Chapter 10Submittals, Review, Operation & Maintenance and Enforcement
10.1 Purpose and scope
10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:
- (a) the submittal stages and their contents (Clauses 10.3–10.4);
- (b) the compliance calculator (Clause 10.5);
- (c) professional certification and review (Clauses 10.6–10.7);
- (d) construction inspection and as-built certification (Clauses 10.8–10.9);
- (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
- (f) handover of public assets (Clause 10.14);
- (g) enforcement (Clause 10.15); and
- (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).
10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.
10.2 Definitions
| Term | Meaning in this chapter |
|---|---|
| Submittal | A set of documents lodged with the Authority at one of the stages of Clause 10.3. |
| Drainage report | The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4. |
| Stormwater facility | Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private. |
| Hold point | A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8). |
| As-built certificate | The certificate of Clause 10.9 that the facility was built as approved and performs as designed. |
| Owner | The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset. |
| O&M plan | The operation and maintenance plan of Clause 10.11. |
| Facility register | The public register of facilities of Clause 10.17. |
Other terms are defined in Clause 1.4.
10.3 Submittal stages
10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the KMC Building Rules 2009 and the West Bengal Municipal (Building) Rules 2007 (Table 10.1):
Table 10.1 — Submittal stages and linked approvals
| Stage | Submittal | When | Linked approval |
|---|---|---|---|
| 0 | Pre-application meeting and Form 1-1 (Applicability Determination) | Before the planning permission or layout application | None (advisory record) |
| 1 | Preliminary drainage report | With the planning permission or layout application | Planning permission / layout approval |
| 2 | Final drainage design | Before building permit, or before commencement where the permit is issued with the planning permission | Building permit / commencement |
| 3 | Construction inspections at hold points | During construction | None (records filed) |
| 4 | As-built certificate and verification tests | Before the completion certificate | Completion / occupancy certificate |
| 5 | Maintenance declaration registered, or handover of public assets | Before or with the completion certificate | Completion certificate; asset acceptance |
| 6 | Annual declarations and inspection reports | Every year after completion | Continuing compliance |
10.3.2 Stage 0 is mandatory for:
- (a) sites of 2 ha or more;
- (b) sites in a flood-sensitive catchment;
- (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
- (d) sites draining to a tidal outfall or adjoining a waterbody.
For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.
10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.
10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.
10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.
Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.
Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the KMCBR/WBMBR steps a West Bengal applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.
10.4 Required contents and checklists
10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:
- (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
- (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
- (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
- (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
- (e) the pre-development condition and hydrologic method (Chapter 3);
- (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
- (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
- (h) the downstream extent and tailwater case (Chapter 5);
- (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
- (j) the land reserved for facilities and maintenance access (Clause 10.13).
10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:
- (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
- (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
- (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
- (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
- (e) construction drawings, details and specifications of every facility;
- (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
- (g) the hold-point schedule (Clause 10.8);
- (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
- (i) the model input files and the GIS data of Clause 10.4.4; and
- (j) the certificates of Clause 10.6.
10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.
10.4.4 Digital submittal.
- (a) Reports and drawings shall be submitted as searchable PDF.
- (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
- (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (45N), with attributes as listed in Annex 10B.
- (d) Levels shall be stated relative to a named vertical datum. The relationship to the tidal datums (chart datum of the nearest port, mean sea level on the GTS datum and, in Kolkata, the Kidderpore Old Datum (KOD)) used in Chapter 5 shall be stated.
