Draft v1.0 prepared by NEER. Not adopted by the Government of NCT of Delhi, DDA or any local body, and has no legal force. About this draft

Annexes to Chapter 11Basin and City Stormwater Master Plans

These annexes support Chapter 11. They give a terms of reference template for a Basin Stormwater Master Plan (BSMP), the layout of the basin list and boundary layer, the layout and method for depth–damage curves, the standard for publishing BSMP data and models, and the annual implementation report form. Annexes 11B and 11C need data that are not yet available; they say so and give the rule to use in the meantime. The template and the form are a model and a draft form for consideration by a competent authority, and are not in force.


Annex 11A — BSMP terms of reference template

Supports Clauses 11.1 to 11.12 of Chapter 11.

Model text for consideration by a competent authority. Not in force. The Lead Authority adapts this template for each basin. Items in "[ ]" are for the Lead Authority to complete. Clause references are to this Manual, which the consultant shall follow in full.

11A.1 Background and purpose

  1. The [Lead Authority] intends to prepare a Basin Stormwater Master Plan for the [name] basin under Chapter 11 of the Delhi Stormwater Design Manual.
  2. The BSMP shall (Clause 11.1.2):
    • (a) map flood hazard for the basin under existing and future conditions;
    • (b) set the level of service for each part of the drainage system;
    • (c) identify, cost and rank the works, storage and land needed to reach that level of service;
    • (d) identify land to be reserved in the statutory land-use plan for regional storage, johad and tank restoration and major flow paths;
    • (e) set the basin inputs for site design: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4; and
    • (f) recommend catchments for notification as flood-sensitive.
  3. The BSMP may make the site criteria of Chapters 4 to 8 stricter for the basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6 (Clause 11.1.3).

11A.2 Client, partners and study area

  1. Client: [Lead Authority] (Clause 11.4.1).
  2. Partners: I&FC, wherever the basin includes a river, canal or tank under its control, and [other local bodies, DDA or UDD, DDMA] (Clause 11.4.1).
  3. Study area: the whole of the [name] basin, draining to [outfall], as delineated under Clause 11.3, including the parts outside the client's limits (Clause 11.3.1). The provisional boundary is in [Annex 11B / attached map]. The consultant shall confirm it in Task 2.
  4. Links to other basins: [for example the Najafgarh drain corridor]. Diversions between basins by canal, drain or surplus course shall be mapped and represented in the model (Clause 11.3.2).

11A.3 Team

  1. The study shall be led by an engineer empanelled as a Stormwater Design Professional with the basin modelling endorsement of Annex 10E (Clause 11.4.3).
  2. The team shall include at least: [a hydrologist; a hydraulic modeller; a coastal or tidal specialist where the basin has a tidal outfall; a GIS and survey lead; a planner; a cost engineer; a community engagement lead]. The client sets the minimum qualifications and experience of each.

11A.4 Tasks

Task 1 — Inception. Review existing studies, data and projects in the basin. Prepare a data inventory against Table 11.1, a gap list, a survey plan, a consultation plan, and the work programme. Deliver the inception report.

Task 2 — Data and surveys. Assemble, survey where missing, and quality-check every item of Table 11.1 (Clause 11.5.1):

  • (a) terrain: DEM from LiDAR or photogrammetry with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum, with the accuracy test reported;
  • (b) drain network: every public drain, culvert and outfall, with invert levels, sizes, condition and silt depth; private drains above 600 mm;
  • (c) waterbodies: every tank, johad, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels and encroachment, in the fields of Annex 7A;
  • (d) rivers and canals: cross-sections at no more than 200 m spacing and at every structure;
  • (e) outfalls and the Yamuna: outfall invert levels, on a named datum, against the warning, danger and evacuation levels of the Yamuna at the Old Railway Bridge and its recorded peaks; regulators, flap gates and pumping stations on the outfalls, in the Trans-Yamuna bunds and at underpasses, with their capacities and operating rules; embankment crest levels; release records of Hathnikund barrage; and the inflow to the Najafgarh drain from Haryana;
  • (f) rainfall and water levels: all available records (IMD, including the Safdarjung and Palam observatories, the Lodi Road, Ridge and Ayanagar stations and the automatic weather stations and rain gauges across the city, such as those at Pragati Maidan, Mayur Vihar, Pitampura, Pusa, Delhi University, Tughlakabad and Jharoda Kalan; any rain and water-level gauges kept by I&FC, PWD and the local bodies; and the Yamuna gauge at the Old Railway Bridge), including the September 1978 (Yamuna), July 2023 (Safdarjung rainfall and the Yamuna), June 2024 (Safdarjung), July 2024 (Old Rajinder Nagar and Pragati Maidan) and September 2025 (Yamuna) events;
  • (g) flood evidence: surveyed flood marks and mapped extents of past events, including public reports, photographs and residents' records;
  • (h) land use: existing land use and imperviousness; future land use from the statutory master plan;
  • (i) soils and groundwater: HSG map (Annex 3A or Clause 3.7.2), seasonal high groundwater, aquifer and recharge zones; and
  • (j) sewer interaction: known cross-connections, dry-weather flow in drains, solid-waste hotspots.

