Draft v1.0 prepared by NEER. Not adopted by the Government of NCT of Delhi, DDA or any local body, and has no legal force. About this draft

Chapter 1Policy, Applicability and Adoption


1.1 Purpose and objectives

1.1.1 This Manual sets the minimum standards for the planning, design, construction, operation and maintenance of stormwater systems in Delhi. It applies to private development and to public works, as set out in Clause 1.5.

1.1.2 The Manual has the following objectives:

  • (a) to make stormwater management a condition of development approval, so that new development and redevelopment do not increase flood peaks or runoff volumes downstream;
  • (b) to retain frequent rainfall on site, so that groundwater recharge is sustained and pollutant loads are reduced;
  • (c) to size storage for the long-duration south-west monsoon storms of July–September, which fall on ground and water tables raised by weeks of rain and often on a Yamuna already in flood, as well as for short-duration intensities;
  • (d) to design outfalls for the stage of the Yamuna, which closes the regulators on the drains that outfall to it and leaves the Trans-Yamuna basin to be drained by pumping, and the levels of the Najafgarh drain, the Supplementary drain and the other trunk drains into which local drains discharge, including the case where the outfall is closed;
  • (e) to protect tanks (johads), marshes, rivers, supply channels and surplus courses as part of the drainage system;
  • (f) to give every element of the drainage network a safe overland path for the 1% AEP (100-yr) storm;
  • (g) to make design inputs, approvals and facility records public, so that designs can be checked and repeated; and
  • (h) to make sure that facilities, once built, are maintained and remain effective.

1.1.3 This Manual does not replace the rainwater harvesting (RWH) mandate, the building bye-laws made by the Delhi Development Authority under section 57, read with section 13, of the Delhi Development Act, 1957 (the Unified Building Bye-Laws for Delhi 2016), or the statutes on waterbodies. It adds runoff control requirements to them (Clause 1.8).

Commentary. Delhi's floods come from three sources, often together. The first is the Yamuna. The river reached 207.49 m at the Old Railway Bridge on 6 September 1978, a record that stood until 13 July 2023, when it peaked at 208.66 m, more than 3 m above the danger level of 205.33 m (as reported). In 2023 five of the 32 gates of the ITO barrage were jammed by silt, and on the evening of 13 July the regulator of drain No. 12 near the WHO building at ITO gave way: river water flowed back up the drain into ITO, Rajghat and the Ring Road, and reached the approach to the Supreme Court (as reported). The river rose again in September 2025, crossing the danger level on 2 September and peaking at 207.48 m on 4 September, and about 10,000 people were displaced (as reported). The second is the short, intense storm on a city whose drains were never designed for one. Safdarjung recorded 228.1 mm in the 24 hours to 08:30 on 28 June 2024, the second-highest June day since 1901, most of it between 03:00 and 06:00 (IMD, 2024); basements in South Delhi and Defence Colony filled, "upto 10 feet" in the pleadings before the High Court. On 31 July 2024 the Pragati Maidan station recorded 112.5 mm in one hour (as reported). The third is the failure of a building against a street that ponds: on 27 July 2024 three students drowned in the basement library of a coaching centre in Old Rajinder Nagar during a moderate fall of about 31.5 mm in three hours, when the water in the road stood at the same level as the water in the basement (as reported). The 153 mm that fell in the 24 hours to 08:30 on 9 July 2023, the highest July day since 1982, came four days before the river peaked (as reported).

Missing design and divided ownership make all three worse. The city's drainage plan of 1976 listed 201 drains, of which I&FC now lists 44 as untraceable (I&FC). A Drainage Master Plan prepared by IIT Delhi for I&FC was delivered in July 2018 and, the High Court found in 2024, "was not acted upon by GNCTD"; the Court also recorded that no major modelling or remodelling of drains had been done since 1995 (Delhi High Court, 8 April 2024). The 3,740 km of major storm drains are held by seven agencies, and one drain from India Gate to the Yamuna passes through six jurisdictions of four authorities, so that "a consistent slope/level of the drain is not maintained" (Delhi High Court, 8 April 2024). The Delhi Traffic Police listed 330 waterlogging points before 2018 (IIT Delhi, 2018). No published Delhi document sets a design storm that has been approved for drains; the only one is the 2- and 5-year 15-minute storm of the 2018 plan. Objectives (b) to (e) address the storage, outfall and building-level failures, which a drain-sizing manual alone cannot fix.

No national instrument requires on-site detention. CPHEEO (2019) is advisory and describes peak control only as typical practice. NDMA (2010) says detention and retention "will" be included but gives no sizing rule. MBBL 2016 and the Unified Building Bye-Laws for Delhi 2016 mandate RWH only. Objective (a) is therefore the main new step this Manual takes.


1.2 Stormwater management hierarchy

1.2.1 Every development to which Chapter 4 applies shall consider stormwater measures in the following order. A designer shall not use a lower measure in place of a higher one that is practicable on the site.

  1. Preserve — keep or restore natural drainage features, tanks, wetlands, permeable soils, trees and overland flow paths (Chapter 7).
  2. Retain — hold the runoff from the retention depth of Annex 2E on site, by infiltration, reuse or evapotranspiration (Chapters 4 and 8).
  3. Detain — store larger storms temporarily and release them at or below the rates in Chapter 4, checked against downstream and tailwater conditions (Chapters 4 and 5).
  4. Convey — carry the remaining flow safely in the minor system, and the 1% AEP flow in the major system (Chapters 6 and 9).

1.2.2 Maintenance underlies all four measures. A measure that cannot be maintained by its owner under Chapter 10 shall not be credited.

1.2.3 Credits from higher measures reduce the requirements of lower ones. Preserved areas and retained volume reduce detention storage as set out in Chapter 4.

Figure 1.1 — Stormwater management hierarchy Four stacked bars, widest at top: Preserve, Retain, Detain, Convey, with a Maintain bar underneath spanning all. A downward arrow shows the order of consideration; an upward arrow shows that credits from higher measures reduce lower ones. Order of consideration Credits reduce lower measures 1 PRESERVE Chapter 7 Keep tanks, wetlands, marshes, permeable soils, trees and flow paths 2 RETAIN Chapters 4, 8 Hold the Annex 2E depth on site: infiltrate, reuse, evaporate 3 DETAIN Chapters 4, 5 Store larger storms; release below pre-development peaks 4 CONVEY Chapters 6, 9 Minor system, plus a 1% AEP overland path MAINTAIN — underlies every measure Chapter 10 A measure that its owner cannot maintain earns no credit (Clause 1.2.2) Use a lower measure only for what the measures above it cannot practicably achieve (Clause 1.2.1).

