Chapter 11Basin and City Stormwater Master Plans
11.1 Purpose and scope
11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.
11.1.2 A BSMP shall:
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
- (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
- (d) reserve land for regional storage, pukhri and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
- (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
- (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).
11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.
11.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Basin | The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3. |
| Basin Stormwater Master Plan (BSMP) | The plan for one basin prepared under this chapter. |
| Lead Authority | The body responsible for preparing a BSMP (Clause 11.4). |
| Level of service (LoS) | The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6). |
| Flood hazard map | A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario. |
| Regional facility | A storage, conveyance or outfall work serving more than one development, identified in a BSMP. |
| Capital Improvement Programme (CIP) | The ranked, costed list of works in a BSMP (Clause 11.8.4). |
11.3 Planning unit: the basin, not the ward
11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.
11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.
11.3.3 No basin delineation has been published for any Manipur town. For the urban areas where the evidence identifies them, the basins are at least the following, in the order of the flood-sensitive catchments of Clause 4.5.3.2:
- Greater Imphal, the Nambul: the catchment of the Nambul through Greater Imphal, with the Naga Nullah and the Waisel Maril and the 72 drains that fall into it in the 1D network, the breaches of its bunds at four places in 2025 and the flooding of Nagaram, Laipham Khunou and Lairikyengbam Leikai by the clogged Naga Nullah in July 2024 (as reported) as calibration evidence, and the river at Thong Nambonbi (Hump Bridge), with its high flood level of 783.695 m (WRD, as reported), as the boundary, the gates closed (Clause 5.8.5(a) and (b));
- Greater Imphal, the Imphal river: the catchments that drain to the Imphal through the city, with the river at Minuthong (flood level 786.900 m, high flood level 788.400 m) and Lilong (781.350 m or 781.250 m; 782.850 m, exceeded at 783.250 m in September 2025) (WRD, as reported) as the boundary, and the breach paths of 2024 and 2025 at Singjamei, Heingang, Bashikhong, New Checkon, Keirang, Khabam and Lairikyengbam Leikai mapped;
- Lamphelpat: the basin of Lamphelpat, a pat being developed as flood storage, with its pumped outlet through the Shamushang channel to the Nambul, the pat full to its outlet at the start of the storm and the pumps' capacity, once WRD states it [TBC], as the outfall (Clause 5.8.5(e));
- Imphal East, the Kongba and the Iril: the corridors of the Kongba and the Iril, with the Iril at Irilbung (flood level 787.700 m; a printed high flood level below it; 788.850 m reached on 15 September 2025, as reported) and its breach at Kshetri Awang Leikai in September 2025 as evidence;
- Thoubal: the catchments of Thoubal town on the Thoubal below the Thoubal (Mapithel) dam, with the river's WRD levels and the dam's largest recorded release, or its spillway capacity until WRD gives one, as boundary conditions (Clause 5.8.5(d));
- The Loktak margin: the catchments of Moirang, Ningthoukhong, Thanga and Ithai–Sugnu–Wangoo that drain to Loktak, its fringing pats or the Manipur river between Ithai and Sugnu, with the high flood level at the Ithai barrage, 769.320 m, checked at 770.05 m, as the boundary, the backwater of the Chakpi at Sugnu, and the outfalls below the design lake level closed from 1 June to 30 September (Clause 5.8.5(c));
- Nambol and Bishnupur: the catchments that drain to the Nambol and the lower Nambul, with the Nambol at Nambol Thongkhong (774.700 or 774.400 m, as reported) as the boundary;
- Kakching and Wangjing: the catchments that drain to the Sekmai and the Wangjing, with surveyed flood marks as the boundary until a WRD level is obtained;
- Jiribam: the catchments of Jiribam town that drain to the Barak and the Jiri, with the high flood level at the CWC site at Chotebekra (32.1 m, 31 July 1989, as reported) as the boundary for at least the 7-day lock of Clause 5.8.5(g), the reaches below governed by the adjoining edition of this series; and
- Hill towns on landslide ground: the catchments of Noney, with Tupul and the Khoupum valley, Tamenglong, Chandel and Kangpokpi, under the hazard-first rule below.
Hazard first in the hills and at the breaches (set by this Manual). In sub-areas MN-B (Northern, eastern and southern hills) and MN-C (Western hills) of Annex 2A, on the hill parts of MN-C1 and the valley-rim slopes and hillocks of MN-A, and in any basin below a mapped landslide zone, in the breach path behind a river bund, in a dam-release reach, in the Loktak core zone or on its phumdi, on peat and former pats, or on a foothill fan where a hill stream leaves the hills, the BSMP begins with a hazard screening for landslides, debris, bund breaches, dam releases and settlement, made with the inventories of MSDMA and NRSC where they exist [TBC], the hazard maps of the risk-informed master plans once read [TBC] and WRD's records of its bunds and breaches, and uses site-specific hydrology in place of a CWC report, which subzone 2(c) does not have (Clause 2.3.6(c) and (i)). The hills' failures are of another order than the drains': the Tupul landslide of 29 or 30 June 2022, with 56, 58 or 61 dead by different counts, followed 348.5 mm of rain in June in Noney district and has been attributed to "poorly designed or implemented slope excavation coupled with heavy rainfall" (Baruah and others, 2023, as reported), and the reported record for the State, 225 mm in one night at Khoupum on 15 July 2025, inundated the Khoupum valley (as reported; duration and gauge not stated). The hazard zones are shown on the 1% AEP map, no drain, storage or pumping station is sited in them, and no work in the CIP is sized to carry a debris flow, a landslide or a breach. Other Tier A bodies and the other urban local bodies define their basins in the first BSMP that covers them. Where WRD, CWC, NHPC, a master plan, the Flood Zoning Authority or a court has a high flood level, a lake level, a flood line or an operating rule for a dam, barrage, gate or pumping station, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.
Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.
Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Manipur a single channel passes through many hands on its way to a river, and every valley river ends in the same lake. The Imphal, the Nambul and the Kongba run north to south through Greater Imphal and "have numerous tributaries through the town" (Revised GIS Based Master Plan for Greater Imphal – 2043), and the Manipur river basin above the valley's outlet drains 6,332 km² "flowing north to south" (the same plan, as printed), of which the hills are 4,432 km², 70%, and the valley 1,900 km² (MASTEC); the floods of the valley floor come from rain on those hills, as WRD's rule of thumb, as reported, that 135 mm in three days at Kangpokpi floods the valley shows. The city's channels are at once storm drains, sewers and the feeders of a lake: the 72 drains that fall into the Nambul carried a BOD of 42.45–52.34 mg/L (State report to the National Green Tribunal, December 2025), and the Nambul flows on past Bishnupur towards Loktak. No notification assigns the Naga Nullah, the Waisel Maril or the Shamushang channel to one owner (this Manual's reading of the record): IMC and the other urban local bodies keep the municipal drains, PWD the roadside drains, WRD the river bunds, flood channels and the pumping of Lamphelpat to the Nambul, DoECC the interception of the Nambul drains, PHED the sewers, and LDA the lake and, as reported, the cleaning of the Waisel Maril. Beyond the valley the hill streams of the north and east feed the valley rivers through the Thoubal (Mapithel) and Khuga reservoirs, the western hills and Jiribam drain to the Barak, and the east of Ukhrul and Kamjong and the country round Moreh drain towards the Chindwin system in Myanmar (this Manual's reading, to be confirmed [TBC]). This clause makes the basin the planning unit, so that one model carries each channel from the hill stream to the river, the pat or Loktak whoever owns each reach, and the drain register of this Manual gives every reach an owner, the river it reaches, the bund it crosses, with its gate or flap gate, whether it lies in a buffer of bye-law 93 of the Model [TBC: confirm the number and text in the bye-laws the local body has notified], and its outfall, and so that the sewage it carries is separated before it reaches a pat, the lake or a river (Chapter 8, Clause 8.9.5).
11.4 Who prepares, and when
11.4.1 Lead Authority.
- For the basins of the Greater Imphal planning area (151.38 km²): the Imphal Municipal Corporation (IMC), which grants building permits and keeps the municipal drains within its limits, jointly with PDA Manipur, the planning authority under the Manipur Town and Country Planning Act, 1975 for the parts of the planning area beyond municipal limits, and the Town Planning Department (TPD), which prepares the master plan and checks building plans for land use, with MAHUD, which notifies the master plan into which the BSMP is taken (Clause 11.9). Each role is the one the body would have if the Manual were adopted. Which body issues building permission in the planning area outside IMC's limits is to be confirmed [TBC]. Where a basin extends beyond the planning area, the other urban local bodies in the basin are partners, and one BSMP covers the whole basin (Clause 11.3.1).
- No notification dividing the city channels from the municipal drains, or the drains of the local bodies from the rivers, bunds and the lake, was found; until one is made, this Manual assigns the reaches within each BSMP as follows, each body being Lead Authority for the reaches and works it owns or runs and for the parts of the CIP on them: WRD for the rivers, their bunds, gates and flood channels, Lamphelpat and the pumping of its flood water through the Shamushang channel to the Nambul, and the machinery for clearing the city channels (as reported); IMC and the other urban local bodies for the municipal drains within their limits; PWD for the roadside drains, among them the 547 km of the AIIB project in Greater Imphal, and the national-highway agencies for the drains and culverts of the national highways; DoECC for the interception and diversion of the drains that fall into the Nambul and its treatment plant; PHED for the sewers and their pumping stations; LDA for Loktak within the 236.21 km² of the Manipur Loktak Lake (Protection) Act, 2006, and for the cleaning of the Waisel Maril that it was named to lead (as reported); Imphal Smart City Ltd for the drains of its works, until handed over in writing [TBC]; and MSDMA, with the Relief and Disaster Management Department and the Deputy Commissioners, for the mapping of the flood, breach and landslide hazards that a BSMP must show.
- In the other urban local bodies (Thoubal, Kakching, Bishnupur, Nambol, Moirang, Jiribam and the rest) and in Tier B bodies: the Lead Authority is the urban local body, with PDA Manipur or TPD where a master plan or planning area covers the town, as MAHUD would name them. In the hill areas, where no building rule applies, the department that executes a public work, PWD, PHED, WRD or another works agency, prepares the drainage of that work to this chapter, and a District Council, or its administrator, could act as Lead Authority for a hill town only if the Governor entrusts the matter to it or it adopts the Manual (neither has been done). Basins draining to a common river reach, to Loktak or to the Barak may be grouped into one district-level plan.
MSDMA and the Deputy Commissioner shall be consulted on every BSMP; WRD on every BSMP whose basin drains to a river, a bund or a pumped outfall; LDA on every BSMP whose basin drains to Loktak; NHPC on every BSMP whose levels the Ithai barrage sets; the Revenue Department and the Local, District and State Level Committees under the Manipur Conservation of Paddy Land and Wetland Act, 2014 on every BSMP that proposes storage, a corridor or development on paddy land or wetland; the Manipur Pollution Control Board on every BSMP that proposes works on a drain or river that carries sewage, among them the Nambul and the Naga Nullah; the Manipur State Wetlands Authority on every BSMP whose basin includes a wetland it has notified or proposed; and, for a basin whose outfall lies on the Barak below Jiribam, the water resources department of the adjoining State, through WRD.
WRD shall be a partner in every BSMP that includes a river, canal or tank under its control.
11.4.2 When a BSMP is required.
- (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
- (b) A BSMP is required before:
- any regional detention or fee-in-lieu is accepted under Clause 4.13;
- a fee held under Clause 4.5.6.3 is spent; and
- a basin-specific release rate is applied under Clause 11.8.3.
- (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.
11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.
