Chapter 1Policy, Applicability and Adoption


1.1 Purpose and objectives

1.1.1 This Manual sets the minimum standards for the planning, design, construction, operation and maintenance of stormwater systems in Bihar. It applies to private development and to public works, as set out in Clause 1.5.

1.1.2 The Manual has the following objectives:

  • (a) to make stormwater management a condition of development approval, so that new development and redevelopment do not increase flood peaks or runoff volumes downstream;
  • (b) to retain frequent rainfall on site, so that groundwater recharge is sustained and pollutant loads are reduced;
  • (c) to size storage for the long-duration south-west monsoon storms of July–September, brought by monsoon depressions, which fall on ground and water tables raised by weeks of rain and often on rivers already in flood from rain over Nepal and the catchments upstream, as well as for short-duration intensities;
  • (d) to design outfalls for the stage of the rivers into which the cities drain, the Ganga, the Sone and the Punpun at Patna, the Burhi Gandak at Muzaffarpur, the Bagmati and the Adhwara group at Darbhanga, the Ganga at Munger and Bhagalpur and the Mahananda at Purnia, which closes the sluices on outfalls through the river embankments and leaves the land behind them to be drained by pumping, and the levels of the nalas, tals and chaurs into which local drains discharge, including the case where the outfall is closed;
  • (e) to protect tanks (pokhars), marshes, rivers, supply channels and surplus courses as part of the drainage system;
  • (f) to give every element of the drainage network a safe overland path for the 1% AEP (100-yr) storm;
  • (g) to make design inputs, approvals and facility records public, so that designs can be checked and repeated; and
  • (h) to make sure that facilities, once built, are maintained and remain effective.

1.1.3 This Manual does not replace the rainwater harvesting (RWH) mandate, the building bye-laws issued by the Urban Development and Housing Department for the municipal areas and planning areas of the State (the Bihar Building Byelaws 2014), or the statutes on waterbodies. It adds runoff control requirements to them (Clause 1.8).

Commentary. Bihar's floods come from three sources, often together. The first is the rivers. About 68.80 lakh ha of the State's 94.16 lakh ha, some 73%, is flood-prone, and about 3,800 km of embankments, most of them in north Bihar, protect 39.96 lakh ha (WRD Order No. 143, 2025). In August 1975 the Sone began rising on about 19 August, and on the night of about 24 August its waters and the Ganga's crossed the Patna Canal and entered Patna; ground floors were under water for 5–7 days (as reported). The Ganga at Dighaghat in Patna still holds its highest recorded level from that year, 52.52 m, and the Punpun at Sripalpur and the Sone at Maner theirs from 1976, 53.91 m and 53.79 m (CWC). On 18 August 2008 the Kosi breached its eastern afflux bund at Kusaha in Nepal and shifted its course across north Bihar, leaving about three million people homeless (as reported). In August 2017 floods in north Bihar killed 514 people in 19 districts (as reported), and the Mahananda at Dhengraghat and the Parman at Araria set new highest levels that year (CWC). The Ganga at Gandhi Ghat in Patna set its highest recorded level, 50.52 m, in August 2016 (CWC), and is reported to have passed it on 5–6 September 2026, at 50.53–50.57 m (as reported); the CWC bulletin of 31 October 2026 still lists the 2016 level. The second is the heavy storm: Motihari recorded 520.0 mm in a day on 25 August 2005 and Muzaffarpur 436.0 mm on 26 September 2007, both station records (IMD). The third is the city drainage that fails in a fall that is not extreme. Over 26–29 September 2019 Patna received about 210–226 mm in three to four days (the reported totals conflict), less than a 50-year 24-hour depth; Rajendra Nagar, Kankarbagh and Pataliputra Colony were under water for days, the NDRF rescued more than 4,000 people, most of the sump houses were reported not working, and the State's inquiry found that pumps were not started on time and drains had not been cleaned (all as reported). The Patna High Court asked the State to report which sump houses were working, who had cleaned the nalas and what was done after the weather forecast (order of 18 October 2019). On 29 July 2025, 175.4 mm in 24 hours again left parts of Patna waterlogged (as reported).

Missing design makes all three worse. Patna's drainage system "was laid about 200 years ago and is in bad condition", and its natural and man-made drains discharge both runoff and sewage to the Ganga and the Punpun (CAG). Most city outfalls discharge to rivers whose highest flood levels lie 1.2–3.3 m above their danger levels, so an outfall below the river's flood level is shut, or pumped, for days. No published Bihar document sets a design storm, return period or rainfall intensity for a city's drains, and the BBL 2014 control rainwater harvesting pits, not runoff. Objectives (b) to (e) address the storage, outfall and building-level failures, which a drain-sizing manual alone cannot fix.

No national instrument requires on-site detention. CPHEEO (2019) is advisory and describes peak control only as typical practice. NDMA (2010) says detention and retention "will" be included but gives no sizing rule. MBBL 2016 and the Bihar Building Byelaws 2014 mandate RWH only. Objective (a) is therefore the main new step this Manual takes.


1.2 Stormwater management hierarchy

1.2.1 Every development to which Chapter 4 applies shall consider stormwater measures in the following order. A designer shall not use a lower measure in place of a higher one that is practicable on the site.

  1. Preserve — keep or restore natural drainage features, tanks, wetlands, permeable soils, trees and overland flow paths (Chapter 7).
  2. Retain — hold the runoff from the retention depth of Annex 2E on site, by infiltration, reuse or evapotranspiration (Chapters 4 and 8).
  3. Detain — store larger storms temporarily and release them at or below the rates in Chapter 4, checked against downstream and tailwater conditions (Chapters 4 and 5).
  4. Convey — carry the remaining flow safely in the minor system, and the 1% AEP flow in the major system (Chapters 6 and 9).

1.2.2 Maintenance underlies all four measures. A measure that cannot be maintained by its owner under Chapter 10 shall not be credited.

1.2.3 Credits from higher measures reduce the requirements of lower ones. Preserved areas and retained volume reduce detention storage as set out in Chapter 4.

Figure 1.1 — Stormwater management hierarchy Four stacked bars, widest at top: Preserve, Retain, Detain, Convey, with a Maintain bar underneath spanning all. A downward arrow shows the order of consideration; an upward arrow shows that credits from higher measures reduce lower ones. Order of consideration Credits reduce lower measures 1 PRESERVE Chapter 7 Keep tanks, wetlands, marshes, permeable soils, trees and flow paths 2 RETAIN Chapters 4, 8 Hold the Annex 2E depth on site: infiltrate, reuse, evaporate 3 DETAIN Chapters 4, 5 Store larger storms; release below pre-development peaks 4 CONVEY Chapters 6, 9 Minor system, plus a 1% AEP overland path MAINTAIN — underlies every measure Chapter 10 A measure that its owner cannot maintain earns no credit (Clause 1.2.2) Use a lower measure only for what the measures above it cannot practicably achieve (Clause 1.2.1).

