Chapter 4Site Runoff Control: Retention and Detention


4.1 Purpose and scope

4.1.1 This chapter sets the performance standard that every regulated development shall meet for runoff leaving the site. It covers:

  • (a) the order in which runoff-control measures are to be applied (Clause 4.3);
  • (b) retention of frequent rainfall, and how retained volume is credited against detention (Clause 4.4);
  • (c) release-rate criteria for standard and flood-sensitive catchments (Clause 4.5);
  • (d) the procedure for sizing detention storage and outlets (Clauses 4.6 to 4.9);
  • (e) facility types, rainwater harvesting (RWH) accounting, and high-groundwater sites (Clauses 4.10 to 4.12);
  • (f) regional detention and fee-in-lieu (Clause 4.13);
  • (g) simplified methods for small sites: the Tier B tables and the fixed-coefficient route (Clause 4.14); and
  • (h) public safety (Clause 4.15).

4.1.2 This chapter applies to land disturbance of 0.1 ha or more, or new or replaced impervious area of 500 m² or more, as set in Chapter 1. Single dwellings below that threshold, and road resurfacing that adds no impervious area, are exempt. The existing RWH mandate of the building rules (roof rainwater harvesting by the owner where the rooftop is 100 m² or more, in the areas that the Competent Authority notifies, and groundwater recharge for every building on a plot of more than 500 m², with no occupation certificate until the system is built and certified functional, under Code 8.1 of the Haryana Building Code 2017; and at least one recharge bore for every 5,000 m² of built-up area for buildings of 5,000–20,000 m² under Code 12.1; the rules are discussed in the Commentary to Clause 4.11) continues to apply to every building it covers, whether or not this chapter applies.

4.1.3 Rainfall inputs come from Chapter 2. Hydrologic methods come from Chapter 3. Tailwater, downstream analysis and the outfall-closed check come from Chapter 5. Water quality volume (WQv) treatment comes from Chapter 8. Where this chapter and those chapters overlap, the more stringent requirement governs.

Commentary. No Indian national rule or Haryana rule found during research for this Manual limits the rate of discharge from a site, and none requires on-site detention or "zero run-off". Haryana has one building code for the whole State, the Haryana Building Code 2017, issued by the Town and Country Planning Department with memo No. Misc-138-A-Loose/7/5/2006-2TCP dated 7 March 2017 and applicable to the entire State from 6 January 2017 (Code 1.1(2)); it replaced the Haryana Building Code 2016, which had applied from 30 June 2016. It is a departmental code, not a notification in the Gazette under an Act: each Competent Authority, whether DTCP, HSVP, a municipal body or HSIIDC, applies it under its own Act (Code 1.2(1)(ii)), and it is amended by further memos, of which those of 27 May 2020 and 19 January 2022 were read; amendments of 8 December 2025 (occupation certificates) and 5 June 2026 (charging of electric vehicles) and a proposal of November 2026 on purchasable FAR are reported, none of them touching rainwater harvesting, the plinth or basements (as reported [TBC]). Its drainage provisions protect the building and the drain, not the catchment. The site plan shows the existing drains (Code 3.2); the building plan shows "the method of disposal of waste water, sewage, storm water" (Code 3.4(2)(vi)); the plinth is to be "so located … that proper drainage of the site is assured", at 450 mm to 1.5 m (Code 7.3); rainwater harvesting and recharge are required by Code 8.1 (Commentary to Clause 4.11); and for buildings of 5,000–20,000 m² of built-up area the environmental conditions of Code 12.1 require that "The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water", that at least one recharge bore be provided for every 5,000 m² of built-up area, and that "The unpaved area shall be more than or equal to 20% of the recreational open spaces". Its rule of "zero waste water discharge" (Code 11.7) concerns sewage, not storm water. None of these sets a design storm, a release rate, a storage volume or an overflow path, and the Code sets no setback from a drain, nala, canal, pond or river. The Haryana Municipal Corporation Act 1994 allows no premises to be erected or occupied until a drain is made "of such size, materials, and with such fall" as the Commissioner thinks necessary "for the effectual drainage", emptying into a Corporation drain within thirty metres (section 198), forbids any building on a municipal drain without written permission (section 206) and any direct connection to a storm water overflow drain (section 196); none of these sets a design standard either. No instruction of I&WRD forbidding construction within a stated distance of a drain or canal was found. The lines that do exist come from a statute and the courts: the floodplain zone of the Ghaggar in Panchkula, notified on 27 October 2023 under section 45 of the Haryana Canal and Drainage Act 1974, within which any obstruction is prohibited; the pond land, green belt and catchment of every public pond of 0.5 acre or more, on which no structure may be built and no inflow or outflow obstructed without the permission of the Haryana Pond and Waste Water Management Authority (Act 33 of 2018, sections 2(k) and 14); and the green belt round the Badkhal and Surajkund lakes at Faridabad, with no construction within 1 km of them and prior approval of the Central and State Pollution Control Boards for all plans within 1–5 km (Supreme Court, M.C. Mehta, order of 11 October 1996). The hydraulic corridor of Chapter 7, with its Zone 1 floor of at least 15 m, and the setback zones of that chapter are this Manual's proposal; the section 45 floodplain, the pond land and the court lines apply where they bind and are wider. The design norms in use are history, to be replaced. The NCR Planning Board reports that "The intensity of rainfall adopted is 25mm per hour and run off coefficient is 1/8 for designing of storm water drainage channels in Haryana urban area", which is about 9 L/s per hectare (by NEER's arithmetic), and that the rural drains were sized by the Boston Society formula, Q = 200·√A (cusecs, A in square miles), cut by reduction factors of 1/12 to 1/4 "on the premise that relatively smaller sections gave better hydraulic performance" (NCR Planning Board, Functional Plan on Drainage for NCR, 2016, §5.2.2); the Sub-Regional Plan for the Haryana Sub-Region of the NCR sizes rural drains for "three days rainfall of five years frequency to be drained in three days" and leaves urban drains to the CPHEEO manual; and the master drains of Gurugram have design discharges but no stated return period (Commentary to Clause 4.5). This Manual uses none of these. Basements are regulated, but not for flooding. The roof of a basement may stand 0.9–1.5 m above the average surrounding ground on plots of up to 1,000 m², the open area beside it is to be "effectively drained", and "The responsibility of draining a basement storey and for protecting it from rain shall be that of the owner" (Code 7.16(5)); no rule on the level of a basement ramp or opening, or on basements in low-lying or flood-prone land, was found, and no order on basement flooding in Haryana after 2024 was found [TBC]. In Gurugram, where "Within half an hour of rain, the entire city was waterlogged" on 19 August 2020 (as reported) and the roads become flow paths, a basement whose ramp starts at road level takes the flood first. This Manual therefore adds its own requirements for every basement: no detention storage in a habitable basement (Clause 4.10.1); the crest of every basement ramp and the sill of every basement opening at least 0.5 m above the 1% AEP flood level, with basement drainage pumped to the surface drain through a non-return valve (Clauses 6.11.1 and 6.11.4); and no basement in Zone 2 (Clause 7.5.2). In the flood-sensitive catchments of Clause 4.5.3.2 and in any catchment notified under Clause 4.5.4, it recommends that no basement be permitted where the 1% AEP flood level stands 0.45 m or more above the road in front, because the plinth rule of Code 7.3 then leaves the ground floor and every opening at plinth level below the flood; and in the Rohtak–Jhajjar–Sonipat belt and on the floodplains, where the water table is within 3 m of the surface, that a basement be permitted only as a watertight structure checked against flotation at the design groundwater level (Clauses 4.12.1 and 4.12.3). These are the Manual's proposals, not rules of the Code. This chapter is written so that it can supply, as a technical companion to the Code and the municipal Acts, the sizing for the storm-water disposal that Code 3.4(2)(vi) already requires to be shown on the plans, and the channel size that Code 12.1 leaves open; it has not been adopted for either purpose. In practice the storm drains carry sewage. In 2023 the BOD of Leg-I, Leg-II and Leg-III averaged 48, 63 and 44 mg/l and that of the Budhiya nala 76 mg/l (State of Haryana report in NGT E.A. 35/2023), against the condition of not more than 30 mg/l on which the Gurugram drains may outfall to the Najafgarh drain (GMDA status report in NGT O.A. 454/2018), and the dry-season flow of Leg-III averaged 126.53 cusecs in 2021 (Haryana Vidhan Sabha, starred question 1397, 2022), although the Canal and Drainage Act excludes "works for the removal of sewage from towns" from its drainage works (section 2(7)) and the Municipal Corporation Act forbids foul water in a drain provided for surface water (section 196). Clause 8.9 deals with that dry-weather flow. Retention and detention apply in full on every site whatever the drain carries: every litre a site releases at the peak of a storm takes up capacity in a drain that is already part-filled with sewage. The CPHEEO (2019) manual describes limiting outflow to the pre-development peak as typical practice, but it uses no "shall" and names no storm frequencies (CPHEEO Part A §8.5.1). This chapter turns that description into a development-control requirement.


4.2 Definitions

Term Meaning in this Manual
Retention Permanent removal of runoff from the surface drainage system by infiltration, evapotranspiration or reuse, so that the water never reaches the outfall.
Retention depth The 90th percentile wet-day 24-hour rainfall depth for the site's zone (Clause 2.10, Annex 2E).
Required retention volume (RRV) The runoff volume from the retention depth over the post-development site (Clause 4.4.2).
Detention Temporary storage of runoff, released through a controlled outlet at a rate set by Clause 4.5.
Retention credit The reduction in required detention storage that results from retention practices, determined by routing under Clause 4.4.6. It is not the same as the retained volume.
Permissible site discharge (PSD) The maximum rate at which a site may discharge for a stated AEP, in L/s or L/s/ha.
Site storage requirement (SSR) The detention storage required per hectare of site under the simplified method of Clause 4.14.
Multi-stage outlet An outlet structure with separate openings at different levels, each controlling a different AEP (Figure 4.2).
Drawdown time Time from the peak stored volume until the stated fraction of that volume has been released.
Emergency spillway A secondary overflow that passes flows above the primary outlet capacity, or all flow when the primary outlet is blocked, without overtopping the embankment.
Freeboard Vertical distance between the maximum design water level and the embankment crest or other critical level.
Flood-sensitive catchment A catchment listed in Clause 4.5.3 or notified under Clause 4.5.4.
Authority The approving authority under Chapter 1 (the Competent Authority that applies the Haryana Building Code 2017 under its own Act (Code 1.2): DTCP for licensed colonies and controlled areas, HSVP in its Urban Estates, the Municipal Corporation, Municipal Council or Municipal Committee in its area, HSIIDC in its industrial estates, and GMDA, FMDA or PMDA where it grants the approval [TBC], as applicable).
Tier A / Tier B Adoption tiers defined in Chapter 1. Tier A: the Municipal Corporation of Gurugram (MCG), and GMDA and every other approving authority within the Gurugram Metropolitan Area; every other Municipal Corporation constituted under the Haryana Municipal Corporation Act 1994, among them those of Faridabad and Manesar, with every other approving authority within its limits; the Faridabad and Panchkula Metropolitan Development Authorities (FMDA and PMDA), and any metropolitan development authority constituted later by an Act of the State, with every approving authority within its notified area; and, wherever they lie, HSVP in its Urban Estates and DTCP for the colonies it licenses. Tier B: Municipal Councils and Municipal Committees.

4.3 Order of measures

4.3.1 Every site runoff-control design shall apply measures in the following order, and shall document in the submittal why each earlier step could not do more:

  1. Preserve. Keep existing waterbodies, johads, natural drainage lines, wetlands, and permeable soils and vegetation. Avoid fill in flood storage (Chapter 7).
  2. Retain. Retain the RRV on site by infiltration, reuse or evapotranspiration (Clause 4.4).
  3. Detain. Detain the remaining runoff so that the release-rate criteria of Clause 4.5 are met for every design storm and duration (Clauses 4.6 to 4.9).
  4. Convey. Convey the 1% AEP (100-yr) flow safely through the site to the receiving system on a defined overland path (Chapter 6), and check the receiving system downstream (Chapter 5).

