Chapter 10Submittals, Review, Operation & Maintenance and Enforcement


10.1 Purpose and scope

10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:

  • (a) the submittal stages and their contents (Clauses 10.3–10.4);
  • (b) the compliance calculator (Clause 10.5);
  • (c) professional certification and review (Clauses 10.6–10.7);
  • (d) construction inspection and as-built certification (Clauses 10.8–10.9);
  • (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
  • (f) handover of public assets (Clause 10.14);
  • (g) enforcement (Clause 10.15); and
  • (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).

10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.

Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Haryana the failure is one of missing criteria and of conditions checked only for rainwater harvesting. No document of DTCP, HSVP, the Urban Local Bodies Department, a Municipal Corporation, GMDA or FMDA stating a design return period for urban storm drains was found; the only urban figure on record is the 25 mm/h and runoff coefficient of 1/8 that the NCR Planning Board reports for Haryana's urban channels (2016). The approval route shapes this chapter. The Haryana Building Code 2017 is a departmental code, not a Gazette notification: it was circulated by the Town and Country Planning Department under memo No. Misc-138-A-Loose/7/5/2006-2TCP of 7 March 2017, applies to the whole State from 6 January 2017 (Code 1.1(2)), and is applied by each Competent Authority under its own Act (Code 1.2(1)(ii)), that is by DTCP for colonies licensed under the Haryana Development and Regulation of Urban Areas Act 1975, by HSVP in its sectors under the HSVP (HUDA) Act 1977, and by the Municipal Corporations, Councils and Committees under the Haryana Municipal Corporation Act 1994 and the Haryana Municipal Act 1973; it is amended by further memos (27 May 2020 and 19 January 2022 read; 8 December 2025 and 5 June 2026 reported; no amendment to its rainwater harvesting, plinth or basement clauses was found). Under it the site plan must show existing drains (Code 3.2), the building plan must show "the method of disposal of … storm water" and the rainwater harvesting system (Code 3.4(2)(vi)–(vii)), the plinth must be 450 mm to 1.5 m high so that "proper drainage of the site is assured" (Code 7.3), and basement drainage is the owner's responsibility (Code 7.16(5)(iv)); an architect or engineer certifies that the rainwater harvesting system works, and the occupation certificate is withheld until it is built (Code 8.1(3)(vii) and (ix)); and for 5,000–20,000 m² built-up the natural drainage inlets and outlets must be kept and at least 20% of the recreational open space left unpaved, certified with the occupation certificate application (Code 12.1). The licence for a colony includes its storm drains, as internal development works built by the colonizer and as external development works executed by HSVP (HDRUA Act 1975, s.2, as quoted by DTCP). In a Municipal Corporation no premises may be built or occupied until a drain is made "of such size, materials, and with such fall" as effectual drainage needs, to a Corporation drain within 30 m (HMC Act 1994, s.198), no drain may communicate directly with a storm water overflow drain (s.196), and nothing may be built on a municipal drain without the Commissioner's written permission (s.206). A spatial or development plan that covers a pond needs the prior approval of the Haryana Pond and Waste Water Management Authority (Pond Authority Act 2018, s.17); an obstruction within the limits notified under s.45 of the Haryana Canal and Drainage Act 1974, as on the Ghaggar floodplain in Panchkula, needs I&WRD's permission; an outfall to an I&WRD drain needs I&WRD's consent; and in Gurgaon district, a CGWA notified area since 2011, the groundwater rules apply. No rule asks for a drainage report, limits peak runoff, requires on-site detention or sets a setback from a drain, river or pond, and no I&WRD rule barring construction within a set distance of a drain or canal was found. Every stormwater item in this chapter is therefore written so that the architect or engineer on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it with the building plan, with the licence and at the occupation certificate. This chapter is the process.


10.2 Definitions

Term Meaning in this chapter
Submittal A set of documents lodged with the Authority at one of the stages of Clause 10.3.
Drainage report The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4.
Stormwater facility Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private.
Hold point A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8).
As-built certificate The certificate of Clause 10.9 that the facility was built as approved and performs as designed.
Owner The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset.
O&M plan The operation and maintenance plan of Clause 10.11.
Facility register The public register of facilities of Clause 10.17.

