Chapter 4Site Runoff Control: Retention and Detention
4.1 Purpose and scope
4.1.1 This chapter sets the performance standard that every regulated development shall meet for runoff leaving the site. It covers:
- (a) the order in which runoff-control measures are to be applied (Clause 4.3);
- (b) retention of frequent rainfall, and how retained volume is credited against detention (Clause 4.4);
- (c) release-rate criteria for standard and flood-sensitive catchments (Clause 4.5);
- (d) the procedure for sizing detention storage and outlets (Clauses 4.6 to 4.9);
- (e) facility types, rainwater harvesting (RWH) accounting, and high-groundwater sites (Clauses 4.10 to 4.12);
- (f) regional detention and fee-in-lieu (Clause 4.13);
- (g) simplified methods for small sites: the Tier B tables and the fixed-coefficient route (Clause 4.14); and
- (h) public safety (Clause 4.15).
4.1.2 This chapter applies to land disturbance of 0.1 ha or more, or new or replaced impervious area of 500 m² or more, as set in Chapter 1. Single dwellings below that threshold, and road resurfacing that adds no impervious area, are exempt. The existing RWH mandate of the building rules (rainwater harvesting on plots of all sizes, with recharge pits or trenches of at least 6 m³ for every 100 m² of roof area, under bye-law 51 of the Bihar Building Byelaws 2014; the directions that the Bihar State Ground Water Authority may issue, and the conditions that a Municipal Corporation or other local authority may impose on building plans, for premises of 1,000 m² and more under section 18 of the Bihar Ground Water (Regulation and Control of Development and Management) Act 2006, whose commencement and notified areas were not confirmed [TBC]; and, if it is notified, clause 24 of the Draft Bihar Building Byelaws 2026, which would require a complete rainwater harvesting proposal on plots of 100 m² and more; the rules are discussed in the Commentary to Clause 4.11) continues to apply to every building it covers, whether or not this chapter applies.
4.1.3 Rainfall inputs come from Chapter 2. Hydrologic methods come from Chapter 3. Tailwater, downstream analysis and the outfall-closed check come from Chapter 5. Water quality volume (WQv) treatment comes from Chapter 8. Where this chapter and those chapters overlap, the more stringent requirement governs.
4.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Retention | Permanent removal of runoff from the surface drainage system by infiltration, evapotranspiration or reuse, so that the water never reaches the outfall. |
| Retention depth | The 90th percentile wet-day 24-hour rainfall depth for the site's zone (Clause 2.10, Annex 2E). |
| Required retention volume (RRV) | The runoff volume from the retention depth over the post-development site (Clause 4.4.2). |
| Detention | Temporary storage of runoff, released through a controlled outlet at a rate set by Clause 4.5. |
| Retention credit | The reduction in required detention storage that results from retention practices, determined by routing under Clause 4.4.6. It is not the same as the retained volume. |
| Permissible site discharge (PSD) | The maximum rate at which a site may discharge for a stated AEP, in L/s or L/s/ha. |
| Site storage requirement (SSR) | The detention storage required per hectare of site under the simplified method of Clause 4.14. |
| Multi-stage outlet | An outlet structure with separate openings at different levels, each controlling a different AEP (Figure 4.2). |
| Drawdown time | Time from the peak stored volume until the stated fraction of that volume has been released. |
| Emergency spillway | A secondary overflow that passes flows above the primary outlet capacity, or all flow when the primary outlet is blocked, without overtopping the embankment. |
| Freeboard | Vertical distance between the maximum design water level and the embankment crest or other critical level. |
| Flood-sensitive catchment | A catchment listed in Clause 4.5.3 or notified under Clause 4.5.4. |
| Authority | The approving authority under Chapter 1 (the Nagar Nigam, Nagar Parishad or Nagar Panchayat that grants building or layout permission under the Bihar Municipal Act 2007 and the Bihar Building Byelaws 2014; the Patna Metropolitan Area Authority or another authority under the Bihar Urban Planning and Development Act 2012, where it grants that permission; or BIADA in its industrial areas [TBC], as applicable). |
| Tier A / Tier B | Adoption tiers defined in Chapter 1. Tier A: the Patna Municipal Corporation (PMC), every approving authority within the Patna Metropolitan Area under the Bihar Urban Planning and Development Act 2012, including PMAA where it is the approving authority and the Nagar Parishads and Nagar Panchayats in that area, and every other Nagar Nigam constituted under the Bihar Municipal Act 2007. Tier B: Nagar Parishads and Nagar Panchayats. |
4.3 Order of measures
4.3.1 Every site runoff-control design shall apply measures in the following order, and shall document in the submittal why each earlier step could not do more:
- Preserve. Keep existing waterbodies, pokhars, natural drainage lines, wetlands, and permeable soils and vegetation. Avoid fill in flood storage (Chapter 7).
- Retain. Retain the RRV on site by infiltration, reuse or evapotranspiration (Clause 4.4).
- Detain. Detain the remaining runoff so that the release-rate criteria of Clause 4.5 are met for every design storm and duration (Clauses 4.6 to 4.9).
- Convey. Convey the 1% AEP (100-yr) flow safely through the site to the receiving system on a defined overland path (Chapter 6), and check the receiving system downstream (Chapter 5).
4.3.2 Preservation and retention reduce the detention required (Clauses 4.4.6 and 4.4.7). They do not relieve the site of the release-rate criteria of Clause 4.5 or of the downstream analysis of Chapter 5.
Commentary. This order follows the "layers of stormwater management" adopted in the Kansas City Metro APWA Section 5600 Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet; MARC Supplement, Nov 2025). Maintenance is the fifth layer and is set in Chapter 10. The 2025.01 manual credits retention and natural-area preservation against detention size (MARC Supplement, Nov 2025). Clause 4.4.6 adopts that credit, and defines it so that it cannot be claimed twice.
4.4 Retention
4.4.1 Requirement
The site shall retain the RRV. Retention shall be achieved by one or more of the following:
- infiltration practices (soakaways, infiltration trenches, permeable pavement with an infiltration base, bioretention);
- rainwater reuse that is drawn down by a demonstrated non-potable demand;
- green roofs and landscape areas that do not drain to the outfall in the retention-depth storm.
The limits of Clause 4.4.4 apply.
4.4.2 Computation of the RRV
RRV (m³) = 10 × Q_R × A
where:
- Q_R (mm) is the runoff depth from the retention depth P_R (Annex 2E). It is computed with the SCS-CN method for the post-development cover of each sub-area, at AMC II, with Ia = 0.2S (Chapter 3); and
- A (ha) is the area of the site that drains to the outfall.
Q_R shall be computed for each sub-area separately and summed. An area-weighted CN shall not be used where impervious and pervious areas differ by more than 20 CN points.
The volumetric method RRV = 10 × P_R × Rv × A, with Rv = 0.05 + 0.009 × I (I = percent impervious), may be used for sites under 0.5 ha and under the Tier B method.
Commentary. The Rv formula is the one used in the KC water quality volume (MARC BMP Manual 2012). It is simple to review for small sites. The SCS-CN form is required for larger sites so that the retention computation uses the same runoff model as the detention routing. That keeps the credit computation of Clause 4.4.6 consistent.
4.4.3 Verification
Retention by infiltration shall be supported by:
- (a) site infiltration tests at the location and depth of each practice, at the frequency set in Chapter 8;
- (b) a design infiltration rate of no more than half of the measured rate; and
- (c) groundwater evidence showing the seasonal high groundwater table at least 1.0 m below the base of the practice (Chapter 8).
Retention by reuse shall be supported by a demand calculation showing that the RRV is drawn down within 72 hours by a continuous non-potable use, such as toilet flushing, cooling or irrigation.
Commentary. The factor of 2 on measured infiltration rate has no direct precedent; this Manual sets it to allow for clogging and for the difference between a test pit and a full-scale practice. Chapter 8 may set a different factor; if it does, Chapter 8 governs.
4.4.4 Limits on retention
4.4.4.1 Infiltration practices shall not be used:
- where the seasonal high groundwater table is less than 1.0 m below the base (Chapter 8);
- on contaminated land;
- within the setbacks from foundations, wells and septic systems set in Chapter 8; or
- on fill, unless tested after placement.
4.4.4.2 Where the RRV cannot be fully retained, the shortfall shall be stated in the submittal. The shortfall shall be treated as WQv under Chapter 8 and shall get no retention credit.
4.4.5 Drawdown of retention
Retention storage shall be emptied by infiltration or reuse within 72 hours of the end of the retention-depth storm, verified by the tests of Clause 4.4.3.
4.4.6 Retention credit: definition and computation
4.4.6.1 What the credit is. The retention credit is the reduction in required detention storage that results when the retention practices are included in the post-development routing. It is computed. It is not assumed equal to the RRV.
4.4.6.2 Tier A method (routing). For each design storm and duration of Clause 4.6.3:
- (a) model each retention practice explicitly as a storage that is empty at the start of the storm, unless Clause 4.11 says otherwise;
- (b) let the practice fill from the front of the storm, and let it lose water during the storm only at the design infiltration or reuse rate of Clause 4.4.3;
- (c) once it is full, route its overflow to the detention facility; and
- (d) size the detention for the residual hydrograph.
The required detention storage is the largest storage over all storms and durations. The credit is the difference between that storage and the storage required with no retention. No further deduction shall be made.
4.4.6.3 Tier B method (simplified). The detention storage required by Clause 4.14 may be reduced by:
V_credit = C_R × RRV_provided
where C_R is the retention credit factor from Annex 4B for the zone, soil group and drawdown rate. Until Annex 4B is published, C_R = 0.
4.4.6.4 Retention that is not verified under Clause 4.4.3 gets no credit.
Commentary. "Credited against detention" (APWA 5600 2025.01) can be read in two ways. One reading subtracts the retained volume from the detention volume, cubic metre for cubic metre. The other routes the storms with retention in place and sees what detention is still needed. The two readings give very different answers in Bihar, because the mandatory 48- and 72-hour storms (Clause 2.5.2) fill any retention practice on the first day, long before the peak arrives on the last day (Clause 2.9.2). Unless the practice keeps infiltrating during the storm, it is full at the peak and does nothing to reduce the peak storage.
The illustrative example in Clause 4.6.7 shows the size of the effect. A 2 ha site with 552 m³ of retention (no infiltration during the storm) needs 138 m³ less detention for the 24-hour storm. That is a credit of about a quarter of the retained volume. For the 48- and 72-hour storms, which govern, the credit is close to zero. Subtracting the retained volume directly would have under-sized the detention by about 545 m³ (about 19%).
This Manual therefore defines the credit as the result of routing. Retention on fast-draining sandy soils, which keeps infiltrating through a multi-day storm, will earn a real credit. Retention that only fills will earn little. Both outcomes are physically correct. Setting C_R = 0 until Annex 4B exists is a safe default for Tier B, not a judgement that retention has no value: retention is still required for water quality and recharge (Chapter 8).
4.4.7 Preservation credit
Areas of the site that are permanently preserved in natural cover may be modelled at their pre-development CN in the post-development condition, provided that:
- they are protected by a registered covenant or dedication; and
- their runoff is not concentrated onto impervious surfaces.
This lowers both the RRV and the detention required. No other preservation credit applies.
4.5 Release-rate criteria
4.5.1 General
4.5.1.1 Peak discharge from the site shall be computed by a hydrograph method (Chapter 3) for the pre-development and post-development conditions with identical design storms (Clause 2.11.1). The Rational Method shall not be used for any part of storage sizing.
4.5.1.2 Pre-development is greenfield: open land in good condition for the mapped HSG. Existing impervious cover is not counted (Clause 2.11.5, Chapter 3). This applies to redevelopment as well, subject only to the constrained-redevelopment route of Clause 4.5.6.
4.5.1.3 The criteria apply at each point where runoff leaves the site. Where a site drains to more than one outfall, the criteria apply to each outfall for the area draining to it. Runoff shall not be diverted between catchments.
