Draft v1.0 prepared by NEER. Not adopted by the Government of Manipur, any District Council, authority or local body, and has no legal force. About this draft

Annexes to Chapter 5Downstream and Tailwater Analysis

These annexes support Chapter 5. Annex 5C is a worked example of the outfall-closed check of Clause 5.10, for the illustrative facility of Annex 4C. Annexes 5A and 5B need tidal, surge, survey and river data that this draft does not yet contain; each lists what the chapter already sets, gives the intended layout and states the interim rule of Chapter 5 that applies until it is published. Forms 5-1 and 5-2 are the submittal forms required by Clause 5.14. They are draft forms and have no statutory status.


Annex 5A — Tidal datums (MSL, MHWS, HAT vs CD and Survey of India datum), surge allowances and 1% still-water levels by coastal segment

Supports Clauses 5.7, 5.9, 5.10, 5.11 and 5.12 of Chapter 5.

5A.1 Table 5A.1 shows how the values of this annex enter the design tailwater levels of Table 5.1. The sea-level allowance is set by Clause 5.7.4 and does not depend on this annex.

Table 5A.1 — Use of the Annex 5A values in the design tailwater (Table 5.1)

Design case Tailwater Annex 5A values used Chapter value
Minor-system design MHWS + SLA MHWS SLA ≥ +0.3 m (Clause 5.7.4)
Major-system and storage design HAT + surge + SLA HAT; 10% AEP surge (Clause 5.7.3(a)) SLA ≥ +0.3 m
Joint case (Clause 2.12(b)) 1% AEP still-water level + SLA 1% AEP still-water level (Clause 5.7.3(b)) SLA ≥ +0.3 m
Datum conversion Chart datum to project datum Offset from chart datum to the Survey of India datum (Clause 5.7.2(b)) —

Not prepared for Manipur. Manipur has no coast, so no outfall in the State has a tidal tailwater, and this annex has no Manipur content (Clause 5.1.4). Its tables are kept, empty, so that the annex and table numbers match the other editions of this Manual. Rows F1 to F7 of Form 5-1 are entered as "not applicable", and the tailwater is derived under rows F8 to F10; for a bund-locked outfall, row F10 records the gate, the WRD gauge and its datum, the design and check levels, the lock and the pump-down of Clause 5.8.5(a); for an outfall on the Loktak margin, the design lake level and the closure of Clause 5.8.5(c); and for an outfall to a pat, pukhri or pond, its starting level and surveyed stage–storage relation under Clause 5.8.5(e).

Table 5A.2 — Tidal datums, surge and still-water levels by coastal segment (layout)

Coastal segment Reference port and tide-table edition MSL (m CD) MHWS (m CD) HAT (m CD) CD to Survey of India datum (m) 10% AEP surge (m) 1% AEP still-water level (m CD) Wave set-up (m), open-sea outfalls Sources
                   
                   
                   

Annex 5B — Major drains, riverine outfall reaches, and river mouths subject to sand-bar closure; map

Supports Clauses 5.2, 5.3, 5.8 and 5.13 of Chapter 5.

5B.1 Table 5B.1 lists the water bodies that Chapter 5 already names. It is not complete: the annex will add the extents of each reach, the other rivers, canals and mouths of the State, and a map.

