shall be run with the river model's downstream boundary at the J1 tidal curve. The Authority may also require them at J2.
5.9.4 Where tailwater is constant at a level above the outfall invert for the whole storm, the case is treated as a fully closed outfall. Storage and pumps shall then handle the full storm volume.
Commentary. Clause 2.12 sets two joint cases. Case (a) is design rainfall with MHWS plus the sea-level allowance. Case (b) is the 10-yr, 48-hour storm with the 1% still-water level. This Manual adds HAT plus surge for major-system design (Clause 5.7.1). Case J2 combines these. J4 is the outfall-closed check, which tests the timing of tide against the storm rather than a single level. Rainfall and surge share a cyclone cause, so they cannot be treated as independent (Clause 2.12 commentary). These cases are simple surrogates, to be replaced when a statistical joint analysis of IMD rainfall and tide-gauge records is adopted.
5.10 Outfall-closed (tide-locked) storage check
5.10.1 Where it applies. The check applies to:
- every storage facility;
- every minor- and major-system element; and
- every pumped system
whose outfall invert is below HAT + surge + SLA, or which drains to a reach subject to tide-lock or sand-bar closure (Clause 5.13).
5.10.2 Storm. Use the 48-hour design storm built per Clause 2.9.2 (peak day last), at:
- the AEP of the element: 1% AEP for detention, tanks and the major system; the minor-system AEP for minor drains; and
- AMC III.
The 72-hour storm shall also be run and reported.
5.10.3 Lock windows. Unless a site study under 5.10.6 gives otherwise:
- (a) the outfall is closed for two consecutive lock windows of 6 hours each, centred on two consecutive high tides of the local tidal curve. For a semi-diurnal tide, the window starts are therefore about 12.4 hours apart.
- (b) During each lock window, gravity discharge is zero.
- (c) Between lock windows, gravity discharge is computed against the J1 tidal curve, including the head loss of the flap gate and any non-return valve.
- (d) The first lock window shall be placed so that it is centred on the peak 1-hour block of the final 24 hours of the storm. A second run with the first window starting at that peak block shall also be made. The more severe governs.
5.10.4 Requirement. Storage plus pumping (where provided) shall hold the inflow so that, throughout the check:
- (a) the maximum stage in any detention facility stays below its emergency spillway crest, so the spillway does not operate. Where the outfall-closed stage is higher than the 1% AEP maximum water level of the free-outfall design, it becomes the facility's 1% AEP maximum water level for Clause 4.9.3, and the spillway crest, freeboard and wall height are set from it;
- (b) the maximum stage in the minor and major systems meets the Chapter 6 limits: building floor levels, and street depths of no more than 150 mm at the crown and no more than 350 mm at the deepest point; and
- (c) no property connection surcharges above the lowest opening it serves, or a non-return valve is fitted under Clause 5.11.
In volume terms, over each lock window and the full storm:
V_inflow ≤ V_storage available + V_pumped + V_gravity (between locks)
This shall be demonstrated by routing, not by a single volume balance. The release from each facility after a lock window ends may exceed the release caps of Chapter 4, because the facility is emptying into a drain that has just reopened. That release shall be included in the downstream analysis (Clauses 5.4 and 5.9).
5.10.5 Drawdown after the storm. After the second lock window, the storage shall drain under the J1 tidal curve. The drawdown requirement of Clause 4.7 shall be met, with pumping where gravity cannot meet it (Clause 5.12).
5.10.6 Site study. A longer or shorter lock may be used where a site study gives a time series of still-water level for the design case. The study may use a calibrated hydrodynamic model, gauge records of past events, or a surge hindcast. Locks shorter than the default require the Authority's approval. A longer lock shall be used where:
- sand-bar closure (Clause 5.13) or river backwater (Clause 5.8) keeps the outfall closed for longer; or
- the gauge record shows tailwater above the outfall invert for more than 6 hours per tide in comparable past events.