11.5 Data and surveys
11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:
Table 11.1 — Minimum data and surveys for a BSMP
| Data | Minimum requirement |
|---|---|
| Terrain | Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum |
| Drain network | Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm |
| Waterbodies | Survey of every tank, pukhri, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment |
| Rivers and canals | Cross-sections at no more than 200 m spacing and at every structure |
| Outfalls, rivers, khongs, pats, pukhris, Loktak and reservoirs | The datum of every level named; outfall invert levels against the warning, flood and high flood levels of the receiving river at the nearest WRD gauge (the Imphal at Minuthong, 785.900, 786.900 and 788.400 m, and at Lilong, 780.350 m, 781.350 or 781.250 m and 782.850 m, exceeded at 783.250 m on 15 September 2025; the Iril at Irilbung, 786.700 and 787.700 m, with a printed high flood level below its flood level; the Thoubal, 778.915 and 779.915 m; the Nambul at Thong Nambonbi (Hump Bridge), high flood level 783.695 m; the Nambol at Nambol Thongkhong, 774.700 or 774.400 m; the Manipur river at the Ithai barrage, 769.320 m, exceeded at 770.05 m on 15 September 2025; WRD levels as reported, the datum not stated [TBC]), with every conflict stated and WRD's gauge register obtained [TBC]; Loktak's full reservoir level (768.5 m, NHPC, or 769.63 m in another account) and minimum drawdown level (766.2 m, NHPC, or 766.01 m, CEA), as quoted, naming which is used; the Barak at the CWC site at Chotebekra (high flood level 32.1 m, 31 July 1989, as reported); the full reservoir level (880.7 m, as reported) and spillway design discharge (2,240 m³/s, as reported) of the Thoubal (Mapithel) dam, and the levels of the Khuga and Singda dams from WRD [TBC]; the sill, gate-closing level and bund crest at every gate in a bund, the capacity and operating rule of every pumping station, among them the pumping of Lamphelpat to the Nambul through the Shamushang channel, and the breach paths of the bunds; pats and pukhris at their surveyed outlet levels; for ungauged khongs and hill streams, surveyed flood marks and the 1% AEP level with its sediment, debris and garbage; and the landslide hazards of the Disang shale slopes and the foothill fans above the basin |
| Rainfall and levels | All available rain gauges (IMD, including Imphal (Tulihal) (A), 42623, the only Manipur station in IMD's Extremes (rainfall data 1953–2012), and the gauges behind the district warnings of the Meteorological Centre Imphal (list not read [TBC]); the river gauges of WRD and the rain gauge at Kangpokpi that its flood rule uses (as reported); the gauges at Kangpokpi, Saikul and Litan used by MASTEC (owners and record lengths [TBC]); the CWC level-monitoring site on the Barak at Chotebekra; the Loktak levels of NHPC and CEA; the IMD stations on the Barak plain downstream that Clause 2.3.6(c)(ii) uses for the Jiribam plain; and any gauges or sensors kept by IMC, Imphal Smart City Ltd, LDA, MSDMA or the flood management system proposed for Lamphelpat [TBC]) and water-level records, including those for the 28–31 May 2024 (Cyclone Remal: the Imphal at Minuthong above its high flood level of 788.400 m and at Lilong at 782.250 m, and the Manipur river at Ithai at 768.640 m, on 29 May; 18 embankment breaches; 1,88,143 people and 24,265 houses affected by the Minister's count of 30 May, or 1,26,950 people, 255 localities and 16,364 houses by the Relief and Disaster Management Department's report of 31 May, all as reported; no IMD rainfall for the event was found), 30 May–June 2025 (breaches of the Imphal at Singjamei, Heingang, Bashikhong and New Checkon and of the Nambul at four places after 123 mm in 24 hours and 175 mm in 72 hours at Kangpokpi on 30–31 May, as reported; no IMD rainfall for Imphal was found), September 2025 (the Imphal at Lilong at 783.250 m and the Manipur river at Ithai at 770.05 m on 15 September, both above their printed high flood levels, and a breach of the Iril at Kshetri Awang Leikai, as reported; no rainfall value was found), late July–August 2015 (rain 46% above normal in Imphal West on 23–27 July, the Mapithel reservoir at 876 m on 1 August and about 5 lakh people displaced by 3 August by a State revenue estimate, as reported; no gauge value was found) and July–August 1989 (158.6 mm at Imphal (Tulihal) on 30 July, the station's 24-hour record, after daily rain from 28 July to 1 August, with 461.9 mm at Imphal and 617.6 mm at Kangpokpi in the month, 40 breaches and 361 localities flooded, IMD and MASTEC) events |
| Flood evidence | Surveyed flood marks and mapped flood extents from past events, including public reports |
| Land use | Existing land use and imperviousness; future land use from the statutory master plan |
| Soils and groundwater | HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones |
| Sewer interaction | Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots |
Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the Imphal valley floor, "virtually a flat alluvium filled valley … with a very low southerly gradient" (MASTEC), where the rivers in flood stand within a metre or two of the city's ground behind their bunds, on the paddy land and pat margins round Lamphelpat and the other pats, on the Loktak margin, where the lake level sets the water's edge, and on the Jiribam plain under the backwater of the Barak, where slopes are gentle, a closed gate ponds the land behind it, and a raised road, a bund or a dumped fill can turn an overflow from one part of a town to another, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The 28–31 May 2024 (Cyclone Remal: the Imphal at Minuthong above its high flood level of 788.400 m and at Lilong at 782.250 m, and the Manipur river at Ithai at 768.640 m, on 29 May; 18 embankment breaches; 1,88,143 people and 24,265 houses affected by the Minister's count of 30 May, or 1,26,950 people, 255 localities and 16,364 houses by the Relief and Disaster Management Department's report of 31 May, all as reported; no IMD rainfall for the event was found), 30 May–June 2025 (breaches of the Imphal at Singjamei, Heingang, Bashikhong and New Checkon and of the Nambul at four places after 123 mm in 24 hours and 175 mm in 72 hours at Kangpokpi on 30–31 May, as reported; no IMD rainfall for Imphal was found), September 2025 (the Imphal at Lilong at 783.250 m and the Manipur river at Ithai at 770.05 m on 15 September, both above their printed high flood levels, and a breach of the Iril at Kshetri Awang Leikai, as reported; no rainfall value was found), late July–August 2015 (rain 46% above normal in Imphal West on 23–27 July, the Mapithel reservoir at 876 m on 1 August and about 5 lakh people displaced by 3 August by a State revenue estimate, as reported; no gauge value was found) and July–August 1989 (158.6 mm at Imphal (Tulihal) on 30 July, the station's 24-hour record, after daily rain from 28 July to 1 August, with 461.9 mm at Imphal and 617.6 mm at Kangpokpi in the month, 40 breaches and 361 localities flooded, IMD and MASTEC) events are the best calibration data Manipur has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.