Other terms are defined in Clause 1.4.


10.3 Submittal stages

10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Haryana Building Code 2017 (Table 10.1):

Table 10.1 — Submittal stages and linked approvals

Stage Submittal When Linked approval
0 Pre-application meeting and Form 1-1 (Applicability Determination) Before the planning permission or layout application None (advisory record)
1 Preliminary drainage report With the planning permission or layout application Planning permission / layout approval
2 Final drainage design Before building permit, or before commencement where the permit is issued with the planning permission Building permit / commencement
3 Construction inspections at hold points During construction None (records filed)
4 As-built certificate and verification tests Before the completion certificate Completion / occupancy certificate
5 Maintenance declaration registered, or handover of public assets Before or with the completion certificate Completion certificate; asset acceptance
6 Annual declarations and inspection reports Every year after completion Continuing compliance

10.3.2 Stage 0 is mandatory for:

  • (a) sites of 2 ha or more;
  • (b) sites in a flood-sensitive catchment;
  • (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
  • (d) sites draining to a tidal outfall or adjoining a waterbody.

For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.

10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.

10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.

10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.

Figure 10.1 — Submittal, review and approval workflow Two columns: applicant stages 0 to 6 on the left, Approving Authority actions and approval gates on the right. Stages 1 and 2 can be returned with comments for resubmittal. Stage 6 repeats every year. Applicant / certifying professional Approving Authority Stage 0 — Pre-application Form 1-1 Applicability Determination Confirms applicability; advises Mandatory: ≥ 2 ha, flood-sensitive, waterbody Stage 1 — Preliminary drainage report Forms 2-1, 10-1, 10-2, 10-3 comments Check 5 days; review 15 (resubmit 10) → Planning permission / layout Stage 2 — Final drainage design Models, GIS, draft O&M plan, Form 10-3 comments Review 15 working days (resubmit 10) → Building permit / commencement Stage 3 — Construction Hold-point inspections, Form 10-4 Notified of key hold points (3 working days); may attend Stage 4 — As-built certification Survey, re-run, drawdown tests, Form 10-5 Accepts as-built certificate → Completion certificate Stage 5 — Maintenance declaration Form 10-6, or handover with Form 10-8 Enters facility / asset register → Public asset accepted Stage 6 — Every year, pre-monsoon Form 10-7 annual declaration Inspects; enforces (Clause 10.15) Publishes register (Clause 10.17) yearly Approval gate (accent text) Returned with comments; resubmit Periods in working days (Clause 10.7)

Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.

Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the HBC 2017 steps a Haryana applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.


10.4 Required contents and checklists

10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:

  • (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
  • (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
  • (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
  • (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
  • (e) the pre-development condition and hydrologic method (Chapter 3);
  • (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
  • (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
  • (h) the downstream extent and tailwater case (Chapter 5);
  • (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
  • (j) the land reserved for facilities and maintenance access (Clause 10.13).

10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:

  • (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
  • (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
  • (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
  • (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
  • (e) construction drawings, details and specifications of every facility;
  • (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
  • (g) the hold-point schedule (Clause 10.8);
  • (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
  • (i) the model input files and the GIS data of Clause 10.4.4; and
  • (j) the certificates of Clause 10.6.

10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.

10.4.4 Digital submittal.

  • (a) Reports and drawings shall be submitted as searchable PDF.
  • (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
  • (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (43N), with attributes as listed in Annex 10B.
  • (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the CWC and I&WRD gauges on the receiving rivers and of I&WRD's drain, regulator and embankment levels, and, for a drain that reaches the Najafgarh drain, the levels of Delhi's Irrigation and Flood Control Department used in Chapter 5 shall be stated.

