Chapter 1Policy, Applicability and Adoption


1.1 Purpose and objectives

1.1.1 This Manual sets the minimum standards for the planning, design, construction, operation and maintenance of stormwater systems in Jharkhand. It applies to private development and to public works, as set out in Clause 1.5.

1.1.2 The Manual has the following objectives:

  • (a) to make stormwater management a condition of development approval, so that new development and redevelopment do not increase flood peaks or runoff volumes downstream;
  • (b) to retain frequent rainfall on site, so that groundwater recharge is sustained and pollutant loads are reduced;
  • (c) to size storage for the long-duration south-west monsoon storms of July–September, brought by depressions from the Bay of Bengal, which fall on thin soils over granite-gneiss that weeks of rain have saturated, have put more than 500 mm in a day on gauges of the Santhal Parganas (601.4 mm at Taljhari on 25 September 1999, the State record), and often reach rivers already raised by releases from the dams upstream, as well as for short-duration intensities;
  • (d) to design outfalls for the stage of the rivers into which the towns drain: the Subarnarekha and the Kharkai at Jamshedpur, raised by releases from the Chandil dam and from the dams on the Kharkai in Odisha; the Damodar and the Barakar below Tenughat and the reservoirs of the Damodar Valley Corporation (DVC); the Ganga at Sahebganj and Rajmahal; and the North Koel at Medininagar; the levels of the reservoirs and talabs that receive the nalas of Ranchi, Kanke, Hatia (Dhurwa) and Getalsud and Bada Talab; and, in the coalfields, the levels of mine voids and subsidence hollows, including the case where the outfall is closed;
  • (e) to protect tanks (talabs), marshes, rivers, supply channels and surplus courses as part of the drainage system;
  • (f) to give every element of the drainage network a safe overland path for the 1% AEP (100-yr) storm;
  • (g) to make design inputs, approvals and facility records public, so that designs can be checked and repeated; and
  • (h) to make sure that facilities, once built, are maintained and remain effective.

1.1.3 This Manual does not replace the rainwater harvesting (RWH) mandate, the building byelaws notified by the Urban Development and Housing Department under section 434 of the Jharkhand Municipal Act 2011 for the urban local bodies and development authorities of the State (the Jharkhand Building Byelaws 2016), or the statutes on waterbodies. It adds runoff control requirements to them (Clause 1.8).

Commentary. Jharkhand's floods come from three sources, often together. The first is the Bay of Bengal storm: of the 450 storms and depressions that influenced the State's weather in 1891–2010, 143 came in August, 89 in September, 29 in October and 4 in November (IMD), and the late-September storms put the largest falls on record on several gauges at once. On 25 September 1999 Taljhari in Sahebganj district recorded 601.4 mm, the State's highest fall in a day, with 450.0 mm at Boarijor the day before and 366.5 mm at Sahebganj (IMD); the storms of 26–28 September 1978 and 20–21 September 2000 set the highest flood levels on the Damodar at Ramgarh and the Mayurakshi at Maharo (CWC, as copied). The second is the river, raised by the dams upstream. In June 2008 Jamshedpur (A) recorded 338.1 mm on the 18th (IMD), the Kharkai at Adityapur set its highest flood level, 137.8 m (CWC, as copied), and more than 500 houses were flooded in Jugsalai, Bagbera, Sonari and nearby after the gates of the dam on the Kharkai in Odisha were opened; the army was called in (as reported). When Cyclone Yaas crossed the State on 27 May 2021, Chaibasa received 21 cm, Mandar 18 cm, Ranchi 15 cm and Jamshedpur 11 cm in 24 hours (IMD), the Kharkai rose to 132.40–132.87 m against a danger mark of 129 m, and about 14,000 people were evacuated in Kolhan (as reported). On 17 September 2024 the combined release of DVC's Maithon and Panchet dams reached about 2.5 lakh cusecs (as reported), and the Damodar, the Barakar, the North Koel and the Sone stood above their danger levels at six CWC sites in the State (CWC). The third is the town drain that fails in rain that is not extreme. In Ranchi the channel of the Harmu river, built for a 25-year flood, was damaged in July 2016 and again in July 2017 (CAG); on a day in August 2022 when the city recorded 54.2 mm, Kanke Road stood under knee-deep water; and in June 2025 Ranchi district received 459 mm in 1–23 June against a normal of 125.7 mm, in flash floods that led to calls to update the State's disaster management plan (all as reported). At Sahebganj the Ganga reached 28.61–28.72 m in August 2025 and September 2026, against a danger level of 27.25 m (as reported).

Missing design makes all three worse. The only design storm found for a town's drains in the State is the 1-year storm of the Dhanbad drainage project, chosen because 2- and 5-year drains needed land beyond the road (JUIDCO, 2017); the Harmu channel was designed for 25 years against the 100-year frequency of IS 12094 for the protection of towns, then for 50 (CAG Report No. 1 of 2023); and in nine towns the CAG test-checked, 60% of 939.55 km of drains were uncovered, and household wastewater ran in the same drains as the storm water (CAG, 2017). The JBBL 2016 control rainwater harvesting pits, not runoff. Objectives (b) to (e) address the storage, outfall and building-level failures, which a drain-sizing manual alone cannot fix.

No national instrument requires on-site detention. CPHEEO (2019) is advisory and describes peak control only as typical practice. NDMA (2010) says detention and retention "will" be included but gives no sizing rule. MBBL 2016 and the Jharkhand Building Byelaws 2016 mandate RWH only. Objective (a) is therefore the main new step this Manual takes.


1.2 Stormwater management hierarchy

1.2.1 Every development to which Chapter 4 applies shall consider stormwater measures in the following order. A designer shall not use a lower measure in place of a higher one that is practicable on the site.

  1. Preserve — keep or restore natural drainage features, tanks, wetlands, permeable soils, trees and overland flow paths (Chapter 7).
  2. Retain — hold the runoff from the retention depth of Annex 2E on site, by infiltration, reuse or evapotranspiration (Chapters 4 and 8).
  3. Detain — store larger storms temporarily and release them at or below the rates in Chapter 4, checked against downstream and tailwater conditions (Chapters 4 and 5).
  4. Convey — carry the remaining flow safely in the minor system, and the 1% AEP flow in the major system (Chapters 6 and 9).

1.2.2 Maintenance underlies all four measures. A measure that cannot be maintained by its owner under Chapter 10 shall not be credited.

1.2.3 Credits from higher measures reduce the requirements of lower ones. Preserved areas and retained volume reduce detention storage as set out in Chapter 4.

Figure 1.1 — Stormwater management hierarchy Four stacked bars, widest at top: Preserve, Retain, Detain, Convey, with a Maintain bar underneath spanning all. A downward arrow shows the order of consideration; an upward arrow shows that credits from higher measures reduce lower ones. Order of consideration Credits reduce lower measures 1 PRESERVE Chapter 7 Keep tanks, wetlands, marshes, permeable soils, trees and flow paths 2 RETAIN Chapters 4, 8 Hold the Annex 2E depth on site: infiltrate, reuse, evaporate 3 DETAIN Chapters 4, 5 Store larger storms; release below pre-development peaks 4 CONVEY Chapters 6, 9 Minor system, plus a 1% AEP overland path MAINTAIN — underlies every measure Chapter 10 A measure that its owner cannot maintain earns no credit (Clause 1.2.2) Use a lower measure only for what the measures above it cannot practicably achieve (Clause 1.2.1).

