Annexes to Chapter 7Waterbodies, Tals (Lakes and Ponds) and Setbacks
These annexes support Chapter 7. They give the inventory field specification, the fixed-width setback table, a template operating rule, the desilting and restoration specification, a glossary of Hindi and Pahari waterbody terms, and the three forms that Clause 7.15 requires. Where an annex cannot yet be completed it says so and gives the rule to use in the meantime. The forms are draft forms; the template and model text are for consideration by a competent authority and are not in force.
Annex 7A — Statewide waterbody GIS layer and inventory fields
Supports Clauses 7.3.1, 7.3.3 and 7.3.5 of Chapter 7.
To be prepared. This annex will contain the statewide GIS layer of waterbodies required by Clause 7.3.1, prepared by each Authority with the Jal Shakti Vibhag and the Revenue Department. It needs the Revenue records and village maps of the Revenue Department, in which rivers, khads, nallahs, kuhls, tals, baolis and land covered by water are recorded; the existing water bodies, "like Bauri, Well, Nallah, khud", that the site plan forms of the TCP Rules 2014 require on every application for planning permission; the land use maps, sinking and sliding zones, non-developable land and distances from the highest flood level along rivers, khads and nullahs of each Interim Development Plan or Development Plan, such as the Shimla Development Plan (published on 20 June 2023); the drains and nallahs in the records of a Municipal Corporation, Nagar Parishad or Nagar Panchayat, and SJPNL's records of Shimla's sources and sewers; the kuhls listed by district and tehsil in Schedules I and II of the Himachal Pradesh Minor Canals Act, 1976; the boundaries of the Ramsar sites at Pong, Chandertal and Renuka and of any wetland notified under the Wetlands (Conservation and Management) Rules, 2017, and the wetlands of the national atlas; BBMB's and the other dam operators' records of reservoir levels and acquired land; the spring inventories (about 500 springs inventoried in a standard format, NITI Aayog, 2021); and the lists of encroachment and muck dumping filed before the High Court of Himachal Pradesh and the National Green Tribunal; the JSV and Gram Panchayat tank registers with FTL and MWL; surveyed levels on a common datum; the ISRO National Wetland Inventory and Assessment (NRSC); Survey of India topographic maps; and any list of waterbodies published under court directions. Until it is published, each Applicant identifies waterbodies from all the sources of Clause 7.3.3, with the larger extent governing, and records them on the Waterbody Sheet (Form 7-1).
The field specification below is complete. It is written so that every field the chapter asks for (Clause 7.3.1(a) to (g)) has a defined name, type and source, and so that the same fields can be filled from a project's Form 7-1.
7A.1 Layers
- WB_POLY — one polygon per waterbody: the Revenue record boundary (Clause 7.3.1(c)).
- WB_FTL — the surveyed FTL contour (tanks, lakes, ponds) or top of bank (channels), as a polygon or line.
- WB_MWL — the MWL contour of each tank, as a polygon.
- WB_FLOOD — the 1% AEP flood extent, where mapped (Clause 7.3.1(f)), with the floodway where delineated (Clause 7.6.1).
- WB_STRUCT — points for surplus weirs, sluices, regulators, inlets and drain outfalls.
- WB_LINK — lines for supply channels, surplus courses and the links between tanks in a cascade (Clause 7.3.1(e)).
- WB_ENCR — polygons of known encroachments, each with the date recorded (Clause 7.3.1(g)).
- WB_SETBACK — Zone 1 and Zone 2 polygons (Clause 7.4), derived from the layers above.
All layers shall carry the waterbody identifier (WB_ID) so that they can be joined. All levels shall be stated to one datum (Clause 7.3.5), named in the layer metadata.
Table 7A.1 — Attribute fields of the waterbody inventory (WB_POLY)
| Field | Type | Unit / domain | Required | Content | Clause |
|---|---|---|---|---|---|
| WB_ID | Text | District code + serial | Yes | Unique identifier, never reused | 7.3.1 |
| WB_NAME | Text | — | Yes | Name as in Revenue and JSV records, with local name | 7.3.1(a) |
| WB_NAME_HI | Text | Hindi script | Yes | Name in Hindi | 7.3.1(a) |
| WB_TYPE | Code | Table 7A.2 | Yes | Waterbody type | 7.2, 7.3.1(a) |
| SURVEY_NOS | Text | Village, survey and subdivision numbers | Yes | Revenue survey numbers of the waterbody | 7.3.1(a) |
| VILLAGE | Text | — | Yes | Revenue village, tehsil and district | 7.3.1(a) |
| CUSTODIAN | Code | Table 7A.2 | Yes | Custodian body | 7.3.1(b) |
| AREA_REC | Number | ha | Yes | Area within the Revenue record boundary | 7.3.1(c) |
| AREA_FTL | Number | ha | Tanks | Waterspread at FTL, surveyed | 7.2, 7.3.1(d) |
| FTL | Number | m (datum) | Tanks | Full tank level | 7.3.1(d) |
| MWL | Number | m (datum) | Tanks | Maximum water level (Clause 7.2 definition) | 7.3.1(d) |
| MWL_BASIS | Code | JSV record / 1% AEP computed | Tanks | Which value governs MWL | 7.2 |
| TBL | Number | m (datum) | Tanks | Top bund level, lowest point | 7.3.1(d) |
| WEIR_CREST | Number | m (datum) | Tanks | Surplus weir crest level | 7.3.1(d) |
| WEIR_LEN | Number | m | Tanks | Surplus weir crest length | 7.3.1(d) |
| WEIR_TYPE | Text | — | Tanks | Surplus weir type (for example fixed crest, with shutters or falling boards) | 7.3.1(d) |
| SLUICE_N | Integer | — | Tanks | Number of sluices; details in WB_STRUCT | 7.3.1(d) |
| SUPPLY_CH | Text | WB_ID(s) | Tanks | Supply channel(s) feeding the tank | 7.3.1(d) |
| SURPLUS_CS | Text | WB_ID(s) | Tanks | Surplus course(s) leaving the tank | 7.3.1(d) |
| UPSTR_WB | Text | WB_ID(s) | Cascades | Upstream tank(s) in the cascade | 7.3.1(e) |
| DNSTR_WB | Text | WB_ID | Cascades | Downstream tank, river, drain or sea outfall | 7.3.1(e) |
