Draft v1.0 prepared by NEER. Not adopted by the Government of Rajasthan or any authority or local body, and has no legal force. About this draft

Chapter 10Submittals, Review, Operation & Maintenance and Enforcement


10.1 Purpose and scope

10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:

  • (a) the submittal stages and their contents (Clauses 10.3–10.4);
  • (b) the compliance calculator (Clause 10.5);
  • (c) professional certification and review (Clauses 10.6–10.7);
  • (d) construction inspection and as-built certification (Clauses 10.8–10.9);
  • (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
  • (f) handover of public assets (Clause 10.14);
  • (g) enforcement (Clause 10.15); and
  • (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).

10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.

Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Rajasthan the failure is one of missing criteria and of conditions checked only for rainwater harvesting. No document of UDH, the LSG Department, a Municipal Corporation, a development authority or an Urban Improvement Trust stating a design return period, intensity or runoff coefficient for urban storm drains was found, other than RUIDP's guidance of 2008 for its own projects (1–2 years for town drains). The Rajasthan Municipalities Act 2009 makes drainage a duty of the Municipality (s.45), vests in it the public tanks and streams and the drains and watercourses in, alongside or under any street (s.68), and puts all drains within the Municipality under its survey and control (s.200); the rivers, dams and reservoirs that receive the drains are with WRD. The approval route shapes this chapter. The Building Regulations 2025 were issued by UDH with its order No. P.11(5) नविवि/Building Regulations-2025/2025 of 12 May 2025, under s.337 of the Municipalities Act, s.104-A of the Rajasthan Urban Improvement Act 1959 and the Acts of the development authorities; each urban local body or authority brings them into force by its own publication in the Gazette (reg. 1.2), so the date of commencement varies by city [TBC for each city; one secondary source gives 5 December 2025], and on commencement they repeal the earlier regulations, among them the Model Building Regulations 2020 and the JDA (Jaipur Region) Building Regulations 2020 (reg. 18.1). Under them a building plan is approved by the urban local body, the development authority or the Urban Improvement Trust, or by an empanelled architect; rainwater harvesting on plots of 225 m² or more is declared by affidavit at approval and checked for the completion certificate (Schedule 3), and the refundable deposit of ₹50,000 to ₹5 lakh is returned only after the Ground Water Department, WRD or an experienced retired engineer reports that the structure works (reg. 8.3(ii) and Schedule 2); the plinth must stand at least 0.45 m above the road in front (reg. 6.6). The Municipalities Act bars the construction or occupation of a building until a drain is built "at such level and with such fall" as effectual drainage needs, emptying to a municipal drain within 50 ft or else to a cess-pool (s.202), requires written consent to connect to, or build over, a drain vested in the Municipality (s.213), and bars a public water connection to a new building without the Municipality's certificate that rainwater harvesting has been provided (s.238(4)), a condition PHED is reported to apply (as reported). In a lake's protected area, construction needs the prior permission of the Lakes Development Authority, and a plan that covers a lake its prior approval (Lakes Act 2015, s.5, as read from the Bill), though no protected area was found notified. Since 7 August 2026 the Supreme Court has barred any department, statutory authority or local body from granting fresh permissions for industrial, commercial or residential development within the identified river corridors of the State until the High Flood Line and ecological buffer of every river system have been demarcated (In Re: 2 Million Lives at Risk, Contamination in Jojari River, Rajasthan). No rule asks for a drainage report, limits peak runoff, requires on-site detention or sets a setback from a nala, river or lake. Every stormwater item in this chapter is therefore written so that the architect or engineer on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it with the building plan at approval, at the completion certificate and at the functionality check that releases the rainwater harvesting deposit. This chapter is the process.


10.2 Definitions

Term Meaning in this chapter
Submittal A set of documents lodged with the Authority at one of the stages of Clause 10.3.
Drainage report The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4.
Stormwater facility Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private.
Hold point A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8).
As-built certificate The certificate of Clause 10.9 that the facility was built as approved and performs as designed.
Owner The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset.
O&M plan The operation and maintenance plan of Clause 10.11.
Facility register The public register of facilities of Clause 10.17.

