Chapter 10Submittals, Review, Operation & Maintenance and Enforcement


10.1 Purpose and scope

10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:

  • (a) the submittal stages and their contents (Clauses 10.3–10.4);
  • (b) the compliance calculator (Clause 10.5);
  • (c) professional certification and review (Clauses 10.6–10.7);
  • (d) construction inspection and as-built certification (Clauses 10.8–10.9);
  • (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
  • (f) handover of public assets (Clause 10.14);
  • (g) enforcement (Clause 10.15); and
  • (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).

10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.

Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Uttarakhand the failure is one of missing criteria and of drains that have not kept up with the towns. No document of the Housing Department, the Urban Development Department, T&CP, a Nagar Nigam or a development authority stating a design return period, intensity or runoff coefficient for the storm drains of any town was found; the only stated basis is that of the consultants for ADB's Dehradun drains, 2 years for roadside drains and 5 years for the main channels, with no allowance for climate change (ADB, 2021; Chapter 11). The approval route shapes this chapter. Uttarakhand did not replace the building rules it took from Uttar Pradesh in 2000 with a new code: it still amends the Uttarakhand Building Construction and Development Bye-laws/Regulations 2011 (Amendment 2015), which the Housing Department makes under s.57 of the Uttar Pradesh Urban Planning and Development Act 1973 as applicable to and amended in Uttarakhand, piecemeal, by notifications of 27 September 2022, 13 March 2023, 10 January 2024 and 13 June 2024 among others, of which only that of 10 January 2024 touches water, by keeping filling stations at least 50 m from rivers, nalas, waterbodies, springs and the flood plain and 5 m from a nala; each development authority must adopt every amendment through its board (notification of 10 January 2024). A comprehensive "Amendment 2017" with green-building and climate-resilience provisions was put out for comment by MDDA as a draft in 2018 and has not been seen notified, so it is not cited as law. Building permission is given by the development authority in its area (MDDA for Dehradun, Mussoorie and Rishikesh, HRDA for Haridwar and Roorkee, and the district development authorities formed in 2016–17) or by UHUDA or the local body elsewhere, under the Bye-laws. They already ask for much of what a drainage submittal needs: rainwater harvesting shown on the plan before approval (bye-law 6.5(IV)); a contour plan at 2 m intervals with sections of the site (4.4(IV)(i)); a site plan in the hills showing the landslide-prone areas near the site and, on a sloping site, the diversion of the uphill runoff away from the foundations (4.4(V)); the setbacks of 30 m from rivers and lakes, 10 m from springs and at least 5 m from nalas (4.4(III)); structural and soil certificates for a basement, covering the stability of the ground around it and the water table (5.6(xi)); a sewer-capacity no-objection, or a sewage treatment plant, for premises of more than 1,000 m² (6.4(III)); an external development charge for sewer and drainage; and an inspection at plinth level, or before the basement slab is cast. In a reach notified under the Uttarakhand Flood Plain Zoning Act 2012 no activity may be undertaken in the prohibited (25-year) or restricted (100-year) area without the permission of the Flood Zoning Authority, which is deemed given if not refused in 90 days (s.12(3)); in the restricted area the Rishikesh notification of 2020 asks for a plinth at least 1.00 m above the high flood level and a no-objection from Peyjal Nigam on sewerage; and on the banks of the Ganga in the hills the Housing Department's order of 29 November 2017, revised on 1 June 2023, applies where the Irrigation Department has not notified the floodplain. The Ground Water Act of 2016, which would have let the State enforce rainwater harvesting for recharge, was repealed in 2017, so rainwater harvesting rests on bye-law 6.5 alone. The municipal Acts, the Uttar Pradesh Municipal Corporation Act 1959 and the Uttar Pradesh Municipalities Act 1916 as adapted in Uttarakhand in 2002 (CAG, 2022), vest the public drains in the local body, but their Uttarakhand texts were not read [TBC]. No rule asks for a drainage report, limits peak runoff, requires on-site detention or sets a "zero runoff" condition. Every stormwater item in this chapter is therefore written so that the architect or engineer on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it with the building plan, alongside the contour plan, the runoff-diversion proposal and the rainwater harvesting that the Bye-laws already require, at the plinth-level inspection, at completion, and, in a notified reach, with the permission of the Flood Zoning Authority and the Irrigation Department. This chapter is the process.