11.6 Levels of service
11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.
Table 11.2 — Minimum levels of service
| Element | Minimum level of service |
|---|---|
| Minor system | The design AEP of Chapter 6 (Table 6.1) |
| Habitable buildings | No flooding above floor level in the 1% AEP (100-yr) event |
| Critical facilities (hospitals, emergency services, substations, water and sewage plants) | No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event |
| Evacuation routes and arterial roads | Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event |
| Ponding drain time | Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event |
| Tank and pukhri storage | No net loss of flood storage below the MWL in the basin, measured against the earliest available survey |
| Outfalls | Functioning under the joint and outfall-closed cases of Chapter 5 |
Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been reported but rarely measured. Manipur's storage is in Loktak, its pats, its pukhris and its paddy land more than in tanks; it has no irrigation tank cascades. Loktak covers 236.21 km² under the Manipur Loktak Lake (Protection) Act, 2006, with a Core Zone of 70.30 km² that is a "No-Development Zone or Totally Protected Zone" (s.3); MASTEC gives 246.72 km² with its swamps and other sources "250 km²" (as reported), and the Ithai barrage, commissioned in 1983 by most accounts (1979 and 1986 are also printed, as reported), is reported to have raised its average level by about a metre. Loktak was designated a Ramsar site on 23 March 1990 and placed on the Montreux Record on 16 June 1993 (as reported). The Manipur State Wetlands Authority, set up on 31 January 2018, has named seven priority wetlands, Jaimeng, Kachouphung (Achau Maki), Utra Pat, Yaral Pat, Waithou–Phumnom Pat, Pumlen–Khoidum Pat and Ikop–Kharung Pat, delineated 71 wetlands and published draft notifications for Yaral, Utra and Waithou–Phumnom pats, none yet final (DoECC, 2025-26). The SAC Wetland Atlas of 2021 counts 132 wetlands larger than 2.25 ha in the State, and after the Tribunal's order of 22 May 2020 about 4,000 water bodies were inventoried, with "Ground truthing, engineering surveys, and quality monitoring … pending" (DoECC); twenty pond projects under AMRUT 2.0, worth ₹4.11 crore, are carried out by the municipal councils (TPD, 2025-26). Paddy land and wetland are protected from conversion by the Manipur Conservation of Paddy Land and Wetland Act, 2014, whose "conversion" includes the land's "drainage channels, ponds, canals, bunds and ridges" (s.2(c)), and the master plan for Greater Imphal says that "the paddy fields cannot be used for construction" because of it, yet plans the fall in wetland and agricultural land given above. No survey of the stage–storage of any pat or pukhri, or of the flood storage of the valley's paddy land, was found [TBC].
11.7 Modelling and scenarios
11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:
- the minor system;
- the major (overland) system;
- rivers, canals and tanks; and
- the outfalls.
Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.
11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.
11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.
11.7.4 Scenarios. Each BSMP shall model at least:
- (a) Existing: existing land use, network, tanks and outfalls;
- (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
- (c) Future, controlled: future land use with the site controls of Chapter 4;
- (d) Future, with plan: scenario (c) plus the works of the CIP; and
- (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Manipur has been adopted with a design factor, the State Action Plan on Climate Change was not read [TBC], and the figures for future rainfall that officials have given in the press differ from one another and are not used; annual rainfall in Manipur shows "a statistically significant downward trend" over 1991–2024 (Singh, 2025), yet the valley floods of 2015, 2024 and 2025 are among the largest on record (as reported), which is a reason to keep the factors, not to reduce them; and in sub-areas MN-B, MN-C and MN-C1 the hazard screening of Clause 11.3.3 is made in every scenario.
11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the 28–31 May 2024 (Cyclone Remal: the Imphal at Minuthong above its high flood level of 788.400 m and at Lilong at 782.250 m, and the Manipur river at Ithai at 768.640 m, on 29 May; 18 embankment breaches; 1,88,143 people and 24,265 houses affected by the Minister's count of 30 May, or 1,26,950 people, 255 localities and 16,364 houses by the Relief and Disaster Management Department's report of 31 May, all as reported; no IMD rainfall for the event was found), 30 May–June 2025 (breaches of the Imphal at Singjamei, Heingang, Bashikhong and New Checkon and of the Nambul at four places after 123 mm in 24 hours and 175 mm in 72 hours at Kangpokpi on 30–31 May, as reported; no IMD rainfall for Imphal was found), September 2025 (the Imphal at Lilong at 783.250 m and the Manipur river at Ithai at 770.05 m on 15 September, both above their printed high flood levels, and a breach of the Iril at Kshetri Awang Leikai, as reported; no rainfall value was found), late July–August 2015 (rain 46% above normal in Imphal West on 23–27 July, the Mapithel reservoir at 876 m on 1 August and about 5 lakh people displaced by 3 August by a State revenue estimate, as reported; no gauge value was found) and July–August 1989 (158.6 mm at Imphal (Tulihal) on 30 July, the station's 24-hour record, after daily rain from 28 July to 1 August, with 461.9 mm at Imphal and 617.6 mm at Kangpokpi in the month, 40 breaches and 361 localities flooded, IMD and MASTEC) events where data exist.
Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and pukhris with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.
Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).
11.8 Options, outputs and the Capital Improvement Programme
11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:
- Protect and restore storage: pukhris, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
- Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
- Conveyance upgrades to drains, canals and culverts;
- Outfall works: gates and flap gates on the outfalls through the bunds of the Imphal, the Nambul, the Iril, the Kongba, the Thoubal and the other valley rivers, with the storage and pumping behind them sized for the outfall-closed durations of Chapter 5 (Clause 5.8.5), among them the pumping of Lamphelpat to the Nambul through the Shamushang channel and the outfalls of the city channels, the Naga Nullah and the Waisel Maril; standby power and fuel for the whole closure; on the Loktak margin, pumped outfalls for the drains whose inverts lie below the design lake level; screens against phumdi and garbage where drains enter a pump sump, a gate, a pat or Loktak; silt traps and debris racks where hill streams reach the valley floor; drop structures, chutes and energy dissipators where the drains of the hill towns reach a stream, never an unprotected slope; the interception and screening of dry-weather flow before every outfall to a pat, Loktak or a river stretch on CPCB's list (Chapter 8, Clause 8.9); and the operating rules of WRD's gates and pumps and of the releases of the Thoubal (Mapithel) dam, agreed with WRD;
- Property-level protection where works cannot reach the level of service; and
- Non-structural measures: flood warning (for example IMD district rainfall warnings and nowcasts from the Meteorological Centre Imphal, the river levels that WRD publishes for its gauges at Minuthong, Lilong, Irilbung, Thong Nambonbi, Nambol Thongkhong, Thoubal and Ithai against their warning, flood and high flood levels, WRD's rule of thumb that 135 mm in three days at Kangpokpi floods the valley (as reported), level gauges with alarms at the gates and pumping stations of the city channels and of the Lamphelpat outfall, the "real time flood management system with a command center" proposed for the Lamphelpat project (NDB), warnings before releases from the Thoubal (Mapithel) dam, whose release rules were not found [TBC], and the levels of the Barak at the CWC site at Chotebekra for Jiribam), flood-hazard zoning, emergency planning and public information.
11.8.2 Option assessment. Each option shall be assessed for:
- reduction in flood risk (buildings and people flooded; expected annual damage);
- capital and 30-year maintenance cost;
- land required;
- effect on the clay and peat of the valley floor, on which no infiltration is allowed (Clause 4.11, valley-floor rule), and the water table 2 to 5 m below ground in most of Imphal West (CGWB, 2013), which makes buoyancy and inflow a hazard to sumps, tanks and basements, the Disang shale of the hills, which has "less infiltration and more run off" (MASTEC) and slides when cut and wet, as at Tupul in 2022, recharge on the tested foothill fans, Barail sandstone cappings and sand lenses, the only ground where it is allowed (Clause 4.11, recharge rule), although every assessment unit in the State is safe (stage of extraction 8.00%, GWRA 2024, as quoted from CGWB), and the quality of the rivers, pats and Loktak that the runoff reaches, the Imphal, the Nambul and the Iril among them, from which Imphal draws about 90% of its drinking water (Chapter 8);
- effect on downstream basins and the receiving river, khong or pat; and
- who benefits.
11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.
11.8.4 Outputs. Each BSMP shall produce:
- (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
- (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
- (c) regional facility sites, with storage volumes, land needs and the sites they serve;
- (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
- (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
- (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
- (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.
Commentary. Restoring storage comes first because the valley's outfalls are closed in the wettest weeks and its storage is being built on. The rivers that enter the valley carry a few hundred cubic metres a second each in flood while the only outlet, at Ithai, carries "of the order of 400 cumecs" and the river below the barrage "does not have the capacity to cope up with such flow, as a result, water is piled up upstream" (MASTEC), so the valley holds its floods in Loktak, the pats and the paddy until the outlet can pass them, and drains that cannot discharge behind their bunds leave "waterlogging in the low-lying areas for several weeks" (AIIB, 2024). That storage is shrinking: "there were nearly 500 lakes in Manipur Valley", and Lamphelpat, Porompat, Takyelpat, Sangaipat, Kharungpat and Ikop pat are among those degraded or disappearing (MASTEC); Loktak is "becoming shallower" (the same report); and the master plan for Greater Imphal plans a fall in wetlands from 374.48 ha to 232.21 ha and in agricultural land from 5,616.53 ha to 2,604.70 ha between 2020 and 2043, while water bodies grow from 563.54 ha to 643.42 ha (Revised GIS Based Master Plan for Greater Imphal – 2043). Lamphelpat is being dredged back into flood storage with a pumped outlet to the Nambul because pumping alone was "not adequate and the area remains waterlogged for many days every year" (NDB). Wider drains on their own would only bring the water sooner to a closed gate, and on the clay and peat of the valley floor storage means lined or surface storage, never a pond that soaks into the ground (Clause 4.11, valley-floor rule); the rainwater storage of at least 25 litres per m² of roof that Clause 4.11 sets, where bye-law 66(a) of the Model requires rainwater harvesting without a volume, is the first of it, and it also serves the dry months, when the city draws about 90% of its drinking water from its three rivers (the master plan). The storms are modest at Imphal, 158.6 mm in 24 hours on 30 July 1989 the station's record (IMD), but the floods they bring last for days because the outfalls do. Conveyance upgrades on their own move water faster to an outfall that the Imphal, the Nambul, the Iril or another valley river in flood closes at its gate for days or weeks, to Loktak, held up by the Ithai barrage and the rock sill below it, to a pat that a closed outfall holds full, or to an outfall limited by the capacity of its gate or pumping station, as at Lamphelpat, where pumping is "not adequate and the area remains waterlogged for many days every year" (NDB). Groundwater in Manipur calls for storage, not recharge. Every assessment unit in the State is safe, with a stage of extraction of 8.00% in the assessment of 2024 and 7.99% in 2023 (CGWB, as quoted), and Imphal draws about 90% of its drinking water from the Imphal, the Nambul and the Iril (Revised GIS Based Master Plan for Greater Imphal – 2043), so the groundwater is not short. The ground of the valley floor will not take water: Imphal West has "approximately 30 to 50 m of clayey formation" in which "construction of shallow tube wells is problematic", with clay "down to depth range of 30 to 65 m bgl", water 2 to 5 m below ground in most of the district and "emanation of gas while constructing deep tube wells in some places" (CGWB, 2013), and round the lakes of Bishnupur "peaty soils have high acidity" (CGWB, 2013); so the water table is a hazard to the buoyancy of sumps, tanks and basements more than a resource to recharge. Water put into the hills can do harm: Disang shale, most of the hills, has "less infiltration and more run off" (MASTEC), and the slide at Tupul in 2022 has been attributed to slope excavation coupled with heavy rainfall (as reported). No State observation-well network was found: CGWB's dug-well monitoring in Imphal West stopped "since 1991 due to disturbed law and order" (CGWB, 2013), and a Manipur Ground Water (Control & Regulation) Policy, 2023 was prepared, as listed by DoECC, but its text was not read [TBC]. This is why storage and reuse, buoyancy, slope stability, recharge only on the tested foothill fans, sandstone cappings and sand lenses, and the quality of the rivers that supply the city are all assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.