10.4.5 Summary of forms used in submittals (Table 10.2):
Table 10.2 — Forms used in submittals
| Form | Title | Stage |
|---|---|---|
| 1-1 | Applicability Determination | 0 or 1 |
| 1-2 | Variance / Waiver Request | 1 |
| 2-1 | Design Rainfall Sheet | 1, 2 |
| 10-1 | Drainage Report Checklist | 1, 2 |
| 10-2 | Compliance Calculator Summary | 1, 2, 4 |
| 10-3 | Professional Design Certificate | 1, 2 |
| 10-4 | Hold-Point Inspection Record | 3 |
| 10-5 | As-built Certificate | 4 |
| 10-6 | Maintenance Declaration | 5 |
| 10-7 | Annual Maintenance Declaration and Inspection Report | 6 |
| 10-8 | Asset Handover Certificate | 5 |
Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. The design basis of public drains in West Bengal is rarely published. Kolkata's first brick sewer, commissioned in 1876, was designed for 6.35 mm/h of rain (a quarter of an inch an hour) with 100% runoff; attempts were made in the 1970s to raise the capacity to 12.7 mm/h, but the city received 54 mm in one hour in 2003 (Gupta 2005). A KMC engineer is still quoted as saying that the network prevents waterlogging only if it rains up to 6 mm in an hour (press reports). The CMPO Drainage Master Plan for the metropolitan area "has been based on the design consideration, of flood frequency of once in two months (6 times in a year)" with an imperviousness of 70%, and its intensity–frequency–duration curve "has been adopted by KMDA / ULBs" (CPHEEO appraisal note); the curve itself was not found. KMC's works under KEIIP follow its Sewerage and Drainage Master Plan of December 2007 and its 2014 Action Plan to Mitigate Flood, Cyclone and Water Logging (ADB 2016), neither of which was found, and the KEIIP environmental examinations give the design period, the combined design and the canals that receive the storm flow, but no rainfall intensity, return period or runoff coefficient (KMC 2015; ADB 2017). No design-criteria document was found for Howrah, Bidhannagar, New Town, Siliguri, Asansol, Durgapur or Haldia. Form 2-1 and Form 10-2 ensure that every design states its inputs.
10.5 Compliance calculator
10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:
- (a) applies the applicability tests of Clause 1.5;
- (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
- (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
- (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
- (e) on alternative S-2, gives the permissible site discharge for each AEP; and
- (f) produces the Compliance Calculator Summary (Form 10-2).
10.5.2 Use.
- (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
- (b) On the design-aid route, the calculator may be the only storage calculation.
- (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.
10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.
10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.
Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A West Bengal calculator serves Tier B authorities in particular, where it may be the whole calculation.
10.6 Professional certification
10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or UD&MA:
- (a) Tier A sites of 1 ha or more;
- (b) any site in a flood-sensitive catchment;
- (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
- (d) any pumped facility, tide gate or regional facility.
10.6.2 Empanelment criteria shall be issued by UD&MA and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.
10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:
- (a) the design complies with this Manual, except for variances listed and approved;
- (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
- (c) the models submitted reproduce the results reported.
10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.
10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.
Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the KMCBR/WBMBR registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.
10.7 Review procedure and timelines
10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.
10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:
- (a) 15 working days of acceptance for a first submittal; and
- (b) 10 working days of acceptance for a resubmittal.
10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.
10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the UD&MA list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.
10.7.5 Concurrent clearances. Where a WBCZMA recommendation (in the Coastal Regulation Zone), I&WD's consent for a discharge to or a work on one of its rivers, canals, khals, embankments or sluices, EKWMA's sanction within the East Kolkata Wetlands, or the Fisheries Department's permission under section 17A of the West Bengal Inland Fisheries Act 1984 to fill or alter a water area or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.
10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.
10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.
Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.
10.8 Construction inspection
10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:
- (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
- (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
- (c) the infiltration tests of Clause 10.9.3;
- (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
- (e) pumps and controls, at commissioning.
10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.
10.8.3 Protection during construction.
- (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
- (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
- (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.
Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.
Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.
10.9 As-built certification
10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:
- (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
- (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
- (c) the completed hold-point records (Form 10-4); and
- (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).
10.9.2 Acceptance. The as-built facility is accepted where:
- (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
- (b) the outlet dimensions and inverts match the approved design; and
- (c) the re-run shows compliance with every criterion of Chapters 4 and 5.
Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.
10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.
10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.
Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.
10.10 Maintenance declarations and covenants
10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:
- (a) identify each facility, its location and the approved O&M plan;
- (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
- (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
- (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
- (e) be registered so that it runs with the land and is disclosed to purchasers.