10.2 Definitions

Term Meaning in this chapter
Submittal A set of documents lodged with the Authority at one of the stages of Clause 10.3.
Drainage report The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4.
Stormwater facility Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private.
Hold point A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8).
As-built certificate The certificate of Clause 10.9 that the facility was built as approved and performs as designed.
Owner The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset.
O&M plan The operation and maintenance plan of Clause 10.11.
Facility register The public register of facilities of Clause 10.17.

Other terms are defined in Clause 1.4.


10.3 Submittal stages

10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Uttarakhand Building Construction and Development Bye-laws 2011 (Table 10.1):

Table 10.1 — Submittal stages and linked approvals

Stage Submittal When Linked approval
0 Pre-application meeting and Form 1-1 (Applicability Determination) Before the planning permission or layout application None (advisory record)
1 Preliminary drainage report With the planning permission or layout application Planning permission / layout approval
2 Final drainage design Before building permit, or before commencement where the permit is issued with the planning permission Building permit / commencement
3 Construction inspections at hold points During construction None (records filed)
4 As-built certificate and verification tests Before the completion certificate Completion / occupancy certificate
5 Maintenance declaration registered, or handover of public assets Before or with the completion certificate Completion certificate; asset acceptance
6 Annual declarations and inspection reports Every year after completion Continuing compliance

10.3.2 Stage 0 is mandatory for:

  • (a) sites of 2 ha or more;
  • (b) sites in a flood-sensitive catchment;
  • (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
  • (d) sites draining to a tidal outfall or adjoining a waterbody.

For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.

10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.

10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.

10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.

Figure 10.1 — Submittal, review and approval workflow Two columns: applicant stages 0 to 6 on the left, Approving Authority actions and approval gates on the right. Stages 1 and 2 can be returned with comments for resubmittal. Stage 6 repeats every year. Applicant / certifying professional Approving Authority Stage 0 — Pre-application Form 1-1 Applicability Determination Confirms applicability; advises Mandatory: ≥ 2 ha, flood-sensitive, waterbody Stage 1 — Preliminary drainage report Forms 2-1, 10-1, 10-2, 10-3 comments Check 5 days; review 15 (resubmit 10) → Planning permission / layout Stage 2 — Final drainage design Models, GIS, draft O&M plan, Form 10-3 comments Review 15 working days (resubmit 10) → Building permit / commencement Stage 3 — Construction Hold-point inspections, Form 10-4 Notified of key hold points (3 working days); may attend Stage 4 — As-built certification Survey, re-run, drawdown tests, Form 10-5 Accepts as-built certificate → Completion certificate Stage 5 — Maintenance declaration Form 10-6, or handover with Form 10-8 Enters facility / asset register → Public asset accepted Stage 6 — Every year, pre-monsoon Form 10-7 annual declaration Inspects; enforces (Clause 10.15) Publishes register (Clause 10.17) yearly Approval gate (accent text) Returned with comments; resubmit Periods in working days (Clause 10.7)

Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.

Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the Bye-laws 2011 steps an Uttarakhand applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.


10.4 Required contents and checklists

10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:

  • (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
  • (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
  • (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
  • (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
  • (e) the pre-development condition and hydrologic method (Chapter 3);
  • (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
  • (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
  • (h) the downstream extent and tailwater case (Chapter 5);
  • (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
  • (j) the land reserved for facilities and maintenance access (Clause 10.13).

10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:

  • (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
  • (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
  • (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
  • (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
  • (e) construction drawings, details and specifications of every facility;
  • (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
  • (g) the hold-point schedule (Clause 10.8);
  • (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
  • (i) the model input files and the GIS data of Clause 10.4.4; and
  • (j) the certificates of Clause 10.6.

10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.

10.4.4 Digital submittal.

  • (a) Reports and drawings shall be submitted as searchable PDF.
  • (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
  • (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (44N east of 78° E, which includes Dehradun city, Mussoorie, Rishikesh, Haridwar and all of Kumaon, and 43N west of 78° E, which includes Roorkee, Vikasnagar, Herbertpur, Chakrata, Selaqui and Prem Nagar; the meridian of 78° E passes about 2.7 km west of the centre of Dehradun, and a project that crosses it uses one zone for all its layers and states which), with attributes as listed in Annex 10B.
  • (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the CWC gauges on the receiving rivers, of the Irrigation Department's barrage, reservoir and canal levels, of the dam and barrage levels of THDC India Ltd and UJVN Ltd, of the PWD gauge at Tallital for Naini lake (read in feet on its own zero) and of the flood lines of notifications under the Uttarakhand Flood Plain Zoning Act 2012 used in Chapter 5 shall be stated.

