Annexes to Chapter 11Basin and City Stormwater Master Plans
These annexes support Chapter 11. They give a terms of reference template for a Basin Stormwater Master Plan (BSMP), the layout of the basin list and boundary layer, the layout and method for depth–damage curves, the standard for publishing BSMP data and models, and the annual implementation report form. Annexes 11B and 11C need data that are not yet available; they say so and give the rule to use in the meantime. The template and the form are a model and a draft form for consideration by a competent authority, and are not in force.
Annex 11A — BSMP terms of reference template
Supports Clauses 11.1 to 11.12 of Chapter 11.
Model text for consideration by a competent authority. Not in force. The Lead Authority adapts this template for each basin. Items in "[ ]" are for the Lead Authority to complete. Clause references are to this Manual, which the consultant shall follow in full.
11A.1 Background and purpose
- The [Lead Authority] intends to prepare a Basin Stormwater Master Plan for the [name] basin under Chapter 11 of the Manipur Stormwater Design Manual.
- The BSMP shall (Clause 11.1.2):
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service for each part of the drainage system;
- (c) identify, cost and rank the works, storage and land needed to reach that level of service;
- (d) identify land to be reserved in the statutory land-use plan for regional storage, pukhri and tank restoration and major flow paths;
- (e) set the basin inputs for site design: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4; and
- (f) recommend catchments for notification as flood-sensitive.
- The BSMP may make the site criteria of Chapters 4 to 8 stricter for the basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6 (Clause 11.1.3).
11A.2 Client, partners and study area
- Client: [Lead Authority] (Clause 11.4.1).
- Partners: WRD, wherever the basin includes a river, canal or tank under its control, and [other local bodies, PDA Manipur or TPD, MSDMA] (Clause 11.4.1).
- Study area: the whole of the [name] basin, draining to [outfall], as delineated under Clause 11.3, including the parts outside the client's limits (Clause 11.3.1). The provisional boundary is in [Annex 11B / attached map]. The consultant shall confirm it in Task 2.
- Links to other basins: [for example the receiving river, khong or pat corridor]. Diversions between basins by canal, drain or surplus course shall be mapped and represented in the model (Clause 11.3.2).
11A.3 Team
- The study shall be led by an engineer empanelled as a Stormwater Design Professional with the basin modelling endorsement of Annex 10E (Clause 11.4.3).
- The team shall include at least: [a hydrologist; a hydraulic modeller; a coastal or tidal specialist where the basin has a tidal outfall; a GIS and survey lead; a planner; a cost engineer; a community engagement lead]. The client sets the minimum qualifications and experience of each.
11A.4 Tasks
Task 1 — Inception. Review existing studies, data and projects in the basin. Prepare a data inventory against Table 11.1, a gap list, a survey plan, a consultation plan, and the work programme. Deliver the inception report.
Task 2 — Data and surveys. Assemble, survey where missing, and quality-check every item of Table 11.1 (Clause 11.5.1):
- (a) terrain: DEM from LiDAR or photogrammetry with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum, with the accuracy test reported;
- (b) drain network: every public drain, culvert and outfall, with invert levels, sizes, condition and silt depth; private drains above 600 mm;
- (c) waterbodies: every tank, pukhri, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels and encroachment, in the fields of Annex 7A;
- (d) rivers and canals: cross-sections at no more than 200 m spacing and at every structure;
