Chapter 5Downstream and Tailwater Analysis
5.1 Purpose and scope
5.1.1 This chapter sets two checks that every regulated development and every public drainage project must pass.
- The downstream analysis (Clauses 5.3 to 5.5) confirms that the project does not make flooding worse below its outfall.
- The tailwater analysis (Clauses 5.6 to 5.13) sets the water level the system discharges into, including tide, storm surge, sea-level rise, river backwater and sand-bar closure. It also requires the system to cope when its outfall is closed.
5.1.2 This chapter applies to:
- (a) every site to which Chapter 4 applies;
- (b) every minor- and major-system drainage project under Chapter 6; and
- (c) every regional detention or tank restoration project under Clause 4.13 and Chapter 7.
5.1.3 Rainfall and joint-occurrence inputs come from Chapter 2, in particular Clauses 2.5.3 and 2.12. Hydrologic methods come from Chapter 3. Site release criteria come from Chapter 4. Hydraulic design of gates, culverts and pumps follows Chapter 9.
5.1.4 No tidal outfalls in Manipur. Manipur is landlocked: it has no coast, no tide and no Coastal Regulation Zone, and the monsoon reaches it as rainfall and as the floods of its valley rivers, of Loktak and of the Barak, which are dealt with in Chapter 2 and in Clause 5.8, not as a tidal or surge level. No outfall in the State discharges to the sea, a tidal creek or an estuary, so the provisions of this chapter that depend on tide, storm surge, sea-level rise or a river mouth do not apply in Manipur: Clause 5.7 and Annex 5A, cases J1 to J3 of Table 5.2, the tidal lock windows of Clause 5.10.3, the seawater requirement of Clause 5.11.3(a) (gates and seats shall still be of corrosion-resistant materials, and shall resist abrasion by silt and attack by water that carries sewage), and Clause 5.13. They are kept so that the clause numbers of this Manual match its other State editions. In Manipur the receiving water is one of seven kinds: a valley river reached through a gate or flap gate (ithong, Manipuri: a sluice gate or floodgate) in a river bund (pan, Manipuri: a bund or embankment), or through a pumping station, which is normally closed in the monsoon because the river stands higher than the town behind it; the city rivers and channels of Imphal, among them the Nambul, the Naga Nullah and the Waisel Maril, and Lamphelpat with its pumped outlet through the Shamushang nallah; Loktak, held up by the Ithai barrage and by a rock sill below it, whose level is the tailwater for the south of the valley; a river below a dam, such as the Thoubal below the Mapithel dam; a pat (Manipuri: a lake or wetland, as in Lamphelpat) or a pukhri (Manipuri: a pond; plural pukhris) that stores the town's water while its outlet is closed; a khong (Manipuri: a stream) or other hill stream coming down from the hills, laden with silt and debris; or the Barak and the Jiri on the Jiribam plain; and:
- (a) its tailwater is set by Clauses 5.6 and 5.8, including Clause 5.8.5;
- (b) where Clauses 5.10 to 5.12, Form 5-1 or Chapter 6 refer to the J1 tailwater or the J1 tidal curve, the minor-system tailwater of Clause 5.6.2 or 5.8.5 applies, as a time series where the receiving level varies; where they refer to the J2 tailwater or to HAT + surge + SLA, the major-system tailwater applies: the design-AEP river level of Clause 5.8.4(b), or the major-system tailwater of Clause 5.8.5, whichever is higher at the outfall; and
- (c) the outfall-closed check of Clause 5.10 applies where an outfall is closed by a river behind a bund gate, a pumped outfall, Loktak, a release reach, a full pat or pukhri, a hill stream or a receiving drain, with the locks and closures of Clause 5.8.5(a) to (g) in place of the tidal lock windows.
5.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Analysis point | A location on the downstream system where pre- and post-project conditions are compared (Clause 5.3.3). |
| Contributing catchment | The whole area draining to an analysis point, on and off site. |
| Major drain | A channel listed as a major drain in the basin plan or Annex 5B, or any river, WRD canal, the Naga Nullah, the Waisel Maril and the Shamushang nallah in Imphal, every city channel and flood channel of WRD and every drain that discharges through a gate or flap gate in a river bund, any drain built or held by IMC, a Municipal Council, a Nagar Panchayat, PDA Manipur, PWD or a national-highway agency with an internal width of 1.0 m or more, and every khong or other natural channel that drains 8 ha or more, or a tidal creek. |
| Chart datum (CD) | The datum of the published tide tables and nautical charts, to which tidal heights are referred. |
| Mean sea level (MSL) | Average sea level over a long period at a tide gauge. |
| MHWS | Mean high water springs: the average of high waters at spring tides. |
| HAT | Highest astronomical tide: the highest level predicted under average meteorological conditions over a full tidal cycle (18.6 years). |
| Storm surge | The rise in sea level above the astronomical tide caused by wind and low pressure, mainly during cyclones. |
| Still-water level | Astronomical tide plus surge, excluding individual waves. |
| Sea-level allowance (SLA) | The allowance added to present-day tidal levels for sea-level rise over the design life (Clause 5.7.4). |
| Tailwater | The water level at the downstream end of a drain, outlet or storage. |
| Tide-lock | The condition in which the tailwater is at or above the upstream water level, so a gravity outfall cannot discharge. |
| Lock window | A period during which the outfall-closed check of Clause 5.10 sets gravity discharge to zero. |
| Sand bar | A bar of beach sand that partly or fully closes a river mouth or creek inlet. |
| Project datum | The levelling datum used on the project drawings. It must be tied to a Survey of India benchmark (Clause 5.7.2). |
5.3 Extent of the downstream analysis
5.3.1 The downstream analysis shall start at each site or project outfall. It shall continue downstream to the first of:
- (a) the point at which the project area is 10% or less of the contributing catchment;
- (b) the next tank, pukhri or other waterbody with a surplus weir or controlled outlet; or
- (c) the next major drain, or the sea.
The end point itself shall be analysed (Figure 5.1).
5.3.2 Where the analysis ends at a tank or pukhri under 5.3.1(b), it shall report:
- the change in the tank's maximum water level; and
- the change in surplus-weir discharge, for the AEPs and durations of Clause 5.4.3.
If the maximum water level rises, the analysis shall continue below the surplus weir to the next end point.
5.3.3 Analysis points shall be set at least at:
- (a) each site outfall;
- (b) each confluence with a drain or channel whose contributing catchment is at least half that of the receiving drain at that point;
- (c) each culvert, bridge or road crossing;
- (d) each location recorded as flood-prone by the local body, IMC, MSDMA or WRD; and
- (e) each building or road segment lying within the 1% AEP flood extent along the route. Representative points may be used where buildings are closely spaced.
5.3.4 Small sites. For sites of less than 0.5 ha, the Authority may accept a simplified downstream statement (Form 5-2) in place of the full analysis, where all of the following hold:
- the receiving public drain has documented capacity for its minor-system design flow (Chapter 6);
- no flood-prone location is recorded within 500 m downstream; and
- the site does not drain to a tidal or backwater-affected outfall.
Figure 5.1 — Extent of downstream analysis: analysis points A–D, the contributing area at each point, the 10% point, and the next pukhri or major drain as an alternative end point. Schematic; percentages are illustrative. Original drawing for this Manual, adapted from the ten-percent rule in the Georgia Stormwater Management Manual (2016, Vol. 2 §3.1.9) and KC APWA Section 5600 (2006, 5601.5).
Commentary. The 10% rule has established precedent. KC APWA 5600 (2006) required the downstream system to be analysed "to the point the development's land mass is less than 10% of the total watershed". The Georgia manual makes the ten-percent analysis a mandatory standard (GSMM 2016, Standard #8). The tank or major-drain end point has no direct precedent; this Manual adds it for Manipur. In the Imphal valley, where the drains of Greater Imphal run to the Nambul, the Imphal river, the Kongba and the Iril, and every valley river runs on across the valley floor and its pats to Loktak and to the valley's one outlet past the Ithai barrage, in a basin that the master plan gives as 6,332 km² (as printed), the 10% point can lie many kilometres downstream, across several tanks. A tank with a working surplus weir changes the hydrograph completely, so the analysis is better ended there and the tank level reported. Clause 5.3.2 prevents that end point from hiding a rise in the tank level. The small-site statement (5.3.4) and its 500 m distance have no direct precedent and are set by this Manual.
5.4 What the analysis must check
5.4.1 Scenarios. Each analysis shall compare:
- (a) Existing: the present downstream system and present land use of the whole contributing catchment, with the project site at its pre-project state; and
- (b) With project: the same, with the project and all its controls (Chapter 4) in place.
Where the Authority's basin plan defines future land use, the Authority may also require:
- (c) Future: the catchment fully developed under the plan, all to Chapter 4 standards, with and without the project.
5.4.2 Quantities to be checked at every analysis point:
- (a) Capacity: peak flow against the capacity of every channel, pipe, culvert and crossing, for the minor-system AEP of that element (Chapter 6) and for 1% AEP;
- (b) Flood levels: 1% AEP maximum water level at buildings (at the lowest opening) and on roads (at the crown and at the deepest point);
- (c) Velocities: peak velocity for 50%, 10% and 1% AEP;
- (d) Timing of combined peaks: the hydrograph at each confluence, showing the time to peak of the project outflow and of the receiving drain; and
- (e) Duration of inundation: on roads and at buildings, the time above the Chapter 6 depth limits.
5.4.3 Storms. The analysis shall use:
- 50%, 10% and 1% AEP;
- the duration set of Clause 2.5.2, at least the durations that give the highest level at each analysis point (these will usually be longer than at the site); and
- the 24-, 48- and 72-hour storms in every case.
The AMC rule of Clause 2.11.4 applies. Areal reduction follows Clause 2.7, applied to the contributing catchment at each analysis point and never to the site storage.
5.4.4 Method. The analysis shall:
- use a hydrograph method that combines hydrographs at confluences (SWMM, HEC-HMS, or an equivalent);
- include a hydraulic model with backwater (SWMM dynamic wave, HEC-RAS, or equivalent) wherever tailwater or backwater affects any analysis point; and
- not use the Rational Method at any analysis point, because it cannot represent timing.
Off-site areas shall be modelled at their present land use. Upstream detention shall be included only where it is built, maintained and documented.
5.4.5 Tailwater. The downstream end of the model shall use the tailwater of Clauses 5.6 to 5.9 and the sand-bar condition of Clause 5.13 where applicable.
Commentary. Clause 5.4.2(d) exists because detention changes when the site's water arrives, not only how much arrives (Clause 4.16). A Colorado State University thesis and a Water (2016) optimisation study both found that delayed site releases can coincide with the main-stem peak and raise it. Georgia's manual states the result directly: some structural practices "fail to reduce discharge peaks to pre-development levels downstream" because of "peak flow timing and runoff volume effects" (GSMM 2016). The duration-of-inundation check (5.4.2(e)) matters in the Imphal valley, whose capital "is below the high flood level of Imphal river" and lives behind embankment roads on both banks (master plan), where "the failure of river dikes causes waterlogging in the low-lying areas for several weeks" (AIIB, 2024), where Lamphelpat "remains waterlogged for many days every year" although it is pumped (NDB), and where the rivers bring a few hundred cubic metres a second each in a flood while the only outlet at Ithai carries "of the order of 400 cumecs", so that "water is piled up upstream" (MASTEC). Detention that prolongs releases can lengthen that time even when it lowers the peak.