Figure 1.1 — Stormwater management hierarchy: preserve, retain, detain, convey, with maintenance underlying each measure. Original drawing for this Manual, adapted from Mid-America Regional Council / Kansas City Metro Chapter APWA, "Layers of Stormwater Management", APWA 5600 Manual Factsheet, 2025 (concept).

Commentary. The order follows the "layers" of Kansas City Metro APWA Section 5600, Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet, 2025). The same logic is behind Georgia's runoff-reduction standard and CSE's "attenuate and infiltrate first" principle (CSE, 2023). For Jharkhand, the top layer has a particular meaning. Much of the State's flood storage lies in its talabs, in the bandh (embanked tanks), the ahar of the north-west and the dobha (farm ponds) of the villages, in the don (terraced paddy lowland) of the valley floors, and in the reservoirs that its towns grew round: Bada Talab, built in 1842 in the centre of Ranchi (as reported), the Kanke, Hatia (Dhurwa) and Getalsud dams above the city, and Dimna lake above Jamshedpur. Losing it has a record: about 71 ponds were said to have existed in Ranchi, of which the High Court was told in 2024 that four or five could still be seen (as reported), and the Jamshedpur Master Plan 2027 shows 1,186.31 ha of water area against the 1,280.00 ha that existed in 2016–17 (UD&HD notification of 23 October 2017). The law protects some of it. The Ranchi Master Plan 2037 bars construction within 20 m of the full tank level of the Kanke, Dhurwa and Rukka (Getalsud) dams and within at least 10 m of every river and natural nala (condition 2.9); the JBBL 2016 bar building within 10–15 m of rivers (byelaw 23.2); public tanks and the land appertaining to them vest in the municipality (Jharkhand Municipal Act 2011, s.203); and the High Court has ordered the surroundings of Ranchi's water bodies made no-entry zones (2025, as reported). The same Act still lets a municipality order a private tank or pool to be filled up (s.341). The coalfields add a storage of their own, the mine voids and pit lakes of the Damodar valley, which may hold water but are neither stable nor free (Chapter 7). The larger wetlands are a separate layer: the State has notified no wetland under the Wetlands Rules 2017, and Udhwa Lake, a Ganga floodplain wetland of 935.5 ha joined to the river by the Udhwa nala, is its only Ramsar site (Ramsar Information Sheet). Losing that storage cannot be offset economically by pipes and pumps.


1.3.1 Notification. This Manual shall be given statutory effect by the Government of Jharkhand through:

  • (a) an amendment to the Jharkhand Building Byelaws 2016 that makes compliance with this Manual a condition of planning permission, building permit, layout approval and completion certificate, for development to which Clause 1.5 applies; and
  • (b) bye-laws or standing orders of each urban local body (ULB), adopting the Manual for works executed or approved by that ULB, including the ULB's own drains and roads.

1.3.2 Higher State standards. The design return periods and performance criteria of this Manual exceed the national advisory minimums of the CPHEEO Manual on Storm Water Drainage Systems (2019). The State shall constitute, by notification, a high-powered committee (the State Stormwater Technical Committee, Clause 1.9) to adopt these higher standards. This is the route that CPHEEO (2019) provides for higher return periods.

1.3.3 Precedence. Within its scope, this Manual governs where it is stricter than CPHEEO (2019), IRC:SP:42-2014, IRC:SP:50-2013 or any departmental standard. Where a statute or statutory rule sets a stricter requirement (for example a waterbody setback), the statute governs.

1.3.4 Design-practice standard for public works. Departments and ULBs that procure drainage, road or waterbody works shall require compliance with this Manual in detailed project reports (DPRs) and contracts, from the dates in Clause 1.11.

Commentary. In Jharkhand the building rules are the Jharkhand Building Byelaws, 2016, notified by the Urban Development and Housing Department (UD&HD) by Notification No. 7/न0वि0/अधि0/स0सो0/102/2013-2006 of 5 April 2016 "under Section-434 of the Jharkhand Municipal Act 2011 and in supersession and modification of all the existing rules on the subject", and enforceable by all the Regional Development Authorities, Urban Local Bodies, the Mineral Area Development Authority and all Industrial Area Development Authorities; the notification asks the Government Press to publish it in the extraordinary Gazette, whose number was not seen [TBC]. The amendments read for this Manual, of 15 May 2017 (the first, made on the recommendation of the Building Bye-laws Review Committee), 17 August 2017 (the second), 6 June 2019 (the fifth) and 2019 (the sixth), change approval timelines, inspections, transferable development rights and lifts, and the 2017 amendment cut the share of soft paving round multi-storeyed buildings from 50% to 40%; the tenth (March 2024) and eleventh (27 April 2026) were seen only in summaries, the eleventh raising permitted ground coverage to 65% for commercial and industrial plots (as reported) [TBC]. None of them touches the river-front, basement or rainwater harvesting byelaws. The byelaws set no design storm, return period, release rate or detention volume, and no "zero runoff" rule. They make rainwater harvesting mandatory on plots of 300 m² and more, with recharge pits or trenches of at least 6 m³ for every 100 m² of roof (byelaw 51.1); bar construction within the boundary of a river, within a strip of 10–15 m from the outer boundary of rivers other than the Ganga, and, on the Ganga, within its boundary or a larger distance the State prescribes (byelaws 23.1 to 23.3), although the list of rivers to which byelaw 23.2 applies, which the State "shall notify", was not found [TBC]; refuse permission in the natural waterways and drains shown in the Development Plan and drainage plan (30.1); and bar basements in low-lying and flood-prone areas (48.1) without defining either term. In Jharkhand the route of Clause 1.3.1(a) therefore runs through UD&HD, which would amend the 2016 byelaws under section 434, as it has done for each earlier amendment. This Manual is a draft; neither the Government nor any authority has adopted it. MoHUA told Parliament in July 2026 that urban flooding "falls under the purview of the State Governments and the ULBs" and listed the CPHEEO manual among "advisory guidelines" (Lok Sabha AU1847). The State therefore needs no central approval to adopt higher standards. CPHEEO's Note 2 to Table 4.1 (§4.4.1.4) allows "a high powered committee constituted by State/UT Government through a notification" to adopt higher return periods. Clause 1.3.2 uses that route so that higher standards are on record for centrally funded schemes.


1.4 Definitions

1.4.1 The following terms apply throughout this Manual. Chapter-specific terms are defined in each chapter (for example Clause 2.2).