Other terms are defined in Clause 1.4.


10.3 Submittal stages

10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Model Rajasthan Building Regulations 2025 (Table 10.1):

Table 10.1 — Submittal stages and linked approvals

Stage Submittal When Linked approval
0 Pre-application meeting and Form 1-1 (Applicability Determination) Before the planning permission or layout application None (advisory record)
1 Preliminary drainage report With the planning permission or layout application Planning permission / layout approval
2 Final drainage design Before building permit, or before commencement where the permit is issued with the planning permission Building permit / commencement
3 Construction inspections at hold points During construction None (records filed)
4 As-built certificate and verification tests Before the completion certificate Completion / occupancy certificate
5 Maintenance declaration registered, or handover of public assets Before or with the completion certificate Completion certificate; asset acceptance
6 Annual declarations and inspection reports Every year after completion Continuing compliance

10.3.2 Stage 0 is mandatory for:

  • (a) sites of 2 ha or more;
  • (b) sites in a flood-sensitive catchment;
  • (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
  • (d) sites draining to a tidal outfall or adjoining a waterbody.

For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.

10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.

10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.

10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.

Figure 10.1 — Submittal, review and approval workflow Two columns: applicant stages 0 to 6 on the left, Approving Authority actions and approval gates on the right. Stages 1 and 2 can be returned with comments for resubmittal. Stage 6 repeats every year. Applicant / certifying professional Approving Authority Stage 0 — Pre-application Form 1-1 Applicability Determination Confirms applicability; advises Mandatory: ≥ 2 ha, flood-sensitive, waterbody Stage 1 — Preliminary drainage report Forms 2-1, 10-1, 10-2, 10-3 comments Check 5 days; review 15 (resubmit 10) → Planning permission / layout Stage 2 — Final drainage design Models, GIS, draft O&M plan, Form 10-3 comments Review 15 working days (resubmit 10) → Building permit / commencement Stage 3 — Construction Hold-point inspections, Form 10-4 Notified of key hold points (3 working days); may attend Stage 4 — As-built certification Survey, re-run, drawdown tests, Form 10-5 Accepts as-built certificate → Completion certificate Stage 5 — Maintenance declaration Form 10-6, or handover with Form 10-8 Enters facility / asset register → Public asset accepted Stage 6 — Every year, pre-monsoon Form 10-7 annual declaration Inspects; enforces (Clause 10.15) Publishes register (Clause 10.17) yearly Approval gate (accent text) Returned with comments; resubmit Periods in working days (Clause 10.7)

Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.

Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the Building Regulations 2025 steps a Rajasthan applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.


10.4 Required contents and checklists

10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:

  • (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
  • (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
  • (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
  • (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
  • (e) the pre-development condition and hydrologic method (Chapter 3);
  • (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
  • (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
  • (h) the downstream extent and tailwater case (Chapter 5);
  • (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
  • (j) the land reserved for facilities and maintenance access (Clause 10.13).

10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:

  • (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
  • (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
  • (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
  • (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
  • (e) construction drawings, details and specifications of every facility;
  • (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
  • (g) the hold-point schedule (Clause 10.8);
  • (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
  • (i) the model input files and the GIS data of Clause 10.4.4; and
  • (j) the certificates of Clause 10.6.

10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.

10.4.4 Digital submittal.

  • (a) Reports and drawings shall be submitted as searchable PDF.
  • (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
  • (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (43N statewide, except the districts of Jaisalmer and Barmer, which use 42N; the part of Dholpur district east of 78° E also uses 43N; one zone is used for the whole of a project), with attributes as listed in Annex 10B.
  • (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the CWC and WRD gauges on the receiving rivers and the level datums of WRD and the lake custodians for the lakes and reservoirs that receive city drainage, with lake gauge readings in feet above a local zero converted to metres on a named datum used in Chapter 5 shall be stated.

