Chapter 10Submittals, Review, Operation & Maintenance and Enforcement
10.1 Purpose and scope
10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:
- (a) the submittal stages and their contents (Clauses 10.3–10.4);
- (b) the compliance calculator (Clause 10.5);
- (c) professional certification and review (Clauses 10.6–10.7);
- (d) construction inspection and as-built certification (Clauses 10.8–10.9);
- (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
- (f) handover of public assets (Clause 10.14);
- (g) enforcement (Clause 10.15); and
- (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).
10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.
10.2 Definitions
| Term | Meaning in this chapter |
|---|---|
| Submittal | A set of documents lodged with the Authority at one of the stages of Clause 10.3. |
| Drainage report | The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4. |
| Stormwater facility | Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private. |
| Hold point | A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8). |
| As-built certificate | The certificate of Clause 10.9 that the facility was built as approved and performs as designed. |
| Owner | The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset. |
| O&M plan | The operation and maintenance plan of Clause 10.11. |
| Facility register | The public register of facilities of Clause 10.17. |
Other terms are defined in Clause 1.4.
10.3 Submittal stages
10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Uttar Pradesh Development Authority Building Construction and Development Byelaws 2025 (Table 10.1):
Table 10.1 — Submittal stages and linked approvals
| Stage | Submittal | When | Linked approval |
|---|---|---|---|
| 0 | Pre-application meeting and Form 1-1 (Applicability Determination) | Before the planning permission or layout application | None (advisory record) |
| 1 | Preliminary drainage report | With the planning permission or layout application | Planning permission / layout approval |
| 2 | Final drainage design | Before building permit, or before commencement where the permit is issued with the planning permission | Building permit / commencement |
| 3 | Construction inspections at hold points | During construction | None (records filed) |
| 4 | As-built certificate and verification tests | Before the completion certificate | Completion / occupancy certificate |
| 5 | Maintenance declaration registered, or handover of public assets | Before or with the completion certificate | Completion certificate; asset acceptance |
| 6 | Annual declarations and inspection reports | Every year after completion | Continuing compliance |
10.3.2 Stage 0 is mandatory for:
- (a) sites of 2 ha or more;
- (b) sites in a flood-sensitive catchment;
- (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
- (d) sites draining to a tidal outfall or adjoining a waterbody.
For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.
10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.
10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.
10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.
Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.
Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the Byelaws 2025 steps an Uttar Pradesh applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.
10.4 Required contents and checklists
10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:
- (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
- (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
- (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
- (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
- (e) the pre-development condition and hydrologic method (Chapter 3);
- (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
- (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
- (h) the downstream extent and tailwater case (Chapter 5);
- (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
- (j) the land reserved for facilities and maintenance access (Clause 10.13).
10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:
- (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
- (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
- (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
- (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
- (e) construction drawings, details and specifications of every facility;
- (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
- (g) the hold-point schedule (Clause 10.8);
- (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
- (i) the model input files and the GIS data of Clause 10.4.4; and
- (j) the certificates of Clause 10.6.
10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.
10.4.4 Digital submittal.
- (a) Reports and drawings shall be submitted as searchable PDF.
- (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
- (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (44N statewide, or 43N for a project wholly in the NCR districts or Mathura, west of 78° E), with attributes as listed in Annex 10B.
- (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the CWC and I&WRD gauges on the receiving rivers and of I&WRD's embankment, regulator and drain levels used in Chapter 5 shall be stated.