Figure 1.1 — Stormwater management hierarchy: preserve, retain, detain, convey, with maintenance underlying each measure. Original drawing for this Manual, adapted from Mid-America Regional Council / Kansas City Metro Chapter APWA, "Layers of Stormwater Management", APWA 5600 Manual Factsheet, 2025 (concept).

Commentary. The order follows the "layers" of Kansas City Metro APWA Section 5600, Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet, 2025). The same logic is behind Georgia's runoff-reduction standard and CSE's "attenuate and infiltrate first" principle (CSE, 2023). For Delhi, the top layer has a particular meaning. Much of the city's flood storage sits in the Yamuna floodplain (the khadar), which the National Green Tribunal ordered kept free of construction up to the line of the 1-in-25-year flood (NGT, 2015) and which MPD-2047 makes a "no construction zone" where it is the active floodplain; in the Najafgarh jheel depression in the south-west, into which the Sahibi drains from Haryana; in the city's ponds, johads, hauz and baolis, of which the Wetlands Authority of Delhi holds an inventory of 1,367 (1,045 listed and 322 found on satellite imagery), with only 674 confirmed on the ground by September 2024 and none yet notified under the Wetlands Rules 2017 (DPCC, 2024); and in the parks that MPD-2047 asks local bodies to earmark as "flood sinks". The Ridge is the city's main recharge zone rather than a store. MPD-2047 lists the river and its floodplain, all natural drains, marshes and wetlands and water bodies of 1 ha and more as Environmentally Sensitive Areas, requires a "minimum mandatory buffer" along natural drains and water bodies, and the NGT has forbidden the covering of any drain in Delhi (NGT, 2015). Losing that storage cannot be offset economically by pipes and pumps.


1.3.1 Notification. This Manual shall be given statutory effect by the Government of Delhi through:

  • (a) an amendment to the Unified Building Bye-Laws for Delhi 2016 that makes compliance with this Manual a condition of planning permission, building permit, layout approval and completion certificate, for development to which Clause 1.5 applies; and
  • (b) bye-laws or standing orders of each urban local body (ULB), adopting the Manual for works executed or approved by that ULB, including the ULB's own drains and roads.

1.3.2 Higher State standards. The design return periods and performance criteria of this Manual exceed the national advisory minimums of the CPHEEO Manual on Storm Water Drainage Systems (2019). The State shall constitute, by notification, a high-powered committee (the State Stormwater Technical Committee, Clause 1.9) to adopt these higher standards. This is the route that CPHEEO (2019) provides for higher return periods.

1.3.3 Precedence. Within its scope, this Manual governs where it is stricter than CPHEEO (2019), IRC:SP:42-2014, IRC:SP:50-2013 or any departmental standard. Where a statute or statutory rule sets a stricter requirement (for example a waterbody setback), the statute governs.

1.3.4 Design-practice standard for public works. Departments and ULBs that procure drainage, road or waterbody works shall require compliance with this Manual in detailed project reports (DPRs) and contracts, from the dates in Clause 1.11.

Commentary. Delhi has one set of building rules for the whole NCT. The Unified Building Bye-Laws for Delhi 2016 (UBBL) were made by DDA "with the previous approval of the Central Government" under section 57, read with section 13, of the Delhi Development Act, 1957, by notification S.O. 1191(E) of 22 March 2016, replacing the Building Bye-Laws 1983; they were amended several times up to S.O. 668(E) of 12 February 2020, and amendments after that date were not checked for this Manual [TBC]. They apply in the area of DDA "and concerned local bodies", uniformly, and the Sanctioning Authorities are DDA, NDMC, the municipal corporations (now MCD) and the Delhi Cantonment Board (bye-laws 1.1 and 1.4.10). Above them sits the Master Plan for Delhi with the perspective for 2047 (MPD-2047), approved by the Central Government under section 11-A of the Act and notified by S.O. 4597(E) of 20 August 2026, which replaced MPD-2021. The UBBL set no design storm, return period, runoff coefficient, release rate or detention volume, no "zero run-off" rule, and no setback in metres from a drain or water body. They make recharge-type rainwater harvesting mandatory on every plot of more than 105 m², sized to capture at least the "peak-month rainfall" runoff (Table 10.1 and Annexure X); require only that "surface drainage does not enter the basement" (bye-law 7.4.4), with no bar on basements in low-lying or flood-prone areas; and, for projects of 5,000 m² of built-up area and more, require the natural drainage to be maintained, allow "Check dams, bio-swales, landscape, and other sustainable urban drainage systems (SUDS)", and require at least 20% of the required open space to be pervious. In Delhi the route of Clause 1.3.1(a) therefore runs through DDA and MoHUA, which make the UBBL, and not through GNCTD alone: an amendment would be made by DDA with the previous approval of the Central Government, and GNCTD, which owns most of the drains through PWD and I&FC, would propose it and would constitute the State Stormwater Technical Committee. This Manual is a draft; neither DDA, MoHUA nor GNCTD has adopted it. MoHUA told Parliament in July 2026 that urban flooding "falls under the purview of the State Governments and the ULBs" and listed the CPHEEO manual among "advisory guidelines" (Lok Sabha AU1847). The State therefore needs no central approval to adopt higher standards. CPHEEO's Note 2 to Table 4.1 (§4.4.1.4) allows "a high powered committee constituted by State/UT Government through a notification" to adopt higher return periods. Clause 1.3.2 uses that route so that higher standards are on record for centrally funded schemes.


1.4 Definitions

1.4.1 The following terms apply throughout this Manual. Chapter-specific terms are defined in each chapter (for example Clause 2.2).

