Draft v1.0 prepared by NEER. Not adopted by the Government of Uttarakhand or any authority or local body, and has no legal force. About this draft

Chapter 11Basin and City Stormwater Master Plans


11.1 Purpose and scope

11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.

11.1.2 A BSMP shall:

  • (a) map flood hazard for the basin under existing and future conditions;
  • (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
  • (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
  • (d) reserve land for regional storage, taal and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
  • (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
  • (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).

11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.

Commentary. Uttarakhand's towns have drainage projects and plans, but no published storm-drainage master plan with a design storm. In Dehradun, ADB's Uttarakhand Integrated and Resilient Urban Development Project is building at least 117 km of storm drains "factoring potential climate risks", with outfalls to the Bindal and to the Harrawala, Nakraunda, Kaunwala and Natthanpur nalas whose inverts are to stand above the high flood level of the receiving water, but its stated basis is a 2-year storm for roadside drains and a 5-year storm for the main channels, with no allowance for climate change (ADB, 2021–22); that is practice, and this Manual supersedes it. Dehradun Smart City Ltd's integrated drainage work, of about ₹17 crore, built new drains without the storm-water reuse its proposal had promised (CAG, 2025). The Rispana and Bindal are being "rejuvenated" piecemeal: 187 of the 208 drains reaching the Rispana have been intercepted and diverted to sewage treatment plants (Peyjal Nigam, 2025), the Rispana's floodplain was finally notified on 5 May 2025, and an elevated road of about 26 km is proposed along the two rivers, whose piers the cabinet has allowed in their flood zones (as reported). In Kumaon the Irrigation Department, not the local bodies, is preparing drainage master plans: a committee under the Kumaon Commissioner endorsed plans for seven towns, among them Bageshwar, Pithoragarh, Tanakpur and Banbasa, in April 2026, and Haldwani's plan, of about ₹1,003 crore, with a first phase approved in principle, lines the Rakasia and Kalasia nalas and adds pumping stations in low-lying areas, within a Kumaon-wide programme of about ₹3,394 crore for 15 towns (as reported, April and August 2026); no design storm for them has been published. The Haridwar–Roorkee master plan was reported in February 2026 to await the disposal of objections, and the works for the Kumbh of 2027 include drainage without a storm-drainage plan. No published document sets a design return period for the storm-drain network of any Uttarakhand town. This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by the Housing Department, the Urban Development Department, T&CP, UHUDA, MDDA, HRDA, any Nagar Nigam, the Irrigation Department or any other body. A site-level manual cannot fix basin-level problems: lost tank storage, raos and gadheras that carry boulders and debris onto the towns built on their fans and terraces, river beds and floodplains built over, as along the Rispana, where 330 structures were counted in its 1-in-5-year flood zone (NMCG, 2026), drains that end in rivers held high by barrages or in Naini lake, raos that carry sewage through interception structures that floods break, and single drains split between a Nagar Nigam, a development authority, PWD, Peyjal Nigam and the Irrigation Department, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:

  • Denver's Mile High Flood District prepares major drainageway master plans that set regional facilities and release rates.
  • The Kansas City APWA criteria rest on regional watershed studies (MARC).
  • England's Surface Water Management Plans (Defra, Surface Water Management Plan Technical Guidance, 2010) set a phased method of preparation, risk assessment, options and implementation.
  • Malaysia's MSMA requires drainage master plans for urban areas.

This chapter adapts that method to Uttarakhand, the first mountain State in the series: to towns in three belts, the terai and Ganga plain of Haridwar, Roorkee, Rudrapur and Khatima, whose flat drains outfall to rivers held high by floods and barrages; the Doon and the bhabar fans of Dehradun, Rishikesh, Haldwani, Ramnagar and Kotdwar, crossed by raos and gadheras that are dry most of the year and carry boulders in flood; and the hill towns, Nainital, Mussoorie, Almora, Pithoragarh, Srinagar, Uttarkashi and Joshimath among them, built on slopes, fans and river terraces where landslides and debris flows decide more than the design storm; to a lake town, Nainital, whose every drain ends in Naini lake and whose lake drains only through sluices limited by rules that protect the slope below; to river beds built over, as along the Rispana and the Bindal, and raos that carry sewage through interception structures that the floods of September 2025 broke; to drains vested in the Nagar Nigams beside raos whose beds are forest or revenue land and whose floodplains are the Irrigation Department's; to a State that has a floodplain zoning law and has notified some 615 km of the Ganga system in the hills and the Rispana, but no design return period for the drains of any town; to springs that supply the hill towns and slopes that infiltration can destabilise; and to a monsoon whose recorded days, 487.0 mm at Dehradun in July 1966 and 403.9 mm at Pantnagar in October 2021 (IMD; as reported), exceed the 100-year depths of the CWC plates there, and whose worst floods in the high valleys, Kedarnath in 2013, Raini in 2021 and Dharali in 2025, were debris flows and outbursts that no drain can carry, so that in the high mountains a BSMP begins with the hazard, not the storm (Clause 11.3.3).