11.9 Integration with land-use planning
11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the master plans notified under the Manipur Town and Country Planning Act, 1975, among them the Revised GIS Based Master Plan for Greater Imphal – 2043 (1st Modification) and the risk-informed master plans for Imphal and Moirang, once their status and contents are confirmed [TBC], and the GIS master plans that TPD is preparing for the other towns and the district headquarters, with the Unified Zoning/Use Regulation Bye-laws for the Master Plan Areas of Manipur, 2026 and the building bye-laws that each urban local body and PDA Manipur have brought into force on the Model; the flood zones notified under the Manipur Flood Plain Zoning Act, 1978, once any are; in the hill areas outside any notified planning area, a development plan under s.29(1A) of the Manipur (Hill Areas) District Councils Act, 1971, once that provision is in force and if the District Council adopts the Manual; and the layouts and buildings permitted under them. In particular:
- (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
- (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
- (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
- (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.
11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.
Commentary. Manipur already draws some of its water lines by bye-law and by statute, and has a floodplain Act with no zone. Bye-law 93 of the Model prohibits "any new construction within the designated buffer zone" along named reaches of ten rivers, both banks alike, measured from mid-stream: 55 m to 62 m on the Imphal, 50 m on the Iril, 48 m on the Thoubal, 35 m on the Sekmai, 31 m on the Wangjing, 30 m on the Nambul within Greater Imphal and on the Arong, each "from mid-stream or 6 m from outer toe of bund, whichever is further from mid-stream", and 22.5–28 m on the Merakhong, 35 m on the Kongba and 25 m on the Nambol from mid-stream only; activity in a "prohibited area or restricted area" then needs "the previous permission of the Flood Zoning Authority constituted under the Flood Plain Zoning Act, 1978" [TBC: confirm the number and text in the bye-laws the local body has notified]. Because the distances run from mid-stream, a 30 m buffer on a reach 40 m wide leaves 10 m from the bank (this Manual's reading). Bye-law 94 sets the plinth "above 1m above the highest flood level of the surrounding areas" in "high Flood Risk Areas identified in the Master Plan of the towns", but the risk-informed master plans that would show those areas were not read [TBC], so where it applies is not known, and no local authority's highest flood level was found for any town. The Manipur Flood Plain Zoning Act, 1978 defines a flood zone as the area required to carry "the maximum probable" flood and provides for zones by "relative risk", but no Flood Zoning Authority has been found constituted and demarcation "is yet to be done" (as reported, June 2026); no pat or pukhri has a setback in the bye-laws. Loktak's Core Zone of 70.30 km² is a "No-Development Zone or Totally Protected Zone", and its Buffer Zone bars "Land reclamation, bunding or disturbing the natural course of drainages" (Manipur Loktak Lake (Protection) Act, 2006, ss.3 and 19), and the High Court has barred development in or around the lake "without the Court's leave" (orders of 2019 and 2022, as reported). The Manipur Conservation of Paddy Land and Wetland Act, 2014 forbids the conversion of paddy land and wetland without the committees' approval and bars a licence for construction on land converted in contravention (s.12); a Bill of 2026 would exempt land that conforms to a notified master plan, but it is not law. The Unified Zoning/Use Regulation Bye-laws for the Master Plan Areas of Manipur, 2026 have a use zone "Pond, Drain, Rivers and Canals", the hook for reserving a corridor in the master plan. Where a notified flood zone, a statutory line or a master-plan line governs, it applies; elsewhere, and where it is narrower, the hydraulic corridor and setback zones of Chapter 7 apply, with a Zone 1 of at least 15 m on every channel draining 8 ha or more and round every pat and pukhri, measured on a bunded reach from the landward toe of the bund, and a Zone 2 to the 1% AEP extent plus 10 m, whichever is wider, as this Manual's proposal, with the 1% AEP map offered as an input to any future zoning under the 1978 Act, not as a zone, and Zone 1 land that is private patta land reserved in the master plan or secured by agreement, not taken. A BSMP gives the master plans, TPD and any future Flood Zoning Authority the 1% AEP drainage-flood map, with the outfalls closed, and the buffer widths of Chapter 7, that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because the Model already makes rainwater harvesting mandatory on plots of 100 m² and above, with the storm-water drainage and the points of collection of rain water "in surface reservoirs or in recharge wells" shown on the plans (bye-law 66(a)), requires soft cover of at least 15% of the plot for buildings with a covered area of 500 m² or more and 10% for others (66(b)), allows no open drain "except for rain water" in the open spaces it requires, and counts among its green-building criteria to "Minimize storm water run-off from site by reducing hard paving on site", and the Unified Zoning/Use Regulation Bye-laws for the Master Plan Areas of Manipur, 2026 list a "Rain Water Harvesting System" as a use and a use zone "Pond, Drain, Rivers and Canals", but no rule sets a detention or peak-runoff limit; storage placed in a layout's open space builds on these duties, and because that land still serves as open space, the storage must stay usable as one, and on the valley floor, where the water table lies 2 to 5 m below ground over 30 to 65 m of clay (CGWB, 2013), it is a shallow lined storage that drains to the outfall, never an infiltration basin (Clause 4.11, valley-floor rule). Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.
