Chapter 11Basin and City Stormwater Master Plans
11.1 Purpose and scope
11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.
11.1.2 A BSMP shall:
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
- (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
- (d) reserve land for regional storage, johad and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
- (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
- (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).
11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.
11.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Basin | The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3. |
| Basin Stormwater Master Plan (BSMP) | The plan for one basin prepared under this chapter. |
| Lead Authority | The body responsible for preparing a BSMP (Clause 11.4). |
| Level of service (LoS) | The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6). |
| Flood hazard map | A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario. |
| Regional facility | A storage, conveyance or outfall work serving more than one development, identified in a BSMP. |
| Capital Improvement Programme (CIP) | The ranked, costed list of works in a BSMP (Clause 11.8.4). |
11.3 Planning unit: the basin, not the ward
11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.
11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.
11.3.3 No basin delineation has been published for any Haryana city. For the urban areas where the evidence identifies them, the basins are at least the following:
- Gurugram, Badshahpur: the catchment of Leg-III, the Badshahpur drain, from the Aravalli slopes through the city to its outfall to the Najafgarh drain, with the HUDA sub-catchments of 2017–2020, the reaches at Khandsa and Hero Honda Chowk and Leg-IV in the 1D network, its sewage interceptions mapped (Clause 8.9.5), and the level of the Najafgarh drain at the outfall as the boundary condition;
- Gurugram, Legs I and II: the catchments of Leg-I and Leg-II and the old town to their outfalls to the Najafgarh drain, with the Ghata, Chakarpur, Jharsa and Wazirabad bundhs and the water bodies inventoried by GMDA as storage in the basin in which each lies, and the inflow from the Ghata catchment in Delhi as a boundary condition;
- Faridabad, Budhiya nala: the catchment of the Budhiya (Buria) nala from the Aravalli slopes to the Yamuna, with the Badkhal and Surajkund lakes and the lines drawn around them by the Supreme Court shown, and the Yamuna level at the outfall as the boundary condition;
- Panchkula and Ambala, Ghaggar: the catchments that drain to the Ghaggar, the Kaushalya and the Tangri and their choes, with the floodplain notified under s.45 shown, releases from the Kaushalya dam and the floods from the Shivaliks as inflows, and the outfall-closed case a design case;
- Yamuna-bank towns: for Yamunanagar–Jagadhri, Karnal, Panipat and Sonipat, the catchments that drain to the Yamuna directly or through I&WRD drains such as Drain No. 2 at Panipat, with the river level at the nearest CWC gauge or at Hathnikund barrage as the boundary condition and the outfall-closed case a design case;
- Rohtak–Jhajjar waterlogged towns: for Rohtak, Jhajjar and Bahadurgarh, the catchments that drain to Outfall Drain No. 8 and on to the Dhansa regulator, with the capacity of the drain as the boundary condition, the water table as a design condition, and pumped outfalls with storage in the 1D network; and
- Najafgarh drain, Haryana part: the Haryana part of the basin of the Najafgarh drain, which takes the Sahibi below the Masani barrage, Outfall Drain No. 8 and Gurugram's master drains, prepared together with the plan for the part of the basin in Delhi, through I&WRD and Delhi's Irrigation and Flood Control Department, with agreed flows and levels at the State border at Dhansa and at the outfalls of the master drains.
Other Tier A bodies, among them Hisar, Sirsa, Kurukshetra, Kaithal, Rewari, Bhiwani and Manesar, shall define their basins in the first BSMP that covers them. Where I&WRD, CWC, the Pond Authority or a court has a high flood level, a design water level, limits notified under s.45, a protected area or a line around a lake, or an operating rule for a barrage, a dam, a regulator or a pumping station, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.
Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.
Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Haryana a single drain can pass through several hands on its way to a river or to the Najafgarh drain. The Haryana Municipal Corporation Act 1994 vests in the Corporation all public drains and all drains in, alongside or under any public street (s.193), and the land appertaining to any public tank (s.161); GMDA's "infrastructure development work" includes drainage that connects two or more sectors, and its infrastructure development plan must cover storm water drainage (GMDA Act 2017, as read from the Bill); HSVP executes the external development works of its Urban Estates, storm drains among them, as the nodal agency, and the colonizer builds the internal drains of a licensed colony (DTCP, quoting the HDRUA Act 1975); HSIIDC runs the drains of its industrial estates; I&WRD's drainage works are the channels and embankments the State keeps for flood protection, which by definition exclude "works for the removal of sewage from towns" (Canal and Drainage Act 1974, s.2(7)); and the ponds of 0.5 acre or more on public land, with their green belt and catchment, fall under the Pond Authority (Pond Authority Act 2018, s.2). Of the 644 water bodies GMDA inventoried in Gurugram district, about 60% by number are owned by the local bodies, 35% by private owners and 5% by government departments (GMDA). No rule divides the I&WRD drains from the municipal, HSVP and GMDA drains (as this Manual reads the record). The drains carry sewage across these boundaries: GMDA reported in 2020 that 51.30 MLD of untreated discharge still had to be diverted from Legs I–III, and the Najafgarh drain into which they flow runs through Delhi. This clause makes the basin the planning unit, so that one model carries each drain from its head to the river or the Najafgarh drain whoever owns each reach, and so that the interception works are tested against the capacity of the drains they tap (Chapter 8, Clause 8.9.5).