10.4.5 Summary of forms used in submittals (Table 10.2):

Table 10.2 — Forms used in submittals

Form Title Stage
1-1 Applicability Determination 0 or 1
1-2 Variance / Waiver Request 1
2-1 Design Rainfall Sheet 1, 2
10-1 Drainage Report Checklist 1, 2
10-2 Compliance Calculator Summary 1, 2, 4
10-3 Professional Design Certificate 1, 2
10-4 Hold-Point Inspection Record 3
10-5 As-built Certificate 4
10-6 Maintenance Declaration 5
10-7 Annual Maintenance Declaration and Inspection Report 6
10-8 Asset Handover Certificate 5

Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Uttarakhand has no notified design return period or design storm for its urban drains. The only stated basis is in ADB's climate risk assessment for the Uttarakhand Integrated and Resilient Urban Development Project (2021), which quotes the national consultants for the Dehradun drains: "a storm frequency of once in 2 years" for roadside drains in residential areas, "once in 5 years" for the primary and secondary channels, a minimum drain of 250 mm × 250 mm, velocities of 0.6–3.0 m/s and outfall inverts above the high flood level of the receiving water; it adds that the designs "do not include an allowance for climate change" and recommends drains that carry "10-20% more flow" (ADB, 2021). It is a project's basis for one city, not a State standard, and this Manual supersedes it. The integrated drainage works of Dehradun Smart City Ltd were built without the storm-water reuse its proposal promised (CAG, 2025), the drainage master plans that the Irrigation Department is preparing for Haldwani and the Kumaon towns have been reported without a design storm (as reported), and no design basis was found for the drains of Haridwar, Rishikesh, Roorkee, Rudrapur, Kashipur or the hill towns. The rainfall studies do not supply one either: the Dehradun panel of IMD's national IDF study (Das et al., 2022) repeats a generic curve and is not Dehradun data, and the regional equation of Ram Babu, Dhyani and Nirmal Kumar (2006) gives a 2-year 24-hour depth at Dehradun of about 63 mm against about 152 mm from the station record (ADB, 2021), and is not used. The bursts on record, 98 mm in an hour, 143 mm in 3 hours and 189 mm in 6 hours at the Dehradun self-recording gauge (1970) and 100 mm in an hour at Uttarkashi (1979), and the 24-hour records, 487.0 mm at Dehradun on 25 July 1966 (IMD), exceed what the drains were built for. The State's design values are therefore those of the CWC Flood Estimation Reports for subzone 1(e) in the plains and zone 7 (Western Himalayas) in the Doon and the hills, with the interim provisions of Chapter 2, and each submission must state its own design basis. Form 2-1 and Form 10-2 ensure that every design states its inputs.


10.5 Compliance calculator

10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:

  • (a) applies the applicability tests of Clause 1.5;
  • (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
  • (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
  • (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
  • (e) on alternative S-2, gives the permissible site discharge for each AEP; and
  • (f) produces the Compliance Calculator Summary (Form 10-2).

10.5.2 Use.

  • (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
  • (b) On the design-aid route, the calculator may be the only storage calculation.
  • (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.

10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.

10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.

Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). An Uttarakhand calculator serves Tier B authorities in particular, where it may be the whole calculation.


10.6 Professional certification

10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or T&CP:

  • (a) Tier A sites of 1 ha or more;
  • (b) any site in a flood-sensitive catchment;
  • (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
  • (d) any pumped facility, tide gate or regional facility.

10.6.2 Empanelment criteria shall be issued by T&CP and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.

10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:

  • (a) the design complies with this Manual, except for variances listed and approved;
  • (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
  • (c) the models submitted reproduce the results reported.

10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.

10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.

Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the Bye-laws 2011 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.


10.7 Review procedure and timelines

10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.

10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:

  • (a) 15 working days of acceptance for a first submittal; and
  • (b) 10 working days of acceptance for a resubmittal.

10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.

10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the T&CP list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.

