Chapter 1Policy, Applicability and Adoption


1.1 Purpose and objectives

1.1.1 This Manual sets the minimum standards for the planning, design, construction, operation and maintenance of stormwater systems in Manipur. It applies to private development and to public works, as set out in Clause 1.5.

1.1.2 The Manual has the following objectives:

  • (a) to make stormwater management a condition of development approval, so that new development and redevelopment do not increase flood peaks or runoff volumes downstream;
  • (b) to retain frequent rainfall on site, so that groundwater recharge is sustained and pollutant loads are reduced;
  • (c) to size storage for the long-duration storms of the monsoon season, which in the Imphal valley come as spells of several days on the hills that feed its rivers (rain on 28 July–1 August 1989, when Imphal recorded its highest day, 158.6 mm on 30 July, and Kangpokpi 617.6 mm in the month; 175 mm in 72 hours at Kangpokpi on 30–31 May 2025, as reported) and fill the pats and Loktak while the bund gates are shut, and which in the western hills bring the State's heaviest falls (225 mm in one night at Khoupum on 15 July 2025, as reported), from the pre-monsoon storms of April and May to the October storms about the withdrawal of the south-west monsoon, as well as for short-duration intensities;
  • (d) to design outfalls for the rivers of the Imphal valley, which in the monsoon stand above the towns behind their bunds ("The town is below the high flood level of Imphal river and hence there are embankment roads on both sides of the river", master plan for Greater Imphal), so that most valley outfalls pass through gates or flap gates that close, or are pumped, when the river is high: the Imphal river at Minuthong, whose highest flood level of 788.400 m lies within a metre or two of the city's ground (WRD level as reported), the Nambul, the Iril, the Kongba, the Thoubal and the other valley rivers; Loktak, held up by the Ithai barrage and the rock sill below it, the "Sugnu hump", whose level is the tailwater of the south of the valley; the pats that store a district's water while its outfall is shut, among them Lamphelpat with its pumped outlet to the Nambul; the Barak and the Jiri at Jiribam; the reaches below the Mapithel dam on the Thoubal and the dams on the Khuga and the Nambul, into which floods are released; and the hill streams, which rise within the hour, including the case where the outfall is closed;
  • (e) to protect tanks (pukhris), marshes, rivers, supply channels and surplus courses as part of the drainage system;
  • (f) to give every element of the drainage network a safe overland path for the 1% AEP (100-yr) storm;
  • (g) to make design inputs, approvals and facility records public, so that designs can be checked and repeated; and
  • (h) to make sure that facilities, once built, are maintained and remain effective.

1.1.3 This Manual does not replace the rainwater harvesting (RWH) mandate, the building bye-laws that each urban local body and the Planning and Development Authority, Manipur bring into force, by notification in the Manipur Gazette, on the model published by MAHUD under section 213 of the Manipur Municipalities Act, 1994 and section 26(1) of the Manipur Town and Country Planning Act, 1975 (the Model Manipur Unified Building Bye-Laws 2024), or the statutes on waterbodies. It adds runoff control requirements to them (Clause 1.8).

Commentary. Manipur's floods come from three sources, often together. The first is the river flood of the Imphal valley, a closed basin whose rivers run in bunds above the towns ("The town is below the high flood level of Imphal river and hence there are embankment roads on both sides of the river", master plan for Greater Imphal) and leave by one outlet, past the Ithai barrage and a rock sill, the "Sugnu hump", that "does not have the capacity to cope up with such flow, as a result, water is piled up upstream" (MASTEC). The valley floods when days of rain on the hills, about 70% of its catchment, fill the rivers, the bunds breach and the drains cannot discharge. MASTEC records the floods of June–July and October 1966, with breaches at 60 places; of late July and August 1989, after "continuous daily rainfall from 28th July to 1st August", when Imphal (Tulihal) recorded its highest day, 158.6 mm on 30 July, and the flood reached 361 localities through 40 breaches, affecting 7 lakh people, 97,500 ha of paddy and 49,069 houses; of October 1992; of September 1997; of September 1999; of September 2000, when the Iril carried 532.5 m³/s and the bunds breached at 30 places; and of August 2002, with 59 breaches, 10,000 houses and 20,000 ha affected (MASTEC). In late July and August 2015 about 5 lakh people were displaced by 3 August, by a State revenue estimate, and 60,000 ha were flooded, in what officials called a flood that "could be the worst flood in 200 years"; the Mapithel reservoir stood at 876 m on 1 August (all as reported). The monsoon of 2017 killed 22 people (as reported). On 28–31 May 2024, in the storm of Cyclone Remal, before the south-west monsoon's normal onset, the Imphal river at Minuthong rose above its highest flood level and the bunds breached at 18 places, 17 of which were sealed; the Minister gave 1,88,143 people and 24,265 houses affected on 30 May, while the Relief and Disaster Management Department's report of 31 May gave 1,26,950 people, 255 localities and 16,364 houses, and 3 to 5 deaths were reported (all as reported; conflict). From 30 May 2025, again before the onset, the Imphal river breached at Singjamei, Heingang, Bashikhong and New Checkon, and at Keirang, Khabam and Lairikyengbam Leikai, and the Nambul at four places, after Kangpokpi received 175 mm in 72 hours; 56,000 people and 10,477 houses were reported affected at an early stage, and 4 deaths, about 1.65 lakh people affected and more than 35,000 houses damaged by 24 June (official figures as reported). On 15 September 2025 the Imphal river at Lilong stood at 783.250 m and the Manipur river at Ithai at 770.05 m, both above their printed highest flood levels, the Iril breached at Kshetri Awang Leikai and one man was swept away (as reported). The tolls differ in what they count and by the date of the report, and the official final tolls of the Relief and Disaster Management Department or MSDMA were not obtained [TBC].

The second source is the town drain that cannot discharge or is blocked. Lamphelpat "remains waterlogged for many days every year" (NDB); the solid waste of the main market is "dumped in the Naga Nullah on the backside of the market, which creates a stagnant pool all along the year" (master plan for Greater Imphal), and its clogging flooded Nagaram, Laipham Khunou and Lairikyengbam Leikai in July 2024 (as reported); and when the river dikes fail, "waterlogging in the low-lying areas" lasts "for several weeks" (AIIB). The third, found in no plains State of the series, is landslides and debris on the Disang shale of the hills, which "occupies almost 85 p.c. of the hilly region" (MASTEC). On 1 August 2015, in the week of the valley flood, a landslide at Joumol in Chandel killed 20 or 21 people, or 24 by ActionAid's count (as reported; conflict). On 29 or 30 June 2022 a landslide at Tupul in Noney, at the site of the Jiribam–Imphal railway and a Territorial Army camp, killed 56 (reported on 20 July), 58 (29 soldiers and 29 civilians, with 3 missing) or 61 people (all as reported; the date and the toll conflict); NRSC's note of 5 July reported 42 dead and 20 missing at that date (as quoted). Noney district received 348.5 mm in June 2022, and May and June together 705.5 mm, "130% higher than the mean" of the previous decade (Baruah et al., 2023, as summarised). On 15 July 2025, 225 mm fell at Khoupum in Noney "on Tuesday night", the highest fall "ever in Manipur's recorded history" according to IMD Imphal officials, and the Khoupum valley was inundated (as reported; duration and gauge not stated).

Missing design makes all three worse. No design storm, return period or drain standard was found for the drains of any town in the State: the largest drainage programme, 547 km of "both side stormwater covered drains" along the roads of Greater Imphal, states none (AIIB, Approval Project Document, 2024), and the master plan for Greater Imphal has no storm-water drainage section. The building bye-laws set a river buffer table, a plinth rule and rainwater harvesting, not runoff, and they do not reach the hill areas at all. Objectives (b) to (e) address the storage, outfall and building-level failures, which a drain-sizing manual alone cannot fix; the hill source is answered by the siting, screening, infiltration and debris rules of Chapters 2, 4, 6 and 7, because no drain is sized to carry a slide, and the river source by the outfall-closed checks of Chapter 5 and the corridors and floor levels of Chapters 6 and 7.

No national instrument requires on-site detention. CPHEEO (2019) is advisory and describes peak control only as typical practice. NDMA (2010) says detention and retention "will" be included but gives no sizing rule. MBBL 2016 and the Model Manipur Unified Building Bye-Laws 2024 mandate RWH only. Objective (a) is therefore the main new step this Manual takes.


1.2 Stormwater management hierarchy

1.2.1 Every development to which Chapter 4 applies shall consider stormwater measures in the following order. A designer shall not use a lower measure in place of a higher one that is practicable on the site.

  1. Preserve — keep or restore natural drainage features, tanks, wetlands, permeable soils, trees and overland flow paths (Chapter 7).
  2. Retain — hold the runoff from the retention depth of Annex 2E on site, by infiltration, reuse or evapotranspiration (Chapters 4 and 8).
  3. Detain — store larger storms temporarily and release them at or below the rates in Chapter 4, checked against downstream and tailwater conditions (Chapters 4 and 5).
  4. Convey — carry the remaining flow safely in the minor system, and the 1% AEP flow in the major system (Chapters 6 and 9).

1.2.2 Maintenance underlies all four measures. A measure that cannot be maintained by its owner under Chapter 10 shall not be credited.

1.2.3 Credits from higher measures reduce the requirements of lower ones. Preserved areas and retained volume reduce detention storage as set out in Chapter 4.

Figure 1.1 — Stormwater management hierarchy Four stacked bars, widest at top: Preserve, Retain, Detain, Convey, with a Maintain bar underneath spanning all. A downward arrow shows the order of consideration; an upward arrow shows that credits from higher measures reduce lower ones. Order of consideration Credits reduce lower measures 1 PRESERVE Chapter 7 Keep tanks, wetlands, marshes, permeable soils, trees and flow paths 2 RETAIN Chapters 4, 8 Hold the Annex 2E depth on site: infiltrate, reuse, evaporate 3 DETAIN Chapters 4, 5 Store larger storms; release below pre-development peaks 4 CONVEY Chapters 6, 9 Minor system, plus a 1% AEP overland path MAINTAIN — underlies every measure Chapter 10 A measure that its owner cannot maintain earns no credit (Clause 1.2.2) Use a lower measure only for what the measures above it cannot practicably achieve (Clause 1.2.1).

Figure 1.1 — Stormwater management hierarchy: preserve, retain, detain, convey, with maintenance underlying each measure. Original drawing for this Manual, adapted from Mid-America Regional Council / Kansas City Metro Chapter APWA, "Layers of Stormwater Management", APWA 5600 Manual Factsheet, 2025 (concept).