11.4 Who prepares, and when
11.4.1 Lead Authority.
- For the basins of a city with a Municipal Corporation: the Municipal Corporation (in Gurugram, MCG), in which the public drains and street drains vest (Haryana Municipal Corporation Act 1994, s.193), jointly with the metropolitan development authority where there is one (in Gurugram, GMDA; in Faridabad, FMDA; in Panchkula, PMDA), which plans and builds the drainage that connects sectors and carries it into its infrastructure development plan; either may prepare the plan as the State directs, and DTCP carries it into the development plan (Clause 11.9). Where a basin extends beyond the Corporation, the other local bodies and the authority in the basin are partners, and one BSMP covers the whole basin (Clause 11.3.1).
- No order dividing the I&WRD drains from the drains of the local bodies, GMDA, FMDA and HSVP was found; until one is made, this Manual assigns the reaches within each BSMP as follows, each body being Lead Authority for the reaches and works it owns or runs and for the parts of the CIP on them: I&WRD for the rivers, the I&WRD drains (among them Outfall Drain No. 8 and Drain No. 2), the canals, embankments, regulators and barrages, Hathnikund barrage and the Kaushalya dam, and the floodplain limits notified under s.45 of the Canal and Drainage Act 1974; the Haryana Pond and Waste Water Management Authority for the ponds under its Act, their green belts, catchments and protected areas, with the Gram Panchayat or local body that owns each pond; the Wetland Authority of Haryana for notified wetlands; the Municipal Corporation, Municipal Council or Municipal Committee for the drains and public tanks vested in it; GMDA, FMDA and PMDA for the master drains that connect sectors (in Gurugram, Legs I to IV); HSVP for the sector drains of its Urban Estates until they are handed over; the licensed colonizer for the internal drains of a colony until they are taken over; HSIIDC for the drains of its industrial estates; and PWD (B&R) and NHAI for the drains of their roads.
- In Tier B bodies: the Lead Authority is named by the Urban Local Bodies Department with DTCP. Basins draining to a common river reach or I&WRD drain may be grouped into one district-level plan.
The Haryana Pond and Waste Water Management Authority shall be consulted on every BSMP whose basin includes a pond, since a spatial or development plan that covers a pond needs its prior approval (Pond Authority Act 2018, s.17); the Wetland Authority of Haryana on every BSMP whose basin drains to a notified wetland or a Ramsar site (Sultanpur or Bhindawas); HSDMA and the district administration on every BSMP; the Haryana State Pollution Control Board on every BSMP that proposes works on a drain that carries sewage; and, for a basin that is shared with Delhi, such as that of the Najafgarh drain, Delhi's Irrigation and Flood Control Department, through I&WRD.
I&WRD shall be a partner in every BSMP that includes a river, canal or tank under its control.
11.4.2 When a BSMP is required.
- (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
- (b) A BSMP is required before:
- any regional detention or fee-in-lieu is accepted under Clause 4.13;
- a fee held under Clause 4.5.6.3 is spent; and
- a basin-specific release rate is applied under Clause 11.8.3.
- (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.
11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.