- (e) outfalls, rivers, khongs, pats, pukhris, Loktak and reservoirs: outfall invert levels, on a named datum, against the warning, flood and high flood levels of the receiving river at the nearest WRD gauge, with every conflict between published values stated and WRD's gauge register obtained; Loktak's full reservoir and minimum drawdown levels, naming which value is used; the Barak at the CWC site at Chotebekra; the levels, spillways and release records of the Thoubal (Mapithel), Khuga and Singda dams; the sills, gate-closing levels and bund crests of the gates in the river bunds and the capacities and operating rules of the pumping stations; pats and pukhris at their surveyed outlet levels; for ungauged khongs and hill streams, surveyed flood marks and the 1% AEP level with its sediment, debris and garbage; the breach paths of the bunds; and the landslide and debris hazards above the basin;
- (f) rainfall and water levels: all available records (IMD, including Imphal (Tulihal) (A), 42623, the only Manipur station in IMD's Extremes (rainfall data 1953–2012), and the gauges behind the district warnings of the Meteorological Centre Imphal (list not read [TBC]); the river gauges of WRD and the rain gauge at Kangpokpi that its flood rule uses (as reported); the gauges at Kangpokpi, Saikul and Litan used by MASTEC (owners and record lengths [TBC]); the CWC level-monitoring site on the Barak at Chotebekra; the Loktak levels of NHPC and CEA; the IMD stations on the Barak plain downstream that Clause 2.3.6(c)(ii) uses for the Jiribam plain; and any gauges or sensors kept by IMC, Imphal Smart City Ltd, LDA, MSDMA or the flood management system proposed for Lamphelpat [TBC]), including the 28–31 May 2024 (Cyclone Remal: the Imphal at Minuthong above its high flood level of 788.400 m and at Lilong at 782.250 m, and the Manipur river at Ithai at 768.640 m, on 29 May; 18 embankment breaches; 1,88,143 people and 24,265 houses affected by the Minister's count of 30 May, or 1,26,950 people, 255 localities and 16,364 houses by the Relief and Disaster Management Department's report of 31 May, all as reported; no IMD rainfall for the event was found), 30 May–June 2025 (breaches of the Imphal at Singjamei, Heingang, Bashikhong and New Checkon and of the Nambul at four places after 123 mm in 24 hours and 175 mm in 72 hours at Kangpokpi on 30–31 May, as reported; no IMD rainfall for Imphal was found), September 2025 (the Imphal at Lilong at 783.250 m and the Manipur river at Ithai at 770.05 m on 15 September, both above their printed high flood levels, and a breach of the Iril at Kshetri Awang Leikai, as reported; no rainfall value was found), late July–August 2015 (rain 46% above normal in Imphal West on 23–27 July, the Mapithel reservoir at 876 m on 1 August and about 5 lakh people displaced by 3 August by a State revenue estimate, as reported; no gauge value was found) and July–August 1989 (158.6 mm at Imphal (Tulihal) on 30 July, the station's 24-hour record, after daily rain from 28 July to 1 August, with 461.9 mm at Imphal and 617.6 mm at Kangpokpi in the month, 40 breaches and 361 localities flooded, IMD and MASTEC) events;
- (g) flood evidence: surveyed flood marks and mapped extents of past events, including public reports, photographs and residents' records;
- (h) land use: existing land use and imperviousness; future land use from the statutory master plan;
- (i) soils and groundwater: HSG map (Annex 3A or Clause 3.7.2), seasonal high groundwater, aquifer and recharge zones; and
- (j) sewer interaction: known cross-connections, dry-weather flow in drains, solid-waste hotspots.
Confirm the basin boundary and the inter-basin diversions (Clause 11.3.2). Deliver the data report and the data in the formats of Annex 11D.
Task 3 — Model build. Build a coupled 1D–2D hydraulic model of the minor system, the major (overland) system, rivers, canals and tanks, and the outfalls (Clause 11.7.1; Figure 11.2). Use the methods of Chapter 3 and the tidal and river boundaries of Chapter 5. Run the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs, with areal reduction under Clause 2.7.3 (Clause 11.7.2). Where the basin has tank cascades, run continuous simulation under Clause 3.13 with the full IMD gridded daily record where available, and at least 30 years, disaggregated by the temporal patterns of Annex 2D. The two-step approach of Clause 3.13.5 may be used: starting tank levels and antecedent conditions from the continuous run are passed to the design-storm runs (Clause 11.7.3).
