Chapter 10Submittals, Review, Operation & Maintenance and Enforcement
10.1 Purpose and scope
10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:
- (a) the submittal stages and their contents (Clauses 10.3–10.4);
- (b) the compliance calculator (Clause 10.5);
- (c) professional certification and review (Clauses 10.6–10.7);
- (d) construction inspection and as-built certification (Clauses 10.8–10.9);
- (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
- (f) handover of public assets (Clause 10.14);
- (g) enforcement (Clause 10.15); and
- (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).
10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.
10.2 Definitions
| Term | Meaning in this chapter |
|---|---|
| Submittal | A set of documents lodged with the Authority at one of the stages of Clause 10.3. |
| Drainage report | The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4. |
| Stormwater facility | Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private. |
| Hold point | A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8). |
| As-built certificate | The certificate of Clause 10.9 that the facility was built as approved and performs as designed. |
| Owner | The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset. |
| O&M plan | The operation and maintenance plan of Clause 10.11. |
| Facility register | The public register of facilities of Clause 10.17. |
Other terms are defined in Clause 1.4.
10.3 Submittal stages
10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Himachal Pradesh Town and Country Planning Rules 2014 (Table 10.1):
Table 10.1 — Submittal stages and linked approvals
| Stage | Submittal | When | Linked approval |
|---|---|---|---|
| 0 | Pre-application meeting and Form 1-1 (Applicability Determination) | Before the planning permission or layout application | None (advisory record) |
| 1 | Preliminary drainage report | With the planning permission or layout application | Planning permission / layout approval |
| 2 | Final drainage design | Before building permit, or before commencement where the permit is issued with the planning permission | Building permit / commencement |
| 3 | Construction inspections at hold points | During construction | None (records filed) |
| 4 | As-built certificate and verification tests | Before the completion certificate | Completion / occupancy certificate |
| 5 | Maintenance declaration registered, or handover of public assets | Before or with the completion certificate | Completion certificate; asset acceptance |
| 6 | Annual declarations and inspection reports | Every year after completion | Continuing compliance |
10.3.2 Stage 0 is mandatory for:
- (a) sites of 2 ha or more;
- (b) sites in a flood-sensitive catchment;
- (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
- (d) sites draining to a tidal outfall or adjoining a waterbody.
For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.
10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.
10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.
10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.
Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.
Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the TCP Rules 2014 steps a Himachal Pradesh applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.
10.4 Required contents and checklists
10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:
- (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
- (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
- (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
- (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
- (e) the pre-development condition and hydrologic method (Chapter 3);
- (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
- (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
- (h) the downstream extent and tailwater case (Chapter 5);
- (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
- (j) the land reserved for facilities and maintenance access (Clause 10.13).
10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:
- (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
- (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
- (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
- (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
- (e) construction drawings, details and specifications of every facility;
- (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
- (g) the hold-point schedule (Clause 10.8);
- (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
- (i) the model input files and the GIS data of Clause 10.4.4; and
- (j) the certificates of Clause 10.6.
10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.
10.4.4 Digital submittal.
- (a) Reports and drawings shall be submitted as searchable PDF.
- (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
- (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (43N for almost all of the State, and 44N east of 78° E, which includes eastern Kinnaur (Karcham, Kalpa, Reckong Peo, Sangla, Chitkul and Pooh), Spiti east of about Kaza and the Dodra Kwar area of Shimla district; Kaza and Nathpa lie within about 0.1° of the meridian, and a project that crosses it uses one zone for all its layers and states which), with attributes as listed in Annex 10B.
- (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the CWC gauges on the receiving rivers, of the reservoir levels of BBMB for Bhakra (Gobind Sagar), Pong and Pandoh (published in feet and converted at 0.3048 m per foot), of the reservoir and pond levels of NTPC, SJVN, NHPC, HPSEBL and the other dam operators, and of the flood marks surveyed on ungauged khads and nallahs used in Chapter 5 shall be stated.