11.5 Data and surveys
11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:
Table 11.1 — Minimum data and surveys for a BSMP
| Data | Minimum requirement |
|---|---|
| Terrain | Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum |
| Drain network | Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm |
| Waterbodies | Survey of every tank, johad, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment |
| Rivers and canals | Cross-sections at no more than 200 m spacing and at every structure |
| Outfalls, rivers and I&WRD drains | The datum of every level named; outfall invert levels against the warning, danger and high flood levels of the Yamuna at the nearest CWC gauge (at Karnal a danger level of 249.5 m and a high flood level of 250.07 m in 2013; at Mawi 230.85 m and 232.75 m) and its recorded peaks, with the release records of Hathnikund barrage; for the Ghaggar, the Tangri, the Markanda and the choes, on which CWC has no flood sites, the gauge zero, danger level and highest recorded levels of the I&WRD gauges, or surveyed marks of the July 2023 flood; for outfalls to I&WRD drains, the design discharge and design water level of the drain at the outfall from I&WRD (for Outfall Drain No. 8, a capacity of 4,000 cusecs against 5,000 cusecs observed at the Dhansa regulator in 2022); for drains that reach the Najafgarh drain, its level and capacity at the outfall, agreed with Delhi's Irrigation and Flood Control Department; the limits notified under s.45 of the Canal and Drainage Act (the Ghaggar floodplain in Panchkula, drawn on a 100-year flood of 2,933.45 m³/s) and the lines around the Badkhal and Surajkund lakes under the Supreme Court's orders; and the regulators, sluices, flap gates, bundhs, barrages (Masani on the Sahibi, crest 240.00 m) and pumping stations on the outfalls, with their capacities and operating rules |
| Rainfall and levels | All available rain gauges (IMD, including its observatories at Ambala, Hisar, Karnal, Gurgaon, Rohtak, Narnaul and Bhiwani and the automatic weather stations and rain gauges reported by the Meteorological Centre Chandigarh; the district and tehsil rain gauges of the State, such as those at Gurugram, Kadipur, Harsaru, Wazirabad and Sohna; the agromet observatories of CCS Haryana Agricultural University at Hisar and of CSSRI at Karnal; the rain and river gauges of CWC and of I&WRD, including those at Hathnikund barrage and on the Ghaggar; and any gauges kept by the Municipal Corporations, GMDA, FMDA and the Smart City companies) and water-level records, including those for the July 2016 (Gurugram), August 2019 (the Yamuna at Hathnikund), August 2020 (Gurugram), July 2023 (the Ghaggar at Panchkula, Ambala and Kaithal, and the Yamuna), July 2024 (Gurugram) and September 2025 (Gurugram) events |
| Flood evidence | Surveyed flood marks and mapped flood extents from past events, including public reports |
| Land use | Existing land use and imperviousness; future land use from the statutory master plan |
| Soils and groundwater | HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones |
| Sewer interaction | Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots |
Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the khadar floodplains of the Yamuna and the Ghaggar, across the flat waterlogged plains of the Rohtak–Jhajjar–Sonipat belt, around the Najafgarh jheel depression on the Haryana side and the beds of the old bundhs of Gurugram, and around the margins of the johads, where the line of the full level decides what may be built, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The July 2016 (Gurugram), August 2019 (the Yamuna at Hathnikund), August 2020 (Gurugram), July 2023 (the Ghaggar at Panchkula, Ambala and Kaithal, and the Yamuna), July 2024 (Gurugram) and September 2025 (Gurugram) events are the best calibration data Haryana has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.
11.6 Levels of service
11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.
Table 11.2 — Minimum levels of service
| Element | Minimum level of service |
|---|---|
| Minor system | The design AEP of Chapter 6 (Table 6.1) |
| Habitable buildings | No flooding above floor level in the 1% AEP (100-yr) event |
| Critical facilities (hospitals, emergency services, substations, water and sewage plants) | No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event |
| Evacuation routes and arterial roads | Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event |
| Ponding drain time | Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event |
| Tank and johad storage | No net loss of flood storage below the MWL in the basin, measured against the earliest available survey |
| Outfalls | Functioning under the joint and outfall-closed cases of Chapter 5 |
Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been counted but not measured. In law the State's ponds are protected in several layers: the Pond Authority Act 2018 treats as a pond any tank, lake or water body of 0.5 acre or more "whether it contains water or not" that is recorded as a talab, johar or tank, with its green belt, peripheral catchment, feeder inlets, bunds and weirs, bars building on pond land, green belt or catchment and any obstruction of inflow or outflow without permission, and lets the State notify a protected area around a pond (ss.2, 14 and 16), though none was found notified, and it excludes ponds on private land and those under 0.5 acre; in a Municipal Corporation the public tanks and the land appertaining to them vest in the Corporation (HMC Act 1994, s.161); and the National Green Tribunal has ordered unique identifiers for the water bodies of Gurugram and of the State (OA 325/2015, 2018). The Pond Authority has 19,665 ponds on its data system, 18,764 rural and 901 urban (2024). The losses are visible all the same: Gurugram's water bodies fell from 641 in the revenue record of 1956 to 487 in 1976, and of the 644 that GMDA has inventoried, covering about 1,142 acres, 35% by number are privately owned (GMDA); Damdama lake near Sohna shrinks from about 80 to about 35 acres within a month of the monsoon (as reported); and the Najafgarh jheel on the Haryana side had not been notified as a wetland by March 2024 (as reported). Sultanpur (143 ha) and Bhindawas (412 ha) became Ramsar sites on 25 May 2021, but no wetland notified under the Wetlands Rules 2017 was confirmed. No survey of the storage of any johad inside a Municipal Corporation was found.
