Annexes to Chapter 3Hydrologic Methods

These annexes support Chapter 3. Annex 3C sets out benchmark test problems for software acceptance, and Forms 3-1 and 3-2 are the submittal forms required by Clause 3.17. Annexes 3A, 3B, 3D and 3E need survey, gauging or published report data that this draft does not yet contain; each gives the intended layout and the interim rule of Chapter 3 that applies until it is published. The forms are draft forms and have no statutory status.


Annex 3A — Uttarakhand soil series to HSG lookup; seasonal high water table map

Supports Clauses 3.7 and 3.10 of Chapter 3.

To be prepared. This annex will contain (a) a lookup from each soil series mapped in Uttarakhand to its hydrologic soil group (HSG), in both the drained and the undrained state, and (b) a map of the depth to the seasonal high groundwater table in the south-west monsoon (June–September). It needs NBSS&LUP and Uttarakhand Agriculture Department (soil survey) [TBC] series maps with their scales, measured saturated hydraulic conductivity and depth to an impermeable layer for each series, and observation-well records from the Central Ground Water Board and the Irrigation Department, supplemented by piezometers in the terai below the spring line in Udham Singh Nagar, Haridwar and the south of Nainital district, where wells flow under artesian pressure, the floodplains and low terraces of the Ganga at Haridwar and Rishikesh, the Solani at Roorkee and the Gaula, Kosi, Kichha and Kalyani in the Kumaon plains, the margins of Naini lake and Bhimtal, and hill towns with perched water on unstable slopes, such as Nainital and Joshimath. Until it is published, use the interim rules of Chapter 3: assign HSG from measured saturated hydraulic conductivity and depth to an impermeable layer or water table by the criteria of NEH Part 630, Ch. 7 (Clause 3.7.2); verify it by site infiltration tests wherever retention relies on infiltration (Clause 3.7.3); take the seasonal high water table from site piezometers, trial pits or the nearest observation well (Clause 3.10.2); and assign HSG D wherever that level is within 0.6 m of the ground surface (Clause 3.10.1).

Table 3A.1 — Soil series to HSG lookup (layout)

Soil series District(s) Taxonomic class Surface texture Saturated hydraulic conductivity (mm/h) Depth to impermeable layer (m) HSG, drained HSG, undrained Source map and scale
                 
                 
                 

Table 3A.2 — Seasonal high water table, by mapping unit (layout)

Mapping unit or grid cell Observation wells used Years of June–September record Highest June–September level below ground (m) Within 0.6 m of ground (Clause 3.10.1)? Data source
           
           

Annex 3B — Uttarakhand CN calibration and supplementary land covers (terraced fields, oak and chir pine forest, slide scars and debris fans, bare rock and scree, boulder-bed raos, terai paddy, taal and reservoir beds)

Supports Clauses 3.8 and 3.15 of Chapter 3.

To be prepared. This annex will contain (a) curve numbers calibrated against observed rainfall and runoff in Uttarakhand catchments, compared with the TR-55 values of Table 3.5, and (b) curve numbers for land covers that Table 3.5 does not list: the terraced fields of the hill slopes, whose risers and bunds hold water on each terrace until it overtops and which are being abandoned in many hill villages; the oak forest of the outer ridge, with its deep litter, and the chir pine forest of the middle mountains, whose needle litter sheds water; the fresh scars, slide debris and debris fans of landslides and debris flows, and the cut slopes and spoil of hill roads; bare rock, scree and the skeletal soils of the steep hills; the wide boulder beds of the raos of the Doon and of the rivers of the bhabar, which lose flow to the gravels until the bed is saturated; the paddy and sugarcane of the terai, with their bunded fields; and the beds of taals, khals and reservoirs, such as the Sukhatal basin above Naini lake and the margins of the Tehri, Baur, Haripura and Tumaria reservoirs, that are dry or drawn down at the start of a storm. It needs paired rainfall–runoff records for small gauged catchments of known cover and soil, from Irrigation Department gauging sites, agricultural research stations and tank gauges, analysed by event and by antecedent moisture. Until it is published: the pre-development reference stays open space in good condition for every site (Clause 3.3.2), so these covers do not enter the pre-development run; for off-site existing conditions, use the nearest Table 3.5 or TR-55 cover row, including the cultivated rows (Clause 3.8.3(c)), and state the row chosen and the reason on Form 3-1; land under standing water at the start of the design storm is modelled as water surface with no losses (Table 3.5; Clause 3.10.4(b)). Any departure from these defaults requires calibration under Clause 3.15 (Clause 3.15.1(d)).

Table 3B.1 — Supplementary land covers, AMC II (layout)

Cover type HSG A HSG B HSG C HSG D Ia ratio Basis (catchments, events, years)
Terraced fields of the hill slopes, with the riser height recorded (cultivated or abandoned)            
Oak forest of the outer ridge, with deep litter            
Chir pine forest of the middle mountains, with needle litter            
Fresh landslide scar, slide debris or debris fan; hill-road cut slope and spoil            
Bare rock, scree and skeletal soil of steep slopes            
Boulder bed of a rao or bhabar river (Doon raos, Gaula, Kosi, Dabka and the like), dry at the start of the storm            
Terai paddy or sugarcane, with the bund height recorded            
Taal, khal or reservoir bed dry or drawn down at the start of the storm (Sukhatal basin; Tehri, Baur, Haripura and Tumaria margins)            
Other (state)            

Table 3B.2 — CN calibration catchments (layout)

Catchment District Area (km²) Dominant HSG and cover Events used Table 3.5 CN Calibrated CN Calibrated ÷ Table 3.5
               
               

Annex 3C — Benchmark test problems for software acceptance

Supports Clauses 3.5, 3.6, 3.8, 3.9, 3.11, 3.12 and 3.16 of Chapter 3.