10.7.5 Concurrent clearances. Where the permission of the Flood Zoning Authority for any activity in the prohibited or restricted area of a reach notified under the Uttarakhand Flood Plain Zoning Act 2012 (s.12(3)), the approval of the Irrigation Department for a work on, or a discharge to, one of its rivers, embankments, barrages, reservoirs or canals, among them the Gaula barrage and the Baur, Haripura and Tumaria reservoirs, the consent of THDC India Ltd or UJVN Ltd for a work that drains to Tehri, Koteshwar or the Dakpathar or Asan barrage, the conditions of the Housing Department order of 2017 (revised 2023) for the banks of the Ganga in the hills, the permission of the Municipal Commissioner or Executive Officer to connect to a municipal drain or to build over one (Uttar Pradesh Municipal Corporation Act 1959 and Uttar Pradesh Municipalities Act 1916, as adapted in Uttarakhand, whose drain chapters were not read [TBC]), the no-objection of Peyjal Nigam on sewerage that bye-law 6.4(III), a floodplain notification or that order requires, the views of the Lake Development Authority, Nainital, and of the custodian of the Tallital sluices for a work that drains to Naini lake, the views or permission of the Uttarakhand State Wetland Authority or the Forest Department for a work in or next to a notified wetland, the Asan Conservation Reserve or a river bed outside municipal limits, which the High Court has held to be forest land, the consent of PWD, NHAI or NHIDCL for a discharge to a side drain, catch-water drain or culvert of one of their roads, the consent of the body that owns or runs the receiving drain where that body is not the Authority (for example UUSDA or Dehradun Smart City Ltd until its drains are handed over), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.

10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.

10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.

Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.


10.8 Construction inspection

10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:

  • (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
  • (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
  • (c) the infiltration tests of Clause 10.9.3;
  • (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
  • (e) pumps and controls, at commissioning.

10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.

10.8.3 Protection during construction.

  • (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
  • (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
  • (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.

Figure 10.2 — Construction hold points from approval to handover Vertical timeline from Stage 2 approval through construction, verification tests and as-built certification to the maintenance declaration or asset handover. Diamonds mark hold points (a) to (e) of Clause 10.8.1; each step shows the form used. Construction hold points: approval to as-built and handover (not to scale in time) Hold point: work stops until inspected and recorded Other required step Stage 2 Approval Stage 3 Construction Stage 4 Tests and as-built Stage 5 Declaration or handover Final design approved; hold-point schedule set Schedule of hold points approved with the design (Cl. 10.4.2(g), 10.8.1) Form 10-4 (schedule) Protect retention and infiltration areas Fenced off from traffic and stockpiles (Cl. 10.8.3(a)) (a) Excavated base of each facility Retention, infiltration, detention: before media, liner or structure Form 10-4 3-day notice * (b) Outlet structure, orifice, trash screen Before backfill, or before the facility is first allowed to fill Form 10-4 3-day notice * (d) Outfall, flap or tide gate, non-return valve Before the downstream connection is made Form 10-4 (e) Pumps and controls At commissioning Form 10-4 Area stabilised; temporary sediment removed Infiltration not in service until stabilised (Cl. 10.8.3(b), (c)) (c) Verification tests Infiltration retention empties within 72 h; pumps at duty point; gates open and seal (Cl. 10.9.3) Form 10-4 As-built survey and re-run; certificate accepted Licensed surveyor; calculator and model re-run; then completion certificate (Cl. 10.9) Forms 10-5, 10-2 Private facility: maintenance declaration Registered to run with the land; owner and successors bound (Cl. 10.10) Form 10-6 Public asset: handover to the ULB Cleaned, inspected inside, land or easement transferred; defects liability for at least one full monsoon season (Cl. 10.14) Form 10-8 * Notice: for sites under Clause 10.6.1 the Authority is given at least 3 working days’ notice of hold points (a) and (b), and may attend. Every hold point is inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs (Cl. 10.8.2).

Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.

Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.


10.9 As-built certification

10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:

  • (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
  • (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
  • (c) the completed hold-point records (Form 10-4); and
  • (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).

10.9.2 Acceptance. The as-built facility is accepted where:

  • (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
  • (b) the outlet dimensions and inverts match the approved design; and
  • (c) the re-run shows compliance with every criterion of Chapters 4 and 5.

Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.

10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.

10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.

Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.


10.10 Maintenance declarations and covenants

10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:

  • (a) identify each facility, its location and the approved O&M plan;
  • (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
  • (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
  • (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
  • (e) be registered so that it runs with the land and is disclosed to purchasers.

10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.

10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 May each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.

10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.

Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Uttarakhand because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 May date is set by this Manual to fall before the south-west monsoon (June–September), when most Uttarakhand extreme rainfall occurs.


10.11 O&M plans

10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:

  • (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
  • (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
  • (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
  • (d) inspection checklists matching Form 10-7;
  • (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
  • (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
  • (g) safety measures for confined spaces, deep water and public access;
  • (h) access routes and equipment needed (Clause 10.13);
  • (i) an annual cost estimate and who pays it; and
  • (j) the records to be kept, and for how long.

10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.

