Chapter 4Site Runoff Control: Retention and Detention
4.1 Purpose and scope
4.1.1 This chapter sets the performance standard that every regulated development shall meet for runoff leaving the site. It covers:
- (a) the order in which runoff-control measures are to be applied (Clause 4.3);
- (b) retention of frequent rainfall, and how retained volume is credited against detention (Clause 4.4);
- (c) release-rate criteria for standard and flood-sensitive catchments (Clause 4.5);
- (d) the procedure for sizing detention storage and outlets (Clauses 4.6 to 4.9);
- (e) facility types, rainwater harvesting (RWH) accounting, and high-groundwater sites (Clauses 4.10 to 4.12);
- (f) regional detention and fee-in-lieu (Clause 4.13);
- (g) simplified methods for small sites: the Tier B tables and the fixed-coefficient route (Clause 4.14); and
- (h) public safety (Clause 4.15).
4.1.2 This chapter applies to land disturbance of 0.1 ha or more, or new or replaced impervious area of 500 m² or more, as set in Chapter 1. Single dwellings below that threshold, and road resurfacing that adds no impervious area, are exempt. The existing RWH mandate of the building rules (rooftop rainwater harvesting on every plot of 300 m² and more, of all uses including group housing, where there is no collective recharge network, except in waterlogged areas, and recharge reservoirs on at least 1% of the area of every layout of more than 4 ha, under clause 13.1.2 of the Byelaws 2025; the stipulations for rooftop rainwater harvesting that section 31(2) of the UP Ground Water (Management and Regulation) Act 2019 makes binding on every agency that sanctions building plans, with a combined recharge system for group housing and colonies; and, in Noida, Greater Noida and YEIDA, the provisions of their own building regulations [TBC]; the rules are discussed in the Commentary to Clause 4.11) continues to apply to every building it covers, whether or not this chapter applies.
4.1.3 Rainfall inputs come from Chapter 2. Hydrologic methods come from Chapter 3. Tailwater, downstream analysis and the outfall-closed check come from Chapter 5. Water quality volume (WQv) treatment comes from Chapter 8. Where this chapter and those chapters overlap, the more stringent requirement governs.
4.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Retention | Permanent removal of runoff from the surface drainage system by infiltration, evapotranspiration or reuse, so that the water never reaches the outfall. |
| Retention depth | The 90th percentile wet-day 24-hour rainfall depth for the site's zone (Clause 2.10, Annex 2E). |
| Required retention volume (RRV) | The runoff volume from the retention depth over the post-development site (Clause 4.4.2). |
| Detention | Temporary storage of runoff, released through a controlled outlet at a rate set by Clause 4.5. |
| Retention credit | The reduction in required detention storage that results from retention practices, determined by routing under Clause 4.4.6. It is not the same as the retained volume. |
| Permissible site discharge (PSD) | The maximum rate at which a site may discharge for a stated AEP, in L/s or L/s/ha. |
| Site storage requirement (SSR) | The detention storage required per hectare of site under the simplified method of Clause 4.14. |
| Multi-stage outlet | An outlet structure with separate openings at different levels, each controlling a different AEP (Figure 4.2). |
| Drawdown time | Time from the peak stored volume until the stated fraction of that volume has been released. |
| Emergency spillway | A secondary overflow that passes flows above the primary outlet capacity, or all flow when the primary outlet is blocked, without overtopping the embankment. |
| Freeboard | Vertical distance between the maximum design water level and the embankment crest or other critical level. |
| Flood-sensitive catchment | A catchment listed in Clause 4.5.3 or notified under Clause 4.5.4. |
| Authority | The approving authority under Chapter 1 (the development authority or special area development authority constituted under the UP Urban Planning and Development Act 1973 in its development area, under its own edition of the Byelaws 2025; the controlling authority of a regulated area; Noida, GNIDA, YEIDA or UPSIDA in its industrial development area, under its own building regulations; or, where it grants building or layout permission, the Nagar Nigam, Nagar Palika Parishad or Nagar Panchayat concerned, as applicable). |
| Tier A / Tier B | Adoption tiers defined in Chapter 1. Tier A: the Lucknow Municipal Corporation (LMC), every approving authority within the development area of LDA or of any other development authority constituted under the UP Urban Planning and Development Act 1973, including the development authorities themselves and the Nagar Nigams, Nagar Palika Parishads and Nagar Panchayats in those areas, Noida, GNIDA, YEIDA and UPSIDA in their industrial development areas, and every other Nagar Nigam. Tier B: Nagar Palika Parishads and Nagar Panchayats. |
4.3 Order of measures
4.3.1 Every site runoff-control design shall apply measures in the following order, and shall document in the submittal why each earlier step could not do more:
- Preserve. Keep existing waterbodies, tals, natural drainage lines, wetlands, and permeable soils and vegetation. Avoid fill in flood storage (Chapter 7).
- Retain. Retain the RRV on site by infiltration, reuse or evapotranspiration (Clause 4.4).
- Detain. Detain the remaining runoff so that the release-rate criteria of Clause 4.5 are met for every design storm and duration (Clauses 4.6 to 4.9).
- Convey. Convey the 1% AEP (100-yr) flow safely through the site to the receiving system on a defined overland path (Chapter 6), and check the receiving system downstream (Chapter 5).
4.3.2 Preservation and retention reduce the detention required (Clauses 4.4.6 and 4.4.7). They do not relieve the site of the release-rate criteria of Clause 4.5 or of the downstream analysis of Chapter 5.
Commentary. This order follows the "layers of stormwater management" adopted in the Kansas City Metro APWA Section 5600 Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet; MARC Supplement, Nov 2025). Maintenance is the fifth layer and is set in Chapter 10. The 2025.01 manual credits retention and natural-area preservation against detention size (MARC Supplement, Nov 2025). Clause 4.4.6 adopts that credit, and defines it so that it cannot be claimed twice.
4.4 Retention
4.4.1 Requirement
The site shall retain the RRV. Retention shall be achieved by one or more of the following:
- infiltration practices (soakaways, infiltration trenches, permeable pavement with an infiltration base, bioretention);
- rainwater reuse that is drawn down by a demonstrated non-potable demand;
- green roofs and landscape areas that do not drain to the outfall in the retention-depth storm.
The limits of Clause 4.4.4 apply.
4.4.2 Computation of the RRV
RRV (m³) = 10 × Q_R × A
where:
- Q_R (mm) is the runoff depth from the retention depth P_R (Annex 2E). It is computed with the SCS-CN method for the post-development cover of each sub-area, at AMC II, with Ia = 0.2S (Chapter 3); and
- A (ha) is the area of the site that drains to the outfall.
Q_R shall be computed for each sub-area separately and summed. An area-weighted CN shall not be used where impervious and pervious areas differ by more than 20 CN points.
The volumetric method RRV = 10 × P_R × Rv × A, with Rv = 0.05 + 0.009 × I (I = percent impervious), may be used for sites under 0.5 ha and under the Tier B method.
Commentary. The Rv formula is the one used in the KC water quality volume (MARC BMP Manual 2012). It is simple to review for small sites. The SCS-CN form is required for larger sites so that the retention computation uses the same runoff model as the detention routing. That keeps the credit computation of Clause 4.4.6 consistent.
4.4.3 Verification
Retention by infiltration shall be supported by:
- (a) site infiltration tests at the location and depth of each practice, at the frequency set in Chapter 8;
- (b) a design infiltration rate of no more than half of the measured rate; and
- (c) groundwater evidence showing the seasonal high groundwater table at least 1.0 m below the base of the practice (Chapter 8).
Retention by reuse shall be supported by a demand calculation showing that the RRV is drawn down within 72 hours by a continuous non-potable use, such as toilet flushing, cooling or irrigation.
Commentary. The factor of 2 on measured infiltration rate has no direct precedent; this Manual sets it to allow for clogging and for the difference between a test pit and a full-scale practice. Chapter 8 may set a different factor; if it does, Chapter 8 governs.
4.4.4 Limits on retention
4.4.4.1 Infiltration practices shall not be used:
- where the seasonal high groundwater table is less than 1.0 m below the base (Chapter 8);
- on contaminated land;
- within the setbacks from foundations, wells and septic systems set in Chapter 8; or
- on fill, unless tested after placement.
4.4.4.2 Where the RRV cannot be fully retained, the shortfall shall be stated in the submittal. The shortfall shall be treated as WQv under Chapter 8 and shall get no retention credit.
4.4.5 Drawdown of retention
Retention storage shall be emptied by infiltration or reuse within 72 hours of the end of the retention-depth storm, verified by the tests of Clause 4.4.3.
4.4.6 Retention credit: definition and computation
4.4.6.1 What the credit is. The retention credit is the reduction in required detention storage that results when the retention practices are included in the post-development routing. It is computed. It is not assumed equal to the RRV.
4.4.6.2 Tier A method (routing). For each design storm and duration of Clause 4.6.3:
- (a) model each retention practice explicitly as a storage that is empty at the start of the storm, unless Clause 4.11 says otherwise;
- (b) let the practice fill from the front of the storm, and let it lose water during the storm only at the design infiltration or reuse rate of Clause 4.4.3;
- (c) once it is full, route its overflow to the detention facility; and
- (d) size the detention for the residual hydrograph.
The required detention storage is the largest storage over all storms and durations. The credit is the difference between that storage and the storage required with no retention. No further deduction shall be made.
4.4.6.3 Tier B method (simplified). The detention storage required by Clause 4.14 may be reduced by:
V_credit = C_R × RRV_provided
where C_R is the retention credit factor from Annex 4B for the zone, soil group and drawdown rate. Until Annex 4B is published, C_R = 0.
4.4.6.4 Retention that is not verified under Clause 4.4.3 gets no credit.
Commentary. "Credited against detention" (APWA 5600 2025.01) can be read in two ways. One reading subtracts the retained volume from the detention volume, cubic metre for cubic metre. The other routes the storms with retention in place and sees what detention is still needed. The two readings give very different answers in Uttar Pradesh, because the mandatory 48- and 72-hour storms (Clause 2.5.2) fill any retention practice on the first day, long before the peak arrives on the last day (Clause 2.9.2). Unless the practice keeps infiltrating during the storm, it is full at the peak and does nothing to reduce the peak storage.
The illustrative example in Clause 4.6.7 shows the size of the effect. A 2 ha site with 552 m³ of retention (no infiltration during the storm) needs 138 m³ less detention for the 24-hour storm. That is a credit of about a quarter of the retained volume. For the 48- and 72-hour storms, which govern, the credit is close to zero. Subtracting the retained volume directly would have under-sized the detention by about 545 m³ (about 19%).
This Manual therefore defines the credit as the result of routing. Retention on fast-draining sandy soils, which keeps infiltrating through a multi-day storm, will earn a real credit. Retention that only fills will earn little. Both outcomes are physically correct. Setting C_R = 0 until Annex 4B exists is a safe default for Tier B, not a judgement that retention has no value: retention is still required for water quality and recharge (Chapter 8).
4.4.7 Preservation credit
Areas of the site that are permanently preserved in natural cover may be modelled at their pre-development CN in the post-development condition, provided that:
- they are protected by a registered covenant or dedication; and
- their runoff is not concentrated onto impervious surfaces.
This lowers both the RRV and the detention required. No other preservation credit applies.
4.5 Release-rate criteria
4.5.1 General
4.5.1.1 Peak discharge from the site shall be computed by a hydrograph method (Chapter 3) for the pre-development and post-development conditions with identical design storms (Clause 2.11.1). The Rational Method shall not be used for any part of storage sizing.
4.5.1.2 Pre-development is greenfield: open land in good condition for the mapped HSG. Existing impervious cover is not counted (Clause 2.11.5, Chapter 3). This applies to redevelopment as well, subject only to the constrained-redevelopment route of Clause 4.5.6.
4.5.1.3 The criteria apply at each point where runoff leaves the site. Where a site drains to more than one outfall, the criteria apply to each outfall for the area draining to it. Runoff shall not be diverted between catchments.
