Chapter 5Downstream and Tailwater Analysis
5.1 Purpose and scope
5.1.1 This chapter sets two checks that every regulated development and every public drainage project must pass.
- The downstream analysis (Clauses 5.3 to 5.5) confirms that the project does not make flooding worse below its outfall.
- The tailwater analysis (Clauses 5.6 to 5.13) sets the water level the system discharges into, including tide, storm surge, sea-level rise, river backwater and sand-bar closure. It also requires the system to cope when its outfall is closed.
5.1.2 This chapter applies to:
- (a) every site to which Chapter 4 applies;
- (b) every minor- and major-system drainage project under Chapter 6; and
- (c) every regional detention or tank restoration project under Clause 4.13 and Chapter 7.
5.1.3 Rainfall and joint-occurrence inputs come from Chapter 2, in particular Clauses 2.5.3 and 2.12. Hydrologic methods come from Chapter 3. Site release criteria come from Chapter 4. Hydraulic design of gates, culverts and pumps follows Chapter 9.
5.1.4 No tidal outfalls in Himachal Pradesh. Himachal Pradesh is landlocked and mountainous: it has no coast, no tide and no Coastal Regulation Zone, and a monsoon system reaches it only as rainfall, often meeting a western disturbance over the hills, as in July 2023; that rainfall is dealt with in Chapter 2, not as a tidal or surge level. No outfall in the State discharges to the sea, a tidal creek or an estuary, so the provisions of this chapter that depend on tide, storm surge, sea-level rise or a river mouth do not apply in Himachal Pradesh: Clause 5.7 and Annex 5A, cases J1 to J3 of Table 5.2, the tidal lock windows of Clause 5.10.3, the seawater requirement of Clause 5.11.3(a) (gates and seats shall still be of corrosion-resistant materials, and shall resist abrasion by gravel and boulders), and Clause 5.13. They are kept so that the clause numbers of this Manual match its other State editions. In Himachal Pradesh the receiving water is one of five kinds: a river, reached directly, through a gate in a bank or embankment or through a pumping station, such as the Yamuna at Paonta Sahib, the Sutlej at Rampur, the Beas at Kullu and Mandi, the Swan at Una and the Ravi at Chamba, whose level rises and falls within hours in the mountains but is held up for days by long monsoon spells and by the releases of the dams above it; a khad or nallah, such as the nallahs of Shimla and the Ashwani Khad, the Suketi at Mandi, the khads below Dharamshala or the Sirsa and the Balad at Baddi–Nalagarh, ungauged, seasonal and laden with boulders, whose bed rises and falls in a single flood; a reservoir held near its full level, such as Gobind Sagar at Bilaspur, the Pong reservoir and the Pandoh reservoir; a tal (ताल; a pond, lake or tank), such as Rewalsar, Khajjiar or Renuka; or a kuhl (कूहल; a gravity irrigation channel) or canal; and:
- (a) its tailwater is set by Clauses 5.6 and 5.8, including Clause 5.8.5;
- (b) where Clauses 5.10 to 5.12, Form 5-1 or Chapter 6 refer to the J1 tailwater or the J1 tidal curve, the minor-system tailwater of Clause 5.6.2 or 5.8.5 applies, as a time series where the receiving level varies; where they refer to the J2 tailwater or to HAT + surge + SLA, the major-system tailwater applies: the design-AEP river level of Clause 5.8.4(b), or the major-system tailwater of Clause 5.8.5, whichever is higher at the outfall; and
- (c) the outfall-closed check of Clause 5.10 applies where an outfall is closed by a river, a khad or nallah, a reservoir or barrage pond, a tal, a kuhl or canal or a receiving drain, with the river lock of Clause 5.8.5(a) and the closures of Clause 5.8.5(b) to (e) in place of the tidal lock windows.
5.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Analysis point | A location on the downstream system where pre- and post-project conditions are compared (Clause 5.3.3). |
| Contributing catchment | The whole area draining to an analysis point, on and off site. |
| Major drain | A channel listed as a major drain in the basin plan or Annex 5B, or any river, Jal Shakti Vibhag canal, the nallahs of Shimla that run north to the Sutlej and south to the Ashwani Khad and the Giri, the Suketi and its khads at Mandi, the Manjhi, Gaj, Banner and Neugal khads and the Bhagsunag nala below Dharamshala, Kangra and Palampur, the Sirsa, the Balad and the Sandholi and other nallahs of Baddi–Barotiwala–Nalagarh, the Swan and its tributary khads at Una, the Bata at Paonta Sahib, the side khads of the Beas in the Kullu valley, any kuhl in Schedule I or II of the Himachal Pradesh Minor Canals Act 1976 that receives storm water, the Beas–Sutlej Link, any drain built or held by a Municipal Corporation, a Nagar Parishad or Nagar Panchayat, HIMUDA, BBNDA, HPSIDC, a Smart City company or PWD with an internal width of 1.0 m or more, and every khad, nallah or choe that drains 8 ha or more, or a tidal creek. |
| Chart datum (CD) | The datum of the published tide tables and nautical charts, to which tidal heights are referred. |
| Mean sea level (MSL) | Average sea level over a long period at a tide gauge. |
| MHWS | Mean high water springs: the average of high waters at spring tides. |
| HAT | Highest astronomical tide: the highest level predicted under average meteorological conditions over a full tidal cycle (18.6 years). |
| Storm surge | The rise in sea level above the astronomical tide caused by wind and low pressure, mainly during cyclones. |
| Still-water level | Astronomical tide plus surge, excluding individual waves. |
| Sea-level allowance (SLA) | The allowance added to present-day tidal levels for sea-level rise over the design life (Clause 5.7.4). |
| Tailwater | The water level at the downstream end of a drain, outlet or storage. |
| Tide-lock | The condition in which the tailwater is at or above the upstream water level, so a gravity outfall cannot discharge. |
| Lock window | A period during which the outfall-closed check of Clause 5.10 sets gravity discharge to zero. |
| Sand bar | A bar of beach sand that partly or fully closes a river mouth or creek inlet. |
| Project datum | The levelling datum used on the project drawings. It must be tied to a Survey of India benchmark (Clause 5.7.2). |
5.3 Extent of the downstream analysis
5.3.1 The downstream analysis shall start at each site or project outfall. It shall continue downstream to the first of:
- (a) the point at which the project area is 10% or less of the contributing catchment;
- (b) the next tank, tal or other waterbody with a surplus weir or controlled outlet; or
- (c) the next major drain, or the sea.
The end point itself shall be analysed (Figure 5.1).
5.3.2 Where the analysis ends at a tank or tal under 5.3.1(b), it shall report:
- the change in the tank's maximum water level; and
- the change in surplus-weir discharge, for the AEPs and durations of Clause 5.4.3.
If the maximum water level rises, the analysis shall continue below the surplus weir to the next end point.
5.3.3 Analysis points shall be set at least at:
- (a) each site outfall;
- (b) each confluence with a drain or channel whose contributing catchment is at least half that of the receiving drain at that point;
- (c) each culvert, bridge or road crossing;
- (d) each location recorded as flood-prone by the local body, SMC, HPSDMA or Jal Shakti Vibhag; and
- (e) each building or road segment lying within the 1% AEP flood extent along the route. Representative points may be used where buildings are closely spaced.
5.3.4 Small sites. For sites of less than 0.5 ha, the Authority may accept a simplified downstream statement (Form 5-2) in place of the full analysis, where all of the following hold:
- the receiving public drain has documented capacity for its minor-system design flow (Chapter 6);
- no flood-prone location is recorded within 500 m downstream; and
- the site does not drain to a tidal or backwater-affected outfall.
Figure 5.1 — Extent of downstream analysis: analysis points A–D, the contributing area at each point, the 10% point, and the next tal or major drain as an alternative end point. Schematic; percentages are illustrative. Original drawing for this Manual, adapted from the ten-percent rule in the Georgia Stormwater Management Manual (2016, Vol. 2 §3.1.9) and KC APWA Section 5600 (2006, 5601.5).
Commentary. The 10% rule has established precedent. KC APWA 5600 (2006) required the downstream system to be analysed "to the point the development's land mass is less than 10% of the total watershed". The Georgia manual makes the ten-percent analysis a mandatory standard (GSMM 2016, Standard #8). The tank or major-drain end point has no direct precedent; this Manual adds it for Himachal Pradesh. In the hill towns, where a colony's drain runs down a nallah to a khad, and the khad to a river many kilometres below, as Shimla's nallahs run to the Ashwani Khad and the Giri on one side of the ridge and to the Sutlej on the other, and on the Siwalik valley floors of Una, Baddi–Nalagarh and Paonta Sahib, where the drains run across the fans to the Swan, the Sirsa and the Balad, and the Yamuna, the 10% point can lie many kilometres downstream, across several tanks. A tank with a working surplus weir changes the hydrograph completely, so the analysis is better ended there and the tank level reported. Clause 5.3.2 prevents that end point from hiding a rise in the tank level. The small-site statement (5.3.4) and its 500 m distance have no direct precedent and are set by this Manual.
5.4 What the analysis must check
5.4.1 Scenarios. Each analysis shall compare:
- (a) Existing: the present downstream system and present land use of the whole contributing catchment, with the project site at its pre-project state; and
- (b) With project: the same, with the project and all its controls (Chapter 4) in place.
Where the Authority's basin plan defines future land use, the Authority may also require:
- (c) Future: the catchment fully developed under the plan, all to Chapter 4 standards, with and without the project.
5.4.2 Quantities to be checked at every analysis point:
- (a) Capacity: peak flow against the capacity of every channel, pipe, culvert and crossing, for the minor-system AEP of that element (Chapter 6) and for 1% AEP;
- (b) Flood levels: 1% AEP maximum water level at buildings (at the lowest opening) and on roads (at the crown and at the deepest point);
- (c) Velocities: peak velocity for 50%, 10% and 1% AEP;
- (d) Timing of combined peaks: the hydrograph at each confluence, showing the time to peak of the project outflow and of the receiving drain; and
- (e) Duration of inundation: on roads and at buildings, the time above the Chapter 6 depth limits.
5.4.3 Storms. The analysis shall use:
- 50%, 10% and 1% AEP;
- the duration set of Clause 2.5.2, at least the durations that give the highest level at each analysis point (these will usually be longer than at the site); and
- the 24-, 48- and 72-hour storms in every case.
The AMC rule of Clause 2.11.4 applies. Areal reduction follows Clause 2.7, applied to the contributing catchment at each analysis point and never to the site storage.
5.4.4 Method. The analysis shall:
- use a hydrograph method that combines hydrographs at confluences (SWMM, HEC-HMS, or an equivalent);
- include a hydraulic model with backwater (SWMM dynamic wave, HEC-RAS, or equivalent) wherever tailwater or backwater affects any analysis point; and
- not use the Rational Method at any analysis point, because it cannot represent timing.
Off-site areas shall be modelled at their present land use. Upstream detention shall be included only where it is built, maintained and documented.
5.4.5 Tailwater. The downstream end of the model shall use the tailwater of Clauses 5.6 to 5.9 and the sand-bar condition of Clause 5.13 where applicable.
