Chapter 11Basin and City Stormwater Master Plans
11.1 Purpose and scope
11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.
11.1.2 A BSMP shall:
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
- (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
- (d) reserve land for regional storage, pokhar and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
- (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
- (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).
11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.
11.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Basin | The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3. |
| Basin Stormwater Master Plan (BSMP) | The plan for one basin prepared under this chapter. |
| Lead Authority | The body responsible for preparing a BSMP (Clause 11.4). |
| Level of service (LoS) | The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6). |
| Flood hazard map | A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario. |
| Regional facility | A storage, conveyance or outfall work serving more than one development, identified in a BSMP. |
| Capital Improvement Programme (CIP) | The ranked, costed list of works in a BSMP (Clause 11.8.4). |
11.3 Planning unit: the basin, not the ward
11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.
11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.
11.3.3 No basin delineation has been published for any Bihar city. For the urban areas where the evidence identifies them, the basins are at least the following:
- Patna, Ganga: the catchment of each drain that outfalls to the Ganga through its sluice or drainage pumping station, 19 ghat drains from Digha Ghat to Balu Ghat in BUIDCO's list (BUIDCO 2025), each as a basin with the Ganga level at Dighaghat or Gandhi Ghat as the boundary condition and the outfall-closed case of Chapter 5, with the capacity of its pumping station, as a design case;
- Patna, Punpun and Sone: the catchments of the city that drain south to the Punpun, among them those of the Badshahi and Bakipur Gorakh drains (BUIDCO 2025), with the Punpun level at Sripalpur as the boundary condition, and those that drain west to the Sone, with its level at Maner; in both the outfall-closed case is a design case;
- Patna, trunk nalas: the Kurji (Rajiv Nagar), Anandpuri, Saidpur and Bakarganj nalas now being rebuilt (as reported), each mapped within the basin of its outfall, with the Saidpur nala, which is reported to carry the discharge of nine drainage pumping stations and one treatment plant, and every other pumped transfer mapped as a link between basins (Clause 11.3.2); BUIDCO's Catchment-1 and Catchment-2, and the drains of Danapur, Khagaul and Phulwari, shall be reconciled with these basins;
- Muzaffarpur, Burhi Gandak: the catchments that drain to the Burhi Gandak, with its level at Sikandarpur as the boundary condition; and
- Darbhanga, Bagmati and Adhwara: the catchments that drain to the Bagmati and the Adhwara group, with their levels at Hayaghat and Ekmighat as boundary conditions, and the Harahi, Digghi and Ganga Sagar ponds, before the Tribunal in O.A. 155/2022/EZ, as storage to be kept.
Other Tier A bodies, including Gaya, Bhagalpur, Bihar Sharif, Purnia and Arrah, shall define their basins in the first BSMP that covers them. Where WRD or CWC has a high flood level, a Flood Plain Zone under WRD Order No. 143 of 2025, a 5-, 25- or 100-year line from the NIH study of the Ganga, an embankment crest level or an operating rule for a river, a barrage, a sluice or a pumping station, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.
Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.
Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Bihar a single drain can pass through several owners' hands on its way to the river. The Bihar Municipal Act 2007 vests the public drains in the Municipality (s.195) but lets it make a drain over to another authority with State approval (s.196). In Patna the trunk drains and sump houses passed with the Bihar Rajya Jal Parshad to BUIDCO (Bihar Act 3 of 2018), PMC has said in an affidavit that the drainage system is not directly under it (as cited; not read), and no order dividing the drains between them was found. WRD keeps the rivers, the embankments and their sluices; BUIDCO also builds the sewers and the interception works that tap the drains under Namami Gange; and the drains of the industrial areas belong to BIADA (as this Manual reads the institutional record). The storm drains carry sewage across these boundaries: BUIDCO's table of December 2025 lists 19 drains to the Ganga at Patna, several of them untapped, and two untapped drains to the Punpun (BUIDCO 2025), and 19 Patna drains were found to discharge 628.5 MLD (CAG, Patna sewerage). This clause makes the basin the planning unit, so that one model carries each drain from its head to the river whoever owns each reach, and so that the interception structures are tested against the capacity of the drains they tap (Chapter 8, Clause 8.9.5).