Figure 1.1 — Stormwater management hierarchy: preserve, retain, detain, convey, with maintenance underlying each measure. Original drawing for this Manual, adapted from Mid-America Regional Council / Kansas City Metro Chapter APWA, "Layers of Stormwater Management", APWA 5600 Manual Factsheet, 2025 (concept).

Commentary. The order follows the "layers" of Kansas City Metro APWA Section 5600, Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet, 2025). The same logic is behind Georgia's runoff-reduction standard and CSE's "attenuate and infiltrate first" principle (CSE, 2023). For Bihar, the top layer has a particular meaning. Much of the State's flood storage lies in its pokhars and talabs, in the ahars and pynes of south Bihar, in the chaurs and mauns (oxbow lakes) of the north Bihar plain, in the Mokama group of tals, about 1,062 km² of low land in Patna, Nalanda and Munger districts that is waterlogged each monsoon (NIH, as reported), and in the diara land of the Ganga and the Kosi. The law protects some of it. The BBL 2014 refuse permission for a building within 9 m of the highest water mark of a tank (bye-law 30(B)) and in the natural waterways and drains shown in the Development Plan or drainage plan (bye-law 29(A)); public tanks in a municipal area vest in the Municipality (Bihar Municipal Act, 2007, s.177); and the Bihar Public Land Encroachment Act, 1956 treats as public land any land over which the community has a right of irrigation, which brings community ahars and pynes within it. The same Municipal Act, however, still lets a Municipality order a tank or pond to be filled up where it appears "injurious to health" (ss.184 and 251(e)). The State's Jal-Jeevan-Hariyali campaign reports encroachment removed from 28,685 ponds, ahars, pynes and wells and 26,381 ponds and 78,090 ahars and pynes restored (State portal). The larger wetlands are a separate layer: Bihar has six Ramsar sites, among them Kabartal in Begusarai, designated on 21 July 2020 over 2,620 ha, a complex of 18 interconnected wetlands between the Burhi Gandak and an old channel of the Bagmati that is inundated to 1.5 m in the monsoon and drains through the Bagras maun (Ramsar Information Sheet). The land between the embankments of the embanked rivers is a Prohibited Zone (WRD Order No. 143, 2025). Losing that storage cannot be offset economically by pipes and pumps.


1.3.1 Notification. This Manual shall be given statutory effect by the Government of Bihar through:

  • (a) an amendment to the Bihar Building Byelaws 2014 that makes compliance with this Manual a condition of planning permission, building permit, layout approval and completion certificate, for development to which Clause 1.5 applies; and
  • (b) bye-laws or standing orders of each urban local body (ULB), adopting the Manual for works executed or approved by that ULB, including the ULB's own drains and roads.

1.3.2 Higher State standards. The design return periods and performance criteria of this Manual exceed the national advisory minimums of the CPHEEO Manual on Storm Water Drainage Systems (2019). The State shall constitute, by notification, a high-powered committee (the State Stormwater Technical Committee, Clause 1.9) to adopt these higher standards. This is the route that CPHEEO (2019) provides for higher return periods.

1.3.3 Precedence. Within its scope, this Manual governs where it is stricter than CPHEEO (2019), IRC:SP:42-2014, IRC:SP:50-2013 or any departmental standard. Where a statute or statutory rule sets a stricter requirement (for example a waterbody setback), the statute governs.

1.3.4 Design-practice standard for public works. Departments and ULBs that procure drainage, road or waterbody works shall require compliance with this Manual in detailed project reports (DPRs) and contracts, from the dates in Clause 1.11.

Commentary. In Bihar the building rules are the Bihar Building Bye-Laws, 2014, issued by the Urban Development and Housing Department (UDHD). The English text in use on the PMC building plan approval portal is titled "Dec-2014" and its pages are initialled 4 December 2014, and the official Hindi text gives UDHD Notification No. 577 (file 11/न०वि०(मा०)-06/2013), Patna, 8 December 2014; no Gazette date for the bye-laws, and no notification for any amendment, was found in research for this Manual [TBC]. One amendment is reported, raising the permitted coverage of commercial buildings from 40% to 70% of the plot by relaxing their setbacks; its number and date are not known [TBC]. In Patna, Chapter III (zoning) of the bye-laws is reported to be substituted by the land-use rules of the Patna Master Plan 2031 (seen only through a search summary). The bye-laws set no design storm, return period, release rate or detention volume, and no "zero runoff" rule. They make rainwater harvesting mandatory on plots of every size, with recharge pits or trenches of at least 6 m³ for every 100 m² of roof (bye-law 51); refuse permission within 9 m of the highest water mark of a tank, in natural waterways and drains shown in the Development Plan or drainage plan, and over or under a municipal drain (bye-laws 30(B), 29(A) and 29(D)); bar basements in flood-prone areas (bye-law 47(1)); require at least 5% of the land under tree cover (bye-law 32); and require surface-water drains within the curtilage where the Authority so requires, and written approval to connect a surface-water drain to a sewer (bye-law 30(D)). A Draft Bihar Building Byelaws 2026 was posted by UDHD on 5 June 2026; it had not been notified as of September 2026 (as reported) and is a draft only. If notified it would repeal the 2014 bye-laws "with all its amendments and associated executive orders" (cl. 41(1)), require a rainwater harvesting proposal on plots of 100 m² and more (cl. 24), prohibit permanent construction within the boundary of a water body but set no buffer around it (Table 5), and drop the 9 m tank rule. In Bihar the route of Clause 1.3.1(a) therefore runs through UDHD, which would amend the 2014 bye-laws, or include the rule in the 2026 bye-laws before they are notified. This Manual is a draft; neither the Government nor any authority has adopted it. MoHUA told Parliament in July 2026 that urban flooding "falls under the purview of the State Governments and the ULBs" and listed the CPHEEO manual among "advisory guidelines" (Lok Sabha AU1847). The State therefore needs no central approval to adopt higher standards. CPHEEO's Note 2 to Table 4.1 (§4.4.1.4) allows "a high powered committee constituted by State/UT Government through a notification" to adopt higher return periods. Clause 1.3.2 uses that route so that higher standards are on record for centrally funded schemes.


1.4 Definitions

1.4.1 The following terms apply throughout this Manual. Chapter-specific terms are defined in each chapter (for example Clause 2.2).