Commentary. Clause 5.4.2(d) exists because detention changes when the site's water arrives, not only how much arrives (Clause 4.16). A Colorado State University thesis and a Water (2016) optimisation study both found that delayed site releases can coincide with the main-stem peak and raise it. Georgia's manual states the result directly: some structural practices "fail to reduce discharge peaks to pre-development levels downstream" because of "peak flow timing and runoff volume effects" (GSMM 2016). The duration-of-inundation check (5.4.2(e)) matters in the valley and reservoir-shore towns of Himachal Pradesh, whose outfalls lie below rivers and reservoirs held high for days by monsoon spells and dam releases: the Pong reservoir rose from 1,374.20 ft to 1,399.65 ft over 11–15 August 2023 and then released 1.40 to 1.50 lakh cusec into the Beas for days, and in 2025 it released more than one lakh cusec from 29 August and peaked on 5 September (as reported); and on 9 July 2023 the Beas at Mandi rose over the Panchvaktra temple at its confluence with the Suketi (as reported). Detention that prolongs releases can lengthen that time even when it lowers the peak.
5.5 Acceptance criteria
5.5.1 The project is acceptable if, at every analysis point and for every AEP and duration of Clause 5.4.3, comparing "with project" to "existing":
- (a) the 1% AEP maximum water level does not rise by more than 10 mm at any habitable building, at any building's lowest opening, or on any road carriageway;
- (b) no building that is not flooded in the existing case is flooded with the project, and no building or road that meets the Chapter 6 freeboard or depth limits in the existing case fails them;
- (c) peak flow does not exceed the existing peak at the minor-system AEP of each element, or at 1% AEP;
- (d) peak velocity in lined channels stays within the permissible velocity for the lining (Chapter 6: 3.0 m/s maximum); and
- (e) in unlined or natural channels, peak velocity for 50% and 10% AEP does not increase by more than 10%, unless protection is provided under Chapter 9.
5.5.2 The duration of inundation under 5.4.2(e) shall be reported. The Authority may refuse a project that increases the duration of road closure on an arterial or emergency route.
5.5.3 Where the criteria are not met, the project shall do one or more of the following:
- (a) reduce release rates or increase storage (Chapter 4);
- (b) build downstream improvements, with the consent of the owner of the downstream system. These shall not transfer the problem further downstream, and shall be re-analysed under this chapter;
- (c) contribute to a regional facility under Clause 4.13; or
- (d) under Clause 5.5.4, change the release strategy.
5.5.4 Timing exception. Where the analysis shows that detention raises downstream levels because of timing, the Authority may vary the site release-rate criteria of Clause 4.5. This applies only where the site discharges within the lower tenth of the contributing catchment, directly to a major drain, tidal creek or the sea, and only on the following conditions:
- (a) the varied strategy meets 5.5.1;
- (b) the retention requirement (Clause 4.4) and WQv treatment (Chapter 8) are met in full; and
- (c) the outfall-closed check (Clause 5.10) is met.
Commentary. The 10 mm tolerance (5.5.1(a)) has no direct precedent. It is meant to be at or below the numerical precision of a typical one-dimensional model, so that "no increase" can be tested without arguing over rounding. The 10% velocity tolerance is likewise set by this Manual. The timing exception in 5.5.4 follows the Georgia manual, where the downstream analysis can show "that peak controls are not needed" and allow them to be waived (GSMM 2016, Standard #8). It is limited here to sites low in the catchment, which is where synchronisation with the main-stem peak is most likely (Water 2016, 8(7):290). It is not available above that, because the evidence on scale (Clause 4.16) shows that early release from many upstream sites raises peaks.
5.6 Tailwater: general and non-tidal outfalls
5.6.1 Every drain, outlet and storage shall be designed against a stated tailwater. A free outfall shall be assumed only where the outlet invert is above the maximum receiving water level for the case being checked.
5.6.2 Minor-system tailwater, non-tidal. The tailwater is the receiving system's water level at the time of the minor-system peak, from the downstream model. Where no model exists, use:
- for a receiving pipe, its obvert; or
- for a receiving open drain, its full-bank level less freeboard (Chapter 6).
5.6.3 Major-system tailwater, non-tidal. The tailwater is the receiving system's 1% AEP water level, unless Clause 5.8 allows a coincident lower level.
5.6.4 Tidal and backwater outfalls. Clauses 5.7 to 5.13 apply in addition.
5.6.5 Storage elements. Detention, tanks and pumped sumps shall be routed with a time-varying tailwater (Clause 4.6.6), not a constant level, wherever the tailwater varies with tide or with the receiving system's hydrograph.
5.7 Tidal tailwater: datums, surge and sea-level allowance
5.7.1 Design tailwater levels. For outfalls to the sea, tidal creeks, estuaries, backwaters and tidal reaches of rivers and canals:
Table 5.1 — Design tailwater levels for tidal outfalls
| Design case | Tailwater |
|---|---|
| Minor-system design (Chapter 6) | MHWS + SLA |
| Major-system design and storage design | HAT + surge + SLA, with the surge term defined in Clause 5.7.3 |
| Joint case (Clause 2.12(b)) | 1% AEP still-water level + SLA |
The SLA is +0.3 m minimum (Clause 5.7.4). The cases to be run are listed in Clause 5.9.
5.7.2 Sources and datums.
- (a) Tidal levels. MHWS, HAT and MSL shall be taken from the current edition of the Indian tide tables published by the National Hydrographic Office (NHO) or by the Survey of India, for the nearest standard or secondary port, or from the port authority's published tidal levels. The edition and port shall be stated.
- (b) Datum conversion. Tide-table heights are referred to chart datum. They shall be converted to the project datum through a documented connection between chart datum, the tide gauge zero and a Survey of India benchmark. The offset and its source shall be stated on Form 5-1.
- (c) Estuaries, creeks and canals. For outfalls inside estuaries, creeks, backwaters or tidal canals (for example the estuaries of the coastal States; there is none in Himachal Pradesh, Clause 5.1.4), tidal levels may differ from the open coast. Open-coast levels shall be used unless measured levels over at least one spring–neap cycle, or a calibrated hydrodynamic model, justify a different value. No reduction below open-coast levels shall be taken without such evidence.
- (d) Interim. Until Annex 5A is published, the designer shall obtain the values directly from the sources in (a) and record them.
5.7.3 Storm surge.
- (a) Major-system and storage design. The surge term in "HAT + surge" is the 10% AEP (10-yr) storm surge for the coastal segment, given in Annex 5A. The 1% AEP surge is used only in the joint case of Clause 2.12(b), with the 10-yr 48-hour storm. That keeps the two cases symmetric, so that a rare rainfall is never paired with a rare surge.
- (b) Joint case. The 1% AEP still-water level for Clause 2.12(b) is taken from Annex 5A.
- (c) Until Annex 5A is published, both values shall be taken from a site-specific study using INCOIS, IMD or NCCR surge hindcasts or return-level analyses. The study shall state its source, method and record length.
- (d) Wave set-up shall be added where the outfall faces the open sea without a protected entrance.
5.7.4 Sea-level allowance. The SLA shall be:
- (a) +0.3 m minimum for every element;
- (b) greater than 0.3 m where the State, a SADA or the Authority adopts a higher projection for the planning area; and
- (c) assessed for the design life of the element. For elements with a design life of more than 50 years, the designer shall report the effect of a sea-level rise of twice the SLA as a sensitivity run.
Figure 5.2 — Tidal outfall: flap gate, property non-return valve, and the design tailwater levels (MHWS + 0.3 m for the minor system; HAT + surge + 0.3 m for the major system), with a seasonal sand bar at the mouth. Schematic, not to scale. Original drawing for this Manual, adapted from the tidal tailwater table in MoHUA/CPHEEO Manual on Storm Water Drainage Systems (2019), Part A, Table 6.2.
Commentary. CPHEEO (2019) Table 6.2 sets the design tailwater for coastal outfalls as:
- MHWN to MHWS for a minor storm (more frequent than 1 in 5 years);
- MHWS to HAT for a major storm; and
- "Effect of climate change: additional 0.3 m".
CPHEEO also says the joint probability of storm, tide and surge "should" be considered, with the state maritime board consulted. This Manual takes the upper end of each CPHEEO range, adds surge for the major system, and makes the joint case explicit (Clause 2.12). CPHEEO does not require surge to be added; this Manual adds it because the surge records of the coastal States showed why it is needed there; Himachal Pradesh has no coast, and the surge term does not arise in the State, which a monsoon system reaches only as rainfall, often meeting a western disturbance over the hills, as in July 2023 (Chapter 2).
Indian tide tables have been published by the Survey of India since the nineteenth century (Survey of India, Tidal Predictions). Current Indian tidal predictions also appear in the NHO's tide tables. One port document describes the current edition as covering 95 Indian ports, based on NHO observations and on data from civil ports, NIO and INCOIS (Adani Ports, Dahej tide table 2025, citing NHO INP-12). INCOIS runs coastal tide gauges and issues storm-surge and swell-surge warnings. None of these is used for design in Himachal Pradesh, which has no coast, and Annex 5A is not prepared for the State (Clause 5.1.4).
5.8 Riverine backwater
5.8.1 Where it applies. Outfalls to rivers and canals whose water level in a storm can exceed the outfall invert shall be designed with riverine backwater. This includes:
- the Yamuna at Paonta Sahib past the Paonta gauge, with the Bata at Ganguwala and the khads and nallahs of the Paonta valley that end in them, and the Giri at Yaswant Nagar, Dadahu and the Jatton barrage (Clauses 5.8.3 and 5.8.5(a) and (c));
- the Sutlej at Rampur Bushahr below the Nathpa Jhakri and Karcham Wangtoo projects, at Nathpa and at Pandoa below Shimla, with the nallahs of the north face of Shimla that run to it, and the Baspa at Sangla (Clauses 5.8.3 and 5.8.5(a) and (c));
- the Beas at Manali, Kullu and Bhuntar, below the Larji and Pandoh dams, and at Mandi at its confluence with the Suketi, and below the Pong dam in the Mand area of Indora, with the side khads of the Kullu valley and the Parbati (Clauses 5.8.3 and 5.8.5(a) and (c));
- the Swan at Una and Ghaluwal, channelised with its tributaries from Daulatpur to the Gagret bridge (Clause 5.8.5(a) and (b));
- the Ravi at Chamba, with the Chamera reservoir (Clauses 5.8.3 and 5.8.5(a) and (c));
- the Pabbar and the Tons at Meenus, and the Meenus Khad (Clause 5.8.5(a));
- the khads and nallahs of the hill and valley towns, among them the thirteen major nallahs of Shimla, which drain north to the Sutlej and south to the Ashwani Khad and the Giri; the Suketi and its khads at Mandi; the Manjhi, Gaj, Banner and Neugal khads and the Bhagsunag nala below Dharamshala, Kangra and Palampur; the Sirsa, the Balad and the nallahs of Baddi–Barotiwala–Nalagarh; the tributary khads of the Swan at Una; the side khads of the Beas in the Kullu valley; and the choes of the Siwalik hills (Clause 5.8.5(b));
- Gobind Sagar (the Bhakra reservoir) at Bilaspur, the Pong reservoir (Maharana Pratap Sagar) at Dehra and the Pong shore, and the Pandoh, Larji, Kol, Nathpa Jhakri, Karcham Wangtoo and Chamera reservoirs and the pond of the Jatton barrage (Clause 5.8.5(c));
- Rewalsar, Khajjiar, Renuka and the other tals (Clause 5.8.5(d));
- any kuhl in Schedule I or II of the Himachal Pradesh Minor Canals Act 1976, the Beas–Sutlej Link of BBMB, any canal of the Jal Shakti Vibhag, and any drain or channel of another body that receives storm water (Clause 5.8.5(e)); and
- elsewhere: any river or Jal Shakti Vibhag channel listed in Annex 5B.
