Chapter 11Basin and City Stormwater Master Plans
11.1 Purpose and scope
11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.
11.1.2 A BSMP shall:
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
- (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
- (d) reserve land for regional storage, tal and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
- (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
- (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).
11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.
11.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Basin | The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3. |
| Basin Stormwater Master Plan (BSMP) | The plan for one basin prepared under this chapter. |
| Lead Authority | The body responsible for preparing a BSMP (Clause 11.4). |
| Level of service (LoS) | The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6). |
| Flood hazard map | A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario. |
| Regional facility | A storage, conveyance or outfall work serving more than one development, identified in a BSMP. |
| Capital Improvement Programme (CIP) | The ranked, costed list of works in a BSMP (Clause 11.8.4). |
11.3 Planning unit: the basin, not the ward
11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.
11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.
11.3.3 No basin delineation has been published for any Himachal Pradesh town. For the urban areas where the evidence identifies them, the basins are at least the following:
- Shimla, nallahs and sinking zones: the catchments of the nallahs of the Shimla Planning Area that drain north to the Sutlej and south to the Ashwani Khad and the Giri, among them the 13 major nallahs of the Corporation's plan of 2015, with the drains of the British period and those built under AMRUT in the 1D network, the two sinking and sliding zones shown, the water intakes and sewage treatment plants on the Ashwani Khad marked, and the 1% AEP level of the ungauged nallahs and khads, with sediment and debris, as the boundary condition;
- Mandi, Beas and Suketi: the catchments of Mandi that drain to the Beas and the Suketi at their confluence, with the releases of Larji and Pandoh upstream and surveyed flood marks of 2023 and 2025 (the Panchvaktra temple was submerged in July 2023, as reported) as boundary conditions, since CWC has no site there;
- Kullu, Bhuntar and Manali, Beas: the catchments of the valley towns and of every side khad that crosses them, including the Sarvari at Kullu and the Parbati at Bhuntar, with the old channels of the Beas that the floods of 2023 reoccupied mapped, the releases of Malana and the Parbati projects as an upstream boundary, and surveyed flood marks as the river boundary;
- Dharamshala–Kangra, Dhauladhar khads: the catchments of the khads that cross Dharamshala, McLeodganj and Kangra, among them the Manjhi, the Gaj, the Banner and the nallah at Bhagsunag that flooded on 12 July 2021, with debris racks and basins at the foot of the range and the 1% AEP level with debris as the boundary condition;
- Baddi–Barotiwala–Nalagarh, Sirsa and Balad: the catchments that drain to the Sirsa and the Balad through the Sandholi, Housing Board, Chikni and Ratta khads and the industrial drains, with the effluent plant outfall in the 1D network and the separation of industrial drains from storm drains shown;
- Parwanoo, Sukhna: the catchments of Parwanoo that drain to the Sukhna, with its sewage loads;
- Una, Swan: the catchments of Una that drain to the Swan through its embankments, with the level at CWC's Ghaluwal site (high flood level 367 m) and the surveyed 1% AEP level of the channelised river as the boundary, and the outfall-closed case a design case;
- Paonta Sahib, Yamuna and Bata: the catchments that drain to the Yamuna and the Bata, with the level at CWC's Paonta site (danger 384.5 m, high flood level 384.6 m) and at Ganguwala (373.52 m) as the boundary and the outfall-closed case a design case;
- Bilaspur and the Pong shore, reservoirs: the catchments of Bilaspur that drain to Gobind Sagar and of Dehra and the other towns that drain to Pong, with the reservoir at the level of Chapter 5, converted from feet, as the boundary, and the khads feeding the reservoir kept free of muck;
- Rampur Bushahr, Sutlej: the catchments of the town and its khads, with the high flood level at CWC's Rampur site (933 m, set by the Parechu outburst of 2005; a 2023 reading of 924.5 m conflicts) and a glacial-lake or landslide-lake outburst scenario as boundary conditions; and
- Chamba, Ravi, and other valley towns: the catchments of the town and of every khad that crosses it, with surveyed flood marks where CWC has no site, and the debris fans, landslide and sinking zones above the town mapped.
Hazard first in the high mountains (set by this Manual). In sub-area HP-C (High and trans-Himalaya; Kinnaur–Lahaul–Spiti; snow-fed) of Annex 2A, and in any basin with a glacier, a glacial lake or a mapped debris-flow fan above it, the BSMP begins with a hazard screening for glacial-lake outbursts, debris flows and landslide dams, made with HPSDMA, the State Centre on Climate Change and CWC's glacial-lake monitoring, and uses site-specific hydrology in place of the zone-7 report (Clause 2.3.6(i)). The State Centre on Climate Change counted 562 glacial lakes in the Sutlej basin, 242 in the Chenab, 93 in the Beas and 37 (38 in another report) in the Ravi in 2019 (as reported), and the outburst of the Parechu lake in Tibet on 26 June 2005 raised the Sutlej by 12–15 m and set the high flood levels at Titang, Nathpa and Rampur (as reported). The hazard zones are shown on the 1% AEP map, no drain, storage or pumping station is sited in them, and no work in the CIP is sized to carry a debris flow or an outburst. Other Tier A bodies, among them Solan, Palampur, Hamirpur and Nahan, shall define their basins in the first BSMP that covers them. Where CWC, BBMB, a dam operator, the Jal Shakti Vibhag, a development plan or a court has a high flood level, a reservoir level, a flood line or an operating rule for a dam, barrage or pumping station, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.
Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.
Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Himachal Pradesh a single nallah passes through many hands on its way to a river. In Shimla the nallahs are at once storm drains, sewage carriers and the catchments of water sources: the Ashwani Khad, which drains the south of the city to the Giri, took the effluent of the Malyana and Dhalli sewage treatment plants and caused the outbreak of hepatitis E that began in January 2016, after which its water intake was shut (Bhagra et al., 2017); the drains in the town are the Municipal Corporation's, its sewers SJPNL's, its road drains PWD's, NHAI's or CPWD's, and the forest slopes above them the Forest Department's; and the drains built under the Smart City Mission are the company's until they are handed over. In Baddi–Barotiwala–Nalagarh the Sirsa, about 54 km long with a catchment of about 550 km², runs 28 km in Himachal Pradesh between reaches in Haryana and Punjab, and its industrial drains, khads and the effluent plant outfall are the concern of BBNDA, HPSIDC, the Jal Shakti Vibhag, HPSPCB and the ULBs. No rule divides the khads and natural nallahs from the municipal drains (as this Manual reads the record); the only State power found to regulate a "line of natural drainage" and order obstructions removed is s.43 of the Minor Canals Act 1976. This clause makes the basin the planning unit, so that one model carries each nallah from its head on the ridge to the river whoever owns each reach, and so that the sewage it carries is separated before it reaches a water source (Chapter 8, Clause 8.9.5).
11.4 Who prepares, and when
11.4.1 Lead Authority.
- For the basins of a town with a Municipal Corporation: the Municipal Corporation (in Shimla, SMC; elsewhere the Municipal Corporations of Dharamshala, Mandi, Solan and Palampur), whose drains are run under the Himachal Pradesh Municipal Corporation Act 1994, jointly with the TCP Department, which prepares the interim and final development plans of the planning areas, among them the Shimla Development Plan 2041, into which the BSMP is taken (Clause 11.9); either may prepare the plan as the Urban Development Department directs. In Baddi–Barotiwala–Nalagarh, BBNDA is joint Lead Authority with the ULBs in its area. Where a basin extends beyond the ULB or the planning area, the other local bodies, the panchayats and the planning authorities in the basin are partners, and one BSMP covers the whole basin (Clause 11.3.1).
- No order dividing the khads and natural nallahs from the municipal drains, or the drains of the local bodies from the rivers and reservoirs, was found; until one is made, this Manual assigns the reaches within each BSMP as follows, each body being Lead Authority for the reaches and works it owns or runs and for the parts of the CIP on them: the Jal Shakti Vibhag for the rivers, khads and nallahs outside ULB limits with their beds, banks and flood-protection and channelisation works, among them the Swan, the Sirsa, the Balad and the Beas, and for the kuhls in its charge; the Municipal Corporation, Nagar Parishad or Nagar Panchayat for the drains and nallahs within its limits; Shimla Smart City Ltd and Dharamshala Smart City Ltd, HIMUDA, HPSIDC, BBNDA or a colony developer for the drains of their works and schemes, until handed over in writing; PWD for the side drains, catch-water drains, scuppers and culverts of the State roads and hill roads, and NHAI, CPWD and BRO for theirs, with the muck dumps of their works; SJPNL in Shimla and the Jal Shakti Vibhag elsewhere for the sewers and treatment plants whose effluent reaches the drains; BBMB for Bhakra (Gobind Sagar), Pong and Pandoh, and NTPC, SJVN, NHPC, HPSEBL and the other operators for their dams, for their reservoir levels and releases; the State Wetlands Authority, with HIMCOSTE as its secretariat, and the Forest Department for Pong Dam Lake, Renuka, Chandertal, Rewalsar, Khajjiar and other wetlands; and HPSDMA, with the State Centre on Climate Change, for the mapping of landslide, debris-flow and glacial-lake hazards that a BSMP must show.
- In Tier B bodies: the Lead Authority is named by the Urban Development Department. Basins draining to a common river reach, reservoir or tal may be grouped into one district-level plan.