Term Meaning in this Manual
Approving Authority (the Authority) The body that grants planning permission, building permit or layout approval for a development, or that sanctions a public work: the Nagar Nigam, Nagar Parishad or Nagar Panchayat concerned, which grants building permission under the BBL 2014; where it grants planning permission or layout approval, the authority of a Metropolitan Area or Planning Area under the Bihar Urban Planning and Development Act, 2012, such as PMAA in the Patna Metropolitan Area; or BIADA in its industrial areas, under the rules that apply there (the division of these powers between the bodies is to be confirmed [TBC]), or a department for its own works.
Applicant The owner, developer or department that seeks approval, and its successors in title.
Development Any building, layout, sub-division, road, paving or land-use change that requires approval under the Bihar Building Byelaws 2014 or that is executed as a public work.
Redevelopment Development on a site where impervious cover already exists.
Land disturbance Clearing, grading, excavation, filling or paving of land, measured in plan area over the whole of a common plan of development (Clause 1.5.5).
Impervious area Roofs, paving, compacted gravel, decks and other surfaces that prevent infiltration. Permeable paving designed to Chapter 8 is counted as pervious only for the area it treats.
New or replaced impervious area Impervious area created, or removed and rebuilt down to the subgrade, by the development. Resurfacing that leaves the base in place is not "replaced".
Retention Permanent removal of runoff from the drainage system on site, by infiltration, reuse or evapotranspiration (Chapter 4).
Detention Temporary storage of runoff with a controlled outlet, emptied after the storm (Chapter 4).
Rainwater harvesting (RWH) Collection of rainfall for supply or recharge under the RWH mandate. RWH storage is not detention unless Chapter 4 allows it.
Minor system Drains, pipes and inlets designed for the minor-system AEP of Chapter 6.
Major system The overland and floodway path that carries the 1% AEP (100-yr) flow (Chapter 6).
Pre-development condition Greenfield: open land in good condition for the mapped hydrologic soil group. Existing impervious cover is not counted (Chapter 3).
Flood-sensitive catchment The catchments of the drains of Patna, Danapur, Phulwari and Khagaul that outfall to the Ganga and the Punpun through sump houses, drainage pumping stations and sluices, including Rajendra Nagar, Kankarbagh and Pataliputra Colony; the catchments of the drains of Muzaffarpur that outfall to the Burhi Gandak; the catchments of the drains of Darbhanga that outfall to the Bagmati and the Adhwara group; and tal and chaur land, including the Mokama group of tals and the chaurs and mauns of north Bihar, and any catchment the Authority notifies (Chapter 4; Annex 1B).
Waterbody A river, stream, canal, tank (pokhar), lake, pond, marsh, supply channel or surplus course, whether perennial or seasonal (Chapter 7).
Regional facility A detention, retention or tank storage facility serving more than one development, built or restored under a basin plan (Chapter 4).
Tier A / Tier B authority An Approving Authority classed under Clause 1.6.
Policy supplement The set of adoptable alternative clauses in Clause 1.7 and Annex 1C.
Drainage report The preliminary or final report required by Chapter 10.
Registered professional A person registered under the Bihar Building Byelaws 2014 to prepare and sign the relevant plans, with any further qualification required by Clause 10.6.
Compliance calculator The State-issued tool for computing and reporting compliance (Clause 10.5).
Maintenance declaration The registered undertaking by an owner to maintain a stormwater facility (Clause 10.10).
Variance Approval to depart from a numeric requirement, with equivalent performance shown (Clause 1.10).
Waiver Approval that a requirement does not apply to a site, on the grounds in Clause 1.10.
Notified Published by the Government or the State Stormwater Technical Committee in the Bihar Gazette.

Commentary. "Replaced" impervious area is defined to the subgrade so that redevelopment of a fully paved site is captured, while routine resurfacing is not. This follows the approach of the APWA 5600 (2025.01) redevelopment triggers (MARC Supplement, 2025).


1.5 Applicability

1.5.1 Who is covered. This Manual applies to:

  • (a) all development requiring planning permission, building permit or layout approval under the Bihar Building Byelaws 2014;
  • (b) all drainage, road, bridge, culvert, waterbody and flood-mitigation works executed by a ULB, a State department, a board, or a State undertaking; and
  • (c) works executed by Central agencies or their contractors within Bihar, to the extent that the Authority's approval or no-objection is required.

1.5.2 Retention and detention threshold. Chapters 4 and 5 (retention, detention, downstream and tailwater analysis) apply to any development that, over the common plan of development, involves:

  • (a) land disturbance of 0.1 ha or more; or
  • (b) new or replaced impervious area of 500 m² or more.

1.5.3 RWH. The existing RWH mandate continues to apply under bye-law 51 of the BBL 2014 to plots of all sizes, with recharge pits or trenches of at least 6 m³ for every 100 m² of roof area; and, under section 18 of the Bihar Ground Water (Regulation and Control of Development and Management) Act, 2006, to residential, commercial and other premises of 1,000 m² and more in urban areas notified under the Act, whose commencement and notified areas were not confirmed for this Manual [TBC], as now. This Manual does not change it.

1.5.4 Provisions that apply at every size. The following apply to all development under Clause 1.5.1, whatever its size, unless exempted by Clause 1.5.8:

  • (a) no sewage connection to a storm drain (Chapter 8);
  • (b) lowest habitable floor and openings at or above the 1% AEP level plus 0.5 m, where a 1% AEP level is mapped or determinable (Chapter 6);
  • (c) waterbody setbacks and the no-fill zone (Chapter 7); and
  • (d) no obstruction of a natural drainage path or major-system flow path (Chapter 6).

1.5.5 Common plan of development. The thresholds of Clause 1.5.2 apply to the total area of a development, including all phases, plots and sub-divisions under one layout approval or one ownership at the date of application. A development shall not be divided to avoid the thresholds.

1.5.6 Redevelopment. For redevelopment, the thresholds apply to new plus replaced impervious area. Retention and detention apply to the whole of the new and replaced impervious area, and the pre-development condition is greenfield (Clause 1.4). Where greenfield control cannot be achieved on a constrained redevelopment site, the relief route of Clause 4.5.6 applies: a minimum on-site cut of 50% from existing peaks, with the shortfall paid as fee-in-lieu into basin storage.

1.5.7 Linear public works. For roads, widening and other linear works, the impervious area threshold applies to the added impervious area within each drainage catchment crossed. Retention and detention shall be provided within the right of way, or in a regional facility under Chapter 4, where the right of way cannot hold them.

1.5.8 Exemptions. The following are exempt from Chapters 4 and 5:

  • (a) a single dwelling on its own plot, where the thresholds of Clause 1.5.2 are not met; and
  • (b) linear road resurfacing that adds no impervious area.

Exempt development remains subject to the RWH mandate and to Clause 1.5.4.

1.5.9 Applicability determination. The Applicant shall record the applicability decision on Form 1-1 (Applicability Determination) with the first submittal under Chapter 10. The Authority may confirm or correct it at the pre-application stage.