5.8.2 River levels. River water levels shall be taken from:
- (a) Jal Shakti Vibhag design flood levels or recorded highest flood levels for the reach, where published; or
- (b) a hydraulic model (HEC-RAS or equivalent) of the river reach. The model shall use:
- the river design flood from a hydrograph method (Chapter 3), with continuous simulation where Chapter 3 requires it;
- the tidal boundary of Clause 5.7 at the mouth; and
- the sand-bar condition of Clause 5.13.
5.8.3 Reservoir and tank releases. Where a reservoir or tank upstream can release to the river (for example on the Sutlej, the Karcham Wangtoo and Nathpa Jhakri projects above Rampur, the Kol dam above Bilaspur and the Bhakra dam below it; on the Beas and its tributaries, the Malana and Parbati projects in the Kullu valley, the Larji and Pandoh dams above Mandi and the Pong dam above Indora; the Chamera dam on the Ravi; and the Jatton barrage on the Giri), the river level shall include the release given by the reservoir's operating rule for the storm being checked. Where there is no published rule, it shall include the largest recorded release.
5.8.4 Coincidence of site storm and river flood. Unless a joint-probability study is accepted by the Authority, the more severe of the following governs:
- (a) the site design storm (AEP as required), with the river at its 10% AEP (10-yr) level; and
- (b) the site 10% AEP storm, with the river at its design-AEP level (1% AEP for the major system).
The two storms in each pair shall have the same duration and timing where they are generated by the same rainfall event.
5.8.5 River-locked outfalls, khads and nallahs, reservoirs and dam releases, tals, kuhls, canals and the drains of other bodies, and Jal Shakti Vibhag consent.
- (a) River-locked outfalls. For an outfall to a river directly, through a gate in a bank, a flood wall or an embankment, or through a pumping station, or into a drain that itself discharges in one of those ways, the designer shall identify the body that operates each gate and pumping station, and obtain the sill of each gate, the crest of the bank, wall or embankment, the installed pumping capacity and the operating levels, including the river level at which each gate is closed. Every level shall state its datum and its connection to the gauge datum of the nearest CWC gauge, or of the BBMB or other gauge used, with its operator named.
- Design river level. The river level of Clause 5.8.2 at the outfall shall be, for the major-system cases (Clause 5.8.4(b)), the 1% AEP river level at the outfall, from a hydraulic model under Clause 5.8.2(b), with the dam releases of item (c). Himachal Pradesh has no floodplain zoning law and no published flood level for any reach of any river (the post-disaster needs assessment of 2023 calls for river-boundary mapping and floodplain management guidelines), so no level is available from a floodplain study [TBC]. The level shall in no case be less than the highest recorded level at the nearest CWC gauge on the same river, transferred to the outfall, nor less than the 10% AEP level of this item. The highest levels found during research (Table 5B.1), all from SANDRP's copies of CWC tables and posts, with no datum stated and none read in a CWC site sheet [TBC], are: the Yamuna at Paonta 384.6 m (5 September 1995); the Bata at Ganguwala 373.52 m (22 July 2023, above the 372.6 m of 18 August 2019); the Sutlej at Rampur 933 m (26 June 2005, the flood from the burst of the landslide lake on the Parechu in Tibet), against which a level of 924.5 m for 2023 has also been quoted: the two are in conflict, and 933 m governs until CWC confirms the record [TBC]; the Sutlej at Nathpa 1,451 m (26 June 2005); the Swan at Ghaluwal 367 m, dated 3 June 2017, a date to be confirmed with CWC [TBC]; the Giri at Yaswant Nagar 902.9 m (5 September 1995) and at Dadahu 629.02 m (18 August 2019); the Tons (Pabbar) at Meenus 730.35 m and the Meenus Khad 735.3 m (both 10 July 2023); the Ashni at Gaura 918.2 m (18 August 2019); the Uhl at Barot 1,832.68 m (30 August 2016; listed by CWC as the Beas); the Baspa at Sangla 2,515.2 m (31 July 2017); the Bhaga at Tandi, below Keylong, 2,855.31 m (13 August 2009); and the Ropa Khad at Ropa 3,050.85 m and the Spiti at Gulling 3,580.34 m (9 and 10 July 2023). At Pandoa, on the Sutlej below Shimla, the CWC list of 2022 gives 740.6 m (3 August 2005) and SANDRP's account of July 2023 gives 689.6 m (1 June 2022) and calls the first "incorrect"; neither shall be used until CWC confirms the level in its site sheet, the reach is treated as a reach with no gauge level under the next item, and the peak of 688.78 m recorded there on 10 July 2023 is a floor (set by this Manual) [TBC]. Where a later flood has exceeded the listed level, the later level governs; five of these levels were set in July 2023. The recorded level shall be transferred along the river with the water-surface slope of the flood that set it, from the CWC gauge records, or from the model. Until either is available, the recorded level of the nearest gauge upstream applies unchanged at the outfall, except that where the outfall lies between two gauges on the same river, with no tributary joining between them, the level may be interpolated linearly by river distance between the highest recorded levels of the two gauges; and on a mountain river, whose bed falls several metres in a kilometre, a profile of the flood marks of the same flood, surveyed between the gauge and the outfall and tied to a Survey of India benchmark, may be used in place of the unchanged level (set by this Manual).
- Rivers and reaches with no gauge level. No CWC site with a published level exists on the Beas at Manali, Kullu, Bhuntar, Mandi or Pandoh, on the Sutlej at Bilaspur, on the Ravi at Chamba, on the Sirsa at Nalagarh, on the Pabbar at Rohru or on the Markanda at Kala Amb; CWC's map of July 2025 shows stations of BBMB named Manali, Bhuntar Beas, Mandi and Pandoh Dam, all marked inactive, with no level found (as copied by SANDRP) [TBC]. On such a reach, and for an outfall upstream of every gauge on its reach, the river level shall be the higher of the level from a model under Clause 5.8.2(b) and the highest flood level surveyed at the outfall from flood marks, including those of July and August 2023, July 2024 and the monsoon of 2025, and from the records of the Jal Shakti Vibhag, the local body or the Deputy Commissioner, with its source stated. Where a level is known only as a gauge reading, the designer shall tie the gauge zero to the project datum and a Survey of India benchmark by levelling. No outfall shall be designed on such a reach without one of these levels (set by this Manual).
- 10% AEP level. For the cases with the river at its 10% AEP level (Clause 5.8.4(a)), the level shall be taken from the same model or a frequency analysis of the gauge record, and not less than the danger level at the nearest CWC gauge, transferred in the same way. The only CWC site in the State with a warning and a danger level is the Yamuna at Paonta: danger level 384.5 m, warning level 383.5 m, against a highest recorded level of 384.6 m, only 0.1 m above the danger level (SANDRP's copy of the CWC list of 2022) [TBC]. Every other CWC site in the State is a level-monitoring site with no danger level; there, the 10% AEP case shall use the design river level of this item until a frequency analysis is accepted (all set by this Manual). The datum of every level is to be confirmed for each gauge [TBC].
- Tailwater. The tailwater at the outfall shall be the higher of that river level beyond the gate, bank, wall or embankment, and the maximum level in the drain behind it, computed by routing the drain as a closed storage for as long as the river stands above the level behind it, with the inflow of the whole catchment that drains to it, its storage as surveyed in its present condition, net of silt, boulders, debris, encroachment, solid waste and weed, and an outflow of no more than the pumping capacity that the operator confirms in writing is available in a storm, and in no case more than the installed capacity of the permanent pumps less the largest pump (set by this Manual), with gravity discharge through the gate only while the river is lower than the level behind it. Pumps shall deliver against the design river level of this item, and every pump, panel and control shall remain operable with the river at that level (Clause 5.12.5).
- River lock. Portable dewatering pumps brought in for an event, and capacity that has been sanctioned or proposed but not commissioned, shall not be counted. The outfall-closed check of Clause 5.10 applies with a single lock that lasts for as long as the river stays above the outfall invert, or above the level at which its gate is closed if that is lower, taken from the river model or from the stage record of the nearest CWC gauge in the flood that set the highest recorded level or in a comparable flood, with the releases of item (c), and not less than 72 hours, or, on a river below a dam or barrage, the time for which the largest recorded release of the dams and barrages above stayed above the flow at which the outfall is closed, from the operator's records, if that is longer (set by this Manual). The lock covers the whole of the 48- and 72-hour storms of Clause 5.10.2, so that storage and pumping handle the full storm volume (Clause 5.9.4) and the drawdown of Clause 5.10.5 is met by pumping until the lock ends. An outfall to a reservoir, or to the pond of the Jatton barrage on the Giri, whose invert is below the level of item (c), is closed for the whole storm. A shorter lock may be used only where the outfall invert is above the 1% AEP river level of this item, or where an analysis of the stage record of a CWC gauge under Clause 5.10.6, including the releases of the dams and barrages above, shows it and the Authority approves it.
- Gate failure and breach. Floor levels and pumped outfalls behind a gate, flood wall or embankment, such as the embankments of the Swan, shall also be checked for the failure of the gate and for a breach of the wall or embankment, with the land and drains behind it filled to the river level beyond it. Below a dam or barrage they shall also be checked for the release that results from a gate failing open.
- (b) Khads, nallahs and other ungauged hill streams. For an outfall to a khad (खड्ड; a seasonal hill torrent or ravine stream), a nallah (नाला; a natural drainage channel), a choe or another seasonal hill stream, such as the thirteen major nallahs of Shimla and the Ashwani Khad below them, the Suketi and its khads at Mandi, the Manjhi, Gaj, Banner and Neugal khads and the Bhagsunag nala below Dharamshala, Kangra and Palampur, the Sirsa, the Balad and the Sandholi and other nallahs of Baddi–Barotiwala–Nalagarh, the tributary khads of the Swan at Una, the side khads of the Beas in the Kullu valley, and the khads that come down to Rampur, Chamba, Solan and Nahan, or into a drain that ends in one:
- No gauge. None of these streams has a CWC gauge at a town, except the Bata at Ganguwala below Paonta Sahib and the Ashni at Gaura, and none has a published flood level [TBC]. They are seasonal, steep and boulder-laden: the gauged khads of the State are the steepest in CWC's zone 7, the Neogal falling 84.04 m and the Banu 69.21 m in a kilometre (CWC, 1994); they rise within an hour of a burst of rain, carry gravel, boulders, timber and debris, and raise or scour their beds in a single flood.
- Design level. The tailwater for the major-system and storage cases shall be the highest of: (i) the 1% AEP level at the outfall from a study of the stream, made with a hydrograph method of Chapter 3 for the whole catchment above the outfall, with the rainfall of its sub-area in Annex 2A, the AMC of Clause 3.8.4 and the bulking factor of Clause 6.3.6(b) on the peak flow, and routed through a hydraulic model (Clause 5.8.2(b)) of the channel as surveyed, with the crossings downstream blocked as Clause 6.3.6(c) requires; (ii) the level at the outfall of any flood study of the stream made by or for the Jal Shakti Vibhag, such as the hydraulic modelling for the embankments of the Swan (NITI Aayog, 2020), where it gives one [TBC]; and (iii) the highest flood level surveyed at the outfall from flood marks, such as debris lines, silt and scour marks and the accounts of residents, of the floods of July and August 2023, July 2024 and the monsoon of 2025 or a later flood, and from the records of the Jal Shakti Vibhag, the local body or the Deputy Commissioner, with its source stated. No outfall to such a stream shall be designed without items (i) and (iii) (set by this Manual).