HPSDMA, the Deputy Commissioner and the State Geologist shall be consulted on every BSMP; BBMB or the dam operator on every BSMP whose basin drains to a reservoir or to a river below a dam; the State Wetlands Authority on every BSMP whose basin drains to a Ramsar site or wetland of national importance; HPSPCB on every BSMP that proposes works on a drain or khad that carries sewage or industrial effluent, among them the Ashwani Khad, the Sirsa, the Balad and the Sukhna; the Collector or the managing body on any work that crosses or discharges to a scheduled kuhl; and, for a basin whose outfall lies on a river shared with a neighbouring State, such as the Sirsa below Nalagarh, the Swan below Una or the Yamuna at Paonta, that State's water resources department, through the Jal Shakti Vibhag.
The Jal Shakti Vibhag shall be a partner in every BSMP that includes a river, canal or tank under its control.
11.4.2 When a BSMP is required.
- (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
- (b) A BSMP is required before:
- any regional detention or fee-in-lieu is accepted under Clause 4.13;
- a fee held under Clause 4.5.6.3 is spent; and
- a basin-specific release rate is applied under Clause 11.8.3.
- (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.
11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.
11.5 Data and surveys
11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:
Table 11.1 — Minimum data and surveys for a BSMP
| Data | Minimum requirement |
|---|---|
| Terrain | Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum |
| Drain network | Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm |
| Waterbodies | Survey of every tank, tal, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment |
| Rivers and canals | Cross-sections at no more than 200 m spacing and at every structure |
| Outfalls, rivers, khads, reservoirs and tals | The datum of every level named; outfall invert levels against the warning, danger and high flood levels of the receiving river at the nearest CWC site and its recorded peaks (on the Yamuna at Paonta a warning level of 383.5 m, a danger level of 384.5 m and a high flood level of 384.6 m; elsewhere high flood levels only, such as 367 m on the Swan at Ghaluwal and 933 m on the Sutlej at Rampur, where a reading of 924.5 m is also quoted; CWC levels as transcribed by SANDRP, as reported), with any local gauge kept as a separate series; for the Beas at Manali, Kullu, Mandi and Pandoh, the Sutlej at Bilaspur, the Ravi at Chamba and the ungauged khads and nallahs, surveyed flood marks, the debris lines of 2023 and 2025 and the 1% AEP flood level with its sediment and debris; for outfalls to reservoirs and tals, the maximum water level, full reservoir level and spillway and gate data from BBMB or the operator, converted from feet where BBMB publishes them so (for example Gobind Sagar, full reservoir level 1,680 ft, about 512.06 m; Pong, full reservoir level 1,390 ft, about 423.67 m, with a maximum level quoted as 1,400, 1,410 or 1,421 ft; Kol, reservoir level 642 m), naming which is used, and Rewalsar and the other tals at their outlet levels; the release records of Larji, Pandoh, Malana, the Parbati projects, Nathpa Jhakri, Kol, Bhakra and Pong; the debris-flow fans, landslide zones, muck dumps and glacial lakes above the basin, from HPSDMA, the State Centre on Climate Change and CWC's glacial-lake monitoring where mapped; and the sluices, flap gates, debris racks, sediment traps, debris basins and pumping stations on the outfalls, with their capacities and operating rules |
| Rainfall and levels | All available rain gauges (IMD, including its observatories and stations at Shimla, Dharamshala, Kangra (Gaggal), Mandi, Sundernagar, Una, Solan, Bhuntar, Manali, Kalpa and Keylong and the automatic weather stations reported by the Meteorological Centre Shimla, among them Una Rampur and Kangra Aero; the district and tehsil rain gauges of the State; the self-recording gauges at Shimla, Dharamshala, Dharampur, Nahan, Dalhousie, Sundernagar and Bhuntar used for the CWC Flood Estimation Report for zone 7; the river gauges of CWC; the rain and reservoir records of BBMB at Bhakra, Pong and Pandoh, and of NTPC, SJVN, NHPC and HPSEBL at their dams; and any gauges kept by the Municipal Corporations, the Smart City companies, HPSDMA and the Jal Shakti Vibhag) and water-level records, including those for the 9–11 July 2023 (228.5 mm at Una Rampur AWS on 9 July and 250.0 mm at Nahan on 11 July, IMD, with new high flood levels on the khads of Sirmaur and Kinnaur, as reported), 14–15 August 2023 (273.4 mm at Kangra Aero and 250.2 mm at Dharmsala, IMD, with the slides at Summer Hill and Krishna Nagar in Shimla), 31 July–1 August 2024 (the cloudbursts at Samej, Bagipul and Rajban, where no gauge recorded the rain, as reported), 30 June–1 July 2025 (140.7 mm over Mandi district in 24 hours, with the floods of Seraj and Thunag, as reported) and 5 September 1995 (the Yamuna at Paonta at its high flood level of 384.6 m, CWC as transcribed by SANDRP) events |
| Flood evidence | Surveyed flood marks and mapped flood extents from past events, including public reports |
| Land use | Existing land use and imperviousness; future land use from the statutory master plan |
| Soils and groundwater | HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones |
| Sewer interaction | Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots |
Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the Siwalik valley floors of Una, Paonta–Kala Amb and Baddi–Nalagarh and in the Balh valley, where slopes are gentle and, in the Balh, the water table is near the surface, on the fans and river terraces of Kullu, Manali, Mandi and the other valley towns, where a raised road, a muck dump or a low wall can turn the overflow of a khad from one side of a fan to the other, and along the old channels of the Beas that its floods reoccupied in 2023, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The 9–11 July 2023 (228.5 mm at Una Rampur AWS on 9 July and 250.0 mm at Nahan on 11 July, IMD, with new high flood levels on the khads of Sirmaur and Kinnaur, as reported), 14–15 August 2023 (273.4 mm at Kangra Aero and 250.2 mm at Dharmsala, IMD, with the slides at Summer Hill and Krishna Nagar in Shimla), 31 July–1 August 2024 (the cloudbursts at Samej, Bagipul and Rajban, where no gauge recorded the rain, as reported), 30 June–1 July 2025 (140.7 mm over Mandi district in 24 hours, with the floods of Seraj and Thunag, as reported) and 5 September 1995 (the Yamuna at Paonta at its high flood level of 384.6 m, CWC as transcribed by SANDRP) events are the best calibration data Himachal Pradesh has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.