11.2 Definitions

Term Meaning in this Manual
Basin The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3.
Basin Stormwater Master Plan (BSMP) The plan for one basin prepared under this chapter.
Lead Authority The body responsible for preparing a BSMP (Clause 11.4).
Level of service (LoS) The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6).
Flood hazard map A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario.
Regional facility A storage, conveyance or outfall work serving more than one development, identified in a BSMP.
Capital Improvement Programme (CIP) The ranked, costed list of works in a BSMP (Clause 11.8.4).

11.3 Planning unit: the basin, not the ward

11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.

11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.

11.3.3 No basin delineation has been published for any Uttarakhand town. For the urban areas where the evidence identifies them, the basins are at least the following:

  • Dehradun, Rispana and Bindal: the catchments of Dehradun that drain to the Rispana and the Bindal through their khalas, from the hill slopes above Rajpur to their meeting, with the interception and diversion structures on their drains and the sewage treatment plants at Mothrowala in the 1D network (Clause 8.9.5), the final floodplain notification of the Rispana (5 May 2025) and the 1-in-5-year line that NMCG has asked for shown, and the 1% AEP level of the ungauged raos, with sediment and debris, as the boundary condition;
  • Dehradun east and Doiwala, Song and Suswa: the catchments that drain to the Song and the Suswa, with the level at CWC's Satyanarayan site on the Song (warning 337.2 m, danger 338.2 m, high flood level 338.49 m) as the boundary condition;
  • Dehradun west and Vikasnagar, Tons and Asan: the catchments that drain to the Tons (Tamsa) and the Asan, with the pond of the Asan barrage (maximum pond level 401.50 m), which is also the Asan Conservation Reserve, as the boundary condition;
  • Rishikesh: the catchments that drain to the Ganga through the Chandrabhaga, the Rambha and the town drains, with the level at CWC's Rishikesh site (danger 340.5 m, high flood level 341.72 m), the releases of Tehri and Koteshwar and the pond of the Pashulok barrage as boundary conditions, and the floodplain lines of the Irrigation Department shown;
  • Haridwar: the catchments that drain to the Ganga at and below the Bhimgoda barrage and across the Upper Ganga Canal, with the level at CWC's Dudhia Band site (danger 294.0 m, high flood level 296.30 m) as the boundary condition and the outfall-closed case a design case;
  • Roorkee: the catchments that drain to the Solani, with the level at CWC's Roorkee site and the crossings of the Upper Ganga Canal in the 1D network, and the outfall-closed case a design case;
  • Haldwani, Gaula: the catchments of Haldwani and Kathgodam that drain to the Gaula through the Rakasia and Kalasia nalas, with the Irrigation Department's drainage master plan as the starting point, the Gaula barrage pond (maximum pond level 510.750 m, high pond level 513.250 m) upstream and the high flood level at Kathgodam (498.93 m) as boundary conditions, and the low-lying areas where pumping is proposed modelled with the outfall closed;
  • Nainital, Naini lake: the catchment of Naini lake, 4.7 km² with the lake and the Sukhatal sub-basin (NIH), with the lake as storage, the Tallital sluices and their rules as the outlet, the recharge flat of Sukhatal kept open, and the Balia Nala below the sluices shown as a landslide hazard;
  • Rudrapur, Kichha and Kashipur: the terai catchments that drain to the Kalyani, the Kichha and the Dhela, with the Baur, Haripura and Tumaria reservoirs and the Dhela barrage as boundary conditions where they reach them;
  • Ramnagar: the catchments that drain to the Kosi below the Ramnagar barrage, with its high flood level (220.75 m or 220.95 m; conflict stated) as the boundary condition;
  • Banbasa, Tanakpur and Khatima: the catchments that drain to the Sarda, with the level at the Banbasa barrage (danger 223.3 m, high flood level 224.9 m) as the boundary condition; and
  • valley towns, among them Srinagar, Rudraprayag, Uttarkashi and Joshimath: the catchments of the town and of every gadhera that crosses it, with the high flood level of the river at the nearest CWC site (Srinagar 537.9 m, Rudraprayag 634.85 m, Uttarkashi 1,124.13 m, Joshimath 1,388.65 m) as the boundary condition, and the debris fans, landslide and creep zones above the town mapped.

Hazard first in the high mountains (set by this Manual). In sub-area UK-F (High Himalaya and snow-fed) of Annex 2A, and in any basin with a glacier, a glacial lake or a mapped debris-flow fan above it, the BSMP begins with a hazard screening for glacial-lake outbursts, debris flows and landslide dams, made with USDMA, ULMMC and CWC's glacial-lake monitoring, and uses site-specific hydrology in place of the zone-7 report (Clause 2.3.6(i)); the hazard zones are shown on the 1% AEP map, no drain, storage or pumping station is sited in them, and no work in the CIP is sized to carry a debris flow or an outburst. Other Tier A bodies, among them Kotdwar, Almora and Pithoragarh, shall define their basins in the first BSMP that covers them. Where the Irrigation Department, CWC, THDC India Ltd, UJVN Ltd, the Lake Development Authority or a court has a high flood level, a pond or lake level, a floodplain line or an operating rule for a dam, barrage, sluice or pumping station, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.