11.10 Consultation and publication
11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.
11.10.2 After approval, the following shall be published as open data:
- the model files;
- the flood hazard maps;
- the data of Clause 11.5.1, except security-sensitive asset details; and
- the CIP.
They shall also be shown on a public map viewer.
Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.
11.11 Approval, review and reporting
11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.
11.11.2 Review. Each BSMP shall be reviewed:
- every 10 years;
- within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
- when the statutory land-use plan is revised.
11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each monsoon (by 31 March). The report shall show:
- CIP progress;
- the fee-in-lieu ledger (Clause 4.13.4);
- maintenance completed; and
- any flooding against the levels of service.
11.12 Interim arrangements
11.12.1 Until a BSMP is approved for a basin:
- (a) all site criteria of Chapters 4 to 8 apply in full;
- (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
- (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
- (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.
References (chapter)
- Government of Manipur, MAHUD. Revised GIS Based Master Plan for Greater Imphal – 2043 (1st Modification), notified by No. SCS-401/3/2021-MAHUD-MAHUD-Part(3) of 4 December 2024 (planning area; physical infrastructure; land use 2020 and 2043; wetlands and water bodies; sewerage). http://web.archive.org/web/20250810073559/https://tpmanipur.mn.gov.in/media/filer_public/81/1c/811cef92-cba3-43cb-9e7f-caeef3738b68/revised_imphal_master_plan_report-1st_modification.pdf
- Town Planning Department, Manipur. Annual Administrative Report 2025-26 (GIS master plans; risk-informed master plans for Imphal and Moirang; OBPS land-use checks; AMRUT 2.0). https://www.tpmanipur.mn.gov.in/media/filer_public/1a/48/1a484b87-afaa-41de-8d64-f6d2f27c49c7/admn_report2025-26.pdf
- Asian Infrastructure Investment Bank (2024). Approval Project Document and Project Summary Information, Manipur Urban Road, Drainage and Asset Management Improvement Project (P000723). https://www.aiib.org/en/projects/details/2024/_download/India/AIIB-PSI-P000723-India-Manipur-Urban-Road-Drainage-and-Asset-Management-Improvement-Project_clean_20241129.pdf
- New Development Bank (2021). Proposed Project Summary, Lamphelpat Waterbody Rejuvenation Project. https://www.ndb.int/wp-content/uploads/2021/11/Project-Summary-Lamphelpat.pdf
- High Court of Manipur. PIL No. 8 of 2025, order of 16 June 2025, with WRD's site report on Lamphelpat (dredging; pumping through the Shamushang channel). https://rawlaw.in/wp-content/uploads/2025/06/Meeyam-Amata-Oina-Punsinba-Lup.pdf
- Manipur Science and Technology Council (MASTEC). Flood Hazard Zonation in Manipur Valley, final report to DST-NRDMS (floods to 2002; Imphal annual maxima 1974–2000; discharges 1999–2001; Loktak, Ithai and the Sugnu hump; former lakes). https://www.mastec.nic.in/images/Completed_projects/ReportFloodHazard.pdf
- Central Ground Water Board, North Eastern Region (2013). Ground Water Information Booklets, Imphal West and Bishnupur districts; and the dynamic groundwater resources of Manipur, 2023 and 2024 (as quoted).
- Government of Manipur. Reports to the National Green Tribunal in O.A. No. 606 of 2018 (July and December 2025: sewage generation and treatment; the interception of the 72 drains of the Nambul). https://www.greentribunal.gov.in/
- Defra (2010). Surface Water Management Plan Technical Guidance. Department for Environment, Food and Rural Affairs, London.
- Mile High Flood District (Denver). Master planning programme and Urban Storm Drainage Criteria Manual.
- Mid-America Regional Council (2025). APWA Stormwater Standards Supplement; KC Metro APWA Section 5600, Version 2025.01.
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- Government of Manipur, MAHUD. The Model Manipur Unified Building Bye-Laws, 2024, Notification No. BBL-101/1/2024-MAHUD-MAHUD-Part(1) of 4 December 2024 (Manipur Gazette Extraordinary No. 253, 5 December 2024): bye-laws 66, 93 and 94 (provision numbers of the Model [TBC]); and Unified Zoning/Use Regulation Bye-laws for the Master Plan Areas of Manipur, 2026, Notification No. BBL-101/1/2024-MAHUD-MAHUD of 22 July 2026 (Gazette Extraordinary No. 157, 23 July 2026). https://www.tpmanipur.mn.gov.in/media/filer_public/44/2b/442b7923-b910-494a-83d5-767f50c0c87c/unified_zoning_final_gazette.pdf
- The Manipur Loktak Lake (Protection) Act, 2006 (Manipur Act 3 of 2006), as amended, ss.1(3), 3 and 19; The Manipur Conservation of Paddy Land and Wetland Act, 2014 (Manipur Act 10 of 2014), ss.2 and 12; The Manipur Flood Plain Zoning Act, 1978 (Manipur Act 10 of 1978), ss.1–7.