4.3.2 Preservation and retention reduce the detention required (Clauses 4.4.6 and 4.4.7). They do not relieve the site of the release-rate criteria of Clause 4.5 or of the downstream analysis of Chapter 5.

Commentary. This order follows the "layers of stormwater management" adopted in the Kansas City Metro APWA Section 5600 Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet; MARC Supplement, Nov 2025). Maintenance is the fifth layer and is set in Chapter 10. The 2025.01 manual credits retention and natural-area preservation against detention size (MARC Supplement, Nov 2025). Clause 4.4.6 adopts that credit, and defines it so that it cannot be claimed twice.


4.4 Retention

4.4.1 Requirement

The site shall retain the RRV. Retention shall be achieved by one or more of the following:

  • infiltration practices (soakaways, infiltration trenches, permeable pavement with an infiltration base, bioretention);
  • rainwater reuse that is drawn down by a demonstrated non-potable demand;
  • green roofs and landscape areas that do not drain to the outfall in the retention-depth storm.

The limits of Clause 4.4.4 apply.

4.4.2 Computation of the RRV

RRV (m³) = 10 × Q_R × A

where:

  • Q_R (mm) is the runoff depth from the retention depth P_R (Annex 2E). It is computed with the SCS-CN method for the post-development cover of each sub-area, at AMC II, with Ia = 0.2S (Chapter 3); and
  • A (ha) is the area of the site that drains to the outfall.

Q_R shall be computed for each sub-area separately and summed. An area-weighted CN shall not be used where impervious and pervious areas differ by more than 20 CN points.

The volumetric method RRV = 10 × P_R × Rv × A, with Rv = 0.05 + 0.009 × I (I = percent impervious), may be used for sites under 0.5 ha and under the Tier B method.

Commentary. The Rv formula is the one used in the KC water quality volume (MARC BMP Manual 2012). It is simple to review for small sites. The SCS-CN form is required for larger sites so that the retention computation uses the same runoff model as the detention routing. That keeps the credit computation of Clause 4.4.6 consistent.

4.4.3 Verification

Retention by infiltration shall be supported by:

  • (a) site infiltration tests at the location and depth of each practice, at the frequency set in Chapter 8;
  • (b) a design infiltration rate of no more than half of the measured rate; and
  • (c) groundwater evidence showing the seasonal high groundwater table at least 1.0 m below the base of the practice (Chapter 8).

Retention by reuse shall be supported by a demand calculation showing that the RRV is drawn down within 72 hours by a continuous non-potable use, such as toilet flushing, cooling or irrigation.

Commentary. The factor of 2 on measured infiltration rate has no direct precedent; this Manual sets it to allow for clogging and for the difference between a test pit and a full-scale practice. Chapter 8 may set a different factor; if it does, Chapter 8 governs.

4.4.4 Limits on retention

4.4.4.1 Infiltration practices shall not be used:

  • where the seasonal high groundwater table is less than 1.0 m below the base (Chapter 8);
  • on contaminated land;
  • within the setbacks from foundations, wells and septic systems set in Chapter 8; or
  • on fill, unless tested after placement.

4.4.4.2 Where the RRV cannot be fully retained, the shortfall shall be stated in the submittal. The shortfall shall be treated as WQv under Chapter 8 and shall get no retention credit.

4.4.5 Drawdown of retention

Retention storage shall be emptied by infiltration or reuse within 72 hours of the end of the retention-depth storm, verified by the tests of Clause 4.4.3.

4.4.6 Retention credit: definition and computation

4.4.6.1 What the credit is. The retention credit is the reduction in required detention storage that results when the retention practices are included in the post-development routing. It is computed. It is not assumed equal to the RRV.

4.4.6.2 Tier A method (routing). For each design storm and duration of Clause 4.6.3:

  • (a) model each retention practice explicitly as a storage that is empty at the start of the storm, unless Clause 4.11 says otherwise;
  • (b) let the practice fill from the front of the storm, and let it lose water during the storm only at the design infiltration or reuse rate of Clause 4.4.3;
  • (c) once it is full, route its overflow to the detention facility; and
  • (d) size the detention for the residual hydrograph.

The required detention storage is the largest storage over all storms and durations. The credit is the difference between that storage and the storage required with no retention. No further deduction shall be made.

4.4.6.3 Tier B method (simplified). The detention storage required by Clause 4.14 may be reduced by:

V_credit = C_R × RRV_provided

where C_R is the retention credit factor from Annex 4B for the zone, soil group and drawdown rate. Until Annex 4B is published, C_R = 0.

4.4.6.4 Retention that is not verified under Clause 4.4.3 gets no credit.

Commentary. "Credited against detention" (APWA 5600 2025.01) can be read in two ways. One reading subtracts the retained volume from the detention volume, cubic metre for cubic metre. The other routes the storms with retention in place and sees what detention is still needed. The two readings give very different answers in Haryana, because the mandatory 48- and 72-hour storms (Clause 2.5.2) fill any retention practice on the first day, long before the peak arrives on the last day (Clause 2.9.2). Unless the practice keeps infiltrating during the storm, it is full at the peak and does nothing to reduce the peak storage.

The illustrative example in Clause 4.6.7 shows the size of the effect. A 2 ha site with 552 m³ of retention (no infiltration during the storm) needs 138 m³ less detention for the 24-hour storm. That is a credit of about a quarter of the retained volume. For the 48- and 72-hour storms, which govern, the credit is close to zero. Subtracting the retained volume directly would have under-sized the detention by about 545 m³ (about 19%).

This Manual therefore defines the credit as the result of routing. Retention on fast-draining sandy soils, which keeps infiltrating through a multi-day storm, will earn a real credit. Retention that only fills will earn little. Both outcomes are physically correct. Setting C_R = 0 until Annex 4B exists is a safe default for Tier B, not a judgement that retention has no value: retention is still required for water quality and recharge (Chapter 8).

4.4.7 Preservation credit

Areas of the site that are permanently preserved in natural cover may be modelled at their pre-development CN in the post-development condition, provided that:

  • they are protected by a registered covenant or dedication; and
  • their runoff is not concentrated onto impervious surfaces.

This lowers both the RRV and the detention required. No other preservation credit applies.


4.5 Release-rate criteria

4.5.1 General

4.5.1.1 Peak discharge from the site shall be computed by a hydrograph method (Chapter 3) for the pre-development and post-development conditions with identical design storms (Clause 2.11.1). The Rational Method shall not be used for any part of storage sizing.

4.5.1.2 Pre-development is greenfield: open land in good condition for the mapped HSG. Existing impervious cover is not counted (Clause 2.11.5, Chapter 3). This applies to redevelopment as well, subject only to the constrained-redevelopment route of Clause 4.5.6.

4.5.1.3 The criteria apply at each point where runoff leaves the site. Where a site drains to more than one outfall, the criteria apply to each outfall for the area draining to it. Runoff shall not be diverted between catchments.

4.5.2 Standard catchments

For each of the 50%, 10% and 1% AEP (2-, 10- and 100-yr) storms, and for every duration in {1, 2, 3, 6, 12, 24, 48, 72 h}:

Q_post(T, d) ≤ 0.9 × Q_pre(T, d)

4.5.3 Flood-sensitive catchments

4.5.3.1 In the catchments listed below, the mixed-frequency rule of Clause 2.11.3 applies, for every duration in Clause 2.5.2:

Q_post(1% AEP, 100-yr) ≤ Q_pre(10% AEP, 10-yr), and Q_post(50% AEP, 2-yr) ≤ Q_pre(50% AEP, 2-yr).

Each cap is the pre-development peak at the duration that maximises it: the 10-yr peak for the 100-yr check, and the 2-yr peak for the 2-yr check. The cap applies to every post-development duration (Clause 2.11.3).

4.5.3.2 The flood-sensitive catchments are:

  • (a) Gurugram on Legs I–III and the Badshahpur drain: the catchments of Leg-I, Leg-II and Leg-III (the Badshahpur drain), from the Aravalli foothills to their outfalls to the Najafgarh drain, including the land that drains to the Badshahpur drain at Khandsa and Hero Honda Chowk;
  • (b) Faridabad on the Budhiya nala: the catchment of the Budhiya (Buria) nala and of the city drains that join it, down to its outfall towards the Yamuna;
  • (c) the Rohtak–Jhajjar waterlogged towns: Rohtak, Jhajjar, Bahadurgarh, Beri and Sampla, and the land that drains from them to Outfall Drain No. 8 and the other I&WRD drains of sub-area HR-D;
  • (d) Panchkula and Ambala on the Ghaggar: the land of Panchkula and Ambala that drains to the Ghaggar and its tributaries and choes, among them the Kaushalya and the Tangri, including the Ghaggar floodplain zone notified in Panchkula under section 45 of the Haryana Canal and Drainage Act 1974;
  • (e) the Yamuna floodplain at Karnal, Panipat and Sonipat: the land of those towns that drains across the floodplain (khadar) of the Yamuna to the river, or to drains that outfall to it, whose outfalls are held up when the Yamuna is high; and
  • (f) any catchment notified under Clause 4.5.4.

The boundaries shall be those mapped in Annex 4A.

4.5.4 Notification of further flood-sensitive catchments

4.5.4.1 The Authority may propose that a catchment be notified as flood-sensitive where one or more of the following is documented:

  • (a) buildings or arterial roads flooded in an event of 1% AEP or more frequent, on at least two occasions in the previous 20 years;
  • (b) receiving drains or channels with capacity below the 10% AEP flow under existing conditions;
  • (c) an outfall that is closed by a regulator or flap gate when the receiving river or drain is high, as on the Yamuna at Yamunanagar, Karnal, Panipat, Sonipat and Faridabad, at the Dhansa regulator on Outfall Drain No. 8 or where the Gurugram drains meet the Najafgarh drain, that depends on pumping, as in much of the Rohtak–Jhajjar–Sonipat waterlogged belt, or that is held up by the Ghaggar or one of its tributaries in flood, for part of the SW monsoon (Chapter 5);
  • (d) loss of more than a quarter of the mapped tank and johad storage in the catchment since the earliest available survey; or
  • (e) a basin master plan that relies on limiting site discharge.

4.5.4.2 The procedure shall be:

  1. The Authority prepares a technical note with the catchment boundary in GIS form and the evidence for 4.5.4.1.
  2. The State-level technical committee constituted under Chapter 1 reviews the note.
  3. The draft notification and map are published for public comment for at least 60 days.
  4. The Government notifies the catchment and the map is added to Annex 4A.
  5. The rule applies to applications received 6 months or more after notification. Applications received earlier are assessed under Clause 4.5.2.

4.5.4.3 A notified catchment may be de-notified only by the same procedure, and only after a basin study shows that the downstream system meets Chapter 5 with all development under Clause 4.5.2.