Basin Stormwater Master Plan (BSMP) — process and links to site design 1. Basin set-up Delineate by basin, not ward (Cl. 11.3) Lead Authority + partners 2. Data DEM, drains, tanks, river levels, flood marks (Cl. 11.5) 3. Model 1D–2D, 24–72 h storms, river, continuous sim. calibrate to past floods 4. Gap vs LoS Scenarios: existing, future ± site controls, climate (Cl. 11.6–11.7) 5. Options Restore tanks first, then regional storage, conveyance, outfalls 6. Outputs (Cl. 11.8.4) — approved by State Stormwater Technical Committee • Flood hazard maps 10% / 1% / 0.2% AEP • Flood-sensitive catchments, basin release rates • Regional facility sites and fee-in-lieu rate • Capital Improvement Programme, ranked • Pre-monsoon maintenance programme • Monitoring network • Open data + public map viewer • Annual report, pre-monsoon Land-use plan Statutory master plan: reserve storage sites, flow paths, hazard zoning (Cl. 11.9) Site design Ch 4 release rates, regional detention and fee-in-lieu (Cl. 4.13, 4.5.6) Floors and setbacks 1% AEP future-with-plan map sets floor levels (Ch 6) and setbacks (Ch 7) Public works CIP funds: ULB, State, Union; O&M and desilting (Ch 10) Review every 10 yr, after a >1% AEP event, or plan revision (Cl. 11.11)

Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.

Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Uttarakhand a single rao passes through many hands on its way to a river. In Dehradun the beds of the Rispana and the Bindal outside municipal limits are forest land (High Court, 2022); their floodplains are zoned by the Irrigation Department under the Flood Plain Zoning Act; the interception and diversion of the 208 drains that reach the Rispana, and the sewers behind them, are Peyjal Nigam's (2025); the drains in the town vest in the Nagar Nigam under the adapted Municipal Corporation Act; encroachments on the floodplain are counted separately by the Nagar Nigam, MDDA, the Nagar Palika Parishad of Mussoorie and the District Magistrate (National Green Tribunal, 2025); the drains built under ADB's project and the Smart City Mission are UUSDA's and Dehradun Smart City Ltd's until they are handed over; and the road drains are PWD's. No rule divides the raos and natural nalas from the municipal drains (as this Manual reads the record). The raos carry sewage across these boundaries: the Rispana, the Bindal Rao, the Rambha at Rishikesh and the Kalyani at Rudrapur are among the "rivers reported as drains" (CPCB, as quoted, 2026), and statewide 70 drains were untapped in 2025. This clause makes the basin the planning unit, so that one model carries each rao from its head on the hill to the river whoever owns each reach, and so that the interception works are tested against the capacity of the raos they tap (Chapter 8, Clause 8.9.5).


11.4 Who prepares, and when

11.4.1 Lead Authority.

  • For the basins of a town with a Nagar Nigam: the Nagar Nigam (in Dehradun, DMC; elsewhere the Nagar Nigams of Haridwar, Rishikesh, Roorkee, Kotdwar, Srinagar, Haldwani, Rudrapur, Kashipur, Almora and Pithoragarh, as reported [TBC]), in which the public drains vest under the Uttar Pradesh Municipal Corporation Act 1959 as adapted in Uttarakhand, jointly with the development authority of its area, MDDA for Dehradun, Mussoorie and Rishikesh, HRDA for Haridwar and Roorkee, or the district development authority, which prepares or carries the master plan into which the BSMP is taken (Clause 11.9); either may prepare the plan as the Urban Development Department and the Housing Department direct. Where the Irrigation Department has prepared, or is preparing, a drainage master plan for a town, as for Haldwani and the Kumaon towns, it is a joint Lead Authority with the local body, and its plan is brought up to this chapter as the first BSMP. Where a basin extends beyond the Nagar Nigam, the other local bodies and development authorities in the basin are partners, and one BSMP covers the whole basin (Clause 11.3.1).
  • No order dividing the raos and natural nalas from the municipal drains, or the drains of the local bodies from the rivers, barrages and reservoirs, was found; until one is made, this Manual assigns the reaches within each BSMP as follows, each body being Lead Authority for the reaches and works it owns or runs and for the parts of the CIP on them: the Irrigation Department for the rivers, raos and gadheras with their beds, banks and floodplains, for flood works, for floodplain zoning under the Flood Plain Zoning Act 2012 and for its barrages, reservoirs and canals, among them the Gaula barrage and the Baur, Haripura and Tumaria reservoirs; THDC India Ltd for Tehri and Koteshwar and UJVN Ltd for the Dakpathar and Asan barrages, for their pond levels and releases; the Forest Department as owner of the river beds outside municipal limits; the Nagar Nigam, Nagar Palika Parishad or Nagar Panchayat for the drains and nalas vested in it; MDDA, HRDA, a district development authority, UHUDA or a colony developer for the drains of their schemes, and UUSDA and Dehradun Smart City Ltd for the drains they build, until handed over in writing; PWD for the side drains, catch-water drains, scuppers and culverts of the State roads and hill roads, and NHAI, NHIDCL and BRO for theirs; Peyjal Nigam and Jal Sansthan for the sewers and the interception and diversion structures on the drains and raos; the Lake Development Authority, Nainital, with the custodian of the Tallital sluices [TBC], for Naini lake and its catchment; the Uttarakhand State Wetland Authority, with the Forest Department, for notified wetlands and the Asan Conservation Reserve; and USDMA and ULMMC for the mapping of landslide, debris-flow and glacial-lake hazards that a BSMP must show.
  • In Tier B bodies: the Lead Authority is named by the Urban Development Department. Basins draining to a common river reach, barrage pond or taal may be grouped into one district-level plan.