Commentary. Uttarakhand has no dated State order fixing pre-monsoon desilting: the Chief Minister's direction that drains and canals be cleaned before 15 June (2024), a minister's call to clean them "at least twice before the monsoon" and the setting up of flood posts in every district before 15 June are known from the press, and USDMA's standard operating procedure, which is reported to fix a "monsoon session" of 5 June to 15 September, could not be read. The drains are run by several hands: the Nagar Nigams, Nagar Palika Parishads and Nagar Panchayats for the municipal drains; PWD for road drains, which in Dehradun's Paltan Bazaar were split between it and Dehradun Smart City Ltd, with electricity poles left standing in the drain line (CAG, 2025); UUSDA and Dehradun Smart City Ltd for the drains they build until they are handed over; Peyjal Nigam for the interception and diversion structures on the raos and Jal Sansthan for their operation; and the Irrigation Department for the rivers, flood works and barrages. The gates that matter most are run by rules made for other purposes: the Tallital sluices of Naini lake by the Hill Slide Committee's rules of 1927, which limit their opening to protect the Balia ravine, with the operation reported moved from PWD to the Irrigation Department in 2018; and Tehri, whose moderation of the flood of June 2013 was called a matter of chance, not design (as reported). No operating rule for any sluice, flap gate, interception structure or pumping station in an Uttarakhand town, linking it to a river stage, a barrage release or a rainfall warning, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.


10.12 Inspection frequencies

10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:

Table 10.3 — Minimum owner inspection frequencies

Facility type Routine Pre-monsoon (by 31 May) After a heavy-rainfall event
Retention / infiltration (soakaways, trenches, bioretention, permeable paving) Every 6 months Yes Yes
Surface detention basin or multi-use open space area Every 6 months Yes Yes
Underground or podium detention tank, gravity outlet Every 6 months Yes Yes
Pumped detention, pumps and controls Monthly test run Yes, with full duty test Yes
Flap / tide gate, non-return valve Every 3 months Yes, with seal test Yes
Gross pollutant trap / first-flush device Every 3 months Yes Yes
Private drains and inlets Every 6 months Yes —

A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Uttarakhand, the pre-monsoon inspection of sluices, flap gates, non-return valves, debris racks, sediment traps, debris basins, culvert inlets and pumped facilities, including the sluices and gates on outfalls to barrage ponds, reservoirs and taals and on outfalls that the Ganga, the Solani, the Song, the Gaula, the Kosi or the Sarda can close, with the desilting and the clearance of boulders and debris from every drain, inlet, rack, trap, basin and culvert and the pump duty and gate seal tests, shall be completed by 31 May; inlets, trash and debris racks, culverts, outfall gates and pumped facilities, with their standby generators, shall be certified ready by 15 June, before the normal onset of 20 June at Dehradun, with every gate on an outfall to a river, barrage pond or taal operated through its full travel. Pumps, their standby power and the gates shall then be kept on monsoon standby, with the monthly test run, until 31 October, after the normal withdrawal of 25 September to 1 October, because the storms of 9 October 1956 and 18–19 October 2021 were among the largest on record in Kumaon, and at an outfall to a river regulated by a dam or barrage upstream until the releases have ended and the river at the governing gauge has fallen below its danger level where one is published, if that is later. In the hill area of bye-law 2.3 of the Bye-laws 2011, every public drain, inlet, debris rack, sediment trap, debris basin and culvert shall be cleared a second time, of the sediment and debris of the monsoon, by 15 October. In towns above about 1,500 m, inlets, gratings, catch-water drains and culvert entrances shall be kept clear of snow and ice from December to March, and checked after every snowfall and every winter storm.

10.12.2 Authority inspections. The Authority shall inspect:

  • (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
  • (b) a random sample of at least 10% of other facilities each year.

10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).

