Chapter 11Basin and City Stormwater Master Plans
11.1 Purpose and scope
11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.
11.1.2 A BSMP shall:
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
- (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
- (d) reserve land for regional storage, johad and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
- (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
- (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).
11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.
11.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Basin | The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3. |
| Basin Stormwater Master Plan (BSMP) | The plan for one basin prepared under this chapter. |
| Lead Authority | The body responsible for preparing a BSMP (Clause 11.4). |
| Level of service (LoS) | The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6). |
| Flood hazard map | A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario. |
| Regional facility | A storage, conveyance or outfall work serving more than one development, identified in a BSMP. |
| Capital Improvement Programme (CIP) | The ranked, costed list of works in a BSMP (Clause 11.8.4). |
11.3 Planning unit: the basin, not the ward
11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.
11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.
11.3.3 The NCT of Delhi drains through three basins, those modelled by IIT Delhi (2018) and used for the basin plans procured by PWD (Delhi High Court 2024). Each shall have one BSMP covering the whole basin within the NCT, with its inflows from outside the NCT as boundary conditions:
- Najafgarh: the basin of the Najafgarh drain (the Sahibi), which enters south-west Delhi from Haryana at Dhansa and runs 57.5 km, past the Kakraula regulator, to the Yamuna below Wazirabad barrage, with the Supplementary drain, which joins it just before its outfall, and the 123 natural drains of the basin (IIT Delhi 2018). Its area within the NCT is 977.26 km², close to two-thirds of Delhi, in IIT Delhi (2018), but 918 km² in the 2025 plan (as reported); the first BSMP shall settle the boundary. The inflow from Haryana and the Yamuna level at the outfall are its boundary conditions;
- Barapullah: the basin of the Barapullah drain and the other drains of central, New Delhi and south Delhi that outfall to the Yamuna on its west bank, through regulators such as that of drain No. 12 near ITO, 374.81 km² (376.27 km² with the small Aruna Nagar and Old Chanderwal basins), about a tenth of it on the Ridge, with 44 natural drains (IIT Delhi 2018). The Yamuna level at each outfall, with its regulator closed, is a design case; and
- Trans-Yamuna: the land east of the river behind the Shahdara Marginal Bund and the Left Marginal Bund, 196.93 km², with 34 natural drains, the Relief Drain, its only gravity outfall to the river, and the pumped outfalls and the Shahdara Outfall Drain (IIT Delhi 2018). The outfall-closed case of Chapter 5, with the capacity of the pumping stations, is a design case.
The 22 drains that outfall to the Yamuna shall each be a sub-basin of the BSMP in which they lie. Where I&FC or CWC has a high flood level, an embankment crest level or an operating rule for the Yamuna, a regulator or a pumping station, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.
Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.
Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Delhi a single drain can pass through several owners' hands on its way to the Yamuna. The drain from India Gate to the river runs through NDMC, PWD, MCD, PWD again, MCD again and I&FC, six jurisdictions of four authorities, and the High Court found that, because of this, "a consistent slope/level of the drain is not maintained"; it directed that the 22 drains that outfall to the Yamuna be placed under one agency, and the Chief Secretary reported an office order of 29 April 2024 assigning them to I&FC, with takeover after the 2024 monsoon (Delhi High Court 2024). In July 2025 another bench still found "enormous confusion" between the agencies on the Tamoor Nagar drain (Delhi High Court 2025). The storm drains also carry sewage across these boundaries. In law DJB's drains exclude rain water (Delhi Water Board Act 1998, section 2(m)), but the CAG found that 212.59 MGD of sewage from 1,080 unauthorised colonies was discharged untreated into storm water drains (CAG Report No. 3 of 2025), and the High Court ordered 191 points where sewage enters storm drains and 121 points where storm water enters sewers to be sealed (Delhi High Court 2024). DJB's interceptor sewers run along the Najafgarh, Supplementary and Shahdara drains; the Shahdara pipeline was reported in October 2026 to be about 90% complete, with completion expected by 31 December 2026 (as reported). This clause makes the basin the planning unit, so that one model carries each drain from its head to the Yamuna whoever owns each reach, and so that the interceptors are tested against the capacity of the trunk drains they run along (Chapter 8, Clause 8.9.5).