Commentary. The 0.9 factor is derived from the Denver (MHFD) analysis. In that analysis, ten basins each releasing 100% of the historic 100-yr peak still produced 106% of the historic peak at the outlet; releasing 90% at each gave 97% (UDFCD Full Spectrum Detention Release Rate Memorandum, 2012). The mixed-frequency rule has no direct precedent; the nearest is the Malaysian DID (2008) checklist, which required post-development 2-, 10-, 50- and 100-yr peaks below the pre-development 2-yr peak. The specific "100-yr post ≤ 10-yr pre" form appears in a New Berlin, Wisconsin planning discussion (not an adopted rule). The Gurugram entry follows the city's drainage and its record. Three master drains, Leg-I, Leg-II and Leg-III (the Badshahpur drain), carry the runoff of the city from the Aravallis to the Najafgarh drain (GMDA status report in NGT O.A. 454/2018, 2 October 2020), across a fall of about 78 m (Lok Sabha reply of 8 August 2025, as reported). DTCP's master storm-water drainage drawing for Gurugram–Manesar 2031 (No. DTP(G) 2104/2012, 9 November 2012) gives them design discharges of 541, 1,305 and 3,702 cusecs, and HUDA's management plan for the Badshahpur catchment (2017, revised 24 November 2020) gives reach discharges of up to 2,300 cusecs, but neither states a return period or a rainfall intensity; the capacity of the Badshahpur drain has been reported at anything from 500 to 3,800 cusecs, with a bottleneck of about 800 cusecs at Khandsa (as reported). On 28 July 2016 a storm of about 46 mm in three hours (as reported by the Chief Secretary; no IMD reading was found) flooded Hero Honda Chowk and jammed NH-48 for more than 18 hours, and the city flooded again in 2020, 2023, 2024 and 2025, on 9–10 July 2025 after about 103 mm in 90 minutes and on 1 September 2025 after more than 100 mm in four hours (as reported). The Punjab and Haryana High Court recorded on 22 September 2026 that "Gurugram is facing severe waterlogging during the monsoon season" while the channels that fed its water bodies "remain largely blocked", and summoned officers of MCG, HSVP and GMDA (Sunil Singh, CWP-20032-2008). The Faridabad entry follows the Budhiya (Buria) nala, which drains the Aravalli side of the city towards the Yamuna; its capacity is reported as having been raised from 280 to 1,700 cusecs (NCR Planning Board, 2016), and it carries sewage, with a BOD of 76 mg/l in 2023 (State of Haryana report in NGT E.A. 35/2023). The Rohtak–Jhajjar entry follows the water table and the outfall: the water table was within 3 m of the surface over 49.9% of Rohtak district and 42.6% of Jhajjar district in June 2023 (HWRA Atlas 2025), the towns drain to Outfall Drain No. 8, whose capacity of 4,000 cusecs was exceeded by a flow of 5,000 cusecs at the Dhansa regulator in 2022 (I&WRD report in NGT O.A. 627/2022), and the Municipal Corporation of Rohtak lists 16 waterlogging-prone areas (as reported). The belt holds the State's largest recorded day, 484.1 mm at Rohtak on 19 September 1933 (IMD, Climate of Haryana). The Panchkula–Ambala entry follows July 2023. On 9 July 2023 Chandigarh recorded 302.2 mm and Ambala 224.1 mm in 24 hours (IMD, July 2023 summary, from real-time data); the Ghaggar breached near Ambala and the breach was closed with the help of the Army, while the Municipal Corporation used 19 pump sets and I&WRD inventory pumps of 962 cusecs in the city (Haryana Vidhan Sabha, starred question 16, September 2023). The Ghaggar floodplain zone in Panchkula was notified under section 45 of the Haryana Canal and Drainage Act 1974 on 27 October 2023, on a 100-year flood of 2,933.45 m³/s computed by Gumbel's method from 54 years of data (I&WRD replies in NGT O.A. 421/2022); the CWC report's own example, on the Ghaggar near Ambala, gives a 50-year peak of 2,706 m³/s (Annex 3E). The Yamuna entry follows the river: Hathnikund passed its highest flow since it was commissioned, about 8.28 lakh cusecs, on 18 August 2019, and about 3.59 lakh cusecs in July 2023 (as reported); the river has reached 250.07 m at the CWC gauge at Karnal (danger level 249.5 m) and 232.75 m at Mawi (danger level 230.85 m), both in June 2013 (CWC site list, as transcribed by SANDRP); and no floodplain notification under section 45 for the Yamuna in Haryana was found. The Ghaggar towns downstream, Kaithal, Fatehabad and Sirsa, where the river breached its banks in July 2023, Yamunanagar–Jagadhri on the Somb and Pathrala, Shahabad on the Markanda, the towns of Palwal and Hisar, and Rewari on the Sahibi below the Masani barrage, are candidates for notification under Clause 4.5.4. The notification triggers in 4.5.4.1 have no direct precedent and are set by this Manual. The 6-month lead time follows the update rule of Clause 2.14.2. Clause 4.16 explains why releases below pre-development are needed at all.

4.5.5 Minimum outlet and short-duration 2-yr checks

4.5.5.1 Where the PSD for any AEP and duration is less than the discharge of a 50 mm orifice (Clause 4.8.2) at the corresponding stage, the 50 mm orifice is deemed to comply for that AEP and duration.

4.5.5.2 Where meeting the 2-yr criterion at a duration of 3 hours or less would require a low-flow orifice so small that the drawdown requirement of Clause 4.7 cannot be met, the designer shall:

  • size the low-flow orifice as the smallest opening that meets Clause 4.7; and
  • report the resulting 2-yr exceedance for those durations.

The Authority may accept the design if the exceedance is below the discharge of the 50 mm orifice at the 2-yr stage, or if the downstream analysis of Chapter 5 shows no adverse effect.

Commentary. Under AMC II, a greenfield site produces almost no runoff in a 1- or 2-hour, 2-yr storm, because most of the rain is lost to initial abstraction. A pre-development peak of a few litres per second, compared duration by duration, then forces a very small low-flow orifice. That orifice cannot release the 10-yr volume within 48 hours. Checked as if it were outside a flood-sensitive catchment, the illustrative example of Clause 4.6.7 would need a low-flow orifice of about 75 mm to match the 1-hour, 2-yr pre-development peak. 90% drawdown of the 10-yr volume would then take about 84 hours even with a clean orifice, against the 48-hour limit. The 170 mm orifice that meets drawdown with 50% blockage exceeds the 1-hour, 2-yr pre-development peak by about 11 L/s. Clause 4.5.5.2 resolves that conflict in favour of drawdown, because a basin that is still partly full when the next SW monsoon storm arrives fails in the event that matters more. KC APWA 5600 (2006) used a 75 mm (3 in) minimum orifice with trash racks. This Manual sets a 50 mm minimum (Clause 4.8.2).

4.5.6 Constrained redevelopment sites

4.5.6.1 Eligibility. The relief route of this clause is available only for redevelopment where all of the following hold:

  • (a) the existing site is at least 60% impervious, as surveyed before demolition;
  • (b) the site is 1 ha or less; and
  • (c) the designer shows, in a Constraint Statement submitted with Form 4-1, that the greenfield criteria of Clauses 4.5.2 or 4.5.3 cannot be met on the site. The statement must show that every storage option of Clause 4.10 has been assessed: rooftop and podium storage, tanks under parking or landscape, permeable paving with sub-base storage, and landscape depressions. It must also give the storage each option can provide.

New development on undeveloped land is never eligible.

4.5.6.2 Minimum on-site performance. An eligible site shall provide all of the following on site:

  • (a) the full retention volume (Clause 4.4) and the WQv treatment (Chapter 8), with no relief;
  • (b) post-development peak discharge no more than 50% of the existing-condition peak for the 50%, 10% and 1% AEP storms, at each duration of Clause 2.5.2. The existing condition is modelled under Clause 3.3.4; and
  • (c) no increase in the 1% AEP water level at any building or road downstream (Chapter 5).

4.5.6.3 Shortfall. The shortfall is the detention storage required to meet the greenfield criteria (Clause 4.6) minus the storage provided on site under 4.5.6.2. The applicant shall pay for the shortfall as a fee-in-lieu at the unit rate of Clause 4.13.3. The fee shall be:

  • (a) paid into the ring-fenced account of the basin in which the site lies;
  • (b) spent only on regional detention or on restoring johad or tank flood storage identified in the basin stormwater master plan (Chapter 11); and
  • (c) recorded in the public ledger of Clause 4.13.4, which shall show the volume owed and the volume delivered in each basin.

Where no basin master plan has yet been approved, the fee shall be held for up to 5 years. If no plan is approved in that time, it shall be spent on restoring tank flood storage in the same basin, with I&WRD agreement.

4.5.6.4 Flood-sensitive catchments. In the catchments of Clause 4.5.3, the route is available under the same conditions. The Authority may, however, refuse it where the downstream analysis of Chapter 5 shows existing flooding of buildings in the 10% AEP event within the analysis extent.

Commentary. Greenfield is the target for all redevelopment, because a dense city only reduces its runoff as it rebuilds. On small, fully built plots in areas such as the old cores of Rohtak, Panipat, Hisar, Ambala and Sonipat, the old town of Faridabad, or the village abadis (abadi deh) inside the sectors of Gurugram, there is often no space for the full greenfield storage. A rule that cannot be met invites variances and non-compliance, which help no one downstream. This clause follows the approach of the UK Non-statutory Technical Standards for Sustainable Drainage (Defra, 2015, S2–S3). For previously developed sites, those standards require peak runoff "as close as reasonably practicable to the greenfield runoff rate" and never above the pre-redevelopment rate. The fixed 50% minimum reduction has no direct precedent; this Manual sets it to give reviewers a clear number in place of a "reasonably practicable" judgement. The fee-in-lieu turns the shortfall into regional storage in the same basin, so the basin still receives greenfield-equivalent control in total. Retention and water quality get no relief, because they are small volumes that almost every site can hold.


4.6 Detention sizing procedure

4.6.1 Method

Detention shall be sized by hydrograph routing through the stage–storage–discharge relationship of the facility, by level-pool (Modified Puls) or an equivalent numerical method (SWMM, HEC-HMS). Fixed-ratio and Rational-based storage formulae shall not be used. The simplified methods of Clause 4.14 (the Tier B tables and the fixed-coefficient route) are the only exceptions.

4.6.2 Steps

  1. Delineate the site and sub-areas. Map HSG and confirm by testing (Chapter 3).
  2. Extract design rainfall for 50%, 10% and 1% AEP and every duration in Clause 2.5.2, with the climate factor (Chapter 2, Form 2-1).
  3. Build design hyetographs: alternating block for ≤ 24 h; the "peak day last" pattern for 48 and 72 h (Clause 2.9).
  4. Compute pre-development hydrographs (greenfield CN; AMC III for storms of every duration from 1 July to 15 September in sub-areas HR-A and HR-D and on river floodplains, and in July–August in HR-B and HR-C, and at other sites and times after a 5-day total of more than 53 mm, AMC II otherwise).
  5. Compute the release caps for each AEP and duration under Clause 4.5.2 or 4.5.3.
  6. Compute post-development hydrographs with the same storms and AMC, including retention practices (Clause 4.4.6).
  7. Choose a trial facility geometry (stage–storage) and a multi-stage outlet (Clause 4.6.5).
  8. Route every storm and duration. Use a time step of no more than 5 minutes, and no more than Tc/3 of the post-development catchment.
  9. Check every release against its cap, and check drawdown (Clause 4.7). Adjust the outlet and storage and repeat.
  10. Check the tailwater condition of Clause 4.6.6 and the downstream analysis of Chapter 5.
  11. Size the emergency spillway and set freeboard (Clause 4.9).
  12. Report the governing storm for storage, for each outlet stage, and for the spillway (Clause 4.17).

4.6.3 Storms to be routed

Every facility shall be routed for the full matrix:

Table 4.1 — Design storms to be routed for detention sizing

AEP Durations (h) AMC
50% (2-yr) 1, 2, 3, 6, 12, 24, 48, 72 II for ≤ 6 h; III for ≥ 12 h
10% (10-yr) 1, 2, 3, 6, 12, 24, 48, 72 II for ≤ 6 h; III for ≥ 12 h
1% (100-yr) 1, 2, 3, 6, 12, 24, 48, 72 II for ≤ 6 h; III for ≥ 12 h

The 24-, 48- and 72-hour runs are mandatory whatever the critical-duration result (Clause 2.5.2). Where Ia = 0.05S sensitivity is required by Chapter 3, it shall be run for the governing storage case.

4.6.4 Initial conditions

Each run shall start with:

  • detention storage empty, down to the invert of the lowest outlet;
  • any permanent pool full;
  • retention practices empty, except as limited by Clause 4.11; and
  • RWH storage full (Clause 4.11).

The 48- and 72-hour storms already contain their antecedent rain, so no further pre-filling is applied.

4.6.5 Multi-stage outlet design

4.6.5.1 The outlet shall have a separate control for each criterion, normally stacked as in Figure 4.2:

  • Stage 1, at the invert: the low-flow orifice. It releases the WQv over 24–48 h (Chapter 8) and controls the 2-yr release.
  • Stage 2: an orifice or slot set at or near the maximum 2-yr level. It controls the 10-yr release.
  • Stage 3: a weir, riser crest or larger orifice set at or near the maximum 10-yr level. It controls the 100-yr release.
  • Emergency spillway: separate from the primary outlet (Clause 4.9).