| CATCH_AREA | Number | ha | Channels | Drainage area at the downstream end of the reach (for the 8 ha trigger of Clause 7.4.1(b) and Table 7.1) | 7.4.1 |
| DATUM | Text | — | Yes | Datum of all levels; conversion from any older JSV datum | 7.3.5 |
| LEVEL_DATE | Date | — | Tanks | Date of the level survey | 7.7.1(a) |
| SSC_DATE | Date | — | Tanks | Date of the latest stage–storage survey | 7.7.1(b) |
| FLOOD_SRC | Code | Adopted map / site study / none | Yes | Source of the 1% AEP extent | 7.3.4 |
| FLOODWAY | Code | Delineated / whole 1% extent / below MWL | Yes | Basis of the floodway | 7.6.1 |
| ENCR_KNOWN | Code | Yes / No | Yes | Known encroachment; details in WB_ENCR | 7.3.1(g) |
| CREDITED | Code | Yes / No | Tanks | Storage counted under Clause 7.7, with the scheme reference | 7.7.1 |
| WETLAND | Code | Notified / listed / other | Wetlands | Status under Clause 7.12.1 | 7.12.1 |
| SOURCES | Text | — | Yes | Sources used, from the list in Clause 7.3.3(a) to (e) | 7.3.3 |
| UPDATED | Date | — | Yes | Date of the last edit, and by whom | 7.3.1 |
Table 7A.2 — Code lists
| Code list | Values | Clause |
|---|---|---|
| WB_TYPE | River; khad (hill torrent); nallah (natural drain or storm channel); nali (street, roadside or house drain); cho (seasonal Siwalik torrent); kuhl (irrigation channel; scheduled or not); canal; lake or tal; reservoir or barrage pond (with its drawdown zone); spring (naun, baoli or chashma) and its recharge area; khatri (rock-cut seepage tank); wetland; glacial or moraine-dammed lake; supply channel; surplus course | 7.2 |
| CUSTODIAN | Municipal Corporation, Nagar Parishad or Nagar Panchayat (Municipal Acts, 1994 [TBC]); SJPNL (Shimla sources and sewers); JSV (division); HPPWD or NHAI (road drains and culverts); Government, local authority or beneficiaries with the Collector (scheduled kuhl, Minor Canals Act, 1976); BBMB, NTPC, SJVN, NHPC, HPSEBL or other dam operator; Forest Department (forest land; wildlife sanctuary); State Government through the Deputy Commissioner or Tehsildar; Gram Panchayat; HIMUDA, HPSIDC, BBNDA or developer (until handed over); Himachal Pradesh State Wetlands Authority (wetland); private owner; other (name) | 7.3.1(b) |
| Structure (WB_STRUCT) | Surplus weir; sluice; regulator; inlet; drain outfall; gross pollutant trap; crossing | 7.3.1(d), 7.10 |
| Encroachment (WB_ENCR) | Building; fill; road; wall; dumping; cultivation; other — each with date recorded, area (m²) and source | 7.3.1(g), 7.13 |
Table 7A.3 — Attribute fields of structures (WB_STRUCT)
| Field | Type | Unit | Content | Clause |
|---|---|---|---|---|
| STR_ID | Text | — | Unique identifier | 7.3.1(d) |
| WB_ID | Text | — | Waterbody served | 7.3.1(d) |
| STR_TYPE | Code | Table 7A.2 | Structure type | 7.3.1(d) |
| CREST_SILL | Number | m (datum) | Weir crest or sluice sill level | 7.7.1(a) |
| LENGTH_SIZE | Text | m | Weir crest length, or sluice opening size | 7.7.1(a) |
| GATED | Code | Yes / No | Controllable outlet (needed for a flood cushion, Clause 7.8.2(a)) | 7.8.2 |
| CONDITION | Code | Serviceable / defective | Result of the latest pre-monsoon inspection, with date | 7.7.1(d), 7.14.4 |
Annex 7B — Fixed-width setback table (alternative S-3, with Annex 1C)
Supports Clauses 7.3.4, 7.4.3, 7.4.6 and 7.4.7 of Chapter 7, and alternative S-3 of the Policy Supplement (Annex 1C).
7B.1 When the table may be used
The fixed-width setback may be used only where all of the following apply:
- (a) the Authority has not adopted a 1% AEP flood extent map for the waterbody (Clause 7.3.4);
- (b) Clause 7.3.4 does not require the Applicant to determine the 1% AEP extent by a hydraulic study: the site is not in a flood-sensitive catchment, is not a site of 1 ha or more adjoining a waterbody, and the Authority has not asked for a study; and
- (c) the waterbody is one to which setbacks apply (Clause 7.4.1): any recorded or found waterbody, and any natural channel draining 8 ha or more at the site.
Where an Authority adopts alternative S-3 under Clause 1.7, the table below is the S-3 table. Clause 1.7.3(e) provides for the S-3 table to be issued by the State Stormwater Technical Committee. Until it is issued, the values are those of Clause 7.4.6, repeated here without change.
Table 7B.1 — Fixed-width setback by waterbody class (alternative S-3)
| Waterbody class | Drainage area at the site | Total setback (Zone 1 + Zone 2) | Of which Zone 1 | Measured from |
|---|---|---|---|---|
| Channel, small | 8 ha to 65 ha | 25 m | 15 m | Top of bank (Clause 7.4.3) |
| Channel, medium | 65 ha to 20 km² | 40 m | 15 m | Top of bank |
| Channel, large, and rivers | More than 20 km² | 50 m | 20 m | Top of bank |
| Tank, lake or pond | Any | MWL contour + 25 m | To the MWL contour, and not less than 15 m from FTL | FTL contour (Zone 1); MWL contour (total) |
| Marsh, estuary or backwater | Any | As notified by the Authority, and not less than 50 m | 15 m | The waterbody boundary of Clause 7.13.1 |
Values from Clause 7.4.6 (Table 7.1). Zone 2 is the total setback less Zone 1.
7B.2 Rules of application
- (a) Measurement. Measure horizontally on plan, outward from the boundary of Clause 7.13.1: the larger of the Revenue record boundary and the surveyed FTL (or top of bank). Where FTL and top of bank both apply, use whichever gives the wider zone (Clause 7.4.3).
- (b) Drainage area. For a channel, use the drainage area at the downstream end of the reach that adjoins the site. Where a reach crosses a class limit within the site, apply the wider setback to the whole reach within the site.
- (c) Both banks. The setback applies on each bank of a channel and all round a tank, lake, pond or marsh.
- (d) Minimum set by this Manual. Zone 1 is never less than 15 m (Clause 7.4.7). A wider statutory or approval setback governs for the uses it restricts (Clause 7.4.5).