10.4.5 Summary of forms used in submittals (Table 10.2):

Table 10.2 — Forms used in submittals

Form Title Stage
1-1 Applicability Determination 0 or 1
1-2 Variance / Waiver Request 1
2-1 Design Rainfall Sheet 1, 2
10-1 Drainage Report Checklist 1, 2
10-2 Compliance Calculator Summary 1, 2, 4
10-3 Professional Design Certificate 1, 2
10-4 Hold-Point Inspection Record 3
10-5 As-built Certificate 4
10-6 Maintenance Declaration 5
10-7 Annual Maintenance Declaration and Inspection Report 6
10-8 Asset Handover Certificate 5

Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Rajasthan has no notified design return period, runoff coefficient or design storm for its drains. The only statewide guidance found is RUIDP's Circular No. 8 of 4 March 2008 for the drainage works of its ADB-funded towns, which allows a return period of 1–2 years for town drains, 25 years for culverts and 50 years for bridges, the Rational method up to 50 km² and runoff coefficients of 0.7–0.9 in dense areas, and says that design intensities in India are "usually in the range of 12mm/hr to 20mm/hr"; that is far below Jaipur's measured 5-year 1-hour depth of 53.1 mm, so the circular is history, not a design basis. JDA designed the Dravyavati channel in Jaipur to pass the 100-year flood (EIA), but its design discharge was not found; the ADB documents for the Jodhpur storm water drains and for other RUIDP towns state no return period, intensity or runoff coefficient; and the return period of JDA's integrated storm water model of 2025 was not found. In IMD's national IDF study (Das et al. 2022) the Jaipur and Jaisalmer panels repeat a generic curve drawn for several other cities and are not used; the only station fit is the study of 44 years of IMD hourly data at Jaipur (Ghate and Timbadiya 2022), whose 50-year 1-hour depth of 93 mm is about a third above the value from the CWC ratios. The State's sub-daily design values are otherwise the short-duration ratios of the CWC Flood Estimation Reports for subzones 1(a), 1(b), 1(e) and 3(a), with the interim floors of Chapter 2. Form 2-1 and Form 10-2 therefore carry the whole design basis of each submission. Form 2-1 and Form 10-2 ensure that every design states its inputs.


10.5 Compliance calculator

10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:

  • (a) applies the applicability tests of Clause 1.5;
  • (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
  • (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
  • (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
  • (e) on alternative S-2, gives the permissible site discharge for each AEP; and
  • (f) produces the Compliance Calculator Summary (Form 10-2).

10.5.2 Use.

  • (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
  • (b) On the design-aid route, the calculator may be the only storage calculation.
  • (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.

10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.

10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.

Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Rajasthan calculator serves Tier B authorities in particular, where it may be the whole calculation.


10.6 Professional certification

10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or UDH:

  • (a) Tier A sites of 1 ha or more;
  • (b) any site in a flood-sensitive catchment;
  • (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
  • (d) any pumped facility, tide gate or regional facility.

10.6.2 Empanelment criteria shall be issued by UDH and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.

10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:

  • (a) the design complies with this Manual, except for variances listed and approved;
  • (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
  • (c) the models submitted reproduce the results reported.

10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.

10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.

Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the Building Regulations 2025 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.


10.7 Review procedure and timelines

10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.

10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:

  • (a) 15 working days of acceptance for a first submittal; and
  • (b) 10 working days of acceptance for a resubmittal.

10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.

10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the UDH list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.

10.7.5 Concurrent clearances. Where the permission of WRD for a work on, or a discharge to, one of its rivers, dams, reservoirs or canals, the written consent of the Municipality to connect to a municipal drain or to build over a drain vested in it under the Rajasthan Municipalities Act 2009 (s.213), the prior permission of the Rajasthan Lakes Development Authority for construction in the protected area of a lake, or its prior approval of a plan that covers a lake (Rajasthan Lakes (Protection and Development) Authority Act 2015, s.5), the approval of the Rajasthan State Wetland Authority for a regulated activity in a notified wetland, the consent of the custodian of a lake or reservoir for a discharge to it, the consent of RIICO for a discharge to a drain in one of its industrial areas, the consent of the body that owns or runs the receiving drain where that body is not the Authority (for example a development authority or an Urban Improvement Trust), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.