11.4 Who prepares, and when
11.4.1 Lead Authority.
- For the basins of a city with a Nagar Nigam: the Nagar Nigam (in Patna, PMC), which the Bihar Municipal Act 2007 makes responsible for the city's drains and a safe outfall (s.193), jointly with BUIDCO, which carries out the State's storm water drainage schemes and runs Patna's trunk drains and sump houses, for the reaches and works it holds; either may prepare the plan as UDHD directs. Where a basin extends beyond the Nagar Nigam, the other local bodies in the basin, and PMAA within the Patna Metropolitan Area, are partners, and one BSMP covers the whole basin (Clause 11.3.1).
- No order dividing the drains of the local bodies, BUIDCO and WRD was found; until one is made, this Manual assigns the reaches within each BSMP as follows, each body being Lead Authority for the reaches it owns or runs and for the parts of the CIP on them: WRD for the rivers, their embankments and sluices, the Flood Plain Zones under its Order No. 143 of 2025 and its flood-control drains; the Minor Water Resources Department for the ahar-pyne systems and the ponds and tanks in its charge; the Nagar Nigam, Nagar Parishad or Nagar Panchayat for the municipal nalas, road drains and the public tanks vested in it (s.177); BUIDCO for the trunk drains and drainage pumping stations it built or runs and for the sewers, interceptors and drain-tapping works; PMAA for the Patna Metropolitan Area outside the local bodies and for carrying the BSMPs into the Patna Master Plan 2031 (Clause 11.9); the Road Construction Department and NHAI for the drains of their roads; and BIADA for the drains of its industrial areas.
- In Tier B bodies: the Lead Authority is named by UDHD. Basins draining to a common river reach may be grouped into one district-level plan.
The Bihar State Wetland Authority shall be consulted on every BSMP whose basin drains to a notified wetland or a Ramsar site; BSDMA and the district administration on every BSMP; and NMCG, through BUIDCO, on every BSMP that proposes works on a drain tapped or to be tapped under Namami Gange.
WRD, or the Minor Water Resources Department, shall be a partner in every BSMP that includes a river, canal or tank under its control.
11.4.2 When a BSMP is required.
- (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
- (b) A BSMP is required before:
- any regional detention or fee-in-lieu is accepted under Clause 4.13;
- a fee held under Clause 4.5.6.3 is spent; and
- a basin-specific release rate is applied under Clause 11.8.3.
- (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.
11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.
11.5 Data and surveys
11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:
Table 11.1 — Minimum data and surveys for a BSMP
| Data | Minimum requirement |
|---|---|
| Terrain | Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum |
| Drain network | Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm |
| Waterbodies | Survey of every tank, pokhar, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment |
| Rivers and canals | Cross-sections at no more than 200 m spacing and at every structure |
| Outfalls and rivers | The datum of every level named; outfall invert levels against the warning, danger and high flood levels of the receiving river at the nearest CWC or WRD gauge and its recorded peaks; the Flood Plain Zones of embanked rivers under WRD Order No. 143 of 2025 and, when published, the 5-, 25- and 100-year lines of the NIH study of the Ganga from Chausa to Manihari; the sluices, flap gates, interception structures and drainage pumping stations (sump houses) on the outfalls and in the river embankments, with their pump capacities, sump volumes and operating rules; embankment crest levels; and releases from any barrage or dam upstream |
| Rainfall and levels | All available rain gauges (IMD, including the Patna (A), Gaya (A), Bhagalpur, Sabour, Muzaffarpur, Darbhanga, Purnea, Motihari, Chapra, Forbesganj and Dehri stations and the automatic weather stations and rain gauges reported by the Meteorological Centre Patna, among them Anisabad in Patna; the district rain gauges; the rain and river gauges of CWC (Lower Ganga Division-2, Patna) and of WRD and its FMISC, with the rainfall FMISC compiles from Nepal for the rivers that rise there; and any gauges kept by the Nagar Nigams and BUIDCO) and water-level records, including those for the August 1975 (the Sone and the Ganga at Patna), August 2016 (the Ganga at Patna), August 2017 (north Bihar), September 2019 (Patna) and September 2026 (the Ganga at Patna) events |
| Flood evidence | Surveyed flood marks and mapped flood extents from past events, including public reports |
| Land use | Existing land use and imperviousness; future land use from the statutory master plan |
| Soils and groundwater | HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones |
| Sewer interaction | Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots |
Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the diara and floodplains of the Ganga, the Gandak, the Kosi and the other rivers, behind the river embankments, in the chaurs of the north Bihar plain and in the tal lands of the south bank, such as the Mokama group of tals, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The August 1975 (the Sone and the Ganga at Patna), August 2016 (the Ganga at Patna), August 2017 (north Bihar), September 2019 (Patna) and September 2026 (the Ganga at Patna) events are the best calibration data Bihar has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.