Table 5B.1 — Water bodies named in Chapter 5

Water body Region Listed as Clause
Imphal river at Minuthong and Lilong Imphal valley floor (Greater Imphal and below) Riverine outfall reach through WRD bund gates; WRD levels as reported, datum [TBC]: Minuthong WL 785.900, FL 786.900, HFL 788.400 m (above HFL on 29 May 2024); Lilong WL 780.350, FL 781.350 m (2025) or 781.250 m (2024), the higher applies, HFL 782.850 m, exceeded at 783.250 m on 15 September 2025; design at FL, check at the HFL or the highest reading above it; lock the 72-hour storm and while the river stays above the sill, not less than 7 days without a stage record; bye-law 93 buffer of the Model [TBC: confirm the number and text in the bye-laws the local body has notified] 55, 60 and 62 m by reach 5.8.1, 5.8.5
Nambul at Thong Nambonbi (Hump Bridge), with the Naga Nullah and the Waisel Maril Greater Imphal Riverine outfall reach and major drains; HFL 783.695 m (WRD, as reported; no FL printed), above it on 29 May 2024; breached at four places in 2025 (as reported); 72 drains that carry sewage, intercepted and diverted (State report, December 2025); city channels with no single owner; bye-law 93 buffer 30 m within Greater Imphal 5.2, 5.8.1, 5.8.5
Lamphelpat and the Shamushang nallah Greater Imphal (Lamphel) Receiving storage: a pat being developed as flood storage, about 300 acres dredged from November 2023, pumped to the Nambul through the Shamushang nallah in high floods (WRD site report, 2025); starts full; stage–storage and pump capacity [TBC]; counted when complete and confirmed by WRD; proposed drinking-water source, interception before it 5.8.5
Iril at Irilbung, and the Kongba Imphal East Riverine outfall reaches; Irilbung WL 786.700, FL 787.700 m, printed HFL 782.200 m (an error, not used), 788.850 m on 15 September 2025 (as reported); breach at Kshetri Awang Leikai (September 2025, as reported); Kongba level [TBC]; bye-law 93 buffers 50 m (Iril) and 35 m (Kongba, from mid-stream) 5.8.1, 5.8.5
Thoubal, Sekmai, Wangjing, Nambol, Khuga, Merakhong and Arong Imphal valley floor Riverine outfall reaches; Thoubal WL 778.915, FL 779.915 m (gauge not named); Nambol at Nambol Thongkhong HFL 774.700 m (2024) or 774.400 m (2025), the higher applies; others [TBC]; ungauged rule of Clause 5.8.5(a); lock not less than 7 days without a stage record 5.8.1, 5.8.5
Loktak and the Manipur river at the Ithai barrage, with the Sugnu hump and the Chakpi Loktak margin (MN-A1) Lake tailwater; Ithai HFL 769.320 m, 770.05 m on 15 September 2025 (WRD, as reported); FRL 768.5 m and MDDL 766.2 m (NHPC, as quoted), MDDL 766.01 m (CEA, as quoted), FRL 769.63 m (ORF, as reported) — conflict; design 769.320 m, check 770.05 m, not below the FRL in June–September; outfalls below the design level closed 1 June–30 September; rock sill at 763.7 m below the barrage; Chakpi backwater to Sugnu and Wangoo; phumdi screens; Loktak Act zones (Core 70.30 km², 236.21 km² in all) 5.8.1, 5.8.5
Thoubal below the Mapithel dam; Khuga below its dam; Nambul below the Singda dam Imphal valley Release reaches; Mapithel FRL 880.7 m (WRD, 2025, as reported), 876 m "nearly 2 m above the spillways" on 1 August 2015 (as reported) — conflict; spillway 2,240 m³/s (as reported); Khuga and Singda levels and releases [TBC]; release before, during and after the storm; lock not less than 72 hours 5.8.3, 5.8.5
Mapithel (Thoubal Multipurpose Project), Khuga and Singda dams; the Ithai barrage (NHPC) Upstream of the valley's reaches; outlet of Loktak Releases and gate operation to be included in river levels (operating rules and release records [TBC]); no credit for warnings, drawdown, attenuation or early barrage opening 5.8.3, 5.8.5
Pats and pukhris that receive town drains, among them Porompat, Takyelpat, Sangaipat, Kharungpat, Ikop pat, Utra, Yaral, Waithou–Phumnom, Pumlen–Khoidum and Ikop–Kharung pats, and the public pukhris of the towns Imphal valley Receiving storage; full to the outlet at the start; surveyed stage–storage [TBC]; storage belongs to the system; interception and screens before any outfall that carries sewage; Yaral, Utra and Waithou–Phumnom pats in draft notification under the Wetlands Rules, 2017 5.8.5
Khongs and hill streams of Tamenglong, Noney, Ukhrul, Senapati, Kangpokpi, Chandel and Churachandpur, of the valley rim, and of the Makru, Irang, Leimatak and Tuivai catchments Hill sub-areas MN-B and MN-C Hill streams; ungauged; 1% AEP study with bulking and blockage and surveyed flood marks; invert at least 0.5 m above the highest surveyed bed; silt trap where they reach the valley floor; lock not less than 24 hours 5.2, 5.8.1, 5.8.5
Barak at Chotebekra, and the Jiri Jiribam plain (MN-C1) Riverine outfall reaches; Chotebekra HFL 32.1 m (31 July 1989; SANDRP, as reported), danger level 26.2 m (press only, as reported), datum [TBC]; the Barak-valley lock, not less than 7 days without a stage record; the Assam edition governs the reaches downstream 5.8.1, 5.8.5
Drains of IMC, the Municipal Councils and Nagar Panchayats, PDA Manipur, PWD and the national-highway agencies 1.0 m wide or more; WRD's city and flood channels; DoECC's interception works on the Nambul Manipur Major drains; WRD permission through a bund; owner's consent, design water level and flap gate 5.2, 5.8.5
River mouths subject to sand-bar closure None in Manipur Not applicable (Clause 5.1.4) 5.13.1