10.4.5 Summary of forms used in submittals (Table 10.2):
Table 10.2 — Forms used in submittals
| Form | Title | Stage |
|---|---|---|
| 1-1 | Applicability Determination | 0 or 1 |
| 1-2 | Variance / Waiver Request | 1 |
| 2-1 | Design Rainfall Sheet | 1, 2 |
| 10-1 | Drainage Report Checklist | 1, 2 |
| 10-2 | Compliance Calculator Summary | 1, 2, 4 |
| 10-3 | Professional Design Certificate | 1, 2 |
| 10-4 | Hold-Point Inspection Record | 3 |
| 10-5 | As-built Certificate | 4 |
| 10-6 | Maintenance Declaration | 5 |
| 10-7 | Annual Maintenance Declaration and Inspection Report | 6 |
| 10-8 | Asset Handover Certificate | 5 |
Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Uttar Pradesh has no notified design return period, runoff coefficient or design storm for its drains. The Urban Development Department's guideline of December 2024 records that existing drains are usually designed for a 1–2 year return period, requires drainage master plans and DPRs to follow the CPHEEO Manual on Storm Water Drainage Systems (2019), and asks every DPR for IMD autographic rainfall for the last 25–30 years with an IDF curve, but sets no return period, intensity or runoff coefficient of its own (UDD 2024). The only station IDF published for the State is for Lucknow, from about 25 years of autographic records ending before 1985 (Kathuria, Kaur and Mehra 1987). The one drainage DPR read, for the Taj East Drain at Agra, adopted a 2-year intensity of 28.2 mm/h from an IMD daily series whose printed values are implausible (Agra Smart City DPR). No circular of a Nagar Nigam, development authority, UP Jal Nigam (Urban) or I&WRD giving a return period, an intensity or a runoff coefficient for drain design was found. Form 2-1 and Form 10-2 therefore carry the whole design basis of each submission. Form 2-1 and Form 10-2 ensure that every design states its inputs.
10.5 Compliance calculator
10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:
- (a) applies the applicability tests of Clause 1.5;
- (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
- (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
- (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
- (e) on alternative S-2, gives the permissible site discharge for each AEP; and
- (f) produces the Compliance Calculator Summary (Form 10-2).
10.5.2 Use.
- (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
- (b) On the design-aid route, the calculator may be the only storage calculation.
- (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.
10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.
10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.
Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). An Uttar Pradesh calculator serves Tier B authorities in particular, where it may be the whole calculation.
10.6 Professional certification
10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or TCPD:
- (a) Tier A sites of 1 ha or more;
- (b) any site in a flood-sensitive catchment;
- (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
- (d) any pumped facility, tide gate or regional facility.
10.6.2 Empanelment criteria shall be issued by TCPD and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.
10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:
- (a) the design complies with this Manual, except for variances listed and approved;
- (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
- (c) the models submitted reproduce the results reported.
10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.
10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.
Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the Byelaws 2025 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.
10.7 Review procedure and timelines
10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.
10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:
- (a) 15 working days of acceptance for a first submittal; and
- (b) 10 working days of acceptance for a resubmittal.
10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.
10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the TCPD list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.
10.7.5 Concurrent clearances. Where the NOC of the Irrigation or Ground Water Department listed among the NOCs for building permission in the Byelaws 2025, the permission of I&WRD for a work on, or a discharge to, one of its rivers, drains, canals, embankments or regulators, the approval of the UP State Wetland Authority for a regulated activity in a notified wetland or its zone of influence, the consent of the body that owns the receiving drain where that body is not the Authority, or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.
10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.
10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.
Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.
10.8 Construction inspection
10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:
- (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
- (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
- (c) the infiltration tests of Clause 10.9.3;
- (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
- (e) pumps and controls, at commissioning.
10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.
10.8.3 Protection during construction.
- (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
- (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
- (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.
Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.
Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.
10.9 As-built certification
10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:
- (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
- (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
- (c) the completed hold-point records (Form 10-4); and
- (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).
10.9.2 Acceptance. The as-built facility is accepted where:
- (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
- (b) the outlet dimensions and inverts match the approved design; and
- (c) the re-run shows compliance with every criterion of Chapters 4 and 5.
Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.
10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.
10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.
Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.
10.10 Maintenance declarations and covenants
10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:
- (a) identify each facility, its location and the approved O&M plan;
- (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
- (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
- (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
- (e) be registered so that it runs with the land and is disclosed to purchasers.
10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.
10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 May each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.
10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.
Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Uttar Pradesh because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 May date is set by this Manual to fall before the south-west monsoon (June–September), when most Uttar Pradesh extreme rainfall occurs.