Purpose. Software not listed in Clause 3.16.1 shall reproduce the results of the five problems below (Clause 3.16.3). Each problem is fully specified and uses only the methods and tables of Chapter 3, so every answer can be checked by hand. The acceptance tolerance is ±5% on each tabulated result, the equivalence threshold of Clause 3.16.2; for closed-form results (Problems 3C-1 to 3C-4), software should agree to the rounding shown. The submittal shall report the software result next to each answer below.

Illustrative — not design values. The inputs (areas, intensities, rainfall depths, slopes and the basin) are chosen for testing only. They are not design data for any site.

Problem 3C-1 — Rational Method peak (Clause 3.5)

Inputs. A 2.0 ha catchment draining to one inlet: 1.2 ha concrete paving and roofs, C = 0.90 (Table 3.2, upper half of 0.80–0.95); 0.8 ha lawns on sandy soil, average slope, C = 0.15 (Table 3.2, upper half of 0.10–0.15). Design AEP 1% (100-yr). Rainfall intensity at Tc, including the climate factor: i = 120 mm/h.

Part (b): a separate 0.5 ha fully paved catchment, C = 0.90, design AEP 1%, i = 150 mm/h.

Table 3C.1 — Problem 3C-1 solution

Step Calculation Result
Composite C (Clause 3.5.4) (1.2 × 0.90 + 0.8 × 0.15) / 2.0 0.60
Frequency factor (Table 3.3) 1% AEP Cf = 1.25
C · Cf (≤ 1.0) 0.60 × 1.25 0.75
Peak flow (Clause 3.5.1) 0.75 × 120 × 2.0 / 360 Q = 0.500 m³/s
Part (b): C · Cf 0.90 × 1.25 = 1.125, capped at 1.0 (Clause 3.5.3) 1.00
Part (b): peak flow 1.00 × 150 × 0.5 / 360 Q = 0.208 m³/s

Problem 3C-2 — Time of concentration by the segment method (Clause 3.6)

Inputs. Pre-development flow path: sheet flow over greenfield, n = 0.15 (Clause 3.6.3), L = 30 m, S = 0.01; P2 (50% AEP 24-hour rainfall, no climate factor) = 80 mm. Shallow concentrated flow, unpaved, L = 200 m, S = 0.01. Channel flow, L = 400 m, bank-full velocity V = 1.0 m/s (given).

Table 3C.2 — Problem 3C-2 solution

Segment Calculation Travel time
Sheet flow (Clause 3.6.2(a)) 0.091 × (0.15 × 30)^0.8 / (80^0.5 × 0.01^0.4) = 0.2138 h 12.83 min
Shallow concentrated (Clause 3.6.2(c)) V = 4.918 × 0.01^0.5 = 0.4918 m/s; 200 / (3,600 × 0.4918) = 0.1130 h 6.78 min
Channel (Clause 3.6.2(d)) 400 / (3,600 × 1.0) = 0.1111 h 6.67 min
Tc (Clause 3.6.1; ≥ 10 min) 12.83 + 6.78 + 6.67 26.27 min
Lag (Clause 3.6.5) 0.6 × 26.27 15.76 min

Problem 3C-3 — SCS-CN runoff depth, AMC and Ia sensitivity (Clause 3.8)

Inputs. Pre-development reference on HSG C: CN = 74 at AMC II (Table 3.5), all pervious. Cumulative rainfall P = 100 mm; second case P = 25 mm.

Table 3C.3 — Problem 3C-3 solution

Case S (mm) Ia (mm) Runoff Q (mm), P = 100 mm Runoff Q (mm), P = 25 mm
(a) AMC II, Ia = 0.2S: S = 25,400 / 74 − 254 89.24 17.85 39.38 0.53
(b) AMC III, Ia = 0.2S: CN(III) = 23 × 74 / (10 + 0.13 × 74) = 86.75 38.80 7.76 64.93 —
(c) AMC II, Ia = 0.05S: S0.05 = 25.4 × 1.33 × (89.24 / 25.4)^1.15 143.31 7.17 36.49 1.97

Runoff is Q = (P − Ia)² / (P − Ia + S). Case (c) gives less runoff than case (a) at 100 mm but more at 25 mm, as Clause 3.8.5 and Figure 3.3 describe.

Problem 3C-4 — Separate vs composite impervious representation, and SCS unit hydrograph peak (Clauses 3.9 and 3.11.2)

Inputs, part (a). A site that is 50% directly connected impervious (CN 98) and 50% open space on HSG B (CNp = 61), AMC II, Ia = 0.2S, P = 25 mm.

Inputs, part (b). A sub-area of A = 2.5 km² with Tc = 1.0 h and computation interval Δt = 0.1 h.