4.5.2 Standard catchments
For each of the 50%, 10% and 1% AEP (2-, 10- and 100-yr) storms, and for every duration in {1, 2, 3, 6, 12, 24, 48, 72 h}:
Q_post(T, d) ≤ 0.9 × Q_pre(T, d)
4.5.3 Flood-sensitive catchments
4.5.3.1 In the catchments listed below, the mixed-frequency rule of Clause 2.11.3 applies, for every duration in Clause 2.5.2:
Q_post(1% AEP, 100-yr) ≤ Q_pre(10% AEP, 10-yr), and Q_post(50% AEP, 2-yr) ≤ Q_pre(50% AEP, 2-yr).
Each cap is the pre-development peak at the duration that maximises it: the 10-yr peak for the 100-yr check, and the 2-yr peak for the 2-yr check. The cap applies to every post-development duration (Clause 2.11.3).
4.5.3.2 The flood-sensitive catchments are:
- (a) Lucknow behind the Gomti embankments: the catchments of the drains of Lucknow that outfall to the Gomti through pumping stations, gates or regulators in its embankments, including the Kukrail, which cannot discharge to the river by gravity when it is high;
- (b) Gorakhpur behind the Rapti and Rohin embankments: the city of Gorakhpur, including the catchments of the nalas that drain to Ramgarh Tal and of the Goddhoia nala, whose outfalls are held up when the Rapti is high;
- (c) Prayagraj at the confluence: the catchments of the drains of Prayagraj that outfall to the Ganga and the Yamuna, including the low-lying wards of George Town, Tagore Town and Rambagh;
- (d) the Hindon at Ghaziabad and Noida: the low-lying land of Ghaziabad and Gautam Buddh Nagar beside the Hindon, including Karhera, whose drains outfall to the Hindon; and
- (e) any catchment notified under Clause 4.5.4.
The boundaries shall be those mapped in Annex 4A.
4.5.4 Notification of further flood-sensitive catchments
4.5.4.1 The Authority may propose that a catchment be notified as flood-sensitive where one or more of the following is documented:
- (a) buildings or arterial roads flooded in an event of 1% AEP or more frequent, on at least two occasions in the previous 20 years;
- (b) receiving drains or channels with capacity below the 10% AEP flow under existing conditions;
- (c) an outfall that is closed by a gate, regulator or flap gate in a river embankment when the river is high, that depends on pumping, as along the embanked Gomti at Lucknow and the Rapti at Gorakhpur, or that is held up by a river in flood, such as the Ganga at Kanpur, Prayagraj and Varanasi, the Yamuna at Prayagraj and Agra or the Hindon at Ghaziabad and Noida, for part of the SW monsoon (Chapter 5);
- (d) loss of more than a quarter of the mapped tank and tal storage in the catchment since the earliest available survey; or
- (e) a basin master plan that relies on limiting site discharge.
4.5.4.2 The procedure shall be:
- The Authority prepares a technical note with the catchment boundary in GIS form and the evidence for 4.5.4.1.
- The State-level technical committee constituted under Chapter 1 reviews the note.
- The draft notification and map are published for public comment for at least 60 days.
- The Government notifies the catchment and the map is added to Annex 4A.
- The rule applies to applications received 6 months or more after notification. Applications received earlier are assessed under Clause 4.5.2.
4.5.4.3 A notified catchment may be de-notified only by the same procedure, and only after a basin study shows that the downstream system meets Chapter 5 with all development under Clause 4.5.2.
Commentary. The 0.9 factor is derived from the Denver (MHFD) analysis. In that analysis, ten basins each releasing 100% of the historic 100-yr peak still produced 106% of the historic peak at the outlet; releasing 90% at each gave 97% (UDFCD Full Spectrum Detention Release Rate Memorandum, 2012). The mixed-frequency rule has no direct precedent; the nearest is the Malaysian DID (2008) checklist, which required post-development 2-, 10-, 50- and 100-yr peaks below the pre-development 2-yr peak. The specific "100-yr post ≤ 10-yr pre" form appears in a New Berlin, Wisconsin planning discussion (not an adopted rule). The Lucknow entry follows the way the city drains. Thirty-three of its 34 drains join the Gomti (Jal Kal, LMC, reply in NGT O.A. 403/2024, from a search summary), the river is held between embankments through the city, and outfalls inside them are pumped when it is high; an inspection report found that "at Kukrail pumping station, only half the pumps" were working and that "in Wazirganj, all pumps were non-functional" (search summary of an undated report [TBC]), and LDA has proposed 12 more pumping stations along the embanked river between IIM Road and Kisan Path (as reported). The Gomti's highest flood level at Lucknow is 110.85 m (11 September 1971), against a danger level of 109.5 m (CWC values as compiled by SANDRP, as reported; another report gives a "normal high flood level" of 108.81 m [TBC]). The city's storms are heavy: 20 cm fell at Lucknow in the 24 hours to 16 September 2022 and 14 cm in the 24 hours to 11 September 2023 (IMD), and the UDD guideline of December 2024 cites "Lucknow 2023" as a flash flood. In May 2024 the Supreme Court agreed with the High Court that the Akbar Nagar colony on the Kukrail stood on its floodplain (as reported). The Gorakhpur entry follows August 1998, when the Rapti reached 77.54 m at Birdghat, 2.56 m above its danger level, with 13 breaches of embankments in the district (as reported); it reached 77.27 m in 2020 (as reported). Wards such as Mehewa flood "after relatively small amounts of rain" (ISET and CDKN 2014, from its summary), and six nalas of the city flow into Ramgarh Tal, whose notification of 7 December 2020 gives it a 50 m zone of influence. The Prayagraj entry follows the river levels and August 2026. The Ganga at Phaphamau and the Yamuna at Naini reached 87.98 m and 87.99 m on 8 September 1978, about 3.25 m above their danger levels (as reported). On 17 August 2026 only 73.4 mm fell at Prayagraj in 24 hours, yet George Town, Tagore Town and Rambagh were waterlogged, and the Allahabad High Court took suo motu cognizance and ordered the water pumped out within 24 hours (as reported): the failure was of drainage, not of rainfall. The Hindon entry follows July 2023, when the Hindon at Noida reached 197.28 m on 26 July, 1.81 m above its earlier highest level, Karhera in Ghaziabad was evacuated and about 350 cars in a yard on the floodplain at Ecotech-3 were submerged (as reported). The Hindon floodplain had still not been demarcated in May 2026, when I&WRD gave its 100-year flood levels as 205.39 m at km 49 and 205.20 m at km 110 of its reach (I&WRD progress report in NGT O.A. 569/2023). The catchments of the Varuna and the Assi at Varanasi, where the Ganga's highest level of 73.901 m (1978) is 2.64 m above its danger level of 71.262 m (as reported), and the drains of Kanpur to the Ganga are candidates for notification under Clause 4.5.4. The notification triggers in 4.5.4.1 have no direct precedent and are set by this Manual. The 6-month lead time follows the update rule of Clause 2.14.2. Clause 4.16 explains why releases below pre-development are needed at all.
4.5.5 Minimum outlet and short-duration 2-yr checks
4.5.5.1 Where the PSD for any AEP and duration is less than the discharge of a 50 mm orifice (Clause 4.8.2) at the corresponding stage, the 50 mm orifice is deemed to comply for that AEP and duration.
4.5.5.2 Where meeting the 2-yr criterion at a duration of 3 hours or less would require a low-flow orifice so small that the drawdown requirement of Clause 4.7 cannot be met, the designer shall:
- size the low-flow orifice as the smallest opening that meets Clause 4.7; and
- report the resulting 2-yr exceedance for those durations.
The Authority may accept the design if the exceedance is below the discharge of the 50 mm orifice at the 2-yr stage, or if the downstream analysis of Chapter 5 shows no adverse effect.
Commentary. Under AMC II, a greenfield site produces almost no runoff in a 1- or 2-hour, 2-yr storm, because most of the rain is lost to initial abstraction. A pre-development peak of a few litres per second, compared duration by duration, then forces a very small low-flow orifice. That orifice cannot release the 10-yr volume within 48 hours. Checked as if it were outside a flood-sensitive catchment, the illustrative example of Clause 4.6.7 would need a low-flow orifice of about 75 mm to match the 1-hour, 2-yr pre-development peak. 90% drawdown of the 10-yr volume would then take about 84 hours even with a clean orifice, against the 48-hour limit. The 170 mm orifice that meets drawdown with 50% blockage exceeds the 1-hour, 2-yr pre-development peak by about 11 L/s. Clause 4.5.5.2 resolves that conflict in favour of drawdown, because a basin that is still partly full when the next SW monsoon storm arrives fails in the event that matters more. KC APWA 5600 (2006) used a 75 mm (3 in) minimum orifice with trash racks. This Manual sets a 50 mm minimum (Clause 4.8.2).
4.5.6 Constrained redevelopment sites
4.5.6.1 Eligibility. The relief route of this clause is available only for redevelopment where all of the following hold:
- (a) the existing site is at least 60% impervious, as surveyed before demolition;
- (b) the site is 1 ha or less; and
- (c) the designer shows, in a Constraint Statement submitted with Form 4-1, that the greenfield criteria of Clauses 4.5.2 or 4.5.3 cannot be met on the site. The statement must show that every storage option of Clause 4.10 has been assessed: rooftop and podium storage, tanks under parking or landscape, permeable paving with sub-base storage, and landscape depressions. It must also give the storage each option can provide.
New development on undeveloped land is never eligible.
4.5.6.2 Minimum on-site performance. An eligible site shall provide all of the following on site:
- (a) the full retention volume (Clause 4.4) and the WQv treatment (Chapter 8), with no relief;
- (b) post-development peak discharge no more than 50% of the existing-condition peak for the 50%, 10% and 1% AEP storms, at each duration of Clause 2.5.2. The existing condition is modelled under Clause 3.3.4; and
- (c) no increase in the 1% AEP water level at any building or road downstream (Chapter 5).
4.5.6.3 Shortfall. The shortfall is the detention storage required to meet the greenfield criteria (Clause 4.6) minus the storage provided on site under 4.5.6.2. The applicant shall pay for the shortfall as a fee-in-lieu at the unit rate of Clause 4.13.3. The fee shall be:
- (a) paid into the ring-fenced account of the basin in which the site lies;
- (b) spent only on regional detention or on restoring tal or tank flood storage identified in the basin stormwater master plan (Chapter 11); and
- (c) recorded in the public ledger of Clause 4.13.4, which shall show the volume owed and the volume delivered in each basin.
Where no basin master plan has yet been approved, the fee shall be held for up to 5 years. If no plan is approved in that time, it shall be spent on restoring tank flood storage in the same basin, with I&WRD agreement.
4.5.6.4 Flood-sensitive catchments. In the catchments of Clause 4.5.3, the route is available under the same conditions. The Authority may, however, refuse it where the downstream analysis of Chapter 5 shows existing flooding of buildings in the 10% AEP event within the analysis extent.
Commentary. Greenfield is the target for all redevelopment, because a dense city only reduces its runoff as it rebuilds. On small, fully built plots in areas such as the old city of Lucknow, the old cores of Kanpur and Prayagraj, or the lanes behind the ghats of Varanasi, there is often no space for the full greenfield storage. A rule that cannot be met invites variances and non-compliance, which help no one downstream. This clause follows the approach of the UK Non-statutory Technical Standards for Sustainable Drainage (Defra, 2015, S2–S3). For previously developed sites, those standards require peak runoff "as close as reasonably practicable to the greenfield runoff rate" and never above the pre-redevelopment rate. The fixed 50% minimum reduction has no direct precedent; this Manual sets it to give reviewers a clear number in place of a "reasonably practicable" judgement. The fee-in-lieu turns the shortfall into regional storage in the same basin, so the basin still receives greenfield-equivalent control in total. Retention and water quality get no relief, because they are small volumes that almost every site can hold.