Stages may be combined where routing shows that every cap is met.

4.6.5.2 Orifices shall be computed with a discharge coefficient of 0.60 unless a rated device is used. Weirs shall use a coefficient appropriate to their shape. Submerged-outlet and tailwater effects shall be included (Clause 4.6.6).

4.6.5.3 Vortex flow controls and other proprietary devices may be used where the supplier provides a certified head–discharge curve and the minimum clear opening is at least 50 mm.

4.6.6 Tailwater on the outlet

The outlet shall be routed against the tailwater of the receiving system, not free outfall, wherever the receiving water level can rise above the outlet invert. The tailwater shall be:

  • for a receiving drain: its water level in the same storm, from the Chapter 5 analysis or, for Tier B, the drain obvert;
  • for tidal or backwater-affected outfalls: the levels and joint cases of Clause 2.12 and Chapter 5, including the outfall-closed check (Clause 5.10).

Where tailwater governs, a flap gate shall be fitted to the outlet (Clause 5.11). The storage below the tailwater level shall not be counted as available unless the routing includes the gate closure.

4.6.7 Illustrative example

Illustrative — not design values. This example shows the procedure and the sizes it produces. The inputs are invented to be plausible for a sector draining to the Badshahpur drain in Gurugram. They are not NIH-DHAARA values and must not be used for design.

Inputs:

  • Site: 2.0 ha, flood-sensitive catchment (Clause 4.5.3).
  • Land cover: pre-development all pervious, CN 70. Post-development as two sub-areas (Clause 3.9.2): 1.57 ha of directly connected impervious surface at CN 98, never converted for AMC, and 0.43 ha of pervious open space at CN 70, on the same soil as pre-development; the area-weighted CN at AMC II is 92. For storms of 12 h and longer the pervious CN only is converted to AMC III: CN_III = 23·CN / (10 + 0.13·CN) = 84.3 (Clause 3.8.4).
  • Time of concentration (Tc): 45 min pre-development, 15 min post-development (used for both sub-areas). SCS triangular unit hydrograph; 5-minute time step.
  • 24-h depths: 110, 200 and 350 mm for 2-, 10- and 100-yr (the same 10- and 100-yr values as Clause 2.11).
  • Shorter durations: P(t) = P24·(t/24)^0.40, an assumed ratio set and not Annex 2B.
  • Longer durations: 48-h and 72-h depths taken as 1.25 and 1.40 × P24, laid out per Clause 2.9.2.
  • Storage: vertical-walled, 2,500 m² plan area.
  • Outlet, sized so that drawdown is met with the low-flow orifice 50% blocked (Clause 4.8.3). Annex 4C shows the trial outlet that failed this check.
    • Stage 1: 170 mm orifice at the invert.
    • Stage 2: 460 mm orifice with its invert 0.53 m above the floor.
    • Stage 3: none needed, because the 100-yr cap is met by Stages 1 and 2.

Results (discharges in L/s; storage in m³):

Table 4.2 — Illustrative example: peak discharges and storage used, by duration (Illustrative — not design values)

Duration (h) 2-yr pre 2-yr post, detained 10-yr pre 10-yr post, detained 100-yr post, uncontrolled 100-yr post, detained 100-yr storage used 10-yr drawdown, 50% blocked (h)
1 4 15 51 28 922 42 1,426 31.3
2 14 20 84 34 961 79 1,911 32.1
3 19 22 104 37 981 139 1,999 32.8
6 32 25 150 41 1,010 194 2,154 34.2
12 127 30 302 46 1,074 276 2,512 39.0
24 149 32 327 49 1,081 320 2,766 45.3
48 173 34 349 82 1,087 343 2,913 44.8
72 180 34 356 84 1,089 343 2,911 44.7

How to read it:

  • 100-yr cap. The cap is the largest pre-development 10-yr peak, 356 L/s (72 h). Every 100-yr detained peak is at or below it; the largest is 343 L/s.
  • 2-yr cap. The site is flood-sensitive, so the 2-yr cap is the largest pre-development 2-yr peak, 180 L/s (72 h; Clause 4.5.3.1). The largest 2-yr detained peak is 34 L/s. At 1, 2 and 3 hours the detained 2-yr peak is above the pre-development peak of the same duration (15 against 4 L/s, 20 against 14 L/s, and 22 against 19 L/s). That comparison is not required here. It would be for a site under Clause 4.5.2, and Clause 4.5.5.2 would then apply.
  • Governing storage. Storage is governed by the 48- and 72-hour storms: 2,913 m³, which is 0.146 m³ per m² of site, at a maximum depth of 1.17 m. A design that checked only the critical-duration peak storm (1–3 h here) would have provided about 2,000 m³, roughly two-thirds of what is needed.
  • Drawdown. With the low-flow orifice 50% blocked (Clause 4.8.3), 90% of the 10-yr storage drains in at most 45.3 h (the 24-hour storm), within the 48 hours of Clause 4.7. A 120 mm orifice would drain it in about 42 h when clean but 54 to 75 h when half blocked, so it fails. Annex 4C shows that trial and the routing step by step.
  • Retention credit. With an illustrative retention depth of 40 mm, RRV = 552 m³, computed for each sub-area (Clause 3.9.4). Modelled as filling from the start of the storm with no infiltration during it, the retention reduces the 24-hour storage by 138 m³ and the 48- and 72-hour storage by 7 m³ or less. The credit under Clause 4.4.6 is therefore effectively zero for this site.

The order of magnitude, about 0.15 m³ per m² of site, is consistent with the indication in Clause 2.11.

2026-11-01T10:14:56.974241 image/svg+xml Matplotlib v3.9.4, https://matplotlib.org/ 0 5 10 15 20 25 30 35 40 Time from start of 24 h design storm (h) 0 200 400 600 800 1000 1200 Discharge (L/s) Release cap = max pre-development 10-yr peak over all durations (356 L/s) Uncontrolled peak 1081 L/s Detained: peak later and flatter, recession prolonged (volume unchanged) Illustrative — not design values. 2 ha site, 24 h storm, AMC III, mixed-frequency rule Post-development 1% AEP (100-yr), uncontrolled Post-development 1% AEP (100-yr), detained Pre-development 10% AEP (10-yr)

Figure 4.1 — Pre-development 10-yr, post-development 100-yr uncontrolled and detained hydrographs for the 24-hour storm of the illustrative example (Clause 4.6.7). Illustrative — not design values. Original drawing for this Manual, adapted from the pre/post-development hydrograph concept in MARC/KC APWA Section 5600 and the Georgia Stormwater Management Manual (2016).

Commentary. Figure 4.1 shows what detention does and does not do. It cuts and delays the peak. It does not reduce the volume: the area under the detained curve equals the area under the uncontrolled curve, more than twice the pre-development 10-yr volume. The extra volume leaves the site over many hours after the storm. That prolonged release can coincide with the peak of the larger catchment downstream (Clause 4.16), and it must still drain when the outfall is tide-locked (Chapter 5).


4.7 Drawdown

4.7.1 Detention. At least 90% of the maximum volume stored in the 10% AEP (10-yr) storm of each duration shall be released within 48 hours of the time of maximum storage, by gravity, with the tailwater of Clause 4.6.6.

4.7.2 Water quality volume. The WQv shall be released over not less than 24 hours and not more than 48 hours (Chapter 8).

4.7.3 Retention. Retention storage shall be emptied within 72 hours by infiltration or reuse (Clause 4.4.5).

4.7.4 Tidal outfalls. Where gravity drawdown is prevented by tide for part of each cycle, the 48-hour limit applies with the tidal tailwater modelled. Where it cannot be met by gravity, pumped drawdown shall be provided under Clause 5.12.

Commentary. KC APWA 5600 (2006) required dry basins to release at least 80% of storage within 24 hours of the inflow peak and to empty within 72 hours. Singapore PUB requires detention to be restored within 4 hours. The 48-hour, 90% rule is longer than PUB's because Haryana storage must hold multi-day volumes. It is still short enough that a basin filled by one SW monsoon depression will have most of its volume back before the next, which in August–September 1995 at Bhiwani (197.4 mm in 24 hours on 28 August and 246.6 mm on 4 September, IMD) followed within days.


4.8 Outlet structures

4.8.1 General. Primary outlets shall be:

  • unattended, with no moving parts, valves or pumps, except where Clause 5.12 permits pumped drawdown;
  • accessible for inspection and cleaning from the surface without confined-space entry, where practicable; and
  • built of durable materials. In coastal areas these shall be corrosion-resistant (Clause 4.12.5).

4.8.2 Minimum orifice. No control orifice shall be smaller than 50 mm in diameter, or 50 mm in least dimension for a slot.

4.8.3 Trash racks and screens. Every orifice and weir shall be protected by a trash rack or screen. The rack shall:

  • have a clear bar spacing no greater than half the smallest opening it protects, and not less than 25 mm;
  • have a clear open area at least 10 times the area of the opening it protects;
  • be inclined, or set as a cage around the riser, so that debris rises with the water and does not pin against the bars;
  • be removable or hinged for cleaning; and
  • for routing, be assumed 50% blocked at the low-flow orifice when checking drawdown.

4.8.4 Anti-vortex devices. Riser crests and orifices that may run under more than 1.5 times their diameter of head shall have an anti-vortex plate or hood (Figure 4.2).

4.8.5 Outlet barrels. Outlet barrels through embankments shall:

  • be at least 300 mm in diameter (Chapter 6);
  • have watertight joints;
  • have a filter diaphragm or seepage collars over the length within the embankment; and
  • have an energy-dissipating outfall (Chapter 9).

4.8.6 Isolation. Facilities serving more than 1 ha shall have a means of isolating the outlet for maintenance, such as a stop-log slot or penstock. In normal service it shall be left fully open.

Commentary. The 50 mm minimum is smaller than the 75 mm (3 in) of KC APWA 5600 (2006), so the trash-rack requirements are correspondingly stricter. The ratios in 4.8.3 (bar spacing at half the opening, open area 10 times the opening, 50% blockage for the drawdown check) have no direct precedent and are set by this Manual. The blockage factor matches the 50% grate clogging factor for sag inlets in Chapter 6. Indian urban drains carry heavy loads of solid waste, so a low-flow orifice without an effective rack will block within one season.

Figure 4.2 — Detention storage stack and multi-stage outlet (schematic) Schematic cross-section of a detention basin showing stacked storage zones (permanent pool, water quality volume, 2-yr, 10-yr and 100-yr zones, spillway surcharge and freeboard) and a multi-stage riser outlet with trash rack, anti-vortex plate, outlet barrel and emergency spillway. Not to scale. Storage stack and multi-stage outlet — schematic section, not to scale Embankment crest Max level, spillway flowing (outlet blocked) Emergency spillway crest 1% AEP (100-yr) max water level 10% AEP (10-yr) max water level 50% AEP (2-yr) max water level Top of water quality volume (WQv) Permanent pool (wet basin only) Basin floor / pool bottom Spillway surcharge (Clause 4.9) 100-yr detention zone 10-yr detention zone 2-yr / channel-protection zone WQv — 24–48 h release (Ch 8) Permanent pool / retention Freeboard ≥ 0.3 m Spillway crest (offset in plan) 1 2 3 4 5 6 7 Key 1 Stage 1 low-flow orifice (≥ 50 mm, Clause 4.8.2) — releases WQv over 24–48 h 2 Stage 1 second orifice — with 1, controls 50% AEP (2-yr) release 3 Stage 2 orifice or weir slot — controls 10% AEP (10-yr) release 4 Stage 3 riser crest / overflow grate with anti-vortex plate — controls 1% AEP (100-yr) release 5 Trash rack enclosing all openings (Clause 4.8.3) 6 Seepage collar or filter diaphragm on outlet barrel 7 Outlet barrel, energy dissipation and outfall apron Levels and zone thicknesses are diagrammatic only.