Commentary. The order follows the "layers" of Kansas City Metro APWA Section 5600, Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet, 2025). The same logic is behind Georgia's runoff-reduction standard and CSE's "attenuate and infiltrate first" principle (CSE, 2023). For Manipur, the top two layers have a particular meaning. Much of the valley's storage lies in its pats, the natural lakes and marshes of the valley floor; in Loktak, held up by the Ithai barrage; in its pukhris; and in its paddy land, which stands under water through the monsoon. MASTEC records that "there were nearly 500 lakes in Manipur Valley" and lists Lamphelpat, Porompat, Takyelpat, Sangaipat, Kharungpat and Ikop pat among the pats that are degraded or disappearing, and CGWB that the valley "was once full of swamps and marshy land represented by the places having the word PAT meaning lake" (MASTEC; CGWB, Imphal West, 2013). The notified master plan for Greater Imphal shrinks the planning area's wetlands from 374.48 ha to 232.21 ha and its agricultural land from 5,616.53 ha to 2,604.70 ha by 2043, while its water bodies grow from 563.54 ha to 643.42 ha (master plan for Greater Imphal). The law protects some of this. The Manipur Loktak Lake (Protection) Act, 2006 makes the lake's Core Zone of 70.30 km² a "No-Development Zone or Totally Protected Zone" and bans, in the Buffer Zone, the "Discharge of untreated wastes and effluents from industries, cities or towns" and "Land reclamation, bunding or disturbing the natural course of drainages" (ss.3, 19); the Manipur Conservation of Paddy Land and Wetland Act, 2014 forbids the conversion of paddy land and wetland, counting its "drainage channels, ponds, canals, bunds and ridges" as part of it, except through its committees (ss.2(c), 3); the Manipur State Wetlands Authority has published draft notifications of the Yaral, Utra and Waithou–Phumnom pats under the Wetlands Rules, 2017, none yet final; and the bye-laws set a buffer along the named rivers of the valley (bye-law 93 of the Model [TBC: confirm the number and text in the bye-laws the local body has notified]). No statute or bye-law sets a buffer round a pat or pukhri outside Loktak, and no flood zone has been notified under the Manipur Flood Plain Zoning Act, 1978. On the valley floor the second layer changes. Retention there is storage and reuse, not infiltration: the floor is "approximately 30 to 50 m of clayey formation", with water "2 to 5 m bgl" in most of Imphal West (CGWB, Imphal West, 2013), and peat with "high acidity" round the lakes (CGWB, Bishnupur, 2013), so a soak pit fills from below in the monsoon. This Manual therefore bars deliberate infiltration on the clay, silt and peat of the valley floor, below the 1% AEP flood level, behind a river bund and round a pat or pukhri (Clause 4.11, valley-floor rule); bars it in the hills on natural slopes of more than 10°, on the Disang shale at any slope, on colluvium, fill or slide debris and close upslope of a cut or retaining wall, unless a geotechnical certificate allows it (Clause 4.11, hill rule); and allows recharge only on the tested foothill fans at the edge of the valley, on Barail sandstone cappings of gentle slope and on tested sand lenses, because every groundwater assessment unit of the State is "Safe", with a stage of extraction of 8.00% (GWRA 2024, as quoted), and recharge is not a design objective there (Clause 4.11, recharge rule) (all set by this Manual). Rainwater harvesting is storage for the dry season: Imphal draws about 90% of its drinking water from the Imphal, Nambul and Iril rivers (master plan for Greater Imphal). Losing the pats and the paddy land cannot be offset by pipes, and in the hills drains that put water into a slope of shale can make it fail.


1.3.1 Notification. This Manual shall be given statutory effect by the Government of Manipur through:

  • (a) an amendment to the Model Manipur Unified Building Bye-Laws 2024 that makes compliance with this Manual a condition of planning permission, building permit, layout approval and completion certificate, for development to which Clause 1.5 applies; and
  • (b) bye-laws or standing orders of each urban local body (ULB), adopting the Manual for works executed or approved by that ULB, including the ULB's own drains and roads.

1.3.2 Higher State standards. The design return periods and performance criteria of this Manual exceed the national advisory minimums of the CPHEEO Manual on Storm Water Drainage Systems (2019). The State shall constitute, by notification, a high-powered committee (the State Stormwater Technical Committee, Clause 1.9) to adopt these higher standards. This is the route that CPHEEO (2019) provides for higher return periods.

1.3.3 Precedence. Within its scope, this Manual governs where it is stricter than CPHEEO (2019), IRC:SP:42-2014, IRC:SP:50-2013 or any departmental standard. Where a statute or statutory rule sets a stricter requirement (for example a waterbody setback), the statute governs.

1.3.4 Design-practice standard for public works. Departments and ULBs that procure drainage, road or waterbody works shall require compliance with this Manual in detailed project reports (DPRs) and contracts, from the dates in Clause 1.11.

Commentary. In Manipur the building rules are a model that each local body brings into force. The Model Manipur Unified Building Bye-Laws, 2024 were published by MAHUD Notification No. BBL-101/1/2024-MAHUD-MAHUD-Part(1) of 4 December 2024 (Manipur Gazette Extraordinary No. 253 of 5 December 2024), under section 213 of the Manipur Municipalities Act, 1994 (Act 43 of 1994) and section 26(1) of the Manipur Town and Country Planning Act, 1975 (Manipur Act 11 of 1975), "for adoption by the Urban Local Bodies and Planning & Development Authority, Manipur", after a draft notice of 29 October 2024 (No. BBL-101/1/2024-MAHUD-MAHUD(Part-1)). The Model "shall extend to the Master Plan areas or notified Planning areas and area under the jurisdiction of all the Urban Local Bodies of Manipur" (bye-law 1(2)), and its "Act" is the Municipalities Act in the areas of urban local bodies and the 1975 Act "in respect of Master Plan areas but beyond the municipal limits" (2(2)). A permit, however, is given under the bye-laws that the urban local body or the Planning and Development Authority, Manipur (PDA Manipur) has brought into force on the Model. The TPD's site lists final gazettes of the building bye-laws of the Kumbi, Moirang and Jiribam Municipal Councils, 2025, of 16 January 2025, and a "Building Bye-laws for ULBs of Manipur – Final Gazette Notification" of 15 December 2025 (as listed; the second was not read for this Manual); Imphal Municipal Corporation Building Bye-Laws, 2025 are reported to have been notified on 15 December 2025 (as reported). Before the Model, Imphal had the IMC Building Bye-laws, 2013, amended in 2019 and 2022 (as listed); eight other local bodies had bye-laws "based on Model Building Bye-laws of 1998", and 18 had none (recitals of the Model). The IMC Building Bye-Laws (3rd Amendment), 2024 were published as a draft for objections, to "come into force on such date as the State Government may, by notification in the Official Gazette, appoint"; whether they were made final was not confirmed [TBC]. Provision numbers in this Manual are those of the Model: bye-laws 1(2), 2(2), 2(11), 6(1)(A), 6(1)(C)(j), 6(1)(D), 16, 28, 66, 67, 68 and 92–94 [TBC: confirm the number and text in the bye-laws the local body has notified]; where a local body's notified text differs, its text governs.

The Model asks for a "Detailed drainage plan for both internal and external required to be constructed up to the available permanent/pucca drain of municipal/other authority" for multi-storeyed, lifeline and special buildings (6(1)(D)); forbids building "over any municipal drain" (16); sends rain-water pipes of at least 75 mm to a surface drain, "in no case" directly into a closed drain, and never into a soil pipe (28); makes rainwater harvesting mandatory on plots of 100 m² and more, with soft cover of 10% or 15% of the plot (66), grey-water recycling on the larger buildings (67) and a fee rebate (68); bars new construction within a buffer measured from mid-stream along named reaches of ten valley rivers, from 22.5 m to 62 m, "or 6 m from outer toe of bund, whichever is further from mid-stream" on most of them, subject to "the previous permission of the Flood Zoning Authority constituted under the Flood Plain Zoning Act, 1978" (93); and sets the plinth "above 1m above the highest flood level of the surrounding areas" in "high Flood Risk Areas identified in the Master Plan of the towns" (94). Its bye-law 92, as printed, reads "No construction shall be permitted on land above 600 m from the mean sea level and with an average slope of 30 degrees", which would bar all of Greater Imphal, which lies above 600 m (NEER reading); the IMC (3rd Amendment) draft of 2024 gives the intended rule, that "no construction will be permitted in the areas which have a slope of more than 30 degrees", that development is permitted "only upto two floors or 7m height in areas which have a slope of 21-30 degrees" (92.1) and that "no cutting of slopes will be permitted" above 30° (92.2), and this Manual reads bye-law 92 with that text. The Model sets no design storm, return period, release rate or detention volume. The Unified Zoning/Use Regulation Bye-laws for the Master Plan Areas of Manipur, 2026 (MAHUD Notification No. BBL-101/1/2024-MAHUD-MAHUD of 22 July 2026; Gazette Extraordinary No. 157 of 23 July 2026), made under section 91(1)(iv) read with section 24(e) of the 1975 Act, add a use zone "Pond, Drain, Rivers and Canals" in every Master Plan area. The route of Clause 1.3.1(a) therefore runs through an amendment to the Model by MAHUD under the same two sections, and its adoption by each urban local body and PDA Manipur in their bye-laws: MAHUD could amend bye-laws 6(1)(D), 66 and 92–94 and the zoning bye-laws' "Pond, Drain, Rivers and Canals" zone and commend the amendment to the local bodies and PDA Manipur, which could adopt it in their bye-laws (Annex 1D).