4.6 Detention sizing procedure
4.6.1 Method
Detention shall be sized by hydrograph routing through the stage–storage–discharge relationship of the facility, by level-pool (Modified Puls) or an equivalent numerical method (SWMM, HEC-HMS). Fixed-ratio and Rational-based storage formulae shall not be used. The simplified methods of Clause 4.14 (the Tier B tables and the fixed-coefficient route) are the only exceptions.
4.6.2 Steps
- Delineate the site and sub-areas. Map HSG and confirm by testing (Chapter 3).
- Extract design rainfall for 50%, 10% and 1% AEP and every duration in Clause 2.5.2, with the climate factor (Chapter 2, Form 2-1).
- Build design hyetographs: alternating block for ≤ 24 h; the "peak day last" pattern for 48 and 72 h (Clause 2.9).
- Compute pre-development hydrographs (greenfield CN; AMC III for storms of every duration in July–September in sub-areas UP-C and UP-D and on floodplain or embanked low-lying land, and in July–August in UP-B, and in UP-A and UP-E after a 5-day total of more than 53 mm, AMC II otherwise).
- Compute the release caps for each AEP and duration under Clause 4.5.2 or 4.5.3.
- Compute post-development hydrographs with the same storms and AMC, including retention practices (Clause 4.4.6).
- Choose a trial facility geometry (stage–storage) and a multi-stage outlet (Clause 4.6.5).
- Route every storm and duration. Use a time step of no more than 5 minutes, and no more than Tc/3 of the post-development catchment.
- Check every release against its cap, and check drawdown (Clause 4.7). Adjust the outlet and storage and repeat.
- Check the tailwater condition of Clause 4.6.6 and the downstream analysis of Chapter 5.
- Size the emergency spillway and set freeboard (Clause 4.9).
- Report the governing storm for storage, for each outlet stage, and for the spillway (Clause 4.17).
4.6.3 Storms to be routed
Every facility shall be routed for the full matrix:
Table 4.1 — Design storms to be routed for detention sizing
| AEP | Durations (h) | AMC |
|---|---|---|
| 50% (2-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
| 10% (10-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
| 1% (100-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
The 24-, 48- and 72-hour runs are mandatory whatever the critical-duration result (Clause 2.5.2). Where Ia = 0.05S sensitivity is required by Chapter 3, it shall be run for the governing storage case.
4.6.4 Initial conditions
Each run shall start with:
- detention storage empty, down to the invert of the lowest outlet;
- any permanent pool full;
- retention practices empty, except as limited by Clause 4.11; and
- RWH storage full (Clause 4.11).
The 48- and 72-hour storms already contain their antecedent rain, so no further pre-filling is applied.
4.6.5 Multi-stage outlet design
4.6.5.1 The outlet shall have a separate control for each criterion, normally stacked as in Figure 4.2:
- Stage 1, at the invert: the low-flow orifice. It releases the WQv over 24–48 h (Chapter 8) and controls the 2-yr release.
- Stage 2: an orifice or slot set at or near the maximum 2-yr level. It controls the 10-yr release.
- Stage 3: a weir, riser crest or larger orifice set at or near the maximum 10-yr level. It controls the 100-yr release.
- Emergency spillway: separate from the primary outlet (Clause 4.9).
Stages may be combined where routing shows that every cap is met.
4.6.5.2 Orifices shall be computed with a discharge coefficient of 0.60 unless a rated device is used. Weirs shall use a coefficient appropriate to their shape. Submerged-outlet and tailwater effects shall be included (Clause 4.6.6).
4.6.5.3 Vortex flow controls and other proprietary devices may be used where the supplier provides a certified head–discharge curve and the minimum clear opening is at least 50 mm.
4.6.6 Tailwater on the outlet
The outlet shall be routed against the tailwater of the receiving system, not free outfall, wherever the receiving water level can rise above the outlet invert. The tailwater shall be:
- for a receiving drain: its water level in the same storm, from the Chapter 5 analysis or, for Tier B, the drain obvert;
- for tidal or backwater-affected outfalls: the levels and joint cases of Clause 2.12 and Chapter 5, including the outfall-closed check (Clause 5.10).
Where tailwater governs, a flap gate shall be fitted to the outlet (Clause 5.11). The storage below the tailwater level shall not be counted as available unless the routing includes the gate closure.
4.6.7 Illustrative example
Illustrative — not design values. This example shows the procedure and the sizes it produces. The inputs are invented to be plausible for the Kukrail catchment in north Lucknow. They are not NIH-DHAARA values and must not be used for design.
Inputs:
- Site: 2.0 ha, flood-sensitive catchment (Clause 4.5.3).
- Land cover: pre-development all pervious, CN 70. Post-development as two sub-areas (Clause 3.9.2): 1.57 ha of directly connected impervious surface at CN 98, never converted for AMC, and 0.43 ha of pervious open space at CN 70, on the same soil as pre-development; the area-weighted CN at AMC II is 92. For storms of 12 h and longer the pervious CN only is converted to AMC III: CN_III = 23·CN / (10 + 0.13·CN) = 84.3 (Clause 3.8.4).
- Time of concentration (Tc): 45 min pre-development, 15 min post-development (used for both sub-areas). SCS triangular unit hydrograph; 5-minute time step.
- 24-h depths: 110, 200 and 350 mm for 2-, 10- and 100-yr (the same 10- and 100-yr values as Clause 2.11).
- Shorter durations: P(t) = P24·(t/24)^0.40, an assumed ratio set and not Annex 2B.
- Longer durations: 48-h and 72-h depths taken as 1.25 and 1.40 × P24, laid out per Clause 2.9.2.
- Storage: vertical-walled, 2,500 m² plan area.
- Outlet, sized so that drawdown is met with the low-flow orifice 50% blocked (Clause 4.8.3). Annex 4C shows the trial outlet that failed this check.
- Stage 1: 170 mm orifice at the invert.
- Stage 2: 460 mm orifice with its invert 0.53 m above the floor.
- Stage 3: none needed, because the 100-yr cap is met by Stages 1 and 2.
Results (discharges in L/s; storage in m³):
Table 4.2 — Illustrative example: peak discharges and storage used, by duration (Illustrative — not design values)
| Duration (h) | 2-yr pre | 2-yr post, detained | 10-yr pre | 10-yr post, detained | 100-yr post, uncontrolled | 100-yr post, detained | 100-yr storage used | 10-yr drawdown, 50% blocked (h) |
|---|---|---|---|---|---|---|---|---|
| 1 | 4 | 15 | 51 | 28 | 922 | 42 | 1,426 | 31.3 |
| 2 | 14 | 20 | 84 | 34 | 961 | 79 | 1,911 | 32.1 |
| 3 | 19 | 22 | 104 | 37 | 981 | 139 | 1,999 | 32.8 |
| 6 | 32 | 25 | 150 | 41 | 1,010 | 194 | 2,154 | 34.2 |
| 12 | 127 | 30 | 302 | 46 | 1,074 | 276 | 2,512 | 39.0 |
| 24 | 149 | 32 | 327 | 49 | 1,081 | 320 | 2,766 | 45.3 |
| 48 | 173 | 34 | 349 | 82 | 1,087 | 343 | 2,913 | 44.8 |
| 72 | 180 | 34 | 356 | 84 | 1,089 | 343 | 2,911 | 44.7 |
How to read it:
- 100-yr cap. The cap is the largest pre-development 10-yr peak, 356 L/s (72 h). Every 100-yr detained peak is at or below it; the largest is 343 L/s.
- 2-yr cap. The site is flood-sensitive, so the 2-yr cap is the largest pre-development 2-yr peak, 180 L/s (72 h; Clause 4.5.3.1). The largest 2-yr detained peak is 34 L/s. At 1, 2 and 3 hours the detained 2-yr peak is above the pre-development peak of the same duration (15 against 4 L/s, 20 against 14 L/s, and 22 against 19 L/s). That comparison is not required here. It would be for a site under Clause 4.5.2, and Clause 4.5.5.2 would then apply.
- Governing storage. Storage is governed by the 48- and 72-hour storms: 2,913 m³, which is 0.146 m³ per m² of site, at a maximum depth of 1.17 m. A design that checked only the critical-duration peak storm (1–3 h here) would have provided about 2,000 m³, roughly two-thirds of what is needed.
- Drawdown. With the low-flow orifice 50% blocked (Clause 4.8.3), 90% of the 10-yr storage drains in at most 45.3 h (the 24-hour storm), within the 48 hours of Clause 4.7. A 120 mm orifice would drain it in about 42 h when clean but 54 to 75 h when half blocked, so it fails. Annex 4C shows that trial and the routing step by step.
- Retention credit. With an illustrative retention depth of 40 mm, RRV = 552 m³, computed for each sub-area (Clause 3.9.4). Modelled as filling from the start of the storm with no infiltration during it, the retention reduces the 24-hour storage by 138 m³ and the 48- and 72-hour storage by 7 m³ or less. The credit under Clause 4.4.6 is therefore effectively zero for this site.
The order of magnitude, about 0.15 m³ per m² of site, is consistent with the indication in Clause 2.11.
Figure 4.1 — Pre-development 10-yr, post-development 100-yr uncontrolled and detained hydrographs for the 24-hour storm of the illustrative example (Clause 4.6.7). Illustrative — not design values. Original drawing for this Manual, adapted from the pre/post-development hydrograph concept in MARC/KC APWA Section 5600 and the Georgia Stormwater Management Manual (2016).
Commentary. Figure 4.1 shows what detention does and does not do. It cuts and delays the peak. It does not reduce the volume: the area under the detained curve equals the area under the uncontrolled curve, more than twice the pre-development 10-yr volume. The extra volume leaves the site over many hours after the storm. That prolonged release can coincide with the peak of the larger catchment downstream (Clause 4.16), and it must still drain when the outfall is tide-locked (Chapter 5).
4.7 Drawdown
4.7.1 Detention. At least 90% of the maximum volume stored in the 10% AEP (10-yr) storm of each duration shall be released within 48 hours of the time of maximum storage, by gravity, with the tailwater of Clause 4.6.6.
4.7.2 Water quality volume. The WQv shall be released over not less than 24 hours and not more than 48 hours (Chapter 8).
4.7.3 Retention. Retention storage shall be emptied within 72 hours by infiltration or reuse (Clause 4.4.5).
4.7.4 Tidal outfalls. Where gravity drawdown is prevented by tide for part of each cycle, the 48-hour limit applies with the tidal tailwater modelled. Where it cannot be met by gravity, pumped drawdown shall be provided under Clause 5.12.
Commentary. KC APWA 5600 (2006) required dry basins to release at least 80% of storage within 24 hours of the inflow peak and to empty within 72 hours. Singapore PUB requires detention to be restored within 4 hours. The 48-hour, 90% rule is longer than PUB's because Uttar Pradesh storage must hold multi-day volumes. It is still short enough that a basin filled by one SW monsoon depression will have most of its volume back before the next, which in mid-September 2022 in Gorakhpur district (20 cm at Gorakhpur in the 24 hours to 08:30 on 15 September and 22 cm at Chanderdeepghat two days later, IMD) followed within days.
4.8 Outlet structures
4.8.1 General. Primary outlets shall be:
- unattended, with no moving parts, valves or pumps, except where Clause 5.12 permits pumped drawdown;
- accessible for inspection and cleaning from the surface without confined-space entry, where practicable; and
- built of durable materials. In coastal areas these shall be corrosion-resistant (Clause 4.12.5).
4.8.2 Minimum orifice. No control orifice shall be smaller than 50 mm in diameter, or 50 mm in least dimension for a slot.
4.8.3 Trash racks and screens. Every orifice and weir shall be protected by a trash rack or screen. The rack shall:
- have a clear bar spacing no greater than half the smallest opening it protects, and not less than 25 mm;
- have a clear open area at least 10 times the area of the opening it protects;
- be inclined, or set as a cage around the riser, so that debris rises with the water and does not pin against the bars;
- be removable or hinged for cleaning; and
- for routing, be assumed 50% blocked at the low-flow orifice when checking drawdown.