Term Meaning in this Manual
Approving Authority (the Authority) The body that grants planning permission, building permit or layout approval for a development, or that sanctions a public work: the Sanctioning Authority for the site under bye-law 1.4.10 of the Unified Building Bye-Laws for Delhi 2016: the Municipal Corporation of Delhi (MCD), or, in their areas, the New Delhi Municipal Council (NDMC), the Delhi Cantonment Board (DCB) or the Delhi Development Authority (DDA), which are bodies of the Union, or a department for its own works.
Applicant The owner, developer or department that seeks approval, and its successors in title.
Development Any building, layout, sub-division, road, paving or land-use change that requires approval under the Unified Building Bye-Laws for Delhi 2016 or that is executed as a public work.
Redevelopment Development on a site where impervious cover already exists.
Land disturbance Clearing, grading, excavation, filling or paving of land, measured in plan area over the whole of a common plan of development (Clause 1.5.5).
Impervious area Roofs, paving, compacted gravel, decks and other surfaces that prevent infiltration. Permeable paving designed to Chapter 8 is counted as pervious only for the area it treats.
New or replaced impervious area Impervious area created, or removed and rebuilt down to the subgrade, by the development. Resurfacing that leaves the base in place is not "replaced".
Retention Permanent removal of runoff from the drainage system on site, by infiltration, reuse or evapotranspiration (Chapter 4).
Detention Temporary storage of runoff with a controlled outlet, emptied after the storm (Chapter 4).
Rainwater harvesting (RWH) Collection of rainfall for supply or recharge under the RWH mandate. RWH storage is not detention unless Chapter 4 allows it.
Minor system Drains, pipes and inlets designed for the minor-system AEP of Chapter 6.
Major system The overland and floodway path that carries the 1% AEP (100-yr) flow (Chapter 6).
Pre-development condition Greenfield: open land in good condition for the mapped hydrologic soil group. Existing impervious cover is not counted (Chapter 3).
Flood-sensitive catchment The Trans-Yamuna basin behind the Shahdara Marginal and Left Marginal bunds, whose drains, other than the Relief Drain, are pumped to the Yamuna, the catchments of drains No. 12 and No. 14 near ITO, from India Gate and Purana Qila Road to their regulators on the Yamuna, the catchments of the Defence Colony, Kotla Mubarakpur and Garhi drains of south Delhi down to the Barapullah drain, and the catchments of the drains that join the Najafgarh drain below the Kakraula regulator, including Kirari, Nangloi and Mundka, and any catchment the Authority notifies (Chapter 4; Annex 1B).
Waterbody A river, stream, canal, tank (johad), lake, pond, marsh, supply channel or surplus course, whether perennial or seasonal (Chapter 7).
Regional facility A detention, retention or tank storage facility serving more than one development, built or restored under a basin plan (Chapter 4).
Tier A / Tier B authority An Approving Authority classed under Clause 1.6.
Policy supplement The set of adoptable alternative clauses in Clause 1.7 and Annex 1C.
Drainage report The preliminary or final report required by Chapter 10.
Registered professional A person registered under the Unified Building Bye-Laws for Delhi 2016 to prepare and sign the relevant plans, with any further qualification required by Clause 10.6.
Compliance calculator The State-issued tool for computing and reporting compliance (Clause 10.5).
Maintenance declaration The registered undertaking by an owner to maintain a stormwater facility (Clause 10.10).
Variance Approval to depart from a numeric requirement, with equivalent performance shown (Clause 1.10).
Waiver Approval that a requirement does not apply to a site, on the grounds in Clause 1.10.
Notified Published by the Government or the State Stormwater Technical Committee in the Gazette of India or the Delhi Gazette, as the instrument requires.
State The National Capital Territory of Delhi. Delhi is a Union territory with a Legislative Assembly (article 239AA of the Constitution), not a State; "State" is used in this Manual as in section 3(58)(b) of the General Clauses Act, 1897, under which a State includes a Union territory.
State Government, Government The Government of the National Capital Territory of Delhi (GNCTD). Bodies of the Union that act in Delhi, among them DDA under the Ministry of Housing and Urban Affairs (MoHUA), NDMC, the Delhi Cantonment Board, CWC and CGWA, are named as such and are not part of the State Government.

Commentary. "Replaced" impervious area is defined to the subgrade so that redevelopment of a fully paved site is captured, while routine resurfacing is not. This follows the approach of the APWA 5600 (2025.01) redevelopment triggers (MARC Supplement, 2025).


1.5 Applicability

1.5.1 Who is covered. This Manual applies to:

  • (a) all development requiring planning permission, building permit or layout approval under the Unified Building Bye-Laws for Delhi 2016;
  • (b) all drainage, road, bridge, culvert, waterbody and flood-mitigation works executed by a ULB, a State department, a board, or a State undertaking; and
  • (c) works executed by Central agencies or their contractors within Delhi, to the extent that the Authority's approval or no-objection is required.

1.5.2 Retention and detention threshold. Chapters 4 and 5 (retention, detention, downstream and tailwater analysis) apply to any development that, over the common plan of development, involves:

  • (a) land disturbance of 0.1 ha or more; or
  • (b) new or replaced impervious area of 500 m² or more.

1.5.3 RWH. The existing RWH mandate continues to apply under Chapter 10 of the Unified Building Bye-Laws for Delhi 2016 to every plot of more than 105 m², as recharge-type rainwater harvesting sized to capture at least the "peak-month rainfall" runoff volume from roof and non-roof areas (Table 10.1 and Annexure X), and, under the notification of the Ministry of Urban Development of 28 July 2001 amending the Building Bye-Laws 1983, which MCD applies at building approval and DJB enforces through its water bills, to buildings on plots of 100 m² and above, as now. This Manual does not change it.

1.5.4 Provisions that apply at every size. The following apply to all development under Clause 1.5.1, whatever its size, unless exempted by Clause 1.5.8:

  • (a) no sewage connection to a storm drain (Chapter 8);
  • (b) lowest habitable floor and openings at or above the 1% AEP level plus 0.5 m, where a 1% AEP level is mapped or determinable (Chapter 6);
  • (c) waterbody setbacks and the no-fill zone (Chapter 7); and
  • (d) no obstruction of a natural drainage path or major-system flow path (Chapter 6).

1.5.5 Common plan of development. The thresholds of Clause 1.5.2 apply to the total area of a development, including all phases, plots and sub-divisions under one layout approval or one ownership at the date of application. A development shall not be divided to avoid the thresholds.

1.5.6 Redevelopment. For redevelopment, the thresholds apply to new plus replaced impervious area. Retention and detention apply to the whole of the new and replaced impervious area, and the pre-development condition is greenfield (Clause 1.4). Where greenfield control cannot be achieved on a constrained redevelopment site, the relief route of Clause 4.5.6 applies: a minimum on-site cut of 50% from existing peaks, with the shortfall paid as fee-in-lieu into basin storage.

1.5.7 Linear public works. For roads, widening and other linear works, the impervious area threshold applies to the added impervious area within each drainage catchment crossed. Retention and detention shall be provided within the right of way, or in a regional facility under Chapter 4, where the right of way cannot hold them.

1.5.8 Exemptions. The following are exempt from Chapters 4 and 5:

  • (a) a single dwelling on its own plot, where the thresholds of Clause 1.5.2 are not met; and
  • (b) linear road resurfacing that adds no impervious area.

Exempt development remains subject to the RWH mandate and to Clause 1.5.4.

1.5.9 Applicability determination. The Applicant shall record the applicability decision on Form 1-1 (Applicability Determination) with the first submittal under Chapter 10. The Authority may confirm or correct it at the pre-application stage.