4.5.2 Standard catchments
For each of the 50%, 10% and 1% AEP (2-, 10- and 100-yr) storms, and for every duration in {1, 2, 3, 6, 12, 24, 48, 72 h}:
Q_post(T, d) ≤ 0.9 × Q_pre(T, d)
4.5.3 Flood-sensitive catchments
4.5.3.1 In the catchments listed below, the mixed-frequency rule of Clause 2.11.3 applies, for every duration in Clause 2.5.2:
Q_post(1% AEP, 100-yr) ≤ Q_pre(10% AEP, 10-yr), and Q_post(50% AEP, 2-yr) ≤ Q_pre(50% AEP, 2-yr).
Each cap is the pre-development peak at the duration that maximises it: the 10-yr peak for the 100-yr check, and the 2-yr peak for the 2-yr check. The cap applies to every post-development duration (Clause 2.11.3).
4.5.3.2 The flood-sensitive catchments are:
- (a) Patna behind the Ganga, the Sone and the Punpun: the catchments of the drains of Patna, Danapur, Phulwari and Khagaul that outfall to the Ganga or the Punpun through sump houses, drainage pumping stations or sluices, including the low-lying colonies of Rajendra Nagar, Kankarbagh and Pataliputra Colony, which cannot discharge to the rivers by gravity when they are high;
- (b) Muzaffarpur on the Burhi Gandak: the city of Muzaffarpur, whose drains outfall to the Burhi Gandak and are held up when the river is high;
- (c) Darbhanga between the Bagmati and the Adhwara group: the city of Darbhanga, with its pokhars, whose drains outfall to the Bagmati and the Adhwara group of rivers and are held up when they are high;
- (d) tal and chaur land: land in the Mokama group of tals (the Fatuha, Bakhtiarpur, Barh, More, Mokama, Barahiya and Singhaul tals) and in the chaurs and mauns of north Bihar, and the catchments that drain to them; and
- (e) any catchment notified under Clause 4.5.4.
The boundaries shall be those mapped in Annex 4A.
4.5.4 Notification of further flood-sensitive catchments
4.5.4.1 The Authority may propose that a catchment be notified as flood-sensitive where one or more of the following is documented:
- (a) buildings or arterial roads flooded in an event of 1% AEP or more frequent, on at least two occasions in the previous 20 years;
- (b) receiving drains or channels with capacity below the 10% AEP flow under existing conditions;
- (c) an outfall that is closed by a sluice, gate or flap gate in a river embankment or town protection wall when the river is high, or that depends on a sump house or drainage pumping station, as along the Ganga and the Punpun at Patna, or that is held up by a river in flood, such as the Burhi Gandak at Muzaffarpur, the Bagmati at Darbhanga, the Ganga at Bhagalpur and Munger or the Mahananda at Purnia, for part of the SW monsoon (Chapter 5);
- (d) loss of more than a quarter of the mapped tank and pokhar storage in the catchment since the earliest available survey; or
- (e) a basin master plan that relies on limiting site discharge.
4.5.4.2 The procedure shall be:
- The Authority prepares a technical note with the catchment boundary in GIS form and the evidence for 4.5.4.1.
- The State-level technical committee constituted under Chapter 1 reviews the note.
- The draft notification and map are published for public comment for at least 60 days.
- The Government notifies the catchment and the map is added to Annex 4A.
- The rule applies to applications received 6 months or more after notification. Applications received earlier are assessed under Clause 4.5.2.
4.5.4.3 A notified catchment may be de-notified only by the same procedure, and only after a basin study shows that the downstream system meets Chapter 5 with all development under Clause 4.5.2.
Commentary. The 0.9 factor is derived from the Denver (MHFD) analysis. In that analysis, ten basins each releasing 100% of the historic 100-yr peak still produced 106% of the historic peak at the outlet; releasing 90% at each gave 97% (UDFCD Full Spectrum Detention Release Rate Memorandum, 2012). The mixed-frequency rule has no direct precedent; the nearest is the Malaysian DID (2008) checklist, which required post-development 2-, 10-, 50- and 100-yr peaks below the pre-development 2-yr peak. The specific "100-yr post ≤ 10-yr pre" form appears in a New Berlin, Wisconsin planning discussion (not an adopted rule). The Patna entry follows the way the city drains. Patna is ringed by the Ganga on the north, the Sone on the west and the Punpun on the south; its outfalls are pumped, and when the rivers are high the sluices on the Ganga and the Punpun are closed and the city drains only through its sump houses and drainage pumping stations (as reported). In the waterlogging of 27–30 September 2019, after about 211–226 mm of rain in four days (the totals reported differ), Rajendra Nagar, Kankarbagh and Pataliputra Colony stayed under water for days, the NDRF rescued more than 4,000 people, and about 38 of the city's 39 sump houses were reported not working (as reported); the Patna High Court, by an order of 18 October 2019 in CWJC No. 15027 of 2018, called on the State to report on the sump houses and the nala contractors. That rain was less than a 50-yr 24-hour depth: the failure was of drainage and pumping, not of rainfall. Rajendra Nagar and Kankarbagh are reported to have flooded in every monsoon since the 1970s (as reported). The Punpun at Sripalpur reached 53.91 m in 1976, 3.31 m above its danger level of 50.60 m, the largest margin of any CWC site at Patna (CWC); it is the backwater that holds up the drains of south Patna. The Muzaffarpur entry follows the Burhi Gandak, which reached 54.29 m at Sikandarpur in 1987, 1.76 m above its danger level of 52.53 m (CWC), and the city's recurrent waterlogging (as reported); 436.0 mm fell at Muzaffarpur on 26 September 2007 (IMD). The Darbhanga entry follows the Bagmati at Hayaghat, which reached 48.96 m in 1987 against a danger level of 45.72 m, and the Adhwara group at Ekmighat, 49.52 m in 2004 against 46.94 m (CWC); the city's ponds are the subject of NGT O.A. 155/2022/EZ, and its storm water drainage project was challenged before the NGT in 2025 (as reported). The tal and chaur entry follows the land itself: about 1,062 km² of the Mokama group of tals is waterlogged in the monsoon and drains slowly to the Ganga (NIH and other reports, as reported), and a chaur is a low tal "in which rainwater stays for many days" (Hindi Shabdasagara), so a site in either drains to storage that is already full. Bhagalpur and Munger on the Ganga, where Bhagalpur set its highest level of 34.86 m in 2021 (CWC), Purnia on the Mahananda, which set its highest level at Dhengraghat in 2017, Hajipur on the Gandak and Chhapra on the Ghaghra are candidates for notification under Clause 4.5.4. The notification triggers in 4.5.4.1 have no direct precedent and are set by this Manual. The 6-month lead time follows the update rule of Clause 2.14.2. Clause 4.16 explains why releases below pre-development are needed at all.
4.5.5 Minimum outlet and short-duration 2-yr checks
4.5.5.1 Where the PSD for any AEP and duration is less than the discharge of a 50 mm orifice (Clause 4.8.2) at the corresponding stage, the 50 mm orifice is deemed to comply for that AEP and duration.
4.5.5.2 Where meeting the 2-yr criterion at a duration of 3 hours or less would require a low-flow orifice so small that the drawdown requirement of Clause 4.7 cannot be met, the designer shall:
- size the low-flow orifice as the smallest opening that meets Clause 4.7; and
- report the resulting 2-yr exceedance for those durations.
The Authority may accept the design if the exceedance is below the discharge of the 50 mm orifice at the 2-yr stage, or if the downstream analysis of Chapter 5 shows no adverse effect.
Commentary. Under AMC II, a greenfield site produces almost no runoff in a 1- or 2-hour, 2-yr storm, because most of the rain is lost to initial abstraction. A pre-development peak of a few litres per second, compared duration by duration, then forces a very small low-flow orifice. That orifice cannot release the 10-yr volume within 48 hours. Checked as if it were outside a flood-sensitive catchment, the illustrative example of Clause 4.6.7 would need a low-flow orifice of about 75 mm to match the 1-hour, 2-yr pre-development peak. 90% drawdown of the 10-yr volume would then take about 84 hours even with a clean orifice, against the 48-hour limit. The 170 mm orifice that meets drawdown with 50% blockage exceeds the 1-hour, 2-yr pre-development peak by about 11 L/s. Clause 4.5.5.2 resolves that conflict in favour of drawdown, because a basin that is still partly full when the next SW monsoon storm arrives fails in the event that matters more. KC APWA 5600 (2006) used a 75 mm (3 in) minimum orifice with trash racks. This Manual sets a 50 mm minimum (Clause 4.8.2).
4.5.6 Constrained redevelopment sites
4.5.6.1 Eligibility. The relief route of this clause is available only for redevelopment where all of the following hold:
- (a) the existing site is at least 60% impervious, as surveyed before demolition;
- (b) the site is 1 ha or less; and
- (c) the designer shows, in a Constraint Statement submitted with Form 4-1, that the greenfield criteria of Clauses 4.5.2 or 4.5.3 cannot be met on the site. The statement must show that every storage option of Clause 4.10 has been assessed: rooftop and podium storage, tanks under parking or landscape, permeable paving with sub-base storage, and landscape depressions. It must also give the storage each option can provide.
New development on undeveloped land is never eligible.
4.5.6.2 Minimum on-site performance. An eligible site shall provide all of the following on site:
- (a) the full retention volume (Clause 4.4) and the WQv treatment (Chapter 8), with no relief;
- (b) post-development peak discharge no more than 50% of the existing-condition peak for the 50%, 10% and 1% AEP storms, at each duration of Clause 2.5.2. The existing condition is modelled under Clause 3.3.4; and
- (c) no increase in the 1% AEP water level at any building or road downstream (Chapter 5).
4.5.6.3 Shortfall. The shortfall is the detention storage required to meet the greenfield criteria (Clause 4.6) minus the storage provided on site under 4.5.6.2. The applicant shall pay for the shortfall as a fee-in-lieu at the unit rate of Clause 4.13.3. The fee shall be:
- (a) paid into the ring-fenced account of the basin in which the site lies;
- (b) spent only on regional detention or on restoring pokhar or tank flood storage identified in the basin stormwater master plan (Chapter 11); and
- (c) recorded in the public ledger of Clause 4.13.4, which shall show the volume owed and the volume delivered in each basin.
Where no basin master plan has yet been approved, the fee shall be held for up to 5 years. If no plan is approved in that time, it shall be spent on restoring tank flood storage in the same basin, with WRD agreement.
4.5.6.4 Flood-sensitive catchments. In the catchments of Clause 4.5.3, the route is available under the same conditions. The Authority may, however, refuse it where the downstream analysis of Chapter 5 shows existing flooding of buildings in the 10% AEP event within the analysis extent.
Commentary. Greenfield is the target for all redevelopment, because a dense city only reduces its runoff as it rebuilds. On small, fully built plots in areas such as the old town of Patna City at the east end of Patna, or the old cores of Gaya, Bhagalpur and Darbhanga, there is often no space for the full greenfield storage. A rule that cannot be met invites variances and non-compliance, which help no one downstream. This clause follows the approach of the UK Non-statutory Technical Standards for Sustainable Drainage (Defra, 2015, S2–S3). For previously developed sites, those standards require peak runoff "as close as reasonably practicable to the greenfield runoff rate" and never above the pre-redevelopment rate. The fixed 50% minimum reduction has no direct precedent; this Manual sets it to give reviewers a clear number in place of a "reasonably practicable" judgement. The fee-in-lieu turns the shortfall into regional storage in the same basin, so the basin still receives greenfield-equivalent control in total. Retention and water quality get no relief, because they are small volumes that almost every site can hold.
4.6 Detention sizing procedure
4.6.1 Method
Detention shall be sized by hydrograph routing through the stage–storage–discharge relationship of the facility, by level-pool (Modified Puls) or an equivalent numerical method (SWMM, HEC-HMS). Fixed-ratio and Rational-based storage formulae shall not be used. The simplified methods of Clause 4.14 (the Tier B tables and the fixed-coefficient route) are the only exceptions.
4.6.2 Steps
- Delineate the site and sub-areas. Map HSG and confirm by testing (Chapter 3).