- (e) Stricter of the two. Where a hydraulic study is made voluntarily, the setback is the wider of Table 7B.1 and Clauses 7.4.3 and 7.4.4.
- (f) Record. The basis of the setback (fixed width) shall be stated on the Waterbody Sheet (Form 7-1) and in the approval (Clause 7.4, Disclosure).
- (g) Review. The table shall be reviewed within 2 years of the Authority adopting 1% AEP flood maps (Clause 7.16.1).
7B.3 Source of the channel widths
The channel widths were set by this Manual with reference to the 2006 Kansas City APWA default stream buffers, rounded up and floored at the 15 m minimum (Clause 7.4.6, commentary). The source values, as cited in the chapter, are:
Table 7B.2 — Source buffers cited in Clause 7.4.6 (KC APWA 5600, 2006, §5605.3)
| Drainage area (source, acres) | Approximate SI equivalent | Source buffer |
|---|---|---|
| Less than 40 ac | Less than 16 ha | 40 ft (12 m) |
| 40–160 ac | 16–65 ha | 60 ft (18 m) |
| 160–5,000 ac | 65 ha – 20 km² | 100 ft (30 m) |
| More than 5,000 ac | More than 20 km² | 120 ft (37 m) |
The 65 ha and 20 km² class limits in Table 7B.1 are the SI equivalents of 160 ac and 5,000 ac. The 8 ha lower limit is the 20-acre trigger of APWA 2025.01 (Clause 7.4.1(b)).
Annex 7C — Template tank operating rule, with flood cushion
Supports Clauses 7.7.1(c), 7.7.3, 7.8 and 7.14.4 of Chapter 7.
Model text for consideration by a competent authority. Not in force. For tanks under JSV control, the operating rule is JSV's rule (Clause 7.8.4); this template sets out the content that Clause 7.8 asks for, so that the custodian's rule can be checked against it. Text in square brackets is to be completed for each tank.
7C.1 Identification
- Tank: [name, WB_ID of Annex 7A, village, tehsil, district].
- Custodian: [JSV division / ULB / Gram Panchayat / other].
- Cascade position: upstream tank(s) [ ]; downstream tank, river or drain [ ].
- Datum: [ ]. Surveyed levels (Clause 7.7.1(a)), date of survey [ ]: FTL [ ] m; MWL [ ] m; TBL (lowest point) [ ] m; surplus weir crest [ ] m, length [ ] m; sluice sills [ ] m.
- Stage–storage curve (Clause 7.7.1(b)): survey date [ ]; attached as Schedule 1.
- Controllable outlets (Clause 7.8.2(a)): [gated sluice / regulator / none]; capacity at FTL [ ] m³/s.
7C.2 Purposes and priority
- The tank serves [irrigation of a command area of [ ] ha / drinking water supply / recharge / flood storage]. Irrigation and water supply remain primary unless the custodian records otherwise (Clause 7.8.2(d)).
7C.3 Levels and dates through the year (Clause 7.8.1(a))
- The tank shall be operated to the levels in Table 7C.1.
Table 7C.1 — Rule levels by period (to be completed for each tank)
| Period | Target level (m) | Upper limit (m) | Lower limit (m) | Purpose |
|---|---|---|---|---|
| [1 Jan – date] | [ ] | FTL | [ ] | Holding for irrigation / supply |
| [date – start of cushion period] | [ ] | FTL | [ ] | Holding |
| [Flood-cushion period, if any] | Cushion level [ ] | Cushion level [ ] | [ ] | Flood cushion (Clause 7.8.2) |
| [End of cushion period – 31 Dec] | [ ] | FTL | [ ] | Refilling |
- Where no flood cushion is adopted, the starting level for design is FTL (Clause 7.7.3) and the row for the cushion period is deleted.
7C.4 Flood cushion (Clause 7.8.2)
- Cushion level: [ ] m, which is [ ] m below FTL, giving a cushion volume of [ ] m³ from Schedule 1.
- Dates: the cushion applies from [ ] to [ ].
- Drawdown: the tank can be drawn down from FTL to the cushion level through [outlet] in [ ] hours, with a release not exceeding the maximum release rate of paragraph 18.
- Reliability: continuous simulation (Clause 3.13) over the record [years] shows that the cushion is available at the start of a design storm in [ ]% of SW monsoon seasons, which shall be at least 90%. The simulation report is Schedule 2.
- Yield: the custodian accepts the loss of irrigation or supply yield stated in Schedule 3 [and the compensation recorded there].
- Where the tank has no controllable outlet, this section does not apply and no flood cushion is assumed (Clause 7.8.3).
7C.5 Releases (Clause 7.8.1(b) to (d))
- Sluice and regulator settings at each level: Table 7C.2.
- Operator: the sluices and regulators are operated by [post]. A release above [ ] m³/s may be ordered only by [post], or, in an emergency, by [post].
- Maximum release rate: [ ] m³/s. This rate, added to the flow from the downstream catchment, does not flood buildings downstream (Schedule 4 gives the downstream check).
- No person shall cut, lower or breach the bund or surplus weir except under the custodian's emergency procedure (Clause 7.14.5).
Table 7C.2 — Outlet settings by level (to be completed for each tank)
| Tank level (m) | Sluice 1 | Sluice 2 | Regulator | Expected outflow (m³/s) | Notes |
|---|---|---|---|---|---|
| Below cushion level | [ ] | [ ] | [ ] | [ ] | |
| Cushion level to FTL | [ ] | [ ] | [ ] | [ ] | |
| FTL (weir begins to spill) | [ ] | [ ] | [ ] | [ ] | |
| Above FTL to MWL | [ ] | [ ] | [ ] | [ ] | Check freeboard to TBL (Clause 7.7.4(b)) |
7C.6 Forecasts, warnings and communication (Clause 7.8.1(e) and (f))
- The triggers and actions are in Table 7C.3.
- Before any release under this rule, the operator shall inform the ULBs and the district administration downstream, and residents by the means stated in Schedule 5, at least [ ] hours before the release where the forecast allows.