That route reaches only the areas of the urban local bodies and the notified Master Plan and planning areas. The hill areas are a second legal geography. They are the areas in the First Schedule to the Manipur Legislative Assembly (Hill Areas Committee) Order, 1972, for which Article 371C provides a Hill Areas Committee of the Assembly (as summarised). The Manipur Municipalities Act, 1994 "extends to the whole of the State of Manipur except the Hill Areas" (as quoted), the Model reaches no hill area that is not a notified planning area, and the paddy-land Act stops at the hill boundary (NEER reading); the Manipur Town and Country Planning Act, 1975 and the Manipur Flood Plain Zoning Act, 1978 extend to the whole State. The Manipur (Hill Areas) District Councils Act, 1971, as amended, gives the District Councils functions that include "water supply and sanitation schemes", "the construction, repair and maintenance of embankments", soil conservation, the allotment of land for "residential or other non-agricultural purposes" and, by entrustment of the Governor "in consultation with the Hill Areas Committee", "village planning or any other matter" (s.29(1), the numbering of its items read from page images and to be verified [TBC]), but no building control. A section 29(1A), inserted in 2006, would let a Council "notify any part of the area of the Autonomous District as urban area for the purpose of formulation of development plan", on a date to be notified that was not found; this Manual does not treat it as in force. The Councils' terms expired on 30 November 2022, and the Governor appointed the Deputy Commissioners of six hill districts as their administrators in June 2025 (as reported); whether there are six Councils or ten after a reported amendment of 2022 is not settled [U]. No building or drainage rule for the hill areas was found for this Manual. In the hill areas the Manual can therefore reach the public works executed by the State's departments and agencies, among them roads, bridges, culverts, drains, water supply, embankments and flood works (Clause 1.5.1(b)); any body that adopts it; and, in future, the master plans that the TPD is preparing for the district headquarters "both valley and hills", with a horizon of 2042, under which the Model could extend to a notified planning area. A District Council could take the Manual up as a matter entrusted by the Governor under section 29, or through a development plan under section 29(1A) once that is in force. For a household or village in the hill areas the Manual is guidance only. This Manual is a draft: neither the Government, MAHUD, the TPD, PDA Manipur, IMC, any Municipal Council or Nagar Panchayat, the Hill Areas Committee, any District Council or its administrator, nor any other authority has adopted it. MoHUA told Parliament in July 2026 that urban flooding "falls under the purview of the State Governments and the ULBs" and listed the CPHEEO manual among "advisory guidelines" (Lok Sabha AU1847). The State therefore needs no central approval to adopt higher standards. CPHEEO's Note 2 to Table 4.1 (§4.4.1.4) allows "a high powered committee constituted by State/UT Government through a notification" to adopt higher return periods. Clause 1.3.2 uses that route so that higher standards are on record for centrally funded schemes.


1.4 Definitions

1.4.1 The following terms apply throughout this Manual. Chapter-specific terms are defined in each chapter (for example Clause 2.2).

Term Meaning in this Manual
Approving Authority (the Authority) The body that grants planning permission, building permit or layout approval for a development, or that sanctions a public work: the competent authority for the area: in the area of an urban local body, that body (the Imphal Municipal Corporation (IMC), a Municipal Council or a Nagar Panchayat) for the building permit and for its own drains and works, under the building bye-laws it has brought into force on the Model Manipur Unified Building Bye-Laws, 2024 and under the Manipur Municipalities Act, 1994; in a Master Plan area or notified planning area outside municipal limits, the Planning and Development Authority, Manipur (PDA Manipur) under the Manipur Town and Country Planning Act, 1975 (bye-law 2(2) of the Model); the Town Planning Department (TPD) for the land-use check of a building plan against the master plan on the online building permission system (OBPS); the Water Resources Department (WRD) for any work on, through or within a river bund, flood channel, river or pumped outfall that it holds, as owner (no embankment statute of the State was found); the Flood Zoning Authority under the Manipur Flood Plain Zoning Act, 1978, where a flood zone has been notified (none has); the Loktak Development Authority (LDA) within the 236.21 km² of the Manipur Loktak Lake (Protection) Act, 2006 (prior permission under section 20); the Local, District and State Level Committees for the conversion of paddy land or wetland under the Manipur Conservation of Paddy Land and Wetland Act, 2014; the Manipur State Wetlands Authority (MSWA) for a wetland notified under the Wetlands (Conservation and Management) Rules, 2017 (no notification is final); and, in the hill areas, the department that executes a public work (the Public Works Department (PWD), the Public Health Engineering Department (PHED), the WRD or another works agency) for that work and, for any other development, the District Council or its administrator, the Deputy Commissioner, only where the Governor has entrusted the matter to it under section 29 of the Manipur (Hill Areas) District Councils Act, 1971 or the Council has adopted this Manual (neither has been done), or a department for its own works.
Applicant The owner, developer or department that seeks approval, and its successors in title.
Development Any building, layout, sub-division, road, paving or land-use change that requires approval under the Model Manipur Unified Building Bye-Laws 2024 or that is executed as a public work.
Redevelopment Development on a site where impervious cover already exists.
Land disturbance Clearing, grading, excavation, filling or paving of land, measured in plan area over the whole of a common plan of development (Clause 1.5.5).
Impervious area Roofs, paving, compacted gravel, decks and other surfaces that prevent infiltration. Permeable paving designed to Chapter 8 is counted as pervious only for the area it treats.
New or replaced impervious area Impervious area created, or removed and rebuilt down to the subgrade, by the development. Resurfacing that leaves the base in place is not "replaced".
Retention Permanent removal of runoff from the drainage system on site, by infiltration, reuse or evapotranspiration (Chapter 4).
Detention Temporary storage of runoff with a controlled outlet, emptied after the storm (Chapter 4).
Rainwater harvesting (RWH) Collection of rainfall for supply or recharge under the RWH mandate. RWH storage is not detention unless Chapter 4 allows it.
Minor system Drains, pipes and inlets designed for the minor-system AEP of Chapter 6.
Major system The overland and floodway path that carries the 1% AEP (100-yr) flow (Chapter 6).
Pre-development condition Greenfield: open land in good condition for the mapped hydrologic soil group. Existing impervious cover is not counted (Chapter 3).
Flood-sensitive catchment The catchments of the Nambul through Greater Imphal, with the Naga Nullah and Waisel Maril channels and the 72 drains that fall into it; of the Imphal river through Imphal; of the Lamphelpat basin, with its pumped outlet through the Shamushang nallah to the Nambul; of the Kongba and Iril corridors of Imphal East; of Thoubal on the Thoubal river below the Mapithel dam; of the Loktak margin, Moirang, Ningthoukhong, Thanga, and Ithai–Sugnu–Wangoo with the Chakpi backwater; of Nambol and Bishnupur on the Nambol and Nambul rivers; of Kakching and Wangjing on the Sekmai and Wangjing rivers; of Jiribam on the Barak and the Jiri; and of the hill towns on landslide ground, Noney (Tupul), Tamenglong, Chandel and Kangpokpi, and any catchment the Authority notifies (Chapter 4; Annex 1B).
Waterbody A river, stream, canal, tank (pukhri), lake, pond, marsh, supply channel or surplus course, whether perennial or seasonal (Chapter 7).
Regional facility A detention, retention or tank storage facility serving more than one development, built or restored under a basin plan (Chapter 4).
Tier A / Tier B authority An Approving Authority classed under Clause 1.6.
Policy supplement The set of adoptable alternative clauses in Clause 1.7 and Annex 1C.
Drainage report The preliminary or final report required by Chapter 10.
Registered professional A person registered under the Model Manipur Unified Building Bye-Laws 2024 to prepare and sign the relevant plans, with any further qualification required by Clause 10.6.
Compliance calculator The State-issued tool for computing and reporting compliance (Clause 10.5).
Maintenance declaration The registered undertaking by an owner to maintain a stormwater facility (Clause 10.10).
Variance Approval to depart from a numeric requirement, with equivalent performance shown (Clause 1.10).
Waiver Approval that a requirement does not apply to a site, on the grounds in Clause 1.10.
Notified Published by the Government or the State Stormwater Technical Committee in the Manipur Gazette.
Competent authority for the area The body that grants permission for the site, or consents to the work, under the instrument that applies there: in the area of an urban local body, that body (the Imphal Municipal Corporation (IMC), a Municipal Council or a Nagar Panchayat) for the building permit and for its own drains and works, under the building bye-laws it has brought into force on the Model Manipur Unified Building Bye-Laws, 2024 and under the Manipur Municipalities Act, 1994; in a Master Plan area or notified planning area outside municipal limits, the Planning and Development Authority, Manipur (PDA Manipur) under the Manipur Town and Country Planning Act, 1975 (bye-law 2(2) of the Model); the Town Planning Department (TPD) for the land-use check of a building plan against the master plan on the online building permission system (OBPS); the Water Resources Department (WRD) for any work on, through or within a river bund, flood channel, river or pumped outfall that it holds, as owner (no embankment statute of the State was found); the Flood Zoning Authority under the Manipur Flood Plain Zoning Act, 1978, where a flood zone has been notified (none has); the Loktak Development Authority (LDA) within the 236.21 km² of the Manipur Loktak Lake (Protection) Act, 2006 (prior permission under section 20); the Local, District and State Level Committees for the conversion of paddy land or wetland under the Manipur Conservation of Paddy Land and Wetland Act, 2014; the Manipur State Wetlands Authority (MSWA) for a wetland notified under the Wetlands (Conservation and Management) Rules, 2017 (no notification is final); and, in the hill areas, the department that executes a public work (the Public Works Department (PWD), the Public Health Engineering Department (PHED), the WRD or another works agency) for that work and, for any other development, the District Council or its administrator, the Deputy Commissioner, only where the Governor has entrusted the matter to it under section 29 of the Manipur (Hill Areas) District Councils Act, 1971 or the Council has adopted this Manual (neither has been done). Where this Manual says "the Authority", the competent authority for the area is meant.
Model bye-laws; local body's bye-laws The Model Manipur Unified Building Bye-Laws, 2024 (the Model), published by MAHUD "for adoption by the Urban Local Bodies and Planning & Development Authority, Manipur" (Notification No. BBL-101/1/2024-MAHUD-MAHUD-Part(1) of 4 December 2024), and the building bye-laws that an urban local body or PDA Manipur has brought into force on it by notification in the Manipur Gazette. A building permit is given under the local body's bye-laws. Provision numbers cited in this Manual are those of the Model; where the text a local body has notified differs, that text governs.
Master Plan area; planning area An area for which a master plan has been notified under section 22 of the Manipur Town and Country Planning Act, 1975, or an area notified as a planning area; beyond municipal limits PDA Manipur, constituted under section 13 of that Act, is the Authority there (bye-law 2(2) of the Model). The Greater Imphal planning area of the Revised GIS Based Master Plan for Greater Imphal – 2043 (1st Modification) covers 151.38 km², more than the area of IMC.
Hill areas The areas specified in the First Schedule to the Manipur Legislative Assembly (Hill Areas Committee) Order, 1972 (the definition substituted in the Manipur (Hill Areas) District Councils Act, 1971 in 2008), for which Article 371C of the Constitution provides a Hill Areas Committee of the Legislative Assembly (as summarised). The Manipur Municipalities Act, 1994 does not extend to them (as quoted), and the Model applies only in the areas of urban local bodies and in notified Master Plan or planning areas. The functions of the District Councils under section 29(1) of the 1971 Act include water supply and sanitation schemes, embankments, soil conservation and the allotment of land for residential or other non-agricultural purposes, but not building control. No building or drainage rule for the hill areas was found for this Manual. The Councils' terms expired in November 2022 and the Deputy Commissioners of six hill districts were appointed their administrators in June 2025 (as reported).
River bund; gated outfall An embankment along a river or flood channel of the valley, built and held by the WRD, and an outfall that passes a town's drain through it by a gate, a flap gate or a pump. Most outfalls of the valley towns are of this kind, and they close when the river is high (Chapter 5).
Loktak; Core Zone; Buffer Zone Loktak as defined by section 1(3) of the Manipur Loktak Lake (Protection) Act, 2006: 236.21 km² of open water and marshy land in the south of the valley up to the confluence of the Manipur river and the Khuga, excluding the Keibul Lamjao National Park (40 km²) and the Takmu Fishery Farm (5 km²). Its Core Zone of 70.30 km² is "the No-Development Zone or Totally Protected Zone" and the rest of the lake is the Buffer Zone (s.3).
Paddy land; wetland (2014 Act) Land under paddy farming and "its allied constructions like drainage channels, ponds, canals, bunds and ridges", and wetland, as defined in section 2 of the Manipur Conservation of Paddy Land and Wetland Act, 2014, which may be converted only through the committees of that Act. The Act extends to the areas of the Manipur Land Revenue and Land Reforms Act, 1960, and so not to the hill areas (NEER reading).
Patta land Land held privately and recorded in the revenue records of the valley under the Manipur Land Revenue and Land Reforms Act, 1960, by district, sub-division and revenue village. Where this Manual reserves a drainage corridor, an easement or a regional facility site on patta land, it is reserved in the master plan or secured by agreement, not taken (set by this Manual). In the hill areas land is allotted by the District Councils and held under customary tenure [TBC: not researched].