11.6 Levels of service
11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.
Table 11.2 — Minimum levels of service
| Element | Minimum level of service |
|---|---|
| Minor system | The design AEP of Chapter 6 (Table 6.1) |
| Habitable buildings | No flooding above floor level in the 1% AEP (100-yr) event |
| Critical facilities (hospitals, emergency services, substations, water and sewage plants) | No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event |
| Evacuation routes and arterial roads | Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event |
| Ponding drain time | Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event |
| Tank and pokhar storage | No net loss of flood storage below the MWL in the basin, measured against the earliest available survey |
| Outfalls | Functioning under the joint and outfall-closed cases of Chapter 5 |
Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been counted but not measured. In law the ponds of Bihar's towns are public: the public tanks and the land appertaining to them vest in the Municipality and no new tank or pond may be dug without permission (Bihar Municipal Act 2007, ss.177, 183 and 252); public land under the Bihar Public Land Encroachment Act 1956 includes land over which the community has a right of irrigation, which brings community ahars and pynes within it; and the Bihar Building Byelaws 2014 bar building within 9 m of the highest water mark of a tank (bye-law 30(B)), which this Manual reads as setting the protected extent at the monsoon water line. The same Municipal Act, however, lets a tank or pond be ordered filled up if it appears injurious to health (ss.184 and 251(e)). The State reports encroachment removed from 28,685 ponds, ahars, pynes and wells under Jal-Jeevan-Hariyali (State portal), while press counts of encroached and recovered ponds conflict, and one reports that the State lost over 100,000 ponds in three decades (as reported). Kabartal in Begusarai, a Ramsar site of 2,620 ha designated on 21 July 2020, is inundated to 1.5 m in the monsoon and drains through the Bagras maun to the Burhi Gandak (Ramsar RIS); in Darbhanga the Tribunal directed the removal of encroachment from three ponds in 2023 (O.A. 155/2022/EZ). No inventory of the pokhars inside any Nagar Nigam, and no survey of the storage of any of them, was found.
11.7 Modelling and scenarios
11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:
- the minor system;
- the major (overland) system;
- rivers, canals and tanks; and
- the outfalls.
Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.
11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.
11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.
11.7.4 Scenarios. Each BSMP shall model at least:
- (a) Existing: existing land use, network, tanks and outfalls;
- (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
- (c) Future, controlled: future land use with the site controls of Chapter 4;
- (d) Future, with plan: scenario (c) plus the works of the CIP; and
- (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Bihar was found, and the reported rise in the intensity of monsoon daily rainfall over north Bihar since about 1960 (as reported) gives no reason to depart from them.
11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the August 1975 (the Sone and the Ganga at Patna), August 2016 (the Ganga at Patna), August 2017 (north Bihar), September 2019 (Patna) and September 2026 (the Ganga at Patna) events where data exist.
Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and pokhars with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.
Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).
11.8 Options, outputs and the Capital Improvement Programme
11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:
- Protect and restore storage: pokhars, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
- Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
- Conveyance upgrades to drains, canals and culverts;
- Outfall works: sluices and flap gates on the outfalls to the rivers, drainage pumping stations (sump houses) and the storage behind them, including those behind river embankments, interception structures that keep the storm capacity of the drain, and the river embankments;
- Property-level protection where works cannot reach the level of service; and
- Non-structural measures: flood warning (for example IMD district rainfall warnings issued by the Meteorological Centre Patna, CWC flood forecasts and river stages at its sites on the Ganga, the Sone, the Punpun, the Gandak, the Burhi Gandak, the Bagmati, the Kosi, the Mahananda and other rivers against their warning and danger levels, and the daily flood bulletin that WRD's FMISC issues from 15 June to 15 October), flood-hazard zoning, emergency planning and public information.