Figure 5.3 — Outfall-closed check: 48-hour storm with the peak day last (Clause 2.9.2), tailwater of astronomical tide plus surge, two 6-hour design lock windows, and the resulting stage upstream of the flap gate. Illustrative — not design values. Original drawing for this Manual, adapted from the tidal tailwater and joint-probability concepts of MoHUA/CPHEEO Manual on Storm Water Drainage Systems (2019), Part A, §6.3.6.
Commentary. The outfall-closed check is the distinctive Rajasthan requirement in this Manual. In Rajasthan it applies where an outfall is shut not by the tide but by a lake held at its full gauge, by a river raised by the releases of the dams above it, or by the absence of any outfall at all. In September 2019 the Kota Barrage was reported releasing about 6.5 to 7.9 lakh cusec, the Chambal at Kota City set its highest recorded level, 248.68 m, 6.68 m above its danger level (CWC), and low-lying Nayapura, Balita and Gavndi were evacuated (as reported). In July 2025 Ana Sagar was reported at 15 ft 11 in on its gauge against a full level of 13 ft, and the opening of its escape gates flooded the land along the channel (as reported). In the closed depressions of the west the water has nowhere to go: after the Barmer storm of August 2006, Kawas was reported still under 3 to 4 ft of water seven months later. A lake at its full gauge stays there for the rest of the monsoon, a river below a spilling dam stays high for as long as the dam spills, and a closed depression empties only by infiltration and evaporation, which is why Clause 5.8.5 replaces the two 6-hour windows described below with a closure for the whole storm at a lake outfall and where there is no outfall, and with a single river lock of at least 72 hours. A rate rule cannot help when there is no outlet: an orificed basin behind a closed gate simply fills.
The default of two consecutive 6-hour locks has no direct precedent. It represents gravity outfalls failing to discharge for about half of each tidal cycle around the two high tides nearest the storm peak. Figure 5.3 shows why both windows matter. The first lock catches the storm peak. The second arrives before the storage has drained, so the stage rises again.
Placing the first window on the rainfall peak is deliberately unfavourable. Cyclone rainfall and surge share a cause, and Clause 2.12 already treats them as dependent. The check replaces neither the J2 and J3 level checks nor the downstream analysis; it adds a test of timing and volume.
5.11 Flap gates, tide gates and non-return valves
5.11.1 Where required. A flap gate, tide gate or equivalent non-return device is required on every outfall whose invert is below the 1% AEP still-water level (Clause 5.7.3). It is also required on outfalls into irrigation channels under Clause 5.8.5.
5.11.2 Hydraulics. The design shall include:
- the gate's head loss and opening head, from the manufacturer's certified head–discharge curve; and
- the reduction in effective outfall capacity when the gate is partly open.
Gates shall not be assumed to seal perfectly in the outfall-closed check unless they are tested.
5.11.3 Construction.
- (a) Gates, hinges and seats shall be of corrosion-resistant materials suitable for seawater (Clause 4.12.5).
- (b) The gate shall be set so that sand, silt or debris on the downstream side cannot hold it shut or open. Where the bed is mobile, the gate invert shall be raised above the bed, or the approach shall be protected.
- (c) A trash screen shall be provided upstream where the gate could be jammed by debris.
- (d) A stop-log slot or penstock shall be provided upstream for maintenance isolation on outfalls larger than 600 mm.
- (e) The gate chamber shall be accessible at all tides, with its access above HAT + surge + SLA.
5.11.4 Non-return valves on property connections. A non-return valve, or a backwater valve with an accessible cleaning eye, is required on every property drainage connection where the lowest opening served is below:
- the major-system tailwater (J2) at the point of connection; or
- the maximum stage in the outfall-closed check (Clause 5.10).
Basement drainage shall in addition be pumped to a level above both, with its own non-return valve.
5.11.5 Inspection. Gates and valves shall be inspected and operated:
- before 20 June each year;
- after every event in which they closed against a storm flow; and
- as set in the maintenance plan (Chapter 10).