10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.
10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 15 May each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.
10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.
Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in West Bengal because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 15 May date is set by this Manual to fall before the south-west monsoon (June–September), when most West Bengal extreme rainfall occurs.
10.11 O&M plans
10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:
- (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
- (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
- (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
- (d) inspection checklists matching Form 10-7;
- (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
- (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
- (g) safety measures for confined spaces, deep water and public access;
- (h) access routes and equipment needed (Clause 10.13);
- (i) an annual cost estimate and who pays it; and
- (j) the records to be kept, and for how long.
10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.
Commentary. West Bengal's outfalls depend on locks, sluices and pumps whose operating rules are not published. Kolkata's storm water reaches the Kulti through pumping stations of KMC and I&WD; the three main KMC stations at Ballygunge, Palmer Bazar and Dhapa Lock have about 2,900 cusec installed between them (I&WD). The KEIIP stations have separate pumps for dry-weather and storm flow; Begore, for example, has 300 l/s of dry-weather pumping and 4,500 l/s of storm pumping in 6 + 2 units, and the storm pumps discharge storm water mixed with sewage to the Churial and other canals (KMC 2015). On the Hooghly side the drainage depends on lock gates such as Chitpur, and KMC was reported to plan lifting stations at five points in the outfall zones so that the city can drain while the lock gates are shut (press reports). Releases from DVC's Maithon and Panchet dams set the level of the lower Damodar: a State government statement put the combined peak release on 17 September 2024 at 2.5 lakh cusec, while other reports gave figures from 1.7 to 5 lakh cusec, and the Union Ministry said that the reservoirs are regulated by a committee that includes West Bengal and Jharkhand (press reports). Dredging of about 80 km of the Kestopur and Bagjola canals began in 2022 after a gap of five years (press report). No operating rules for the Kolkata pumping stations and locks, the Sundarbans embankment sluices or the DVC reservoirs were found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.
10.12 Inspection frequencies
10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:
Table 10.3 — Minimum owner inspection frequencies
| Facility type | Routine | Pre-monsoon (by 15 May) | After a heavy-rainfall event |
|---|---|---|---|
| Retention / infiltration (soakaways, trenches, bioretention, permeable paving) | Every 6 months | Yes | Yes |
| Surface detention basin or multi-use open space area | Every 6 months | Yes | Yes |
| Underground or podium detention tank, gravity outlet | Every 6 months | Yes | Yes |
| Pumped detention, pumps and controls | Monthly test run | Yes, with full duty test | Yes |
| Flap / tide gate, non-return valve | Every 3 months | Yes, with seal test | Yes |
| Gross pollutant trap / first-flush device | Every 3 months | Yes | Yes |
| Private drains and inlets | Every 6 months | Yes | — |
A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In West Bengal, pumped facilities, flap and tide gates, sluices, non-return valves and regional facilities shall also be inspected a second time by 30 September, with the pump duty and gate seal tests of the pre-monsoon column, so that they are ready for the cyclone storms of October and November.
10.12.2 Authority inspections. The Authority shall inspect:
- (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
- (b) a random sample of at least 10% of other facilities each year.
10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).
Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 15 May) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the south-west monsoon (June–September); tick positions within the year are illustrative.
Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The pre-monsoon deadline is set for the cyclone season as well as the SW monsoon. The monsoon sets in during the first week of June in most districts, the second week in Nadia and Darjeeling and the third week in Purulia (ICAR-CRIDA district plans). NDMA (2010) sets 31 March for pre-monsoon desilting nationally, and no published desilting deadline was found for KMC or any other West Bengal city. The State's most damaging recent cyclones struck in the second half of May: Aila on 25 May 2009, Amphan on 20 May 2020, Yaas on 26 May 2021 and Remal on 26 May 2024 (I&WD; IMD; press reports). May storms are also heavy inland: Dum Dum recorded 220.0 mm on 8 May 1949, Cooch Behar 353.2 mm on 28 May 1989 and Jalpaiguri 312.8 mm on 24 May 1999, and Diamond Harbour's all-time 24-hour record, 290.7 mm, fell on 27 May 1993 (IMD). This Manual therefore adopts 15 May statewide. For the storms of October and November it adds the second inspection of gates, sluices, pumps and regional facilities by 30 September, after the monsoon and before the cyclone months: Midnapore recorded 325.1 mm on 17 October 1942, and Haldia, Dum Dum and Uluberia all set their post-monsoon records on 9 November 1986 (IMD). The post-event inspections of Table 10.3 cover storms at any time of year.