Table 3C.4 — Problem 3C-4 solution

Step Calculation Result
(a) Impervious half (Clause 3.9.2) S = 5.18 mm, Ia = 1.04 mm; Q = 23.96² / (23.96 + 5.18) 19.70 mm
(a) Pervious half S = 162.39 mm, Ia = 32.48 mm > P 0 mm
(a) Area-weighted runoff, separate sub-areas 0.5 × 19.70 + 0.5 × 0 9.85 mm
(a) Composite CN (Clause 3.9.4) 61 + 0.50 × (98 − 61) 79.5
(a) Runoff with composite CN S = 65.50 mm, Ia = 13.10 mm; Q = 11.90² / (11.90 + 65.50) 1.83 mm
(b) Interval check (Clause 3.11.3(a)) 0.133 × 1.0 = 0.133 h ≥ Δt = 0.1 h satisfied
(b) Lag and time to peak (Clause 3.11.2) tL = 0.6 × 1.0 = 0.60 h; tp = 0.1 / 2 + 0.60 tp = 0.65 h
(b) Unit hydrograph peak, Q = 1 mm 0.208 × 2.5 × 1 / 0.65 qp = 0.800 m³/s per mm

Part (a) reproduces the comparison in the commentary to Clause 3.9 (about 9.9 mm vs 1.8 mm).

Problem 3C-5 — Level-pool (modified Puls) storage routing (Clause 3.12.1)

Inputs. A detention basin with vertical sides and plan area 500 m², with the stage–storage–discharge relationship of Table 3C.5. Triangular inflow hydrograph: 0 at t = 0, rising linearly to 0.50 m³/s at t = 30 min, falling linearly to 0 at t = 90 min. Basin empty at t = 0. Routing interval Δt = 10 min (600 s). No tailwater.

Table 3C.5 — Problem 3C-5 stage–storage–discharge relationship

Stage (m) Storage S (m³) Outflow O (m³/s)
0.0 0 0.00
0.5 250 0.05
1.0 500 0.10
1.5 750 0.15
2.0 1,000 0.20
2.5 1,250 0.25

Method. The storage-indication equation is (I1 + I2) + (2S1/Δt − O1) = (2S2/Δt + O2). The table gives O = S / 5,000 (S in m³, O in m³/s), so 2S/Δt + O = 17.667 O and 2S/Δt − O = 15.667 O, and each step is O2 = [(I1 + I2) + 15.667 O1] / 17.667. Software interpolating linearly in Table 3C.5 shall give the same result.

Table 3C.6 — Problem 3C-5 routed outflow

Time (min) Inflow I (m³/s) Outflow O (m³/s) Storage (m³) Stage (m)
0 0.0000 0.0000 0.0 0.000
10 0.1667 0.0094 47.2 0.094
20 0.3333 0.0367 183.3 0.367
30 0.5000 0.0797 398.4 0.797
40 0.4167 0.1226 612.8 1.226
50 0.3333 0.1511 755.7 1.511
60 0.2500 0.1670 835.2 1.670
70 0.1667 0.1717 858.6 1.717
80 0.0833 0.1664 832.1 1.664
90 0.0000 0.1523 761.5 1.523
120 0.0000 0.1062 531.1 1.062
180 0.0000 0.0517 258.3 0.517

Results. Peak outflow 0.172 m³/s at 70 min; peak storage 859 m³; peak stage 1.72 m. The inflow peak of 0.50 m³/s is reduced to 34% of its value.

Table 3C.7 — Benchmark results to be reported by the applicant

Problem Result Benchmark Software result Difference (%) Within ±5%?
3C-1 Q, main case (m³/s) 0.500      
3C-1 Q, part (b) (m³/s) 0.208      
3C-2 Tc (min) 26.27      
3C-3 Q, case (a), P = 100 mm (mm) 39.38      
3C-3 Q, case (b), P = 100 mm (mm) 64.93      
3C-3 Q, case (c), P = 100 mm (mm) 36.49      
3C-3 Q, case (c), P = 25 mm (mm) 1.97      
3C-4 Runoff, separate sub-areas (mm) 9.85      
3C-4 Runoff, composite CN (mm) 1.83      
3C-4 qp (m³/s per mm) 0.800      
3C-5 Peak outflow (m³/s) 0.172      
3C-5 Peak storage (m³) 859      

Annex 3D — Peak rate factor study for flat coastal land

Supports Clauses 3.11.5 and 3.15 of Chapter 3.

Not required in Uttarakhand. Uttarakhand is landlocked and has no flat coastal plain, so no land in the State meets Clause 3.11.5(a), and the standard factor 484 (PRF′ = 0.208) applies to all land (Clause 3.11.5). The terai, the Ganga alluvium and the taal and reservoir margins are flat in places but are not coastal plain; their slow response is represented by storage and backwater (Clauses 3.10.4 and 3.12.4), not by a lower peak rate factor, while the hills, the Doon and the bhabar respond fast. The annex and the layout of Table 3D.1 are kept only so that the annex numbering is unchanged.

Table 3D.1 — Calibrated peak rate factors (layout)

Catchment Area (km²) Mean slope (m/m) Drainage condition Events used Calibrated PRF (US customary) PRF′ (SI) Range of applicability
               
               

Annex 3E — CWC SUH parameters for subzone 1(e) and zone 7, with worked example

Supports Clauses 3.4.3 and 3.11.4 of Chapter 3.