11.7 Modelling and scenarios
11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:
- the minor system;
- the major (overland) system;
- rivers, canals and tanks; and
- the outfalls.
Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.
11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.
11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.
11.7.4 Scenarios. Each BSMP shall model at least:
- (a) Existing: existing land use, network, tanks and outfalls;
- (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
- (c) Future, controlled: future land use with the site controls of Chapter 4;
- (d) Future, with plan: scenario (c) plus the works of the CIP; and
- (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Haryana with a design factor was found, and the State Action Plan on Climate Change 2.0 both projects very heavy precipitation events rising by 2.5% by mid-century under RCP 8.5 and the one-day maximum falling marginally, two findings that do not agree; the station records of 30 June 1981 at Rohtak (297.9 mm) and Gurgaon (261.2 mm), after the CWC plates were drawn, exceed the 50-year depths of those plates (IMD; this Manual's reading), which is a reason to keep the factors, not to reduce them.
11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the July 2016 (Gurugram), August 2019 (the Yamuna at Hathnikund), August 2020 (Gurugram), July 2023 (the Ghaggar at Panchkula, Ambala and Kaithal, and the Yamuna), July 2024 (Gurugram) and September 2025 (Gurugram) events where data exist.
Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and johads with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.
Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).
11.8 Options, outputs and the Capital Improvement Programme
11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:
- Protect and restore storage: johads, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
- Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
- Conveyance upgrades to drains, canals and culverts;
- Outfall works: regulators, sluices and flap gates on the outfalls to the Yamuna, the Ghaggar and the I&WRD drains, pumping stations and the storage behind them where an outfall can be closed or its capacity is short, including those at Gurugram's underpasses and on the drains of the Rohtak–Jhajjar–Sonipat belt that reach Outfall Drain No. 8, interception works that keep sewage out of the master drains without taking their storm capacity, the restoration of Gurugram's old bundhs as detention, the river embankments, and the operating rules of Hathnikund barrage, the Kaushalya dam and the regulators that set the receiving levels, agreed with I&WRD and, for the Najafgarh drain, with Delhi's Irrigation and Flood Control Department;
- Property-level protection where works cannot reach the level of service; and
- Non-structural measures: flood warning (for example IMD district rainfall warnings and nowcasts issued by the Meteorological Centre Chandigarh, CWC flood forecasts and river stages at its Yamuna sites against their warning and danger levels, notice of releases from Hathnikund barrage to the towns downstream, warnings from the I&WRD gauges on the Ghaggar, the Tangri and the Markanda, where CWC has no flood sites, and the district flood control rooms), flood-hazard zoning, emergency planning and public information.
11.8.2 Option assessment. Each option shall be assessed for:
- reduction in flood risk (buildings and people flooded; expected annual damage);
- capital and 30-year maintenance cost;
- land required;
- effect on groundwater recharge where the water table is deep and over-exploited, as under Gurugram, Faridabad, Kurukshetra, Karnal, Panipat and the south, waterlogging where it is within 3 m, as over about half of Rohtak and Jhajjar districts, and the quality of the groundwater, which is saline over much of the south, west and centre of the State, and of the drains and johads that the runoff reaches (Chapter 8);
- effect on downstream basins and the receiving river or drain; and
- who benefits.
11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.
11.8.4 Outputs. Each BSMP shall produce:
- (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
- (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
- (c) regional facility sites, with storage volumes, land needs and the sites they serve;
- (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
- (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
- (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
- (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.