Table 7C.3 — Triggers and actions (to be completed for each tank)
| Trigger | Source | Action | By whom |
|---|---|---|---|
| IMD district heavy-rainfall warning for the catchment | IMD | Read gauges [ ] hourly; check outlets are free; confirm the tank is at or below its rule level | [ ] |
| IMD or HPSDMA red alert | IMD, HPSDMA | Begin releases needed to reach the rule level, within the maximum release rate; notify downstream bodies (paragraph 21) | [ ] |
| City forecast system warning, where available | [ ] | [ ] | [ ] |
| Tank level reaches FTL | Gauge | Record outflow hourly; inspect bund and weir | [ ] |
| Tank level reaches [MWL − [ ] m] | Gauge | Emergency procedure; warning to the breach area of any emergency action plan (Clause 7.14.3(c)) | [ ] |
7C.7 Records and review (Clause 7.8.1(g))
- During the SW monsoon (15 June to 31 October) the operator shall record daily: the tank level, every release (time, rate and duration), and every gate setting. Outside the SW monsoon, records shall be kept [weekly].
- Records shall be kept with the O&M plan (Chapter 10) and given to the Authority on request.
- The tank shall be inspected before the SW monsoon (by 31 May) and after every heavy-rainfall event (Clause 7.14.4).
- This rule shall be reviewed after any event in which the tank surplused at a level above [ ] m, after any change to the weir, sluices or bund (Clause 7.7.6), and in any case with the review of the Manual.
Schedules: 1 stage–storage curve; 2 continuous simulation report; 3 yield and compensation; 4 downstream check of the maximum release; 5 communication list.
Annex 7D — Desilting and restoration specification
Supports Clauses 7.7.1(b), 7.9 and 7.14.4 of Chapter 7.
This specification applies to every desilting, restoration or deepening of a tank, pond or other waterbody under Clause 7.9. Values are those of Chapter 7. Where the chapter does not set a value, it is marked "to be confirmed in design" and shall be stated in the works design.
7D.1 Pre-works survey (Clause 7.9.1)
- (a) Topographic and bathymetric survey of the waterspread, foreshore (to the MWL contour), bund, surplus weir and sluices, levelled to the datum of Clause 7.3.5. Survey grid and point density: to be confirmed in design.
- (b) Original bed level found by test pits or augering on a grid (grid spacing to be confirmed in design), and from historical records where available. Each pit log shall show the silt thickness, the level of the original bed, and any clay or silt layer below it.
- (c) Silt testing where the tank receives urban runoff or sewage: samples from the pits of (b), tested for heavy metals and other contaminants before disposal is planned. The parameters and limits shall be those the Himachal Pradesh State Pollution Control Board (HPSPCB) directs.
- (d) Structures: condition of the bund (seepage, slips, cracks, animal burrows, trees), surplus weir and sluices, as in Clause 7.14.4.
- (e) Existing stage–storage curve from the survey of (a).
7D.2 Limits of excavation (Clauses 7.9.2 and 7.9.3)
- (a) Desilting removes accumulated sediment down to the original bed level of 7D.1(b), and no deeper.
- (b) Deepening below the original bed only with a hydrogeological report showing each of Clause 7.9.3(a) to (c).
- (c) Storage created below the lowest sluice sill is not flood storage, and shall not be shown as such in the revised stage–storage curve.
- (d) Excavation shall stay clear of the bund toe by a distance to be confirmed in design, so that the bund's stability is not reduced.
7D.3 Edges and safety (Clause 7.9.4)
Where the public has access to the edge:
- (a) side slopes no steeper than 1V:4H from 0.5 m above FTL down to 1.2 m below FTL; or
- (b) a level safety bench at least 3 m wide, between 0.3 m and 0.5 m below FTL; and
- (c) no isolated deep pit or vertical cut left in the bed. Borrow pits shall be regraded to the bed.
7D.4 Storage not reduced (Clause 7.9.5)
- (a) Islands, walkways, bund widening into the waterspread, ring roads, parking, buildings and lake-front platforms within the waterspread or foreshore are lost storage.
- (b) Lost storage shall be offset by compensatory storage at equivalent levels, band by band, using Form 7-3.
7D.5 Silt handling and disposal (Clause 7.9.6)
- (a) Desilted material shall not be placed within the setback, on the bund (except approved bund strengthening), or on any flood path.
- (b) Contaminated silt shall be disposed of as the Himachal Pradesh State Pollution Control Board (HPSPCB) directs.
- (c) Haul routes and temporary stockpiles shall meet the construction erosion and sediment control rules of Clause 8.12, including stockpiles outside Zone 1.
7D.6 Inlets (Clause 7.9.7)
Every inlet that brings urban runoff shall have a sediment forebay, a constructed wetland inlet zone or a gross pollutant trap, designed under Chapter 8 (Annex 8D).
7D.7 Timing (Clause 7.9.8)
Desilting shall be complete, and the waterbody made safe, by 31 May. No excavation shall be left open, and no sluice or weir left dismantled, during the SW monsoon.
7D.8 Completion records
- (a) As-built survey and revised stage–storage curve. The curve is the one that Clause 7.7.1(b) requires "after the last desilting".
- (b) Volume removed, its disposal site, and the silt test results.
- (c) Photographs of the bund, weir, sluices and inlet works.
- (d) Update of the inventory record (Annex 7A: SSC_DATE, LEVEL_DATE, CONDITION).
Table 7D.1 — Hold points for desilting and restoration works
| Hold point | Check | Clause |
|---|---|---|
| 1. Before excavation | Pre-works survey, pit logs, silt tests, and hydrogeological report if deepening | 7.9.1, 7.9.3 |
| 2. Original bed reached | Levels checked against pit logs; no excavation below the original bed unless approved | 7.9.2 |
| 3. Edges formed | Side slopes or safety bench as 7D.3 | 7.9.4 |
| 4. Inlet works | Forebay, wetland inlet zone or GPT built | 7.9.7 |
| 5. Completion (by 31 May) | As-built survey, stage–storage curve, silt disposal record | 7.9.8, 7.7.1(b) |
Annex 7E — Glossary of Hindi and Pahari waterbody terms and regional variants
Supports Clause 7.2 and Clause 7.3 of Chapter 7.