Figure 1.2 — Applicability decision flowchart Flowchart for Clause 1.5: approval test, exemption test, size threshold test, and flood-sensitive catchment test, leading to the requirements that apply. Development or public work (Clause 1.5.1) Needs building-rules approval, or is it a public work? No Manual not triggered; other rules apply Yes Exempt under Clause 1.5.8? (single dwelling below the threshold, or road resurfacing that adds no impervious area) Yes Exempt from Chapters 4–5. RWH (where mandated) and Clause 1.5.4 still apply No Land disturbance ≥ 0.1 ha, or new or replaced impervious area ≥ 500 m² (Clause 1.5.2)? No Below threshold: RWH (where mandated) and Clause 1.5.4 apply Yes Chapters 4 and 5 apply: retention, detention, downstream and tailwater analysis (+ RWH, 1.5.4) In a flood-sensitive catchment (Annex 1B)? Yes Mixed-frequency rule; full methods only; no Policy Supplement alternatives No Standard rule: Q_post ≤ 0.9 × Q_pre Tier B: design-aid route may be used (Clause 1.7) Decision Chapters 4–5 requirements Chapters 4–5 do not apply

Figure 1.2 — Applicability decision flowchart for Clause 1.5. Original drawing for this Manual.

Commentary. The thresholds have no single direct precedent; they are set by this Manual. Precedents span a wide range:

  • Singapore controls peak runoff from developments of 0.2 ha or more (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5).
  • Malaysia's 2008 DID checklist used on-site detention for sites up to 0.1 ha and community ponds above that.
  • The APWA 5600 (2025.01) Policy Supplement offers alternative triggers of ¼ acre (about 0.1 ha) disturbed, or 1 acre (about 0.4 ha) with 10,000 sq ft (about 930 m²) impervious, and warns agencies not to exceed a 1-acre trigger.
  • MBBL 2016 makes recharge mandatory for buildings over 500 m².

The 0.1 ha / 500 m² trigger sits at the strict end of these, because typical Delhi plots are small and the cumulative effect of many small plots is what fills Delhi's drains. For small buildings in Delhi, the green-building provisions of the UBBL, including rainwater harvesting by recharge, apply only to plots of more than 105 m² (Table 10.1), while the 2001 notification and DJB apply rainwater harvesting from 100 m². The UBBL require every basement to keep out surface drainage (bye-law 7.4.4) but set no entry or plinth level above the road or above a flood level, and do not bar basements in low-lying areas; the basement deaths at Old Rajinder Nagar in July 2024 followed a fall of only about 31.5 mm in three hours (as reported). Whether the UBBL were amended after 2024 on basements was not found [TBC]. Clause 1.5.4(b) applies to every building whatever its size for this reason.

Clause 1.5.4(b) has no direct precedent; this Manual sets it because floor levels are the cheapest protection a building can have, and it would be perverse to protect only large developments. Where no 1% AEP level is mapped, Chapter 6 gives the method for small sites.


1.6 Tiered adoption

1.6.1 Tier A authorities. The following are Tier A:

  • (a) the Municipal Corporation of Delhi (MCD), constituted under the Delhi Municipal Corporation Act, 1957;
  • (b) the New Delhi Municipal Council (NDMC), constituted under the New Delhi Municipal Council Act, 1994, and the Delhi Cantonment Board, constituted under the Cantonments Act, 2006, in their areas; and
  • (c) the Delhi Development Authority (DDA), constituted under the Delhi Development Act, 1957, where it is the Sanctioning Authority under the UBBL, and any other body that grants building or layout approval in the NCT. Every Sanctioning Authority in Delhi is therefore Tier A, and no Tier B authority exists in Delhi at present.

1.6.2 Tier B authorities. All other local authorities are Tier B.

1.6.3 What differs between tiers. All criteria of this Manual apply in both tiers. The tiers differ only in method and review:

Table 1.1 — Differences between Tier A and Tier B authorities

Item Tier A Tier B
Performance criteria (Chapters 2–9) Apply in full Apply in full
Hydrologic method for storage Hydrograph method (Chapter 3) Hydrograph method, or the design-aid route of Clause 1.7 where eligible
Compliance calculator (Clause 10.5) Required as a summary Required; may be the sole calculation on the design-aid route
Policy supplement alternatives (Clause 1.7) Only with State Stormwater Technical Committee concurrence May be adopted by council resolution
Technical review By the Authority By the Authority, with UDD regional support or an empanelled reviewer (Clause 10.7)
Flood-sensitive catchment rule Applies Applies

1.6.4 Moving between tiers. A Tier B authority may opt into Tier A by council resolution. The Government may notify a Tier B authority as Tier A when it becomes a Corporation, joins the area of a Tier A authority, or is found by a post-event review (Clause 10.16) to need the full methods.

1.6.5 Flood-sensitive catchments override tier. In a flood-sensitive catchment, whatever the tier, the alternatives of Clause 1.7 are available only as Table 1.2 allows: S-1 (the design-aid route) for sites of 0.5 ha or less (Clause 4.14.1), and S-5 fee-in-lieu where a basin plan has been notified (Clause 1.10.3(d)). S-2, S-3 and S-4 are not available.

Commentary. Municipal Corporation of Delhi, with its engineering departments and 521.87 km of major storm drains in its charge, and a small local authority with one assistant engineer cannot be asked to review the same hydrograph models. The Kansas City solution was to keep one regional standard and publish adoptable alternatives for the most contested criteria, so that smaller agencies can "opt down" without leaving the standard (MARC Supplement, Nov 2025). The tiers here keep the performance criteria the same in both tiers and vary only the method, so that a building in a Tier B town is protected to the same level as one in Delhi.


1.7 Policy supplement: adoptable alternatives

1.7.1 The Government shall publish, with this Manual, a Policy Supplement (Annex 1C) of alternative clauses. An Approving Authority may adopt one or more alternatives under the conditions in Clause 1.7.3.