Figure 4.2 — Detention storage stack (permanent pool, WQv, 2-yr, 10-yr and 100-yr zones, spillway surcharge and freeboard) and multi-stage riser outlet. Schematic, not to scale. Original drawing for this Manual, adapted from the multi-stage outlet and storage-zone concepts in MARC/KC APWA Section 5600 (2006, 2025.01) and the Mile High Flood District Urban Storm Drainage Criteria Manual, Volume 2 (full-spectrum detention).


4.9 Emergency spillway, freeboard and embankment safety

4.9.1 Spillway capacity. Every detention facility formed wholly or partly by an embankment, or whose overflow would reach buildings, shall have an emergency spillway that passes the 1% AEP (100-yr) peak inflow:

  • with the primary outlet assumed fully blocked;
  • with the facility full to the spillway crest at the start of the storm; and
  • with at least 0.3 m freeboard from the maximum water level to the embankment crest.

4.9.2 High-hazard facilities. A facility is high-hazard if its failure or overflow could:

  • endanger life;
  • flood a habitable building or critical facility; or
  • close an arterial road.

High-hazard facilities shall also be checked for the 0.2% AEP (500-yr) peak inflow under the conditions of 4.9.1, with the embankment not overtopped.

4.9.3 Spillway crest. The spillway crest shall be at or above the 1% AEP maximum water level from routing with the primary outlet working. The recommended clearance is 0.15 m.

4.9.4 Spillway location. The spillway shall be:

  • on natural ground or a reinforced section, not on fill, unless protected against erosion for the full design flow;
  • discharging to the 1% AEP overland flow path of Chapter 6; and
  • placed so that its flow does not reach a building.

4.9.5 Underground and enclosed facilities. Tanks, vaults and podium storage shall have an overflow route that operates when the outlet is blocked. The route shall carry the 1% AEP inflow to the overland path without surcharging any building, basement or lift pit.

4.9.6 Embankments.

  • (a) Embankments more than 2 m high (measured from the downstream toe to the crest) shall be designed by a qualified geotechnical engineer. The design shall include stability, seepage and settlement analysis.
  • (b) Side slopes shall be no steeper than 3H:1V on any face that is mown or accessible to the public. Slopes shall be flatter where Clause 4.15 requires.
  • (c) Embankments shall have:
    • a crest width of at least 3 m;
    • compacted, engineered fill with a core or cut-off where required by the seepage analysis; and
    • no trees or large shrubs.
  • (d) An embankment structure that falls within the Dam Safety Act, 2021 is subject to that Act in addition to this Manual.

4.9.7 Excavated facilities. Facilities wholly below the surrounding ground, with no embankment, need not meet 4.9.6. They shall still meet 4.9.1, with the overflow route treated as the spillway.

Commentary. The spillway criterion (1% inflow, outlet blocked, basin full, 0.3 m freeboard; 0.2% for high hazard) follows the KC APWA 5600 (2006) rule: the spillway passes the 1% storm with 1 ft (0.3 m) freeboard to the top of the dam, assuming zero storage and a clogged primary outlet, with the crest at least 0.5 ft (0.15 m) above the 1% maximum water surface. KC designed dams above 10 ft (3 m) to SCS TR-60 Class C. The 2 m embankment trigger, the 3H:1V slope (KC wet ponds), and the 3 m crest width have no direct precedent and are set by this Manual.


4.10 Facility types

4.10.1 General. Any storage that meets Clauses 4.5 to 4.9 may be used. Surface storage that is visible and can be inspected without confined-space entry is preferred. Storage shall not be placed in a habitable basement or in any space whose flooding would endanger life.

4.10.2 Underground tanks and vaults.

  • (a) Gravity outlet is required where the receiving drain allows it. Pumped outlets are permitted only under Clause 5.12, with a registered maintenance declaration (Chapter 10).
  • (b) Access openings shall be provided over the outlet chamber and over every inlet. In tanks over 500 m², they shall be no more than 30 m apart.
  • (c) The floor shall fall at least 1% to a sump at the outlet, with a sediment pocket below the low-flow orifice invert.
  • (d) The tank shall be ventilated.
  • (e) Inlets shall pass through a silt trap or gross pollutant trap (Chapter 8).
  • (f) Flotation and groundwater ingress shall be checked under Clause 4.12.

4.10.3 Rooftop detention.

  • (a) It is permitted on flat roofs designed for the full ponded load with the outlet blocked. The ponding depth shall not exceed 150 mm unless a structural engineer certifies a greater depth.
  • (b) Each roof outlet shall have a flow-control ring or weir with a certified rating, and every roof area shall have at least one overflow scupper, independent of the controlled outlets, that passes the 1% AEP inflow.
  • (c) Roofs used for RWH collection may also provide rooftop detention. The detained volume is released through the control, not into the RWH sump.

4.10.4 Podium and landscape-deck detention.

  • (a) It is permitted above ground level or above a basement car park, provided the structure is designed for full saturation and ponding, and waterproofed.
  • (b) The release, overflow and safety rules for rooftop detention (4.10.3) apply.

4.10.5 Parking-lot detention.

  • (a) It is permitted only on surface parking. Ponding depth shall not exceed:
    • 200 mm in the 10% AEP storm and 300 mm in the 1% AEP storm at any parking bay;
    • zero on accessible routes, ramps and pedestrian crossings; and
    • zero in the 10% AEP storm on fire-tender access routes.
  • (b) Signs shall warn that the area floods.
  • (c) Ponding shall not reach a building wall unless the wall is waterproofed above the 1% level plus freeboard (Chapter 6).

4.10.6 Multi-use detention (parks, playfields, open space reservation).

  • (a) Open space land may be used for detention, provided its primary use remains available in at least the 50% AEP storm.
  • (b) The storage areas shall be graded to drain fully within the times of Clause 4.7.
  • (c) A low-flow channel or underdrain shall carry dry-weather and frequent flows, so that the park is not waterlogged.
  • (d) The depth and slope limits of Clause 4.15 apply.
  • (e) Play equipment and seating shall be placed above the 10% AEP level.

4.10.7 Ponds and wet basins.

  • (a) A permanent pool shall be at least 1.2 m deep over most of its area to discourage weed growth and mosquito breeding, with a vegetated safety bench at the edge (Clause 4.15).
  • (b) Only storage above the permanent pool counts as detention.

Commentary.

  • The rooftop depth (150 mm) and parking depths (200 and 300 mm) have no direct precedent. This Manual sets them so that a blocked outlet is noticed before it becomes dangerous.
  • The 1.2 m pool depth equals the 4 ft minimum permanent pool of KC APWA 5600 (2006). This Manual adopts it mainly for weed and mosquito control.
  • Pumped detention tanks need maintenance declarations in Singapore (PUB Addendum No. 3, April 2025). This Manual adopts the same approach through Chapter 10.
  • Using open space for multi-use detention fits the Haryana Building Code 2017, under which at least 20% of the recreational open space of a building of 5,000–20,000 m² of built-up area is to be unpaved (Code 12.1) and groundwater recharge is mandatory "for open spaces like parks, parking, plazas, playgrounds and other common areas" (Code 8.1(2)(ii)). It also fits the policy of the Sub-Regional Plan for the Haryana Sub-Region of the NCR, which asks for "retention of rain water where it is received as much as possible, by ponding, retardation dams, grass waterways", and GMDA's finding that the "natural low lying water collection areas" of Gurugram "need to be preserved through appropriate legal mechanisms" (GMDA report in NGT O.A. 325/2015). A detention area graded into the open space below the level of the road keeps it pervious and usable, which is what 4.10.6 requires. Two kinds of land are not open space for this purpose. A johad or talab on the land, with its green belt and catchment where the Haryana Pond and Waste Water Management Authority Act 2018 applies, is preserved under step 1 of Clause 4.3.1 and modelled as a water surface (Clause 3.3.2(e)) that starts at its full level (Clause 3.12.5), so only its flood storage above that level can count, only as Chapter 7 allows and only with the Authority's permission. And land within the Ghaggar floodplain zone notified under section 45 of the Haryana Canal and Drainage Act 1974, the green belt round the Badkhal and Surajkund lakes (Supreme Court, 1996), a municipal drain on which no structure may be built without permission (Haryana Municipal Corporation Act 1994, section 206), and land in the hydraulic corridor of a drain or water body under Chapter 7 are corridor or flood land already: water reaches them first, so they are not counted as detention for the development beside them (Chapter 7).

4.11 Rainwater harvesting versus detention accounting

4.11.1 No double counting. RWH storage (sumps, tanks, recharge pits and wells provided under the RWH mandate) shall not be counted as detention.

4.11.2 RWH sumps assumed full. For all routing under this chapter, RWH sumps and tanks shall be assumed full at the start of every storm, in every season. Their overflow shall be routed to the detention facility, or directly to the outfall if it bypasses detention. In the latter case the bypass flow counts against the PSD.

4.11.3 Combined tanks. A single tank may provide both RWH and detention only if:

  • (a) the detention zone lies wholly above the RWH overflow level;
  • (b) the detention zone is drained by its own gravity control orifice set at the RWH overflow level, meeting Clauses 4.7 and 4.8;
  • (c) no pump, valve or user action can hold water in the detention zone; and
  • (d) the two zones and the orifice level are shown on the drawings and in the maintenance declaration.

Only the volume between the RWH overflow level and the detention overflow level counts as detention.

4.11.4 Recharge structures. Recharge pits, trenches, shafts and wells may count as retention (not detention) if they meet Clauses 4.4.3 to 4.4.5. In particular, the seasonal high groundwater table shall be at least 1.0 m below their base. In the routing they are treated under Clause 4.4.6 with the groundwater level for the SW monsoon season.

4.11.5 RWH remains mandatory. Nothing in this chapter reduces the RWH requirement of Code 8.1 and the environmental conditions of Code 12.1 of the Haryana Building Code 2017, the notification of HSVP (then HUDA) of 31 October 2001 for its Urban Estates, any condition of a licence, building plan or occupation certificate, the conditions of the Central Ground Water Authority or the Haryana Water Resources Authority for the area notified in Gurugram district, or any rainwater harvesting rule or direction of an approving authority.

Commentary. RWH in Haryana is required by Code 8.1 of the Haryana Building Code 2017, with two thresholds on different bases. In the areas that the Competent Authority specifies by notification, the owner shall arrange roof rainwater harvesting where "the area of the rooftop is 100 square metres or more" (Code 8.1(1)); and "Recharging of ground water shall be mandatory … for all types of buildings, including Group Housing Societies having a plot area more than 500 square metres", and for parks, parking, plazas, playgrounds and other common areas (Code 8.1(2)). The system shall let only clear water in, with the first shower segregated and filtered; a recharge well shall be "not less than 10 metres away from any structure handling sewage or industrial waste water", though not from leak-proof manholes and sewers; an architect or engineer certifies that the system is functional, and without it "no occupation certificate shall be issued"; and the owner shall keep it in good repair (Code 8.1(3)). The Code names ten towns where it is to be "strictly implemented": Panchkula, Kurukshetra, Shahabad, Karnal, Panipat, Sonipat, Gohana, Faridabad, Yamunanagar and Gurugram (Code 8.1(4)). Buildings of 5,000–20,000 m² of built-up area shall also keep the natural drain inlets and outlets, leave at least 20% of the recreational open space unpaved, and provide at least one recharge bore for every 5,000 m² of built-up area, with the harvested water stored for reuse and the excess led to the tube well bore after filtration (Code 12.1). The predecessor rule is the notification of HSVP (then HUDA) of 31 October 2001, which made roof harvesting mandatory in its Urban Estates where the roof is 100 m² or more, and by December 2023 HSVP counted 460 systems in its open spaces and 1,92,700 in private plotted buildings (I&WRD report in NGT O.A. 694/2023); since 2024 HSVP asks its allottees for an undertaking that the recharge well on their plot works (HSVP Chief Engineer's memo of 2024). The whole of Gurugram district was declared a "notified area" by the Central Ground Water Authority (public notice of 13 August 2011, from a search summary; the sources differ on its number [TBC]), and since 2020 the Haryana Water Resources Authority issues the groundwater permissions, with power to direct rainwater harvesting and recharge "as per geohydrological conditions" (HWRA Act 2020, section 21). A direction of the Chief Minister of 30 June 2026 to extend RWH to residential plots of more than 250 square yards is reported, but no notification was found [TBC]. None of these rules sets a storage volume, a design storm, an infiltration test or a depth to the water table, so the functionality certificate of Code 8.1(3) has no stated standard; the tests of Clauses 4.4.3 and 4.11.4 can supply one. This Manual credits these structures against its own retention requirement (Clause 4.4) as follows:

  • An RWH storage tank or sump, including the reuse tank of Code 12.1, is RWH storage. It is not detention (Clause 4.11.1), and it is assumed full at the start of every storm (Clause 4.11.2). A tank may also provide detention only if it is built as a combined tank under Clause 4.11.3, with a detention zone above its RWH overflow level that drains through its own orifice; only that zone counts.
  • An RWH tank counts toward the retention requirement of Clause 4.4 only to the extent that it is emptied within 72 hours by a continuous non-potable use, such as toilet flushing, demonstrated under Clause 4.4.3; it is then modelled under Clause 4.4.6 like any other retention practice. Where recharge earns no credit (below), reuse is the practical way to earn retention.
  • Recharge pits, trenches, shafts, wells and bores, including the recharge wells of Code 8.1 and the recharge bores of Code 12.1, count as retention only where they meet Clause 4.11.4: they are credited only to the extent that they drain within 72 hours at half the rate measured in a site test (Clauses 4.4.3 and 4.4.5), with their base at least 1.0 m above the seasonal high water table, and the credit is found by routing under Clause 4.4.6, not by deducting their volume.
  • Recharge depends on the depth to water. Haryana has both extremes. The State draws more groundwater than is recharged, at a stage of extraction of 135.96% in 2024, with 88 of its 143 assessment blocks over-exploited (CGWB, Dynamic Ground Water Resources of India 2024); in June 2023 the water table was deeper than 30 m under 97.2% of Kurukshetra district, 85.3% of Mahendragarh and 51.1% of Gurugram. Yet it was within 3 m of the surface under 49.9% of Rohtak district and 42.6% of Jhajjar, where every block is "safe" because the water is near the surface and much of the land is waterlogged and saline-sodic (HWRA Atlas 2025; shares by NEER's reading of its tables). The credit for recharge therefore follows the seasonal high (post-monsoon, October–November) water table at the site, from Clause 3.10.2 or Clause 4.12.1:
    • (a) deeper than 10 m below ground: recharge first. Retention shall be provided by recharge before reuse or detention wherever site tests allow, as in Gurugram, Faridabad, Kurukshetra, Kaithal, Karnal, Panipat, Mahendragarh and Rewari, and every pit, shaft, bore or well shall have pre-treatment ahead of it: a silt trap, a filter and a first-flush diverter, as Code 8.1(3) already requires;
    • (b) within 3 m of the ground: no recharge credit. In sub-area HR-D, on most of the floodplains of the Yamuna and the Ghaggar, within the Ghaggar floodplain zone notified under section 45 and on the land of a pond under the Haryana Pond and Waste Water Management Authority Act 2018, no recharge or infiltration practice earns retention credit, whatever a test shows; detention, conveyance and reuse govern there, and a recharge structure that the Code requires is built as the Code requires but is not counted. This follows the State's own water law, which directs that activities likely to lead to waterlogging be discouraged and prevented (HWRA Act 2020, section 21(7));
    • (c) 3–10 m below ground: recharge earns credit only after a check by a hydrogeologist shows that the practice will not raise the water table to within 3 m of the surface at the site or its neighbours, and that the groundwater below is not saline, as it is over much of Sirsa, Fatehabad, Hisar, Jind, Jhajjar, Bhiwani, Nuh, Mahendragarh, Rewari and Faridabad districts (CGWB, Ground Water Year Book Haryana 2021-22); and
    • (d) everywhere, road and parking runoff shall be recharged only through a surface infiltration practice with a filter, such as a vegetated basin or trench, never directly into a bore or well, and runoff from a drain that carries sewage, such as the Gurugram Legs or the Budhiya nala, shall not be recharged at all. In the area notified by the Central Ground Water Authority in Gurugram district, the conditions of the CGWA and of the Haryana Water Resources Authority apply in addition.
  • On the Aravalli rock of Gurugram, Faridabad and Nuh, a recharge bore or shaft earns credit only on a borehole test at its own depth, in a fractured zone that the test proves.
  • The unpaved area of Code 12.1 and the pervious open space of a layout are pervious area. They enter the post-development run as pervious land under Clause 3.9.2 and get no further credit as retention or detention unless they are built and tested as an infiltration practice.

In the Rohtak–Jhajjar–Sonipat belt and on the floodplains, a recharge pit drains slowly or not at all in the SW monsoon, and a sump is full after the first heavy rain. Treating RWH as detention would therefore credit storage that does not exist when it is needed. That is why this Manual assumes RWH sumps are full at the start of every storm. Applying the assumption to every season keeps one simple rule. The combined-tank provision (4.11.3) lets an owner build one structure, as long as the detention part is empty when the storm arrives. The depth-to-water rule, its 10 m and 3 m thresholds, the hydrogeologist's check in between, the borehole test on rock and the pre-treatment and road-runoff rules are set by this Manual; no Haryana rule on where recharge may or may not be credited was found.


4.12 High-groundwater and sandy coastal sites

4.12.1 Design groundwater level. Each site in the Rohtak–Jhajjar–Sonipat waterlogged belt (sub-area HR-D of Annex 2A) and the waterlogged parts of Hisar, Jind and Ambala districts, the floodplains (khadar) of the Yamuna and the Ghaggar and of their tributaries, including the Ghaggar floodplain zone notified in Panchkula, and the beds and green belts of johads and talabs, or any area where the groundwater table lies within 3 m of the surface at any time of year shall establish a design groundwater level (DGWL) for the facility. The DGWL is the seasonal high level during or after the SW monsoon, from:

  • (a) site piezometer readings over at least one full June–November season; or
  • (b) where (a) is not available, the higher of the CGWB or Haryana Water Resources Authority record for the nearest observation well, plus 0.5 m, and the design flood level of any adjacent river, drain or johad.

For the flotation check of 4.12.3 at sites in the Rohtak–Jhajjar–Sonipat waterlogged belt and the Yamuna and Ghaggar floodplains, where (a) is not available, the DGWL shall be taken as existing ground level.

4.12.2 Lined storage. Where the DGWL is less than 1.0 m below the base of a storage facility:

  • (a) the facility shall be watertight (lined or of watertight concrete), and no infiltration credit applies (Clause 4.4.4); or
  • (b) if unlined, the volume below the DGWL shall not be counted as detention, and groundwater inflow shall be added to the routed inflow.

4.12.3 Uplift and flotation. Every below-ground tank, vault, lined pond or chamber shall be checked for flotation:

  • with the facility empty;
  • with groundwater at the DGWL; and
  • for coastal sites, with groundwater also at the major-system tailwater level of Chapter 5, where that is higher.

The factor of safety against uplift, counting only permanent dead loads and ignoring wall friction unless supported by geotechnical design, shall be at least 1.2. Anchoring by ballast, toe extensions or tension piles may be used.

4.12.4 Shallow and above-ground storage preferred. On sites where the DGWL is within 1.5 m of ground, storage should be provided above ground where possible: rooftop, podium, landscape or surface storage. Deep tanks should be avoided.

4.12.5 Durability. Concrete and metal parts in contact with saline or brackish groundwater or tidal water shall be designed for the exposure class appropriate to coastal conditions under IS 456:2000. Outlet fittings, trash racks and gates shall be of stainless steel, HDPE, FRP or another corrosion-resistant material.

4.12.6 Sandy soils with deep groundwater. Where the DGWL is 1.0 m or more below the base, infiltration retention in sandy soils is encouraged. The design infiltration rate of Clause 4.4.3 applies, and the Chapter 8 requirements on pollution of shallow aquifers shall be met.

Commentary. Haryana is landlocked, so the coastal provisions of this clause, the tidal water levels of 4.12.1 and 4.12.3, do not apply in the State. The exposure provisions of 4.12.5 apply where groundwater at a site is saline or brackish, which over much of the State it is: the conductivity of groundwater ranged from 99 µS/cm at Kami in Sonipat district to 24,060 µS/cm at Nagina in Nuh district, 21.89% of samples exceeded 3,000 µS/cm, and the groundwater of the southern, western and central districts, Sirsa, Fatehabad, Hisar, Jind, Jhajjar, Bhiwani, Nuh, Mahendragarh, Rewari and Faridabad, is "mostly saline" (CGWB, Ground Water Year Book Haryana 2021-22). The State's groundwater runs to both extremes. Depths ranged from 0.85 m to 53.45 m below ground in June 2021 and from 0.63 m to 76.50 m in October–November 2021 (same source); in June 2023 the water table was within 3 m of the surface over 49.9% of Rohtak district and 42.6% of Jhajjar district, and deeper than 30 m over 97.2% of Kurukshetra district and 51.1% of Gurugram district (HWRA Atlas 2025; shares by NEER's reading of its tables). Where it is deep, infiltration is the best retention and should be used, subject to the depth-to-water rule of the Commentary to Clause 4.11, the 1.0 m separation of Clause 4.4.3 and Chapter 8. The Rohtak–Jhajjar–Sonipat belt and the floodplains are the opposite case. There the water table is within a few metres of the surface before the monsoon and rises through it, so an unlined tank fills with groundwater before the storm, and an empty lined tank can float, especially when the Yamuna or the Ghaggar is high and the river raises the water table of the floodplain beside it. The design groundwater level of 4.12.1(b) therefore takes the design flood level of the adjacent river, drain or johad where that is higher than the well record, and in the Rohtak–Jhajjar–Sonipat belt and on the floodplains the flotation check takes ground level unless piezometers show otherwise. The June–November monitoring season of 4.12.1(a) is set by this Manual to cover the SW monsoon and the post-monsoon high: the area of the State with the water table within 3 m grew from about 2.93 lakh ha in June 2023 to about 3.79 lakh ha in October 2023 (by NEER's reading of the HWRA Atlas), so a reading taken in June understates the design level. No monsoon water-table depths for individual town sites in Gurugram, Faridabad, Rohtak or Jhajjar were obtained [TBC]. The factor of 1.2, the 0.5 m allowance and the "ground level" default for the waterlogged belt and the floodplains have no direct precedent; this Manual sets them because no published site-scale seasonal groundwater depths for Haryana were found during research.


4.13 Regional detention and fee-in-lieu

4.13.1 Where permitted. In a basin covered by a Basin Stormwater Master Plan approved under Chapter 11, a development may meet all or part of its detention requirement through:

  • (a) a regional detention facility identified in the plan; or
  • (b) a fee-in-lieu paid toward restoration of johad or tank storage identified in the plan.

4.13.2 Conditions. Regional detention or fee-in-lieu shall be accepted only where:

  • (a) the regional facility or restored tank is operational, or is funded and scheduled to be operational within 3 years. Until then, interim on-site detention is required.
  • (b) the conveyance from the site to the facility carries the 1% AEP post-development flow without increasing water levels at buildings or roads between them (Chapter 5);
  • (c) the storage credited at a tank is the flood storage only. This is the volume between full tank level (FTL) and the maximum water level the bund and surplus weir can safely hold, plus any volume below FTL that a notified operating rule commits to empty before the SW monsoon. Storage below FTL that is held for irrigation or supply through June to September shall not be credited.
  • (d) the tank meets Chapter 7: surveyed FTL, a documented operating rule, and a maintained surplus weir;
  • (e) the site still provides retention (Clause 4.4) and WQv treatment (Chapter 8) on site; and
  • (f) in flood-sensitive catchments, the regional facility meets the mixed-frequency rule for its whole contributing area.

4.13.3 Fee. The fee-in-lieu shall be computed as:

Fee = (detention volume required on site under Clause 4.6, m³) × (unit rate, ₹/m³, notified by the Authority)

The unit rate shall include land, construction and 10 years of maintenance. Fees shall be held in a ring-fenced basin account and spent only on the facilities named in the plan.