Figure 10.3 — Maintenance cycle and responsibility A one-year strip from January to December with the south-west monsoon (late June to late September) shaded, the onset period from 20 to 28 June and the withdrawal period from 25 September to 1 October shaded more lightly, and October marked as a month of late storms. Lanes show routine inspections; desilting and the clearance of boulders and debris with the pre-monsoon inspection and the Form 10-7 declaration by 31 May; inlets, debris racks, culverts, gates and pumps certified ready by 15 June; pumps and gates on standby to 31 October; a second debris clearance in hill towns by 15 October; inlets kept clear of snow and ice from December to March in towns above about 1,500 m; inspections after heavy rainfall; and Authority inspections. Boxes below show who is responsible: the owner, the ULB and the Authority. Maintenance cycle and responsibility (Clauses 10.10–10.12, 10.14) Oct storms South-west monsoon Onset End Winter: snow above ≈1,500 m Snow Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 31 May 15 Jun 15 Oct 31 Oct Routine Monthly: pump test run (continues through the standby period) Every 3 months: gates, valves, GPTs Every 6 months: retention, detention, drains Pre-monsoon readiness, standby By 31 May: desilting and clearance of boulders and debris, pump and gate tests. By 15 Jun: inlets, racks, culverts, gates and pumps ready. To 31 Oct: standby. Hill towns: second clearance by 15 Oct; above ≈1,500 m, snow and ice Dec–Mar After heavy rain After each day at or above IMD “heavy rainfall”, or a district red alert (in any month, including October and winter storms) Annual declaration Form 10-7 Form 10-7 lodged by 31 May: Tier A facilities; pumped, gate and regional facilities anywhere Authority Every 2 years (yearly if flood-sensitive) for sites ≥ 1,000 m² or Cl. 10.6.1(c), (d); 10% sample of others → register (Cl. 10.17) Who is responsible Owner — private facility Maintenance declaration, Form 10-6; binds successors in title (Cl. 10.10.1) Layouts and apartments: the association; the developer until it accepts (Cl. 10.10.2) Inspects; lodges Form 10-7 ULB — handed-over public asset Accepted with Form 10-8 (Cl. 10.14) O&M plan in the asset register, funded in the annual budget (Cl. 10.11.2) Developer liable for defects and routine maintenance, ≥ one monsoon to 31 Oct (10.14.2) Authority Inspects and records results in the facility register (Cl. 10.12.2–10.12.3) Enforces: notice, penalty, works in default with cost recovered (Cl. 10.15) Publishes the register (Cl. 10.17) Tick positions are illustrative; only 31 May, 15 June, 15 October (hill towns) and 31 October are fixed. Normal onset 20 June (Dehradun) to 28 June (Roorkee); normal withdrawal 25 September (Roorkee) to 1 October (State) (IMD). Late storms: 9 Oct 1956, 18–19 Oct 2021.

Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 May) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the south-west monsoon (June–September); tick positions within the year are illustrative.

Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 31 May deadline is set by this Manual for the onset of the south-west monsoon in the second half of June: the new normal onset is 20 June at Dehradun and 28 June at Roorkee, and the monsoon covers the State by about 30 June (IMD, 1961–2019 normals); it covered the whole State on 28 June in 2024 and 24 June in 2025 (IMD). Large falls come in June and before it: 350.5 mm at Ranikhet on 16 June 1970, 98 mm in an hour at the Dehradun self-recording gauge in June 1970, the storm of 15–17 June 2013 that destroyed Kedarnath, and 208.3 mm at Nainital on 31 May 1956 (IMD; WIHG). No dated State or municipal order fixing a deadline for desilting was found, only a direction to clean drains before 15 June and a monsoon period of 5 June to 15 September in USDMA's procedure, both known from the press; this Manual takes 31 May for desilting and debris clearance, the pre-monsoon inspection and the annual declaration. NDMA (2010) sets 31 March for pre-monsoon desilting nationally; this Manual allows until 31 May so that dry-season work can be finished. Inlets, racks, culverts, gates and pumps must in addition be certified ready by 15 June, before the earliest normal onset. The normal withdrawal is 25 September at Roorkee and 27 September at Dehradun, and the State is clear by about 1 October (IMD; the Meteorological Centre Dehradun gives 30 September), but October brings the largest storms of Kumaon, on 9 October 1956 and on 18–19 October 2021, when 403.9 mm fell at Pantnagar and 340.8 mm at Mukteshwar in 24 hours (IMD, as reported), and 315.0 mm fell at Kashipur on 2 October 1954 and 291.0 mm at Ramnagar on 14 October 1985 (IMD); pumps and gates are therefore kept on standby to 31 October (Figure 10.3). Hill drains fill with sediment and debris during the season, so in the hill area a second clearance is made by 15 October, the date on which the sluices of Naini lake are sealed. Winter storms of western disturbances bring snow above about 1,500 m and falls of 100–200 mm in a day, 192.0 mm at Mukhim in February 1979 and 210.0 mm at Naitwar in February 1986 (IMD), so inlets in the higher towns are kept clear of snow and ice from December to March. The post-event inspections of Table 10.3 cover storms at any time of year.


10.13 Maintenance access

10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.

10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.

10.13.3 Underground facilities. Tanks shall have:

  • (a) an access opening over the inlet, the outlet and each chamber;
  • (b) fixed ladders or steps, and ventilation for confined-space entry;
  • (c) a sump or low point for sediment removal; and
  • (d) headroom sufficient for manual cleaning.