11.4 Who prepares, and when
11.4.1 Lead Authority.
- For each of the three basins of Clause 11.3.3, one BSMP shall be prepared, with one model of the whole basin (Clause 11.3.1). I&FC shall coordinate it and keep the basin model, consistent with MPD-2047's reference to "the Drainage Master Plan of the I&FC Department", with PWD, which procured the basin plans of 2023–25, as joint preparer.
- Within each BSMP, each drain-owning agency is Lead Authority for the drains it owns and is responsible for the parts of the CIP on them: I&FC for the natural and trunk drains, including the 22 drains that outfall to the Yamuna (assigned to it by an office order of 29 April 2024, as reported to the High Court), the Yamuna embankments, the regulators and its pumping stations; PWD for the drains along its roads; MCD, NDMC and the Delhi Cantonment Board for the local drains in their areas; DDA for the Yamuna floodplain, its own lands and the drains on them; and DSIIDC for the drains of its industrial areas.
- DJB shall be a partner in every BSMP, for its interceptor sewers along the Najafgarh, Supplementary and Shahdara drains, the sewage that enters the storm drains, and the points where storm water enters its sewers.
- Where a basin receives flow from, or passes flow to, Haryana or Uttar Pradesh (the Najafgarh drain, which enters from Haryana; drains maintained by the Uttar Pradesh Irrigation Department, such as the Abul Fazal drain and the Old Agra Canal), the irrigation or drainage department of that State shall be consulted, and the cross-boundary flows shall be recorded in the BSMP.
The Integrated Drainage Management Cell, DDMA and the Wetlands Authority of Delhi shall be consulted on every BSMP. Every BSMP that proposes works in the Yamuna floodplain shall record the views of DDA and I&FC on them.
I&FC shall be a partner in every BSMP that includes a river, canal or tank under its control.
11.4.2 When a BSMP is required.
- (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
- (b) A BSMP is required before:
- any regional detention or fee-in-lieu is accepted under Clause 4.13;
- a fee held under Clause 4.5.6.3 is spent; and
- a basin-specific release rate is applied under Clause 11.8.3.
- (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.
11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.
11.5 Data and surveys
11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:
Table 11.1 — Minimum data and surveys for a BSMP
| Data | Minimum requirement |
|---|---|
| Terrain | Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum |
| Drain network | Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm |
| Waterbodies | Survey of every tank, johad, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment |
| Rivers and canals | Cross-sections at no more than 200 m spacing and at every structure |
| Outfalls and the Yamuna | The datum of every level named; outfall invert levels against the warning, danger and evacuation levels of the Yamuna at the Old Railway Bridge and its recorded peaks; the regulators, flap gates and pumping stations on the drains that outfall to the Yamuna, in the Shahdara and Left Marginal bunds and at underpasses, with their capacities and operating rules; embankment crest levels; release records of Hathnikund barrage; and the inflow to the Najafgarh drain from Haryana |
| Rainfall and levels | All available rain gauges (IMD, including the Safdarjung and Palam observatories, the Lodi Road, Ridge and Ayanagar stations and the automatic weather stations and rain gauges across the city, such as those at Pragati Maidan, Mayur Vihar, Pitampura, Pusa, Delhi University, Tughlakabad and Jharoda Kalan; any rain and water-level gauges kept by I&FC, PWD and the local bodies; and the Yamuna gauge at the Old Railway Bridge) and water-level records, including those for the September 1978 (Yamuna), July 2023 (Safdarjung rainfall and the Yamuna), June 2024 (Safdarjung), July 2024 (Old Rajinder Nagar and Pragati Maidan) and September 2025 (Yamuna) events |
| Flood evidence | Surveyed flood marks and mapped flood extents from past events, including public reports |
| Land use | Existing land use and imperviousness; future land use from the statutory master plan |
| Soils and groundwater | HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones |
| Sewer interaction | Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots |
Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the Yamuna floodplain, behind the Trans-Yamuna bunds and in the Najafgarh jheel depression a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The September 1978 (Yamuna), July 2023 (Safdarjung rainfall and the Yamuna), June 2024 (Safdarjung), July 2024 (Old Rajinder Nagar and Pragati Maidan) and September 2025 (Yamuna) events are the best calibration data Delhi has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.