4.13.4 Ledger. The Authority shall keep a public ledger of:

  • detention volume credited to each regional facility;
  • volume delivered; and
  • fees received and spent.

Commentary. The Malaysian DID (2008) checklist favoured community ponds over on-site detention for sites above 0.1 ha. Studies of on-site detention show that its benefit depends on location and fades with distance downstream (Colorado State University thesis; McEnroe for Kansas City), and that a pond low in the catchment can synchronise with the main-stem peak (Water 2016). Regional storage therefore has to be sited by basin modelling, not simply aggregated.

Haryana has a pond Act but no working tank cascade. Its regional storage is of three kinds: the johads and talabs regulated by the Haryana Pond and Waste Water Management Authority, the old flood-detention bunds of the Aravalli foot at Gurugram, and the drains and regulators of I&WRD. The Haryana Pond and Waste Water Management Authority Act 2018 (Act 33 of 2018) defines a pond as a tank, lake or other inland water body of 0.5 acre or more, "whether it contains water or not", recorded in the revenue records "as talab, johar, tank or by any other name", including its green belt, peripheral catchment, feeder inlets, bunds, weirs and sluices, but not a notified wetland, a pond in a notified forest or a pond on private land (sections 1(3) and 2(k)); no structure may be built on pond land, its green belt or its catchment, and no inflow or outflow obstructed, without the Authority's permission (section 14), and no spatial or development plan of an area that includes a pond may be approved without the Authority's prior approval (section 17). No protected area under section 16 was found to have been notified [TBC]. Three points follow:

  • A pond on a list may not exist, or may be private. The Authority's Pond Data Management System holds 19,665 ponds (HPWWMA written statement in NGT O.A. 573/2023, 21 February 2024); in Gurugram, GMDA's committee checked 826 features in 242 villages and inventoried 644 water bodies of about 1,142 acres, of which about 35% by number are privately owned, and only 123 appear in all of the revenue record of 1956, the Survey of India sheets of 1976 and the imagery of 2011-12 (GMDA report in NGT O.A. 325/2015). A johad is credited only after a survey shows its bed, bund and outlet, only for the storage above its full level, and only with the Authority's permission where the Act applies.
  • The old bunds were regional detention, and most no longer work. The Ghata bundh, about 1.25 km long and 5 m high, closes a gap of about 1.5 km in the Quaderpur–Mehrauli ridge where the Li, Kausat and Dhulaint nalas converge, and once held a pondage of about 60 ha below 240 m and 100 ha up to 245 m from a catchment of about 12,575 ha, of which about 3,500 ha is in Haryana (GMDA report in NGT O.A. 325/2015); the Chakarpur, Jharsa, Wazirabad and Ghata bunds of the late nineteenth century were described to Parliament in 2025 as made obsolete by urbanisation (as reported). Restoring such pondage is the kind of regional storage that Clause 4.13 can credit, once it is identified in a basin master plan (Chapter 11), surveyed, and given an operating rule under Chapter 7.
  • A drain of I&WRD, or a floodplain, is not regional storage. Outfall Drain No. 8 has already carried more than its capacity (5,000 cusecs against 4,000 at the Dhansa regulator in 2022; I&WRD report in NGT O.A. 627/2022), the Gurugram Legs and Outfall Drain No. 8 end in the Najafgarh drain in Delhi, whose level the State does not control, and the Ghaggar floodplain zone notified under section 45 of the Haryana Canal and Drainage Act 1974 is the river's own flood land. Storm water spilled to any of them uses capacity that the drain or river needs for its whole basin; it can be relied on only with the written agreement of I&WRD, for a stated flow and level, and for the Najafgarh drain in coordination with the Irrigation and Flood Control Department of Delhi (Chapter 5).

The first point is the basis of condition 4.13.2(c) in Haryana. A johad or talab gives flood storage only above its full level, unless a notified operating rule commits it to be lowered before the SW monsoon. The 3-year operational limit and the 10-year maintenance allowance have no direct precedent and are set by this Manual.


4.14 Simplified methods for small sites

4.14.1 Applicability. Tier B local bodies may permit the simplified method for sites of 2 ha or less outside flood-sensitive catchments. In flood-sensitive catchments, it may be used for sites of 0.5 ha or less. All other sites shall use Clause 4.6. Until Table 4.3 (Annex 4B) is published, all Tier B sites shall also use Clause 4.6.

4.14.2 Method.

  1. Read the PSD (L/s/ha) and SSR (m³/ha) for the site's zone, HSG and post-development imperviousness from Table 4.3 (Annex 4B).
  2. Required storage: V = SSR × A − V_credit (Clause 4.4.6.3).
  3. Permissible discharges: Q_PSD,T = PSD_T × A for the 2-yr and 100-yr stages.
  4. Select the low-flow orifice and upper control from the standard outlet table in Annex 4B (orifice sizes for the PSD at the stated depths), subject to the 50 mm minimum.
  5. Provide a spillway or overflow under Clause 4.9, the RWH accounting of Clause 4.11, and the safety provisions of Clause 4.15.
  6. Complete Form 4-2 (Tier B site sheet).

Table 4.3 — Tier B permissible site discharge and site storage requirement (template)

Zone (Annex 2A) HSG Imperviousness PSD 2-yr (L/s/ha) PSD 100-yr (L/s/ha), standard PSD 100-yr (L/s/ha), flood-sensitive SSR (m³/ha), standard SSR (m³/ha), flood-sensitive
HR-Z1 Shivalik foothills: HR-A Shivalik foothills and choes A / B / C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
HR-Z2 Northern, NCR and central plains: HR-B Upper Yamuna–Ghaggar plains B / C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
HR-Z2 Northern, NCR and central plains: HR-C NCR south (Aravalli–Sahibi) B / C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
HR-Z2 Northern, NCR and central plains: HR-D Rohtak–Jhajjar–Sonipat waterlogged belt B / C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
HR-Z3 Dry south-west: HR-E Central and south-west dry plains and dunes A / B / C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
HR-Z3 Dry south-west: HR-F Ahirwal Aravalli south A / B / C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]

Worked example (illustrative — not design values).

A 0.4 ha residential layout in a Tier B Municipality, in a flood-sensitive catchment, with about 80% directly connected impervious area (area-weighted post-development CN about 92). Suppose Table 4.3 had been computed and gave the per-hectare equivalent of the Clause 4.6.7 example:

  • PSD 100-yr = 356 / 2.0 = 178 L/s/ha
  • SSR = 2,913 / 2.0 ≈ 1,460 m³/ha
  • PSD 2-yr ≈ 17 L/s/ha

Then:

  • Storage: V = 1,460 × 0.4 = 584 m³. C_R = 0, so there is no retention credit.
  • 100-yr release: 178 × 0.4 = 71 L/s.
  • 2-yr release: 17 × 0.4 = 7 L/s. At about 1 m head this needs a low-flow orifice of about 60 mm, above the 50 mm minimum (Clause 4.8.2).
  • Layout options:
    • a 400 m² underground tank 1.5 m deep; or
    • 250 m² of podium storage at 0.3 m (75 m³) plus a 350 m² tank 1.5 m deep (525 m³).
    • Rooftop storage at 150 mm over 1,200 m² of roof (180 m³) could replace part of the tank.
  • RWH sumps are additional, and are assumed full (Clause 4.11).

Commentary. Australian councils use permissible site discharge and site storage requirement tables in the same way (Sydney Water OSD guide; the Upper Parramatta River Catchment Trust handbook listed SSR of about 455 m³/ha). The illustrative SSR here, about 1,460 m³/ha, is much larger. That is the expected effect of combining a mixed-frequency cap with mandatory 48–72-hour storms at AMC III. MSMA 2 in Malaysia offers a similar simplified OSD method for sites under 5 ha. The MARC policy supplement offers smaller Kansas City municipalities adoptable alternatives within the regional standard; Clause 4.14 follows that model for Tier B.

4.14.3 Fixed-coefficient route. As an alternative to Clauses 4.6 and 4.14.2, the designer of any site of 1 ha or less, under any Approving Authority and in any catchment, may size detention by Clauses 4.14.4 to 4.14.7. The route shall not be used where:

  • (a) the site counts tank or waterbody storage in its design (Chapter 7);
  • (b) any part of the site lies within a waterbody setback (Chapter 7); or
  • (c) the site drains to a tank cascade whose storage is counted in a downstream design.

The route sets the release caps by fixed coefficients and does not need Table 4.3. It may therefore be used before Annex 4B is published. Retention (Clause 4.4), drawdown (Clause 4.7), outlets (Clause 4.8), the spillway (Clause 4.9), the downstream and tailwater checks (Chapter 5) and water quality (Chapter 8) still apply.

4.14.4 Release caps. Two caps apply at each point where runoff leaves the site:

Q_cap,10 = 2.78 × C_10 × i_10 × A and Q_cap,2 = 2.78 × C_2 × i_2 × A

where Q_cap is in L/s; A is the site area (ha); i_10 and i_2 are the 10% AEP (10-yr) and 50% AEP (2-yr) rainfall intensities (mm/h) for a 15-minute duration at the site, from the sources of Chapter 2, with the climate factor of Clause 2.8; and C_10 and C_2 are the fixed coefficients of Table 4.3A for the site's hydrologic soil group (Clause 3.7). For a site with more than one soil group, the coefficients are area-weighted.

Table 4.3A — Fixed release coefficients (provisional)

Hydrologic soil group C_10 C_2
A (sandy, well drained) 0.05 0.02
B 0.08 0.03
C 0.15 0.08
D (clay, poorly drained) 0.25 0.15

Q_cap,10 is the maximum release for every storm up to and including the 1% AEP (100-yr) storm, in every catchment. Q_cap,2 is the maximum release for the 50% AEP (2-yr) storm. Where a cap is smaller than the discharge of a 50 mm orifice at the corresponding stage, the 50 mm orifice is deemed to comply (Clause 4.5.5.1).

4.14.5 Storage. The detention storage V (m³) is the larger of V_100 and V_2, each the largest over the durations d of Clause 2.5.2 (1 to 72 hours):

V_100 = max over d of [ 10 × C_v × P_100(d) × A − 1.8 × Q_cap,10 × d ]

V_2 = max over d of [ 10 × C_v × P_2(d) × A − 1.8 × Q_cap,2 × d ]

where P_100(d) and P_2(d) are the 1% and 50% AEP rainfall depths (mm) for duration d (hours), with the climate factor; and C_v is the post-development volumetric coefficient: the composite C of Table 3.2 (upper half of each range), multiplied by Cf of Table 3.3 for the 1% AEP. For durations of 12 hours or more, C for every pervious surface shall be taken as not less than 0.50. The factor 1.8 assumes an average release of half the cap over the storm (3.6 × 0.5).

4.14.6 Outlet. The outlet shall be a two-stage control: a low-flow orifice that passes Q_cap,2 when the storage holding V_2 is full, and an upper orifice or weir that limits the total release to Q_cap,10 at the top of V. The outlet table of Annex 4B may be used once it is published.

4.14.7 Retention. The retention volume of Clause 4.4 is provided in addition to V. No retention credit (Clause 4.4.6) is taken under this route.