10.11 O&M plans
10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:
- (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
- (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
- (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
- (d) inspection checklists matching Form 10-7;
- (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
- (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
- (g) safety measures for confined spaces, deep water and public access;
- (h) access routes and equipment needed (Clause 10.13);
- (i) an annual cost estimate and who pays it; and
- (j) the records to be kept, and for how long.
10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.
Commentary. Uttar Pradesh runs its river flood season through I&WRD, but no comparable order for urban drains was found. At the State review of May 2025 the Chief Minister directed that all flood prevention works be completed by 15 June, and for 2026 about 4,000 km of embankments were reported secured, with flood control rooms in all 18 divisions set up by 31 May and working from 15 June to 15 October (as reported). No order of the Urban Development Department, the Directorate of Local Bodies or a Nagar Nigam setting a deadline for desilting the nalas (nala safai) was found. The UDD scheme of December 2024 allows five years of operation and maintenance to be included in project costs and contracts and treats flood pumping stations as an eligible work (UDD 2024). Gorakhpur is reported to run its monsoon pumping with a decision-support system and automated pumps, while at Lucknow an inspection found only half the pumps working at the Kukrail pumping station and none at Wazirganj (as reported). No operating rule for any regulator, flap gate or drainage pumping station in an Uttar Pradesh city, and none for the Gomti barrage at Lucknow, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.
10.12 Inspection frequencies
10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:
Table 10.3 — Minimum owner inspection frequencies
| Facility type | Routine | Pre-monsoon (by 31 May) | After a heavy-rainfall event |
|---|---|---|---|
| Retention / infiltration (soakaways, trenches, bioretention, permeable paving) | Every 6 months | Yes | Yes |
| Surface detention basin or multi-use open space area | Every 6 months | Yes | Yes |
| Underground or podium detention tank, gravity outlet | Every 6 months | Yes | Yes |
| Pumped detention, pumps and controls | Monthly test run | Yes, with full duty test | Yes |
| Flap / tide gate, non-return valve | Every 3 months | Yes, with seal test | Yes |
| Gross pollutant trap / first-flush device | Every 3 months | Yes | Yes |
| Private drains and inlets | Every 6 months | Yes | — |
A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Uttar Pradesh, the pre-monsoon inspection of regulators, flap gates, non-return valves and pumped facilities, with the pump duty and gate seal tests, shall be completed by 31 May, and these facilities, with their standby generators, shall be checked again for readiness by 15 June, with every gate on an outfall to a river operated through its full travel. Pumps, their standby power and the regulators shall then be kept on monsoon standby, with the monthly test run, until 15 October.
10.12.2 Authority inspections. The Authority shall inspect:
- (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
- (b) a random sample of at least 10% of other facilities each year.
10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).
Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 May) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the south-west monsoon (June–September); tick positions within the year are illustrative.
Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 31 May deadline is set by this Manual for the onset of the south-west monsoon in the second half of June; no order of the Urban Development Department or of a local body setting a desilting deadline was found. The monsoon normally reaches the east of the State by 20 June and covers it by 30 June, but it arrived on 18 June in 2025, and very large falls have come in June: 487.2 mm at Gonda on 12 June 1984, 259.0 mm at Gorakhpur on 9 June 1984, and 327.2 mm at Aligarh on 30 June 1981 (IMD). The north-east terai is already wet in June, with normals of 187.8 mm at Gorakhpur and 180.8 mm at Bahraich (IMD). NDMA (2010) sets 31 March for pre-monsoon desilting nationally; this Manual allows until 31 May so that dry-season work can be finished, and keeps 31 May for the annual declaration. Regulators, gates, pumps and their standby generators must in addition be shown ready by 15 June, the date by which I&WRD's flood works are to be complete and its flood control rooms open (as reported). The normal withdrawal is 10 October, and it came on 13 October in 2025 (IMD); October storms include 310.0 mm at Hardoi on 13 October 1985 (IMD) and 193 mm at Gorakhpur on 2 October 2021 (as reported). Pumps and regulators are therefore kept on standby to 15 October, the day the flood control rooms close (Figure 10.3). The post-event inspections of Table 10.3 cover storms at any time of year, including pre-monsoon storms such as the 129.5 mm at Lucknow on 21 April 1909 and the 110.2 mm at Gorakhpur on 13 May 1956 (IMD).
