Chapter 10Submittals, Review, Operation & Maintenance and Enforcement
10.1 Purpose and scope
10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:
- (a) the submittal stages and their contents (Clauses 10.3–10.4);
- (b) the compliance calculator (Clause 10.5);
- (c) professional certification and review (Clauses 10.6–10.7);
- (d) construction inspection and as-built certification (Clauses 10.8–10.9);
- (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
- (f) handover of public assets (Clause 10.14);
- (g) enforcement (Clause 10.15); and
- (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).
10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.
10.2 Definitions
| Term | Meaning in this chapter |
|---|---|
| Submittal | A set of documents lodged with the Authority at one of the stages of Clause 10.3. |
| Drainage report | The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4. |
| Stormwater facility | Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private. |
| Hold point | A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8). |
| As-built certificate | The certificate of Clause 10.9 that the facility was built as approved and performs as designed. |
| Owner | The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset. |
| O&M plan | The operation and maintenance plan of Clause 10.11. |
| Facility register | The public register of facilities of Clause 10.17. |
Other terms are defined in Clause 1.4.
10.3 Submittal stages
10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Model Manipur Unified Building Bye-Laws 2024 (Table 10.1):
Table 10.1 — Submittal stages and linked approvals
| Stage | Submittal | When | Linked approval |
|---|---|---|---|
| 0 | Pre-application meeting and Form 1-1 (Applicability Determination) | Before the planning permission or layout application | None (advisory record) |
| 1 | Preliminary drainage report | With the planning permission or layout application | Planning permission / layout approval |
| 2 | Final drainage design | Before building permit, or before commencement where the permit is issued with the planning permission | Building permit / commencement |
| 3 | Construction inspections at hold points | During construction | None (records filed) |
| 4 | As-built certificate and verification tests | Before the completion certificate | Completion / occupancy certificate |
| 5 | Maintenance declaration registered, or handover of public assets | Before or with the completion certificate | Completion certificate; asset acceptance |
| 6 | Annual declarations and inspection reports | Every year after completion | Continuing compliance |
10.3.2 Stage 0 is mandatory for:
- (a) sites of 2 ha or more;
- (b) sites in a flood-sensitive catchment;
- (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
- (d) sites draining to a tidal outfall or adjoining a waterbody.
For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.
10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.
10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.
10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.
Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.
Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the Unified Bye-Laws 2024 steps a Manipur applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.
10.4 Required contents and checklists
10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:
- (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
- (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
- (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
- (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
- (e) the pre-development condition and hydrologic method (Chapter 3);
- (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
- (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
- (h) the downstream extent and tailwater case (Chapter 5);
- (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
- (j) the land reserved for facilities and maintenance access (Clause 10.13).
10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:
- (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
- (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
- (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
- (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
- (e) construction drawings, details and specifications of every facility;
- (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
- (g) the hold-point schedule (Clause 10.8);
- (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
- (i) the model input files and the GIS data of Clause 10.4.4; and
- (j) the certificates of Clause 10.6.
10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.
10.4.4 Digital submittal.
- (a) Reports and drawings shall be submitted as searchable PDF.
- (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
- (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (46N for the whole State, which lies between about 92°58′ E (the State portal) or 93.03° E (knowindia) and about 94.78° E (both as quoted), inside zone 46N (90°–96° E), so that no project needs another zone (this Manual's reading)), with attributes as listed in Annex 10B.
- (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the WRD gauges on the valley rivers and at the Ithai barrage (levels published in the press in metres, presumed above mean sea level, the datum not stated [TBC]), of the CWC level-monitoring site on the Barak at Chotebekra, of the Loktak levels of NHPC and CEA, of the reservoir levels of the Thoubal (Mapithel) dam, of WRD's bund crests, gate sills and gate-closing levels, and of the flood marks surveyed on ungauged rivers, khongs, pats and pukhris used in Chapter 5 shall be stated.