USDMA, ULMMC and the district administration shall be consulted on every BSMP; the Lake Development Authority on every BSMP in the catchment of a Kumaon lake; the Uttarakhand State Wetland Authority on every BSMP whose basin drains to a notified wetland or the Asan Conservation Reserve; the Uttarakhand Environment Protection and Pollution Control Board and the State Mission for Clean Ganga on every BSMP that proposes works on a drain or rao that carries sewage to the Ganga system; and, for a basin whose outfall lies on a river or canal shared with Uttar Pradesh, such as the Ganga and the Upper Ganga Canal below Haridwar or the Solani below Roorkee, the irrigation department of that State, through the Irrigation Department.

The Irrigation Department shall be a partner in every BSMP that includes a river, canal or tank under its control.

11.4.2 When a BSMP is required.

  • (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
  • (b) A BSMP is required before:
    • any regional detention or fee-in-lieu is accepted under Clause 4.13;
    • a fee held under Clause 4.5.6.3 is spent; and
    • a basin-specific release rate is applied under Clause 11.8.3.
  • (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.

11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.


11.5 Data and surveys

11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:

Table 11.1 — Minimum data and surveys for a BSMP

Data Minimum requirement
Terrain Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum
Drain network Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm
Waterbodies Survey of every tank, taal, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment
Rivers and canals Cross-sections at no more than 200 m spacing and at every structure
Outfalls, rivers, raos, barrages, reservoirs and taals The datum of every level named; outfall invert levels against the warning, danger and high flood levels of the receiving river at the nearest CWC site and its recorded peaks (on the Ganga at Haridwar a warning level of 293.0 m, a danger level of 294.0 m and a high flood level of 296.30 m, dated 19 September 2010 in one source and 17 June 2013 in another; at Rishikesh 339.5 m, 340.5 m and 341.72 m; on the Song at Satyanarayan 337.2 m, 338.2 m and 338.49 m; on the Solani at Roorkee 260.5 m and 261.5 m, with a high flood level of 260.58 m; CWC levels as transcribed by SANDRP, as reported), with any local gauge kept as a separate series; for the ungauged raos and gadheras, surveyed flood marks and the 1% AEP flood level with its sediment and debris, and the 25-year and 100-year lines of any notification under the Uttarakhand Flood Plain Zoning Act 2012, with the 1-in-5-year line that NMCG has asked for on the Rispana; for outfalls to barrage ponds, reservoirs and taals, the maximum pond or water level, full reservoir level and spillway and gate data from the Irrigation Department, THDC India Ltd or UJVN Ltd (for example Tehri, full reservoir level 830 m and maximum water level 835 m; Dakpathar, maximum pond level 456.40 m; Asan, maximum pond level 401.50 m; the Gaula barrage, maximum and high pond levels of 510.750 m and 513.250 m; Baur and Haripura, full reservoir level 242.32 m), naming which is used; for Naini lake, the Tallital gauge (maximum level 12.5 ft, NIH; 12 ft in the press) tied to a level above mean sea level, the sluices and the rules of 1927 for opening them and the sealing date of 15 October; the release records of Tehri, Koteshwar and the barrages; the debris-flow fans, landslide and creep zones and glacial lakes above the basin, from USDMA, ULMMC and CWC's glacial-lake monitoring where mapped; and the sluices, flap gates, debris racks, sediment traps, debris basins, interception and diversion structures and pumping stations on the outfalls, with their capacities and operating rules
Rainfall and levels All available rain gauges (IMD, including its observatories at Dehradun, Roorkee and Mukteshwar (rainfall since 1901), its stations at Tehri, Mussoorie, Joshimath and Nainital, whose records end between 1980 and 2012, and the automatic weather stations and rain gauges reported by the Meteorological Centre Dehradun, among them Sahastradhara, Maldevta, Jolly Grant, Narendranagar, Kalsi and Didihat; the district and tehsil rain gauges of the State, whose records IMD tabulates in the Climate of Uttarakhand; the observatory at Pantnagar; the self-recording gauges at Dehradun, Nainital, Tehri and Uttarkashi used for the CWC Flood Estimation Report for zone 7; the rain and river gauges of CWC and of the Irrigation Department, including those at its barrages and reservoirs; the records of THDC India Ltd and UJVN Ltd at their dams and barrages; and any gauges kept by the Nagar Nigams, the development authorities, USDMA and Dehradun Smart City Ltd) and water-level records, including those for the 16–17 June 2013 (370.2 mm at Dehradun on 17 June, IMD), 18–19 October 2021 (403.9 mm at Pantnagar and 401 mm at Nainital in the 24 hours to 08:30 on 19 October, with new high flood levels on the Gaula, the Kosi and the Sarda, as reported), 14 August 2023 (175.1 mm at Dehradun, IMD, with the Ganga above its danger level at Rishikesh, as reported) and 15–16 September 2025 (264 mm in 24 hours and 54 mm in an hour at Sahastradhara, with the raos of Dehradun in flood, as reported) events
Flood evidence Surveyed flood marks and mapped flood extents from past events, including public reports
Land use Existing land use and imperviousness; future land use from the statutory master plan
Soils and groundwater HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones
Sewer interaction Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots

Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the terai and on the Ganga plain at Haridwar and Roorkee, where slopes are gentle and the water table is near the surface, on the fans and river terraces of the Doon, Haldwani and the valley towns, where a raised road or a low wall can turn the overflow of a rao from one side of a fan to the other, and around Naini lake, where the 30 m line of bye-law 4.4(III) is drawn from the lake's maximum level, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The 16–17 June 2013 (370.2 mm at Dehradun on 17 June, IMD), 18–19 October 2021 (403.9 mm at Pantnagar and 401 mm at Nainital in the 24 hours to 08:30 on 19 October, with new high flood levels on the Gaula, the Kosi and the Sarda, as reported), 14 August 2023 (175.1 mm at Dehradun, IMD, with the Ganga above its danger level at Rishikesh, as reported) and 15–16 September 2025 (264 mm in 24 hours and 54 mm in an hour at Sahastradhara, with the raos of Dehradun in flood, as reported) events are the best calibration data Uttarakhand has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.


11.6 Levels of service

11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.

Table 11.2 — Minimum levels of service

Element Minimum level of service
Minor system The design AEP of Chapter 6 (Table 6.1)
Habitable buildings No flooding above floor level in the 1% AEP (100-yr) event
Critical facilities (hospitals, emergency services, substations, water and sewage plants) No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event
Evacuation routes and arterial roads Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event
Ponding drain time Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event
Tank and taal storage No net loss of flood storage below the MWL in the basin, measured against the earliest available survey
Outfalls Functioning under the joint and outfall-closed cases of Chapter 5

Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been reported but rarely measured. Uttarakhand's storage is in its lakes, its floodplains and its recharge flats more than in tanks. Naini lake, 0.46 km² of water holding about 8.58 million m³ in a basin of 4.7 km², is the one urban taal whose water balance has been studied (NIH, 1998–99); about half of its subsurface recharge is estimated to enter through the Sukhatal zone of about 2 ha (NIH, as cited by NITI Aayog, 2018), on whose bed the High Court stopped construction in 2022 (as reported), and the lake fell to 4.7 ft on its gauge, a five-year low, in 2025 (as reported). Bhimtal, of about 47.8 ha, drains a catchment of about 17 km² (as reported). Bye-law 4.4(III) of the Bye-laws 2011 bars construction within 30 m of the bank or maximum level of every lake in the State, and the Unified Zoning Regulations 2025 put ponds, lakes, nalas and streams in a Conservation Use Zone. The Asan Conservation Reserve, 444.4 ha at the meeting of the Asan and the Yamuna canal behind the Asan barrage, is the State's only Ramsar site (2020); the State Wetland Authority, constituted in 2019, lists 192 wetlands from the national atlas but no wetland has been found notified under the Wetlands Rules 2017. In the hills the khals and chals, small ponds in the saddles of ridges, have been revived in places as recharge ponds (as reported). The losses are visible in the floodplains: about 95 ha of river bed found encroached in Dehradun and Vikasnagar tehsils (High Court, 2022) and the structures counted in the Rispana's active floodplain (NMCG, 2026). No survey of the storage of any taal other than Naini lake, or of any floodplain inside a Nagar Nigam, was found.


11.7 Modelling and scenarios

11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:

  • the minor system;
  • the major (overland) system;
  • rivers, canals and tanks; and
  • the outfalls.

Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.

11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.

11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.