10.13 Maintenance access
10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.
10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.
10.13.3 Underground facilities. Tanks shall have:
- (a) an access opening over the inlet, the outlet and each chamber;
- (b) fixed ladders or steps, and ventilation for confined-space entry;
- (c) a sump or low point for sediment removal; and
- (d) headroom sufficient for manual cleaning.
10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.
10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.
Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Uttar Pradesh cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.
10.14 Handover of public assets to the ULB
10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:
- (a) the as-built certificate (Clause 10.9) has been accepted;
- (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
- (c) the land, or an easement over it, has been transferred to the ULB;
- (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
- (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.
10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 15 June to 15 October, after handover. The ULB may hold a security deposit for this period.
10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.
10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.
Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Uttar Pradesh drainage show up only in the first SW monsoon.
10.15 Enforcement
10.15.1 Offences. The following are contraventions of this Manual:
- (a) building without an approved drainage design where one is required;
- (b) building a facility other than as approved;
- (c) removing, filling, covering, reducing or changing the use of a facility without approval;
- (d) failing to maintain a facility, or to submit Form 10-7;
- (e) a sewage connection to a storm drain;
- (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
- (g) obstructing a natural drainage path or major-system flow path; and
- (h) false or negligent certification.
10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):
Table 10.4 — Graduated enforcement response
| Step | Action |
|---|---|
| 1 | Written notice stating the contravention, the clause breached, the remedy and a compliance period. |
| 2 | Stop-work order, or withholding of the completion certificate, for development not yet complete. |
| 3 | Penalty under the applicable Act or rules. |
| 4 | Works in default by the Authority, with the cost recovered from the owner. |
| 5 | Disconnection of the private drain connection to the public system, where this causes no hazard to others. |
| 6 | Report of the certifying professional to the registering authority, and suspension from the empanelled list. |
10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.
10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.
10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.
Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Uttar Pradesh Development Authority Building Construction and Development Byelaws 2025 are made and from the municipal Acts. The graduated steps are set by this Manual. In Uttar Pradesh the courts and the National Green Tribunal have become the working regulators of floodplains, ponds and drains. The Tribunal has driven the demarcation of the Ganga, Yamuna and Hindon floodplains on the 1-in-100-year flood, in O.A. 341/2022 (Kanpur) and O.A. 275/2023 and 569/2023 (Gautam Buddh Nagar and Ghaziabad), where the Hindon was still not demarcated in May 2026 (I&WRD 2025; I&WRD 2026). The Supreme Court held that where "a pond exists and the area covered by it varies in rainy season … no part of it could have been allotted" and directed the State to restore it (Hinch Lal Tiwari v. Kamala Devi, 2001), and in October 2025 the Allahabad High Court warned Pradhans, Lekhpals and Tahsildars of contempt for inaction on encroachment of ponds and public land (as reported). In August 2026, after 73.4 mm of rain in a day at Prayagraj, the High Court took up waterlogging in the city on its own motion and ordered pumping within 24 hours with a ward-wise compliance affidavit (as reported). In Lucknow the Supreme Court in May 2024 upheld the clearance of Akbar Nagar from the floodplain of the Kukrail (as reported). Two recent CAG audits concern authorities in the National Capital Region. Report No. 4 of 2023, on land acquisition and allotment by GNIDA, was tabled on 13 August 2025; the press then reported its findings on farmhouse plots in Haibatpur, 130–553 m from the Hindon, on land the Regional Plan 2021 classed as a natural conservation zone, and the Tribunal took up the report on its own motion as O.A. 437/2025 (CAG 2025; NGT 2025; as reported). Report No. 11 of 2025, on development and allotment by the Ghaziabad Development Authority for 2017-18 to 2021-22, was tabled on 20 February 2026 and covers development works including drainage systems; its drainage findings were not read (CAG 2026). The statutes carry some penalties: construction on ponds, reservoirs, rivers or drains shown in a plan or in the revenue records cannot be compounded (Byelaws 2025, cl. 16.3.2(xi)), and an owner who fails to install the rainwater harvesting system shown on the sanctioned drawings is liable to a penalty (UP Ground Water (Management and Regulation) Act 2019, s.39(4)). This shows that a rule without routine enforcement does little. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.