To be prepared. This annex will list and map (a) the major drains of each basin plan, (b) the riverine outfall reaches where backwater shall be modelled, with their upstream and downstream limits and the source of their design flood levels, and (c) the river mouths and creek inlets subject to seasonal sand-bar closure, with the most recent pre-monsoon bar crest levels and any WRD mouth-maintenance programme. It needs WRD river and canal records, design and recorded flood levels, reservoir operating rules, mouth-condition, dredging and bar-cutting records and pre-monsoon bar surveys (WRD), the drain inventories of IMC and other local bodies, basin stormwater master plans (Chapter 11), and base mapping from the Survey of India and NRSC. Until it is published: every river, WRD canal, the Naga Nullah, the Waisel Maril and the Shamushang nallah in Imphal, every city channel and flood channel of WRD and every drain that discharges through a gate or flap gate in a river bund, any drain built or held by IMC, a Municipal Council, a Nagar Panchayat, PDA Manipur, PWD or a national-highway agency with an internal width of 1.0 m or more, and every khong or other natural channel that drains 8 ha or more and every tidal creek is a major drain (Clause 5.2); the water bodies of Table 5B.1 are riverine outfall reaches (Clause 5.8.1); and the mouths of the coastal States' rivers (there is none in Manipur) are assumed closed at the start of the monsoon unless the Water Resources Department certifies otherwise (Clause 5.13.2).

Table 5B.2 — Attributes of the Annex 5B layers (layout)

Field Content Unit or format
feature_id Unique identifier text
name Name of the drain, river, canal, creek or mouth text
category Major drain; riverine outfall reach; mouth subject to sand-bar closure text
clause Clause of Chapter 5 under which it is listed text
reach_limits Upstream and downstream limits of the reach text
design_flood_level_source WRD design or highest recorded flood level, or hydraulic model (Clause 5.8.2) text
reservoir_release Upstream reservoir or tank and its operating rule, where any (Clause 5.8.3) text
bar_crest_level Most recent pre-monsoon bar crest level, for mouths m (Survey of India datum)
mouth_programme WRD mouth-maintenance programme and certification (Clause 5.13.2) text
source Source agency and date text
geometry Line (drains and reaches) or point (mouths) line / point

Annex 5C — Worked example: outfall-closed check for a hill-fringe colony in Jiribam town draining to a stream of the Jiri

Supports Clauses 5.9, 5.10, 5.11 and 5.12 of Chapter 5 and Clause 4.6.6 of Chapter 4.

Illustrative — not design values. This example applies the outfall-closed check of Clause 5.10 to the revised detention facility of Annex 4C. The site, its levels and its receiving drain are invented to show the method. No tidal level is used: the tide enters only through the illustrative statements in Table 5C.1 about whether the receiving drain is above or below the site outlet.

Inputs

5C.1 The site is the 2.0 ha flood-sensitive site of Annex 4C, on the hill fringe of Jiribam town. It discharges through its own outlet chamber and a flap gate to a public storm drain that joins a stream of the Jiri, whose level rises when the stream comes down from the hills in spate and stays up while the Jiri and the Barak below it are in flood, so Clause 5.10.1 applies to the facility. To show the method, this example uses the two 6-hour lock windows of Clause 5.10.3, as the coastal editions of this Manual do. In Manipur an outfall to a hill stream whose invert is below its design level is closed for the storm and the stream's recession, and for not less than 24 hours; where the Barak backs the stream up, as it can on the Jiribam plain, the outfall is closed for the whole 72-hour storm and for as long as the river stays above the sill, not less than 7 days where no stage record has been analysed, and its stored volume is pumped down within 48 hours with the gate still shut; a bund-locked outfall on the Imphal valley floor is closed in the same way, and an outfall below the design level of Loktak is closed from 1 June to 30 September; an outfall to a release reach is closed for not less than 72 hours; and an outfall below the design level of a full pat, pukhri or pond is closed for the whole storm, under Clause 5.8.5. In each of those cases the facility must store or pump the volume of the longer closure, up to the whole storm volume (Clause 5.9.4); that needs more storage, or pumping, than this example shows. The routing, the volume balance of Clause 5.10.4 and the assessment are the same. The public drain's own outfall to the stream would also need the debris rack, the bulking factor and the silt trap of Clause 6.3.6 and an invert above the range of bed movement of Clause 5.8.5(f); and on a natural slope of more than 10°, or on Disang shale at any slope, the facility itself would be a lined tank, not an infiltrating basin (Clause 4.11 (hill rule)).