To be prepared. This annex will tabulate, for CWC subzone 1(e) (Upper Indo-Ganga Plains) and zone 7 (Western Himalayas), the regression relationships for the synthetic unit hydrograph parameters, the design storm duration, loss rate, base flow, areal reduction and time distribution, each with its reference to the Flood Estimation Report, and a worked example for one catchment. It needs the two CWC Flood Estimation Reports that cover Uttarakhand, split at the Siwalik front: the Western Himalayas zone 7 report (No. WH/22/1994, November 1994), which names "Uttar Pradesh" because the State did not exist in 1994 and covers the Doon and the hills, including Dehradun, Doiwala, Rishikesh, Mussoorie, Vikasnagar, Nainital, Bhimtal, Almora, Ranikhet, Pithoragarh, Champawat, Tehri, Srinagar, Pauri, Rudraprayag, Gopeshwar, Uttarkashi and Joshimath, but whose relationships are not to be used in its snow-fed catchments; and the Upper Indo-Ganga Plains subzone 1(e) report, approved at the 40th meeting of the Planning and Co-ordination Committee on 23–24 July 1984, whose design-office report number is not on the scanned copy read for this Manual [TBC], and which covers Haridwar, Roorkee, Laksar, Bhagwanpur and the bhabar–terai of Kotdwara, Haldwani, Ramnagar, Kashipur, Rudrapur, Kichha, Sitarganj and Khatima (see the References of Chapter 3); with the zone 7 areal reduction factors for areas above 300 km² and for 24 hours, the 1(e) areal reduction and time-distribution tables, the zone 7 plates for Almora, Pithoragarh, Srinagar and Joshimath, which are not legible on the copy read, the loss rate of the zone 7 worked example, printed as 0.20 cm/h against the 0.5 cm/h the report recommends, and the boundary between the two reports along the Siwalik front, including that at Kathgodam, Haridwar's northern wards and Rishikesh, still to be confirmed on the reports' page images and index maps [TBC], transcribed and checked against the published reports, and a catchment with physiographic parameters measured from survey or a DEM. Until it is published, take all SUH inputs directly from the applicable Flood Estimation Report (Clause 3.11.4(a)), apply the 24-hour design rainfall of Clauses 2.3.3(b) and 2.7.3 with the climate factor of Clause 2.8 (Clause 3.11.4(b)), report the SUH result alongside the HEC-HMS or SWMM result for the existing natural condition (Clause 3.11.4(c)), and, where the hydrograph model gives a lower 1% AEP peak, either justify it by calibration under Clause 3.15 or adopt the SUH peak (Clause 3.11.4(d)).

Table 3E.1 — SUH relationships by subzone (layout)