10.4.5 Summary of forms used in submittals (Table 10.2):
Table 10.2 — Forms used in submittals
| Form | Title | Stage |
|---|---|---|
| 1-1 | Applicability Determination | 0 or 1 |
| 1-2 | Variance / Waiver Request | 1 |
| 2-1 | Design Rainfall Sheet | 1, 2 |
| 10-1 | Drainage Report Checklist | 1, 2 |
| 10-2 | Compliance Calculator Summary | 1, 2, 4 |
| 10-3 | Professional Design Certificate | 1, 2 |
| 10-4 | Hold-Point Inspection Record | 3 |
| 10-5 | As-built Certificate | 4 |
| 10-6 | Maintenance Declaration | 5 |
| 10-7 | Annual Maintenance Declaration and Inspection Report | 6 |
| 10-8 | Asset Handover Certificate | 5 |
Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Himachal Pradesh has no notified design return period or design storm for its urban drains, and no document of the TCP Department, the Urban Development Department, a Municipal Corporation, the Jal Shakti Vibhag or a Smart City company stating a return period, a runoff coefficient or a drain standard was found. The expert committee before the National Green Tribunal found that storm drains covered about 30% of Shimla and that their "Carrying capacity … is not sufficient", their catchments "improperly selected" and their gradients "much lesser … than actually required", so that they were "not able to carry the peak flow" (judgment of 16 November 2017, set aside by the Supreme Court in 2024; the findings are cited as expert evidence only); the 191 drains and nallahs, 55.43 km, built in Shimla under AMRUT, the drainage component of the Shimla Smart City proposal, and the Jal Shakti Vibhag's proposal of ₹19.66 crore for storm drainage at Una state no design storm. The rainfall studies do not supply one either: IMD's national IDF study (Das et al., 2022) has no Himachal Pradesh panel, and the northern-zone equation of Ram Babu, Dhyani and Nirmal Kumar (2006) gives a 50-year 24-hour depth of about 129 mm (this Manual's computation), against about 160–200 mm on the CWC plate at Shimla and 270 mm recorded in 24 hours at the Dharamshala self-recording gauge, and is not used. The bursts on record, 100 mm in an hour at Dharampur on 9 August 1985, 84 mm at Nahan in 1980 and 73 mm at Dharamshala in 1975 (CWC Flood Estimation Report, zone 7), and the 24-hour falls, 600 mm at Dharamshala on 18 July 1967 (the same report) and 273.4 mm at Kangra Aero on 14 August 2023 (IMD), exceed anything the drains were built for. The State's design values are therefore those of the CWC Flood Estimation Report for zone 7 (Western Himalayas), which covers the whole State, with the interim provisions of Chapter 2, and each submission must state its own design basis. Form 2-1 and Form 10-2 ensure that every design states its inputs.
10.5 Compliance calculator
10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:
- (a) applies the applicability tests of Clause 1.5;
- (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
- (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
- (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
- (e) on alternative S-2, gives the permissible site discharge for each AEP; and
- (f) produces the Compliance Calculator Summary (Form 10-2).
10.5.2 Use.
- (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
- (b) On the design-aid route, the calculator may be the only storage calculation.
- (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.
10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.
10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.
Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Himachal Pradesh calculator serves Tier B authorities in particular, where it may be the whole calculation.
10.6 Professional certification
10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or TCP:
- (a) Tier A sites of 1 ha or more;
- (b) any site in a flood-sensitive catchment;
- (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
- (d) any pumped facility, tide gate or regional facility.
10.6.2 Empanelment criteria shall be issued by TCP and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.
10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:
- (a) the design complies with this Manual, except for variances listed and approved;
- (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
- (c) the models submitted reproduce the results reported.
10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.
10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.
Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the TCP Rules 2014 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.
10.7 Review procedure and timelines
10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.
10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:
- (a) 15 working days of acceptance for a first submittal; and
- (b) 10 working days of acceptance for a resubmittal.
10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.
10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the TCP list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.
10.7.5 Concurrent clearances. Where the approval of the Jal Shakti Vibhag for a work on, or a discharge to, a river, khad or flood-protection work in its charge, among them the channelised Swan and its tributaries, the consent of BBMB for a work that drains to Gobind Sagar, Pong or Pandoh, or of NTPC, SJVN, NHPC, HPSEBL or another operator for a work that drains to its reservoir, the consent of the managing body or the Collector for a work that crosses or discharges to a kuhl scheduled under the Himachal Pradesh Minor Canals Act 1976 (s.46), the permission of the Commissioner or Executive Officer to connect to a municipal drain or to build over one (Himachal Pradesh Municipal Corporation Act 1994 and Himachal Pradesh Municipal Act 1994, whose drain sections were not read [TBC]), the no-objection of SJPNL in Shimla, or of the Jal Shakti Vibhag elsewhere, on sewerage, the views of the State Wetlands Authority (HIMCOSTE) or the Forest Department for a work in or next to a Ramsar site, a wetland of national importance such as Rewalsar or Khajjiar, or forest land, the consent of PWD, NHAI or BRO for a discharge to a side drain, catch-water drain or culvert of one of their roads, the consent of BBNDA or HPSIDC in their areas, the consent of the body that owns or runs the receiving drain where that body is not the Authority (for example Shimla Smart City Ltd or Dharamshala Smart City Ltd until its drains are handed over), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.
10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.
10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.
Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.
10.8 Construction inspection
10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:
- (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
- (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
- (c) the infiltration tests of Clause 10.9.3;
- (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
- (e) pumps and controls, at commissioning.
10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.
10.8.3 Protection during construction.
- (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
- (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
- (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.
Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.
Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.
10.9 As-built certification
10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:
- (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
- (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
- (c) the completed hold-point records (Form 10-4); and
- (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).