11.6 Levels of service
11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.
Table 11.2 — Minimum levels of service
| Element | Minimum level of service |
|---|---|
| Minor system | The design AEP of Chapter 6 (Table 6.1) |
| Habitable buildings | No flooding above floor level in the 1% AEP (100-yr) event |
| Critical facilities (hospitals, emergency services, substations, water and sewage plants) | No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event |
| Evacuation routes and arterial roads | Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event |
| Ponding drain time | Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event |
| Tank and tal storage | No net loss of flood storage below the MWL in the basin, measured against the earliest available survey |
| Outfalls | Functioning under the joint and outfall-closed cases of Chapter 5 |
Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been reported but rarely measured. Himachal Pradesh's storage is in its reservoirs, its few natural lakes, its valley floors and its springs more than in tanks. Pong Dam Lake (Ramsar site, 15,662 ha), Renuka (20 ha) and Chandertal (49 ha) are its Ramsar sites (MoEFCC; the State Wetlands Authority's booklet gives the larger areas of the sanctuaries), and Rewalsar and Khajjiar are wetlands of national importance; Rewalsar, a lake of 2.6 ha in a catchment of 173 ha, is reported eutrophic from leaking sewage drains, and Khajjiar silting from its streamlets (State Wetlands Authority). The State Wetlands Authority was constituted on 7 November 2017 under the Wetlands Rules 2017, with HIMCOSTE as its secretariat, but no wetland has been found notified under Rule 4. Pong's water spread varies from about 125 km² at 1,280 ft to about 220 km² at 1,390 ft (booklet), and Gobind Sagar has lost a large part of its storage to silt, by 38% or 47% depending on the source (as reported). Kuhls, the gravity channels scheduled under the Minor Canals Act 1976, and the nauns and baolis of the hill towns are small stores and carriers of hill runoff; the site plans of the TCP Rules must show every "Bauri, Well, Nallah, khud". The losses are visible in the khads and on the shores: muck dumped into Gobind Sagar and its feeding khuds, which the High Court ordered cleared (2024), and the old channels of the Beas built over in Kullu (PDNA, 2023). No survey of the storage of any tal, or of any floodplain inside a ULB, was found.
11.7 Modelling and scenarios
11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:
- the minor system;
- the major (overland) system;
- rivers, canals and tanks; and
- the outfalls.
Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.
11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.
11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.
11.7.4 Scenarios. Each BSMP shall model at least:
- (a) Existing: existing land use, network, tanks and outfalls;
- (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
- (c) Future, controlled: future land use with the site controls of Chapter 4;
- (d) Future, with plan: scenario (c) plus the works of the CIP; and
- (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Himachal Pradesh has been adopted with a design factor; the State Action Plan on Climate Change (version 2, 2021–2030) projects annual rainfall rising by 5.9% (RCP4.5) to 14% (RCP8.5) by mid-century and says that heavy rainfall and floods are "likely to increase", while it finds decreasing trends in annual rainfall and rainy days (high confidence) and in the 1-day maximum (low confidence) over 1951–2013; and the monsoons of 2023 and 2025 brought new 24-hour records at several stations (IMD, with the conflicts stated in Chapter 2) and new high flood levels on the khads of Sirmaur and Kinnaur (as reported), which is a reason to keep the factors, not to reduce them; in snow-fed basins of sub-area HP-C the climate scenario adds no rainfall factor, and the debris-flow and glacial-lake hazards of Clause 11.3.3 are mapped instead.