10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.

10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.

Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Uttarakhand cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.


10.14 Handover of public assets to the ULB

10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:

  • (a) the as-built certificate (Clause 10.9) has been accepted;
  • (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
  • (c) the land, or an easement over it, has been transferred to the ULB;
  • (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
  • (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.

10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 15 June to 31 October, after handover. The ULB may hold a security deposit for this period.

10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.

10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.

Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Uttarakhand drainage show up only in the first SW monsoon.


10.15 Enforcement

10.15.1 Offences. The following are contraventions of this Manual:

  • (a) building without an approved drainage design where one is required;
  • (b) building a facility other than as approved;
  • (c) removing, filling, covering, reducing or changing the use of a facility without approval;
  • (d) failing to maintain a facility, or to submit Form 10-7;
  • (e) a sewage connection to a storm drain;
  • (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
  • (g) obstructing a natural drainage path or major-system flow path; and
  • (h) false or negligent certification.

10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):

Table 10.4 — Graduated enforcement response

Step Action
1 Written notice stating the contravention, the clause breached, the remedy and a compliance period.
2 Stop-work order, or withholding of the completion certificate, for development not yet complete.
3 Penalty under the applicable Act or rules.
4 Works in default by the Authority, with the cost recovered from the owner.
5 Disconnection of the private drain connection to the public system, where this causes no hazard to others.
6 Report of the certifying professional to the registering authority, and suspension from the empanelled list.

10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.

10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.

10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.

Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Uttarakhand Building Construction and Development Bye-laws 2011 are made and from the municipal Acts. The graduated steps are set by this Manual. In Uttarakhand the courts and the National Green Tribunal have become the working regulators of the raos, lakes and floodplains. The High Court, on a petition against encroachment on "water bodies and khalas/storm water drains" in the Rajpur area of the Doon, recorded a survey of 37.93 ha of encroached river bed in Dehradun tehsil and 57.4 ha in Vikasnagar, held the river beds outside municipal limits to be forest land, made the Municipal Commissioner personally responsible for removal within them and asked for weekly reports with photographs (Urmila Thapa v. State, WPPIL 58/2019, August 2022); it has heard the Gaula at Haldwani (Ravi Shankar Joshi v. State, WPPIL 178/2013), stopped construction on the Sukhatal lakebed that recharges Naini lake (2022, as reported) and upheld the relocation of families living in the dry bed of the Rispana as rehabilitation from flash floods (Rajeshwari Yadav Gupta v. State, WPMS 739/2026, 1 April 2026). On the Rispana the Tribunal directed the Chief Secretary to remove encroachments from its floodplain (16 December 2024), an order the Supreme Court held in abeyance (10 February 2025), and on 18 August 2025 recorded 89 encroachments on Nagar Nigam land and 413 on MDDA's, most of them older than 11 March 2016, and the final floodplain notification of 5 May 2025 (OA 417/2022); NMCG has since counted 330 structures in the river's 1-in-5-year flood zone and issued notices under the Environment (Protection) Act (2026). The statutes carry limited powers: the Flood Plain Zoning Act fines a breach up to ₹500 (s.13) but lets the Flood Zoning Authority order an unauthorised obstruction removed at the owner's cost (s.24), and the Uttarakhand Special Provisions for Urban Local Bodies and Authorities Act 2018 bars the eviction of settlements that existed before 11 March 2016, a moratorium extended in 2025 (as reported in the High Court's judgment of 2026). Rainwater harvesting has been enforced case by case, as when MDDA ordered the systems of residential projects put right within a week and recharge pits built where approved plans showed systems that were never built (2024, as reported). This shows that a rule without routine enforcement does little, and that where the State has not drawn a line on the ground the courts and the Tribunal have. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.


10.16 Monitoring and post-event review

10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.

10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:

  • (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
  • (b) the level of the receiving river (the Ganga at Haridwar or Rishikesh, the Song at Satyanarayan, the Solani at Roorkee, the Gaula at Kathgodam, the Kosi at Ramnagar, the Sarda at Banbasa, or the Alaknanda, the Bhagirathi or the Mandakini at the CWC site nearest a valley town) or of the receiving barrage pond, reservoir or taal, with the level of Naini lake on the Tallital gauge and the openings of its sluices, and, where it is gauged, at the outfall, each on a named datum, with any reading of a local gauge kept apart from the CWC levels; for an ungauged rao or gadhera, the flood marks surveyed after the event and the debris and boulders deposited at crossings; the state of every sluice, flap gate, debris rack, sediment trap, debris basin, interception and diversion structure and pumping station on the outfall and on the drain upstream of it, with the volume of debris removed from each, the hours each pump ran and any loss of power; and the gate openings and releases of any dam or barrage that sets the receiving level, such as Tehri and Koteshwar, the Pashulok and Bhimgoda barrages, the Dakpathar and Asan barrages, the Gaula barrage, the Kosi barrage at Ramnagar or the Banbasa barrage;
  • (c) flooded locations, depths and durations, with flood marks surveyed where possible;
  • (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
  • (e) recommended actions.