10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.

10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.

Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.


10.8 Construction inspection

10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:

  • (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
  • (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
  • (c) the infiltration tests of Clause 10.9.3;
  • (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
  • (e) pumps and controls, at commissioning.

10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.

10.8.3 Protection during construction.

  • (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
  • (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
  • (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.

Figure 10.2 — Construction hold points from approval to handover Vertical timeline from Stage 2 approval through construction, verification tests and as-built certification to the maintenance declaration or asset handover. Diamonds mark hold points (a) to (e) of Clause 10.8.1; each step shows the form used. Construction hold points: approval to as-built and handover (not to scale in time) Hold point: work stops until inspected and recorded Other required step Stage 2 Approval Stage 3 Construction Stage 4 Tests and as-built Stage 5 Declaration or handover Final design approved; hold-point schedule set Schedule of hold points approved with the design (Cl. 10.4.2(g), 10.8.1) Form 10-4 (schedule) Protect retention and infiltration areas Fenced off from traffic and stockpiles (Cl. 10.8.3(a)) (a) Excavated base of each facility Retention, infiltration, detention: before media, liner or structure Form 10-4 3-day notice * (b) Outlet structure, orifice, trash screen Before backfill, or before the facility is first allowed to fill Form 10-4 3-day notice * (d) Outfall, flap or tide gate, non-return valve Before the downstream connection is made Form 10-4 (e) Pumps and controls At commissioning Form 10-4 Area stabilised; temporary sediment removed Infiltration not in service until stabilised (Cl. 10.8.3(b), (c)) (c) Verification tests Infiltration retention empties within 72 h; pumps at duty point; gates open and seal (Cl. 10.9.3) Form 10-4 As-built survey and re-run; certificate accepted Licensed surveyor; calculator and model re-run; then completion certificate (Cl. 10.9) Forms 10-5, 10-2 Private facility: maintenance declaration Registered to run with the land; owner and successors bound (Cl. 10.10) Form 10-6 Public asset: handover to the ULB Cleaned, inspected inside, land or easement transferred; defects liability for at least one full monsoon season (Cl. 10.14) Form 10-8 * Notice: for sites under Clause 10.6.1 the Authority is given at least 3 working days’ notice of hold points (a) and (b), and may attend. Every hold point is inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs (Cl. 10.8.2).

Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.

Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.


10.9 As-built certification

10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:

  • (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
  • (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
  • (c) the completed hold-point records (Form 10-4); and
  • (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).

10.9.2 Acceptance. The as-built facility is accepted where:

  • (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
  • (b) the outlet dimensions and inverts match the approved design; and
  • (c) the re-run shows compliance with every criterion of Chapters 4 and 5.

Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.

10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.

10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.

Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.


10.10 Maintenance declarations and covenants

10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:

  • (a) identify each facility, its location and the approved O&M plan;
  • (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
  • (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
  • (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
  • (e) be registered so that it runs with the land and is disclosed to purchasers.

10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.

10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 15 June each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.

10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.

Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Rajasthan because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 15 June date is set by this Manual to fall before the south-west monsoon (June–September), when most Rajasthan extreme rainfall occurs.


10.11 O&M plans

10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:

  • (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
  • (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
  • (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
  • (d) inspection checklists matching Form 10-7;
  • (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
  • (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
  • (g) safety measures for confined spaces, deep water and public access;
  • (h) access routes and equipment needed (Clause 10.13);
  • (i) an annual cost estimate and who pays it; and
  • (j) the records to be kept, and for how long.

10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.

