Chapter 5Downstream and Tailwater Analysis
5.1 Purpose and scope
5.1.1 This chapter sets two checks that every regulated development and every public drainage project must pass.
- The downstream analysis (Clauses 5.3 to 5.5) confirms that the project does not make flooding worse below its outfall.
- The tailwater analysis (Clauses 5.6 to 5.13) sets the water level the system discharges into, including tide, storm surge, sea-level rise, river backwater and sand-bar closure. It also requires the system to cope when its outfall is closed.
5.1.2 This chapter applies to:
- (a) every site to which Chapter 4 applies;
- (b) every minor- and major-system drainage project under Chapter 6; and
- (c) every regional detention or tank restoration project under Clause 4.13 and Chapter 7.
5.1.3 Rainfall and joint-occurrence inputs come from Chapter 2, in particular Clauses 2.5.3 and 2.12. Hydrologic methods come from Chapter 3. Site release criteria come from Chapter 4. Hydraulic design of gates, culverts and pumps follows Chapter 9.
5.1.4 No tidal outfalls in Bihar. Bihar is landlocked: it has no coast, no tide and no Coastal Regulation Zone. No outfall in the State discharges to the sea, a tidal creek or an estuary, so the provisions of this chapter that depend on tide, storm surge, sea-level rise or a river mouth do not apply in Bihar: Clause 5.7 and Annex 5A, cases J1 to J3 of Table 5.2, the tidal lock windows of Clause 5.10.3, the seawater requirement of Clause 5.11.3(a) (gates and seats shall still be of corrosion-resistant materials), and Clause 5.13. They are kept so that the clause numbers of this Manual match its other State editions. In Bihar the receiving water is a river, reached directly, through a sluice or gate in an embankment or a town protection wall, or through a drainage pumping station (a sump house); a drain or canal of WRD; a nala of a Nagar Nigam, of BUIDCO or of another drain-owning body; a pumped sump behind a river embankment; or a pokhar, chaur, maun, tal or other water body, and:
- (a) its tailwater is set by Clauses 5.6 and 5.8, including Clause 5.8.5;
- (b) where Clauses 5.10 to 5.12, Form 5-1 or Chapter 6 refer to the J1 tailwater or the J1 tidal curve, the minor-system tailwater of Clause 5.6.2 or 5.8.5 applies, as a time series where the receiving level varies; where they refer to the J2 tailwater or to HAT + surge + SLA, the major-system tailwater applies: the design-AEP river level of Clause 5.8.4(b), or the major-system tailwater of Clause 5.8.5, whichever is higher at the outfall; and
- (c) the outfall-closed check of Clause 5.10 applies where an outfall is closed by a river or by a receiving drain, with the river lock of Clause 5.8.5(a) in place of the tidal lock windows.
5.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Analysis point | A location on the downstream system where pre- and post-project conditions are compared (Clause 5.3.3). |
| Contributing catchment | The whole area draining to an analysis point, on and off site. |
| Major drain | A channel listed as a major drain in the basin plan or Annex 5B, or any river, WRD canal, the nalas and ghat drains of Patna that outfall to the Ganga, including the Bakarganj nala and the 19 ghat drains listed by BUIDCO, the drains of Patna that outfall to the Punpun, including the Badshahi drain, the Saidpur, Kurji and Anandpuri nalas of Patna, the drains that outfall to the Burhi Gandak at Muzaffarpur, to the Bagmati and the Adhwara group at Darbhanga, to the Gandak and the Ganga at Hajipur, to the Ganga at Bhagalpur and Munger and to the Mahananda and its tributaries in Purnia district, any drain or canal of WRD, any drain maintained by a Nagar Nigam, BUIDCO or BIADA with an internal width of 1.0 m or more, any irrigation canal that receives storm water, or a tidal creek. |
| Chart datum (CD) | The datum of the published tide tables and nautical charts, to which tidal heights are referred. |
| Mean sea level (MSL) | Average sea level over a long period at a tide gauge. |
| MHWS | Mean high water springs: the average of high waters at spring tides. |
| HAT | Highest astronomical tide: the highest level predicted under average meteorological conditions over a full tidal cycle (18.6 years). |
| Storm surge | The rise in sea level above the astronomical tide caused by wind and low pressure, mainly during cyclones. |
| Still-water level | Astronomical tide plus surge, excluding individual waves. |
| Sea-level allowance (SLA) | The allowance added to present-day tidal levels for sea-level rise over the design life (Clause 5.7.4). |
| Tailwater | The water level at the downstream end of a drain, outlet or storage. |
| Tide-lock | The condition in which the tailwater is at or above the upstream water level, so a gravity outfall cannot discharge. |
| Lock window | A period during which the outfall-closed check of Clause 5.10 sets gravity discharge to zero. |
| Sand bar | A bar of beach sand that partly or fully closes a river mouth or creek inlet. |
| Project datum | The levelling datum used on the project drawings. It must be tied to a Survey of India benchmark (Clause 5.7.2). |
5.3 Extent of the downstream analysis
5.3.1 The downstream analysis shall start at each site or project outfall. It shall continue downstream to the first of:
- (a) the point at which the project area is 10% or less of the contributing catchment;
- (b) the next tank, pokhar or other waterbody with a surplus weir or controlled outlet; or
- (c) the next major drain, or the sea.
The end point itself shall be analysed (Figure 5.1).
5.3.2 Where the analysis ends at a tank or pokhar under 5.3.1(b), it shall report:
- the change in the tank's maximum water level; and
- the change in surplus-weir discharge, for the AEPs and durations of Clause 5.4.3.
If the maximum water level rises, the analysis shall continue below the surplus weir to the next end point.
5.3.3 Analysis points shall be set at least at:
- (a) each site outfall;
- (b) each confluence with a drain or channel whose contributing catchment is at least half that of the receiving drain at that point;
- (c) each culvert, bridge or road crossing;
- (d) each location recorded as flood-prone by the local body, PMC, BSDMA or WRD; and
- (e) each building or road segment lying within the 1% AEP flood extent along the route. Representative points may be used where buildings are closely spaced.
5.3.4 Small sites. For sites of less than 0.5 ha, the Authority may accept a simplified downstream statement (Form 5-2) in place of the full analysis, where all of the following hold:
- the receiving public drain has documented capacity for its minor-system design flow (Chapter 6);
- no flood-prone location is recorded within 500 m downstream; and
- the site does not drain to a tidal or backwater-affected outfall.
Figure 5.1 — Extent of downstream analysis: analysis points A–D, the contributing area at each point, the 10% point, and the next pokhar or major drain as an alternative end point. Schematic; percentages are illustrative. Original drawing for this Manual, adapted from the ten-percent rule in the Georgia Stormwater Management Manual (2016, Vol. 2 §3.1.9) and KC APWA Section 5600 (2006, 5601.5).
Commentary. The 10% rule has established precedent. KC APWA 5600 (2006) required the downstream system to be analysed "to the point the development's land mass is less than 10% of the total watershed". The Georgia manual makes the ten-percent analysis a mandatory standard (GSMM 2016, Standard #8). The tank or major-drain end point has no direct precedent; this Manual adds it for Bihar. In Patna, whose drainage "comprises hierarchy of natural and man-made drains that ultimately discharge surface run off and sewage to River Ganga and Punpun" (CAG, 2020) and where the 5.61 km Saidpur nala carries the runoff of nine drainage pumping stations and one sewage treatment plant (as reported), and in north Bihar, where drains end in chaurs and mauns that drain on to the rivers, as Kabartal drains through the Bagras maun to the Burhi Gandak (Ramsar Information Sheet, 2020), the 10% point can lie many kilometres downstream, across several tanks. A tank with a working surplus weir changes the hydrograph completely, so the analysis is better ended there and the tank level reported. Clause 5.3.2 prevents that end point from hiding a rise in the tank level. The small-site statement (5.3.4) and its 500 m distance have no direct precedent and are set by this Manual.
5.4 What the analysis must check
5.4.1 Scenarios. Each analysis shall compare:
- (a) Existing: the present downstream system and present land use of the whole contributing catchment, with the project site at its pre-project state; and
- (b) With project: the same, with the project and all its controls (Chapter 4) in place.
Where the Authority's basin plan defines future land use, the Authority may also require:
- (c) Future: the catchment fully developed under the plan, all to Chapter 4 standards, with and without the project.
5.4.2 Quantities to be checked at every analysis point:
- (a) Capacity: peak flow against the capacity of every channel, pipe, culvert and crossing, for the minor-system AEP of that element (Chapter 6) and for 1% AEP;
- (b) Flood levels: 1% AEP maximum water level at buildings (at the lowest opening) and on roads (at the crown and at the deepest point);
- (c) Velocities: peak velocity for 50%, 10% and 1% AEP;
- (d) Timing of combined peaks: the hydrograph at each confluence, showing the time to peak of the project outflow and of the receiving drain; and
- (e) Duration of inundation: on roads and at buildings, the time above the Chapter 6 depth limits.