Figure 4.3 — Fixed-coefficient route: release caps, storage by the mass-curve method and two-stage outlet (schematic) Schematic. Left: cumulative inflow volume against storm duration for the 1% and 50% AEP storms, with straight release lines 1.8 x Q_cap x d; the storage is the largest vertical gap. Right: two-stage outlet. Not to scale. Fixed-coefficient route for sites of 1 ha or less (Clauses 4.14.3–4.14.7) — schematic, not to scale 0 12 24 36 48 60 72 Storm duration d (h) Volume (m³) V_100 = largest gap V_2 = largest gap 1% AEP inflow 10·C_v·P_100(d)·A Release line 1.8·Q_cap,10·d 50% AEP inflow 10·C_v·P_2(d)·A Release line 1.8·Q_cap,2·d Dots: durations of Clause 2.5.2 (1, 2, 3, 6, 12, 24, 48, 72 h). Pervious C ≥ 0.50 for d ≥ 12 h. Two-stage outlet (Clause 4.14.6) Top of V Top of V_2 Overflow / spillway (Clause 4.9) Upper orifice or weir: total release ≤ Q_cap,10 at top of V Low-flow orifice (≥ 50 mm): passes Q_cap,2 at top of V_2 Retention (Clause 4.4) is provided in addition; no retention credit (Clause 4.14.7) Q_cap,10 = 2.78 × C_10 × i_10 × A ; Q_cap,2 = 2.78 × C_2 × i_2 × A ; (L/s; A in ha; i in mm/h) C_10, C_2 from Table 4.3A by soil group; i_10, i_2 for a 15-minute duration with the climate factor (Clause 2.8) V = max(V_100, V_2); V_T = max over d of [ 10 × C_v × P_T(d) × A − 1.8 × Q_cap × d ] (m³) ; 1.8 = 3.6 × 0.5 (average release of half the cap)

Figure 4.3 — Fixed-coefficient route for sites of 1 ha or less (Clauses 4.14.3 to 4.14.7): the release caps Q_cap,10 and Q_cap,2 from Table 4.3A; the storage V as the largest gap, over the durations of Clause 2.5.2, between the cumulative inflow 10·C_v·P(d)·A and the release line 1.8·Q_cap·d, for the 1% and 50% AEP storms; and the two-stage outlet that passes Q_cap,2 at the top of V_2 and Q_cap,10 at the top of V. Schematic, not to scale. Original drawing for this Manual, adapted from the rainfall mass-curve (inflow minus outflow) storage concept and the single-coefficient peak cap of the PUB Code of Practice on Surface Water Drainage, 7th ed. (cl. 7.1.5).

Commentary. The fixed-coefficient route follows Singapore, which caps the peak runoff from every development of 0.2 ha or more with one runoff coefficient, C = 0.55, applied to the 10-yr storm (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5, Addendum No. 3, 2025). It is quick to apply and quick to check: the cap needs only the site area, the soil group and two intensities. PUB's 0.55 is not used here, because Singapore's baseline is the existing urban drainage system, while this Manual's baseline is greenfield land (Clause 4.5.1.2). The coefficients of Table 4.3A are set by this Manual from the greenfield curve numbers of Clause 3.3 (CN 39, 61, 74 and 80 for soil groups A to D). They are the ratios of runoff to rainfall that those curve numbers give for 1-hour depths typical of the Gurugram plain, rounded down. They are therefore provisional. The State Stormwater Technical Committee shall confirm or revise them against NIH-DHAARA values for each zone when it issues Annex 4B.

The route is deliberately stricter than the full method, so that simplicity costs the developer storage rather than costing the people downstream. The 100-yr release is held to about the greenfield 10-yr peak everywhere, which is the flood-sensitive rule of Clause 4.5.3; the storage assumes the outlet releases only half the cap on average; pervious ground is assumed wet in long storms; and no retention credit is taken. A designer who wants a smaller tank can use the full method of Clause 4.6. The storage formula is the rainfall-mass (inflow minus outflow) method. Clause 3.4.2 otherwise forbids rainfall-based peak methods for storage, because they ignore the shape of the hydrograph; this route is a stated exception because its conservative assumptions cover that error for small sites, and the 24- to 72-hour durations are always checked.


4.15 Safety, fencing and multi-use

4.15.1 Depth limits for publicly accessible storage. Where the public has access to a storage area (parks, playfields, open space, school grounds):

  • (a) maximum depth in the 10% AEP storm: 0.45 m;
  • (b) maximum depth in the 1% AEP storm: 1.2 m, except in a fenced zone under 4.15.3;
  • (c) side slopes: no steeper than 4H:1V, with at least a quarter of the perimeter at 6H:1V or flatter for escape; and
  • (d) no vertical drop greater than 0.3 m within the storage area or at its edge.

4.15.2 Wet basins. Permanent pools shall have:

  • a safety bench at least 3 m wide, no more than 0.3 m below the normal water level; and
  • an emergent planting fringe that deters entry.

4.15.3 Fencing. A fence at least 1.2 m high, of a non-climbable design with a lockable gate, is required around any part of a storage that:

  • has a vertical wall or headwall drop greater than 0.6 m;
  • exceeds 1.2 m depth in the 1% AEP storm with slopes steeper than 4H:1V; or
  • contains an outlet structure with an opening larger than 300 mm that is not grated.

4.15.4 Outlets. Every inlet and outlet opening larger than 300 mm accessible to the public shall be fitted with a grate or rack. The grate shall be designed so that a person pinned against it can escape: low approach velocity, inclined, with a large open area.

4.15.5 Signs and depth markers. Every publicly accessible storage shall have signs in Hindi and English stating that the area floods during rain, and a depth marker at the deepest point.

4.15.6 Confined spaces. Underground tanks shall have lockable covers. They shall be marked as confined spaces, and the maintenance declaration (Chapter 10) shall state the entry procedure.

4.15.7 Vector control. Dry storage shall drain completely (Clause 4.7) and have no low points that pond for more than 72 hours. Wet basins shall meet Clause 4.10.7.

Commentary. The numeric limits in Clause 4.15 have no single direct precedent. They are drawn from common international practice, for example KC APWA 5600 (2006), which required at least a quarter of a dry-pond perimeter at 5:1 or flatter, a 20 ft (6 m) clearance from property lines and a 15 ft (4.6 m) maintenance strip. They are made somewhat stricter here because multi-use storage on open space land and in schools will be used by children during the monsoon. Standing water in dry basins is a mosquito-breeding risk, so complete drainage (Clause 4.15.7) is a public-health requirement, not an amenity.


4.16 Basis: why peak matching alone fails

Commentary. This section has no requirements. It records why this chapter requires release below pre-development rates, retention, long-duration checks and a downstream analysis, rather than simple peak matching.

  1. Timing. Detention lowers a site's peak but stretches its hydrograph (Figure 4.1). Downstream, the stretched releases from many sites overlap with each other and with the main-stem peak. In Denver's study, ten basins each releasing 100% of the historic 100-yr peak produced 106% of the historic peak at the outlet. Only releasing 90% at each site brought it to 97% (UDFCD memo, 2012). A Colorado State University thesis found that location-blind on-site detention "can actually increase peak flows above post-development peaks". An optimisation study found that a downstream pond performed worse than upstream ponds because its outflow synchronised with the main stem (Water 2016, 8(7):290).
  2. Volume. Detention does not remove volume. In the illustrative example, the post-development 100-yr storm produces about three times the runoff volume of the pre-development 10-yr storm (Clause 2.11). Only retention, or storage that empties to somewhere other than the receiving drain, reduces volume.
  3. Scale. Kansas City modelling (McEnroe, 2005) found that uniform 3 cfs/ac control reduced Q100 by 36% in a 200-ac watershed. With the same control everywhere, Q100 still rose by 40% at 14 sq mi, and the benefit faded beyond about 1–2 sq mi. The KC committee concluded that "'match existing' can harm streams" (MARC Evolution deck). Georgia makes a ten-percent downstream analysis mandatory for the same reason: "Due to peak flow timing and runoff volume effects, some structural practices fail to reduce discharge peaks to pre-development levels downstream" (GSMM 2016).
  4. Design-storm dependence. An Australian study of 20 real on-site detention systems found that designs using even ten temporal patterns "cannot reliably produce an OSD system design that will always be effective" under real rainfall (Water Science and Engineering, 2019). This is why Clause 4.6.3 routes the full duration matrix rather than one critical storm.
  5. Closed outfalls. In Haryana, the governing failure is volume with no outlet when the receiving water is high. Gurugram's master drains end in the Najafgarh drain, which is held up by its own flood from the Sahibi and Outfall Drain No. 8 and, at its outfall in Delhi, by the Yamuna; GMDA describes the city's drainage as three master drains "having outfall into Najafgarh Drain" (GMDA status report in NGT O.A. 454/2018), and the capacity actually available at the Khandsa bottleneck of the Badshahpur drain has been reported as about 800 cusecs (as reported). Outfall Drain No. 8 ends at the Dhansa regulator on the Delhi border; its capacity is 4,000 cusecs, but 5,000 cusecs was observed there in 2022 (I&WRD report in NGT O.A. 627/2022), and in the Sahibi flood of 6 August 1977 the water stood at 213.575 m above Dhansa against a bund top of 214 m (Delhi I&FC). The towns of the Yamuna bank outfall through gates that are closed when the river rises: Hathnikund passed about 8.28 lakh cusecs on 18 August 2019 and about 3.59 lakh cusecs in July 2023, and the river has reached 250.07 m at Karnal, 0.57 m above its danger level (CWC; as reported). Releases from Hathnikund take about 35–75 hours to reach Delhi, 237 km downstream (MoJS committee interim report, January 2024), which gives warning of the river but none of a local burst, and the two can come together: Chandigarh recorded 302.2 mm and Ambala 224.1 mm on 9 July 2023, two days before the Hathnikund peak of 11 July (IMD; MoJS committee). On the Ghaggar there is no CWC flood gauge, and the river breached its banks near Ambala and in Kaithal, Fatehabad and Sirsa in July 2023 (as reported). In the Rohtak–Jhajjar–Sonipat belt much of the land drains only by pumping, to drains that could carry only the 1- and 2-day rainfall of 5-year return period when they were studied (Irrigation and Drainage, 2006, from a search summary [TBC]). A perfectly orificed basin behind a closed outfall simply fills. No release-rate rule can fix that; it is handled by the outfall-closed check of Chapter 5.

The response in this Manual is layered:

  • release below pre-development (Clause 4.5);
  • retain the frequent storms (Clause 4.4);
  • route long SW monsoon storms (Clause 4.6.3);
  • prefer regional storage in the johad system (Clause 4.13); and
  • check downstream and at the outfall (Chapter 5).

Kansas City's own history shows the price. On a test site, peak matching needed 3.0 ac-ft of storage and the 2011 comprehensive criteria needed 4.9 ac-ft (MARC Evolution deck). Over-detention costs more storage. That is the cost of protecting the catchment rather than only the site boundary.


4.17 Submittal requirements

Every site runoff-control submittal shall include a Site Runoff Control Report (Form 4-1) containing:

  1. the Design Rainfall Sheet (Form 2-1) and the hydrology inputs (Chapter 3);
  2. the evidence for the order of measures under Clause 4.3.1;
  3. the RRV computation, infiltration tests, groundwater evidence and drawdown calculation (Clause 4.4);
  4. the retention credit computation (Clause 4.4.6);
  5. the release-rate criterion applied, standard or flood-sensitive, with the Annex 4A map extract (Clause 4.5);
  6. a results table in the format of Clause 4.6.7 for every AEP and duration, with the governing case highlighted;
  7. stage–storage and stage–discharge tables and plots, and inflow/outflow hydrographs for the governing cases;
  8. the drawdown calculation (Clause 4.7);
  9. outlet details, including orifice sizes and levels, trash racks and anti-vortex devices (Clause 4.8);
  10. the spillway or overflow calculation, freeboard and hazard classification, and the geotechnical report where required (Clause 4.9);
  11. the RWH and detention accounting, with tank sections showing zone levels (Clause 4.11);
  12. the design groundwater level and flotation check (Clause 4.12);
  13. the downstream and tailwater report (Chapter 5, Form 5-1); and
  14. the safety provisions (Clause 4.15) and the draft maintenance declaration (Chapter 10).

Tier B sites using Clause 4.14.2 shall submit Form 4-2 in place of items 6 and 7. Sites using the fixed-coefficient route (Clause 4.14.3) shall submit Form 4-3 in place of items 6 and 7.


References (chapter)

Annexes and forms

Annex / Form Content
4A Flood-sensitive catchment boundaries (GIS); shallow-groundwater zone map
4B Tier B tables: PSD and SSR (Table 4.3), retention credit factor C_R, standard outlet sizes; confirmed fixed release coefficients (Table 4.3A)
4C Worked example (Tier A) with full routing tables
Form 4-1 Site Runoff Control Report
Form 4-2 Tier B Site Sheet
Form 4-3 Fixed-coefficient Route Sheet (Clauses 4.14.3 to 4.14.7)