11.7.4 Scenarios. Each BSMP shall model at least:

  • (a) Existing: existing land use, network, tanks and outfalls;
  • (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
  • (c) Future, controlled: future land use with the site controls of Chapter 4;
  • (d) Future, with plan: scenario (c) plus the works of the CIP; and
  • (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Uttarakhand has been adopted with a design factor; ADB's climate risk assessment for the Dehradun drains (2021) projects a mean rise in heavy daily rainfall of 10% (RCP4.5) to 16% (RCP8.5) by 2036–65 and recommends drains that carry 10–20% more flow, while noting that its own designs include no allowance; no significant trend in heavy-rain days has been found at Dehradun, Pantnagar, Tehri or Mukteshwar over 1983–2023 (Singh and Thapliyal, 2026); and station records, 487.0 mm at Dehradun on 25 July 1966 (IMD) and 403.9 mm at Pantnagar on 19 October 2021 (as reported), exceed the 100-year 24-hour depths of the CWC plates there (this Manual's reading), which is a reason to keep the factors, not to reduce them; in snow-fed basins of sub-area UK-F the climate scenario adds no rainfall factor, and the debris-flow and glacial-lake hazards of Clause 11.3.3 are mapped instead.

11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the 16–17 June 2013 (370.2 mm at Dehradun on 17 June, IMD), 18–19 October 2021 (403.9 mm at Pantnagar and 401 mm at Nainital in the 24 hours to 08:30 on 19 October, with new high flood levels on the Gaula, the Kosi and the Sarda, as reported), 14 August 2023 (175.1 mm at Dehradun, IMD, with the Ganga above its danger level at Rishikesh, as reported) and 15–16 September 2025 (264 mm in 24 hours and 54 mm in an hour at Sahastradhara, with the raos of Dehradun in flood, as reported) events where data exist.

Figure 11.2 — BSMP model schematic Schematic plan of a basin model: design rainfall over sub-catchments; two tanks in cascade with surplus course; a 1D drain network linked to a 2D surface grid; a river or canal reach with an inter-basin link; an outfall with a flap gate and pumps; and a river or lake level boundary. Numbered notes on the right explain each element. BSMP model: elements required by Clause 11.7 (schematic, not to scale) River / receiving water 1 S1 S2 S3 2 Upper tank Lower tank start level start level 3 2D surface 5 4 River / canal (1D) 6 Inter-basin link Gate Pumps 7 8 1 Design rainfall Ch. 2 storms incl. 24, 48, 72 h; 50%, 10%, 1%, 0.2% AEP; areal reduction (Cl. 2.7.3, 11.7.2) 2 Sub-catchments Runoff by Ch. 3 methods; land use for each scenario (a)–(e) of Cl. 11.7.4 3 Tanks and ponds Surveyed FTL, MWL, stage–storage, sluices, surplus weirs (Cl. 11.5.1); start level from continuous run (Cl. 3.13.5, 11.7.3) 4 1D drain network Minor system: drains, pipes, culverts with surveyed inverts and silt (Cl. 11.5.1) 5 2D surface Major (overland) system on the DEM, 0.15 m RMSE or better; exchange with 1D at inlets and manholes 6 Rivers and canals (1D) Sections ≤ 200 m apart and at every structure; diversions between basins mapped (Cl. 11.3.2) 7 Outfall Sluices, flap gates and pumps; joint and outfall-closed cases of Ch. 5 8 Downstream boundary River (CWC or UKID gauge) or lake level (MWL or FTL + surcharge), per Ch. 5 Calibrate and validate with at least two major past flood events where data exist (Cl. 11.7.5).

Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and taals with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.

Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).


11.8 Options, outputs and the Capital Improvement Programme

11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:

  1. Protect and restore storage: taals, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
  2. Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
  3. Conveyance upgrades to drains, canals and culverts;
  4. Outfall works: flap gates and penstocks on the outfalls to the Ganga at Haridwar and Rishikesh, the Solani at Roorkee, the Song, the Gaula, the Kosi and the Sarda, with storage or pumping behind them where a river in flood or a barrage pond can close an outfall, as the Irrigation Department is reported to propose for the low-lying parts of Haldwani; debris racks, sediment traps and debris basins where raos and gadheras from the hills enter the towns, with ramps for the machines that empty them; drop structures, chutes, energy dissipators and protected outfalls where steep drains reach a rao or river; interception and diversion structures that take the dry-weather flow of the drains of the Rispana, the Bindal and the Ganga to the sewage treatment plants without taking their storm capacity, rebuilt above the 25-year flood line where they can be; the Tallital sluices of Naini lake, whose operation is limited by the rules that protect the Balia Nala below; and the operating rules of Tehri, Koteshwar and the barrages that set the receiving levels, agreed with the Irrigation Department, THDC India Ltd and UJVN Ltd;
  5. Property-level protection where works cannot reach the level of service; and
  6. Non-structural measures: flood warning (for example IMD district rainfall warnings and nowcasts issued by the Meteorological Centre Dehradun, CWC flood forecasts and river stages at its sites, among them the Ganga at Rishikesh and Haridwar and the Song at Satyanarayan, notice of releases from Tehri, Koteshwar and the barrages at Pashulok, Bhimgoda, Dakpathar, Asan, Kathgodam, Ramnagar and Banbasa to the towns downstream, the sirens and the flash-flood and landslide monitoring that USDMA is reported to be installing, and the district emergency operation centres), flood-hazard zoning, emergency planning and public information.