11.6 Levels of service
11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.
Table 11.2 — Minimum levels of service
| Element | Minimum level of service |
|---|---|
| Minor system | The design AEP of Chapter 6 (Table 6.1) |
| Habitable buildings | No flooding above floor level in the 1% AEP (100-yr) event |
| Critical facilities (hospitals, emergency services, substations, water and sewage plants) | No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event |
| Evacuation routes and arterial roads | Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event |
| Ponding drain time | Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event |
| Tank and johad storage | No net loss of flood storage below the MWL in the basin, measured against the earliest available survey |
| Outfalls | Functioning under the joint and outfall-closed cases of Chapter 5 |
Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been counted but not measured. Delhi's inventory holds 1,367 water bodies, 1,045 listed and 322 more identified from satellite imagery; by September 2024 ground-truthing had covered 674, all of them visible (DPCC 2024). Agencies had asked for 232 of the listed water bodies to be deleted, and not a single wetland had been notified in Delhi under the Wetlands (Conservation and Management) Rules 2017, although the Wetlands Authority of Delhi was constituted on 23 April 2019 (DPCC 2024, quoting a news report adopted in the NGT order of 29 May 2024; GNCTD 2019). The High Court recorded 272 water bodies restored and 72 in progress, and directed that each be entered in the revenue records and assigned to a named officer (Delhi High Court 2024). MPD-2047 makes water bodies of 1 ha and more Environmentally Sensitive Areas (MPD-2047, Annexure 3). No survey of the storage of any of Delhi's water bodies was found.
11.7 Modelling and scenarios
11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:
- the minor system;
- the major (overland) system;
- rivers, canals and tanks; and
- the outfalls.
Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.
11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.
11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.
11.7.4 Scenarios. Each BSMP shall model at least:
- (a) Existing: existing land use, network, tanks and outfalls;
- (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
- (c) Future, controlled: future land use with the site controls of Chapter 4;
- (d) Future, with plan: scenario (c) plus the works of the CIP; and
- (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8; the 11% allowance in rainfall intensity reported for the 2025 drainage master plan is smaller than those factors for short storms and is not used.
11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the September 1978 (Yamuna), July 2023 (Safdarjung rainfall and the Yamuna), June 2024 (Safdarjung), July 2024 (Old Rajinder Nagar and Pragati Maidan) and September 2025 (Yamuna) events where data exist.
Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and johads with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.
Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).
11.8 Options, outputs and the Capital Improvement Programme
11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:
- Protect and restore storage: johads, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
- Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
- Conveyance upgrades to drains, canals and culverts;
- Outfall works: regulators and flap gates on the outfalls to the Yamuna, pumping stations and the storage behind them, including those behind the Shahdara and Left Marginal bunds and at underpasses, and the Yamuna embankments;
- Property-level protection where works cannot reach the level of service; and
- Non-structural measures: flood warning (for example IMD rainfall warnings and nowcasts, the Yamuna stage at the Old Railway Bridge against its warning, danger and evacuation levels, advance notice of releases from Hathnikund barrage upstream in Haryana, and the Central Flood Control Room run under the annual Flood Control Order), flood-hazard zoning, emergency planning and public information.