Commentary. "Replaced" impervious area is defined to the subgrade so that redevelopment of a fully paved site is captured, while routine resurfacing is not. This follows the approach of the APWA 5600 (2025.01) redevelopment triggers (MARC Supplement, 2025).


1.5 Applicability

1.5.1 Who is covered. This Manual applies to:

  • (a) all development requiring planning permission, building permit or layout approval under the Model Manipur Unified Building Bye-Laws 2024;
  • (b) all drainage, road, bridge, culvert, waterbody and flood-mitigation works executed by a ULB, a State department, a board, or a State undertaking; and
  • (c) works executed by Central agencies or their contractors within Manipur, to the extent that the Authority's approval or no-objection is required.

1.5.2 Retention and detention threshold. Chapters 4 and 5 (retention, detention, downstream and tailwater analysis) apply to any development that, over the common plan of development, involves:

  • (a) land disturbance of 0.1 ha or more; or
  • (b) new or replaced impervious area of 500 m² or more.

1.5.3 RWH. The existing RWH mandate continues to apply under bye-law 66 of the Model Manipur Unified Building Bye-Laws, 2024, as each urban local body and PDA Manipur bring it into force, to "all existing and new buildings on plots of 100 square metre and above", whose plans "shall indicate the system of storm water drainage along with points of collection of rain water in surface reservoirs or in recharge wells" (66(a)), with soft cover of at least 15% of the plot where the covered area is 500 m² or more and 10% otherwise (66(b)), with grey-water recycling on the larger buildings, its excess "suitably connected to the rain water recharge structures for ground water recharge" (67), and with a rebate of 10% of the permission fee where both are provided (68), but with no storage volume or roof-area rate; no rainwater harvesting rule applies in the hill areas, as now. This Manual does not change it.

1.5.4 Provisions that apply at every size. The following apply to all development under Clause 1.5.1, whatever its size, unless exempted by Clause 1.5.8:

  • (a) no sewage connection to a storm drain (Chapter 8);
  • (b) lowest habitable floor and openings at or above the 1% AEP level plus 0.5 m, where a 1% AEP level is mapped or determinable (Chapter 6);
  • (c) waterbody setbacks and the no-fill zone (Chapter 7); and
  • (d) no obstruction of a natural drainage path or major-system flow path (Chapter 6).

1.5.5 Common plan of development. The thresholds of Clause 1.5.2 apply to the total area of a development, including all phases, plots and sub-divisions under one layout approval or one ownership at the date of application. A development shall not be divided to avoid the thresholds.

1.5.6 Redevelopment. For redevelopment, the thresholds apply to new plus replaced impervious area. Retention and detention apply to the whole of the new and replaced impervious area, and the pre-development condition is greenfield (Clause 1.4). Where greenfield control cannot be achieved on a constrained redevelopment site, the relief route of Clause 4.5.6 applies: a minimum on-site cut of 50% from existing peaks, with the shortfall paid as fee-in-lieu into basin storage.

1.5.7 Linear public works. For roads, widening and other linear works, the impervious area threshold applies to the added impervious area within each drainage catchment crossed. Retention and detention shall be provided within the right of way, or in a regional facility under Chapter 4, where the right of way cannot hold them.

1.5.8 Exemptions. The following are exempt from Chapters 4 and 5:

  • (a) a single dwelling on its own plot, where the thresholds of Clause 1.5.2 are not met; and
  • (b) linear road resurfacing that adds no impervious area.

Exempt development remains subject to the RWH mandate and to Clause 1.5.4.

1.5.9 Applicability determination. The Applicant shall record the applicability decision on Form 1-1 (Applicability Determination) with the first submittal under Chapter 10. The Authority may confirm or correct it at the pre-application stage.

Figure 1.2 — Applicability decision flowchart Flowchart for Clause 1.5: approval test, exemption test, size threshold test, and flood-sensitive catchment test, leading to the requirements that apply. Development or public work (Clause 1.5.1) Needs building-rules approval, or is it a public work? No Manual not triggered; other rules apply Yes Exempt under Clause 1.5.8? (single dwelling below the threshold, or road resurfacing that adds no impervious area) Yes Exempt from Chapters 4–5. RWH (where mandated) and Clause 1.5.4 still apply No Land disturbance ≥ 0.1 ha, or new or replaced impervious area ≥ 500 m² (Clause 1.5.2)? No Below threshold: RWH (where mandated) and Clause 1.5.4 apply Yes Chapters 4 and 5 apply: retention, detention, downstream and tailwater analysis (+ RWH, 1.5.4) In a flood-sensitive catchment (Annex 1B)? Yes Mixed-frequency rule; full methods only; no Policy Supplement alternatives No Standard rule: Q_post ≤ 0.9 × Q_pre Tier B: design-aid route may be used (Clause 1.7) Decision Chapters 4–5 requirements Chapters 4–5 do not apply

Figure 1.2 — Applicability decision flowchart for Clause 1.5. Original drawing for this Manual.

Commentary. The thresholds have no single direct precedent; they are set by this Manual. Precedents span a wide range:

  • Singapore controls peak runoff from developments of 0.2 ha or more (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5).
  • Malaysia's 2008 DID checklist used on-site detention for sites up to 0.1 ha and community ponds above that.
  • The APWA 5600 (2025.01) Policy Supplement offers alternative triggers of ¼ acre (about 0.1 ha) disturbed, or 1 acre (about 0.4 ha) with 10,000 sq ft (about 930 m²) impervious, and warns agencies not to exceed a 1-acre trigger.
  • MBBL 2016 makes recharge mandatory for buildings over 500 m².

The 0.1 ha / 500 m² trigger sits at the strict end of these, because typical Manipur plots are small and the cumulative effect of many small plots is what fills Imphal's drains. For small buildings in Manipur, the bye-laws that the local bodies have brought into force on the Model reach every plot of 100 m² and more with rainwater harvesting, a plan showing "the system of storm water drainage along with points of collection of rain water in surface reservoirs or in recharge wells" and a soft cover of 10% of the plot or more (bye-law 66). None of it sets a volume, and on the valley floor the tank is full and the ground saturated when the season's storm arrives, so none of it limits what leaves the plot in a design storm. On the valley floor, too, a "recharge well" is a soak pit in clay below the water table; this Manual requires storage there instead (Clause 4.11, valley-floor rule), and where bye-law 67 sends the excess grey water of a larger building "to the rain water recharge structures for ground water recharge", the two conflict: this Manual requires storage or a sewer connection in its place, the applicant seeks the local body's relaxation, and the Manual does not override the bye-law (Table 1.3). No rule asks a single building on the valley floor to set its floor above the water ponded behind a bund, except where bye-law 94 applies in a "high Flood Risk Area" of a master plan, which this Manual cannot locate until the risk-informed master plans are read [TBC]; Clause 1.5.4(b) applies to every building whatever its size for this reason. In the hill areas no building rule was found, and there is no permit to which a small building's drainage could be tied. There the small-site method of Chapter 4 and the hill rule of Clause 4.11, no soak pit on a slope of more than 10° or on the Disang shale, roof water to storage and its overflow to a lined drain, never down an unprotected slope, are offered to the household, the village and the agencies that build in the hills as guidance, not as a condition of any permit.

Clause 1.5.4(b) has no direct precedent; this Manual sets it because floor levels are the cheapest protection a building can have, and it would be perverse to protect only large developments. Where no 1% AEP level is mapped, Chapter 6 gives the method for small sites.


1.6 Tiered adoption

1.6.1 Tier A authorities. The following are Tier A:

  • (a) the Imphal Municipal Corporation (IMC); and
  • (b) PDA Manipur and every other approving authority within the Greater Imphal planning area (151.38 km², the area of the Revised GIS Based Master Plan for Greater Imphal – 2043 (1st Modification)), as that area is notified from time to time under the Manipur Town and Country Planning Act, 1975, whichever has jurisdiction over a site (which body issues building permission in the planning area outside IMC's limits is to be confirmed [TBC]).

1.6.2 Tier B authorities. All other Municipal Councils, Nagar Panchayats and planning authorities are Tier B.

1.6.3 What differs between tiers. All criteria of this Manual apply in both tiers. The tiers differ only in method and review:

Table 1.1 — Differences between Tier A and Tier B authorities

Item Tier A Tier B
Performance criteria (Chapters 2–9) Apply in full Apply in full
Hydrologic method for storage Hydrograph method (Chapter 3) Hydrograph method, or the design-aid route of Clause 1.7 where eligible
Compliance calculator (Clause 10.5) Required as a summary Required; may be the sole calculation on the design-aid route
Policy supplement alternatives (Clause 1.7) Only with State Stormwater Technical Committee concurrence May be adopted by council resolution
Technical review By the Authority By the Authority, with TPD regional support or an empanelled reviewer (Clause 10.7)
Flood-sensitive catchment rule Applies Applies

1.6.4 Moving between tiers. A Tier B authority may opt into Tier A by council resolution. The Government may notify a Tier B authority as Tier A when it becomes a Corporation, joins the Greater Imphal planning area of the Revised GIS Based Master Plan for Greater Imphal – 2043 (1st Modification), or is found by a post-event review (Clause 10.16) to need the full methods.