Commentary. Restoring storage comes first because many of the outfalls of Haryana's towns are closed or limited in the wettest weeks. Gurugram's master drains end in the Najafgarh drain in Delhi, and reaches of the Badshahpur drain have been reported to carry far less than its drawn capacity (as reported); Outfall Drain No. 8 carried 5,000 cusecs at the Dhansa regulator against its capacity of 4,000 (I&WRD, 2022); and the Yamuna and the Ghaggar can stand above the town outfalls for days. Gurugram once held its runoff in storage: the Ghata, Chakarpur, Jharsa and Wazirabad bundhs were built in the late nineteenth century and have been made obsolete by building (Ministry of Housing and Urban Affairs, Lok Sabha, 2025, as reported), the city's water bodies numbered 641 in the revenue record of 1956, 487 on the Survey of India map of 1976 and 557 on imagery of 2011–12 (GMDA), and HARSAC found 47 ponds in and around the city dried up or filled with waste (2021). The city failed in July 2016 after about 50 mm of rain (as reported), which points to capacity and outfalls, not to an extreme storm. The storms are large for drains with no stated design basis: IMD has recorded 484.1 mm in a day at Rohtak (19 September 1933), 398.8 mm at Palwal (9 September 1875) and 282.2 mm at Gurgaon (14 July 1968), above the 50-year 24-hour depths of the CWC plates there (IMD; this Manual's reading). Conveyance upgrades on their own move water faster to an outfall that the Yamuna or the Ghaggar in flood may close, or that is limited by the capacity of its regulator, its pumping station or the receiving drain, as at the Najafgarh drain and Outfall Drain No. 8. Groundwater in Haryana calls for recharge in most of the State and forbids it in part of it. The State's stage of extraction was 135.96% in 2024, with 88 of its 143 assessment units over-exploited, and every block of Gurugram, Kaithal, Karnal, Kurukshetra and Panipat over-exploited (CGWB); the water table is deeper than 30 m under 97% of Kurukshetra district and 51% of Gurugram (HWRA, June 2023). But every block of Rohtak and Jhajjar is "safe" because the water table is near the surface: it stood within 3 m over about half of Rohtak and 43% of Jhajjar district in June 2023, and the waterlogged or prone area of the State grew from about 2.93 lakh ha in June to about 3.79 lakh ha in October (HWRA; this Manual's arithmetic); there, recharge adds to waterlogging. Quality limits recharge too: CGWB describes the groundwater of the southern, western and central districts as mostly saline, and found 18.45% of its samples above 1.5 mg/L of fluoride (2021–22). The Building Code asks for recharge on every plot of more than 500 m² without regard to depth (Code 8.1(2)), while the Water Resources Authority Act 2020 requires the Authority to prevent activities likely to lead to waterlogging (s.21(7)). This is why recharge, waterlogging and groundwater quality are all assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.
11.9 Integration with land-use planning
11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the development plans of the controlled areas prepared by DTCP under the Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Act 1963 (s.5), among them the Final Development Plan 2031 of the Gurugram–Manesar Urban Complex, the sector plans of HSVP and the layouts of colonies licensed under the Haryana Development and Regulation of Urban Areas Act 1975, and the infrastructure development plans of GMDA, FMDA and PMDA under their Acts; and, for a plan that covers a pond, with the prior approval of the Haryana Pond and Waste Water Management Authority (Pond Authority Act 2018, s.17). In particular:
- (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
- (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
- (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
- (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.
11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.
Commentary. Haryana draws its water lines by notification in one place and by court order elsewhere. The Haryana Building Code 2017 sets no setback from a drain, river or pond, and keeps only the natural drainage inlets and outlets of large projects (Code 12.1); no I&WRD rule barring construction within a set distance of a drain or canal was found. Section 45 of the Canal and Drainage Act 1974 lets the State prohibit obstructions within notified limits along a river, stream or drainage channel, and the only such notification found is the Ghaggar floodplain in Panchkula (27 October 2023), drawn on a 100-year flood of 2,933.45 m³/s; the State has told the National Green Tribunal that all construction is banned on river floodplains under that section, but no notification for the Yamuna or any other river was found. The other lines come from the courts: the Supreme Court has barred construction in the green belt and within 1 km of the Badkhal and Surajkund lakes and made plans within 1–5 km subject to the pollution control boards (1996), and has held land notified under the Punjab Land Preservation Act 1900 in the Aravallis to be forest (2018, as reported). The Pond Authority Act 2018 provides for a protected area around a pond, by notification, but none was found notified; notified wetlands carry a 50 m line from the mean high flood level (Wetlands Rules 2017), though no wetland in Haryana was confirmed notified. These are river, lake and waterbody lines, not drainage-flood lines; the hydraulic corridor and setback zones of Chapter 7 are this Manual's proposal, and where the s.45 limits or a court line bind and are wider, they apply. A BSMP gives the development plans the 1% AEP drainage-flood map, and the buffer widths of Chapter 7, that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because the Haryana Building Code 2017 already requires, for projects of 5,000–20,000 m² built-up, that the inlet and outlet points of the natural drainage be kept with a channel of adequate size and that at least 20% of the recreational open space be left unpaved, with one recharge bore per 5,000 m² (Code 12.1), and makes groundwater recharge mandatory for parks, parking, plazas, playgrounds and other common areas (Code 8.1(2)(ii)), but sets no detention or pervious-area rule; storage placed in a layout's open space builds on these duties, and because that land still serves as open space, the storage must stay usable as one. Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.
11.10 Consultation and publication
11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.
11.10.2 After approval, the following shall be published as open data:
- the model files;
- the flood hazard maps;
- the data of Clause 11.5.1, except security-sensitive asset details; and
- the CIP.
They shall also be shown on a public map viewer.
Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.