1.7.2 The alternatives are:

Table 1.2 — Policy supplement: adoptable alternatives S-1 to S-5

No. Main-text requirement Adoptable alternative Eligibility
S-1 Storage sized by hydrograph method (Chapter 3) Design-aid route: retention and detention volumes taken from the unit-storage tables (m³ per ha, by rainfall zone, soil group and impervious fraction) in Annex 4 and the compliance calculator Sites ≤ 2 ha outside flood-sensitive catchments; ≤ 0.5 ha within them (as Clause 4.14.1)
S-2 Release rate Q_post(T) ≤ 0.9 × Q_pre(T), computed for the site Permissible site discharge (PSD): a tabulated unit-area release rate (m³/s/ha) by zone and AEP, derived from the 0.9 × Q_pre rule Any site outside flood-sensitive catchments
S-3 Waterbody setback extended to the mapped 1% AEP flood extent plus margin (Chapter 7) Fixed-width setback table by waterbody class, where no 1% AEP extent is mapped. Never less than the Zone 1 minimum of Clause 7.4.7 Waterbodies with no mapped 1% AEP extent
S-4 Downstream analysis by hydraulic model (Chapter 5) Screening checklist of downstream capacity and known flooding, with a model only where the screen fails Sites < 1 ha, outside flood-sensitive catchments, not discharging to a tidal outfall
S-5 On-site detention Fee-in-lieu toward a regional facility or restored tank storage in a master-planned basin (Chapter 4) Where a basin plan has been notified

1.7.3 Conditions on adoption.

  • (a) An alternative shall not lower any criterion below the values of this Manual. S-1 and S-2 are simplified methods for meeting the same criterion. They are not lower criteria.
  • (b) A Tier B authority adopts an alternative by council resolution, sent to the State Stormwater Technical Committee within 30 days. A Tier A authority needs the Committee's concurrence before adoption.
  • (c) The adopted alternatives shall be published on the Authority's website and in the register of Clause 10.17.
  • (d) Retention (Annex 2E depth) cannot be replaced by any alternative, except where fee-in-lieu under S-5 funds equivalent retention in the same basin.
  • (e) The tables for S-1, S-2 and S-3 shall be issued by the State Stormwater Technical Committee, and reviewed with Chapter 2 (Clause 2.14).

Commentary. The supplement follows the model of the APWA 5600 (2025.01) Policy Supplement, which gives alternatives for the four most contested criteria (applicability, Rational Method limits, stream setback trigger, and Zone 2 setback width). Two of those map onto S-3 and onto the applicability threshold of Clause 1.5.2. Alternative S-3 copies the APWA answer to the same problem: the 1% AEP extent is not mapped for small drainage areas, so a fixed-width table is offered. S-2 follows the Kansas City 2011 shift from "match existing" to fixed unit-area release rates. Local agencies preferred a set rate because existing conditions were hard to determine consistently (MARC Evolution deck). It also reflects the Sydney Water permissible site discharge (PSD) method. The 2 ha / 0.5 ha limits for S-1 (matching Clause 4.14.1) and the 1 ha limit for S-4 have no direct precedent; they are set by this Manual.