Commentary. The requirement for gates below the 1% still-water level is set by this Manual. The construction details follow common coastal-drainage practice. A gate that is jammed open by debris lets the tide into the drain. A gate held shut by a sand bank turns a gravity outfall into a dead end. In Rajasthan the outfalls do not cross a beach, but many of them end in a lake whose level is held by gates, or in a river whose level is set by the gates of the dams upstream. Ana Sagar at Ajmer is held at 13 ft on its gauge by opening its four escape gates, but readings of 14 ft to 15 ft 11 in have been reported before the gates were opened, and when they were opened in September 2024 and July 2025 the colonies along the escape channel were waterlogged (as reported). At Udaipur the gate between Pichola and Fateh Sagar is reported to be closed once Fateh Sagar reaches 11 ft, and the main bund of Fateh Sagar has been reported to have about 0.75 m of freeboard, with sandbags holding the lake 20–25 cm above its design full tank level (India Water Portal, 2010). On the Chambal, SANDRP attributes the Kota flood of September 2019 to the late opening of the Gandhi Sagar gates upstream (SANDRP, 2019). A gate that is opened late, or not at all, raises the lake and every outfall that drains to it; a gate opened in a hurry raises the channel or river below. The lakes, dams and gates are held by WRD, the Municipal Corporation or another custodian, while the drains that reach them belong to the Municipal Corporation, a development authority, an Urban Improvement Trust or a colony developer, and no rule linking the operation of any of these gates to the levels of the drains was found during research [TBC], so a gate and the drains behind it can belong to different bodies. The 20 June inspection date is set ahead of the SW monsoon.
5.12 Pumped outfalls
5.12.1 When required. Pumping shall be provided where gravity discharge cannot meet:
- the outfall-closed check of Clause 5.10;
- the drawdown requirement of Clause 4.7; or
- the J2 and J3 cases.
Pumping shall not be used where a gravity solution meets these requirements.
5.12.2 Capacity.
- (a) The duty pumps together, with the storage provided, shall pass every case of Clause 5.9 (including J4), demonstrated by routing.
- (b) Standby capacity at least equal to the largest duty pump shall be installed (duty + 1 standby as a minimum).
- (c) Pump capacity shall be stated at the static head for the J2 tailwater, not at mean tide.
5.12.3 Effect on the receiving water. Pumped discharge to a river, canal or creek shall be included in the river or creek level analysis of Clause 5.8. Pumping that raises the receiving water level above the acceptance criteria of Clause 5.5 elsewhere is not permitted.
5.12.4 Power supply. Pumping stations shall have either:
- two independent power supplies; or
- standby generation for 100% of the duty capacity, with on-site fuel for at least 72 hours of duty operation.
Changeover shall be automatic.
5.12.5 Flood immunity. Electrical panels, control equipment, generators and fuel storage shall be set above the higher of:
- the 1% AEP flood level + 0.5 m; and
- HAT + surge + SLA + 0.5 m.
Access to the station shall remain usable in the 1% AEP event.
5.12.6 Discharge arrangement. Rising mains shall discharge:
- over a level above the J2 tailwater; or
- through a non-return valve and a flap gate.
The arrangement shall prevent back-siphoning.
5.12.7 Controls and monitoring. Each station shall have:
- automatic level control;
- remote alarms for high level, pump failure and power failure, sent to the operator; and
- a level and run-time log kept for at least 5 years.
Wet wells shall be sized to keep pump starts within the manufacturer's limits.
5.12.8 Screens. Inlet screens shall be provided with a cleaning method that works during a storm (a mechanical rake, or duplicate screens).
5.12.9 Testing. Every pumped outfall shall be test-run at full duty, including on standby power, before 20 June each year. Private pumped systems shall be covered by a registered maintenance declaration (Chapter 10).
Commentary. Duty + standby, 72 hours of fuel and flood-immune electrics have no single direct precedent and are set by this Manual. The 72-hour fuel figure matches the longest mandatory design storm (Clause 2.5.2). A pump station that depends only on grid power can stop exactly when it is needed, because supply to flooded areas is often switched off for safety. Singapore's April 2025 amendments added annual maintenance declarations for pumped detention tanks (PUB Addendum No. 3). Clause 5.12.9 and Chapter 10 adopt the same approach. Clause 5.12.3 prevents pumping that simply moves water from one tide-locked drain into a tide-locked river.