4.8.4 Anti-vortex devices. Riser crests and orifices that may run under more than 1.5 times their diameter of head shall have an anti-vortex plate or hood (Figure 4.2).
4.8.5 Outlet barrels. Outlet barrels through embankments shall:
- be at least 300 mm in diameter (Chapter 6);
- have watertight joints;
- have a filter diaphragm or seepage collars over the length within the embankment; and
- have an energy-dissipating outfall (Chapter 9).
4.8.6 Isolation. Facilities serving more than 1 ha shall have a means of isolating the outlet for maintenance, such as a stop-log slot or penstock. In normal service it shall be left fully open.
Commentary. The 50 mm minimum is smaller than the 75 mm (3 in) of KC APWA 5600 (2006), so the trash-rack requirements are correspondingly stricter. The ratios in 4.8.3 (bar spacing at half the opening, open area 10 times the opening, 50% blockage for the drawdown check) have no direct precedent and are set by this Manual. The blockage factor matches the 50% grate clogging factor for sag inlets in Chapter 6. Indian urban drains carry heavy loads of solid waste, so a low-flow orifice without an effective rack will block within one season.
Figure 4.2 — Detention storage stack (permanent pool, WQv, 2-yr, 10-yr and 100-yr zones, spillway surcharge and freeboard) and multi-stage riser outlet. Schematic, not to scale. Original drawing for this Manual, adapted from the multi-stage outlet and storage-zone concepts in MARC/KC APWA Section 5600 (2006, 2025.01) and the Mile High Flood District Urban Storm Drainage Criteria Manual, Volume 2 (full-spectrum detention).
4.9 Emergency spillway, freeboard and embankment safety
4.9.1 Spillway capacity. Every detention facility formed wholly or partly by an embankment, or whose overflow would reach buildings, shall have an emergency spillway that passes the 1% AEP (100-yr) peak inflow:
- with the primary outlet assumed fully blocked;
- with the facility full to the spillway crest at the start of the storm; and
- with at least 0.3 m freeboard from the maximum water level to the embankment crest.
4.9.2 High-hazard facilities. A facility is high-hazard if its failure or overflow could:
- endanger life;
- flood a habitable building or critical facility; or
- close an arterial road.
High-hazard facilities shall also be checked for the 0.2% AEP (500-yr) peak inflow under the conditions of 4.9.1, with the embankment not overtopped.
4.9.3 Spillway crest. The spillway crest shall be at or above the 1% AEP maximum water level from routing with the primary outlet working. The recommended clearance is 0.15 m.
4.9.4 Spillway location. The spillway shall be:
- on natural ground or a reinforced section, not on fill, unless protected against erosion for the full design flow;
- discharging to the 1% AEP overland flow path of Chapter 6; and
- placed so that its flow does not reach a building.
4.9.5 Underground and enclosed facilities. Tanks, vaults and podium storage shall have an overflow route that operates when the outlet is blocked. The route shall carry the 1% AEP inflow to the overland path without surcharging any building, basement or lift pit.
4.9.6 Embankments.
- (a) Embankments more than 2 m high (measured from the downstream toe to the crest) shall be designed by a qualified geotechnical engineer. The design shall include stability, seepage and settlement analysis.
- (b) Side slopes shall be no steeper than 3H:1V on any face that is mown or accessible to the public. Slopes shall be flatter where Clause 4.15 requires.
- (c) Embankments shall have:
- a crest width of at least 3 m;
- compacted, engineered fill with a core or cut-off where required by the seepage analysis; and
- no trees or large shrubs.
- (d) An embankment structure that falls within the Dam Safety Act, 2021 is subject to that Act in addition to this Manual.
4.9.7 Excavated facilities. Facilities wholly below the surrounding ground, with no embankment, need not meet 4.9.6. They shall still meet 4.9.1, with the overflow route treated as the spillway.
Commentary. The spillway criterion (1% inflow, outlet blocked, basin full, 0.3 m freeboard; 0.2% for high hazard) follows the KC APWA 5600 (2006) rule: the spillway passes the 1% storm with 1 ft (0.3 m) freeboard to the top of the dam, assuming zero storage and a clogged primary outlet, with the crest at least 0.5 ft (0.15 m) above the 1% maximum water surface. KC designed dams above 10 ft (3 m) to SCS TR-60 Class C. The 2 m embankment trigger, the 3H:1V slope (KC wet ponds), and the 3 m crest width have no direct precedent and are set by this Manual.
4.10 Facility types
4.10.1 General. Any storage that meets Clauses 4.5 to 4.9 may be used. Surface storage that is visible and can be inspected without confined-space entry is preferred. Storage shall not be placed in a habitable basement or in any space whose flooding would endanger life.
4.10.2 Underground tanks and vaults.
- (a) Gravity outlet is required where the receiving drain allows it. Pumped outlets are permitted only under Clause 5.12, with a registered maintenance declaration (Chapter 10).
- (b) Access openings shall be provided over the outlet chamber and over every inlet. In tanks over 500 m², they shall be no more than 30 m apart.
- (c) The floor shall fall at least 1% to a sump at the outlet, with a sediment pocket below the low-flow orifice invert.
- (d) The tank shall be ventilated.
- (e) Inlets shall pass through a silt trap or gross pollutant trap (Chapter 8).
- (f) Flotation and groundwater ingress shall be checked under Clause 4.12.
4.10.3 Rooftop detention.
- (a) It is permitted on flat roofs designed for the full ponded load with the outlet blocked. The ponding depth shall not exceed 150 mm unless a structural engineer certifies a greater depth.
- (b) Each roof outlet shall have a flow-control ring or weir with a certified rating, and every roof area shall have at least one overflow scupper, independent of the controlled outlets, that passes the 1% AEP inflow.
- (c) Roofs used for RWH collection may also provide rooftop detention. The detained volume is released through the control, not into the RWH sump.
4.10.4 Podium and landscape-deck detention.
- (a) It is permitted above ground level or above a basement car park, provided the structure is designed for full saturation and ponding, and waterproofed.
- (b) The release, overflow and safety rules for rooftop detention (4.10.3) apply.
4.10.5 Parking-lot detention.
- (a) It is permitted only on surface parking. Ponding depth shall not exceed:
- 200 mm in the 10% AEP storm and 300 mm in the 1% AEP storm at any parking bay;
- zero on accessible routes, ramps and pedestrian crossings; and
- zero in the 10% AEP storm on fire-tender access routes.
- (b) Signs shall warn that the area floods.
- (c) Ponding shall not reach a building wall unless the wall is waterproofed above the 1% level plus freeboard (Chapter 6).
4.10.6 Multi-use detention (parks, playfields, open space reservation).
- (a) Open space land may be used for detention, provided its primary use remains available in at least the 50% AEP storm.
- (b) The storage areas shall be graded to drain fully within the times of Clause 4.7.
- (c) A low-flow channel or underdrain shall carry dry-weather and frequent flows, so that the park is not waterlogged.
- (d) The depth and slope limits of Clause 4.15 apply.
- (e) Play equipment and seating shall be placed above the 10% AEP level.
4.10.7 Ponds and wet basins.
- (a) A permanent pool shall be at least 1.2 m deep over most of its area to discourage weed growth and mosquito breeding, with a vegetated safety bench at the edge (Clause 4.15).
- (b) Only storage above the permanent pool counts as detention.
Commentary.
- The rooftop depth (150 mm) and parking depths (200 and 300 mm) have no direct precedent. This Manual sets them so that a blocked outlet is noticed before it becomes dangerous.
- The 1.2 m pool depth equals the 4 ft minimum permanent pool of KC APWA 5600 (2006). This Manual adopts it mainly for weed and mosquito control.
- Pumped detention tanks need maintenance declarations in Singapore (PUB Addendum No. 3, April 2025). This Manual adopts the same approach through Chapter 10.
- Using open space for multi-use detention fits the Byelaws 2025. All public open spaces and recreational areas "shall make provisions for rainwater harvesting"; concrete construction in parks is limited to 5% of their area, with permeable or semi-permeable blocks (clause 13.1.2); where parking is built under up to 70% of a park or open area, the remaining 30% "shall allow seepage of rainwater for ground water recharge" (clause 3.1.2.3); road margins are kept "as unpaved as possible" (clause 3.1.3.6); and the recharge reservoir of a layout of more than 4 ha, with its recharge pit or shaft in one corner of the park, already puts storage in open space (clause 13.1.2). A detention area graded into the open space below the level of the road keeps it pervious and usable, which is what 4.10.6 requires. Two kinds of land are not open space for this purpose. A tal, pond or other water body on the land is preserved under step 1 of Clause 4.3.1 and modelled as a water surface (Clause 3.3.2(e)) that starts at its full level (Clause 3.12.5), so only its flood storage above that level can count, and only as Chapter 7 allows; a pond recorded in the revenue records may not be built on at all (UP Revenue Code 2006, sections 61 and 77(1)(i); Byelaws clause 16.3.2(xi)). And the strip within 200 m of the bank of the Ganga in which the Byelaws allow only repair and renovation (clause 2.11), the floodplain zones of the Ganga and the Yamuna notified on the 1-in-100-year flood, the 50 m zone of influence of a notified wetland such as Ramgarh Tal, and land in the hydraulic corridor of a nala, tal or river under Chapter 7 are corridor or flood land already: water reaches them first, so they are not counted as detention for the development beside them (Chapter 7).
4.11 Rainwater harvesting versus detention accounting
4.11.1 No double counting. RWH storage (sumps, tanks, recharge pits and wells provided under the RWH mandate) shall not be counted as detention.
4.11.2 RWH sumps assumed full. For all routing under this chapter, RWH sumps and tanks shall be assumed full at the start of every storm, in every season. Their overflow shall be routed to the detention facility, or directly to the outfall if it bypasses detention. In the latter case the bypass flow counts against the PSD.
4.11.3 Combined tanks. A single tank may provide both RWH and detention only if:
- (a) the detention zone lies wholly above the RWH overflow level;
- (b) the detention zone is drained by its own gravity control orifice set at the RWH overflow level, meeting Clauses 4.7 and 4.8;
- (c) no pump, valve or user action can hold water in the detention zone; and
- (d) the two zones and the orifice level are shown on the drawings and in the maintenance declaration.
Only the volume between the RWH overflow level and the detention overflow level counts as detention.
4.11.4 Recharge structures. Recharge pits, trenches, shafts and wells may count as retention (not detention) if they meet Clauses 4.4.3 to 4.4.5. In particular, the seasonal high groundwater table shall be at least 1.0 m below their base. In the routing they are treated under Clause 4.4.6 with the groundwater level for the SW monsoon season.
4.11.5 RWH remains mandatory. Nothing in this chapter reduces the RWH requirement of clause 13.1.2 of the Byelaws 2025, section 31(2) of the UP Ground Water (Management and Regulation) Act 2019 and any notification made under it, the building regulations of Noida, GNIDA or YEIDA, or any rainwater harvesting rule of an approving authority.