1.8 Relationship with other instruments

1.8.1 This Manual shall be applied together with the instruments below. Where they overlap, Clause 1.3.3 governs.

Table 1.3 — Relationship with other instruments

Instrument Relationship
Master Plan for Delhi with the perspective for 2047 (MPD-2047), notified by MoHUA by S.O. 4597(E) of 20 August 2026 under section 11-A of the Delhi Development Act, 1957, replacing MPD-2021 Continues. MPD-2047 requires greenfield projects along natural drains and water bodies to keep a "minimum mandatory buffer" from the edge of the drain or water body, with "No construction or parking" in it (3.1.2(i)(f)), and, in the controls for recreational use, a buffer of 10 m "wherever feasible" for new projects along drains or water bodies of more than 1.0 ha (10.2.3(v)); makes the active Yamuna floodplain a "no construction zone" and restricts development outside it (3.1.2); lists the river and its floodplain, all natural drains, marshes and wetlands and water bodies of 1 ha and more as Environmentally Sensitive Areas (Annexure 3); and requires water-sensitive urban design, drainage networks in new developments that discharge to "identified groundwater recharge sites", parks in flood-prone areas earmarked as "flood sinks", and implementation of "The Drainage Master Plan of the I&FC Department" (3.7.1 and 3.7.2). The general buffer clause gives no width; the 10 m of 10.2.3(v) applies "wherever feasible" to new projects along drains or water bodies of more than 1.0 ha under the recreational-use controls, and its reach beyond them has not been established. The plan sets no design storm or runoff limit. The hydraulic corridor and setbacks of Chapter 7, whose Zone 1 of at least 15 m is wider than the plan's 10 m, and the design criteria of Chapters 2–6 are this Manual's proposals for those terms; they are not statutory widths or values, and no authority has adopted them. Where the plan or a Zonal Development Plan is stricter, it governs (Clause 1.3.3).
Rainwater harvesting: UBBL 2016, Chapter 10, Table 10.1 and Annexure X; notification of the Ministry of Urban Development of 28 July 2001 amending the Building Bye-Laws 1983; DJB requirement Continue unchanged. The UBBL require recharge-type rainwater harvesting on every plot of more than 105 m², designed "to capture at least 'peak-month rainfall' runoff volume from roof and non-roof areas"; the Delhi High Court restated the rule in April 2024 and directed that its existence and working be checked before an occupation certificate is granted (Delhi High Court, 8 April 2024). The 2001 notification, applied by MCD at building approval, covers plots of 100 m² and above, and DJB charges a penalty of an "inflated 50%" of the monthly water bill to societies and institutions on plots of more than 100 m² without a system (DPCC, 2024). Both thresholds are in force. None gives an outlet rule or a storage that is empty when a storm arrives. RWH storage is not detention unless it is a dedicated empty-on-arrival volume with an outlet, and tanks are assumed full at the start of SW monsoon storms (Chapter 4). Recharge structures may count toward retention where they meet Chapters 4 and 8.
UBBL 2016: basements, drains and the environmental conditions for large projects Continue. Basements keep out surface drainage and are watertight (bye-laws 7.4.4 and 7.4.5); their pumping is not counted as outlet capacity, and Clause 1.5.4(b) and Chapter 6 add the floor and entry levels the bye-laws lack. A "jhot", land kept open for drainage, is not to be used as an access way (bye-law 1.4.62). Projects of 5,000 m² of built-up area and more keep the natural drainage, build nothing on wetlands and water bodies, may use "Check dams, bio-swales, landscape, and other sustainable urban drainage systems (SUDS)", and keep at least 20% of the required open space pervious; those measures are sized under Chapter 4.
Delhi Development Act, 1957 DDA, a body of the Union under MoHUA, prepares the Master Plan and the Zonal Development Plans, including Zone O, "River Yamuna / Riverfront", makes the UBBL (sections 11-A, 13 and 57), is a Sanctioning Authority in its areas and holds much of the land along the drains and the river. The High Court calls DDA "the designated owner of the Yamuna Flood plains" (Delhi High Court, 8 April 2024). This Manual does not decide zoning.
Delhi Municipal Corporation Act, 1957; New Delhi Municipal Council Act, 1994; Cantonments Act, 2006 MCD, NDMC (a body of the Union) and the Delhi Cantonment Board (under the Ministry of Defence) build and maintain the drains in their areas and grant building permission under the UBBL. Their drainage and encroachment sections were not read for this Manual [TBC].
Delhi Water Board Act, 1998 (Delhi Act 4 of 1998) DJB supplies water and collects, treats and disposes of sewage. The Act defines DJB's "drain" as a conduit for sewage "but not designed to carry rain water or sub-soil water" (s.2(m)), so the law assumes the separate system that this Manual assumes; DJB also plans and regulates the use of groundwater in consultation with CGWA (s.9(1)(b)) (text as reproduced from the DJB website). In practice 212.59 MGD of untreated sewage from 1,080 unauthorised colonies was found entering the storm drains (CAG, 2025), and the High Court ordered 191 points where sewage enters storm drains and 121 points where storm water enters sewers to be closed (Delhi High Court, 8 April 2024). The interception of dry-weather flow under Chapter 8 (Clause 8.9) applies until the connections are removed.
Groundwater: Environment (Protection) Act, 1986 and the Central Ground Water Authority (CGWA) Delhi has no groundwater Act. CGWA, a body of the Union, regulates abstraction, and the Deputy Commissioners (Revenue) act for it on groundwater recharge and rooftop rainwater harvesting under its order of 25 May 2010 (DPCC, 2024); parts of the NCT, among them the South and South-West districts, are notified areas (as reported) [TBC]. MPD-2047 treats extraction from bore wells not registered with DJB or another competent authority as illegal (3.7.1). Recharge wells and deep infiltration under Chapters 4 and 8 are subject to the groundwater separation and quality limits of Chapter 8, which rule them out where the water table is within 2 m of the surface, as on much of the Yamuna floodplain in the monsoon.
Yamuna floodplain: judgment of the National Green Tribunal in Manoj Misra v. Union of India, O.A. 6/2012, 13 January 2015 Continues. The Tribunal held that "floodplain zoning should be taken with reference to the flood of once in 25 years", directed DDA to map and physically demarcate the floodplain, permitted no construction in it except as it stated, and directed that there "shall be no construction and/or coverage of any of the drains in Delhi" (NGT, 2015). The 1-in-25-year line is a statutory minimum, not the design extent of this Manual: where the 1% AEP extent of Chapter 7 is mapped, it governs where it is wider. No drain may be covered under this Manual; access openings and grates under Chapter 6 are not a covering.
Wetlands (Conservation and Management) Rules, 2017; Wetlands Authority of Delhi The Wetlands Authority of Delhi was constituted on 23 April 2019, with the Chief Secretary as chairperson (GNCTD notification No. F.1(07)/DPGS/C.Case/2017-18/9397-9429). Its inventory holds 1,367 water bodies, 1,045 listed and 322 found on satellite imagery, of which 674 had been confirmed on the ground by September 2024 (DPCC, 2024), and no wetland in Delhi had been notified under the Rules as of 2024 (as quoted before the NGT). Delhi has no Ramsar site [TBC]. The High Court has directed that water bodies be entered in the revenue records with a named officer for each (Delhi High Court, 8 April 2024). Where a notification or order is wider than the setback of Chapter 7, it governs (Clause 1.3.3).
Orders of the Delhi High Court on drainage: W.P.(C) 7594/2018 and W.P.(C) 9617/2022, judgment of 8 April 2024 and orders of 25 July 2024 and 25 September 2026; W.P.(C) 13190/2024, order of 28 July 2025 Continue. The Court recorded the drain lengths held by each agency (Table 1.5), directed that the 22 open drains outfalling to the Yamuna be placed under one agency, which an office order of 29 April 2024 made I&FC (as reported to the Court; the order was not read for this Manual) [TBC], set deadlines for the basin drainage master plans, desilting and the closing of sewage connections, and made the Integrated Drainage Management Cell, constituted under the NGT's order of 5 March 2020 in O.A. 6/2012, responsible for reporting each month. In July 2025 another bench still found "enormous confusion" between agencies over a drain and asked the Chief Secretary to consider "centralisation" (Delhi High Court, 28 July 2025). This Manual gives the agencies one technical standard for that work; it does not change the orders.
Flood Control Order (I&FC, issued each year before the monsoon); Disaster Management Act, 2005 and the Delhi Disaster Management Plan (DDMA) Continue. The Flood Control Order and the Central Flood Control Room, run from 15 June to 15 October, govern flood warning and response on the Yamuna and the major drains (I&FC); MPD-2047 requires layouts and construction to comply with the Delhi and District Disaster Management Plans (3.7.2). The current Flood Control Order was not found online [TBC]. Chapter 10 links its pre-monsoon checks to these.
CPHEEO Manual on Storm Water Drainage Systems (2019) Engineering reference. This Manual sets higher return periods under Clause 1.3.2.
NDMA Guidelines on Management of Urban Flooding (2010) and MoHUA SOP (2017) This Manual puts into effect the NDMA directives on catchment-based design, detention and retention, waterbody protection and climate-adjusted IDF.
NDMA Urban Flood Risk Management Programme (UFRMP) and AMRUT 2.0 Works funded under these programmes shall comply with this Manual. The development controls of Chapters 4–5 protect the capacity those works create.
IRC:SP:42-2014 and IRC:SP:50-2013 Apply to road drainage only where they do not conflict with Chapter 6.
MBBL 2016, Chapter 9 Model for RWH and for the inspection regime in Chapter 10.

Commentary. RWH in Delhi is framed as a water supply and recharge measure. It works well for that purpose. It cannot, however, be relied on for flood control in the SW monsoon, because RWH sumps are usually full or the ground saturated by the time a July or August monsoon burst arrives after weeks of rain. The Manual therefore keeps harvest volume and attenuation volume apart, while letting recharge count as retention where it truly removes water from the system.

Delhi is planning to spend on drainage. A drainage master plan led by PWD, prepared with eight agencies for the Najafgarh, Barapullah and Trans-Yamuna basins, was unveiled on 19 September 2025 at an estimated ₹57,363 crore over 30 years, with its detailed project reports awaiting approval; its consultant states that drain capacity is to rise from 25 mm/h, the basis of the 1976 plan, to 70 mm/h, with an allowance of 11% for climate change, but neither the duration nor the return period of the 70 mm/h has been published (as reported). MPD-2047 calls for "The Drainage Master Plan of the I&FC Department" to be implemented, without saying which document that is. The earlier plan by IIT Delhi (2018) used 2- and 5-year 15-minute storms, modelled the whole city as hydrologic soil group D, and left regulators, gates and portable pumps out of its model; it was not acted upon (Delhi High Court, 8 April 2024). No development-control condition stops new plots in the same catchments from using up the capacity such works create. Linking Chapters 4–5 to approvals closes that gap.