11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the 9–11 July 2023 (228.5 mm at Una Rampur AWS on 9 July and 250.0 mm at Nahan on 11 July, IMD, with new high flood levels on the khads of Sirmaur and Kinnaur, as reported), 14–15 August 2023 (273.4 mm at Kangra Aero and 250.2 mm at Dharmsala, IMD, with the slides at Summer Hill and Krishna Nagar in Shimla), 31 July–1 August 2024 (the cloudbursts at Samej, Bagipul and Rajban, where no gauge recorded the rain, as reported), 30 June–1 July 2025 (140.7 mm over Mandi district in 24 hours, with the floods of Seraj and Thunag, as reported) and 5 September 1995 (the Yamuna at Paonta at its high flood level of 384.6 m, CWC as transcribed by SANDRP) events where data exist.
Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and tals with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.
Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).
11.8 Options, outputs and the Capital Improvement Programme
11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:
- Protect and restore storage: tals, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
- Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
- Conveyance upgrades to drains, canals and culverts;
- Outfall works: flap gates and penstocks on the outfalls to the Yamuna at Paonta, the Swan at Una and the Beas at Mandi, and on the outfalls of Bilaspur and the Pong-shore towns to the reservoirs, with storage or pumping behind them where a river in flood or a reservoir held near its full level can close an outfall; debris racks, sediment traps and debris basins where khads and nallahs from the hills enter the towns, with ramps for the machines that empty them, and the removal of muck dumped in the khads and nallahs; drop structures, chutes, energy dissipators and protected outfalls where steep drains reach a khad or river, never an unprotected slope; screening, and the separation of sewage and industrial effluent, before the outfalls to the Ashwani Khad, the Sirsa, the Balad and the Sukhna; and the release rules of Larji, Pandoh, Bhakra, Pong and the other dams that set the receiving levels, agreed with BBMB and the dam operators;
- Property-level protection where works cannot reach the level of service; and
- Non-structural measures: flood warning (for example IMD district rainfall warnings and nowcasts issued by the Meteorological Centre Shimla, the CWC flood forecast for the Yamuna at Paonta and the river stages at its other sites, notice of releases from Larji, Pandoh, Malana, Kol, Nathpa Jhakri, Bhakra and Pong to the towns downstream, the forecast-based dam management system and early warning that the PDNA of 2023 proposes, and the district emergency operation centres of HPSDMA), flood-hazard zoning, emergency planning and public information.
11.8.2 Option assessment. Each option shall be assessed for:
- reduction in flood risk (buildings and people flooded; expected annual damage);
- capital and 30-year maintenance cost;
- land required;
- effect on groundwater recharge on the Siwalik valley fills of Una, Paonta–Kala Amb and Nalagarh, where the stage of extraction is highest (Una 63.72%, Solan 57.89%; CGWB, 2024), the stability of hill slopes, where water put into debris cover, colluvium or moraine raises the pore pressure, as at Summer Hill and Krishna Nagar in Shimla in 2023, the springs, nauns and baolis that supply the hill towns and their recharge areas, such as that of the Bohal spring above Palampur, the kuhls that carry hill runoff, the high water table of the Balh valley, and the quality of the groundwater, which the Ground Water Act 2005 protects against effluent (s.5A), and of the rivers, khads, reservoirs and tals that the runoff reaches (Chapter 8);
- effect on downstream basins and the receiving river, khad, reservoir, tal or kuhl; and
- who benefits.
11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.
11.8.4 Outputs. Each BSMP shall produce:
- (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
- (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
- (c) regional facility sites, with storage volumes, land needs and the sites they serve;
- (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
- (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
- (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
- (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.
Commentary. Restoring storage comes first because many of Himachal Pradesh's town outfalls are closed or limited in the wettest weeks, and because the storage left is on valley floors and in khad beds that the towns are filling. In July 2023 the Bata beside Paonta and the Meenus and other khads of Sirmaur rose to new high flood levels and the Beas submerged the Panchvaktra temple at Mandi, and Gobind Sagar and Pong were held near their full levels in August and September of 2023 and 2025 (as reported). The rivers once spread their floods over wide beds and old channels: the PDNA of 2023 found that the damage along the Beas in Kullu followed the palaeo-channels on which building had taken place, and muck from roads and hydro projects has been dumped into khads and Gobind Sagar (High Court, 2024). Concrete channels alone have not served: the PDNA advised against concreting the Beas and for nature-based solutions, and the expert committee before the Tribunal found Shimla's drains unable to carry the peak flow (2017). On a hill slope storage means a lined tank or a terrace, never a pond that soaks into the slope (Clause 8.8.1), and the roof-top storage of 20 litres per m² that the TCP Rules require is the first of it. The storms are large for drains with no stated design basis: the Flood Estimation Report lists 600 mm in a day at Dharamshala (18 July 1967), and 273.4 mm fell at Kangra Aero on 14 August 2023 (IMD). Conveyance upgrades on their own move water faster to an outfall that the Yamuna at Paonta, the Swan at Una or the Beas below Pandoh in flood, or Gobind Sagar, Pong or another reservoir held near its full level, may close, to a khad or nallah whose bed and banks shift with the boulders, slide