Task 4 — Calibration and validation. Calibrate and validate the model under Clause 3.15, using at least two of the 28–31 May 2024 (Cyclone Remal: the Imphal at Minuthong above its high flood level of 788.400 m and at Lilong at 782.250 m, and the Manipur river at Ithai at 768.640 m, on 29 May; 18 embankment breaches; 1,88,143 people and 24,265 houses affected by the Minister's count of 30 May, or 1,26,950 people, 255 localities and 16,364 houses by the Relief and Disaster Management Department's report of 31 May, all as reported; no IMD rainfall for the event was found), 30 May–June 2025 (breaches of the Imphal at Singjamei, Heingang, Bashikhong and New Checkon and of the Nambul at four places after 123 mm in 24 hours and 175 mm in 72 hours at Kangpokpi on 30–31 May, as reported; no IMD rainfall for Imphal was found), September 2025 (the Imphal at Lilong at 783.250 m and the Manipur river at Ithai at 770.05 m on 15 September, both above their printed high flood levels, and a breach of the Iril at Kshetri Awang Leikai, as reported; no rainfall value was found), late July–August 2015 (rain 46% above normal in Imphal West on 23–27 July, the Mapithel reservoir at 876 m on 1 August and about 5 lakh people displaced by 3 August by a State revenue estimate, as reported; no gauge value was found) and July–August 1989 (158.6 mm at Imphal (Tulihal) on 30 July, the station's 24-hour record, after daily rain from 28 July to 1 August, with 461.9 mm at Imphal and 617.6 mm at Kangpokpi in the month, 40 breaches and 361 localities flooded, IMD and MASTEC) events where data exist (Clause 11.7.5). Report the performance measures of Clause 3.15.4 and the reasonableness check of Clause 3.15.6.
Task 5 — Scenarios and hazard maps. Model the scenarios of Clause 11.7.4: (a) existing; (b) future, uncontrolled; (c) future, controlled; (d) future, with plan; and (e) climate, applied to (a) and (d). Produce flood hazard maps of extent, depth, velocity and hazard class (H1–H6, Chapter 6) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan (Clause 11.8.4(a)).
Task 6 — Level-of-service assessment. Compare scenarios (a), (c) and (d) with the levels of service of Table 11.2 and any stricter levels the client adopts (Clause 11.6.1). Map every shortfall.
Task 7 — Options. Develop options in the order of Clause 11.8.1: protect and restore storage; regional retention and detention, sited by modelling; conveyance; outfall works; property-level protection; non-structural measures. Assess each option for the criteria of Clause 11.8.2: reduction in flood risk (buildings and people flooded, and expected annual damage using Annex 11C); capital and 30-year maintenance cost; land required; effect on the clay and peat of the valley floor, on which no infiltration is allowed (Clause 4.11, valley-floor rule), and the water table 2 to 5 m below ground in most of Imphal West (CGWB, 2013), which makes buoyancy and inflow a hazard to sumps, tanks and basements, the Disang shale of the hills, which has "less infiltration and more run off" (MASTEC) and slides when cut and wet, as at Tupul in 2022, recharge on the tested foothill fans, Barail sandstone cappings and sand lenses, the only ground where it is allowed (Clause 4.11, recharge rule), although every assessment unit in the State is safe (stage of extraction 8.00%, GWRA 2024, as quoted from CGWB), and the quality of the rivers, pats and Loktak that the runoff reaches, the Imphal, the Nambul and the Iril among them, from which Imphal draws about 90% of its drinking water; effect on downstream basins and the receiving river, khong or pat; and who benefits.
Task 8 — Basin inputs for site design. Where scenario (c) does not meet the level of service, propose basin release rates (m³/s/ha) by AEP and sub-catchment (Clause 11.8.3). Recommend catchments for notification as flood-sensitive, with the evidence of Clause 4.5.4.1. Identify regional facility sites, with storage volumes, land needs and the sites they serve, and compute the fee-in-lieu unit rate, including land, construction and 10 years of maintenance (Clauses 4.13.3, 11.8.4(c), (d)).
Task 9 — Capital Improvement Programme. Rank the works by risk reduction per rupee, with cost, phasing and responsible agency (Clause 11.8.4(e)).
Task 10 — Maintenance and monitoring. Prepare the pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Clause 11.8.4(f); Chapters 7 and 10). Specify monitoring needs: new rain gauges, level sensors and flood-mark survey points (Clause 11.8.4(g); Clause 10.16.1).
Task 11 — Land-use integration. Prepare the material for the statutory land-use plan required by Clause 11.9.1: sites to be reserved; the 1% AEP hazard map with the Chapter 7 setbacks; land in hazard classes H5–H6 in the 1% AEP event; and open space locations that can form part of flow paths or regional storage.
Task 12 — Consultation. Publish the draft BSMP for public comment for at least 60 days, with public meetings in each affected local body (Clause 11.10.1). Keep a log of comments and responses.
Task 13 — Final BSMP and publication. Revise the BSMP after consultation. Prepare the package for approval by the State Stormwater Technical Committee, including the model for review (Clause 11.11.1). Publish the data, models, maps and CIP under Annex 11D (Clause 11.10.2).