- Bed level, scour and aggradation. The designer shall survey the bed of the stream at the outfall and for at least 100 m upstream and downstream, and state the range within which the bed has moved, from past surveys, cross-sections, exposed foundations and pipes, and the records of the Jal Shakti Vibhag and the local body. The outfall invert, and the seat of any flap gate on it, shall stand at least 0.5 m above the highest bed level found in that range within 50 m downstream of the outfall, and the foundation of the outfall structure and its apron shall be taken below the scour depth computed under Chapter 9 (Clause 9.6) for the 1% AEP flow with the bulking factor (set by this Manual).
- Siting. An outfall shall be built into the bank and shall not project into the bed or the active channel, taken for this Manual as the land flooded once in 5 years (set by this Manual). It shall discharge in the direction of the stream's flow, with the bank protection that Chapter 9 requires, and no pipe, interceptor or chamber of the drainage system shall be laid along the bed of the stream. No muck, spoil or excavated material from the works shall be placed in the stream or where a storm can carry it into one (Clause 6.3.6(g)).
- Closed outfall. Where the outfall invert is below the design level of this item, the outfall-closed check of Clause 5.10 applies with a single lock that lasts for as long as the level of the stream, computed under item (i) for the coincident cases of Clause 5.8.4, stays above the invert, and, where no hydrograph of the stream has been computed, for the whole storm (Clause 5.9.4) (set by this Manual).
- Interceptors and water sources. An interception and diversion structure on a khad or nallah or its drains (Clause 8.9) shall not raise the design level of this item or reduce the capacity of the drain; it shall stand above that level or be designed to be overtopped without damage. Where the khad is a source of drinking water, such as the Ashwani Khad below Shimla, Clause 8.9 also applies.
- (c) Reservoirs and dam releases. For an outfall to a reservoir or barrage pond, directly or through a drain, khad or nallah that ends in it, such as Gobind Sagar, the reservoir of the Bhakra dam on the Sutlej, at Bilaspur; the Pong reservoir on the Beas (Maharana Pratap Sagar) at Dehra and along its shore; the Pandoh and Larji reservoirs on the Beas; the Kol, Nathpa Jhakri and Karcham Wangtoo reservoirs on the Sutlej; the Chamera reservoir on the Ravi; and the pond of the Jatton barrage on the Giri:
- Consent. Storm water shall not be discharged to a reservoir or barrage pond without the written consent of its custodian: BBMB for Bhakra (Gobind Sagar), Pong and Pandoh; NTPC for Kol; SJVN for Nathpa Jhakri; NHPC for Chamera; HPSEBL for Larji; and, for Karcham Wangtoo and the Jatton barrage, the body that operates them, which was not confirmed during research [TBC]. The Pong reservoir is a Ramsar site (Pong Dam Lake, 15,662 ha), where the permission of the State Wetlands Authority and the Forest Department is also required (Chapter 7). An outfall that carries dry-weather flow is dealt with under Clause 8.9.
- Design level. The tailwater for the major-system and storage cases shall be the waterbody's maximum water level (MWL) as its custodian publishes it, or, where only the full reservoir level (FRL) or maximum pond level is published, FRL plus the surcharge in its design flood, computed from the rating of its spillway and gates with the gates operated only as the custodian's written rule provides. Where neither the MWL nor the surcharge has been published, or where the published MWL is not above the FRL, the tailwater is FRL + 0.5 m (set by this Manual) [TBC]. For a barrage pond, the tailwater is the higher of that level and the river level of item (a) at the barrage with its gates as operated. In every case it shall be not less than the highest level recorded at the waterbody. The minor-system tailwater is the FRL or maximum pond level, or the level at which the custodian's rule opens the gates if that is higher. The project's discharge shall be included in the level (Clauses 5.3.2 and 5.12.3).
- Levels in feet. BBMB publishes the levels of Bhakra and Pong in feet. Every level in feet shall be converted to metres at 1 ft = 0.3048 m exactly, and the conversion and the datum stated on Form 5-1. No source found states the datum of the feet; this Manual takes them as feet above mean sea level, to be confirmed with BBMB before final design [TBC].
- The named reservoirs. Until the custodian confirms the MWL or the design-flood level and its datum, the tailwaters are (set by this Manual) [TBC]: Gobind Sagar (Bhakra), FRL 1,680 ft (512.06 m) and an earlier technical limit of 1,690 ft (515.11 m) reported by BBMB (as copied by SANDRP), with no MWL found and a highest level found of 1,679 ft (511.76 m) on 4 September 2025 (as reported): 515.11 m, the higher of FRL + 0.5 m (512.56 m) and the reported technical limit; and Pong, FRL 1,390 ft (423.67 m), whose maximum level is quoted as 1,400 ft (426.72 m; SANDRP, 2025), 1,410 ft (429.77 m; press) and, as a "technical" limit, 1,421 ft (433.12 m; SANDRP): the three are in conflict, and until BBMB confirms the MWL the tailwater is 433.12 m, the highest of them; the highest levels found are 1,399.65 ft (426.61 m) on 15 August 2023 and 1,394.71 ft (425.11 m) on 5 September 2025 (as reported). For Kol, a reservoir level of 642 m, for Chamera, 763 m, and for Karcham Wangtoo, 1,810 m, are reported, none confirmed as the FRL (as reported); until the operator confirms it, the tailwater is that level + 0.5 m: 642.5 m, 763.5 m and 1,810.5 m [TBC]. No level on a stated datum was found for Pandoh, Larji, Nathpa Jhakri or the Jatton barrage [TBC]; no outfall to any of them shall be designed without the custodian's FRL or pond level and spillway rating in writing, or, until the custodian gives them, the higher of a survey of the crest tied to a Survey of India benchmark and the river level of item (a) (set by this Manual).
- Closed outfall. Where the outfall invert is below the design level of this item, the outfall shall be treated as closed for the whole storm (Clause 5.9.4), with storage and pumping handling the full storm volume, unless the custodian's stage record shows the waterbody below the invert at the start of comparable storms and the Authority accepts it. Every reservoir and barrage pond starts every design storm at its FRL or maximum pond level (Clause 7.7.3), and no lowering of a reservoir or pond before a storm and no early or additional gate opening shall be assumed unless the custodian's written operating rule and records show it. The drawdown zone of a reservoir, such as the land between 1,280 ft and 1,390 ft at Pong, is part of the reservoir: no outfall structure, pumping station or storage shall be built in it without the custodian's consent.
- Rivers below dams and barrages. For an outfall to a river below a dam or barrage, such as the Beas below Larji and Pandoh, at Mandi, and below Pong in the Mand area of Indora, the Sutlej below Karcham Wangtoo and Nathpa Jhakri at Rampur and below Kol, the Ravi below Chamera, and the Giri below the Jatton barrage, in addition to the cases of Clause 5.8.4, the site design storm (each AEP required) shall be run with the river at the level that results from the largest recorded release of the dams and barrages above, routed to the outfall, with the flow of the catchment below them as it occurred in the same event, and with the release placed before, during and after the site storm (set by this Manual), until the operator publishes an operating rule that bounds the release [TBC]. The largest recorded releases found are about 1.40 to 1.50 lakh cusec (about 3,960 to 4,250 m³/s) from Pong from 15 August 2023, above which, its chief engineer said, the dam has never released (as reported); 85,000 cusec (about 2,410 m³/s) from Bhakra on 4–5 September 2025 (as reported); and nearly 44,000 cusec (about 1,250 m³/s) from Pandoh, with all five gates open, on 30 June 2025, after a release from Larji (as reported). The largest recorded release of each dam and barrage and its duration shall be obtained from its operator and stated [TBC]. A release, or a release rule, alone shall not be taken to bound the river level: the level shall also be checked for the largest recorded event at the nearest gauge, with the local inflows as they occurred. No attenuation by the storage of Pong, Bhakra or any other reservoir shall be credited to the river below unless the operator's written rule commits that storage to flood control for the event; and no dam or barrage gate shall be assumed to open earlier or wider than the operator's records show. The river level shall not be reduced on the ground that the flood comes from rain that falls outside the town, from snow or glacier melt, or from the burst of a glacial or landslide lake, inside the State or in Tibet, as on the Parechu in 2005, or that the site storm is small.
- (d) Tals. For an outfall to Rewalsar, Khajjiar, Renuka or another tal (ताल; a pond, lake or tank), directly or through a drain or stream that ends in it:
- Consent. Storm water shall not be discharged to a tal without the written consent of its custodian. The custodian of each tal was not confirmed during research [TBC]: Renuka is a Ramsar site (20 ha) within a wildlife sanctuary, and Rewalsar and Khajjiar are wetlands of national importance whose action plans are approved by the State Level Steering Committee on Wetlands; until the State names a custodian, the consent of the State Wetlands Authority, the Forest Department and the local body is required (Chapter 7).
- Design level. No level on a stated datum, and no outlet or overflow level, was found for Rewalsar, Khajjiar, Renuka or any other tal [TBC]. Until the custodian gives one, the tailwater is the level at which the tal spills, from its outlet or overflow crest surveyed and tied to a Survey of India benchmark, plus the head over that crest needed to pass the 1% AEP inflow, and not less than the highest level recorded at the tal; the tal starts every design storm at its spill level, and an outfall below the tailwater is closed for the whole storm (Clause 5.9.4) (set by this Manual). Khajjiar, whose water body is fed by streamlets carrying rain and snow-melt water from a catchment of about 6 km², and Renuka, fed by 21 seasonal streams, shall be checked for the snow-melt and the inflow of their whole catchments.
- Drains to the tal. Every drain that discharges to a tal shall pass a debris trap and a sediment trap (Clause 6.3.6(a) and Chapter 8) before it reaches the tal, sized for the bulked flow of Clause 6.3.6(b). No runoff shall be infiltrated on the slopes of the tal's catchment except as Clause 4.11 allows, and no drain that carries sewage shall discharge to a tal (Clause 8.9): at Rewalsar the sewage drains built around the lake are reported to leak at many points and to cause eutrophication (State Wetlands Authority).