10.9.2 Acceptance. The as-built facility is accepted where:
- (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
- (b) the outlet dimensions and inverts match the approved design; and
- (c) the re-run shows compliance with every criterion of Chapters 4 and 5.
Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.
10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.
10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.
Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.
10.10 Maintenance declarations and covenants
10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:
- (a) identify each facility, its location and the approved O&M plan;
- (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
- (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
- (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
- (e) be registered so that it runs with the land and is disclosed to purchasers.
10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.
10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 May each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.
10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.
Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Himachal Pradesh because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 May date is set by this Manual to fall before the south-west monsoon (June–September), when most Himachal Pradesh extreme rainfall occurs.
10.11 O&M plans
10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:
- (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
- (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
- (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
- (d) inspection checklists matching Form 10-7;
- (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
- (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
- (g) safety measures for confined spaces, deep water and public access;
- (h) access routes and equipment needed (Clause 10.13);
- (i) an annual cost estimate and who pays it; and
- (j) the records to be kept, and for how long.
10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.
Commentary. Himachal Pradesh has no dated State order fixing pre-monsoon desilting: the Chief Secretary's directions to clean drains, channels and nallahs, and the Shimla Municipal Corporation's directions to PWD, CPWD and NHAI to keep roadside drains and culverts clean before the monsoon "or face … legal action", are known from the press. The drains are run by several hands: the Municipal Corporations and other ULBs for the municipal drains, the Shimla Municipal Corporation having built its AMRUT drains through its own works wing; PWD, CPWD and NHAI for the road drains and culverts, which carry much of the runoff of the hill towns; SJPNL for water and sewerage in Shimla, over which the Corporation has "limited control"; the Jal Shakti Vibhag for water supply outside Shimla, Solan and Palampur, for sewerage outside Shimla and Solan, and for flood protection, including the channelised Swan; HIMUDA and HPSIDC in their colonies and industrial areas; and the Smart City companies of Shimla and Dharamshala, accountable to the State rather than to the ULBs, whose works are executed by other agencies (CAG, Report No. 1 of 2022). The gates that matter most are run by rules made for other purposes: Bhakra and Pong by BBMB for irrigation and power, Pong releasing about 1.4–1.5 lakh cusecs from 15 August 2023 after its highest inflow on record (as reported); Pandoh, whose five gates were opened together on 30 June 2025 (as reported); and Malana II, whose gates jammed when its reservoir filled with debris in July 2023 (as reported). No operating rule for any sluice, flap gate or pumping station in a Himachal Pradesh town, linking it to a river stage, a dam release or a rainfall warning, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.
10.12 Inspection frequencies
10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:
Table 10.3 — Minimum owner inspection frequencies
| Facility type | Routine | Pre-monsoon (by 31 May) | After a heavy-rainfall event |
|---|---|---|---|
| Retention / infiltration (soakaways, trenches, bioretention, permeable paving) | Every 6 months | Yes | Yes |
| Surface detention basin or multi-use open space area | Every 6 months | Yes | Yes |
| Underground or podium detention tank, gravity outlet | Every 6 months | Yes | Yes |
| Pumped detention, pumps and controls | Monthly test run | Yes, with full duty test | Yes |
| Flap / tide gate, non-return valve | Every 3 months | Yes, with seal test | Yes |
| Gross pollutant trap / first-flush device | Every 3 months | Yes | Yes |
| Private drains and inlets | Every 6 months | Yes | — |
A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Himachal Pradesh, the pre-monsoon inspection of sluices, flap gates, non-return valves, debris racks, sediment traps, debris basins, culvert inlets and pumped facilities, including the gates on outfalls to Gobind Sagar, Pong, Pandoh and the other reservoirs and tals and on outfalls that the Yamuna at Paonta, the Swan at Una or the Beas at Mandi can close, with the desilting and the clearance of boulders, debris and muck from every drain, inlet, rack, trap, basin and culvert and the pump duty and gate seal tests, shall be completed by 31 May; inlets, trash and debris racks, culverts, outfall gates and pumped facilities, with their standby generators, shall be certified ready by 15 June, before the normal onset of 25 June (the earliest recorded onset was 9 June, in 2000), with every gate on an outfall to a river or reservoir operated through its full travel. Pumps, their standby power and the gates shall then be kept on monsoon standby, with the monthly test run, until 31 October, after the normal withdrawal of 25 September, because the monsoon withdrew later than normal in 8 of the 9 years 2018–2026 and western disturbances bring heavy rain after it, as on 5–7 October 2025, and at an outfall to a river regulated by a dam or barrage upstream, or to a reservoir of BBMB, until the releases have ended and the river at the governing gauge has fallen below its danger level where one is published, if that is later. In the hill towns, and on every drain with an undeveloped hill catchment, every public drain, inlet, debris rack, sediment trap, debris basin and culvert shall be cleared a second time, of the sediment, slide debris and muck of the monsoon, by 31 October. In towns above about 1,500 m, inlets, gratings, catch-water drains and culvert entrances shall be kept clear of snow and ice from December to March, and checked after every snowfall and every winter storm.