5.4.3 Storms. The analysis shall use:
- 50%, 10% and 1% AEP;
- the duration set of Clause 2.5.2, at least the durations that give the highest level at each analysis point (these will usually be longer than at the site); and
- the 24-, 48- and 72-hour storms in every case.
The AMC rule of Clause 2.11.4 applies. Areal reduction follows Clause 2.7, applied to the contributing catchment at each analysis point and never to the site storage.
5.4.4 Method. The analysis shall:
- use a hydrograph method that combines hydrographs at confluences (SWMM, HEC-HMS, or an equivalent);
- include a hydraulic model with backwater (SWMM dynamic wave, HEC-RAS, or equivalent) wherever tailwater or backwater affects any analysis point; and
- not use the Rational Method at any analysis point, because it cannot represent timing.
Off-site areas shall be modelled at their present land use. Upstream detention shall be included only where it is built, maintained and documented.
5.4.5 Tailwater. The downstream end of the model shall use the tailwater of Clauses 5.6 to 5.9 and the sand-bar condition of Clause 5.13 where applicable.
Commentary. Clause 5.4.2(d) exists because detention changes when the site's water arrives, not only how much arrives (Clause 4.16). A Colorado State University thesis and a Water (2016) optimisation study both found that delayed site releases can coincide with the main-stem peak and raise it. Georgia's manual states the result directly: some structural practices "fail to reduce discharge peaks to pre-development levels downstream" because of "peak flow timing and runoff volume effects" (GSMM 2016). The duration-of-inundation check (5.4.2(e)) matters in the river-locked cities of Bihar, whose outfalls lie behind sluices, embankments or a town protection wall and below the highest flood levels of the rivers they drain to, and where the rivers stand high for days: the highest flood levels at the CWC gauges of the cities stand 0.6–3.3 m above the danger levels (the Ganga at Gandhi Ghat, Patna, 50.52 m against 48.60 m; the Punpun at Sripalpur 53.91 m against 50.60 m) (CWC, 2026), ground floors in Patna were reported under water for 5–7 days in the flood of August 1975, and the Ganga at Gandhi Ghat was reported above its highest flood level on 5 and 6 September 2026 (as reported). Detention that prolongs releases can lengthen that time even when it lowers the peak.
5.5 Acceptance criteria
5.5.1 The project is acceptable if, at every analysis point and for every AEP and duration of Clause 5.4.3, comparing "with project" to "existing":
- (a) the 1% AEP maximum water level does not rise by more than 10 mm at any habitable building, at any building's lowest opening, or on any road carriageway;
- (b) no building that is not flooded in the existing case is flooded with the project, and no building or road that meets the Chapter 6 freeboard or depth limits in the existing case fails them;
- (c) peak flow does not exceed the existing peak at the minor-system AEP of each element, or at 1% AEP;
- (d) peak velocity in lined channels stays within the permissible velocity for the lining (Chapter 6: 3.0 m/s maximum); and
- (e) in unlined or natural channels, peak velocity for 50% and 10% AEP does not increase by more than 10%, unless protection is provided under Chapter 9.
5.5.2 The duration of inundation under 5.4.2(e) shall be reported. The Authority may refuse a project that increases the duration of road closure on an arterial or emergency route.
5.5.3 Where the criteria are not met, the project shall do one or more of the following:
- (a) reduce release rates or increase storage (Chapter 4);
- (b) build downstream improvements, with the consent of the owner of the downstream system. These shall not transfer the problem further downstream, and shall be re-analysed under this chapter;
- (c) contribute to a regional facility under Clause 4.13; or
- (d) under Clause 5.5.4, change the release strategy.
5.5.4 Timing exception. Where the analysis shows that detention raises downstream levels because of timing, the Authority may vary the site release-rate criteria of Clause 4.5. This applies only where the site discharges within the lower tenth of the contributing catchment, directly to a major drain, tidal creek or the sea, and only on the following conditions:
- (a) the varied strategy meets 5.5.1;
- (b) the retention requirement (Clause 4.4) and WQv treatment (Chapter 8) are met in full; and
- (c) the outfall-closed check (Clause 5.10) is met.
Commentary. The 10 mm tolerance (5.5.1(a)) has no direct precedent. It is meant to be at or below the numerical precision of a typical one-dimensional model, so that "no increase" can be tested without arguing over rounding. The 10% velocity tolerance is likewise set by this Manual. The timing exception in 5.5.4 follows the Georgia manual, where the downstream analysis can show "that peak controls are not needed" and allow them to be waived (GSMM 2016, Standard #8). It is limited here to sites low in the catchment, which is where synchronisation with the main-stem peak is most likely (Water 2016, 8(7):290). It is not available above that, because the evidence on scale (Clause 4.16) shows that early release from many upstream sites raises peaks.
5.6 Tailwater: general and non-tidal outfalls
5.6.1 Every drain, outlet and storage shall be designed against a stated tailwater. A free outfall shall be assumed only where the outlet invert is above the maximum receiving water level for the case being checked.
5.6.2 Minor-system tailwater, non-tidal. The tailwater is the receiving system's water level at the time of the minor-system peak, from the downstream model. Where no model exists, use:
- for a receiving pipe, its obvert; or
- for a receiving open drain, its full-bank level less freeboard (Chapter 6).
5.6.3 Major-system tailwater, non-tidal. The tailwater is the receiving system's 1% AEP water level, unless Clause 5.8 allows a coincident lower level.
5.6.4 Tidal and backwater outfalls. Clauses 5.7 to 5.13 apply in addition.
5.6.5 Storage elements. Detention, tanks and pumped sumps shall be routed with a time-varying tailwater (Clause 4.6.6), not a constant level, wherever the tailwater varies with tide or with the receiving system's hydrograph.
5.7 Tidal tailwater: datums, surge and sea-level allowance
5.7.1 Design tailwater levels. For outfalls to the sea, tidal creeks, estuaries, backwaters and tidal reaches of rivers and canals:
Table 5.1 — Design tailwater levels for tidal outfalls
| Design case | Tailwater |
|---|---|
| Minor-system design (Chapter 6) | MHWS + SLA |
| Major-system design and storage design | HAT + surge + SLA, with the surge term defined in Clause 5.7.3 |
| Joint case (Clause 2.12(b)) | 1% AEP still-water level + SLA |
The SLA is +0.3 m minimum (Clause 5.7.4). The cases to be run are listed in Clause 5.9.
5.7.2 Sources and datums.
- (a) Tidal levels. MHWS, HAT and MSL shall be taken from the current edition of the Indian tide tables published by the National Hydrographic Office (NHO) or by the Survey of India, for the nearest standard or secondary port, or from the port authority's published tidal levels. The edition and port shall be stated.
- (b) Datum conversion. Tide-table heights are referred to chart datum. They shall be converted to the project datum through a documented connection between chart datum, the tide gauge zero and a Survey of India benchmark. The offset and its source shall be stated on Form 5-1.
- (c) Estuaries, creeks and canals. For outfalls inside estuaries, creeks, backwaters or tidal canals (for example the estuaries of the coastal States; there is none in Bihar, Clause 5.1.4), tidal levels may differ from the open coast. Open-coast levels shall be used unless measured levels over at least one spring–neap cycle, or a calibrated hydrodynamic model, justify a different value. No reduction below open-coast levels shall be taken without such evidence.
- (d) Interim. Until Annex 5A is published, the designer shall obtain the values directly from the sources in (a) and record them.
5.7.3 Storm surge.
- (a) Major-system and storage design. The surge term in "HAT + surge" is the 10% AEP (10-yr) storm surge for the coastal segment, given in Annex 5A. The 1% AEP surge is used only in the joint case of Clause 2.12(b), with the 10-yr 48-hour storm. That keeps the two cases symmetric, so that a rare rainfall is never paired with a rare surge.
- (b) Joint case. The 1% AEP still-water level for Clause 2.12(b) is taken from Annex 5A.
- (c) Until Annex 5A is published, both values shall be taken from a site-specific study using INCOIS, IMD or NCCR surge hindcasts or return-level analyses. The study shall state its source, method and record length.
- (d) Wave set-up shall be added where the outfall faces the open sea without a protected entrance.
5.7.4 Sea-level allowance. The SLA shall be:
- (a) +0.3 m minimum for every element;
- (b) greater than 0.3 m where the State, PMAA or the Authority adopts a higher projection for the planning area; and
- (c) assessed for the design life of the element. For elements with a design life of more than 50 years, the designer shall report the effect of a sea-level rise of twice the SLA as a sensitivity run.
Figure 5.2 — Tidal outfall: flap gate, property non-return valve, and the design tailwater levels (MHWS + 0.3 m for the minor system; HAT + surge + 0.3 m for the major system), with a seasonal sand bar at the mouth. Schematic, not to scale. Original drawing for this Manual, adapted from the tidal tailwater table in MoHUA/CPHEEO Manual on Storm Water Drainage Systems (2019), Part A, Table 6.2.