- (e) Kuhls, canals and the drains of other bodies. Storm water shall not be discharged to a kuhl (कूहल; a gravity irrigation channel) in Schedule I or II of the Himachal Pradesh Minor Canals Act 1976 without the written consent of the Jal Shakti Vibhag and, for a private kuhl in Schedule II, of the Collector after notice to its beneficiaries, who maintain it (ss.46–48 of the Act) (set by this Manual); nor to the Beas–Sutlej Link without the consent of BBMB, or to any other canal without the consent of its operator; nor to a drain of another body, such as a drain of a Municipal Corporation, a Nagar Parishad or Nagar Panchayat, HIMUDA, BBNDA, HPSIDC, a Smart City company, PWD or NHAI, without the written consent of that body. Obstructing a kuhl, or fouling its water, is an offence under s.65 of the Act, and the beneficiaries are required to provide works for the passage of a kuhl across or under a road or a drain (s.46). A drain that crosses a kuhl or canal shall cross by a cross-drainage work built with the consent of the kuhl's or canal's manager, and not discharge into it. Where consent is given:
- the discharge shall not exceed the rate the consent allows;
- the tailwater is the higher of the channel's design water level as its owner states it in writing and its level in the coincident case of Clause 5.8.4, computed from all the storm water it receives, including the drains of other bodies and the runoff that the kuhl intercepts from the slope above it, and with its downstream boundary at the river, khad, reservoir or tal level of items (a) to (d); until a design water level is published for a channel, the computed level governs [TBC];
- the channel shall be taken in its present condition, net of silt, boulders, debris, encroachment, solid waste, weed and obstruction by crossing services and culverts, and with its narrowest section as surveyed, and with any weir that intercepts its dry-weather flow (Clause 8.9) at its crest level; a widening, lining, channelisation, rejuvenation or diversion that has been proposed but not completed, such as the channelisation of the Beas proposed in 2021 or the rejuvenation of Shimla's major nallahs in the draft city development plan, shall not be counted, and a channel designed for a stated return period shall not be taken to carry more than its surveyed section carries; and
- the outfall shall have a flap gate (Clause 5.11) where the design water level or the computed level is above the outfall invert.
- (f) Jal Shakti Vibhag consent; plan, wetland and court lines. No outfall structure, gate, pumping station or drain shall be built in the bed, bank or floodplain of a river, khad or nallah, in a flood-protection work of the Jal Shakti Vibhag, such as the embankments of the Swan, or in a kuhl, without the consent of the Jal Shakti Vibhag, or of BBMB or the operator of a dam, reservoir or barrage for their structures; the procedure for that consent was not found during research [TBC]. The State has no floodplain zoning law and no notified flood line (Chapter 7). The designer shall also check the outfall against the lines that the building rules, the development plans, the wetland rules and the courts have set, as they stand at the time of design (Chapter 7): the 3.00 m from a nullah and 5.00 m from a khud within which Appendix-1, cl. 16 of the TCP Rules 2014 does not allow construction where no Interim Development Plan or Development Plan has been prepared, a rule that names no line from which the distances are measured; the distance from the highest flood level along rivers, khuds and nullahs "as delineated in the Interim Development Plans / Development Plans", with no construction "in parcel of land prone to floods" in other areas (Appendices 3 and 7); the flood plains and "areas adjacent to major drainage lines" that a development plan treats as non-developable, as the Chopal Planning Area Development Plan 2041 does; the Shimla Development Plan 2041, published on 20 June 2023 according to the Supreme Court (notified on 23 June 2023, as reported), whose storm-water chapter and lines were not read [TBC]; Pong Dam Lake, Renuka and Chandertal, Ramsar sites, and Rewalsar and Khajjiar; the orders of the High Court that no muck be dumped "in Govind Sagar Lake and its feeding khuds/nallahas" (22 May 2023) and that the muck already dumped in the lake, its tributaries and on public land be cleared (Madan Lal, CWPIL 31/2023, 31 May 2024), and on the dumping of muck by the contractors of the Kiratpur–Nerchowk four-lane highway near water bodies (Fourlane Visthapit and Prabhavit Samiti, CWP 5243/2022, 26 June 2023); and the power of the State under s.43 of the Minor Canals Act to regulate the flow in any "line of natural drainage" and to prohibit or remove an obstruction of it. The distances of 5 m from drains and 7 m from rivers and ravines for buildings, of 150 m from rivers, nullahs and other water bodies for government buildings, and the ban on building along the banks of rivers and streams in the model bye-laws for rural construction, all announced in 2025, are reported in the press only; no gazetted text of any of them was found during research, and they are not applied by this Manual until it is [TBC]. Whether a drain outfall is permitted within each line is to be confirmed with the authority concerned before design [TBC].
No pump, gate, sluice, barrage or dam operation that helps drainage, such as pumping a drain down before a storm, lowering a reservoir, barrage pond or tal before a storm, closing a gate late or opening dam or barrage gates early, shall be assumed unless the operator's written records show it. Where the outfall invert is below the tailwater of this clause, the outfall shall have its own flap gate (Clause 5.11) and, where the outfall-closed check requires it, pumping (Clause 5.12), with the pumped volume included in the routing of the drain, the waterbody or the river (Clause 5.12.3). Pumping shall not be used to move water into a tal, a reservoir, a kuhl or another catchment without the consent of its custodian, or onto a slope.
Commentary. In large continental river basins, a site storm and a river flood are usually treated as roughly independent. That is the basis of tables of coincident frequencies such as FHWA HEC-22 Table 7.3. Himachal Pradesh's rivers break that assumption, because their catchments are small and steep and the storms that fill them fall on the towns at the same time. On 9–11 July 2023, when an active monsoon met a western disturbance, Pachhad recorded 220.3 mm and Nahan 250.0 mm in a day (IMD), the Tons at Meenus and the Meenus Khad set new highest levels on 10 July, and the Ropa Khad and the Spiti set theirs on 9 and 10 July; and on 14 August 2023, when Kangra Aero recorded 273.4 mm and Dharamshala 250.2 mm in a day (IMD), the Pong reservoir took what was reported as the highest inflow since it began to operate in 1974 (IMD; CWC data, as copied by SANDRP; as reported). The two cannot be treated as independent, and a local storm can fall before, during or after the river peak. Clause 5.8.4 therefore pairs a design event on one side with a 10-yr event on the other, in the same way as Clause 2.12(b). This pairing has no direct precedent. It is more severe than an independence assumption would give.
Clause 5.8.3 reflects the dams above and beside the State's towns. BBMB publishes the levels of its two storage reservoirs in feet. Gobind Sagar, behind the Bhakra dam on the Sutlej, has a full reservoir level of 1,680 ft (512.06 m), and BBMB is reported to have given its earlier technical limit as 1,690 ft (515.11 m); it stood at 1,675.71 ft on 14 August 2023 and at 1,679 ft on 4 September 2025, when it released up to 85,000 cusec (as reported). The Pong reservoir on the Beas has a full level of 1,390 ft (423.67 m), at which its water spreads over about 220 km², against about 125 km² at its minimum level of 1,280 ft (State Wetlands Authority); its maximum level is quoted as 1,400 ft, 1,410 ft and, as a technical limit, 1,421 ft, a conflict that only BBMB can resolve [TBC]. In August 2023 Pong took an inflow reported as 7.3 lakh cusec on 14 August by one account and 5.13 lakh cusec to the morning of that day by another, released about 18,000 cusec until 14 August and then 1.40 to 1.50 lakh cusec, and rose to 1,399.65 ft (as reported); SANDRP has alleged that it was filled too early and released too late, an allegation and not a finding. In 2025 it rose to 1,394.71 ft on 5 September after releasing more than one lakh cusec from 29 August (as reported). The Pandoh dam, which diverts about 9,000 cusec of the Beas to the Sutlej through the Beas–Sutlej Link, opened all five gates and released nearly 44,000 cusec on 30 June 2025, after a release from Larji upstream, and people at Pandoh blamed its releases for the flooding there in July 2023 (as reported); 14 students died in a release from Larji in 2014 (as reported). The spillway of the Kol dam is designed for 16,500 m³/s and that of Nathpa Jhakri for 5,660 m³/s (as reported). No operating rule or release record for any of these dams, no full or maximum level for Pandoh or Larji, and no hourly stage record for any gauge in the State was obtained during research [TBC]; the Chief Secretary is reported to have listed dams, among them Pandoh, that do not meet dam-safety norms, a list that was not obtained (as reported) [TBC]. Until these are available, the largest recorded release applies, with the flow of the catchment below the dam as it occurred in the same event (Clause 5.8.5(c)). The river levels used in this Manual come from SANDRP's copies of CWC data, because the CWC websites refused access during research; their datum and gauge zero are to be confirmed with CWC [TBC].
Clause 5.8.5 is set by this Manual. In Himachal Pradesh the tailwater at a town outfall is set not by the tide but by a river held high by a monsoon spell or by the releases of a dam, by a khad or nallah whose level no one has recorded and whose bed moves, by a reservoir at its full level, by a tal, or by a kuhl or canal, and no document found during research gives a design level for any of them. No design standard for any town drain in the State was found: the expert committee that reported to the National Green Tribunal on Shimla in 2017 found that the city's drains were "not able to carry the peak flow" and that their catchments were "improperly selected", but set no design level (Yogindra Mohan Sengupta, judgment of 16 November 2017, para 53; the judgment was set aside by the Supreme Court on 11 January 2024, 2024 INSC 30, and its committee's findings are cited here as expert evidence only). The drainage sections of the State's municipal Acts were not read [TBC]. The State has no floodplain zoning law, and the post-disaster needs assessment of the 2023 monsoon found that "the lack of well-defined river boundaries in floodplains is a prominent issue in Himachal Pradesh" and called for "comprehensive river boundary mapping and the establishment of floodplain management guidelines" (Chapter 7).
The first is the river. Item (a) follows the interim river rule of Uttarakhand, the first mountain State in this series: the design level is the 1% AEP level, and never below the highest level recorded at the nearest CWC gauge. Only one CWC site in Himachal Pradesh, the Yamuna at Paonta, has a warning and a danger level; the other 29 sites in the State, by SANDRP's count of the CWC list of 2022, record levels only, and the Beas, the river of Manali, Kullu and Mandi, has no CWC site with a published level at any town. On the Beas, the Ravi and the Sirsa the design level must therefore come from a model and from flood marks, and item (a) allows a surveyed profile of flood marks in place of the unchanged gauge level on a mountain river, because the bed of such a river falls several metres in a kilometre and a level carried unchanged from a gauge upstream would be several metres too high, or, from a gauge downstream, too low. At Rampur the record of 933 m was set by the Parechu flood of 2005, which came from a landslide lake outside the State and not from rain on the town; item (a) keeps it, because the next such flood will not ask where the town's storm fell, and states the conflicting level of 924.5 m quoted for 2023 [TBC]. At Pandoa the conflict is too large to resolve by taking the higher: the CWC list gives 740.6 m and SANDRP, which reads the same gauge, says that figure "is incorrect" and gives 689.6 m, so item (a) treats Pandoa as ungauged until CWC confirms its level. The danger level is used as the floor of the 10% AEP level at Paonta because the river's highest recorded level there stands only 0.1 m above it. The rivers of the hills rise and fall within hours, which might seem to justify a shorter lock than in the plains. Item (a) keeps 72 hours for three reasons: no hourly stage record for any gauge in the State was obtained during research [TBC]; the storms that raise the rivers last for days, as on 7–11 July 2023, when the State received 223 mm in four days (post-disaster needs assessment, 2023, citing IMD), and the dams pass a flood for days after it, as Pong did when it released 1.40 to 1.50 lakh cusec from 15 August 2023 and more than one lakh cusec from 29 August 2025 (as reported); and an outfall into a reservoir or barrage pond stays closed for as long as the pond is held, which items (a) and (c) treat as the whole storm. The lock covers the whole of the longest design storm of Clause 2.5.2, so that the site does not rely on the river falling during the storm. A designer who has the stage record of a CWC gauge can justify a shorter lock under Clause 5.10.6, and the mountain rivers are where that analysis is most likely to succeed. Item (a) counts only the permanent pumps less the largest one, for the same reason that Clause 5.12.2(b) requires a standby pump.