10.4.5 Summary of forms used in submittals (Table 10.2):

Table 10.2 — Forms used in submittals

Form Title Stage
1-1 Applicability Determination 0 or 1
1-2 Variance / Waiver Request 1
2-1 Design Rainfall Sheet 1, 2
10-1 Drainage Report Checklist 1, 2
10-2 Compliance Calculator Summary 1, 2, 4
10-3 Professional Design Certificate 1, 2
10-4 Hold-Point Inspection Record 3
10-5 As-built Certificate 4
10-6 Maintenance Declaration 5
10-7 Annual Maintenance Declaration and Inspection Report 6
10-8 Asset Handover Certificate 5

Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Haryana has no notified design return period or design storm for its urban drains. The NCR Planning Board's Functional Plan on Drainage for NCR (2016) reports that Haryana's drains were sized by the Boston Society formula Q = 200·√A (cusecs, square miles) cut by ad-hoc reduction factors of 1/12 to 1/4, and its urban channels for "25mm per hour" with a runoff coefficient of 1/8; it proposed, but did not make binding, a 5-year storm for internal and peripheral urban drains, a 10-year storm for main drains and a runoff coefficient of at least 0.6. The Sub-Regional Plan for the Haryana sub-region of NCR (2021) sizes rural drains for "three days rainfall of five years frequency to be drained in three days" and refers urban drains to CPHEEO. DTCP's master storm water drainage drawing for the Gurugram–Manesar Urban Complex (2012) gives Legs I, II and III (Badshahpur) as 541, 1,305 and 3,702 cusecs, and HUDA's catchment management plan for the Badshahpur drain (2017, revised 2020) gives reach discharges of up to 2,300 cusecs, but neither states a return period or a rainfall intensity. These figures are history, not a design basis: 25 mm/h is below the 2-year 1-hour intensity of 43.7 mm/h used for Delhi in 1976 (NCR Planning Board, 2016). In IMD's national IDF study (Das et al. 2022) the Hissar panel repeats a generic curve drawn for several other cities and is not used, and no station IDF has been published for any Haryana station. The State's sub-daily design values are therefore the CWC Flood Estimation Report for subzone 1(e) with the interim floors of Chapter 2, which in the NCR south take the absolute floors of the Delhi edition. Form 2-1 and Form 10-2 therefore carry the whole design basis of each submission. Form 2-1 and Form 10-2 ensure that every design states its inputs.


10.5 Compliance calculator

10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:

  • (a) applies the applicability tests of Clause 1.5;
  • (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
  • (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
  • (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
  • (e) on alternative S-2, gives the permissible site discharge for each AEP; and
  • (f) produces the Compliance Calculator Summary (Form 10-2).

10.5.2 Use.

  • (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
  • (b) On the design-aid route, the calculator may be the only storage calculation.
  • (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.

10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.

10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.

Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Haryana calculator serves Tier B authorities in particular, where it may be the whole calculation.


10.6 Professional certification

10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or DTCP:

  • (a) Tier A sites of 1 ha or more;
  • (b) any site in a flood-sensitive catchment;
  • (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
  • (d) any pumped facility, tide gate or regional facility.

10.6.2 Empanelment criteria shall be issued by DTCP and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.

10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:

  • (a) the design complies with this Manual, except for variances listed and approved;
  • (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
  • (c) the models submitted reproduce the results reported.

10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.

10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.

Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the HBC 2017 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.


10.7 Review procedure and timelines

10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.

10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:

  • (a) 15 working days of acceptance for a first submittal; and
  • (b) 10 working days of acceptance for a resubmittal.

10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.

10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the DTCP list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.