5.13 Sand-bar closure of river mouths
5.13.1 Where it applies. This clause applies to outfalls into any river or creek whose mouth is subject to seasonal sand-bar closure. That includes the mouths of the coastal States (there is none in Rajasthan: Clause 5.1.4), and any other mouth listed in Annex 5B.
5.13.2 Assumption at the start of the SW monsoon. The mouth shall be assumed closed by a bar at the start of the June–September season, at the crest level of the most recent pre-monsoon survey. This applies unless WRD certifies that:
- a mouth-maintenance programme (dredging, bar cutting or training walls) has kept the mouth open at the start of each of the previous three SW monsoon seasons; and
- the programme is funded for the current season.
5.13.3 Tailwater with a closed mouth. With the mouth closed, the tailwater at the outfall shall be the higher of:
- (a) the tidal tailwater of Clause 5.7; and
- (b) the level in the river reach behind the bar, computed with the bar as a weir at its surveyed crest level. That level shall include the river flow of Clause 5.8 and the head needed to pass the flow over or through the bar.
5.13.4 No credit for emergency cutting. Bar cutting or breaching during the storm shall not be assumed in design, unless WRD has a documented operating procedure, with equipment stationed for it. Where it does, the bar may be assumed lowered to the procedure's target level only after the time the procedure states.
5.13.5 Outfall-closed check. Where the closed-mouth level of 5.13.3(b) exceeds the outfall invert for longer than the default lock windows, the lock duration of Clause 5.10 shall be extended to that period.
Commentary. Rajasthan has no coast and no river mouth, so Clause 5.13 does not apply in the State (Clause 5.1.4). Its nearest inland counterparts are the gated outlets and escape channels of its lakes and the silt and sand that its rivers leave at an outfall. A lake whose gates are not opened when it reaches its full gauge rises above it and holds every drain that ends in it, as Ana Sagar has been reported to do at 14 ft to 15 ft 11 in against a full gauge of 13 ft, and silt and sand left by a flash flood in a dry river bed can hold a flap gate shut or open. No written gate-operation rule for the escape gates of Ana Sagar, the gates of the Udaipur lakes or any other lake outlet was found during research [TBC]. Clause 5.8.5 deals with both by giving no credit for a gate operation or a storage that the custodian's records do not show. Clause 5.13.2 has no direct precedent. It puts the burden of proof on showing that the mouth is open rather than assuming it.
5.14 Documentation
Every project subject to this chapter shall submit a Downstream and Tailwater Report (Form 5-1). It shall contain:
- a plan of the analysis extent showing:
- the site;
- each analysis point with its contributing catchment area and the site's percentage of it; and
- the end point and the reason it was chosen (Clause 5.3);
- the model description:
- software and version;
- the network schematic, with survey sources for the drains and crossings;
- land use and CN for off-site areas;
- any upstream detention included; and
- calibration or validation evidence where available;
- for each analysis point, AEP and duration, the existing and with-project:
- peak flow;
- time to peak;
- maximum water level and velocity; and
- duration of inundation (Clause 5.4);
- the comparison against Clause 5.5, with each failure identified and the remedy adopted;
- the tailwater derivation:
- tide-table edition and port;
- MHWS, HAT and MSL relative to chart datum;
- the datum connection to the Survey of India benchmark and the project datum;
- surge source and value;
- SLA; and
- river levels and their sources (Clauses 5.6 to 5.8);
- the joint-case table of Clause 5.9 with results;
- the outfall-closed check (Clause 5.10):
- storm and lock alignment;
- stage hydrographs; and
- the volume balance for each lock window;
- a schedule of flap gates, tide gates and non-return valves, with certified head–discharge data (Clause 5.11);
- pumped outfall design, power supply, flood immunity and controls, where provided (Clause 5.12);
- the sand-bar assumption and supporting WRD certification, where relevant (Clause 5.13); and
- inspection and maintenance requirements for Chapter 10.