Figure 1.2 — Applicability decision flowchart Flowchart for Clause 1.5: approval test, exemption test, size threshold test, and flood-sensitive catchment test, leading to the requirements that apply. Development or public work (Clause 1.5.1) Needs building-rules approval, or is it a public work? No Manual not triggered; other rules apply Yes Exempt under Clause 1.5.8? (single dwelling below the threshold, or road resurfacing that adds no impervious area) Yes Exempt from Chapters 4–5. RWH (where mandated) and Clause 1.5.4 still apply No Land disturbance ≥ 0.1 ha, or new or replaced impervious area ≥ 500 m² (Clause 1.5.2)? No Below threshold: RWH (where mandated) and Clause 1.5.4 apply Yes Chapters 4 and 5 apply: retention, detention, downstream and tailwater analysis (+ RWH, 1.5.4) In a flood-sensitive catchment (Annex 1B)? Yes Mixed-frequency rule; full methods only; no Policy Supplement alternatives No Standard rule: Q_post ≤ 0.9 × Q_pre Tier B: design-aid route may be used (Clause 1.7) Decision Chapters 4–5 requirements Chapters 4–5 do not apply

Figure 1.2 — Applicability decision flowchart for Clause 1.5. Original drawing for this Manual.

Commentary. The thresholds have no single direct precedent; they are set by this Manual. Precedents span a wide range:

  • Singapore controls peak runoff from developments of 0.2 ha or more (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5).
  • Malaysia's 2008 DID checklist used on-site detention for sites up to 0.1 ha and community ponds above that.
  • The APWA 5600 (2025.01) Policy Supplement offers alternative triggers of ¼ acre (about 0.1 ha) disturbed, or 1 acre (about 0.4 ha) with 10,000 sq ft (about 930 m²) impervious, and warns agencies not to exceed a 1-acre trigger.
  • MBBL 2016 makes recharge mandatory for buildings over 500 m².

The 0.1 ha / 500 m² trigger sits at the strict end of these, because typical Bihar plots are small and the cumulative effect of many small plots is what fills Patna's drains. For small buildings in Bihar, bye-law 51 of the BBL 2014 already requires rainwater harvesting on plots of every size, with recharge pits of 6 m³ for every 100 m² of roof, about 60 mm of roof runoff; that is a pit volume, not a rule on what leaves the plot, and in north Bihar, where the water table is within a few metres of the ground in the monsoon, the pits may stand full. The Draft Bihar Building Byelaws 2026, not in force, would narrow the rule to plots of 100 m² and more (cl. 24). The 2014 bye-laws bar basements in flood-prone areas (bye-law 47(1)) but do not say what land is flood-prone; their plinth rule was not read for this Manual [TBC], and the draft sets a plinth of 0.45–0.90 m (Table 6), not related to any flood level. The draft would also approve low-risk buildings on self-certification (as reported). Clause 1.5.4(b) applies to every building whatever its size for this reason.

Clause 1.5.4(b) has no direct precedent; this Manual sets it because floor levels are the cheapest protection a building can have, and it would be perverse to protect only large developments. Where no 1% AEP level is mapped, Chapter 6 gives the method for small sites.


1.6 Tiered adoption

1.6.1 Tier A authorities. The following are Tier A:

  • (a) the Patna Municipal Corporation (PMC);
  • (b) every Approving Authority within the Patna Metropolitan Area under the Bihar Urban Planning and Development Act, 2012, as that area is notified from time to time, including PMAA where it is the Approving Authority, and the Nagar Parishads and Nagar Panchayats in that area; and
  • (c) every other Nagar Nigam constituted under the Bihar Municipal Act, 2007, as constituted from time to time.

1.6.2 Tier B authorities. All other Nagar Parishads and Nagar Panchayats are Tier B.

1.6.3 What differs between tiers. All criteria of this Manual apply in both tiers. The tiers differ only in method and review:

Table 1.1 — Differences between Tier A and Tier B authorities

Item Tier A Tier B
Performance criteria (Chapters 2–9) Apply in full Apply in full
Hydrologic method for storage Hydrograph method (Chapter 3) Hydrograph method, or the design-aid route of Clause 1.7 where eligible
Compliance calculator (Clause 10.5) Required as a summary Required; may be the sole calculation on the design-aid route
Policy supplement alternatives (Clause 1.7) Only with State Stormwater Technical Committee concurrence May be adopted by council resolution
Technical review By the Authority By the Authority, with UDHD regional support or an empanelled reviewer (Clause 10.7)
Flood-sensitive catchment rule Applies Applies

1.6.4 Moving between tiers. A Tier B authority may opt into Tier A by council resolution. The Government may notify a Tier B authority as Tier A when it becomes a Corporation, joins the Patna Metropolitan Area under the Bihar Urban Planning and Development Act, 2012, or is found by a post-event review (Clause 10.16) to need the full methods.

1.6.5 Flood-sensitive catchments override tier. In a flood-sensitive catchment, whatever the tier, the alternatives of Clause 1.7 are available only as Table 1.2 allows: S-1 (the design-aid route) for sites of 0.5 ha or less (Clause 4.14.1), and S-5 fee-in-lieu where a basin plan has been notified (Clause 1.10.3(d)). S-2, S-3 and S-4 are not available.

Commentary. Patna Municipal Corporation, with its engineering wing and a city of about 535 drains, much of whose runoff is lifted into the Ganga and the Punpun by sump houses that BUIDCO runs (as reported), and a small Nagar Panchayat with one assistant engineer cannot be asked to review the same hydrograph models. The Kansas City solution was to keep one regional standard and publish adoptable alternatives for the most contested criteria, so that smaller agencies can "opt down" without leaving the standard (MARC Supplement, Nov 2025). The tiers here keep the performance criteria the same in both tiers and vary only the method, so that a building in a Tier B town is protected to the same level as one in Patna.


1.7 Policy supplement: adoptable alternatives

1.7.1 The Government shall publish, with this Manual, a Policy Supplement (Annex 1C) of alternative clauses. An Approving Authority may adopt one or more alternatives under the conditions in Clause 1.7.3.

1.7.2 The alternatives are:

Table 1.2 — Policy supplement: adoptable alternatives S-1 to S-5

No. Main-text requirement Adoptable alternative Eligibility
S-1 Storage sized by hydrograph method (Chapter 3) Design-aid route: retention and detention volumes taken from the unit-storage tables (m³ per ha, by rainfall zone, soil group and impervious fraction) in Annex 4 and the compliance calculator Sites ≤ 2 ha outside flood-sensitive catchments; ≤ 0.5 ha within them (as Clause 4.14.1)
S-2 Release rate Q_post(T) ≤ 0.9 × Q_pre(T), computed for the site Permissible site discharge (PSD): a tabulated unit-area release rate (m³/s/ha) by zone and AEP, derived from the 0.9 × Q_pre rule Any site outside flood-sensitive catchments
S-3 Waterbody setback extended to the mapped 1% AEP flood extent plus margin (Chapter 7) Fixed-width setback table by waterbody class, where no 1% AEP extent is mapped. Never less than the Zone 1 minimum of Clause 7.4.7 Waterbodies with no mapped 1% AEP extent
S-4 Downstream analysis by hydraulic model (Chapter 5) Screening checklist of downstream capacity and known flooding, with a model only where the screen fails Sites < 1 ha, outside flood-sensitive catchments, not discharging to a tidal outfall
S-5 On-site detention Fee-in-lieu toward a regional facility or restored tank storage in a master-planned basin (Chapter 4) Where a basin plan has been notified

1.7.3 Conditions on adoption.

  • (a) An alternative shall not lower any criterion below the values of this Manual. S-1 and S-2 are simplified methods for meeting the same criterion. They are not lower criteria.
  • (b) A Tier B authority adopts an alternative by council resolution, sent to the State Stormwater Technical Committee within 30 days. A Tier A authority needs the Committee's concurrence before adoption.
  • (c) The adopted alternatives shall be published on the Authority's website and in the register of Clause 10.17.
  • (d) Retention (Annex 2E depth) cannot be replaced by any alternative, except where fee-in-lieu under S-5 funds equivalent retention in the same basin.
  • (e) The tables for S-1, S-2 and S-3 shall be issued by the State Stormwater Technical Committee, and reviewed with Chapter 2 (Clause 2.14).