10.16 Monitoring and post-event review
10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.
10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:
- (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
- (b) the stage of the receiving river (the Gomti, the Ganga, the Yamuna, the Rapti, the Hindon or another river) at the nearest CWC or I&WRD gauge and, where it is gauged, at the outfall, each on a named datum; the state of every regulator, flap gate, interception structure and pumping station on the outfall and on the drain upstream of it; and releases from any barrage or dam upstream;
- (c) flooded locations, depths and durations, with flood marks surveyed where possible;
- (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
- (e) recommended actions.
10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), UPSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.
10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.
Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Uttar Pradesh's urban floods have been examined by courts and tribunals rather than by technical reviews. No technical review was found of the rain of 15–16 September 2022, when IMD recorded 20 cm in 24 hours at Gorakhpur and at Lucknow (IMD 2022) and nine people died when a wall collapsed in Dilkusha, Lucknow (as reported); of the rain of 10–11 September 2023, with 14 cm at Lucknow and 15 cm at Kanpur (IMD 2023), the event the Urban Development Department cites as a flash flood (UDD 2024); or of the Hindon flood of July 2023, when the river at Noida rose 1.81 m above its old high flood level and about 350 cars were submerged in a yard on the floodplain at Ecotech-3 (as reported). At Prayagraj in August 2026, 73.4 mm in a day, below the 2-year daily rainfall of the CWC Flood Estimation Report plates (this Manual's reading), was enough to waterlog George Town, Tagore Town and Rambagh, and it was the High Court that called for a ward-wise account (as reported). No record of flood extents, depths or durations kept by any Nagar Nigam was found. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.
10.17 Data publication
10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:
- (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
- (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
- (c) the register of variances and waivers (Clause 1.10);
- (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
- (e) enforcement actions (Clause 10.15.5); and
- (f) event reports and post-event reviews (Clause 10.16).
10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.
10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.
10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.
Commentary. Transparency is a design criterion in its own right here. Some of Uttar Pradesh's drainage records are public: the Urban Development Department publishes its storm water drainage guideline of December 2024, the English text of the Byelaws 2025 is published by the State, and I&WRD's floodplain orders and progress reports can be read as filed before the National Green Tribunal. Much else could not be found in the public domain: an approved Integrated Urban Storm Water Drainage Master Plan for any city, or the terms of reference for one; the list of Nagar Nigams whose plans are in preparation (seen only in a summary of a Lok Sabha reply); an inventory of the regulators, flap gates, interception structures and pumping stations on the drains of any city, with their capacities and operating rules; any design river level at an outfall; CWC's station sheets and hourly river records for the Gomti, Ganga, Yamuna, Rapti and Hindon sites; the operating rule of the Gomti barrage; an urban flood plan or SOP of UPSDMA; the UP Ground Water (Management and Regulation) Rules 2020; the number of the Yamuna floodplain order of January 2025; the Hindi text of the Byelaws 2025 and the authorities' own notified copies; the current building regulations of Noida, Greater Noida and YEIDA; and the chapters of CAG Reports No. 4 of 2023 and No. 11 of 2025. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.
10.18 Review of this chapter
10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.