- Extract design rainfall for 50%, 10% and 1% AEP and every duration in Clause 2.5.2, with the climate factor (Chapter 2, Form 2-1).
- Build design hyetographs: alternating block for ≤ 24 h; the "peak day last" pattern for 48 and 72 h (Clause 2.9).
- Compute pre-development hydrographs (greenfield CN; AMC III for storms of every duration from 15 June to 30 September in sub-areas BR-A, BR-B and BR-C and on tal, chaur and diara land, and in July–August in BR-D and BR-E, and at other sites and times after a 5-day total of more than 53 mm, AMC II otherwise).
- Compute the release caps for each AEP and duration under Clause 4.5.2 or 4.5.3.
- Compute post-development hydrographs with the same storms and AMC, including retention practices (Clause 4.4.6).
- Choose a trial facility geometry (stage–storage) and a multi-stage outlet (Clause 4.6.5).
- Route every storm and duration. Use a time step of no more than 5 minutes, and no more than Tc/3 of the post-development catchment.
- Check every release against its cap, and check drawdown (Clause 4.7). Adjust the outlet and storage and repeat.
- Check the tailwater condition of Clause 4.6.6 and the downstream analysis of Chapter 5.
- Size the emergency spillway and set freeboard (Clause 4.9).
- Report the governing storm for storage, for each outlet stage, and for the spillway (Clause 4.17).
4.6.3 Storms to be routed
Every facility shall be routed for the full matrix:
Table 4.1 — Design storms to be routed for detention sizing
| AEP | Durations (h) | AMC |
|---|---|---|
| 50% (2-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
| 10% (10-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
| 1% (100-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
The 24-, 48- and 72-hour runs are mandatory whatever the critical-duration result (Clause 2.5.2). Where Ia = 0.05S sensitivity is required by Chapter 3, it shall be run for the governing storage case.
4.6.4 Initial conditions
Each run shall start with:
- detention storage empty, down to the invert of the lowest outlet;
- any permanent pool full;
- retention practices empty, except as limited by Clause 4.11; and
- RWH storage full (Clause 4.11).
The 48- and 72-hour storms already contain their antecedent rain, so no further pre-filling is applied.
4.6.5 Multi-stage outlet design
4.6.5.1 The outlet shall have a separate control for each criterion, normally stacked as in Figure 4.2:
- Stage 1, at the invert: the low-flow orifice. It releases the WQv over 24–48 h (Chapter 8) and controls the 2-yr release.
- Stage 2: an orifice or slot set at or near the maximum 2-yr level. It controls the 10-yr release.
- Stage 3: a weir, riser crest or larger orifice set at or near the maximum 10-yr level. It controls the 100-yr release.
- Emergency spillway: separate from the primary outlet (Clause 4.9).
Stages may be combined where routing shows that every cap is met.
4.6.5.2 Orifices shall be computed with a discharge coefficient of 0.60 unless a rated device is used. Weirs shall use a coefficient appropriate to their shape. Submerged-outlet and tailwater effects shall be included (Clause 4.6.6).
4.6.5.3 Vortex flow controls and other proprietary devices may be used where the supplier provides a certified head–discharge curve and the minimum clear opening is at least 50 mm.
4.6.6 Tailwater on the outlet
The outlet shall be routed against the tailwater of the receiving system, not free outfall, wherever the receiving water level can rise above the outlet invert. The tailwater shall be:
- for a receiving drain: its water level in the same storm, from the Chapter 5 analysis or, for Tier B, the drain obvert;
- for tidal or backwater-affected outfalls: the levels and joint cases of Clause 2.12 and Chapter 5, including the outfall-closed check (Clause 5.10).
Where tailwater governs, a flap gate shall be fitted to the outlet (Clause 5.11). The storage below the tailwater level shall not be counted as available unless the routing includes the gate closure.
4.6.7 Illustrative example
Illustrative — not design values. This example shows the procedure and the sizes it produces. The inputs are invented to be plausible for a low-lying colony in south Patna behind the Punpun. They are not NIH-DHAARA values and must not be used for design.
Inputs:
- Site: 2.0 ha, flood-sensitive catchment (Clause 4.5.3).
- Land cover: pre-development all pervious, CN 70. Post-development as two sub-areas (Clause 3.9.2): 1.57 ha of directly connected impervious surface at CN 98, never converted for AMC, and 0.43 ha of pervious open space at CN 70, on the same soil as pre-development; the area-weighted CN at AMC II is 92. For storms of 12 h and longer the pervious CN only is converted to AMC III: CN_III = 23·CN / (10 + 0.13·CN) = 84.3 (Clause 3.8.4).
- Time of concentration (Tc): 45 min pre-development, 15 min post-development (used for both sub-areas). SCS triangular unit hydrograph; 5-minute time step.
- 24-h depths: 110, 200 and 350 mm for 2-, 10- and 100-yr (the same 10- and 100-yr values as Clause 2.11).
- Shorter durations: P(t) = P24·(t/24)^0.40, an assumed ratio set and not Annex 2B.
- Longer durations: 48-h and 72-h depths taken as 1.25 and 1.40 × P24, laid out per Clause 2.9.2.
- Storage: vertical-walled, 2,500 m² plan area.
- Outlet, sized so that drawdown is met with the low-flow orifice 50% blocked (Clause 4.8.3). Annex 4C shows the trial outlet that failed this check.
- Stage 1: 170 mm orifice at the invert.
- Stage 2: 460 mm orifice with its invert 0.53 m above the floor.
- Stage 3: none needed, because the 100-yr cap is met by Stages 1 and 2.
Results (discharges in L/s; storage in m³):
Table 4.2 — Illustrative example: peak discharges and storage used, by duration (Illustrative — not design values)
| Duration (h) | 2-yr pre | 2-yr post, detained | 10-yr pre | 10-yr post, detained | 100-yr post, uncontrolled | 100-yr post, detained | 100-yr storage used | 10-yr drawdown, 50% blocked (h) |
|---|---|---|---|---|---|---|---|---|
| 1 | 4 | 15 | 51 | 28 | 922 | 42 | 1,426 | 31.3 |
| 2 | 14 | 20 | 84 | 34 | 961 | 79 | 1,911 | 32.1 |
| 3 | 19 | 22 | 104 | 37 | 981 | 139 | 1,999 | 32.8 |
| 6 | 32 | 25 | 150 | 41 | 1,010 | 194 | 2,154 | 34.2 |
| 12 | 127 | 30 | 302 | 46 | 1,074 | 276 | 2,512 | 39.0 |
| 24 | 149 | 32 | 327 | 49 | 1,081 | 320 | 2,766 | 45.3 |
| 48 | 173 | 34 | 349 | 82 | 1,087 | 343 | 2,913 | 44.8 |
| 72 | 180 | 34 | 356 | 84 | 1,089 | 343 | 2,911 | 44.7 |
How to read it:
- 100-yr cap. The cap is the largest pre-development 10-yr peak, 356 L/s (72 h). Every 100-yr detained peak is at or below it; the largest is 343 L/s.
- 2-yr cap. The site is flood-sensitive, so the 2-yr cap is the largest pre-development 2-yr peak, 180 L/s (72 h; Clause 4.5.3.1). The largest 2-yr detained peak is 34 L/s. At 1, 2 and 3 hours the detained 2-yr peak is above the pre-development peak of the same duration (15 against 4 L/s, 20 against 14 L/s, and 22 against 19 L/s). That comparison is not required here. It would be for a site under Clause 4.5.2, and Clause 4.5.5.2 would then apply.
- Governing storage. Storage is governed by the 48- and 72-hour storms: 2,913 m³, which is 0.146 m³ per m² of site, at a maximum depth of 1.17 m. A design that checked only the critical-duration peak storm (1–3 h here) would have provided about 2,000 m³, roughly two-thirds of what is needed.
- Drawdown. With the low-flow orifice 50% blocked (Clause 4.8.3), 90% of the 10-yr storage drains in at most 45.3 h (the 24-hour storm), within the 48 hours of Clause 4.7. A 120 mm orifice would drain it in about 42 h when clean but 54 to 75 h when half blocked, so it fails. Annex 4C shows that trial and the routing step by step.
- Retention credit. With an illustrative retention depth of 40 mm, RRV = 552 m³, computed for each sub-area (Clause 3.9.4). Modelled as filling from the start of the storm with no infiltration during it, the retention reduces the 24-hour storage by 138 m³ and the 48- and 72-hour storage by 7 m³ or less. The credit under Clause 4.4.6 is therefore effectively zero for this site.
The order of magnitude, about 0.15 m³ per m² of site, is consistent with the indication in Clause 2.11.
Figure 4.1 — Pre-development 10-yr, post-development 100-yr uncontrolled and detained hydrographs for the 24-hour storm of the illustrative example (Clause 4.6.7). Illustrative — not design values. Original drawing for this Manual, adapted from the pre/post-development hydrograph concept in MARC/KC APWA Section 5600 and the Georgia Stormwater Management Manual (2016).
Commentary. Figure 4.1 shows what detention does and does not do. It cuts and delays the peak. It does not reduce the volume: the area under the detained curve equals the area under the uncontrolled curve, more than twice the pre-development 10-yr volume. The extra volume leaves the site over many hours after the storm. That prolonged release can coincide with the peak of the larger catchment downstream (Clause 4.16), and it must still drain when the outfall is tide-locked (Chapter 5).
4.7 Drawdown
4.7.1 Detention. At least 90% of the maximum volume stored in the 10% AEP (10-yr) storm of each duration shall be released within 48 hours of the time of maximum storage, by gravity, with the tailwater of Clause 4.6.6.
4.7.2 Water quality volume. The WQv shall be released over not less than 24 hours and not more than 48 hours (Chapter 8).
4.7.3 Retention. Retention storage shall be emptied within 72 hours by infiltration or reuse (Clause 4.4.5).
4.7.4 Tidal outfalls. Where gravity drawdown is prevented by tide for part of each cycle, the 48-hour limit applies with the tidal tailwater modelled. Where it cannot be met by gravity, pumped drawdown shall be provided under Clause 5.12.
Commentary. KC APWA 5600 (2006) required dry basins to release at least 80% of storage within 24 hours of the inflow peak and to empty within 72 hours. Singapore PUB requires detention to be restored within 4 hours. The 48-hour, 90% rule is longer than PUB's because Bihar storage must hold multi-day volumes. It is still short enough that a basin filled by one SW monsoon depression will have most of its volume back before the next, which in late September 2019 at Patna (rain on four successive days, 26 to 29 September, about 211–226 mm in all, as reported) followed within days.
4.8 Outlet structures
4.8.1 General. Primary outlets shall be:
- unattended, with no moving parts, valves or pumps, except where Clause 5.12 permits pumped drawdown;
- accessible for inspection and cleaning from the surface without confined-space entry, where practicable; and
- built of durable materials. In coastal areas these shall be corrosion-resistant (Clause 4.12.5).
4.8.2 Minimum orifice. No control orifice shall be smaller than 50 mm in diameter, or 50 mm in least dimension for a slot.
4.8.3 Trash racks and screens. Every orifice and weir shall be protected by a trash rack or screen. The rack shall:
- have a clear bar spacing no greater than half the smallest opening it protects, and not less than 25 mm;
- have a clear open area at least 10 times the area of the opening it protects;
- be inclined, or set as a cage around the riser, so that debris rises with the water and does not pin against the bars;
- be removable or hinged for cleaning; and
- for routing, be assumed 50% blocked at the low-flow orifice when checking drawdown.
4.8.4 Anti-vortex devices. Riser crests and orifices that may run under more than 1.5 times their diameter of head shall have an anti-vortex plate or hood (Figure 4.2).
4.8.5 Outlet barrels. Outlet barrels through embankments shall:
- be at least 300 mm in diameter (Chapter 6);
- have watertight joints;
- have a filter diaphragm or seepage collars over the length within the embankment; and
- have an energy-dissipating outfall (Chapter 9).