1.6.5 Flood-sensitive catchments override tier. In a flood-sensitive catchment, whatever the tier, the alternatives of Clause 1.7 are available only as Table 1.2 allows: S-1 (the design-aid route) for sites of 0.5 ha or less (Clause 4.14.1), and S-5 fee-in-lieu where a basin plan has been notified (Clause 1.10.3(d)). S-2, S-3 and S-4 are not available.

Commentary. Imphal Municipal Corporation, with 27 wards, no drain inventory or drainage design standard found for this Manual, and a drainage network that, across Greater Imphal, "is also not in good condition and is not properly connected to the primary drain", where "Drainage system links are missing … the drains are clogged" and "Imphal lacks decentralized stormwater management along streets" (AIIB, Approval Project Document, 2024), while the roadside drains, the river bunds, the city channels and the sewers within its limits are held by other bodies, and the Greater Imphal planning area extends beyond its limits, and a small Nagar Panchayat with one assistant engineer cannot be asked to review the same hydrograph models. The Kansas City solution was to keep one regional standard and publish adoptable alternatives for the most contested criteria, so that smaller agencies can "opt down" without leaving the standard (MARC Supplement, Nov 2025). The tiers here keep the performance criteria the same in both tiers and vary only the method, so that a building in a Tier B town is protected to the same level as one in Imphal.


1.7 Policy supplement: adoptable alternatives

1.7.1 The Government shall publish, with this Manual, a Policy Supplement (Annex 1C) of alternative clauses. An Approving Authority may adopt one or more alternatives under the conditions in Clause 1.7.3.

1.7.2 The alternatives are:

Table 1.2 — Policy supplement: adoptable alternatives S-1 to S-5

No. Main-text requirement Adoptable alternative Eligibility
S-1 Storage sized by hydrograph method (Chapter 3) Design-aid route: retention and detention volumes taken from the unit-storage tables (m³ per ha, by rainfall zone, soil group and impervious fraction) in Annex 4 and the compliance calculator Sites ≤ 2 ha outside flood-sensitive catchments; ≤ 0.5 ha within them (as Clause 4.14.1)
S-2 Release rate Q_post(T) ≤ 0.9 × Q_pre(T), computed for the site Permissible site discharge (PSD): a tabulated unit-area release rate (m³/s/ha) by zone and AEP, derived from the 0.9 × Q_pre rule Any site outside flood-sensitive catchments
S-3 Waterbody setback extended to the mapped 1% AEP flood extent plus margin (Chapter 7) Fixed-width setback table by waterbody class, where no 1% AEP extent is mapped. Never less than the Zone 1 minimum of Clause 7.4.7 Waterbodies with no mapped 1% AEP extent
S-4 Downstream analysis by hydraulic model (Chapter 5) Screening checklist of downstream capacity and known flooding, with a model only where the screen fails Sites < 1 ha, outside flood-sensitive catchments, not discharging to a tidal outfall
S-5 On-site detention Fee-in-lieu toward a regional facility or restored tank storage in a master-planned basin (Chapter 4) Where a basin plan has been notified

1.7.3 Conditions on adoption.

  • (a) An alternative shall not lower any criterion below the values of this Manual. S-1 and S-2 are simplified methods for meeting the same criterion. They are not lower criteria.
  • (b) A Tier B authority adopts an alternative by council resolution, sent to the State Stormwater Technical Committee within 30 days. A Tier A authority needs the Committee's concurrence before adoption.
  • (c) The adopted alternatives shall be published on the Authority's website and in the register of Clause 10.17.
  • (d) Retention (Annex 2E depth) cannot be replaced by any alternative, except where fee-in-lieu under S-5 funds equivalent retention in the same basin.
  • (e) The tables for S-1, S-2 and S-3 shall be issued by the State Stormwater Technical Committee, and reviewed with Chapter 2 (Clause 2.14).

Commentary. The supplement follows the model of the APWA 5600 (2025.01) Policy Supplement, which gives alternatives for the four most contested criteria (applicability, Rational Method limits, stream setback trigger, and Zone 2 setback width). Two of those map onto S-3 and onto the applicability threshold of Clause 1.5.2. Alternative S-3 copies the APWA answer to the same problem: the 1% AEP extent is not mapped for small drainage areas, so a fixed-width table is offered. S-2 follows the Kansas City 2011 shift from "match existing" to fixed unit-area release rates. Local agencies preferred a set rate because existing conditions were hard to determine consistently (MARC Evolution deck). It also reflects the Sydney Water permissible site discharge (PSD) method. The 2 ha / 0.5 ha limits for S-1 (matching Clause 4.14.1) and the 1 ha limit for S-4 have no direct precedent; they are set by this Manual.