The terms below are Hindi words, and Pahari words where they are in use, for waterbodies, springs, channels and land in Himachal Pradesh, given in Devanagari and, where Platts gives it, Urdu script. Many of them appear in the names of lakes, streams and places (Rewalsar, Ashwani Khad, Banu Khad, Sikandara Dhar). The name used in the Revenue, JSV, municipal or SJPNL record for each waterbody should be recorded in the inventory (Annex 7A) alongside the Manual's term. A meaning is given below only where it was confirmed in Tika Ram Joshi, A Dictionary of the Pahari Dialects as Spoken in the Punjab Himalayas (1911), the only Pahari dictionary checked; in J. T. Platts, A Dictionary of Urdu, Classical Hindi, and English (1884), or Syamasundara Dasa, Hindi Shabdasagara (1965–1975), both as served by the Digital South Asia Library, with the page shown there; or in R. L. Turner, A Comparative Dictionary of the Indo-Aryan Languages (CDIAL, 1962–1966), by entry number. Two cautions apply. Joshi's dictionary was read in a poor OCR copy, and its page numbers, taken from the printed running heads, may be one page out (±1); some headwords and accents are lost. The CDIAL entry numbers were taken from web summaries, not from the dictionary pages, and are to be checked on the Digital South Asia Library before this annex is relied on. Meanings are the dictionaries' English glosses, or a translation of their Hindi, and modern usage may be narrower or wider. Every term whose meaning or regional use was not confirmed in a dictionary is in Table 7E.4. The list is to be extended by the State Stormwater Technical Committee, with modern Revenue, JSV and municipal usage and with other Pahari dictionaries.
The Manual's term for a lake, tank or pond in Himachal Pradesh is tal (ताल): it is the only candidate found with a water sense in all four sources, Joshi records it in the hill dialects, and it covers both natural lakes and built tanks. Because ताल also means rhythm and the palm of the hand, it is glossed on first use as "tal (pond, lake or tank)". Naun (नौण) and baoli (बावड़ी) are used, always glossed, only for spring-fed sources; and an engineered detention basin is not called a tal, naun or baoli: it is a detention pond, with the local word in brackets where that helps. The romanised "talab" is avoided, because in Joshi talab is a salary.
Table 7E.1 — Waterbodies
| Term | Meaning | Source of the term | Manual term (Clause 7.2) |
|---|---|---|---|
| ताल / تال (tāl; tal) | "A pond, a lake or tank" (Joshi, marked as Hindi); "pond, pool, tank, lake (= tālāb)" (Platts, second sense; the first is the palm and musical time); in CDIAL, Western Pahari tāl "pond" | Joshi, p. 238; Platts, p. 306; CDIAL 5742 | Tal (lake, tank or pond), see the definitions after Clause 7.2 |
| सर, सरोवर / سروور (sar, sarovar) | सर: "a large sheet of water, lake, pond"; सरोवर: "तालाब । पोखरा । झील । ताल ।", a tank, a pond, a lake | Platts, pp. 648 and 658; Shabdasagara, p. 5003 | In names only, such as Rewalsar; a tal for this chapter |
| झील / جهيل (jhīl; jheel) | "A pool, a shallow lake; a marsh, morass, swamp"; in the Shabdasagara, a very large natural waterbody surrounded by land, some fed by springs in their own bed | Platts, p. 411; Shabdasagara, p. 1848 | A tal; a marsh under Clause 7.12 where it is one |
| कुंड (kuṇḍ; kund) | "A pool, a deep hole in a stream" (Joshi); in the Shabdasagara, "छोटा बँधा हुआ जलाशय । बहुत छोटा तालाब ।", a small embanked waterbody, a very small tank | Joshi, p. 199; Shabdasagara, p. 964 | A pool in a khad, or a small tank; a waterbody for Clause 7.3 |
| नौण (nauṇ; naun) | "A place for water" (Joshi; headword lost in the OCR, its place in the alphabet fits nauṇ); in CDIAL, Western Pahari nauṇ "brick-built tank, well" and Punjabi of Kangra nauṇ "artificial reservoir, spring". Platts and the Shabdasagara have no water sense | Joshi, p. 211; CDIAL 13790a and 13783a | Spring (naun), see the definitions after Clause 7.2 |
| बावड़ी, बाउड़ी / باولي (bāoṛī, bāolī; baoli, bauri) | "A water pool" (Joshi, Báori, from Sanskrit vāpī); in Platts (बावली), "A large masonry well, generally with winding steps down to the water"; in CDIAL, Western Pahari "tank, stone-built reservoir fed by a spring, spring". In the hills a small spring-fed pool or stone tank, in the plains a step-well; the TCP site plan forms ask for every "Bauri" to be shown | Joshi, pp. 126 and 128; Platts, p. 128; CDIAL 11529; TCP Rules 2014, forms | Spring (baoli), see the definitions after Clause 7.2 |
| खाल (khāl); डाबर (dábr) | "a tank, a pond" and "small pond or tank" (Joshi; OCR poor) | Joshi, pp. 191 and 146 | Local only; a tal for this chapter, always glossed |
Table 7E.2 — Springs, streams and channels
| Term | Meaning | Source of the term | Manual term (Clause 7.2) |
|---|---|---|---|
| चश्मा (caśmā; chashma) | "पानी का सोता, स्रोत", a spring, a source (also spectacles) | Shabdasagara, p. 1494 | Spring (chashma), see the definitions after Clause 7.2 |
| सोत, सोता / سوت (sot, sotā) | "A stream, rill, rivulet; current, channel; a spring, source (of a river)"; in the Shabdasagara, a small stream that flows or comes out steadily, a spring | Platts, p. 693; Shabdasagara, p. 5294 | Spring or rill; a spring for this chapter |
| धारा / دهارا (dhārā; dhara) | "A line of descending fluid, a stream, current …, a channel, a water-course; a torrent"; in the Shabdasagara, also a spring. In legal Hindi धारा also means a section of an Act | Platts, p. 538; Shabdasagara, p. 2457 | A spring spout or stream; not used as a defined term |
| खड्ड (khaḍḍ; khad, khud) | "Khad, n.m. A ditch (also khadd)" and "Khád, n.f. A small river" (Joshi); Platts gives खड्डा only as a pit, a hollow; in CDIAL, khaḍḍa "hole, pit", with "valley" in Bashkarik. The stream sense is found only in Joshi. The TCP Rules write "Khud" | Joshi, p. 190; Platts, p. 873; CDIAL 3790; TCP Rules 2014, Appendix-1, clause 16 | Khad (hill torrent; a natural channel), see the definitions after Clause 7.2 |
| नाला / نالا (nālā; nala, nallah) | "A watercourse; channel (for water), a ravine; a rivulet, brook, canal; a drain, gutter" (Platts); in the Shabdasagara, a channel by which rain-water goes to a river; in Joshi, a waterfall, a spring or a small river. The TCP Rules write "Nullah" | Platts, p. 1117; Shabdasagara, p. 2596; Joshi, p. 210 | Nallah (natural drain or storm channel) |
| नाली / نالي (nālī; nali) | "a drain; … a small watercourse" (Platts); "A small rivulet" (Joshi) | Platts, p. 1117; Joshi, p. 210 | Nali (street, roadside or house drain) |
| कूहल (kūhal; kuhl) | Not a Joshi headword (nearest, "Gül or Kül, n.f. A small channel"); in CDIAL, under kulyā́ "small river, canal, ditch", Lahnda kūhl "watercourse", Punjabi kūlh, kūhul "brook, canal" and Western Pahari kull "natural or artificial stream"; in the Shabdasagara, कुल्या "a canal; a small river; a drain". The Minor Canals Act uses "kuhls". Platts's कूल is a bank or slope and is not used | CDIAL 3352; Joshi, p. 169; Shabdasagara, p. 1008; Himachal Pradesh Minor Canals Act, 1976 | Kuhl (gravity irrigation channel), see the definitions after Clause 7.2 |
Table 7E.3 — Land and structures
| Term | Meaning | Source of the term | Use in this Manual |
|---|---|---|---|
| धार / دهار (dhār; dhar) | "(1) The uppermost part of a roof. (2) A peak" (Joshi); "a line or chain (of mountains)", and also "flowing, stream" (Platts) | Joshi, p. 153; Platts, p. 538 | A ridge or crest, and so a catchment divide; always glossed, because Hindi readers take धार as a stream |
| घराट (ghrāṭ; gharat) | A water mill (Joshi, Ghrát); not found in Platts or the Shabdasagara | Joshi, p. 166 | The channel of a gharat on a khad is a supply channel for Clause 7.10 |
| पनिहार (panihār; panihar) | "The water-place of a village" (Joshi, Panhair); in Hindi पनहरा is a water-carrier | Joshi, p. 217; Shabdasagara, p. 2811 | A village water source; a spring for this chapter where it is one |
Table 7E.4 — Terms not yet verified
These terms or senses are in use but were not confirmed in a dictionary during research for this Manual. They shall not be used in a record or a drawing as defined terms until verified.