Term Meaning in this Manual
Approving Authority (the Authority) The body that grants planning permission, building permit or layout approval for a development, or that sanctions a public work: the Authority that approves the building plan or layout for the site under the JBBL 2016, which applies to every urban local body, regional development authority, the Mineral Area Development Authority (MADA) and the Industrial Area Development Authorities (byelaw 1.2): within municipal limits, the Municipal Corporation, Nagar Parishad or Nagar Panchayat; outside the limits of the Ranchi Municipal Corporation, RRDA in the Ranchi Regional Development Area (Jharkhand Municipal Act 2011, s.615(3)); MADA in its area; an Industrial Area Development Authority in its industrial areas; and, in Jamshedpur, the body that administers the industrial town notified on 23 December 2023, or the Jamshedpur Notified Area Committee (JNAC) while it acts (the division of these powers, including in the panchayat areas around Ranchi, is to be confirmed [TBC]), or a department for its own works.
Applicant The owner, developer or department that seeks approval, and its successors in title.
Development Any building, layout, sub-division, road, paving or land-use change that requires approval under the Jharkhand Building Byelaws 2016 or that is executed as a public work.
Redevelopment Development on a site where impervious cover already exists.
Land disturbance Clearing, grading, excavation, filling or paving of land, measured in plan area over the whole of a common plan of development (Clause 1.5.5).
Impervious area Roofs, paving, compacted gravel, decks and other surfaces that prevent infiltration. Permeable paving designed to Chapter 8 is counted as pervious only for the area it treats.
New or replaced impervious area Impervious area created, or removed and rebuilt down to the subgrade, by the development. Resurfacing that leaves the base in place is not "replaced".
Retention Permanent removal of runoff from the drainage system on site, by infiltration, reuse or evapotranspiration (Chapter 4).
Detention Temporary storage of runoff with a controlled outlet, emptied after the storm (Chapter 4).
Rainwater harvesting (RWH) Collection of rainfall for supply or recharge under the RWH mandate. RWH storage is not detention unless Chapter 4 allows it.
Minor system Drains, pipes and inlets designed for the minor-system AEP of Chapter 6.
Major system The overland and floodway path that carries the 1% AEP (100-yr) flow (Chapter 6).
Pre-development condition Greenfield: open land in good condition for the mapped hydrologic soil group. Existing impervious cover is not counted (Chapter 3).
Flood-sensitive catchment The catchment of the Harmu river in Ranchi to its confluence with the Subarnarekha, with the Argora nala and the other nalas and drains that join it, and the low-lying colonies of Ranchi that drain to the Harmu, the Jumar, the Potpoto and the Hinoo and flood in heavy rain; the land of Jamshedpur, Adityapur, Mango, Jugsalai and Bagbera that drains to the Subarnarekha and the Kharkai, whose outfalls are held up when the rivers are high; the Dhanbad–Jharia subsidence belt, the land of Dhanbad, Jharia, Katras and Sindri in the Jharia coalfield that drains to subsidence hollows, mine voids or the Katri, the Jamunia and the Khudia, including the low-lying wards 25, 26, 28 and 29 of Dhanbad; the land of Sahebganj and Rajmahal that drains to the Ganga, including the diara, whose outfalls are held up when the Ganga is high; and the catchments of the drains of the Deoghar Municipal Corporation area, and any catchment the Authority notifies (Chapter 4; Annex 1B).
Waterbody A river, stream, canal, tank (talab), lake, pond, marsh, supply channel or surplus course, whether perennial or seasonal (Chapter 7).
Regional facility A detention, retention or tank storage facility serving more than one development, built or restored under a basin plan (Chapter 4).
Tier A / Tier B authority An Approving Authority classed under Clause 1.6.
Policy supplement The set of adoptable alternative clauses in Clause 1.7 and Annex 1C.
Drainage report The preliminary or final report required by Chapter 10.
Registered professional A person registered under the Jharkhand Building Byelaws 2016 to prepare and sign the relevant plans, with any further qualification required by Clause 10.6.
Compliance calculator The State-issued tool for computing and reporting compliance (Clause 10.5).
Maintenance declaration The registered undertaking by an owner to maintain a stormwater facility (Clause 10.10).
Variance Approval to depart from a numeric requirement, with equivalent performance shown (Clause 1.10).
Waiver Approval that a requirement does not apply to a site, on the grounds in Clause 1.10.
Notified Published by the Government or the State Stormwater Technical Committee in the Jharkhand Gazette.

Commentary. "Replaced" impervious area is defined to the subgrade so that redevelopment of a fully paved site is captured, while routine resurfacing is not. This follows the approach of the APWA 5600 (2025.01) redevelopment triggers (MARC Supplement, 2025).


1.5 Applicability

1.5.1 Who is covered. This Manual applies to:

  • (a) all development requiring planning permission, building permit or layout approval under the Jharkhand Building Byelaws 2016;
  • (b) all drainage, road, bridge, culvert, waterbody and flood-mitigation works executed by a ULB, a State department, a board, or a State undertaking; and
  • (c) works executed by Central agencies or their contractors within Jharkhand, to the extent that the Authority's approval or no-objection is required.

1.5.2 Retention and detention threshold. Chapters 4 and 5 (retention, detention, downstream and tailwater analysis) apply to any development that, over the common plan of development, involves:

  • (a) land disturbance of 0.1 ha or more; or
  • (b) new or replaced impervious area of 500 m² or more.

1.5.3 RWH. The existing RWH mandate continues to apply under byelaw 51.1 of the JBBL 2016 to plots of 300 m² and more, with recharge pits or trenches of at least 6 m³ for every 100 m² of roof area; under byelaw 58.6.6 to multi-storeyed buildings, which need a recharge well to NBC norms; and, in Ranchi, under the Corporation's rainwater harvesting regulation of 2016, reported to use the same 300 m² threshold with a penalty of 1.5 times the annual holding tax (text not read [TBC]), as now. This Manual does not change it.

1.5.4 Provisions that apply at every size. The following apply to all development under Clause 1.5.1, whatever its size, unless exempted by Clause 1.5.8:

  • (a) no sewage connection to a storm drain (Chapter 8);
  • (b) lowest habitable floor and openings at or above the 1% AEP level plus 0.5 m, where a 1% AEP level is mapped or determinable (Chapter 6);
  • (c) waterbody setbacks and the no-fill zone (Chapter 7); and
  • (d) no obstruction of a natural drainage path or major-system flow path (Chapter 6).

1.5.5 Common plan of development. The thresholds of Clause 1.5.2 apply to the total area of a development, including all phases, plots and sub-divisions under one layout approval or one ownership at the date of application. A development shall not be divided to avoid the thresholds.

1.5.6 Redevelopment. For redevelopment, the thresholds apply to new plus replaced impervious area. Retention and detention apply to the whole of the new and replaced impervious area, and the pre-development condition is greenfield (Clause 1.4). Where greenfield control cannot be achieved on a constrained redevelopment site, the relief route of Clause 4.5.6 applies: a minimum on-site cut of 50% from existing peaks, with the shortfall paid as fee-in-lieu into basin storage.

1.5.7 Linear public works. For roads, widening and other linear works, the impervious area threshold applies to the added impervious area within each drainage catchment crossed. Retention and detention shall be provided within the right of way, or in a regional facility under Chapter 4, where the right of way cannot hold them.

1.5.8 Exemptions. The following are exempt from Chapters 4 and 5:

  • (a) a single dwelling on its own plot, where the thresholds of Clause 1.5.2 are not met; and
  • (b) linear road resurfacing that adds no impervious area.

Exempt development remains subject to the RWH mandate and to Clause 1.5.4.

1.5.9 Applicability determination. The Applicant shall record the applicability decision on Form 1-1 (Applicability Determination) with the first submittal under Chapter 10. The Authority may confirm or correct it at the pre-application stage.

Figure 1.2 — Applicability decision flowchart Flowchart for Clause 1.5: approval test, exemption test, size threshold test, and flood-sensitive catchment test, leading to the requirements that apply. Development or public work (Clause 1.5.1) Needs building-rules approval, or is it a public work? No Manual not triggered; other rules apply Yes Exempt under Clause 1.5.8? (single dwelling below the threshold, or road resurfacing that adds no impervious area) Yes Exempt from Chapters 4–5. RWH (where mandated) and Clause 1.5.4 still apply No Land disturbance ≥ 0.1 ha, or new or replaced impervious area ≥ 500 m² (Clause 1.5.2)? No Below threshold: RWH (where mandated) and Clause 1.5.4 apply Yes Chapters 4 and 5 apply: retention, detention, downstream and tailwater analysis (+ RWH, 1.5.4) In a flood-sensitive catchment (Annex 1B)? Yes Mixed-frequency rule; full methods only; no Policy Supplement alternatives No Standard rule: Q_post ≤ 0.9 × Q_pre Tier B: design-aid route may be used (Clause 1.7) Decision Chapters 4–5 requirements Chapters 4–5 do not apply

Figure 1.2 — Applicability decision flowchart for Clause 1.5. Original drawing for this Manual.