5.5 Acceptance criteria
5.5.1 The project is acceptable if, at every analysis point and for every AEP and duration of Clause 5.4.3, comparing "with project" to "existing":
- (a) the 1% AEP maximum water level does not rise by more than 10 mm at any habitable building, at any building's lowest opening, or on any road carriageway;
- (b) no building that is not flooded in the existing case is flooded with the project, and no building or road that meets the Chapter 6 freeboard or depth limits in the existing case fails them;
- (c) peak flow does not exceed the existing peak at the minor-system AEP of each element, or at 1% AEP;
- (d) peak velocity in lined channels stays within the permissible velocity for the lining (Chapter 6: 3.0 m/s maximum); and
- (e) in unlined or natural channels, peak velocity for 50% and 10% AEP does not increase by more than 10%, unless protection is provided under Chapter 9.
5.5.2 The duration of inundation under 5.4.2(e) shall be reported. The Authority may refuse a project that increases the duration of road closure on an arterial or emergency route.
5.5.3 Where the criteria are not met, the project shall do one or more of the following:
- (a) reduce release rates or increase storage (Chapter 4);
- (b) build downstream improvements, with the consent of the owner of the downstream system. These shall not transfer the problem further downstream, and shall be re-analysed under this chapter;
- (c) contribute to a regional facility under Clause 4.13; or
- (d) under Clause 5.5.4, change the release strategy.
5.5.4 Timing exception. Where the analysis shows that detention raises downstream levels because of timing, the Authority may vary the site release-rate criteria of Clause 4.5. This applies only where the site discharges within the lower tenth of the contributing catchment, directly to a major drain, tidal creek or the sea, and only on the following conditions:
- (a) the varied strategy meets 5.5.1;
- (b) the retention requirement (Clause 4.4) and WQv treatment (Chapter 8) are met in full; and
- (c) the outfall-closed check (Clause 5.10) is met.
Commentary. The 10 mm tolerance (5.5.1(a)) has no direct precedent. It is meant to be at or below the numerical precision of a typical one-dimensional model, so that "no increase" can be tested without arguing over rounding. The 10% velocity tolerance is likewise set by this Manual. The timing exception in 5.5.4 follows the Georgia manual, where the downstream analysis can show "that peak controls are not needed" and allow them to be waived (GSMM 2016, Standard #8). It is limited here to sites low in the catchment, which is where synchronisation with the main-stem peak is most likely (Water 2016, 8(7):290). It is not available above that, because the evidence on scale (Clause 4.16) shows that early release from many upstream sites raises peaks.
5.6 Tailwater: general and non-tidal outfalls
5.6.1 Every drain, outlet and storage shall be designed against a stated tailwater. A free outfall shall be assumed only where the outlet invert is above the maximum receiving water level for the case being checked.
5.6.2 Minor-system tailwater, non-tidal. The tailwater is the receiving system's water level at the time of the minor-system peak, from the downstream model. Where no model exists, use:
- for a receiving pipe, its obvert; or
- for a receiving open drain, its full-bank level less freeboard (Chapter 6).
5.6.3 Major-system tailwater, non-tidal. The tailwater is the receiving system's 1% AEP water level, unless Clause 5.8 allows a coincident lower level.
5.6.4 Tidal and backwater outfalls. Clauses 5.7 to 5.13 apply in addition.
5.6.5 Storage elements. Detention, tanks and pumped sumps shall be routed with a time-varying tailwater (Clause 4.6.6), not a constant level, wherever the tailwater varies with tide or with the receiving system's hydrograph.
5.7 Tidal tailwater: datums, surge and sea-level allowance
5.7.1 Design tailwater levels. For outfalls to the sea, tidal creeks, estuaries, backwaters and tidal reaches of rivers and canals:
Table 5.1 — Design tailwater levels for tidal outfalls
| Design case | Tailwater |
|---|---|
| Minor-system design (Chapter 6) | MHWS + SLA |
| Major-system design and storage design | HAT + surge + SLA, with the surge term defined in Clause 5.7.3 |
| Joint case (Clause 2.12(b)) | 1% AEP still-water level + SLA |
The SLA is +0.3 m minimum (Clause 5.7.4). The cases to be run are listed in Clause 5.9.
5.7.2 Sources and datums.
- (a) Tidal levels. MHWS, HAT and MSL shall be taken from the current edition of the Indian tide tables published by the National Hydrographic Office (NHO) or by the Survey of India, for the nearest standard or secondary port, or from the port authority's published tidal levels. The edition and port shall be stated.
- (b) Datum conversion. Tide-table heights are referred to chart datum. They shall be converted to the project datum through a documented connection between chart datum, the tide gauge zero and a Survey of India benchmark. The offset and its source shall be stated on Form 5-1.
- (c) Estuaries, creeks and canals. For outfalls inside estuaries, creeks, backwaters or tidal canals (for example the estuaries of the coastal States; there is none in Manipur, Clause 5.1.4), tidal levels may differ from the open coast. Open-coast levels shall be used unless measured levels over at least one spring–neap cycle, or a calibrated hydrodynamic model, justify a different value. No reduction below open-coast levels shall be taken without such evidence.
- (d) Interim. Until Annex 5A is published, the designer shall obtain the values directly from the sources in (a) and record them.
5.7.3 Storm surge.
- (a) Major-system and storage design. The surge term in "HAT + surge" is the 10% AEP (10-yr) storm surge for the coastal segment, given in Annex 5A. The 1% AEP surge is used only in the joint case of Clause 2.12(b), with the 10-yr 48-hour storm. That keeps the two cases symmetric, so that a rare rainfall is never paired with a rare surge.
- (b) Joint case. The 1% AEP still-water level for Clause 2.12(b) is taken from Annex 5A.
- (c) Until Annex 5A is published, both values shall be taken from a site-specific study using INCOIS, IMD or NCCR surge hindcasts or return-level analyses. The study shall state its source, method and record length.
- (d) Wave set-up shall be added where the outfall faces the open sea without a protected entrance.
5.7.4 Sea-level allowance. The SLA shall be:
- (a) +0.3 m minimum for every element;
- (b) greater than 0.3 m where the State, PDA Manipur or the Authority adopts a higher projection for the planning area; and
- (c) assessed for the design life of the element. For elements with a design life of more than 50 years, the designer shall report the effect of a sea-level rise of twice the SLA as a sensitivity run.
Figure 5.2 — Tidal outfall: flap gate, property non-return valve, and the design tailwater levels (MHWS + 0.3 m for the minor system; HAT + surge + 0.3 m for the major system), with a seasonal sand bar at the mouth. Schematic, not to scale. Original drawing for this Manual, adapted from the tidal tailwater table in MoHUA/CPHEEO Manual on Storm Water Drainage Systems (2019), Part A, Table 6.2.
Commentary. CPHEEO (2019) Table 6.2 sets the design tailwater for coastal outfalls as:
- MHWN to MHWS for a minor storm (more frequent than 1 in 5 years);
- MHWS to HAT for a major storm; and
- "Effect of climate change: additional 0.3 m".
CPHEEO also says the joint probability of storm, tide and surge "should" be considered, with the state maritime board consulted. This Manual takes the upper end of each CPHEEO range, adds surge for the major system, and makes the joint case explicit (Clause 2.12). CPHEEO does not require surge to be added; this Manual adds it because the surge records of the coastal States showed why it is needed there; Manipur has no coast, and the surge term does not arise in the State, whose rivers are held high by their own floods behind the river bunds and by Loktak behind the Ithai barrage, not by the sea (Clause 5.8.5).
Indian tide tables have been published by the Survey of India since the nineteenth century (Survey of India, Tidal Predictions). Current Indian tidal predictions also appear in the NHO's tide tables. One port document describes the current edition as covering 95 Indian ports, based on NHO observations and on data from civil ports, NIO and INCOIS (Adani Ports, Dahej tide table 2025, citing NHO INP-12). INCOIS runs coastal tide gauges and issues storm-surge and swell-surge warnings. None of these is used for design in Manipur, which has no coast, and Annex 5A is not prepared for the State (Clause 5.1.4).
5.8 Riverine backwater
5.8.1 Where it applies. Outfalls to rivers and canals whose water level in a storm can exceed the outfall invert shall be designed with riverine backwater. This includes:
- the bunded rivers of the Imphal valley floor, the Imphal river (at Minuthong and Lilong), the Nambul (at Thong Nambonbi, Hump Bridge), the Iril (at Irilbung), the Kongba, the Thoubal, the Sekmai, the Wangjing, the Nambol (at Nambol Thongkhong), the Khuga, the Merakhong and the Arong, through the gates, flap gates and pumping stations in WRD's river bunds (Clause 5.8.5(a));
- in Imphal, the Imphal river through the city, the Nambul with the Naga Nullah and the Waisel Maril, Lamphelpat with its pumped outlet through the Shamushang nallah to the Nambul, and the Kongba and the Iril in Imphal East (Clause 5.8.5(b));
- Loktak and the pats that fringe it, the Manipur river from the Ithai barrage past the Sugnu hump to Sugnu, and the Chakpi at its confluence, for Moirang, Ningthoukhong, Thanga, Ithai, Sugnu and Wangoo (Clause 5.8.5(c));
- the release reaches of the Thoubal below the Mapithel dam, the Khuga below its dam and the Nambul below the Singda dam (Clauses 5.8.3 and 5.8.5(d));
- every pat, pukhri and detention pond that receives a town's drains, among them Lamphelpat, the pats of the State Wetlands Authority's priority list and the public pukhris of the towns (Clause 5.8.5(e));
- the khongs and hill streams of the hill towns and of the valley rim, where they come down to the valley floor and to Loktak, and the Barak, Makru, Irang, Leimatak and Tuivai catchments of the western hills (Clause 5.8.5(f));
- the Barak at Chotebekra and the Jiri on the Jiribam plain (Clause 5.8.5(g));
- any drain or channel of IMC, a Municipal Council, a Nagar Panchayat, PDA Manipur, PWD, a national-highway agency or DoECC, and any city channel or flood channel of WRD, that receives storm water (Clause 5.8.5(h)); and
- elsewhere: any river or WRD channel listed in Annex 5B.
5.8.2 River levels. River water levels shall be taken from:
- (a) WRD design flood levels or recorded highest flood levels for the reach, where published; or
- (b) a hydraulic model (HEC-RAS or equivalent) of the river reach. The model shall use:
- the river design flood from a hydrograph method (Chapter 3), with continuous simulation where Chapter 3 requires it;
- the tidal boundary of Clause 5.7 at the mouth; and
- the sand-bar condition of Clause 5.13.
5.8.3 Reservoir and tank releases. Where a reservoir or tank upstream can release to the river (for example the Mapithel dam of the Thoubal Multipurpose Project on the Thoubal, the Khuga dam on the Khuga, the Singda dam on the Nambul, and the Ithai barrage of NHPC, which holds up Loktak), the river level shall include the release given by the reservoir's operating rule for the storm being checked. Where there is no published rule, it shall include the largest recorded release.
5.8.4 Coincidence of site storm and river flood. Unless a joint-probability study is accepted by the Authority, the more severe of the following governs:
- (a) the site design storm (AEP as required), with the river at its 10% AEP (10-yr) level; and
- (b) the site 10% AEP storm, with the river at its design-AEP level (1% AEP for the major system).
The two storms in each pair shall have the same duration and timing where they are generated by the same rainfall event.
5.8.5 Bund-locked valley outfalls, Imphal, the Loktak margin and its outlet, dam-release reaches, pats and pukhris, hill streams, Jiribam and the Barak, and consents and lines.