Confirm the basin boundary and the inter-basin diversions (Clause 11.3.2). Deliver the data report and the data in the formats of Annex 11D.

Task 3 — Model build. Build a coupled 1D–2D hydraulic model of the minor system, the major (overland) system, rivers, canals and tanks, and the outfalls (Clause 11.7.1; Figure 11.2). Use the methods of Chapter 3 and the tidal and river boundaries of Chapter 5. Run the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs, with areal reduction under Clause 2.7.3 (Clause 11.7.2). Where the basin has tank cascades, run continuous simulation under Clause 3.13 with the full IMD gridded daily record where available, and at least 30 years, disaggregated by the temporal patterns of Annex 2D. The two-step approach of Clause 3.13.5 may be used: starting tank levels and antecedent conditions from the continuous run are passed to the design-storm runs (Clause 11.7.3).

Task 4 — Calibration and validation. Calibrate and validate the model under Clause 3.15, using at least two of the September 1978 (Yamuna), July 2023 (Safdarjung rainfall and the Yamuna), June 2024 (Safdarjung), July 2024 (Old Rajinder Nagar and Pragati Maidan) and September 2025 (Yamuna) events where data exist (Clause 11.7.5). Report the performance measures of Clause 3.15.4 and the reasonableness check of Clause 3.15.6.

Task 5 — Scenarios and hazard maps. Model the scenarios of Clause 11.7.4: (a) existing; (b) future, uncontrolled; (c) future, controlled; (d) future, with plan; and (e) climate, applied to (a) and (d). Produce flood hazard maps of extent, depth, velocity and hazard class (H1–H6, Chapter 6) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan (Clause 11.8.4(a)).

Task 6 — Level-of-service assessment. Compare scenarios (a), (c) and (d) with the levels of service of Table 11.2 and any stricter levels the client adopts (Clause 11.6.1). Map every shortfall.

Task 7 — Options. Develop options in the order of Clause 11.8.1: protect and restore storage; regional retention and detention, sited by modelling; conveyance; outfall works; property-level protection; non-structural measures. Assess each option for the criteria of Clause 11.8.2: reduction in flood risk (buildings and people flooded, and expected annual damage using Annex 11C); capital and 30-year maintenance cost; land required; effect on groundwater recharge where the water table is deep, and waterlogging where it is shallow; effect on downstream basins and the Najafgarh drain; and who benefits.

Task 8 — Basin inputs for site design. Where scenario (c) does not meet the level of service, propose basin release rates (m³/s/ha) by AEP and sub-catchment (Clause 11.8.3). Recommend catchments for notification as flood-sensitive, with the evidence of Clause 4.5.4.1. Identify regional facility sites, with storage volumes, land needs and the sites they serve, and compute the fee-in-lieu unit rate, including land, construction and 10 years of maintenance (Clauses 4.13.3, 11.8.4(c), (d)).

Task 9 — Capital Improvement Programme. Rank the works by risk reduction per rupee, with cost, phasing and responsible agency (Clause 11.8.4(e)).

Task 10 — Maintenance and monitoring. Prepare the pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Clause 11.8.4(f); Chapters 7 and 10). Specify monitoring needs: new rain gauges, level sensors and flood-mark survey points (Clause 11.8.4(g); Clause 10.16.1).

Task 11 — Land-use integration. Prepare the material for the statutory land-use plan required by Clause 11.9.1: sites to be reserved; the 1% AEP hazard map with the Chapter 7 setbacks; land in hazard classes H5–H6 in the 1% AEP event; and open space locations that can form part of flow paths or regional storage.