Commentary. The supplement follows the model of the APWA 5600 (2025.01) Policy Supplement, which gives alternatives for the four most contested criteria (applicability, Rational Method limits, stream setback trigger, and Zone 2 setback width). Two of those map onto S-3 and onto the applicability threshold of Clause 1.5.2. Alternative S-3 copies the APWA answer to the same problem: the 1% AEP extent is not mapped for small drainage areas, so a fixed-width table is offered. S-2 follows the Kansas City 2011 shift from "match existing" to fixed unit-area release rates. Local agencies preferred a set rate because existing conditions were hard to determine consistently (MARC Evolution deck). It also reflects the Sydney Water permissible site discharge (PSD) method. The 2 ha / 0.5 ha limits for S-1 (matching Clause 4.14.1) and the 1 ha limit for S-4 have no direct precedent; they are set by this Manual.


1.8 Relationship with other instruments

1.8.1 This Manual shall be applied together with the instruments below. Where they overlap, Clause 1.3.3 governs.

Table 1.3 — Relationship with other instruments

Instrument Relationship
Bihar Building Bye-Laws, 2014 (UDHD; Notification No. 577 (file 11/न०वि०(मा०)-06/2013), Patna, 8 December 2014, as printed in the official Hindi text), with the amendment relaxing the setbacks of commercial buildings (as reported; number and date [TBC]) Continue. They refuse permission in natural waterways and drains shown in the Development Plan or drainage plan (bye-law 29(A)), over or under a municipal drain (29(D)), and where structural plans in an area that floods do not take flooding into account (29(G)); refuse permission within 9 m of the highest water mark of a tank unless domestic drainage is kept out of it, and let the Authority require the lowest floor to be raised above the "normal maximum flood level" of the adjoining ground (30(B)); require surface-water drains in the curtilage where the Authority so requires, and written approval to connect them to a sewer (30(D)); require tree cover on at least 5% of the land (32); and bar basements in low-lying areas without adequate drainage and in flood-prone areas (47(1)). They set no design storm, release rate, detention volume or setback in metres from a nala. The 9 m tank rule is the only metre value they set; the design criteria of Chapters 2–6 and the hydraulic corridor and setbacks of Chapter 7, whose Zone 1 is at least 15 m, are this Manual's proposals; they are not statutory values, and no authority has adopted them. Where the bye-laws, the Patna Master Plan 2031 or a statute are stricter, they govern (Clause 1.3.3).
Draft Bihar Building Byelaws 2026 (UDHD, posted on 5 June 2026) A draft, not in force; it had not been notified as of September 2026 (as reported). If notified it would apply to all Municipal Corporations, Municipal Councils, Nagar Panchayats, Metropolitan Areas and Planning Areas, and to BIADA areas if the Department of Industries adopts it (cl. 1(2)), and would repeal the 2014 bye-laws with all their amendments (cl. 41(1)). It would require site plans to show water bodies, "normal flood-affected areas" and contours at 0.5 m where the slope is steeper than 1 in 20 (cl. 6), a rainwater harvesting proposal on plots of 100 m² and more (cl. 24), and no basement in low-lying or flood-prone areas (cl. 23(12)(1)); it would prohibit permanent construction within the boundary of a water body (Table 5) but set no buffer around it, and it has no 9 m tank rule and no detention rule. Clause 1.3.1(a) would apply to it as to the 2014 bye-laws.
Rainwater harvesting: BBL 2014, bye-law 51; Bihar Ground Water (Regulation and Control of Development and Management) Act, 2006, s.18 Continue unchanged. Bye-law 51 makes rainwater harvesting mandatory "for all sizes of plots", with recharge pits or trenches of at least 6 m³ for every 100 m² of roof area filled with pebbles, brick jali or river sand; terrace collection to a sump through a filter, and replacing topsoil with river sand, are optional. Under s.18 of the Act the Bihar State Ground Water Authority may direct rainwater harvesting on premises of 1,000 m² and more in notified urban areas, and a Municipal Corporation or other local authority may make rooftop harvesting a condition of plan approval for such premises, with water and electricity connections given only after compliance. None of these gives an outlet rule or a storage that is empty when a storm arrives. RWH storage is not detention unless it is a dedicated empty-on-arrival volume with an outlet, and tanks are assumed full at the start of SW monsoon storms (Chapter 4). Recharge structures may count toward retention only where they meet Chapters 4 and 8, which allow no infiltration credit on diara, chaur or tal land or in the north Bihar plain in the monsoon.
Bihar Urban Planning and Development Act, 2012 (Act 20 of 2012, amended by Act 4 of 2022) PMAA, constituted under section 11 of the Act, prepares the Patna Master Plan 2031 and area development schemes; the Act lists storm-water drainage among the contents of such schemes. Its sections were not read in full for this Manual [TBC]. This Manual does not decide zoning.
Bihar Municipal Act, 2007, Chapter XXIII (ss.193–219), and ss.177, 183, 184, 251(e) and 252 Continue. The Municipality shall construct and maintain drains and "provide a safe and sufficient outfall … in such manner as may not cause any nuisance, whether by flooding" (s.193); all public drains vest in it (s.195), and it may make them over to another authority with the State's approval (s.196); the Chief Municipal Officer may require one drain for sewage and an "entirely separate drain for rain water" (s.198); no premises may be erected or occupied without a drain to his satisfaction (s.201); a connection to a municipal drain needs his permission (s.204); and the Municipality shall prepare a Municipal Water-supply, Drainage and Sewerage Code (s.219), of which none was found for any city in the State [TBC]. Public tanks vest in the Municipality (s.177); a new tank or pond needs the Chief Municipal Officer's permission (ss.183 and 252), so a detention pond on private land in a municipal area needs it too; and the Municipality may order a tank or pond to be filled up (ss.184 and 251(e)). This Manual does not change those powers; Chapter 7 treats ponds as drainage assets.
Bihar State Water and Sewage Board (Repeal) Act, 2017 (Bihar Act 3 of 2018) The Act repealed the 1982 Act and merged all the assets, liabilities, ongoing projects and staff of the Bihar Rajya Jal Parshad into BUIDCO; its commencement notification was not found [TBC]. BUIDCO has since run Patna's sump houses and trunk drains, while the Municipal Act vests all public drains in the Municipality; the exact split between PMC and BUIDCO is not confirmed (Clause 1.9) [TBC]. Patna's nalas also carry sewage: a CAG report on Patna sewerage under Namami Gange records 19 drains discharging 628.5 MLD against six sanctioned STPs of 350 MLD, and the NGT has directed that storm water be kept separate from sewage and that BUIDCO plan its diversion (O.A. 188/2024/EZ, 5 March 2025). The interception of dry-weather flow under Chapter 8 (Clause 8.9) applies until the connections are removed.