10.4.5 Summary of forms used in submittals (Table 10.2):
Table 10.2 — Forms used in submittals
| Form | Title | Stage |
|---|---|---|
| 1-1 | Applicability Determination | 0 or 1 |
| 1-2 | Variance / Waiver Request | 1 |
| 2-1 | Design Rainfall Sheet | 1, 2 |
| 10-1 | Drainage Report Checklist | 1, 2 |
| 10-2 | Compliance Calculator Summary | 1, 2, 4 |
| 10-3 | Professional Design Certificate | 1, 2 |
| 10-4 | Hold-Point Inspection Record | 3 |
| 10-5 | As-built Certificate | 4 |
| 10-6 | Maintenance Declaration | 5 |
| 10-7 | Annual Maintenance Declaration and Inspection Report | 6 |
| 10-8 | Asset Handover Certificate | 5 |
Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Manipur has no notified design return period or design storm for its urban drains, and no document of MAHUD, TPD, PDA Manipur, IMC or another urban local body, PWD, WRD or Imphal Smart City Ltd stating a return period, a runoff coefficient or a drain standard was found; the Model Manipur Unified Building Bye-Laws, 2024 refer the services of a building to the National Building Code 2016. The two largest drainage works under way state none either: the AIIB's Manipur Urban Road, Drainage and Asset Management Improvement Project (P000723) will build "547 km of both side stormwater covered drains" along the roads of Greater Imphal, but its project document gives no return period, rainfall intensity or runoff coefficient (2024), and the NDB summary of the Lamphelpat project, which will "increase its water detention capacity, restore stormwater drainage system" (2021), states no design storm. The general 5-year return period of the CPHEEO manual for urban drains is cited in a JICA report (as reported) and is not a Manipur value. The rainfall studies do not supply one either. No intensity–duration–frequency relation with constants was found for any Manipur station; an Imphal relation built from 15-minute data of 1986–2009 is described in an online upload whose author and values could not be seen (as reported), and is not cited as a value; IMD's national study (Das et al., 2022) has an Imphal panel that repeats the generic curve of most other cities and implies 24-hour depths above every Imphal record at the long return periods, so it is not used; NIH-DHAARA gives a 50-year 24-hour depth at Imphal of 231 mm, about 1.45 times the station's record of 158.6 mm (tool output; ratio computed for this Manual); and MASTEC's annual-maximum series for Imphal, 1974–2000, is the only station series in print (MASTEC, Table 2). The whole State lies in CWC subzone 2(c), "Barak, Kalden and Manipur rivers", for which CWC has published no Flood Estimation Report. The State's design values are therefore those of Chapter 2: the station series of Clause 2.3.6(c)(i) on the Imphal valley floor and the Loktak margin, the Barak-valley floors of Clause 2.3.6(c)(ii) in the western hills and on the Jiribam plain, and NIH-DHAARA with the valley table as a floor in the northern, eastern and southern hills (Clause 2.3.6(c)(iii)), and each submission must state its own design basis. Form 2-1 and Form 10-2 ensure that every design states its inputs.
10.5 Compliance calculator
10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:
- (a) applies the applicability tests of Clause 1.5;
- (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
- (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
- (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
- (e) on alternative S-2, gives the permissible site discharge for each AEP; and
- (f) produces the Compliance Calculator Summary (Form 10-2).
10.5.2 Use.
- (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
- (b) On the design-aid route, the calculator may be the only storage calculation.
- (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.
10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.
10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.
Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Manipur calculator serves Tier B authorities in particular, where it may be the whole calculation.
10.6 Professional certification
10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or TPD:
- (a) Tier A sites of 1 ha or more;
- (b) any site in a flood-sensitive catchment;
- (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
- (d) any pumped facility, tide gate or regional facility.
10.6.2 Empanelment criteria shall be issued by TPD and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.
10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:
- (a) the design complies with this Manual, except for variances listed and approved;
- (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
- (c) the models submitted reproduce the results reported.
10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.
10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.
Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the Unified Bye-Laws 2024 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.
10.7 Review procedure and timelines
10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.
10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:
- (a) 15 working days of acceptance for a first submittal; and
- (b) 10 working days of acceptance for a resubmittal.
10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.
10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the TPD list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.
10.7.5 Concurrent clearances. Where the consent of WRD for any work on, through or within a river bund, flood channel, river or pumped outfall in its charge, which it gives as owner because no Manipur embankment statute was found, among them the bunds of the Imphal, the Nambul, the Iril, the Kongba and the Thoubal and the pumping of Lamphelpat through the Shamushang channel, the previous permission of the Flood Zoning Authority under bye-law 93 of the Model and the Manipur Flood Plain Zoning Act, 1978 for any activity in a prohibited or restricted area, once an Authority is constituted and an area notified (neither has been found), the prior permission of LDA for an act that the Manipur Loktak Lake (Protection) Act, 2006 forbids without it in the lake's 236.21 km² (s.20), and the leave of the High Court for development in or around Loktak while its orders of 17 July 2019 and 25 February 2022 stand (as reported), the approval of the Local, District or State Level Committee under the Manipur Conservation of Paddy Land and Wetland Act, 2014 for the conversion of paddy land or wetland, the views of the Manipur State Wetlands Authority for a work in or next to a wetland notified under the Wetlands (Conservation and Management) Rules, 2017 (the notifications of the Yaral, Utra and Waithou–Phumnom pats are still drafts), the consent of PWD or the national-highway agency for a discharge to a side drain or culvert of one of their roads, the consent of the Manipur Pollution Control Board for a discharge that carries effluent, and the consent of the body that owns or runs the receiving drain where that body is not the Authority (in Greater Imphal, IMC, PWD, WRD, DoECC for the drains intercepted under the Nambul project, or PHED for a sewer), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.
10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.
10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.
Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.
10.8 Construction inspection
10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:
- (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
- (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
- (c) the infiltration tests of Clause 10.9.3;
- (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
- (e) pumps and controls, at commissioning.
10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.
10.8.3 Protection during construction.
- (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
- (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
- (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.
Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.
Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.
10.9 As-built certification
10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:
- (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
- (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
- (c) the completed hold-point records (Form 10-4); and
- (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).
10.9.2 Acceptance. The as-built facility is accepted where:
- (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
- (b) the outlet dimensions and inverts match the approved design; and
- (c) the re-run shows compliance with every criterion of Chapters 4 and 5.
Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.
10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.
10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.
Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.
10.10 Maintenance declarations and covenants
10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:
- (a) identify each facility, its location and the approved O&M plan;
- (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
- (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
- (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
- (e) be registered so that it runs with the land and is disclosed to purchasers.
10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.
10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 March each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.
10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.
Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Manipur because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 March date is set by this Manual to fall before the monsoon season (April–October), when most Manipur extreme rainfall occurs.