10.13 Maintenance access
10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.
10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.
10.13.3 Underground facilities. Tanks shall have:
- (a) an access opening over the inlet, the outlet and each chamber;
- (b) fixed ladders or steps, and ventilation for confined-space entry;
- (c) a sump or low point for sediment removal; and
- (d) headroom sufficient for manual cleaning.
10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.
10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.
Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in West Bengal cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.
10.14 Handover of public assets to the ULB
10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:
- (a) the as-built certificate (Clause 10.9) has been accepted;
- (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
- (c) the land, or an easement over it, has been transferred to the ULB;
- (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
- (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.
10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full south-west monsoon season after handover. The ULB may hold a security deposit for this period.
10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.
10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.
Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in West Bengal drainage show up only in the first SW monsoon.
10.15 Enforcement
10.15.1 Offences. The following are contraventions of this Manual:
- (a) building without an approved drainage design where one is required;
- (b) building a facility other than as approved;
- (c) removing, filling, covering, reducing or changing the use of a facility without approval;
- (d) failing to maintain a facility, or to submit Form 10-7;
- (e) a sewage connection to a storm drain;
- (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
- (g) obstructing a natural drainage path or major-system flow path; and
- (h) false or negligent certification.
10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):
Table 10.4 — Graduated enforcement response
| Step | Action |
|---|---|
| 1 | Written notice stating the contravention, the clause breached, the remedy and a compliance period. |
| 2 | Stop-work order, or withholding of the completion certificate, for development not yet complete. |
| 3 | Penalty under the applicable Act or rules. |
| 4 | Works in default by the Authority, with the cost recovered from the owner. |
| 5 | Disconnection of the private drain connection to the public system, where this causes no hazard to others. |
| 6 | Report of the certifying professional to the registering authority, and suspension from the empanelled list. |
10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.
10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.
10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.
Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the KMC Building Rules 2009 and the West Bengal Municipal (Building) Rules 2007 are made and from the municipal Acts. The graduated steps are set by this Manual. The powers exist, but much of the enforcement has come through notices, police complaints and the courts. KMC must construct drains and sewers and provide "a safe and sufficient outfall … for the effectual drainage and proper discharge of storm-water and sewage" of Kolkata without flooding the city or the country around the outfall (KMC Act 1980, section 277). All public drains vest in KMC (section 280), the Commissioner may require "an entirely distinct drain for rain water" (section 292), and no premises may be built or occupied without a drain of the size and level the Commissioner requires (section 293). Against the filling of ponds KMC issues restoration notices under section 53 of the West Bengal Town and Country (Planning and Development) Act 1979 and notices under section 400(1) of the KMC Act, followed by police complaints, as in a Behala pond case before the National Green Tribunal in 2024 (DM South 24 Parganas 2024), and it was reported to have filed 870 such complaints (press report). Section 17A of the West Bengal Inland Fisheries Act 1984 bars the filling of a water area, and a 2008 amendment is reported to have removed its minimum size of 5 cottahs (as reported); but in Anuradha Sen v. KMC (January 2024) the Calcutta High Court set aside KMC's action because the Corporation had not first established that the site was a "water area" (as reported). In the municipalities, rule 8 of the West Bengal Municipal (Building) Rules 2007 bars the filling of any pond, canal, wetland or drain without the State's prior approval (as reported). The East Kolkata Wetlands have been protected since the Calcutta High Court's judgment of 1992 in PUBLiC v. State of West Bengal and by the East Kolkata Wetlands (Conservation and Management) Act 2006, yet in May 2026 the State Wetland Authority told the National Green Tribunal that KMC had not cleared encroachments at Ukil Bheri (press report). This shows that a rule without routine enforcement does little. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.