Bihar Ground Water (Regulation and Control of Development and Management) Act, 2006 Continues, to the extent it is in force: it comes into force on dates the State notifies, area by area (s.1(3)), and whether it has been brought into force or any area notified was not confirmed for this Manual [TBC]. Arsenic above 0.01 mg/L is reported in groundwater in 27 districts, mostly along the Ganga, and fluoride above 1.5 mg/L in 19, mostly in the south (CGWB, as cited in the State's report to the NGT in O.A. 728/2023). Under Chapters 4 and 8, untreated runoff is not injected into recharge wells in the arsenic belt unless a hydrogeologist confirms the target aquifer; surface infiltration with soil treatment, or detention, is used instead. Section 18 is the statutory hook for recharge conditions.
Bihar Public Land Encroachment Act, 1956 Continues. "Public land" includes land over which the public or the community has a right of user such as irrigation, which brings community ahars and pynes within the Act; the competent officer serves notice on the occupant (s.3), hears him (s.5) and orders removal (s.6), and the burden of proof lies on the person who claims the land is not public. Chapter 7 relies on it for the recorded extent of pokhars, ahars and pynes.
Bihar Irrigation Act, 1997 Continues. It makes it an offence to erect or add to an embankment without the Collector's permission, or to damage, obstruct or encroach on an irrigation work. No setback in metres from an embankment or canal was found in it.
WRD Order No. 143 of 6 March 2025 (floodplain zoning of embanked rivers) Continues. Where both banks are embanked, the land between the embankments, and where one bank is embanked, the land from the embankment across the river to 500 m beyond the other bank, is the floodplain zone and a Prohibited Zone: no permanent construction, no increase in the floor area or height of existing structures, and nothing that obstructs the natural channel; fully temporary or movable structures are allowed only beyond 250 m from the current river bank; flood-protection works and the discharge of treated wastewater to prescribed standards are among the permitted activities; and the district administration monitors the zone. Un-embanked rivers come in a second phase, beginning with the Ganga from Chausa to Manihari, for which NIH is to delineate 5-, 25- and 100-year zones (MoU of 3 August 2025). Where the 1% AEP extent of Chapter 7 is mapped and wider, it governs.
River Ganga (Rejuvenation, Protection and Management) Authorities Order, 2016 Continues. The Order defines the floodplain by "a flood of frequency once in hundred years", bars structures in the active floodplain of the Ganga and its tributaries, and requires the prior approval of NMCG for embankments and channelisation in it (as quoted by NMCG). An amendment of the Order in 2026 is reported; its text was not read [TBC].
Wetlands (Conservation and Management) Rules, 2017; Bihar State Wetland Authority; the six Ramsar sites of the State Continue. The Rules bar construction of a permanent nature, except boat jetties, "within fifty metres from the mean high flood level" of a notified wetland. The six Ramsar sites are Kabartal (Begusarai), Nagi and Nakti (Jamui), Gokul Jalashay (Buxar), Udaipur Jheel (West Champaran) and Gogabil (Katihar); State notifications under the Rules were seen only in draft [TBC]. Where a notification is wider than the setback of Chapter 7, it governs (Clause 1.3.3).
Bihar Ease of Doing Business Act, 2026 (Act No. 32 of 2026), Schedule V In force from 16 September 2026. Schedule V, an indicative list of NOCs, marks as "Not required" the storm water drains NOC, the Revenue Department NOC for land near water bodies or nalas, the District Collector NOC for development on wet land and the Irrigation Department NOC for sites near canals, and makes groundwater extraction a matter of self-certification. Its scope is enterprises; whether it reaches the sanction of plans for housing is unclear [TBC]. The checks of this Manual are made within the sanction of the building or layout plan (Chapter 10), not as a separate NOC.
Jal-Jeevan-Hariyali Abhiyan (Rural Development Department, nodal, with fourteen other departments) Continues. An executive campaign, for which no statute or notified scheme was found; its components include the removal of encroachment from public water bodies, the restoration of ponds, ahars and pynes, and rooftop rainwater harvesting, with the progress reported on the State portal. Chapter 7 relies on it for the restoration of pokhars.
Disaster Management Act, 2005; BSDMA; the WRD Daily Flood Information Bulletin of FMISC Continue. FMISC issues its flood bulletin generally from 15 June to 15 October, and WRD's anti-erosion works are due by 15 May (as reported). No urban flood plan or SOP of BSDMA was found [TBC]. Chapter 10 links its pre-monsoon checks to these dates.
CPHEEO Manual on Storm Water Drainage Systems (2019) Engineering reference. This Manual sets higher return periods under Clause 1.3.2.
NDMA Guidelines on Management of Urban Flooding (2010) and MoHUA SOP (2017) This Manual puts into effect the NDMA directives on catchment-based design, detention and retention, waterbody protection and climate-adjusted IDF.
NDMA Urban Flood Risk Management Programme (UFRMP) and AMRUT 2.0 Works funded under these programmes shall comply with this Manual. The development controls of Chapters 4–5 protect the capacity those works create.
IRC:SP:42-2014 and IRC:SP:50-2013 Apply to road drainage only where they do not conflict with Chapter 6.
MBBL 2016, Chapter 9 Model for RWH and for the inspection regime in Chapter 10.

Commentary. RWH in Bihar is framed as a water supply and recharge measure. It works well for that purpose. It cannot, however, be relied on for flood control in the SW monsoon, because RWH sumps are usually full or the ground saturated by the time a July to September monsoon depression arrives after weeks of rain. The Manual therefore keeps harvest volume and attenuation volume apart, while letting recharge count as retention where it truly removes water from the system.

Bihar is spending on drainage. The 2026 State budget is reported to provide about ₹3,559 crore for 38 storm-water drainage schemes; BUIDCO's storm-water drainage project in Patna is reported to cover 103 drain lines in nine packages, about 185 km of drains; a Rajya Sabha reply of 27 November 2024 cites storm-water drainage projects worth ₹1,230.74 crore and 22 new drainage pumping stations worth ₹325.48 crore (seen only through a search summary); and a scheme of ₹245 crore is being built by BUIDCO in Darbhanga (as noted in a Patna High Court order, seen only through a search summary). None of these works has a published design return period, and no development-control condition stops new plots in the same catchments from using up the capacity such works create. Linking Chapters 4–5 to approvals closes that gap.