Delhi's law already holds many of the tools. It assumes a separate drain for rain water (DJB Act, s.2(m)); it keeps the Yamuna floodplain and the drains open (NGT, 2015; MPD-2047); it requires a buffer along natural drains and water bodies and water-sensitive design (MPD-2047); and it makes recharge-type rainwater harvesting a condition of building approval (UBBL). What it lacks is a design standard. None of these instruments says how large a drain must be, how wide the buffer is outside the recreational use zone, how high a flood reaches, or how much storage a filled johad or a paved plot removes; this Manual supplies that technical test, as a proposal for the authorities to consider.


1.9 Roles and responsibilities

1.9.1 The responsibilities below apply under this Manual. They do not change any agency's statutory powers.

Table 1.4 — Roles and responsibilities under this Manual

Agency Role under this Manual
Urban Development Department (UDD), GNCTD Would own the Manual for GNCTD. Would propose to DDA and MoHUA the amendment of the UBBL under Clause 1.3.1(a), constitute and service the State Stormwater Technical Committee, and require compliance in the drainage works of the local bodies it oversees. Technical support to any Tier B authority. Maintains the empanelled reviewer list (Clause 10.7).
State Stormwater Technical Committee (Clause 1.3.2) Would adopt higher standards, issue Annexes, tables and the compliance calculator, concur with Tier A alternatives, decide variances referred to it and review the Manual (Clause 1.12). In Delhi it would include the drain-owning agencies of both governments.
Irrigation and Flood Control Department (I&FC), GNCTD Holds the natural drains (426.55 km) and, under the office order of 29 April 2024 reported to the High Court, the 22 open drains that outfall to the Yamuna; the Yamuna embankments and the regulators that close the drains against the river; the Trans-Yamuna drains and outfalls; and the Najafgarh drain with its regulators at Dhansa and Kakraula. Issues the yearly Flood Control Order and runs the Central Flood Control Room with the Revenue Department. Its records identify the river and its floodplain under MPD-2047. Would provide design river levels and the regulator and pump operating rules for Chapter 5, consent to outfalls into its drains, and keep the drainage master plan that MPD-2047 names.
Public Works Department (PWD), GNCTD Holds 2,064.08 km of major storm drains, mostly along the roads it maintains, the largest share in the NCT. Procures the basin drainage master plans for the Najafgarh, Barapullah and Trans-Yamuna basins (2023–2025). Would apply this Manual to its road drains, underpasses and the works of those plans.
Municipal Corporation of Delhi (MCD) Sanctioning Authority for building plans in its area under the UBBL. Holds 521.87 km of major storm drains and the smaller drains of its colonies and roads, and pumps sewage at the river-front regulators while they are closed (Delhi High Court, 8 April 2024). Would apply this Manual to its works, receive handed-over assets (Clause 10.14), and inspect and enforce (Clauses 10.12–10.15).
New Delhi Municipal Council (NDMC), a body of the Union Sanctioning Authority in its area. Holds 335.29 km of major storm drains. Would apply this Manual to its works, and inspect and enforce in its area.
Delhi Cantonment Board (DCB), under the Ministry of Defence Sanctioning Authority in the Delhi Cantonment. Holds 39.68 km of major storm drains. Would apply this Manual to its works, and inspect and enforce in its area.
Delhi Development Authority (DDA), a body of the Union under MoHUA Makes the Master Plan, the Zonal Development Plans and the UBBL, with the approval of the Central Government, and would make the amendment of Clause 1.3.1(a). Sanctioning Authority in its areas. Holds 251.30 km of major storm drains and much of the land along the drains; maps and demarcates the Yamuna floodplain under the NGT's judgment of 2015, and is the floodplain's "designated owner" (Delhi High Court, 8 April 2024). Would show flood-sensitive catchments, drain buffers and regional facility sites in its plans.
Delhi Jal Board (DJB) Sewers, sewage treatment, and the interceptor sewers along the Najafgarh, Supplementary and Shahdara drains. Would remove sewage connections from storm drains and take part in the interception of dry-weather flow (Chapter 8). Issues guidance on rainwater harvesting and charges the penalty for its absence; plans the use of groundwater with CGWA.
Delhi State Industrial and Infrastructure Development Corporation (DSIIDC) Holds 98.12 km of major storm drains in the industrial areas. Would apply this Manual to its works.
Delhi Pollution Control Committee (DPCC) Monitors the quality of the drains and the Yamuna, consents to sewage treatment works, and reports on rainwater harvesting and water bodies to the NGT. Supports the removal of sewage from storm drains (Chapter 8).
Delhi Disaster Management Authority (DDMA) and the District Disaster Management Authorities Approve the Delhi and District Disaster Management Plans. Would recommend flood-sensitive catchments, hold the record of flood-prone locations with the Revenue Department, and lead the post-event review (Clause 10.16).
Revenue Department, GNCTD: the Divisional Commissioner, the District Magistrates (Deputy Commissioners) and the Flood Control Room In charge of flood control and relief, with the Apex Committee on flood control chaired by the Chief Minister (I&FC). Keeps the land records in which the High Court directed water bodies to be entered, with a named officer for each. The Deputy Commissioners act for CGWA on groundwater recharge and rooftop rainwater harvesting. Evict encroachments.
Department of Environment and Forests, GNCTD, and the Wetlands Authority of Delhi The Wetlands Authority (secretariat: the Delhi Parks and Gardens Society) keeps the inventory of water bodies and would notify wetlands under the Wetlands Rules 2017 (Chapter 7).
Central Water Commission (CWC), a body of the Union Publishes the Flood Estimation Report for subzone 1(e) used in Chapter 2, and liaises through its Upper Yamuna Division with the Central Flood Control Room on river levels (I&FC). Would supply river stage records and forecasts at the Old Railway Bridge for Chapter 5.
Upper Yamuna River Board, a body of the Union Concerned with the sharing of the waters of the upper Yamuna among the basin States. Its role in flood releases was not researched for this Manual [TBC].
Irrigation and Water Resources Department, Haryana Operates the Hathnikund barrage, whose releases reach Delhi in about 48–50 hours, and, as reported, the ITO barrage in Delhi; the first flood warning in Delhi is reported to come when Hathnikund passes more than 1 lakh cusecs (about 2,830 m³/s). Its releases set the river tailwater of Chapter 5, and the Sahibi reaches the Najafgarh drain from Haryana. Would be consulted for release scenarios.
Uttar Pradesh Irrigation Department Operates the Okhla barrage (as reported) and the Agra Canal, and is augmenting the Abul Fazal drain under the High Court's orders (Delhi High Court, 25 September 2026). Would be consulted on outfalls and levels in its reaches.
DJB and the Central Ground Water Board Would supply groundwater levels for the infiltration checks of Chapters 4 and 8.
IMD, the Delhi Traffic Police and other road and rail owners (NHAI, Indian Railways, DMRC) IMD's stations supply the rainfall records of Chapter 2. The Traffic Police list waterlogging points. Road and rail owners would apply this Manual to road drainage (Chapter 6), culverts and linear works (Clause 1.5.7).