4.8.6 Isolation. Facilities serving more than 1 ha shall have a means of isolating the outlet for maintenance, such as a stop-log slot or penstock. In normal service it shall be left fully open.
Commentary. The 50 mm minimum is smaller than the 75 mm (3 in) of KC APWA 5600 (2006), so the trash-rack requirements are correspondingly stricter. The ratios in 4.8.3 (bar spacing at half the opening, open area 10 times the opening, 50% blockage for the drawdown check) have no direct precedent and are set by this Manual. The blockage factor matches the 50% grate clogging factor for sag inlets in Chapter 6. Indian urban drains carry heavy loads of solid waste, so a low-flow orifice without an effective rack will block within one season.
Figure 4.2 — Detention storage stack (permanent pool, WQv, 2-yr, 10-yr and 100-yr zones, spillway surcharge and freeboard) and multi-stage riser outlet. Schematic, not to scale. Original drawing for this Manual, adapted from the multi-stage outlet and storage-zone concepts in MARC/KC APWA Section 5600 (2006, 2025.01) and the Mile High Flood District Urban Storm Drainage Criteria Manual, Volume 2 (full-spectrum detention).
4.9 Emergency spillway, freeboard and embankment safety
4.9.1 Spillway capacity. Every detention facility formed wholly or partly by an embankment, or whose overflow would reach buildings, shall have an emergency spillway that passes the 1% AEP (100-yr) peak inflow:
- with the primary outlet assumed fully blocked;
- with the facility full to the spillway crest at the start of the storm; and
- with at least 0.3 m freeboard from the maximum water level to the embankment crest.
4.9.2 High-hazard facilities. A facility is high-hazard if its failure or overflow could:
- endanger life;
- flood a habitable building or critical facility; or
- close an arterial road.
High-hazard facilities shall also be checked for the 0.2% AEP (500-yr) peak inflow under the conditions of 4.9.1, with the embankment not overtopped.
4.9.3 Spillway crest. The spillway crest shall be at or above the 1% AEP maximum water level from routing with the primary outlet working. The recommended clearance is 0.15 m.
4.9.4 Spillway location. The spillway shall be:
- on natural ground or a reinforced section, not on fill, unless protected against erosion for the full design flow;
- discharging to the 1% AEP overland flow path of Chapter 6; and
- placed so that its flow does not reach a building.
4.9.5 Underground and enclosed facilities. Tanks, vaults and podium storage shall have an overflow route that operates when the outlet is blocked. The route shall carry the 1% AEP inflow to the overland path without surcharging any building, basement or lift pit.
4.9.6 Embankments.
- (a) Embankments more than 2 m high (measured from the downstream toe to the crest) shall be designed by a qualified geotechnical engineer. The design shall include stability, seepage and settlement analysis.
- (b) Side slopes shall be no steeper than 3H:1V on any face that is mown or accessible to the public. Slopes shall be flatter where Clause 4.15 requires.
- (c) Embankments shall have:
- a crest width of at least 3 m;
- compacted, engineered fill with a core or cut-off where required by the seepage analysis; and
- no trees or large shrubs.
- (d) An embankment structure that falls within the Dam Safety Act, 2021 is subject to that Act in addition to this Manual.
4.9.7 Excavated facilities. Facilities wholly below the surrounding ground, with no embankment, need not meet 4.9.6. They shall still meet 4.9.1, with the overflow route treated as the spillway.
Commentary. The spillway criterion (1% inflow, outlet blocked, basin full, 0.3 m freeboard; 0.2% for high hazard) follows the KC APWA 5600 (2006) rule: the spillway passes the 1% storm with 1 ft (0.3 m) freeboard to the top of the dam, assuming zero storage and a clogged primary outlet, with the crest at least 0.5 ft (0.15 m) above the 1% maximum water surface. KC designed dams above 10 ft (3 m) to SCS TR-60 Class C. The 2 m embankment trigger, the 3H:1V slope (KC wet ponds), and the 3 m crest width have no direct precedent and are set by this Manual.
4.10 Facility types
4.10.1 General. Any storage that meets Clauses 4.5 to 4.9 may be used. Surface storage that is visible and can be inspected without confined-space entry is preferred. Storage shall not be placed in a habitable basement or in any space whose flooding would endanger life.
4.10.2 Underground tanks and vaults.
- (a) Gravity outlet is required where the receiving drain allows it. Pumped outlets are permitted only under Clause 5.12, with a registered maintenance declaration (Chapter 10).
- (b) Access openings shall be provided over the outlet chamber and over every inlet. In tanks over 500 m², they shall be no more than 30 m apart.
- (c) The floor shall fall at least 1% to a sump at the outlet, with a sediment pocket below the low-flow orifice invert.
- (d) The tank shall be ventilated.
- (e) Inlets shall pass through a silt trap or gross pollutant trap (Chapter 8).
- (f) Flotation and groundwater ingress shall be checked under Clause 4.12.
4.10.3 Rooftop detention.
- (a) It is permitted on flat roofs designed for the full ponded load with the outlet blocked. The ponding depth shall not exceed 150 mm unless a structural engineer certifies a greater depth.
- (b) Each roof outlet shall have a flow-control ring or weir with a certified rating, and every roof area shall have at least one overflow scupper, independent of the controlled outlets, that passes the 1% AEP inflow.
- (c) Roofs used for RWH collection may also provide rooftop detention. The detained volume is released through the control, not into the RWH sump.
4.10.4 Podium and landscape-deck detention.
- (a) It is permitted above ground level or above a basement car park, provided the structure is designed for full saturation and ponding, and waterproofed.
- (b) The release, overflow and safety rules for rooftop detention (4.10.3) apply.
4.10.5 Parking-lot detention.
- (a) It is permitted only on surface parking. Ponding depth shall not exceed:
- 200 mm in the 10% AEP storm and 300 mm in the 1% AEP storm at any parking bay;
- zero on accessible routes, ramps and pedestrian crossings; and
- zero in the 10% AEP storm on fire-tender access routes.
- (b) Signs shall warn that the area floods.
- (c) Ponding shall not reach a building wall unless the wall is waterproofed above the 1% level plus freeboard (Chapter 6).
4.10.6 Multi-use detention (parks, playfields, open space reservation).
- (a) Open space land may be used for detention, provided its primary use remains available in at least the 50% AEP storm.
- (b) The storage areas shall be graded to drain fully within the times of Clause 4.7.
- (c) A low-flow channel or underdrain shall carry dry-weather and frequent flows, so that the park is not waterlogged.
- (d) The depth and slope limits of Clause 4.15 apply.
- (e) Play equipment and seating shall be placed above the 10% AEP level.
4.10.7 Ponds and wet basins.
- (a) A permanent pool shall be at least 1.2 m deep over most of its area to discourage weed growth and mosquito breeding, with a vegetated safety bench at the edge (Clause 4.15).
- (b) Only storage above the permanent pool counts as detention.
Commentary.
- The rooftop depth (150 mm) and parking depths (200 and 300 mm) have no direct precedent. This Manual sets them so that a blocked outlet is noticed before it becomes dangerous.
- The 1.2 m pool depth equals the 4 ft minimum permanent pool of KC APWA 5600 (2006). This Manual adopts it mainly for weed and mosquito control.
- Pumped detention tanks need maintenance declarations in Singapore (PUB Addendum No. 3, April 2025). This Manual adopts the same approach through Chapter 10.
- Using open space for multi-use detention fits BBL 2014, which requires at least 5% of the land of a plot under tree cover (bye-law 32) and allows the topsoil of open ground to be replaced with river sand "to allow slow percolation of rain water" (bye-law 51(B)); no Bihar rule limiting the paving of parks or open spaces was found [TBC]. A detention area graded into the open space below the level of the road keeps it pervious and usable, which is what 4.10.6 requires. Three kinds of land are not open space for this purpose. A pokhar, ahar, chaur or tal on the land is preserved under step 1 of Clause 4.3.1 and modelled as a water surface (Clause 3.3.2(e)) that starts at its full level (Clause 3.12.5), so only its flood storage above that level can count, and only as Chapter 7 allows; public tanks vest in the Municipality (Bihar Municipal Act 2007, section 177), land over which the community has a right of irrigation is public land under the Bihar Public Land Encroachment Act 1956, and no building may be permitted within 9 m of the highest water mark of a tank (BBL 2014, bye-law 30(B)). The land between the embankments of an embanked river, or from the embankment to 500 m beyond the far bank where only one bank is embanked, is a Prohibited Zone under WRD Order No. 143 of 6 March 2025, in which only temporary or movable structures are allowed, and only beyond 250 m from the river bank. And the 50 m zone of a wetland notified under the Wetlands (Conservation and Management) Rules 2017, and land in the hydraulic corridor of a nala, pokhar, chaur or river under Chapter 7, are corridor or flood land already: water reaches them first, so they are not counted as detention for the development beside them (Chapter 7).
4.11 Rainwater harvesting versus detention accounting
4.11.1 No double counting. RWH storage (sumps, tanks, recharge pits and wells provided under the RWH mandate) shall not be counted as detention.
4.11.2 RWH sumps assumed full. For all routing under this chapter, RWH sumps and tanks shall be assumed full at the start of every storm, in every season. Their overflow shall be routed to the detention facility, or directly to the outfall if it bypasses detention. In the latter case the bypass flow counts against the PSD.
4.11.3 Combined tanks. A single tank may provide both RWH and detention only if:
- (a) the detention zone lies wholly above the RWH overflow level;
- (b) the detention zone is drained by its own gravity control orifice set at the RWH overflow level, meeting Clauses 4.7 and 4.8;
- (c) no pump, valve or user action can hold water in the detention zone; and
- (d) the two zones and the orifice level are shown on the drawings and in the maintenance declaration.
Only the volume between the RWH overflow level and the detention overflow level counts as detention.
4.11.4 Recharge structures. Recharge pits, trenches, shafts and wells may count as retention (not detention) if they meet Clauses 4.4.3 to 4.4.5. In particular, the seasonal high groundwater table shall be at least 1.0 m below their base. In the routing they are treated under Clause 4.4.6 with the groundwater level for the SW monsoon season.
4.11.5 RWH remains mandatory. Nothing in this chapter reduces the RWH requirement of bye-law 51 of the Bihar Building Byelaws 2014, section 18 of the Bihar Ground Water (Regulation and Control of Development and Management) Act 2006 and any direction or condition made under it, clause 24 of the Draft Bihar Building Byelaws 2026 if it is notified, or any rainwater harvesting rule of an approving authority.
Commentary. RWH in Bihar is required by bye-law 51 of BBL 2014, which sets a recharge volume but no storage volume, and section 18 of the Bihar Ground Water (Regulation and Control of Development and Management) Act 2006 is its statutory hook. Bye-law 51 reads: "Provision of rainwater harvesting shall be mandatory for all sizes of plots. The dimension of recharging pits/trenches shall be at least 6 cubic meters for every 100 Sq. m. of roof area." The pits are to be filled with small pebbles, brick jali or river sand under perforated concrete slabs; terrace collection to a sump through a filtering tank, with a valve to discharge the first, dirty water, and the replacement of topsoil by river sand on open ground are optional. A pit of 6 m³ per 100 m² of roof is about 60 mm over the roof, of the same order as the retention depth of Clause 4.4; but it is a volume of filled pit, not of water that infiltrates, and the bye-law sets no infiltration test and no depth to the water table. Section 18 of the 2006 Act lets the Bihar State Ground Water Authority identify recharge-worthy areas, issue guidelines and, in urban areas within notified areas, direct RWH structures on residential, commercial and other premises of 1,000 m² and more; and it lets a Municipal Corporation or other local authority impose rooftop RWH conditions on building plans of 1,000 m² and more, with permanent water and electricity connections given only after compliance. Whether the Act has been brought into force, whether any area has been notified and whether the Authority has been constituted were not confirmed [TBC]. The Draft Bihar Building Byelaws 2026, if notified, would require "the complete proposal of rainwater harvesting" with the plans of every plot of 100 m² and more (clause 24), without the 6 m³ rule; it is a draft only. None of these rules requires a tank to be empty before a storm, and none restricts recharge where the water table is shallow or the aquifer is contaminated. This Manual credits these structures against its own retention requirement (Clause 4.4) as follows:
- An RWH storage tank or sump is RWH storage. It is not detention (Clause 4.11.1), and it is assumed full at the start of every storm (Clause 4.11.2), because after the July rains it is full. A tank may also provide detention only if it is built as a combined tank under Clause 4.11.3, with a detention zone above its RWH overflow level that drains through its own orifice; only that zone counts.