11.8.2 Option assessment. Each option shall be assessed for:
- reduction in flood risk (buildings and people flooded; expected annual damage);
- capital and 30-year maintenance cost;
- land required;
- effect on groundwater recharge where the water table is deep, and waterlogging where it is shallow (Chapter 8);
- effect on downstream basins and the Najafgarh drain; and
- who benefits.
11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.
11.8.4 Outputs. Each BSMP shall produce:
- (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
- (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
- (c) regional facility sites, with storage volumes, land needs and the sites they serve;
- (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
- (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
- (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
- (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.
Commentary. Restoring storage comes first because Delhi's outfalls cannot always take more water. When the Yamuna is high its regulators are shut, and the Trans-Yamuna drains reach the river only by pumping (IIT Delhi 2018), so faster conveyance only fills the drains behind them sooner. MPD-2047 already points the same way: parks in flood-prone areas are to serve as "flood sinks", and 13 projects on about 1,700 ha of the Yamuna floodplain are to create wetlands "by developing and deepening the existing depressions into storage basins" (MPD-2047). The storms are large for drains reported to have been designed for 25 mm/h: 228.1 mm fell at Safdarjung on 28 June 2024 (IMD 2024), and 112.5 mm in one hour at Pragati Maidan on 31 July 2024 (as reported). Conveyance upgrades on their own move water faster to an outfall that the Yamuna may close, or that is limited by the capacity of its regulator or pumping station. Groundwater in Delhi sets opposite limits in different parts of the city. In May 2023 the depth to water ranged from 1.08 m to 66.84 m below ground: more than 65 m over the Delhi quartzite in the Central, New Delhi and South districts, and less than 2 m on the Yamuna floodplain and in parts of the North-West and West districts (CGWB Ground Water Year Book 2023–24, seen only in a search summary). Recharge is most valuable on the Ridge and in central and New Delhi, where the water table is deep, and least feasible on the floodplain, where infiltration adds to waterlogging (Chapter 8). CGWB has assessed that 24.39 MCM a year of rainwater runoff is available for recharge, to be realised through check dams and recharge structures in rainwater drains, and DJB proposes check dams and nala bunds in the Ridge (MPD-2047). Delhi has no groundwater Act; DJB plans and regulates the use of groundwater in consultation with CGWA (Delhi Water Board Act 1998, section 9(1)(b)), and rain water harvesting is mandatory under the UBBL. This is why recharge and waterlogging are both assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.
11.9 Integration with land-use planning
11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the Master Plan for Delhi with the perspective for the year 2047 (MPD-2047, S.O. 4597(E) of 20 August 2026) and the Zonal Development Plans under it, made under the Delhi Development Act 1957, including the plan for Zone O (River Yamuna / Riverfront), and the layout plans approved under them by DDA and the local bodies. In particular:
- (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
- (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
- (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
- (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.
11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.
Commentary. Delhi has a tribunal-set floodplain line for the Yamuna but no flood-line system for its drains. The National Green Tribunal directed in 2015 that "floodplain zoning should be taken with reference to the flood of once in 25 years", that DDA map and physically demarcate the floodplain, and that no construction be permitted in it (NGT 2015). MPD-2047 makes the active floodplain a "no construction zone", restricts development outside it, and leaves the river and its floodplain to be identified from the "records and technical assessment" of I&FC; it does not define the active floodplain (MPD-2047). It also requires greenfield projects along natural drains and water bodies to keep a "minimum mandatory buffer" with "no construction or parking", without a width (MPD-2047, 3.1.2(i)(f)); only its controls for recreational use set one, "a minimum mandatory buffer of 10m from the edge of the water bodies/drains wherever feasible" for new projects along drains or water bodies "(above 1.0 ha)" (MPD-2047, 10.2.3(v)). Neither MPD-2047 nor the UBBL restricts basements in flood-prone areas (UBBL 2016, 7.4; MPD-2047, 13.1.3). The NGT's 1-in-25-year line is a statutory minimum, not the design extent of this Manual. A BSMP gives the land-use plans the 1% AEP drainage-flood map, and the buffer widths of Chapter 7, that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because MPD-2047 already asks that parks in flood-prone areas serve as "flood sinks" and that the drainage networks of new developments discharge to identified groundwater recharge sites, and the environmental conditions of the UBBL for larger building projects already require at least 20% of the open spaces required by the bye-laws to be pervious and allow check dams, bio-swales and other sustainable urban drainage systems to maintain the drainage pattern; storage placed in a layout's open space builds on these duties, and because that land still serves as open space, the storage must stay usable as one. Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.