Parameter Symbol Unit Zone 7 (Western Himalayas) relationship Subzone 1(e) (Upper Indo-Ganga Plains) relationship
Time from centre of unit rainfall to peak tp h tp = 2.498 (L·Lc/S)^0.156 (printed with S, not √S; see the note) tp = 1.858 qp^−1.038
Peak discharge per unit area qp m³/s per km² qp = 1.048 tp^−0.178 qp = 2.030 (L/√S)^−0.649
Width of UH at 50% of peak W50 h W50 = 1.954 (L·Lc/S)^0.099 W50 = 2.217 qp^−0.990
Width of UH at 75% of peak W75 h W75 = 0.972 (L·Lc/S)^0.124 W75 = 1.477 qp^−0.876
Width of rising limb at 50% of peak WR50 h WR50 = 0.189 W50^1.769 WR50 = 0.812 qp^−0.907
Width of rising limb at 75% of peak WR75 h WR75 = 0.419 W75^1.246 WR75 = 0.606 qp^−0.791
Base width of UH TB h TB = 7.845 tp^0.453 TB = 7.744 tp^0.779
Unit duration tr h 1 2
Design storm duration TD h TD = 1.1 tp (it gave the highest peak on all the gauged catchments) TD = 1.1 tp, limited to 24 h
Design loss rate — mm/h 5 (printed "0.5 cm/hr"; the observed modal value of 0.6 cm/h was judged "on higher side", and "Designers can modify this value as per local conditions"); the worked example uses 0.20 cm/h "as recommended in para 3.5", which conflicts with para 3.5 [TBC]; not for snow-fed areas 3.0 (printed "3.0 mm per hour" and, in the worked example, 0.3 cm/h)
Design base flow — m³/s per km² 0.05 (27 of 45 events in the range 0.00–0.10) 0.05 (the average of 126 flood events in the range 0.01–0.09)
Ratio of t-hour to 24-hour rainfall — — 10-yr, from 9 self-recording gauges: 1 h 0.425; 3 h 0.600; 6 h 0.725; 9 h 0.790; 12 h 0.845; 15 h 0.895; 18 h 0.935; 24 h 1.000 50-yr: 1 h 0.340; 2 h 0.475; 3 h 0.560; 4 h 0.607; 5 h 0.647; 6 h 0.680; 9 h 0.770; 12 h 0.840; 15 h 0.890; 18 h 0.930; 24 h 1.000
Time distribution of rainfall — cumulative fraction by hour 3-h storm 0.73, 0.92, 1.00; 6-h storm 0.52, 0.69, 0.82, 0.91, 0.97, 1.00; 12-h storm 0.34, 0.49, 0.60, 0.67, 0.74, 0.81, 0.86, 0.90, 0.94, 0.96, 0.98, 1.00; 24-h storm 0.17, 0.27, 0.36, 0.43, 0.48, 0.53, 0.58, 0.63, 0.67, 0.70, 0.73, 0.76, 0.79, 0.82, 0.84, 0.86, 0.88, 0.90, 0.92, 0.94, 0.96, 0.98, 0.99, 1.00 Average curves of Fig. 12; the worked 12-hour storm puts 58% of the total in the first 2 hours; the 24-hour fractions were not transcribed [TBC]
Conversion of 1-day to 24-hour rainfall — factor 1.15 1.15
Areal reduction factor ARF % of point rainfall Annex 4.2: 50 km², 94.00 at 1 h, 96.40 at 3 h, 97.70 at 6 h, 98.25 at 12 h; 100 km², 89.00, 92.90, 95.40, 96.50; 200 km², 80.75, 86.20, 89.80, 93.50; 300 km², 74.25, 80.00, 86.20, 90.50; the worked example uses 0.926 for 3 hours at 103.6 km²; the 24-hour column and the rows above 300 km² (to 2,000 km²) not read [TBC] Table 6 of the report; at 50 km², 1 h 88, 3 h 92, 6 h 95, 12 h 96, 24 h 98, read by optical character recognition only, and the rows for larger areas not read [TBC]
50-yr 24-hour point rainfall at Uttarakhand towns (100-yr in brackets) — mm Plate 9 (Plate 10), read by eye within about one contour: Dehradun about 280–320 (320–360); Mussoorie and Rajpur about 240–280; Rishikesh about 280–320, on the edge of the plate; Nainital above 440, in a closed cell (above 400 on the 25-yr Plate 8); Mukteshwar and Uttarkashi about 240–280; Tehri about 200–240; Almora, Pithoragarh, Srinagar and Joshimath not legible on the copy read [TBC] Plate 9 (Plate 10), read by eye within about one contour: Haridwar and Roorkee about 280 (a spot value of 311 nearby); Kotdwara about 280–320 (about 320); Haldwani–Kathgodam about 400–440 (440–480), with a "450+" spot just north-west; Ramnagar about 320–360; Kashipur, Rudrapur and Kichha about 280–320 (about 320); Khatima and Tanakpur about 320, with no label nearby [TBC]
Gauged catchments in Uttarakhand — — 1 of the 6 used: the Suswa Nadi at railway bridge 139 on the Laksar–Dehradun line (296.84 km²; L 46.50 km, Lc 20.50 km, S 13.95 m/km; 1966–67); the Bannar Khad at bridge 213 (45.00 km², 1962–66) was listed but not used Not identified in the copy read [TBC]
Catchment area for which the relationships apply A km² 25–1,000; not in snow-fed catchments 25–2,500, for "reasonably free catchments"; for "foothill catchments (steep slopes)" a "suitable increase", by an amount the report does not state
Report reference — — §§3.3–3.6, Annexes 3.1 and 3.2, §4.4.2, Annexes 4.1 and 4.2, worked example (pp. 24–26), Plates 8–10 §3.9 (p. 42), §§3.11–3.12 (p. 57), text table (p. 61), Fig. 12, Table 6, §§6.1–6.3, Plates 9 and 10