Task 12 — Consultation. Publish the draft BSMP for public comment for at least 60 days, with public meetings in each affected local body (Clause 11.10.1). Keep a log of comments and responses.

Task 13 — Final BSMP and publication. Revise the BSMP after consultation. Prepare the package for approval by the State Stormwater Technical Committee, including the model for review (Clause 11.11.1). Publish the data, models, maps and CIP under Annex 11D (Clause 11.10.2).

11A.5 Deliverables

Table 11A.1 — Deliverables

No. Deliverable Task Due (months from start)
D1 Inception report, data inventory and survey plan 1 [ ]
D2 Data report and data sets (Annex 11D) 2 [ ]
D3 Model build report and model files 3 [ ]
D4 Calibration and validation report 4 [ ]
D5 Scenario results, hazard maps and level-of-service assessment 5, 6 [ ]
D6 Options report, with basin inputs for site design 7, 8 [ ]
D7 Draft BSMP with draft CIP, for consultation 9–12 [ ]
D8 Final BSMP, consultation log, approval package and open-data release 13 [ ]

11A.6 Ownership and publication

All data, models, maps and reports produced under these terms are owned by the Lead Authority and shall be published under Annex 11D. The consultant shall not use any software licence, data licence or format that prevents publication, or that prevents a third party from re-running the model with the stated software version.


Annex 11B — Basin lists and boundaries for Tier A bodies

Supports Clauses 11.3 and 11.4 of Chapter 11.

To be prepared. This annex will contain the list of basins and sub-basins of the NCT of Delhi, with a GIS layer of basin boundaries delineated under Clause 11.3.2. It needs a DEM of the accuracy of Clause 11.5.1; the drain network of every drain-owning agency (the 3,740 km of major storm drains recorded by the Delhi High Court in 2024, the 201 drains of the 1976 plan with the 44 now untraceable, and the 22 drains that outfall to the Yamuna); the regulators, flap gates and pumping stations on the outfalls and in the Trans-Yamuna bunds, with their capacities; the water bodies in the inventory of the Wetlands Authority of Delhi; DDA's demarcation of the Yamuna floodplain; and the basin and sub-basin maps of the IIT Delhi plan of 2018 and of the basin plans procured by PWD (other likely sources: Survey of India, GSDL, CWC and CGWB). The area of the Najafgarh basin (977.26 km² in IIT Delhi 2018, 918 km² in the 2025 plan as reported) shall be settled in the first BSMP. Until the annex is published, the three basins named in Clause 11.3.3 apply, and the interim arrangements of Clause 11.12 apply in every basin without an approved BSMP.

Table 11B.1 — Basins named in Clause 11.3.3 (provisional)

Tier A body or area Basin Note from Chapter 11
Every drain-owning agency with drains in the basin (Clause 11.4.1) Najafgarh Najafgarh drain (Sahibi) from Dhansa via the Kakraula regulator to the Yamuna below Wazirabad barrage, with the Supplementary drain; 123 natural drains; 977.26 km² (IIT Delhi 2018) or 918 km² (2025 plan, as reported); inflow from Haryana and the Yamuna level as boundaries
Every drain-owning agency with drains in the basin (Clause 11.4.1) Barapullah Barapullah drain and the other west-bank drains to the Yamuna through regulators such as that of drain No. 12; 44 natural drains; 374.81 km² (376.27 km² with the Aruna Nagar and Old Chanderwal basins); regulator-closed case a design case
Every drain-owning agency with drains in the basin, east of the Yamuna (Clause 11.4.1) Trans-Yamuna Behind the Shahdara Marginal and Left Marginal bunds; 34 natural drains; 196.93 km²; Relief Drain the only gravity outfall, the rest pumped; outfall-closed case and pump capacity a design case

Table 11B.2 — Attributes of the basin boundary layer (layout)

Field Type Content
BASIN_ID Text Basin identifier
NAME_EN, NAME_HI Text Basin name in English and Hindi
TIER_A Text Tier A body or bodies in the basin
OUTFALL Text Outfall to the sea, river or major waterbody (Clause 11.2)
AREA_KM2 Real Basin area, km²
LEAD_AUTH Text Lead Authority (Clause 11.4.1)
PARTNERS Text Partners, including I&FC where it applies
LINKS Text Diversions to and from other basins (Clause 11.3.2)
BSMP_STAT Text None / in preparation / draft published / approved
BSMP_DATE Date Date of approval of the current BSMP
REVIEW_DUE Date Date of the next review (Clause 11.11.2)

Annex 11C — Depth–damage curves for Delhi building types

Supports Clause 11.8.2 of Chapter 11.