The second is the khad and the nallah. Shimla's nallahs, the Suketi at Mandi, the khads below the Dhauladhar and the Sirsa and Balad at Baddi–Nalagarh are ungauged, and no flood study of any of them was found. Item (b) therefore requires the designer to make the study, with the bulking factor of Clause 6.3.6(b), and to survey the flood marks, and takes the higher. A khad's bed is not fixed: it rises with the boulders of one flood and is scoured by the next, and the 2023 monsoon damaged 139.766 km of the State's 610.634 km of sewer pipelines (post-disaster needs assessment, 2023). An outfall set at the present bed level is buried by the first and undermined by the second, so item (b) sets the invert at least 0.5 m above the highest bed level surveyed downstream, a margin set by this Manual for the aggradation that a boulder bed can show in a single flood, and takes the foundation below the computed scour. It keeps outfalls out of the active channel and keeps pipes out of the bed, and forbids the works from leaving muck in the stream, because the High Court has had to bar the dumping of muck in Gobind Sagar and the khads that feed it, and to order the muck already dumped cleared (Madan Lal, CWPIL 31/2023).
The third is the reservoir. A reservoir at its full level does not fall for the rest of the season but passes its inflow over its spillway, and its level rises above FRL by whatever head the flood needs. Item (c) therefore takes the MWL, or FRL plus the design-flood surcharge, and treats an outfall below it as closed for the whole storm, which is what Clause 5.9.4 already requires when the tailwater stays above the outfall. BBMB's levels are in feet; item (c) converts them at the exact factor of 0.3048 m and requires the datum to be confirmed. For Pong the maximum level is quoted three ways, 1,400 ft, 1,410 ft and 1,421 ft, and item (c) takes the highest until BBMB confirms the MWL, because a tailwater set too low floods the town while one set too high only costs storage. For Gobind Sagar no MWL was found, and the earlier technical limit of 1,690 ft that BBMB is reported to have given is higher than FRL + 0.5 m, so it is used. Where only a reservoir level is published, FRL + 0.5 m is set as the interim value: it is the freeboard that this Manual uses for floor levels (Clause 6.11.1), and it is a floor, not an estimate of the surcharge, which depends on the spillway and the flood [TBC]. Item (c) also runs the town storm with the river at the largest recorded release because the rain that fills a reservoir and the rain on the town below come from the same monsoon spell (see the Commentary to Clause 5.8.4): on 14 August 2023 Kangra recorded 273.4 mm (IMD) on the day Pong took its record inflow, and the releases that followed raised the Beas through the Mand area of Indora (as reported). It credits no attenuation by Pong or Bhakra, because BBMB has not published an operating rule that commits their storage to flood control, and because the account of 2023 is disputed (as reported).
The fourth is the tal. Rewalsar, Khajjiar and Renuka have no published level and no outlet level, so item (d) uses their surveyed spill level, as Uttarakhand's edition does for its taals. The tals are small, Rewalsar 2.6 ha with a catchment of 173 ha (State Wetlands Authority), and silt and sewage reach them through the same drains, so item (d) requires sediment and debris traps on every drain and keeps sewage out (Clause 8.9).
The fifth is the kuhl, the canal and the drain of another body, and the sixth is the line within which an outfall may be built. The kuhls in the schedules of the Minor Canals Act 1976 are canals in law, managed by the State, a local authority or their beneficiaries, and the Act makes their obstruction or fouling an offence (s.65); a kuhl that runs across a slope also intercepts the runoff of the land above it, so item (e) asks for consent and computes the kuhl's level with that runoff included. Items (c), (e) and (f) ask for the owner's consent and design level because a design that discharges to a channel, a reservoir or a tal cannot be checked without them. The lines of item (f) decide where an outfall can be built, not its level. The TCP Rules 2014 set 3.00 m from a nullah and 5.00 m from a khud where no development plan exists, and leave the distance from the high flood level to the development plans, but name no line from which either is measured (Chapter 7). The distances announced in 2025, 5 m from drains and 7 m from rivers and ravines, 150 m from rivers for government buildings, and a ban on building along river and stream banks in the rural model bye-laws, were reported in the press, and no gazetted text was found; item (f) reports them and does not apply them.
5.9 Joint-probability cases
5.9.1 Every element draining to a tidal or backwater-affected outfall shall be checked for the cases below. The most severe governs each design quantity: storage, water level, pipe size and pump capacity.
Table 5.2 — Joint-probability cases for tidal and riverine outfalls
| Case | Rainfall | Tailwater | Applies to | Basis |
|---|---|---|---|---|
| J1 | Minor-system design AEP, Tc to 24 h | MHWS + SLA (tidal curve) | Minor system | Clause 2.12(a); Clause 5.7.1 |
| J2 | 1% AEP, all durations of Clause 2.5.2 | HAT + surge + SLA | Major system, detention, tanks, pumped systems | Clause 5.7.1 |
| J3 | 10% AEP, 48 h | 1% AEP still-water level + SLA | Major system, detention, tanks, pumped systems | Clause 2.12(b) |
| J4 | Design AEP, 48 h (72 h reported) | Tidal curve per J1 with two 6 h lock windows (Clause 5.10) | All storage and every gated or tide-affected outfall | Clause 5.10 |
| R1 | Site design AEP | River at 10% AEP level | Riverine outfalls | Clause 5.8.4(a) |
| R2 | Site 10% AEP | River at design-AEP level | Riverine outfalls | Clause 5.8.4(b) |
5.9.2 For storage elements, the 48- and 72-hour storms shall be run with the J2 and J3 tailwaters (Clause 2.5.3).
5.9.3 For tidally influenced riverine outfalls, R1 and R2 shall be run with the river model's downstream boundary at the J1 tidal curve. The Authority may also require them at J2.
5.9.4 Where tailwater is constant at a level above the outfall invert for the whole storm, the case is treated as a fully closed outfall. Storage and pumps shall then handle the full storm volume.
Commentary. Clause 2.12 sets two joint cases. Case (a) is design rainfall with MHWS plus the sea-level allowance. Case (b) is the 10-yr, 48-hour storm with the 1% still-water level. This Manual adds HAT plus surge for major-system design (Clause 5.7.1). Case J2 combines these. J4 is the outfall-closed check, which tests the timing of tide against the storm rather than a single level. Rainfall and surge share a cyclone cause, so they cannot be treated as independent (Clause 2.12 commentary). These cases are simple surrogates, to be replaced when a statistical joint analysis of IMD rainfall and tide-gauge records is adopted.
5.10 Outfall-closed (tide-locked) storage check
5.10.1 Where it applies. The check applies to:
- every storage facility;
- every minor- and major-system element; and
- every pumped system
whose outfall invert is below HAT + surge + SLA, or which drains to a reach subject to tide-lock or sand-bar closure (Clause 5.13).
5.10.2 Storm. Use the 48-hour design storm built per Clause 2.9.2 (peak day last), at:
- the AEP of the element: 1% AEP for detention, tanks and the major system; the minor-system AEP for minor drains; and
- AMC III.
The 72-hour storm shall also be run and reported.
5.10.3 Lock windows. Unless a site study under 5.10.6 gives otherwise:
- (a) the outfall is closed for two consecutive lock windows of 6 hours each, centred on two consecutive high tides of the local tidal curve. For a semi-diurnal tide, the window starts are therefore about 12.4 hours apart.
- (b) During each lock window, gravity discharge is zero.
- (c) Between lock windows, gravity discharge is computed against the J1 tidal curve, including the head loss of the flap gate and any non-return valve.
- (d) The first lock window shall be placed so that it is centred on the peak 1-hour block of the final 24 hours of the storm. A second run with the first window starting at that peak block shall also be made. The more severe governs.
5.10.4 Requirement. Storage plus pumping (where provided) shall hold the inflow so that, throughout the check:
- (a) the maximum stage in any detention facility stays below its emergency spillway crest, so the spillway does not operate. Where the outfall-closed stage is higher than the 1% AEP maximum water level of the free-outfall design, it becomes the facility's 1% AEP maximum water level for Clause 4.9.3, and the spillway crest, freeboard and wall height are set from it;
- (b) the maximum stage in the minor and major systems meets the Chapter 6 limits: building floor levels, and street depths of no more than 150 mm at the crown and no more than 350 mm at the deepest point; and
- (c) no property connection surcharges above the lowest opening it serves, or a non-return valve is fitted under Clause 5.11.
In volume terms, over each lock window and the full storm:
V_inflow ≤ V_storage available + V_pumped + V_gravity (between locks)
This shall be demonstrated by routing, not by a single volume balance. The release from each facility after a lock window ends may exceed the release caps of Chapter 4, because the facility is emptying into a drain that has just reopened. That release shall be included in the downstream analysis (Clauses 5.4 and 5.9).
5.10.5 Drawdown after the storm. After the second lock window, the storage shall drain under the J1 tidal curve. The drawdown requirement of Clause 4.7 shall be met, with pumping where gravity cannot meet it (Clause 5.12).
5.10.6 Site study. A longer or shorter lock may be used where a site study gives a time series of still-water level for the design case. The study may use a calibrated hydrodynamic model, gauge records of past events, or a surge hindcast. Locks shorter than the default require the Authority's approval. A longer lock shall be used where:
- sand-bar closure (Clause 5.13) or river backwater (Clause 5.8) keeps the outfall closed for longer; or
- the gauge record shows tailwater above the outfall invert for more than 6 hours per tide in comparable past events.
Figure 5.3 — Outfall-closed check: 48-hour storm with the peak day last (Clause 2.9.2), tailwater of astronomical tide plus surge, two 6-hour design lock windows, and the resulting stage upstream of the flap gate. Illustrative — not design values. Original drawing for this Manual, adapted from the tidal tailwater and joint-probability concepts of MoHUA/CPHEEO Manual on Storm Water Drainage Systems (2019), Part A, §6.3.6.
Commentary. The outfall-closed check is the distinctive Himachal Pradesh requirement in this Manual. In Himachal Pradesh it applies where an outfall is shut not by the tide but by a river held high by a monsoon spell or by the releases of a dam, by a khad or nallah that has risen over the outlet or buried it in boulders, by a reservoir at its full level, or by a tal. The spell of 7–11 July 2023 brought 223 mm to the State in four days, a departure of 436% from normal (post-disaster needs assessment, 2023, citing IMD), and after 15 August 2023 the Pong dam released about 1.40 to 1.50 lakh cusec into the Beas for days (as reported). A river below a dam stays high for as long as the dam passes the flood, a reservoir or tal at its full level stays there for the rest of the monsoon, and a khad in flood can block an outlet with boulders, which is why Clause 5.8.5 replaces the two 6-hour windows described below with a single river lock of at least 72 hours and a closure for the whole storm at a reservoir, tal or khad outfall below its design level. A rate rule cannot help when there is no outlet: an orificed basin behind a closed gate simply fills.
The default of two consecutive 6-hour locks has no direct precedent. It represents gravity outfalls failing to discharge for about half of each tidal cycle around the two high tides nearest the storm peak. Figure 5.3 shows why both windows matter. The first lock catches the storm peak. The second arrives before the storage has drained, so the stage rises again.
Placing the first window on the rainfall peak is deliberately unfavourable. Cyclone rainfall and surge share a cause, and Clause 2.12 already treats them as dependent. The check replaces neither the J2 and J3 level checks nor the downstream analysis; it adds a test of timing and volume.
5.11 Flap gates, tide gates and non-return valves
5.11.1 Where required. A flap gate, tide gate or equivalent non-return device is required on every outfall whose invert is below the 1% AEP still-water level (Clause 5.7.3). It is also required on outfalls into irrigation channels under Clause 5.8.5.