Commentary. CPHEEO (2019) Table 6.2 sets the design tailwater for coastal outfalls as:
- MHWN to MHWS for a minor storm (more frequent than 1 in 5 years);
- MHWS to HAT for a major storm; and
- "Effect of climate change: additional 0.3 m".
CPHEEO also says the joint probability of storm, tide and surge "should" be considered, with the state maritime board consulted. This Manual takes the upper end of each CPHEEO range, adds surge for the major system, and makes the joint case explicit (Clause 2.12). CPHEEO does not require surge to be added; this Manual adds it because the surge records of the coastal States showed why it is needed there; Bihar has no coast, and the surge term does not arise in the State.
Indian tide tables have been published by the Survey of India since the nineteenth century (Survey of India, Tidal Predictions). Current Indian tidal predictions also appear in the NHO's tide tables. One port document describes the current edition as covering 95 Indian ports, based on NHO observations and on data from civil ports, NIO and INCOIS (Adani Ports, Dahej tide table 2025, citing NHO INP-12). INCOIS runs coastal tide gauges and issues storm-surge and swell-surge warnings. None of these is used for design in Bihar, which has no coast, and Annex 5A is not prepared for the State (Clause 5.1.4).
5.8 Riverine backwater
5.8.1 Where it applies. Outfalls to rivers and canals whose water level in a storm can exceed the outfall invert shall be designed with riverine backwater. This includes:
- the Ganga along Patna, from Dighaghat past Gandhi Ghat to the Punpun confluence, with the Sone at Maner and the Punpun at Sripalpur, the town protection wall, the sluices and the gated and pumped outfalls of the city's drains and sump houses (Clause 5.8.5(a) and (b));
- the Burhi Gandak at Muzaffarpur, the Bagmati and the Adhwara group at Darbhanga, the Gandak and the Ganga at Hajipur, the Mahananda and its tributaries in Purnia district, and every other embanked river of north Bihar with the towns behind its embankments (Clause 5.8.5(c));
- the rivers that rise in Nepal, with the releases of the Kosi barrage at Bhimnagar and the Gandak barrage at Valmikinagar (Clauses 5.8.3 and 5.8.5(d));
- the Kosi between its embankments and the land behind them (Clause 5.8.5(e));
- the Ganga at Buxar, Mokama (Hathidah), Munger and Bhagalpur, and the outfalls of the drains that discharge to it there (Clause 5.8.5(a));
- any drain or canal of WRD, and any irrigation canal that receives storm water (Clause 5.8.5(f)); and
- elsewhere: any river or WRD channel listed in Annex 5B.
5.8.2 River levels. River water levels shall be taken from:
- (a) WRD design flood levels or recorded highest flood levels for the reach, where published; or
- (b) a hydraulic model (HEC-RAS or equivalent) of the river reach. The model shall use:
- the river design flood from a hydrograph method (Chapter 3), with continuous simulation where Chapter 3 requires it;
- the tidal boundary of Clause 5.7 at the mouth; and
- the sand-bar condition of Clause 5.13.
5.8.3 Reservoir and tank releases. Where a reservoir or tank upstream can release to the river (for example the Kosi barrage at Bhimnagar in Nepal, the Gandak barrage at Valmikinagar, the Indrapuri barrage on the Sone, and the dams on the Sone and its tributaries upstream of the State), the river level shall include the release given by the reservoir's operating rule for the storm being checked. Where there is no published rule, it shall include the largest recorded release.
5.8.4 Coincidence of site storm and river flood. Unless a joint-probability study is accepted by the Authority, the more severe of the following governs:
- (a) the site design storm (AEP as required), with the river at its 10% AEP (10-yr) level; and
- (b) the site 10% AEP storm, with the river at its design-AEP level (1% AEP for the major system).
The two storms in each pair shall have the same duration and timing where they are generated by the same rainfall event.
5.8.5 River-locked outfalls, the Ganga, the Sone and the Punpun around Patna, the embanked rivers of north Bihar, floods from Nepal, the Kosi, and discharges to WRD drains and irrigation canals.
- (a) River-locked outfalls. For an outfall to a river directly, through a sluice or gate in an embankment or a town protection wall or through a drainage pumping station (a sump house), or into a drain that itself discharges in one of those ways, the designer shall identify the body that operates each sluice, gate and pumping station, and obtain the sill of each gate, the crest of the embankment or wall, the installed pumping capacity and the operating levels, including the river level at which each sluice is closed. Every level shall state its datum and its connection to the gauge datum of the nearest CWC or WRD gauge.
- Design river level. The river level of Clause 5.8.2 at the outfall shall be, for the major-system cases (Clause 5.8.4(b)), the 1% AEP river level at the outfall: the 100-year level of a flood-frequency study or floodplain delineation that gives a level at the outfall, such as the 5-, 25- and 100-year zones that NIH Roorkee is delineating for WRD on the Ganga from Chausa to Manihari, once published, or a level from a hydraulic model under Clause 5.8.2(b). The Flood Plain Zone of WRD Order No. 143 of 6 March 2025 is defined by the embankments and not by a level, and does not give one. The level shall in no case be less than the highest recorded level at the nearest CWC or WRD gauge on the same river, transferred to the outfall. The highest levels in the CWC bulletin (Table 5B.1) are: the Ganga at Dighaghat, Patna, 52.52 m (1975) and at Gandhi Ghat, Patna, 50.52 m (2016); the Sone at Maner 53.79 m (1976); the Punpun at Sripalpur, Patna, 53.91 m (1976); the Burhi Gandak at Sikandarpur, Muzaffarpur, 54.29 m (1987); the Bagmati at Hayaghat 48.96 m (1987) and the Adhwara group at Ekmighat 49.52 m (2004), at Darbhanga; the Gandak at Hajipur 50.93 m (1948); the Mahananda at Dhengraghat, Purnia, 38.20 m (2017); and the Ganga at Buxar 62.09 m (1948), Hathidah 43.52 m (2021), Munger 40.99 m (1976) and Bhagalpur 34.86 m (2021). Where two values are reported for the same gauge, the higher applies until CWC confirms the level [TBC]: at Gandhi Ghat, where the Ganga was reported at 50.53 m on 5 September 2026 and 50.57 m on 6 September 2026, 50.57 m applies. Where a later flood has exceeded the listed level, the later level governs. The recorded level shall be transferred along the river with the water-surface slope of the flood that set it, from the CWC and WRD gauge records, or from the model. Until either is available, the recorded level of the nearest gauge upstream applies unchanged at the outfall, except that where the outfall lies between two gauges on the same river, with no tributary joining between them, the level may be interpolated linearly by river distance between the highest recorded levels of the two gauges (set by this Manual); an outfall upstream of every gauge on its reach shall not be designed without a profile [TBC]. For the cases with the river at its 10% AEP level (Clause 5.8.4(a)), the level shall be taken from the same model or a frequency analysis of the gauge record, and not less than the danger level at the nearest gauge, transferred in the same way: 50.45 m at Dighaghat, 48.60 m at Gandhi Ghat, 52.00 m at Maner, 50.60 m at Sripalpur, 52.53 m at Sikandarpur, 45.72 m at Hayaghat, 46.94 m at Ekmighat, 50.32 m at Hajipur, 35.65 m at Dhengraghat, 60.32 m at Buxar, 41.76 m at Hathidah, 39.33 m at Munger and 33.68 m at Bhagalpur (CWC, 2026) (all set by this Manual). The datum of the CWC levels is to be confirmed for each gauge [TBC].
- Tailwater. The tailwater at the outfall shall be the higher of that river level beyond the sluice, gate or embankment, and the maximum level in the drain behind it, computed by routing the drain as a closed storage for as long as the river stands above the level behind it, with the inflow of the whole catchment that drains to it, its storage as surveyed in its present condition, net of silt, encroachment and vegetation, and an outflow of no more than the pumping capacity that the operator confirms in writing is available in a storm, and in no case more than the installed capacity of the permanent pumps less the largest pump (set by this Manual), with gravity discharge through the sluice only while the river is lower than the level behind it. Pumps shall deliver against the design river level of this item, and every pump, panel and control shall remain operable with the river at that level (Clause 5.12.5).