10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), USDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.

10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.

Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Uttarakhand's disasters have been studied more than its town floods. The Kedarnath disaster of June 2013 was examined by scientists, who recorded 325 mm in 24 hours at the Chorabari glacier camp before the lake above Kedarnath emptied in minutes on 17 June (Dobhal et al., 2013), while Dehradun recorded 370.2 mm on 17 June (IMD); the rock and ice avalanche at Raini on 7 February 2021, which turned into a debris flow without any rain (Shugar et al., 2021), and the subsidence of Joshimath in 2023, in which experts named poor drainage and blocked water paths among the causes (as reported), were reviewed by national institutes whose reports were not found. The CAG found that 508 flood-protection works over 74 km were damaged in 2013, that only 45 of the 77 sanctioned had been completed, and that there was no third-party check of their quality (Report No. 2 of 2018). The town floods have no such record. On 18–19 October 2021 Pantnagar, Nainital and Mukteshwar broke their 24-hour records, Naini lake overflowed and the approach to the Gaula bridge at Haldwani collapsed (as reported); on 14 August 2023 Dehradun recorded 175.1 mm (IMD); and on 15–16 September 2025 Sahastradhara recorded 264 mm in 24 hours, which IMD said was not a cloudburst, and the raos of Dehradun carried away bridges and culverts and damaged 83 interception structures (as reported). No review of any flood event in an Uttarakhand town, and no record of flood extents, depths or durations kept by any Nagar Nigam, development authority or USDMA, was found, and final tolls for the events of 2021 and 2025 were not published. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.


10.17 Data publication

10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:

  • (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
  • (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
  • (c) the register of variances and waivers (Clause 1.10);
  • (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
  • (e) enforcement actions (Clause 10.15.5); and
  • (f) event reports and post-event reviews (Clause 10.16).

10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.

10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.

10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.

Commentary. Transparency is a design criterion in its own right here. Some of Uttarakhand's drainage records are public: the compiled Bye-laws 2011 (labelled a draft compilation on MDDA's website) and the amendment notifications on UHUDA's; the Unified Zoning Regulations 2025; the Flood Plain Zoning Act 2012 and the Irrigation Department's status of floodplain zoning, filed with the National Green Tribunal; the O&M manuals of the Dakpathar and Asan barrages (UJVN Ltd) and the Irrigation Department's sheets for the Gaula barrage and the Baur, Haripura and Tumaria reservoirs; ADB's project documents for the Dehradun drains; the CAG's audits; IMD's Climate of Uttarakhand and the monsoon reports of the Meteorological Centre Dehradun; NIH's water balance of Naini lake; and the State Wetland Authority's status report on wetlands. Much else could not be found in the public domain: the Bye-laws as gazetted and the 2015 notification; the Uttarakhand texts of the drain chapters of the municipal Acts; the Flood Plain Zoning (Amendment) Act 2024, the Rules approved in 2026 and the Rispana notification of 2025; the drainage clauses of any master plan; the design basis of any storm drain, including the Irrigation Department's master plans for Haldwani and the Kumaon towns; CWC's site sheets and gauge datums; the datum of the Naini lake gauge; USDMA's operating procedures; the operating rules of the State's dams, barrages and sluices; and an inventory of the gates, racks, interception structures and pumping stations of any town. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.


10.18 Review of this chapter

10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.


References (chapter)

Annexes and forms

Annex / Form Content
10A Compliance calculator and user guide
10B GIS data specification and attribute schema
10C Maintenance access dimensions
10D Model O&M plans by facility type
10E Empanelment criteria for Stormwater Design Professionals and reviewers
Form 10-1 Drainage Report Checklist
Form 10-2 Compliance Calculator Summary
Form 10-3 Professional Design Certificate
Form 10-4 Hold-Point Inspection Record
Form 10-5 As-built Certificate
Form 10-6 Maintenance Declaration
Form 10-7 Annual Maintenance Declaration and Inspection Report
Form 10-8 Asset Handover Certificate
Form 2-1 Design Rainfall Sheet (Chapter 2)