10.11 O&M plans
10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:
- (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
- (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
- (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
- (d) inspection checklists matching Form 10-7;
- (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
- (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
- (g) safety measures for confined spaces, deep water and public access;
- (h) access routes and equipment needed (Clause 10.13);
- (i) an annual cost estimate and who pays it; and
- (j) the records to be kept, and for how long.
10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.
Commentary. Manipur has no dated State or municipal order fixing pre-monsoon desilting or the readiness of gates and pumps. The drains are run by several hands, and no rule divides them: no notification assigns the Naga Nullah, the Waisel Maril or the Shamushang channel to one owner (this Manual's reading of the record). IMC and the other urban local bodies keep the municipal drains, which the Model names in its bar on building "over any municipal drain" (bye-law 16), though the drainage sections of the Manipur Municipalities Act, 1994 were not read [TBC]; PWD keeps the roadside drains, among them the 547 km of covered drains of the AIIB project in Greater Imphal, and the national-highway agencies those of the national highways; WRD keeps the river bunds and flood channels, Lamphelpat and the pumping of its flood water through the Shamushang channel to the Nambul, and was to provide the machinery for clearing encroachments from the Waisel Maril and the Naga Nallah in April 2025 (as reported); DoECC runs the interception and diversion of the 72 drains that fall into the Nambul and its treatment plant of 16 or 17 MLD, as the reports differ (State reports to the National Green Tribunal in O.A. No. 606 of 2018, 2025); PHED runs the sewers and the five sewage pumping stations of the Imphal Sewerage Project Phase I; LDA governs Loktak under the Manipur Loktak Lake (Protection) Act, 2006 and was named to lead the cleaning of the Waisel Maril (as reported); and the role of Imphal Smart City Ltd in the drains of its area was not found [TBC]. The gates that matter most are run for other purposes: the Ithai barrage holds Loktak for NHPC's Loktak hydroelectric project, and the Loktak Act does not apply to the Power Department acting under its agreements with NHPC (s.36); the release rules of the Thoubal (Mapithel), Khuga and Singda dams were not found [TBC]. No operating rule for any gate, flap gate or pumping station in a Manipur town, linking it to a river level, a dam release or a rainfall warning, was found in the public domain, and the CAG found in its audit of flood control to March 2016 that "The overall flood fighting and control activities remained inadequate" (Report No. 2 of 2017, as summarised). Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.
10.12 Inspection frequencies
10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:
Table 10.3 — Minimum owner inspection frequencies
| Facility type | Routine | Pre-monsoon (by 31 March) | After a heavy-rainfall event |
|---|---|---|---|
| Retention / infiltration (soakaways, trenches, bioretention, permeable paving) | Every 6 months | Yes | Yes |
| Surface detention basin or multi-use open space area | Every 6 months | Yes | Yes |
| Underground or podium detention tank, gravity outlet | Every 6 months | Yes | Yes |
| Pumped detention, pumps and controls | Monthly test run | Yes, with full duty test | Yes |
| Flap / tide gate, non-return valve | Every 3 months | Yes, with seal test | Yes |
| Gross pollutant trap / first-flush device | Every 3 months | Yes | Yes |
| Private drains and inlets | Every 6 months | Yes | — |
A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Manipur, the pre-monsoon inspection of gates, flap gates, non-return valves, screens, silt traps, debris racks and pumped facilities, including the gates and pumps on outfalls through the river bunds of the valley, on the Lamphelpat outfall to the Nambul and on outfalls to Loktak and the other pats, with the desilting of every drain, khongban and city channel, the clearance of inlets, silt traps, screens and hill-stream traps, and the pump duty and gate seal tests, shall be completed by 31 March; gates, flap gates and pumped facilities, with their standby power and fuel, shall be certified ready on the same date, with every gate on an outfall to a river, a pat or Loktak operated through its full travel, by or with WRD where the gate is in its charge, because the season of this Manual begins on 1 April and the storms of April and May are among the State's largest. Pumps, their standby power, gates and screens shall then be kept on standby, with the monthly test run, from 1 April to 31 October, and at an outfall to a river or to Loktak until the river at the governing WRD gauge has fallen below its flood level, or the lake below the outfall invert, and the gates have been reopened, if that is later. Inlets, silt traps, screens and hill-stream traps shall be cleared again by 15 May, of the silt, debris, garbage and phumdi of the April and early-May storms, before the late-May storms that flooded the valley in 2024 and 2025, and every public drain, khongban and city channel, inlet, trap and screen in every town shall be cleared of the silt and debris of the season, and its silt depths surveyed, by 15 November. WRD's own works on the river bunds keep WRD's calendar.
10.12.2 Authority inspections. The Authority shall inspect:
- (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
- (b) a random sample of at least 10% of other facilities each year.
10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).
Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 March) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the monsoon season (April–October); tick positions within the year are illustrative.
Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 31 March deadline is set by this Manual for a wet season that begins before the south-west monsoon. In this Manual the monsoon season runs from 1 April to 31 October, and its first two months bring storms as large as the monsoon's: Imphal (Tulihal) recorded 105.9 mm in 24 hours on 16 April 2004 and 122.4 mm on 27 May 1956, and its wettest April and May months are 459.6 mm (2004) and 464.3 mm (1956), against a 24-hour record for the station of 158.6 mm (IMD, Extremes, data 1953–2012); every month from February to December has a 24-hour maximum of 80–160 mm (this Manual's reading of the same table). Two of the recent damaging valley floods came before the monsoon's onset, with Cyclone Remal on 28–31 May 2024 and the rain of 30 May to early June 2025 (as reported), and the flood of June 1966 also began early (MASTEC). The AIIB found "intense rains from March to October" in Greater Imphal (project document, 2024); CGWB found that in Bishnupur "Rainfall starts from the month of April end" (2013); and MASTEC that the "Rainy season … starts from May and extent up to October". NDMA (2010) sets 31 March for pre-monsoon desilting nationally, and this Manual keeps that date, as the other North-East editions of this series do. December to February is the works window. No Manipur order fixing a date for desilting drains or readying gates and pumps was found. This Manual's 31 March covers the drains, inlets, gates, flap gates and pumps of the drainage system; WRD's own works on the river bunds keep WRD's calendar. This Manual therefore takes 31 March for desilting, the clearance of inlets, silt traps and screens, the pre-monsoon inspection, the annual declaration and the readiness of gates, flap gates, pumps and standby power, with no later readiness date; the research's suggestion of 30 April for the gates in the bunds is not used, because the April storms would find them unready. The south-west monsoon's normal onset at Imphal is 5 June (previously 1 June), and its withdrawal 15 October (IMD's normals in use from 2020, as quoted in IMD's press release). Here Manipur's own record moves one date: the other North-East editions of this series clear inlets and traps a second time by 31 May, before the onset, but in Manipur the floods of 2024 and 2025 struck in the last days of May, so a clearance due by 31 May would fall during them. Inlets, silt traps, screens and hill-stream traps are therefore cleared again by 15 May, after the April and early-May storms and before the late-May storms. Storms continue after the withdrawal: Imphal recorded 119.4 mm on 5 October 1980 and the valley flooded in October 1992 (IMD; MASTEC), so pumps, gates and screens are kept on standby to 31 October (Figure 10.3). Large falls also come outside the season, 80.3 mm on 1 November 1991, 89.6 mm on 13 December 1966, 79.8 mm on 18 February 1993 and 72.9 mm on 24 March 1998 at Imphal (IMD), and the drains fill with silt and garbage during the season, so every town clears its drains a second time, and surveys their silt depths, by 15 November. The post-event inspections of Table 10.3 cover storms at any time of year. The reporting year runs from 1 April to 31 March, so that the annual declaration of 31 March closes it.
10.13 Maintenance access
10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.
10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.
10.13.3 Underground facilities. Tanks shall have:
- (a) an access opening over the inlet, the outlet and each chamber;
- (b) fixed ladders or steps, and ventilation for confined-space entry;
- (c) a sump or low point for sediment removal; and
- (d) headroom sufficient for manual cleaning.
10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.
10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.
Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Manipur cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.
10.14 Handover of public assets to the ULB
10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:
- (a) the as-built certificate (Clause 10.9) has been accepted;
- (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
- (c) the land, or an easement over it, has been transferred to the ULB;
- (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
- (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.
10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 1 April to 31 October, after handover. The ULB may hold a security deposit for this period.
10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.
10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.
Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Manipur drainage show up only in the first monsoon.
10.15 Enforcement
10.15.1 Offences. The following are contraventions of this Manual:
- (a) building without an approved drainage design where one is required;
- (b) building a facility other than as approved;
- (c) removing, filling, covering, reducing or changing the use of a facility without approval;
- (d) failing to maintain a facility, or to submit Form 10-7;
- (e) a sewage connection to a storm drain;
- (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
- (g) obstructing a natural drainage path or major-system flow path; and
- (h) false or negligent certification.
10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):
Table 10.4 — Graduated enforcement response
| Step | Action |
|---|---|
| 1 | Written notice stating the contravention, the clause breached, the remedy and a compliance period. |
| 2 | Stop-work order, or withholding of the completion certificate, for development not yet complete. |
| 3 | Penalty under the applicable Act or rules. |
| 4 | Works in default by the Authority, with the cost recovered from the owner. |
| 5 | Disconnection of the private drain connection to the public system, where this causes no hazard to others. |
| 6 | Report of the certifying professional to the registering authority, and suspension from the empanelled list. |
10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.
10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.
10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.
Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Model Manipur Unified Building Bye-Laws 2024 are made and from the municipal Acts. The graduated steps are set by this Manual. In Manipur the courts and the National Green Tribunal have become working regulators of the lake, the rivers and their pollution. The High Court's special bench barred development or construction in or around Loktak "without the Court's leave" by orders of 17 July 2019 and 25 February 2022 (as reported; case number not found [TBC]), and in a suo motu PIL on the Thoubal river in 2019 forbade quarrying, sand mining and pollution except under licence (as reported); in PIL No. 8 of 2025 it took WRD's inspection report on the dredging of Lamphelpat on record and disposed of the petition, finding "no substance" (order of 16 June 2025). The Tribunal supervises the State's sewage and solid waste in O.A. No. 606 of 2018, under which the interception of the 72 drains that fall into the Nambul is reported as completed (State report, December 2025), and its polluted rivers in O.A. No. 673 of 2018, which names 13 rivers of the State, the Imphal, the Iril, the Nambul and the Manipur among them; its order of 22 May 2020 in M.A. No. 26 of 2019 led to an inventory of about 4,000 water bodies whose "Ground truthing … are pending" (DoECC, 2025-26). The statutes differ in force. The Manipur Conservation of Paddy Land and Wetland Act, 2014 carries a real penalty, imprisonment of not less than three years and up to five, and a fine of ₹50,000 to ₹2 lakh (s.18), and bars any licence or permit for construction on paddy land converted in contravention of it (s.12); a Bill of 2026 would exempt land that conforms to a notified master plan and allow "Deemed Conversion" on self-declaration, but it is a Bill, not law. The Manipur Loktak Lake (Protection) Act, 2006 makes the Core Zone of 70.30 km² a "No-Development Zone or Totally Protected Zone" (s.3), bans in the Buffer Zone the "Discharge of untreated wastes and effluents from industries, cities or towns" and "Land reclamation, bunding or disturbing the natural course of drainages" (s.19), and in the lake forbids discharging sewage or domestic waste except with LDA's prior permission (s.20); its penalties were not read [TBC], and it was used to clear huts from the phumdis (as reported). The Manipur Flood Plain Zoning Act, 1978 is nominal in practice: no Flood Zoning Authority has been found constituted and no zone notified, and demarcation "is yet to be done" (as reported, June 2026), although an eviction order of April 2025 along the channels of the Imphal river cited its "Section 24" (as reported; s.24 not read [TBC]); the permission of the Flood Zoning Authority that bye-law 93 of the Model requires is nominal for the same reason. The penalties of the Manipur Municipalities Act, 1994 and of the Manipur Town and Country Planning Act, 1975 were not read, so whether they are nominal is not known [TBC]. The Model is enforced through the permit and the completion certificate, and its fee rebate of 10% for rainwater harvesting with waste-water recycling (bye-law 68) is its one incentive found. The CAG found that "The overall flood fighting and control activities remained inadequate" (Report No. 2 of 2017, audit of flood control and flood forecasting to March 2016, as summarised; the chapter was not read [TBC]), and earlier audits found the "failure of canals … due to siltation of beds" of the Loktak Lift Irrigation Project (2002 and 2008, as summarised); no audit of the drains of IMC, of Imphal Smart City Ltd, of AMRUT or of LDA was found. This shows that a rule without routine enforcement does little, and that where the State has not drawn a line on the ground the courts have. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.
10.16 Monitoring and post-event review
10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.
10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:
- (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
- (b) the stage of the receiving river at the nearest WRD gauge (the Imphal at Minuthong or Lilong, the Iril at Irilbung, the Nambul at Thong Nambonbi (Hump Bridge), the Nambol at Nambol Thongkhong, the Thoubal, or the Manipur river at the Ithai barrage), against its warning, flood and high flood levels, or the level of Loktak, or, at Jiribam, of the Barak at the CWC site at Chotebekra, and, where it is gauged, at the outfall and inside the bund, each on a named datum, with any reading published in the press kept apart from WRD's register; the times at which each gate and flap gate on the outfall and on the drain upstream of it closed and reopened, the level in the receiving pat or pukhri, the hours each pump ran, any loss of power, the fuel used and the phumdi, garbage and debris removed from each screen; any breach of a river bund, with its time and the level the water reached behind it; and the releases of any dam that set the receiving level, such as the Thoubal (Mapithel), Khuga or Singda dam, with the times of the warnings given;
- (c) flooded locations, depths and durations, with flood marks surveyed where possible;
- (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
- (e) recommended actions.
10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), MSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.
10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.
Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Manipur's floods have been counted more often than they have been reviewed, and the counts conflict. MASTEC's report records the valley floods to 2002: in July–August 1989, after Imphal (Tulihal) recorded 158.6 mm on 30 July, the station's 24-hour record (IMD), and rain fell daily from 28 July to 1 August, 361 localities were flooded, the bunds breached in 40 places, about 7 lakh people and 49,069 houses were affected and 97,500 ha of paddy damaged; and in August 2002 the bunds breached in 59 places. In late July and August 2015 about 5 lakh people were displaced by 3 August, by a State revenue estimate, and officials called it a flood that "could be the worst flood in 200 years", while the Joumol landslide in Chandel on 1 August killed 20 or 21 people, or 24 in another count (as reported). The Tupul landslide in Noney on 29 or 30 June 2022 killed 56, 58 or 61 people by different counts, and NRSC reported 42 dead and 20 missing on 5 July (as reported). For the floods of Cyclone Remal on 28–31 May 2024 the Minister gave 1,88,143 people and 24,265 houses affected on 30 May, and the Relief and Disaster Management Department's report of 31 May gave 1,26,950 people, 255 localities and 16,364 houses, with 3 to 5 deaths reported; for the floods of 30 May–June 2025, more than 56,000 people and 10,477 houses were affected at an early count and about 1.65 lakh people and more than 35,000 houses by the official figures of 24 June, with 4 deaths; and on 15 September 2025 the Imphal at Lilong and the Manipur river at Ithai stood above their printed high flood levels and the Iril breached at Kshetri Awang Leikai (all as reported). The tolls differ in what they count, and the final tolls of the Relief and Disaster Management Department or MSDMA were not obtained [TBC]. No IMD rainfall for the floods of 2024 and 2025 was found, only press values such as 123 mm in 24 hours and 175 mm in 72 hours at Kangpokpi on 30–31 May 2025 (as reported); no review of any flood in a Manipur town, and no record of flood extents, depths or durations kept by IMC, another urban local body, WRD or MSDMA, was found. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.