Commentary. Ownership of Delhi's storm drains is split between two governments and at least seven agencies, and the High Court has found the split itself to be a cause of flooding. Table 1.5 gives the lengths it recorded.

Table 1.5 — Major storm drains in Delhi by owning agency (Delhi High Court, 8 April 2024)

Agency Government Length (km)
Public Works Department (PWD) GNCTD 2,064.08
Municipal Corporation of Delhi (MCD) Local body 521.87
Irrigation and Flood Control Department (I&FC) GNCTD 426.55
New Delhi Municipal Council (NDMC) Union 335.29
Delhi Development Authority (DDA) Union 251.30
Delhi State Industrial and Infrastructure Development Corporation (DSIIDC) GNCTD 98.12
Delhi Cantonment Board (DCB) Union 39.68
Others — 3.42
Total 3,740.31

One drain from India Gate to the Yamuna passes NDMC, PWD, MCD, PWD again, MCD and I&FC on its way, and becomes drain No. 14 at Gate 5 of the ITPO grounds; the regulators that stop the river from flowing back up the 22 outfall drains are I&FC's, but the pumping of sewage while they are closed is MCD's (Delhi High Court, 8 April 2024). The Court directed that the 22 outfall drains be placed under one agency, and an office order of 29 April 2024 assigned them to I&FC, with the takeover after the 2024 monsoon (Delhi High Court, 25 July 2024); in July 2025 another bench still found "enormous confusion" over a drain in south Delhi (Delhi High Court, 28 July 2025). Which drains MCD holds below PWD's is reported to depend on a width of about four feet, but the source and meaning of that rule were not found [TBC]. MPD-2047 names "The Drainage Master Plan of the I&FC Department" while the basin plans of 2025 were procured by PWD. This Manual names departments and authorities as the statutes, orders and records name them, and does not change any agency's powers. A manual that names one owner for each task does not fix institutions by itself, but it removes ambiguity about who signs what.


1.10 Variances and waivers

1.10.1 Variance. The Authority may grant a variance from a numeric requirement where the Applicant shows, through a report certified under Clause 10.6, that:

  • (a) compliance is impracticable because of site conditions such as a high groundwater table, contaminated soil, rock, or a site area too small for the required facility; and
  • (b) the proposed alternative gives equal or better performance at the downstream point of Chapter 5, or the shortfall is made up by fee-in-lieu or off-site works in the same catchment.

1.10.2 Waiver. The Authority may waive Chapter 4 detention requirements (not retention) where a hydraulic analysis certified under Clause 10.6 shows that the site discharges directly to the sea, or to a tidal reach with no flood-prone property downstream, and that undetained flow does not worsen the outfall-closed condition of Chapter 5. Delhi has no coast and no tidal reach, so no site in Delhi qualifies for this waiver. A site that drains to the Yamuna or to a trunk drain through a regulator or flap gate, or only by pumping, as in the Trans-Yamuna basin, is in the outfall-closed condition of Chapter 5 whenever the river is high, and detention is not waived for it.

1.10.3 No variance or waiver. No variance or waiver shall be granted for:

  • (a) a sewage connection to a storm drain;
  • (b) the lowest habitable floor level of Chapter 6;
  • (c) any reduction of a waterbody setback below the Zone 1 minimum of Clause 7.4.7, or any fill or construction in the no-fill zone of Chapter 7; or
  • (d) the retention requirement in a flood-sensitive catchment, except by fee-in-lieu under Clause 1.7.

1.10.4 Procedure.

  • (a) The request shall be made on Form 1-2 (Variance / Waiver Request) with the preliminary drainage report.
  • (b) A Tier B authority shall refer any variance on a site of 1 ha or more to the State Stormwater Technical Committee.
  • (c) A decision shall state its reasons and any conditions, and shall be entered in the public register of Clause 10.17.
  • (d) A variance runs with the approval. It lapses if the approval lapses.

Commentary. The 2006 APWA 5600 included a waivers section (5601.6), and Georgia allows waivers where downstream analysis shows a peak control is unnecessary. The waiver of Clause 1.10.2 is narrow: on a tidal coast, undetained flow can help by passing through before the tide closes the outfall, but only an analysis can show that. This Manual requires every decision to be published because publication deters case-by-case erosion of the standard; in Delhi, agencies asked in 2024 for 232 of the 1,045 listed water bodies to be deleted from the inventory, and I&FC lists 44 of the 201 drains of the 1976 Drainage Master Plan as untraceable (NGT order of 29 May 2024, as quoted by DPCC; I&FC).


1.11 Transition provisions

1.11.1 Effective date. This Manual takes effect for new applications 6 months after notification (the effective date).

1.11.2 Applications in process. An application filed complete before the effective date may be decided under the rules in force when it was filed, if a decision is issued within 12 months of the effective date. Otherwise, this Manual applies.

1.11.3 Phased start for Tier B. In Tier B authorities, Chapters 4 and 5 apply from 24 months after notification, except in flood-sensitive catchments, where they apply from the effective date.

1.11.4 Public works. DPRs sanctioned before the effective date may proceed as sanctioned. Any DPR revised or re-tendered after the effective date shall comply. Departments shall report non-compliant works in progress to the State Stormwater Technical Committee within 12 months.

1.11.5 Before the annexes are issued. Until an annex referred to in this Manual is issued, the Applicant shall use the method stated in the clause, with values agreed with the Authority and recorded in the drainage report.

Commentary. The 6-month lead time matches the lead time for NIH-DHAARA updates in Clause 2.14.2. Singapore gave a similar interval for its 2025 detention addendum (issued 16 Apr 2025, applied from 1 Oct 2025). The 12- and 24-month periods are set by this Manual to let Tier B authorities train staff and to let the State issue the design-aid tables (Clause 1.7).


1.12 Review and amendment

1.12.1 The State Stormwater Technical Committee shall review this Manual every 10 years, and after any event that exceeds the 1% AEP design depth as set out in Clause 2.14.1.

1.12.2 Amendments shall be notified in the Gazette, published with a change log, and take effect 6 months after notification unless the notification states otherwise.

1.12.3 Any person may propose an amendment to the Committee. Proposals and the Committee's decisions shall be published.


References (chapter)

Annexes and forms

Annex / Form Content
1A List of Tier A authorities, with the areas of MCD, NDMC and the Delhi Cantonment Board and the development areas of DDA
1B Maps of flood-sensitive catchments
1C Policy Supplement: text of alternatives S-1 to S-5 and model council resolution
1D Model UBBL amendment and model ULB bye-law
Form 1-1 Applicability Determination
Form 1-2 Variance / Waiver Request