Small sites under Clause 5.3.4 shall submit Form 5-2 (Simplified Downstream Statement) instead.
References (chapter)
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A, §6.3.6 and Table 6.2 (coastal tailwater; +0.3 m climate allowance). https://web.archive.org/web/2024/https://mohua.gov.in/upload/uploadfiles/files/VolumeI-Part%20A-Engineering-Design.pdf
- MoHUA / CPHEEO (2013). Manual on Sewerage and Sewage Treatment Systems (pumping stations).
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (5601.5, ten-percent downstream analysis). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Atlanta Regional Commission / Georgia EPD (2016). Georgia Stormwater Management Manual, Vol. 1 (Standard #8) and Vol. 2 §3.1.9. https://documents.atlantaregional.com/gastormwater/GSMM_2016%20EDITION_FINAL_V1.pdf
- MARC. The Evolution of Regional Stormwater Design Standards. https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Optimisation of urban detention (2016). Water 8(7):290. https://doi.org/10.3390/w8070290
- Colorado State University. Spatially Dependent On-Site Detention Policies (thesis). https://mountainscholar.org/bitstreams/f4dbec4e-a44f-4933-8d54-a097e741f44a/download
- Central Water Commission. Central Flood Control Room, Daily Flood Situation Summary, bulletins of 16 and 17 September 2019 (Bulletin No. 140), read through archived copies (warning, danger and highest flood levels at Kota City and Dholpur; levels of the Kota Barrage, Rana Pratap Sagar, Bisalpur and Gandhi Sagar). https://cwc.gov.in/sites/default/files/cfcr-cwcdfb17092019.pdf ; and the bulletin of 23 August 2022 and the daily flood situation report of 14 September 2019, seen only as search summaries. The datum and gauge zero of each gauge are to be confirmed. https://cwc.gov.in/
- SANDRP (2022). 2022 overview of CWC flood monitoring sites in West India (a copy of the CWC site list: warning, danger and highest flood levels for the Chambal, Banas, Luni, West Banas, Gambhiri and other sites; full and maximum levels of the reservoirs). https://sandrp.in/2022/10/02/2022-overview-of-cwc-flood-monitoring-sites-in-west-india/ ; and SANDRP (2019). Man-made national crisis that Gandhi Sagar dam faced in Sept 2019. https://sandrp.in/2019/09/24/man-made-national-crisis-that-gandhi-sagar-dam-faced-in-sept-2019/
- National Institute of Hydrology, North Western Regional Centre (2025). Assessment of the Water Level Rise Crisis in Jodhpur City, final report (Kailana and Takhat Sagar: full reservoir levels and capacities; the Rajiv Gandhi Lift Canal; drainage to the Jojari). https://nihroorkee.gov.in/studies_2014-2025/135-Assessment%20of%20water%20level%20rise%20crises%20in%20Jodhpur_S.%20Nema.pdf
- Jaipur Development Authority. Dravyavati River Rejuvenation Project, EIA/EMP Chapter 2 (47.50 km; the 100-year flood; discharge to the Dhund). https://environmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/170520176S4VOAIDChapter-2.pdf
- Rajasthan Municipalities Act, 2009 (Act 18 of 2009), ss.68 and 202, as read from a third-party copy (amendments not checked). https://lawgist.in/states/rajasthan/rajasthan-municipalities-act-2009
- Rajasthan Lakes (Protection and Development) Authority Act, 2015 (Act 5 of 2015), read from the Bill (Bill No. 11 of 2015, authorised English translation), ss.2–6. https://www.ielrc.org/Content/e1501.pdf
- Supreme Court of India. In Re: 2 Million Lives at Risk, Contamination in Jojari River, Rajasthan, Suo Motu WP (C) 8 of 2025: judgment of 21 November 2025 (2025 INSC 1341), https://api.sci.gov.in/supremecourt/2025/53967/53967_2025_3_50_66079_Judgement_21-Nov-2025.pdf ; and order of 7 August 2026 (2026 INSC 812; the High Flood Line and ecological buffer for all river systems; no fresh permissions in identified river corridors), https://api.sci.gov.in/supremecourt/2025/53967/53967_2025_2_58_72891_Judgement_07-Aug-2026.pdf ; and the interim order of 24 August 2026 (100 m from the edge of the Jojari; 500 m for hazardous industries), as reported (PTI, ThePrint).