- An RWH tank counts toward the retention requirement of Clause 4.4 only to the extent that it is emptied within 72 hours by a continuous non-potable use, such as toilet flushing, demonstrated under Clause 4.4.3; it is then modelled under Clause 4.4.6 like any other retention practice. On the diara, in chaurs and tal land and over most of the north Bihar plain in the monsoon, reuse is the practical way to earn retention.
- The recharge pits and trenches of bye-law 51, and any structure required under section 18, count as retention only where they meet Clause 4.11.4: they are credited only to the extent that they drain within 72 hours at half the rate measured in a site test (Clauses 4.4.3 and 4.4.5), with their base at least 1.0 m above the seasonal high water table, and the credit is found by routing under Clause 4.4.6, not by deducting their volume. Infiltration is the exception in Bihar, not the rule. Recharge can earn credit only where the seasonal high water table is deep enough, as it may be in parts of the south Bihar plain and in the peri-urban blocks of Patna, shown by current observation-well or piezometer data; on the diara, in chaurs and tal land, and on the north Bihar plain in the monsoon, a recharge structure gets no retention credit.
- Arsenic belt. Arsenic above 0.01 mg/L has been found in the groundwater of 27 districts, along the Ganga, and fluoride above 1.5 mg/L in 19 districts, mostly in the south (CGWB, December 2023, as cited in the report of the Government of Bihar in NGT O.A. 728/2023 [TBC]). In the arsenic belt the shallow aquifer is the one that recharge reaches. There, untreated runoff shall not be injected into a recharge well, bore or shaft. Retention is provided by surface infiltration through a soil or filter layer (basins, swales and permeable pavement that infiltrate through their own floors) or by detention and reuse, unless a hydrogeologist confirms that the target aquifer is not the arsenic-affected one (Chapter 8). This rule is set by this Manual; no Bihar rule restricting recharge in the arsenic belt was found.
- The open ground of bye-law 51(B), where topsoil is replaced with river sand, and the tree cover of bye-law 32 are pervious area. They enter the post-development run as pervious land under Clause 3.9.2 and get no further credit as retention or detention unless they are built and tested as an infiltration practice.
On the diara, in the chaurs and over the north Bihar plain, a recharge pit drains slowly or not at all in the SW monsoon. Treating RWH as detention would therefore credit storage that does not exist when it is needed. That is why this Manual assumes RWH sumps are full at the start of every storm. Applying the assumption to every season keeps one simple rule. The combined-tank provision (4.11.3) lets an owner build one structure, as long as the detention part is empty when the storm arrives.
4.12 High-groundwater and sandy coastal sites
4.12.1 Design groundwater level. Each site in the diara lands of the Ganga, the Kosi, the Gandak and the other rivers, the north Bihar plain, where the water table before the monsoon is about 1.5–5.7 m below ground and rises in it, the chaurs and mauns, the Kosi plain, the Mokama group of tals and the other tal lands, and the low-lying land of Patna behind the Ganga and the Punpun, or any area where the groundwater table lies within 3 m of the surface at any time of year shall establish a design groundwater level (DGWL) for the facility. The DGWL is the seasonal high level during or after the SW monsoon, from:
- (a) site piezometer readings over at least one full June–November season; or
- (b) where (a) is not available, the higher of the CGWB or Minor Water Resources Department (groundwater directorate) record for the nearest observation well, plus 0.5 m, and the design flood level of any adjacent river, nala, pokhar or chaur.
For the flotation check of 4.12.3 at sites in the diara lands, the chaurs, the Kosi plain and the tal lands, where (a) is not available, the DGWL shall be taken as existing ground level.
4.12.2 Lined storage. Where the DGWL is less than 1.0 m below the base of a storage facility:
- (a) the facility shall be watertight (lined or of watertight concrete), and no infiltration credit applies (Clause 4.4.4); or
- (b) if unlined, the volume below the DGWL shall not be counted as detention, and groundwater inflow shall be added to the routed inflow.
4.12.3 Uplift and flotation. Every below-ground tank, vault, lined pond or chamber shall be checked for flotation:
- with the facility empty;
- with groundwater at the DGWL; and
- for coastal sites, with groundwater also at the major-system tailwater level of Chapter 5, where that is higher.
The factor of safety against uplift, counting only permanent dead loads and ignoring wall friction unless supported by geotechnical design, shall be at least 1.2. Anchoring by ballast, toe extensions or tension piles may be used.
4.12.4 Shallow and above-ground storage preferred. On sites where the DGWL is within 1.5 m of ground, storage should be provided above ground where possible: rooftop, podium, landscape or surface storage. Deep tanks should be avoided.
4.12.5 Durability. Concrete and metal parts in contact with saline or brackish groundwater or tidal water shall be designed for the exposure class appropriate to coastal conditions under IS 456:2000. Outlet fittings, trash racks and gates shall be of stainless steel, HDPE, FRP or another corrosion-resistant material.
4.12.6 Sandy soils with deep groundwater. Where the DGWL is 1.0 m or more below the base, infiltration retention in sandy soils is encouraged. The design infiltration rate of Clause 4.4.3 applies, and the Chapter 8 requirements on pollution of shallow aquifers shall be met.
Commentary. Bihar is landlocked, so the coastal provisions of this clause, the tidal water levels of 4.12.1 and 4.12.3, do not apply in the State. The exposure provisions of 4.12.5 apply only where groundwater at a site is shown to be saline or brackish. Over most of Bihar the water table is shallow. On the north Bihar plain it is about 1.5–5.7 m below ground before the monsoon and rises in it (CGWB district profiles of 2011, from search summaries [TBC]); the diara is under or beside the river every monsoon; and the chaurs and tals hold water at the surface through the season. There an unlined tank fills with groundwater before the storm, and an empty lined tank can float, especially when a river in flood raises the water table of the floodplain beside it. The design groundwater level of 4.12.1(b) therefore takes the design flood level of the adjacent river, nala, pokhar or chaur where that is higher than the well record, and in the diara lands, the chaurs, the Kosi plain and the tal lands it is taken as existing ground level for the flotation check unless piezometers show otherwise. Groundwater is plentiful over most of the State, with 473 of its 535 assessment units classed safe in the 2024 assessment and only 4 over-exploited and 9 critical (CGWB, from a search summary [TBC]), so the case for recharge is weaker than in the over-exploited cities of other States; current depths for Patna and its peri-urban blocks, where recharge may be worthwhile, were not obtained [TBC]. Water quality limits recharge further: arsenic above 0.01 mg/L has been found in 27 districts along the Ganga and fluoride above 1.5 mg/L in 19 districts (CGWB, as cited in the report of the Government of Bihar in NGT O.A. 728/2023 [TBC]), and in the arsenic belt this Manual allows no injection of untreated runoff into recharge wells (Commentary to Clause 4.11; Chapter 8). The June–November monitoring season of 4.12.1(a) is set by this Manual to cover the SW monsoon and the post-monsoon high that the CGWB measures in November. The factor of 1.2, the 0.5 m allowance and the "ground level" default for the diara lands, the chaurs, the Kosi plain and the tal lands have no direct precedent; this Manual sets them because no published site-scale seasonal groundwater depths for Bihar were found during research.
4.13 Regional detention and fee-in-lieu
4.13.1 Where permitted. In a basin covered by a Basin Stormwater Master Plan approved under Chapter 11, a development may meet all or part of its detention requirement through:
- (a) a regional detention facility identified in the plan; or
- (b) a fee-in-lieu paid toward restoration of pokhar or tank storage identified in the plan.
4.13.2 Conditions. Regional detention or fee-in-lieu shall be accepted only where:
- (a) the regional facility or restored tank is operational, or is funded and scheduled to be operational within 3 years. Until then, interim on-site detention is required.
- (b) the conveyance from the site to the facility carries the 1% AEP post-development flow without increasing water levels at buildings or roads between them (Chapter 5);
- (c) the storage credited at a tank is the flood storage only. This is the volume between full tank level (FTL) and the maximum water level the bund and surplus weir can safely hold, plus any volume below FTL that a notified operating rule commits to empty before the SW monsoon. Storage below FTL that is held for irrigation or supply through June to September shall not be credited.
- (d) the tank meets Chapter 7: surveyed FTL, a documented operating rule, and a maintained surplus weir;
- (e) the site still provides retention (Clause 4.4) and WQv treatment (Chapter 8) on site; and
- (f) in flood-sensitive catchments, the regional facility meets the mixed-frequency rule for its whole contributing area.
4.13.3 Fee. The fee-in-lieu shall be computed as:
Fee = (detention volume required on site under Clause 4.6, m³) × (unit rate, ₹/m³, notified by the Authority)
The unit rate shall include land, construction and 10 years of maintenance. Fees shall be held in a ring-fenced basin account and spent only on the facilities named in the plan.
4.13.4 Ledger. The Authority shall keep a public ledger of:
- detention volume credited to each regional facility;
- volume delivered; and
- fees received and spent.
Commentary. The Malaysian DID (2008) checklist favoured community ponds over on-site detention for sites above 0.1 ha. Studies of on-site detention show that its benefit depends on location and fades with distance downstream (Colorado State University thesis; McEnroe for Kansas City), and that a pond low in the catchment can synchronise with the main-stem peak (Water 2016). Regional storage therefore has to be sited by basin modelling, not simply aggregated.
Bihar has no tank Act, and no pokhar, chaur or tal in its cities was found to be operated as part of a cascade with a documented rule [TBC]. The ahar-pyne systems of south Bihar, ahars that store rain and flood water and pynes that carry it to the fields, are irrigation works of the Minor Water Resources Department with no Act of their own, and their engineering layout was not found in a primary source [TBC]. The State's regional storage is of four kinds: the pokhars and talabs of the towns, the ahars and pynes of the south, the chaurs, mauns and tals of the floodplains, and the river floodplains with the embankments of WRD. Pokhars are protected by campaign and encroachment law rather than by a drainage rule. Public tanks vest in the Municipality (Bihar Municipal Act 2007, section 177), and land over which the community has a right of irrigation is public land under the Bihar Public Land Encroachment Act 1956; but the same Municipal Act lets the Chief Municipal Officer direct the filling up of a tank or pond that appears "injurious to health" (sections 184 and 251(e)), and no new tank or pond may be dug without that officer's permission (sections 183 and 252), so a new detention pond inside a municipality needs that permission. Under the Jal-Jeevan-Hariyali campaign the State reports encroachment removed from 28,685 ponds, ahars, pynes and wells, and 26,381 ponds and 78,090 ahars and pynes restored (State portal, as reported). The NGT (Eastern Zone) has ordered encroachments removed from three ponds of Darbhanga (O.A. 155/2022/EZ, as reported). Six wetlands are Ramsar sites, among them Kabartal in Begusarai, 2,620 ha, designated on 21 July 2020; the Bihar State Wetland Authority has published draft notifications for other wetlands and chaurs under the Wetlands (Conservation and Management) Rules 2017, which bar permanent construction within 50 m of the mean high flood level of a notified wetland, but no final notification was seen [TBC]. Three points follow:
- A pokhar on the record may not be a working pokhar. No inventory of the pokhars within PMC or the other Nagar Nigams was found [TBC]. A pokhar is credited only after a survey shows its bed, bund and outlet, and only for the storage above its full level.