- River lock. Portable dewatering pumps and temporary drainage pumping stations brought in for an event, and capacity that has been sanctioned or proposed but not commissioned, shall not be counted. The outfall-closed check of Clause 5.10 applies with a single lock that lasts for as long as the river stays above the outfall invert, or above the level at which its sluice is closed if that is lower, taken from the river model or from the stage record of the nearest CWC or WRD gauge in the flood that set the highest recorded level (1975 for the Ganga at Dighaghat; 1976 for the Sone, the Punpun and the Ganga at Munger; 2016 and 2026 for the Ganga at Gandhi Ghat; 1987 for the Burhi Gandak and the Bagmati; 2017 for the Mahananda; 2021 for the Ganga at Hathidah and Bhagalpur) or in a comparable flood, and not less than 7 days (168 hours), covering the whole of the 48- and 72-hour storms of Clause 5.10.2, so that storage and pumping handle the full storm volume (Clause 5.9.4) and the drawdown of Clause 5.10.5 is met by pumping until the lock ends (set by this Manual). A shorter lock may be used only where the outfall invert is above the 1% AEP river level of this item, or where a gauge analysis under Clause 5.10.6 shows it and the Authority approves it. Floor levels and pumped outfalls behind a sluice, embankment or town protection wall shall also be checked for the failure of the gate and for a breach of the embankment or wall, with the land and drains behind it filled to the river level beyond it.
- (b) The Ganga, the Sone and the Punpun around Patna. For an outfall in Patna, Danapur, Khagaul, Phulwari or another town of the Patna area to the Ganga, the Sone or the Punpun, or to a drain that ends in one of them:
- the outfalls through the sluices, embankments and town protection wall shall be taken as river-locked under item (a), with the sump houses and drainage pumping stations behind them credited only with the permanent pumps that PMC or BUIDCO, as the operator, confirms in writing are working; temporary pumping stations, and pumping stations that have been proposed or sanctioned but not commissioned, shall not be counted;
- the river level at an outfall shall be the highest of the Ganga, the Sone and the Punpun levels at the outfall, with the three rivers in flood together, as the Sone and the Ganga were in August 1975 and the Sone and the Punpun in 1976, unless a model of the confluences shows a lower coincident level;
- an outfall in south Patna to the Punpun, or to a drain that ends in it, shall take as tailwater the Punpun level of item (a), not less than 53.91 m at Sripalpur transferred to the outfall, with the backwater of the Ganga at the Punpun's confluence included, and an outfall in west Patna, Danapur or Maner, in place of the nearest gauge upstream, the higher of the Sone level at Maner and the Ganga level at Dighaghat;
- a drain into which drainage pumping stations discharge, such as the Saidpur nala, which is reported to carry the runoff of nine pumping stations and one sewage treatment plant, shall be routed with all of those pumped inflows, and a project's pumped discharge into it shall be included in its level (Clause 5.12.3);
- floor levels and pumped outfalls behind the town protection wall, and behind roads and embankments that act as flood barriers, such as the Digha–Maner road, which was reported breached at seven places in 1975, shall be checked for a breach under item (a); and
- the interception works on the ghat drains (Clause 8.9.5) shall be included in the routing of item (a) as obstructions, at their present condition.
- (c) The embanked rivers of north Bihar. For an outfall in Muzaffarpur, Darbhanga, Hajipur, Purnia or another town behind the embankment of a river of north Bihar, to that river or to a drain that is gated or pumped through its embankment:
- the outfall shall be taken as river-locked under item (a), with the river level not less than the highest recorded level of item (a) at the nearest gauge, transferred to the outfall: the Burhi Gandak at Sikandarpur for Muzaffarpur; the higher of the Bagmati at Hayaghat and the Adhwara group at Ekmighat for Darbhanga, until a model of both gives the profile; the higher of the Gandak at Hajipur and the Ganga at the confluence for Hajipur; and the Mahananda at Dhengraghat, or the nearest gauge on the river that receives the drain, for Purnia;
- the land behind the embankment shall be routed as a closed storage under item (a), and no storage shall be credited in a chaur, maun, pokhar or other low ground behind the embankment unless the operator's records show the storage available at the start of a storm; any hydrological intervention in a notified wetland or a Ramsar site needs the permission of the Bihar State Wetland Authority (Chapter 7);
- no outfall structure, sluice, pumping station or drain shall be built in the Flood Plain Zone of WRD Order No. 143 of 6 March 2025 (the land between the embankments, or from the embankment to 500 m beyond the far bank where only one bank is embanked), which the Order makes a Prohibited Zone, except as the Order permits and with the consent of WRD; whether a drain outfall is one of the permitted flood-protection structures or essential linear services is to be confirmed with WRD before design [TBC]. A cut through an embankment, or a structure in it, also needs any permission the Bihar Irrigation Act 1997 requires; and
- floor levels and pumped outfalls behind the embankment shall be checked for a breach under item (a).
- (d) Floods from Nepal. For an outfall to the Gandak, the Burhi Gandak, the Bagmati, the Kamla, the Kosi, the Mahananda or another river whose catchment extends into Nepal:
- the river level shall not be reduced on the ground that the flood comes from rain that falls outside the State or that the site storm is small, and the cases of Clause 5.8.4 shall be checked with the river peak placed before, during and after the site storm;
- the river level shall include the releases of Clause 5.8.3 from the Kosi barrage at Bhimnagar and the Gandak barrage at Valmikinagar, as they occurred in the largest recorded event, with the flow of the catchment below each barrage, and shall not assume that any gate opens fully or early unless the operator's records show it, until an operating rule is published [TBC]; and
- the highest recorded level shall be taken from the latest CWC and WRD bulletins, because many of the highest flood levels on these rivers were set after 2015.
- (e) The Kosi. For an outfall to the Kosi, or to a drain behind its embankments:
- no drainage work shall be built between the Kosi embankments except as WRD Order No. 143 permits (item (c));
- the river level shall not be less than the highest recorded level at the nearest of the Kosi gauges at Basua (49.24 m, 2017), Baltara (36.40 m, 1987) and Kursela (32.10 m, 1982), transferred under item (a), with the danger levels of 47.75 m, 33.85 m and 30.00 m as the floor of the 10% AEP level (CWC, 2026), and the channel and bed levels shall be taken from the most recent survey, with its date stated; and
- floor levels and pumped outfalls behind the embankments shall be checked for a breach under item (a), as the Kosi breached its eastern afflux bund at Kusaha in Nepal on 18 August 2008 and changed its course across north Bihar.
- (f) WRD drains and irrigation canals. Storm water shall not be discharged to a drain or canal of WRD, or to another irrigation canal, without the consent of WRD or of the channel's owner. Where consent is given:
- the discharge shall not exceed the rate the consent allows;
- the tailwater is the higher of the channel's design water level as WRD or the owner states it and its level in the coincident case of Clause 5.8.4, computed from all the storm water it receives, including the nalas of other bodies, and with its downstream boundary at the river level of item (a); until WRD publishes a design water level for a channel, the computed level governs [TBC];
- the channel shall be taken in its present condition, net of silt, encroachment and obstruction by crossing services, and a widening, lining, remodelling or diversion that has been proposed but not completed, including the works of a storm water drainage scheme that are not yet built, shall not be counted; and
- the outfall shall have a flap gate (Clause 5.11) where the design water level or the computed level is above the outfall invert.
No pump, sluice, gate or barrage operation that helps drainage, such as pumping a drain down before a storm, closing a sluice late or opening barrage gates early, shall be assumed unless the operator's written records show it. Where the outfall invert is below the tailwater of this clause, the outfall shall have its own flap gate (Clause 5.11) and, where the outfall-closed check requires it, pumping (Clause 5.12), with the pumped volume included in the routing of the drain or the river (Clause 5.12.3).
Commentary. In large continental river basins, a site storm and a river flood are usually treated as roughly independent. That is the basis of tables of coincident frequencies such as FHWA HEC-22 Table 7.3. Bihar's rivers break that assumption. The Punpun drains the south Bihar plain, and its basin lies in the same CWC subzone as Patna (the Sone subzone 1(d), whose report names the Punpun and the Phalgu among its rivers), so the monsoon systems that flood south Patna also raise the river behind it. The Sone and the Ganga bring water from far upstream, but the same monsoon spells fall on the cities they pass: in August 1975 the Sone began to rise on 19 August after heavy rain upstream, and its waters and the Ganga's entered Patna together on the night of 24 August (as reported); the highest recorded levels of the Ganga at Dighaghat were set in 1975, and of the Sone at Maner and the Punpun at Sripalpur both in 1976 (CWC, 2026). September brings the most storms and depressions to Bihar, 43 of the 113 recorded in 1891–2010 (IMD, Climate of Bihar), Patna's highest 24-hour rainfall, 273.5 mm, fell on 20 September 1967 (IMD), and the Ganga at Gandhi Ghat was reported above its highest flood level in early September 2026 (as reported). The rivers of north Bihar rise with the same monsoon systems over Nepal and north Bihar. The two cannot be treated as independent, and a local storm can fall before, during or after the river peak. Clause 5.8.4 therefore pairs a design event on one side with a 10-yr event on the other, in the same way as Clause 2.12(b). This pairing has no direct precedent. It is more severe than an independence assumption would give.