11.8.2 Option assessment. Each option shall be assessed for:
- reduction in flood risk (buildings and people flooded; expected annual damage);
- capital and 30-year maintenance cost;
- land required;
- effect on groundwater recharge where the water table is deep, waterlogging where it is shallow, and the quality of the shallow aquifer in the arsenic belt (Chapter 8);
- effect on downstream basins and the receiving river; and
- who benefits.
11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.
11.8.4 Outputs. Each BSMP shall produce:
- (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
- (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
- (c) regional facility sites, with storage volumes, land needs and the sites they serve;
- (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
- (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
- (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
- (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.
Commentary. Restoring storage comes first because the outfalls of Bihar's larger cities cannot always take more water. When the Ganga, the Sone or the Punpun is high, Patna's sluices are closed and its drains reach the rivers only through the sump houses (as reported), so faster conveyance only fills the sumps and the low colonies behind them sooner; the high flood level of the Punpun at Sripalpur stands 3.31 m above its danger level (CWC), and the Ganga at Gandhi Ghat was reported above its 2016 high flood level in September 2026 (as reported). The State has already restored ponds at scale: the Jal-Jeevan-Hariyali campaign reports encroachment removed from 28,685 ponds, ahars, pynes and wells, and 26,381 ponds and 78,090 ahars and pynes restored (State portal). The storms are large for drains with no stated design basis: IMD has recorded 520.0 mm in a day at Motihari (25 August 2005) and 436.0 mm at Muzaffarpur (26 September 2007), and days of 1.5 to 2 times the 50-year 24-hour depths of the CWC plates have fallen at gauges in every part of the State (IMD; this Manual's reading). Conveyance upgrades on their own move water faster to an outfall that the river may close, or that is limited by the capacity of its sluice, interception structure or drainage pumping station. Groundwater in Bihar more often limits recharge than invites it. Over much of the north Bihar plain the water table stood 1.5–5.7 m below ground in the district profiles of 2011 (CGWB, as reported), and of the 535 assessment units of 2024 only 4 were over-exploited and 9 critical, against 473 safe (CGWB, as reported). Along the Ganga the shallow aquifer that recharge reaches carries arsenic above 0.01 mg/L in 27 districts, and fluoride exceeds 1.5 mg/L in 19 districts, mostly in the south (CGWB, as cited in the State's report to the National Green Tribunal in O.A. 728/2023). The law asks for recharge without regard to either: the Bihar Building Byelaws 2014 require recharge pits or trenches on plots of all sizes (bye-law 51), and the Bihar Ground Water Act 2006 lets the local authority make rooftop rainwater harvesting a condition of a building plan of 1,000 m² or more (s.18), though whether the Act has been brought into force was not confirmed. This is why recharge, waterlogging and groundwater quality are all assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.
11.9 Integration with land-use planning
11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the Patna Master Plan 2031 and the other master plans and area development schemes made under the Bihar Urban Planning and Development Act 2012, and the layout plans approved under them and under the Bihar Building Byelaws 2014. In particular:
- (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
- (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
- (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
- (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.
11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.
Commentary. Bihar draws its floodplain lines by embankment, not yet by return period. WRD Order No. 143 of 6 March 2025 makes the land between the embankments of a river embanked on both banks, or from the embankment to 500 m beyond the far bank where only one bank is embanked, a Prohibited Zone, in which permanent construction is barred and only temporary or movable structures are allowed, beyond 250 m from the current bank, with the district administration to monitor (WRD 2025). For the rivers that are not embanked, the Ganga from Chausa to Manihari comes first: NIH is to delineate its 5-, 25- and 100-year zones under an MoU of 3 August 2025, the Survey of India has supplied a 10 m DEM of the State, and WRD has asked again for 1 m contours (Chief Secretary 2026). Notified wetlands carry a 50 m line from the mean high flood level (Wetlands Rules 2017), but only draft notifications of Bihar wetlands were seen. In the towns the Bihar Building Byelaws 2014 refuse permission in natural waterways or drains shown in the Development Plan or drainage plan and within 9 m of the highest water mark of a tank, and bar basements in flood-prone areas (bye-laws 29(A), 30(B) and 47(1)); the Draft Bihar Building Byelaws 2026 would drop the 9 m rule, bar permanent construction only within a water body's boundary, and require site plans to show flood-affected areas (Draft 2026, cl. 6 and Table 5). No setback in metres from a nala exists, and "flood prone" is not defined. These are river-flood and waterbody lines, not drainage-flood lines. A BSMP gives the land-use plans the 1% AEP drainage-flood map, and the buffer widths of Chapter 7, that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because the Bihar Building Byelaws 2014 already require at least 5% of the land of a building site to be under tree cover, and call 10% desirable for larger buildings (bye-law 32), require rainwater harvesting on plots of all sizes, with recharge pits or trenches of at least 6 m³ per 100 m² of roof, and suggest replacing topsoil in open ground with river sand so that rain water percolates slowly (bye-law 51), but set no detention or pervious-area rule; storage placed in a layout's open space builds on these duties, and because that land still serves as open space, the storage must stay usable as one. Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.