5.11.2 Hydraulics. The design shall include:
- the gate's head loss and opening head, from the manufacturer's certified head–discharge curve; and
- the reduction in effective outfall capacity when the gate is partly open.
Gates shall not be assumed to seal perfectly in the outfall-closed check unless they are tested.
5.11.3 Construction.
- (a) Gates, hinges and seats shall be of corrosion-resistant materials suitable for seawater (Clause 4.12.5).
- (b) The gate shall be set so that sand, silt or debris on the downstream side cannot hold it shut or open. Where the bed is mobile, the gate invert shall be raised above the bed, or the approach shall be protected.
- (c) A trash screen shall be provided upstream where the gate could be jammed by debris.
- (d) A stop-log slot or penstock shall be provided upstream for maintenance isolation on outfalls larger than 600 mm.
- (e) The gate chamber shall be accessible at all tides, with its access above HAT + surge + SLA.
5.11.4 Non-return valves on property connections. A non-return valve, or a backwater valve with an accessible cleaning eye, is required on every property drainage connection where the lowest opening served is below:
- the major-system tailwater (J2) at the point of connection; or
- the maximum stage in the outfall-closed check (Clause 5.10).
Basement drainage shall in addition be pumped to a level above both, with its own non-return valve.
5.11.5 Inspection. Gates and valves shall be inspected and operated:
- before 15 June each year;
- after every event in which they closed against a storm flow; and
- as set in the maintenance plan (Chapter 10).
Commentary. The requirement for gates below the 1% still-water level is set by this Manual. The construction details follow common coastal-drainage practice. A gate that is jammed open by debris lets the tide into the drain. A gate held shut by a sand bank turns a gravity outfall into a dead end. In Himachal Pradesh the outfalls do not cross a beach, but many of them end in a river whose level is set by a dam upstream, or in a reservoir held near its full level. In August 2023 the Pong reservoir took an inflow reported as 7.3 lakh cusec on 14 August by one account and 5.13 lakh cusec by another, released about 18,000 cusec until that day and then 1.40 to 1.50 lakh cusec (as reported); on 30 June 2025 all five gates of the Pandoh dam were opened, releasing nearly 44,000 cusec, after a release from Larji upstream (as reported); and after the cloudburst of 24 July 2023 the Malana II project filled with debris and silt and overflowed, its gates jammed (as reported). A gate opened in a hurry raises the river below; a gate held shut or jammed raises the reservoir and every outfall that drains to it. The dams are held by BBMB (Bhakra, Pong and Pandoh), NTPC (Kol), SJVN (Nathpa Jhakri), NHPC (Chamera and Parbati) and HPSEBL (Larji), and the drains that reach the rivers and reservoirs below them belong to the Municipal Corporations, the Nagar Parishads and Nagar Panchayats, PWD and the Jal Shakti Vibhag; no rule linking the operation of any of these gates to the levels of the drains was found during research [TBC], and the list of dams, among them Pandoh, that the Chief Secretary is reported to have found in breach of dam-safety norms was not obtained (as reported) [TBC]. A gate and the drains behind it can therefore belong to different bodies. The 15 June inspection date is set ahead of the SW monsoon.
5.12 Pumped outfalls
5.12.1 When required. Pumping shall be provided where gravity discharge cannot meet:
- the outfall-closed check of Clause 5.10;
- the drawdown requirement of Clause 4.7; or
- the J2 and J3 cases.
Pumping shall not be used where a gravity solution meets these requirements.
5.12.2 Capacity.
- (a) The duty pumps together, with the storage provided, shall pass every case of Clause 5.9 (including J4), demonstrated by routing.
- (b) Standby capacity at least equal to the largest duty pump shall be installed (duty + 1 standby as a minimum).
- (c) Pump capacity shall be stated at the static head for the J2 tailwater, not at mean tide.
5.12.3 Effect on the receiving water. Pumped discharge to a river, canal or creek shall be included in the river or creek level analysis of Clause 5.8. Pumping that raises the receiving water level above the acceptance criteria of Clause 5.5 elsewhere is not permitted.
5.12.4 Power supply. Pumping stations shall have either:
- two independent power supplies; or
- standby generation for 100% of the duty capacity, with on-site fuel for at least 72 hours of duty operation.
Changeover shall be automatic.
5.12.5 Flood immunity. Electrical panels, control equipment, generators and fuel storage shall be set above the higher of:
- the 1% AEP flood level + 0.5 m; and
- HAT + surge + SLA + 0.5 m.
Access to the station shall remain usable in the 1% AEP event.
5.12.6 Discharge arrangement. Rising mains shall discharge:
- over a level above the J2 tailwater; or
- through a non-return valve and a flap gate.
The arrangement shall prevent back-siphoning.
5.12.7 Controls and monitoring. Each station shall have:
- automatic level control;
- remote alarms for high level, pump failure and power failure, sent to the operator; and
- a level and run-time log kept for at least 5 years.
Wet wells shall be sized to keep pump starts within the manufacturer's limits.
5.12.8 Screens. Inlet screens shall be provided with a cleaning method that works during a storm (a mechanical rake, or duplicate screens).
5.12.9 Testing. Every pumped outfall shall be test-run at full duty, including on standby power, before 15 June each year. Private pumped systems shall be covered by a registered maintenance declaration (Chapter 10).
Commentary. Duty + standby, 72 hours of fuel and flood-immune electrics have no single direct precedent and are set by this Manual. The 72-hour fuel figure matches the longest mandatory design storm (Clause 2.5.2). A pump station that depends only on grid power can stop exactly when it is needed, because supply to flooded areas is often switched off for safety. Singapore's April 2025 amendments added annual maintenance declarations for pumped detention tanks (PUB Addendum No. 3). Clause 5.12.9 and Chapter 10 adopt the same approach. Clause 5.12.3 prevents pumping that simply moves water from one tide-locked drain into a tide-locked river.
5.13 Sand-bar closure of river mouths
5.13.1 Where it applies. This clause applies to outfalls into any river or creek whose mouth is subject to seasonal sand-bar closure. That includes the mouths of the coastal States (there is none in Himachal Pradesh: Clause 5.1.4), and any other mouth listed in Annex 5B.
5.13.2 Assumption at the start of the SW monsoon. The mouth shall be assumed closed by a bar at the start of the June–September season, at the crest level of the most recent pre-monsoon survey. This applies unless the Jal Shakti Vibhag certifies that:
- a mouth-maintenance programme (dredging, bar cutting or training walls) has kept the mouth open at the start of each of the previous three SW monsoon seasons; and
- the programme is funded for the current season.
5.13.3 Tailwater with a closed mouth. With the mouth closed, the tailwater at the outfall shall be the higher of:
- (a) the tidal tailwater of Clause 5.7; and
- (b) the level in the river reach behind the bar, computed with the bar as a weir at its surveyed crest level. That level shall include the river flow of Clause 5.8 and the head needed to pass the flow over or through the bar.
5.13.4 No credit for emergency cutting. Bar cutting or breaching during the storm shall not be assumed in design, unless the Jal Shakti Vibhag has a documented operating procedure, with equipment stationed for it. Where it does, the bar may be assumed lowered to the procedure's target level only after the time the procedure states.
5.13.5 Outfall-closed check. Where the closed-mouth level of 5.13.3(b) exceeds the outfall invert for longer than the default lock windows, the lock duration of Clause 5.10 shall be extended to that period.
Commentary. Himachal Pradesh has no coast and no river mouth, so Clause 5.13 does not apply in the State (Clause 5.1.4). Its nearest inland counterparts are the boulders, gravel, timber and silt that hill streams leave at an outfall or a gate. After the cloudburst of 24 July 2023 the Malana II project "filled with debris and silts causing its overspill", and its gates jammed (as reported); in the flood of 2005 the silt in the Sutlej at Nathpa Jhakri rose above 25,000 ppm (International Hydropower Association, case study); Gobind Sagar is reported to have lost between 38% and 47% of its gross storage to silt, by the estimates of IIT Ropar and BBMB (as reported); and the expert committee that reported to the National Green Tribunal in 2017 found Shimla's slope debris dumped "near water channels, obstructing the natural drainage". A flap gate held open or shut by gravel or debris, an outlet buried by a rising bed or left hanging by scour, or a gate that cannot be moved, turns a designed outfall into a dead end or a back-flow path. No written gate-operation rule for the gates of any dam, barrage or tal outlet in the State was found during research [TBC]. Clause 5.8.5 deals with both by setting outfalls above the range of bed movement and by giving no credit for a gate operation or a storage that the operator's records do not show. Clause 5.13.2 has no direct precedent. It puts the burden of proof on showing that the mouth is open rather than assuming it.
5.14 Documentation
Every project subject to this chapter shall submit a Downstream and Tailwater Report (Form 5-1). It shall contain:
- a plan of the analysis extent showing:
- the site;
- each analysis point with its contributing catchment area and the site's percentage of it; and
- the end point and the reason it was chosen (Clause 5.3);
- the model description:
- software and version;
- the network schematic, with survey sources for the drains and crossings;
- land use and CN for off-site areas;
- any upstream detention included; and
- calibration or validation evidence where available;
- for each analysis point, AEP and duration, the existing and with-project:
- peak flow;
- time to peak;
- maximum water level and velocity; and
- duration of inundation (Clause 5.4);
- the comparison against Clause 5.5, with each failure identified and the remedy adopted;
- the tailwater derivation:
- tide-table edition and port;
- MHWS, HAT and MSL relative to chart datum;
- the datum connection to the Survey of India benchmark and the project datum;
- surge source and value;
- SLA; and
- river levels and their sources (Clauses 5.6 to 5.8);
- the joint-case table of Clause 5.9 with results;
- the outfall-closed check (Clause 5.10):
- storm and lock alignment;
- stage hydrographs; and
- the volume balance for each lock window;
- a schedule of flap gates, tide gates and non-return valves, with certified head–discharge data (Clause 5.11);
- pumped outfall design, power supply, flood immunity and controls, where provided (Clause 5.12);
- the sand-bar assumption and supporting Jal Shakti Vibhag certification, where relevant (Clause 5.13); and
- inspection and maintenance requirements for Chapter 10.
Small sites under Clause 5.3.4 shall submit Form 5-2 (Simplified Downstream Statement) instead.
References (chapter)
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A, §6.3.6 and Table 6.2 (coastal tailwater; +0.3 m climate allowance). https://web.archive.org/web/2024/https://mohua.gov.in/upload/uploadfiles/files/VolumeI-Part%20A-Engineering-Design.pdf
- MoHUA / CPHEEO (2013). Manual on Sewerage and Sewage Treatment Systems (pumping stations).