Commentary. RWH in Uttar Pradesh is required by the Byelaws 2025 and by the UP Ground Water (Management and Regulation) Act 2019, and neither sets a volume. Clause 13.1.2 of the Byelaws requires, where there is no collective recharge network, a rooftop rainwater harvesting system "in plots of all uses of 300 square meters and more area (including group housing) except waterlogged areas"; on plots of 100–300 m² in new schemes an individual system is not required if the roof water flows into the scheme's collective recharge network. Layouts of more than 4 ha must build recharge reservoirs on at least 1% of the scheme area, with a maximum depth of 2 m, into which "only the 'surface-run-off' of that scheme" is led, with a recharge pit or shaft in one corner of the park; and projects that need environmental clearance must provide at least one recharge bore per 5,000 m² of built-up area, limit recharge "to shallow aquifer" and keep at least 20% of the open space pervious. "Ground water recharging system should not be adopted in areas with water logging problem", where roof water may be collected for use instead. Section 31(2) of the Act requires the Municipal Water Management Committee to impose the rooftop rainwater harvesting conditions that the State notifies, makes them "binding on concerned Government agencies sanctioning or approving building plans", and makes a "Combined Recharge System for group housing/colonies" mandatory under the bye-laws; no notification under it was found [TBC]. Section 39(4) penalises an owner who fails to install the system as sanctioned. Two more sections bear on design. Section 28 forbids rain falling on "open land, ground, roads (paved/unpaved), agricultural farms" from being recharged directly into the aquifer "through recharge well, bore well, recharge shaft, injection well etc."; rooftop water is excepted. Section 33 requires the authorities to "discourage and prevent such activities that are likely to lead to potential water logging". The Chief Minister was reported in October 2025 to have directed that RWH be made mandatory in buildings of more than 100 m² (as reported); no Government Order giving effect to it was found [TBC], and the 300 m² of the Byelaws is the rule this Manual cites. Nothing in any of these rules requires a tank to be empty before a storm. This Manual credits these structures against its own retention requirement (Clause 4.4) as follows:
- An RWH storage tank or sump is RWH storage. It is not detention (Clause 4.11.1), and it is assumed full at the start of every storm (Clause 4.11.2), because after the July rains it is full. A tank may also provide detention only if it is built as a combined tank under Clause 4.11.3, with a detention zone above its RWH overflow level that drains through its own orifice; only that zone counts.
- An RWH tank counts toward the retention requirement of Clause 4.4 only to the extent that it is emptied within 72 hours by a continuous non-potable use, such as toilet flushing, demonstrated under Clause 4.4.3; it is then modelled under Clause 4.4.6 like any other retention practice. In the khadar, the north-east terai and the waterlogged canal commands, where the Byelaws themselves rule out recharge, reuse is the practical way to earn retention.
- The recharge pits, trenches, shafts and bores of the Byelaws and of section 31(2) count as retention only where they meet Clause 4.11.4: they are credited only to the extent that they drain within 72 hours at half the rate measured in a site test (Clauses 4.4.3 and 4.4.5), with their base at least 1.0 m above the seasonal high water table, and the credit is found by routing under Clause 4.4.6, not by deducting their volume. Over the deep water table of Lucknow, where the depth to water before the monsoon of 2023 was 7.65–45.6 m below ground and the city is classed over-exploited (CGWB, in NGT O.A. 594/2024), and of the NCR cities and Agra, the separation is easily met, and recharge through the bangar, with pre-treatment, is the best retention these cities have. Under section 28 only roof water may go to a recharge well, bore or shaft. Runoff from roads, paving and open land is retained in surface systems, such as basins, swales and permeable pavement that infiltrate through their own floors, and never passes directly to a recharge well or shaft (Chapter 8). In the khadar, the terai, the waterlogged canal commands and on usar land, a recharge structure gets no retention credit; the Byelaws do not require one in waterlogged areas, and section 33 is the basis on which the Authority may refuse one there.
- The layout recharge reservoir of clause 13.1.2 is a shallow basin fed by surface runoff. It counts as retention only for the volume that infiltrates within 72 hours, routed under Clause 4.4.6, and as detention only for a zone above that volume that drains through an outlet meeting Clauses 4.7 and 4.8.
- The pervious open space of the environmental conditions is pervious area. It enters the post-development run as pervious land under Clause 3.9.2, or as permeable pavement under Clause 4.4.1 where it is built with an infiltration base, and gets no further credit as retention or detention.
In the khadar and the terai, a recharge pit drains slowly or not at all in the SW monsoon. Treating RWH as detention would therefore credit storage that does not exist when it is needed. That is why this Manual assumes RWH sumps are full at the start of every storm. Applying the assumption to every season keeps one simple rule. The combined-tank provision (4.11.3) lets an owner build one structure, as long as the detention part is empty when the storm arrives.
4.12 High-groundwater and sandy coastal sites
4.12.1 Design groundwater level. Each site in the khadar floodplains of the Ganga, the Yamuna and their tributaries, the north-east terai, the waterlogged canal commands such as that of the Sharda Sahayak, and the low-lying land behind the embankments of the Gomti at Lucknow and the Rapti at Gorakhpur, or any area where the groundwater table lies within 3 m of the surface at any time of year shall establish a design groundwater level (DGWL) for the facility. The DGWL is the seasonal high level during or after the SW monsoon, from:
- (a) site piezometer readings over at least one full June–November season; or
- (b) where (a) is not available, the higher of the CGWB or UP Ground Water Department record for the nearest observation well, plus 0.5 m, and the design flood level of any adjacent river, nala or tal.
For the flotation check of 4.12.3 at sites in the khadar floodplains and the north-east terai, where (a) is not available, the DGWL shall be taken as existing ground level.
4.12.2 Lined storage. Where the DGWL is less than 1.0 m below the base of a storage facility:
- (a) the facility shall be watertight (lined or of watertight concrete), and no infiltration credit applies (Clause 4.4.4); or
- (b) if unlined, the volume below the DGWL shall not be counted as detention, and groundwater inflow shall be added to the routed inflow.
4.12.3 Uplift and flotation. Every below-ground tank, vault, lined pond or chamber shall be checked for flotation:
- with the facility empty;
- with groundwater at the DGWL; and
- for coastal sites, with groundwater also at the major-system tailwater level of Chapter 5, where that is higher.
The factor of safety against uplift, counting only permanent dead loads and ignoring wall friction unless supported by geotechnical design, shall be at least 1.2. Anchoring by ballast, toe extensions or tension piles may be used.
4.12.4 Shallow and above-ground storage preferred. On sites where the DGWL is within 1.5 m of ground, storage should be provided above ground where possible: rooftop, podium, landscape or surface storage. Deep tanks should be avoided.
4.12.5 Durability. Concrete and metal parts in contact with saline or brackish groundwater or tidal water shall be designed for the exposure class appropriate to coastal conditions under IS 456:2000. Outlet fittings, trash racks and gates shall be of stainless steel, HDPE, FRP or another corrosion-resistant material.
4.12.6 Sandy soils with deep groundwater. Where the DGWL is 1.0 m or more below the base, infiltration retention in sandy soils is encouraged. The design infiltration rate of Clause 4.4.3 applies, and the Chapter 8 requirements on pollution of shallow aquifers shall be met.
Commentary. Uttar Pradesh is landlocked, so the coastal provisions of this clause, the tidal water levels of 4.12.1 and 4.12.3, do not apply in the State. The exposure provisions of 4.12.5 apply only where groundwater at a site is shown to be saline or brackish; groundwater quality, including salinity, fluoride, nitrate and the arsenic of the east of the State, was not researched for this Manual [TBC]. The State's groundwater runs to both extremes. In Lucknow the depth to water before the monsoon of 2023 was 7.65–45.6 m below ground, after a fall of 1.4–13.1 m since 2014, and the city was classed over-exploited in the assessments of 2017, 2020, 2022 and 2023 (CGWB, in NGT O.A. 594/2024); in the 2024 assessment 59 of the State's 836 assessment units were over-exploited, 46 critical and 165 semi-critical (CGWB, from a search summary [TBC]); and in the NCR the depth before the monsoon was 3.35–14.40 m below ground in Gautam Buddh Nagar in May 2007 and about 22.8 m in Ghaziabad in 2006 (a CGWB district profile and other reports, from search summaries; current values were not obtained [TBC]). There, infiltration is the best retention and should be used, with pre-treatment, subject to the 1.0 m separation of Clause 4.4.3, to section 28 of the UP Ground Water (Management and Regulation) Act 2019, which allows only roof water to go directly to a recharge well, bore or shaft, and to Chapter 8. The khadar, the north-east terai and the waterlogged canal commands are the opposite case. There the water table is within a metre or two of the surface in the monsoon, and in the terai wells flow under artesian pressure (CGWB state profile, from a search summary [TBC]), so an unlined tank fills with groundwater before the storm, and an empty lined tank can float, especially when a river in flood raises the water table of the floodplain beside it. The design groundwater level of 4.12.1(b) therefore takes the design flood level of the adjacent river, nala or tal where that is higher than the well record. The June–November monitoring season of 4.12.1(a) is set by this Manual to cover the SW monsoon and the post-monsoon high that the CGWB measures in November. The factor of 1.2, the 0.5 m allowance and the "ground level" default for the khadar floodplains and the north-east terai have no direct precedent; this Manual sets them because no published site-scale seasonal groundwater depths for Uttar Pradesh were found during research.
4.13 Regional detention and fee-in-lieu
4.13.1 Where permitted. In a basin covered by a Basin Stormwater Master Plan approved under Chapter 11, a development may meet all or part of its detention requirement through:
- (a) a regional detention facility identified in the plan; or
- (b) a fee-in-lieu paid toward restoration of tal or tank storage identified in the plan.
4.13.2 Conditions. Regional detention or fee-in-lieu shall be accepted only where:
- (a) the regional facility or restored tank is operational, or is funded and scheduled to be operational within 3 years. Until then, interim on-site detention is required.
- (b) the conveyance from the site to the facility carries the 1% AEP post-development flow without increasing water levels at buildings or roads between them (Chapter 5);
- (c) the storage credited at a tank is the flood storage only. This is the volume between full tank level (FTL) and the maximum water level the bund and surplus weir can safely hold, plus any volume below FTL that a notified operating rule commits to empty before the SW monsoon. Storage below FTL that is held for irrigation or supply through June to September shall not be credited.
- (d) the tank meets Chapter 7: surveyed FTL, a documented operating rule, and a maintained surplus weir;
- (e) the site still provides retention (Clause 4.4) and WQv treatment (Chapter 8) on site; and
- (f) in flood-sensitive catchments, the regional facility meets the mixed-frequency rule for its whole contributing area.
4.13.3 Fee. The fee-in-lieu shall be computed as:
Fee = (detention volume required on site under Clause 4.6, m³) × (unit rate, ₹/m³, notified by the Authority)
The unit rate shall include land, construction and 10 years of maintenance. Fees shall be held in a ring-fenced basin account and spent only on the facilities named in the plan.
4.13.4 Ledger. The Authority shall keep a public ledger of:
- detention volume credited to each regional facility;
- volume delivered; and
- fees received and spent.
Commentary. The Malaysian DID (2008) checklist favoured community ponds over on-site detention for sites above 0.1 ha. Studies of on-site detention show that its benefit depends on location and fades with distance downstream (Colorado State University thesis; McEnroe for Kansas City), and that a pond low in the catchment can synchronise with the main-stem peak (Water 2016). Regional storage therefore has to be sited by basin modelling, not simply aggregated.
Uttar Pradesh has no tank Act, and no tal in its cities was found to be operated as part of a cascade with a documented rule [TBC]; the old tanks and bandhs of Bundelkhand were not researched for this Manual [TBC]. Its regional storage is of three kinds: the tals, ponds and lakes, the river floodplains, and the drains and embankments of I&WRD. The tals are protected by revenue law and the courts rather than by a drainage rule. The UP Revenue Code 2006 vests the beds of "rivers, streams, nallas, lakes, ponds and tanks" in the State (section 54), reserves a village tank of 0.5 acre or less "for public use by the inhabitants of the village", the term "tank" including "talab, pond, pokhar and other land covered with water" (section 61), and allows no bhumidhari rights in land "covered by a pond, tank or lake" (section 77(1)(i)). The Supreme Court held that where "a pond exists and the area covered by it varies in rainy season … no part of it could have been allotted", and directed the State to restore the pond (Hinch Lal Tiwari v. Kamala Devi, 2001). The Wetlands (Conservation and Management) Rules 2017 bar permanent construction within 50 m of the mean high flood level of a notified wetland, and Ramgarh Tal at Gorakhpur, 742.245 ha, was notified on 7 December 2020 with a 50 m zone of influence and its six inflow nalas. The UDD guideline of December 2024 asks the city drainage master plans to integrate existing detention ponds and lakes, to rejuvenate the storage ponds inside the city, and to set their pre- and post-monsoon levels. Three points follow:
- A pond on the record may not be a working tal. About 16,630 Amrit Sarovars, which are village ponds, were reported complete by March 2025 (as reported), but no inventory of the ponds and tals within the Nagar Nigams was found [TBC]. A tal is credited only after a survey shows its bed, bund and outlet, and only for the storage above its full level.