1.8 Relationship with other instruments

1.8.1 This Manual shall be applied together with the instruments below. Where they overlap, Clause 1.3.3 governs.

Table 1.3 — Relationship with other instruments

Instrument Relationship
Model Manipur Unified Building Bye-Laws, 2024 (MAHUD Notification No. BBL-101/1/2024-MAHUD-MAHUD-Part(1) of 4 December 2024; Manipur Gazette Extraordinary No. 253 of 5 December 2024), published under section 213 of the Manipur Municipalities Act, 1994 and section 26(1) of the Manipur Town and Country Planning Act, 1975 "for adoption by the Urban Local Bodies and Planning & Development Authority, Manipur" (read) Continue, as each urban local body and PDA Manipur bring them into force. They extend to "the Master Plan areas or notified Planning areas and area under the jurisdiction of all the Urban Local Bodies of Manipur" (1(2)). They require a "Detailed drainage plan for both internal and external" drains "up to the available permanent/pucca drain" for multi-storeyed, lifeline and special buildings and an intermediate treatment chamber before any soak-pit outlet to a municipal drain (6(1)(A), (D)); forbid building over a municipal drain (16); send rain-water pipes to a surface drain, never directly into a closed drain or a soil pipe (28); allow no open drain "except for rain water" in a required open space; bar new construction in the buffers of bye-law 93 and set the plinth 1 m above the highest flood level in high flood risk areas of a master plan (94); define a basement (2(11)) without excluding it from low-lying or flood-prone land; and reference IS 14458 for retaining walls in hill areas. Bye-law 92, as printed, would bar all of Greater Imphal and is read with the IMC (3rd Amendment) 2024 draft text (Commentary to Clause 1.3). They set no design storm, return period, release rate or detention volume. The design criteria of Chapters 2–6, the valley-floor, hill and recharge rules of Clause 4.11 and the corridors of Chapter 7, whose Zone 1 is at least 15 m, are this Manual's proposals; they are not statutory values, and no authority has adopted them. Where the bye-laws, a master plan or a statute are stricter, they govern (Clause 1.3.3).
The building bye-laws brought into force on the Model: the Kumbi, Moirang and Jiribam Municipal Councils' building bye-laws, 2025 (final gazette of 16 January 2025, as listed on the TPD site); "Building Bye-laws for ULBs of Manipur – Final Gazette Notification" (15 December 2025, as listed; not read); the IMC Building Bye-Laws, 2025 (reported notified on 15 December 2025, as reported); the IMC Building Bye-laws, 2013, as amended in 2019 and 2022 (as listed), and the IMC Building Bye-Laws (3rd Amendment), 2024 (draft read) Govern where in force. A building permit is given under them, not under the Model. Which text is in force in IMC and in each Municipal Council and Nagar Panchayat, and whether bye-laws 66 and 92–94 survive in it unchanged, are to be confirmed [TBC]; provision numbers in this Manual are the Model's. The IMC (3rd Amendment) 2024 draft inserts the slope classes of 92.1 and 92.2, repeats the river buffer table (93.1) and ties the plinth rule to "High Flood Risk Areas identified in the Risk-Informed GIS-Based Master Plan for Greater Imphal" (93.2); it was to come into force on a date to be appointed, and its final status was not confirmed [TBC].
Rainwater harvesting and grey water: bye-laws 66, 67, 68 and 6(1)(C)(j) of the Model; the green-building criteria annexed to it Continue unchanged. Bye-law 66(a) makes "Water harvesting through storing of water runoff including rainwater in all existing and new buildings on plots of 100 square metre and above" mandatory, with "points of collection of rain water in surface reservoirs or in recharge wells" on the plans; 66(b) sets soft cover of at least 15% of the plot where the covered area is 500 m² or more, and 10% otherwise; 67 requires grey-water recycling for a covered area of 500 m² or more or 10,000 L/day, with the excess "suitably connected to the rain water recharge structures for ground water recharge"; 68 rebates 10% of the permission fee where both are provided; and the green-building criteria ask to "Minimize storm water run-off from site by reducing hard paving on site" and for "erosion and sedimentation control". None sets a storage volume or a roof-area rate. This Manual counts stored water against its retention requirement only as reuse (Clause 4.4.3), never as detention. Bye-law 66 is no conflict on the valley floor, because it allows surface reservoirs and the Manual chooses them; bye-law 67's routing to recharge structures is: on the valley floor such a structure is a soak pit in clay, so this Manual requires storage or a sewer connection in its place, the applicant seeks the local body's relaxation, and the Manual does not override the bye-law (Clause 4.11, valley-floor rule).
Manipur Town and Country Planning Act, 1975 (Manipur Act 11 of 1975; the (Fifth Amendment) Act, 2023 and (Sixth Amendment) Ordinance, 2026 listed, not read); the Planning and Development Authority, Manipur (PDA Manipur), constituted under its section 13; the Unified Zoning/Use Regulation Bye-laws for the Master Plan Areas of Manipur, 2026 (MAHUD Notification No. BBL-101/1/2024-MAHUD-MAHUD of 22 July 2026; Gazette Extraordinary No. 157 of 23 July 2026); the Revised GIS Based Master Plan for Greater Imphal – 2043 (1st Modification) (No. SCS-401/3/2021-MAHUD-MAHUD-Part(3) of 4 December 2024); the Risk Informed GIS Based Master Plans for Imphal and Moirang (final notifications listed for 17 January 2025; not read) Continue. The 1975 Act "extends to the whole of the State of Manipur" (s.1(2)), provides for master plans (s.22) and for Authorities with jurisdiction over notified areas (s.13), in which State khas land within the master-plan area vests; PDA Manipur's year of constitution is given as 1975 and as 1976 (as reported) [U]. The zoning bye-laws of 2026 classify uses in every Master Plan area, including the zones "Agriculture" and "Pond, Drain, Rivers and Canals", and list "Rain Water Harvesting System" as a use. The master plan for Greater Imphal covers 151.38 km² and has no storm-water drainage section: its "Physical Infrastructure" covers water supply, sewerage, electricity and solid waste. It records that "The town is below the high flood level of Imphal river", earmarks about 500 ha of wetland "for the construction of water bodies", and shrinks wetlands from 374.48 ha to 232.21 ha and agricultural land from 5,616.53 ha to 2,604.70 ha by 2043. The TPD reports the draft report of the risk-informed master plans for Imphal and Moirang as "submitted" while its site lists their final notifications, an inconsistency not resolved here [U]; their flood zones were not read and are not cited [TBC]. GIS master plans are being prepared for Thoubal, Kakching, Lilong (Thoubal), Mayang Imphal and Nambol and for 14 district headquarters "both valley and hills", with a horizon of 2042. Master plans would show the flood-sensitive catchments, drainage reserves and regional facility sites of this Manual (Chapter 11).
Manipur Municipalities Act, 1994 (Act 43 of 1994) Continue. The Act "extends to the whole of the State of Manipur except the Hill Areas" (as quoted), and the bye-laws are made under its section 213. Its sections on the vesting of drains, consent to connect and nuisance were not read for this Manual [TBC]. The State has 27 urban local bodies, among them the Imphal Municipal Corporation with 27 wards; IMC's corporation status is dated 2014 by some sources and to the Manipur Municipalities (Tenth Amendment) Act, 2016 by another (as reported) [U].
Manipur Loktak Lake (Protection) Act, 2006 (Manipur Act 3 of 2006; No. 2/14/2006-Leg/L of 5 April 2006; Gazette Extraordinary No. 13(E)), as amended by Acts 5 of 2007 and 8 of 2019 (Act 1 of 2012 listed, not read) Apply within the lake's 236.21 km² (s.1(3)), excluding the Keibul Lamjao National Park (40 km²) and the Takmu Fishery Farm (5 km²). The Core Zone of 70.30 km² is "the No-Development Zone or Totally Protected Zone" (s.3); in the Buffer Zone the Act bans, among other things, the "Discharge of untreated wastes and effluents from industries, cities or towns and other human settlements" and "Land reclamation, bunding or disturbing the natural course of drainages" (s.19(iv), (vi)); in the Core Zone no person shall "discharge or emit any sewage or domestic waste into the lake" without the Authority's prior permission (s.20). Its "Sewage effluent" includes "sludge from open drains" (s.2). The Loktak Development Authority administers it, with the Forest and Environment Department as nodal department (s.35(2)). The Act does not reach upstream of its 236.21 km², and this Manual does not claim that it does; the interception rules of Chapter 8 apply to outfalls in the lake's catchment.
Manipur Flood Plain Zoning Act, 1978 (Manipur Act 10 of 1978; assent 26 August 1978; Gazette Extraordinary No. 185 of 1 September 1978; read only in the OCR of a truncated copy, sections 1–7) Apply in a flood zone once one is notified; none has been. The Act provides that flood plain zoning "shall be made" by notification, for surveys by the Deputy Commissioner "or such other authority" as the Flood Zoning Authority, and for zones delineated "with reference to relative risk", the flood zone being the area required to carry the flow of "the maximum probable" flood (OCR damaged); its provisions other than section 1 come into force on dates to be appointed. Demarcation of flood zones in the State "is yet to be done" (as reported, June 2026), and no constitution of a Flood Zoning Authority or zone notification was found; an eviction order of April 2025 along the channels of the Imphal river cited its "Section 24" (as reported; section 24 not read [TBC]). Bye-law 93 routes activity in "the prohibited area or restricted area" through that Authority. This Manual's 1% AEP map of Chapter 7 is offered as an input to any future zoning, not as a zone.
Manipur Conservation of Paddy Land and Wetland Act, 2014 (Manipur Act 10 of 2014; No. 2/38/2014-Leg/L of 2 September 2014; Gazette Extraordinary No. 150); the Manipur Conservation of Paddy Land and Wetland (Third Amendment) Bill, 2026 (Bill No. 6 of 2026, as introduced; not law) Continue in the areas of the Manipur Land Revenue and Land Reforms Act, 1960, that is, not in the hill areas (NEER reading). Paddy land, with its "drainage channels, ponds, canals, bunds and ridges", and wetland may be converted only through the Local Level Monitoring Committees, led by Sub-Divisional Officers, and the District and State Level Committees (ss.2–4); "no local authority shall grant any licence or permit … for carrying out any activity or construction in a paddy land, converted or reclaimed in contravention" of the Act (s.12); and the penalty is imprisonment of three to five years and a fine of ₹50,000 to ₹2 lakh (s.18). The Bill of 2026 would exempt land in a notified Master Plan area used in "strict conformity" with the plan and allow "Deemed Conversion" on self-declaration; it is not cited as law. Where valley paddy land or wetland is converted and built on, this Manual requires the flood storage lost below the 1% AEP level to be replaced in the same basin (Chapter 7).
Manipur (Hill Areas) District Councils Act, 1971, as amended (continued under the Manipur (Adaptation of Laws) Order, 1972; amended in 2006, 2008, 2017 and 2018); Article 371C of the Constitution and the Manipur Legislative Assembly (Hill Areas Committee) Order, 1972; the Manipur Village Authorities in Hill Areas Act, 1956 (not read) Continue in the hill areas. The District Councils' functions under section 29(1) include water supply and sanitation schemes, embankments, soil conservation and the allotment of land for non-agricultural purposes, and any matter the Governor entrusts "in consultation with the Hill Areas Committee"; they include no building control. Section 29(1A), inserted in 2006, would let a Council notify an urban area "for the purpose of formulation of development plan" from a date to be notified, which was not found; it is not treated as in force. Section 52(c) of the 1971 text provides for bye-laws on the pollution of waters "set apart for drinking or culinary purposes". The Deputy Commissioners of six hill districts have administered the Councils since June 2025 (as reported). No building or drainage rule of a District Council or Village Authority was found [TBC]. The Manual has no force in the hill areas except through public works and a body that adopts it (Commentary to Clause 1.3).
Wetlands (Conservation and Management) Rules, 2017; the Manipur State Wetlands Authority (set up on 31 January 2018) Continue. The Authority has 22 members, with the Minister of Forest, Environment and Climate Change as Chairperson and the Director of the Directorate of Environment and Climate Change as Member Secretary; its seven priority wetlands are Jaimeng, Kachouphung (Achau Maki), Utra Pat, Yaral Pat, Waithou–Phumnom Pat, Pumlen–Khoidum Pat and Ikop–Kharung Pat; 71 wetlands have been delineated and 3 demarcated, and draft notifications of the Yaral, Utra and Waithou–Phumnom pats have been published (DoECC, 2025-26). Until a notification is final, no prohibition under rule 4 applies to them (NEER reading). Loktak is a Ramsar site (as reported). Pats and pukhris are governed by Chapter 7.
High Court of Manipur, PIL No. 8 of 2025, Meeyam Amata Oina Punsinba Lup v. State of Manipur (order of 16.06.2025); the special bench on Loktak (orders of 17.07.2019 and 25.02.2022, as reported; case number not found); the suo motu PIL on the Thoubal river (2019, as reported) Apply where they bind; they are directions, not rules of this Manual. In PIL No. 8 of 2025 the Court recorded the WRD's inspection of Lamphelpat of 2 May 2025, found "no substance" in the petition and disposed of it; the petition recorded that "the entire rain water are required to be discharged through the water canal from Lamphelpat through Samushang and discharged to the Nambul River". The special bench is reported to have barred development or construction in or around Loktak "without the Court's leave" (as reported) [TBC]. The Thoubal river PIL is reported to bar quarrying, sand mining and pollution except under licence (as reported).
National Green Tribunal, OA 606/2018 (the State's reports of July 2025 and December 2025), OA 673/2018 (polluted river stretches; 13 rivers of the State named), OA 325/2015, OA 593/2017, OA 360/2018, OA 351/2019, OA 438/2018 and OA 392/2022, OA 462/2018, and M.A. 26/2019 (order of 22 May 2020) (as listed by DoECC) Apply where they bind. The State reports the interception and diversion of all 72 drains that fall into the Nambul as completed, with their BOD at 42.45–52.34 mg/L and COD at 78.56–97.23 mg/L, sewage generation in urban areas of 70 MLD against 44 MLD of treatment, and treated effluent disposed to "Agriculture canals" (State reports in OA 606/2018); CPCB lists 18 polluted stretches in the State, all Priority V, among them the Nambul from the Singda dam to Bishnupur (CPCB, 2025); and some 4,000 water bodies have been inventoried under M.A. 26/2019, with "Ground truthing … pending" (DoECC). Sewage in storm drains is dealt with in Chapter 8 (Clause 8.9).
Comptroller and Auditor General of India, Report No. 2 of 2017 (Economic and Revenue Sectors, Government of Manipur), performance audit of flood control and flood forecasting to March 2016, and the audits of 2002 and 2008 of the Irrigation and Flood Control Department (as summarised; not read) Inform this Manual. The 2017 audit found that "The overall flood fighting and control activities remained inadequate" (as quoted); the earlier audits cover the Loktak Lift Irrigation Project, whose canals failed "due to siltation of beds", and the Khoupum dam, the Sekmai and Imphal barrages and the Singda dam (as quoted). No audit of IMC's drainage, the Smart City works, AMRUT or the LDA was found.
Groundwater: no State groundwater Act; the Manipur Ground Water (Control & Regulation) Policy, 2023 (prepared, as listed by DoECC; text not read) Continue. No State law regulating groundwater was found. Every assessment unit of the State is "Safe", with a stage of extraction of 8.00% (CGWB, GWRA 2024, as quoted), so recharge is not a design objective of this Manual (Clause 4.11, recharge rule). The WRD is named in this Manual for groundwater records; no State observation-well network was found, and CGWB's dug-well monitoring in Imphal West stopped "since 1991 due to disturbed law and order" (CGWB, Imphal West, 2013).
Environment (Protection) Act, 1986; Water (Prevention and Control of Pollution) Act, 1974; the Manipur Pollution Control Board (MPCB) Continue. The MPCB gives consent to industry and categories of industry in the zoning bye-laws. Sewage in storm drains is dealt with in Chapter 8.
Disaster Management Act, 2005; MSDMA, the Relief and Disaster Management Department, the Revenue Department and the District Disaster Management Authorities Continue. The Relief and Disaster Management Department issues the flood situation reports (as reported); no urban flood plan or standard operating procedure of MSDMA was read for this Manual [TBC], and no order of the State fixing a date for pre-monsoon desilting was found; the works calendar of Chapter 10 sets this Manual's dates, beginning with 31 March.
IRC:SP:42-2014, IRC:SP:48 (Hill Road Manual), IS 14458 ("Guidelines for retaining wall for hill area", referenced by the Model) and the practice of the Public Works Department and the national-highway agencies on road and hill-road drainage Apply to the drainage of roads and hill roads, cross-referenced from Chapter 6, where they do not conflict with it; the drainage clauses of IRC:SP:48 were not read for this Manual [TBC].
CPHEEO Manual on Storm Water Drainage Systems (2019) Engineering reference. This Manual sets higher return periods under Clause 1.3.2.
NDMA Guidelines on Management of Urban Flooding (2010) and MoHUA SOP (2017) This Manual puts into effect the NDMA directives on catchment-based design, detention and retention, waterbody protection and climate-adjusted IDF.
NDMA Urban Flood Risk Management Programme (UFRMP) and AMRUT 2.0 Works funded under these programmes shall comply with this Manual. The development controls of Chapters 4–5 protect the capacity those works create.
IRC:SP:42-2014 and IRC:SP:50-2013 Apply to road drainage only where they do not conflict with Chapter 6.
MBBL 2016, Chapter 9 Model for RWH and for the inspection regime in Chapter 10.