Note: relationships as printed in the two CWC reports that cover Uttarakhand (References of Chapter 3), read from scanned copies and checked against the page images except where marked. L is the length of the main stream in km, Lc the length to the point nearest the catchment centroid in km, S the equivalent slope in m/km and A the catchment area in km². Zone 7 relates tp to L·Lc/S, printed without the square root that most subzone reports use, and the printed equations reproduce the report's own unit hydrograph only in that form; 1(e) relates qp to L/√S and derives tp from qp. Each column shall be used only in its own area. Zone 7. The report was written for Jammu and Kashmir, Punjab, Himachal Pradesh and Uttar Pradesh, whose hill districts are now Uttarakhand, over a zone of 322,170 km², of which the Ganga, the Yamuna, the Ramganga and the Sarda make up about 49,600 km². Its unit hydrograph rests on only six catchments of 44–658 km² (five railway bridges and the Sewa hydro-electric project), with 2–5 years of record each in 1962–67 and 45 flood events, all near the southern edge of the zone in Jammu & Kashmir, Punjab, Himachal Pradesh and the Doon: about 1% of the zone. The report itself warns that a design flood computed from these relations is not to be used "without verifying the results on the basis of alternate methods", and that the relations are "not to be utilised for computation of design flood in the snow fed area of the zone". Its only Uttarakhand catchment is the Suswa at bridge 139; for that catchment the printed relationships give L·Lc/S = 68.3, tp ≈ 4.8 h, qp ≈ 0.79 m³/s per km², TB ≈ 16 h and TD ≈ 5 h (NEER's computation; a yardstick, not a design value). The worked example, the Banu Khad at bridge 629 in Himachal Pradesh (103.60 km², L 21.32 km, Lc 11.58 km, S 69.21 m/km), has two errors. It prints tp = 2.5 h, while its own equations give about 3.05 h, with which the printed qp (0.86) and TB (13.0 h) agree; and it applies a loss of 0.20 cm/h, "as recommended in para 3.5", where para 3.5 recommends 0.5 cm/h. With the 50-yr 24-hour point rainfall of 32.00 cm (Plate 9), the 3-hour ratio of 0.600 and an ARF of 0.926, the report gives a 50-yr peak of 1,365.22 m³/s, about 13.2 m³/s per km²; with 0.5 cm/h the same unit hydrograph gives about 1,311 m³/s (NEER's recomputation). This Manual uses 0.5 cm/h and reads tp from the equations [TBC]. The gauged catchments have slopes of 9.9–84 m/km; the urban hill catchments of Nainital, Mussoorie, Almora and the like are far steeper and far smaller than 25 km², and are designed by the methods of Clause 3.4 with the rules for steep ground of the Commentary to Clause 3.7. In the hill sub-areas the SUH applies to the rural raos, gadheras and rivers of 25–1,000 km² that enter the towns, such as the Rispana (about 53–58 km²) and Bindal (about 44 km²) above Dehradun, the Song, the Suswa, the Tons and the Asan in the Doon, the Chandrabhaga at Rishikesh and the Balia Nala below Nainital; the Irrigation Department's floodplain zoning of the Rispana used the CWC subzone SUH with PMP atlas data (affidavit in NGT OA 417/2022). In sub-area UK-F (High Himalaya and snow-fed) the zone 7 SUH does not apply: catchments with snow or glacier cover, such as those above Joshimath, Badrinath, Kedarnath, Gangotri, Harsil and Dharchula, require a site-specific hydrological study, and no design there is complete without a debris-flow and glacial-lake-outburst screening (Chapter 2). Subzone 1(e). The report was derived from 23 gauged catchments (137 bridge-years, 1961–1982), none urban; in Uttarakhand it applies to the rural streams of 25–2,500 km² that enter Haridwar, Roorkee and the towns of the bhabar–terai, such as the Solani, the Ratmau and the Banganga in Haridwar district and the Kichha, the Kalyani, the Dhela and the Bhakra in Udham Singh Nagar, and to the Gaula above Haldwani (617.5 km² at the Gaula barrage) and the Kosi above Ramnagar with the "suitable increase" for foothill catchments, which the designer shall state and justify. Both. Where a city catchment lies within the range, the SUH is computed only as the benchmark of its natural condition (Clause 3.11.4), and the catchment itself is designed by the methods of Clause 3.4 with the design rainfall of Chapter 2. The Ganga at Rishikesh and Haridwar, the Yamuna (7,340 km² at Dakpathar), the Alaknanda and the Bhagirathi are far larger than the catchments of either report and are outside Clause 3.11.4 (Clause 3.4.5); below Tehri, Koteshwar, Dakpathar, the Virbhadra and Bhimgoda barrages and the Gaula, Kosi and Banbasa barrages the flood is set by releases (Chapter 5). The design loss rates, 5 mm/h in zone 7 and 3.0 mm/h in 1(e), are φ-indices fitted to the monsoon floods of whole rural catchments; they are used only in rural SUH runs, are not soil infiltration capacities and are not used to assign HSG (Clause 3.7), in urban SCS-CN or SWMM models, or to size infiltration practices (Chapter 4). The ratios are not to be used to derive intensities for durations shorter than the TD of the SUH (Chapter 2): with the zone 7 ratio of 0.425, the highest 1-hour ratio of any report in this series, the 50-yr 1-hour depth is about 119–136 mm at Dehradun and more than 187 mm at Nainital, against a largest recorded 1-hour fall of 98 mm at Dehradun (14 June 1970) and 79 mm at Nainital (July 1972) (Annex 4.4 of the zone 7 report); with the 1(e) ratio it is about 95 mm at Haridwar and 136–150 mm at Haldwani; Clause 2.3.6 deals with the difference. At 24 hours the opposite holds: Dehradun (487.0 mm on 25 July 1966), Raipur in Dehradun (487.5 mm on 2 August 1959), Rajpur (440.4 mm), Hardwar (495.3 mm on 18 September 1880), Pantnagar (403.9 mm on 19 October 2021), Khatima (405.6 mm) and Mukteshwar (340.8 mm on 19 October 2021) have recorded more than the 100-yr plate values (IMD), so the plate values are a floor under Clause 2.3.3, not a ceiling. Boundary. By NEER's reading of the plates, the boundary between the two reports runs along the Siwalik front: the dashed line of zone 7 Plate 9 passes just south of Dehradun, near bridge 139, so Dehradun, Doiwala, Rishikesh, Mussoorie and Vikasnagar are in zone 7; Haridwar (its northern wards within about 5–10 km of the line) and Roorkee are in 1(e); the line meets the Kumaon hills at Kathgodam, about 7–10 km north of Haldwani, which is in 1(e), with Nainital in zone 7; and subzone 1(f) does not reach the State [TBC]. The report is chosen by the catchment's outfall and the location of most of its area, not by its district. Where a catchment drains across the Siwalik front, or its outfall lies near the line, as at Kathgodam, the northern wards of Haridwar, Rishikesh, Ramnagar and Kotdwara, this Manual requires the SUH to be computed with the parameters of each report and the higher 1% AEP peak to be adopted, unless calibration under Clause 3.15 supports the other.