- The chaurs, the tals and the river floodplain are not spare capacity for a site. About 1,062 km² of the Mokama group of tals is waterlogged in the monsoon (NIH, as reported); the land between the embankments of an embanked river is a Prohibited Zone under WRD Order No. 143 of 6 March 2025; and NIH is to delineate the 5-, 25- and 100-year flood zones of the Ganga from Chausa to Manihari under a memorandum of 3 August 2025. Storage on this land is a matter for the basin master plan of Chapter 11, not for a site.
- An embankment, sluice or drain of WRD is not regional storage. Storm water spilled to a river through its embankment uses capacity that the river needs for its whole basin, and the outfall is shut by its sluice when the river is high; it can be relied on only with the written agreement of WRD, for a stated flow and level. The drains and sump houses of Patna are divided between PMC and BUIDCO, which took over the assets and projects of the Bihar Rajya Jal Parshad under the Bihar State Water and Sewage Board (Repeal) Act 2017 (Act 3 of 2018), but no order fixing the split was found [TBC]; until one is made, this Manual treats rivers, floodplains, embankments and their sluices as WRD's, and the nalas, sump houses and road drains within the limits of an urban local body as that body's or BUIDCO's, as the record shows.
The first point is the basis of condition 4.13.2(c) in Bihar. A pokhar gives flood storage only above its full level, unless a notified operating rule commits it to be lowered before the SW monsoon. The 3-year operational limit and the 10-year maintenance allowance have no direct precedent and are set by this Manual.
4.14 Simplified methods for small sites
4.14.1 Applicability. Tier B local bodies may permit the simplified method for sites of 2 ha or less outside flood-sensitive catchments. In flood-sensitive catchments, it may be used for sites of 0.5 ha or less. All other sites shall use Clause 4.6. Until Table 4.3 (Annex 4B) is published, all Tier B sites shall also use Clause 4.6.
4.14.2 Method.
- Read the PSD (L/s/ha) and SSR (m³/ha) for the site's zone, HSG and post-development imperviousness from Table 4.3 (Annex 4B).
- Required storage: V = SSR × A − V_credit (Clause 4.4.6.3).
- Permissible discharges: Q_PSD,T = PSD_T × A for the 2-yr and 100-yr stages.
- Select the low-flow orifice and upper control from the standard outlet table in Annex 4B (orifice sizes for the PSD at the stated depths), subject to the 50 mm minimum.
- Provide a spillway or overflow under Clause 4.9, the RWH accounting of Clause 4.11, and the safety provisions of Clause 4.15.
- Complete Form 4-2 (Tier B site sheet).
Table 4.3 — Tier B permissible site discharge and site storage requirement (template)
| Zone (Annex 2A) | HSG | Imperviousness | PSD 2-yr (L/s/ha) | PSD 100-yr (L/s/ha), standard | PSD 100-yr (L/s/ha), flood-sensitive | SSR (m³/ha), standard | SSR (m³/ha), flood-sensitive |
|---|---|---|---|---|---|---|---|
| BR-Z1 South Bihar: BR-D South Bihar plain (Magadh–Bhojpur) | A / B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| BR-Z1 South Bihar: BR-E South-east Ganga fringe and plateau margin | A / B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| BR-Z2 North Bihar plain: BR-A Gandak–Burhi Gandak plain | A / B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| BR-Z2 North Bihar plain: BR-B Mithila and Kosi plain | A / B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| BR-Z3 Seemanchal and Champaran terai: BR-C Seemanchal | A / B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| BR-Z3 Seemanchal and Champaran terai: Champaran terai strip of BR-A (Bagaha, Valmikinagar, Ramnagar, Narkatiaganj) | C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
Worked example (illustrative — not design values).
A 0.4 ha residential layout in a Tier B Municipality, in a flood-sensitive catchment, with about 80% directly connected impervious area (area-weighted post-development CN about 92). Suppose Table 4.3 had been computed and gave the per-hectare equivalent of the Clause 4.6.7 example:
- PSD 100-yr = 356 / 2.0 = 178 L/s/ha
- SSR = 2,913 / 2.0 ≈ 1,460 m³/ha
- PSD 2-yr ≈ 17 L/s/ha
Then:
- Storage: V = 1,460 × 0.4 = 584 m³. C_R = 0, so there is no retention credit.
- 100-yr release: 178 × 0.4 = 71 L/s.
- 2-yr release: 17 × 0.4 = 7 L/s. At about 1 m head this needs a low-flow orifice of about 60 mm, above the 50 mm minimum (Clause 4.8.2).
- Layout options:
- a 400 m² underground tank 1.5 m deep; or
- 250 m² of podium storage at 0.3 m (75 m³) plus a 350 m² tank 1.5 m deep (525 m³).
- Rooftop storage at 150 mm over 1,200 m² of roof (180 m³) could replace part of the tank.
- RWH sumps are additional, and are assumed full (Clause 4.11).
Commentary. Australian councils use permissible site discharge and site storage requirement tables in the same way (Sydney Water OSD guide; the Upper Parramatta River Catchment Trust handbook listed SSR of about 455 m³/ha). The illustrative SSR here, about 1,460 m³/ha, is much larger. That is the expected effect of combining a mixed-frequency cap with mandatory 48–72-hour storms at AMC III. MSMA 2 in Malaysia offers a similar simplified OSD method for sites under 5 ha. The MARC policy supplement offers smaller Kansas City municipalities adoptable alternatives within the regional standard; Clause 4.14 follows that model for Tier B.
4.14.3 Fixed-coefficient route. As an alternative to Clauses 4.6 and 4.14.2, the designer of any site of 1 ha or less, under any Approving Authority and in any catchment, may size detention by Clauses 4.14.4 to 4.14.7. The route shall not be used where:
- (a) the site counts tank or waterbody storage in its design (Chapter 7);
- (b) any part of the site lies within a waterbody setback (Chapter 7); or
- (c) the site drains to a tank cascade whose storage is counted in a downstream design.
The route sets the release caps by fixed coefficients and does not need Table 4.3. It may therefore be used before Annex 4B is published. Retention (Clause 4.4), drawdown (Clause 4.7), outlets (Clause 4.8), the spillway (Clause 4.9), the downstream and tailwater checks (Chapter 5) and water quality (Chapter 8) still apply.
4.14.4 Release caps. Two caps apply at each point where runoff leaves the site:
Q_cap,10 = 2.78 × C_10 × i_10 × A and Q_cap,2 = 2.78 × C_2 × i_2 × A
where Q_cap is in L/s; A is the site area (ha); i_10 and i_2 are the 10% AEP (10-yr) and 50% AEP (2-yr) rainfall intensities (mm/h) for a 15-minute duration at the site, from the sources of Chapter 2, with the climate factor of Clause 2.8; and C_10 and C_2 are the fixed coefficients of Table 4.3A for the site's hydrologic soil group (Clause 3.7). For a site with more than one soil group, the coefficients are area-weighted.
Table 4.3A — Fixed release coefficients (provisional)
| Hydrologic soil group | C_10 | C_2 |
|---|---|---|
| A (sandy, well drained) | 0.05 | 0.02 |
| B | 0.08 | 0.03 |
| C | 0.15 | 0.08 |
| D (clay, poorly drained) | 0.25 | 0.15 |
Q_cap,10 is the maximum release for every storm up to and including the 1% AEP (100-yr) storm, in every catchment. Q_cap,2 is the maximum release for the 50% AEP (2-yr) storm. Where a cap is smaller than the discharge of a 50 mm orifice at the corresponding stage, the 50 mm orifice is deemed to comply (Clause 4.5.5.1).
4.14.5 Storage. The detention storage V (m³) is the larger of V_100 and V_2, each the largest over the durations d of Clause 2.5.2 (1 to 72 hours):
V_100 = max over d of [ 10 × C_v × P_100(d) × A − 1.8 × Q_cap,10 × d ]
V_2 = max over d of [ 10 × C_v × P_2(d) × A − 1.8 × Q_cap,2 × d ]
where P_100(d) and P_2(d) are the 1% and 50% AEP rainfall depths (mm) for duration d (hours), with the climate factor; and C_v is the post-development volumetric coefficient: the composite C of Table 3.2 (upper half of each range), multiplied by Cf of Table 3.3 for the 1% AEP. For durations of 12 hours or more, C for every pervious surface shall be taken as not less than 0.50. The factor 1.8 assumes an average release of half the cap over the storm (3.6 × 0.5).
4.14.6 Outlet. The outlet shall be a two-stage control: a low-flow orifice that passes Q_cap,2 when the storage holding V_2 is full, and an upper orifice or weir that limits the total release to Q_cap,10 at the top of V. The outlet table of Annex 4B may be used once it is published.
4.14.7 Retention. The retention volume of Clause 4.4 is provided in addition to V. No retention credit (Clause 4.4.6) is taken under this route.
Figure 4.3 — Fixed-coefficient route for sites of 1 ha or less (Clauses 4.14.3 to 4.14.7): the release caps Q_cap,10 and Q_cap,2 from Table 4.3A; the storage V as the largest gap, over the durations of Clause 2.5.2, between the cumulative inflow 10·C_v·P(d)·A and the release line 1.8·Q_cap·d, for the 1% and 50% AEP storms; and the two-stage outlet that passes Q_cap,2 at the top of V_2 and Q_cap,10 at the top of V. Schematic, not to scale. Original drawing for this Manual, adapted from the rainfall mass-curve (inflow minus outflow) storage concept and the single-coefficient peak cap of the PUB Code of Practice on Surface Water Drainage, 7th ed. (cl. 7.1.5).
Commentary. The fixed-coefficient route follows Singapore, which caps the peak runoff from every development of 0.2 ha or more with one runoff coefficient, C = 0.55, applied to the 10-yr storm (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5, Addendum No. 3, 2025). It is quick to apply and quick to check: the cap needs only the site area, the soil group and two intensities. PUB's 0.55 is not used here, because Singapore's baseline is the existing urban drainage system, while this Manual's baseline is greenfield land (Clause 4.5.1.2). The coefficients of Table 4.3A are set by this Manual from the greenfield curve numbers of Clause 3.3 (CN 39, 61, 74 and 80 for soil groups A to D). They are the ratios of runoff to rainfall that those curve numbers give for 1-hour depths typical of the north Bihar plain, rounded down. They are therefore provisional. The State Stormwater Technical Committee shall confirm or revise them against NIH-DHAARA values for each zone when it issues Annex 4B.
The route is deliberately stricter than the full method, so that simplicity costs the developer storage rather than costing the people downstream. The 100-yr release is held to about the greenfield 10-yr peak everywhere, which is the flood-sensitive rule of Clause 4.5.3; the storage assumes the outlet releases only half the cap on average; pervious ground is assumed wet in long storms; and no retention credit is taken. A designer who wants a smaller tank can use the full method of Clause 4.6. The storage formula is the rainfall-mass (inflow minus outflow) method. Clause 3.4.2 otherwise forbids rainfall-based peak methods for storage, because they ignore the shape of the hydrograph; this route is a stated exception because its conservative assumptions cover that error for small sites, and the 24- to 72-hour durations are always checked.
4.15 Safety, fencing and multi-use
4.15.1 Depth limits for publicly accessible storage. Where the public has access to a storage area (parks, playfields, open space, school grounds):
- (a) maximum depth in the 10% AEP storm: 0.45 m;
- (b) maximum depth in the 1% AEP storm: 1.2 m, except in a fenced zone under 4.15.3;
- (c) side slopes: no steeper than 4H:1V, with at least a quarter of the perimeter at 6H:1V or flatter for escape; and
- (d) no vertical drop greater than 0.3 m within the storage area or at its edge.
4.15.2 Wet basins. Permanent pools shall have:
- a safety bench at least 3 m wide, no more than 0.3 m below the normal water level; and
- an emergent planting fringe that deters entry.
4.15.3 Fencing. A fence at least 1.2 m high, of a non-climbable design with a lockable gate, is required around any part of a storage that:
- has a vertical wall or headwall drop greater than 0.6 m;
- exceeds 1.2 m depth in the 1% AEP storm with slopes steeper than 4H:1V; or
- contains an outlet structure with an opening larger than 300 mm that is not grated.