Table 5C.1 — Inputs (Illustrative — not design values)

Item Value Basis
Facility Revised facility of Annex 4C: 2,500 m² plan area, vertical walls; 170 mm orifice at the floor; 460 mm orifice, invert 0.53 m Annex 4C, Table 4C.14
Storm 1% AEP, 48 h, peak day last, AMC III; 72 h also run Clause 5.10.2
Inflow Post-development 1% AEP hydrographs of Annex 4C (48 h: 8,420 m³; 72 h: 9,468 m³) Annex 4C
Receiving drain levels at the connection, J1, J2 and J3 Below the site outlet invert (from the drain owner's model) Illustrative input
Receiving drain during each lock window Backs up above the site outlet invert, so the site cannot discharge Illustrative input; Clause 5.10.3(b)
Flap gate on the site outlet Set 0.15 m below the orifice inverts in the outlet chamber, so that outside the lock windows its opening head and head loss do not affect the orifice control Illustrative input; to be confirmed from the certified curve (Clause 5.11.2)
Lock windows Two of 6 h each, starts 12.4 h apart (semi-diurnal tide) Clause 5.10.3(a)
Pumps None —

5C.2 Cases of Table 5.2. Because the receiving drain stays below the site outlet in J1, J2 and J3 (Table 5C.1), those cases give the free-outfall results of Annex 4C: in J2 the 1% AEP maximum water level is 1.17 m (2,913 m³), and in J3 (10% AEP, 48 h) it is 0.77 m. R1 and R2 do not apply, because the site does not drain to a river. J4, the outfall-closed check, is worked below.

Lock windows (Clause 5.10.3)

5C.3 The peak 1-hour block of the final 24 hours of the 48-hour storm is 35:35–36:35 h, with 98.2 mm (the 1-hour depth of Table 4C.2). Two runs are made:

  • Run A: the first window is centred on that block: 33:05–39:05 h; the second starts 12.4 h later: 45:29–51:29 h.
  • Run B: the first window starts at that block: 35:35–41:35 h; the second: 47:59–53:59 h.

For the 72-hour storm, every time is 24 h later.

5C.4 Gravity discharge is zero inside each window. Outside the windows the outlet discharges through the orifices of Table 4C.10. The routing is the same level-pool routing as in Annex 4C.

Results

Table 5C.2 — Outfall-closed check results (Illustrative — not design values)

Storm Run Lock windows (h:min) Maximum stage (m) Maximum storage (m³) Time of maximum (h:min) Largest release after a window (L/s)
1% AEP, 48 h A 33:05–39:05; 45:29–51:29 2.01 5,019 39:05 566
1% AEP, 48 h B 35:35–41:35; 47:59–53:59 2.10 5,238 41:35 584
1% AEP, 72 h A 57:05–63:05; 69:29–75:29 2.00 5,012 63:05 565
1% AEP, 72 h B 59:35–65:35; 71:59–77:59 2.09 5,233 65:35 584

Run B of the 48-hour storm governs. The first window closes the outlet just as the storm peak arrives, so the whole peak is stored. The second window arrives when the facility has drained to about 0.7 m, below the Stage 2 orifice, and adds little.

5C.5 Volume balance (Clause 5.10.4). Table 5C.3 gives the balance for Run B. The outflow in each period is found by continuity: outflow = storage at start + inflow − storage at end.

Table 5C.3 — Volume balance, 1% AEP 48-hour storm, Run B (Illustrative — not design values)

Period (h:min) Inflow (m³) Gravity outflow (m³) Pumped (m³) Storage at start (m³) Storage at end (m³)
0:00–35:35, before window 1 3,817 2,213 0 0 1,604
35:35–41:35, window 1 3,634 0 0 1,604 5,238
41:35–47:59, between windows 941 4,423 0 5,238 1,756
47:59–53:59, window 2 28 0 0 1,756 1,784
After 53:59 0 1,784 0 1,784 0
Total 8,420 8,420 0 — —

Check for window 1: V_inflow = 3,634 m³ ≤ V_storage available + V_pumped + V_gravity = (5,238 − 1,604) + 0 + 0 = 3,634 m³. The facility therefore needs 5,238 m³ of storage, which the routing confirms.