Table 3E.2 — Worked example outline (layout)

Step Content Clause
1 Catchment area, main stream length, length to centroid and equivalent slope, from survey or DEM 3.11.4(a)
2 SUH parameters from Table 3E.1 and the plotted unit hydrograph 3.11.4(a)
3 Design storm duration, point and areal 24-hour rainfall with climate factor, time distribution 3.11.4(a), (b)
4 Effective rainfall after the design loss rate; convolution with the SUH; base flow added 3.11.4(a)
5 1% AEP peak compared with the HEC-HMS or SWMM peak for the existing natural condition 3.11.4(c), (d)

Form 3-1 — Hydrologic Calculation Summary

Supports Clauses 3.4, 3.6, 3.7, 3.8, 3.10–3.13, 3.15–3.17 of Chapter 3.

Draft form — Uttarakhand Stormwater Design Manual, Draft v1.0. One form per submittal. Attach the documents listed in Section H.

A. Project

Table 3F.1 — Form 3-1: project

Field Entry
A1. Project name and applicant  
A2. Location (village or ward, survey numbers, district)  
A3. Site area (ha) and number of points of comparison (POCs)  
A4. Catchment class: standard (Clause 2.11.2) or flood-sensitive (Clause 2.11.3)  
A5. Design Rainfall Sheet reference (Form 2-1)  

B. Method and software (Clauses 3.4, 3.11, 3.12, 3.16)

Table 3F.2 — Form 3-1: method and software

Field Entry
B1. Purpose of each calculation (conveyance, storage, comparison, catchment study)  
B2. Contributing area for each purpose (ha or km²)  
B3. Method used and the row of Table 3.1 that permits it  
B4. Reason for the choice of method  
B5. Software and version; engine and version for packages built on SWMM or HEC (Clause 3.16.1, 3.16.2)  
B6. For other software: benchmark results of Annex 3C attached (Table 3C.7) and the 5% comparison of Clause 3.16.2  
B7. Runoff transform (Clause 3.11.1)  
B8. Computation interval Δt (h), with 0.133 Tc of the smallest sub-area and the hyetograph time step (Clause 3.11.3(a))  
B9. Storage routing and channel routing methods (Clauses 3.12.1, 3.12.2)  
B10. Dynamic-wave routing required? If yes, which condition of Clause 3.12.4  
B11. CWC SUH benchmark required (25–5,000 km², Clause 3.11.4)? Result reference  
B12. Continuous simulation required (Clause 3.13.1)? Record used and starting tank levels (Clause 3.13.5)  
B13. Calibration required (Clause 3.15.1)? Calibration report reference  

C. Soils and groundwater (Clauses 3.3.3(b), 3.7, 3.10)

Table 3F.3 — Form 3-1: soils and groundwater

Field Entry
C1. HSG source map, scale and lookup used (Clause 3.7.1, Annex 3A) or NEH Part 630, Ch. 7 assignment (Clause 3.7.2)  
C2. Infiltration tests: number, locations, depths, results (Clause 3.7.3)  
C3. Seasonal high water table: depth below ground and source (Clause 3.10.2)  
C4. Areas within 0.6 m assigned HSG D (Clause 3.10.1)  
C5. Disturbed pervious areas and HSG downgrade applied (Clause 3.3.3(b))  

D. Parameters by sub-area and condition (Clauses 3.3, 3.5, 3.8, 3.9; Clause 3.17 item 4)

Table 3F.4 — Form 3-1: parameters by sub-area and condition

Sub-area Condition (pre / post) Area (ha) Impervious: roofs / paved / roads (ha) DCIA (ha) Disconnected (ha) HSG CN, AMC II CN, AMC III (pervious part) C and Cf (if Rational) Tc (min)
                     
                     
                     

E. Time of concentration worksheet (Clause 3.6)

One worksheet per sub-area and condition.

Table 3F.5 — Form 3-1: time of concentration worksheet

Segment Flow type Surface and n (Table 3.4) L (m) S (m/m) P2 (mm) V (m/s) Tt (min)
1 Sheet         —  
2 Shallow concentrated       —    
3 Channel or pipe       —    
Tc (not less than 10 min)  

E1. Is the post-development Tc shorter than the pre-development Tc? If not, explain (Clause 3.6.6): ______

F. Rainfall and losses (Clauses 3.8.4, 3.8.5, 3.11.5, 3.12, 3.3.5)

Table 3F.6 — Form 3-1: rainfall, losses and starting levels

Field Entry
F1. AEPs and durations run; climate factor applied (Chapter 2)  
F2. AMC used for each duration (Clause 3.8.4)  
F3. Ia ratio for design runs; Ia = 0.05S sensitivity run made (Clause 3.8.5)  
F4. Peak rate factor used; if lower than 484, the Annex 3D value and the land it applies to (Clause 3.11.5)  
F5. Starting water level of each tank or waterbody, and its basis (Clauses 3.12.5, 3.13.5)  
F6. Off-site run-on: land use assumed for conveyance and for the comparison (Clause 3.3.5)  
F7. Incidental storage counted? If yes, the authority's acceptance (Clause 3.12.3)  