11.10 Consultation and publication
11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.
11.10.2 After approval, the following shall be published as open data:
- the model files;
- the flood hazard maps;
- the data of Clause 11.5.1, except security-sensitive asset details; and
- the CIP.
They shall also be shown on a public map viewer.
Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.
11.11 Approval, review and reporting
11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.
11.11.2 Review. Each BSMP shall be reviewed:
- every 10 years;
- within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
- when the statutory land-use plan is revised.
11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each SW monsoon (by 31 May). The report shall show:
- CIP progress;
- the fee-in-lieu ledger (Clause 4.13.4);
- maintenance completed; and
- any flooding against the levels of service.
11.12 Interim arrangements
11.12.1 Until a BSMP is approved for a basin:
- (a) all site criteria of Chapters 4 to 8 apply in full;
- (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
- (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
- (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.
References (chapter)
- Chief Secretary, Government of Bihar (2026). Supplementary affidavit of 12 January 2026 in National Green Tribunal O.A. 200/2014, M.C. Mehta v. Union of India, annexing UDHD letter No. 516 of 9 December 2025, BUIDCO letter No. 4400 of 13 December 2025 with the status of drains and their tapping, the correspondence of WRD with the Survey of India and NIH, and WRD Order No. 143 of 6 March 2025, Implementation of Flood Plain Zoning for embanked rivers within Bihar State (Hindi). https://www.greentribunal.gov.in/sites/default/files/news_updates/Supplementary%20affidavit%20on%20behalf%20of%20the%20Chief%20Secretary,%20State%20of%20Bihar%20in%20OA%20No.%20200%20of%202014%20(M%20C%20MEHTA%20Vs.%20UNION%20OF%20INDIA%20and%20Ors).pdf
- Defra (2010). Surface Water Management Plan Technical Guidance. Department for Environment, Food and Rural Affairs, London.
- Mile High Flood District (Denver). Master planning programme and Urban Storm Drainage Criteria Manual.
- Mid-America Regional Council (2025). APWA Stormwater Standards Supplement; KC Metro APWA Section 5600, Version 2025.01.
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- Urban Development and Housing Department, Government of Bihar (2014). Bihar Building Bye-Laws, 2014 (English, file "Dec-2014"; Notification No. 577 (file 11/न०वि०(मा०)-06/2013), Patna, 8 December 2014, as printed in the official Hindi text) (bye-laws 29, 30, 32, 47 and 51). https://automap.bihar.gov.in/PATNABPASPORTAL/PlanningPortals/images/Bihar%20Building%20Bylaw%20English%20Dec-2014.pdf
- Urban Development and Housing Department, Government of Bihar (2026). Bihar Building Byelaws 2026, draft posted on 5 June 2026 (not notified; cl. 6 and Table 5). https://betastate.bihar.gov.in/file_2/FileUpload/2026/Jun/05-Jun-2026/19/LatestNews/0424d72a-9e14-4227-8221-8adb08c0c009.pdf
- Bihar Urban Planning and Development Act 2012 (Act 20 of 2012, with Act 4 of 2022 appended; PRS copy). https://prsindia.org/files/bills_acts/acts_states/bihar/2012/2012Bihar20.pdf
- Bihar Municipal Act 2007, sections 177, 183, 184, 193, 195, 196, 251 and 252 (IELRC copy). https://www.ielrc.org/content/e0715.pdf
- Bihar Ground Water (Regulation and Control of Development and Management) Act 2006, section 18 (Bihar Gazette scan, FAOLEX; commencement not confirmed). https://faolex.fao.org/docs/pdf/IND197019.pdf
- Bihar State Water and Sewage Board (Repeal) Act 2017 (Bihar Act 3 of 2018) (FAOLEX copy). https://faolex.fao.org/docs/pdf/ind198266.pdf