10.7.5 Concurrent clearances. Where the consent of I&WRD for an outfall to, or a work on, one of its drains, canals, embankments or regulators, or for an obstruction within limits notified under s.45 of the Haryana Canal and Drainage Act 1974, such as the Ghaggar floodplain in Panchkula, the prior approval of the Haryana Pond and Waste Water Management Authority for a spatial or development plan that covers a pond, or its permission for construction in a pond's protected area (Haryana Pond and Waste Water Management Authority Act 2018, s.17), the written permission of the Commissioner to build on a municipal drain (Haryana Municipal Corporation Act 1994, s.206), the prior approval of the Central Pollution Control Board and the Haryana State Pollution Control Board for plans within 1–5 km of the Badkhal and Surajkund lakes (Supreme Court, 1996), the approval of the Wetland Authority of Haryana for a regulated activity in a notified wetland, the consent of the body that owns the receiving drain where that body is not the Authority (for example GMDA, FMDA, HSVP or HSIIDC), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.

10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.

10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.

Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.


10.8 Construction inspection

10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:

  • (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
  • (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
  • (c) the infiltration tests of Clause 10.9.3;
  • (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
  • (e) pumps and controls, at commissioning.

10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.

10.8.3 Protection during construction.

  • (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
  • (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
  • (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.

Figure 10.2 — Construction hold points from approval to handover Vertical timeline from Stage 2 approval through construction, verification tests and as-built certification to the maintenance declaration or asset handover. Diamonds mark hold points (a) to (e) of Clause 10.8.1; each step shows the form used. Construction hold points: approval to as-built and handover (not to scale in time) Hold point: work stops until inspected and recorded Other required step Stage 2 Approval Stage 3 Construction Stage 4 Tests and as-built Stage 5 Declaration or handover Final design approved; hold-point schedule set Schedule of hold points approved with the design (Cl. 10.4.2(g), 10.8.1) Form 10-4 (schedule) Protect retention and infiltration areas Fenced off from traffic and stockpiles (Cl. 10.8.3(a)) (a) Excavated base of each facility Retention, infiltration, detention: before media, liner or structure Form 10-4 3-day notice * (b) Outlet structure, orifice, trash screen Before backfill, or before the facility is first allowed to fill Form 10-4 3-day notice * (d) Outfall, flap or tide gate, non-return valve Before the downstream connection is made Form 10-4 (e) Pumps and controls At commissioning Form 10-4 Area stabilised; temporary sediment removed Infiltration not in service until stabilised (Cl. 10.8.3(b), (c)) (c) Verification tests Infiltration retention empties within 72 h; pumps at duty point; gates open and seal (Cl. 10.9.3) Form 10-4 As-built survey and re-run; certificate accepted Licensed surveyor; calculator and model re-run; then completion certificate (Cl. 10.9) Forms 10-5, 10-2 Private facility: maintenance declaration Registered to run with the land; owner and successors bound (Cl. 10.10) Form 10-6 Public asset: handover to the ULB Cleaned, inspected inside, land or easement transferred; defects liability for at least one full monsoon season (Cl. 10.14) Form 10-8 * Notice: for sites under Clause 10.6.1 the Authority is given at least 3 working days’ notice of hold points (a) and (b), and may attend. Every hold point is inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs (Cl. 10.8.2).

Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.

Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.


10.9 As-built certification

10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:

  • (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
  • (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
  • (c) the completed hold-point records (Form 10-4); and
  • (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).

10.9.2 Acceptance. The as-built facility is accepted where:

  • (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
  • (b) the outlet dimensions and inverts match the approved design; and
  • (c) the re-run shows compliance with every criterion of Chapters 4 and 5.

Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.

10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.

10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.

Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.


10.10 Maintenance declarations and covenants

10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:

  • (a) identify each facility, its location and the approved O&M plan;
  • (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
  • (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
  • (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
  • (e) be registered so that it runs with the land and is disclosed to purchasers.

10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.

10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 15 June each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.

10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.

Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Haryana because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 15 June date is set by this Manual to fall before the south-west monsoon (June–September), when most Haryana extreme rainfall occurs.


10.11 O&M plans

10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:

  • (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
  • (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
  • (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
  • (d) inspection checklists matching Form 10-7;
  • (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
  • (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
  • (g) safety measures for confined spaces, deep water and public access;
  • (h) access routes and equipment needed (Clause 10.13);
  • (i) an annual cost estimate and who pays it; and
  • (j) the records to be kept, and for how long.

10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.