10.17 Data publication
10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:
- (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
- (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
- (c) the register of variances and waivers (Clause 1.10);
- (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
- (e) enforcement actions (Clause 10.15.5); and
- (f) event reports and post-event reviews (Clause 10.16).
10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.
10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.
10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.
Commentary. Transparency is a design criterion in its own right here. Much of Manipur's drainage record is public: the Model Manipur Unified Building Bye-Laws, 2024, the draft IMC Building Bye-Laws (3rd Amendment), 2024, the Unified Zoning/Use Regulation Bye-laws for the Master Plan Areas of Manipur, 2026 and the report of the Revised GIS Based Master Plan for Greater Imphal – 2043 (1st Modification) on the Town Planning Department's website; the Manipur Town and Country Planning Act, 1975, the Manipur Loktak Lake (Protection) Act, 2006, the Manipur Conservation of Paddy Land and Wetland Act, 2014 and its amending Bill of 2026, and the Manipur Official Language Act, 1979 as amended in 2021, in PRS's collection; the amendments to the Manipur (Hill Areas) District Councils Act, 1971 on the State portal; the High Court's order in PIL No. 8 of 2025 with WRD's site report on Lamphelpat; the State's reports to the National Green Tribunal in O.A. No. 606 of 2018; CPCB's list of polluted river stretches (2025); the administrative reports of DoECC and TPD for 2025-26; NDB's summary of the Lamphelpat project and the AIIB's documents for its road and drainage project; MASTEC's report on flood hazard zonation in the valley; CGWB's booklets for Imphal West and Bishnupur; and IMD's station extremes for Imphal (Tulihal). Much else could not be found or read: the building bye-laws for the urban local bodies notified on 15 December 2025, posted only as a folder of files, and the final text and commencement of the IMC (3rd Amendment); the risk-informed master plans for Imphal and Moirang, listed as notified in January 2025 but reported elsewhere as a draft report submitted, and with them the "High Flood Risk Areas" on which bye-law 94 of the Model depends; the Manipur Flood Plain Zoning Act, 1978 beyond its section 7, any constitution of a Flood Zoning Authority and any zone; the drainage sections and penalties of the Manipur Municipalities Act, 1994; WRD's gauge register, with the zero, datum and any revision of each level, and any rule for its gates; NHPC's operating rule for the Ithai barrage and a record of the lake's levels; the release rules of the Thoubal (Mapithel), Khuga and Singda dams; the design basis of any storm drain, including the AIIB project's drainage design, the Lamphelpat project report and the works of Imphal Smart City Ltd; the High Court's case number for its Loktak orders; the chapter of the CAG's Report No. 2 of 2017 on flood control; MSDMA's procedures for urban floods and its final tolls; the State Action Plan on Climate Change; and an inventory of the gates, flap gates, screens and pumping stations of any town. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.
10.18 Review of this chapter
10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.
References (chapter)
- Government of Manipur, Municipal Administration, Housing and Urban Development Department (MAHUD). The Model Manipur Unified Building Bye-Laws, 2024, Notification No. BBL-101/1/2024-MAHUD-MAHUD-Part(1) of 4 December 2024 (Manipur Gazette Extraordinary No. 253, 5 December 2024), under section 213 of the Manipur Municipalities Act, 1994 and section 26(1) of the Manipur Town and Country Planning Act, 1975, for adoption by the urban local bodies and PDA Manipur: bye-laws 1(2), 2(2), 6(1)(A), 6(1)(C)(j), 6(1)(D), 16, 28, 66–68, 92–94, drawing requirements and the completion certificate (provision numbers of the Model; the text each local body has notified governs [TBC]). https://www.tpmanipur.mn.gov.in/media/filer_public/5b/3d/5b3d9440-3e85-4cf5-bd26-d113882dfb9a/model_manipur_ubbl_final_gazette.pdf
- Imphal Municipal Corporation. Building Bye-Laws (3rd Amendment), 2024, draft published for objections (bye-laws 92–94; final status not confirmed [TBC]). https://www.tpmanipur.mn.gov.in/media/filer_public/22/ef/22ef77df-5b8c-4a80-9fa0-553d8a60a170/amendment_of_imc_building_bye_laws_2024.pdf
- Town Planning Department, Manipur. Lists of acts and notifications, among them the building bye-laws of the Kumbi, Moirang and Jiribam Municipal Councils (16 January 2025) and "Building Bye-laws for ULBs of Manipur – Final Gazette Notification" (15 December 2025; not read), and the circular of 17 October 2022 on the Online Building Permission System (as listed); and Annual Administrative Report 2025-26. https://www.tpmanipur.mn.gov.in/media/filer_public/1a/48/1a484b87-afaa-41de-8d64-f6d2f27c49c7/admn_report2025-26.pdf
- The Manipur Town and Country Planning Act, 1975 (Manipur Act 11 of 1975), ss.1(2), 2, 13, 22 and 26. https://prsindia.org/files/bills_acts/acts_states/manipur/1975/Act11of1975Manipur.pdf
- The Manipur Municipalities Act, 1994 (Act 43 of 1994), s.213 and extent (as quoted; drainage sections not read [TBC]).