Table 5C.4 — Stage hydrograph, 1% AEP 48-hour storm, Run B (Illustrative — not design values)

Time (h) Inflow (L/s) Outlet Outflow (L/s) Stage (m) Storage (m³)
24 20 Open 18 0.18 445
28 39 Open 24 0.25 621
32 59 Open 32 0.36 906
34 85 Open 37 0.47 1,166
36 286 Closed 0 0.78 1,944
38 106 Closed 0 1.73 4,321
40 66 Closed 0 1.96 4,904
42 51 Open 529 1.79 4,472
44 42 Open 204 0.87 2,181
46 37 Open 49 0.74 1,854
48 33 Open 47 0.70 1,756
50 0 Closed 0 0.71 1,784
54 0 Closed 0 0.71 1,784
56 0 Open 43 0.58 1,459
60 0 Open 32 0.37 921
66 0 Open 16 0.16 397
72 0 Open 7 0.06 162

Assessment

5C.6 Clause 5.10.4(a). The facility of Annex 4C reaches 1.17 m in J2, and its spillway crest is at 1.35 m (Annex 4C). In the outfall-closed check the stage reaches 2.10 m, so the spillway would operate. The facility of Annex 4C fails the check.

5C.7 Remedy. Pumping (Clause 5.12) does not help here: during the lock windows the receiving drain is itself closed, and pumping into it would raise its level, which Clause 5.12.3 does not permit. The remedy is more storage. Keeping the plan area of 2,500 m² and the outlets of Annex 4C:

  • the facility must hold 5,238 m³, to a stage of 2.10 m;
  • the spillway crest is set above that stage, with the 0.15 m clearance recommended in Clause 4.9.3: 2.25 m;
  • with the 4.0 m spillway of Annex 4C (head 0.30 m), the maximum level with the spillway flowing is 2.55 m, and with 0.3 m freeboard the top of the walls is at least 2.85 m above the floor.

The outfall-closed check therefore governs the storage: 5,238 m³ against 2,913 m³ from the release-rate checks, about 80% more. A larger plan area would make the facility shallower; the outlet, caps and drawdown would then have to be re-checked, because the stage–discharge relationship changes.

5C.8 Release after the lock. When the first window ends, the stored water is released under a head of about 2 m, at up to 584 L/s. This is above the 100-yr cap of 356 L/s. Clause 5.10.4 allows this, because the release reaches a drain that has itself just reopened, and requires it to be included in the J4 run of the downstream analysis (Clauses 5.4 and 5.9) and reported on Form 5-1, Section H.

5C.9 Drawdown after the storm (Clause 5.10.5). The J1 tidal curve stays below the site outlet (Table 5C.1), so the drawdown of Annex 4C applies: 45.3 h for 90% of the 10-yr storage with the low-flow orifice 50% blocked, within the 48-hour limit of Clause 4.7. In Run B, 90% of the maximum J4 storage is released 22.6 h after the maximum.

5C.10 Other requirements.

  • The flap gate on the site outlet is inspected and operated before 31 March each year and after every event in which it closed against a storm flow (Clause 5.11.5).
  • The deeper facility is checked for flotation with groundwater at the design groundwater level; in the Imphal valley floor, with its lacustrine clays, peat and paddy land, the margins of Loktak and the other pats and pukhris, the land behind river bunds, and the Barak and Jiri flood plain of the Jiribam plain without piezometer readings that level is existing ground level (Clauses 4.12.1 and 4.12.3).
  • The fence and signs of Annex 4C apply to the deeper facility (Clause 4.15).

Table 5C.5 — Summary (Illustrative — not design values)

Item Value
Governing case J4, 1% AEP 48-hour storm, Run B (first window starting at the peak 1-hour block)
Storage required 5,238 m³ (Annex 4C release-rate design: 2,913 m³)
Maximum stage 2.10 m, with 2,500 m² plan area
Spillway crest 2.25 m
Top of walls ≥ 2.85 m above the floor
Largest release after a lock window 584 L/s, to be included in the downstream J4 run
Drawdown Annex 4C result applies: 45.3 h with the low-flow orifice 50% blocked

Form 5-1 — Downstream and Tailwater Report

Supports Clauses 5.3 to 5.14 of Chapter 5.

Draft form — Manipur Stormwater Design Manual, Draft v1.0. One report for each project. Sites of less than 0.5 ha that meet Clause 5.3.4 may submit Form 5-2 instead, where the Authority accepts it. Attach the plans, model files and hydrographs referred to.