Clause 5.8.3 reflects the barrages and dams above the State's cities. The Kosi and the Gandak enter Bihar from Nepal through the barrages at Bhimnagar and Valmikinagar, and the Sone reaches Patna below the Indrapuri barrage and the dams upstream of the State; the flood of August 1975 began with a rise of the Sone after heavy rain upstream (as reported). No operating rule or release record for any of them was obtained during research, and the CWC hourly stage records at Dighaghat, Gandhi Ghat, Maner, Sripalpur, Sikandarpur, Hayaghat, Ekmighat, Hajipur, Dhengraghat, Munger and Bhagalpur, and the WRD flood-control orders, were not obtained [TBC]. Until they are, the largest recorded release applies, with the flow of the catchment below the barrage as it occurred in the same event (Clause 5.8.5(d)). The danger and highest flood levels used in this Manual are those of the CWC daily bulletin for Bihar of 31 October 2026, read from the page image; the bulletin gives them in metres without a stated datum, so the datum and gauge zero of each gauge are to be confirmed from CWC [TBC].
Clause 5.8.5 is set by this Manual. In Bihar the tailwater at a city outfall is set not by the tide but by a river that stands high for days, by an embankment or the town protection wall and their sluices, by a barrage, or by a pump behind an embankment, and no document found during research gives a design river level for any of them. The Bihar Municipal Act 2007 requires the Municipality to provide "a safe and sufficient outfall" for the "effectual drainage and proper discharge of storm-water" without flooding any part of the municipal area (s.193), but it does not say against which river level. WRD Order No. 143 of 6 March 2025 zones the floodplain of embanked rivers by the embankments, not by a flood level, and no design return period has been published for the drainage of any Bihar city.
The first is the river lock. Clause 5.8.5(a) asks for a 1% AEP level. For the Ganga, the second phase of WRD's floodplain zoning has NIH Roorkee delineating 5-, 25- and 100-year zones from Chausa to Manihari (MoU of 3 August 2025, a one-year study); it had not been published when research was done [TBC]. Until a level is available at the outfall, the highest recorded level is the floor. The levels are those of the CWC daily bulletin for Bihar of 31 October 2026, read from the page image; the bulletin does not state the datum, so the datum and gauge zero of each gauge are to be confirmed [TBC]. The floor is not an estimate of the 1% AEP level, which may be higher: about half of the highest flood levels at the CWC gauges of north Bihar were set after 2015, and the Ganga at Gandhi Ghat was reported 1–5 cm above its 2016 level on 5 and 6 September 2026, while the bulletin of 31 October 2026 still listed 50.52 m (2016). That is why item (a) uses the higher reported value at Gandhi Ghat until CWC settles it, and lets a later flood replace a listed level; the Gandak at Hajipur and the Ganga at Buxar still carry levels of 1948. Carrying a gauge level unchanged downstream is conservative, because the river falls downstream; upstream of the gauge it would not be, so an outfall upstream of every gauge needs a profile. The gauges on the Ganga are far apart, so between two gauges item (a) allows a straight-line interpolation of their highest levels: carrying the upstream level unchanged would put the 1975 level of Dighaghat, 52.52 m, about 2 m above the Gandhi Ghat record, on every outfall down to Gandhi Ghat. The interpolation is not the profile of any one flood, and a model of the reach replaces it. West Patna and Danapur lie upstream of Dighaghat but below the Sone confluence, and the nearest Ganga gauge upstream of them, at Buxar, is far up the river, so item (b) uses the Maner and Dighaghat levels there instead. The danger level is used as the floor of the 10% AEP river level because the highest recorded levels stand 0.6–3.3 m above the danger levels and the rivers have crossed them often in recent years, with new highest levels at Gandhi Ghat in 2016 and 2026 (as reported), on the Mahananda, the Parman and the Kosi at Basua in 2017 and at Hathidah and Bhagalpur in 2021 (CWC, 2026), so a level reached about once in ten years is unlikely to lie below it; it is to be replaced by a frequency analysis of the CWC record [TBC].
A river flood also lasts. No hourly hydrograph for any gauge in the State was obtained during research [TBC]. In the flood of August 1975, ground floors in Patna were reported under water for 5–7 days; the Ganga flood of September 2026 was described as a third prolonged flood spell of the season (as reported), and the Ganga at Gandhi Ghat still stood at 45.41 m on 31 October 2026 (CWC); and a river that peaks 1.9 m (Gandhi Ghat) or 3.3 m (Sripalpur) above its danger level must fall all of that before an outfall set at the danger level can open. A tide lock opens again within hours; a river lock lasts as long as the flood. The single lock of at least 7 days is therefore a floor, to be lengthened from the gauge record of the flood that set the highest recorded level on each river. It also covers the whole design storm, so that a site behind an embankment stores or pumps its whole storm, which is what Clause 5.9.4 already requires when the tailwater stays above the outfall. It counts only the permanent pumps less the largest one, for the same reason that Clause 5.12.2(b) requires a standby pump; temporary pumping stations and portable pumps brought in for an event are not a design capacity. A Rajya Sabha reply of 27 November 2024 counted "56 permanent Drainage Pumping Stations and 28 Temporary" (seen only as an extract; whether for Patna or the State is unclear). The gate-failure and embankment-breach checks follow 1975, when the Sone and the Ganga crossed the Patna canal and the Digha–Maner road was reported breached at seven places, and 2008, when the Kosi breached its afflux bund at Kusaha.
The second is Patna. The city is "surrounded on three sides by rivers – The Ganga, Sone, and Punpun", and its drainage "was laid about 200 years ago and is in bad condition" (CAG, 2020). When the rivers rise, the sluice gates on the Ganga and the Punpun are closed and the city drains only through its sump houses and drainage pumping stations, such as Saidpur, Pahadi, Yogipur, Mandiri, Rajapur–Gosaitola, Kurji and Eco Park, nine of which are reported to be monitored from the Patna Smart City control centre (as reported). In September 2019, 38 of 39 sump houses were reported not working, and the State's inquiry was reported to have recommended 14 new pumping stations and 100 dewatering pumps (as reported), which is why item (b) counts only permanent, commissioned pumps that the operator confirms. No inventory of the pumping stations with their capacities and sump volumes, and no rule linking the closing of the sluices to the river stage, was found [TBC], and the division of the stations between PMC and BUIDCO is unconfirmed (Chapter 6, Clause 6.9). Item (b) takes the three rivers as coincident because their records show it: the Ganga at Dighaghat set its highest level in 1975, when the Sone and the Ganga entered the city together, and the Sone at Maner and the Punpun at Sripalpur both set theirs in 1976 (CWC, 2026). The Punpun's highest level, 53.91 m, stands 3.31 m above its danger level, the largest margin of any gauge around Patna, and on 31 October 2026 the river still stood at 46.68 m at Sripalpur (CWC); its backwater is what holds the drains of south Patna. A town protection wall of about 8.5 km was reported built after the 1975 flood (as reported). How the outfalls of south Patna were locked in 1975 and 1976 was not documented in any source read, and the report Patna Deluge 1975 could not be obtained [TBC].
The third is north Bihar. WRD Order No. 143 records about 3,606 km of embankments in north Bihar, out of 3,800 km in the State, and 68.80 lakh ha of the State's 94.16 lakh ha as flood-prone. Muzaffarpur, Darbhanga, Hajipur and Purnia drain to rivers whose highest levels at the city gauges stand 0.6–3.2 m above danger (CWC, 2026), and whose floods come from rain in Nepal as well as in Bihar: WRD's flood centre compiles heavy-rainfall reports from CWC and from Nepal's Department of Hydrology and Meteorology, and a record rise of the Gandak was reported after rain in Nepal in late September 2026 (as reported). Item (d) therefore does not let a designer reduce the river level because the local storm is small. The Kosi runs between embankments, and in the flood of 18 August 2008 it breached its eastern afflux bund at Kusaha in Nepal and changed its course across north Bihar, leaving about three million people homeless (as reported); item (e) requires a breach check for every pumped outfall and floor level behind its embankments. Item (c) gives no storage credit in chaurs and mauns, which are part of the flood plain: Kabartal, the largest of a complex of 18 interconnected wetlands, is inundated to a depth of up to 1.5 m in the monsoon (Ramsar Information Sheet, 2020).
The fourth is the drain that another body owns. No rule dividing the drains of WRD from the nalas of the Nagar Nigams and BUIDCO was found during research (Chapter 6, Clause 6.9). WRD runs the embankments, canals and flood-control drainage works, and in Darbhanga an application to the NGT describes a WRD canal-lining project on an old storm-water canal (Talab Bachao Abhiyan, 2025), which would make the canal's level the tailwater of the drains that enter it. No WRD design water level was found for any drain or canal. Item (f) asks for the owner's consent and design water level and, until the level is published, computes it from the channel's present condition, without counting works that are not built. Schedule V of the Bihar Ease of Doing Business Act 2026 lists an "Irrigation Department NOC for sites near canals" and a "Storm Water Drains NOC" as "Not required" for enterprises; item (f) does not add a NOC, but a design that discharges to a channel cannot be checked without the owner's level and permitted rate.