Commentary. The thresholds have no single direct precedent; they are set by this Manual. Precedents span a wide range:

  • Singapore controls peak runoff from developments of 0.2 ha or more (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5).
  • Malaysia's 2008 DID checklist used on-site detention for sites up to 0.1 ha and community ponds above that.
  • The APWA 5600 (2025.01) Policy Supplement offers alternative triggers of ¼ acre (about 0.1 ha) disturbed, or 1 acre (about 0.4 ha) with 10,000 sq ft (about 930 m²) impervious, and warns agencies not to exceed a 1-acre trigger.
  • MBBL 2016 makes recharge mandatory for buildings over 500 m².

The 0.1 ha / 500 m² trigger sits at the strict end of these, because typical Jharkhand plots are small and the cumulative effect of many small plots is what fills Ranchi's drains. For small buildings in Jharkhand, byelaw 51.1 of the JBBL 2016 requires rainwater harvesting only on plots of 300 m² and more, with recharge pits of 6 m³ for every 100 m² of roof, about 60 mm of roof runoff; that is a pit volume, not a rule on what leaves the plot, and on the laterite and thin soils over rock of the plateau a pit that ends in hardpan may stand full. The plinth must be at least 450 mm above the surrounding ground "so located … that adequate drainage of the site is assured" (byelaw 42.1.1), with no reference to any flood level, and basements are barred in low-lying and flood-prone areas (48.1) that no instrument defines. Clause 1.5.4(b) applies to every building whatever its size for this reason.

Clause 1.5.4(b) has no direct precedent; this Manual sets it because floor levels are the cheapest protection a building can have, and it would be perverse to protect only large developments. Where no 1% AEP level is mapped, Chapter 6 gives the method for small sites.


1.6 Tiered adoption

1.6.1 Tier A authorities. The following are Tier A:

  • (a) the Ranchi Municipal Corporation (RMC), and RRDA and every other Approving Authority within the area of the Ranchi Master Plan 2037, as approved by the notification of 30 November 2015 and as revised from time to time;
  • (b) every other Municipal Corporation constituted under the Jharkhand Municipal Act 2011, as constituted from time to time, among them those of Dhanbad, Deoghar, Chas, Hazaribagh, Giridih, Adityapur, Mango and Medininagar, with every other Approving Authority within its limits; and
  • (c) MADA in its area, and the body that grants building permission in Jamshedpur: the Jamshedpur Notified Area Committee (JNAC), or its successor under the industrial-town notification of 23 December 2023, which is under challenge [TBC].

1.6.2 Tier B authorities. All other Nagar Parishads and Nagar Panchayats are Tier B.

1.6.3 What differs between tiers. All criteria of this Manual apply in both tiers. The tiers differ only in method and review:

Table 1.1 — Differences between Tier A and Tier B authorities

Item Tier A Tier B
Performance criteria (Chapters 2–9) Apply in full Apply in full
Hydrologic method for storage Hydrograph method (Chapter 3) Hydrograph method, or the design-aid route of Clause 1.7 where eligible
Compliance calculator (Clause 10.5) Required as a summary Required; may be the sole calculation on the design-aid route
Policy supplement alternatives (Clause 1.7) Only with State Stormwater Technical Committee concurrence May be adopted by council resolution
Technical review By the Authority By the Authority, with UD&HD regional support or an empanelled reviewer (Clause 10.7)
Flood-sensitive catchment rule Applies Applies

1.6.4 Moving between tiers. A Tier B authority may opt into Tier A by council resolution. The Government may notify a Tier B authority as Tier A when it becomes a Corporation, joins the Ranchi Master Plan 2037 area, or is found by a post-event review (Clause 10.16) to need the full methods.

1.6.5 Flood-sensitive catchments override tier. In a flood-sensitive catchment, whatever the tier, the alternatives of Clause 1.7 are available only as Table 1.2 allows: S-1 (the design-aid route) for sites of 0.5 ha or less (Clause 4.14.1), and S-5 fee-in-lieu where a basin plan has been notified (Clause 1.10.3(d)). S-2, S-3 and S-4 are not available.

Commentary. Ranchi Municipal Corporation, with its engineering wing and some 1,400 km of drains, more than half of them uncovered (as reported), beside JUIDCO, which builds the trunk works, and a small Nagar Panchayat with one assistant engineer cannot be asked to review the same hydrograph models. The Kansas City solution was to keep one regional standard and publish adoptable alternatives for the most contested criteria, so that smaller agencies can "opt down" without leaving the standard (MARC Supplement, Nov 2025). The tiers here keep the performance criteria the same in both tiers and vary only the method, so that a building in a Tier B town is protected to the same level as one in Ranchi.


1.7 Policy supplement: adoptable alternatives

1.7.1 The Government shall publish, with this Manual, a Policy Supplement (Annex 1C) of alternative clauses. An Approving Authority may adopt one or more alternatives under the conditions in Clause 1.7.3.

1.7.2 The alternatives are:

Table 1.2 — Policy supplement: adoptable alternatives S-1 to S-5

No. Main-text requirement Adoptable alternative Eligibility
S-1 Storage sized by hydrograph method (Chapter 3) Design-aid route: retention and detention volumes taken from the unit-storage tables (m³ per ha, by rainfall zone, soil group and impervious fraction) in Annex 4 and the compliance calculator Sites ≤ 2 ha outside flood-sensitive catchments; ≤ 0.5 ha within them (as Clause 4.14.1)
S-2 Release rate Q_post(T) ≤ 0.9 × Q_pre(T), computed for the site Permissible site discharge (PSD): a tabulated unit-area release rate (m³/s/ha) by zone and AEP, derived from the 0.9 × Q_pre rule Any site outside flood-sensitive catchments
S-3 Waterbody setback extended to the mapped 1% AEP flood extent plus margin (Chapter 7) Fixed-width setback table by waterbody class, where no 1% AEP extent is mapped. Never less than the Zone 1 minimum of Clause 7.4.7 Waterbodies with no mapped 1% AEP extent
S-4 Downstream analysis by hydraulic model (Chapter 5) Screening checklist of downstream capacity and known flooding, with a model only where the screen fails Sites < 1 ha, outside flood-sensitive catchments, not discharging to a tidal outfall
S-5 On-site detention Fee-in-lieu toward a regional facility or restored tank storage in a master-planned basin (Chapter 4) Where a basin plan has been notified

1.7.3 Conditions on adoption.

  • (a) An alternative shall not lower any criterion below the values of this Manual. S-1 and S-2 are simplified methods for meeting the same criterion. They are not lower criteria.
  • (b) A Tier B authority adopts an alternative by council resolution, sent to the State Stormwater Technical Committee within 30 days. A Tier A authority needs the Committee's concurrence before adoption.
  • (c) The adopted alternatives shall be published on the Authority's website and in the register of Clause 10.17.
  • (d) Retention (Annex 2E depth) cannot be replaced by any alternative, except where fee-in-lieu under S-5 funds equivalent retention in the same basin.
  • (e) The tables for S-1, S-2 and S-3 shall be issued by the State Stormwater Technical Committee, and reviewed with Chapter 2 (Clause 2.14).