- The Manipur Loktak Lake (Protection) Act, 2006 (Manipur Act 3 of 2006), with Amendment Acts 5 of 2007 and 8 of 2019, ss.1(3), 2, 3, 19, 20 and 36. https://prsindia.org/files/bills_acts/acts_states/manipur/2006/Manipur%20Act%203%20of%202006.pdf
- The Manipur Conservation of Paddy Land and Wetland Act, 2014 (Manipur Act 10 of 2014), ss.2, 12 and 18; and the (Third Amendment) Bill, 2026 (Bill No. 6 of 2026, as introduced; not law). https://faolex.fao.org/docs/pdf/ind194970.pdf
- The Manipur Flood Plain Zoning Act, 1978 (Manipur Act 10 of 1978), ss.1–7, read from the OCR of a truncated copy. https://www.indiacode.nic.in/bitstream/123456789/13383/1/the_manipur_flood_plain_zoning_act%2C_1978.pdf
- The Manipur (Hill Areas) District Councils Act, 1971, with its amendments of 2006, 2008, 2017 and 2018, ss.29, 29(1A) and 52. https://manipur.gov.in/wp-content/uploads/2026/05/The-Manipur-Hill-Areas-District-Councils-Act-1971-subsequent-Amendments.pdf
- Asian Infrastructure Investment Bank (2024). Approval Project Document, Manipur Urban Road, Drainage and Asset Management Improvement Project (P000723), and its initial environmental examination. https://aiib.org/en/projects/details/2024/_download/India/AIIB-APD_P000723_Manipur-Urban-Road-Drainage-and-Asset-Management-Improvement-Project.pdf
- New Development Bank (2021). Proposed Project Summary, Lamphelpat Waterbody Rejuvenation Project. https://www.ndb.int/wp-content/uploads/2021/11/Project-Summary-Lamphelpat.pdf
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012): Imphal (Tulihal) (A), 42623; and the press release on the revised normal dates of onset and withdrawal of the south-west monsoon (2020, as quoted).
- Manipur Science and Technology Council (MASTEC). Flood Hazard Zonation in Manipur Valley, final report to DST-NRDMS (data to 2001). https://www.mastec.nic.in/images/Completed_projects/ReportFloodHazard.pdf
- Central Ground Water Board, North Eastern Region (2013). Ground Water Information Booklets, Imphal West and Bishnupur districts.
- Das, S.K. et al. (2022). Isopluvial analysis and intensity–duration–frequency curves for different cities in India. MAUSAM 73(4), 887–898 (the Imphal panel, not used).
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities, §5608 (easements, maintenance, submittals) and §5609 (plan requirements). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Mid-America Regional Council (2025). Stormwater management page: 2025 Stormwater Standards Manual, Compliance Calculator, Calculator Start-Up Guide, Policy Supplement. https://www.marc.org/environment/environment-plans/stormwater-management
- PUB Singapore (2018, with Addendum No. 3 of 16 Apr 2025). Code of Practice on Surface Water Drainage, 7th ed. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
- PUB Singapore (2024). On-site Stormwater Detention Tank Technical Guide. https://www.pub.gov.sg/-/media/PUB/PDF/detentionTank.pdf
- PUB Singapore (11 Nov 2024). Amendments to Sewerage and Drainage Act (press release). https://www.pub.gov.sg/Resources/News-Room/PressReleases/2024/11/Amendments-to-Sewerage-and-Drainage-Act
- MoHUA (2016). Model Building Bye-Laws, Chapter 9, §9.6. https://web.archive.org/web/2022/https://mohua.gov.in/upload/uploadfiles/files/MBBL.pdf
- National Disaster Management Authority (2010). National Guidelines on Management of Urban Flooding. https://sdma.goa.gov.in/sites/default/files/2022-05/management_urban_flooding.pdf
- High Court of Manipur. Meeyam Amata Oina Punsinba Lup v. State of Manipur, PIL No. 8 of 2025, order of 16 June 2025, with WRD's site inspection report on Lamphelpat. https://rawlaw.in/wp-content/uploads/2025/06/Meeyam-Amata-Oina-Punsinba-Lup.pdf
- National Green Tribunal. O.A. No. 606 of 2018, Government of Manipur, updated report (July 2025) and sixth six-monthly progress report (as on December 2025); O.A. No. 673 of 2018 (polluted river stretches); M.A. No. 26 of 2019, order of 22 May 2020. https://www.greentribunal.gov.in/
- Comptroller and Auditor General of India. Report No. 2 of 2017, Economic and Revenue Sectors, Government of Manipur (performance audit of flood control and flood forecasting, as summarised; chapter not read [TBC]); and the audits of 2002 and 2008 of the Irrigation and Flood Control Department (as summarised). https://cag.gov.in/
- Central Pollution Control Board (2025). Polluted River Stretches for Restoration of Water Quality (Manipur: 18 stretches, Priority V).
- Directorate of Environment and Climate Change, Manipur. Administrative Report 2025-26. https://assembly.mn.gov.in/user/pages/files/administrative-reports/A%20Report%202025-26%20(DoECC).pdf
- Government of Manipur, MAHUD. Revised GIS Based Master Plan for Greater Imphal – 2043 (1st Modification), notified by No. SCS-401/3/2021-MAHUD-MAHUD-Part(3) of 4 December 2024 (sewerage; Naga Nullah).