5.9 Joint-probability cases
5.9.1 Every element draining to a tidal or backwater-affected outfall shall be checked for the cases below. The most severe governs each design quantity: storage, water level, pipe size and pump capacity.
Table 5.2 — Joint-probability cases for tidal and riverine outfalls
| Case | Rainfall | Tailwater | Applies to | Basis |
|---|---|---|---|---|
| J1 | Minor-system design AEP, Tc to 24 h | MHWS + SLA (tidal curve) | Minor system | Clause 2.12(a); Clause 5.7.1 |
| J2 | 1% AEP, all durations of Clause 2.5.2 | HAT + surge + SLA | Major system, detention, tanks, pumped systems | Clause 5.7.1 |
| J3 | 10% AEP, 48 h | 1% AEP still-water level + SLA | Major system, detention, tanks, pumped systems | Clause 2.12(b) |
| J4 | Design AEP, 48 h (72 h reported) | Tidal curve per J1 with two 6 h lock windows (Clause 5.10) | All storage and every gated or tide-affected outfall | Clause 5.10 |
| R1 | Site design AEP | River at 10% AEP level | Riverine outfalls | Clause 5.8.4(a) |
| R2 | Site 10% AEP | River at design-AEP level | Riverine outfalls | Clause 5.8.4(b) |
5.9.2 For storage elements, the 48- and 72-hour storms shall be run with the J2 and J3 tailwaters (Clause 2.5.3).
5.9.3 For tidally influenced riverine outfalls, R1 and R2 shall be run with the river model's downstream boundary at the J1 tidal curve. The Authority may also require them at J2.
5.9.4 Where tailwater is constant at a level above the outfall invert for the whole storm, the case is treated as a fully closed outfall. Storage and pumps shall then handle the full storm volume.
Commentary. Clause 2.12 sets two joint cases. Case (a) is design rainfall with MHWS plus the sea-level allowance. Case (b) is the 10-yr, 48-hour storm with the 1% still-water level. This Manual adds HAT plus surge for major-system design (Clause 5.7.1). Case J2 combines these. J4 is the outfall-closed check, which tests the timing of tide against the storm rather than a single level. Rainfall and surge share a cyclone cause, so they cannot be treated as independent (Clause 2.12 commentary). These cases are simple surrogates, to be replaced when a statistical joint analysis of IMD rainfall and tide-gauge records is adopted.
5.10 Outfall-closed (tide-locked) storage check
5.10.1 Where it applies. The check applies to:
- every storage facility;
- every minor- and major-system element; and
- every pumped system
whose outfall invert is below HAT + surge + SLA, or which drains to a reach subject to tide-lock or sand-bar closure (Clause 5.13).
5.10.2 Storm. Use the 48-hour design storm built per Clause 2.9.2 (peak day last), at:
- the AEP of the element: 1% AEP for detention, tanks and the major system; the minor-system AEP for minor drains; and
- AMC III.
The 72-hour storm shall also be run and reported.
5.10.3 Lock windows. Unless a site study under 5.10.6 gives otherwise:
- (a) the outfall is closed for two consecutive lock windows of 6 hours each, centred on two consecutive high tides of the local tidal curve. For a semi-diurnal tide, the window starts are therefore about 12.4 hours apart.
- (b) During each lock window, gravity discharge is zero.
- (c) Between lock windows, gravity discharge is computed against the J1 tidal curve, including the head loss of the flap gate and any non-return valve.
- (d) The first lock window shall be placed so that it is centred on the peak 1-hour block of the final 24 hours of the storm. A second run with the first window starting at that peak block shall also be made. The more severe governs.
5.10.4 Requirement. Storage plus pumping (where provided) shall hold the inflow so that, throughout the check:
- (a) the maximum stage in any detention facility stays below its emergency spillway crest, so the spillway does not operate. Where the outfall-closed stage is higher than the 1% AEP maximum water level of the free-outfall design, it becomes the facility's 1% AEP maximum water level for Clause 4.9.3, and the spillway crest, freeboard and wall height are set from it;
- (b) the maximum stage in the minor and major systems meets the Chapter 6 limits: building floor levels, and street depths of no more than 150 mm at the crown and no more than 350 mm at the deepest point; and
- (c) no property connection surcharges above the lowest opening it serves, or a non-return valve is fitted under Clause 5.11.
In volume terms, over each lock window and the full storm:
V_inflow ≤ V_storage available + V_pumped + V_gravity (between locks)
This shall be demonstrated by routing, not by a single volume balance. The release from each facility after a lock window ends may exceed the release caps of Chapter 4, because the facility is emptying into a drain that has just reopened. That release shall be included in the downstream analysis (Clauses 5.4 and 5.9).
5.10.5 Drawdown after the storm. After the second lock window, the storage shall drain under the J1 tidal curve. The drawdown requirement of Clause 4.7 shall be met, with pumping where gravity cannot meet it (Clause 5.12).
5.10.6 Site study. A longer or shorter lock may be used where a site study gives a time series of still-water level for the design case. The study may use a calibrated hydrodynamic model, gauge records of past events, or a surge hindcast. Locks shorter than the default require the Authority's approval. A longer lock shall be used where:
- sand-bar closure (Clause 5.13) or river backwater (Clause 5.8) keeps the outfall closed for longer; or
- the gauge record shows tailwater above the outfall invert for more than 6 hours per tide in comparable past events.
Figure 5.3 — Outfall-closed check: 48-hour storm with the peak day last (Clause 2.9.2), tailwater of astronomical tide plus surge, two 6-hour design lock windows, and the resulting stage upstream of the flap gate. Illustrative — not design values. Original drawing for this Manual, adapted from the tidal tailwater and joint-probability concepts of MoHUA/CPHEEO Manual on Storm Water Drainage Systems (2019), Part A, §6.3.6.
Commentary. The outfall-closed check is the distinctive Bihar requirement in this Manual. In Bihar it applies where an outfall is shut not by the tide but by a river. When the Ganga and the Punpun rise, the sluice gates on both rivers at Patna are closed and the drains connected to the Ganga are blocked, and the city then drains only through its pumping stations (as reported, September 2026). In the waterlogging of September 2019, 38 of the city's 39 sump houses were reported not working, and Rajendra Nagar and Kankarbagh stayed under water for days (as reported). In the flood of August 1975, ground floors in Patna were reported under water for 5–7 days. A river flood lasts for days, not hours, which is why Clause 5.8.5(a) replaces the two 6-hour windows described below with a single lock of at least 7 days. A rate rule cannot help when there is no outlet: an orificed basin behind a closed gate simply fills.
The default of two consecutive 6-hour locks has no direct precedent. It represents gravity outfalls failing to discharge for about half of each tidal cycle around the two high tides nearest the storm peak. Figure 5.3 shows why both windows matter. The first lock catches the storm peak. The second arrives before the storage has drained, so the stage rises again.
Placing the first window on the rainfall peak is deliberately unfavourable. Cyclone rainfall and surge share a cause, and Clause 2.12 already treats them as dependent. The check replaces neither the J2 and J3 level checks nor the downstream analysis; it adds a test of timing and volume.
5.11 Flap gates, tide gates and non-return valves
5.11.1 Where required. A flap gate, tide gate or equivalent non-return device is required on every outfall whose invert is below the 1% AEP still-water level (Clause 5.7.3). It is also required on outfalls into irrigation channels under Clause 5.8.5.
5.11.2 Hydraulics. The design shall include:
- the gate's head loss and opening head, from the manufacturer's certified head–discharge curve; and
- the reduction in effective outfall capacity when the gate is partly open.
Gates shall not be assumed to seal perfectly in the outfall-closed check unless they are tested.
5.11.3 Construction.
- (a) Gates, hinges and seats shall be of corrosion-resistant materials suitable for seawater (Clause 4.12.5).
- (b) The gate shall be set so that sand, silt or debris on the downstream side cannot hold it shut or open. Where the bed is mobile, the gate invert shall be raised above the bed, or the approach shall be protected.
- (c) A trash screen shall be provided upstream where the gate could be jammed by debris.
- (d) A stop-log slot or penstock shall be provided upstream for maintenance isolation on outfalls larger than 600 mm.
- (e) The gate chamber shall be accessible at all tides, with its access above HAT + surge + SLA.
5.11.4 Non-return valves on property connections. A non-return valve, or a backwater valve with an accessible cleaning eye, is required on every property drainage connection where the lowest opening served is below:
- the major-system tailwater (J2) at the point of connection; or
- the maximum stage in the outfall-closed check (Clause 5.10).
Basement drainage shall in addition be pumped to a level above both, with its own non-return valve.
5.11.5 Inspection. Gates and valves shall be inspected and operated:
- before 1 June each year;
- after every event in which they closed against a storm flow; and
- as set in the maintenance plan (Chapter 10).