- Bihar Public Land Encroachment Act 1956 (copy on the Bihar State Wetland Authority site). https://bswa.bihar.gov.in/Downloads/BIHAR%20PUBLIC%20LAND%20ENCROACHMENT%20ACT,%201956.pdf
- Ministry of Environment, Forest and Climate Change (2017). Wetlands (Conservation and Management) Rules, 2017, rule 4(2)(vi); Bihar State Wetland Authority, home and notifications pages (draft notifications of Bihar wetlands). https://bswa.bihar.gov.in/ ; https://bswa.bihar.gov.in/ActRulesandNotification.aspx
- Ramsar Convention. Ramsar Information Sheet, Kabartal Wetland, site 2436 (designated 21 July 2020). https://rsis.ramsar.org/RISapp/files/RISrep/IN2436RIS_2010_en.pdf
- Government of Bihar. Jal-Jeevan-Hariyali Abhiyan page, State portal (components and progress). https://betastate.bihar.gov.in/jaljivan.aspx
- Comptroller and Auditor General of India. Audit Report (Performance and Compliance Audit) for the year ended March 2020, Government of Bihar, Chapter III, para 3.1, Development of Sewerage Infrastructure in Patna under Namami Gange Programme (report number and tabling date to be confirmed). https://cag.gov.in/uploads/download_audit_report/2020/05-%20Report%20No-5%20-English%20-%20Chapter%20-%203-06244310a0bd463.62428332.pdf
- Talab Bachao Abhiyan (2025). Application to the National Green Tribunal (Eastern Zone) against the Darbhanga storm water drainage and canal-lining projects; and objection of 23 November 2024 in M.A. 18/2024 in O.A. 155/2022/EZ (Darbhanga ponds). https://www.greentribunal.gov.in/sites/default/files/news_updates/1755167303.pdf ; https://www.greentribunal.gov.in/sites/default/files/news_updates/1732521637_pagenumber.pdf
- Central Water Commission, Lower Ganga Division-2, Patna (2026). Daily water level and flood forecast bulletin of 31 October 2026 (warning, danger and highest levels at the Bihar sites; read from the page image; datum to be confirmed), via WRD's FMISC. https://www.fmiscwrdbihar.gov.in/bulletin/CWC_Bulletin.pdf
- Water Resources Department, Government of Bihar, FMISC. Home page (daily flood bulletin, 15 June to 15 October). https://fmiscwrdbihar.gov.in/
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012) (Bihar stations). https://imdpune.gov.in/library/public/EXTREMES%20OF%20TEMPERATURE%20and%20RAINFALL%20upto%202012.pdf
- Central Ground Water Board. Dynamic ground water resources of Bihar, 2024 assessment (as summarised; secondary source). https://www.cgwb.gov.in/cgwbpnm/public/uploads/documents/1743584819841710360file.pdf
- Rajya Sabha (2024). Reply to a question of 27 November 2024 on storm water drainage and drainage pumping stations in Bihar (listing seen; not read). https://rsdebate.nic.in/bitstream/123456789/754718/1/PQ_266_27112024_S10_p23_p25.pdf
- NBM&CW. Construction begins on stormwater drainage project in Patna to prevent floods (103 drain lines, nine packages, 185 km; secondary source, undated). https://www.nbmcw.com/news/infra-development/construction-begins-on-stormwater-drainage-project-in-patna-to-prevent-floods.html
- Patna Press (2026). Bihar budget 2026: urban development, drainage and waste management; BUIDCO inspection of Catchment-1 and -2 works; the Saidpur and Bakarganj nalas (secondary sources). https://patnapress.com/bihar-budget-urban-development-drainage-waste-management-2026/ ; https://patnapress.com/buidco-drainage-inspection-catchment-1-2-patna-monsoon-work-2026/ ; https://patnapress.com/?p=63534
- Press reports of August 2025 on the foundation of the Kurji (Rajiv Nagar) and Anandpuri nala works (secondary sources; addresses not retained).