Commentary. Haryana runs its monsoon season through the Haryana State Drought Relief and Flood Control Board, chaired by the Chief Minister, which approves flood-control schemes each year and has directed that short-term schemes, pump procurement and drain cleaning be finished before 30 June, or in one direction before 15 June (as reported), and through district flood control plans supervised by the Deputy Commissioners (as reported); no urban flood plan of HSDMA was found. For the town drains the orders found are local: Gurugram's pre-monsoon plans list 111 to 159 waterlogging hotspots (as reported), GMDA desilts the master drains without a published date (as reported), and the Union Ministry of Housing and Urban Affairs reported 141 pumps and 77 suction tankers deployed in Gurugram (Lok Sabha, 2025, as reported); in July 2023 the Municipal Corporation of Ambala ran 19 pump sets and I&WRD deployed inventory pumps of 962 cusecs against the Ghaggar (Haryana Vidhan Sabha reply). The rivers are run by gate operation: at Hathnikund barrage only the spillway bays are operated up to an inflow of 70,000 cusecs and all gates are fully opened at 2,15,400 cusecs and above (MoJS committee, 2024). No operating rule for any regulator, sluice, flap gate or pumping station in a Haryana town, linking it to a river stage, a release from Hathnikund barrage or the Kaushalya dam, or a rainfall warning, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.


10.12 Inspection frequencies

10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:

Table 10.3 — Minimum owner inspection frequencies

Facility type Routine Pre-monsoon (by 15 June) After a heavy-rainfall event
Retention / infiltration (soakaways, trenches, bioretention, permeable paving) Every 6 months Yes Yes
Surface detention basin or multi-use open space area Every 6 months Yes Yes
Underground or podium detention tank, gravity outlet Every 6 months Yes Yes
Pumped detention, pumps and controls Monthly test run Yes, with full duty test Yes
Flap / tide gate, non-return valve Every 3 months Yes, with seal test Yes
Gross pollutant trap / first-flush device Every 3 months Yes Yes
Private drains and inlets Every 6 months Yes —

A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Haryana, the pre-monsoon inspection of regulators, sluices, flap gates, non-return valves and pumped facilities, including the pumps at underpasses and at outfalls to I&WRD drains, with the pump duty and gate seal tests, shall be completed by 15 June; these facilities, with their standby generators, shall be certified ready by 25 June, before the normal onset reaches the State (27 June at Sonipat to 3 July at Hisar), with every gate on an outfall to a river or an I&WRD drain operated through its full travel. Pumps, their standby power and the gates shall then be kept on monsoon standby, with the monthly test run, until 30 September, and at an outfall to the Yamuna or the Ghaggar until the river at the governing gauge has fallen below its danger level and the releases upstream have ended, if that is later.

10.12.2 Authority inspections. The Authority shall inspect:

  • (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
  • (b) a random sample of at least 10% of other facilities each year.

10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).