- High Court of Rajasthan. Ramji Lal Saini v. State of Rajasthan, D.B. CWP (PIL) 6614/2021, order of 7 May 2026 (quoting Abdul Rahman v. State of Rajasthan, DBCWP 1536/2003, 2 August 2004, and Gulab Kothari v. State of Rajasthan, DBCWP 1554/2004, 12 January 2017), https://www.livelaw.in/pdf_upload/2026/05/22/ramji-lal-675710.pdf ; suo motu order on the wetlands of the State, 1 June 2026, https://www.livelaw.in/pdf_upload/2026/06/05/suot-motu-wetlands-uploaded-678250.pdf ; suo motu SBCWP 11153/2011 (the Ramgarh catchment; orders of 23 August 2011 and 29 May 2012), as quoted by the Supreme Court in National Institute of Medical Science University v. State of Rajasthan, judgment of 9 November 2017, https://hcraj.nic.in/sci/2012/1-38041-2012_2017-11-09.pdf ; and the Udaipur lakes (the no-construction zone notification of 17 January 1997; the Fateh Sagar catchment order of November 2025; suo motu CW 12630/2026), as reported (Down To Earth; Udaipur Times; Verdictum, 10 June 2026).
- National Green Tribunal, Central Zone, and Supreme Court of India: Ana Sagar, Ajmer (structures in the wetland; orders of 2023 and 2025; demolition from 12 September 2025), as reported (ThePrint; The Week).
- Soni, G.P. (2010). Storage above design full tank level in Pichola, Swaroop Sagar and Fatah Sagar lakes, Udaipur. India Water Portal. https://www.indiawaterportal.org/climate-change/disasters/storage-above-design-full-tank-level-pichola-swaroop-saagar-and-fatah-saagar-lakes-udaipur
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012), Rajasthan pages (Jaipur and Kanota, 19 July 1981; Pindwara, 1 September 1973). https://imdpune.gov.in/library/public/EXTREMES%20OF%20TEMPERATURE%20and%20RAINFALL%20upto%202012.pdf
- Singh, R.S., Ramakrishna, Y.S., Sharma, K.D., Purohit, R.S. and Bohra, D.N. (1992). Some hydrometeorological aspects of an unprecedented rainstorm in the Indian desert. Annals of Arid Zone 31(3), 205–210 (citing Dhir et al., 1982, on the July 1979 flash flood in the Luni). https://epubs.icar.org.in/index.php/AAZ/article/download/66155/28315/165909
- Ramsar sites of Rajasthan: Keoladeo National Park (1981), Sambhar Lake (1990), and Khichan and Menar (4 June 2025), as listed in secondary sources.
- The share of the State that drains inland (about 60%), from secondary sources, and the basin table of the Ground Water Year Book 2016–17, as reproduced; the two use different definitions.
- Press reports on the Kota flood of September 2019 and the Kota Barrage releases (PTI/Business Standard; Hindustan Times; Lokmat Times); on the Ana Sagar gauge and escape gates (Patrika), https://www.patrika.com/ajmer-news/heavy-rain-water-flows-from-anasagar-channel-gate-4925040/ and https://www.patrika.com/ajmer-news/ajmer-anasagar-13-not-20-feet-of-water-in-anasagar-5071793/ ; on the Ajmer floods of September 2024 and July 2025 (ANI; Free Press Journal; The Week); on the Udaipur lake levels (Amar Ujala, July 2025), https://www.amarujala.com/rajasthan/udaipur-news-city-submerged-due-to-two-hours-of-torrential-rain-in-udaipur-drainage-system-failed-2025-07-06 , and Udaipur Times; on the Barmer flood of August 2006 (Down To Earth); and on the Ghaggar and the Ottu weir (The Statesman).