References (chapter)
- Urban Development Department, Government of Uttar Pradesh (2024). Urban Flood/Jalplavan Niyantran evam Storm Water Drainage Yojana: Dishanirdesh (guidelines for the urban flood and waterlogging control and storm water drainage scheme), Hindi, file dated 24 December 2024. https://urbandevelopment.up.nic.in/assets-new/pdf/Storm%20water/FINAL%20SWD%20GUIDELINE%2024-12-2024%20Designed%20Hindi_R2.pdf
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities, §5608 (easements, maintenance, submittals) and §5609 (plan requirements). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Mid-America Regional Council (2025). Stormwater management page: 2025 Stormwater Standards Manual, Compliance Calculator, Calculator Start-Up Guide, Policy Supplement. https://www.marc.org/environment/environment-plans/stormwater-management
- PUB Singapore (2018, with Addendum No. 3 of 16 Apr 2025). Code of Practice on Surface Water Drainage, 7th ed. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
- PUB Singapore (2024). On-site Stormwater Detention Tank Technical Guide. https://www.pub.gov.sg/-/media/PUB/PDF/detentionTank.pdf
- PUB Singapore (11 Nov 2024). Amendments to Sewerage and Drainage Act (press release). https://www.pub.gov.sg/Resources/News-Room/PressReleases/2024/11/Amendments-to-Sewerage-and-Drainage-Act
- MoHUA (2016). Model Building Bye-Laws, Chapter 9, §9.6. https://web.archive.org/web/2022/https://mohua.gov.in/upload/uploadfiles/files/MBBL.pdf
- National Disaster Management Authority (2010). National Guidelines on Management of Urban Flooding. https://sdma.goa.gov.in/sites/default/files/2022-05/management_urban_flooding.pdf
- Housing and Urban Planning Department, Government of Uttar Pradesh (2025). G.O. No. 1323/2025/8-3099/208/2025 of July 2025, approving the Uttar Pradesh Development Authority Building Construction and Development Byelaws 2025 and Model Zoning Regulations 2025, with the English text (Version PRF3, 3 July 2025) (clauses 1.1, 2.2, 2.3.2, 2.9, 13.1.2 and 16.3.2). https://invest.up.gov.in/wp-content/uploads/2026/08/Model_Building_Byla_250826.pdf
- Uttar Pradesh Ground Water (Management and Regulation) Act 2019 (U.P. Act No. 13 of 2019), section 39 (FAOLEX copy). https://faolex.fao.org/docs/pdf/IND214528.pdf
- Supreme Court of India (2001). Hinch Lal Tiwari v. Kamala Devi, judgment of 25 July 2001, AIR 2001 SC 3215. https://leap.unep.org/sites/default/files/court-case/COU-156224.pdf
- Irrigation and Water Resources Department, Government of Uttar Pradesh (2025). Compliance report of 2 April 2025 in National Green Tribunal O.A. 341/2022, Deepak Awasthi v. State of U.P., annexing G.O. No. 24/2025/107/2025-27-Sin-4-16(Writ)(NGT)/2023 of 29 January 2025. https://www.greentribunal.gov.in/sites/default/files/news_updates/REPORT%20BY%20IRRIGATION%20DEPARTMENT,%20UP%20IN%20OA%20NO.%20341%20of%202022%20%20Deepak%20Awasthi%20Vs.%20State%20of%20U.P..pdf
- Irrigation and Water Resources Department, Government of Uttar Pradesh (2026). Progress report of 23 May 2026 in National Green Tribunal O.A. 569/2023, Alok Kumar v. Union of India (Hindon floodplain). https://www.greentribunal.gov.in/sites/default/files/news_updates/Progress%20Report%20By%20Irrigation%20Department,%20State%20of%20Uttar%20Pradesh%20DATED%2023-05-2026%20in%20OA%20569%20of%202023%20Alok%20Kumar%20Vs%20UOI%20and%20Ors.pdf
- National Green Tribunal (2025). O.A. 437/2025, News item titled "CAG slams Greater Noida for allowing farmhouses on Hindon floodplain": reply of the DM Gautam Buddh Nagar of 13 October 2025, annexing the order of 1 September 2025. https://www.greentribunal.gov.in/sites/default/files/news_updates/REPLY%20BY%20DM,%20GAUTAM%20BUDH%20NAGAR%20IN%20OA%20NO.%20437%20of%202025%20NEWS%20ITEM%20TITLED%20CAG%20SLAMS%20GREATER%20NOIDA%20FOR%20ALLOWING%20FARMHOUSES%20ON%20HINDON%20FLOODPLAIN%20APPEARING%20IN%20THE%20TIMES%20OF%20INDIA%20DATED%2018.08.2025..pdf