10.16 Monitoring and post-event review
10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.
10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:
- (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
- (b) tide and river levels at the outfalls, each on a named datum, the state of every lock, sluice, tide gate and pumping station on the outfall and its channel, and releases from the DVC dams or any other dam or barrage upstream;
- (c) flooded locations, depths and durations, with flood marks surveyed where possible;
- (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
- (e) recommended actions.
10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), WBSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.
10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.
Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. West Bengal has few published technical reviews of floods. After the Kolkata storm of 23 September 2025, IMD published an analysis of the rainfall: 185.6 mm in three hours at Alipore and a peak hour of 98 mm, below its 100 mm criterion for a cloudburst (IMD 2025). The Calcutta High Court, hearing petitions on the deaths, most of them by electrocution, sought reports from KMC on its drainage, from the power utility CESC and from the State (press reports); those reports were not found. IMD's report on Cyclone Amphan records the track, winds, rainfall and storm tide of May 2020 (IMD 2020). After the DVC releases of September 2024 the State government called the flooding "man-made" and the Union Ministry pointed to the joint regulation committee (press reports), but no technical review was found. The CAG used CWC's data on the July 2017 floods, which affected 8.7 million people, took 217 lives and caused ₹17,727.94 crore of damage, in its audit of flood control (CAG 2019). I&WD publishes daily and annual flood reports, which could not be read for this Manual. The State Disaster Management Plan and any urban flood procedure of WBSDMA were not reviewed. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.
10.17 Data publication
10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:
- (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
- (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
- (c) the register of variances and waivers (Clause 1.10);
- (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
- (e) enforcement actions (Clause 10.15.5); and
- (f) event reports and post-event reviews (Clause 10.16).
10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.
10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.
10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.
Commentary. Transparency is a design criterion in its own right here. Much of the information on which West Bengal's drainage depends could not be found in the public domain: KMC's Sewerage and Drainage Master Plan (2007) and its 2014 Action Plan to Mitigate Flood, Cyclone and Water Logging; the design rainfall, return period and runoff coefficients of the KEIIP and KMC-SHARP works; the CMPO intensity–frequency–duration curve; the present capacities and operating rules of the pumping stations, locks and sluices on the Kolkata outfall channels, and the status of the Kulti pump-house upgrade; MHWS and HAT on chart datum at Garden Reach, Haldia and Sagar, and the relation of the Kidderpore Old Datum to mean sea level; the DVC reservoir regulation rules; the components and progress of the Ghatal Master Plan; the drainage plans of Howrah, Siliguri, Asansol and Durgapur; and consolidated texts of the KMC Building Rules 2009 and the West Bengal Municipal (Building) Rules 2007 with their amendments. West Bengal government websites could not be reached during the research for this Manual, so several statutes were read only in extracts, and KMC's ward rain-gauge records appear only as totals in the press. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.
10.18 Review of this chapter
10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.