debris and muck it carries, or to an outfall limited by the capacity of its gate or pumping station. Groundwater in Himachal Pradesh calls for recharge in the valley fills and for restraint on the slopes. The State's stage of extraction was 35.48% in 2024, and all ten assessed valley units were safe, the highest being Una (63.72%) and Solan, for the Nalagarh valley (57.89%); seven districts, Kullu, Shimla, Bilaspur, Hamirpur, Chamba, Kinnaur and Lahaul–Spiti, have no assessment unit (CGWB, 2024). The coarse Siwalik fills of Una, Paonta–Kala Amb and Nalagarh have deep water tables, so recharge there helps; in the Balh valley the water stood 0.3–7 m below ground, so recharge there adds to waterlogging (CGWB). On the hill slopes water put into the ground can bring them down: the committee on the Shimla slides of 2023 found old buried stream channels and structural depressions acting as "conduits for the infiltration of subsurface water", and the draft Ground Water Rules of 2006 exempt sinking zones from rainwater-harvesting directions where structures "would be detrimental to the safety of the building structures". The hill towns depend on springs, nauns and baolis, of which about 500 have been inventoried in a standard format (NITI Aayog, 2021), and Palampur pays the forest committee of Bohal to protect the recharge area of the spring that supplies it (2010). The Ground Water Act 2005 is in force, with an enabling power for rainwater harvesting on premises of 100 m² or more (s.15) and a bar on effluent that contaminates groundwater (s.5A). This is why recharge, slope stability, springs, waterlogging and groundwater quality are all assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.
11.9 Integration with land-use planning
11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the interim and final development plans of the planning areas and special areas notified under the Himachal Pradesh Town and Country Planning Act 1977, among them the Shimla Development Plan 2041 and the development plans of 2041 for the other planning areas, with their regulations and the TCP Rules 2014; the plans of BBNDA, HIMUDA and HPSIDC for their areas; and the layouts and buildings permitted under them. In particular:
- (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
- (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
- (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
- (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.
11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.
Commentary. Himachal Pradesh draws few water lines by rule, and no drainage-flood line. Where no development plan exists, Appendix-1 of the TCP Rules 2014 allows construction 3.00 m from a nullah and 5.00 m from a khud, without saying from what line they are measured, and a slope of up to 45°; in planning areas the distance from the high flood level along rivers, khuds and nullahs is as the development plan delineates it, and the Chopal plan of 2041, for example, puts flood plains and land "adjacent to major drainage lines" among its non-developable land; elsewhere no construction is allowed on land "prone to floods" (Appendices 3 and 7). The 5 m buffer of Shimla's interim plan is from the green belts, not from the nallahs. The State has no floodplain zoning law and no notified flood line, and the PDNA of 2023 found that "the lack of well-defined river boundaries in floodplains is a prominent issue in Himachal Pradesh", that the destruction along the Beas in Kullu followed its old channels, built over, and that "there is a pressing need for comprehensive river boundary mapping and the establishment of floodplain management guidelines". The setbacks announced in 2025, 5 m from drains and 7 m from rivers and ravines, 150 m for government buildings, and no building along rural river and stream banks, are press reports without a gazette text and are not applied. These are watercourse lines, not drainage-flood lines: where a development plan draws a high-flood line it governs; elsewhere the hydraulic corridor and setback zones of Chapter 7, with a Zone 1 of at least 15 m, and the TCP lines of 3 m and 5 m apply, whichever is wider, as this Manual's proposal, and old river courses are kept free. A BSMP gives the development plans the 1% AEP drainage-flood map, including the khads and nallahs that no plan yet covers, and the buffer widths of Chapter 7, that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because the TCP Rules 2014 already require roof-top rainwater storage of 20 litres per m² of roof for every building and, in colonies and IT parks, underground rainwater storage in the parks and open spaces (Appendix 6), reserve 5% of a new sub-division for soak pits and the like, and ask that plots be laid out for the natural flow of surface drainage (Appendix-1, cl. 20(4)–(5)), but no rule sets a detention or peak-runoff limit; storage placed in a layout's open space builds on these duties, and because that land still serves as open space, the storage must stay usable as one, and on a hill slope it is a lined tank or a shallow terrace, never an infiltration basin (Clause 8.8.1). Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.
11.10 Consultation and publication
11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.
11.10.2 After approval, the following shall be published as open data:
- the model files;
- the flood hazard maps;
- the data of Clause 11.5.1, except security-sensitive asset details; and
- the CIP.
They shall also be shown on a public map viewer.
Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.
11.11 Approval, review and reporting
11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.
11.11.2 Review. Each BSMP shall be reviewed:
- every 10 years;
- within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
- when the statutory land-use plan is revised.
11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each SW monsoon (by 31 May). The report shall show:
- CIP progress;
- the fee-in-lieu ledger (Clause 4.13.4);
- maintenance completed; and
- any flooding against the levels of service.