- The Manipur (Hill Areas) District Councils Act, 1971, as amended, ss.29 and 29(1A). https://manipur.gov.in/wp-content/uploads/2026/05/The-Manipur-Hill-Areas-District-Councils-Act-1971-subsequent-Amendments.pdf
- Directorate of Environment and Climate Change, Manipur. Administrative Report 2025-26 (Manipur State Wetlands Authority; priority wetlands; draft notifications; inventory of water bodies; groundwater policy). https://assembly.mn.gov.in/user/pages/files/administrative-reports/A%20Report%202025-26%20(DoECC).pdf
- Singh (2025). NEHU Journal XXIII(1), 85–99 (abstract read: the trend of total annual rainfall in Manipur, 1991–2024; title not recorded [TBC]). https://dspace.nehu.ac.in/server/api/core/bitstreams/ea6898d7-8ab2-4c2e-9287-e95a54da42b5/content
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012): Imphal (Tulihal) (A), 42623.
- South Asia Network on Dams, Rivers and People (2018). Overview of CWC's flood monitoring and forecasting in North East India (transcription of CWC site data, including the Barak at Chotebekra). https://sandrp.in/2018/08/05/overview-of-cwcs-flood-monitoring-forecasting-in-north-east-india/
- The Sangai Express, Imphal Free Press, India Today NE, Down To Earth, Business Standard and other newspapers (2015–2026). Reports of the WRD river levels and the floods of 2015, 2024 and 2025, the Lamphelpat project, the Naga Nullah and Waisel Maril, the Mapithel dam, the Tupul landslide, the Loktak orders and the status of floodplain zoning (secondary sources).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 11A | BSMP terms of reference template |
| 11B | Basin lists and boundaries for Tier A bodies |
| 11C | Depth–damage curves for Manipur building types |
| 11D | BSMP data and model publication standard |
| Form 11-1 | Annual implementation report |
Commentary. Manipur's capital has a master plan, a river project and a road-drainage programme, but no published storm-drainage master plan with a design storm. The Revised GIS Based Master Plan for Greater Imphal – 2043 (1st Modification), notified by MAHUD (No. SCS-401/3/2021-MAHUD-MAHUD-Part(3) of 4 December 2024), covers a planning area of 151.38 km² in Imphal East and Imphal West, wider than IMC's limits; it finds that "The town is below the high flood level of Imphal river and hence there are embankment roads on both sides of the river", records that wetlands in the planning area are "earmarked by the government for the construction of water bodies for an area of approximately 500 hectares", and plans the land use of 2043, but its chapter on physical infrastructure covers water supply, sewerage, electricity and solid waste and has no section on storm-water drainage. The Risk Informed GIS Based Master Plans for Imphal and Moirang are listed as finally notified on 17 January 2025, while TPD's report for 2025-26 says their draft report "has been submitted", an inconsistency; they were not read, so the flood-risk areas they may map are not known [TBC]. TPD is preparing GIS master plans for Thoubal, Kakching, Lilong (Thoubal), Mayang Imphal and Nambol and for 14 district headquarters "both valley and hills", with a horizon of 2042 (TPD administrative report, 2025-26). Drainage capacity is being built by project, not by plan. The AIIB's Manipur Urban Road, Drainage and Asset Management Improvement Project (P000723) will rehabilitate 547 km of roads in Greater Imphal with "547 km of both side stormwater covered drains" that "channelize the storm water … to the out fall (river)", without a stated return period, intensity or runoff coefficient (project document, 2024). The Lamphelpat Waterbody Rejuvenation Project of the Water Resources Department (WRD), with a loan from NDB (total cost USD 87.84 million, loan USD 70.27 million, concept approval 17 November 2021), is to "increase its water detention capacity, restore stormwater drainage system and channels / streams in the catchment area" and set up a "real time flood management system with a command center" (NDB summary); dredging of about 300 acres began under a work order of 9 November 2023, with WAPCOS as monitoring consultant (WRD's site report in PIL No. 8 of 2025), and press accounts of its cost, area and funders differ (as reported). DoECC's interception of the 72 drains that fall into the Nambul is a pollution work, not a capacity work. No published document sets a design return period for the storm-drain network of any Manipur town. This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by MAHUD, TPD, the Planning and Development Authority, Manipur (PDA Manipur), IMC or any other urban local body, WRD, LDA, MSDMA, any District Council or its administrator, or any other body. A site-level manual cannot fix basin-level problems: lost tank storage, pats and paddy land that once held the valley's floods being filled and built on, river bunds that breach and drains that cannot discharge while the rivers stand above their flood levels, city channels such as the Naga Nullah and the Waisel Maril clogged with garbage, drains that carry the sewage of most of Greater Imphal to the Nambul, Lamphelpat and Loktak, hill slopes of Disang shale that slide when cut and wet, and single channels split between IMC, PWD, WRD, DoECC and LDA with no notification assigning them to one owner, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:
This chapter adapts that method to Manipur, the series' third North-East edition and its first closed lake basin inside a hill State: to a capital on a flat valley floor at about 780–790 m whose rivers stand in flood above its drains, behind bunds that breach, and whose only outlet runs through Loktak, the Ithai barrage and a rock sill below it; to a lake margin where the lake level is the tailwater for the season; to pats and paddy land that once stored the valley's floods and are being filled; to hill towns on Disang shale that slides when cut and wet, as at Tupul in 2022, and to the western hills and the Jiribam plain, which face the Barak and receive far more rain than the valley; to a State that lies wholly in a CWC subzone for which no Flood Estimation Report has been published; to drains that carry the sewage of most of Greater Imphal to the Nambul, Lamphelpat and Loktak; to a building rule that is a model each local body brings into force, with a river-buffer table and a flood-plinth rule but no design storm, a Flood Plain Zoning Act of 1978 with no zone, and hill areas that no building rule reaches; and to a wet season that begins with the storms of April and May, so that on the valley floor a BSMP begins with the river and the lake, and in the hills with the hazard (Clause 11.3.3).