10.12.2 Authority inspections. The Authority shall inspect:
- (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
- (b) a random sample of at least 10% of other facilities each year.
10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).
Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 May) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the south-west monsoon (June–September); tick positions within the year are illustrative.
Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 31 May deadline is set by this Manual for the onset of the south-west monsoon in the second half of June: the normal onset over Himachal Pradesh is 25 June (IMD normals used from 2024; 24 June before), but the monsoon arrived on 9 June in 2000, 13 June in 2021 and 20 June in 2025 (IMD), and heavy falls come before it, such as 182 mm in 24 hours at the Dalhousie self-recording gauge on 9–10 June 1971 (CWC Flood Estimation Report, zone 7) and the storms reported as cloudbursts in Mandi on 10–13 June 2023 (as reported). No dated State or municipal order fixing a deadline for desilting was found: the Chief Secretary's direction to the ULBs and Panchayati Raj institutions to clean drains, channels and nallahs "in a campaign mode" within 15 days (2019), the yearly directions on pre-monsoon de-siltation and the removal of blockages, and the Shimla Municipal Corporation's directions to PWD, CPWD and NHAI to clean roadside drains before the onset are all known from the press; this Manual takes 31 May for desilting and the clearance of boulders, debris and muck, the pre-monsoon inspection and the annual declaration. NDMA (2010) sets 31 March for pre-monsoon desilting nationally; this Manual allows until 31 May so that dry-season work can be finished. Inlets, racks, culverts, gates and pumps must in addition be certified ready by 15 June, ten days before the normal onset. The normal withdrawal is 25 September, but the monsoon withdrew later than normal in 8 of the 9 years 2018–2026, as late as 11 October in 2019 (IMD), and western disturbances bring heavy rain and snow after it: 285 mm at Batheri on 4 October 1955, 268 mm at Nichar and 246 mm at Rainka on 10–12 October 1956 and 236 mm at Kullu on 4 October 1888 (CWC Flood Estimation Report, zone 7), and the very heavy rain and first snow of 5–7 October 2025, after the monsoon had withdrawn on 26 September (IMD; as reported); pumps and gates are therefore kept on standby to 31 October (Figure 10.3). Hill drains fill with sediment, slide debris and muck during the season, so in the hill towns a second clearance is made by 31 October. Winter storms bring snow above about 1,500 m, and the Flood Estimation Report lists falls of 610 mm at Kilba and 559 mm at Sangla in December 1958, which this Manual treats as doubtful (Chapter 2), so inlets in the higher towns are kept clear of snow and ice from December to March. The post-event inspections of Table 10.3 cover storms at any time of year.
10.13 Maintenance access
10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.
10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.
10.13.3 Underground facilities. Tanks shall have:
- (a) an access opening over the inlet, the outlet and each chamber;
- (b) fixed ladders or steps, and ventilation for confined-space entry;
- (c) a sump or low point for sediment removal; and
- (d) headroom sufficient for manual cleaning.
10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.
10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.
Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Himachal Pradesh cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.
10.14 Handover of public assets to the ULB
10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:
- (a) the as-built certificate (Clause 10.9) has been accepted;
- (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
- (c) the land, or an easement over it, has been transferred to the ULB;
- (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
- (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.
10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 15 June to 31 October, after handover. The ULB may hold a security deposit for this period.
10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.
10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.
Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Himachal Pradesh drainage show up only in the first SW monsoon.
10.15 Enforcement
10.15.1 Offences. The following are contraventions of this Manual:
- (a) building without an approved drainage design where one is required;
- (b) building a facility other than as approved;
- (c) removing, filling, covering, reducing or changing the use of a facility without approval;
- (d) failing to maintain a facility, or to submit Form 10-7;
- (e) a sewage connection to a storm drain;
- (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
- (g) obstructing a natural drainage path or major-system flow path; and
- (h) false or negligent certification.
10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):
Table 10.4 — Graduated enforcement response
| Step | Action |
|---|---|
| 1 | Written notice stating the contravention, the clause breached, the remedy and a compliance period. |
| 2 | Stop-work order, or withholding of the completion certificate, for development not yet complete. |
| 3 | Penalty under the applicable Act or rules. |
| 4 | Works in default by the Authority, with the cost recovered from the owner. |
| 5 | Disconnection of the private drain connection to the public system, where this causes no hazard to others. |
| 6 | Report of the certifying professional to the registering authority, and suspension from the empanelled list. |
10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.
10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.
10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.
Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Himachal Pradesh Town and Country Planning Rules 2014 are made and from the municipal Acts. The graduated steps are set by this Manual. In Himachal Pradesh the courts and the National Green Tribunal have become the working regulators of the slopes, khads and muck of the hill towns. On Shimla the Tribunal froze new construction in the core and green areas and gave 29 directions, among them that runoff from "all the concretised areas like roads, lanes, platforms and market places" be diverted so that it does "not go in to over burden or flow along hills and depressions" (direction XV) and that rainwater harvesting be mandatory (direction XIV) (Yogindra Mohan Sengupta v. Union of India, O.A. No. 121 of 2014, 16 November 2017); the Supreme Court set all its orders aside on 11 January 2024, holding that the Tribunal had "transgressed its limitations", and let the State implement the Shimla Development Plan as published on 20 June 2023 (2024 INSC 30), so the directions are cited in this Manual as expert guidance only. The High Court barred the dumping of muck in Gobind Sagar and "its feeding khuds/nallahas" (22 May 2023) and later directed penal action against the violators and the clearing of the muck from the shores of the lake, its tributaries and public lands within six months (Madan Lal v. State, CWPIL 31/2023, 31 May 2024); in another case it observed that a concessionaire's payment of ₹8,45,700 would not make dumped muck "disappear in thin air" (CWP 5243/2022, 26 June 2023). The Tribunal supervises the action plans for the Ashwani Khad and the State's polluted stretches (O.A. No. 735 of 2023; O.A. No. 673 of 2018), and the Supreme Court has taken up the ecology of the State on its own motion (W.P.(C) No. 758 of 2025), with a first report of its Central Empowered Committee reported in October 2026 (as reported; orders not read). The statutes carry limited powers: the TCP Act 1977 deals with unauthorised construction (s.39); the Minor Canals Act 1976 lets the Government regulate the flow in any "line of natural drainage" and order obstructions removed (s.43), and punishes the obstruction or fouling of a kuhl with a fine of up to ₹1,000 (s.65); and the Ground Water Act 2005 lets its Authority direct rainwater harvesting on premises of 100 m² or more (s.15). Rainwater harvesting is enforced through the water connection, which may not be given until the roof-top storage of Appendix 6 of the TCP Rules is in place. The setbacks announced in 2025, 5 m from drains and 7 m from rivers and ravines for buildings, no government building within 150 m of rivers, nullahs and water bodies, and a ban on building along the banks of rivers and streams in model bye-laws for rural areas, are known only from the press, no gazette text was found, and they are not applied in this Manual as rules. This shows that a rule without routine enforcement does little, and that where the State has not drawn a line on the ground the courts have. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.
10.16 Monitoring and post-event review
10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.
10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:
- (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
- (b) the level of the receiving river (the Yamuna at Paonta, the only CWC site in the State with warning and danger levels, or the level-monitoring CWC site nearest the town, such as the Swan at Ghaluwal or the Sutlej at Rampur) or of the receiving reservoir or tal, with the level of Gobind Sagar, Pong or Pandoh as BBMB publishes it, converted from feet, and, where it is gauged, at the outfall, each on a named datum, with any reading of a local gauge kept apart from the CWC levels; for an ungauged khad or nallah, and for the Beas at Manali, Kullu and Mandi, which CWC does not gauge, the flood marks surveyed after the event and the boulders, debris and muck deposited at crossings; the state of every sluice, flap gate, debris rack, sediment trap, debris basin and pumping station on the outfall and on the drain upstream of it, with the volume of debris removed from each, the hours each pump ran and any loss of power; and the gate openings and releases of any dam or barrage that sets the receiving level, such as Larji, Pandoh, Malana, Kol, Bhakra, Pong or the Dakpathar barrage above Paonta;
- (c) flooded locations, depths and durations, with flood marks surveyed where possible;
- (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
- (e) recommended actions.
10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), HPSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.
10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.
Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Himachal Pradesh's disasters have been assessed more fully than its town floods. The Post-Disaster Needs Assessment of the monsoon of 2023, prepared with the support of NDMA, put recovery needs at ₹8,667.66 crore, with ₹375 crore for disaster risk reduction, recorded more than 500 deaths, more than 5,400 landslides (5,748 mapped over 45.44 km²) and 83 flash floods, and found that most of the destruction along the Beas in Kullu was "due to overflow of the water along the palaeo channels following the old river course along which the developmental activities have taken place"; its damage totals differ between its tables and its text, and its counts of cloudbursts (45 and 27) differ from the 52 reported by HPSDMA. HPSDMA's technical committees examined the slides of August 2023 in Shimla, Mandi, Kullu, Solan and Hamirpur; the Shimla committee named the saturated debris cover, open drainage and an old buried stream channel among the causes of the Summer Hill slide of 14 August 2023, in which about 20 people died at Shiv Bawri. The CAG found in its audit of flood protection (reported as Report No. 6 of 2017, laid in 2018; number as reported) that only about 11% of the State's estimated 2.31 lakh ha of flood-prone land had been covered by March 2017, that the department had made no scientific assessment of flood-prone areas and no basin-wise plan, that three of the five projects checked had no morphological study and that no robust flood-forecasting system existed (as reported); and in 2025 it reported ₹22.61 crore of the State Disaster Response Fund diverted to inadmissible works in five districts (Report No. 2 of 2025, as reported). The events since, the cloudbursts at Samej, Bagipul and Rajban on 31 July 2024, in which 56 people were reported killed at Samej, and the floods of Seraj and Thunag in Mandi on 30 June–1 July 2025, fell where no gauge recorded the rain (IMD; as reported). No review of any flood in a Himachal Pradesh town, and no record of flood extents, depths or durations kept by any ULB or by HPSDMA, was found, and final tolls for 2023, 2024 and 2025 were not published. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.