- Comptroller and Auditor General of India (2025). Report No. 4 of 2023, Land Acquisition and Allotment of Properties in Greater Noida Industrial Development Authority, Government of Uttar Pradesh (tabled 13 August 2025; report page). https://cag.gov.in/ag2/uttar-pradesh/en/audit-report/details/122410
- Comptroller and Auditor General of India (2026). Report No. 11 of 2025, Development and Allotment of Properties by Ghaziabad Development Authority (tabled 20 February 2026; report page). https://cag.gov.in/en/audit-report/details/123698
- Kathuria, S.N., Kaur, S. and Mehra, A.K. (1987). Rainfall intensity for local drainage design in Lucknow and its neighbouring area. Mausam 38(1), 85–88. https://mausamjournal.imd.gov.in/index.php/MAUSAM/article/download/2654/2468
- Agra Smart City. Improvements to Taj East Drain, detailed project report, chapter 9 (rainfall). https://agrasmartcity.in/pdf/wc13581914%20Improvements%20to%20Taj%20East%20Drain.pdf
- India Meteorological Department (2022, 2023). Press releases of 15 and 16 September 2022 and 11 September 2023 (heavy rainfall over Uttar Pradesh). https://internal.imd.gov.in/press_release/20220915_pr_1821.pdf ; https://internal.imd.gov.in/press_release/20220916_pr_1823.pdf ; https://internal.imd.gov.in/press_release/20230911_pr_2523.pdf
- India Meteorological Department, Meteorological Centre Lucknow (2024, 2025). Southwest Monsoon Report 2024 and 2025 for Uttar Pradesh (onset and withdrawal dates); station climatological tables, 1991–2020 normals. https://mausam.imd.gov.in/lucknow/mcdata/monsoon.pdf ; https://mausam.imd.gov.in/lucknow/mcdata/swreport.pdf
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012) (Uttar Pradesh stations). https://imdpune.gov.in/library/public/EXTREMES%20OF%20TEMPERATURE%20and%20RAINFALL%20upto%202012.pdf
- SANDRP (2018, updated 2019). Overview of CWC Flood Forecasting Sites 2018: North India (compiled from CWC; secondary source). https://sandrp.in/2018/08/03/overview-of-cwc-flood-forecasting-sites-north-india/
- SANDRP (3 August 2023). Rivers breaching highest flood levels in July 2023 (Hindon at Noida; secondary source). https://sandrp.in/2023/08/03/rivers-breaching-highest-flood-levels-in-july-2023/
- The Week/PTI (16 May 2025). Report on the Chief Minister's review of flood preparedness (secondary source). https://www.theweek.in/wire-updates/national/2025/05/16/des87-up-adityanath-flood-prep.html
- Free Press Journal (2026). UP govt strengthens 4,000 km embankments ahead of monsoon (flood control rooms, 15 June–15 October; secondary source). https://www.freepressjournal.in/uttar-pradesh/up-govt-strengthens-4000-km-embankments-ahead-of-monsoon-to-prevent-flood-damage
- The Realty Today (2025). CAG report highlights violations in GNIDA's farmhouse land schemes (secondary source). https://therealtytoday.com/news/cag-report-highlights-violations-in-gnidas-farmhouse-land-schemes
- LiveLaw (2025, 2026). Allahabad High Court orders on Gram Sabha land encroachments (October 2025) and on Prayagraj waterlogging (August 2026); Supreme Court on the Akbar Nagar demolitions, Lucknow (May 2024) (secondary sources). https://www.livelaw.in/high-court/allahabad-high-court/allahabad-high-court-crackdown-gram-sabha-land-encroachments-pradhans-lekhpals-tahsildars-inaction-306753 ; https://www.livelaw.in/high-court/allahabad-high-court/prayagraj-waterlogging-allahabad-hc-pumps-24-hours-municipal-corporation-546731 ; https://www.livelaw.in/top-stories/supreme-court-lucknow-akbarnagar-demolitions-eviction-upheld-slum-dwellers-alternative-accommodation-257604
- Scroll (16 September 2022). Report on the Dilkusha wall collapse in Lucknow (secondary source). https://scroll.in/latest/1032979/scroll_in