11.10 Consultation and publication
11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.
11.10.2 After approval, the following shall be published as open data:
- the model files;
- the flood hazard maps;
- the data of Clause 11.5.1, except security-sensitive asset details; and
- the CIP.
They shall also be shown on a public map viewer.
Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.
11.11 Approval, review and reporting
11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.
11.11.2 Review. Each BSMP shall be reviewed:
- every 10 years;
- within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
- when the statutory land-use plan is revised.
11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each SW monsoon (by 31 May). The report shall show:
- CIP progress;
- the fee-in-lieu ledger (Clause 4.13.4);
- maintenance completed; and
- any flooding against the levels of service.
11.12 Interim arrangements
11.12.1 Until a BSMP is approved for a basin:
- (a) all site criteria of Chapters 4 to 8 apply in full;
- (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
- (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
- (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.
References (chapter)
- Indian Institute of Technology Delhi (2018). Drainage Master Plan for NCT of Delhi, Final Report, July 2018, prepared for the Department of Irrigation and Flood Control, GNCTD (posted by I&FC as "Draft Drainage Master Plan"). https://ifc.delhi.gov.in/sites/default/files/inline-files/main_report_dmp_version51.pdf
- Defra (2010). Surface Water Management Plan Technical Guidance. Department for Environment, Food and Rural Affairs, London.
- Mile High Flood District (Denver). Master planning programme and Urban Storm Drainage Criteria Manual.
- Mid-America Regional Council (2025). APWA Stormwater Standards Supplement; KC Metro APWA Section 5600, Version 2025.01.
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- Delhi High Court (2024). Judgment of 8 April 2024 in W.P.(C) 7594/2018 and W.P.(C) 9617/2022, Court on its own motion v. Union of India and GNCTD, with the order of 25 July 2024 (read as filed by DDA in National Green Tribunal O.A. 230/2025). https://www.greentribunal.gov.in/sites/default/files/news_updates/Document%20filed%20by%20R%206%20in%20OA%20No%20230%20of%202025%20NEWS%20ITEM%20TITLED%20DEADLINE%20LOOMING%20MCD%20MET%20JUST%2021%20OF%20DESILTING%20TARGET%20BY%20END%20OF%20APRIL%20APPEARING%20IN%20THE%20TIMES%20OF%20INDIA%20DATED%2005-05-2025.pdf
- Delhi High Court (2025). Order of 28 July 2025 in W.P.(C) 13190/2024, Maharani Bagh CHBS v. Union of India (Tamoor Nagar drain). https://delhihighcourt.nic.in/app/showFileJudgment/PMS28072025CW131902024_201344.pdf
- Ministry of Housing and Urban Affairs (Delhi Division) (2026). Master Plan for Delhi with the perspective for the year 2047 (MPD-2047), Notification S.O. 4597(E) of 20 August 2026 (1.7.2, 1.8, 3.1.2, 3.7.1, 3.7.2, 10.2.3, 13.1.3 and Annexure 3). https://dda.gov.in/sites/default/files/notice/275618.pdf
- Delhi Development Authority (2016). Unified Building Bye-Laws for Delhi 2016, compendium incorporating amendments up to 12 February 2020 (clause 7.4 and the environmental conditions for building projects). https://dda.gov.in/sites/default/files/public-notice/COMPENDIUM_OF_UBBL_201605082020.pdf
- Department of Irrigation and Flood Control, GNCTD. List of 201 drains as per Master Plan Drainage 1976; List of 44 Untraceable Drains from MPD 1976. https://ifc.delhi.gov.in/sites/default/files/ifc/generic_multiple_files/201_drains_mpd.pdf ; https://ifc.delhi.gov.in/sites/default/files/ifc/generic_multiple_files/44_drains.pdf