To be prepared. This annex will contain depth–damage curves for the main building types of Delhi, for structure and contents, for use in computing expected annual damage under Clause 11.8.2. It needs a building-type classification and building stock data (Census housing tables, property-tax records, Lead Authority GIS), damage surveys and claims from the September 1978 (Yamuna), July 2023 (Safdarjung rainfall and the Yamuna), June 2024 (Safdarjung), July 2024 (Old Rajinder Nagar and Pragati Maidan) and September 2025 (Yamuna) floods (Revenue Department and DDMA damage assessments, insurers), and replacement costs (PWD schedules of rates). Until it is published, each BSMP shall state the depth–damage relations it uses and their source, and shall report the reduction in buildings and people flooded for every option (Clause 11.8.2), which does not depend on the curves.

Table 11C.1 — Depth–damage curve (layout, one table per building type)

Depth of water above floor level (m) 0 0.25 0.5 1.0 1.5 2.0 3.0
Structure damage (% of replacement cost) ______ ______ ______ ______ ______ ______ ______
Contents damage (% of contents value) ______ ______ ______ ______ ______ ______ ______
Building type, source and year of costs ______

11C.1 Use in option assessment

Expected annual damage (EAD) is computed for each scenario from the damages at the modelled AEPs. With damages D_1, D_2, … at annual exceedance probabilities P_1 > P_2 > …, using at least the 50%, 10%, 1% and 0.2% AEP results of Clause 11.7.2:

EAD ≈ Σ ½ × (D_i + D_(i+1)) × (P_i − P_(i+1))

The reduction in EAD between scenario (c) and scenario (d), or between options, is the risk-reduction benefit used to rank works per rupee (Clause 11.8.4(e)). The BSMP shall state how damages beyond the 0.2% AEP and below the 50% AEP were treated.


Annex 11D — BSMP data and model publication standard

Supports Clauses 11.5.1 and 11.10 of Chapter 11, and Clause 10.17 of Chapter 10.

11D.1 What is published, and when

Table 11D.1 — Items to be published

Item Format At draft (Clause 11.10.1) At approval (Clause 11.10.2)
BSMP report, with the level-of-service assessment and options Searchable PDF Yes Yes, final
Flood hazard maps: extent, depth, velocity, hazard class, for each AEP and scenario of Clause 11.8.4(a) GeoTIFF rasters; extents also as GeoPackage polygons Yes Yes
Capital Improvement Programme CSV and PDF Draft Yes
Basin release rates, recommended flood-sensitive catchments, regional facility sites, fee-in-lieu unit rate GeoPackage and CSV Yes Yes
Data of Table 11.1 (terrain, drains, waterbodies, cross-sections, Yamuna levels and outfall structures, rainfall and levels, flood evidence, land use, soils and groundwater, sewer interaction) GeoTIFF (terrain); GeoPackage (features); CSV (tables and time series) Summary Yes, except security-sensitive asset details
Model files: native, runnable, with all boundary-condition, rainfall and control files, the software name and version, and a run log Native format, zipped No Yes
Calibration and validation report Searchable PDF Yes Yes
Consultation log of comments and responses PDF or CSV — Yes

11D.2 Formats and references

  • (a) Raster data shall be GeoTIFF, preferably cloud-optimised, with the cell size stated. Vector data shall be GeoPackage. Tables and time series shall be CSV in UTF-8, with a header row and units in the column names.
  • (b) Horizontal and vertical references shall be as in Annex 10B.1(b) and (c). The vertical datum and its relationship to the Chapter 5 river and drain datums of the Yamuna gauge at the Old Railway Bridge and of I&FC's drain, regulator and embankment levels shall be stated in every data set that carries levels.
  • (c) Times shall be in Indian Standard Time, written as ISO 8601 (yyyy-mm-ddThh:mm+05:30). Units shall be SI.
  • (d) Hazard map files shall be named <basin>_<scenario>_<AEP>_<variable>.tif, where scenario is a to e of Clause 11.7.4, AEP is written as 50, 10, 1 or 0p2, and variable is depth, velocity, hazard or extent; for example barapullah_d_1_depth.tif.
  • (e) Waterbody data shall use the fields of Annex 7A. Facility and outfall data shall use the fields of Annex 10B.