- The river floodplain is not spare capacity for a site. It is the river's own flood land, now notified by coordinates on the 1-in-100-year flood for the Ganga from Unnao to Ballia (G.O. of I&WRD of 29 January 2025) and reported to be notified for the Yamuna in 17 districts (January 2025; as reported). Storage on it is a matter for the basin master plan of Chapter 11, not for a site.
- A drain or embankment of I&WRD is not regional storage. Storm water spilled to a river through its embankment, or to a drain of a canal command, uses capacity that the river or drain needs for its whole basin, and the outfall can be shut by its gate when the river is high; it can be relied on only with the written agreement of I&WRD, for a stated flow and level. No rule dividing the natural drains of I&WRD from the nalas of the Nagar Nigams was found [TBC]; until one is made, this Manual treats rivers, floodplains, embankments, canals and canal-command drains as I&WRD's, and the nalas and road drains within the limits of an urban local body as that body's.
The first point is the basis of condition 4.13.2(c) in Uttar Pradesh. A tal gives flood storage only above its full level, unless a notified operating rule commits it to be lowered before the SW monsoon. The 3-year operational limit and the 10-year maintenance allowance have no direct precedent and are set by this Manual.
4.14 Simplified methods for small sites
4.14.1 Applicability. Tier B local bodies may permit the simplified method for sites of 2 ha or less outside flood-sensitive catchments. In flood-sensitive catchments, it may be used for sites of 0.5 ha or less. All other sites shall use Clause 4.6. Until Table 4.3 (Annex 4B) is published, all Tier B sites shall also use Clause 4.6.
4.14.2 Method.
- Read the PSD (L/s/ha) and SSR (m³/ha) for the site's zone, HSG and post-development imperviousness from Table 4.3 (Annex 4B).
- Required storage: V = SSR × A − V_credit (Clause 4.4.6.3).
- Permissible discharges: Q_PSD,T = PSD_T × A for the 2-yr and 100-yr stages.
- Select the low-flow orifice and upper control from the standard outlet table in Annex 4B (orifice sizes for the PSD at the stated depths), subject to the 50 mm minimum.
- Provide a spillway or overflow under Clause 4.9, the RWH accounting of Clause 4.11, and the safety provisions of Clause 4.15.
- Complete Form 4-2 (Tier B site sheet).
Table 4.3 — Tier B permissible site discharge and site storage requirement (template)
| Zone (Annex 2A) | HSG | Imperviousness | PSD 2-yr (L/s/ha) | PSD 100-yr (L/s/ha), standard | PSD 100-yr (L/s/ha), flood-sensitive | SSR (m³/ha), standard | SSR (m³/ha), flood-sensitive |
|---|---|---|---|---|---|---|---|
| UP-Z1 West: UP-A West doab and NCR | A / B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| UP-Z2 Central–east plain and Bundelkhand: UP-B Central–east Ganga plain | A / B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| UP-Z2 Central–east plain and Bundelkhand: UP-E Bundelkhand and Vindhyan | C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| UP-Z3 Terai and Rohilkhand: UP-C North-east terai | C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| UP-Z3 Terai and Rohilkhand: UP-D Rohilkhand and western terai | A / B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
Worked example (illustrative — not design values).
A 0.4 ha residential layout in a Tier B Municipality, in a flood-sensitive catchment, with about 80% directly connected impervious area (area-weighted post-development CN about 92). Suppose Table 4.3 had been computed and gave the per-hectare equivalent of the Clause 4.6.7 example:
- PSD 100-yr = 356 / 2.0 = 178 L/s/ha
- SSR = 2,913 / 2.0 ≈ 1,460 m³/ha
- PSD 2-yr ≈ 17 L/s/ha
Then:
- Storage: V = 1,460 × 0.4 = 584 m³. C_R = 0, so there is no retention credit.
- 100-yr release: 178 × 0.4 = 71 L/s.
- 2-yr release: 17 × 0.4 = 7 L/s. At about 1 m head this needs a low-flow orifice of about 60 mm, above the 50 mm minimum (Clause 4.8.2).
- Layout options:
- a 400 m² underground tank 1.5 m deep; or
- 250 m² of podium storage at 0.3 m (75 m³) plus a 350 m² tank 1.5 m deep (525 m³).
- Rooftop storage at 150 mm over 1,200 m² of roof (180 m³) could replace part of the tank.
- RWH sumps are additional, and are assumed full (Clause 4.11).
Commentary. Australian councils use permissible site discharge and site storage requirement tables in the same way (Sydney Water OSD guide; the Upper Parramatta River Catchment Trust handbook listed SSR of about 455 m³/ha). The illustrative SSR here, about 1,460 m³/ha, is much larger. That is the expected effect of combining a mixed-frequency cap with mandatory 48–72-hour storms at AMC III. MSMA 2 in Malaysia offers a similar simplified OSD method for sites under 5 ha. The MARC policy supplement offers smaller Kansas City municipalities adoptable alternatives within the regional standard; Clause 4.14 follows that model for Tier B.
4.14.3 Fixed-coefficient route. As an alternative to Clauses 4.6 and 4.14.2, the designer of any site of 1 ha or less, under any Approving Authority and in any catchment, may size detention by Clauses 4.14.4 to 4.14.7. The route shall not be used where:
- (a) the site counts tank or waterbody storage in its design (Chapter 7);
- (b) any part of the site lies within a waterbody setback (Chapter 7); or
- (c) the site drains to a tank cascade whose storage is counted in a downstream design.
The route sets the release caps by fixed coefficients and does not need Table 4.3. It may therefore be used before Annex 4B is published. Retention (Clause 4.4), drawdown (Clause 4.7), outlets (Clause 4.8), the spillway (Clause 4.9), the downstream and tailwater checks (Chapter 5) and water quality (Chapter 8) still apply.
4.14.4 Release caps. Two caps apply at each point where runoff leaves the site:
Q_cap,10 = 2.78 × C_10 × i_10 × A and Q_cap,2 = 2.78 × C_2 × i_2 × A
where Q_cap is in L/s; A is the site area (ha); i_10 and i_2 are the 10% AEP (10-yr) and 50% AEP (2-yr) rainfall intensities (mm/h) for a 15-minute duration at the site, from the sources of Chapter 2, with the climate factor of Clause 2.8; and C_10 and C_2 are the fixed coefficients of Table 4.3A for the site's hydrologic soil group (Clause 3.7). For a site with more than one soil group, the coefficients are area-weighted.
Table 4.3A — Fixed release coefficients (provisional)
| Hydrologic soil group | C_10 | C_2 |
|---|---|---|
| A (sandy, well drained) | 0.05 | 0.02 |
| B | 0.08 | 0.03 |
| C | 0.15 | 0.08 |
| D (clay, poorly drained) | 0.25 | 0.15 |
Q_cap,10 is the maximum release for every storm up to and including the 1% AEP (100-yr) storm, in every catchment. Q_cap,2 is the maximum release for the 50% AEP (2-yr) storm. Where a cap is smaller than the discharge of a 50 mm orifice at the corresponding stage, the 50 mm orifice is deemed to comply (Clause 4.5.5.1).
4.14.5 Storage. The detention storage V (m³) is the larger of V_100 and V_2, each the largest over the durations d of Clause 2.5.2 (1 to 72 hours):
V_100 = max over d of [ 10 × C_v × P_100(d) × A − 1.8 × Q_cap,10 × d ]
V_2 = max over d of [ 10 × C_v × P_2(d) × A − 1.8 × Q_cap,2 × d ]
where P_100(d) and P_2(d) are the 1% and 50% AEP rainfall depths (mm) for duration d (hours), with the climate factor; and C_v is the post-development volumetric coefficient: the composite C of Table 3.2 (upper half of each range), multiplied by Cf of Table 3.3 for the 1% AEP. For durations of 12 hours or more, C for every pervious surface shall be taken as not less than 0.50. The factor 1.8 assumes an average release of half the cap over the storm (3.6 × 0.5).
4.14.6 Outlet. The outlet shall be a two-stage control: a low-flow orifice that passes Q_cap,2 when the storage holding V_2 is full, and an upper orifice or weir that limits the total release to Q_cap,10 at the top of V. The outlet table of Annex 4B may be used once it is published.
4.14.7 Retention. The retention volume of Clause 4.4 is provided in addition to V. No retention credit (Clause 4.4.6) is taken under this route.
Figure 4.3 — Fixed-coefficient route for sites of 1 ha or less (Clauses 4.14.3 to 4.14.7): the release caps Q_cap,10 and Q_cap,2 from Table 4.3A; the storage V as the largest gap, over the durations of Clause 2.5.2, between the cumulative inflow 10·C_v·P(d)·A and the release line 1.8·Q_cap·d, for the 1% and 50% AEP storms; and the two-stage outlet that passes Q_cap,2 at the top of V_2 and Q_cap,10 at the top of V. Schematic, not to scale. Original drawing for this Manual, adapted from the rainfall mass-curve (inflow minus outflow) storage concept and the single-coefficient peak cap of the PUB Code of Practice on Surface Water Drainage, 7th ed. (cl. 7.1.5).
Commentary. The fixed-coefficient route follows Singapore, which caps the peak runoff from every development of 0.2 ha or more with one runoff coefficient, C = 0.55, applied to the 10-yr storm (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5, Addendum No. 3, 2025). It is quick to apply and quick to check: the cap needs only the site area, the soil group and two intensities. PUB's 0.55 is not used here, because Singapore's baseline is the existing urban drainage system, while this Manual's baseline is greenfield land (Clause 4.5.1.2). The coefficients of Table 4.3A are set by this Manual from the greenfield curve numbers of Clause 3.3 (CN 39, 61, 74 and 80 for soil groups A to D). They are the ratios of runoff to rainfall that those curve numbers give for 1-hour depths typical of the Ganga plain, rounded down. They are therefore provisional. The State Stormwater Technical Committee shall confirm or revise them against NIH-DHAARA values for each zone when it issues Annex 4B.
The route is deliberately stricter than the full method, so that simplicity costs the developer storage rather than costing the people downstream. The 100-yr release is held to about the greenfield 10-yr peak everywhere, which is the flood-sensitive rule of Clause 4.5.3; the storage assumes the outlet releases only half the cap on average; pervious ground is assumed wet in long storms; and no retention credit is taken. A designer who wants a smaller tank can use the full method of Clause 4.6. The storage formula is the rainfall-mass (inflow minus outflow) method. Clause 3.4.2 otherwise forbids rainfall-based peak methods for storage, because they ignore the shape of the hydrograph; this route is a stated exception because its conservative assumptions cover that error for small sites, and the 24- to 72-hour durations are always checked.
4.15 Safety, fencing and multi-use
4.15.1 Depth limits for publicly accessible storage. Where the public has access to a storage area (parks, playfields, open space, school grounds):
- (a) maximum depth in the 10% AEP storm: 0.45 m;
- (b) maximum depth in the 1% AEP storm: 1.2 m, except in a fenced zone under 4.15.3;
- (c) side slopes: no steeper than 4H:1V, with at least a quarter of the perimeter at 6H:1V or flatter for escape; and
- (d) no vertical drop greater than 0.3 m within the storage area or at its edge.
4.15.2 Wet basins. Permanent pools shall have:
- a safety bench at least 3 m wide, no more than 0.3 m below the normal water level; and
- an emergent planting fringe that deters entry.