| Term | Reported meaning or use | Status |
|---|---|---|
| खात्री (khātrī; khatri) | A chamber cut by hand into hard rock to collect seepage water, with a capacity reported at tens of thousands of litres, in Hamirpur and the neighbouring parts of Mandi and Kangra | Sourced only to non-dictionary reports (Rajan, The Tribune, 2011, on the khatris of Bamsan; a CGWB district brochure for Hamirpur, seen only as a search summary); not found in Joshi; not checked in Platts, the Shabdasagara or CDIAL; used in this Manual only with this gloss |
| कोहली (kohli) | The overseer of a kuhl, who runs its distribution and its upkeep for the irrigators | Sourced only to Baker (2005), The Kuhls of Kangra; not found in Joshi, Platts or the Shabdasagara, and not named in the Minor Canals Act as read |
| cho, choe | A seasonal Siwalik torrent, as the southern streamlets of the Pong reservoir, "ephemeral in nature and locally called choes" | HP State Wetlands Authority booklet; Platts's चोआ (p. 447) is only a cross-reference, with no meaning confirmed |
| CDIAL entries 3352, 3790, 5742, 11529, 13783a, 13790a | As cited in Tables 7E.1 and 7E.2 | Entry numbers from web summaries; to be checked on the Digital South Asia Library |
| छ्रुडू (chhrudu) and other Pahari spring words | A small spring | Not found as a headword in Joshi (an entry "A spring of water" on p. 141 has lost its headword); unsourced |
| Pahari forms of tal, nallah and the other terms in the dialects of Kangra, Mandi, Kullu, Chamba, Shimla and Sirmaur | Regional words and spellings | Not checked beyond Joshi (1911) |
The Manual uses the terms in the last column of Tables 7E.1 and 7E.2, the land terms of Table 7E.3, and the Himachal Pradesh terms defined after Clause 7.2.
Form 7-1 — Waterbody Sheet
Supports Clauses 7.3.2, 7.4 and 7.15(1) of Chapter 7.
Draft form — Himachal Pradesh Stormwater Design Manual, Draft v1.0. One sheet per waterbody. Attach the plan of Clause 7.3.2 at 1:1,000 or larger.
Table 7F.1 — Form 7-1, Section A: Project and waterbody
| No. | Field | Entry | Clause |
|---|---|---|---|
| A1 | Project name and Authority file number | ______ | — |
| A2 | Waterbody name (English and Hindi) and inventory ID (Annex 7A), if any | ______ | 7.3.1 |
| A3 | Waterbody type (Clause 7.2) | ______ | 7.2 |
| A4 | Position: within the site / within 100 m of the site boundary / downstream within the Chapter 5 extent | ______ | 7.3.2 |
| A5 | Survey numbers and village | ______ | 7.3.1(a) |
| A6 | Custodian | ______ | 7.3.1(b) |
| A7 | Sources checked (tick): Revenue records and village maps, TCP site plan (bauri, well, nallah, khud), IDP/DP land use, HFL lines and sinking/sliding zones, municipal drain and SJPNL records, Minor Canals Act kuhl schedules, Ramsar and wetland boundaries, BBMB and dam-operator records, spring inventories, court and NGT lists ☐; JSV / Gram Panchayat registers ☐; Authority inventory or court list ☐; historical maps and imagery, including NWIA ☐; site survey ☐ | ______ | 7.3.3 |
| A8 | Where sources conflict: which extent governs (the larger) | ______ | 7.3.3 |
| A9 | Datum of all levels, and conversion from any JSV datum | ______ | 7.3.5 |
Table 7F.2 — Form 7-1, Section B: Levels and features
| No. | Field | Entry | Clause |
|---|---|---|---|
| B1 | FTL (tanks, lakes, ponds) or top of bank (channels), m | ______ | 7.2 |
| B2 | MWL (tanks), m, and basis (JSV record or 1% AEP computed) | ______ | 7.2 |
| B3 | TBL, lowest point (tanks), m | ______ | 7.3.1(d) |
| B4 | 1% AEP flood level, m, and source (adopted map / hydraulic study / not available) | ______ | 7.3.4 |
| B5 | Drainage area at the site (channels), ha | ______ | 7.4.1(b) |
| B6 | Supply channels, surplus courses, sluices and surplus weirs shown on plan (yes / no) | ______ | 7.3.2 |
| B7 | Known encroachments, with date recorded | ______ | 7.3.1(g) |
Table 7F.3 — Form 7-1, Section C: Setback
| No. | Field | Entry | Clause |
|---|---|---|---|
| C1 | Basis of setback: mapped extent / hydraulic study / fixed width (Annex 7B) | ______ | 7.15(1) |
| C2 | Is a hydraulic study required under Clause 7.3.4 (a) / (b) / (c)? | ______ | 7.3.4 |
| C3 | Floodway outer edge, m from FTL or top of bank, and how delineated | ______ | 7.6.1 |
| C4 | Zone 1 width, m (greatest of 15 m, floodway edge, MWL contour) | ______ | 7.4.3 |
| C5 | Zone 2 width, m (to 1% AEP extent + 10 m, or 10 m) | ______ | 7.4.4 |
| C6 | Wider statutory or approval setback, if any, and its source | ______ | 7.4.5 |