4.15.4 Outlets. Every inlet and outlet opening larger than 300 mm accessible to the public shall be fitted with a grate or rack. The grate shall be designed so that a person pinned against it can escape: low approach velocity, inclined, with a large open area.
4.15.5 Signs and depth markers. Every publicly accessible storage shall have signs in Hindi and English stating that the area floods during rain, and a depth marker at the deepest point.
4.15.6 Confined spaces. Underground tanks shall have lockable covers. They shall be marked as confined spaces, and the maintenance declaration (Chapter 10) shall state the entry procedure.
4.15.7 Vector control. Dry storage shall drain completely (Clause 4.7) and have no low points that pond for more than 72 hours. Wet basins shall meet Clause 4.10.7.
Commentary. The numeric limits in Clause 4.15 have no single direct precedent. They are drawn from common international practice, for example KC APWA 5600 (2006), which required at least a quarter of a dry-pond perimeter at 5:1 or flatter, a 20 ft (6 m) clearance from property lines and a 15 ft (4.6 m) maintenance strip. They are made somewhat stricter here because multi-use storage on open space land and in schools will be used by children during the monsoon. Standing water in dry basins is a mosquito-breeding risk, so complete drainage (Clause 4.15.7) is a public-health requirement, not an amenity.
4.16 Basis: why peak matching alone fails
Commentary. This section has no requirements. It records why this chapter requires release below pre-development rates, retention, long-duration checks and a downstream analysis, rather than simple peak matching.
- Timing. Detention lowers a site's peak but stretches its hydrograph (Figure 4.1). Downstream, the stretched releases from many sites overlap with each other and with the main-stem peak. In Denver's study, ten basins each releasing 100% of the historic 100-yr peak produced 106% of the historic peak at the outlet. Only releasing 90% at each site brought it to 97% (UDFCD memo, 2012). A Colorado State University thesis found that location-blind on-site detention "can actually increase peak flows above post-development peaks". An optimisation study found that a downstream pond performed worse than upstream ponds because its outflow synchronised with the main stem (Water 2016, 8(7):290).
- Volume. Detention does not remove volume. In the illustrative example, the post-development 100-yr storm produces about three times the runoff volume of the pre-development 10-yr storm (Clause 2.11). Only retention, or storage that empties to somewhere other than the receiving drain, reduces volume.
- Scale. Kansas City modelling (McEnroe, 2005) found that uniform 3 cfs/ac control reduced Q100 by 36% in a 200-ac watershed. With the same control everywhere, Q100 still rose by 40% at 14 sq mi, and the benefit faded beyond about 1–2 sq mi. The KC committee concluded that "'match existing' can harm streams" (MARC Evolution deck). Georgia makes a ten-percent downstream analysis mandatory for the same reason: "Due to peak flow timing and runoff volume effects, some structural practices fail to reduce discharge peaks to pre-development levels downstream" (GSMM 2016).
- Design-storm dependence. An Australian study of 20 real on-site detention systems found that designs using even ten temporal patterns "cannot reliably produce an OSD system design that will always be effective" under real rainfall (Water Science and Engineering, 2019). This is why Clause 4.6.3 routes the full duration matrix rather than one critical storm.
- Closed outfalls. In Bihar, the governing failure is volume with no outlet when the river is high. Most large cities drain to a river that is embanked or that stands above their outfalls for days in a flood. Patna is ringed by the Ganga, the Sone and the Punpun; when they rise, the sluice gates on the Ganga and the Punpun are closed, PMC blocks the drains connected to the Ganga, and the city then drains only through its sump houses and drainage pumping stations (as reported; a Rajya Sabha reply of 27 November 2024 cites 56 permanent and 28 temporary drainage pumping stations, of unclear scope [TBC]). In September 2019 most of Patna's sump houses were reported not working, and the State's inquiry found that pumps had been started late and drains not cleaned (as reported). The highest recorded levels of the rivers at the cities stand well above their danger levels: the Punpun at Sripalpur, Patna, 53.91 m (1976) against 50.60 m; the Ganga at Gandhi Ghat, Patna, 50.52 m (2016) against 48.60 m; the Burhi Gandak at Sikandarpur, Muzaffarpur, 54.29 m (1987) against 52.53 m; the Bagmati at Hayaghat, Darbhanga, 48.96 m (1987) against 45.72 m; and the Mahananda at Dhengraghat, Purnia, 38.20 m (2017) against 35.65 m (CWC; datum to be confirmed [TBC]). In August 1975 the Sone and the Ganga entered Patna and ground floors stayed under water for 5–7 days (as reported). No hourly record of how long a river in Bihar stays above a city's outfalls was obtained [TBC], and no document was found that sets a design river level for an outfall; this Manual uses the highest recorded level at the nearest gauge and a closure of at least 7 days (Chapter 5). The Ganga showed in September 2026 how a river can exceed its record: press reports put it at 50.53–50.57 m at Gandhi Ghat on 5–6 September, above the level of 2016 (as reported). A perfectly orificed basin behind a closed outfall simply fills. No release-rate rule can fix that; it is handled by the outfall-closed check of Chapter 5.
The response in this Manual is layered:
- release below pre-development (Clause 4.5);
- retain the frequent storms (Clause 4.4);
- route long SW monsoon storms (Clause 4.6.3);
- prefer regional storage in the pokhar system (Clause 4.13); and
- check downstream and at the outfall (Chapter 5).
Kansas City's own history shows the price. On a test site, peak matching needed 3.0 ac-ft of storage and the 2011 comprehensive criteria needed 4.9 ac-ft (MARC Evolution deck). Over-detention costs more storage. That is the cost of protecting the catchment rather than only the site boundary.
4.17 Submittal requirements
Every site runoff-control submittal shall include a Site Runoff Control Report (Form 4-1) containing:
- the Design Rainfall Sheet (Form 2-1) and the hydrology inputs (Chapter 3);
- the evidence for the order of measures under Clause 4.3.1;
- the RRV computation, infiltration tests, groundwater evidence and drawdown calculation (Clause 4.4);
- the retention credit computation (Clause 4.4.6);
- the release-rate criterion applied, standard or flood-sensitive, with the Annex 4A map extract (Clause 4.5);
- a results table in the format of Clause 4.6.7 for every AEP and duration, with the governing case highlighted;
- stage–storage and stage–discharge tables and plots, and inflow/outflow hydrographs for the governing cases;
- the drawdown calculation (Clause 4.7);
- outlet details, including orifice sizes and levels, trash racks and anti-vortex devices (Clause 4.8);
- the spillway or overflow calculation, freeboard and hazard classification, and the geotechnical report where required (Clause 4.9);
- the RWH and detention accounting, with tank sections showing zone levels (Clause 4.11);
- the design groundwater level and flotation check (Clause 4.12);
- the downstream and tailwater report (Chapter 5, Form 5-1); and
- the safety provisions (Clause 4.15) and the draft maintenance declaration (Chapter 10).
Tier B sites using Clause 4.14.2 shall submit Form 4-2 in place of items 6 and 7. Sites using the fixed-coefficient route (Clause 4.14.3) shall submit Form 4-3 in place of items 6 and 7.
References (chapter)
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01 (approved 10 Dec 2025). https://kcmetro.apwa.org/wp-content/uploads/sites/23/2026/01/APWA-Section-5600_Storm-Drainage-Systems-Facilities.pdf
- Mid-America Regional Council (2025). APWA 5600 Stormwater Standards Policy Supplement (7 Nov 2025); APWA 5600 Manual factsheet. https://www.marc.org/document/apwa-stormwater-standards-supplement ; https://www.marc.org/document/apwa-5600-manual-factsheet
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (5601.8, 5608.4). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- MARC / APWA (2012). Manual of Best Management Practices for Stormwater Quality. https://www.marc.org/sites/default/files/2022-05/Best_Management_Practices_for_Stormwater_Quality.pdf
- MARC. The Evolution of Regional Stormwater Design Standards (presentation; McEnroe 2005 results). https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Atlanta Regional Commission / Georgia EPD (2016). Georgia Stormwater Management Manual, Volume 1. https://documents.atlantaregional.com/gastormwater/GSMM_2016%20EDITION_FINAL_V1.pdf
- Urban Drainage and Flood Control District (now MHFD) (2012). Full Spectrum Detention Release Rate Memorandum. https://mhfd.specialdistrict.org/files/23cb85ce8/UDFCD_Full_Spectrum_Detention_Release_Rate_Memorandum.pdf
- Mile High Flood District. Urban Storm Drainage Criteria Manual, Volume 2 (Storage).
- Department of Irrigation and Drainage Malaysia (2008). Submission Checklist for Stormwater Management. https://www.water.gov.my/jps/resources/auto%20download%20images/5844dfbba8fc1.pdf
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- PUB Singapore (2024). On-site Detention Tank Technical Guide, Rev. 3; Code of Practice on Surface Water Drainage, 7th ed., Addendum No. 3 (16 Apr 2025). https://www.pub.gov.sg/-/media/PUB/PDF/detentionTank.pdf
- Sydney Water (2020). On-site Stormwater Detention Guide (SW201). https://www.sydneywater.com.au/content/dam/sydneywater/documents/on-site-stormwater-detention-guide.pdf
- Upper Parramatta River Catchment Trust (2005). On-site Stormwater Detention Handbook, 4th ed.
- "On-site stormwater detention for Australian development projects: does it meet frequent flow management objectives?" Water Science and Engineering (2019). https://www.sciencedirect.com/science/article/pii/S1674237019300213
- Optimisation of urban detention (2016). Water 8(7):290. https://doi.org/10.3390/w8070290
- Colorado State University. Spatially Dependent On-Site Detention Policies (thesis). https://mountainscholar.org/bitstreams/f4dbec4e-a44f-4933-8d54-a097e741f44a/download
- Bihar Municipal Act, 2007, sections 177, 183, 184, 193, 195, 196, 198, 201, 219, 251 and 252 (IELRC copy). https://www.ielrc.org/content/e0715.pdf
- Bihar Public Land Encroachment Act, 1956 (copy on the Bihar State Wetland Authority site). https://bswa.bihar.gov.in/Downloads/BIHAR%20PUBLIC%20LAND%20ENCROACHMENT%20ACT,%201956.pdf
- Government of Bihar. Jal-Jeevan-Hariyali Abhiyan (components and progress; the progress table is mislabelled "As on 17.12.2026"). https://betastate.bihar.gov.in/jaljivan.aspx
- Bihar State Wetland Authority. Home page (Ramsar sites) and "Acts/Rules/Notification" page (draft notifications under the Wetlands (Conservation and Management) Rules 2017). https://bswa.bihar.gov.in/ ; https://bswa.bihar.gov.in/ActRulesandNotification.aspx
- Ramsar Convention. Ramsar Information Sheet, Kabartal Wetland (site 2436). https://rsis.ramsar.org/RISapp/files/RISrep/IN2436RIS_2010_en.pdf
- Water Resources Department, Government of Bihar (2025). Order No. 143 of 6 March 2025, Implementation of Flood Plain Zoning for embanked rivers within Bihar State (in Hindi), and the memorandum with NIH Roorkee of 3 August 2025 for the Ganga from Chausa to Manihari, as annexed to the supplementary affidavit of the Chief Secretary, Bihar, of 12 January 2026 in NGT O.A. 200/2014 (M.C. Mehta v. Union of India). https://www.greentribunal.gov.in/sites/default/files/news_updates/Supplementary%20affidavit%20on%20behalf%20of%20the%20Chief%20Secretary,%20State%20of%20Bihar%20in%20OA%20No.%20200%20of%202014%20(M%20C%20MEHTA%20Vs.%20UNION%20OF%20INDIA%20and%20Ors).pdf
- Talab Bachao Abhiyan. Objection of 23 November 2024 in M.A. 18/2024 in NGT O.A. 155/2022/EZ (three ponds of Darbhanga). https://www.greentribunal.gov.in/sites/default/files/news_updates/1732521637_pagenumber.pdf
- National Institute of Hydrology. Waterlogged area mapping and hydrological data analysis of the Mokama tal area, research report (cited from a summary). https://www.indiawaterportal.org/articles/waterlogged-area-mapping-and-hydrological-data-analysis-mokama-tal-area-research-report
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A (§8.5).