10.17 Data publication
10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:
- (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
- (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
- (c) the register of variances and waivers (Clause 1.10);
- (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
- (e) enforcement actions (Clause 10.15.5); and
- (f) event reports and post-event reviews (Clause 10.16).
10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.
10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.
10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.
Commentary. Transparency is a design criterion in its own right here. Some of Himachal Pradesh's drainage records are public: the TCP Rules 2014 as consolidated to 2022 and their appendices on the TCP Department's website; the Chopal and other development plans; the Supreme Court's judgment of 2024 and the Tribunal's of 2017, with the expert committee's findings on Shimla's drains; the Ground Water Act 2005 and the Minor Canals Act 1976; the PDNA of 2023 and the State's recovery plan; HPSDMA's technical committee reports on the slides of 2023; the affidavits and action plans for the polluted stretches filed before the Tribunal; the Shimla Municipal Corporation's disaster-risk plan of 2015 and its AMRUT status reports; the CAG's audits; IMD's monsoon reports for the State; and the State Wetlands Authority's booklet on its major wetlands. Much else could not be found in the public domain: the TCP amendments after 2022, including the draft Sixteenth Amendment of 2025 and any text of the setbacks announced in 2025; the rural model bye-laws; the text of the Shimla Development Plan 2041 and its storm-water chapter and zone maps; the drain sections of the municipal Acts; the design basis of any storm drain, including SJPNL's drainage study for Shimla, the Dharamshala Smart City drains and the Jal Shakti Vibhag's proposal for Una; the design flood of the Swan embankments; CWC's site sheets and gauge datums; the datum of BBMB's reservoir gauges and the maximum water level of Pong; the full reservoir level of Pandoh; the operating rules of the State's dams and barrages; HPSDMA's operating procedures for urban floods; and an inventory of the gates, racks and pumping stations of any town. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.
10.18 Review of this chapter
10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.
References (chapter)
- Government of Himachal Pradesh, Town and Country Planning Department. Himachal Pradesh Town and Country Planning Rules, 2014, consolidated to 2022: Rule 21(1); Appendix-1 (areas without an Interim Development Plan or Development Plan; cls. 3, 8, 11, 16 and 20); Appendices 3 and 7 (distance from the high flood level); Appendix 6 (collection of rain water); site-plan forms. https://tcp.hp.gov.in/Application/uploadDocuments/rule/Rule20221126_160623.pdf ; https://tcp.hp.gov.in/content/appendix-1
- Himachal Pradesh Town and Country Planning Act, 1977, ss.16–20 and 39, as summarised in the Supreme Court's judgment of 11 January 2024.
- Government of Himachal Pradesh, Town and Country Planning Department (2023). Shimla Development Plan 2041, published on 20 June 2023 (Supreme Court; 23 June in the press), §17.2.2.9 (sinking and sliding zones), as quoted by the Supreme Court; and Chopal Planning Area Development Plan 2041. https://tcp.hp.gov.in/Application/uploadDocuments/devlopmentPlan/PlanDoc020240108_160640.pdf
- Himachal Pradesh Ground Water (Regulation and Control of Development and Management) Act, 2005 (Act No. 31 of 2005), as amended in 2022 and 2023, ss.5A and 15; draft Rules 2006, r.29. https://prsindia.org/files/bills_acts/acts_states/himachal-pradesh/2005/Act31of2005HP.pdf
- Himachal Pradesh Minor Canals Act, 1976 (Act No. 42 of 1976), ss.3, 43–48 and 65 (PRS copy).
- Comptroller and Auditor General of India (2022). Report No. 1 of 2022, Performance Audit on Efficacy of Implementation of 74th Constitution Amendment Act, 1992, Government of Himachal Pradesh (press brief: devolution; SJPNL; HIMUDA; HPSIDC; Smart City SPVs; water supply and sewerage).