- (a) Bund-locked valley outfalls. For an outfall on the Imphal valley floor (sub-areas MN-A and MN-A1 of Annex 2A) to a river directly, through a gate, flap gate or culvert (ithong) in a river bund (pan), through a drainage pumping station, or into a drain, khong, pat or pukhri that itself discharges in one of those ways, the designer shall identify the body that operates each gate, flap gate and pumping station, and obtain from its written records the sill of each gate, the crest of the bund, the installed permanent capacity of each pumping station and its duty point, its sump levels, and the river level at which each gate is closed. Every level shall state its datum and its connection to a Survey of India benchmark, and shall name the WRD gauge with which it is compared. The river bunds, the flood channels and the pumping from Lamphelpat are WRD's. No Manipur statute on embankments was found during research (NEER reading), so WRD's consent is that of the owner of the bunds (item (h)); no list of the valley's gates, flap gates and pumping stations with these values, and no WRD rule for operating them, was found [TBC]. The bunds are long and weak in places: MASTEC counted 11 vulnerable points on the bunds of the Imphal river, 14 on the Thoubal and 5 on the Iril, and recorded breaches at 60 places in 1966, 40 in 1989 and 59 in 2002 (MASTEC).
- WRD levels. The river levels of Clause 5.8.2(a) in the valley are the warning (WL), flood (FL) and highest flood levels (HFL) that WRD publishes through the press for its gauges. All are as reported, and none states its datum; they are taken as metres above mean sea level, to be confirmed for each gauge [TBC] (Table 5B.1): the Imphal river at Minuthong (Imphal city) WL 785.900 m, FL 786.900 m and HFL 788.400 m; the Imphal river at Lilong WL 780.350 m, FL 781.350 m (2025 reports) or 781.250 m (2024 reports) and HFL 782.850 m (2024 report); the Iril at Irilbung WL 786.700 m and FL 787.700 m, with an HFL printed as 782.200 m, below its own flood level, which is an error in the report or its source [U]; the Thoubal (gauge not named) WL 778.915 m and FL 779.915 m; the Nambul at Thong Nambonbi (Hump Bridge) HFL 783.695 m, with no flood level printed; the Nambol at Nambol Thongkhong HFL 774.700 m (2024) or 774.400 m (2025) [U]; and the Manipur river at the Ithai barrage HFL 769.320 m. These levels have been passed. On 29 May 2024 the Imphal river at Minuthong ran above its HFL, and the Nambul and the Nambol above theirs; on 15 September 2025 the Imphal river stood at 783.250 m at Lilong, above the printed HFL, the Iril at 788.850 m at Irilbung, "above FL, below HFL", and the Manipur river at 770.05 m at Ithai, above its HFL (all as reported). WRD may have revised its HFLs since (NEER reading). The WRD gauge register, with the gauge zero, datum and levels of each gauge and every revision, is the first data request for every valley outfall [TBC].
- Design and check levels. For an outfall to a gauged valley river, the design case for the major system and for storage (Clause 5.8.4(b) and Clause 5.10) is the river at its WRD flood level at the governing gauge, transferred to the outfall, with the gate closed. Where two flood levels are printed for one gauge, the higher applies (at Lilong, 781.350 m); this Manual does not decide which of them is right. The check case is the river at the higher of its HFL and the highest reading reported above it (Minuthong 788.400 m; Lilong 783.250 m; Ithai 770.05 m), with the gate closed and the volume stored in the storm held behind it: in the check case no building floor or opening shall flood (Clause 6.11), and the pumps shall deliver against that level. Where only an HFL is printed, that HFL is the design level and the highest reading reported above it, or surveyed from flood marks at the gauge, is the check level: the Nambul at Hump Bridge, 783.695 m; the Nambol at Nambol Thongkhong, the higher printed value, 774.700 m; and the Manipur river at Ithai, 769.320 m and 770.05 m. At Irilbung the flood level of 787.700 m is the design level, and the highest reading reported, 788.850 m (15 September 2025), is the check level until WRD corrects the printed HFL [TBC]. For the cases with the river at its 10% AEP level (Clause 5.8.4(a)) and for the minor-system tailwater of Clause 5.1.4(b), the river stands at its WRD warning level, transferred (Minuthong 785.900 m; Lilong 780.350 m; Irilbung 786.700 m; the Thoubal 778.915 m), or, at a gauge with no warning level printed, at the design level of this item. All of these are set by this Manual. The recorded level of the nearest gauge upstream applies unchanged at the outfall, except that between two gauges on the same river with no tributary joining between them it may be interpolated linearly by river distance (set by this Manual). On an ungauged river or stream, the level is the highest of the highest recorded level at the nearest WRD gauge on the same river, transferred; the flood marks of May 2024, May–June 2025 and September 2025, surveyed at the outfall with their source stated; and a hydraulic model under Clause 5.8.2(b); and no outfall shall be designed without the flood marks or the model (set by this Manual). The city's ground stands at about 790 m (AIIB, 2024), so on this Manual's reading drains near the Imphal river discharge within a metre or two of its highest flood level.
- Gravity outfalls closed. Every gravity outfall through a river bund, and every outfall to a drain, khong or pat that the river backs up, shall be taken as closed from the time the river reaches the outfall invert or the level at which its gate is shut, and in no case later than the time the river reaches its WRD flood level at the governing gauge, and shall stay closed for the whole of the river lock of this item. While the gates are shut, the area behind the bund drains only by storage and pumping (set by this Manual).
- Tailwater. The tailwater at the outfall shall be the higher of the river level beyond the gate or bund and the maximum level in the drain behind it, computed by routing the drain, with every pat, pukhri and low paddy field that it fills, as a closed storage for as long as the gates are shut, with the inflow of the whole catchment that drains to it, its storage as surveyed in its present condition, net of silt, solid waste, weed, phumdi and encroachment, and an outflow of no more than the pumping capacity that the operator confirms in writing is available in a storm, and in no case more than the installed capacity of the permanent pumps less the largest pump (set by this Manual). A pat or pukhri behind the gate starts the storm full to its outlet level (item (e)). Every pump, panel, generator and control shall remain operable with the river at the check level of this item and with the land behind the bund ponded (Clause 5.12.5).
- River lock. Portable dewatering pumps brought in for an event, and capacity that has been sanctioned or proposed but not commissioned, shall not be counted; they are a reserve for the failure of a station and for a breach. The outfall-closed check of Clause 5.10 applies with a single lock: the gate is closed for the whole of the 72-hour storm of Clause 5.10.2 and for as long after it as the river stays above the gate sill, or above the level at which the gate is shut if that is lower, taken from a river model or from WRD's stage record of the governing gauge in the floods of May 2024, May–June 2025 or September 2025 or in a comparable flood. Where no stage record has been analysed, the lock is not less than 7 days (168 hours) on the Imphal, Nambul, Iril, Kongba, Thoubal, Sekmai, Wangjing, Nambol, Khuga and Manipur rivers, and not less than 72 hours on a smaller stream (set by this Manual). The lock covers the whole of the 48- and 72-hour storms, so that storage and pumping handle the full storm volume (Clause 5.9.4). With the gate still closed, the volume stored in the storm shall be pumped down to the level at which the storm started within 48 hours of the end of the storm, the drawdown time of Clause 4.7, so that the storage is ready for the next storm while the river stays high (set by this Manual). A shorter lock may be used only where the outfall invert is above the check level of this item, or where an analysis of a WRD stage record under Clause 5.10.6 shows it and the Authority approves it. Catchments behind a bund take the AMC that Chapter 3 sets for them.
- Joint drain–pump–river analysis. Every DPR for the drainage of a town on the valley floor, and every development whose outfall drains to a pumping station, shall route the drains, the storage behind the bund, the pumps and the river together, with the river hydrograph at the governing gauge as the downstream boundary, for two cases: a short storm on the town with the river at its warning level, and the 72-hour storm with the river at its flood level and the gates closed for the lock of this item, and shall report the check case. The installed and confirmed capacity of each pumping station, its sump levels and the level at which its gate is shut shall be entered on the drain register (Clause 6.9) [TBC: no station list was found].
- Gate failure and breach. A breach of a river bund is a residual risk, not a design case: no drain, pump or storage is sized for it. Floor levels behind a bund, the pumping stations and the emergency routes shall be checked, and the result reported on Form 5-1, for a gate that fails open and for a breach, with the land behind the bund filled to the river level beyond it. The valley's recent floods were breach floods: 18 embankment breaches in May 2024, 17 of them later sealed; breaches of the Imphal river at Singjamei, Heingang, Bashikhong and New Checkon and at Keirang, Khabam and Lairikyengbam Leikai, and of the Nambul at four places, in 2024 and 2025; and a breach of the Iril at Kshetri Awang Leikai in September 2025 (all as reported). Land on a breach path is a hazard-first site (Clause 2.3.6(i)).
- (b) Imphal. For an outfall in Greater Imphal (the 151.38 km² of the Revised GIS Based Master Plan for Greater Imphal – 2043 (1st Modification), which is wider than IMC's area), where "the town is below the high flood level of Imphal river and hence there are embankment roads on both sides of the river to protect the settlement from seasonal floods" and where "Imphal river, Nambul river and Kongba river running in north-south direction have numerous tributaries through the town" (master plan):
- The Imphal river at Minuthong. Every outfall to the Imphal river in the city is bund-locked under item (a), with Minuthong as the governing gauge (design 786.900 m; check 788.400 m, or a higher level surveyed from the flood marks of 29 May 2024, when the river ran above it), and downstream of the city with Lilong (design 781.350 m; check 783.250 m). Every outfall in the city whose invert is below 788.400 m is a bund-locked outfall.
- The Nambul at Hump Bridge. The Nambul is "the main urban river", and "the rapid flows of water directed to the main urban river Nambul from its tributaries cannot be contained. As a result, the failure of river dikes causes waterlogging in the low-lying areas for several weeks" (AIIB, 2024). An outfall to the Nambul is bund-locked under item (a) at Thong Nambonbi (Hump Bridge): design 783.695 m, and check at the level surveyed from the flood marks of 29 May 2024, when the river ran above that HFL (as reported; the reading was not printed) [TBC]. The Nambul receives 72 drains that carry sewage, whose interception and diversion the State reports as completed (State report to the NGT in O.A. 606/2018, December 2025) (Clause 6.3.6(e); Clause 8.9).
- The Naga Nullah and the Waisel Maril. These city channels drain to the Nambul and are owned by no single body (Chapter 6, Clause 6.9). Market waste is dumped in the Naga Nullah, "which creates a stagnant pool all along the year" (master plan); its clogging flooded Nagaram, Laipham Khunou and Lairikyengbam Leikai in July 2024; and in April 2025 encroachments along the Waisel Maril, the Naga Nullah and the eastern bank of the Nambul from Keishampat to Keishamthong and Elangbam Leikai were ordered removed, with WRD to provide machinery, while the cleaning of the Waisel Maril was led by LDA (all as reported). An outfall to either channel shall take as tailwater the higher of the channel's level, routed with its whole catchment and its section as surveyed, net of silt and waste, and the Nambul level of this item at the channel's outfall; a desilting or widening that has been proposed but not completed shall not be counted.