- Urban Development and Housing Department, Government of Bihar (2014). Bihar Building Bye-Laws, 2014 (English copy dated December 2014, on the PMC building plan approval portal; Notification No. 577 (file 11/न०वि०(मा०)-06/2013), Patna, 8 December 2014, as printed in the official Hindi text): bye-laws 29, 30, 32, 47 and 51. https://automap.bihar.gov.in/PATNABPASPORTAL/PlanningPortals/images/Bihar%20Building%20Bylaw%20English%20Dec-2014.pdf
- Urban Development and Housing Department, Government of Bihar (2026). Draft Bihar Building Byelaws 2026, posted 5 June 2026 (draft; not notified as of September 2026): clauses 6, 23, 24 and 41 and Table 5. https://betastate.bihar.gov.in/file_2/FileUpload/2026/Jun/05-Jun-2026/19/LatestNews/0424d72a-9e14-4227-8221-8adb08c0c009.pdf
- Reports on the status of the Draft Bihar Building Byelaws 2026 (GKToday; Patna Press). https://www.gktoday.in/bihar-drafts-new-building-map-approval-rules/ ; https://patnapress.com/bihar-building-bye-laws-2026-self-certification-draft/
- Report on the amendment of the 2014 Byelaws relaxing commercial setbacks (Patna Press; number and date not given). https://patnapress.com/bihar-commercial-building-bye-laws-setback-rules-relaxed/
- Urban Development and Housing Department, Government of Bihar (2024). Guidebook on Application, Approval and Occupancy Procedure under Bihar Building Bye Laws, 2014. https://betastate.bihar.gov.in/file_2/FileUpload/2024/May/07-May-2024/19/DyPage/cd47e267-11d1-4671-a56a-b63a6c83a779.pdf
- Bihar Ground Water (Regulation and Control of Development and Management) Act, 2006, sections 1(3), 2(c), 5 and 18 (Bihar Gazette scan, FAOLEX copy; commencement and notified areas not confirmed [TBC]). https://faolex.fao.org/docs/pdf/IND197019.pdf
- Bihar Municipal Act, 2007, sections 193, 198, 201 and 219 (IELRC copy). https://www.ielrc.org/content/e0715.pdf
- Bihar State Water and Sewage Board (Repeal) Act, 2017 (Bihar Act 3 of 2018), Bihar Gazette (Extraordinary) No. 311, 5 April 2018 (FAOLEX copy). https://faolex.fao.org/docs/pdf/ind198266.pdf
- Bihar Ease of Doing Business Act, 2026 (Act No. 32 of 2026), Bihar Gazette (Extraordinary) No. 1120, 16 September 2026, Schedule V (PRS copy). https://prsindia.org/files/bills_acts/acts_states/bihar/2026/Act32of2026BR.pdf
- Comptroller and Auditor General of India. Audit Report (Performance and Compliance Audit) for the year ended March 2020, Government of Bihar, Chapter III, para 3.1, Development of Sewerage Infrastructure in Patna under Namami Gange Programme (report number and tabling date not confirmed [TBC]). https://cag.gov.in/uploads/download_audit_report/2020/05-%20Report%20No-5%20-English%20-%20Chapter%20-%203-06244310a0bd463.62428332.pdf
- Government of Bihar. Report in NGT O.A. 728/2023, citing CGWB (December 2023) on arsenic and fluoride in groundwater by district (cited from a search summary of the NGT news-updates page; not read) [TBC].
- Central Ground Water Board. Dynamic ground water resources of Bihar, 2024 assessment (cited from a search summary). https://www.cgwb.gov.in/cgwbpnm/public/uploads/documents/1743584819841710360file.pdf
- Central Ground Water Board. District ground water profiles of Supaul, Saharsa, Katihar and Sitamarhi (2011) (cited from search summaries) [TBC].
- Central Water Commission, Lower Ganga Division-2, Patna. Daily water level and flood forecast bulletin, 31 October 2026. https://www.fmiscwrdbihar.gov.in/bulletin/CWC_Bulletin.pdf
- Rajya Sabha. Reply to Question No. 266 of 27 November 2024 (storm-water drainage projects and drainage pumping stations in Bihar; seen only through a search summary). https://rsdebate.nic.in/bitstream/123456789/754718/1/PQ_266_27112024_S10_p23_p25.pdf
- Patna High Court. CWJC No. 15027 of 2018 with connected writs, oral order of 18 October 2019. https://slic.org.in/uploads/2019/10/Vishal-PIL-ORDER.pdf
- Reports on the Patna waterlogging of September 2019 and its inquiry (Business Standard, 14 October 2019; Hindustan Times; CBS News, AFP). https://business-standard.com/article/news-ani/show-cause-notices-served-to-officials-responsible-for-patna-water-logging-says-chief-secretary-119101401451_1.html ; https://www.pressreader.com/india/hindustan-times-lucknow/20191001/281797105729423 ; https://www.cbsnews.com/news/monsoon-season-flooding-india-heavy-late-rains-kills-more-than-100-in-several-days-2019-09-30
- Lok Sabha. Statement of 16 January 1976 on the Patna flood of August 1975 (seen only through a search extract). https://eparlib.sansad.in/bitstream/123456789/857276/1/05_XV_16-01-1976_p57_p59_PII.pdf
- Reports on the Ganga at Gandhi Ghat, Patna, in September 2026 and the closing of the sluice gates (ThePrint, PTI; Patna Press). https://theprint.in/india/ganga-water-level-breaches-highest-flood-mark-at-patnas-gandhi-ghat-amid-heavy-rain/3034353/
- Talab Bachao Abhiyan. Application in the NGT (Eastern Zone), 2025, against the Darbhanga storm water drainage and canal-lining projects. https://www.greentribunal.gov.in/sites/default/files/news_updates/1755167303.pdf
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012) (Bihar stations, pp. M32–M38). https://imdpune.gov.in/library/public/EXTREMES%20OF%20TEMPERATURE%20and%20RAINFALL%20upto%202012.pdf
- Dasa, Syamasundara (ed.). Hindi Shabdasagara. Kashi: Nagari Pracarini Sabha, 1965–1975 (entry चौर), via DSAL. https://dsal.uchicago.edu/dictionaries/dasa-hindi/
- Report on the recurrent waterlogging of Rajendra Nagar and Kankarbagh, Patna (Dialogue Earth, 2019; cited from the research notes for this Manual, not re-read) [TBC].
- Bureau of Indian Standards. IS 456:2000 Plain and Reinforced Concrete — Code of Practice.
- Government of India. Dam Safety Act, 2021.
- Chow, V.T., Maidment, D.R. and Mays, L.W. (1988). Applied Hydrology. McGraw-Hill (AMC conversion).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 4A | Flood-sensitive catchment boundaries (GIS); shallow-groundwater zone map |
| 4B | Tier B tables: PSD and SSR (Table 4.3), retention credit factor C_R, standard outlet sizes; confirmed fixed release coefficients (Table 4.3A) |
| 4C | Worked example (Tier A) with full routing tables |
| Form 4-1 | Site Runoff Control Report |
| Form 4-2 | Tier B Site Sheet |
| Form 4-3 | Fixed-coefficient Route Sheet (Clauses 4.14.3 to 4.14.7) |
Commentary. No Indian national rule or Bihar rule found during research for this Manual limits the rate of discharge from a site, and none requires on-site detention or "zero run-off". The building rules are the Bihar Building Byelaws 2014 (BBL 2014), made by UDHD; the English text in use on the building plan approval portal of PMC is dated December 2014, and the official Hindi text gives the notification as UDHD Notification No. 577 (file 11/न०वि०(मा०)-06/2013), Patna, 8 December 2014. An amendment reported in the press relaxed the setbacks of commercial buildings (as reported; its number and date were not found [TBC]). The Draft Bihar Building Byelaws 2026, posted by UDHD on 5 June 2026, would repeal BBL 2014 "with all its amendments and associated executive orders" when notified (clause 41); it had not been notified as of September 2026 (as reported), and this Manual cites it as a draft only. The drainage provisions of BBL 2014 protect the building, the drain and the tank, not the catchment. No building may be permitted "In areas of natural waterways or drains, as detailed in the Development Plan, and drainage plan" (bye-law 29(A)), over or under a municipal drain (29(D)), or, in areas that flood, where the structural plans do not take that into account (29(G)); no building may be permitted within 9 m of the highest water mark of a tank unless the owner satisfies the Authority that domestic drainage will not pass into it, and the Authority may require the lowest floor to be raised above "the normal maximum flood level of the adjoining ground" (30(B)); land within the curtilage shall, if the Authority requires, "be effectively drained by surface water drains or other means", and connecting a surface-water drain to a sewer needs its written approval (30(D)); at least 5% of the land shall be under tree cover (32); and rainwater harvesting is mandatory on plots of all sizes, with recharge pits or trenches of at least 6 m³ for every 100 m² of roof area (51; Commentary to Clause 4.11). The Bihar Municipal Act 2007 makes the Municipality responsible for drains and "a safe and sufficient outfall" (section 193), lets the Chief Municipal Officer require separate drains for sewage and for rain water (section 198), and allows no premises without a drain of the size and level that the Chief Municipal Officer thinks necessary (section 201); section 219 requires each Municipality to keep a water-supply, drainage and sewerage code, but none was found for any Bihar city [TBC]. The 2026 draft would require site plans to show "normal flood-affected areas" and contours at 0.5 m intervals where the slope is more than 1 in 20 (clause 6), would forbid "All permanent construction within the water body boundary" but set no buffer beyond it and drop the 9 m tank rule (Table 5), and would require a complete rainwater harvesting proposal on plots of 100 m² and more (clause 24). None of these, in force or in draft, sets a design storm, a release rate, a storage volume or an overflow path, and no drainage design standard of UDHD, BUIDCO or PMC stating a return period was found [TBC]. The Bihar Ease of Doing Business Act 2026 lists a "Storm Water Drains NOC" and a revenue NOC "for land near water bodies or nalas" as "Not required" for enterprises (Schedule V), so the requirements of this chapter are best checked within building-plan sanction, as part of the drain section and rainwater harvesting plan that UDHD's guidebook already asks for, rather than as a separate clearance. Basements are already restricted. Bye-law 47(1) provides that basements "shall not be permitted in low lying area and without adequate drainage facilities" and that "Basement shall not be allowed in flood prone areas", and the 2026 draft keeps both (clause 23(12)). BBL 2014 does not define a low-lying or flood-prone area. This Manual proposes that, for bye-law 47(1), the flood-sensitive catchments of Clause 4.5.3.2, any catchment notified under Clause 4.5.4, and land in Zone 1 or Zone 2 of Chapter 7 be treated as flood-prone, and it adds its own requirements for every basement that is permitted elsewhere: no detention storage in a habitable basement (Clause 4.10.1), the crest of every basement ramp and the sill of every basement opening at least 0.5 m above the 1% AEP flood level, with basement drainage pumped to the surface drain through a non-return valve (Clauses 6.11.1 and 6.11.4), and no basement in Zone 2 (Clause 7.5.2). This chapter is written so that it can supply, as a technical companion to BBL 2014 and to the storm-water drainage schemes of UDHD and BUIDCO, the design storm, release rates and storage volumes that the Byelaws leave open; it has not been adopted for either purpose. In practice many city nalas in Bihar carry sewage: a CAG report on Patna sewerage under Namami Gange records 19 drains of Patna discharging 628.5 MLD to the Ganga and the Punpun (Clause 8.9). Retention and detention apply in full on every site whatever the drain carries: every litre a site releases at the peak of a storm takes up capacity in a drain that is already part-filled with sewage. The CPHEEO (2019) manual describes limiting outflow to the pre-development peak as typical practice, but it uses no "shall" and names no storm frequencies (CPHEEO Part A §8.5.1). This chapter turns that description into a development-control requirement.