Figure 10.3 — Maintenance cycle and responsibility A one-year strip from January to December with the south-west monsoon (early July to late September) shaded, and the onset period from 27 June to 3 July and the withdrawal period from 21 to 25 September shaded more lightly. Lanes show routine inspections, the pre-monsoon inspection and desilting of every facility with the Form 10-7 declaration by 15 June, the readiness of regulators, sluices, flap gates, pumps and standby generators by 25 June, pumps and gates on standby to 30 September, inspections after heavy rainfall, and Authority inspections. Boxes below show who is responsible: the owner, the ULB and the Authority. Maintenance cycle and responsibility (Clauses 10.10–10.12, 10.14) South-west monsoon Onset Late Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 15 Jun 25 Jun 30 Sep Routine Monthly: pump test run (continues through the standby period) Every 3 months: gates, valves, GPTs Every 6 months: retention, detention, drains Pre-monsoon readiness, standby By 15 Jun: desilting, pump and gate tests, defects corrected. By 25 Jun: regulators, flap gates, pumps ready. To 30 Sep: on standby After heavy rain After each day at or above IMD “heavy rainfall”, or a district red alert Annual declaration Form 10-7 Form 10-7 lodged by 15 June: Tier A facilities; pumped, gate and regional facilities anywhere Authority At least every 2 years (every year if flood-sensitive) for sites ≥ 1,000 m² or Cl. 10.6.1(c), (d); 10% random sample of others each year → facility register (Cl. 10.17) Who is responsible Owner — private facility Maintenance declaration, Form 10-6; binds successors in title (Cl. 10.10.1) Layouts and apartments: the association; the developer until it accepts (Cl. 10.10.2) Inspects; lodges Form 10-7 ULB — handed-over public asset Accepted with Form 10-8 (Cl. 10.14) O&M plan in the asset register, funded in the annual budget (Cl. 10.11.2) Developer liable for defects and routine maintenance, ≥ one monsoon to 30 Sep (10.14.2) Authority Inspects and records results in the facility register (Cl. 10.12.2–10.12.3) Enforces: notice, penalty, works in default with cost recovered (Cl. 10.15) Publishes the register (Cl. 10.17) Tick positions are illustrative; only 15 June, 25 June and 30 September are fixed. Normal onset over Haryana 27 June (Sonipat) to 3 July (Hisar); normal withdrawal 21 September (Hisar) to 25 September (Sonipat) (IMD, new normals).

Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 15 June) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the south-west monsoon (June–September); tick positions within the year are illustrative.

Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 15 June deadline is set by this Manual for the onset of the south-west monsoon in the last days of June: the normal onset is 27 June at Sonipat, 28 June at Ambala, 30 June at Bhiwani and 3 July at Hisar (IMD, 1961–2019 normals), and large falls have come at the onset, 297.9 mm at Rohtak and 261.2 mm at Gurgaon on 30 June 1981 (IMD). The State's own deadline for flood works and drain cleaning is usually 30 June, and once 15 June (as reported); 30 June falls after the onset in the north and east, so this Manual takes 15 June for desilting, the pre-monsoon inspection and the annual declaration. NDMA (2010) sets 31 March for pre-monsoon desilting nationally; this Manual allows until 15 June so that dry-season work can be finished. Regulators, sluices, flap gates, pumps and their standby generators must in addition be certified ready by 25 June, before the onset reaches Sonipat. The normal withdrawal runs from 21 September at Hisar to 25 September at Sonipat (IMD), so pumps and gates are kept on standby to 30 September (Figure 10.3), and at an outfall to the Yamuna or the Ghaggar until the river has fallen below its danger level and the releases upstream have ended, if that is later. October storms do occur, 141.6 mm at Ambala on 5 October 1973, 130.3 mm at Karnal on 9 October 1956 and 241.3 mm at Punahana on 2 October 1910 (IMD), and the post-event inspections of Table 10.3 cover storms at any time of year.


10.13 Maintenance access

10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.

10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.

10.13.3 Underground facilities. Tanks shall have:

  • (a) an access opening over the inlet, the outlet and each chamber;
  • (b) fixed ladders or steps, and ventilation for confined-space entry;
  • (c) a sump or low point for sediment removal; and
  • (d) headroom sufficient for manual cleaning.

10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.

10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.

Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Haryana cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.


10.14 Handover of public assets to the ULB

10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:

  • (a) the as-built certificate (Clause 10.9) has been accepted;
  • (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
  • (c) the land, or an easement over it, has been transferred to the ULB;
  • (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
  • (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.

10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 15 June to 30 September, after handover. The ULB may hold a security deposit for this period.

10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.

10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.

Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Haryana drainage show up only in the first SW monsoon.


10.15 Enforcement

10.15.1 Offences. The following are contraventions of this Manual:

  • (a) building without an approved drainage design where one is required;
  • (b) building a facility other than as approved;
  • (c) removing, filling, covering, reducing or changing the use of a facility without approval;
  • (d) failing to maintain a facility, or to submit Form 10-7;
  • (e) a sewage connection to a storm drain;
  • (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
  • (g) obstructing a natural drainage path or major-system flow path; and
  • (h) false or negligent certification.