- Comptroller and Auditor General of India. Performance audit of flood protection works, Irrigation and Public Health Department, Government of Himachal Pradesh, reported as Report No. 6 of 2017 (Social, General and Economic Sectors), laid in 2018 (overview and press coverage only; number as reported). https://cag.gov.in/uploads/download_audit_report/2018/
- Comptroller and Auditor General of India (2021). Performance audit of solid waste management in urban areas, Government of Himachal Pradesh, in the report on the Social, General and Economic Sectors (Non-PSUs) for 2018–19, Chapter II (as reported; report number not confirmed). https://cag.gov.in/uploads/download_audit_report/2021/04_Overview-0611646714789d9.50958405.pdf
- Comptroller and Auditor General of India (2025). Report No. 2 of 2025, Compliance Audit Report I, Government of Himachal Pradesh, para 4.11 (State Disaster Response Fund), as reported. https://cag.gov.in/uploads/download_audit_report/2025/Himachal-Report-No.-02-CAR-I-English-06932c40dc33557.79875130.pdf
- Government of Himachal Pradesh with NDMA (2023). Himachal Pradesh Post Disaster Needs Assessment, Monsoon 2023; and Government of Himachal Pradesh, Monsoon 2023 Recovery and Reconstruction Plan.
- India Meteorological Department, Meteorological Centre Shimla. Onset and Withdrawal Dates of Monsoon in Himachal Pradesh (2024–2026) and Monsoon Reports 2023–2026.
- Central Water Commission (1994). Flood Estimation Report for Western Himalayas – Zone 7, Design Office Report No. WH/22/1994, Annexes 4.3 and 4.4 (station maxima; self-recording gauges).
- Das, S.K. et al. (2022). Isopluvial analysis and intensity–duration–frequency curves for different cities in India. MAUSAM 73(4), 887–898. https://metnet.imd.gov.in/docs/mausamdocs/173412_F.pdf
- Ram Babu, Dhyani, B.L. and Nirmal Kumar (2006). Regional rainfall intensity–duration–frequency relationships for India (ISCO 2006; northern-zone equation).
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities, §5608 (easements, maintenance, submittals) and §5609 (plan requirements). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Mid-America Regional Council (2025). Stormwater management page: 2025 Stormwater Standards Manual, Compliance Calculator, Calculator Start-Up Guide, Policy Supplement. https://www.marc.org/environment/environment-plans/stormwater-management
- PUB Singapore (2018, with Addendum No. 3 of 16 Apr 2025). Code of Practice on Surface Water Drainage, 7th ed. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
- PUB Singapore (2024). On-site Stormwater Detention Tank Technical Guide. https://www.pub.gov.sg/-/media/PUB/PDF/detentionTank.pdf
- PUB Singapore (11 Nov 2024). Amendments to Sewerage and Drainage Act (press release). https://www.pub.gov.sg/Resources/News-Room/PressReleases/2024/11/Amendments-to-Sewerage-and-Drainage-Act
- MoHUA (2016). Model Building Bye-Laws, Chapter 9, §9.6. https://web.archive.org/web/2022/https://mohua.gov.in/upload/uploadfiles/files/MBBL.pdf
- National Disaster Management Authority (2010). National Guidelines on Management of Urban Flooding. https://sdma.goa.gov.in/sites/default/files/2022-05/management_urban_flooding.pdf
- National Green Tribunal. O.A. No. 121 of 2014 with O.A. No. 505 (THC) of 2015, Yogindra Mohan Sengupta v. Union of India, judgment of 16 November 2017 (expert committee report of May 2017; directions XIII–XV) — set aside by the Supreme Court; cited as expert guidance only.
- Supreme Court of India. State of Himachal Pradesh v. Yogendera Mohan Sengupta, C.A. Nos. 5348–5349 of 2019 with T.C.(C) No. 2 of 2023, 2024 INSC 30, judgment of 11 January 2024.
- Supreme Court of India. In Re: Issues Relating to Ecology and Environmental Conditions Prevailing in the State of Himachal Pradesh, W.P.(C) No. 758 of 2025 (orders and the Central Empowered Committee's report known from the press).
- High Court of Himachal Pradesh. Madan Lal v. State of Himachal Pradesh, CWPIL No. 31 of 2023, order of 31 May 2024; Fourlane Visthapit and Prabhavit Samiti v. State of Himachal Pradesh, CWP No. 5243 of 2022, order of 26 June 2023.
- National Green Tribunal. O.A. No. 726 of 2023 (monsoon disaster of 2023), reply of HPSPCB of 20 February 2024; O.A. No. 735 of 2023 (Ashwani Khad), affidavits of the Chief Secretary (2024; 1 February 2026) and CPCB interim report of 6 May 2024; O.A. No. 673 of 2018 (polluted river stretches). https://www.greentribunal.gov.in/
- HIMCOSTE-led State technical committee (2023). Report on the landslides in Shimla, monsoon 2023 (HPSDMA, document 3578).
- Indian Roads Congress (2014). IRC:SP:42-2014, Guidelines on Road Drainage, §8.5.1 (hill roads). https://law.resource.org/pub/in/bis/irc/irc.gov.in.sp.042.2014.pdf
- NITI Aayog, DMEO (2020). Best practice note: Swan River Flood Management Project, Una.