The State's law already holds many of the tools. It refuses building within 9 m of a tank and in the natural waterways and drains shown in plans, and bars basements in flood-prone areas (BBL 2014); makes rainwater harvesting mandatory on every plot; lets the Chief Municipal Officer require separate drains for sewage and rain water and forbid new tanks without permission (Bihar Municipal Act, 2007, ss.198, 183 and 252); prohibits permanent construction between the embankments of the embanked rivers (WRD Order No. 143, 2025); and recovers public land, including land under ponds, ahars and pynes, from encroachment (Bihar Public Land Encroachment Act, 1956). What it lacks is a design standard. None of these instruments says how large a drain must be, which storm it must carry, how wide the reserve along a nala or around a pokhar should be, or how much storage a filled pond or a paved plot removes. The Bihar Ease of Doing Business Act, 2026 has meanwhile marked the storm water drain and water-body NOCs as not required for enterprises, so this Manual's checks are framed as part of the sanction of the building or layout plan rather than as a separate NOC. This Manual is offered as a technical companion to these instruments and to the drainage works of BUIDCO and the Nagar Nigams: it supplies the design storm, detention and buffer numbers they do not set, as a proposal for the Government and the authorities to consider. Neither UDHD nor any other body has adopted it.


1.9 Roles and responsibilities

1.9.1 The responsibilities below apply under this Manual. They do not change any agency's statutory powers.

Table 1.4 — Roles and responsibilities under this Manual

Agency Role under this Manual
Urban Development and Housing Department (UDHD) Issues the building bye-laws, as it did the BBL 2014 and the draft of 2026; oversees the Nagar Nigams, Nagar Parishads and Nagar Panchayats, BUIDCO and PMAA; sanctions the storm-water drainage schemes of the cities. Would make the amendment of Clause 1.3.1(a), issue the model ULB bye-law of Clause 1.3.1(b), give regional support to Tier B authorities (Table 1.1) and maintain the empanelled reviewer list (Clause 10.7).
State Stormwater Technical Committee (Clause 1.3.2) Would adopt higher standards, issue Annexes, tables and the compliance calculator, concur with Tier A alternatives, decide variances referred to it and review the Manual (Clause 1.12).
Bihar Urban Infrastructure Development Corporation (BUIDCO) A company of UDHD; executes the storm-water drainage schemes of Patna and other cities, sewerage and the Namami Gange works, and, as successor to the Bihar Rajya Jal Parshad (Repeal Act of 2017), runs the sump houses and drainage pumping stations of Patna. Would apply this Manual in its DPRs and designs, design interception works that keep the storm capacity of the nala (Chapter 8), and certify the readiness of pumps and sluices (Chapter 10).
Patna Municipal Corporation (PMC) and the other Nagar Nigams; Nagar Parishads and Nagar Panchayats Hold the public drains of their areas by statute (Bihar Municipal Act, 2007, s.195), clean and maintain them, and grant building permission under the BBL 2014. In Patna the division of drains and sump houses between PMC and BUIDCO is not confirmed [TBC]. Would apply this Manual to their works, receive handed-over assets (Clause 10.14), and inspect and enforce (Clauses 10.12–10.15).
Patna Metropolitan Area Authority (PMAA) Constituted under section 11 of the Bihar Urban Planning and Development Act, 2012; prepares the Patna Master Plan 2031 and area development schemes. Would show flood-sensitive catchments, drain reserves and regional facility sites in its plans and schemes.
Water Resources Department (WRD) and its Flood Management Improvement Support Centre (FMISC) Holds the rivers, embankments, sluices and the flood-control drainage channels; zones the floodplains of the embanked rivers (Order No. 143, 2025); issues the daily flood bulletin from 15 June to 15 October (FMISC). Would provide design river levels and the sluice and pump operating rules for Chapter 5, and consent to outfalls through its embankments.
Minor Water Resources Department Holds the ahar-pyne systems and minor irrigation tanks, and the State's groundwater directorate. Would supply groundwater levels for the infiltration checks of Chapters 4 and 8, with CGWB, and certify the recorded extent of ahars and pynes for Chapter 7.
Rural Development Department Nodal department of the Jal-Jeevan-Hariyali Abhiyan, which removes encroachment from public water bodies and restores ponds, ahars and pynes. Would share its inventories of restored water bodies for Chapter 7.
Environment, Forest and Climate Change Department and the Bihar State Wetland Authority The Authority implements the Wetlands Rules 2017 in the State, identifies and notifies wetlands and proposes Ramsar sites. Would keep the list of notified wetlands and permit regulated activities in their zones (Chapter 7).
BSDMA and the District Disaster Management Authorities Approve the State and district disaster management plans. Would recommend flood-sensitive catchments, hold the record of flood-prone locations with the District Magistrates, and lead the post-event review (Clause 10.16). No urban flood SOP of BSDMA was found [TBC].
Bihar State Pollution Control Board (BSPCB) Monitors the drains and rivers and identified the drains of Patna that discharge sewage to the Ganga and the Punpun; a respondent in the NGT cases on them. Supports the removal of sewage from storm drains (Chapter 8).
Bihar Industrial Area Development Authority (BIADA) Develops and manages the industrial areas of the State; would apply this Manual to the drains of those areas, and the 2026 bye-laws, if notified, would apply there only if the Department of Industries adopts them [TBC].
Revenue and Land Reforms Department: the District Magistrates, the Sub-Divisional Officers and the anchal (circle) offices Keep the land records in which ponds, ahars, pynes and nalas are recorded; remove encroachment from public land under the 1956 Act; monitor floodplain zoning in their districts (WRD Order No. 143); lead flood relief. Would certify the recorded extent of a pokhar for Chapter 7.
Central Water Commission (CWC), a body of the Union Publishes the Flood Estimation Reports for subzones 1(d), 1(f) and 1(g) used in Chapters 2 and 3, and the river levels at its flood forecasting sites, such as Gandhi Ghat and Dighaghat on the Ganga and Sripalpur on the Punpun in Patna, Sikandarpur on the Burhi Gandak, Hayaghat on the Bagmati and Dhengraghat on the Mahananda. Would supply river stage records and forecasts for Chapter 5.
Central Ground Water Board (CGWB), a body of the Union Assesses the groundwater units of the State and their categories, and the arsenic and fluoride in groundwater. Would supply groundwater levels and quality with the Minor Water Resources Department.
National Institute of Hydrology (NIH), Roorkee, and its regional centre at Patna Runs NIH-DHAARA (Chapter 2); is to delineate the 5-, 25- and 100-year floodplain zones of the Ganga from Chausa to Manihari for WRD (MoU of 3 August 2025); its regional centre reported on short-interval rainfall in the Punpun basin (Clause 2.3.6(b)).
IMD (Meteorological Centre Patna), and road and rail owners (the Road Construction Department, NHAI, Indian Railways) IMD's stations supply the rainfall records of Chapter 2. Road and rail owners would apply this Manual to road drainage (Chapter 6), culverts and linear works (Clause 1.5.7).