Commentary. The supplement follows the model of the APWA 5600 (2025.01) Policy Supplement, which gives alternatives for the four most contested criteria (applicability, Rational Method limits, stream setback trigger, and Zone 2 setback width). Two of those map onto S-3 and onto the applicability threshold of Clause 1.5.2. Alternative S-3 copies the APWA answer to the same problem: the 1% AEP extent is not mapped for small drainage areas, so a fixed-width table is offered. S-2 follows the Kansas City 2011 shift from "match existing" to fixed unit-area release rates. Local agencies preferred a set rate because existing conditions were hard to determine consistently (MARC Evolution deck). It also reflects the Sydney Water permissible site discharge (PSD) method. The 2 ha / 0.5 ha limits for S-1 (matching Clause 4.14.1) and the 1 ha limit for S-4 have no direct precedent; they are set by this Manual.


1.8 Relationship with other instruments

1.8.1 This Manual shall be applied together with the instruments below. Where they overlap, Clause 1.3.3 governs.

Table 1.3 — Relationship with other instruments

Instrument Relationship
Jharkhand Building Byelaws, 2016 (UD&HD; Notification No. 7/न0वि0/अधि0/स0सो0/102/2013-2006 of 5 April 2016, under section 434 of the Jharkhand Municipal Act 2011), with the amendments of 15 May 2017, 17 August 2017 (second), 6 June 2019 (fifth) and 2019 (sixth), and the tenth (March 2024) and eleventh (27 April 2026) amendments, seen only in summaries [TBC] Continue. They apply to every urban local body, regional development authority, MADA and Industrial Area Development Authority (byelaw 1.2). They bar any building within the boundary of a river (23.3); on the Ganga, within the river boundary or such higher distance as the State prescribes (23.1); and on other rivers within a strip of "10-15 metres (where area is open and not develop 15m. up to)" from the outer boundary, "as prescribed by the Irrigation Department", for a list of rivers that the State "shall notify" (23.2) and that was not found [TBC]; but they let a Planning Authority or Government body undertake riverfront development "on reclaimed lands" with the Government's approval (23.4). They refuse permission in natural waterways and drains shown in the Development Plan and drainage plan (30.1), over or under a municipal drain (30.3), and where structural plans in an area that floods do not take flooding into account (30.5); require land within the curtilage to be drained by surface-water drains where the Authority so requires, and its written approval to connect a surface-water drain to a sewer (31.3–31.4); set a plinth of at least 450 mm (42.1.1); and bar basements in low-lying areas without adequate drainage and in flood-prone areas, and require that surface drainage not enter a basement (48.1, 48.6.4). They set no design storm, release rate or detention volume. The 10–15 m strip is the only metre value they set; the design criteria of Chapters 2–6 and the hydraulic corridor and setbacks of Chapter 7, whose Zone 1 is at least 15 m, are this Manual's proposals; they are not statutory values, and no authority has adopted them. Where the byelaws, a master plan or a statute are stricter, they govern (Clause 1.3.3).
Rainwater harvesting and soft paving: JBBL 2016, byelaws 51.1, 58.6.6 and 58.6.15; the rainwater harvesting regulation of the Ranchi Municipal Corporation (2016) and a Jharkhand regulation of 2017 (both as reported) Continue unchanged. Byelaw 51.1 makes rainwater harvesting mandatory "for 300 sqm. and above size of plots", with recharge pits or trenches of at least 6 m³ for every 100 m² of roof area, filled with pebbles, brick jali or river sand; terrace collection to a sump through a filter with a first-flush valve, and replacing topsoil with river sand, are optional. Multi-storeyed buildings need a recharge well "as per NBC norms" (58.6.6), and soft paving on at least 40% of the paving round them (58.6.15, as amended in 2017). Ranchi's regulation is reported to apply to plots of 300 m² and more, with a penalty of 1.5 times the annual holding tax (as reported); neither regulation's text was read [TBC]. None of these gives an outlet rule or a storage that is empty when a storm arrives. RWH storage is not detention unless it is a dedicated empty-on-arrival volume with an outlet, and tanks are assumed full at the start of SW monsoon storms (Chapter 4). Recharge structures may count toward retention only where they meet Chapters 4 and 8, which allow none in mine-disturbed ground, on floodplains or where the water table is shallow.
Jharkhand Municipal Act, 2011 (Jharkhand Act 07 of 2012), ss.70, 203, 219, 221, 222, 224, 227, 235, 341, 358, 434, 481 and 615 Continue. "Storm water drains" are a municipal function (s.70); the municipality shall "construct and maintain drains … and provide a safe and efficient outfall … for effectual drainage and proper discharge of storm-water and sewage … in such manner as may not cause any nuisance, whether by flooding" (s.219); all public drains and drains along streets vest in it (s.221), and it may make them over to another authority with the State's approval (s.222); the Commissioner or Executive Officer may require "an entirely separate drain for rain water" (s.224); no premises may be erected or occupied without a drain of the size, level and fall he requires, emptying into a municipal drain not more than 30 m away (s.227); no structure may be built on a municipal drain without permission (s.235); and land not drained to his satisfaction may be ordered drained (s.358). Public tanks and the land appertaining to them vest in the municipality (s.203), but it may order a private tank or pool to be filled up (s.341). RRDA's operation ceases within the limits of the Ranchi Municipal Corporation (s.615(3)), and MADA's operations vest in the Dhanbad Municipal Corporation "to the extent notified" (s.615(4)); no such notification was found [TBC]. Section 481 provides for industrial townships (Clause 1.9). This Manual does not change those powers; Chapter 7 treats tanks as drainage assets.
Ranchi Master Plan 2037 (UD&HD Notification No. 02/न0वि0/मास्टर प्लान-104/2008-4371 of 30 November 2015, under section 24(1) of the Jharkhand Regional Development Authority Act, 1981, as adopted); Jamshedpur (UA) Master Plan 2027 (23 October 2017) and Dhanbad Master Plan 2041 (24 October 2017), under section 33 of the Jharkhand Town Planning and Improvement Trust Act, 2002, as adopted Continue. Condition 2.9 of the Ranchi approval bars any construction within 20 m of the full tank level round the Kanke, Dhurwa and Rukka dams, a distance that does not count as setback, and within at least 10–15 m of rivers and natural nalas as space allows, with a strip at least 10 m wide barred in every case; the plan covers 652.02 km² (condition 3.1). The Jamshedpur and Dhanbad approvals, read only in part, record 1,280.00 ha and 2,283.53 ha of existing water area, and the Jamshedpur plan proposes 1,186.31 ha. Where a master-plan line is wider than the setback of Chapter 7, it governs (Clause 1.3.3).
Jamshedpur: the lease between the Government and Tata Steel of 20 August 2005, and the notification of 23 December 2023 of an industrial town under section 481 of the Jharkhand Municipal Act 2011 The lease obliges Tata Steel to "continue to maintain the standard of municipal services and civic amenities" in the leased area, but names no drain or storm water (third-party copy). The 2023 notification is reported to amalgamate JNAC with Tata Steel facilities into an industrial town; it is under challenge in PIL 2636/2024 in the High Court, and its text and the outcome of the case were not read [TBC]. This Manual applies to the Approving Authority for the site, whichever body that is (Clause 1.4).
Chota Nagpur Tenancy Act, 1908 and Santhal Parganas Tenancy (Supplementary Provisions) Act, 1949; Jharkhand (Bihar) Public Land Encroachment Act, 1956 Continue. The tenancy Acts restrict the transfer of a raiyat's holding (CNT Act s.46; SPT Act s.20, as summarised; texts not read [TBC]), so land for a regional detention site, a drainage reserve or an outfall is found first on public land, road reserves, existing tanks and nala buffers, or by acquisition, and transferable development rights under the Jharkhand Transferable Development Rights Rules, 2017, which count land surrendered for drainage. Under the 1956 Act the Circle Officers of Jamshedpur and Mango ordered 56 structures within 15 m of the Subarnarekha demolished in May 2025 (as reported).
Floodplains: no floodplain zoning law and no notified flood zone Jharkhand has no floodplain zoning law. WRD has appointed a consultant to demarcate the floodplain of the Ganga, about 83 km of which flows through Sahebganj district, and was awaiting hydrology from the National Hydrology Project "by march 2024" (State report to the NGT in O.A. 200/2014); no Subarnarekha floodplain has been designated, so the NGT's Joint Committee in O.A. 145/2023 (EZ) applied the 10–15 m of byelaw 23.2 at Jamshedpur (report of 14 March 2024, as quoted). Until a 1% AEP extent is mapped, the hydraulic corridor and setbacks of Chapter 7 are this Manual's proposal, disclosed as such; the master-plan and byelaw lines apply where they bind and are wider.
Wetlands (Conservation and Management) Rules, 2017; the Jharkhand State Wetlands Authority (notification No. 1079 of 10 March 2017, reconstituted on 22 May 2018); Udhwa Lake Bird Sanctuary (Ramsar site) Continue. The Rules bar construction of a permanent nature, except boat jetties, within 50 m of the mean high flood level of a notified wetland, but no wetland had been notified in Jharkhand as of 13 February 2025 (Rajya Sabha reply), and a draft notification of 44 wetlands was reported in 2023 (as reported). Udhwa Lake, 935.5 ha in Sahebganj district, is the State's only Ramsar site, with a designation date of 8 January 2024 in its Ramsar Information Sheet; its designation was announced on 2 February 2025 (as reported). Where a notification is wider than the setback of Chapter 7, it governs (Clause 1.3.3).
High Court of Jharkhand, W.P.(PIL) 1325 of 2011 (rivers) and W.P.(PIL) 1463 of 2020 (the water bodies of Ranchi) Continue to bind. In 2013 the Court found that "nothing has been done … except some paper orders" on the Subarnarekha and the Kharkai and directed the Chief Secretary to report on encroachment and the reclamation of the rivers (Order No. 33, 16 April 2013). On 31 July 2025 it ordered encroachments removed from Ranchi's water bodies and their catchments and their surroundings fenced as no-entry zones, and in August 2025 set up a committee to monitor encroachment (as reported); its later orders, including that of 7 January 2026, were not read [TBC]. Chapter 7 applies these orders where they are stricter.
Mining: environmental clearance conditions of coal mines; Coal Mines Regulations, 2017, reg. 149; Ministry of Coal guidelines for mining plans and mine closure plans (29 May 2020); the Jharia Master Plan (2009, revised 25 June 2025) Continue; they govern the leasehold, not the town. Clearance conditions require garland drains "keeping at least 50% safety margin over and above the peak sudden rainfall and maximum discharge", settling ponds, and no alteration of major water channels (standard coal-sector text, as in a clearance of 13 August 2024 for a mine outside the State). Regulation 149 is reported to require the lowest point at which surface water could enter a mine to be at least 1.5 m above the highest flood level there (as reported; Gazette text not read [TBC]). The closure guidelines list "Excavated Void" and "Water Body" among post-closure land uses. No drainage or waterlogging content was found in either Jharia plan. Under Chapters 5 and 7, no development drains into an active mine, and a mine void is not a design outfall or storage without the lessee's and DGMS's consent and a survey of its level and spill.
Jharkhand Urban Water Conservation and Drinking Water Regulatory Authority Act, 2016 (Jharkhand Act 04 of 2017) Its objects include rainwater harvesting and the recharge and conservation of surface water; whether the Authority has been constituted was not found [TBC].
Disaster Management Act, 2005; JSDMA Continue. No State disaster management plan text, urban flood plan or SOP of JSDMA was found [TBC], and no State order fixing a date for pre-monsoon desilting was found; Ranchi's drains are reported to be cleaned "by early June" (as reported). Chapter 10 sets the pre-monsoon dates.
CPHEEO Manual on Storm Water Drainage Systems (2019) Engineering reference. This Manual sets higher return periods under Clause 1.3.2.
NDMA Guidelines on Management of Urban Flooding (2010) and MoHUA SOP (2017) This Manual puts into effect the NDMA directives on catchment-based design, detention and retention, waterbody protection and climate-adjusted IDF.
NDMA Urban Flood Risk Management Programme (UFRMP) and AMRUT 2.0 Works funded under these programmes shall comply with this Manual. The development controls of Chapters 4–5 protect the capacity those works create.
IRC:SP:42-2014 and IRC:SP:50-2013 Apply to road drainage only where they do not conflict with Chapter 6.
MBBL 2016, Chapter 9 Model for RWH and for the inspection regime in Chapter 10.