11A.5 Deliverables
Table 11A.1 — Deliverables
| No. | Deliverable | Task | Due (months from start) |
|---|---|---|---|
| D1 | Inception report, data inventory and survey plan | 1 | [ ] |
| D2 | Data report and data sets (Annex 11D) | 2 | [ ] |
| D3 | Model build report and model files | 3 | [ ] |
| D4 | Calibration and validation report | 4 | [ ] |
| D5 | Scenario results, hazard maps and level-of-service assessment | 5, 6 | [ ] |
| D6 | Options report, with basin inputs for site design | 7, 8 | [ ] |
| D7 | Draft BSMP with draft CIP, for consultation | 9–12 | [ ] |
| D8 | Final BSMP, consultation log, approval package and open-data release | 13 | [ ] |
11A.6 Ownership and publication
All data, models, maps and reports produced under these terms are owned by the Lead Authority and shall be published under Annex 11D. The consultant shall not use any software licence, data licence or format that prevents publication, or that prevents a third party from re-running the model with the stated software version.
Annex 11B — Basin lists and boundaries for Tier A bodies
Supports Clauses 11.3 and 11.4 of Chapter 11.
To be prepared. This annex will contain the list of basins for every Tier A body, with a GIS layer of basin boundaries delineated under Clause 11.3.2. It needs the list of Tier A bodies (Annex 1A), a DEM of the accuracy of Clause 11.5.1, flown again over the valley floor, the Loktak margin and the slide-prone slopes after any large flood or landslide, the drain network of every drain-owning body (IMC and the other urban local bodies, PWD and the national-highway agencies, WRD, DoECC, PHED, LDA and Imphal Smart City Ltd), a drain register giving every reach its owner, the river it reaches, the bund it crosses with its gate or flap gate, whether it lies in a river buffer of the bye-laws, its land status (patta or government land) and its outfall, the river bunds of WRD with their crests, gates, sills and breach records, the gauge register of WRD with the datum of every level, the pumping stations with their capacities and operating rules, among them the Lamphelpat pumps on the Shamushang channel, the levels of Loktak and the operating rule of the Ithai barrage from NHPC, the levels, spillways and release rules of the Thoubal (Mapithel), Khuga and Singda dams, the pats and pukhris with their outlet levels and stage–storage, the paddy land and wetland of the valley floor, and the landslide hazards of the Disang shale slopes mapped by MSDMA and NRSC (other likely sources: Survey of India, CWC, CGWB, MASTEC, TPD's GIS master-plan maps and the Revenue Department's land records). No basin map of any Manipur town was found. The NAME_MNI field of Table 11B.2 holds each basin's name in Manipuri, written in Meetei Mayek; while the concurrent use of the Bengali script allowed by the Manipur Official Language (Amendment) Act, 2021 continues, a Bengali-script form may be added in a note. Until the annex is published, the basins of the Nambul, the Imphal river through the city, Lamphelpat, the Kongba and the Iril, Thoubal below the Mapithel dam, the Loktak margin, Nambol and Bishnupur, Kakching and Wangjing, Jiribam and the hill towns on landslide ground named in Clause 11.3.3 are at least those named there; other Tier A bodies define their basins in their first BSMP (Clause 11.3.3); in the hills, at the breach paths of the bunds and in the dam-release reaches the hazard screening of Clause 11.3.3 comes first; and the interim arrangements of Clause 11.12 apply in every basin without an approved BSMP.