- Lamphelpat, the Shamushang nallah and the Nambul. Lamphelpat is a pat being developed as regional flood storage with a pumped outlet. About 300 acres are being dredged under a work order of 9 November 2023 for two years, by a cutter-suction dredger, with WAPCOS as monitoring consultant, and with "provision for pumping of flood water from the Lamphel pat water body to the Nambul River through Shamushang Nalla during high flood season" (WRD site report, High Court PIL No. 8 of 2025). The NDB project is to "increase its water detention capacity, restore stormwater drainage system" and set up a "real time flood management system with a command center", at a cost of USD 87.84 million with a loan of USD 70.27 million (concept approval 17 November 2021); its summary records that "Coping measures undertaken in the form of pumping … are not adequate and the area remains waterlogged for many days every year" (NDB). A cost of about ₹650 crore and an area of 443 acres are also reported, and the funders are named differently in different reports (as reported). An outfall to Lamphelpat, or to a drain that ends in it, shall take as tailwater the pat's level under item (e), starting full to its outlet, with an outflow of no more than the Shamushang pumps that WRD confirms in writing are permanent and working, less the largest pump, and with gravity flow to the Nambul only while the Nambul at the Shamushang outfall stands below the pat. The storage made by the dredging, and the pumps and command centre of the project, are counted only once they are complete and WRD confirms the pat's stage–storage relation and the pumping capacity in writing; that storage belongs to the drainage system and is not credited to any one project. Lamphelpat is also a proposed source of drinking water, so no drain that carries sewage shall reach it without the interception of Clause 6.3.6(e).
- The Kongba and the Iril. Outfalls in Imphal East to the Iril are bund-locked under item (a) at Irilbung (design 787.700 m; check 788.850 m). No WRD level was found for the Kongba [TBC], so its outfalls take the ungauged rule of item (a). The largest discharge that MASTEC records in the valley is the Iril's, 532.488 m³/s at Moirang Kampu on 2 September 2000 (MASTEC).
- Projects counted when built. The AIIB project is to provide "547 km of both side stormwater covered drains" along the roads of Greater Imphal that "channelize the storm water … to the out fall (river)" (AIIB, 2024), and states no return period, intensity or outfall level. Each of its outfalls is a bund-locked outfall under item (a). No drainage master plan with a design level was found for Greater Imphal: the master plan has no storm-water drainage section.
- (c) The Loktak margin and its outlet. For an outfall in sub-area MN-A1 (Moirang, Ningthoukhong, Thanga, Ithai, Sugnu and Wangoo, and the land within the 236.21 km² of the Loktak Lake (Protection) Act, 2006) to Loktak, to a pat that fringes it, or to the Manipur river between Ithai and Sugnu, or to a drain that ends in one:
- The lake and its levels. Loktak is held up by the Ithai barrage of NHPC's Loktak project (105 MW; commissioned in 1983 according to most sources, with 1979 and 1986 also printed), which "permanently raised the average water level of Loktak Lake by about a metre" (as reported). Its levels conflict, and this Manual states the conflict without resolving it: a full reservoir level (FRL) of 768.5 m and a minimum drawdown level of 766.2 m (NHPC, as quoted); a minimum drawdown level of 766.01 m (CEA, as quoted); and an FRL of 769.63 m, with 768.50 m called the "flood level" (ORF, as reported) [U]. CEA's daily reports of August 2026 show the lake at about 767.46–767.73 m (as quoted), its ordinary monsoon level; it reached 768.5 m in August 2002 (as reported). NHPC's and LDA's stage records and the barrage's operating rule were not obtained [TBC].
- Design lake level. The tailwater is the lake level, static for the whole event: the Ithai HFL of 769.320 m (WRD, as reported) for design, checked at 770.05 m, the reading of 15 September 2025 (as reported), and in June to September never below the FRL (768.5 m, or a higher FRL that the operator confirms in writing) (set by this Manual). No fall of the lake during the storm shall be credited.
- Outfalls closed June to September. An outfall whose invert lies below the design lake level is closed from 1 June to 30 September: the storm is stored and pumped, and no gravity discharge is credited. Outside that period the lock of item (a) applies, with the lake level of this item in place of the river level. The pump-down of item (a) applies (set by this Manual).
- The Sugnu hump. The Manipur river's bed is 762.2 m at Ithai and falls below the barrage to a "deepest bed level of 756.7 m"; then "in a short stretch of about 800 metres, the bed level rises steeply upto 763.7 m and remains at the general elevation of 762.5 m … the outflow of the sediment is restricted" (MASTEC). At Ithai, "flow of the Manipur river during monsoon is of the order of 400 cumecs and river down below the barrage does not have the capacity to cope up with such flow, as a result, water is piled up upstream" (MASTEC). On this Manual's reading the rock sill controls the valley's only outlet whatever the barrage gates do, so no design shall assume that opening the barrage lowers Loktak or the river at an outfall during a storm unless NHPC's written records show it.
- The Chakpi backwater. The Chakpi "meets the Manipur River at a reverse direction, thereby checking the current … making inundation of the surrounding area of Sugnu extending upto Wangoo" (MASTEC). An outfall at Sugnu or Wangoo, or to the Chakpi near its confluence, takes as tailwater the higher of the Manipur river level at Ithai of this item and the Chakpi level from a model or from surveyed flood marks; no Chakpi gauge was found [TBC].
- Phumdi at outlets. Phumdi, which the Loktak Act defines as a "heterogeneous mixture of vegetation, organic debris and soil in floating condition" (s.2), drift and block outlets, gates and screens. Every outfall to Loktak or to a pat that carries phumdi shall have a screen or boom, designed under Chapter 9 (Clause 9.8), that keeps phumdi out of the gate, with machine access and a place to stack what it catches outside the lake; the flap gate shall be checked as held open by phumdi under item (a) (set by this Manual).
- The lake's law. Within the lake's extent the consents of item (h) apply: no discharge into the Core Zone without LDA's prior permission (s.20), and none of the activities that s.19 bars in the Buffer Zone.
- (d) Dam-release reaches. For an outfall to the Thoubal below the Mapithel dam (the dam of the Thoubal Multipurpose Project), to the Khuga below its dam, or to the Nambul below the Singda dam, or to a drain that ends in one:
- Consent and levels of the operator. Storm water shall not be discharged to a reservoir or its release reach without the written consent of its operator. The operator's levels shall be used as it gives them in writing; a level given in feet shall be converted at 1 ft = 0.3048 m exactly, with the conversion and the datum stated on Form 5-1.
- The Mapithel dam. WRD gave the dam's FRL as 880.7 m in September 2025, when the reservoir stood at 878.10 m; on 1 August 2015 it was reported at 876 m, "nearly 2 m above the spillways"; its spillway design discharge is reported as 2,240 m³/s, and the earth dam as 66 m high and 1,074 m long (all as reported). The 2015 report puts the spillway crest near 874 m, about 6.7 m below the FRL given in 2025 (NEER arithmetic), and the two reports do not reconcile [U]; the operator's levels in writing govern [TBC]. The Thoubal below the dam is also a bund-locked river under item (a) (design 779.915 m at the Thoubal gauge), and the higher tailwater of the two items governs.
- The Khuga and Singda dams. No level, spillway capacity or release record was found for the Khuga dam or for the Singda dam, which the CPCB names as the head of the polluted stretch of the Nambul (CPCB, 2025) [TBC].
- Release reaches. In addition to the cases of Clause 5.8.4, the site design storm (each AEP required) and the 72-hour storm shall be run with the river at the level that results from the largest recorded release of the dam, routed to the outfall, with the flow of the catchment below the dam as it occurred, and with the release placed before, during and after the site storm; until the operator states a larger recorded release and its duration, the release is the spillway design capacity (Mapithel, 2,240 m³/s, as reported; the Khuga and Singda dams, the operator's spillway capacity in writing [TBC]). The lock of item (a) applies for not less than 72 hours (set by this Manual). No attenuation by the storage of a reservoir shall be credited to the river below, and no dam gate shall be assumed to open earlier or wider than the operator's records show. Catchments that drain to a reservoir, its backwater or a release reach take the AMC that Chapter 3 sets for them.
- Warnings are not notices. No design shall rely on a notice or a warning of a release, on a reservoir being drawn down before a storm, or on a gate being opened early, late or partly: the release scenarios of this item govern (set by this Manual).
- (e) Pats and pukhris as receiving storage. For an outfall to a pat, a pukhri, a low paddy field that ponds or a detention pond, directly or through a drain that ends in it, among them Lamphelpat, Porompat, Takyelpat, Sangaipat, Kharungpat and Ikop pat, the pats of the State Wetlands Authority's priority list (Utra, Yaral, Waithou–Phumnom, Pumlen–Khoidum and Ikop–Kharung) and the public pukhris of the towns:
- Starting level. The waterbody starts every design storm full to its outlet level: the crest of its outlet weir, the sill of its gate or the invert of the khong that drains it, or, where it has no defined outlet, its highest monsoon water line surveyed and tied to a Survey of India benchmark, and in every case not less than the highest level recorded at it (set by this Manual). This is the rule of the adjoining edition of this series for its floodplain lakes, which it took from a design that assumed the lake "is full and the drain is also flowing full" (as quoted there): a pat that has filled in the first storm of a spell is full for the next.
- Design level. The tailwater for the major-system and storage cases is the level reached when the inflow of the waterbody's whole catchment is routed through its stage–storage relation from that starting level, with its outlet closed for as long as the river, lake or khong beyond it stands above the outlet (items (a) and (c)), and with the project's discharge included (Clause 5.12.3). The stage–storage relation shall be surveyed: none was found for Lamphelpat or any other pat or pukhri in the State, and the inventory of about 4,000 water bodies made after the NGT's order of 22 May 2020 records that "Ground truthing, engineering surveys, and quality monitoring … are pending" (DoECC, 2025-26) [TBC]. The minor-system tailwater is the starting level.
- Closed outfall. Where the outfall invert is below the design level of this item, the outfall is closed for the whole storm (Clause 5.9.4), and where the waterbody itself drains through a bund-locked outlet or to Loktak, the lock of item (a) or the closure of item (c) applies to both.
- Storage is the system's. The storage of a pat or pukhri is part of the drainage system: it shall not be credited to one project, and no project shall reduce it (Chapter 7). A pukhri with no outlet is a closed basin, and an outfall to it is closed for the whole storm. Low paddy land that ponds behind a gate is counted in the routing as it is when the design is made; storage lost when paddy land or wetland is filled is replaced under the compensatory storage rule of Chapter 7, not by an outfall. Engineered storage is a detention pond, never a pukhri or a pat; a pat developed as flood storage, such as Lamphelpat, remains a pat. No drain that carries sewage shall discharge to a pat or pukhri without the interception and screens of Clause 6.3.6(e) and Clause 8.9.
- (f) Hill streams. For an outfall to a khong or other hill stream in sub-areas MN-B and MN-C, in the hill parts of MN-C1 or on the hill fringes and hillocks of the valley, such as the streams of Tamenglong, Noney, Ukhrul, Senapati, Kangpokpi, Chandel and Churachandpur and the streams that come down to the valley floor and to Loktak, or to a drain that ends in one:
- Design level. These streams have no gauge or published flood level [TBC]. The tailwater for the major-system and storage cases shall be the highest of: (i) the 1% AEP level at the outfall from a study of the stream, made with a hydrograph method of Chapter 3 for the whole catchment above the outfall with the rainfall of its sub-area in Annex 2A, the bulking factor of Clause 6.3.6(g) on the peak flow and the crossings downstream blocked as Clause 6.3.6(h) requires, routed through a hydraulic model of the channel as surveyed, net of encroachment, silt, slide debris and solid waste; (ii) the level at the outfall of any flood study of the stream made by or for WRD, PWD or the local body [TBC]; and (iii) the highest flood level surveyed at the outfall from flood marks, such as those of the Khoupum valley flood of 15 July 2025 or of a later flood, and from the records of the local body, WRD or the Deputy Commissioner, with its source stated. No outfall to such a stream shall be designed without items (i) and (iii) (set by this Manual).