Commentary. RWH in Jharkhand is framed as a water supply and recharge measure. It works well for that purpose. It cannot, however, be relied on for flood control in the SW monsoon, because RWH sumps are usually full or the ground saturated by the time a July to September monsoon depression or the remnant of a Bay of Bengal cyclone arrives after weeks of rain. The Manual therefore keeps harvest volume and attenuation volume apart, while letting recharge count as retention where it truly removes water from the system.

Jharkhand has spent on drainage without a design standard. The Harmu river scheme in Ranchi cost ₹92.78 crore and was completed in October 2018, and a committee found in 2019 that it had produced "no visible results"; the Ranchi sewerage and drainage project, begun in 2005, contracted 207 km of storm drains for ₹129.10 crore and built 1.49 km, and the Cabinet has sanctioned ₹31.17 crore to revise its plan (CAG Report No. 1 of 2023); and the World Bank-financed drainage of Dhanbad and Sindri was planned as 153.95 km of new drains with 94 outfalls, 19 of them into ponds, designed for a 1-year storm (JUIDCO, 2017). None of these works has a published design basis that meets the return periods of Table 2.1, and no development-control condition stops new plots in the same catchments from using up the capacity such works create. Linking Chapters 4–5 to approvals closes that gap.

The State's law already holds many of the tools. It bars building within the boundary of a river and within 10–15 m of it, and basements in flood-prone areas (JBBL 2016); bars construction within 20 m of the full tank level of Ranchi's three dams and within 10 m of every river and natural nala in the Ranchi Master Plan 2037 area; makes storm-water drains an express municipal duty, vests public drains and tanks in the municipality, and lets it require separate drains for rain water and a drain to a municipal drain before a building is occupied (Jharkhand Municipal Act 2011, ss.70, 219, 221, 203, 224 and 227); and recovers public land from encroachment (Public Land Encroachment Act, 1956). The High Court and the NGT have filled some gaps case by case. What it lacks is a design standard. None of these instruments says how large a drain must be, which storm it must carry, where a river's flood line lies, which land is "flood prone" for the basement rule, or how much storage a filled talab, a paved plot or a mine dump removes or adds. This Manual is offered as a technical companion to these instruments and to the drainage works of JUIDCO and the Municipal Corporations: it supplies the design storm, detention and buffer numbers they do not set, as a proposal for the Government and the authorities to consider. Neither UD&HD nor any other body has adopted it.