11.8.2 Option assessment. Each option shall be assessed for:

  • reduction in flood risk (buildings and people flooded; expected annual damage);
  • capital and 30-year maintenance cost;
  • land required;
  • effect on groundwater recharge on the Doon Gravels and the bhabar, which feed the artesian aquifers of the terai and include the semi-critical blocks of Bahadrabad, Bhagwanpur, Haldwani and Kashipur (CGWB, 2020 and 2022), the stability of hill slopes, where water put into colluvium, slide debris or moraine raises the pore pressure, as along the Balia Nala at Nainital and at Joshimath, the naulas and dharas that supply the hill towns and their recharge areas, the recharge of Naini lake through Sukhatal, the high water table of the terai, and the quality of the groundwater, with nitrate and arsenic at places in Haridwar and Udham Singh Nagar, and of the rivers, raos and taals that the runoff reaches (Chapter 8);
  • effect on downstream basins and the receiving river, rao, taal or canal; and
  • who benefits.

11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.

11.8.4 Outputs. Each BSMP shall produce:

  • (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
  • (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
  • (c) regional facility sites, with storage volumes, land needs and the sites they serve;
  • (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
  • (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
  • (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
  • (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.

Commentary. Restoring storage comes first because many of Uttarakhand's town outfalls are closed or limited in the wettest weeks, and because the storage left is in floodplains and lakes that the towns are filling. The Ganga at Haridwar and Rishikesh, the Song, the Solani, the Gaula, the Kosi and the Sarda have all stood near or above their danger levels in recent floods, and in October 2021 the Kosi at Ramnagar and the Sarda at Banbasa rose to new high flood levels (as reported). The raos once spread their floods over wide beds: the High Court recorded 37.93 ha of encroached river bed in Dehradun tehsil and 57.4 ha in Vikasnagar (2022), NMCG counted 330 structures in the Rispana's 1-in-5-year flood zone (2026), and the Flood Plain Zoning (Amendment) Act 2024 lets a final notification be narrowed where "riverbank development" can protect land and buildings (as quoted), which would trade floodplain storage for embankments. Conveyance alone has not served: ADB's Dehradun drains are built for the 2- and 5-year storms (ADB, 2021), and on 15–16 September 2025 the raos of Dehradun destroyed bridges, culverts and interception works (as reported). On a hill slope storage means a lined tank or a terrace, not a pond that soaks into the slope (Clause 8.8.1). The storms are large for drains with no stated design basis: IMD has recorded 487.0 mm in a day at Dehradun (25 July 1966), and 403.9 mm fell at Pantnagar on 19 October 2021 (as reported), above the 100-year 24-hour depths of the CWC plates there (this Manual's reading). Conveyance upgrades on their own move water faster to an outfall that the Ganga, the Solani, the Song, the Gaula, the Kosi or the Sarda in flood, or a barrage pond held at its maximum level, may close, to Naini lake, whose outflow is limited by the rules for its sluices, to a rao or gadhera whose bed and banks shift with the boulders and debris it carries, or to an outfall limited by the capacity of its sluice, interception structure or pumping station. Groundwater in Uttarakhand calls for recharge in one belt and for restraint in the others. The State's stage of extraction was 53.54% in 2024, with 16 of its 20 assessment units safe and 4 semi-critical (CGWB, 2024); in 2020 and 2022 the semi-critical blocks were Bahadrabad and Bhagwanpur in Haridwar district, Haldwani and Kashipur, all on or below the bhabar. The Doon Gravels and the bhabar fans take water readily, with hydraulic conductivities of 13–583 m/day in the Doon and water 40–75 m below ground in the bhabar of Nainital district (CGWB), and they feed the terai, where more than 2,000 artesian wells were counted in five blocks of Udham Singh Nagar and the water stands 1–7 m below ground (CGWB), so recharge there adds to waterlogging. In the hills about 85% of the State is hard rock (CGWB), the springs supply most of the drinking water in many blocks, about 70% in Chamoli and up to 84–87% in some blocks (GBPNIHE, 2019), and the functional springs of the Almora region have fallen from 360 to 60 over 150 years (NITI Aayog, 2018); but water put into a hill slope raises the pore pressure in its colluvium, as along the Balia Nala at Nainital (2022 study) and at Joshimath (2023, as reported). Quality limits recharge too: nitrate above 45 mg/l in about 17% of samples and arsenic above 10 µg/l in about 4%, in Haridwar and Udham Singh Nagar among other districts (CGWB, 2024). Uttarakhand has no groundwater law in force, the Act of 2016 having been repealed in 2017, and bye-law 6.5 credits recharge without regard to slope or water table. This is why recharge, slope stability, springs, waterlogging and groundwater quality are all assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.