Table 11B.1 — Basins named in Clause 11.3.3 (provisional)
| Tier A body or area | Basin | Note from Chapter 11 |
|---|---|---|
| Greater Imphal planning area (IMC, PDA Manipur, TPD) | Catchment of the Nambul through Greater Imphal, with the Naga Nullah, the Waisel Maril and the 72 drains that fall into it | Gates closed; Thong Nambonbi (Hump Bridge) high flood level 783.695 m (WRD, as reported) as boundary; breaches of 2025 and Naga Nullah flooding of 2024 as evidence |
| Greater Imphal planning area (as above) | Catchments draining to the Imphal river through the city | Minuthong and Lilong WRD levels as boundary, with the conflicts stated; breach paths of 2024 and 2025 mapped |
| Greater Imphal planning area (as above; WRD) | Lamphelpat basin, with its pumped outlet through the Shamushang channel to the Nambul | Pat full to its outlet at the start of the storm; pump capacity from WRD [TBC] |
| Greater Imphal planning area (as above) | Corridors of the Kongba and the Iril in Imphal East | Irilbung WRD levels as boundary; 2025 breach as evidence |
| Thoubal (urban local body) | Catchments of Thoubal on the Thoubal below the Mapithel dam | WRD levels and the dam's largest recorded release or spillway capacity as boundary |
| Moirang, Ningthoukhong, Thanga, Ithai–Sugnu–Wangoo | Catchments draining to Loktak, its pats and the Manipur river between Ithai and Sugnu | Ithai high flood level 769.320 m, checked at 770.05 m; outfalls below the design lake level closed 1 June–30 September; Chakpi backwater |
| Nambol and Bishnupur | Catchments draining to the Nambol and the lower Nambul | Nambol Thongkhong WRD level as boundary, with the conflict stated |
| Kakching and Wangjing | Catchments draining to the Sekmai and the Wangjing | Surveyed flood marks as boundary until a WRD level is obtained |
| Jiribam (Municipal Council) | Catchments draining to the Barak and the Jiri | Chotebekra high flood level 32.1 m (CWC, as reported); lock not less than 7 days |
| Noney, Tamenglong, Chandel and Kangpokpi | Catchments of the hill towns on landslide ground | Hazard screening first; site-specific hydrology |
| Other Tier A bodies and urban local bodies | To be defined in the first BSMP | Clause 11.3.3 |
Table 11B.2 — Attributes of the basin boundary layer (layout)
| Field | Type | Content |
|---|---|---|
| BASIN_ID | Text | Basin identifier |
| NAME_EN, NAME_MNI | Text | Basin name in English and Manipuri |
| TIER_A | Text | Tier A body or bodies in the basin |
| OUTFALL | Text | Outfall to the sea, river or major waterbody (Clause 11.2) |
| AREA_KM2 | Real | Basin area, km² |
| LEAD_AUTH | Text | Lead Authority (Clause 11.4.1) |
| PARTNERS | Text | Partners, including WRD where it applies |
| LINKS | Text | Diversions to and from other basins (Clause 11.3.2) |
| BSMP_STAT | Text | None / in preparation / draft published / approved |
| BSMP_DATE | Date | Date of approval of the current BSMP |
| REVIEW_DUE | Date | Date of the next review (Clause 11.11.2) |
Annex 11C — Depth–damage curves for Manipur building types
Supports Clause 11.8.2 of Chapter 11.
To be prepared. This annex will contain depth–damage curves for the main building types of Manipur cities, for structure and contents, for use in computing expected annual damage under Clause 11.8.2. It needs a building-type classification and building stock data (Census housing tables, property-tax records, Lead Authority GIS), damage surveys and claims from the 28–31 May 2024 (Cyclone Remal: the Imphal at Minuthong above its high flood level of 788.400 m and at Lilong at 782.250 m, and the Manipur river at Ithai at 768.640 m, on 29 May; 18 embankment breaches; 1,88,143 people and 24,265 houses affected by the Minister's count of 30 May, or 1,26,950 people, 255 localities and 16,364 houses by the Relief and Disaster Management Department's report of 31 May, all as reported; no IMD rainfall for the event was found), 30 May–June 2025 (breaches of the Imphal at Singjamei, Heingang, Bashikhong and New Checkon and of the Nambul at four places after 123 mm in 24 hours and 175 mm in 72 hours at Kangpokpi on 30–31 May, as reported; no IMD rainfall for Imphal was found), September 2025 (the Imphal at Lilong at 783.250 m and the Manipur river at Ithai at 770.05 m on 15 September, both above their printed high flood levels, and a breach of the Iril at Kshetri Awang Leikai, as reported; no rainfall value was found), late July–August 2015 (rain 46% above normal in Imphal West on 23–27 July, the Mapithel reservoir at 876 m on 1 August and about 5 lakh people displaced by 3 August by a State revenue estimate, as reported; no gauge value was found) and July–August 1989 (158.6 mm at Imphal (Tulihal) on 30 July, the station's 24-hour record, after daily rain from 28 July to 1 August, with 461.9 mm at Imphal and 617.6 mm at Kangpokpi in the month, 40 breaches and 361 localities flooded, IMD and MASTEC) floods (Revenue Department and MSDMA damage assessments, insurers), and replacement costs (Public Works Department schedules of rates). Until it is published, each BSMP shall state the depth–damage relations it uses and their source, and shall report the reduction in buildings and people flooded for every option (Clause 11.8.2), which does not depend on the curves.