10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):

Table 10.4 — Graduated enforcement response

Step Action
1 Written notice stating the contravention, the clause breached, the remedy and a compliance period.
2 Stop-work order, or withholding of the completion certificate, for development not yet complete.
3 Penalty under the applicable Act or rules.
4 Works in default by the Authority, with the cost recovered from the owner.
5 Disconnection of the private drain connection to the public system, where this causes no hazard to others.
6 Report of the certifying professional to the registering authority, and suspension from the empanelled list.

10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.

10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.

10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.

Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Haryana Building Code 2017 is issued and from the municipal Acts. The graduated steps are set by this Manual. In Haryana the courts have become the working regulators of lakes, ponds, the Aravallis and the drains. The Supreme Court barred construction in the green belt and within 1 km of the Badkhal and Surajkund lakes in Faridabad, with limited exceptions, and required the prior approval of the Central Pollution Control Board and the Haryana Pollution Control Board for every development scheme and building plan from 1 km to 5 km, noting that "the natural drainage pattern of the surrounding hill areas feed these water bodies" (M.C. Mehta, order of 11 October 1996); it later held that land notified under the Punjab Land Preservation Act 1900 is forest land and ordered constructions in Kant Enclave built after 18 August 1992 to be demolished (2018, as reported). The National Green Tribunal ordered unique identifiers and restoration for at least 123 water bodies in Gurugram and the exercise repeated statewide (OA 325/2015, 20 July 2018), has tracked the sewage in Gurugram's master drains, which must meet a BOD of 30 mg/l before they reach the Najafgarh drain (OA 454/2018), and questioned whether the procedure for the Ghaggar floodplain zone in Panchkula was followed (OA 421/2022, 22 May 2024). The Punjab and Haryana High Court, finding that "Gurugram is facing severe waterlogging during the monsoon season" while its groundwater falls and the channels that fed its water bodies "remain largely blocked", summoned officers of MCG, HSVP and GMDA (Sunil Singh, CWP-20032-2008, order of 22 September 2026). The statutes carry real powers: the Divisional Canal Officer may remove an obstruction within notified limits and recover the cost as land revenue (Canal and Drainage Act 1974, s.46); the Commissioner may remove a structure built on a municipal drain (HMC Act 1994, s.206(2)); the Pond Authority may direct the removal of any obstruction within a protected area or on pond land, and building on pond land, its green belt or catchment is punishable with a fine of up to ₹25,000 or imprisonment of up to three months (Pond Authority Act 2018, ss.14, 15 and 20); and no occupation certificate is issued until rainwater harvesting is built (HBC 2017, Code 8.1(3)(ix)), a duty HSVP now asks allottees to reaffirm by undertaking (2024). DTCP issued more than 150 show-cause notices in one Gurugram colony in June 2025, among them for fully covered basements (as reported). CAG's Report No. 4 of 2026 includes a chapter on sewage and sewerage management in the urban areas of Haryana (as reported; the report could not be downloaded), and no audit by CAG of urban storm drainage, of GMDA or of HSVP drainage was found. This shows that a rule without routine enforcement does little, and that where the State has not drawn a line the courts have. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.


10.16 Monitoring and post-event review

10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.

10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:

  • (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
  • (b) the level of the receiving river (the Yamuna at Hathnikund barrage or at the CWC gauges at Karnal and Mawi; the Ghaggar, the Tangri or the Markanda at the nearest I&WRD gauge) or of the receiving I&WRD drain, and, where it is gauged, at the outfall, each on a named datum; for a drain that reaches the Najafgarh drain, the level and flow at its outfall and at the Dhansa regulator; the state of every regulator, sluice, flap gate and pumping station on the outfall and on the drain upstream of it, including those at underpasses, with the hours each pump ran and any loss of power; and the releases from Hathnikund barrage, the Kaushalya dam or any other barrage, dam or regulator that set the receiving level;
  • (c) flooded locations, depths and durations, with flood marks surveyed where possible;
  • (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
  • (e) recommended actions.