11.11 Approval, review and reporting
11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.
11.11.2 Review. Each BSMP shall be reviewed:
- every 10 years;
- within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
- when the statutory land-use plan is revised.
11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each SW monsoon (by 15 June). The report shall show:
- CIP progress;
- the fee-in-lieu ledger (Clause 4.13.4);
- maintenance completed; and
- any flooding against the levels of service.
11.12 Interim arrangements
11.12.1 Until a BSMP is approved for a basin:
- (a) all site criteria of Chapters 4 to 8 apply in full;
- (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
- (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
- (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.
References (chapter)
- Central Ground Water Board. Dynamic Ground Water Resources of India, 2024: Haryana (stage of extraction and categories). https://cgwb.gov.in/cgwbpnm/public/uploads/documents/1742295665450434455file.pdf
- Central Ground Water Board. Ground Water Year Book Haryana 2021-22 (depth to water and quality; Wayback copy). https://www.cgwb.gov.in/old_website/Regions/NWR/Reports/GWYB%20Haryana%202021-22.pdf
- Haryana Water Resources (Conservation, Regulation and Management) Authority. Haryana Water Resources Atlas 2025 (depth to water classes, June and October 2023). https://hwra.org.in/Atlas2025/files/basic-html/page61.html
- Defra (2010). Surface Water Management Plan Technical Guidance. Department for Environment, Food and Rural Affairs, London.
- Mile High Flood District (Denver). Master planning programme and Urban Storm Drainage Criteria Manual.
- Mid-America Regional Council (2025). APWA Stormwater Standards Supplement; KC Metro APWA Section 5600, Version 2025.01.
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- Gurugram Metropolitan Development Authority. Revised report in OA 523/2019, Vaishali Rana Chandra v. Union of India, before the National Green Tribunal, with DTCP's drawing "Master Storm Water Drainage, G.M.U.C. 2031 A.D." (No. DTP(G) 2104/2012 of 9 November 2012) and HUDA's catchment management plan for the Badshahpur drain (3 November 2017, revision 2 of 24 November 2020). https://www.greentribunal.gov.in/sites/default/files/news_updates/REVISED%20REPORT%20BY%20GURUGRAM%20METROPOLITAN%20DEVELOPMENT%20AUTHORITY,%20GURUGRAM%20IN%20OA%20NO.%20523%20of%202019%20(Vaishali%20Rana%20Chandra%20vs%20UOI).pdf
- Gurugram Metropolitan Development Authority. Compliance report on water bodies in OA 325/2015, Lt. Col. Sarvadaman Singh Oberoi v. Union of India, before the National Green Tribunal (water-body counts and inventory; the Ghata bundh). https://www.greentribunal.gov.in/sites/default/files/all_documents/GMDA-Compliance%20Report%20In%20O.A.%20No.%20325%20of%202015.pdf
- Gurugram Metropolitan Development Authority (2020). Status report of 2 October 2020 in OA 454/2018, Subhash Gupta v. Union of India, before the National Green Tribunal (sewage in Legs I–III). https://www.greentribunal.gov.in/sites/default/files/news_updates/STATUS%20REPORT%20in%20OA%20454%20Of%202018%20(Subhash%20Gupta%20&%20Ors.%20VS.%20Union%20Of%20India%20&%20Ors.).pdf
- Gurugram Metropolitan Development Authority Bill 2017 (Bill No. 36-HLA of 2017; enacted as Haryana Act 34 of 2017), definitions and section 17. https://prsindia.org/files/bills_acts/bills_states/haryana/2017/Haryana%20Bill%20No.%2036%20of%202017.pdf
- Haryana Municipal Corporation Act 1994 (Act 16 of 1994), sections 161 and 193 (PRS copy). https://prsindia.org/files/bills_acts/acts_states/haryana/1994/1994Haryana16.pdf