References (chapter)
- Comptroller and Auditor General of India (2019). Report No. 2 of 2019, Government of West Bengal: Performance Audit of Implementation of Flood Control Measures in West Bengal, Chapter 6 (Conclusion). https://cag.gov.in/webroot/uploads/download_audit_report/2019/7.%20Chapter%206-0624302347a92f2.77846330.pdf
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities, §5608 (easements, maintenance, submittals) and §5609 (plan requirements). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Mid-America Regional Council (2025). Stormwater management page: 2025 Stormwater Standards Manual, Compliance Calculator, Calculator Start-Up Guide, Policy Supplement. https://www.marc.org/environment/environment-plans/stormwater-management
- PUB Singapore (2018, with Addendum No. 3 of 16 Apr 2025). Code of Practice on Surface Water Drainage, 7th ed. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
- PUB Singapore (2024). On-site Stormwater Detention Tank Technical Guide. https://www.pub.gov.sg/-/media/PUB/PDF/detentionTank.pdf
- PUB Singapore (11 Nov 2024). Amendments to Sewerage and Drainage Act (press release). https://www.pub.gov.sg/Resources/News-Room/PressReleases/2024/11/Amendments-to-Sewerage-and-Drainage-Act
- MoHUA (2016). Model Building Bye-Laws, Chapter 9, §9.6. https://web.archive.org/web/2022/https://mohua.gov.in/upload/uploadfiles/files/MBBL.pdf
- National Disaster Management Authority (2010). National Guidelines on Management of Urban Flooding. https://sdma.goa.gov.in/sites/default/files/2022-05/management_urban_flooding.pdf
- Kolkata Municipal Corporation Building Rules, 2009, as published by KMC (copy headed "The Kolkata Gazette, Extraordinary, September 9, 2009", apparently with later amendments; rules 2(27), 65A, 74(4), 76, 81(9), 105, 117, 118, 144 and the procedure chapter; notification number not seen). https://www.kmcgov.in/KMCPortal/downloads/Building_%20Rules2009.pdf ; consolidation: https://www.kmcgov.in/KMCPortal/downloads/KMC_Building_Rule.pdf
- Kolkata Municipal Corporation Act, 1980 (West Bengal Act LIX of 1980), PRS compilation with amendments to 2023 (sections 277, 280, 292, 293 and 400; quotations reconstructed from a poor scan). https://prsindia.org/files/bills_acts/acts_states/west-bengal/1980/ActNo.59of1980WB.pdf
- West Bengal Municipal (Building) Rules, 2007, Notification No. 67/MA/O/C-4/3R-8/2002 of 14 February 2007, as amended (rule 8 read only in a legal-database text; salient features on the Department of Municipal Affairs page). https://www.legitquest.com/act/west-bengal-municipal-building-rules-2007/CE73 ; https://sudawb.org/wbdma_oldversion_old/HTM/MUNI_Legislation_WB_BuildingRules_2007.htm
- Urban Development and Municipal Affairs Department (2021). New Town Kolkata (Building) Rules, 2009, amendment, Notification No. 2282-T&CP/C-2/2C-17/2020 of 8 September 2021, Kolkata Gazette Extraordinary. https://nkdamar.org/storage/files/sar-365-urban-devp-municipal-departmentnkda-no-2282-tcp_1.pdf
- West Bengal Inland Fisheries Act, 1984, section 17A, as inserted by West Bengal Act XIX of 1993 and amended by West Bengal Act 7 of 2008 (seen only in extracts). https://wbxpress.com/west-bengal-inland-fisheries-amendment-act-1993/
- East Kolkata Wetlands (Conservation and Management) Act, 2006 (West Bengal Act VII of 2006) (seen only in a legal-database text). https://wbxpress.com/east-kolkata-wetlands-conservation-management-act-2006/
- District Magistrate and Collector, South 24 Parganas (2024). Compliance report in MA 122/2024 in OA 258/2024, Banibrata Mukherjee v. State of West Bengal, National Green Tribunal (Principal Bench), with KMC action-taken reports and notices under section 53 of the West Bengal Town and Country (Planning and Development) Act 1979 and section 400(1) of the KMC Act. https://www.greentribunal.gov.in/sites/default/files/news_updates/Compliance%20Report%20by%20DISTRICT%20MAGISTRATE%20%26%20COLLECTOR%2C%20SOUTH%2024%20PARGANAS%20DISTRICT%20in%20MA%20NO%20122%20of%202024%20IN%20OA%20NO%20258%20of%202024%20(Banibrata%20Mukherjee%20Vs.%20State%20of%20WB).pdf
- SCC Online Blog (12 Jan 2024). Calcutta High Court quashes KMC's action under section 17A of the West Bengal Inland Fisheries Act (Anuradha Sen v. Kolkata Municipal Corporation, 2024 SCC OnLine Cal 185) (secondary source). https://www.scconline.com/blog/post/2024/01/12/calcutta-high-court-quashes-kmcs-action-under-section-17a-of-west-bengal-inland-fisheries-act-scc-blog/
- ICSF (repost of a news report). KMC police complaints under the Fisheries and Town and Country Planning Acts (secondary source). https://icsf.net/?p=127445
- Down To Earth (court digest, 26 May 2026). State Wetland Authority before the National Green Tribunal on Ukil Bheri, East Kolkata Wetlands (secondary source).