1.9 Roles and responsibilities

1.9.1 The responsibilities below apply under this Manual. They do not change any agency's statutory powers.

Table 1.4 — Roles and responsibilities under this Manual

Agency Role under this Manual
Urban Development and Housing Department (UD&HD) Notifies the building byelaws under section 434 of the Jharkhand Municipal Act 2011, as it did the JBBL 2016 and their amendments, and constitutes the Building Bye-laws Review Committee; approves the master plans of Ranchi, Jamshedpur and Dhanbad; oversees the Municipal Corporations, Nagar Parishads and Nagar Panchayats, JUIDCO, the State Urban Development Agency and RRDA; sanctions drainage schemes. Would make the amendment of Clause 1.3.1(a), issue the model ULB bye-law of Clause 1.3.1(b), give regional support to Tier B authorities (Table 1.1) and maintain the empanelled reviewer list (Clause 10.7).
State Stormwater Technical Committee (Clause 1.3.2) Would adopt higher standards, issue Annexes, tables and the compliance calculator, concur with Tier A alternatives, decide variances referred to it and review the Manual (Clause 1.12).
Ranchi Municipal Corporation (RMC) and the other Municipal Corporations (Dhanbad, Deoghar, Chas, Hazaribagh, Giridih, Adityapur, Mango and Medininagar); Nagar Parishads and Nagar Panchayats Hold the public drains and public tanks of their areas by statute (Jharkhand Municipal Act 2011, ss.221 and 203), with storm-water drains an express function (s.70) and a duty to provide a safe outfall (s.219); clean and maintain them; and grant building permission under the JBBL 2016. RMC executed the Ranchi storm-drain contract that the CAG examined. Would apply this Manual to their works, receive handed-over assets (Clause 10.14), and inspect and enforce (Clauses 10.12–10.15).
Jharkhand Urban Infrastructure Development Company (JUIDCO) A company of UD&HD; executes trunk drainage and river schemes, among them the Harmu river scheme in Ranchi, whose operation and maintenance it still held in 2022, the drainage of Dhanbad and Sindri, and AMRUT works. Would apply this Manual in its DPRs and designs, and hand over completed assets with their records (Clause 10.14).
Ranchi Regional Development Authority (RRDA) Prepared the Ranchi Master Plan 2037 under the Jharkhand Regional Development Authority Act (as adopted) and grants permission in the Ranchi Regional Development Area outside the limits of RMC, where its operation has ceased (Jharkhand Municipal Act 2011, s.615(3)); the High Court held in 2025 that the Panchayati Raj Act prevails over its Act in panchayat areas (as reported). Would show flood-sensitive catchments, nala reserves and regional facility sites in its plans.
The Jamshedpur civic body (JNAC, or its successor under the industrial-town notification of 23 December 2023, under challenge) and Tata Steel Utilities and Infrastructure Services (Tata Steel UISL) JNAC is the statutory civic body of the notified area; Tata Steel UISL provides the civic services of the leased area for Tata Steel, including pre-monsoon desilting (as reported), under a lease that names no drain (2005). Who is legally responsible for the storm drains of the leased area is to be confirmed [TBC]. Would apply this Manual to the drains and outfalls of the leased area and record which body holds each.
Mineral Area Development Authority (MADA) Applies the JBBL 2016 in its area of the Dhanbad coalfield; its operations are to vest in the Dhanbad Municipal Corporation to the extent notified (s.615(4)), but no notification was found [TBC]. Would apply this Manual to approvals and works in its area.
Water Resources Department (WRD) Holds the rivers, dams, reservoirs and flood-control works, including the Kanke, Hatia (Dhurwa), Getalsud and Chandil dams; prescribes the river boundary from which byelaw 23 is measured; has appointed a consultant to demarcate the Ganga floodplain. Would provide design river and reservoir levels and gate-operation rules for Chapter 5, consent to outfalls into its rivers and reservoirs, and demarcate floodplains for Chapter 7.
Drinking Water and Sanitation Department Supplies drinking water and rural sanitation, and is treated as the State's groundwater agency for this Manual; the State told the NGT in 2024 that the Ground Water Directorate at Ranchi issues no permissions and that CGWB issues the NOCs. Would supply groundwater levels and quality for the infiltration and recharge checks of Chapters 4 and 8, with CGWB, and consent to works at any reservoir from which it draws water [TBC].
Damodar Valley Corporation (DVC), a body of the Union Operates the Tilaiya, Konar, Maithon and Panchet dams in the State; the releases of Maithon and Panchet are advised by the Damodar Valley Reservoir Regulation Committee, on which the State and CWC sit (as reported). Would supply reservoir levels, release records and release scenarios for the tailwater checks of Chapter 5 on the Damodar and the Barakar.
JSDMA and the District Disaster Management Authorities Approve the State and district disaster management plans. Would recommend flood-sensitive catchments, hold the record of flood-prone locations with the Deputy Commissioners, and lead the post-event review (Clause 10.16). No urban flood plan or SOP of JSDMA was found [TBC].
Jharkhand State Pollution Control Board (JSPCB) Monitors the rivers and drains, examined the pollution of the Subarnarekha, the Kharkai and the Damodar on the High Court's direction (2013), and has directed a coal company to build the garland drains and retaining walls its clearance required (counter-affidavit in NGT O.A. 38/2020 (EZ)). Supports the removal of sewage from storm drains (Chapter 8) and the control of mine runoff (Chapter 8).
Coal companies (CCL, BCCL and other lessees) and the Directorate General of Mines Safety (DGMS), a body of the Union The lessees build and maintain the garland drains, settling ponds, toe walls and embankments that their environmental clearances require, and hold the mine voids, pit lakes and overburden dumps; DGMS regulates the danger of inundation of mines (Coal Mines Regulations 2017, reg. 149, as reported). Their consent is needed before any mine void is used as an outfall or as storage (Chapters 5 and 7).
Forest, Environment and Climate Change Department and the Jharkhand State Wetlands Authority The Authority, chaired by the Minister for Forest, Environment and Climate Change with the Secretaries of UD&HD, WRD and Revenue among its members, implements the Wetlands Rules 2017 and proposes wetlands for notification. Would keep the list of notified wetlands and permit regulated activities in their zones (Chapter 7).
Revenue, Registration and Land Reforms Department: the Deputy Commissioners, the Sub-Divisional Officers and the Circle Officers of each anchal (circle) Keep the land records (khatiyan) in which tanks, nalas and rivers are recorded; remove encroachment from public land under the 1956 Act; administer the restrictions of the Chota Nagpur and Santhal Parganas tenancy laws; lead flood relief. Would certify the recorded extent of a talab or nala for Chapter 7.
Central Water Commission (CWC), a body of the Union Publishes the Flood Estimation Reports for subzones 1(d), 1(g) and 3(d) used in Chapters 2 and 3, and the river levels at its flood forecasting and monitoring sites, such as Jamshedpur on the Subarnarekha, Sahibganj on the Ganga, Daltonganj on the North Koel and Ramgarh and Pupunki on the Damodar. Would supply river stage records and forecasts for Chapter 5.
Central Ground Water Board (CGWB), a body of the Union Assesses the groundwater units of the State and their categories, among them the over-exploited Jamshedpur Urban, Golmuri-cum-Jugsalai, Baliapur and Bermo units and the critical Dhanbad Urban and Topchanchi units (2023), and the fluoride and arsenic in groundwater. Would supply groundwater levels and quality with the Drinking Water and Sanitation Department.
IMD (Meteorological Centre Ranchi), and road and rail owners (the Road Construction Department, NHAI, Indian Railways) IMD's stations supply the rainfall records of Chapter 2. Road and rail owners would apply this Manual to road drainage (Chapter 6), culverts and linear works (Clause 1.5.7).