11.9 Integration with land-use planning

11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the master plans and zonal plans approved by the State under the Uttar Pradesh Urban Planning and Development Act 1973, as applicable to and amended in Uttarakhand, among them those of the MDDA area and of Nainital and, when it is issued, the Haridwar–Roorkee master plan, with the Unified Zoning Regulations 2025 that form part of them; the plans of the district development authorities and of UHUDA's regulated areas; and the layouts and buildings permitted under them and under the Bye-laws 2011. In particular:

  • (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
  • (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
  • (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
  • (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.

11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.

Commentary. Uttarakhand draws more water lines by rule than most States, but not yet a drainage-flood line. Bye-law 4.4(III) of the Bye-laws 2011 keeps building at least 30 m from a river bank, 10 m from a spring, 5 m from a nala and 30 m from the bank or maximum level of every lake (the first two printed as "30.0–30.0" and "10.0–10.0" m, read here as single distances); bye-law 4.4(IV) bars building on natural slopes steeper than 30°, or 26.5° in Nainital, where landslides are likely to be severe and continuous, and within 250 m of a landslide-prone site; and the Unified Zoning Regulations 2025 put rivers, lakes, nalas and streams in a Conservation Use Zone with no new construction within 30 m of river and lake banks. The Flood Plain Zoning Act 2012 is the State's flood line: the Irrigation Department models the 25-year and 100-year floods, marks them on the revenue maps and the ground, and the final notification makes the first a prohibited and the second a restricted area; some 614.6 km of the Bhagirathi, the Ganga, the Bhilangana, the Alaknanda and the Mandakini and the Rispana (5 May 2025) are finally notified, the Asan's notification was approved by the cabinet in June 2025 (as reported), and the Gaula, the Kosi, the Suswa, the Song, the Baldi and the Solani have been studied but not notified; an amendment of 2024 extends the period for notices to 24 months and allows a notification to be narrowed by "riverbank development" (as quoted), and Rules approved by the cabinet on 12 October 2026 have not been published. On the Ganga in the hills the Housing Department's order of 2017, revised in 2023, prohibits building within 100 m of the middle of the river or the 25-year flood line, whichever is wider, with a regulated zone of 200 m beyond, while the National Green Tribunal set 100 m from the edge of the river for Haridwar to Unnao until the floodplain is demarcated; the two are stated, not merged. NMCG now asks for the 5-year line as well. These are watercourse and river-flood lines, not drainage-flood lines: where a floodplain line is notified it governs; elsewhere the hydraulic corridor and setback zones of Chapter 7, with a Zone 1 of at least 15 m, and the bye-law lines of 30 m and 5 m apply, whichever is wider, as this Manual's proposal. A BSMP gives the master plans the 1% AEP drainage-flood map, including the raos and gadheras that no notification yet covers, and the buffer widths of Chapter 7, that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because the Bye-laws 2011 already require rainwater storage under bye-law 6.5, keep drainage and storage structures out of the ground coverage, and require the site plan of a sloping site to divert the uphill runoff away from the foundations (bye-law 4.4(V)(b)), and the Unified Zoning Regulations 2025 put rivers, lakes, nalas and streams in a Conservation Use Zone whose green buffer may be used for plantation, open space and parks, but no rule sets a detention or peak-runoff limit; storage placed in a layout's open space builds on these duties, and because that land still serves as open space, the storage must stay usable as one, and on a hill slope it is a lined tank or a shallow terrace, never an infiltration basin (Clause 8.8.1). Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.


11.10 Consultation and publication

11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.

11.10.2 After approval, the following shall be published as open data:

  • the model files;
  • the flood hazard maps;
  • the data of Clause 11.5.1, except security-sensitive asset details; and
  • the CIP.

They shall also be shown on a public map viewer.

Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.


11.11 Approval, review and reporting

11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.

11.11.2 Review. Each BSMP shall be reviewed:

  • every 10 years;
  • within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
  • when the statutory land-use plan is revised.

11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each SW monsoon (by 31 May). The report shall show:

  • CIP progress;
  • the fee-in-lieu ledger (Clause 4.13.4);
  • maintenance completed; and
  • any flooding against the levels of service.

11.12 Interim arrangements

11.12.1 Until a BSMP is approved for a basin:

  • (a) all site criteria of Chapters 4 to 8 apply in full;
  • (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
  • (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
  • (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.

References (chapter)

Annexes and forms

Annex / Form Content
11A BSMP terms of reference template
11B Basin lists and boundaries for Tier A bodies
11C Depth–damage curves for Uttarakhand building types
11D BSMP data and model publication standard
Form 11-1 Annual implementation report