Commentary. The requirement for gates below the 1% still-water level is set by this Manual. The construction details follow common coastal-drainage practice. A gate that is jammed open by debris lets the tide into the drain. A gate held shut by a sand bank turns a gravity outfall into a dead end. In Bihar the outfalls do not cross a beach, but the sluices and pumps on the outfalls through the river embankments and the town protection wall are the cities' defence against the rivers, and the rivers carry heavy silt in flood. When the Ganga and the Punpun rose in September 2026, the sluice gates on both rivers at Patna were closed and the drains connected to the Ganga blocked, and from then the city drained only through its pumping stations (as reported). In the waterlogging of September 2019, 38 of Patna's 39 sump houses were reported not working, and the State's inquiry was reported to have found that the pumps were not started on time (as reported); in 2024 the pumps of the Gosaitola station were reported to total only 143 HP (press report). The river embankments are WRD's, while the drains and sump houses behind them are PMC's or BUIDCO's, and who operates each sluice was not established during research [TBC], so a gate and the pumps behind it can belong to different bodies. The 1 June inspection date is set ahead of the SW monsoon.
5.12 Pumped outfalls
5.12.1 When required. Pumping shall be provided where gravity discharge cannot meet:
- the outfall-closed check of Clause 5.10;
- the drawdown requirement of Clause 4.7; or
- the J2 and J3 cases.
Pumping shall not be used where a gravity solution meets these requirements.
5.12.2 Capacity.
- (a) The duty pumps together, with the storage provided, shall pass every case of Clause 5.9 (including J4), demonstrated by routing.
- (b) Standby capacity at least equal to the largest duty pump shall be installed (duty + 1 standby as a minimum).
- (c) Pump capacity shall be stated at the static head for the J2 tailwater, not at mean tide.
5.12.3 Effect on the receiving water. Pumped discharge to a river, canal or creek shall be included in the river or creek level analysis of Clause 5.8. Pumping that raises the receiving water level above the acceptance criteria of Clause 5.5 elsewhere is not permitted.
5.12.4 Power supply. Pumping stations shall have either:
- two independent power supplies; or
- standby generation for 100% of the duty capacity, with on-site fuel for at least 72 hours of duty operation.
Changeover shall be automatic.
5.12.5 Flood immunity. Electrical panels, control equipment, generators and fuel storage shall be set above the higher of:
- the 1% AEP flood level + 0.5 m; and
- HAT + surge + SLA + 0.5 m.
Access to the station shall remain usable in the 1% AEP event.
5.12.6 Discharge arrangement. Rising mains shall discharge:
- over a level above the J2 tailwater; or
- through a non-return valve and a flap gate.
The arrangement shall prevent back-siphoning.
5.12.7 Controls and monitoring. Each station shall have:
- automatic level control;
- remote alarms for high level, pump failure and power failure, sent to the operator; and
- a level and run-time log kept for at least 5 years.
Wet wells shall be sized to keep pump starts within the manufacturer's limits.
5.12.8 Screens. Inlet screens shall be provided with a cleaning method that works during a storm (a mechanical rake, or duplicate screens).
5.12.9 Testing. Every pumped outfall shall be test-run at full duty, including on standby power, before 1 June each year. Private pumped systems shall be covered by a registered maintenance declaration (Chapter 10).
Commentary. Duty + standby, 72 hours of fuel and flood-immune electrics have no single direct precedent and are set by this Manual. The 72-hour fuel figure matches the longest mandatory design storm (Clause 2.5.2). A pump station that depends only on grid power can stop exactly when it is needed, because supply to flooded areas is often switched off for safety. Singapore's April 2025 amendments added annual maintenance declarations for pumped detention tanks (PUB Addendum No. 3). Clause 5.12.9 and Chapter 10 adopt the same approach. Clause 5.12.3 prevents pumping that simply moves water from one tide-locked drain into a tide-locked river.
5.13 Sand-bar closure of river mouths
5.13.1 Where it applies. This clause applies to outfalls into any river or creek whose mouth is subject to seasonal sand-bar closure. That includes the mouths of the coastal States (there is none in Bihar: Clause 5.1.4), and any other mouth listed in Annex 5B.
5.13.2 Assumption at the start of the SW monsoon. The mouth shall be assumed closed by a bar at the start of the June–September season, at the crest level of the most recent pre-monsoon survey. This applies unless WRD certifies that:
- a mouth-maintenance programme (dredging, bar cutting or training walls) has kept the mouth open at the start of each of the previous three SW monsoon seasons; and
- the programme is funded for the current season.
5.13.3 Tailwater with a closed mouth. With the mouth closed, the tailwater at the outfall shall be the higher of:
- (a) the tidal tailwater of Clause 5.7; and
- (b) the level in the river reach behind the bar, computed with the bar as a weir at its surveyed crest level. That level shall include the river flow of Clause 5.8 and the head needed to pass the flow over or through the bar.
5.13.4 No credit for emergency cutting. Bar cutting or breaching during the storm shall not be assumed in design, unless WRD has a documented operating procedure, with equipment stationed for it. Where it does, the bar may be assumed lowered to the procedure's target level only after the time the procedure states.
5.13.5 Outfall-closed check. Where the closed-mouth level of 5.13.3(b) exceeds the outfall invert for longer than the default lock windows, the lock duration of Clause 5.10 shall be extended to that period.
Commentary. Bihar has no coast and no river mouth, so Clause 5.13 does not apply in the State (Clause 5.1.4). Its nearest inland counterparts are silt and the chaurs, mauns and tals. Silt deposited by a river in flood at a drain's outfall can hold a flap gate shut or open, and a chaur or tal whose outlet is uncontrolled or obstructed limits what can leave the drains that end in it: Kabartal drains through the Bagras maun to the Burhi Gandak (Ramsar Information Sheet, 2020), and the Mokama group of tals, about 1,062 km², stays waterlogged for part of each year (as reported). No outflow control for either was found during research [TBC]. Clause 5.8.5 deals with both by giving no credit for a gate operation or a storage that the operator's records do not show. Clause 5.13.2 has no direct precedent. It puts the burden of proof on showing that the mouth is open rather than assuming it.
5.14 Documentation
Every project subject to this chapter shall submit a Downstream and Tailwater Report (Form 5-1). It shall contain:
- a plan of the analysis extent showing:
- the site;
- each analysis point with its contributing catchment area and the site's percentage of it; and
- the end point and the reason it was chosen (Clause 5.3);
- the model description:
- software and version;
- the network schematic, with survey sources for the drains and crossings;
- land use and CN for off-site areas;
- any upstream detention included; and
- calibration or validation evidence where available;
- for each analysis point, AEP and duration, the existing and with-project:
- peak flow;
- time to peak;
- maximum water level and velocity; and
- duration of inundation (Clause 5.4);
- the comparison against Clause 5.5, with each failure identified and the remedy adopted;
- the tailwater derivation:
- tide-table edition and port;
- MHWS, HAT and MSL relative to chart datum;
- the datum connection to the Survey of India benchmark and the project datum;
- surge source and value;
- SLA; and
- river levels and their sources (Clauses 5.6 to 5.8);
- the joint-case table of Clause 5.9 with results;
- the outfall-closed check (Clause 5.10):
- storm and lock alignment;
- stage hydrographs; and
- the volume balance for each lock window;
- a schedule of flap gates, tide gates and non-return valves, with certified head–discharge data (Clause 5.11);
- pumped outfall design, power supply, flood immunity and controls, where provided (Clause 5.12);
- the sand-bar assumption and supporting WRD certification, where relevant (Clause 5.13); and
- inspection and maintenance requirements for Chapter 10.
Small sites under Clause 5.3.4 shall submit Form 5-2 (Simplified Downstream Statement) instead.
References (chapter)
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A, §6.3.6 and Table 6.2 (coastal tailwater; +0.3 m climate allowance). https://web.archive.org/web/2024/https://mohua.gov.in/upload/uploadfiles/files/VolumeI-Part%20A-Engineering-Design.pdf
- MoHUA / CPHEEO (2013). Manual on Sewerage and Sewage Treatment Systems (pumping stations).