10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), HSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.

10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.

Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Haryana's urban floods have been examined by the courts and the press rather than by technical reviews. On 28 July 2016 Gurugram's NH-48 was jammed for more than 18 hours after about 46–54 mm of rain, figures that conflict and none of which is an IMD reading (as reported); the 91.8 mm often quoted for that day is from a report of 2021. On 19 August 2020 the city's underpasses flooded within half an hour of a three-hour spell (as reported); on 31 July 2024 three people were electrocuted near IFFCO Chowk in ponded water (as reported); and on 1 September 2025 more than 100 mm fell in four hours, by the district administration's account (as reported). On 9 July 2023 Chandigarh recorded 302.2 mm and Ambala 224.1 mm (IMD, real-time data), and the Ghaggar and its choes breached at Ambala, Kaithal, Fatehabad and Sirsa in the days that followed (as reported). On the Yamuna, Hathnikund barrage passed 8.28 lakh cusecs on 18 August 2019 (as reported) and 3,59,760 cusecs on 11 July 2023 (MoJS committee, 2024). The records of the past are larger still: 484.1 mm at Rohtak on 19 September 1933 and 398.8 mm at Palwal on 9 September 1875 (IMD). The Punjab and Haryana High Court took up Gurugram's waterlogging in 2026 (Sunil Singh), and the Haryana Human Rights Commission was reported to have opened a suo motu case after the floods of August 2026 (as reported). No technical review of any of these events was found, and no record of flood extents, depths or durations kept by any Municipal Corporation, GMDA or FMDA was found. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.


10.17 Data publication

10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:

  • (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
  • (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
  • (c) the register of variances and waivers (Clause 1.10);
  • (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
  • (e) enforcement actions (Clause 10.15.5); and
  • (f) event reports and post-event reviews (Clause 10.16).

10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.

10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.

10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.

Commentary. Transparency is a design criterion in its own right here. Some of Haryana's drainage records are public: the Haryana Building Code 2017 and its amendment memos (in archived copies of the DTCP website), the Acts on the Pond Authority, the Canal and Drainage Act, the Municipal Corporations and GMDA (in PRS copies), the reports that GMDA, I&WRD, DTCP, the Pond Authority and the Wetland Authority have filed before the National Green Tribunal, including GMDA's copies of the master drainage drawings of Gurugram, replies in the Vidhan Sabha, the NCR Planning Board's drainage plan, the Sub-Regional Plan for the Haryana sub-region of NCR, CGWB's groundwater assessments and the Water Resources Atlas of the Haryana Water Resources Authority. Much else could not be found in the public domain: the hydrology behind the capacities of Gurugram's master drains, and GMDA's drainage master plan; any drainage norm of HSVP, FMDA or the Panchkula Metropolitan Development Authority; the Gazette text of the Ghaggar floodplain notification under s.45; any protected-area notification under the Pond Authority Act; the texts of the Building Code amendments of December 2025 and June 2026; an inventory of the regulators, sluices, flap gates and pumping stations of any town, with their capacities and operating rules; the operating rule of the Dhansa regulator; an urban flood plan of HSDMA; the list of wetlands notified under the Wetlands Rules 2017; and the text of CAG's Report No. 4 of 2026. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.


10.18 Review of this chapter

10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.


References (chapter)

Annexes and forms

Annex / Form Content
10A Compliance calculator and user guide
10B GIS data specification and attribute schema
10C Maintenance access dimensions
10D Model O&M plans by facility type
10E Empanelment criteria for Stormwater Design Professionals and reviewers
Form 10-1 Drainage Report Checklist
Form 10-2 Compliance Calculator Summary
Form 10-3 Professional Design Certificate
Form 10-4 Hold-Point Inspection Record
Form 10-5 As-built Certificate
Form 10-6 Maintenance Declaration
Form 10-7 Annual Maintenance Declaration and Inspection Report
Form 10-8 Asset Handover Certificate