- National Green Tribunal (2015). Judgment of 13 January 2015 in O.A. 6/2012, Manoj Misra v. Union of India (third-party copy). https://thebastion.co.in/writereaddata/fileupload/ngtmatters/NGT%20judgement%2013.01.15.pdf
- GNCTD, Department of Environment, Forests and Wildlife (2019). Notification No. F.1(07)/DPGS/C.Case/2017-18/9397-9429 of 23 April 2019 constituting the Wetlands Authority of Delhi, Delhi Gazette Extraordinary, Part IV, No. 77 (as annexed to the Authority's status report of 14 September 2024 in National Green Tribunal O.A. 633/2024). https://www.greentribunal.gov.in/sites/default/files/news_updates/REPORT%20BY%20R-1%20WETLAND%20AUTHORITY%20OF%20DELHI%20IN%20OA%20NO.%20633%20of%202024%20NEWS%20ITEM%20TITLED%20THE%20CURIOUS%20CASE%20OF%20DELHI,S%20DISAPPEARING%20WATER%20BODIES.pdf
- Delhi Pollution Control Committee (2024). Response of 11 September 2024 in National Green Tribunal O.A. 633/2024 (water-body counts, quoting the Tribunal's order of 29 May 2024). https://www.greentribunal.gov.in/sites/default/files/news_updates/REPORT%20BY%20DPCC%20IN%20OA%20NO.%20633%20of%202024%20NEWS%20ITEM%20TITLED%20THE%20CURIOUS%20CASE%20OF%20DELHI,S%20DISAPPEARING%20WATER%20BODIES%20APPEARING%20IN%20THE%20HINDU%20DATED%2025.04.2024.pdf
- Delhi Water Board Act, 1998 (Delhi Act 4 of 1998), sections 2(m) and 9 (text as reproduced by IELRC from the DJB website). https://www.ielrc.org/content/e9802.pdf
- Comptroller and Auditor General of India (2026). Report No. 3 of 2025, Performance Audit on Functioning of Delhi Jal Board (laid on 23 March 2026): press release and executive summary. https://cag.gov.in/uploads/PressRelease/PR-Press-Release-on-Report-No-3-of-2025-069c383c1c5b4d3-75064279.pdf ; https://cag.gov.in/uploads/download_audit_report/2025/Executive-Summary-069c28684277b53.34142481.pdf
- Comptroller and Auditor General of India. Audit of flood control and drainage in Delhi, in the report on GNCTD for the year ended March 2013 (report number not found; seen only through a CAG podcast page and press reports; secondary source). https://cag.gov.in/uploads/journal/august-2015/visual-podcast.html
- Central Ground Water Board. Ground Water Year Book, NCT Delhi, 2023–24 (seen only through a search summary; the site was unavailable). https://gwdata.cgwb.gov.in/download/Yearbook/Delhi_GWYB%202023-24.pdf
- India Meteorological Department (2024). Press release on heavy rainfall over Delhi, 28 June 2024 (Wayback capture). https://mausam.imd.gov.in/Forecast/marquee_data/Press%20Release%20Delhi%20heavy%20rainfall%2028-06-2024.pdf
- The Week/PTI (19 September 2025). Report on the drainage master plan unveiled on 19 September 2025 (secondary source). https://www.theweek.in/wire-updates/national/2025/09/19/des66-dl-drainage-ld-masterplan.html
- The Tribune (20 September 2025). ₹57,000-cr drainage master plan unveiled (secondary source). https://www.tribuneindia.com/news/delhi/57000-cr-drainage-master-plan-unveiled
- The Week/PTI (2 April 2025). Report on the PWD drainage master plan and the 2018 plan (secondary source). https://www.theweek.in/wire-updates/national/2025/04/02/des71-dl-pwd-drainage-master-plan.html
- Newslaundry (3 July 2019). Delhi's ready for rain, but its drainage system might not be (secondary source). https://www.newslaundry.com/2019/07/03/delhis-ready-for-rain-but-its-drainage-system-might-not-be
- Haskoning (5 October 2025). Securing the sustainable future of Delhi drainage system (consultant news page; secondary source). https://www.haskoning.com/en/newsroom/news/2025/securing-the-sustainable-future-of-delhi-drainage-system