Commentary. Stormwater in Bihar is split between UDHD, through the bye-laws, the Nagar Nigams, BUIDCO and PMAA; WRD, through the rivers, embankments, sluices and floodplain zoning; and the Minor Water Resources Department, through the ahar-pyne systems; the Jal-Jeevan-Hariyali campaign adds the Rural Development Department. Patna shows why the split matters. Since the Bihar Rajya Jal Parshad was merged into BUIDCO, BUIDCO has run the city's sump houses and trunk drains, while the Bihar Municipal Act, 2007 vests all public drains in the Municipality (s.195) and lets it make them over to another authority only with the State's approval (s.196). No order under section 196, and no order of UDHD, dividing Patna's drains and sump houses between PMC and BUIDCO was found [TBC]; PMC is reported to have told the NGT that the drainage system is not directly under it (seen only through a search summary), and after the waterlogging of September 2019 the Patna High Court had to ask the State which sump houses had been working and who had cleaned the nalas. Until such a rule is made, this Manual assigns the drainage elements as in Table 1.5. The assignment is this Manual's working split for applying its clauses; it does not change any agency's powers.

Table 1.5 — Working assignment of drainage elements under this Manual

Element Assigned to
Rivers, their floodplains and embankments, the sluices on the embankments, and flood-control drainage channels WRD
Ahars, pynes and minor irrigation tanks Minor Water Resources Department
Sump houses, drainage pumping stations and trunk drains in Patna, and the storm-water drainage schemes that BUIDCO builds in other cities, until an order assigns them otherwise BUIDCO
Nalas, road-side and lane drains and public tanks within the limits of a local body, other than those assigned to BUIDCO The Nagar Nigam, Nagar Parishad or Nagar Panchayat
Sewers, interceptors and the interception and diversion of nalas, and sewage treatment plants BUIDCO
Drains of State and national highways The Road Construction Department or NHAI
Drains within an industrial area BIADA
Notified wetlands The Bihar State Wetland Authority, with the owner of the land

This Manual names departments and authorities as the statutes, orders and records name them. A manual that names one owner for each task does not fix institutions by itself, but it removes ambiguity about who signs what.


1.10 Variances and waivers

1.10.1 Variance. The Authority may grant a variance from a numeric requirement where the Applicant shows, through a report certified under Clause 10.6, that:

  • (a) compliance is impracticable because of site conditions such as a high groundwater table, contaminated soil, rock, or a site area too small for the required facility; and
  • (b) the proposed alternative gives equal or better performance at the downstream point of Chapter 5, or the shortfall is made up by fee-in-lieu or off-site works in the same catchment.

1.10.2 Waiver. The Authority may waive Chapter 4 detention requirements (not retention) where a hydraulic analysis certified under Clause 10.6 shows that the site discharges directly to the sea, or to a tidal reach with no flood-prone property downstream, and that undetained flow does not worsen the outfall-closed condition of Chapter 5. Bihar has no coast and no tidal reach, so no site in the State qualifies for this waiver. A site that drains to a river through a sluice or flap gate in an embankment, as along the Ganga and the Punpun at Patna, or only by pumping through a sump house, is in the outfall-closed condition of Chapter 5 whenever the river is high, and detention is not waived for it.

1.10.3 No variance or waiver. No variance or waiver shall be granted for:

  • (a) a sewage connection to a storm drain;
  • (b) the lowest habitable floor level of Chapter 6;
  • (c) any reduction of a waterbody setback below the Zone 1 minimum of Clause 7.4.7, or any fill or construction in the no-fill zone of Chapter 7; or
  • (d) the retention requirement in a flood-sensitive catchment, except by fee-in-lieu under Clause 1.7.

1.10.4 Procedure.

  • (a) The request shall be made on Form 1-2 (Variance / Waiver Request) with the preliminary drainage report.
  • (b) A Tier B authority shall refer any variance on a site of 1 ha or more to the State Stormwater Technical Committee.
  • (c) A decision shall state its reasons and any conditions, and shall be entered in the public register of Clause 10.17.
  • (d) A variance runs with the approval. It lapses if the approval lapses.

Commentary. The 2006 APWA 5600 included a waivers section (5601.6), and Georgia allows waivers where downstream analysis shows a peak control is unnecessary. The waiver of Clause 1.10.2 is narrow: on a tidal coast, undetained flow can help by passing through before the tide closes the outfall, but only an analysis can show that. This Manual requires every decision to be published because publication deters case-by-case erosion of the standard; in Bihar the NGT has had to direct that encroachment be removed from three ponds in Darbhanga within three months (O.A. 155/2022/EZ, order of 23 March 2023, as stated in the applicants' later filing), and the State's own Jal-Jeevan-Hariyali campaign reports encroachment removed from 28,685 ponds, ahars, pynes and wells (State portal).


1.11 Transition provisions

1.11.1 Effective date. This Manual takes effect for new applications 6 months after notification (the effective date).

1.11.2 Applications in process. An application filed complete before the effective date may be decided under the rules in force when it was filed, if a decision is issued within 12 months of the effective date. Otherwise, this Manual applies.

1.11.3 Phased start for Tier B. In Tier B authorities, Chapters 4 and 5 apply from 24 months after notification, except in flood-sensitive catchments, where they apply from the effective date.

1.11.4 Public works. DPRs sanctioned before the effective date may proceed as sanctioned. Any DPR revised or re-tendered after the effective date shall comply. Departments shall report non-compliant works in progress to the State Stormwater Technical Committee within 12 months.

1.11.5 Before the annexes are issued. Until an annex referred to in this Manual is issued, the Applicant shall use the method stated in the clause, with values agreed with the Authority and recorded in the drainage report.

Commentary. The 6-month lead time matches the lead time for NIH-DHAARA updates in Clause 2.14.2. Singapore gave a similar interval for its 2025 detention addendum (issued 16 Apr 2025, applied from 1 Oct 2025). The 12- and 24-month periods are set by this Manual to let Tier B authorities train staff and to let the State issue the design-aid tables (Clause 1.7).


1.12 Review and amendment

1.12.1 The State Stormwater Technical Committee shall review this Manual every 10 years, and after any event that exceeds the 1% AEP design depth as set out in Clause 2.14.1.

1.12.2 Amendments shall be notified in the Gazette, published with a change log, and take effect 6 months after notification unless the notification states otherwise.

1.12.3 Any person may propose an amendment to the Committee. Proposals and the Committee's decisions shall be published.


References (chapter)

Annexes and forms

Annex / Form Content
1A List of Tier A authorities, with the boundaries of the Nagar Nigams and of the Patna Metropolitan Area
1B Maps of flood-sensitive catchments
1C Policy Supplement: text of alternatives S-1 to S-5 and model council resolution
1D Model BBL 2014 amendment and model ULB bye-law
Form 1-1 Applicability Determination
Form 1-2 Variance / Waiver Request