- Hindustan Times (30 May 2022). Report on the Danapur–Khagaul–Phulwari drainage DPR (secondary source). https://www.pressreader.com/india/hindustan-times-ranchi/20220530/281556589453660
- Down To Earth. Reports on encroached and recovered water bodies in Bihar (secondary sources). https://www.downtoearth.org.in/water/over-20-000-water-bodies-freed-from-encroachment-in-bihar-for-rainwater-harvesting-78741 ; https://www.downtoearth.org.in/water/nearly-3-years-since-campaign-only-5-public-ponds-free-of-encroachment-in-bihar-76044
- Hydrology (MDPI) (2024). Study of Bihar rainfall on 1901–2020 gridded data (abstract; secondary source). https://doaj.org/article/69bb222448444c808df7ab0c9320a2e0
- ThePrint/PTI (5 September 2026). Ganga water level breaches highest flood mark at Patna's Gandhi Ghat (secondary source). https://theprint.in/india/ganga-water-level-breaches-highest-flood-mark-at-patnas-gandhi-ghat-amid-heavy-rain/3034353/
Annexes and forms
| Annex / Form | Content |
|---|---|
| 11A | BSMP terms of reference template |
| 11B | Basin lists and boundaries for Tier A bodies |
| 11C | Depth–damage curves for Bihar building types |
| 11D | BSMP data and model publication standard |
| Form 11-1 | Annual implementation report |
Commentary. Bihar is spending heavily on city storm drains, but no city drainage master plan or design standard has been published. The 2026 State budget was reported to provide about ₹3,559 crore for 38 storm water drainage schemes (as reported), and a Rajya Sabha reply is reported to cite State approval of storm water drainage projects worth ₹1,230.74 crore and of 22 new drainage pumping stations (as reported; not read). In Patna, BUIDCO's storm water drainage project is reported to cover 103 drain lines in nine packages, a network of 185 km, worked by catchment, with Catchment-1 and Catchment-2 works in Danapur, Khagaul and Phulwari (as reported); covered trunk drains are being built on the Kurji (Rajiv Nagar) nala, at ₹181 crore, and the Anandpuri nala, at ₹91.27 crore, both begun in August 2025 (as reported); and a DPR for 34.72 km of drains in Danapur and Khagaul, at about ₹197.72 crore, mooted after the floods of 2019, was awaiting Cabinet clearance in May 2022 (as reported). In Darbhanga a storm water drainage scheme of ₹245 crore is being carried out by BUIDCO (Patna High Court order of 20 June 2025, as cited), and petitioners before the Tribunal say that the same scheme of UDHD covers 19 other cities and towns and that the new drains are closed, concrete and connected to sewage (as alleged). The Patna Master Plan 2031, approved by the Cabinet in October 2016 (as reported) and taken forward by PMAA under the Bihar Urban Planning and Development Act 2012, has a storm water drainage section that was not read. No published document sets a design return period for the drains of any Bihar city. This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by UDHD, BUIDCO or any other body. A site-level manual cannot fix basin-level problems: lost tank storage, city outfalls to the Ganga, the Sone, the Punpun and the rivers of north Bihar closed when the rivers are high, drains that then reach the river only through sump houses, nalas that carry sewage to interception structures at their outfalls, pokhars, ahars and chaurs narrowed or filled by encroachment, single drains split between a Nagar Nigam, BUIDCO and WRD, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:
This chapter adapts that method to Bihar: to city outfalls on the Ganga, the Sone and the Punpun at Patna, and on the Burhi Gandak, the Bagmati and the other rivers of the State, that the rivers close in flood, and to drains that then reach the river only through sluices and sump houses; to nalas that carry sewage to interception structures at their outfalls; to drains held by Nagar Nigams, BUIDCO and WRD without an order that divides them; to pokhars, ahars, chaurs and tals that the law and the Jal-Jeevan-Hariyali campaign protect but encroachment has reduced; to a State programme of storm water drainage schemes, carried out by BUIDCO, with no published design return period; to a water table so shallow over much of the State that infiltration is the exception; and to a south-west monsoon whose recorded days reach 1.5 to 2 times the 50-year depths of the CWC plates.