- Survey of India. Tidal Predictions: Geodetic and Research Branch. https://www.geographyandyou.com/survey-of-india/tidal-predictions-geodetic-and-research-branch-survey-of-india
- GLOSS. India national report (tide-gauge network and datums). https://gloss-sealevel.org/gloss/gloss/sites/gloss/files/publications/documents/india_ge9.pdf
- Adani Ports (2025). Tide Table 2025, Dahej (notes on NHO INP-12 coverage and data sources). https://www.adaniports.com/-/media/Project/Ports/PortsAndTerminals/Dahej-Port/Marine-Documents/Tide-Table-2025-Dahej.pdf
- INCOIS. Storm-surge and swell-surge warning services. https://incois.gov.in/
- FHWA. HEC-22 Urban Drainage Design Manual (current edition), Table 7.3 (coincident frequencies).
- Purdue University JTRP (2023). Development of a Multiple Water Course Joint Probability Analysis Procedure for Indiana Watersheds, FHWA/IN/JTRP-2023/09. https://docs.lib.purdue.edu/jtrp/1820
- PUB Singapore (2025). Code of Practice on Surface Water Drainage, 7th ed., Addendum No. 3. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
Annexes and forms
| Annex / Form | Content |
|---|---|
| 5A | Tidal datums (MSL, MHWS, HAT vs CD and Survey of India datum), surge allowances and 1% still-water levels by coastal segment |
| 5B | Major drains, riverine outfall reaches, and river mouths subject to sand-bar closure; map |
| 5C | Worked example: outfall-closed check for a site on a Dravyavati tributary nala in south Jaipur |
| Form 5-1 | Downstream and Tailwater Report |
| Form 5-2 | Simplified Downstream Statement (small sites) |
Commentary. The drains of Rajasthan's cities fail in places that site design does not see, and in three different ways. About 60% of the State drains inland, to no river and no sea (as reported); there, in the interdunal depressions and the town sites of the Thar, Shekhawati and the canal command, and in the basin of the Sambhar salt lake, water that runs off stays where it collects, and after the Barmer storm of August 2006 (about 577 mm in 3 days against an annual normal of about 277 mm, as reported) Kawas was reported still under water seven months later. In the east and south the drains end in lakes held at their full level by gates or escape channels, or in rivers whose level is set by the dams above them. The lakes of Udaipur form a chain: Pichola and Fateh Sagar are joined by a gated channel and both spill to the Ayad (Ahar), which runs to Udai Sagar (as reported). Ana Sagar at Ajmer is held at its full gauge by opening escape gates, and the escape channel floods the colonies along it (as reported, 2024 and 2025). Jaipur's nalas end in the Dravyavati, which discharges to the Dhund (JDA, Dravyavati EIA), and Jodhpur's in the Jojari. At Kota the Chambal is raised by the releases of Gandhi Sagar, Rana Pratap Sagar, Jawahar Sagar and the Kota Barrage, and in September 2019 the river at Kota City set its highest recorded level, 248.68 m, against a danger level of 242 m (CWC). The outfalls also belong to one body while the drains above them belong to others: the dams, reservoirs and canals are held by WRD, the public tanks and street drains by the Municipality, the land recorded as gair mumkin nala by the Revenue Department, and the drains of new schemes by the development authority, the Urban Improvement Trust or the colony developer, and no rule divides them (Chapter 6, Clause 6.9). No document found during research sets a design level for any lake or river outfall, and the only design return period published for a city channel is the 100-year flood of the Dravyavati (JDA, Dravyavati EIA). A detention basin that meets every release rate in Chapter 4 still fails if the drain below it is already full, if the lake or river it drains to stands above its outfall for days, or if there is nowhere for the water to go. This chapter makes all three failure modes part of the design. Rajasthan has no tidal outfall, so Clause 5.1.4 says which of the chapter's coastal provisions fall away and what takes their place.