Table 11C.1 — Depth–damage curve (layout, one table per building type)
| Depth of water above floor level (m) | 0 | 0.25 | 0.5 | 1.0 | 1.5 | 2.0 | 3.0 |
|---|---|---|---|---|---|---|---|
| Structure damage (% of replacement cost) | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Contents damage (% of contents value) | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Building type, source and year of costs | ______ |
11C.1 Use in option assessment
Expected annual damage (EAD) is computed for each scenario from the damages at the modelled AEPs. With damages D_1, D_2, … at annual exceedance probabilities P_1 > P_2 > …, using at least the 50%, 10%, 1% and 0.2% AEP results of Clause 11.7.2:
EAD ≈ Σ ½ × (D_i + D_(i+1)) × (P_i − P_(i+1))
The reduction in EAD between scenario (c) and scenario (d), or between options, is the risk-reduction benefit used to rank works per rupee (Clause 11.8.4(e)). The BSMP shall state how damages beyond the 0.2% AEP and below the 50% AEP were treated.
Annex 11D — BSMP data and model publication standard
Supports Clauses 11.5.1 and 11.10 of Chapter 11, and Clause 10.17 of Chapter 10.
11D.1 What is published, and when
Table 11D.1 — Items to be published
| Item | Format | At draft (Clause 11.10.1) | At approval (Clause 11.10.2) |
|---|---|---|---|
| BSMP report, with the level-of-service assessment and options | Searchable PDF | Yes | Yes, final |
| Flood hazard maps: extent, depth, velocity, hazard class, for each AEP and scenario of Clause 11.8.4(a) | GeoTIFF rasters; extents also as GeoPackage polygons | Yes | Yes |
| Capital Improvement Programme | CSV and PDF | Draft | Yes |
| Basin release rates, recommended flood-sensitive catchments, regional facility sites, fee-in-lieu unit rate | GeoPackage and CSV | Yes | Yes |
| Data of Table 11.1 (terrain, drains, waterbodies, cross-sections, river, lake, pat, pukhri and reservoir levels, bund gates and pumping stations, slope and debris hazards and outfall structures, rainfall and levels, flood evidence, land use, soils and groundwater, sewer interaction) | GeoTIFF (terrain); GeoPackage (features); CSV (tables and time series) | Summary | Yes, except security-sensitive asset details |
| Model files: native, runnable, with all boundary-condition, rainfall and control files, the software name and version, and a run log | Native format, zipped | No | Yes |
| Calibration and validation report | Searchable PDF | Yes | Yes |
| Consultation log of comments and responses | PDF or CSV | — | Yes |
11D.2 Formats and references
- (a) Raster data shall be GeoTIFF, preferably cloud-optimised, with the cell size stated. Vector data shall be GeoPackage. Tables and time series shall be CSV in UTF-8, with a header row and units in the column names.
- (b) Horizontal and vertical references shall be as in Annex 10B.1(b) and (c). The vertical datum and its relationship to the Chapter 5 river datums of the WRD gauges on the valley rivers and at the Ithai barrage (levels published in the press in metres, presumed above mean sea level, the datum not stated [TBC]), of the CWC level-monitoring site on the Barak at Chotebekra, of the Loktak levels of NHPC and CEA, of the reservoir levels of the Thoubal (Mapithel) dam, of WRD's bund crests, gate sills and gate-closing levels, and of the flood marks surveyed on ungauged rivers, khongs, pats and pukhris shall be stated in every data set that carries levels.
- (c) Times shall be in Indian Standard Time, written as ISO 8601 (yyyy-mm-ddThh:mm+05:30). Units shall be SI.
- (d) Hazard map files shall be named
<basin>_<scenario>_<AEP>_<variable>.tif, where scenario is a to e of Clause 11.7.4, AEP is written as 50, 10, 1 or 0p2, and variable is depth, velocity, hazard or extent; for examplenambul_d_1_depth.tif. - (e) Waterbody data shall use the fields of Annex 7A. Facility and outfall data shall use the fields of Annex 10B.