- Haryana Canal and Drainage Act 1974 (Act 29 of 1974), sections 2(7) and 45 (PRS copy). https://prsindia.org/files/bills_acts/acts_states/haryana/1974/1974HR29.pdf
- Haryana Pond and Waste Water Management Authority Act 2018 (Act 33 of 2018), sections 2, 14, 16 and 17; and the Authority's written statement of 21 February 2024 in OA 573/2023 before the National Green Tribunal (19,665 ponds). https://www.greentribunal.gov.in/sites/default/files/news_updates/WRITTEN%20STATEMENT%20ON%20BEHALF%20OF%20R-5%20MS,%20HARYANA%20POND%20AND%20WASTE%20WATER%20MANAGEMENT%20AUTHORITY%20IN%20OA%20NO.%20573%20of%202023%20PRAKASH%20YADAV%20VS%20STATE%20OF%20HARYANA.pdf
- Haryana Water Resources (Conservation, Regulation and Management) Authority Act 2020 (Act 29 of 2020, as amended), section 21. https://hwra.org.in/Content/Images/The%20Haryana%20Water%20Resources%20(Conservation,%20Regulation%20and%20Management)%20Authority,%20Act%202020%20as%20Amendment%20Uptodate.pdf
- Irrigation and Water Resources Department, Haryana. Replies in OA 421/2022, Ranvir Singh v. State of Haryana (the Ghaggar floodplain zone under s.45; 100-year flood of 2,933.45 m³/s). https://www.greentribunal.gov.in/sites/default/files/news_updates/REPLY%20BY%20IRRIGATION%20AND%20WATER%20RESOURCE%20DEPARTMENT,%20HARYANA%20IN%20OA%20NO.%20421%20of%202022%20RANVIR%20SINGH%20VS%20STATE%20OF%20HARYANA.pdf
- Irrigation and Water Resources Department, Haryana. Committee report in OA 627/2022, Prakash Yadav v. State of Haryana, filed 7 February 2024 (Sahibi, Masani barrage, Outfall Drain No. 8). https://www.greentribunal.gov.in/sites/default/files/news_updates/REPORT%20BY%20IRRIGATION%20AND%20WATER%20RESOURCES%20DEPT,%20HARYANA%20IN%20OA%20627%20of%202022%20(PRAKASH%20YADAV%20VS.%20STATE%20OF%20HARYANA%20&%20ORS.%20).pdf
- Haryana State Wetland Authority (2022). Action taken report of 18 August 2022 in EA 16/2019 in OA 153/2014 before the National Green Tribunal (Najafgarh jheel; the Tribunal's order of 21 January 2022). https://www.greentribunal.gov.in/sites/default/files/news_updates/REPORT%20BY%20HARYANA%20STATE%20WETLAND%20AUTHORITY%20IN%20EA%20NO.%2016%20of%202019%20IN%20OA%20NO.%20153%20of%202014%20(Indian%20National%20Trust%20for%20Art%20and%20Cultural%20Heritage%20Versus%20Govt.%20of%20NCT%20of%20Delhi%20&%20Ors.).PDF
- Haryana Space Applications Centre (2021). Scientific Action Plan for Gurugram, Report No. 06 (ponds in and around the city). https://hsac.org.in/jal/Notification/Gurugram.pdf
- National Capital Region Planning Board (2016). Functional Plan on Drainage for NCR. https://ncrpb.nic.in/pdf_files/FunctionalPlanondriangeforNCR.pdf
- Government of Haryana, Town and Country Planning Department. Sub-Regional Plan for Haryana Sub-Region of NCR-2021, Chapter 9 (Wayback copy). http://web.archive.org/web/20140806083003id_/http://tcpharyana.gov.in/ncrpb/FINAL%20SRP%20FOR%20WEB-HOSTING/09_Sewerage,%20SWM,%20Drainage%20&%20Irrigation.pdf
- Government of Haryana, Town and Country Planning Department (2017). The Haryana Building Code, 2017, Codes 8.1 and 12.1 (Wayback copy). http://web.archive.org/web/20170714152920id_/https://tcpharyana.gov.in/Notifications_Judgements/The_Haryana_Building_Code_2017.pdf
- Supreme Court of India. M.C. Mehta v. Union of India (Badkhal and Surajkund Lakes), I.A. 29 in W.P. (C) 4677 of 1985, order of 11 October 1996. https://elaw.org/es/system/files/attachments/publicresource/wp4677of1985ddOct11of1996.pdf
- Ministry of Environment, Forest and Climate Change (2017). Wetlands (Conservation and Management) Rules, 2017, rule 4(2)(vi).