Commentary. Rajasthan runs its monsoon season through State and district control rooms, which the Disaster Management, Relief and Civil Defence Department ordered to work round the clock from 15 June (2026, as reported), when WRD was also told to inspect and repair the gates of its dams before the monsoon (as reported), and through the gate operations of WRD and of the custodians of the lakes. For the urban drains the orders found are local: Jaipur's corporations have run nala-cleaning drives without a stated date, and in July 2026 the Chief Minister directed that every drain be cleaned (as reported); no order of the LSG Department or UDH setting a statewide deadline for desilting the nalas was found. Several city outfalls are governed by gates: Ana Sagar in Ajmer is held at its full gauge by opening the gates of its escape channel, which floods the colonies along the channel (as reported); the Udaipur lakes spill from one to the next through gated links; and at Kota the river level is set by releases from the Kota Barrage and the dams above it. No operating rule for any lake escape channel, sluice, flap gate or pumping station in a Rajasthan city, linking it to a lake level, a river stage or a rainfall warning, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.


10.12 Inspection frequencies

10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:

Table 10.3 — Minimum owner inspection frequencies

Facility type Routine Pre-monsoon (by 15 June) After a heavy-rainfall event
Retention / infiltration (soakaways, trenches, bioretention, permeable paving) Every 6 months Yes Yes
Surface detention basin or multi-use open space area Every 6 months Yes Yes
Underground or podium detention tank, gravity outlet Every 6 months Yes Yes
Pumped detention, pumps and controls Monthly test run Yes, with full duty test Yes
Flap / tide gate, non-return valve Every 3 months Yes, with seal test Yes
Gross pollutant trap / first-flush device Every 3 months Yes Yes
Private drains and inlets Every 6 months Yes —

A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Rajasthan, the pre-monsoon inspection of sluices, flap gates, non-return valves, lake escape-channel gates and pumped facilities, including the gates on outfalls to lakes, talabs and reservoirs, with the pump duty and gate seal tests, shall be completed by 15 June; these facilities, with their standby generators, shall be certified ready by 20 June, as the normal onset reaches the State (24 June at Jhalawar to 6 July at Bikaner and Pokaran), with every gate on an outfall to a river or lake, and every escape-channel gate, operated through its full travel. Pumps, their standby power and the gates shall then be kept on monsoon standby, with the monthly test run, until 30 September, and at an outfall to the Chambal or another river regulated by a dam or barrage upstream until the river at the governing gauge has fallen below its danger level and the releases have ended, if that is later.

10.12.2 Authority inspections. The Authority shall inspect:

  • (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
  • (b) a random sample of at least 10% of other facilities each year.

10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).

Figure 10.3 — Maintenance cycle and responsibility A one-year strip from January to December with the south-west monsoon (early July to mid-September) shaded, and the onset period from 24 June to 6 July and the withdrawal period from 17 to 28 September shaded more lightly. Lanes show routine inspections, the pre-monsoon inspection and desilting of every facility with the Form 10-7 declaration by 15 June, the readiness of sluices, gates, lake escape channels, pumps and standby generators by 20 June, pumps and gates on standby to 30 September, inspections after heavy rainfall, and Authority inspections. Boxes below show who is responsible: the owner, the ULB and the Authority. Maintenance cycle and responsibility (Clauses 10.10–10.12, 10.14) South-west monsoon Onset Late Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 15 Jun 20 Jun 30 Sep Routine Monthly: pump test run (continues through the standby period) Every 3 months: gates, valves, GPTs Every 6 months: retention, detention, drains Pre-monsoon readiness, standby By 15 Jun: desilting, pump and gate tests, defects corrected. By 20 Jun: gates, escape channels, pumps ready. To 30 Sep: on standby After heavy rain After each day at or above IMD “heavy rainfall”, or a district red alert Annual declaration Form 10-7 Form 10-7 lodged by 15 June: Tier A facilities; pumped, gate and regional facilities anywhere Authority At least every 2 years (every year if flood-sensitive) for sites ≥ 1,000 m² or Cl. 10.6.1(c), (d); 10% random sample of others each year → facility register (Cl. 10.17) Who is responsible Owner — private facility Maintenance declaration, Form 10-6; binds successors in title (Cl. 10.10.1) Layouts and apartments: the association; the developer until it accepts (Cl. 10.10.2) Inspects; lodges Form 10-7 ULB — handed-over public asset Accepted with Form 10-8 (Cl. 10.14) O&M plan in the asset register, funded in the annual budget (Cl. 10.11.2) Developer liable for defects and routine maintenance, ≥ one monsoon to 30 Sep (10.14.2) Authority Inspects and records results in the facility register (Cl. 10.12.2–10.12.3) Enforces: notice, penalty, works in default with cost recovered (Cl. 10.15) Publishes the register (Cl. 10.17) Tick positions are illustrative; only 15 June, 20 June and 30 September are fixed. Normal onset over Rajasthan 24 June (Jhalawar) to 6 July (Bikaner, Pokaran); normal withdrawal 17 September (Pokaran) to 28 September (Jhalawar) (IMD, new normals).

Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 15 June) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the south-west monsoon (June–September); tick positions within the year are illustrative.

Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 15 June deadline is set by this Manual for the onset of the south-west monsoon in the last week of June and the first week of July, and is the day on which the State and district control rooms begin to work round the clock (as reported); no order of the LSG Department or UDH setting a statewide desilting deadline was found. The normal onset is 24 June at Jhalawar, 25–26 June at Udaipur and Kota, 29 June at Jaipur, 1–2 July at Ajmer and Jodhpur and 6 July at Bikaner and Pokaran (IMD, 1961–2019 normals), and large falls have been recorded before it, 412.3 mm at Ajmer on 10 June 2002 (IMD). NDMA (2010) sets 31 March for pre-monsoon desilting nationally; this Manual allows until 15 June so that dry-season work can be finished, and keeps 15 June for the annual declaration. Sluices, gates, lake escape channels, pumps and their standby generators must in addition be certified ready by 20 June, as the onset reaches the south-east. The normal withdrawal runs from 17 September at Pokaran to 28 September at Jhalawar (IMD), so pumps and gates are kept on standby to 30 September (Figure 10.3), and at an outfall to the Chambal or another river regulated by a dam or barrage until the river has fallen below its danger level and the releases have ended, if that is later. October storms do occur, 500.0 mm at Nasirabad on 5 October 1989 and 350.0 mm at Jhalawar on 5 October 1997 (IMD), and the post-event inspections of Table 10.3 cover storms at any time of year.


10.13 Maintenance access

10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.

10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.

10.13.3 Underground facilities. Tanks shall have:

  • (a) an access opening over the inlet, the outlet and each chamber;
  • (b) fixed ladders or steps, and ventilation for confined-space entry;
  • (c) a sump or low point for sediment removal; and
  • (d) headroom sufficient for manual cleaning.

10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.

10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.

Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Rajasthan cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.


10.14 Handover of public assets to the ULB

10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:

  • (a) the as-built certificate (Clause 10.9) has been accepted;
  • (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
  • (c) the land, or an easement over it, has been transferred to the ULB;
  • (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
  • (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.

10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 15 June to 30 September, after handover. The ULB may hold a security deposit for this period.

10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.

10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.

Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Rajasthan drainage show up only in the first SW monsoon.


10.15 Enforcement

10.15.1 Offences. The following are contraventions of this Manual:

  • (a) building without an approved drainage design where one is required;
  • (b) building a facility other than as approved;
  • (c) removing, filling, covering, reducing or changing the use of a facility without approval;
  • (d) failing to maintain a facility, or to submit Form 10-7;
  • (e) a sewage connection to a storm drain;
  • (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
  • (g) obstructing a natural drainage path or major-system flow path; and
  • (h) false or negligent certification.