Commentary. Stormwater in Jharkhand is split by place and by tier: between UD&HD, through the byelaws, the master plans and the schemes of JUIDCO; the Municipal Corporations, Nagar Parishads and Nagar Panchayats, through the drains and tanks vested in them; RRDA, MADA and the Industrial Area Development Authorities outside municipal limits; Tata Steel and its utility company in the leased area of Jamshedpur; WRD, through the rivers and the dams; DVC, through the reservoirs of the Damodar valley; and the coal companies, through the drains, voids and dumps of their leases, with the High Court and the NGT setting the lines along the Subarnarekha and round the water bodies of Ranchi. Ranchi shows why the split matters. The Harmu is a river, whose boundary WRD prescribes for byelaw 23; its channel was rebuilt by JUIDCO, which still held its maintenance in 2022; the drains and nalas that enter it vest in RMC; and of its 14 major inlets, the nine connected to the sewers overflowed into it even in the dry season (CAG Report No. 1 of 2023). No rule or order found divides natural nalas and urban rivers from municipal drains, or the drains of the leased area of Jamshedpur from those of JNAC and the Municipal Corporations of Mango and Adityapur [TBC]; Tata Steel UISL is reported to have declined to clean drains in Mango as the Corporation's duty (as reported). Until such a rule is made, this Manual assigns the drainage elements as in Table 1.5. The assignment is this Manual's working split for applying its clauses; it does not change any agency's powers.

Table 1.5 — Working assignment of drainage elements under this Manual

Element Assigned to
Rivers and their floodplains, including the urban rivers of Ranchi (the Harmu, the Jumar, the Potpoto and the Hinoo) below the point where a natural nala becomes a river, and the dams, reservoirs and flood-control works of the State WRD
The reservoirs of the Damodar Valley Corporation and their releases DVC
Trunk drains and river schemes built by JUIDCO, until handed over to the local body JUIDCO
Natural nalas, street and public drains and public tanks within the limits of a local body The Municipal Corporation, Nagar Parishad or Nagar Panchayat
Drains, nalas and tanks in the leased area of Jamshedpur The body that administers the area under the 2023 notification, or JNAC, with Tata Steel UISL as service provider, until the legal holder is confirmed [TBC]
Drains within an industrial area The Industrial Area Development Authority
Drains, nalas and tanks outside municipal limits in the Ranchi Regional Development Area or the area of MADA RRDA or MADA, with the Gram Panchayat where the Panchayati Raj Act applies [TBC]
Garland drains, settling ponds, toe drains, embankments, mine voids and pit lakes within a mining lease The lessee, under its environmental clearance and DGMS
Sewers, interceptors and sewage treatment plants The local body, or JUIDCO where it executes the work
Drains of State and national highways The Road Construction Department or NHAI
Notified wetlands and the Udhwa Ramsar site The Jharkhand State Wetlands Authority, with the owner of the land

This Manual names departments and authorities as the statutes, orders and records name them. A manual that names one owner for each task does not fix institutions by itself, but it removes ambiguity about who signs what.


1.10 Variances and waivers

1.10.1 Variance. The Authority may grant a variance from a numeric requirement where the Applicant shows, through a report certified under Clause 10.6, that:

  • (a) compliance is impracticable because of site conditions such as a high groundwater table, contaminated soil, rock, or a site area too small for the required facility; and
  • (b) the proposed alternative gives equal or better performance at the downstream point of Chapter 5, or the shortfall is made up by fee-in-lieu or off-site works in the same catchment.

1.10.2 Waiver. The Authority may waive Chapter 4 detention requirements (not retention) where a hydraulic analysis certified under Clause 10.6 shows that the site discharges directly to the sea, or to a tidal reach with no flood-prone property downstream, and that undetained flow does not worsen the outfall-closed condition of Chapter 5. Jharkhand has no coast and no tidal reach, so no site in the State qualifies for this waiver. A site whose outfall is held up by a river in flood, as on the Subarnarekha and the Kharkai at Jamshedpur and the Ganga at Sahebganj, by the level of a reservoir or talab, or by a flap gate or a pump, is in the outfall-closed condition of Chapter 5 whenever the receiving water is high, and detention is not waived for it.

1.10.3 No variance or waiver. No variance or waiver shall be granted for:

  • (a) a sewage connection to a storm drain;
  • (b) the lowest habitable floor level of Chapter 6;
  • (c) any reduction of a waterbody setback below the Zone 1 minimum of Clause 7.4.7, or any fill or construction in the no-fill zone of Chapter 7; or
  • (d) the retention requirement in a flood-sensitive catchment, except by fee-in-lieu under Clause 1.7.

1.10.4 Procedure.

  • (a) The request shall be made on Form 1-2 (Variance / Waiver Request) with the preliminary drainage report.
  • (b) A Tier B authority shall refer any variance on a site of 1 ha or more to the State Stormwater Technical Committee.
  • (c) A decision shall state its reasons and any conditions, and shall be entered in the public register of Clause 10.17.
  • (d) A variance runs with the approval. It lapses if the approval lapses.

Commentary. The 2006 APWA 5600 included a waivers section (5601.6), and Georgia allows waivers where downstream analysis shows a peak control is unnecessary. The waiver of Clause 1.10.2 is narrow: on a tidal coast, undetained flow can help by passing through before the tide closes the outfall, but only an analysis can show that. This Manual requires every decision to be published because publication deters case-by-case erosion of the standard; in Jharkhand, the High Court was told in 2024 that of about 71 ponds said to have existed in Ranchi only four or five could still be seen, and in July 2025 it ordered the encroachments on the city's water bodies removed and their surroundings made "no-entry zones" (W.P.(PIL) 1463 of 2020, as reported), while the CAG found that the Harmu river had narrowed by 18.70 m at Karma Chowk bridge between 2009 and 2021 (CAG Report No. 1 of 2023).


1.11 Transition provisions

1.11.1 Effective date. This Manual takes effect for new applications 6 months after notification (the effective date).

1.11.2 Applications in process. An application filed complete before the effective date may be decided under the rules in force when it was filed, if a decision is issued within 12 months of the effective date. Otherwise, this Manual applies.

1.11.3 Phased start for Tier B. In Tier B authorities, Chapters 4 and 5 apply from 24 months after notification, except in flood-sensitive catchments, where they apply from the effective date.

1.11.4 Public works. DPRs sanctioned before the effective date may proceed as sanctioned. Any DPR revised or re-tendered after the effective date shall comply. Departments shall report non-compliant works in progress to the State Stormwater Technical Committee within 12 months.

1.11.5 Before the annexes are issued. Until an annex referred to in this Manual is issued, the Applicant shall use the method stated in the clause, with values agreed with the Authority and recorded in the drainage report.

Commentary. The 6-month lead time matches the lead time for NIH-DHAARA updates in Clause 2.14.2. Singapore gave a similar interval for its 2025 detention addendum (issued 16 Apr 2025, applied from 1 Oct 2025). The 12- and 24-month periods are set by this Manual to let Tier B authorities train staff and to let the State issue the design-aid tables (Clause 1.7).


1.12 Review and amendment

1.12.1 The State Stormwater Technical Committee shall review this Manual every 10 years, and after any event that exceeds the 1% AEP design depth as set out in Clause 2.14.1.

1.12.2 Amendments shall be notified in the Gazette, published with a change log, and take effect 6 months after notification unless the notification states otherwise.

1.12.3 Any person may propose an amendment to the Committee. Proposals and the Committee's decisions shall be published.


References (chapter)

Annexes and forms

Annex / Form Content
1A List of Tier A authorities, with the boundaries of the Municipal Corporations and of the Ranchi Master Plan 2037 area
1B Maps of flood-sensitive catchments
1C Policy Supplement: text of alternatives S-1 to S-5 and model council resolution
1D Model JBBL 2016 amendment and model ULB bye-law
Form 1-1 Applicability Determination
Form 1-2 Variance / Waiver Request