- Bed level and siting. The designer shall survey the bed at the outfall and for at least 100 m upstream and downstream and state the range within which it has moved. The outfall invert, and the seat of any flap gate on it, shall stand at least 0.5 m above the highest bed level found within 50 m downstream; the foundation shall be taken below the scour depth of Chapter 9 (Clause 9.6) for the 1% AEP flow with the bulking factor; and the outfall shall be built into the bank and not project into the active channel (set by this Manual). Where a hill stream drops its load on reaching the valley floor, the silt trap of Clause 6.3.6(m) shall be placed above the outfall: the hill streams "flow down with steep slope for a short distance before meeting the Loktak Lake … load carrying capacity is high which causes siltation of the lake" (MASTEC). A slide, a cut slope or fill on the Disang shale, and the path of a channel shift on a foothill fan, are hazard-first sites (Clause 2.3.6(i)), and no outfall structure shall be placed on them.
- Closed outfall. Where the outfall invert is below the design level of this item, the outfall-closed check of Clause 5.10 applies with a single lock that lasts for the design storm plus the stream's recession, computed under item (i) for as long as the stream stays above the invert, and not less than 24 hours; where no hydrograph of the stream has been computed, the lock lasts for the whole storm (set by this Manual). Where the hill stream itself ends at a bunded river on the valley floor, at Loktak or at the Barak, the lock of item (a), (c) or (g) governs. Where a stream leaves the State, for Nagaland, Mizoram or Myanmar, no lowering of its level downstream shall be assumed.
- (g) Jiribam and the Barak. For an outfall in sub-area MN-C1, the Jiribam plain, to the Barak or the Jiri, or to a drain or stream that ends in one:
- River levels. CWC has one site in the State: the Barak at Chotebekra, printed under Imphal East and now in Jiribam district (NEER reading), a level-monitoring site with an HFL of 32.1 m (31 July 1989) (SANDRP, 2018, as reported); a danger level of 26.2 m is given only in the press (as reported). Neither states its datum [TBC]. The river level for the major-system and storage cases is the 1% AEP level at the outfall from a hydraulic model under Clause 5.8.2(b), and not less than 32.1 m, transferred; for the 10% AEP case it is not less than 26.2 m until CWC confirms the danger level [TBC] (set by this Manual). No gauge was found on the Jiri [TBC]: an outfall to it takes the ungauged rule of item (a), and near its confluence not less than the Barak level of this item.
- The Barak-valley lock. The rule of the adjoining edition of this series for the Barak plain downstream applies in full: an outfall through a bund, gate or pumping station to the Barak, or to the Jiri where the Barak backs it up, is closed for the whole of the 72-hour storm and for as long after it as the river stays above the gate sill, not less than 7 days (168 hours) where no stage record has been analysed, and not less than 72 hours on a smaller stream that the Barak does not back up; receiving storage starts full to its outlet (item (e)); and the stored volume is pumped down within 48 hours with the gate still closed (set by this Manual). The Barak at Chotebekra and at Lakhipur downstream set their highest levels on the same day, 31 July 1989 (as reported), so one flood reads alike on both sides of the border.
- Below Jiribam. The Barak plain downstream, with its gauges at Lakhipur (HFL 26.96 m, 31 July 1989) and Fulertal (26.39 m, 21 July 2004) (as reported), is outside this Manual: the Assam edition governs those reaches.
- (h) Consents and lines.
- WRD and the bunds. No outfall structure, gate, pumping station or drain shall cut, cross, alter or discharge through a river bund, a flood channel or a pumped outfall of WRD without WRD's written permission as the owner of the works; no Manipur statute on embankments, and no written procedure or form for this permission, was found during research [TBC]. Storm water shall not be discharged to a drain of another body without that body's written consent: a municipal drain of IMC or another urban local body, under its bye-laws on the Model and the Manipur Municipalities Act, 1994, whose drainage sections were not read [TBC]; a road drain or culvert of PWD or a national-highway agency; the interception works on the Nambul, of DoECC; and a city channel, flood channel or Lamphelpat, of WRD (Chapter 6, Clause 6.9) (set by this Manual). Where consent is given, the discharge shall not exceed the rate the consent allows; the tailwater is the higher of the channel's design water level as its owner states it in writing and its level in the coincident case of Clause 5.8.4, computed from all the storm water it receives and with its downstream boundary at the level of items (a) to (g); the channel shall be taken in its present condition, net of silt, encroachment, solid waste and weed, and a widening, resectioning or diversion that has been proposed but not completed shall not be counted; and the outfall shall have a flap gate (Clause 5.11) where the design water level or the computed level is above the outfall invert.
- Loktak. Within the 236.21 km² of the Loktak Lake (Protection) Act, 2006 (Keibul Lamjao National Park, 40 km², and the Takmu fishery farm, 5 km², are outside it), no one shall "discharge or emit any sewage or domestic waste into the lake" in the Core Zone of 70.30 km², a "No-Development Zone or Totally Protected Zone", "except with the prior permission of the authority" (ss.3 and 20); in the Buffer Zone the Act bars the "Discharge of untreated wastes and effluents from industries, cities or towns and other human settlements" and "Land reclamation, bunding or disturbing the natural course of drainages" (s.19(iv) and (vi)). An outfall, drain or bund within the lake's extent therefore needs LDA's prior permission, and the High Court's special bench orders of 17 July 2019 and 25 February 2022 against development in or around Loktak "without the Court's leave" (as reported; the case number was not found [TBC]) are to be checked for the site. The Act does not reach upstream of its 236.21 km².
- Flood zones. Bye-law 93 of the Model [TBC: confirm the number and text in the bye-laws the local body has notified] requires "the previous permission of the Flood Zoning Authority constituted under the Flood Plain Zoning Act, 1978" for any activity in a prohibited or restricted area. No Flood Zoning Authority, and no prohibited or restricted area, was found constituted or notified (NEER reading), and the demarcation of flood zones "is yet to be done" (as reported, June 2026), so that permission is needed only where a zone has been notified, and none has. The 1% AEP levels of this clause are offered as an input to any future zoning, not as a zone.
- The lines that bind. The designer shall check every outfall against the lines that bind at the time of design (Chapter 7): the buffers of the river table of bye-law 93, measured from mid-stream "or 6 m from outer toe of bund, whichever is further from mid-stream" on the bunded rivers, and from mid-stream only on the Merakhong, the Kongba and the Nambol; the corridor of Clause 7.4; and the plinth of bye-law 94 [TBC: confirm the number and text in the bye-laws the local body has notified], "above 1m above the highest flood level of the surrounding areas" in the "high Flood Risk Areas identified in the Master Plan of the towns". The risk-informed master plans that would show those areas were not read [TBC] and no local authority's highest flood level was found for any town [TBC], while the September 2025 readings passed the printed HFLs at Lilong and Ithai (as reported), so the 1% AEP level of this clause, not below the check level of item (a), and the floor levels of Clause 6.11 govern where they are higher.
- Paddy land and wetlands. An outfall, drain or storage built on paddy land or a wetland in the valley converts it, and the Manipur Conservation of Paddy Land and Wetland Act, 2014 counts "drainage channels, ponds, canals, bunds and ridges" as part of paddy land (s.2(c)): the conversion needs the approval of the Local, District and State Level Committees, and "no local authority shall grant any licence or permit … for carrying out any activity or construction in a paddy land, converted or reclaimed in contravention" of the Act (s.12). The (Third Amendment) Bill, 2026 is a Bill, not law, and is not applied by this clause. Of the pats, the Yaral, Utra and Waithou–Phumnom pats have draft notifications under the Wetlands (Conservation and Management) Rules, 2017 (DoECC, 2025-26); until they are final, no prohibition of those Rules applies to them (NEER reading), and the designer shall check their status with the Manipur State Wetlands Authority.
No pump, gate, barrage or dam operation that helps drainage, such as pumping a drain, pat or pukhri down before a storm, closing a gate late, opening a gate while the river is higher than the land behind it, or opening the Ithai barrage or a dam's gates early, shall be assumed unless the operator's written records show it. Where the outfall invert is below the tailwater of this clause, the outfall shall have its own flap gate (Clause 5.11) and, where the outfall-closed check requires it, pumping (Clause 5.12), with the pumped volume included in the routing of the drain, the pat or the river (Clause 5.12.3). Pumping shall not be used to move water into a pat, a pukhri or another catchment without the consent of its custodian.
Commentary. In large continental river basins, a site storm and a river flood are usually treated as roughly independent. That is the basis of tables of coincident frequencies such as FHWA HEC-22 Table 7.3. Manipur's rivers and towns break that assumption, because the same rain spell fills the rivers, the pats and Loktak and falls on the towns behind the bunds. The valley's floods follow spells of five to twelve days of rain on the hills, which are 70% of the catchment that drains through the valley: 28 July to 1 August 1989, when Imphal recorded 158.6 mm on 30 July; 22 to 28 September 1997; 24 August to 3 September 1999; and 26 August to 6 September 2000 (MASTEC; IMD Extremes). WRD's rule of thumb is that 135 mm in three days at Kangpokpi floods the valley (as reported). In 2024 and 2025 the rivers stood above their flood levels for days: the Imphal river and the Nambul were above danger from 28 May 2024 and above their highest flood levels on 29 May (as reported); in May and June 2025 the Imphal river breached at four places and the Iril was above danger on 1 June (as reported); and on 15 September 2025 the Imphal river at Lilong and the Manipur river at Ithai stood above their printed highest flood levels (as reported). Loktak, held up by the Ithai barrage, stays high for the whole season. Two of these floods, on 28–31 May 2024 and 30 May–2 June 2025, came before the south-west monsoon's normal onset at Imphal (as reported), so the coincident case is not confined to June–September. The two cannot be treated as independent, and a local storm can fall before, during or after the river peak. Clause 5.8.4 therefore pairs a design event on one side with a 10-yr event on the other, in the same way as Clause 2.12(b). This pairing has no direct precedent. It is more severe than an independence assumption would give.
Clause 5.8.3 reflects the dams on the rivers that feed the valley. The Mapithel dam of the Thoubal Multipurpose Project, an earth dam reported as 66 m high and 1,074 m long with a spillway design discharge of 2,240 m³/s (as reported), stands above Thoubal town. In the flood of late July and August 2015 its reservoir was reported at 876 m on 1 August, "nearly 2 m above the spillways", after rain in Imphal West 46% above normal on 23 to 27 July (as reported); in September 2025 WRD gave its FRL as 880.7 m with the reservoir at 878.10 m (as reported). The two reports put the spillway and the FRL more than 6 m apart and do not reconcile (NEER arithmetic) [U], and no operating rule or release record of the dam was obtained [TBC]. No level, spillway capacity or release record was found for the Khuga dam on the Khuga, which joins the Manipur river at the south of the valley, or for the Singda dam on the Nambul, above Greater Imphal [TBC]; the CPCB names the Singda dam as the head of the Nambul's polluted stretch (CPCB, 2025), and the CAG audited the Singda and Khoupum dams and the Sekmai and Imphal barrages in its audits of 2002 and 2008 (as listed). The Ithai barrage of NHPC holds up Loktak and so sets the level of the whole south of the valley (Clause 5.8.5(c)); it is a barrage, not a storage dam, and its gates do not lower the lake below the control of the rock sill downstream (MASTEC; NEER reading). Until the operators give their levels and releases in writing, Clause 5.8.5(d) uses the largest recorded release or the spillway design capacity, with the flow of the catchment below the dam as it occurred in the same event. The river levels used in this Manual are WRD's as printed in the press, and CWC's single Manipur level as transcribed by SANDRP; their datums and gauge zeros are to be confirmed with WRD and CWC [TBC].