11.12 Interim arrangements
11.12.1 Until a BSMP is approved for a basin:
- (a) all site criteria of Chapters 4 to 8 apply in full;
- (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
- (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
- (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.
References (chapter)
- Central Ground Water Board (2024). Dynamic Ground Water Resources of India, 2024: Himachal Pradesh (stage of extraction; assessment units), with the assessment of 2022 and the Ground Water Year Book of Himachal Pradesh 2021–22 (depth to water).
- NITI Aayog, IWMI and SDC (2021). Resource Book on Springshed Management in the Indian Himalayan Region (spring inventories; the Palampur–Bohal agreement of 2010).
- Bhagra, S. et al. (2017). Water quality and hepatitis E in Shimla. International Journal of Community Medicine and Public Health 4(6), 1966–1971.
- Shimla Municipal Corporation with GoI–UNDP (2015). Disaster Risk Reduction and Climate Change Adaptation Action Plan, Shimla (13 major nallahs; storm drains; draft City Development Plan 2041 items); and Shimla Municipal Corporation, AMRUT status report (2022).
- Government of Himachal Pradesh. Action plans for the polluted stretches of the Sirsa and the Balad (Baddi–Nalagarh), filed before the National Green Tribunal in O.A. No. 673 of 2018 and O.A. No. 735 of 2023 (drain flows and loads; Baddi sewerage scheme).
- Defra (2010). Surface Water Management Plan Technical Guidance. Department for Environment, Food and Rural Affairs, London.
- Mile High Flood District (Denver). Master planning programme and Urban Storm Drainage Criteria Manual.
- Mid-America Regional Council (2025). APWA Stormwater Standards Supplement; KC Metro APWA Section 5600, Version 2025.01.
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- Government of Himachal Pradesh with NDMA (2023). Himachal Pradesh Post Disaster Needs Assessment, Monsoon 2023 (palaeo-channels of the Beas; river boundaries and floodplain guidelines; Beas channelisation and nature-based solutions; forecast-based dam management); and Monsoon 2023 Recovery and Reconstruction Plan (projects on the Beas at Manali and Bhuntar; storm drainage at Una).
- National Green Tribunal. O.A. No. 121 of 2014, Yogindra Mohan Sengupta v. Union of India, judgment of 16 November 2017 (expert committee's findings on Shimla's drains; set aside by the Supreme Court on 11 January 2024, 2024 INSC 30; cited as expert evidence only).
- National Green Tribunal. O.A. No. 735 of 2023 (Ashwani Khad): affidavit of the Chief Secretary (2024) on dropping river channelisation. https://www.greentribunal.gov.in/
- High Court of Himachal Pradesh. Madan Lal v. State of Himachal Pradesh, CWPIL No. 31 of 2023, order of 31 May 2024 (muck in Gobind Sagar and its feeding khuds).
- Government of Himachal Pradesh, Town and Country Planning Department. Himachal Pradesh Town and Country Planning Rules, 2014, consolidated to 2022, Appendix-1 (cls. 3 and 16) and Appendices 3 and 7; Chopal Planning Area Development Plan 2041 (non-developable land). https://tcp.hp.gov.in/
- Himachal Pradesh State Wetlands Authority. Notification No. STE-E(3)-10/2017-Pt-I of 7 November 2017 (constitution); booklet Major Wetlands of Himachal Pradesh (Pong, Renuka, Chandertal, Rewalsar, Khajjiar). Ministry of Environment, Forest and Climate Change, 80 Ramsar sites of India (31 January 2024). https://moef.gov.in/uploads/2024/03/80-Ramsar-sites-of-India-31-01-2024.pdf
- Government of Himachal Pradesh, Department of Environment, Science and Technology (2021). State Action Plan on Climate Change, Version 2.0 (2021–2030). https://napccindia.moef.gov.in/resources/pdfs/himachal-pradesh-sapcc-2.0.pdf
- NITI Aayog, DMEO (2020). Best practice note: Swan River Flood Management Project, Una; Rajya Sabha answer of 29 July 2024 (project cost).
- India Meteorological Department, Meteorological Centre Shimla. Monsoon Report 2023 and 2025 (extremely heavy rainfall stations; records).