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (5601.5, ten-percent downstream analysis). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Atlanta Regional Commission / Georgia EPD (2016). Georgia Stormwater Management Manual, Vol. 1 (Standard #8) and Vol. 2 §3.1.9. https://documents.atlantaregional.com/gastormwater/GSMM_2016%20EDITION_FINAL_V1.pdf
- MARC. The Evolution of Regional Stormwater Design Standards. https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Optimisation of urban detention (2016). Water 8(7):290. https://doi.org/10.3390/w8070290
- Colorado State University. Spatially Dependent On-Site Detention Policies (thesis). https://mountainscholar.org/bitstreams/f4dbec4e-a44f-4933-8d54-a097e741f44a/download
- Central Water Commission, Lower Ganga Division-2, Patna. Daily water level and flood forecast bulletin, 31 October 2026, 06:00 levels (warning, danger and highest flood levels of the CWC sites in Bihar; datum not stated), as posted by WRD's Flood Management Improvement Support Centre. https://www.fmiscwrdbihar.gov.in/bulletin/CWC_Bulletin.pdf
- Water Resources Department, Government of Bihar, Flood Management Improvement Support Centre. Daily Flood Information Bulletin, 31 October 2026 (issued generally from 15 June to 15 October). https://www.fmiscwrdbihar.gov.in/bulletin/Flood%20Bulletin.pdf ; https://fmiscwrdbihar.gov.in/
- Water Resources Department, Government of Bihar. Order No. 143, 6 March 2025, Implementation of Flood Plain Zoning for embanked rivers within Bihar State (in Hindi), with the correspondence on the NIH study of the Ganga from Chausa to Manihari (MoU of 3 August 2025), annexed to the supplementary affidavit of the Chief Secretary, Bihar, dated 12 January 2026, in NGT O.A. 200/2014, M.C. Mehta v. Union of India. https://www.greentribunal.gov.in/sites/default/files/news_updates/Supplementary%20affidavit%20on%20behalf%20of%20the%20Chief%20Secretary,%20State%20of%20Bihar%20in%20OA%20No.%20200%20of%202014%20(M%20C%20MEHTA%20Vs.%20UNION%20OF%20INDIA%20and%20Ors).pdf
- Comptroller and Auditor General of India. Audit Report (Performance and Compliance Audit) for the year ended March 2020, Government of Bihar, Chapter III, para 3.1, Development of Sewerage Infrastructure in Patna under Namami Gange Programme (report number and tabling date not confirmed). https://cag.gov.in/uploads/download_audit_report/2020/05-%20Report%20No-5%20-English%20-%20Chapter%20-%203-06244310a0bd463.62428332.pdf
- Bihar Municipal Act, 2007, ss.193, 195 and 196. https://www.ielrc.org/content/e0715.pdf
- Bihar State Water and Sewage Board (Repeal) Act, 2017 (Bihar Act 3 of 2018), Bihar Gazette (Extraordinary) No. 311, 5 April 2018. https://faolex.fao.org/docs/pdf/ind198266.pdf
- Bihar Ease of Doing Business Act, 2026 (Act No. 32 of 2026), Bihar Gazette (Extraordinary) No. 1120, 16 September 2026, Schedule V. https://prsindia.org/files/bills_acts/acts_states/bihar/2026/Act32of2026BR.pdf
- Bihar Irrigation Act, 1997 (offences relating to embankments and irrigation works; seen only in legal-database extracts).
- Central Water Commission (1987). Flood Estimation Report for Sone Subzone 1(d), S/15/1987 (the Punpun and the Phalgu among the subzone's rivers).
- India Meteorological Department (2011). Climate of Bihar, Climatological Summaries of States Series No. 18, Table VII (storms and depressions, 1891–2010). https://mausam.imd.gov.in/patna/mcdata/climateofbihar.pdf ; and Extremes of Temperature and Rainfall for Indian Stations (up to 2012), Bihar pages (Patna (A), 20 September 1967). https://imdpune.gov.in/library/public/EXTREMES%20OF%20TEMPERATURE%20and%20RAINFALL%20upto%202012.pdf
- Ramsar Convention (2020). Ramsar Information Sheet: Kabartal Wetland, site 2436 (designated 21 July 2020; 18 interconnected wetlands; drainage through the Bagras maun to the Burhi Gandak). https://rsis.ramsar.org/RISapp/files/RISrep/IN2436RIS_2010_en.pdf
- Lok Sabha. Statement on the Patna flood of August 1975, 16 January 1976 (seen only as an extract; text partly illegible). https://eparlib.sansad.in/bitstream/123456789/857276/1/05_XV_16-01-1976_p57_p59_PII.pdf
- Rajya Sabha. Reply of 27 November 2024 on drainage pumping stations ("56 permanent Drainage Pumping Stations and 28 Temporary"; seen only as an extract; scope unclear).
- Talab Bachao Abhiyan v. Government of Bihar, application to the National Green Tribunal (Eastern Zone), 2025 (Darbhanga storm water drainage and canal-lining projects; allegations of the applicant). https://www.greentribunal.gov.in/sites/default/files/news_updates/1755167303.pdf
- Press reports on the Ganga at Gandhi Ghat above its highest flood level on 5 September 2026 (PTI via ThePrint), https://theprint.in/india/ganga-water-level-breaches-highest-flood-mark-at-patnas-gandhi-ghat-amid-heavy-rain/3034353/ , and on 6 September 2026 (DT Next), https://www.dtnext.in/news/national/bihar-downstream-areas-on-alert-as-ganga-water-level-rises-in-patna-19-lakh-affected-by-floods ; on the closing of the sluice gates on the Ganga and the Punpun and the drainage pumping stations of Patna (Patna Press, 2025–2026), including the Saidpur nala, https://patnapress.com/?p=63534 ; on the Patna waterlogging inquiry of 2019 (Business Standard/ANI, 14 October 2019), https://business-standard.com/article/news-ani/show-cause-notices-served-to-officials-responsible-for-patna-water-logging-says-chief-secretary-119101401451_1.html ; on the sump houses of Patna in 2019 (The Wire, Millennium Post); on the Patna town protection wall (Al Jazeera, 2016); and on the Kosi breach at Kusaha of 18 August 2008 (Down To Earth; Business Standard/IANS, 2 August 2014).
- Survey of India. Tidal Predictions: Geodetic and Research Branch. https://www.geographyandyou.com/survey-of-india/tidal-predictions-geodetic-and-research-branch-survey-of-india
- GLOSS. India national report (tide-gauge network and datums). https://gloss-sealevel.org/gloss/gloss/sites/gloss/files/publications/documents/india_ge9.pdf
- Adani Ports (2025). Tide Table 2025, Dahej (notes on NHO INP-12 coverage and data sources). https://www.adaniports.com/-/media/Project/Ports/PortsAndTerminals/Dahej-Port/Marine-Documents/Tide-Table-2025-Dahej.pdf
- INCOIS. Storm-surge and swell-surge warning services. https://incois.gov.in/
- FHWA. HEC-22 Urban Drainage Design Manual (current edition), Table 7.3 (coincident frequencies).
- Purdue University JTRP (2023). Development of a Multiple Water Course Joint Probability Analysis Procedure for Indiana Watersheds, FHWA/IN/JTRP-2023/09. https://docs.lib.purdue.edu/jtrp/1820
- PUB Singapore (2025). Code of Practice on Surface Water Drainage, 7th ed., Addendum No. 3. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
Annexes and forms
| Annex / Form | Content |
|---|---|
| 5A | Tidal datums (MSL, MHWS, HAT vs CD and Survey of India datum), surge allowances and 1% still-water levels by coastal segment |
| 5B | Major drains, riverine outfall reaches, and river mouths subject to sand-bar closure; map |
| 5C | Worked example: outfall-closed check for a site in south Patna behind the Punpun |
| Form 5-1 | Downstream and Tailwater Report |
| Form 5-2 | Simplified Downstream Statement (small sites) |
Commentary. The drains of Bihar's large cities fail in places that site design does not see, because almost every one of those cities stands on a river that decides when its drains can discharge. Patna is "surrounded on three sides by rivers – The Ganga, Sone, and Punpun" (CAG, 2020); its drains discharge to the Ganga and the Punpun through sluices that are closed when the rivers rise, and from then the city drains only through its drainage pumping stations, the sump houses (as reported). Muzaffarpur stands on the Burhi Gandak, Darbhanga on the Bagmati and the Adhwara group of rivers, Hajipur at the meeting of the Gandak and the Ganga, Bhagalpur and Munger on the Ganga, and Purnia in the basin of the Mahananda. The highest flood levels at the CWC gauges of these cities stand 0.6–3.3 m above their danger levels (CWC, 2026), and in September 2026 the Ganga at Gandhi Ghat, Patna, was reported above its highest flood level (as reported), so an outfall set below the highest flood level is closed by the river for days, not hours. The rivers of north Bihar run between about 3,606 km of embankments (WRD Order No. 143, 2025) and rise with rain that falls in Nepal. The outfalls also belong to one body while the drains above them belong to others: the embankments are WRD's, while the drains and sump houses behind them are those of PMC or BUIDCO, which took over the assets of the Bihar Rajya Jal Parshad in 2018; the split between the two is unconfirmed (Chapter 6, Clause 6.9). No document found during research sets a design river level for any outfall, and no design return period has been published for the drainage of any Bihar city. A detention basin that meets every release rate in Chapter 4 still fails if the drain below it is already full, or if the river it drains to stands above its outfall for days. This chapter makes both failure modes part of the design. Bihar has no tidal outfall, so Clause 5.1.4 says which of the chapter's coastal provisions fall away and what takes their place.