Commentary. RWH in Manipur is framed as a water supply and recharge measure. It works well for that purpose. It cannot, however, be relied on for flood control in the monsoon, because RWH sumps are usually full or the ground saturated by the time a July to September monsoon storm, such as those of late July 1989 and late July 2015, arrives after weeks of rain. The Manual therefore keeps harvest volume and attenuation volume apart, while letting recharge count as retention where it truly removes water from the system.

Manipur is spending on its drains and channels, but without a design basis. The AIIB's Manipur Urban Road, Drainage and Asset Management Improvement Project (P000723) will rehabilitate 547 km of roads in Greater Imphal with "547 km of both side stormwater covered drains" that "channelize the storm water … to the out fall (river)", and states no return period, rainfall intensity or runoff coefficient (AIIB, Approval Project Document, October 2024); the Lamphelpat Waterbody Rejuvenation Project is to "increase its water detention capacity, restore stormwater drainage system" and set up a "real time flood management system with a command center", at a cost of USD 87.84 million, with no design storm in its published summary (NDB, 2021), while the WRD dredges about 300 acres of the pat with "provision for pumping of flood water from the Lamphel pat water body to the Nambul River through Shamushang Nalla during high flood season" (WRD site report in PIL No. 8 of 2025); and the State reports the "Interception & Diversion (I & D) of all drains (72 Nos.) falling into the Nambul River" as completed, with the drains' BOD at 42.45–52.34 mg/L (State report to the NGT in OA 606/2018, December 2025). None of these states a design storm, and no development-control condition stops new plots in the same catchments from using up the capacity such works create. Linking Chapters 4–5 to approvals closes that gap.

The State's law holds some of the tools. The bye-laws on the Model set a river buffer table and a flood plinth, require a drainage plan to "the available permanent/pucca drain" for larger buildings and rainwater harvesting on plots of 100 m² and more (bye-laws 6(1)(D), 66, 93, 94); the Unified Zoning Bye-laws, 2026 provide a use zone "Pond, Drain, Rivers and Canals"; the Loktak Act bans the discharge of untreated urban effluent and the disturbing of "the natural course of drainages" in the lake's Buffer Zone (s.19); the paddy-land Act bars any local authority from licensing construction on land converted in contravention of it (s.12); and the Manipur Flood Plain Zoning Act, 1978 provides for flood zones, none of which has been notified (zone demarcation "is yet to be done", as reported in June 2026). The courts and the tribunal have acted too: the High Court disposed of a PIL on Lamphelpat after the WRD's inspection (PIL No. 8 of 2025, order of 16.06.2025), its special bench is reported to have barred development in or around Loktak "without the Court's leave" (orders of 17.07.2019 and 25.02.2022, as reported), and the NGT's supervision of waste and polluted rivers (OA 606/2018; OA 673/2018) produced the Nambul interception works. What the law lacks is a design standard. None of these instruments says how large a drain must be, which storm it must carry, how long a gated outfall stays shut while the river is high, how much storage a converted paddy field removes, or how much water a hill site may put into its slope; the bye-law buffers are measured from mid-stream, so that on a wide reach they leave little room beside the bank (NEER reading); and none applies in the hill areas. This Manual's checks are framed as part of the permission given by the competent authority for the area, under the bye-laws a local body has brought into force on the Model, not as a separate no-objection certificate. This Manual is offered as a technical companion to these instruments, to the orders of the courts and the tribunal and to the drainage and river works of the towns: it supplies the design storm, detention, outfall-closed, infiltration, hill-site drainage and corridor numbers they do not set, as a proposal for the Government, the local bodies and the other authorities to consider. Neither MAHUD, the TPD, PDA Manipur, IMC, any Municipal Council or Nagar Panchayat, the WRD, any District Council nor any other body has adopted it.


1.9 Roles and responsibilities

1.9.1 The responsibilities below apply under this Manual. They do not change any agency's statutory powers.

Table 1.4 — Roles and responsibilities under this Manual

Agency Role under this Manual
Municipal Administration, Housing and Urban Development Department (MAHUD) Publishes the Model bye-laws and the Unified Zoning Bye-laws and notifies the master plans. Would prepare the amendment of Clause 1.3.1(a) to the Model, under section 213 of the Manipur Municipalities Act, 1994 and section 26(1) of the Manipur Town and Country Planning Act, 1975, and commend it to the urban local bodies and PDA Manipur; could add the Manual's drainage reserves to the zoning bye-laws' "Pond, Drain, Rivers and Canals" zone.
Town Planning Department (TPD) Prepares the master plans of Greater Imphal and the towns, and of 14 district headquarters "both valley and hills"; checks building plans for land-use compatibility with the master plan on OBPS (about 150 plans forwarded by IMC in 2025-26); is the nodal department for AMRUT and AMRUT 2.0, including 20 pond-rejuvenation projects. Would show flood-sensitive catchments, drainage reserves, pat buffers, the 1% AEP areas and regional facility sites in the master plans (Chapter 11), add the drainage report to the OBPS check, issue the model bye-law of Clause 1.3.1(b) and give regional support to Tier B authorities (Table 1.1).
Planning and Development Authority, Manipur (PDA Manipur) The "Authority" under the Manipur Town and Country Planning Act, 1975 in the Master Plan and planning areas beyond municipal limits (bye-law 2(2) of the Model). Could adopt the amendment in its bye-laws; if it did, it would require the drainage report of Chapter 10 with each application, check floor levels and the hill rule at the plinth inspection, and record drainage reserves and easements in the permissions it grants.
State Stormwater Technical Committee (Clause 1.3.2) Would adopt higher standards, issue Annexes, tables and the compliance calculator, concur with Tier A alternatives, decide variances referred to it and review the Manual (Clause 1.12).
Imphal Municipal Corporation (IMC) and the other urban local bodies (Municipal Councils and Nagar Panchayats; 27 in all) Give building permits under the bye-laws they have brought into force on the Model and hold the municipal drains of their areas (bye-law 16). Could adopt the amendment in their bye-laws; would then apply this Manual to their own works, keep the drain register of Table 1.5, receive handed-over assets (Clause 10.14), and inspect and enforce (Clauses 10.12–10.15). IMC would also keep its drains free of the market waste that blocks the Naga Nullah.
Water Resources Department (WRD), formerly the Irrigation and Flood Control Department Builds and holds the river bunds and flood channels of the valley, develops Lamphelpat as flood storage with its pumped outlet through the Shamushang nallah to the Nambul, provides machinery to clear the city channels, and keeps the river gauges whose levels the press prints. Would supply river levels, gauge zeros and flood marks for Chapter 5, set the conditions for any outfall, gate or pump through its bunds, approve the site study of Clause 2.3.6(b) for rural rivers, could advise any Flood Zoning Authority, and would apply this Manual to its own works.
Public Health Engineering Department (PHED) Builds and runs the Imphal Sewerage Project (Phase I in 11 wards since June 2020; Phase II for the other 16 wards and 4 outgrowths) and the water supply. Would keep the sewer and storm networks separate in the Phase II wards and keep sewage overflows out of the storm drains it serves (Chapter 8).
Public Works Department (PWD) and the national-highway agencies Build and maintain the roads, their side drains and culverts, among them the 547 km of roads and "both side stormwater covered drains" of the AIIB project in Greater Imphal, and NH-37 and NH-2. Would apply Chapter 6 and the hill-road rules to them and never discharge a road drain onto an unprotected slope; in the hill areas they are the main route by which this Manual reaches drainage.
Directorate of Environment and Climate Change (DoECC), under the Forest, Environment and Climate Change Department Runs the Nambul rejuvenation, with the interception and diversion of 72 drains to a plant of 16–17 MLD, monitors the rivers, and is the secretariat of the Manipur State Wetlands Authority; its Department is the nodal department for the Loktak Act (s.35(2)). Would receive the records of sewage found in storm drains under Chapter 8 and could align wetland protection with the corridors of Chapter 7.
Loktak Development Authority (LDA) Administers the Loktak Act within the lake's 236.21 km² and gives the prior permission of section 20; is reported to have led the cleaning of the Waisel Maril channel in Imphal (as reported). Could apply this Manual within the lake and its margin and would be the competent authority for the area there.
Manipur State Wetlands Authority (MSWA) Identifies and notifies wetlands under the 2017 Rules; has published draft notifications of the Yaral, Utra and Waithou–Phumnom pats. Its consent would be needed before a notified wetland is used for storage or as an outfall (Chapter 7).
Manipur Pollution Control Board (MPCB) Gives consent to industry. Would receive the records of sewage found in storm drains under Chapter 8.
Local, District and State Level Committees under the paddy-land Act Decide the conversion of paddy land and wetland (the Local Level Monitoring Committees led by Sub-Divisional Officers). Could make the replacement of lost flood storage (Chapter 7) a condition of conversion.
Flood Zoning Authority (Manipur Flood Plain Zoning Act, 1978; not found constituted) Once constituted, would survey rivers, notify flood zones and grant the permissions that bye-law 93 refers to; it could use the corridor maps of Chapter 7. Until then no flood zone exists.
Imphal Smart City Ltd Carries out area-based development in Thangal, Paona Bazar, the DM College campus and Kangla, about 504 acres (as reported); its drainage role was not found [TBC]. Would design its drainage works to this Manual from the dates of Clause 1.11 and hand them over under Clause 10.14.
Hill Areas Committee, the District Councils (administered by the Deputy Commissioners since June 2025, as reported) and the Village Authorities Govern the hill areas under Article 371C and the 1971 Act; the District Councils' functions include water supply and sanitation schemes, embankments and land allotment, but no building control, and no building or drainage rule of theirs was found [TBC]. The Manual has no force in the hill areas unless a body adopts it. A District Council could take it up as a matter entrusted by the Governor under section 29, or through a development plan under section 29(1A) once in force; none has. The Village Authorities hold or speak for much of the land on which hill drains and streams lie.
MSDMA, the Relief and Disaster Management Department, the Revenue Department, the Deputy Commissioners and the District Disaster Management Authorities Prepare for and respond to floods and landslides, report their tolls and keep the land records of the valley. Would supply the flood, breach and landslide inventories used in the screening of Clause 2.3.6(i) and lead post-event reviews with the Authority (Clause 10.16). In the hill areas land is allotted by the District Councils and held under customary tenure [TBC].
NHPC (Loktak Hydroelectric Project and the Ithai barrage) and the operators of the Mapithel (Thoubal Multipurpose Project), Khuga and Singda dams [TBC] Hold Loktak up at the Ithai barrage and the valley's reservoirs. Would supply lake and reservoir levels, release rules and release records in writing for Chapter 5 and the screening of Clause 2.3.6(i).
Central Water Commission (CWC), a body of the Union Monitors the level of the Barak at Chotebekra, its one site in the State. Would supply its records for Chapter 5 and confirm whether a Flood Estimation Report for subzone 2(c) exists or is in preparation (Clause 2.3.6(b)).
Central Ground Water Board (CGWB), North Eastern Region, a body of the Union Assesses the State's groundwater (every unit "Safe"; stage of extraction 8.00% in 2024, as quoted) and published the district booklets on which the valley-floor rule of Clause 4.11 rests. Would supply groundwater levels with the WRD.
IMD (Meteorological Centre Imphal), NRSC, MASTEC, and road and rail owners IMD's station at Imphal (Tulihal) (42623) supplies the rainfall record of Chapter 2 and is the first data request of Clause 2.3.6(a); NRSC and MASTEC hold landslide and flood-hazard studies used in the screening of Clause 2.3.6(i). Road and rail owners would apply this Manual to road drainage (Chapter 6), culverts and linear works (Clause 1.5.7).