| C7 | Setback applied: Manual standard / a wider statutory, plan or approval line: the distance from the highest flood level along rivers, khads and nullahs delineated in an Interim Development Plan or Development Plan; non-developable land of a development plan (flood plains and land adjacent to major drainage lines); the 3.00 m (nullah) and 5.00 m (khud) of Appendix-1, clause 16, of the TCP Rules 2014, where no plan exists (narrower than Zone 1; stated, never governing alone); the boundary of a Ramsar site, a wildlife sanctuary or a notified wetland; a kuhl or line of natural drainage regulated under the Himachal Pradesh Minor Canals Act, 1976; a court or Tribunal line (such as the High Court's orders on muck in Gobind Sagar and its feeding khads); a BBMB, JSV, NTPC, SJVN, NHPC or HPSEBL line; or other (state which) | ______ | 7.4, Disclosure |
| C8 | Uses proposed in Zone 1 and Zone 2, and the custodian's NOC for any work in Zone 1 | ______ | 7.5, 7.15(5) |
| C9 | Fill proposed in the flood fringe (yes / no); if yes, Form 7-3 attached | ______ | 7.6.3 |
| C10 | Zone 1 marker positions shown (not more than 30 m apart) | ______ | 7.13.4 |
Table 7F.4 — Form 7-1, Section D: Prepared by
| Field | Entry |
|---|---|
| Name, registration and empanelment number (Clause 10.6) | ______ |
| Signature and date | ______ |
| Licensed surveyor for the levels (name, licence number) | ______ |
Form 7-2 — Tank Storage Credit Sheet
Supports Clauses 7.7, 7.8, 7.11, 7.14 and 7.15(4) of Chapter 7.
Draft form — Himachal Pradesh Stormwater Design Manual, Draft v1.0. One sheet per tank whose storage is counted. Storage that fails any item in Section B shall not be counted (Clause 7.7.1).
Table 7F.5 — Form 7-2, Section A: Tank and scheme
| No. | Field | Entry | Clause |
|---|---|---|---|
| A1 | Tank name and inventory ID (Annex 7A); custodian | ______ | 7.3.1 |
| A2 | Scheme in which storage is counted: basin plan / regional facility / fee-in-lieu (S-5) | ______ | 7.7.1, 7.11 |
| A3 | Cascade modelled: uppermost tank ______ to outfall ______ | ______ | 7.7.2 |
| A4 | Datum | ______ | 7.3.5 |
Table 7F.6 — Form 7-2, Section B: Conditions for counting storage
| No. | Condition | Date / reference | Met (yes / no) | Clause |
|---|---|---|---|---|
| B1 | FTL, MWL, TBL, weir crest and length, sluice sills surveyed within the previous 5 years | ______ | ______ | 7.7.1(a) |
| B2 | Stage–storage curve from a bathymetric and topographic survey within 5 years or after the last desilting, whichever is later | ______ | ______ | 7.7.1(b) |
| B3 | Documented operating rule agreed with the custodian (Annex 7C) | ______ | ______ | 7.7.1(c), 7.8 |
| B4 | Weir, sluices and bund under an O&M plan; latest pre-monsoon inspection found them serviceable | ______ | ______ | 7.7.1(d), 7.14.4 |
| B5 | Custodian's written concurrence | ______ | ______ | 7.7.1(e) |
Table 7F.7 — Form 7-2, Section C: Levels and creditable volume
| No. | Item | Value | Clause |
|---|---|---|---|
| C1 | Starting level: FTL, or cushion level under a rule meeting Clause 7.8.2, m | ______ | 7.7.3 |
| C2 | If a cushion is used: controllable outlet (type) and drawdown time, h | ______ | 7.8.2(a) |
| C3 | If a cushion is used: reliability from continuous simulation, % of SW monsoon seasons (≥ 90%) | ______ | 7.8.2(c) |
| C4 | Computed maximum level, 1% AEP inflow with climate factor routed through the cascade, m | ______ | 7.7.4 |
| C5 | MWL, m; is C4 ≤ MWL? | ______ | 7.7.4(a) |
| C6 | Freeboard C4 to TBL, m; JSV freeboard standard, m; met? | ______ | 7.7.4(b) |
| C7 | Storage between C1 and C4, from the stage–storage curve, m³ | ______ | 7.7.5 |
| C8 | Volume already committed to another facility or scheme, m³ | ______ | 7.7.5 |
| C9 | Creditable volume = C7 − C8, m³ | ______ | 7.7.5 |
| C10 | Register entry under Clause 10.17 (fee-in-lieu storage) | ______ | 7.11.2(d) |
Table 7F.8 — Form 7-2, Section D: Bund safety
| No. | Item | Entry | Clause |
|---|---|---|---|
| D1 | Specified dam under the Dam Safety Act, 2021? Height, crest length, capacity, maximum flood discharge | ______ | 7.14.1 |
| D2 | Hazard class: high / low | ______ | 7.14.2 |
| D3 | High hazard: weir passes 1% AEP at MWL with freeboard; 0.2% AEP check without overtopping | ______ | 7.14.3(a) |
| D4 | High hazard: breach analysis and emergency action plan (references) | ______ | 7.14.3(b), (c) |
| D5 | High hazard: independent check under Clause 10.6 (name) | ______ | 7.14.3(d) |
Table 7F.9 — Form 7-2, Section E: Signatures
| Role | Name and designation | Signature and date |
|---|---|---|
| Designer (Clause 10.6) | ______ | ______ |
| Independent checker, where Clause 7.14.3(d) applies | ______ | ______ |
| Custodian's concurrence (Clause 7.7.1(e)) | ______ | ______ |
Form 7-3 — Compensatory Storage Calculation (by elevation band)
Supports Clauses 7.6.3 to 7.6.5, 7.9.5 and 7.15(3) of Chapter 7.
Draft form — Himachal Pradesh Stormwater Design Manual, Draft v1.0.