- ThePrint (2024). Six Delhi weather stations record over 100 mm rainfall (Pragati Maidan, 31 July 2024; secondary source). https://theprint.in/india/six-delhi-weather-stations-record-over-100-mm-rainfall-imd-calls-it-extremely-intense-spell/2202691/
- Down To Earth (27 October 2026). Daily court digest: major environment orders (Shahdara drain interceptor pipeline; secondary source). https://www.downtoearth.org.in/amp/story/waste/daily-court-digest-major-environment-orders-october-27-2026
Annexes and forms
| Annex / Form | Content |
|---|---|
| 11A | BSMP terms of reference template |
| 11B | Basin lists and boundaries for Tier A bodies |
| 11C | Depth–damage curves for Delhi building types |
| 11D | BSMP data and model publication standard |
| Form 11-1 | Annual implementation report |
Commentary. Delhi has had three drainage master plans, and none is an approved design standard. The first, of 1976, listed 201 drains, of which I&FC now lists 44 as untraceable (I&FC), and is reported to have used a design intensity of 25 mm/h (as reported). The second was prepared by IIT Delhi for I&FC and delivered as a Final Report in July 2018: it modelled the city's three drainage basins, Najafgarh, Barapullah and Trans-Yamuna, with 2-year design storms (IIT Delhi 2018). Its approval was reported pending in 2019 and the plan was later reported to have been rejected as "generic" (as reported), and the High Court found in 2024 that it "was not acted upon by GNCTD till date" (Delhi High Court 2024). An earlier CAG audit of flood control and drainage in Delhi is reported to have found that a committee set up in 2005 did nothing on a drainage master plan until 2012 (as reported; the report itself was not read). The third generation is a plan by basin procured by PWD: the consultancy for the Najafgarh basin was awarded on 10 June 2023, with other consultants for the Barapullah and Trans-Yamuna basins, under deadlines set by the High Court (Delhi High Court 2024). A plan of ₹57,363 crore, with a network of 18,958 km, was unveiled on 19 September 2025 and was awaiting approval of its detailed project reports (as reported); its design storm and return period have not been published. MPD-2047, notified in August 2026, still describes the Delhi Drainage Master Plan as "under preparation by GNCTD", while requiring that "the Drainage Master Plan of the I&FC Department shall be implemented through multi-agency coordination" (MPD-2047). A site-level manual cannot fix basin-level problems: lost tank storage, outfalls to the Yamuna closed by regulators when the river is high, Trans-Yamuna drains that reach the river only by pumping, single drains split between several owning agencies, natural drains narrowed or covered by encroachment, storm drains that carry sewage, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:
This chapter adapts that method to Delhi: to three drainage basins that do not follow the boundaries of the seven agencies that own most of the major drains; to outfalls on the Yamuna that its regulators close when the river is high, and to the Trans-Yamuna drains that reach the river only by pumping, behind the Shahdara and Left Marginal bunds; to the Najafgarh drain, which brings water into Delhi from Haryana; to storm drains that carry sewage from unsewered colonies although the law separates them from sewers; to a Yamuna floodplain that the National Green Tribunal and MPD-2047 protect without a published design level; and to a south-west monsoon whose short bursts exceed what the older design methods assume.