10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):

Table 10.4 — Graduated enforcement response

Step Action
1 Written notice stating the contravention, the clause breached, the remedy and a compliance period.
2 Stop-work order, or withholding of the completion certificate, for development not yet complete.
3 Penalty under the applicable Act or rules.
4 Works in default by the Authority, with the cost recovered from the owner.
5 Disconnection of the private drain connection to the public system, where this causes no hazard to others.
6 Report of the certifying professional to the registering authority, and suspension from the empanelled list.

10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.

10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.

10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.

Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Model Rajasthan Building Regulations 2025 are made and from the municipal Acts. The graduated steps are set by this Manual. In Rajasthan the courts have become the working regulators of catchments, natural channels, lakes and river corridors. The High Court ordered the catchment of the Ramgarh dam, about 769.20 km² over four tehsils, cleared of construction and encroachment (Abdul Rahman, D.B.C.W.P. 1536/2003, 2 August 2004), and in a suo motu case barred allotments in the catchments of "Johar, Nala, Tank, River, Pond" (S.B.C.W.P. 11153/2011, orders of 23 August 2011 and 29 May 2012); the Supreme Court found the lake "still bone dry" and nothing substantive achieved on the ground, awarded costs and ordered a demolition on catchment land (NIMS University v. State of Rajasthan, 9 November 2017). The High Court has held that master plans cannot disturb rivers, lakes, nalas and their catchments (Gulab Kothari, D.B.C.W.P. 1554/2004, 12 January 2017), that land recorded as gair mumkin nala is a natural channel that may not be diverted or built on even for a public purpose (Ramji Lal Saini, 7 May 2026), and that no wetland or its catchment may be filled, built on or receive untreated sewage while a statewide survey is made (suo motu, 1 June 2026). Udaipur's lakes have a no-construction zone under a notification of 1997, and a project within 200 m of the high flood level of Udai Sagar was held void (as reported); at Ana Sagar the National Green Tribunal ordered structures built in the wetland removed (2023), the Supreme Court refused to stay or modify the order (2023–2025), and demolition began on 12 September 2025 (as reported). On the Jojari the Supreme Court has directed a High Flood Line and ecological buffer for every river system in the State, frozen fresh permissions in the identified river corridors meanwhile and ordered a River Commission or River Rejuvenation Authority (7 August 2026), and has barred construction within 100 m of the river's edge pending demarcation (24 August 2026, as reported). The statutes carry real powers: the Municipality may require a building put up over a drain vested in it without consent to be pulled down (Municipalities Act 2009, s.213(2)), an owner who does not provide rainwater harvesting is liable to a fine of ₹10,000–20,000 and a new building gets no public water connection without the Municipality's certificate (s.238), and the Lakes Development Authority may remove an obstruction in the protected area or the flow area of a lake (Lakes Act 2015, s.6(2), as read from the Bill). No audit by CAG of urban drainage, of AMRUT drainage works or of the lakes in Rajasthan was found; CAG's Rajasthan audits found cover solid waste management in the urban local bodies (Report No. 4 of 2025, as reported) and land revenue. This shows that a rule without routine enforcement does little, and that where the State has not drawn a line the courts have. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.


10.16 Monitoring and post-event review

10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.

10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:

  • (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
  • (b) the level of the receiving river (the Chambal at Kota or Dholpur, the Banas, the Luni or another river) at the nearest CWC or WRD gauge, or of the receiving lake or reservoir (in Udaipur, Pichola, Fateh Sagar or Udai Sagar; in Ajmer, Ana Sagar; in Jodhpur, Kailana or Takhat Sagar), and, where it is gauged, at the outfall, each on a named datum, with lake gauge readings in feet converted to metres; for a catchment with no outfall, the peak level in the terminal basin or depression and the time it took to empty; the state of every sluice, flap gate, escape-channel gate, interception structure and pumping station on the outfall and on the drain upstream of it, with the hours each pump ran and any loss of power; and the gate openings and releases of any lake, dam or barrage that sets the receiving level, such as the Kota Barrage or the escape-channel gates of Ana Sagar;
  • (c) flooded locations, depths and durations, with flood marks surveyed where possible;
  • (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
  • (e) recommended actions.