11D.3 Metadata

Every published data set shall carry: title; description; Lead Authority; source and method; date of capture; accuracy (for the DEM, the measured vertical RMSE); horizontal and vertical reference; scenario and AEP, where relevant; BSMP version; licence; and a contact.

11D.4 Withholding and personal data

  • (a) Security-sensitive details of critical assets may be withheld, with the reason recorded and published (Clauses 10.17.3, 11.10.2). The flood hazard maps and the model shall still be published; only the sensitive attributes are removed.
  • (b) Personal data shall not be published (Clause 10.17.3). Flood evidence collected from residents shall be published without names or contact details unless the person consents.

11D.5 Licence, viewer and versions

  • (a) Published data and models shall be released under the Government Open Data Licence – India or an equivalent open licence (Clause 10.17.4).
  • (b) The hazard maps, regional facility sites and CIP shall also be shown on a public map viewer (Clause 11.10.2).
  • (c) Each approved BSMP shall carry a version number and date. Superseded versions shall stay available, marked as superseded, so that designs approved under them can be checked.
  • (d) The published model package shall allow a third party with the stated software version to reproduce the published results. Designers may use its boundary conditions for site designs in the basin (Clause 11.10, Commentary).

Form 11-1 — Annual implementation report

Supports Clause 11.11.3 of Chapter 11, with Clauses 4.5.6.3 and 4.13.4 of Chapter 4.

Draft form — Delhi Stormwater Design Manual, Draft v1.0. Published by the Lead Authority for each basin with an approved BSMP before each south-west monsoon, by 31 May (Clause 11.11.3).

Table 11F.1 — Form 11-1, Section A: Basin and plan

No. Field Entry
A1 Basin; Lead Authority; partners ______
A2 BSMP version and date of approval ______
A3 Reporting year (1 June to 31 May) ______
A4 Date of publication (by 31 May) and web address ______

Table 11F.2 — Form 11-1, Section B: CIP progress

CIP rank Work Agency Cost in CIP (₹) Spent this year (₹) Spent to date (₹) Status Expected completion
______ ______ ______ ______ ______ ______ ______ ______
______ ______ ______ ______ ______ ______ ______ ______

Table 11F.3 — Form 11-1, Section C: Fee-in-lieu ledger (Clauses 4.5.6.3(c) and 4.13.4)

Regional facility or tank Volume credited to sites (m³) Volume delivered (m³) Fees received (₹) Fees spent (₹) Fees held, with year received
______ ______ ______ ______ ______ ______
Basin total: volume owed and delivered ______ ______ ______ ______ ______

Table 11F.4 — Form 11-1, Section D: Maintenance completed (Clause 11.8.4(f))

No. Item Planned Done Date completed
D1 Desilting of drains and canals (length, km; volume, m³) ______ ______ ______
D2 Tank and johad desilting and restoration (tanks, number; storage restored, m³) ______ ______ ______
D3 Gate tests (number of gates) ______ ______ ______
D4 Pump station duty tests (number of stations) ______ ______ ______
D5 Tank operating rules reviewed with the custodian (number) ______ ______ ______
D6 Monitoring added: rain gauges, level sensors, flood-mark points (Clause 11.8.4(g)) ______ ______ ______

Table 11F.5 — Form 11-1, Section E: Flooding against the levels of service

Event (dates) Rainfall compared with the design depths (Clause 10.16.2(a)) Level-of-service element (Table 11.2) Location Met (yes / no) Event report reference (Clause 10.16.2)
______ ______ ______ ______ ______ ______

Table 11F.6 — Form 11-1, Section F: Review triggers and sign-off

No. Field Entry
F1 Event exceeding the 1% AEP design depth in the basin this year (yes / no). If yes, review due within 2 years (Clause 11.11.2) ______
F2 Statutory land-use plan revised this year (yes / no) (Clause 11.11.2) ______
F3 Next 10-year review due (date) ______
F4 Officer of the Lead Authority: name, designation, signature, date ______