Commentary. Stormwater in Manipur is split, first, by the line between the valley and the hill areas. In the valley MAHUD makes the Model bye-laws, the zoning bye-laws and the master plans, the TPD prepares the plans and checks land use, the urban local bodies and PDA Manipur give permission under the bye-laws they have brought into force, and the land is mostly patta land with revenue records; in the hill areas no building or drainage rule was found, the District Councils hold land and village functions but no building control, and they have been run by Deputy Commissioners as administrators since June 2025 (as reported). The split is then repeated among the bodies that drain the valley: the urban local bodies for the municipal drains, the PWD for the roadside drains, among them the 547 km of the AIIB project, the WRD for the river bunds, the flood channels, Lamphelpat and the Shamushang pumping, PHED for the sewers, DoECC for the interception of the 72 drains that fall into the Nambul, the LDA for Loktak, NHPC for the Ithai barrage that holds the lake up, and the courts and the tribunal, which have acted on Lamphelpat, Loktak and the polluted rivers. Imphal shows why the split matters. The Nambul is at once the city's main urban river (AIIB), a trunk storm drain, the receiving water of drains whose BOD is 42–52 mg/L, a Priority V polluted stretch (CPCB, 2025) and the outfall of Lamphelpat's flood pumps; the Naga Nullah carries market waste into it; and the Imphal river, the Kongba and the Iril stand above the town behind their bunds. No notification assigns the Naga Nullah, the Waisel Maril or the Shamushang nallah to one owner (NEER reading), and the drainage sections of the Manipur Municipalities Act, 1994 were not read [TBC]. Until the State issues a rule [TBC], this Manual assigns the drainage elements as in Table 1.5, as Chapter 6 does for the drains themselves, and recommends that each town keep a drain register giving every reach its owner, the river it reaches, the bund it crosses (with its gate or flap gate), whether it lies in a buffer of bye-law 93, its land status (patta or government land) and its outfall (set by this Manual). The assignment is this Manual's working split for applying its clauses; it does not change any agency's powers, and on private land it is put into effect by reservation in the master plan or by agreement, not by acquisition.

Table 1.5 — Working assignment of drainage elements under this Manual

Element Assigned to
Municipal drains within the limits of an urban local body The urban local body (bye-law 16, "municipal drain"; the drainage sections of the Manipur Municipalities Act, 1994 not read [TBC]); in Imphal, IMC
Roadside drains of State roads, among them the 547 km of "both side stormwater covered drains" of the AIIB project in Greater Imphal PWD
Drains of national highways The national-highway agencies
River bunds, flood channels, Lamphelpat and the Shamushang pumping, and machinery for clearing the city channels The WRD
The interception and diversion of the 72 drains that fall into the Nambul, and its plant of 16–17 MLD DoECC
Sewers and sewage pumping stations PHED
The cleaning of the Waisel Maril (as reported), and Loktak within its 236.21 km² The LDA
Drains and channels of the hill areas The department that executes the work (PWD, PHED or the WRD); other drains [TBC] (no District Council drainage rule was found)
Drains built by Imphal Smart City Ltd, until handed over in writing Imphal Smart City Ltd [TBC], and the urban local body after handover

This Manual names departments and authorities as the statutes, orders and records name them. A manual that names one owner for each task does not fix institutions by itself, but it removes ambiguity about who signs what.


1.10 Variances and waivers

1.10.1 Variance. The Authority may grant a variance from a numeric requirement where the Applicant shows, through a report certified under Clause 10.6, that:

  • (a) compliance is impracticable because of site conditions such as a high groundwater table, contaminated soil, rock, or a site area too small for the required facility; and
  • (b) the proposed alternative gives equal or better performance at the downstream point of Chapter 5, or the shortfall is made up by fee-in-lieu or off-site works in the same catchment.

1.10.2 Waiver. The Authority may waive Chapter 4 detention requirements (not retention) where a hydraulic analysis certified under Clause 10.6 shows that the site discharges directly to the sea, or to a tidal reach with no flood-prone property downstream, and that undetained flow does not worsen the outfall-closed condition of Chapter 5. Manipur has no coast and no tidal reach, so no site in the State qualifies for this waiver. A site that drains to a valley river through a bund gate, a flap gate or a pumping station, to a pat or pukhri behind such an outfall, to Loktak, held up by the Ithai barrage, to the Barak or the Jiri at Jiribam, or to a reach below a dam, is in the outfall-closed condition of Chapter 5 whenever the receiving water is high, and detention is not waived for it; nor is it waived for a site because it drains to a steep hill stream or down a hill slope.

1.10.3 No variance or waiver. No variance or waiver shall be granted for:

  • (a) a sewage connection to a storm drain;
  • (b) the lowest habitable floor level of Chapter 6;
  • (c) any reduction of a waterbody setback below the Zone 1 minimum of Clause 7.4.7, or any fill or construction in the no-fill zone of Chapter 7; or
  • (d) the retention requirement in a flood-sensitive catchment, except by fee-in-lieu under Clause 1.7.

1.10.4 Procedure.

  • (a) The request shall be made on Form 1-2 (Variance / Waiver Request) with the preliminary drainage report.
  • (b) A Tier B authority shall refer any variance on a site of 1 ha or more to the State Stormwater Technical Committee.
  • (c) A decision shall state its reasons and any conditions, and shall be entered in the public register of Clause 10.17.
  • (d) A variance runs with the approval. It lapses if the approval lapses.

Commentary. The 2006 APWA 5600 included a waivers section (5601.6), and Georgia allows waivers where downstream analysis shows a peak control is unnecessary. The waiver of Clause 1.10.2 is narrow: on a tidal coast, undetained flow can help by passing through before the tide closes the outfall, but only an analysis can show that. This Manual requires every decision to be published because publication deters case-by-case erosion of the standard; in Manipur the notified master plan for Greater Imphal shrinks the planning area's wetlands from 374.48 ha to 232.21 ha and its agricultural land, which on the valley floor holds floodwater, from 5,616.53 ha to 2,604.70 ha by 2043 (Revised GIS Based Master Plan for Greater Imphal – 2043 (1st Modification)); a Bill of 2026, not known to have been enacted, would exempt land that conforms to a notified master plan from the paddy-land Act's bar on conversion and allow "Deemed Conversion" on self-declaration (Bill No. 6 of 2026); MASTEC records that "there were nearly 500 lakes in Manipur Valley" and names Lamphelpat, Porompat, Takyelpat, Sangaipat, Kharungpat and Ikop pat among the pats that are degraded or disappearing (MASTEC, Flood Hazard Zonation in Manipur Valley); and in April 2025 the authorities ordered the removal of encroachments along the Waisel Maril, the Naga Nallah and the eastern bank of the Nambul (as reported).


1.11 Transition provisions

1.11.1 Effective date. This Manual takes effect for new applications 6 months after notification (the effective date).

1.11.2 Applications in process. An application filed complete before the effective date may be decided under the rules in force when it was filed, if a decision is issued within 12 months of the effective date. Otherwise, this Manual applies.

1.11.3 Phased start for Tier B. In Tier B authorities, Chapters 4 and 5 apply from 24 months after notification, except in flood-sensitive catchments, where they apply from the effective date.

1.11.4 Public works. DPRs sanctioned before the effective date may proceed as sanctioned. Any DPR revised or re-tendered after the effective date shall comply. Departments shall report non-compliant works in progress to the State Stormwater Technical Committee within 12 months.

1.11.5 Before the annexes are issued. Until an annex referred to in this Manual is issued, the Applicant shall use the method stated in the clause, with values agreed with the Authority and recorded in the drainage report.

Commentary. The 6-month lead time matches the lead time for NIH-DHAARA updates in Clause 2.14.2. Singapore gave a similar interval for its 2025 detention addendum (issued 16 Apr 2025, applied from 1 Oct 2025). The 12- and 24-month periods are set by this Manual to let Tier B authorities train staff and to let the State issue the design-aid tables (Clause 1.7).


1.12 Review and amendment

1.12.1 The State Stormwater Technical Committee shall review this Manual every 10 years, and after any event that exceeds the 1% AEP design depth as set out in Clause 2.14.1.

1.12.2 Amendments shall be notified in the Gazette, published with a change log, and take effect 6 months after notification unless the notification states otherwise.

1.12.3 Any person may propose an amendment to the Committee. Proposals and the Committee's decisions shall be published.


References (chapter)

Annexes and forms

Annex / Form Content
1A List of Tier A authorities, with the boundaries of the Imphal Municipal Corporation and of the Greater Imphal planning area of the Revised GIS Based Master Plan for Greater Imphal – 2043 (1st Modification)
1B Maps of flood-sensitive catchments
1C Policy Supplement: text of alternatives S-1 to S-5 and model council resolution
1D Model Unified Bye-Laws 2024 amendment and model ULB bye-law
Form 1-1 Applicability Determination
Form 1-2 Variance / Waiver Request