4.15.3 Fencing. A fence at least 1.2 m high, of a non-climbable design with a lockable gate, is required around any part of a storage that:
- has a vertical wall or headwall drop greater than 0.6 m;
- exceeds 1.2 m depth in the 1% AEP storm with slopes steeper than 4H:1V; or
- contains an outlet structure with an opening larger than 300 mm that is not grated.
4.15.4 Outlets. Every inlet and outlet opening larger than 300 mm accessible to the public shall be fitted with a grate or rack. The grate shall be designed so that a person pinned against it can escape: low approach velocity, inclined, with a large open area.
4.15.5 Signs and depth markers. Every publicly accessible storage shall have signs in Hindi and English stating that the area floods during rain, and a depth marker at the deepest point.
4.15.6 Confined spaces. Underground tanks shall have lockable covers. They shall be marked as confined spaces, and the maintenance declaration (Chapter 10) shall state the entry procedure.
4.15.7 Vector control. Dry storage shall drain completely (Clause 4.7) and have no low points that pond for more than 72 hours. Wet basins shall meet Clause 4.10.7.
Commentary. The numeric limits in Clause 4.15 have no single direct precedent. They are drawn from common international practice, for example KC APWA 5600 (2006), which required at least a quarter of a dry-pond perimeter at 5:1 or flatter, a 20 ft (6 m) clearance from property lines and a 15 ft (4.6 m) maintenance strip. They are made somewhat stricter here because multi-use storage on open space land and in schools will be used by children during the monsoon. Standing water in dry basins is a mosquito-breeding risk, so complete drainage (Clause 4.15.7) is a public-health requirement, not an amenity.
4.16 Basis: why peak matching alone fails
Commentary. This section has no requirements. It records why this chapter requires release below pre-development rates, retention, long-duration checks and a downstream analysis, rather than simple peak matching.
- Timing. Detention lowers a site's peak but stretches its hydrograph (Figure 4.1). Downstream, the stretched releases from many sites overlap with each other and with the main-stem peak. In Denver's study, ten basins each releasing 100% of the historic 100-yr peak produced 106% of the historic peak at the outlet. Only releasing 90% at each site brought it to 97% (UDFCD memo, 2012). A Colorado State University thesis found that location-blind on-site detention "can actually increase peak flows above post-development peaks". An optimisation study found that a downstream pond performed worse than upstream ponds because its outflow synchronised with the main stem (Water 2016, 8(7):290).
- Volume. Detention does not remove volume. In the illustrative example, the post-development 100-yr storm produces about three times the runoff volume of the pre-development 10-yr storm (Clause 2.11). Only retention, or storage that empties to somewhere other than the receiving drain, reduces volume.
- Scale. Kansas City modelling (McEnroe, 2005) found that uniform 3 cfs/ac control reduced Q100 by 36% in a 200-ac watershed. With the same control everywhere, Q100 still rose by 40% at 14 sq mi, and the benefit faded beyond about 1–2 sq mi. The KC committee concluded that "'match existing' can harm streams" (MARC Evolution deck). Georgia makes a ten-percent downstream analysis mandatory for the same reason: "Due to peak flow timing and runoff volume effects, some structural practices fail to reduce discharge peaks to pre-development levels downstream" (GSMM 2016).
- Design-storm dependence. An Australian study of 20 real on-site detention systems found that designs using even ten temporal patterns "cannot reliably produce an OSD system design that will always be effective" under real rainfall (Water Science and Engineering, 2019). This is why Clause 4.6.3 routes the full duration matrix rather than one critical storm.
- Closed outfalls. In Uttar Pradesh, the governing failure is volume with no outlet when the river is high. Most large cities drain to a river that is embanked through the city or that stands above their outfalls for days in a flood. At Lucknow 33 of the 34 drains join the Gomti, and outfalls inside its embankments are pumped when the river is high; Gorakhpur lies behind the embankments of the Rapti and the Rohin; and at Prayagraj, Varanasi and Agra the drains discharge to the Ganga or the Yamuna, whose highest recorded levels stand 2.4–3.3 m above their danger levels: 87.98 m against 84.734 m on the Ganga at Phaphamau, 73.901 m against 71.262 m at Varanasi and 154.76 m against 152.4 m on the Yamuna at Agra, all in September 1978 (CWC values as compiled by SANDRP, as reported). No hourly record of how long a river in Uttar Pradesh stays above a city's outfalls was obtained [TBC]. The UDD guideline of December 2024 already asks that pumps be able to operate above the high flood level, and that outfalls whose invert is below the normal level of the receiving water, or between it and the high flood level, be given their own pumping provision; it gives no duration of closure. The Hindon showed in July 2023 how far a river can exceed its record: it reached 197.28 m at Noida on 26 July, 1.81 m above its earlier highest level (as reported). A perfectly orificed basin behind a closed outfall simply fills. No release-rate rule can fix that; it is handled by the outfall-closed check of Chapter 5.
The response in this Manual is layered:
- release below pre-development (Clause 4.5);
- retain the frequent storms (Clause 4.4);
- route long SW monsoon storms (Clause 4.6.3);
- prefer regional storage in the tal system (Clause 4.13); and
- check downstream and at the outfall (Chapter 5).
Kansas City's own history shows the price. On a test site, peak matching needed 3.0 ac-ft of storage and the 2011 comprehensive criteria needed 4.9 ac-ft (MARC Evolution deck). Over-detention costs more storage. That is the cost of protecting the catchment rather than only the site boundary.
4.17 Submittal requirements
Every site runoff-control submittal shall include a Site Runoff Control Report (Form 4-1) containing:
- the Design Rainfall Sheet (Form 2-1) and the hydrology inputs (Chapter 3);
- the evidence for the order of measures under Clause 4.3.1;
- the RRV computation, infiltration tests, groundwater evidence and drawdown calculation (Clause 4.4);
- the retention credit computation (Clause 4.4.6);
- the release-rate criterion applied, standard or flood-sensitive, with the Annex 4A map extract (Clause 4.5);
- a results table in the format of Clause 4.6.7 for every AEP and duration, with the governing case highlighted;
- stage–storage and stage–discharge tables and plots, and inflow/outflow hydrographs for the governing cases;
- the drawdown calculation (Clause 4.7);
- outlet details, including orifice sizes and levels, trash racks and anti-vortex devices (Clause 4.8);
- the spillway or overflow calculation, freeboard and hazard classification, and the geotechnical report where required (Clause 4.9);
- the RWH and detention accounting, with tank sections showing zone levels (Clause 4.11);
- the design groundwater level and flotation check (Clause 4.12);
- the downstream and tailwater report (Chapter 5, Form 5-1); and
- the safety provisions (Clause 4.15) and the draft maintenance declaration (Chapter 10).
Tier B sites using Clause 4.14.2 shall submit Form 4-2 in place of items 6 and 7. Sites using the fixed-coefficient route (Clause 4.14.3) shall submit Form 4-3 in place of items 6 and 7.
References (chapter)
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01 (approved 10 Dec 2025). https://kcmetro.apwa.org/wp-content/uploads/sites/23/2026/01/APWA-Section-5600_Storm-Drainage-Systems-Facilities.pdf
- Mid-America Regional Council (2025). APWA 5600 Stormwater Standards Policy Supplement (7 Nov 2025); APWA 5600 Manual factsheet. https://www.marc.org/document/apwa-stormwater-standards-supplement ; https://www.marc.org/document/apwa-5600-manual-factsheet
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (5601.8, 5608.4). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- MARC / APWA (2012). Manual of Best Management Practices for Stormwater Quality. https://www.marc.org/sites/default/files/2022-05/Best_Management_Practices_for_Stormwater_Quality.pdf
- MARC. The Evolution of Regional Stormwater Design Standards (presentation; McEnroe 2005 results). https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Atlanta Regional Commission / Georgia EPD (2016). Georgia Stormwater Management Manual, Volume 1. https://documents.atlantaregional.com/gastormwater/GSMM_2016%20EDITION_FINAL_V1.pdf
- Urban Drainage and Flood Control District (now MHFD) (2012). Full Spectrum Detention Release Rate Memorandum. https://mhfd.specialdistrict.org/files/23cb85ce8/UDFCD_Full_Spectrum_Detention_Release_Rate_Memorandum.pdf
- Mile High Flood District. Urban Storm Drainage Criteria Manual, Volume 2 (Storage).
- Department of Irrigation and Drainage Malaysia (2008). Submission Checklist for Stormwater Management. https://www.water.gov.my/jps/resources/auto%20download%20images/5844dfbba8fc1.pdf
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- PUB Singapore (2024). On-site Detention Tank Technical Guide, Rev. 3; Code of Practice on Surface Water Drainage, 7th ed., Addendum No. 3 (16 Apr 2025). https://www.pub.gov.sg/-/media/PUB/PDF/detentionTank.pdf
- Sydney Water (2020). On-site Stormwater Detention Guide (SW201). https://www.sydneywater.com.au/content/dam/sydneywater/documents/on-site-stormwater-detention-guide.pdf
- Upper Parramatta River Catchment Trust (2005). On-site Stormwater Detention Handbook, 4th ed.
- "On-site stormwater detention for Australian development projects: does it meet frequent flow management objectives?" Water Science and Engineering (2019). https://www.sciencedirect.com/science/article/pii/S1674237019300213
- Optimisation of urban detention (2016). Water 8(7):290. https://doi.org/10.3390/w8070290
- Colorado State University. Spatially Dependent On-Site Detention Policies (thesis). https://mountainscholar.org/bitstreams/f4dbec4e-a44f-4933-8d54-a097e741f44a/download
- Uttar Pradesh Revenue Code, 2006, sections 54, 61 and 77, text updated to 5 March 2021 (LBSNAA copy). https://www.lbsnaa.gov.in/storage/uploads/pdf_data/1742473203_Uttar%20Pradesh%20Revenue%20Code%202006%20updated%20till%2005.03.2021.pdf
- Supreme Court of India. Hinch Lal Tiwari v. Kamala Devi, judgment of 25 July 2001, AIR 2001 SC 3215 (UNEP LEAP copy). https://leap.unep.org/sites/default/files/court-case/COU-156224.pdf
- Government of Uttar Pradesh (2020). Notification No. 1397/LXXXI-4-2020-06-2018 of 7 December 2020, Ramgarh Taal Wetland, district Gorakhpur, and rule 4(2)(vi) of the Wetlands (Conservation and Management) Rules 2017, as annexed to and quoted in the response of CPCB in NGT O.A. 1057/2024. https://www.greentribunal.gov.in/sites/default/files/news_updates/RESPONSE%20BY%20R-3%20CPCB%20IN%20OA%20NO.%201057%20of%202024%20Sudhir%20Kumar%20Jha%20Vs%20Gorakhpur%20Development%20Authority%20Through%20ChiefSecretary.pdf
- Irrigation and Water Resources Department, Government of Uttar Pradesh (2025). G.O. No. 24/2025/107/2025-27-Sin-4-16(Writ)(NGT)/2023 of 29 January 2025 (Ganga floodplain zone, Unnao to Ballia), as Annexure-1 to the Irrigation Department's report of 2 April 2025 in NGT O.A. 341/2022. https://www.greentribunal.gov.in/sites/default/files/news_updates/REPORT%20BY%20IRRIGATION%20DEPARTMENT,%20UP%20IN%20OA%20NO.%20341%20of%202022%20%20Deepak%20Awasthi%20Vs.%20State%20of%20U.P..pdf
- Report on the Yamuna floodplain notification of January 2025 (ThePrint, 4 February 2025). https://theprint.in/india/over-5000-buildings-in-agra-face-risk-of-demolition-after-up-govt-demarcates-yamuna-floodplain/2478998
- Reports on Amrit Sarovars in Uttar Pradesh (Drishti IAS; Free Press Journal). https://www.drishtiias.com/state-pcs-current-affairs/up-ranks-1st-in-amrit-sarovar-construction/print_manually ; https://www.freepressjournal.in/uttar-pradesh/yogi-government-completes-nearly-20000-amrit-sarovars-across-uttar-pradesh
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A (§8.5).