- Asian Development Bank (2016). Periodic Financing Request Report, Kolkata Environmental Improvement Investment Program, Tranche 2 (Project 42266-025). https://ewsdata.rightsindevelopment.org/files/documents/25/ADB-42266-025_dnsshKo.pdf
- Kolkata Municipal Corporation (2015). Initial Environmental Examination, KEIIP Tranche 1, Sewerage and Drainage, updated and revised final report, October 2015, for ADB. https://ewsdata.rightsindevelopment.org/files/documents/23/ADB-42266-023_TfN9hJv.pdf
- Asian Development Bank (2017). Initial Environmental Examination, KEIIP Tranche 2 (42266-025). https://www.adb.org/sites/default/files/project-documents/42266/42266-025-iee-en_0.pdf
- Gupta, K. (2005). The drainage systems of India's cities. Waterlines 23(4), 22–24. https://web.archive.org/web/20241111031826/https://www.ircwash.org/sites/default/files/Gupta-2005-Drainage.pdf
- CPHEEO. Appraisal Note for consideration of projects under JNNURM (Storm Water Drainage): Improvement of drainage in Howrah city and its vicinity, No. Q-12045/28/10/NURM/2006-CPHEEO (CMPO Drainage Master Plan basis). https://sudawb.org/wbdma_oldversion_old/PDF/URBAN_GROVER/Improvement%20of%20drainage%20in%20Howrah%20city%20and%20its%20vici.pdf
- Irrigation and Waterways Department, Government of West Bengal. Kolkata Metropolis Drainage (web page; Wayback capture of 1 May 2026). https://web.archive.org/web/20260501071330/https://wbiwd.gov.in/index.php/applications/kolkata_drainage
- Irrigation and Waterways Department, Government of West Bengal. AILA (web page; Wayback capture of 1 May 2026). https://web.archive.org/web/20260501071547/https://wbiwd.gov.in/index.php/applications/aila
- India Meteorological Department (2025). Press Release: Extremely Heavy Rainfall over Kolkata, 23 September 2025. https://internal.imd.gov.in/press_release/20250923_pr_4321.pdf
- India Meteorological Department (2020). Super Cyclonic Storm "AMPHAN" over the southeast Bay of Bengal (16th–21st May, 2020): A Report, 14 June 2020. https://internal.imd.gov.in/press_release/20200614_pr_840.pdf
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012) (West Bengal stations). https://imdpune.gov.in/library/public/EXTREMES%20OF%20TEMPERATURE%20and%20RAINFALL%20upto%202012.pdf
- ICAR-CRIDA. District Agriculture Contingency Plans, West Bengal, §1.2 (one file per district under https://www.icar-crida.res.in/CCP/WB/).
- Down To Earth (Sep 2025). "Unexpected interaction of atmospheric conditions, not cloudburst, caused Kolkata's intense 180 mm rainfall in 3 hours, says IMD" (secondary source). https://www.downtoearth.org.in/climate-change/unexpected-interaction-of-atmospheric-conditions-not-cloudburst-caused-kolkatas-intense-180mm-rainfall-in-3-hours-says-imd
- Press reports (Free Press Journal, The Statesman, IANS; Sep 2025) on the Calcutta High Court petitions after the Kolkata flood of 23 September 2025 (secondary sources).
- Press reports (ThePrint, Devdiscourse; Sep 2024) of the State government statement on the DVC releases from Maithon and Panchet, 17–19 September 2024 (secondary sources).