Clause 5.8.5 is set by this Manual. In Manipur the tailwater at a town outfall is set not by the tide but by a river held above the town behind its bunds, by a lake held up by a barrage and a rock sill, by a pat that is already full, by the release of a dam, or by a hill stream in spate, and no document found during research gives a design level or a closure duration for any of them. No design standard for any town drain in the State was found either: the master plan for Greater Imphal has no storm-water drainage section, and the AIIB road and drainage project and the NDB Lamphelpat project state no design storm (AIIB, 2024; NDB). The Flood Plain Zoning Act, 1978 has produced no notified zone, and no 1% AEP level has been published for any reach of any river in the State (Chapter 7).
The first case is the bund-locked outfall. Item (a) joins two forms that the series already uses: the river-locked form of the plains editions, which asks for the operator, the sills, crests, pumps and closing levels and ties every level to a gauge, and the valley-floor form of the mountain editions, which treats the gravity outfalls as closed from a declared river stage and asks for one analysis of the drains, the pumps and the river together. The levels come from WRD's gauges as the press prints them, without a datum, so each is "as reported". The design and check levels follow from what the records show. On this Manual's reading WRD's flood level is the stage at which its river is in flood, and the bunded city discharges within a metre or two of it, so the design case closes the gates at that level; where two flood levels are printed for one gauge the higher governs, because a tailwater set too low floods the town, while one set too high only costs storage. The highest flood levels are the check case, not the design case, because they are not stable: in September 2025 the river passed the printed highest levels at Lilong and at Ithai, and the printed level at Irilbung is below its own flood level. The warning level carries the 10% AEP case because no frequency analysis of any WRD gauge was found; it is the lowest stage that WRD reports for a river in flood (NEER reading). The lock is the heart of the clause. Where no stage record has been analysed, the minimum on the valley's main rivers is 7 days, because the valley's floods follow rain spells of five to twelve days (MASTEC), "the failure of river dikes causes waterlogging in the low-lying areas for several weeks" (AIIB, 2024), and the only outlet carries about 400 m³/s while the rivers above it bring more (MASTEC); 7 days is also the lock that the adjoining Barak-valley edition and the valley-floor editions of this series set for their main rivers. On a smaller stream, which rises and falls faster, the minimum is 72 hours, the length of the longest design storm. The pump-down of 48 hours with the gate still shut is the drawdown time of Clause 4.7: storage that is still full when the next storm of the same high stage arrives fails in the event that matters more. Pumps are credited only as permanent, working and confirmed, less the largest unit, because the one pumped outfall described in the sources, at Lamphelpat, is recorded as "not adequate" (NDB). A breach is not a design case: no drain can be sized for a river entering the town, so item (a) asks for the check and the report, and leaves the defence to WRD's bunds and to the floor levels of Clause 6.11. A designer with an analysed WRD stage record can justify a different lock under Clause 5.10.6.
The second case is Imphal. Item (b) names the city's rivers and channels because the capital drains through them, because their bunds and pumps belong to WRD while the channels above them belong to no single body, and because the works that will change them, the AIIB drains and the NDB Lamphelpat project, were not complete when research was done; the clause counts them only once they are. Lamphelpat is the worked example of a pat used as flood storage with a pumped outlet, not a detention pond: it is a natural lake being dredged and pumped, its storage is the system's, and it is also to be a source of drinking water, so sewage is intercepted before it.
The third case is the Loktak margin. Item (c) takes the lake as a static tailwater for the event, because the lake changes over weeks and the storm over hours. The lake's levels conflict, and the Manual does not choose between NHPC's FRL of 768.5 m and the 769.63 m reported by ORF. It takes WRD's highest flood level at Ithai, 769.320 m, which lies between them, for design, and the September 2025 reading of 770.05 m for the check, so that the rule does not depend on which FRL is right. An outfall below that level is closed from June to September because Loktak stands high for the whole of the south-west monsoon, from its onset at Imphal on 5 June to the end of September, and because the outlet is held by the Sugnu hump: whatever the barrage gates do, the rock sill limits how fast the lake can fall, and the Chakpi, entering against the current, backs the water up to Sugnu and Wangoo (MASTEC). Phumdi are part of the lake and block its outlets, so the clause asks for screens.
The fourth case is the release reach. Item (d) applies the reservoir and release-reach rule of the hill editions of this series to the Mapithel dam on the Thoubal and to the Khuga and Singda dams: the largest recorded release, or the spillway capacity until the operator gives one, placed before, during and after the site storm, with no credit for warnings, drawdown or attenuation. The only levels found for the Mapithel dam are two press reports that do not reconcile, and none was found for the other two dams.
The fifth case is the pat and the pukhri. Item (e) treats them as storage that belongs to the drainage system and starts every storm full to its outlet, as the adjoining edition does for its floodplain lakes. The valley was once a field of pats: "there were nearly 500 lakes in Manipur Valley", and Lamphelpat, Porompat, Takyelpat, Sangaipat, Kharungpat and Ikop pat are among those degraded or disappearing (MASTEC). The master plan for Greater Imphal shrinks its wetlands from 374.48 ha to 232.21 ha and its agricultural land from 5,616.53 ha to 2,604.70 ha by 2043, while its water bodies grow from 563.54 ha to 643.42 ha (master plan). The storage lost with the paddy land is replaced under the compensatory storage rule of Chapter 7, not by the outfall. No stage–storage relation was found for any pat, so the clause asks for a survey rather than a figure.
The sixth, seventh and eighth cases are the hill streams, Jiribam and the consents. Item (f) follows the hill-stream rule of the hill and mountain editions of this series: a study with the bulking factor, surveyed flood marks, an invert at least 0.5 m above the highest bed level and a lock of at least 24 hours, because these streams fall within hours of the rain stopping, but carry the silt that fills Loktak (MASTEC). Item (g) carries the Barak-valley rule of the adjoining edition onto the Jiribam plain, because it is the same plain and the same river, and its single CWC gauge set its highest level in the same flood of July 1989 as the gauge downstream. Item (h) asks for WRD's permission and the owner's consent because a design that discharges through a bund or into another body's drain cannot be checked without them, and because no rule divides the drains of the State's towns (Chapter 6). The lines of item (h) decide where an outfall can be built, not its level: the bye-law 93 buffers, the Loktak Act's zones and the paddy-land Act bind where they apply, and the floor levels follow Clause 6.11 because no "highest flood level" of the kind that bye-law 94 refers to has been fixed for any town.
5.9 Joint-probability cases
5.9.1 Every element draining to a tidal or backwater-affected outfall shall be checked for the cases below. The most severe governs each design quantity: storage, water level, pipe size and pump capacity.
Table 5.2 — Joint-probability cases for tidal and riverine outfalls
| Case | Rainfall | Tailwater | Applies to | Basis |
|---|---|---|---|---|
| J1 | Minor-system design AEP, Tc to 24 h | MHWS + SLA (tidal curve) | Minor system | Clause 2.12(a); Clause 5.7.1 |
| J2 | 1% AEP, all durations of Clause 2.5.2 | HAT + surge + SLA | Major system, detention, tanks, pumped systems | Clause 5.7.1 |
| J3 | 10% AEP, 48 h | 1% AEP still-water level + SLA | Major system, detention, tanks, pumped systems | Clause 2.12(b) |
| J4 | Design AEP, 48 h (72 h reported) | Tidal curve per J1 with two 6 h lock windows (Clause 5.10) | All storage and every gated or tide-affected outfall | Clause 5.10 |
| R1 | Site design AEP | River at 10% AEP level | Riverine outfalls | Clause 5.8.4(a) |
| R2 | Site 10% AEP | River at design-AEP level | Riverine outfalls | Clause 5.8.4(b) |
5.9.2 For storage elements, the 48- and 72-hour storms shall be run with the J2 and J3 tailwaters (Clause 2.5.3).
5.9.3 For tidally influenced riverine outfalls, R1 and R2 shall be run with the river model's downstream boundary at the J1 tidal curve. The Authority may also require them at J2.
5.9.4 Where tailwater is constant at a level above the outfall invert for the whole storm, the case is treated as a fully closed outfall. Storage and pumps shall then handle the full storm volume.
Commentary. Clause 2.12 sets two joint cases. Case (a) is design rainfall with MHWS plus the sea-level allowance. Case (b) is the 10-yr, 48-hour storm with the 1% still-water level. This Manual adds HAT plus surge for major-system design (Clause 5.7.1). Case J2 combines these. J4 is the outfall-closed check, which tests the timing of tide against the storm rather than a single level. Rainfall and surge share a cyclone cause, so they cannot be treated as independent (Clause 2.12 commentary). These cases are simple surrogates, to be replaced when a statistical joint analysis of IMD rainfall and tide-gauge records is adopted.
5.10 Outfall-closed (tide-locked) storage check
5.10.1 Where it applies. The check applies to:
- every storage facility;
- every minor- and major-system element; and
- every pumped system
whose outfall invert is below HAT + surge + SLA, or which drains to a reach subject to tide-lock or sand-bar closure (Clause 5.13).
5.10.2 Storm. Use the 48-hour design storm built per Clause 2.9.2 (peak day last), at:
- the AEP of the element: 1% AEP for detention, tanks and the major system; the minor-system AEP for minor drains; and
- AMC III.
The 72-hour storm shall also be run and reported.
5.10.3 Lock windows. Unless a site study under 5.10.6 gives otherwise:
- (a) the outfall is closed for two consecutive lock windows of 6 hours each, centred on two consecutive high tides of the local tidal curve. For a semi-diurnal tide, the window starts are therefore about 12.4 hours apart.
- (b) During each lock window, gravity discharge is zero.
- (c) Between lock windows, gravity discharge is computed against the J1 tidal curve, including the head loss of the flap gate and any non-return valve.
- (d) The first lock window shall be placed so that it is centred on the peak 1-hour block of the final 24 hours of the storm. A second run with the first window starting at that peak block shall also be made. The more severe governs.
5.10.4 Requirement. Storage plus pumping (where provided) shall hold the inflow so that, throughout the check:
- (a) the maximum stage in any detention facility stays below its emergency spillway crest, so the spillway does not operate. Where the outfall-closed stage is higher than the 1% AEP maximum water level of the free-outfall design, it becomes the facility's 1% AEP maximum water level for Clause 4.9.3, and the spillway crest, freeboard and wall height are set from it;
- (b) the maximum stage in the minor and major systems meets the Chapter 6 limits: building floor levels, and street depths of no more than 150 mm at the crown and no more than 350 mm at the deepest point; and
- (c) no property connection surcharges above the lowest opening it serves, or a non-return valve is fitted under Clause 5.11.
In volume terms, over each lock window and the full storm:
V_inflow ≤ V_storage available + V_pumped + V_gravity (between locks)
This shall be demonstrated by routing, not by a single volume balance. The release from each facility after a lock window ends may exceed the release caps of Chapter 4, because the facility is emptying into a drain that has just reopened. That release shall be included in the downstream analysis (Clauses 5.4 and 5.9).
5.10.5 Drawdown after the storm. After the second lock window, the storage shall drain under the J1 tidal curve. The drawdown requirement of Clause 4.7 shall be met, with pumping where gravity cannot meet it (Clause 5.12).