11D.3 Metadata
Every published data set shall carry: title; description; Lead Authority; source and method; date of capture; accuracy (for the DEM, the measured vertical RMSE); horizontal and vertical reference; scenario and AEP, where relevant; BSMP version; licence; and a contact.
11D.4 Withholding and personal data
- (a) Security-sensitive details of critical assets may be withheld, with the reason recorded and published (Clauses 10.17.3, 11.10.2). The flood hazard maps and the model shall still be published; only the sensitive attributes are removed.
- (b) Personal data shall not be published (Clause 10.17.3). Flood evidence collected from residents shall be published without names or contact details unless the person consents.
11D.5 Licence, viewer and versions
- (a) Published data and models shall be released under the Government Open Data Licence – India or an equivalent open licence (Clause 10.17.4).
- (b) The hazard maps, regional facility sites and CIP shall also be shown on a public map viewer (Clause 11.10.2).
- (c) Each approved BSMP shall carry a version number and date. Superseded versions shall stay available, marked as superseded, so that designs approved under them can be checked.
- (d) The published model package shall allow a third party with the stated software version to reproduce the published results. Designers may use its boundary conditions for site designs in the basin (Clause 11.10, Commentary).
Form 11-1 — Annual implementation report
Supports Clause 11.11.3 of Chapter 11, with Clauses 4.5.6.3 and 4.13.4 of Chapter 4.
Draft form — Manipur Stormwater Design Manual, Draft v1.0. Published by the Lead Authority for each basin with an approved BSMP before each monsoon season, by 31 March (Clause 11.11.3).
Table 11F.1 — Form 11-1, Section A: Basin and plan
| No. | Field | Entry |
|---|---|---|
| A1 | Basin; Lead Authority; partners | ______ |
| A2 | BSMP version and date of approval | ______ |
| A3 | Reporting year (1 April to 31 March) | ______ |
| A4 | Date of publication (by 31 March) and web address | ______ |
Table 11F.2 — Form 11-1, Section B: CIP progress
| CIP rank | Work | Agency | Cost in CIP (₹) | Spent this year (₹) | Spent to date (₹) | Status | Expected completion |
|---|---|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
Table 11F.3 — Form 11-1, Section C: Fee-in-lieu ledger (Clauses 4.5.6.3(c) and 4.13.4)
| Regional facility or tank | Volume credited to sites (m³) | Volume delivered (m³) | Fees received (₹) | Fees spent (₹) | Fees held, with year received |
|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ |
| Basin total: volume owed and delivered | ______ | ______ | ______ | ______ | ______ |
Table 11F.4 — Form 11-1, Section D: Maintenance completed (Clause 11.8.4(f))
| No. | Item | Planned | Done | Date completed |
|---|---|---|---|---|
| D1 | Desilting of drains and canals (length, km; volume, m³) | ______ | ______ | ______ |
| D2 | Tank and pukhri desilting and restoration (tanks, number; storage restored, m³) | ______ | ______ | ______ |
| D3 | Gate tests (number of gates) | ______ | ______ | ______ |
| D4 | Pump station duty tests (number of stations) | ______ | ______ | ______ |
| D5 | Tank operating rules reviewed with the custodian (number) | ______ | ______ | ______ |
| D6 | Monitoring added: rain gauges, level sensors, flood-mark points (Clause 11.8.4(g)) | ______ | ______ | ______ |
Table 11F.5 — Form 11-1, Section E: Flooding against the levels of service
| Event (dates) | Rainfall compared with the design depths (Clause 10.16.2(a)) | Level-of-service element (Table 11.2) | Location | Met (yes / no) | Event report reference (Clause 10.16.2) |
|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ |
Table 11F.6 — Form 11-1, Section F: Review triggers and sign-off
| No. | Field | Entry |
|---|---|---|
| F1 | Event exceeding the 1% AEP design depth in the basin this year (yes / no). If yes, review due within 2 years (Clause 11.11.2) | ______ |
| F2 | Statutory land-use plan revised this year (yes / no) (Clause 11.11.2) | ______ |
| F3 | Next 10-year review due (date) | ______ |
| F4 | Officer of the Lead Authority: name, designation, signature, date | ______ |