- Press reports (The Telegraph, Millennium Post) on the Kulti pump house, the Chitpur lock gates, KMC's planned lifting stations and the KMC engineer's 6 mm/h statement (secondary sources, seen through search summaries).
- The Telegraph (2022). Dredging starts in Kestopur, Bagjola canals after five years (secondary source). https://obeta.ttef.in/my-kolkata/news/dredging-starts-in-kestopur-bagjola-canals-after-five-years/cid/1863758
- Coastal Engineering Proceedings (ICCE). Gole, C.V. and Vaidyaraman, P.P. Salinity distribution and effect of fresh water flows in the Hooghly River (CWPRS; tidal range and bores). https://icce-ojs-tamu.tdl.org/icce/article/download/2492/2157/10823
- INCOIS (2025). Technical Report ESSO-INCOIS-OMDA-TR-04(2025) on extreme sea levels (Diamond Harbour). https://incois.gov.in/documents/Reports/TechnicalReports/TR_ESSO-INCOIS-OMDA-TR-04(2025)_20250725114934.pdf
Annexes and forms
| Annex / Form | Content |
|---|---|
| 10A | Compliance calculator and user guide |
| 10B | GIS data specification and attribute schema |
| 10C | Maintenance access dimensions |
| 10D | Model O&M plans by facility type |
| 10E | Empanelment criteria for Stormwater Design Professionals and reviewers |
| Form 10-1 | Drainage Report Checklist |
| Form 10-2 | Compliance Calculator Summary |
| Form 10-3 | Professional Design Certificate |
| Form 10-4 | Hold-Point Inspection Record |
| Form 10-5 | As-built Certificate |
| Form 10-6 | Maintenance Declaration |
| Form 10-7 | Annual Maintenance Declaration and Inspection Report |
| Form 10-8 | Asset Handover Certificate |
| Form 2-1 | Design Rainfall Sheet (Chapter 2) |
Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. No CAG audit of urban storm drainage in West Bengal was found: none of KMC's drainage, of KEIIP or of any other city's drains. The one relevant audit is of flood control by I&WD (CAG Report No. 2 of 2019). It found that "in the absence of basin-wise/river-wise holistic Master Plan, flood management projects were taken up at different locations depending on priority and availability of funds without being linked to a comprehensive plan". Under the Kandi Master Plan, due in March 2017 and still under way in 2019, only embankments had been raised and strengthened, and no additional waterway had been created at bridges and culverts; all the blocks under that plan and the Kaliaghai–Kapaleswari–Baghai scheme were flooded in July 2017. The audit recommended detention basins, diversion of flood water and a floodplain zoning law on the model Bill (CAG 2019). The approval route also shapes this chapter. West Bengal has no single building code. In Kolkata the Municipal Commissioner sanctions building plans under the KMC Building Rules 2009, with the Municipal Building Committee and the Mayor-in-Council for relaxations. The site plan must show the house drains and the "means of communication with any municipal drain", the terrace plan the roof drainage and rain-water pipes, and the application must say whether the land is a filled-up tank. A licensed plumber supervises the drainage work and certifies it under the KMC (Water Supply, Sewerage and Drainage) Regulations 1984. Where the Commissioner considers that a building "will put additional burden on the existing civic services" of the ward, including its drainage, the Commissioner may sanction it subject to conditions (KMC Building Rules 2009). In the municipalities the Board of Councillors sanctions plans under the West Bengal Municipal (Building) Rules 2007, which have a separate chapter for Salt Lake, and buildings over 14.5 m also need the approval of the Municipal Engineering Directorate (as reported). New Town has its own rules under NKDA. The building rules of Howrah, Siliguri, Asansol and the other Municipal Corporations were not read for this Manual. No rule asks for a drainage report or limits peak runoff. Every stormwater item in this chapter is therefore written so that the architect or engineer on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it at the plinth and completion stages; in Kolkata the Commissioner's power to impose conditions on a building that would burden the drainage is the natural hook for them. This chapter is the process.