- The Sangai Express, Imphal Free Press, India Today NE, Down To Earth, Business Standard, Eastern Mirror and other regional newspapers (2015–2026). Reports of the WRD river levels, the floods of 2015, 2024 and 2025, the Tupul and Joumol landslides, the eviction drives of April 2025, the High Court's Loktak orders and the floodplain zoning status (secondary sources).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 10A | Compliance calculator and user guide |
| 10B | GIS data specification and attribute schema |
| 10C | Maintenance access dimensions |
| 10D | Model O&M plans by facility type |
| 10E | Empanelment criteria for Stormwater Design Professionals and reviewers |
| Form 10-1 | Drainage Report Checklist |
| Form 10-2 | Compliance Calculator Summary |
| Form 10-3 | Professional Design Certificate |
| Form 10-4 | Hold-Point Inspection Record |
| Form 10-5 | As-built Certificate |
| Form 10-6 | Maintenance Declaration |
| Form 10-7 | Annual Maintenance Declaration and Inspection Report |
| Form 10-8 | Asset Handover Certificate |
| Form 2-1 | Design Rainfall Sheet (Chapter 2) |
Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Manipur the failure is one of missing criteria, of a building rule that takes effect only through each local body, and of hill areas that no building rule reaches. No document of MAHUD, TPD, the Planning and Development Authority, Manipur (PDA Manipur), IMC or another urban local body, PWD or WRD stating a design return period, intensity or runoff coefficient for the storm drains of any town was found, and the AIIB found that "The existing drainage in the Greater Imphal area is also not in good condition and is not properly connected to the primary drain. Drainage system links are missing … the drains are clogged" (project document, 2024). The approval route shapes this chapter. The Model Manipur Unified Building Bye-Laws, 2024 were published by MAHUD (Notification No. BBL-101/1/2024-MAHUD-MAHUD-Part(1) of 4 December 2024, Manipur Gazette Extraordinary No. 253 of 5 December 2024) under section 213 of the Manipur Municipalities Act, 1994 and section 26(1) of the Manipur Town and Country Planning Act, 1975 "for adoption by the Urban Local Bodies and Planning & Development Authority, Manipur"; they "extend to the Master Plan areas or notified Planning areas and area under the jurisdiction of all the Urban Local Bodies of Manipur" (bye-law 1(2)), but a permit is given under the bye-laws that the local body or PDA Manipur has brought into force on the Model, among them the bye-laws of the Kumbi, Moirang and Jiribam Municipal Councils (final gazette of 16 January 2025, as listed by TPD) and those notified for the urban local bodies on 15 December 2025 (as listed; not read [TBC]); before the Model, eight towns had bye-laws "based on Model Building Bye-laws of 1998" and 18 urban local bodies had none (the Model's recitals). Provision numbers below are the Model's [TBC: confirm the number and text in the bye-laws the local body has notified]. Plans are submitted through the Online Building Permission System, in use since a circular of 17 October 2022 (as listed by TPD), on which TPD checks each plan for land-use compatibility with the master plan; it examined "about 150 building plans forwarded by Imphal Municipal Corporation" in 2025-26 (TPD administrative report). The Model already asks for much of what a drainage submittal needs: a "terrace plan indicating the drainage and the slope of the roof"; "detail provisions made for conservation and harvesting of rain water" (bye-law 6(1)(C)(j)); for multi-storeyed, lifeline and special buildings a "Detailed drainage plan for both internal and external required to be constructed up to the available permanent/pucca drain of municipal/other authority" (6(1)(D)) and "an intermediate treatment chamber" before any soak-pit outlet to a municipal drain (6(1)(A)); rain-water pipes of at least 75 mm that never discharge "directly into any closed drain" or into a soil pipe (28); on plots of 100 m² and above, plans that "indicate the system of storm water drainage along with points of collection of rain water in surface reservoirs or in recharge wells" (66(a)); no building over a municipal drain (16); and a completion certificate in which the professional certifies "that water harvesting as well as waste water re-cycling systems has been provided as per the sanctioned building plan". Other approvals stand beside the permit: the previous permission of the Flood Zoning Authority under the Manipur Flood Plain Zoning Act, 1978 for activity in a prohibited or restricted area (bye-law 93), though no Authority has been found constituted and no zone notified; the prior permission of the Loktak Development Authority (LDA) within the lake's 236.21 km² (Manipur Loktak Lake (Protection) Act, 2006, s.20); and the approval of the Local, District and State Level Committees for converting paddy land or wetland, without which "no local authority shall grant any licence or permit" for construction on it (Manipur Conservation of Paddy Land and Wetland Act, 2014, s.12). The hill areas lie outside all of these: the Manipur Municipalities Act, 1994 "extends to the whole of the State of Manipur except the Hill Areas" (as quoted), the Model reaches only urban local bodies and notified planning areas, and the District Councils' functions under s.29 of the Manipur (Hill Areas) District Councils Act, 1971 include "water supply and sanitation schemes" and land allotment but no building control; no building or drainage rule for the hill areas was found. No rule asks for a drainage report, limits peak runoff, requires on-site detention or sets a design storm. Every stormwater item in this chapter is therefore written so that the architect or engineer on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it with the drawings that the Model already requires through the Online Building Permission System, beside the detailed drainage plan of bye-law 6(1)(D), which the submittals of this chapter extend to every site that Chapter 1 covers and give the design storm it lacks, and at completion; in the hill areas, the department that executes a public work, PWD, PHED, WRD or another works agency, applies it to that work, and a District Council or its administrator could take it up only if the Governor entrusts the matter or the Council adopts the Manual (neither has been done). This chapter is the process.