- South Asia Network on Dams, Rivers and People (2022–2025). Posts on CWC flood monitoring sites in north India and on rivers breaching their high flood levels in July 2023 (transcriptions of CWC data). https://sandrp.in/
- The Tribune, Down To Earth, thenewshimachal.com and PTI (2023–2026). Reports of Shimla's drains and SJPNL's study, the British-era drains, Dharamshala's Smart City drainage, the glacial-lake counts of the State Centre on Climate Change, Pong and Bhakra levels and the Parechu flood of 2005 (secondary sources).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 11A | BSMP terms of reference template |
| 11B | Basin lists and boundaries for Tier A bodies |
| 11C | Depth–damage curves for Himachal Pradesh building types |
| 11D | BSMP data and model publication standard |
| Form 11-1 | Annual implementation report |
Commentary. Himachal Pradesh's towns have drainage projects and proposals, but no published storm-drainage master plan with a design storm. In Shimla, whose network goes back to drains of the British period whose records the Municipal Corporation has sought from the Revenue Department so that they can be reopened (as reported), the expert committee before the National Green Tribunal found in 2017 that storm drains covered about 30% of the city and could not carry the peak flow, with catchments "improperly selected" and gradients far too flat. The counts of the network conflict: the Corporation's disaster-risk plan of 2015 (with UNDP) gives 13 major nallahs and about 67 storm drains with a total length of about 42.33 km, while its AMRUT reports record 191 major storm drains and nallahs, 55.43 km, built for ₹20.64 crore, probably a different scope; its draft City Development Plan 2041 proposes ₹25.47 crore of new drains and ₹179.00 crore for the rejuvenation of the major nallahs; and after the slides of 2023 the Corporation asked SJPNL for a study by geologists, remote sensing and drones and a project report on its drains, whose output was not found (as reported). In Dharamshala the drainage is reported still inadequate after Smart City spending of more than ₹500 crore (as reported), and no drainage project report was found. In Baddi–Barotiwala–Nalagarh the drains are planned through the action plans for the polluted Sirsa and Balad, which list the loads of the Balad Khad, the Sandholi, Housing Board, Khera, Manpura and HPSIDC drains and the common effluent treatment plant outfall, and a sewerage scheme of ₹33.34 crore for Baddi, but no storm-drainage master plan of BBNDA was found. For the Beas at Mandi and in Kullu–Manali a channelisation project report of 2021, of about ₹1,600 crore, "may reach around Rs. 2000/- crore", but the PDNA of 2023 advised that channelisation "predominantly require[s] concretisation, which is not advisable in Himalayan Ecology" and asked that the proposal be reviewed "with Nature Based Solution Approach", and the State has told the Tribunal that it recommended dropping channelisation because it "may affect the cross drainage and hamper the natural drainage system" (O.A. No. 735 of 2023, 2024); the recovery plan lists protection works on the Beas at Manali (₹243.37 crore) and against flash floods at Bhuntar (₹31.23 crore). At Una the Swan has been channelised by the Jal Shakti Vibhag with embankments and the treatment of its tributaries (₹945.49 crore or ₹922.49 crore; the figures conflict), with no design return period stated, and a proposal of ₹19.66 crore for storm drainage in Una town awaits funding. No published document sets a design return period for the storm-drain network of any Himachal Pradesh town. This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by the TCP Department, the Urban Development Department, any Municipal Corporation or other ULB, the Jal Shakti Vibhag, SJPNL, BBNDA, HPSDMA or any other body. A site-level manual cannot fix basin-level problems: lost tank storage, khads and nallahs that carry boulders, slide debris and muck onto towns built on their fans, terraces and old channels, as along the Beas in Kullu in 2023, slopes that open drains saturate, as at Summer Hill and Krishna Nagar in Shimla in 2023, drains that end in reservoirs held high by BBMB or in rivers below dams, nallahs that carry sewage to drinking-water sources, as to the Ashwani Khad in 2016, and single drains split between a Municipal Corporation, PWD, SJPNL, the Jal Shakti Vibhag and a Smart City company, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:
This chapter adapts that method to Himachal Pradesh, the second mountain State in the series after Uttarakhand: to towns in three settings, the Siwalik valleys of Una, Baddi–Nalagarh and Paonta, whose drains cross boulder fans to rivers held high by floods or by channel embankments; the mid-hill towns, Shimla, Solan, Mandi, Dharamshala and Chamba among them, built on slopes of 45°–60° where open drains saturate the debris cover and slides decide more than the design storm; and the valley towns of Kullu, Manali and Rampur, on terraces, fans and old river channels below dams and glaciers; to reservoir towns, Bilaspur and the towns of the Pong shore, whose drains end in BBMB's reservoirs, with levels published in feet; to nallahs that are storm drains, sewers and water-source catchments at once, as the Ashwani Khad showed in 2016; to drains run by ULBs, PWD, SJPNL, the Jal Shakti Vibhag and Smart City companies, beside khads that no rule assigns; to a State with its own planning, groundwater and minor canals Acts, but no floodplain law, no flood line and no design return period for the drains of any town; to springs and kuhls that supply and drain the hill towns, and slopes that infiltration can destabilise; and to a monsoon whose worst days, 600 mm at Dharamshala in July 1967 (CWC Flood Estimation Report, zone 7) and the cloudbursts of 2023–2025, fall where few gauges stand, and whose worst floods in the high valleys, Parechu in 2005 and Samej in 2024, were outbursts and debris flows that no drain can carry, so that in the high mountains a BSMP begins with the hazard, not the storm (Clause 11.3.3).