Method
- Fix the lower limit: the normal water level of the waterbody, or the 50% AEP (2-yr) level where higher (Clause 7.6.4(b)).
- Fix the upper limit: the 1% AEP flood level (with the climate factor).
- Divide the range into bands of not more than 0.3 m. The top band may be thinner.
- For each level z at a band boundary, measure on plan:
- A_fill(z): the area of the fill footprint where existing ground is below z; and
- A_cut(z): the area of the excavation where finished ground is below z and existing ground was above z (new flooded area).
- For each band, by the average end-area method: V = (A(z_bottom) + A(z_top)) / 2 × band thickness. Do this for fill (volume lost) and for excavation (volume gained).
- Check each band: volume gained ≥ volume lost. A surplus in one band does not make up a shortfall in another (Clause 7.6.4(b)).
- Check the other conditions of Clause 7.6.4(c) to (f) in Section C.
Figure 7.2 in Chapter 7 shows the method.
Table 7F.10 — Form 7-3, Section A: Levels
| No. | Field | Entry | Clause |
|---|---|---|---|
| A1 | Waterbody, reach, and inventory ID | ______ | 7.6.4(c) |
| A2 | Normal water level, m; 50% AEP level, m; lower limit (the higher), m | ______ | 7.6.4(b) |
| A3 | 1% AEP flood level with climate factor, m (upper limit) | ______ | 7.6.4(b) |
| A4 | Band thickness, m (≤ 0.3) and number of bands | ______ | 7.6.4(b) |
| A5 | Datum | ______ | 7.3.5 |
Table 7F.11 — Form 7-3, Section B: Band-by-band balance
| Band | From (m) | To (m) | A_fill bottom (m²) | A_fill top (m²) | Volume lost (m³) | A_cut bottom (m²) | A_cut top (m²) | Volume gained (m³) | Gained ≥ lost? |
|---|---|---|---|---|---|---|---|---|---|
| 1 | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| 2 | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| 3 | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| 4 | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Total | ______ | ______ |
Add rows as needed.
Table 7F.12 — Form 7-3, Section C: Other conditions
| No. | Condition | Met (yes / no) and evidence | Clause |
|---|---|---|---|
| C1 | Fill is in the flood fringe, not the floodway, and for a permitted use | ______ | 7.6.2, 7.6.3 |
| C2 | Excavation is in the same reach of the same waterbody, hydraulically connected, and not further downstream than the fill | ______ | 7.6.4(c) |
| C3 | Excavation drains by gravity as the flood recedes; no pumping; no permanent pool below normal water level | ______ | 7.6.4(d) |
| C4 | Excavation built before, or at the same time as, the fill | ______ | 7.6.4(e) |
| C5 | Covenant or handover so that it is never filled (reference) | ______ | 7.6.4(f) |
| C6 | Not counted as detention or retention under Chapter 4 | ______ | 7.6.5 |
| C7 | Signature of designer (Clause 10.6) and date | ______ | 10.6 |
Worked example
Illustrative — not design values. A site in the flood fringe of a channel needs a fill pad for a permitted Zone 2 use (Clause 7.5.2). The inputs are assumed.
- Normal water level 10.00 m; 50% AEP level 9.80 m. Lower limit = 10.00 m (the higher).
- 1% AEP flood level 11.20 m. Range 1.20 m, so four bands of 0.30 m.
- The fill footprint is 1,600 m². Existing ground across the footprint rises evenly from 10.00 m to 11.20 m, so the area of footprint below each level is: 0 m² at 10.00 m; 400 m² at 10.30 m; 800 m² at 10.60 m; 1,200 m² at 10.90 m; 1,600 m² at 11.20 m.
- The excavation is a graded cut beside the channel, with its floor at 10.00 m. The new flooded area below each level (first trial) is: 300 m² at 10.00 m; 900 m² at 10.30 m; 1,100 m² at 10.60 m; 1,500 m² at 10.90 m; 1,500 m² at 11.20 m.
Step 1 — volume lost, band by band (V = average area × 0.3 m):
- Band 1: (0 + 400) / 2 × 0.3 = 60 m³
- Band 2: (400 + 800) / 2 × 0.3 = 180 m³
- Band 3: (800 + 1,200) / 2 × 0.3 = 300 m³
- Band 4: (1,200 + 1,600) / 2 × 0.3 = 420 m³
- Total: 960 m³
Step 2 — volume gained, first trial:
Table 7F.13 — Worked example: first trial (illustrative)
| Band | From (m) | To (m) | Volume lost (m³) | A_cut bottom (m²) | A_cut top (m²) | Volume gained (m³) | Gained ≥ lost? |
|---|---|---|---|---|---|---|---|
| 1 | 10.00 | 10.30 | 60 | 300 | 900 | 180 | Yes |
| 2 | 10.30 | 10.60 | 180 | 900 | 1,100 | 300 | Yes |
| 3 | 10.60 | 10.90 | 300 | 1,100 | 1,500 | 390 | Yes |
| 4 | 10.90 | 11.20 | 420 | 1,500 | 1,500 | 450 | Yes |
| Total | 960 | 1,320 |
Every band passes. Note that a simple total balance would hide a failure if, for example, the cut were made deeper and narrower: suppose the designer instead offers a cut with new flooded areas of 1,400 m² at 10.00 m, 1,400 m² at 10.30 m, 1,000 m² at 10.60 m, 600 m² at 10.90 m and 200 m² at 11.20 m.
Table 7F.14 — Worked example: deeper, narrower cut (illustrative)
| Band | From (m) | To (m) | Volume lost (m³) | A_cut bottom (m²) | A_cut top (m²) | Volume gained (m³) | Gained ≥ lost? |
|---|---|---|---|---|---|---|---|
| 1 | 10.00 | 10.30 | 60 | 1,400 | 1,400 | 420 | Yes |
| 2 | 10.30 | 10.60 | 180 | 1,400 | 1,000 | 360 | Yes |
| 3 | 10.60 | 10.90 | 300 | 1,000 | 600 | 240 | No |
| 4 | 10.90 | 11.20 | 420 | 600 | 200 | 120 | No |
| Total | 960 | 1,140 |
The total gained (1,140 m³) exceeds the total lost (960 m³), but bands 3 and 4 are short by 60 m³ and 300 m³. The surplus low down cannot be counted against them: the low storage fills early in every flood and is not available when the fill takes away storage near the peak. This design fails Clause 7.6.4(b) and must be regraded so that the upper bands gain at least as much as they lose, as in the first trial.