- Government of Haryana (n.d.). Haryana State Action Plan on Climate Change 2.0 (projections of rainfall extremes, 2021–2050). https://napccindia.moef.gov.in/resources/pdfs/haryana-sapcc-2.0.pdf
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012) (Haryana stations), and Climate of Haryana and Union Territories of Delhi and Chandigarh (1991). https://imdpune.gov.in/library/public/EXTREMES%20OF%20TEMPERATURE%20and%20RAINFALL%20upto%202012.pdf
- The Tribune, Swarajya, Down To Earth and the Rajya Sabha (2021–2026). Reports of GMDA's fourth master drain and drainage-plan consultancy, FMDA's desilting, the Lok Sabha reply on Gurugram's bundhs (2025), Damdama lake, the Najafgarh jheel and the Ramsar sites of Haryana (secondary sources; addresses not retained).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 11A | BSMP terms of reference template |
| 11B | Basin lists and boundaries for Tier A bodies |
| 11C | Depth–damage curves for Haryana building types |
| 11D | BSMP data and model publication standard |
| Form 11-1 | Annual implementation report |
Commentary. Haryana's cities are spending on their drains, but no city drainage master plan with a design standard has been published. Gurugram's master drains were laid out in DTCP's "Master Storm Water Drainage, G.M.U.C. 2031" drawing (No. DTP(G) 2104/2012 of 9 November 2012), which takes Legs I, II and III (the Badshahpur drain) to the Najafgarh drain with discharges of 541, 1,305 and 3,702 cusecs, and HUDA's catchment management plan for the Badshahpur drain (3 November 2017, revised 24 November 2020) divides its catchment into zones of 792 to 12,200 ha, gives reach discharges of up to 2,300 cusecs and proposes check dams on the creeks and recharge wells along the drain (GMDA, report to the National Green Tribunal); GMDA began a fourth master drain whose design IIT Roorkee was reported to have approved, and in 2024 sought a consultant for a drainage plan of the city (as reported). None of these states a return period or a rainfall intensity. In Faridabad, FMDA desilts eight storm drains of about 30 km, among them the Budhiya nala (as reported), but no FMDA drainage plan or design norm was found. In Panchkula, I&WRD notified the floodplain of the Ghaggar under s.45 of the Canal and Drainage Act on 27 October 2023, drawn on a 100-year flood of 2,933.45 m³/s computed by Gumbel's method from 54 years of data, though the National Green Tribunal has questioned whether the procedure was followed (2024). The older regional norms are history, not a design basis: the NCR Planning Board's Functional Plan on Drainage for NCR (2016) reports Haryana's urban channels as designed for 25 mm/h with a runoff coefficient of 1/8 and proposed 5-year and 10-year storms for urban drains, and the Sub-Regional Plan for the Haryana sub-region of NCR (2021) sizes rural drains for a 5-year, 3-day rainfall drained in 3 days and says that "first master plan of drain should be prepared and only then drains should be provided". Gurugram's master drains and Outfall Drain No. 8 from the Rohtak–Jhajjar belt all end in the Najafgarh drain, which runs through Delhi to the Yamuna, so the basin is shared between two governments, and the National Green Tribunal has asked an expert group to examine the flow through the Najafgarh drain and the "unwanted submergence of land areas" around the Najafgarh jheel (OA 153/2014, 2022). No published document sets a design return period for the storm drain network of any Haryana city; the only design floods found are the Ghaggar's 100-year flood in Panchkula and the capacities of Gurugram's master drains, without a stated return period. This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by DTCP, HSVP, the Urban Local Bodies Department, any Municipal Corporation, GMDA, FMDA, PMDA, I&WRD or any other body. A site-level manual cannot fix basin-level problems: lost tank storage, town drains that outfall to the Yamuna and the Ghaggar when the rivers are high, Gurugram's master drains that reach the Najafgarh drain in Delhi through narrow reaches, flat drains of the waterlogged Rohtak–Jhajjar–Sonipat belt that reach Outfall Drain No. 8 only as fast as its capacity allows, johads and bundhs filled or cut off by building, storm drains that carry sewage, single drains split between a Municipal Corporation, GMDA or FMDA, HSVP, licensed colonizers, HSIIDC and I&WRD, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:
This chapter adapts that method to Haryana: to town outfalls on the Yamuna, which releases from Hathnikund barrage can hold high for days, and on the Ghaggar and its Shivalik choes, on which CWC has no flood sites; to Gurugram's master drains and Outfall Drain No. 8, which end in the Najafgarh drain in Delhi, so that the State's largest drainage basin is shared with another government; to the waterlogged Rohtak–Jhajjar–Sonipat belt, where the water table is within 3 m of the surface and drainage depends on the capacity of the I&WRD drains and on pumping; to drains that carry sewage, as Gurugram's master drains and Faridabad's Budhiya nala do; to drains vested in the Municipal Corporations, master drains of GMDA and FMDA, sector drains of HSVP, internal drains of licensed colonies, drains and floodplains held by I&WRD, and ponds under the Pond Authority Act 2018, without an order that divides the drains between them; to a State whose only notified floodplain line is the Ghaggar's at Panchkula, and whose other lines around lakes and the Aravallis have been drawn by the courts; to a State with no published design return period for the drains of any city; to aquifers over-exploited across most of the State but standing near the surface in the Rohtak–Jhajjar belt; and to a south-west monsoon whose recorded days far exceed the 50-year depths of the CWC plates, 484.1 mm at Rohtak on 19 September 1933 and 398.8 mm at Palwal on 9 September 1875 (IMD).