5.10.6 Site study. A longer or shorter lock may be used where a site study gives a time series of still-water level for the design case. The study may use a calibrated hydrodynamic model, gauge records of past events, or a surge hindcast. Locks shorter than the default require the Authority's approval. A longer lock shall be used where:
- sand-bar closure (Clause 5.13) or river backwater (Clause 5.8) keeps the outfall closed for longer; or
- the gauge record shows tailwater above the outfall invert for more than 6 hours per tide in comparable past events.
Figure 5.3 — Outfall-closed check: 48-hour storm with the peak day last (Clause 2.9.2), tailwater of astronomical tide plus surge, two 6-hour design lock windows, and the resulting stage upstream of the flap gate. Illustrative — not design values. Original drawing for this Manual, adapted from the tidal tailwater and joint-probability concepts of MoHUA/CPHEEO Manual on Storm Water Drainage Systems (2019), Part A, §6.3.6.
Commentary. The outfall-closed check is the distinctive Manipur requirement in this Manual. In Manipur it applies where an outfall is shut not by the tide but by a river held above the town for days or weeks behind its bunds, by Loktak standing above the outfall for the whole season, by a pat that is already full, by the release of a dam upstream, or by a hill stream in spate. The Imphal river at Minuthong has a highest flood level of 788.400 m against city ground of about 790 m (WRD, as reported; AIIB, 2024), and it ran above that level on 29 May 2024 (as reported); "the failure of river dikes causes waterlogging in the low-lying areas for several weeks" (AIIB, 2024); Lamphelpat "remains waterlogged for many days every year" although it is pumped (NDB); and the floods of the valley follow rain spells of five to twelve days: 28 July to 1 August 1989, 22 to 28 September 1997, 24 August to 3 September 1999 and 26 August to 6 September 2000 (MASTEC). That is why Clause 5.8.5 replaces the two 6-hour windows described below with a gate closed for the whole 72-hour storm and for as long as the river stays above the sill, not less than 7 days on the valley's main rivers and on the Barak and not less than 72 hours on a smaller stream or a release reach where no stage record has been analysed; an outfall below the design level of Loktak closed from 1 June to 30 September; a pat or pukhri full to its outlet at the start; a pump-down within 48 hours with the gate still shut; and a lock of at least 24 hours at a hill-stream outfall. A rate rule cannot help when there is no outlet: an orificed basin behind a closed gate simply fills.
The default of two consecutive 6-hour locks has no direct precedent. It represents gravity outfalls failing to discharge for about half of each tidal cycle around the two high tides nearest the storm peak. Figure 5.3 shows why both windows matter. The first lock catches the storm peak. The second arrives before the storage has drained, so the stage rises again.
Placing the first window on the rainfall peak is deliberately unfavourable. Cyclone rainfall and surge share a cause, and Clause 2.12 already treats them as dependent. The check replaces neither the J2 and J3 level checks nor the downstream analysis; it adds a test of timing and volume.
5.11 Flap gates, tide gates and non-return valves
5.11.1 Where required. A flap gate, tide gate or equivalent non-return device is required on every outfall whose invert is below the 1% AEP still-water level (Clause 5.7.3). It is also required on outfalls into irrigation channels under Clause 5.8.5.
5.11.2 Hydraulics. The design shall include:
- the gate's head loss and opening head, from the manufacturer's certified head–discharge curve; and
- the reduction in effective outfall capacity when the gate is partly open.
Gates shall not be assumed to seal perfectly in the outfall-closed check unless they are tested.
5.11.3 Construction.
- (a) Gates, hinges and seats shall be of corrosion-resistant materials suitable for seawater (Clause 4.12.5).
- (b) The gate shall be set so that sand, silt or debris on the downstream side cannot hold it shut or open. Where the bed is mobile, the gate invert shall be raised above the bed, or the approach shall be protected.
- (c) A trash screen shall be provided upstream where the gate could be jammed by debris.
- (d) A stop-log slot or penstock shall be provided upstream for maintenance isolation on outfalls larger than 600 mm.
- (e) The gate chamber shall be accessible at all tides, with its access above HAT + surge + SLA.
5.11.4 Non-return valves on property connections. A non-return valve, or a backwater valve with an accessible cleaning eye, is required on every property drainage connection where the lowest opening served is below:
- the major-system tailwater (J2) at the point of connection; or
- the maximum stage in the outfall-closed check (Clause 5.10).
Basement drainage shall in addition be pumped to a level above both, with its own non-return valve.
5.11.5 Inspection. Gates and valves shall be inspected and operated:
- before 31 March each year;
- after every event in which they closed against a storm flow; and
- as set in the maintenance plan (Chapter 10).
Commentary. The requirement for gates below the 1% still-water level is set by this Manual. The construction details follow common coastal-drainage practice. A gate that is jammed open by debris lets the tide into the drain. A gate held shut by a sand bank turns a gravity outfall into a dead end. In Manipur the outfalls do not cross a beach, but most outfalls on the Imphal valley floor pass through a gate, flap gate or culvert (ithong) in a WRD river bund (pan), and the gates and the pumps beside them are the towns' defence against the rivers. The valley's recent floods came through and over the bunds: 18 embankment breaches in May 2024; breaches of the Imphal river at Singjamei, Heingang, Bashikhong and New Checkon and of the Nambul at four places in 2025; and a breach of the Iril at Kshetri Awang Leikai in September 2025 (all as reported). The one pumped outfall described in the sources, from Lamphelpat to the Nambul through the Shamushang nallah, is recorded as not enough: "Coping measures undertaken in the form of pumping … are not adequate and the area remains waterlogged for many days every year" (NDB). The bunds and the pumping are WRD's, while the drains behind them are IMC's, another local body's, PWD's or DoECC's; no Manipur statute on embankments, no list of the valley's gates and pumping stations and no WRD rule for operating them was found during research [TBC], so a gate and the drains behind it can belong to different bodies and nobody may be bound to close it in time. The 31 March inspection date is set ahead of the monsoon.
5.12 Pumped outfalls
5.12.1 When required. Pumping shall be provided where gravity discharge cannot meet:
- the outfall-closed check of Clause 5.10;
- the drawdown requirement of Clause 4.7; or
- the J2 and J3 cases.
Pumping shall not be used where a gravity solution meets these requirements.
5.12.2 Capacity.
- (a) The duty pumps together, with the storage provided, shall pass every case of Clause 5.9 (including J4), demonstrated by routing.
- (b) Standby capacity at least equal to the largest duty pump shall be installed (duty + 1 standby as a minimum).
- (c) Pump capacity shall be stated at the static head for the J2 tailwater, not at mean tide.
5.12.3 Effect on the receiving water. Pumped discharge to a river, canal or creek shall be included in the river or creek level analysis of Clause 5.8. Pumping that raises the receiving water level above the acceptance criteria of Clause 5.5 elsewhere is not permitted.
5.12.4 Power supply. Pumping stations shall have either:
- two independent power supplies; or
- standby generation for 100% of the duty capacity, with on-site fuel for at least 72 hours of duty operation.
Changeover shall be automatic.
5.12.5 Flood immunity. Electrical panels, control equipment, generators and fuel storage shall be set above the higher of:
- the 1% AEP flood level + 0.5 m; and
- HAT + surge + SLA + 0.5 m.
Access to the station shall remain usable in the 1% AEP event.
5.12.6 Discharge arrangement. Rising mains shall discharge:
- over a level above the J2 tailwater; or
- through a non-return valve and a flap gate.
The arrangement shall prevent back-siphoning.
5.12.7 Controls and monitoring. Each station shall have:
- automatic level control;
- remote alarms for high level, pump failure and power failure, sent to the operator; and
- a level and run-time log kept for at least 5 years.
Wet wells shall be sized to keep pump starts within the manufacturer's limits.
5.12.8 Screens. Inlet screens shall be provided with a cleaning method that works during a storm (a mechanical rake, or duplicate screens).
5.12.9 Testing. Every pumped outfall shall be test-run at full duty, including on standby power, before 31 March each year. Private pumped systems shall be covered by a registered maintenance declaration (Chapter 10).
Commentary. Duty + standby, 72 hours of fuel and flood-immune electrics have no single direct precedent and are set by this Manual. The 72-hour fuel figure matches the longest mandatory design storm (Clause 2.5.2). A pump station that depends only on grid power can stop exactly when it is needed, because supply to flooded areas is often switched off for safety. Singapore's April 2025 amendments added annual maintenance declarations for pumped detention tanks (PUB Addendum No. 3). Clause 5.12.9 and Chapter 10 adopt the same approach. Clause 5.12.3 prevents pumping that simply moves water from one tide-locked drain into a tide-locked river.
5.13 Sand-bar closure of river mouths
5.13.1 Where it applies. This clause applies to outfalls into any river or creek whose mouth is subject to seasonal sand-bar closure. That includes the mouths of the coastal States (there is none in Manipur: Clause 5.1.4), and any other mouth listed in Annex 5B.
5.13.2 Assumption at the start of the monsoon. The mouth shall be assumed closed by a bar at the start of the April–October season, at the crest level of the most recent pre-monsoon survey. This applies unless the Water Resources Department certifies that:
- a mouth-maintenance programme (dredging, bar cutting or training walls) has kept the mouth open at the start of each of the previous three monsoon seasons; and
- the programme is funded for the current season.
5.13.3 Tailwater with a closed mouth. With the mouth closed, the tailwater at the outfall shall be the higher of:
- (a) the tidal tailwater of Clause 5.7; and
- (b) the level in the river reach behind the bar, computed with the bar as a weir at its surveyed crest level. That level shall include the river flow of Clause 5.8 and the head needed to pass the flow over or through the bar.
5.13.4 No credit for emergency cutting. Bar cutting or breaching during the storm shall not be assumed in design, unless the Water Resources Department has a documented operating procedure, with equipment stationed for it. Where it does, the bar may be assumed lowered to the procedure's target level only after the time the procedure states.
5.13.5 Outfall-closed check. Where the closed-mouth level of 5.13.3(b) exceeds the outfall invert for longer than the default lock windows, the lock duration of Clause 5.10 shall be extended to that period.
Commentary. Manipur has no coast and no river mouth, so Clause 5.13 does not apply in the State (Clause 5.1.4). Its nearest inland counterparts are the silt that the hill streams bring down to the valley floor and to Loktak, the phumdi that drift onto outlets, and the rock sill below Ithai. The hill streams "flow down with steep slope for a short distance before meeting the Loktak Lake … load carrying capacity is high which causes siltation of the lake", and degraded land covers 1,545 km², 24% of the valley's catchment (MASTEC); below the Ithai barrage the bed of the Manipur river rises to 763.7 m in about 800 m, so that "the outflow of the sediment is restricted" (MASTEC); and phumdi, the floating mats that the Loktak Act names, cover much of the lake (as reported). A flap gate held open or shut by silt, phumdi or waste, an outlet buried by a rising bed, or a gate that cannot be moved turns a designed outfall into a dead end or a back-flow path. No WRD rule linking the operation of any gate to the levels of the drains behind it was found during research [TBC]. Clause 5.8.5 deals with this by setting hill-stream outfalls above the range of bed movement, screening outfalls to Loktak against phumdi, and giving no credit for a gate operation, a pump or a storage that the operator's records do not show. Clause 5.13.2 has no direct precedent. It puts the burden of proof on showing that the mouth is open rather than assuming it.