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (5601.5, ten-percent downstream analysis). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Atlanta Regional Commission / Georgia EPD (2016). Georgia Stormwater Management Manual, Vol. 1 (Standard #8) and Vol. 2 §3.1.9. https://documents.atlantaregional.com/gastormwater/GSMM_2016%20EDITION_FINAL_V1.pdf
- MARC. The Evolution of Regional Stormwater Design Standards. https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Optimisation of urban detention (2016). Water 8(7):290. https://doi.org/10.3390/w8070290
- Colorado State University. Spatially Dependent On-Site Detention Policies (thesis). https://mountainscholar.org/bitstreams/f4dbec4e-a44f-4933-8d54-a097e741f44a/download
- SANDRP. 2022 CWC flood monitoring sites in North India (the CWC sites in Himachal Pradesh: Paonta's warning, danger and highest flood levels; the highest flood levels of the level-monitoring sites, among them Rampur, Nathpa, Pandoa and Ghaluwal), https://sandrp.in/2022/08/05/2022-cwc-flood-monitoring-sites-in-north-india/ ; Rivers breaching highest flood levels in July 2023 (Gulling, Ropa, Meenus, Meenus Khad and Ganguwala; the Pandoa conflict; no Beas data), https://sandrp.in/2023/08/03/rivers-breaching-highest-flood-levels-in-july-2023/ ; and its table of the CWC flood monitoring stations in Himachal Pradesh shown as inactive in July 2025 (BBMB stations in the Sutlej and Beas basins). These are copies of CWC data; the CWC websites refused access during research, and the datum and gauge zero of each gauge are to be confirmed with CWC.
- SANDRP. No dispute about role of Pong and Bhakra dams in Punjab Aug 2023 floods (levels in feet, inflows and releases of August 2023), https://sandrp.in/2023/08/21/no-dispute-about-role-of-pong-and-bhakra-dams-in-punjab-aug-2023-floods/ ; Punjab floods 2025: role of Bhakra, Pong and Ranjit Sagar dams (Pong's maximum levels of 1,400 and 1,421 ft; Bhakra's full level and earlier technical limit; the levels and releases of 2025), https://sandrp.in/2025/09/07/punjab-floods-2025-role-of-bhakra-pong-and-ranjit-sagar-dams/ ; and Himachal Pradesh 2023: how we are turning cloudbursts into deadly disasters (Malana II; Larji, Parbati and Sainj; the debris at Thunag), https://sandrp.in/2023/11/09/himachal-pradesh-2023-how-we-are-turning-cloudbursts-into-deadly-disasters/
- Press reports on the Pong reservoir in August 2023 (The Tribune, "Rain fury: Pong dam records highest-ever inflows"), https://www.tribuneindia.com/news/punjab/rain-fury-pong-dam-records-highest-ever-inflows-water-level-goes-5-ft-above-top-mark-535072 , and in 2025 (The Tribune, the Mand area of Kangra), https://www.tribuneindia.com/news/himachal/sleepless-nights-rising-pong-waters-spark-panic-in-kangras-mand-area ; on the opening of the Pandoh gates after a release from Larji (The Tribune, 30 June 2025), https://www.tribuneindia.com/news/himachal/pandoh-dam-gate-opened-after-water-release-from-larji ; on the siltation of the Bhakra reservoir (The Tribune), https://www.tribuneindia.com/news/punjab/iit-ropar-study-counters-bbmb-estimates-on-bhakra-reservoir-siltation/ ; on the Parechu flood of 26 June 2005 (AFP; AGU landslide blog), https://blogs.agu.org/landslideblog/?p=418 ; and on the Panchvaktra temple at Mandi on 9 July 2023. The levels of the Kol, Chamera and Karcham Wangtoo reservoirs and the spillway capacities of Kol and Nathpa Jhakri are taken from public encyclopaedia entries and are to be confirmed with their operators.
- International Hydropower Association. Sediment management case study: Nathpa Jhakri, India (silt loads and the flood of 2005), https://www.hydropower.org/sediment-management-case-studies/india-nathpa-jhakri
- Himachal Pradesh State Wetlands Authority. Major Wetlands of Himachal Pradesh (booklet: Pong's water spread at 1,280 ft and 1,390 ft; Rewalsar, Khajjiar and Renuka); Department of Environment, Science and Technology, notification No. STE-E(3)-10/2017-Pt-I of 7 November 2017 (constitution of the State Wetlands Authority); and Ministry of Environment, Forest and Climate Change, list of 80 Ramsar sites of India, 31 January 2024 (Pong Dam Lake, Chandertal and Renuka), https://moef.gov.in/uploads/2024/03/80-Ramsar-sites-of-India-31-01-2024.pdf
- Himachal Pradesh Minor Canals Act, 1976 (Act No. 42 of 1976), ss.2, 3, 43, 46–48 and 65, with its schedules of kuhls, read from the PRS copy.
- Town and Country Planning Department, Government of Himachal Pradesh. Himachal Pradesh Town and Country Planning Rules, 2014, consolidated to 2022, Appendix-1 (cl. 16), Appendices 3 and 7 (distance from the highest flood level), https://tcp.hp.gov.in/Application/uploadDocuments/rule/Rule20221126_160623.pdf ; and the Chopal Planning Area Development Plan 2041, https://tcp.hp.gov.in/Application/uploadDocuments/devlopmentPlan/PlanDoc020240108_160640.pdf
- Government of Himachal Pradesh (2023). Post Disaster Needs Assessment, Monsoon 2023 (floodplains and river boundaries; the Beas channelisation proposal; sewer damage; the spell of 7–11 July 2023).
- NITI Aayog, Development Monitoring and Evaluation Office (2020). Best-practice note on the Swan River Flood Management Project (embankments designed on hydraulic modelling).
- High Court of Himachal Pradesh, Madan Lal v. State of Himachal Pradesh, CWPIL 31/2023, orders of 22 May 2023 and 31 May 2024 (muck in Govind Sagar and its feeding khuds); and Fourlane Visthapit and Prabhavit Samiti v. State of Himachal Pradesh, CWP 5243/2022, order of 26 June 2023 (muck dumped by the contractors of the Kiratpur–Nerchowk highway).
- National Green Tribunal, O.A. 121/2014, Yogindra Mohan Sengupta v. Union of India, judgment of 16 November 2017 (the expert committee on Shimla's drains and slopes), set aside by the Supreme Court in State of Himachal Pradesh v. Yogendera Mohan Sengupta, 2024 INSC 30, judgment of 11 January 2024 (the Shimla Development Plan published on 20 June 2023).
- Municipal Corporation Shimla and UNDP (2015). Action Plan for Mainstreaming DRR and CCA into Sectoral Development Plan of Municipal Corporation Shimla (the thirteen major nallahs), https://mcslogin.hp.gov.in/SecureFileStructure/DepartmentDetails/Doc/Action%20Plan%20for%20Mainstreaming%20DRR%20and%20CCA%20into%20Sectoral%20Development%20Plan%20of%20Municipal%20Corporation%20Shimla_2_28_2022_50_98.pdf
- India Meteorological Department, Meteorological Centre Shimla. Monsoon Report 2023 (extremely heavy falls of July and August 2023), https://mausam.imd.gov.in/shimla/mcdata/monsoon/images/Monsoon%20in%20HP/monsoon2023.pdf
- Press reports on the setbacks announced in 2025 (thenewshimachal.com, 26 July and 16 September 2025; The Tribune, 30 July 2025), https://www.tribuneindia.com/news/himachal/no-govt-institution-to-be-built-within-150-metres-of-rivers-cm
- Survey of India. Tidal Predictions: Geodetic and Research Branch. https://www.geographyandyou.com/survey-of-india/tidal-predictions-geodetic-and-research-branch-survey-of-india
- GLOSS. India national report (tide-gauge network and datums). https://gloss-sealevel.org/gloss/gloss/sites/gloss/files/publications/documents/india_ge9.pdf
- Adani Ports (2025). Tide Table 2025, Dahej (notes on NHO INP-12 coverage and data sources). https://www.adaniports.com/-/media/Project/Ports/PortsAndTerminals/Dahej-Port/Marine-Documents/Tide-Table-2025-Dahej.pdf
- INCOIS. Storm-surge and swell-surge warning services. https://incois.gov.in/
- FHWA. HEC-22 Urban Drainage Design Manual (current edition), Table 7.3 (coincident frequencies).
- Purdue University JTRP (2023). Development of a Multiple Water Course Joint Probability Analysis Procedure for Indiana Watersheds, FHWA/IN/JTRP-2023/09. https://docs.lib.purdue.edu/jtrp/1820
- PUB Singapore (2025). Code of Practice on Surface Water Drainage, 7th ed., Addendum No. 3. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
Annexes and forms
| Annex / Form | Content |
|---|---|
| 5A | Tidal datums (MSL, MHWS, HAT vs CD and Survey of India datum), surge allowances and 1% still-water levels by coastal segment |
| 5B | Major drains, riverine outfall reaches, and river mouths subject to sand-bar closure; map |
| 5C | Worked example: outfall-closed check for a site on a nallah draining to the Ashwani Khad in Shimla |
| Form 5-1 | Downstream and Tailwater Report |
| Form 5-2 | Simplified Downstream Statement (small sites) |
Commentary. The drains of Himachal Pradesh's towns fail in places that site design does not see, and in five different ways. The first is the river. Paonta Sahib drains to the Yamuna, whose highest recorded level at Paonta, 384.6 m, stands only 0.1 m above its danger level, and to the Bata, which set a new highest level at Ganguwala on 22 July 2023; Rampur drains to the Sutlej, which rose by 12 to 15 m (as reported) when a landslide lake on the Parechu in Tibet burst on 26 June 2005 and set the highest levels at Nathpa and Rampur; and Mandi drains to the Beas at its confluence with the Suketi, where the Panchvaktra temple was submerged to its dome on 9 July 2023 (as reported), at a place where no gauge records the level (CWC data, as copied by SANDRP). The second is the khad and the nallah. Shimla's thirteen major nallahs run north to the Sutlej and south to the Ashwani Khad and the Giri (Municipal Corporation Shimla and UNDP, 2015); none of them is gauged; the expert committee that reported to the National Green Tribunal in 2017 found that the debris of Shimla's slopes "is dumped in the valley or near water channels, obstructing the natural drainage" (Yogindra Mohan Sengupta, judgment of 16 November 2017, para 62, set aside by the Supreme Court on 11 January 2024 and cited here only for its committee's findings); and in July 2023 the khads at Thunag were choked with timber and with debris from a road project (as reported). The third is the reservoir: Gobind Sagar holds every drain of Bilaspur, the Pong reservoir took what was reported as its highest inflow since 1974 on 14 August 2023 and rose from 1,374.20 ft to 1,399.65 ft over 11–15 August (as reported), and the releases of Larji and Pandoh raise the Beas at Mandi. The fourth is the tal. Rewalsar, Khajjiar and Renuka receive the drains of the settlements around them and have no published level. The fifth is the kuhl and the canal: the kuhls of Kangra and the other districts are statutory canals under the Himachal Pradesh Minor Canals Act 1976 and intercept the runoff of the slopes above them. The outfalls also belong to one body while the drains above them belong to others: the rivers, khads and flood works are the Jal Shakti Vibhag's, the reservoirs BBMB's, NTPC's, SJVN's, NHPC's or HPSEBL's, the kuhls the Jal Shakti Vibhag's or their beneficiaries', and the drains the Municipal Corporations', the Nagar Parishads' and Nagar Panchayats' and PWD's, and no rule divides them (Chapter 6, Clause 6.9). No document found during research sets a design level for any river, khad, reservoir, tal or kuhl outfall in the State, or a design standard for any town drain. A detention basin that meets every release rate in Chapter 4 still fails if the river it drains to stands above its outfall, if the khad has buried its outlet in boulders, or if the reservoir or tal is full. This chapter makes these failure modes part of the design. Himachal Pradesh has no tidal outfall, so Clause 5.1.4 says which of the chapter's coastal provisions fall away and what takes their place.