10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), RSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.

10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.

Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Rajasthan's urban floods have been examined by the courts and the press rather than by technical reviews. On 18–20 July 1981 Jaipur city recorded 82 cm of rain in three days and 35 cm in the 24 hours of 19 July, a low having formed over the region and stagnated, and the city was cut off (Gupta and Jindal 1987); IMD's station record for the day is 326.0 mm, against a 50-year 24-hour depth on the CWC plate of about 200 mm. On 19–21 August 2006 about 577 mm fell in three days around Kawas in Barmer district, more than twice the annual normal, and parts of Kawas were reported still under water months later; the reported deaths range from about 50 to more than 300 (as reported), and in the same week Udaipur's lakes overflowed into the colonies below them (as reported). In September 2019 the Chambal reached its high flood level of 248.68 m at Kota City while the Kota Barrage released through 18 or 19 of its gates (CWC; as reported). In July 2022 Jodhpur received about 119 mm in 24 hours, most of it in about five hours, reported as its highest July rain since 1943, and more than 30 colonies were flooded (as reported). On the night of 31 July 2024 three members of one family died in a flooded basement in Jaipur's Vishwakarma Industrial Area (as reported), and in September 2024 and July 2025 the opening of the Ana Sagar escape channel waterlogged colonies in Ajmer (as reported). No technical review of any of these events was found, and no record of flood extents, depths or durations kept by any Municipal Corporation or development authority was found. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.


10.17 Data publication

10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:

  • (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
  • (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
  • (c) the register of variances and waivers (Clause 1.10);
  • (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
  • (e) enforcement actions (Clause 10.15.5); and
  • (f) event reports and post-event reviews (Clause 10.16).

10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.

10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.

10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.

Commentary. Transparency is a design criterion in its own right here. Some of Rajasthan's drainage records are public: the Building Regulations 2025 (in a third-party copy) and the JDA 2020 regulations in their Gazette text, the judgments of the High Court and the Supreme Court on Ramgarh, natural channels, wetlands and the Jojari, the EIA chapter of the Dravyavati project, RUIDP's Circular No. 8 and ADB's project documents, CGWB's groundwater assessments, and the river bulletins of CWC. Much else could not be found in the public domain: the Gazette publication of the Building Regulations 2025 by each city and authority, and the full text of their environmental schedule; the design discharge, rainfall and method of the Dravyavati channel; the return period and model of JDA's 2025 drainage upgrade; the initial environmental examination of the Jodhpur storm water drains; an inventory of the sluices, flap gates, escape channels and pumping stations of any city, with their capacities and operating rules; the operating rules of the Ana Sagar escape channel and of the gates of the Udaipur lakes; the level above mean sea level of the gauge zeros of the Udaipur and Ajmer lakes; any notification of lake boundaries or protected areas under the Lakes Act 2015; an urban flood plan of RSDMA; the list of wetlands notified under the Wetlands Rules 2017; any audit by CAG of urban drainage; and the full text of the Supreme Court's order of 24 August 2026 on the Jojari. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.


10.18 Review of this chapter

10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.


References (chapter)

Annexes and forms

Annex / Form Content
10A Compliance calculator and user guide
10B GIS data specification and attribute schema
10C Maintenance access dimensions
10D Model O&M plans by facility type
10E Empanelment criteria for Stormwater Design Professionals and reviewers
Form 10-1 Drainage Report Checklist
Form 10-2 Compliance Calculator Summary
Form 10-3 Professional Design Certificate
Form 10-4 Hold-Point Inspection Record
Form 10-5 As-built Certificate
Form 10-6 Maintenance Declaration
Form 10-7 Annual Maintenance Declaration and Inspection Report
Form 10-8 Asset Handover Certificate
Form 2-1 Design Rainfall Sheet (Chapter 2)