- Housing and Urban Planning Department, Government of Uttar Pradesh (2025). G.O. No. 1323/2025/8-3099/208/2025 of July 2025, approving the Uttar Pradesh Development Authority Building Construction and Development Byelaws 2025 and the Model Zoning Regulations 2025 under sections 57 and 13(2) of the UP Urban Planning and Development Act 1973; English text (Annexure-2), Version PRF3 of 3 July 2025: definition 28 and clauses 2.3.2, 2.11, 3.1.2.3, 3.1.3.5, 3.1.3.6, 3.3.1.21, 3.3.3.2, 9.3, 13.1.2, 13.3 and 16.3.2, and the environmental conditions for building projects. https://invest.up.gov.in/wp-content/uploads/2026/08/Model_Building_Byla_250826.pdf
- Housing and Urban Planning Department, Government of Uttar Pradesh (2025). Notification No. 57/2025/I/1150135/2025/8-3099/208/2025 of 21 November 2025, amending clauses 1.6, 2.1.2 and 2.1.3 of the Byelaws 2025 (cited from a summary by TeamLease RegTech; not read). https://teamleaseregtech.com/updates/article/49758/u-p-govt-issued-amendments-in-the-uttar-pradesh-development-authority-building-construction-and-development-byelaws-2025/
- Uttar Pradesh Ground Water (Management and Regulation) Act, 2019 (U.P. Act No. 13 of 2019), sections 28, 31, 33 and 39 (FAOLEX copy). https://faolex.fao.org/docs/pdf/IND214528.pdf
- Urban Development Department, Government of Uttar Pradesh (2024). Urban Flood/Waterlogging Control and Storm Water Drainage Scheme: Guidelines (in Hindi, with an English checklist for detailed project reports), file of 24 December 2024, §§1.1, 2.1, 2.2, 3.2 and 3.3 and Annexure 2. https://urbandevelopment.up.nic.in/assets-new/pdf/Storm%20water/FINAL%20SWD%20GUIDELINE%2024-12-2024%20Designed%20Hindi_R2.pdf
- Report on the Chief Minister's direction on rainwater harvesting in buildings of more than 100 m² (Amar Ujala, 4 October 2025). https://www.amarujala.com/lucknow/up-cm-yogi-orders-rainwater-harvesting-to-be-mandatory-in-buildings-larger-than-100-square-meters-potters-ex-2025-10-04
- Centre for Science and Environment (2017). Mainstreaming Rainwater Harvesting in Noida (Noida Building Regulation and Directions 2006). https://www.cseindia.org/content/downloadreports/7991
- Central Ground Water Board, Northern Region. Documents filed on behalf of the CGWA in NGT O.A. 594/2024 (Lucknow city). https://www.greentribunal.gov.in/sites/default/files/news_updates/Documents%20on%20behalf%20of%20CGWA%20in%20OA%20ON%20594%20of%202024%20(NEWS%20ITEM%20TITLED%20LUCKNOW%20ME%20PAANEE%20CHALA%20RASATAL%2010%20SAAL%20ME%20160%20FOOT%20NEECHE%20CHALA%20GAYA%20JALSTAR%20MEL%20RAHE%20KHATARNAK%20SANKET_0.pdf
- Central Ground Water Board. Dynamic ground water resources of Uttar Pradesh, 2024 assessment (cited from a search summary; the download failed). https://www.cgwb.gov.in/cgwbpnm/public/uploads/documents/1742294844551285154file.pdf
- Central Ground Water Board. Ground water information: Uttar Pradesh (state profile; cited from a search summary). https://cgwb.gov.in/old_website/State-Profiles/Uttar%20pradesh.pdf
- SANDRP (2018, updated 2019). Overview of CWC Flood Forecasting Sites 2018: North India (warning, danger and highest flood levels compiled from CWC). https://sandrp.in/2018/08/03/overview-of-cwc-flood-forecasting-sites-north-india/
- SANDRP (2023). Rivers breaching highest flood levels in July 2023 (the Hindon at Noida). https://sandrp.in/2023/08/03/rivers-breaching-highest-flood-levels-in-july-2023/
- Irrigation Department, Government of Uttar Pradesh (2026). Progress report of 23 May 2026 in NGT O.A. 569/2023, Alok Kumar v. Union of India (Hindon floodplain; 100-year flood levels). https://www.greentribunal.gov.in/sites/default/files/news_updates/Progress%20Report%20By%20Irrigation%20Department,%20State%20of%20Uttar%20Pradesh%20DATED%2023-05-2026%20in%20OA%20569%20of%202023%20Alok%20Kumar%20Vs%20UOI%20and%20Ors.pdf
- India Meteorological Department. Press releases of 15 and 16 September 2022 and 11 September 2023 (24-hour rainfall in Uttar Pradesh). https://internal.imd.gov.in/press_release/20220915_pr_1821.pdf ; https://internal.imd.gov.in/press_release/20220916_pr_1823.pdf ; https://internal.imd.gov.in/press_release/20230911_pr_2523.pdf
- India Meteorological Department. Press release No. 1824 of September 2022 (24-hour rainfall to 17 September 2022, including Chanderdeepghat, Gorakhpur) (not re-read for this Manual [TBC]).
- Reports on the pumping stations and embankments of the Gomti at Lucknow (Down To Earth). https://www.downtoearth.org.in/urbanisation/lucknows-floods-are-man-made-encroached-river-space-and-blocked-drains-turn-even-moderate-rain-into-flooding
- Reports on the Supreme Court's decision on the Akbar Nagar demolitions, May 2024 (LiveLaw). https://www.livelaw.in/top-stories/supreme-court-lucknow-akbarnagar-demolitions-eviction-upheld-slum-dwellers-alternative-accommodation-257604
- Reports on the Rapti flood of 1998 at Gorakhpur (Down To Earth, "Waters of woe"). https://www.downtoearth.org.in/news/waters-of-woe-22412
- ISET-International and CDKN (2014). Gorakhpur: Extreme Rainfall, Climate Change and Flooding, technical report (landing-page summary). https://cdkn.org/resource/gorakhpur-extreme-rainfall-technical-report
- Reports on the waterlogging of Prayagraj of 17–18 August 2026 and the Allahabad High Court's order of 20 August 2026 (LiveLaw). https://www.livelaw.in/high-court/allahabad-high-court/prayagraj-waterlogging-allahabad-hc-pumps-24-hours-municipal-corporation-546731
- Reports on the Hindon flood of July 2023 (The Tribune). https://www.tribuneindia.com/news/delhi/about-350-cars-at-ola-dump-yard-submerged-by-overflowing-hindon-529226
- Bureau of Indian Standards. IS 456:2000 Plain and Reinforced Concrete — Code of Practice.
- Government of India. Dam Safety Act, 2021.
- Chow, V.T., Maidment, D.R. and Mays, L.W. (1988). Applied Hydrology. McGraw-Hill (AMC conversion).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 4A | Flood-sensitive catchment boundaries (GIS); shallow-groundwater zone map |
| 4B | Tier B tables: PSD and SSR (Table 4.3), retention credit factor C_R, standard outlet sizes; confirmed fixed release coefficients (Table 4.3A) |
| 4C | Worked example (Tier A) with full routing tables |
| Form 4-1 | Site Runoff Control Report |
| Form 4-2 | Tier B Site Sheet |
| Form 4-3 | Fixed-coefficient Route Sheet (Clauses 4.14.3 to 4.14.7) |
Commentary. No Indian national rule or Uttar Pradesh rule found during research for this Manual limits the rate of discharge from a site, and none requires on-site detention or "zero run-off". The building rules of the development authorities are now the Uttar Pradesh Development Authority Building Construction and Development Byelaws 2025, approved with the Model Zoning Regulations 2025 by G.O. No. 1323/2025/8-3099/208/2025 of July 2025 under sections 57 and 13(2) of the UP Urban Planning and Development Act 1973. They supersede the bye-laws of 2008, each development authority issues them in its own name, and their amendment of 21 November 2025 did not touch their drainage provisions. Noida, Greater Noida (GNIDA) and YEIDA keep their own building regulations of 2010, made under the UP Industrial Area Development Act 1976, which were not read for this Manual [TBC]. The drainage provisions of the Byelaws protect the building, the drain and the aquifer, not the catchment. Site and layout plans must show "the approximate location and size of any water body, flood affected areas", and building plans the drainage lines and the rooftop rainwater harvesting system (clause 2.3.2); drains "shall be an integral part of the road" with "sufficient slope so that water can drain automatically" (clause 3.1.3.5); the minimum plinth is 0.30 m above the surrounding ground (clause 3.3.1.21); rooftop rainwater harvesting is required on plots of 300 m² and more, "except waterlogged areas", and layouts of more than 4 ha must build recharge reservoirs on at least 1% of their area, no more than 2 m deep (clause 13.1.2; Commentary to Clause 4.11); for projects of 20,000 m² of built-up area and more, "The natural drain system shall be maintained", "No construction is allowed on wetland and water bodies" and sustainable urban drainage systems "are allowed for maintaining the drainage pattern" (clause 13.3); construction on land covered by ponds, reservoirs, rivers or drains identified in a Master Plan, Zonal Plan or layout plan or recorded in the revenue records cannot be compounded (clause 16.3.2(xi)); within 200 m of the bank of the Ganga only repair and renovation are permitted, and where a religious building is allowed there, "Drainage shall not be released directly into the river" (clause 2.11); and buildings with a green rating earn 3%, 5% or 7% of extra FAR (clause 9.3). None of these sets a design storm, a release rate, a storage volume or an overflow path. The guideline of the Urban Development Department for its Urban Flood/Waterlogging Control and Storm Water Drainage Scheme (December 2024; ₹1,000 crore in 2024-25, of which ₹100 crore for master plans) records the gap itself: there is at present no integrated plan for urban drainage in the State's urban areas, and existing drains are "usually designed for a 1–2 year" rainfall return period, which climate change has made inadequate. It requires an Integrated Urban Storm Water Drainage Master Plan, prepared by C&DS, UP Jal Nigam (Urban), to the CPHEEO manual of 2019 and approved by a State Level Apex Committee chaired by the Chief Secretary, with the Nagar Nigams eligible first; and its checklist for detailed project reports asks for 25–30 years of IMD autographic rainfall analysed into an IDF curve and for pumps that can operate above the high flood level. It sets no design return period of its own, and no approved master plan was found [TBC]. Basements are where the gap is sharpest. Clause 3.3.3.2(iv) of the Byelaws requires only that "Adequate arrangements shall have to be made to ensure that surface water does not enter the basement", and nothing in the Byelaws restricts basements in low-lying or flood-prone land or in a notified floodplain. This Manual's own requirements therefore apply to every basement in Uttar Pradesh in addition to the Byelaws: no detention storage in a habitable basement (Clause 4.10.1), the crest of every basement ramp and the sill of every basement opening at least 0.5 m above the 1% AEP flood level, with basement drainage pumped to the surface drain through a non-return valve (Clauses 6.11.1 and 6.11.4), and no basement in Zone 2 (Clause 7.5.2). This chapter is written so that it can supply, as a technical companion, the design storm, release rates and storage volumes that the master plans and project reports of the UDD scheme need and that the Byelaws leave open; it has not been adopted for either purpose. The Byelaws define a drain as a conduit or channel "for the carriage of storm water, sewage" and other water (definition 28), and in practice most city nalas carry sewage, which the State intercepts at their outfalls under Namami Gange (Clause 8.9). Retention and detention apply in full on every site whatever the drain carries: every litre a site releases at the peak of a storm takes up capacity in a drain that is already part-filled with sewage. The CPHEEO (2019) manual describes limiting outflow to the pre-development peak as typical practice, but it uses no "shall" and names no storm frequencies (CPHEEO Part A §8.5.1). This chapter turns that description into a development-control requirement.