- South Asia Network on Dams, Rivers and People (2022–2025). Posts on CWC flood monitoring sites in north India, rivers breaching their high flood levels in July 2023, and the Pong and Bhakra reservoirs (transcriptions of CWC and BBMB data). https://sandrp.in/
- The Tribune, Down To Earth, The Indian Express, thenewshimachal.com, ThePrint, PTI and ANI (2019–2026). Reports of the pre-monsoon directions on drain cleaning, the floods of 2023–2025, the releases from Pong, Bhakra and Pandoh, Malana II, the 2025 setback announcements and rural model bye-laws, the CAG's SDRF findings and the Parbati II tunnel failure (secondary sources). https://www.tribuneindia.com/news/himachal/cag-flags-misuse-of-disaster-relief-fund-in-five-himachal-districts ; https://www.tribuneindia.com/news/himachal/no-govt-institution-to-be-built-within-150-metres-of-rivers-cm ; https://thenewshimachal.com/?p=62926
Annexes and forms
| Annex / Form | Content |
|---|---|
| 10A | Compliance calculator and user guide |
| 10B | GIS data specification and attribute schema |
| 10C | Maintenance access dimensions |
| 10D | Model O&M plans by facility type |
| 10E | Empanelment criteria for Stormwater Design Professionals and reviewers |
| Form 10-1 | Drainage Report Checklist |
| Form 10-2 | Compliance Calculator Summary |
| Form 10-3 | Professional Design Certificate |
| Form 10-4 | Hold-Point Inspection Record |
| Form 10-5 | As-built Certificate |
| Form 10-6 | Maintenance Declaration |
| Form 10-7 | Annual Maintenance Declaration and Inspection Report |
| Form 10-8 | Asset Handover Certificate |
| Form 2-1 | Design Rainfall Sheet (Chapter 2) |
Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Himachal Pradesh the failure is one of missing criteria and of drains that have not kept up with the towns. No document of the TCP Department, the Urban Development Department, a Municipal Corporation or the Jal Shakti Vibhag stating a design return period, intensity or runoff coefficient for the storm drains of any town was found, and in 2017 Shimla's drains were found to cover about 30% of the city and to be unable to carry the peak flow (Chapter 11). The approval route shapes this chapter. In the 54 ULBs and about 102 other notified areas where the Himachal Pradesh Town and Country Planning Act 1977 operates, which hold about 21.7% of the State's people but less than 10% of its area (PDNA, 2023), building needs planning permission under the TCP Rules 2014 (read here as consolidated to 2022; later amendments up to the Twelfth of 2024 and a draft Sixteenth of 2025 are known only from the press and were not read). The Rules already ask for much of what a drainage submittal needs: a site plan showing "Existing water bodies like Bauri, Well, Nallah, khud", contours, and the septic tank, soak pit and rainwater-harvesting tank; a soil investigation report by a geologist before building in the sliding and sinking zones of a development plan (Rule 21(1); for Shimla, §17.2.2.9 of the Development Plan); roof-top rainwater storage of 20 litres per m² of roof, compulsory for existing and new buildings, without which no water connection is given (Appendix 6); and, where no interim or final development plan exists, a slope of not more than 45°, a hill cut of not more than 3.50 m, construction at 3.00 m from a nullah and 5.00 m from a khud, and sub-divisions laid out for the "natural flow of surface drainage" (Appendix-1, cls. 3, 11, 16 and 20). In planning areas the distance from the high flood level along rivers, khuds and nullahs is as the development plan delineates it, and elsewhere no construction is allowed on land "prone to floods" (Appendices 3 and 7). In the Shimla Planning Area the Shimla Development Plan 2041 governs, published on 20 June 2023 according to the Supreme Court (the press gives 23 June), whose storm-water chapter was not read [TBC]. HIMUDA approves the plans of its colonies without the ULBs, and HPSIDC plans its industrial areas (CAG, Report No. 1 of 2022). Outside these areas, which cover more than 90% of the State, model bye-laws for rural construction approved by the cabinet in September 2025 are reported to send plans to panchayat technical assistants and the Gram Sabha, with TCP approval above 1,000 m² (as reported; text not read). There is no floodplain zoning law, and the PDNA of 2023 asks for river-boundary mapping and floodplain guidelines. The ULBs run their drains under the Himachal Pradesh Municipal Corporation Act 1994 and the Himachal Pradesh Municipal Act 1994, whose drain sections were not read [TBC]. No rule asks for a drainage report, limits peak runoff, requires on-site detention or sets a "zero runoff" condition. Every stormwater item in this chapter is therefore written so that the architect or engineer on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it with the application for planning permission, alongside the site plan and the rainwater-harvesting tank that the TCP Rules already require; in a sliding or sinking zone with the geologist's report, which shall then also confirm that no runoff is put into the ground (Clause 8.8.1); at the water connection, which waits for the roof-top storage; and at completion. This chapter is the process.