G. Departures

Table 3F.7 — Form 3-1: departures from Chapter 3

No. Clause departed from Value used in place of the Chapter 3 value Justification
1      
2      

H. Attachments (Clause 3.17)

Table 3F.8 — Form 3-1: attachments

Item Attached (yes / no / not applicable) Reference
H1. Catchment maps, pre- and post-development, with sub-areas, Tc flow paths, POCs and off-site run-on    
H2. HSG map, water-table data and infiltration test results    
H3. Parameter tables (Section D) and Tc worksheets (Section E)    
H4. Design Rainfall Sheet (Form 2-1) and hyetographs    
H5. Hydrograph tables and plots; stage–storage and stage–discharge tables; routed outflows; peak water levels    
H6. Form 3-2 for each POC    
H7. Calibration report (Clause 3.15)    
H8. Native model input and output files (Clause 3.16.4)    

I. Statement by the responsible engineer (Clause 3.17 item 10)

I state that the methods and parameters of Chapter 3 of the Uttarakhand Stormwater Design Manual (Draft v1.0) have been used in this submittal, and that every departure is listed and justified in Section G.

Table 3F.9 — Form 3-1: statement by the responsible engineer

Field Entry
Name  
Qualification and registration number  
Organisation  
Signature  
Date  

Draft form — Uttarakhand Stormwater Design Manual, Draft v1.0.


Form 3-2 — Pre- vs Post-Development Comparison

Supports Clauses 3.8.5, 3.11.5 and 3.14 of Chapter 3.

Draft form — Uttarakhand Stormwater Design Manual, Draft v1.0. One form for each point of comparison (POC). Flows in m³/s, volumes in m³.

A. Point of comparison (Clause 3.14.2)

Table 3F.10 — Form 3-2: point of comparison

Field Entry
A1. POC identifier and location  
A2. Area draining to the POC: site (ha) and off-site run-on (ha)  
A3. Off-site run-on passes through site storage? (Clause 3.14.2(c))  
A4. Catchment class: standard (Clause 2.11.2) or flood-sensitive (Clause 2.11.3)  
A5. Tailwater applied, including joint cases of Clause 2.12 (Clause 3.14.9(c))  
A6. Flood-sensitive only: largest 10% AEP pre-development peak over all durations, the cap of Clause 2.11.3 (Clause 3.14.7)  
A7. Flood-sensitive only: 50% AEP pre-development peak at the pre-development critical duration (Clause 2.11.3)  

B. Peak flows (Clauses 3.14.7–3.14.10)

Limit: standard catchments 0.9 × Q_pre for the same AEP and duration (Clause 3.14.10(a)); flood-sensitive catchments the caps A6 (for 1% AEP) and A7 (for 50% AEP) (Clause 3.14.10(b)).

Table 3F.11 — Form 3-2: peak flows by AEP and duration

AEP Duration (h) AMC Q_pre Q_post, uncontrolled Q_post, routed Limit Met?
50% (2-yr) 1 II          
50% (2-yr) 2 II          
50% (2-yr) 3 II          
50% (2-yr) 6 II          
50% (2-yr) 12 III          
50% (2-yr) 24 III          
50% (2-yr) 48 III          
50% (2-yr) 72 III          
10% (10-yr) 1 II          
10% (10-yr) 2 II          
10% (10-yr) 3 II          
10% (10-yr) 6 II          
10% (10-yr) 12 III          
10% (10-yr) 24 III          
10% (10-yr) 48 III          
10% (10-yr) 72 III          
1% (100-yr) 1 II          
1% (100-yr) 2 II          
1% (100-yr) 3 II          
1% (100-yr) 6 II          
1% (100-yr) 12 III          
1% (100-yr) 24 III          
1% (100-yr) 48 III          
1% (100-yr) 72 III          

C. Volumes and storage (Clauses 3.14.8–3.14.10)

Table 3F.12 — Form 3-2: volumes and storage

AEP Governing duration (h) Runoff volume, pre Runoff volume, post uncontrolled Retention volume Detention storage required Peak water level in storage (m)
50% (2-yr)            
10% (10-yr)            
1% (100-yr)            

C1. Governing duration for storage, and the 24, 48 and 72 h results (Clause 3.14.10): ______

D. Sensitivity runs (Clauses 3.8.5, 3.14.11)

Table 3F.13 — Form 3-2: sensitivity runs

Run Governing storm (AEP, duration) Change in Q_post, routed (%) Change in required storage (%) Retention volume or WQv governing (Clause 3.8.5(c))
Ia = 0.05S        
Standard peak rate factor (only where a lower factor is used)       —

E. Associated checks (Clause 3.14.12)

Table 3F.14 — Form 3-2: associated checks

Check Result Reference in submittal
Drawdown times (Chapter 4)    
Minimum orifice and trash screen (Chapter 4)    
Emergency spillway (Chapter 4)    
Outfall-closed storage check (Chapter 5)    
Downstream analysis (Chapter 5)    

F. Statement by the responsible engineer

I state that this comparison has been made by the procedure of Clause 3.14, with the same design storms in the pre- and post-development runs, and that no runoff has been diverted from one natural catchment to another to meet the criterion (Clause 3.14.2(b)).

Table 3F.15 — Form 3-2: statement by the responsible engineer

Field Entry
Name  
Qualification and registration number  
Signature  
Date  