A. Project

Table 5F.1 — Form 5-1: project

Field Entry
A1. Project name, applicant and location  
A2. Project type: site under Chapter 4; drainage project under Chapter 6; regional detention or tank restoration (Clause 5.1.2)  
A3. Site or project area (ha) and outfalls  
A4. Site Runoff Control Report reference (Form 4-1), where applicable  

B. Extent of the analysis (Clause 5.3; Clause 5.14, item 1)

Table 5F.2 — Form 5-1: analysis points

Point Location Type (Clause 5.3.3 (a) to (e)) Contributing catchment (ha) Project area as % of it
         
         
         

Table 5F.3 — Form 5-1: end point

Field Entry
B1. End point and reason: 10% point, tank or pukhri, or major drain or the sea (Clause 5.3.1 (a) to (c))  
B2. Where the end point is a tank or pukhri: change in maximum water level (m) and in surplus-weir discharge (m³/s); continuation below the weir if the level rises (Clause 5.3.2)  
B3. Plan of the analysis extent, showing the site, each point with its contributing area and percentage, and the end point (attach)  

C. Model (Clause 5.4.4; Clause 5.14, item 2)

Table 5F.4 — Form 5-1: model

Field Entry
C1. Software and version; hydrologic and hydraulic methods (Clause 5.4.4)  
C2. Network schematic, with the survey sources for drains and crossings (attach)  
C3. Land use and CN of off-site areas (present land use)  
C4. Upstream detention included, with evidence that it is built, maintained and documented  
C5. Calibration or validation evidence, where available  
C6. Scenarios run: existing, with project, and future where the Authority requires it (Clause 5.4.1)  
C7. Storms run: AEPs and durations, AMC and areal reduction (Clause 5.4.3)  

D. Results at each analysis point (Clause 5.4.2; Clause 5.14, item 3)

Complete one row for each analysis point, AEP and duration. E = existing; P = with project.

Table 5F.5 — Form 5-1: results by analysis point

Point AEP Duration (h) Peak flow E / P (m³/s) Time to peak E / P (h) Maximum water level E / P (m) Peak velocity E / P (m/s) Duration of inundation E / P (h)
               
               
               

E. Acceptance (Clause 5.5; Clause 5.14, item 4)

Table 5F.6 — Form 5-1: acceptance criteria

Criterion Met at every point? Where not met, the remedy adopted (Clause 5.5.3)
E1. 1% AEP water level rise ≤ 10 mm at buildings, lowest openings and carriageways (Clause 5.5.1(a))    
E2. No building newly flooded; no building or road newly failing the Chapter 6 limits (Clause 5.5.1(b))    
E3. Peak flow not above existing at the minor-system AEP of each element or at 1% AEP (Clause 5.5.1(c))    
E4. Velocity in lined channels within the lining limit, 3.0 m/s maximum (Clause 5.5.1(d))    
E5. Velocity in unlined channels, 50% and 10% AEP, not increased by more than 10% (Clause 5.5.1(e))    
E6. Change in duration of road closure on arterial or emergency routes (Clause 5.5.2)    
E7. Timing exception requested (Clause 5.5.4)? Give the conditions met    