- The Tribune (2023). About 350 cars at a dump yard submerged by the overflowing Hindon (secondary source). https://www.tribuneindia.com/news/delhi/about-350-cars-at-ola-dump-yard-submerged-by-overflowing-hindon-529226
- Daily Pioneer (2021). Gorakhpur records highest October rainfall in 100 years (secondary source). https://www.dailypioneer.com/2021/india/gorakhpur-records-highest-october-rainfall-in-100-years.html
Annexes and forms
| Annex / Form | Content |
|---|---|
| 10A | Compliance calculator and user guide |
| 10B | GIS data specification and attribute schema |
| 10C | Maintenance access dimensions |
| 10D | Model O&M plans by facility type |
| 10E | Empanelment criteria for Stormwater Design Professionals and reviewers |
| Form 10-1 | Drainage Report Checklist |
| Form 10-2 | Compliance Calculator Summary |
| Form 10-3 | Professional Design Certificate |
| Form 10-4 | Hold-Point Inspection Record |
| Form 10-5 | As-built Certificate |
| Form 10-6 | Maintenance Declaration |
| Form 10-7 | Annual Maintenance Declaration and Inspection Report |
| Form 10-8 | Asset Handover Certificate |
| Form 2-1 | Design Rainfall Sheet (Chapter 2) |
Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Uttar Pradesh the failure is one of missing criteria and divided ownership. The Urban Development Department found in December 2024 that "there is no integrated plan for urban drainage" in the State's urban areas, that small nalas and nalis are built piecemeal, and that existing drains are "usually designed for a 1–2 year" rainfall return period, which it called inadequate (UDD 2024). No rule dividing the natural drains, which the Irrigation and Water Resources Department (I&WRD) keeps in canal commands and along its rivers and embankments, from the nalas of the Nagar Nigams was found; the guideline makes the Nagar Nigam the regulator of an approved drainage master plan under the UP Municipal Corporations Act 1959 and the UP Municipalities Act 1916 (UDD 2024). The approval route shapes this chapter. The development authorities constituted under the UP Urban Planning and Development Act 1973 apply the Uttar Pradesh Development Authority Building Construction and Development Byelaws 2025, approved by G.O. No. 1323/2025/8-3099/208/2025 of July 2025 under sections 57 and 13(2) of that Act, which superseded the bye-laws of 2008; each authority issues them in its own name (Byelaws 2025, cl. 1.1). Noida, Greater Noida (GNIDA) and YEIDA are industrial development authorities under the UP Industrial Area Development Act 1976 and keep their own building regulations of 2010 (as reported). For a layout, the development permit needs a site plan showing "the approximate location and size of any water body, flood affected areas", the nalas, and contours at 0.3 m intervals where the slope is more than 1:20; building plans must show the "drainage lines and roof top rainwater harvesting system"; and a completion certificate closes the process (Byelaws 2025, cl. 2.3.2 and 2.9). The NOC table lists the Irrigation or Ground Water Department, and an NOC not given within 30 days is deemed to have been given (Byelaws 2025, cl. 2.2). No rule asks for a drainage report, limits peak runoff or requires on-site detention (Byelaws 2025). Every stormwater item in this chapter is therefore written so that the architect or engineer on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it with the layout services plan and its recharge reservoir, with the drainage drawings of the building plan, and before the completion certificate; for public works, the drainage section of a DPR under the UDD scheme must in any case be consistent with the approved master plan (UDD 2024). This chapter is the process.