5.14 Documentation
Every project subject to this chapter shall submit a Downstream and Tailwater Report (Form 5-1). It shall contain:
- a plan of the analysis extent showing:
- the site;
- each analysis point with its contributing catchment area and the site's percentage of it; and
- the end point and the reason it was chosen (Clause 5.3);
- the model description:
- software and version;
- the network schematic, with survey sources for the drains and crossings;
- land use and CN for off-site areas;
- any upstream detention included; and
- calibration or validation evidence where available;
- for each analysis point, AEP and duration, the existing and with-project:
- peak flow;
- time to peak;
- maximum water level and velocity; and
- duration of inundation (Clause 5.4);
- the comparison against Clause 5.5, with each failure identified and the remedy adopted;
- the tailwater derivation:
- tide-table edition and port;
- MHWS, HAT and MSL relative to chart datum;
- the datum connection to the Survey of India benchmark and the project datum;
- surge source and value;
- SLA; and
- river levels and their sources (Clauses 5.6 to 5.8);
- the joint-case table of Clause 5.9 with results;
- the outfall-closed check (Clause 5.10):
- storm and lock alignment;
- stage hydrographs; and
- the volume balance for each lock window;
- a schedule of flap gates, tide gates and non-return valves, with certified head–discharge data (Clause 5.11);
- pumped outfall design, power supply, flood immunity and controls, where provided (Clause 5.12);
- the sand-bar assumption and supporting WRD certification, where relevant (Clause 5.13); and
- inspection and maintenance requirements for Chapter 10.
Small sites under Clause 5.3.4 shall submit Form 5-2 (Simplified Downstream Statement) instead.
References (chapter)
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A, §6.3.6 and Table 6.2 (coastal tailwater; +0.3 m climate allowance). https://web.archive.org/web/2024/https://mohua.gov.in/upload/uploadfiles/files/VolumeI-Part%20A-Engineering-Design.pdf
- MoHUA / CPHEEO (2013). Manual on Sewerage and Sewage Treatment Systems (pumping stations).
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (5601.5, ten-percent downstream analysis). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Atlanta Regional Commission / Georgia EPD (2016). Georgia Stormwater Management Manual, Vol. 1 (Standard #8) and Vol. 2 §3.1.9. https://documents.atlantaregional.com/gastormwater/GSMM_2016%20EDITION_FINAL_V1.pdf
- MARC. The Evolution of Regional Stormwater Design Standards. https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Optimisation of urban detention (2016). Water 8(7):290. https://doi.org/10.3390/w8070290
- Colorado State University. Spatially Dependent On-Site Detention Policies (thesis). https://mountainscholar.org/bitstreams/f4dbec4e-a44f-4933-8d54-a097e741f44a/download
- Manipur Science & Technology Council (MASTEC). Flood Hazard Zonation in Manipur Valley, final report to DST-NRDMS (PDF created 2008; data to 2001) (flood records 1966–2002; vulnerable embankment points; gauged discharges 1999–2001; Loktak, the Ithai outlet and the Sugnu hump; the Chakpi backwater; siltation by hill streams), http://web.archive.org/web/20180219013113id_/http://mastec.nic.in:80/images/Completed_projects/ReportFloodHazard.pdf
- Asian Infrastructure Investment Bank (2024). Approval Project Document, Manipur Urban Road, Drainage and Asset Management Improvement Project (P000723), October 2024 (Imphal at 790 m; "35% of the area being prone to floods"; the Nambul; waterlogging "for several weeks"; the 547 km of covered drains), https://aiib.org/en/projects/details/2024/_download/India/AIIB-APD_P000723_Manipur-Urban-Road-Drainage-and-Asset-Management-Improvement-Project.pdf
- New Development Bank (2021). Proposed Project Summary, Lamphelpat Waterbody Rejuvenation Project, https://www.ndb.int/wp-content/uploads/2021/11/Project-Summary-Lamphelpat.pdf
- High Court of Manipur. PIL No. 8 of 2025, Meeyam Amata Oina Punsinba Lup v. State of Manipur, order of 16 June 2025, with the WRD site inspection report (the Lamphelpat dredging and the pumping through the Shamushang nallah), https://rawlaw.in/wp-content/uploads/2025/06/Meeyam-Amata-Oina-Punsinba-Lup.pdf
- Municipal Administration, Housing and Urban Development Department, Government of Manipur. Revised GIS Based Master Plan for Greater Imphal – 2043 (1st Modification), notified by No. SCS-401/3/2021-MAHUD-MAHUD-Part(3) of 4 December 2024 ("The town is below the high flood level of Imphal river"; land use 2020 and 2043), https://tpmanipur.mn.gov.in/media/filer_public/81/1c/811cef92-cba3-43cb-9e7f-caeef3738b68/revised_imphal_master_plan_report-1st_modification.pdf
- The Manipur Loktak Lake (Protection) Act, 2006 (Manipur Act 3 of 2006), as amended by Acts 5 of 2007 and 8 of 2019, ss.1(3), 2, 3, 19 and 20, https://prsindia.org/files/bills_acts/acts_states/manipur/2006/Manipur%20Act%203%20of%202006.pdf
- The Manipur Flood Plain Zoning Act, 1978 (Manipur Act 10 of 1978), ss.1–7 (read from a truncated copy), https://www.indiacode.nic.in/bitstream/123456789/13383/1/the_manipur_flood_plain_zoning_act%2C_1978.pdf
- The Manipur Conservation of Paddy Land and Wetland Act, 2014 (Manipur Act 10 of 2014), ss.2 and 12, https://faolex.fao.org/docs/pdf/ind194970.pdf
- Municipal Administration, Housing and Urban Development Department, Government of Manipur. The Model Manipur Unified Building Bye-Laws, 2024, Notification No. BBL-101/1/2024-MAHUD-MAHUD-Part(1) of 4 December 2024, Manipur Gazette Extraordinary No. 253 of 5 December 2024 (bye-laws 93 and 94), https://www.tpmanipur.mn.gov.in/media/filer_public/5b/3d/5b3d9440-3e85-4cf5-bd26-d113882dfb9a/model_manipur_ubbl_final_gazette.pdf
- Directorate of Environment and Climate Change, Government of Manipur. Administrative Report 2025-26 (the wetlands of the State Wetlands Authority's priority list; draft notifications; the inventory of water bodies), https://assembly.mn.gov.in/user/pages/files/administrative-reports/A%20Report%202025-26%20(DoECC).pdf
- Government of Manipur. Sixth six-monthly progress report in NGT O.A. 606/2018 (as on December 2025) (the interception and diversion of 72 drains to the Nambul), https://www.greentribunal.gov.in/sites/default/files/news_updates/6TH%20SIX%20MONTHLY%20PROGRESS%20REPORT%20BY%20GOVT.%20OF%20MANIPUR%20IN%20OA%20NO.%20606%20of%202018%20(COMPLIANCE%20OF%20MSW%20MGT%20RULES,%202016%20AND%20OTHER%20ENVIRONMENTAL%20ISSUES).pdf
- Central Pollution Control Board (2025). Polluted River Stretches for Restoration of Water Quality (the Nambul from the Singda dam to Bishnupur), https://dste.py.gov.in/ppcc/pdf/Laboratory/PRS-2025.pdf
- SANDRP (2018). Overview of CWC's flood monitoring and forecasting in North East India (the Barak at Chotebekra, HFL 32.1 m; the Barak downstream), https://sandrp.in/2018/08/05/overview-of-cwcs-flood-monitoring-forecasting-in-north-east-india/ . These are transcriptions of CWC tables; the datum and gauge zero are to be confirmed with CWC.
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012), Imphal (Tulihal) (A), 42623.
- Press reports of WRD's river levels (The Sangai Express, 30 May 2024 and 16 September 2025), https://www.thesangaiexpress.com/Encyc/2024/5/30/By-Our-Staff-ReporterIMPHAL-May-29-With-incessant-rainfall-causing-massive-flooding-in-Manipur-the-wate.html and https://www.thesangaiexpress.com/Encyc/2025/9/16/by-our-staff-reporter-imphal-sep-15-with-the-water-levels-of-almost-all-major-rivers-rising-riverbanks-have-br.html ; of the Mapithel reservoir (2015 and 2025), the Loktak levels (NHPC, CEA and ORF, as quoted or reported), the Ithai barrage, the breaches of 2024 and 2025, the Naga Nullah and the Waisel Maril, the Kangpokpi rainfall rule, and the demarcation of flood zones (June 2026).
- Survey of India. Tidal Predictions: Geodetic and Research Branch. https://www.geographyandyou.com/survey-of-india/tidal-predictions-geodetic-and-research-branch-survey-of-india
- GLOSS. India national report (tide-gauge network and datums). https://gloss-sealevel.org/gloss/gloss/sites/gloss/files/publications/documents/india_ge9.pdf
- Adani Ports (2025). Tide Table 2025, Dahej (notes on NHO INP-12 coverage and data sources). https://www.adaniports.com/-/media/Project/Ports/PortsAndTerminals/Dahej-Port/Marine-Documents/Tide-Table-2025-Dahej.pdf
- INCOIS. Storm-surge and swell-surge warning services. https://incois.gov.in/
- FHWA. HEC-22 Urban Drainage Design Manual (current edition), Table 7.3 (coincident frequencies).
- Purdue University JTRP (2023). Development of a Multiple Water Course Joint Probability Analysis Procedure for Indiana Watersheds, FHWA/IN/JTRP-2023/09. https://docs.lib.purdue.edu/jtrp/1820
- PUB Singapore (2025). Code of Practice on Surface Water Drainage, 7th ed., Addendum No. 3. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
Annexes and forms
| Annex / Form | Content |
|---|---|
| 5A | Tidal datums (MSL, MHWS, HAT vs CD and Survey of India datum), surge allowances and 1% still-water levels by coastal segment |
| 5B | Major drains, riverine outfall reaches, and river mouths subject to sand-bar closure; map |
| 5C | Worked example: outfall-closed check for a hill-fringe colony in Jiribam town draining to a stream of the Jiri |
| Form 5-1 | Downstream and Tailwater Report |
| Form 5-2 | Simplified Downstream Statement (small sites) |
Commentary. Imphal drains into rivers and a lake that stand higher than its drains. "The town is below the high flood level of Imphal river and hence there are embankment roads on both sides of the river to protect the settlement from seasonal floods" (master plan); "the failure of river dikes causes waterlogging in the low-lying areas for several weeks" (AIIB, 2024); and the valley has one outlet. Its rivers bring a few hundred cubic metres a second each in a flood (the largest discharges gauged in 1999–2001 were the Iril's 532.488 m³/s and the Thoubal's 391.636 m³/s), while at Ithai the Manipur river carries "of the order of 400 cumecs" and "river down below the barrage does not have the capacity to cope up with such flow, as a result, water is piled up upstream" (MASTEC). So the closed outfall is the design case, not the exception. The Imphal river at Minuthong has a highest flood level of 788.400 m (WRD, as reported) against city ground of about 790 m (AIIB, 2024), and in September 2025 the river at Lilong and the Manipur river at Ithai stood above their printed highest flood levels (as reported). The outfalls also belong to one body while the drains above them belong to others: the bunds and the pumping from Lamphelpat are WRD's, the municipal drains IMC's or another local body's, the road drains PWD's, the interception works on the Nambul DoECC's, the sewers PHED's, and Loktak is LDA's; no notification assigns the Naga Nullah, the Waisel Maril or the Shamushang nallah to one owner (Chapter 6, Clause 6.9). No document found during research sets a design level or a closure duration for any outfall in the State, and WRD's gate operating rules were not found [TBC]. A detention basin that meets every release rate in Chapter 4 still fails if the gate it drains to is shut for a week, if the pat below it is already full, if Loktak stands above its outlet all season, or if the hill stream it drains to has buried its outlet in silt. This chapter makes these failure modes part of the design. Manipur has no tidal outfall, so Clause 5.1.4 says which of the chapter's coastal provisions fall away and what takes their place.