F. Tailwater derivation (Clauses 5.6 to 5.8; Clause 5.14, item 5)

Table 5F.7 — Form 5-1: tailwater derivation

Field Entry
F1. Tide-table edition and port, or port authority source (Clause 5.7.2(a))  
F2. MHWS, HAT and MSL (m above chart datum)  
F3. Connection from chart datum to the Survey of India benchmark and the project datum: offset (m) and source (Clause 5.7.2(b))  
F4. Estuary, creek or canal outfall: levels used and any evidence for a departure from open-coast levels (Clause 5.7.2(c))  
F5. 10% AEP surge and 1% AEP still-water level: values, source, method and record length (Clause 5.7.3)  
F6. Wave set-up, for outfalls facing the open sea (Clause 5.7.3(d))  
F7. SLA (m), at least +0.3 m; design life; sensitivity run at twice the SLA for design lives over 50 years (Clause 5.7.4)  
F8. Non-tidal tailwater: receiving-system level and source (Clauses 5.6.2, 5.6.3)  
F9. River levels and sources; reservoir or tank releases included (Clauses 5.8.2, 5.8.3)  
F10. Bund-locked valley outfalls, Imphal, the Loktak margin, release reaches, pats and pukhris, hill streams, Jiribam and the Barak, and drains of other bodies: for a bund-locked outfall, the operator of each gate, flap gate and pumping station identified (WRD or the local body), gate sills, bund crest, installed permanent capacity, duty point, sump levels and gate-closing level obtained, with every level tied to a Survey of India benchmark and to the WRD gauge named; the WRD levels used (WL, FL, HFL and the highest reading above the HFL) with their source and the datum confirmed or flagged; the design level (the WRD flood level, the higher printed value where two are printed, e.g. Lilong 781.350 m; the HFL where no flood level is printed, e.g. Hump Bridge 783.695 m, Nambol Thongkhong 774.700 m), the check level (the HFL or the highest reading above it, e.g. Minuthong 788.400 m, Lilong 783.250 m, Irilbung 788.850 m), and the 10% AEP case at the warning level, each transferred to the outfall with the method stated; for an ungauged river or stream, the flood marks of 2024 and 2025 surveyed, or a model; the drain behind the gate routed with its whole catchment, the pats, pukhris and paddy land it fills and its present storage, starting full to its outlet, pumping confirmed available (permanent pumps only, not more than installed capacity less the largest pump), pumps operable at the check level; the lock (the whole 72-hour storm and while the river stays above the sill, from the WRD stage record used, or not less than 7 days on the Imphal, Nambul, Iril, Kongba, Thoubal, Sekmai, Wangjing, Nambol, Khuga and Manipur rivers and 72 hours on a smaller stream) and the pump-down to the starting level within 48 hours with the gate shut; the joint drain–pump–river analysis for the two valley cases; the gate-failure and breach checks reported; for Imphal, the governing gauge (Minuthong, Lilong, Hump Bridge or Irilbung), the channel (the Naga Nullah, the Waisel Maril or another) and its present section, and for Lamphelpat the pat level starting full, the Shamushang pumps confirmed by WRD and the Nambul level at the Shamushang outfall, with the NDB works counted only once complete and confirmed; for the Loktak margin, the design lake level (Ithai HFL 769.320 m, checked at 770.05 m, not below the FRL in June–September) with the FRL conflict recorded, the closure from 1 June to 30 September of an outfall below it, the Chakpi level at Sugnu and Wangoo, the phumdi screen, and LDA's prior permission; for a release reach, the operator's consent, levels in writing (feet converted at 1 ft = 0.3048 m, datum stated), the largest recorded release or the spillway capacity (Mapithel 2,240 m³/s, as reported), placed before, during and after the storm, and a lock of not less than 72 hours, with no warning, drawdown or attenuation credited; for a pat, pukhri or pond, its outlet level, surveyed monsoon water line, surveyed stage–storage relation, starting level and design level, and the interception and screens before it; for a hill stream, the 1% AEP study with the rainfall of its sub-area, the bulking and blockage of Clause 6.3.6, the surveyed flood marks and their sources, the bed survey and range of bed movement, the invert at least 0.5 m above the highest surveyed bed level, the scour depth of the foundation, the silt trap where the stream reaches the valley floor, and a lock of not less than 24 hours; for Jiribam, the Barak level (not below Chotebekra's 32.1 m, transferred; 10% AEP case not below 26.2 m) with its datum flagged, the Jiri level, and the Barak-valley lock; WRD's written permission for any work through a bund; owner's consent (IMC or the local body, PWD, a national-highway agency, DoECC or WRD), permitted rate, design water level or computed channel level, and flap gate; and the bye-law 93 buffers, the corridor of Clause 7.4, the bye-law 94 plinth, the Loktak Act zones, the paddy-land conversion approval and the status of any wetland notification checked (Clause 5.8.5)  

G. Joint cases (Clause 5.9; Clause 5.14, item 6)

Table 5F.8 — Form 5-1: joint-case results

Case Rainfall Tailwater used (m, project datum) Applies? Governing result (storage, level, pipe size or pump capacity)
J1        
J2        
J3        
J4        
R1        
R2        

H. Outfall-closed check (Clause 5.10; Clause 5.14, item 7)

Table 5F.9 — Form 5-1: outfall-closed check

Field Entry
H1. Reason the check applies (Clause 5.10.1)  
H2. Storm: AEP, 48 h and 72 h, AMC III (Clause 5.10.2)  
H3. Lock duration and basis: default of two 6-hour windows, or site study (Clause 5.10.6); extension for sand-bar closure (Clause 5.13.5)  
H4. Lock windows of the two runs (start and end times) (Clause 5.10.3(d))  
H5. Maximum stage in each facility, against its 1% AEP maximum water level (Clause 5.10.4(a))  
H6. Maximum stage in the minor and major systems, against the Chapter 6 limits (Clause 5.10.4(b))  
H7. Property connections: surcharge level, or non-return valves fitted (Clause 5.10.4(c))  
H8. Stage hydrographs (attach)  
H9. Drawdown after the storm under the J1 tidal curve, and pumping where needed (Clause 5.10.5)  

Table 5F.10 — Form 5-1: volume balance for each lock window (Clause 5.10.4)

Period Inflow (m³) Gravity outflow (m³) Pumped (m³) Storage at start (m³) Storage at end (m³)
Before window 1          
Window 1          
Between windows          
Window 2          
After window 2          

I. Gates and valves (Clause 5.11; Clause 5.14, item 8)

Table 5F.11 — Form 5-1: schedule of flap gates, tide gates and non-return valves

Location Type Size (mm) Invert (m, project datum) Certified head–discharge data (reference) Stop-log or penstock (outfalls > 600 mm)
           
           

J. Pumped outfalls (Clause 5.12; Clause 5.14, item 9)

Table 5F.12 — Form 5-1: pumped outfalls

Field Entry
J1. Reason pumping is needed (Clause 5.12.1)  
J2. Duty capacity (m³/s) at the static head for the J2 tailwater; standby capacity (Clause 5.12.2)  
J3. Effect on the receiving water level (Clause 5.12.3)  
J4. Power supply: two independent supplies, or standby generation with 72 h of fuel; automatic changeover (Clause 5.12.4)  
J5. Level of electrical panels, controls, generators and fuel, against the higher of the 1% AEP flood level + 0.5 m and HAT + surge + SLA + 0.5 m (Clause 5.12.5)  
J6. Discharge arrangement (Clause 5.12.6); controls, alarms and logging (Clause 5.12.7); screens (Clause 5.12.8)  

K. Sand bar (Clause 5.13; Clause 5.14, item 10)

Table 5F.13 — Form 5-1: sand-bar assumption

Field Entry
K1. River mouth or creek inlet concerned  
K2. Mouth assumed closed, or open with WRD certification attached (Clause 5.13.2)  
K3. Bar crest level from the most recent pre-monsoon survey (m) and the closed-mouth tailwater (Clause 5.13.3)  
K4. Extension of the lock duration, where required (Clause 5.13.5)  

L. Inspection and maintenance (Clause 5.14, item 11)

Table 5F.14 — Form 5-1: inspection and maintenance

Field Entry
L1. Gate and valve inspection before 31 March and after closure events (Clause 5.11.5)  
L2. Pump test runs before 31 March (Clause 5.12.9)  
L3. Other requirements for the maintenance plan (Chapter 10)  

M. Statement by the registered professional (Clause 10.6)

I state that this report has been prepared under Chapter 5 of the Manipur Stormwater Design Manual (Draft v1.0), that the results reported are reproduced by the models submitted, and that every departure from Chapter 5 is listed with its reason. The Professional Design Certificate (Form 10-3) is attached.

Table 5F.15 — Form 5-1: statement by the registered professional

Field Entry
Name  
Qualification and registration number  
Empanelment number, where Clause 10.6.1 requires it  
Organisation  
Signature  
Date  

Draft form — Manipur Stormwater Design Manual, Draft v1.0.


Form 5-2 — Simplified Downstream Statement (small sites)

Supports Clause 5.3.4 of Chapter 5.

Draft form — Manipur Stormwater Design Manual, Draft v1.0. For sites of less than 0.5 ha. The Authority may accept this statement in place of the full analysis only where every answer in Section B is "Yes". Otherwise submit Form 5-1.

A. Site

Table 5F.16 — Form 5-2: site

Field Entry
A1. Project name, applicant and location  
A2. Site area (ha), less than 0.5 ha  
A3. Receiving public drain: name or reference, type and size  
A4. Site Runoff Control Report reference (Form 4-1)  

B. Conditions (Clause 5.3.4)

Table 5F.17 — Form 5-2: conditions

Condition Yes / No Evidence
B1. The receiving public drain has documented capacity for its minor-system design flow (Chapter 6)    
B2. No flood-prone location is recorded within 500 m downstream of the site outfall. Records checked: local body, IMC, MSDMA, WRD (Clause 5.3.3(d))    
B3. The site does not drain to a tidal or backwater-affected outfall    

C. Route plan

Table 5F.18 — Form 5-2: attachments

Attachment Attached?
C1. Plan of the drainage route from the site outfall for 500 m downstream, with the receiving drain and any recorded flood-prone locations  
C2. Copy or reference of the drain capacity record  

D. Statement

I state that the site meets the conditions of Clause 5.3.4 as shown above, and that the records listed have been checked.

Table 5F.19 — Form 5-2: statement

Field Entry
Name  
Qualification and registration number  
Signature  
Date  

Draft form — Manipur Stormwater Design Manual, Draft v1.0.